INS AND OUTS€¦ · Ivan Graff 2020 Project Management Symposium INS AND OUTS STRUCTURING THE...

21
Ivan Graff 2020 Project Management Symposium INS AND OUTS STRUCTURING THE SCOPE PORTION OF A COMPLEX CONSTRUCTION PROJECT PEER REVIEW

Transcript of INS AND OUTS€¦ · Ivan Graff 2020 Project Management Symposium INS AND OUTS STRUCTURING THE...

Page 1: INS AND OUTS€¦ · Ivan Graff 2020 Project Management Symposium INS AND OUTS STRUCTURING THE SCOPE PORTION OF A COMPLEX CONSTRUCTION PROJECT PEER REVIEW. Ins and Outs STRUCTURING

Ivan Graff2020 Project Management Symposium

INS AND OUTSSTRUCTURING THE SCOPE PORTION OF A COMPLEX CONSTRUCTION PROJECT PEER REVIEW

Page 2: INS AND OUTS€¦ · Ivan Graff 2020 Project Management Symposium INS AND OUTS STRUCTURING THE SCOPE PORTION OF A COMPLEX CONSTRUCTION PROJECT PEER REVIEW. Ins and Outs STRUCTURING

Ins and OutsSTRUCTURING THE SCOPE PORTION OF A COMPLEX CONSTRUCTION PROJECT PEER REVIEW

Page 3: INS AND OUTS€¦ · Ivan Graff 2020 Project Management Symposium INS AND OUTS STRUCTURING THE SCOPE PORTION OF A COMPLEX CONSTRUCTION PROJECT PEER REVIEW. Ins and Outs STRUCTURING

3

31%of projects fail to deliver intended

benefits- State of Project

Management Report 2016 (Wellington Group)

70%of projects fail due to scope

- CHAOS Report 2014 (Standish Group)

May 7, 2020 UNIVERSITY OF MARYLAND PROJECT MANAGEMENT SYMPOSIUM

52%of projects

completed in 2017 experienced

uncontrolled changes to scope

- Pulse of the Profession 2018 (Project Management

Institute)

Change in priorities::

Change in project objectives

::

Inaccurate requirements

¢

Uncontrolled scope.

- Pulse of the Profession 2018 (Project Management Institute)

40%of projects do not

have a scoping document

- State of Project Management Report

2017 (Wellington Group)

Page 4: INS AND OUTS€¦ · Ivan Graff 2020 Project Management Symposium INS AND OUTS STRUCTURING THE SCOPE PORTION OF A COMPLEX CONSTRUCTION PROJECT PEER REVIEW. Ins and Outs STRUCTURING

INITIAL QUESTION

?

How might one understand, and

determine the completeness of, the scope prior to setting

the baseline?

4

Page 5: INS AND OUTS€¦ · Ivan Graff 2020 Project Management Symposium INS AND OUTS STRUCTURING THE SCOPE PORTION OF A COMPLEX CONSTRUCTION PROJECT PEER REVIEW. Ins and Outs STRUCTURING

About your presenterResponsible for capital asset acquisition project policy at the U.S. Department of Energy.

Agency budgets $3 to $5 billion on capital asset acquisition projects annually.Previously employers: National Science Foundation, Smithsonian Institution, USDA, and the University of Maryland College Park.

◦ M.S., Civil Engineering (Construction Management), UMCP.

◦ B.S., Bioresource Engineering (Structures), Rutgers University.

Ivan GraffP.E., PMP, CCP, CFM, LEED-AP

[email protected]

The views expressed by the speaker do not necessarily

reflect those of his employer.

May 7, 2020 UNIVERSITY OF MARYLAND PROJECT MANAGEMENT SYMPOSIUM 5

Page 6: INS AND OUTS€¦ · Ivan Graff 2020 Project Management Symposium INS AND OUTS STRUCTURING THE SCOPE PORTION OF A COMPLEX CONSTRUCTION PROJECT PEER REVIEW. Ins and Outs STRUCTURING

Scope Baseline: 1. Scope Statement2. Work Breakdown Structure3. Work Breakdown Structure Dictionary

PROJECT MANAGEMENT INSTITUTEPROJECT MANAGEMENT BODY OF KNOWLEDGE, 6THED.

SECTION 5.4.3.1

May 7, 2020 UNIVERSITY OF MARYLAND PROJECT MANAGEMENT SYMPOSIUM 6

Page 7: INS AND OUTS€¦ · Ivan Graff 2020 Project Management Symposium INS AND OUTS STRUCTURING THE SCOPE PORTION OF A COMPLEX CONSTRUCTION PROJECT PEER REVIEW. Ins and Outs STRUCTURING

7

PROJECT HIERARCHY

COST

SCHEDULE

SCOPE

Schedule = f (Scope)Cost = f (Scope, Schedule)

May 7, 2020 UNIVERSITY OF MARYLAND PROJECT MANAGEMENT SYMPOSIUM

Based on a Tom Toles cartoon (June 2007)

Page 8: INS AND OUTS€¦ · Ivan Graff 2020 Project Management Symposium INS AND OUTS STRUCTURING THE SCOPE PORTION OF A COMPLEX CONSTRUCTION PROJECT PEER REVIEW. Ins and Outs STRUCTURING

Purpose of a Project Peer Review1. Reduces the likelihood of a project failure by

identifying existing or potential problems.2. Evaluates –

a. Capacity – quality and quantity of assigned resources

b. Compliance – with internal rules, code or record, commitments to oversight entities

c. Fidelity – to stakeholder expectations

d. Thoroughness – comprehensiveness of planning

e. Efficiencies – leveraging others

f. Maturity – readiness for the next stage or phase

May 7, 2020 UNIVERSITY OF MARYLAND PROJECT MANAGEMENT SYMPOSIUM 8

Page 9: INS AND OUTS€¦ · Ivan Graff 2020 Project Management Symposium INS AND OUTS STRUCTURING THE SCOPE PORTION OF A COMPLEX CONSTRUCTION PROJECT PEER REVIEW. Ins and Outs STRUCTURING

Typical Reviewer Roles

May 7, 2020 UNIVERSITY OF MARYLAND PROJECT MANAGEMENT SYMPOSIUM 9

Management and Acquisition Design

Environment, Safety, Health, and Security

Scheduling

Cost Estimating Risk Management

Transition to Operations

Technology ReadinessProject Controls

Review LeadWho’s in

charge of

scope?

Page 10: INS AND OUTS€¦ · Ivan Graff 2020 Project Management Symposium INS AND OUTS STRUCTURING THE SCOPE PORTION OF A COMPLEX CONSTRUCTION PROJECT PEER REVIEW. Ins and Outs STRUCTURING

Indicators of Complexity§ Number and kinds of . . .o Capital assets acquired or improved o Performing entitieso Stakeholderso Schedule activitieso Risks

§ Maturity of . . .o Technologieso Project processes

§ Surrogate: Cost of the Project

May 7, 2020 UNIVERSITY OF MARYLAND PROJECT MANAGEMENT SYMPOSIUM 10

Page 11: INS AND OUTS€¦ · Ivan Graff 2020 Project Management Symposium INS AND OUTS STRUCTURING THE SCOPE PORTION OF A COMPLEX CONSTRUCTION PROJECT PEER REVIEW. Ins and Outs STRUCTURING

11May 7, 2020 UNIVERSITY OF MARYLAND PROJECT MANAGEMENT SYMPOSIUM

• Does not exist. L

• GAO has no plans to write this.

Page 12: INS AND OUTS€¦ · Ivan Graff 2020 Project Management Symposium INS AND OUTS STRUCTURING THE SCOPE PORTION OF A COMPLEX CONSTRUCTION PROJECT PEER REVIEW. Ins and Outs STRUCTURING

GAO Scheduling Guide 16-89G

Best Practice #1, Capturing all activities. § Capturing All Effort§ Work Breakdown Structure§ Activity Codes § Best Practices Checklist: Capturing All Activities § Appendix III Best Practice 1 Capturing All

Activities

12May 7, 2020 UNIVERSITY OF MARYLAND PROJECT MANAGEMENT SYMPOSIUM

Page 13: INS AND OUTS€¦ · Ivan Graff 2020 Project Management Symposium INS AND OUTS STRUCTURING THE SCOPE PORTION OF A COMPLEX CONSTRUCTION PROJECT PEER REVIEW. Ins and Outs STRUCTURING

GAO Cost Estimating Guide 20-195G

From the perspective of a cost estimate:Pin down the technical scope. (p.33)§Purpose, Scope, and Schedule§Technical Baseline Description§Work Breakdown Structure

13May 7, 2020 UNIVERSITY OF MARYLAND PROJECT MANAGEMENT SYMPOSIUM

Page 14: INS AND OUTS€¦ · Ivan Graff 2020 Project Management Symposium INS AND OUTS STRUCTURING THE SCOPE PORTION OF A COMPLEX CONSTRUCTION PROJECT PEER REVIEW. Ins and Outs STRUCTURING

Solution No. 1TOOL TO ORGANIZE THE SCOPE STATEMENT AND THE SECTION OF THE PROJECT REVIEW REPORT SUMMARIZING THE PROJECT SCOPE

May 7, 2020 UNIVERSITY OF MARYLAND PROJECT MANAGEMENT SYMPOSIUM 14

Page 15: INS AND OUTS€¦ · Ivan Graff 2020 Project Management Symposium INS AND OUTS STRUCTURING THE SCOPE PORTION OF A COMPLEX CONSTRUCTION PROJECT PEER REVIEW. Ins and Outs STRUCTURING

15

comprehensive

cause

customization

count

capability

capacity

coverage

configuration

components

complexion contents

chronology

culture

cachet

clauses

codes conditions

complications

PROPOSED CONSIDERATIONS FOR A SCOPE STATEMENT

33 C’s

33 “c”arat SCOPE gem

Regions:

Attributes

Basis

Circumstances

contingency

contamination

customers

covenants

compacts

contributions

criticality

costs

clients

May 7, 2020 UNIVERSITY OF MARYLAND PROJECT MANAGEMENT SYMPOSIUM

catalogue

commissioning

controls

continuity

category

constraints

Page 16: INS AND OUTS€¦ · Ivan Graff 2020 Project Management Symposium INS AND OUTS STRUCTURING THE SCOPE PORTION OF A COMPLEX CONSTRUCTION PROJECT PEER REVIEW. Ins and Outs STRUCTURING

16

ATTR

IBU

TES

A

May 7, 2020 UNIVERSITY OF MARYLAND PROJECT MANAGEMENT SYMPOSIUM

Comprehensiveness

Cause (Charge)

Customization

Count

Capability

Coverage

Configuration

Components

Cachet

Continuity

Contents

Contingency

Capacity

Complexion

Page 17: INS AND OUTS€¦ · Ivan Graff 2020 Project Management Symposium INS AND OUTS STRUCTURING THE SCOPE PORTION OF A COMPLEX CONSTRUCTION PROJECT PEER REVIEW. Ins and Outs STRUCTURING

17

BASI

S

B

May 7, 2020 UNIVERSITY OF MARYLAND PROJECT MANAGEMENT SYMPOSIUM

Clauses

Controls

Codes

Catalogue

Commissioning

Page 18: INS AND OUTS€¦ · Ivan Graff 2020 Project Management Symposium INS AND OUTS STRUCTURING THE SCOPE PORTION OF A COMPLEX CONSTRUCTION PROJECT PEER REVIEW. Ins and Outs STRUCTURING

18

CIRC

UM

STAN

CES

C

May 7, 2020 UNIVERSITY OF MARYLAND PROJECT MANAGEMENT SYMPOSIUM

Clients

Customers

Conditions

Constraints

Complications

Compacts

Covenants

Contributions

Culture

Criticality

Contamination

Chronology

Costs

Page 19: INS AND OUTS€¦ · Ivan Graff 2020 Project Management Symposium INS AND OUTS STRUCTURING THE SCOPE PORTION OF A COMPLEX CONSTRUCTION PROJECT PEER REVIEW. Ins and Outs STRUCTURING

Solution No. 2TOOL TO VALIDATE THE SCOPE

May 7, 2020 UNIVERSITY OF MARYLAND PROJECT MANAGEMENT SYMPOSIUM 19

Page 20: INS AND OUTS€¦ · Ivan Graff 2020 Project Management Symposium INS AND OUTS STRUCTURING THE SCOPE PORTION OF A COMPLEX CONSTRUCTION PROJECT PEER REVIEW. Ins and Outs STRUCTURING

Requirements Traceability Matrix

May 7, 2020 UNIVERSITY OF MARYLAND PROJECT MANAGEMENT SYMPOSIUM 20

ID Type

Desc

riptio

n

Just

ifica

tion

Orig

inat

or

Info

rmat

ion

Prio

rity

Prio

rity

Assi

gnm

ent

Date

WBS

Ref

eren

ce

Com

plet

ion

Test

1

2

3

4

5

6

7

Page 21: INS AND OUTS€¦ · Ivan Graff 2020 Project Management Symposium INS AND OUTS STRUCTURING THE SCOPE PORTION OF A COMPLEX CONSTRUCTION PROJECT PEER REVIEW. Ins and Outs STRUCTURING

May 7, 2020 UNIVERSITY OF MARYLAND PROJECT MANAGEMENT SYMPOSIUM 21

Questions?Please type your questions in the chat box.