Innovative Delivery Systems for Bridge Preservation Contracts · Pennywash Creek Bridge CM/GC...
Transcript of Innovative Delivery Systems for Bridge Preservation Contracts · Pennywash Creek Bridge CM/GC...
![Page 1: Innovative Delivery Systems for Bridge Preservation Contracts · Pennywash Creek Bridge CM/GC delivery method 5 week delivery – 1 week ahead of schedule 10% under initial budget](https://reader033.fdocuments.us/reader033/viewer/2022050408/5f851b3cad4fdd1007438613/html5/thumbnails/1.jpg)
Innovative Delivery Systems for Bridge Preservation Contracts
![Page 2: Innovative Delivery Systems for Bridge Preservation Contracts · Pennywash Creek Bridge CM/GC delivery method 5 week delivery – 1 week ahead of schedule 10% under initial budget](https://reader033.fdocuments.us/reader033/viewer/2022050408/5f851b3cad4fdd1007438613/html5/thumbnails/2.jpg)
![Page 3: Innovative Delivery Systems for Bridge Preservation Contracts · Pennywash Creek Bridge CM/GC delivery method 5 week delivery – 1 week ahead of schedule 10% under initial budget](https://reader033.fdocuments.us/reader033/viewer/2022050408/5f851b3cad4fdd1007438613/html5/thumbnails/3.jpg)
CM/GC Construction Manager/General Contractor
Owner Construction
Manager Designer
Owner, Designer, & CM collaboratively work to
develop project scope, optimize the design,
improve quality, manage costs, and deliver
projects early & under budget 3
![Page 4: Innovative Delivery Systems for Bridge Preservation Contracts · Pennywash Creek Bridge CM/GC delivery method 5 week delivery – 1 week ahead of schedule 10% under initial budget](https://reader033.fdocuments.us/reader033/viewer/2022050408/5f851b3cad4fdd1007438613/html5/thumbnails/4.jpg)
![Page 5: Innovative Delivery Systems for Bridge Preservation Contracts · Pennywash Creek Bridge CM/GC delivery method 5 week delivery – 1 week ahead of schedule 10% under initial budget](https://reader033.fdocuments.us/reader033/viewer/2022050408/5f851b3cad4fdd1007438613/html5/thumbnails/5.jpg)
You are a victim of the rules you live by.
- Jenny Holzer
![Page 6: Innovative Delivery Systems for Bridge Preservation Contracts · Pennywash Creek Bridge CM/GC delivery method 5 week delivery – 1 week ahead of schedule 10% under initial budget](https://reader033.fdocuments.us/reader033/viewer/2022050408/5f851b3cad4fdd1007438613/html5/thumbnails/6.jpg)
adversarial
relationships
![Page 7: Innovative Delivery Systems for Bridge Preservation Contracts · Pennywash Creek Bridge CM/GC delivery method 5 week delivery – 1 week ahead of schedule 10% under initial budget](https://reader033.fdocuments.us/reader033/viewer/2022050408/5f851b3cad4fdd1007438613/html5/thumbnails/7.jpg)
disputes and
change orders
![Page 8: Innovative Delivery Systems for Bridge Preservation Contracts · Pennywash Creek Bridge CM/GC delivery method 5 week delivery – 1 week ahead of schedule 10% under initial budget](https://reader033.fdocuments.us/reader033/viewer/2022050408/5f851b3cad4fdd1007438613/html5/thumbnails/8.jpg)
delays and claims
![Page 9: Innovative Delivery Systems for Bridge Preservation Contracts · Pennywash Creek Bridge CM/GC delivery method 5 week delivery – 1 week ahead of schedule 10% under initial budget](https://reader033.fdocuments.us/reader033/viewer/2022050408/5f851b3cad4fdd1007438613/html5/thumbnails/9.jpg)
high risk
![Page 10: Innovative Delivery Systems for Bridge Preservation Contracts · Pennywash Creek Bridge CM/GC delivery method 5 week delivery – 1 week ahead of schedule 10% under initial budget](https://reader033.fdocuments.us/reader033/viewer/2022050408/5f851b3cad4fdd1007438613/html5/thumbnails/10.jpg)
no incentive for innovation
![Page 11: Innovative Delivery Systems for Bridge Preservation Contracts · Pennywash Creek Bridge CM/GC delivery method 5 week delivery – 1 week ahead of schedule 10% under initial budget](https://reader033.fdocuments.us/reader033/viewer/2022050408/5f851b3cad4fdd1007438613/html5/thumbnails/11.jpg)
loss of control
![Page 12: Innovative Delivery Systems for Bridge Preservation Contracts · Pennywash Creek Bridge CM/GC delivery method 5 week delivery – 1 week ahead of schedule 10% under initial budget](https://reader033.fdocuments.us/reader033/viewer/2022050408/5f851b3cad4fdd1007438613/html5/thumbnails/12.jpg)
STRESS!
![Page 13: Innovative Delivery Systems for Bridge Preservation Contracts · Pennywash Creek Bridge CM/GC delivery method 5 week delivery – 1 week ahead of schedule 10% under initial budget](https://reader033.fdocuments.us/reader033/viewer/2022050408/5f851b3cad4fdd1007438613/html5/thumbnails/13.jpg)
late and over budget projects
![Page 14: Innovative Delivery Systems for Bridge Preservation Contracts · Pennywash Creek Bridge CM/GC delivery method 5 week delivery – 1 week ahead of schedule 10% under initial budget](https://reader033.fdocuments.us/reader033/viewer/2022050408/5f851b3cad4fdd1007438613/html5/thumbnails/14.jpg)
![Page 15: Innovative Delivery Systems for Bridge Preservation Contracts · Pennywash Creek Bridge CM/GC delivery method 5 week delivery – 1 week ahead of schedule 10% under initial budget](https://reader033.fdocuments.us/reader033/viewer/2022050408/5f851b3cad4fdd1007438613/html5/thumbnails/15.jpg)
Connection
![Page 16: Innovative Delivery Systems for Bridge Preservation Contracts · Pennywash Creek Bridge CM/GC delivery method 5 week delivery – 1 week ahead of schedule 10% under initial budget](https://reader033.fdocuments.us/reader033/viewer/2022050408/5f851b3cad4fdd1007438613/html5/thumbnails/16.jpg)
![Page 17: Innovative Delivery Systems for Bridge Preservation Contracts · Pennywash Creek Bridge CM/GC delivery method 5 week delivery – 1 week ahead of schedule 10% under initial budget](https://reader033.fdocuments.us/reader033/viewer/2022050408/5f851b3cad4fdd1007438613/html5/thumbnails/17.jpg)
Why Change Systems
“Management actions are responsible for 85% of all problems.”
- W. Edwards Deming
Union of Japanese Scientists and Engineers Managing Director Kenichi Koyanagi, and
W. Edwards Deming
![Page 18: Innovative Delivery Systems for Bridge Preservation Contracts · Pennywash Creek Bridge CM/GC delivery method 5 week delivery – 1 week ahead of schedule 10% under initial budget](https://reader033.fdocuments.us/reader033/viewer/2022050408/5f851b3cad4fdd1007438613/html5/thumbnails/18.jpg)
![Page 19: Innovative Delivery Systems for Bridge Preservation Contracts · Pennywash Creek Bridge CM/GC delivery method 5 week delivery – 1 week ahead of schedule 10% under initial budget](https://reader033.fdocuments.us/reader033/viewer/2022050408/5f851b3cad4fdd1007438613/html5/thumbnails/19.jpg)
You can’t justify CM/GC for bridge
preservation projects…just use
low bid or design build.
![Page 20: Innovative Delivery Systems for Bridge Preservation Contracts · Pennywash Creek Bridge CM/GC delivery method 5 week delivery – 1 week ahead of schedule 10% under initial budget](https://reader033.fdocuments.us/reader033/viewer/2022050408/5f851b3cad4fdd1007438613/html5/thumbnails/20.jpg)
Pennywash Creek Bridge CM/GC delivery method
5 week delivery – 1 week ahead of schedule
10% under initial budget
Designed around pre-fab girder
No claims, no change orders
Kemper Road Bridge Low- Bid system
5 week delivery – 1 month behind schedule
30% over budget
Change orders and claims during construction
![Page 21: Innovative Delivery Systems for Bridge Preservation Contracts · Pennywash Creek Bridge CM/GC delivery method 5 week delivery – 1 week ahead of schedule 10% under initial budget](https://reader033.fdocuments.us/reader033/viewer/2022050408/5f851b3cad4fdd1007438613/html5/thumbnails/21.jpg)
Parker Bridge – Palm Beach $10M Saved ~ 1.5M
Successful collaboration with USCG & N. Palm Beach & 3rd Parties
$177K in unused Contingency
Significantly Reduced Original Closure Times
FDOT / PCL BASCULE BRIDGES
![Page 22: Innovative Delivery Systems for Bridge Preservation Contracts · Pennywash Creek Bridge CM/GC delivery method 5 week delivery – 1 week ahead of schedule 10% under initial budget](https://reader033.fdocuments.us/reader033/viewer/2022050408/5f851b3cad4fdd1007438613/html5/thumbnails/22.jpg)
Atlantic Blvd – Broward $4M
Saved ~ $275k
~40k in unused contingency
Significantly Reduced Closures
Extensive Innovations
Successful collaboration with USCG & Pompano Beach
FDOT / PCL BASCULE BRIDGES
after
![Page 23: Innovative Delivery Systems for Bridge Preservation Contracts · Pennywash Creek Bridge CM/GC delivery method 5 week delivery – 1 week ahead of schedule 10% under initial budget](https://reader033.fdocuments.us/reader033/viewer/2022050408/5f851b3cad4fdd1007438613/html5/thumbnails/23.jpg)
23
![Page 24: Innovative Delivery Systems for Bridge Preservation Contracts · Pennywash Creek Bridge CM/GC delivery method 5 week delivery – 1 week ahead of schedule 10% under initial budget](https://reader033.fdocuments.us/reader033/viewer/2022050408/5f851b3cad4fdd1007438613/html5/thumbnails/24.jpg)
0
0.2
0.4
0.6
0.8
1
1.2
Design-Bid-Build CM/GC Design-Build
Contingencies & Allowances
Overruns & Change Orders
Base Cost
100%
13%
106% 84%
4%
4%
Award Award
GMP
24
![Page 25: Innovative Delivery Systems for Bridge Preservation Contracts · Pennywash Creek Bridge CM/GC delivery method 5 week delivery – 1 week ahead of schedule 10% under initial budget](https://reader033.fdocuments.us/reader033/viewer/2022050408/5f851b3cad4fdd1007438613/html5/thumbnails/25.jpg)
The opposite of courage in our society is not cowardice,
it is conformity - Rollo May
“It’s Too Much
Work for the
Benefit”
![Page 26: Innovative Delivery Systems for Bridge Preservation Contracts · Pennywash Creek Bridge CM/GC delivery method 5 week delivery – 1 week ahead of schedule 10% under initial budget](https://reader033.fdocuments.us/reader033/viewer/2022050408/5f851b3cad4fdd1007438613/html5/thumbnails/26.jpg)
![Page 27: Innovative Delivery Systems for Bridge Preservation Contracts · Pennywash Creek Bridge CM/GC delivery method 5 week delivery – 1 week ahead of schedule 10% under initial budget](https://reader033.fdocuments.us/reader033/viewer/2022050408/5f851b3cad4fdd1007438613/html5/thumbnails/27.jpg)
Sir Roger Gilbert Bannister
"We are too young to realize that certain things are
impossible... So we will do them anyway."
— William Wiberforce
27
![Page 28: Innovative Delivery Systems for Bridge Preservation Contracts · Pennywash Creek Bridge CM/GC delivery method 5 week delivery – 1 week ahead of schedule 10% under initial budget](https://reader033.fdocuments.us/reader033/viewer/2022050408/5f851b3cad4fdd1007438613/html5/thumbnails/28.jpg)
28
RFP
Award
Design
Construction
Design
RFP
Design Build
Traditional Design Bid Build
Early Construction Selection of both Designer and Builder
CM/GC Design
Early Construction Selection of both Designer and CM
Construction
Construction
![Page 29: Innovative Delivery Systems for Bridge Preservation Contracts · Pennywash Creek Bridge CM/GC delivery method 5 week delivery – 1 week ahead of schedule 10% under initial budget](https://reader033.fdocuments.us/reader033/viewer/2022050408/5f851b3cad4fdd1007438613/html5/thumbnails/29.jpg)
“THINKING is hard work. It’s Why So Few People Do It.” - Henry Ford
![Page 30: Innovative Delivery Systems for Bridge Preservation Contracts · Pennywash Creek Bridge CM/GC delivery method 5 week delivery – 1 week ahead of schedule 10% under initial budget](https://reader033.fdocuments.us/reader033/viewer/2022050408/5f851b3cad4fdd1007438613/html5/thumbnails/30.jpg)
Bitter Creek Bridge Grand County , Utah
100% Plans
Originally slated for full replacement at $4.0 M
Resulted in simple bridge girder repair
Final cost was $400 K
30
![Page 31: Innovative Delivery Systems for Bridge Preservation Contracts · Pennywash Creek Bridge CM/GC delivery method 5 week delivery – 1 week ahead of schedule 10% under initial budget](https://reader033.fdocuments.us/reader033/viewer/2022050408/5f851b3cad4fdd1007438613/html5/thumbnails/31.jpg)
“IT’S RISKY BRINGING
A CONGRACTOR IN
THAT EARLY” 31
“It’s Risky Bringing in
a Contractor that
Early”
![Page 32: Innovative Delivery Systems for Bridge Preservation Contracts · Pennywash Creek Bridge CM/GC delivery method 5 week delivery – 1 week ahead of schedule 10% under initial budget](https://reader033.fdocuments.us/reader033/viewer/2022050408/5f851b3cad4fdd1007438613/html5/thumbnails/32.jpg)
32
Total Risk
Contractor Risk
Contractor Risk Agency Risk
Agency Risk
D-B-B CM/GC D-B
![Page 33: Innovative Delivery Systems for Bridge Preservation Contracts · Pennywash Creek Bridge CM/GC delivery method 5 week delivery – 1 week ahead of schedule 10% under initial budget](https://reader033.fdocuments.us/reader033/viewer/2022050408/5f851b3cad4fdd1007438613/html5/thumbnails/33.jpg)
![Page 34: Innovative Delivery Systems for Bridge Preservation Contracts · Pennywash Creek Bridge CM/GC delivery method 5 week delivery – 1 week ahead of schedule 10% under initial budget](https://reader033.fdocuments.us/reader033/viewer/2022050408/5f851b3cad4fdd1007438613/html5/thumbnails/34.jpg)
1. Innovation
2. Reduction of Risk
3. Aggressive Delivery
4. Cost Control
5. Team Selection
6. Constructability
7. Streamlined Plans
8. Quality
9. Early Work Packages
10. Flexibility in Changing Project Scope 34
![Page 35: Innovative Delivery Systems for Bridge Preservation Contracts · Pennywash Creek Bridge CM/GC delivery method 5 week delivery – 1 week ahead of schedule 10% under initial budget](https://reader033.fdocuments.us/reader033/viewer/2022050408/5f851b3cad4fdd1007438613/html5/thumbnails/35.jpg)
![Page 36: Innovative Delivery Systems for Bridge Preservation Contracts · Pennywash Creek Bridge CM/GC delivery method 5 week delivery – 1 week ahead of schedule 10% under initial budget](https://reader033.fdocuments.us/reader033/viewer/2022050408/5f851b3cad4fdd1007438613/html5/thumbnails/36.jpg)
“Take the first step in faith. You don’t have to
see the whole staircase. Just take the first
step” - Martin Luther King JR.
![Page 37: Innovative Delivery Systems for Bridge Preservation Contracts · Pennywash Creek Bridge CM/GC delivery method 5 week delivery – 1 week ahead of schedule 10% under initial budget](https://reader033.fdocuments.us/reader033/viewer/2022050408/5f851b3cad4fdd1007438613/html5/thumbnails/37.jpg)
Kenneth E. Atkins, P.E.
(720) 963-3416
Lakewood, CO
Gregg A. Hostetler, P.E.
(405) 227-0531
Edmond, OK
QUESTIONS
0
“We can't solve problems by using the same kind of
thinking we used when we created them.”
- Albert Einstein