5:30 –5:35 p.m. Welcome and Introductions – Deputy Commissioner Jessica Fulton
5:35 – 5:55 p.m. Project Overview – Project Team
5:55 – 6:10 p.m. Next Steps
6:10 – 6:15 p.m. Keeping You Informed
6:15 – 6:30 p.m. Questions and Answers
Pre-construction Community Meeting AgendaDekalb Avenue Safety Improvements November 4, 2021
Insert Presentation Title
Jessica Fulton, ATLDOT Deputy Commissioner, Office of Capital Delivery
Michael Word, Construction Director
Kurt Martin, Construction Manager
Glen Behrend, DWM Construction Manager
Adrian Carver, Construction Outreach Liaison
Brandi Peck, Project Manager, Design
Dekalb Avenue Safety Improvements Team
Insert Presentation Title
PROJECT MAP
Insert Presentation Title
Project Scope
❑ Removal of reversible lane and associated signage
❑ Bicycle infrastructure and striping
❑ Pedestrian improvements include sidewalk repair and ADA
improvements
❑ Traffic signal upgrades
❑ Resurfacing
PROJECT OVERVIEW
Insert Presentation Title
SIDEWALKS & MOBILITYJackson Street to Ridgecrest Road (Typical Section)
Insert Presentation Title
BICYCLE INFRASTRUCTUREHurt Street to Elmira Place
Revisions include:• Two-way cycle track on north side• Addition of bicycle intersection
improvements• Moreland Avenue facilities include bicycle
signalization
Insert Presentation Title
All non-compliant ADA ramps to be brought up to compliance
Damaged sidewalk to be repaired
Missing sidewalk to be installed
Two new pedestrian crossing areas with refuge island and rectangular rapid
flashing beacons to be installed
❑ Ridgecrest Road (Access to Trail)
❑ Degress Avenue (Access to MARTA Stop)
PEDESTRIAN IMPROVEMENTS
Insert Presentation Title
Protected bicycle facilities:
❑ Dekalb Avenue from Hurt Street to Elmira Place
Striped bicycle facilities:
❑ Dekalb Avenue from Clifton Road to Arizona Avenue
❑ Whitefoord Avenue from Dekalb Avenue to LaFrance Street
BICYCLE INFRASTRUCTURE
Insert Presentation Title
Signal upgrades at intersections with:
❑ Krog Street
❑ Moreland Avenue
❑ Oakdale Road/Whitefoord Avenue
❑ Arizona Avenue
❑ Rocky Ford Road
TRAFFIC SIGNAL UPGRADES
Insert Presentation Title
Approximately 3 miles of Decatur Street/Dekalb Avenue from Jackson
Street to City Limits
Restriping
❑ Exclusive left-turn only lanes at all signalized intersections
❑ Center-turn lane throughout the remainder of the corridor
RESURFACING
Insert Presentation Title
Installation of portable message boards
Removal of reversible lane
❑ Pole and overhead signal removal
❑ Temporary striping
❑ Begin traffic signal improvements
Adjusting manhole and water valve
CONSTRUCTION ACTIVITIES
Insert Presentation Title
Concrete sidewalk, curb, gutter, and ADA ramp installation
Signage and pedestrian signal installation
CONSTRUCTION ACTIVITIES
Insert Presentation Title
Asphalt patching
Milling and resurfacing
Lane striping
CONSTRUCTION ACTIVITIES
Insert Presentation Title
Repair/replace stormwater infrastructure and catch basins
❑ Krog Street @ Dekalb Avenue work being performed by Department of
Watershed Management (DWM)
❑ Coordinating construction activities to lessen community impact
❑ Tentative start date – Q1 2022
CONSTRUCTION ACTIVITIES
Insert Presentation Title
DWM Dekalb Avenue/Krog Street Stormwater Project Update
Insert Presentation Title
Temporary, single-lane closures with possible traffic delays
❑ Pole and overhead signal removal
❑ Traffic signal improvement
❑ Bike and Pedestrian facilities (concrete work)
❑ Repair/replace stormwater infrastructure and catch basins
❑ Asphalt patching, milling and resurfacing
❑ Lane striping
POTENTIAL IMPACTS
Insert Presentation Title
Restricted driveway access (24 to 48 hours)
❑ Concrete sidewalk, curb, and gutter installation
❑ Repair/replace stormwater infrastructure and/or catch basins
POTENTIAL IMPACTS
Insert Presentation Title
Portable message boards
Visit: ATLDOT.AtlantaGa.gov
❑ Project fact sheets and presentations posted at:
https://atldot.atlantaga.gov/projects/dekalb-ave-safety-improvements
Project updates:
❑ Send email to: [email protected]
❑ Subject heading “DeKalb Avenue Safety Improvements Project Updates”
❑ Request to receive updates on project referenced in heading
PROJECT STATUS UPDATES AVAILABLE VIA…
Follow us on social media!
@.com/ATLDOT@ATLDOT @ATL.DOT
20
ATLDOTCity of Atlanta Department of Transportation
Insert Presentation Title
QUESTIONS?