0 21.Mar.2014 Issue for Construction J. G. Kim H.W.Chung M.K. Kim
A 08.Jan.2014 Issue for Approval J. G. Kim H.W.Chung M.K. Kim
REV. DATE DESCRIPTION DESIGNED CHECKED APPROVED
OWNER
PROJECT
SHUQAIQ STEAM POWER PLANT
ENGINEER
CONTRACTOR
-
8/17/2019 Inspection Test Plan for Electrical
2/38
Doc. No. : S-00-TAA-Q-43-036-001
Rev. No. : 0
Table of Contents
1. S-00-TAA-Q-43-036-001 : ITP for Electrical…….……………………………..1 to 2
2. S-00-TAA-Q-43-036-002 : Cable and Tray & Conduit(Ele)....…….. ………….3 to 6
3. S-00-TAA-Q-43-036-003 : LV MV SWGR………. …………………………...7 to 8
4. S-00-TAA-Q-43-036-004 : Motor Control Center……………………..…........9 to 10
5. S-00-TAA-Q-43-036-005 : Transformer …………………………….……......11 to 12
6. S-00-TAA-Q-43-036-006 : AC / DC UPS System…………………………....13 to 14
7. S-00-TAA-Q-43-036-007 : BUS DUCT……………….……………………...15 to 16
8. S-00-TAA-Q-43-036-008 : Distribution Board(Incl UPS AC/DC Board)…….17 to 18
9. S-00-TAA-Q-43-036-009 : Motor…….……………………………………….19 to 20
10.
S-00-TAA-Q-43-036-010 : Cathodic..……………………………………..….21 to 22
11.S-00-TAA-Q-43-036-011 : Earthing and Bonding…………………………….23 to 24
12.S-00-TAA-Q-43-036-012 : Lighting System…….…………………………….25 to 26
13.S-00-TAA-Q-43-036-013 : Lightning Protection….…..……………………….27 to 27
-
8/17/2019 Inspection Test Plan for Electrical
3/38
Client : SEC, Kingdom of Saudi Arabia
Disc : Electrical
Item : Cable / Tray / Condui t
INSPECTION & TEST PLAN (ITP) ITP No. : S-00-TAA-Q-43-036-002 Rev. 0Page : 3 of 38
Construction of Shuqaiq Steam Power Plant
Contract No. : 31221097/00
No Activit y Description Frequency Procedure /Spec. Inspection Method / Acceptance Criteria ReportingFormat
Inspection By
RemarksSub-Con
HHISEC/OE
1 Material VerificationReceiving Inspection
- Raw Material
100% Related POS/Material Spec.,
General Ass’yDrawing
Receiving Insp.Procedure: S-00-TAA-Q-43-008-001
As per Specified in Applicable Specification and
Drawing
- No Damage, Corrosion & Deformation
- Shall be properly laid out on wooden supports
clear of the soil.
HSFP-ST-01 W W R
2 Installation Cable Tray,Ladder and ConduitInstallation.
100% Approveddrawing.Vender Drawing
- Check tag numbers are correct.
- Verify Cable tray and tray installed as per
construction drawing.
- Check alignment as overlapped of trays.
- Check bonding jumpers installed at tray joint
connections and tight.
HSFP-EL-028
W W M
* Legend : R (Review Point) : To determine subject matter has achieved objectives.
M (Monitoring) : Periodic and systematic check (does not imply any action will be taken)
W (Witness Point) : Observation of an activity to ensure work is progressing as per requirements.
H (Hold Point) : A point beyond which an activity must not proceed without the approval of a designated organization or authority, SEC/OE’s Inspector.
-
8/17/2019 Inspection Test Plan for Electrical
4/38
Client : SEC, Kingdom of Saudi Arabia
Disc : Electrical
Item : Cable / Tray / Condui t
INSPECTION & TEST PLAN (ITP) ITP No. : S-00-TAA-Q-43-036-002 Rev. 0Page : 4 of 38
Construction of Shuqaiq Steam Power Plant
Contract No. : 31221097/00
No Activity Description FrequencyProcedure /
Spec.
Inspection Method / Acceptance CriteriaReporting
Format
Inspection By
RemarksSub-
Con HHI
SEC/
OE
2 Installation Cable Tray,Ladder and ConduitInstallation.
100%Installation All Route
Approveddrawing.Vender Drawing
- Check hold down clamp and brackets are installed.
- Check cable ladder properly supported.
- Check cover installed(to be installed after all the
cables are tested and properly terminated)
- Check junction box supports independent from
conduit and tray.
- Check conduit supports within the specified interval
according to approved drawing.
- Check touch up of galvanizing performed
(if required)
- No sharp edges.
- No obstructions.
- Check tray Labelling
HSFP-EL-028
W W M
3 Excavation,backfilling(Civil), Duct,Sand bed & Sand fill
100%Installation All Route
Approveddrawing.
- Check the cable trench and dimension and
elevation of bottom of trench as approved drawings.
- Check rigid PVC location and size as per drawing,
(if required)
- Check the tiles installed as per approved drawing
HSFP-EL-029
W W M
-
8/17/2019 Inspection Test Plan for Electrical
5/38
Client : SEC, Kingdom of Saudi Arabia
Disc : Electrical
Item : Cable / Tray / Condui t
INSPECTION & TEST PLAN (ITP) ITP No. : S-00-TAA-Q-43-036-002 Rev.0Page : 5 of 38
Construction of Shuqaiq Steam Power Plant
Contract No. : 31221097/00
No Activit y Description FrequencyProcedure /
Spec.
Inspection Method / Acceptance CriteriaReporting
Format
Inspection By
RemarksSub-
Con HHI
SEC/
OE
3 Excavation,backfilling(Civil), Duct,Sand bed & Sand fill
100%Installation All Route
Approveddrawing
- Check using of clean sand without stone for sand
bedding and sand filling with appropriate depth
- Check the Trench route marker and symbol
(after cable testing and complete backfill)
HSFP-EL-029
W W M
4Cable Installation
- Installation & Visual
Check.
- Insulation resistance
Test
All Cable Approved vender
Drawing Approved drawing
-
- Check and confirm cable shall be meggered before
Installation(on reel test/Only Power cable : If
required)
- Verify cable type & configuration.
- Damaged cables shall be replaced before
Sand filling
- Check and confirm cable shall be meggered before
And after installation, record of testing shall be
available.
- Check proper arrangement, segregation and layer
Of cable, bending radius as per vender data, and
allowable Slack.
- Check the barrier between the HV/LV cable
(if required)
- Check cable fix to cable tray and ladder properly.
HSFP-EL-
001
W W M
-
8/17/2019 Inspection Test Plan for Electrical
6/38
Client : SEC, Kingdom of Saudi Arabia
Disc : Electrical
Item : Cable / Tray / Condui t
INSPECTION & TEST PLAN (ITP) ITP No. : S-00-TAA-Q-43-036-002 Rev. 0Page : 6 of 38
Construction of Shuqaiq Steam Power Plant
Contract No. : 31221097/00
No Activit y Description FrequencyProcedure /
Spec.
Inspection Method / Acceptance CriteriaReporting
Format
Inspection By
RemarksSub-
Con HHI
SEC/
OE
4 Cable Installation
- Installation & Visual
Check.
- Insulation resistance
test
All Cable Approved venderDrawing Approved drawing
- Check cable tags correct.
- Check cable caps for protection of cable ends
Shall be properly protected after installation.
HSFP-EL-001/01B
W W M
-
8/17/2019 Inspection Test Plan for Electrical
7/38
1Client : SEC, Kingdom of Saudi Arabia
Disc : Electrical
Item : MV / LV SWGR
INSPECTION & TEST PLAN (ITP) ITP No. : S-00-TAA-Q-43-036-003 Rev. 0Page : 7 of 38
Construction of Shuqaiq Steam Power Plant
Contract No. : 31221097/00
No Activit y Description FrequencyProcedure /
Spec.
Inspection Method / Acceptance CriteriaReporting
Format
Inspection By
RemarksSub-
Con HHI
SEC/
OE
1 Material VerificationReceiving Inspection
- Raw Material
100% Related POS/Material Spec.,
General Ass’y Drawing
Receiving Insp. Pr ocedure: S-00-TAA-Q-43-008-001
As per Specified in Applicable Specification and
Drawing
- No Damage, Corrosion & Deformation
- Shall be properly laid out on wooden supports
clear of the soil.
- Check Shock indicator (if required)
HSFP-ST-01 W W R
2 MV/LV SWGR
-Installation & Visual
Check.
-Busbar conductivity Check.
-Insulation resistance test.
Each Unit - Approved vender
Drawing
- Approved drawing
-Technical
specification(SEC)
- Check installation method as per installation
drawing.
- Check doors and panels to ensure proper
opening and closure.
- Check paint damage, tag plate, warning label
, visual damage etc.
HSFP-EL-006
W W W
* Legend : R (Review Point) : To determine subject matter has achieved objectives.
M (Monitoring) : Periodic and systematic check (does not imply any action will be taken)
W (Witness Point) : Observation of an activity to ensure work is progressing as per requirements.
H (Hold Point) : A point beyond which an activity must not proceed without the approval of a designated organization or authority, SEC/OE’s Inspector.
-
8/17/2019 Inspection Test Plan for Electrical
8/38
Client : SEC, Kingdom of Saudi Arabia
Item : Electrical
Item : MV / LV SWGR
INSPECTION & TEST PLAN (ITP) ITP No. : S-00-TAA-Q-43-036-003 Rev. 0Page : 8 of 38
Construction of Shuqaiq Steam Power Plant
Contract No. : 31221097/00
No Activit y Description FrequencyProcedure /
Spec.
Inspection Method / Acceptance CriteriaReporting
Format
Inspection By
RemarksSub-
Con HHI
SEC/
OE
2 MV/LV SWGR
-Installation & Visual
Check.-Busbar conductivity
Check.
-Insulation resistance test
Each Unit - Approved vender
Drawing
- Approved drawing
- Technical
specification(SEC)
- Check fuse rating, main parts rating / type.
- CT/VT ratios shall be visualy checked against
drawing.
- Check operation of safety shutter.
- Check busbars are installed at correct location.
- Check busbars connection tight ness and correct
phasing.
- Torque check of busbar connection as per
manufacturer recommendation.
- Check busbars conductivity (end to end)
- Check the condition of earthing bar and
connections, measure continuity of switchboard
to main earth.
-Check insulation resistance values of busbars
HSFP-EL-
006
W W W
-
8/17/2019 Inspection Test Plan for Electrical
9/38
Client : SEC, Kingdom of Saudi Arabia
Disc : Electrical
Item : Motor Control Center
INSPECTION & TEST PLAN (ITP) ITP No. : S-00-TAA-Q-43-036-004 Rev. 0Page : 9 of 38
Construction of Shuqaiq Steam Power Plant
Contract No. : 31221097/00
No Activit y Description FrequencyProcedure /
Spec.
Inspection Method / Acceptance CriteriaReporting
Format
Inspection By
RemarksSub-
Con HHI
SEC/
OE
1 Material VerificationReceiving Inspection
- Raw Material
100% Related POS/Material Spec.,
General Ass’yDrawing
Receiving Insp.Procedure: S-00-TAA-Q-43-008-001
As per Specified in Applicable Specification and
Drawing
- No Damage, Corrosion & Deformation
- Shall be properly laid out on wooden supports
clear of the soil.
HSFP-ST-01 W W R
2 Motor Control Center
-Installation & Visual
Check.
-Busbar conductivity Check.
-Insulation resistance test.
Each Unit - Approved vender
Drawing
- Approved drawing
-Technical
specification(SEC)
- Check installation method as per installation
drawing.
- Check doors and panels to ensure proper
opening and closure.
- Check paint damage, tag plate, warning label
, visual damage etc.
HSFP-EL-005
W W W
* Legend : R (Review Point) : To determine subject matter has achieved objectives.
M (Monitoring) : Periodic and systematic check (does not imply any action will be taken)
W (Witness Point) : Observation of an activity to ensure work is progressing as per requirements.
H (Hold Point) : A point beyond which an activity must not proceed without the approval of a designated organization or authority, SEC/OE’s Inspector.
-
8/17/2019 Inspection Test Plan for Electrical
10/38
Client : SEC, Kingdom of Saudi Arabia
Item : Electrical
Item : Motor Control Center
INSPECTION & TEST PLAN (ITP) ITP No. : S-00-TAA-Q-43-036-004 Rev. 0Page : 10 of 38
Construction of Shuqaiq Steam Power Plant
Contract No. : 31221097/00
No Activit y Description FrequencyProcedure /
Spec.
Inspection Method / Acceptance CriteriaReporting
Format
Inspection By
RemarksSub-
Con HHI
SEC/
OE
3 Motor Control Center.
-Installation & VisualCheck.
-Busbar conductivity Check.
-Insulation resistance test
Each Unit - Approved vender
Drawing
- Approved drawing
- Technical
specification(SEC)
- Check fuse rating, main parts rating / type.
- Check operation of safety shutter.
- Check busbars are installed at correct location.
- Check busbars connection tight ness and correct
phasing.
- Torque check of busbar connection as per
manufacturer recommendation.
- Check busbars conductivity.
- Check the condition of earthing bar and
connections, measure continuity of switchboard
to main earth.
-Check insulation resistance values of busbars
HSFP-EL-
005
W W W
-
8/17/2019 Inspection Test Plan for Electrical
11/38
Client : SEC, Kingdom of Saudi Arabia
Disc : Electrical
Item : Transformer
INSPECTION & TEST PLAN (ITP) ITP No. : S-00-TAA-Q-43-036-005 Rev. 0Page : 11 of 38
Construction of Shuqaiq Steam Power Plant
Contract No. : 31221097/00
No Activit y Description FrequencyProcedure /
Spec.
Inspection Method / Acceptance CriteriaReporting
Format
Inspection By
RemarksSub-
Con HHI
SEC/
OE
1 Material VerificationReceiving Inspection
- Raw Material
EachDelivery
Related POS/Material Spec.,
General Ass’yDrawing
Receiving Insp.Procedure: S-00-TAA-Q-43-008-001
As per Specified in Applicable Specification and
Drawing
- No Damage, Corrosion & Deformation
- Shall be properly laid out on wooden supports
clear of the soil.
- Check Shock indicator or Shock record
(if required)
HSFP-ST-01 W W R
2 Transformer
-Installation & Visual
Check.
-Insulation resistance test
-Oil level & dielectric Check
Each Unit Approved vender
Drawing
Approved drawing
Technical
specification(SEC)
- Check installation method as per installation
drawing.
- Check paint damage, tag plate, warning label,
visual damage etc.
-Check insulation resistance for HV-earth
/ LV-earth
- Check explicit all porcelain & other bushings
For damages on the surface
HSFP-EL-011 W W M
* Legend : R (Review Point) : To determine subject matter has achieved objectives.
M (Monitoring) : Periodic and systematic check (does not imply any action will be taken)
W (Witness Point) : Observation of an activity to ensure work is progressing as per requirements.
H (Hold Point) : A point beyond which an activity must not proceed without the approval of a designated organization or authority, SEC/OE’s Inspector.
-
8/17/2019 Inspection Test Plan for Electrical
12/38
Client : SEC, Kingdom of Saudi Arabia
Disc : Electrical
Item : Transformer
INSPECTION & TEST PLAN (ITP) ITP No. : S-00-TAA-Q-43-036-005 Rev. 0Page : 12 of 38
Construction of Shuqaiq Steam Power Plant
Contract No. : 31221097/00
No Activit y Description FrequencyProcedure /
Spec.
Inspection Method / Acceptance CriteriaReporting
Format
Inspection By
RemarksSub-
Con HHI
SEC/
OE
2 Transformer
-Installation & VisualCheck.
-Insulation resistance test
-Oil level & dielectric Check
Each Unit Approved vender
Drawing
Approved drawing
Technicalspecification(SEC)
- Check no-load tap changer for proper
movement.
- Check continuity on all tap position.
- Check oil colour and smell.
- Check connection as approved drawing.
- Check neutral earthing connection.
- Measure neutral earthing, equipment earthing
continuity.
- Check oil level and pressure level.
-
HSFP-EL-011W W W
-
8/17/2019 Inspection Test Plan for Electrical
13/38
Client : SEC, Kingdom of Saudi Arabia
Disc : Electrical
Item : AC / DC UPS System
INSPECTION & TEST PLAN (ITP) ITP No. : S-00-TAA-Q-43-036-006 Rev. 0Page : 13 of 38
Construction of Shuqaiq Steam Power Plant
Contract No. : 31221097/00
No Activit y Description FrequencyProcedure /
Spec.Inspection Method / Acceptance Criteria
ReportingFormat
Inspection By
RemarksSub-
Con HHI
SEC/
OE
1 Material VerificationReceiving Inspection
- Raw Material
100% Related POS/Material Spec.,
General Ass’yDrawing
Receiving Insp.Procedure: S-00-TAA-Q-43-008-001
As per Specified in Applicable Specification and
Drawing
- No Damage, Corrosion & Deformation
- Shall be properly laid out on wooden supports
clear of the soil.
HSFP-ST-01 W W R
2 AC / DC UPS System
-Installation & Visual
Check.
Each Set - Approved vender
Drawing
- Approved drawing
-Technicalspecification(SEC)
- Check installation method as per installation
drawing.
- Check paint damage, tag plate, warning label,
visual damage etc.
- Check installation of inter-connection cabling as
per approved drawing.
HSFP-EL-003
HSFP-EL-004
W W W
* Legend : R (Review Point) : To determine subject matter has achieved objectives.
M (Monitoring) : Periodic and systematic check (does not imply any action will be taken)
W (Witness Point) : Observation of an activity to ensure work is progressing as per requirements.
H (Hold Point) : A point beyond which an activity must not proceed without the approval of a designated organization or authority, SEC/OE’s Inspector.
-
8/17/2019 Inspection Test Plan for Electrical
14/38
Client : SEC, Kingdom of Saudi Arabia
Item : Electrical
Item : AC / DC UPS System
INSPECTION & TEST PLAN (ITP) ITP No. : S-00-TAA-Q-43-036-006 Rev. 0Page : 14 of 38
Construction of Shuqaiq Steam Power Plant
Contract No. : 31221097/00
No Activit y Description FrequencyProcedure /
Spec.Inspection Method / Acceptance Criteria
ReportingFormat
Inspection By
RemarksSub-
Con HHI
SEC/
OE
2 AC / DC UPS System
-Installation & Visual
Check.
Each Set - Approved vender
Drawing
- Approved drawing
- Technical
specification(SEC)
- Check main parts rating / type as per relevant
drawing.
- Check isolation switch Open / Close.
- Check earthing for system cubicle.
- Check battery type.
-
HSFP-EL-003
HSFP-EL-004
W W W
-
8/17/2019 Inspection Test Plan for Electrical
15/38
Client : SEC, Kingdom of Saudi Arabia
Disc : Electrical
Item : BUS DUCT
INSPECTION & TEST PLAN (ITP) ITP No. : S-00-TAA-Q-43-036-007 Rev. 0Page : 15 of 38
Construction of Shuqaiq Steam Power Plant
Contract No. : 31221097/00
No Activit y Description FrequencyProcedure /
Spec.Inspection Method / Acceptance Criteria
ReportingFormat
Inspection By
RemarksSub-
Con HHI
SEC/
OE
1 Material VerificationReceiving Inspection
- Raw Material
100% Related POS/Material Spec.,
General Ass’yDrawing
Receiving Insp.Procedure: S-00-TAA-Q-43-008-001
As per Specified in Applicable Specification and
Drawing
- No Damage, Corrosion & Deformation
- Shall be properly laid out on wooden supports
clear of the soil.
- Check the group Identification number of BUS
DUCT (If required)
HSFP-ST-01W W R
2 BUS DUCT
-Installation & Visual
Check.
-Busbar conductivity Check.
-Insulation resistance test.
Each Set - Approved vender
Drawing
- Approved drawing
-Technical
specification(SEC)
- Check the position of equipment to be connected
with regard to the layout drawing.
- Check assemble & install support as detail
- Check paint damage, tag plate, warning label,
visual damage etc.
- Torque check of busbar connection per vendor
Recommendation.
HSFP-EL-010
W W W
* Legend : R (Review Point) : To determine subject matter has achieved objectives.
M (Monitoring) : Periodic and systematic check (does not imply any action will be taken)
W (Witness Point) : Observation of an activity to ensure work is progressing as per requirements.
H (Hold Point) : A point beyond which an activity must not proceed without the approval of a designated organization or authority, SEC/OE’s Inspector.
-
8/17/2019 Inspection Test Plan for Electrical
16/38
Client : SEC, Kingdom of Saudi Arabia
Item : Electrical
Item : BUS DUCT
INSPECTION & TEST PLAN (ITP) ITP No. : S-00-TAA-Q-43-036-007 Rev. 0Page : 16 of 38
Construction of Shuqaiq Steam Power Plant
Contract No. : 31221097/00
No Activit y Description FrequencyProcedure /
Spec.Inspection Method / Acceptance Criteria
ReportingFormat
Inspection By
RemarksSub-
Con HHI
SEC/
OE
2 BUS DUCT
-Installation & VisualCheck.
-Busbar conductivity Check.
-Insulation resistance test
Each Set - Approved vender
Drawing
- Approved drawing
- Technical
specification(SEC)
- Check the phase sequence of the connection.
- Check the connection of switchboard bus duct
section.
- Check busbars are installed at correct location.
- Check busbar conductivity test.
- Check insulation resistance of busbar
- Check the instrument air condition.
HSFP-EL-
010
W W W
-
8/17/2019 Inspection Test Plan for Electrical
17/38
Client : SEC, Kingdom of Saudi Arabia
Disc : Electrical
Item : Distribution Board(Incl UPS
AC/DC Boar d.
INSPECTION & TEST PLAN (ITP)ITP No. : S-00-TAA-Q-43-036-008 Rev. 0
Page : 17 of 38Construction of Shuqaiq Steam Power Plant
Contract No. : 31221097/00
No Activit y Description Frequency Procedure /Spec. Inspection Method / Acceptance Criteria ReportingFormat
Inspection By
RemarksSub-Con
HHISEC/OE
1 Material VerificationReceiving Inspection
100% Related POS/Material Spec.,
General Ass’y Drawing
Receiving Insp. Procedure: S-00-TAA-Q-43-008-001
As per Specified in Applicable Specification and
Drawing
- No Damage, Corrosion & Deformation
- Shall be properly laid out on wooden supports
clear of the soil.
HSFP-ST-01 W W R
2 Distribution Board
-Installation & Visual
Check.
.
Each Unit- Approved vender
Drawing
- Approved drawing
-Technical
specification(SEC)
- Check installation method as per installation
drawing.
- Check assemble & install supports as drawing.
- Check paint damage, tag plate, warning label
, visual damage etc.
HSFP-EL-007
W W W
* Legend : R (Review Point) : To determine subject matter has achieved objectives.
M (Monitoring) : Periodic and systematic check (does not imply any action will be taken)
W (Witness Point) : Observation of an activity to ensure work is progressing as per requirements.
H (Hold Point) : A point beyond which an activity must not proceed without the approval of a designated organization or authority, SEC/OE’s Inspector.
-
8/17/2019 Inspection Test Plan for Electrical
18/38
Client : SEC, Kingdom of Saudi Arabia
Item : Electrical
Item : Distributio n Board(Incl UPS
AC/DC Board.
INSPECTION & TEST PLAN (ITP) ITP No. : S-00-TAA-Q-43-036-008 Rev. 0Page : 18 of 38
Construction of Shuqaiq Steam Power Plant
Contract No. : 31221097/00
No Activit y Description FrequencyProcedure /
Spec.Inspection Method / Acceptance Criteria
ReportingFormat
Inspection By
RemarksSub-
Con HHI
SEC/
OE
2 Distribution Board
-Installation & Visual
Check.
Each Unit - Approved vender
Drawing
- Approved drawing
- Technical
specification(SEC)
- Check MCB rating, main parts rating / type.
- Check the condition of earthing bar and
connections, measure continuity of switchboard
to main earth.
HSFP-EL-
007W W W
-
8/17/2019 Inspection Test Plan for Electrical
19/38
Client : SEC, Kingdom of Saudi Arabia
Disc : Electrical
Item : Motor
INSPECTION & TEST PLAN (ITP) ITP No. : S-00-TAA-Q-43-036-009 Rev. 0Page : 19 of 38
Construction of Shuqaiq Steam Power Plant
Contract No. : 31221097/00
No Activit y Description FrequencyProcedure /
Spec.Inspection Method / Acceptance Criteria
ReportingFormat
Inspection By
RemarksSub-
Con HHI
SEC/
OE
1 Material VerificationReceiving Inspection
- Raw Material
100% Related POS/Material Spec.,
General Ass’y Drawing
Receiving Insp. Pr ocedure: S-00-TAA-Q-43-008-001
As per Specified in Applicable Specification and
Drawing
- No Damage, Corrosion & Deformation
- Shall be properly laid out on wooden supports
clear of the soil.
HSFP-ST-01 W W R
2 Motor
-Installation & Visual
Check.
-Insulation Check.
Each Unit- Approved vender
Drawing
- Approved drawing
-Technical
specification(SEC)
- Check orientation of installation correct as per
drawing.
- Check motor name plate, visual damage etc.
- Check insulation resistance values of motor.
- Check insulation resistance values of motor
space heater and temperature detector.
- Check motor earthing connection.
HSFP-EL-002
W W W
* Legend : R (Review Point) : To determine subject matter has achieved objectives.
M (Monitoring) : Periodic and systematic check (does not imply any action will be taken)
W (Witness Point) : Observation of an activity to ensure work is progressing as per requirements.
H (Hold Point) : A point beyond which an activity must not proceed without the approval of a designated organization or authority, SEC/OE’s Inspector.
-
8/17/2019 Inspection Test Plan for Electrical
20/38
Client : SEC, Kingdom of Saudi Arabia
Item : Electrical
Item : Motor
INSPECTION & TEST PLAN (ITP) ITP No. : S-00-TAA-Q-43-036-009 Rev. 0Page : 20 of 38
Construction of Shuqaiq Steam Power Plant
Contract No. : 31221097/00
No Activit y Description FrequencyProcedure /
Spec.Inspection Method / Acceptance Criteria
ReportingFormat
Inspection By
RemarksSub-
Con HHI
SEC/
OE
2 Motor
-Installation & VisualCheck.
-Insulation Check.
Each Unit - Approved vender
Drawing
- Approved drawing
- Technical
specification(SEC)
- Check power / control / space heater cable
are connected correctly.
- Check the correct condition(Gland /Foundation
Level)
HSFP-EL-
002
W W W
-
8/17/2019 Inspection Test Plan for Electrical
21/38
Client : SEC, Kingdom of Saudi Arabia
Disc : Electrical
Item : Cathodic
INSPECTION & TEST PLAN (ITP) ITP No. : S-00-TAA-Q-43-036-010 Rev. 0Page : 21 of 38
Construction of Shuqaiq Steam Power Plant
Contract No. : 31221097/00
No Activit y Description FrequencyProcedure /
Spec.Inspection Method / Acceptance Criteria
ReportingFormat
Inspection By
RemarksSub-
Con HHI
SEC/
OE
1 Material Verification
Receiving Inspection
- Raw Material
100% Related POS/Material Spec.,
General Ass’y Drawing
Receiving Insp. Pr ocedure: S-00-TAA-Q-43-008-001
As per Specified in Applicable Specification and
Drawing
- No Damage, Corrosion & Deformation
- Shall be properly laid out on wooden supports
clear of the soil.
HSFP-ST-01 W W R
2 Cathodic
-Installation & VisualCheck.
-Insulation resistance test.
-Installation Check of anode
Each Set - Approved vender
Drawing
- Approved drawing
-Technical
specification(SEC)
1. Common check point
- Check assemble & install supports as drawing.
- Check paint damage, tag plate, warning label,
visual damage etc.
- Check fuse rating , main parts rating / type.
- Check & verify the thermit weld condition.
- Check fuse rating, main parts rating / type.
HSFP-EL-022
W W W
* Legend : R (Review Point) : To determine subject matter has achieved objectives.
M (Monitoring) : Periodic and systematic check (does not imply any action will be taken)
W (Witness Point) : Observation of an activity to ensure work is progressing as per requirements.
H (Hold Point) : A point beyond which an activity must not proceed without the approval of a designated organization or authority, SEC/OE’s Inspector.
-
8/17/2019 Inspection Test Plan for Electrical
22/38
Client : SEC, Kingdom of Saudi Arabia
Item : Electrical
Item : Cathodic
INSPECTION & TEST PLAN (ITP) ITP No. : S-00-TAA-Q-43-036-010 Rev. 0Page : 22 of 38
Construction of Shuqaiq Steam Power Plant
Contract No. : 31221097/00
No Activit y DescriptionFrequen
cyProcedure /
Spec.Inspection Method / Acceptance Criteria
ReportingFormat
Inspection By
RemarksSub-
ConHHI
SEC/
OE
2 Cathodic
-Installation & Visual
Check.
-Insulation resistance test.
-Installation Check of anode
Each
Set
- Approved vender
Drawing
- Approved drawing
- Technical
specification(SEC)
- Check mechanical integrity of cable connection.
- Check epoxy encapsulation of weld.
- Measure the cable resistance to pipe.
- Check location as per requirement and approved
drawing.
- Check anode length,size, and physical damages.
- Check the reference electrode had been soaked.
- Check access point installed beneath isolation
joint.
2, Installation Check & Testing (Sacrificial Anode)
- Check no physical damages, sand bedded and
soaked prior install.
- Check Mg, anode are installed at correct location
- Check anode installed horizontally and paralled
to the pipe per vendor recommendation.
3, Installation Check & Testing (MMO Anode)
- Check if any damages of MMO canistered anode
- Check anode length,size, and physical damages
- Check correct location, depth according to the
approved drawing.
HSFP-EL-
022
W W W
-
8/17/2019 Inspection Test Plan for Electrical
23/38
Client : SEC, Kingdom of Saudi Arabia
Disc : Electrical
Item : Earthing and Bonding
INSPECTION & TEST PLAN (ITP) ITP No. : S-00-TAA-Q-43-036-011 Rev. 0Page : 23 of 38
Construction of Shuqaiq Steam Power Plant
Contract No. : 31221097/00
No Activit y Description FrequencyProcedure /
Spec.Inspection Method / Acceptance Criteria
ReportingFormat
Inspection By
RemarksSub-
ConHHI
SEC/
OE
1 Material VerificationReceiving Inspection
- Raw Material
100% Related POS/Material Spec.,
General Ass’y Dr awing
Receiving Insp.Procedure: S-00-TAA-Q-43-008-001
As per Specified in Applicable Specification and
Drawing
- No Damage, Corrosion & Deformation
- Shall be properly laid out on wooden supports
clear of the soil.
HSFP-ST-01W W R
2 Earthing and Bonding
-Earthing electrode /Cable
Route / Cable connection.
-Inspection earth pit check.
-Electrical system earthing
test
Each unit&
Equipment
Approved vender
Drawing
Approved drawing
Technical
specification(SEC
)
- Verify the marking points for installation rod
As per construction drawing.
- Check and verify the installation of earthing rod
As per project specification.
- Verify the completed section of depth of the
Cable as per specification and construction
-
HSFP-EL-018
HSFP-EL-019
W W W
* Legend : R (Review Point) : To determine subject matter has achieved objectives.
M (Monitoring) : Periodic and systematic check (does not imply any action will be taken)
W (Witness Point) : Observation of an activity to ensure work is progressing as per requirements.
H (Hold Point) : A point beyond which an activity must not proceed without the approval of a designated organization or authority, SEC/OE’s Inspector.
-
8/17/2019 Inspection Test Plan for Electrical
24/38
Client : SEC, Kingdom of Saudi Arabia
Disc : Electrical
Item : Earthing and Bonding
INSPECTION & TEST PLAN (ITP) ITP No. : S-00-TAA-Q-43-036-011 Rev. 0Page : 24 of 38
Construction of Shuqaiq Steam Power Plant
Contract No. : 31221097/00
No Activit y Description FrequencyProcedure /
Spec.Inspection Method / Acceptance Criteria
ReportingFormat
Inspection By
RemarksSub-
ConHHI
SEC/
OE
2 Earthing and Bonding
-Earthing electrode /Cable
Route / Cable connection.
-Inspection earth pit check.
-Electrical system earthing
test
Each unit
&
Equipment
Approved vender
Drawing
Approved drawing
Technical
specification(SEC)
- Verify cable kicker pipes or protection pipes are
adequately
- Check cable size and connection.
- Check cable protection.
- Compression type splice or thermo-weld
connection, wrapped with insulation tape.
- Check inspection earth pit according to the
construction drawing.
- Check earth bar according to the construction
Drawing.
Check individual electrode resistance value.
- Check group or plant earth resistance value
- Check earth connection between the electrode
and the supply neutral and plant earth loop
continuity.
- Check connection of clean earth to plant earth.
HSFP-EL-
018
HSFP-EL-
019
W W W
-
8/17/2019 Inspection Test Plan for Electrical
25/38
Client : SEC, Kingdom of Saudi Arabia
Disc : Electrical
Item : Lighti ng System
INSPECTION & TEST PLAN (ITP) ITP No. : S-00-TAA-Q-43-036-012 Rev. 0Page : 25 of 38
Construction of Shuqaiq Steam Power Plant
Contract No. : 31221097/00
No Activit y Description FrequencyProcedure /
Spec.Inspection Method / Acceptance Criteria
ReportingFormat
Inspection By
RemarksSub-
ConHHI
SEC/
OE
1 Material VerificationReceiving Inspection
- Raw Material
100% Related POS/Material Spec.,
General Ass’y Drawing
Receiving Insp. Pr ocedure: S-00-TAA-Q-43-008-001
As per Specified in Applicable Specification and
Drawing
- No Damage, Corrosion & Deformation
- Shall be properly laid out on wooden supports
clear of the soil.
HSFP-ST-01
W W R
2 Lighting System.
-Installation & Visual
Check.
-Insulation Resistance test.
Each unit&
Equipment
Approved vender
Drawing
Approved drawing
Technical
specification(SEC)
- Check installation method as per installation
drawing.
- Check paint damage, tag plate, warning label
, visual damage etc.
- Check cable size and connection.
- Check lighting model and type with lamp type.
- Fixtures tag number.
HSFP-EL-012
W W W
* Legend : R (Review Point) : To determine subject matter has achieved objectives.
M (Monitoring) : Periodic and systematic check (does not imply any action will be taken)
W (Witness Point) : Observation of an activity to ensure work is progressing as per requirements.
H (Hold Point) : A point beyond which an activity must not proceed without the approval of a designated organization or authority, SEC/OE’s Inspector.
-
8/17/2019 Inspection Test Plan for Electrical
26/38
1Client : SEC, Kingdom of Saudi Arabia
Disc : Electrical
Item : Lighti ng System
INSPECTION & TEST PLAN (ITP) ITP No. : S-00-TAA-Q-43-036-012 Rev. 0Page : 26 of 38
Construction of Shuqaiq Steam Power Plant
Contract No. : 31221097/00
No Activit y Description FrequencyProcedure /
Spec.Inspection Method / Acceptance Criteria
ReportingFormat
Inspection By
RemarksSub-
ConHHI
SEC/
OE
2 Lighting System.
-Installation & Visual
Check.
-Insulation Resistance test.
Each unit
&
Equipment
Approved vender
Drawing
Approved drawing
Technical
specification(SEC)
- Check type of Ex-Protection.
- Check spare hole / cover to seal and cover
tightened.
- Check the earthing wire connection properly.
- Verify continuity and insulation resistance.
- Check the light cable condition
(rigid or flexible conduits, cable glands)
HSFP-EL-012
W W W
-
8/17/2019 Inspection Test Plan for Electrical
27/38
Client : SEC, Kingdom of Saudi Arabia
Disc : Electrical
Item : Lightning Protection
INSPECTION & TEST PLAN (ITP) ITP No. : S-00-TAA-Q-43-036-013 Rev. 0Page : 27 of 38
Construction of Shuqaiq Steam Power Plant
Contract No. : 31221097/00
No Activity Description FrequencyProcedure /
Spec.Inspection Method / Acceptance Criteria
ReportingFormat
Inspection By
RemarksSub-
ConHHI
SEC/
OE
1 Material VerificationReceiving Inspection
- Raw Material
100% Related POS/Material Spec.,
General Ass’y Drawing
Receiving Insp. Pr ocedure: S-00-TAA-Q-43-008-001
As per Specified in Applicable Specification and
Drawing
- No Damage, Corrosion & Deformation
- Shall be properly laid out on wooden supports
clear of the soil.
Mill Certificate&HSFP-ST-01
W W R
2 Lightning Protection.
-Installation & Visual
Check.
Each unit&
Equipment
Approved vender
Drawing
Approved drawing
Technical
specification(SEC)
- Check installation method as per installation
drawing.
- Check tag plate, visual damage etc.
- Check cable size and connection.
- Check lightning model and type.
- Fixtures tag number.
- Check the earthing wire connection properly.
- Verify continuity and insulation resistance.
HSFP-EL-030 W W W
* Legend : R (Review Point) : To determine subject matter has achieved objectives.
M (Monitoring) : Periodic and systematic check (does not imply any action will be taken)
W (Witness Point) : Observation of an activity to ensure work is progressing as per requirements.
H (Hold Point) : A point beyond which an activity must not proceed without the approval of a designated organization or authority, SEC/OE’s Inspector.
-
8/17/2019 Inspection Test Plan for Electrical
28/38
Client : SEC, Kingdom of Saudi Arabia
Disc : Electrical
Item : Receptacle, Junc tion Box,RCU
INSPECTION & TEST PLAN (ITP) ITP No. : S-00-TAA-Q-43-036-014 Rev. 0Page : 28 of 38
Construction of Shuqaiq Steam Power Plant
Contract No. : 31221097/00
No Activit y Description FrequencyProcedure /
Spec.Inspection Method / Acceptance Criteria
ReportingFormat
Inspection By
RemarksSub-
ConHHI
SEC/
OE
1 Material VerificationReceiving Inspection
- Raw Material
100% Related POS/Material Spec.,
General Ass’y Dr awing
Receiving Insp.Procedure: S-00-TAA-Q-43-008-001
As per Specified in Applicable Specification and
Drawing
- No Damage, Corrosion & Deformation
- Shall be properly laid out on wooden supports
clear of the soil.
HSFP-ST-01 W W R
2 Receptacle & Junction Box.
RCU.
-Installation & Visual
Check.
-Insulation Resistance test
Each unit&
Equipment
Approved vender
Drawing
Approved drawing
Technical
specification(SEC
)
- Check installation method as per installation
drawing.
- Check paint damage, name plate, warning label
, visual damage etc. incl (IP protection class)
- Check adequate protection for fittings and cable
Against corrosion weather etc.
- Check earthing bonding correct.
HSFP-EL-
009
HSFP-EL-
013
HSFP-EL-
014
HSFP-EL-
021
W W W
* Legend : R (Review Point) : To determine subject matter has achieved objectives.
M (Monitoring) : Periodic and systematic check (does not imply any action will be taken)
W (Witness Point) : Observation of an activity to ensure work is progressing as per requirements.
H (Hold Point) : A point beyond which an activity must not proceed without the approval of a designated organization or authority, SEC/OE’s Inspector.
-
8/17/2019 Inspection Test Plan for Electrical
29/38
1Client : SEC, Kingdom of Saudi Arabia
Disc : Electrical
Item : Receptacle, Junctio n Box,RCU
INSPECTION & TEST PLAN (ITP) ITP No. : S-00-TAA-Q-43-036-014 Rev. 0Page : 29 of 38
Construction of Shuqaiq Steam Power Plant
Contract No. : 31221097/00
No Activit y Description FrequencyProcedure /
Spec.Inspection Method / Acceptance Criteria
ReportingFormat
Inspection By
RemarksSub-
ConHHI
SEC/
OE
2 Receptacle & Junction Box.
RCU
-Installation & Visual
Check.
-Insulation Resistance test
Each unit&
Equipment
Approved vender
Drawing
Approved drawing
Technical
specification(SEC
- Check type of IP protection class &
Ex-Protection.
- Check spare hole / cover to seal and cover
tightened.
- Inspect wiring inside the junction boxes for
Correct wiring method and wire splicing.
- Verify continuity and insulation resistance.
- Check zone applicable safety code.
- Check that the appropriate cover is installed for
each type of receptacle.
- Verify the position of switch according to the
specification.
HSFP-EL-
009
HSFP-EL-
013
HSFP-EL-
014
HSFP-EL-021
HSFP-EL-
021
W W W
-
8/17/2019 Inspection Test Plan for Electrical
30/38
1Client : SEC, Kingdom of Saudi Arabia
Disc : Electrical
Item : Cable / Tray / Condu it (Telecom)
INSPECTION & TEST PLAN (ITP) ITP No. : S-00-TAA-Q-43-036-015 Rev. 0Page : 30 of 38
Construction of Shuqaiq Steam Power Plant
Contract No. : 31221097/00
No Activit y Description FrequencyProcedure /
Spec.Inspection Method / Acceptance Criteria
ReportingFormat
Inspection By
RemarksSub-
ConHHI
SEC/
OE
1 Material VerificationReceiving Inspection
- Raw Material
100% Related POS/Material Spec.,
General Ass’y Dr awing
Receiving Insp.Procedure: S-00-TAA-Q-43-008-001
As per Specified in Applicable Specification and
Drawing
- No Damage, Corrosion & Deformation
- Shall be properly laid out on wooden supports
clear of the soil.
HSFP-ST-01 W W R
2 Installation Cable Tray,Ladder and ConduitInstallation.
100% Approveddrawing.
Vender Drawing
- Check tag numbers are correct.
- Verify Cable tray and tray installed as per
construction drawing.
- Check alignment as overlapped of trays.
- Check bonding jumpers installed at tray joint
connections and tight.
HSFP-TE-001
W W M
* Legend : R (Review Point) : To determine subject matter has achieved objectives.
M (Monitoring) : Periodic and systematic check (does not imply any action will be taken)
W (Witness Point) : Observation of an activity to ensure work is progressing as per requirements.
H (Hold Point) : A point beyond which an activity must not proceed without the approval of a designated organization or authority, SEC/OE’s Inspector.
-
8/17/2019 Inspection Test Plan for Electrical
31/38
Client : SEC, Kingdom of Saudi Arabia
Disc : Electrical
Item : Cable / Tray / Condui t(Telecom)
INSPECTION & TEST PLAN (ITP) ITP No. : S-00-TAA-Q-43-036-015 Rev. 0Page : 31 of 38
Construction of Shuqaiq Steam Power Plant
Contract No. : 31221097/00
No Activity Description FrequencyProcedure /
Spec.Inspection Method / Acceptance Criteria
ReportingFormat
Inspection By
RemarksSub-
ConHHI
SEC/
OE
2 Installation Cable Tray,Ladder and ConduitInstallation.
100%Installation All Route
Approveddrawing.
Vender Drawing
- Check hold down clamp and brackets are installed.
- Check cable fix to cable tray and ladder properly.
- Check cable ladder properly supported.
- Check cover installed(to be installed after all the
cables are tested and properly terminated)
- Check junction box supports independent from
conduit and tray.
- Check conduit supports within the specified interval
according to approved drawing.
- Check touch up of galvanizing performed
(if required)
- No sharp edges.
- No obstructions.
HSFP-TE-001
W W M
3
Cable Installation- Installation & VisualCheck.
- Insulation resistance
Test
All Cable Approved venderDrawing
Approved drawing
- Check megger test on the reel
(For the construction : If required)
- Verify cable type & configuration.
HSFP-TE-001
W W M
-
8/17/2019 Inspection Test Plan for Electrical
32/38
Client : SEC, Kingdom of Saudi Arabia
Disc : Electrical
Item : Cable / Tray / Condu it(Telecom)
INSPECTION & TEST PLAN (ITP) ITP No. : S-00-TAA-Q-43-036-015 Rev. 0Page : 32 of 38
Construction of Shuqaiq Steam Power Plant
Contract No. : 31221097/00
No Activit y Description FrequencyProcedure /
Spec.Inspection Method / Acceptance Criteria
ReportingFormat
Inspection By
RemarksSub-
ConHHI
SEC/
OE
3 Cable Installation- Installation & VisualCheck.
- Insulation resistance
Test
All Cable Approved venderDrawing
Approved drawing
-
- Check and confirm cable shall be meggered before
And after installation, record of testing shall be
available.
- Check proper arrangement, segregation and layer
Of cable, bending radius as per vendor data, and
allowable Slack.
HSFP-TE-001
W W M
4 Cable Installation- Installation & Visual
Check.
- Insulation resistance
test
All Cable Approved venderDrawing
Approved drawing
- Check cable tags correct.
- Check cable caps for protection of cable ends
Shall be properly protected after installation.
HSFP-TE-001
W W M
-
8/17/2019 Inspection Test Plan for Electrical
33/38
Client : SEC, Kingdom of Saudi Arabia
Disc : Electrical
Item : CCTV
INSPECTION & TEST PLAN (ITP) ITP No. : S-00-TAA-Q-43-036-016 Rev. 0Page : 33 of 38
Construction of Shuqaiq Steam Power Plant
Contract No. : 31221097/00
No Activit y Description FrequencyProcedure /
Spec.Inspection Method / Acceptance Criteria
ReportingFormat
Inspection By
RemarksSub-
ConHHI
SEC/
OE
1 Material Verification
Receiving Inspection
- Raw Material
100% Related POS/Material Spec.,
General Ass’y Drawing
Receiving Insp. Pr ocedure: S-00-TAA-Q-43-008-001
As per Specified in Applicable Specification and
Drawing
- No Damage, type, specification, etc
HSFP-ST-01 W W R
2 CCTV Installation
-Installation & Visual
Check.
Each Unit - Approved Vender
Drawing
- Approved drawing
- Technical
specification(SEC)
- Check name plate, tag No,
- Check the camera’s are mounted on correct
location as per drawing.
- Check the correct lighting is provided for camera
- Check power & signal cables are fixed properly
with appropriate cable marking & The cable
length is ample for movement of camera.
HSFP-IN-004 W W W
* Legend : R (Review Point) : To determine subject matter has achieved objectives.
M (Monitoring) : Periodic and systematic check (does not imply any action will be taken)
W (Witness Point) : Observation of an activity to ensure work is progressing as per requirements.
H (Hold Point) : A point beyond which an activity must not proceed without the approval of a designated organization or authority, SEC/OE’s Inspector.
-
8/17/2019 Inspection Test Plan for Electrical
34/38
Client : SEC, Kingdom of Saudi Arabia
Item : Electrical
Item : CCTV
INSPECTION & TEST PLAN (ITP) ITP No. : S-00-TAA-Q-43-036-016 Rev. 0Page : 34 of 38
Construction of Shuqaiq Steam Power Plant
Contract No. : 31221097/00
No Activit y Description FrequencyProcedure /
Spec.Inspection Method / Acceptance Criteria
ReportingFormat
Inspection By
RemarksSub-
ConHHI
SEC/
OE
2 CCTV Installation
-Installation & Visual
Check.
Each Unit - Approved Vender
Drawing
- Approved drawing
- Technical
specification(SEC)
- Check the accessibility and facilities
maintenance.
- Check No damage.
- Check earthing connection.
HSFP-IN-004 W W W
-
8/17/2019 Inspection Test Plan for Electrical
35/38
Client : SEC, Kingdom of Saudi Arabia
Disc : Electrical
Item : PABX
INSPECTION & TEST PLAN (ITP) ITP No. : S-00-TAA-Q-43-036-017 Rev. 0Page : 35 of 38
Construction of Shuqaiq Steam Power Plant
Contract No. : 31221097/00
No Activit y Description FrequencyProcedure /
Spec.Inspection Method / Acceptance Criteria
ReportingFormat
Inspection By
RemarksSub-
Con
HHISEC/
OE
1 Material Verification
Receiving Inspection
- Raw Material
100% Related POS/Material Spec.,
General Ass’y Drawing
Receiving Insp. Pr ocedure: S-00-TAA-Q-43-008-001
As per Specified in Applicable Specification and
Drawing
- No Damage, type, specification, etc
HSFP-ST-01 W W R
2 PABX Installation
-Installation & Visual
Check.
Each Unit - Approved Vender
Drawing
- Approved drawing
- Technical
specification(SEC)
- Check name plate, tag No,
- Check the wiring as per construction drawing.
- Check the structured cabling cabinet are
installed as per drawing and orientation.
- Check the earthing and arresters for telecom
cabinet(if applicable).
HSFP-TE-002
HSFP-TE-003
W W W
* Legend : R (Review Point) : To determine subject matter has achieved objectives.
M (Monitoring) : Periodic and systematic check (does not imply any action will be taken)
W (Witness Point) : Observation of an activity to ensure work is progressing as per requirements.
H (Hold Point) : A point beyond which an activity must not proceed without the approval of a designated organization or authority, SEC/OE’s Inspector.
-
8/17/2019 Inspection Test Plan for Electrical
36/38
Client : SEC, Kingdom of Saudi Arabia
Item : Telecommunication
Item : PABX Installation
INSPECTION & TEST PLAN (ITP) ITP No. : S-00-TAA-Q-43-036-017 Rev. 0Page : 36 of 38
Construction of Shuqaiq Steam Power Plant
Contract No. : 31221097/00
No Activit y Description FrequencyProcedure /
Spec.Inspection Method / Acceptance Criteria
ReportingFormat
Inspection By
RemarksSub-
Con
HHISEC/
OE
2 PABX Installation
-Installation & Visual
Check.
100%- Approved Vender
Drawing
- Approved drawing
- Technical
specification(SEC)
- Check No damage.
- Verify the Explosion proof telephones are
mounted on easy accessible area.
HSFP-TE-002
HSFP-TE-003
W W W
-
8/17/2019 Inspection Test Plan for Electrical
37/38
Client : SEC, Kingdom of Saudi Arabia
Disc : Electrical
Item : Junction Box(Telecom)
INSPECTION & TEST PLAN (ITP) ITP No. : S-00-TAA-Q-43-036-018 Rev. 0Page : 37 of 38
Construction of Shuqaiq Steam Power Plant
Contract No. : 31221097/00
No Activit y Description FrequencyProcedure /
Spec.Inspection Method / Acceptance Criteria
ReportingFormat
Inspection By
RemarksSub-
Con
HHISEC/
OE
1 Material Verification
Receiving Inspection
- Raw Material
100% Related POS/Material Spec.,
General Ass’yDrawing
Receiving Insp.Procedure: S-00-TAA-Q-43-008-001
As per Specified in Applicable Specification and
Drawing
- No Damage, type, specification, etc
HSFP-ST-01 W W R
2 Junction Box Installation.
-Installation & Visual
Check.
Each Unit - Approved Vender
Drawing
- Approved drawing
- Technical
specification(SEC)
- Verify the junction box identification number.
- Check the junction box specification(cable gland
hole size and quantities and terminal block
arrangement etc.).
- Check earthing connection
- Check the junction box location.
HSFP-TE-005
W W W
* Legend : R (Review Point) : To determine subject matter has achieved objectives.
M (Monitoring) : Periodic and systematic check (does not imply any action will be taken)
W (Witness Point) : Observation of an activity to ensure work is progressing as per requirements.
H (Hold Point) : A point beyond which an activity must not proceed without the approval of a designated organization or authority, SEC/OE’s Inspector.
-
8/17/2019 Inspection Test Plan for Electrical
38/38
Client : SEC, Kingdom of Saudi Arabia
Item : Electrical
Item : Junction Box(Telecom)
INSPECTION & TEST PLAN (ITP) ITP No. : S-00-TAA-Q-43-036-018 Rev. 0Page : 38 of 38
Construction of Shuqaiq Steam Power Plant
Contract No. : 31221097/00
No Activit y Description FrequencyProcedure /
Spec.Inspection Method / Acceptance Criteria
ReportingFormat
Inspection By
RemarksSub-
Con
HHISEC/
OE
2 Junction Box Installation.
-Installation & Visual
Check.
Each Unit - Approved Vender
Drawing
- Approved drawing
- Technical
specification(SEC)
-- Check No damage.
- Check the insulation material between HDG and
stainless steel.
- Check the tightness.
- Check the support welding and touch up paint
Condition.
- Check the cable installed and terminated as per
approved drawing.
HSFP-TE-005
W W W