Innovations on the Asphalt Mix Design for the Rehabilitation of National Route 3 between...

17
Innovations on the Asphalt Mix Design for the Rehabilitation of National Route 3 between Mariannhiill and Key Ridge Jaco Liebenberg Dennis Rossmann Philip Joubert

Transcript of Innovations on the Asphalt Mix Design for the Rehabilitation of National Route 3 between...

Page 1: Innovations on the Asphalt Mix Design for the Rehabilitation of National Route 3 between Mariannhiill and Key Ridge Jaco Liebenberg Dennis Rossmann Philip.

Innovations on the Asphalt Mix Design for

the Rehabilitation of National Route 3

between Mariannhiill and Key Ridge

Jaco Liebenberg

Dennis Rossmann

Philip Joubert

Page 2: Innovations on the Asphalt Mix Design for the Rehabilitation of National Route 3 between Mariannhiill and Key Ridge Jaco Liebenberg Dennis Rossmann Philip.

Overview

• Introduction to project• Structural design limitations• Mix design requirements• Mix design process• Mix design performance tests & results• Construction

Page 3: Innovations on the Asphalt Mix Design for the Rehabilitation of National Route 3 between Mariannhiill and Key Ridge Jaco Liebenberg Dennis Rossmann Philip.

CBR 3 subgrade

Introduction

• N3/1&2 Mariannhill – Key Ridge• Main link Durban - Gauteng• Constructed in 1985• 40 to 50 million E80’s• Constructed as• Maintenance

– 1994/5 (+14 years)

• Identified for Rehabilitation– 2006 (+20 years)

150 mm G7 selected

40 mm AG

125 mm AC

300 mm C3 subbase

40 mm AC

13 mm Bitumen rubber seal

Page 4: Innovations on the Asphalt Mix Design for the Rehabilitation of National Route 3 between Mariannhiill and Key Ridge Jaco Liebenberg Dennis Rossmann Philip.

Introduction

• Major typical defects– Rutting in slow lane– Some isolated rutting in middle lane– Cracking and pumping in slow lane

• Design traffic

• Design requirements– Slow lane: Substantial pavement required– Middle lane: Some repairs required– Fast lane: None required

Slow lane Middle lane

15 years 70 million 22 million

30 years 185 million 54 million

Page 5: Innovations on the Asphalt Mix Design for the Rehabilitation of National Route 3 between Mariannhiill and Key Ridge Jaco Liebenberg Dennis Rossmann Philip.

Pavement Design Options

40 mm AC

125 mm AC

150 mm G7 selected

300 mm C3 subbase

CBR 3 subgrade

? mm overlay? mm Concrete overlay

Page 6: Innovations on the Asphalt Mix Design for the Rehabilitation of National Route 3 between Mariannhiill and Key Ridge Jaco Liebenberg Dennis Rossmann Philip.

Pavement Design Options

40 mm AC

125 mm AC

150 mm G7 selected

300 mm C3 subbase

CBR 3 subgrade

Page 7: Innovations on the Asphalt Mix Design for the Rehabilitation of National Route 3 between Mariannhiill and Key Ridge Jaco Liebenberg Dennis Rossmann Philip.

Pavement Design Options

150 mm G7 selected

300 mm C3 subbase

CBR 3 subgrade

Page 8: Innovations on the Asphalt Mix Design for the Rehabilitation of National Route 3 between Mariannhiill and Key Ridge Jaco Liebenberg Dennis Rossmann Philip.

Structural design

• Stabilised subbase performed well– Only localised repairs required– Not thick enough for traffic volume (req 450 mm)

• Asphalt inlay considered most appropriate– Mix design to compliment structural design– Stiff as possible (req: E = 4 000 Mpa)

• Slow lane– Signs of stripping in lower part of layer replace all asphalt– Selective repairs of subbase

• Middle lane– Some cracking and deformation Only repair upper 80 mm

• Fast lane– Only Isolated repairs

• New surfacing over full width

Paper discuss process to consider for restrictions in structural design by optimising the asphalt mix design

Page 9: Innovations on the Asphalt Mix Design for the Rehabilitation of National Route 3 between Mariannhiill and Key Ridge Jaco Liebenberg Dennis Rossmann Philip.

Mix design requirements

• Primary requirements– Rut resistant– Stiff (≈ 4 000 MPa)– Fatigue resistant

• Secondary requirements– Low permeability– Good moisture susceptibility

• Mix design process– Standard mix design process– 2 mix designs in parallel – selection process– Much emphasis on performance testing– Performance tests on mixes from trial sections

Page 10: Innovations on the Asphalt Mix Design for the Rehabilitation of National Route 3 between Mariannhiill and Key Ridge Jaco Liebenberg Dennis Rossmann Philip.

Mix design

• Aggregate and grading – Coarse aggregate quartzite– Fine aggregate: quartzite & tillite mix– Bailey method to determine optimum grading– Contained 15 % RAP

• Binders– Two binders evaluated– A-P1 (4% EVA) with Optimum binder Content @ 4.2%– vs. A-E2 (3.5% SBS) with Optimum binder Content @ 4.4%

• Min component of mix design:– Performance under accelerated testing

• 6 trial sections constructed– Directly north of toll Plaza in slow lane– A-P1 mix: 3.9% 4.2% and 4.5%– A-E2 mix: 4.0% 4.3% and 4.6%

0.01 0.1 1 10 1000

10

20

30

40

50

60

70

80

90

100

Sieve Size (mm)

% P

as

sin

g

Page 11: Innovations on the Asphalt Mix Design for the Rehabilitation of National Route 3 between Mariannhiill and Key Ridge Jaco Liebenberg Dennis Rossmann Philip.

Trial sections

• From trial sections (extracted from pavement)– 228 cores– 16 beams

• Tested for– Rut resistance under MMLS and Hamburg wheel tracking– Moisture susceptibility under MMLS and mod. Lottmann– Permeability– Fatigue

Page 12: Innovations on the Asphalt Mix Design for the Rehabilitation of National Route 3 between Mariannhiill and Key Ridge Jaco Liebenberg Dennis Rossmann Philip.

Deformation and rutting resistance

• MMLS testing and Hamburg wheel tracking tests– Also discussed in paper by Hugo et.al

4.2% A-P1

4.5% A-P1

4.3 % A-E2

4.5 % A-E2

MMLS Dry, 7200/hr, 60 °C Yes Yes Yes Yes

MMLS Dry, 2400/hr, 60 °C Yes No Yes No

MMLS Wet, 7200/hr, 60 °C Yes No Yes No

Hamburg Yes Yes Yes Yes

A-P1 (3,9%) A-P1 (4,2%) A-P1 (4,5%) A-E2 (4,1%) A-E2 (4,4%) A-E2 (4,7%)0

0.5

1

1.5

2

2.5

3

3.5MMLS

MMLS dry @ 7 200/hour

MMLS wet @ 7 200/hour

Mix

Ru

t a

fte

r 1

00

00

0 r

ep

itit

ion

s (

mm

)

A-P1 (3,9%) A-P1 (4,2%) A-P1 (4,5%) A-E2 (4,1%) A-E2 (4,4%) A-E2 (4,7%)0

0.0001

0.0002

0.0003

0.0004

0.0005

0.0006

0.0007Hamburg wheel tracking

Mix

Ru

t ra

te (

mm

/pa

ss

)

Page 13: Innovations on the Asphalt Mix Design for the Rehabilitation of National Route 3 between Mariannhiill and Key Ridge Jaco Liebenberg Dennis Rossmann Philip.

Fatigue resistance

• Coarse rut resistant mixes generally poor fatigue• Beams extracted from pavement

– 6 beams for 4.2% A-P1 tested– 6 beams for 4.3% A-E2 tested

• Fatigue test– 4 point bending beam– Constant strain

10 000 100 000 1 000 000 10 000 0000

50

100

150

200

250

300

350

400

450

500

Repetitions

Str

ain

(m

e)

A-P1

A-E2

Page 14: Innovations on the Asphalt Mix Design for the Rehabilitation of National Route 3 between Mariannhiill and Key Ridge Jaco Liebenberg Dennis Rossmann Philip.

Adopted mix design

• A-P1 mix considered most appropriate mix– Better rut resistance– Better moisture susceptibility– Fatigue comparable to A-E2, within acceptable guidelines

• A-E2 probably suitable as well• Performance tests A-P1

Page 15: Innovations on the Asphalt Mix Design for the Rehabilitation of National Route 3 between Mariannhiill and Key Ridge Jaco Liebenberg Dennis Rossmann Philip.

Construction

• High level of control comfort design intent is built• Tight control of

– Mix properties– Compaction

• Ability to project trends and act pro-actively• Construction quality

– No rejected work or rework on Asphalt base– Some issues recently with UTFC currently being investigated

Page 16: Innovations on the Asphalt Mix Design for the Rehabilitation of National Route 3 between Mariannhiill and Key Ridge Jaco Liebenberg Dennis Rossmann Philip.

Conclusions

• Limitations during structural design• Possible to optimise mix design to compliment

structural design– Require cooperation

• Asphalt mix design process– Benefits not a standalone process– Tie in with pavement design

• Attention to mix design – mix appropriate for application – considers unique requirements for application

Page 17: Innovations on the Asphalt Mix Design for the Rehabilitation of National Route 3 between Mariannhiill and Key Ridge Jaco Liebenberg Dennis Rossmann Philip.