EXTERIOR GROUTING
OF FRAME
RISER RINGS-MAX. 6"18" to 24"
BOND ALL JOINTS WITH
MASTIC SEAL WITH KEY-
BASE SECTION
1’ to 4’
SECTION
ECCENTRIC
CONE SECTION
36"
CAST IRON
FRAME AND COVER
206
NOTES
1. STANDARD MANHOLE TO BE USED
FOR PIPES 24" AND LESS.
2. PRECAST CONCRETE STRUCTURES
SHALL HAVE STRENGTH OF 4000 PSI.
3. STANDARD MANHOLE DEPTH = 8’
TOP OF FRAME TO INVERT.
4. LATERAL LINES TO MATCH TOP OF
INLET PIPE AT MANHOLE.
5. ALL INTERIOR JOINTS AND CONNECT-
IONS SHALL BE WATER TIGHT,
AND GROUTED WITH NON-SHRINK
GROUT.
6. ALL MANHOLES SHALL BE VACUUM
TESTED PRIOR TO ACCEPTANCE.
7. BOND ALL MANHOLE SECTION
GROOVES WITH MASTIC SEAL.
INSIDEDROP MANHOLE
MANHOLE BASE
SEE STD.
DRAWING 203
RELINER DROP BOWL
OR EQUIVALENT
SECURE TO MANHOLE
WITH STAINLESS STEEL
FASTENERS
PIPE COUPLER
CHANNEL MANHOLE
TO DIRECT FLOW AS
REQUIRED
2’ to 4’
PLACE STEPS UPSTREAM
ON MAIN CHANNEL
LOCK JOINTS
SEE STD. DWG. 209
8. IF END OF LINE MANHOLE, STEPS SHALL
BE LOCATED ON DOWNSTREAM SIDE AND
CHANNEL SHALL BE CONSTRUCTED FULL
WIDTH OF INTERIOR.
FASTENER CONNECTIONS TO MANHOLE
TO BE A MIN OF 6" FROM ANY JOINT
6" MAX DIA. PVC PIPE SECURED TO
STRUCTUREWITH STAINLESS STEEL
FASTENERSAT 4’ INTERVALS (MIN. OF 2)
Newberg
City of
APPROVED
BY:
DATE:
SCALE: N.T.S.
D. Danicic
STANDARD
DRAWING
REVISIONS:
PUBLIC WORKS ENGINEERING DIVISION
414 E. FIRST STREET NEWBERG, OREGON 97132
PHONE 503-537-1240 - FAX 503-537-1277
May 2007