Innovative Driven Pile Solution for the RIDOT Route 6/10 ...
Transcript of Innovative Driven Pile Solution for the RIDOT Route 6/10 ...
Innovative Driven Pile Solution for the RIDOT Route 6/10 Interchange Project
Seth H. Hamblin, P.E.
Geosciences Testing and Research, Inc.
2019 Transportation Innovation Conference 2
Table of ContentsI. Pile Driving Safety
II. Project Information
III. Foundation Selection Considerations
IV. Design Phase Foundation Load Testing Program
V. Construction Phase Foundation Construction
VI. Conclusions and Lessons Learned
2019 Transportation Innovation Conference 3
Pile Driving Safety• Keep a safe distance from the rig –
cranes usually have defined swing radius.
• Engineers should be positioned to the side of the pile/hammer if possible – to avoid falling debris, parts, or worse.
• Be aware of equipment or materials swinging overhead or behind –particularly between piles when you may be pre-occupied with paperwork.
• Ear protection – impact and sound
• Eye protection – debris, welding
• Marine conditions - work over water
• Weather hazards – ice, tripping, etc.
2019 Transportation Innovation Conference 4
6/10 Interchange Location
Project Area
2019 Transportation Innovation Conference 5
6/10 Interchange Layout
Route 6 and 10 Interchange Looking South
Route 10 Northbound & Southbound
Route 6 Eastbound & Westbound
2019 Transportation Innovation Conference 6
6/10 Interchange History The 6/10 Interchange is very old, constructed in the 1950s
Links three major commuter roadways in Providence, RI
Current usage is well above capacity, > 100,000 vehicles daily
Nine (9) existing bridges, seven (7) are structurally deficient
The Viaducts, ramps and bridges have been segmentally repaired and rehabbed over many years
RIDOT has previously spent millions of dollars to keep the interchange open and safe for the traveling public
2019 Transportation Innovation Conference 7
6/10 Interchange Current Conditions
2019 Transportation Innovation Conference 8
6/10 Interchange Current Conditions
2019 Transportation Innovation Conference 9
6/10 Interchange Current Conditions
2019 Transportation Innovation Conference 10
6/10 Interchange Project Information
Barletta Heavy Division O&G Industries D.W. White Construction
Aetna Bridge Company AECOM
Owner: Rhode Island Department of Transportation
Project Team: 6/10 Constructors, JV
2019 Transportation Innovation Conference 11
6/10 Interchange Project Information Project Objective: Reconstruct entire interchange within the
existing highway ROW, while replacing or removing seven structurally deficient bridges and creating a highway link from Rt. 10 NB to Rt. 6 WB
Cost Estimate: $410 Million
Project Delivery Method: Design-Build
Project Schedule: Early 2018 through late 2023
2019 Transportation Innovation Conference 12
6/10 Connector Proposed Layout
2019 Transportation Innovation Conference 13
Proposed Foundation Alternatives Evaluation Criteria
Subsurface Conditions – Depth to Bedrock ~200 ft. Critical Loading Conditions – Uplift, Lateral & Compression Installation Cost Installation Schedule Obstructions Potential Presence Of Contaminated Soils
Deep Foundation Options Pre-Bid Design - Drilled Micropiles
Driven Steel Tapertube Piles Post‐Bid Value Engineering Alternate
2019 Transportation Innovation Conference 14
Drilled Micropile Foundations Pros
Effective in any subsurface condition Limited access situations – low
headroom/confined site Minimal noise and vibration High tension and compression pile
capacities in bedrock Smaller equipment
Cons Limited frictional capacities in soil Contaminated drilling fluid and spoils More expensive per LF than piles Installation time – flushing & grouting
2019 Transportation Innovation Conference 15
Driven Pipe Pile Foundations Pros
Higher capacities than micropiles –w/ closed end
Shorter installation times No spoils or groundwater controls
Cons Piles in sands do not demonstrate
increased capacity with depth Require long piles – End Bearing on
Bedrock Require corrosion protection Increased Noise & Vibration Obstructions – Pre-Augering
2019 Transportation Innovation Conference 16
Driven Tapertube Pile Foundations Pros
Higher capacities for shorter driven lengths
Can develop higher shaft resistance in granular soils
Greater wall thickness and higher durability at tip
Installed with conventional pile driving equipment
Short installation times
Cons Higher cost per LF than pipe piles Increased Noise & Vibration Obstructions – Pre-Augering
2019 Transportation Innovation Conference 17
Design Phase Pile Load Test Program Pre-Construction Feasibility & Drivability Study Two Test Pile Sites – East & West of Amtrak ROW Two Pile Types
16” Dia. Steel Pipe Piles 16” Dia. Steel Tapertube Pile – 16” x 8” x 25’
Environmental Study – Noise, Vibration & Settlement Monitoring Dynamic Pile Testing Internal Instrumentation Static Pile Testing
Compression – ASTM D1143 Tension – ASTM D3689 Lateral – ASTM D3966
2019 Transportation Innovation Conference 18
Design Phase Pile Load Test Program“East of Amtrak” Test Pile Site
Amtrak & MBCR ROW
2019 Transportation Innovation Conference 19
Design Phase Pile Load Test Program“West of Amtrak” Test Pile Site
Amtrak & MBCR ROW
2019 Transportation Innovation Conference 20
Design Phase Pile Load Test ProgramPre-Construction Driven Pile Feasibility & Drivability
Static Capacity Evaluation to Determine Pile Size Relied on limited data collected on prior local project Singular project in NE to attempt to use tapertubes
Wave Equation (WEAP) Analysis – Evaluate Hammer/Soil/Pile System
Drivability Analysis Equipment Recommendations
2019 Transportation Innovation Conference 21
Design Phase Pile Load Test ProgramEnvironmental Study
Vibration & Noise Monitoring during pile driving Performed at 25 ft and 50 ft offset
Surface Deformation Monitoring 15 ft, 25 ft, and 50 ft offsets from test piles
2019 Transportation Innovation Conference 22
Design Phase Pile Load Test ProgramVibration, Noise, and Settlement Monitoring Point Layout
2019 Transportation Innovation Conference 23
Design Phase Pile Load Test ProgramVibration, Noise, and Settlement Monitoring Point Layout
2019 Transportation Innovation Conference 24
Design Phase Pile Load Test ProgramDynamic Pile Testing
Performed during pile installation (EOD) Restrike Testing after 5 days (BOR) - time dependent capacity CAPWAP Analyses on EOD and BOR data
2019 Transportation Innovation Conference 25
Design Phase Pile Load Test ProgramDynamic Pile Testing Results
Driven2 Maximum 4 Maximum 4 Maximum 5
Test Test Time of1 Date Depth Stroke 3 Transferred Comp. Stress Comp. Stress CAPWAP
Site Pile Driving Energy Pile Top Pile Tip RX7 Capacity
(feet) (feet) (kip-ft) (ksi) (ksi) (kips) (kips)
EOD 5/16/18 3 24.8 27.9 16.7 235 220
BOR 5/21/18 3.5 28.2 29.1 28.2 487 465
BOR 5/21/18 3 24.8 28.4 26.8 415 370
EOD 5/16/18 3 25.1 26.4 22.0 343 340
BOR 5/21/18 3.5 33.6 32.1 28.2 438 455
BOR 5/21/18 3.5 28.5 29.5 26.4 421 425
BOR 5/21/18 3.5 28.7 29.4 26.3 412 395
EOD 5/30/18 27.1 29.8 20.8 326 330
BOR 6/4/18 25.2 30.4 21.3 358 355
BOR 6/4/18 21.4 27.3 18.9 325 310
EOD 5/30/18 22.8 26.3 21.0 404 390
BOR 6/4/18 22.2 30.5 19.5 447 420
BOR 6/4/18 20.6 29.7 19.6 397 395
EORD 6/4/18 55.0 21.8 27.2 20.0 368 360
EOA
WOA
Case Metho
Capacity
PP-2 70.0 3
TTP-251.0
3
PP-1 113.0
TTP-1 113.0
2019 Transportation Innovation Conference 26
Design Phase Pile Load Test ProgramTest Pile Instrumentation
Vibrating Wire Strain Gages Inclinometer Casing – Lateral Load Test
2019 Transportation Innovation Conference 27
Design Phase Pile Load Test ProgramTest Pile Instrumentation
2019 Transportation Innovation Conference 28
Design Phase Pile Load Test ProgramTest Pile Instrumentation
2019 Transportation Innovation Conference 29
Design Phase Pile Load Test ProgramTest Pile Instrumentation
2019 Transportation Innovation Conference 30
Design Phase Pile Load Test ProgramTest Pile Instrumentation
2019 Transportation Innovation Conference 31
Design Phase Pile Load Test ProgramTest Pile Instrumentation
2019 Transportation Innovation Conference 32
Design Phase Pile Load Test ProgramStatic Pile Testing
Compression Load Tests on four test piles Tension Load Tests on three test piles One Lateral Test at each test site
2019 Transportation Innovation Conference 33
Design Phase Pile Load Test ProgramCompression Load Tests
2019 Transportation Innovation Conference 34
Design Phase Pile Load Test Program
2019 Transportation Innovation Conference 35
Design Phase Pile Load Test ProgramTension Load Tests
2019 Transportation Innovation Conference 36
Design Phase Pile Load Test ProgramLateral Load Tests
2019 Transportation Innovation Conference 37
Design Phase Pile Load Test ProgramLoad Test Program Summary Data Table
Dynamic Testing
1" 1.5"(kips) (kips)
PP-1 5/16/18 113 16 24.8 57 65* 165 350 465TTP-1 5/16/18 113 41 25.1 39 50 255 430 455PP-2 6/4/18 70 5,5,5,4 bpi 21.4 48 58 N/A 280 355TTP-2 6/4/18 55 26 bpf 21.8 54 70 270 560 420
Nominal Compression
Capacity (kips)
Nominal Resistance Capacity
(kips)
Measured Deflections
WOA
EOA
Static Load Testing
Test Site
Test Pile
Driven Date
Driven Depth
(ft)
Observed Blow Count
(bpf)
Measured Energy (k-ft)
Lateral Load at Nominal Tension Capacity
(kips)
2019 Transportation Innovation Conference 38
Pile Load Test Program Results Tapertubes performed better than pipe piles
Blow Count Pile Capacity – Compression/Tension/Lateral
Static test data suggest ultimate compression capacities ~ 4x greater than assumed micropiles loads
Data was directly incorporated into final design Very low ground vibrations at 25 ft from pile driving - <0.25 IPS Pile Driving noise <100 dB at 50 ft from hammer No observable settlement or heave of adjacent surfaces
SUCCESSFUL TEST PILE PROGRAM
2019 Transportation Innovation Conference 39
Construction Phase Pile Installation 17 substructures founded on 16” tapertube piles Performed dynamic testing on 1st pile in each substructure One (1) substructure supported on micropiles
2019 Transportation Innovation Conference 40
Construction Phase Pile InstallationLogistical and Environmental Challenges
Unexpected variability in subsurface conditions at west end of site
Buried historic foundations - Obstructions Existing underground utilities Proximity to existing viaduct and live traffic Site Grade Elevations – Existing vs. Final Winter Conditions
2019 Transportation Innovation Conference 41
Construction Phase Pile InstallationLogistical and Environmental Challenges
Existing 340kV Duct Bank
Proposed Pile Location
2019 Transportation Innovation Conference 42
Construction Phase Pile InstallationLogistical and Environmental Challenges
2019 Transportation Innovation Conference 43
Construction Phase Pile InstallationLogistical and Environmental Challenges
2019 Transportation Innovation Conference 44
Construction Phase Pile InstallationLogistical and Environmental Challenges
2019 Transportation Innovation Conference 45
Construction Phase Pile InstallationLogistical and Environmental Challenges
2019 Transportation Innovation Conference 46
Construction Phase Pile InstallationLogistical and Environmental Challenges
2019 Transportation Innovation Conference 47
Project Specific Results Tapertubes resulted in a 400% increase to the axial pile design
capacity compared to micropiles Tapertubes satisfied stringent lateral and uplift design
requirements Drive fit sleeve pile splices performed very well Reduced number of elements per substructure by >50% Schedule savings of ~1.5 months per foundation substructure
Estimated micropile pier construction time – 40-50 days Actual tapertube pile pier construction time – 2-4 days
2019 Transportation Innovation Conference 48
Conclusions & Recommendations Tapertubes are a viable foundation solution in New England
Subsurface conditions – med. Dense sand with sand and gravel Increased Design Phase Testing Saves Time & Money Project delivery method provided opportunities for innovation Allow for technical flexibility in project Early Collaboration between Owner / Engineer/ Contractor /
Supplier leads to greater project value Test in Non-Production Locations with Robust Load Frames Incorporate Site Specific data into Final Design
2019 Transportation Innovation Conference 49
QuestionsThank You For Your Attention!