Installation Instructions – Vertical Application · 1 ˜ ˜ ˜D ˜A ˜B ˜C B B B B ˜ B h-c ˜-c...
Transcript of Installation Instructions – Vertical Application · 1 ˜ ˜ ˜D ˜A ˜B ˜C B B B B ˜ B h-c ˜-c...
-
1
2
4
3D
3A 3B
3C
B
B
B
B
1
B
hh-c1-c2
c2
c1≥ l0 5
≥ 15M @250 mm≥ 10M
① + ② ▶ Before installation, check products for conformity with purchase or-
der and that no Isokorb® parts are missing. ▶ Check products for visible damages. ▶ Check the product for correct type conforming to the design draw-
ings of the structural engineer. ▶ Ensure that the materials required to install Schöck Isokorb® for the
construction project are complete including a tape measure, rebar tie-wires, wire cutters, a hammer and a hand saw as required.
③ These images demonstrate the general position for installing the Schöck Isokorb® Type CPA in the vertical orientation with various parapet wall types. Follow the layout drawings of the approved Schöck Technical Proposal to con� rm the exact position of the ther-mal break.
④ + ⑤Additional reinforcement is required to tie in the loops of the Schöck Isokorb® Type CPA. The outside vertical loops of the CPA product need to be tied to a horizontal U-bar (sized 10M) in the slab provided on site. Longitudinal rebar is required at the top and bot-tom corners of the in-slab U-bars. This is to ensure a sti� slab edge and proper transition of forces in compliance with the design draw-ings of the structural engineer.
Installation Instructions – Vertical Application
Schöck Isokorb® Type CPA
TH Schöck Isokorb®/CA-en/2018.1/January
CPA
Inst
alla
tion
-
2
6
7a
8
9
l0
l0
⑥ Note the locations where the Schöck Isokorb® Type CPA are speci-� ed in the design drawings and place the additional reinforcement into the slab as required.
⑦ + ⑧Position each Schöck Isokorb® Type CPA into the roof slab formwork and tie the outside vertical loops from the product to the in-slab horizontal U-bars provided on site. The bottom surface of the Schöck Isokorb® Type CPA insulation block should be � ush with the � nal top surface of the roof slab.
⑨ The horzontal in-slab connectors must be long enough to provide the required lap-length to the primary slab rebar speci� ed by the engineer of record (EOR).
Before placing the concrete, check the alignment of the Schöck Isokorb® Type CPA with the slab and connecting reinforcement. Con� rm all is in accordance with the approved Schöck Technical Proposal and the design drawings of the EOR.
Installation Instructions – Vertical Application
Schöck Isokorb® Type CPA
TH Schöck Isokorb®/CA-en/2018.1/January
CPA
Inst
alla
tion
-
3
10
11
12
l0 l0
13
≥ 10M @250 mm
≥ 10M
⑩ + ⑪Place the concrete in the slab vibrating evenly around the rebar of the Schöck Isokorb® Type CPA. Once the concrete slab has cured, position insulation spacers (Schöck Isokorb® Type ZXT) between the CPA units.
⑫ + ⑬Additional reinforcement is required to tie in the vertical bars of the Schöck Isokorb® Type CPA. The parapet wall requires vertical U-bars sized 10M spaced at minumum 250 mm. Longitudinal rebar is re-quired at the bottom corners of the parapet wall U-bars, and spaced up the height of the wall as speci� ed by the engineer of record.
Installation Instructions – Vertical Application
Schöck Isokorb® Type CPA
TH Schöck Isokorb®/CA-en/2018.1/January
CPA
Inst
alla
tion
-
4
15
14
⑭ Tie the vertical bars of the Schöck Isokorb® Type CPA to the parapet wall longitudinal rebar.
⑮ Once the parapet formwork has been built, place concrete up the parapet wall and ensure it is evenly vibrated.
Installation Instructions – Vertical Application
Schöck Isokorb® Type CPA
TH Schöck Isokorb®/CA-en/2018.1/January
CPA
Inst
alla
tion
-
5
2
3A 3B
3C 3D
≥ 150 mm
≥ 150 mm
≥ 150 mm
≥ 150 mm
1
4
a
① + ② ▶ Before installation, check products for conformity with purchase or-
der and that no Isokorb® parts are missing. ▶ Check products for visible damages. ▶ Check the product for correct type conforming to the design draw-
ings of the structural engineer. ▶ Ensure that the materials required to install Schöck Isokorb® for the
construction project are complete including a tape measure, rebar tie-wires, wire cutters, a hammer and a hand saw as required.
③ These images demonstrate the general position for installing the Schöck Isokorb® Type CPA in the horizontal orientation with various supporting wall types under the roof slab. Follow the layout draw-ings of the approved Schöck Technical Proposal to con� rm the exact position of the thermal break.
④ Position each Schöck Isokorb® Type CPA into the roof slab formwork and tie each horizontal bar provided in the product to the upper and lower in-slab reinfocement bars provided on site. The height of the Schöck Isokorb® Type CPA should match the slab height, with the insulation � ush to the outer edge of the roof slab.
Installation Instructions – Horizontal Application
Schöck Isokorb® Type CPA
TH Schöck Isokorb®/CA-en/2018.1/January
CPA
Inst
alla
tion
-
6
8
5
7
6
l0≥ 10M @125 mm
≥ 10M
⑤ + ⑥Additional reinforcement is required to tie in the loops of the Schöck Isokorb® Type CPA with the parapet wall. Every loop joining into the parapet wall requires a vertical U-bar size 10M to be provid-ed in the wall. Longitudinal rebar is required at the bottom corners of the in-wall U-bars. This is to ensure a proper transition of forces from the parapet wall to the roof slab in compliance with the Schöck Technical Proposal and the design drawings of the engineer of record (EOR).
⑦ + ⑧Once the parapet wall reinforcement has been installed with the loops of the Schöck Isokorb® Type CPA completely tied in, insulation spacers (Schöck Isokorb® Type ZXT) are positioned between the Isokorb® CPA units.
Installation Instructions – Horizontal Application
Schöck Isokorb® Type CPA
TH Schöck Isokorb®/CA-en/2018.1/January
CPA
Inst
alla
tion
-
7
9
11
12
l0
l0
h-c1-c2
c2
c1≥ l0
10
h
≥ 10M @250 mm≥ 10M
⑨ + ⑩Additional reinforcement is required to tie the horizontal bars of the Schöck Isokorb® Type CPA into the slab reinforcement. The roof slab requires additional edge U-bars sized 10M spaced at minumum 250 mm. Longitudinal rebar is required at the top and bottom cor-ners of the slab edge U-bar as recommended by the approved Schöck Technical Proposal and speci� ed by the engineer of record.
⑪ Tie the upper and lower bars of the Schöck Isokorb® Type CPA to the roof slab longitudinal rebar.
⑫ The horzontal in-slab connectors must be long enough to provide the required lap-splice length to the primary slab rebar as speci� ed by the engineer of record (EOR).
Before placing the concrete, check the alignment of the Schöck Isokorb® Type CPA with the slab edge and that all reinforcement is well connected. Con� rm all is in accordance with the approved Schöck Technical Proposal and design drawings of the EOR.
Installation Instructions – Horizontal Application
Schöck Isokorb® Type CPA
TH Schöck Isokorb®/CA-en/2018.1/January
CPA
Inst
alla
tion
-
8
13
14
⑬ Place the concrete in the slab vibrating evenly around the rebar of the Schöck Isokorb® Type CPA.
⑭ Once the parapet formwork has been built, place concrete up the parapet wall and ensure it is evenly vibrated.
Installation Instructions – Horizontal Application
Schöck Isokorb® Type CPA
TH Schöck Isokorb®/CA-en/2018.1/January
CPA
Inst
alla
tion