Innovative Driven Pile Solution for the RIDOT Route 6/10 ...

49
Innovative Driven Pile Solution for the RIDOT Route 6/10 Interchange Project Seth H. Hamblin, P.E. Geosciences Testing and Research, Inc.

Transcript of Innovative Driven Pile Solution for the RIDOT Route 6/10 ...

Page 1: Innovative Driven Pile Solution for the RIDOT Route 6/10 ...

Innovative Driven Pile Solution for the RIDOT Route 6/10 Interchange Project

Seth H. Hamblin, P.E.

Geosciences Testing and Research, Inc.

Page 2: Innovative Driven Pile Solution for the RIDOT Route 6/10 ...

2019 Transportation Innovation Conference 2

Table of ContentsI. Pile Driving Safety

II. Project Information

III. Foundation Selection Considerations

IV. Design Phase Foundation Load Testing Program

V. Construction Phase Foundation Construction

VI. Conclusions and Lessons Learned

Page 3: Innovative Driven Pile Solution for the RIDOT Route 6/10 ...

2019 Transportation Innovation Conference 3

Pile Driving Safety• Keep a safe distance from the rig –

cranes usually have defined swing radius.

• Engineers should be positioned to the side of the pile/hammer if possible – to avoid falling debris, parts, or worse.

• Be aware of equipment or materials swinging overhead or behind –particularly between piles when you may be pre-occupied with paperwork.

• Ear protection – impact and sound

• Eye protection – debris, welding

• Marine conditions - work over water

• Weather hazards – ice, tripping, etc.

Page 4: Innovative Driven Pile Solution for the RIDOT Route 6/10 ...

2019 Transportation Innovation Conference 4

6/10 Interchange Location

Project Area

Page 5: Innovative Driven Pile Solution for the RIDOT Route 6/10 ...

2019 Transportation Innovation Conference 5

6/10 Interchange Layout

Route 6 and 10 Interchange Looking South

Route 10 Northbound & Southbound

Route 6 Eastbound & Westbound

Page 6: Innovative Driven Pile Solution for the RIDOT Route 6/10 ...

2019 Transportation Innovation Conference 6

6/10 Interchange History The 6/10 Interchange is very old, constructed in the 1950s

Links three major commuter roadways in Providence, RI

Current usage is well above capacity, > 100,000 vehicles daily

Nine (9) existing bridges, seven (7) are structurally deficient

The Viaducts, ramps and bridges have been segmentally repaired and rehabbed over many years

RIDOT has previously spent millions of dollars to keep the interchange open and safe for the traveling public

Page 7: Innovative Driven Pile Solution for the RIDOT Route 6/10 ...

2019 Transportation Innovation Conference 7

6/10 Interchange Current Conditions

Page 8: Innovative Driven Pile Solution for the RIDOT Route 6/10 ...

2019 Transportation Innovation Conference 8

6/10 Interchange Current Conditions

Page 9: Innovative Driven Pile Solution for the RIDOT Route 6/10 ...

2019 Transportation Innovation Conference 9

6/10 Interchange Current Conditions

Page 10: Innovative Driven Pile Solution for the RIDOT Route 6/10 ...

2019 Transportation Innovation Conference 10

6/10 Interchange Project Information

Barletta Heavy Division O&G Industries D.W. White Construction

Aetna Bridge Company AECOM

Owner: Rhode Island Department of Transportation

Project Team: 6/10 Constructors, JV

Page 11: Innovative Driven Pile Solution for the RIDOT Route 6/10 ...

2019 Transportation Innovation Conference 11

6/10 Interchange Project Information Project Objective: Reconstruct entire interchange within the

existing highway ROW, while replacing or removing seven structurally deficient bridges and creating a highway link from Rt. 10 NB to Rt. 6 WB

Cost Estimate: $410 Million

Project Delivery Method: Design-Build

Project Schedule: Early 2018 through late 2023

Page 12: Innovative Driven Pile Solution for the RIDOT Route 6/10 ...

2019 Transportation Innovation Conference 12

6/10 Connector Proposed Layout

Page 13: Innovative Driven Pile Solution for the RIDOT Route 6/10 ...

2019 Transportation Innovation Conference 13

Proposed Foundation Alternatives Evaluation Criteria

Subsurface Conditions – Depth to Bedrock ~200 ft. Critical Loading Conditions – Uplift, Lateral & Compression Installation Cost Installation Schedule Obstructions Potential Presence Of Contaminated Soils

Deep Foundation Options Pre-Bid Design - Drilled Micropiles

Driven Steel Tapertube Piles Post‐Bid Value Engineering Alternate

Page 14: Innovative Driven Pile Solution for the RIDOT Route 6/10 ...

2019 Transportation Innovation Conference 14

Drilled Micropile Foundations Pros

Effective in any subsurface condition Limited access situations – low

headroom/confined site Minimal noise and vibration High tension and compression pile

capacities in bedrock Smaller equipment

Cons Limited frictional capacities in soil Contaminated drilling fluid and spoils More expensive per LF than piles Installation time – flushing & grouting

Page 15: Innovative Driven Pile Solution for the RIDOT Route 6/10 ...

2019 Transportation Innovation Conference 15

Driven Pipe Pile Foundations Pros

Higher capacities than micropiles –w/ closed end

Shorter installation times No spoils or groundwater controls

Cons Piles in sands do not demonstrate

increased capacity with depth Require long piles – End Bearing on

Bedrock Require corrosion protection Increased Noise & Vibration Obstructions – Pre-Augering

Page 16: Innovative Driven Pile Solution for the RIDOT Route 6/10 ...

2019 Transportation Innovation Conference 16

Driven Tapertube Pile Foundations Pros

Higher capacities for shorter driven lengths

Can develop higher shaft resistance in granular soils

Greater wall thickness and higher durability at tip

Installed with conventional pile driving equipment

Short installation times

Cons Higher cost per LF than pipe piles Increased Noise & Vibration Obstructions – Pre-Augering

Page 17: Innovative Driven Pile Solution for the RIDOT Route 6/10 ...

2019 Transportation Innovation Conference 17

Design Phase Pile Load Test Program Pre-Construction Feasibility & Drivability Study Two Test Pile Sites – East & West of Amtrak ROW Two Pile Types

16” Dia. Steel Pipe Piles 16” Dia. Steel Tapertube Pile – 16” x 8” x 25’

Environmental Study – Noise, Vibration & Settlement Monitoring Dynamic Pile Testing Internal Instrumentation Static Pile Testing

Compression – ASTM D1143 Tension – ASTM D3689 Lateral – ASTM D3966

Page 18: Innovative Driven Pile Solution for the RIDOT Route 6/10 ...

2019 Transportation Innovation Conference 18

Design Phase Pile Load Test Program“East of Amtrak” Test Pile Site

Amtrak & MBCR ROW

Page 19: Innovative Driven Pile Solution for the RIDOT Route 6/10 ...

2019 Transportation Innovation Conference 19

Design Phase Pile Load Test Program“West of Amtrak” Test Pile Site

Amtrak & MBCR ROW

Page 20: Innovative Driven Pile Solution for the RIDOT Route 6/10 ...

2019 Transportation Innovation Conference 20

Design Phase Pile Load Test ProgramPre-Construction Driven Pile Feasibility & Drivability

Static Capacity Evaluation to Determine Pile Size Relied on limited data collected on prior local project Singular project in NE to attempt to use tapertubes

Wave Equation (WEAP) Analysis – Evaluate Hammer/Soil/Pile System

Drivability Analysis Equipment Recommendations

Page 21: Innovative Driven Pile Solution for the RIDOT Route 6/10 ...

2019 Transportation Innovation Conference 21

Design Phase Pile Load Test ProgramEnvironmental Study

Vibration & Noise Monitoring during pile driving Performed at 25 ft and 50 ft offset

Surface Deformation Monitoring 15 ft, 25 ft, and 50 ft offsets from test piles

Page 22: Innovative Driven Pile Solution for the RIDOT Route 6/10 ...

2019 Transportation Innovation Conference 22

Design Phase Pile Load Test ProgramVibration, Noise, and Settlement Monitoring Point Layout

Page 23: Innovative Driven Pile Solution for the RIDOT Route 6/10 ...

2019 Transportation Innovation Conference 23

Design Phase Pile Load Test ProgramVibration, Noise, and Settlement Monitoring Point Layout

Page 24: Innovative Driven Pile Solution for the RIDOT Route 6/10 ...

2019 Transportation Innovation Conference 24

Design Phase Pile Load Test ProgramDynamic Pile Testing

Performed during pile installation (EOD) Restrike Testing after 5 days (BOR) - time dependent capacity CAPWAP Analyses on EOD and BOR data

Page 25: Innovative Driven Pile Solution for the RIDOT Route 6/10 ...

2019 Transportation Innovation Conference 25

Design Phase Pile Load Test ProgramDynamic Pile Testing Results

Driven2 Maximum 4 Maximum 4 Maximum 5

Test Test Time of1 Date Depth Stroke 3 Transferred Comp. Stress Comp. Stress CAPWAP

Site Pile Driving Energy Pile Top Pile Tip RX7 Capacity

(feet) (feet) (kip-ft) (ksi) (ksi) (kips) (kips)

EOD 5/16/18 3 24.8 27.9 16.7 235 220

BOR 5/21/18 3.5 28.2 29.1 28.2 487 465

BOR 5/21/18 3 24.8 28.4 26.8 415 370

EOD 5/16/18 3 25.1 26.4 22.0 343 340

BOR 5/21/18 3.5 33.6 32.1 28.2 438 455

BOR 5/21/18 3.5 28.5 29.5 26.4 421 425

BOR 5/21/18 3.5 28.7 29.4 26.3 412 395

EOD 5/30/18 27.1 29.8 20.8 326 330

BOR 6/4/18 25.2 30.4 21.3 358 355

BOR 6/4/18 21.4 27.3 18.9 325 310

EOD 5/30/18 22.8 26.3 21.0 404 390

BOR 6/4/18 22.2 30.5 19.5 447 420

BOR 6/4/18 20.6 29.7 19.6 397 395

EORD 6/4/18 55.0 21.8 27.2 20.0 368 360

EOA

WOA

Case Metho

Capacity

PP-2 70.0 3

TTP-251.0

3

PP-1 113.0

TTP-1 113.0

Page 26: Innovative Driven Pile Solution for the RIDOT Route 6/10 ...

2019 Transportation Innovation Conference 26

Design Phase Pile Load Test ProgramTest Pile Instrumentation

Vibrating Wire Strain Gages Inclinometer Casing – Lateral Load Test

Page 27: Innovative Driven Pile Solution for the RIDOT Route 6/10 ...

2019 Transportation Innovation Conference 27

Design Phase Pile Load Test ProgramTest Pile Instrumentation

Page 28: Innovative Driven Pile Solution for the RIDOT Route 6/10 ...

2019 Transportation Innovation Conference 28

Design Phase Pile Load Test ProgramTest Pile Instrumentation

Page 29: Innovative Driven Pile Solution for the RIDOT Route 6/10 ...

2019 Transportation Innovation Conference 29

Design Phase Pile Load Test ProgramTest Pile Instrumentation

Page 30: Innovative Driven Pile Solution for the RIDOT Route 6/10 ...

2019 Transportation Innovation Conference 30

Design Phase Pile Load Test ProgramTest Pile Instrumentation

Page 31: Innovative Driven Pile Solution for the RIDOT Route 6/10 ...

2019 Transportation Innovation Conference 31

Design Phase Pile Load Test ProgramTest Pile Instrumentation

Page 32: Innovative Driven Pile Solution for the RIDOT Route 6/10 ...

2019 Transportation Innovation Conference 32

Design Phase Pile Load Test ProgramStatic Pile Testing

Compression Load Tests on four test piles Tension Load Tests on three test piles One Lateral Test at each test site

Page 33: Innovative Driven Pile Solution for the RIDOT Route 6/10 ...

2019 Transportation Innovation Conference 33

Design Phase Pile Load Test ProgramCompression Load Tests

Page 34: Innovative Driven Pile Solution for the RIDOT Route 6/10 ...

2019 Transportation Innovation Conference 34

Design Phase Pile Load Test Program

Page 35: Innovative Driven Pile Solution for the RIDOT Route 6/10 ...

2019 Transportation Innovation Conference 35

Design Phase Pile Load Test ProgramTension Load Tests

Page 36: Innovative Driven Pile Solution for the RIDOT Route 6/10 ...

2019 Transportation Innovation Conference 36

Design Phase Pile Load Test ProgramLateral Load Tests

Page 37: Innovative Driven Pile Solution for the RIDOT Route 6/10 ...

2019 Transportation Innovation Conference 37

Design Phase Pile Load Test ProgramLoad Test Program Summary Data Table

Dynamic Testing

1" 1.5"(kips) (kips)

PP-1 5/16/18 113 16 24.8 57 65* 165 350 465TTP-1 5/16/18 113 41 25.1 39 50 255 430 455PP-2 6/4/18 70 5,5,5,4 bpi 21.4 48 58 N/A 280 355TTP-2 6/4/18 55 26 bpf 21.8 54 70 270 560 420

Nominal Compression

Capacity (kips)

Nominal Resistance Capacity

(kips)

Measured Deflections

WOA

EOA

Static Load Testing

Test Site

Test Pile

Driven Date

Driven Depth

(ft)

Observed Blow Count

(bpf)

Measured Energy (k-ft)

Lateral Load at Nominal Tension Capacity

(kips)

Page 38: Innovative Driven Pile Solution for the RIDOT Route 6/10 ...

2019 Transportation Innovation Conference 38

Pile Load Test Program Results Tapertubes performed better than pipe piles

Blow Count Pile Capacity – Compression/Tension/Lateral

Static test data suggest ultimate compression capacities ~ 4x greater than assumed micropiles loads

Data was directly incorporated into final design Very low ground vibrations at 25 ft from pile driving - <0.25 IPS Pile Driving noise <100 dB at 50 ft from hammer No observable settlement or heave of adjacent surfaces

SUCCESSFUL TEST PILE PROGRAM

Page 39: Innovative Driven Pile Solution for the RIDOT Route 6/10 ...

2019 Transportation Innovation Conference 39

Construction Phase Pile Installation 17 substructures founded on 16” tapertube piles Performed dynamic testing on 1st pile in each substructure One (1) substructure supported on micropiles

Page 40: Innovative Driven Pile Solution for the RIDOT Route 6/10 ...

2019 Transportation Innovation Conference 40

Construction Phase Pile InstallationLogistical and Environmental Challenges

Unexpected variability in subsurface conditions at west end of site

Buried historic foundations - Obstructions Existing underground utilities Proximity to existing viaduct and live traffic Site Grade Elevations – Existing vs. Final Winter Conditions

Page 41: Innovative Driven Pile Solution for the RIDOT Route 6/10 ...

2019 Transportation Innovation Conference 41

Construction Phase Pile InstallationLogistical and Environmental Challenges

Existing 340kV Duct Bank

Proposed Pile Location

Page 42: Innovative Driven Pile Solution for the RIDOT Route 6/10 ...

2019 Transportation Innovation Conference 42

Construction Phase Pile InstallationLogistical and Environmental Challenges

Page 43: Innovative Driven Pile Solution for the RIDOT Route 6/10 ...

2019 Transportation Innovation Conference 43

Construction Phase Pile InstallationLogistical and Environmental Challenges

Page 44: Innovative Driven Pile Solution for the RIDOT Route 6/10 ...

2019 Transportation Innovation Conference 44

Construction Phase Pile InstallationLogistical and Environmental Challenges

Page 45: Innovative Driven Pile Solution for the RIDOT Route 6/10 ...

2019 Transportation Innovation Conference 45

Construction Phase Pile InstallationLogistical and Environmental Challenges

Page 46: Innovative Driven Pile Solution for the RIDOT Route 6/10 ...

2019 Transportation Innovation Conference 46

Construction Phase Pile InstallationLogistical and Environmental Challenges

Page 47: Innovative Driven Pile Solution for the RIDOT Route 6/10 ...

2019 Transportation Innovation Conference 47

Project Specific Results Tapertubes resulted in a 400% increase to the axial pile design

capacity compared to micropiles Tapertubes satisfied stringent lateral and uplift design

requirements Drive fit sleeve pile splices performed very well Reduced number of elements per substructure by >50% Schedule savings of ~1.5 months per foundation substructure

Estimated micropile pier construction time – 40-50 days Actual tapertube pile pier construction time – 2-4 days

Page 48: Innovative Driven Pile Solution for the RIDOT Route 6/10 ...

2019 Transportation Innovation Conference 48

Conclusions & Recommendations Tapertubes are a viable foundation solution in New England

Subsurface conditions – med. Dense sand with sand and gravel Increased Design Phase Testing Saves Time & Money Project delivery method provided opportunities for innovation Allow for technical flexibility in project Early Collaboration between Owner / Engineer/ Contractor /

Supplier leads to greater project value Test in Non-Production Locations with Robust Load Frames Incorporate Site Specific data into Final Design

Page 49: Innovative Driven Pile Solution for the RIDOT Route 6/10 ...

2019 Transportation Innovation Conference 49

QuestionsThank You For Your Attention!