Initial Presentation Group 3

download Initial Presentation Group 3

of 37

Transcript of Initial Presentation Group 3

  • 8/13/2019 Initial Presentation Group 3

    1/37

    an initial presentation on 16/10/2013

    Muhammad Aiman bin Abdul Rahman (006119) Nur Afiqah binti Jamalludin Al Amini (006081) Nik Muhammad Izzat bin Azhar (006154) Stanley Chia Uei Ying (009786) Lau Lee Yeo (009790)

    H24A03 Group Design Project 2013/2014

    5-STAR MAJESTIC HOTEL

    1

  • 8/13/2019 Initial Presentation Group 3

    2/37

    Documents provided at start

    1. Topographic map of the site2. Soil investigation (SI) report

    2

  • 8/13/2019 Initial Presentation Group 3

    3/37

    CONTENT OF THE PRESENTATION

    1. Aims and objectiv es2. Concept

    3. List of the refurbis hment works4. Conceptual design 5. Construction planning

    6. Basement parkin g const ruction7. Cost Estimation8. Environmental Assessment

    3

  • 8/13/2019 Initial Presentation Group 3

    4/37

    Aimsand Objectives To refurbish the existing building To build a new accommodation block To maintain a heritage building with a luxury of a 5-star hotel To come out with design solutions for complex engineering

    problems To consider public health and safety, cultural, societal, and

    environmental considerations during construction phas e

    4

  • 8/13/2019 Initial Presentation Group 3

    5/37

    A hint of history in a

    modern city -concept established from aims

    Combination of Neo-classical and art decostyle for the new building New building complements the existing

    building

    5

  • 8/13/2019 Initial Presentation Group 3

    6/37

    Refurbishment work-the list of planned activities 1

    Structural work Fatigue and cracking

    repairs Concrete repair or

    strengthening Frame inspection

    Bathroom Floor tiling

    Wall tiling Plumbing work Electrical work

    6

  • 8/13/2019 Initial Presentation Group 3

    7/37

    Refurbishment work-the list of planned activities 2 (continuation)

    Bedroom Carpet Wallpaper Air conditioning Electrical fittings Light fittings Telephone fittings Ceiling Finishing

    Floor Hallway Carpet Wallpaper Decorations Light fittings Ceiling Fire doors Sprinkler system

    7

  • 8/13/2019 Initial Presentation Group 3

    8/37

    Conceptual design of existing building- Majestic Wing

    8

    MajesticWing

    The ColonialCafe

    The TeaLounge

    The BarSuites with

    ButlerService

  • 8/13/2019 Initial Presentation Group 3

    9/37

    Conceptual design of new block- Tower Wing

    9

    Tower Wing

    ReceptionDeluxe

    Rooms &

    Suites

    Opus OneRestaurantGymnasium

    SwimmingPool

    BallroomMeetingRooms

  • 8/13/2019 Initial Presentation Group 3

    10/37

    Conceptual design of new block- facilities provided 1

    Two parts: Accommodations Management and Leisure

    Area Design 1 = 2767 sq.m Area Design 2 = 2400 sq.m 132 deluxe rooms 121 suites

    10

  • 8/13/2019 Initial Presentation Group 3

    11/37

    Conceptual design of new block- facilities provided 2 (continuation)

    An administration and staff floor Entertainment floor Roof garden Basement parking

    11

  • 8/13/2019 Initial Presentation Group 3

    12/37

    Sketches of the 1 st design(lobby)- with the location of columns

    12

  • 8/13/2019 Initial Presentation Group 3

    13/37

    Sketches of the 1 st design(2 nd floor)- with the location of columns

    13

  • 8/13/2019 Initial Presentation Group 3

    14/37

    Sketches of the 1 st design(3 rd floor)- with the location of columns

    14

  • 8/13/2019 Initial Presentation Group 3

    15/37

    Sketches of the 1 st design(floor plan A)- with the location of columns

    15

    22 deluxe rooms4 junior suite5 Premier SuiteThere will be 6 typical floors of

    this layout

  • 8/13/2019 Initial Presentation Group 3

    16/37

    Sketches of the 1 st design(floor plan B)- with the location of columns

    16

    20 Junior Suite2 Premier Suite

    2 typical floors

  • 8/13/2019 Initial Presentation Group 3

    17/37

    Sketches of the 1 st design(floor plan C)- with the location of columns

    17

    16 Premier Suite

  • 8/13/2019 Initial Presentation Group 3

    18/37

    Sketches of the 1 st design(floor plan D)- with the location of columns

    18

    10 Majestic suite2 Premier suite

  • 8/13/2019 Initial Presentation Group 3

    19/37

    Sketches of 2 nd Design- with the location of columns 1

    19

    LobbyRestaurantLounge

    Bar

    2nd FloorSwimming PoolGymnasiumBallroom

  • 8/13/2019 Initial Presentation Group 3

    20/37

    Sketches of 2 nd Design- with the location of columns 2 (continuation)

    20

    Type A LayoutDeluxe roomsMeeting rooms

    4 typical floors

    Type B LayoutPremier Suites5 typical floors

  • 8/13/2019 Initial Presentation Group 3

    21/37

    Sketches of 2 nd Design- with the location of columns 3 (continuation)

    21

    Type C Layout12 Majestic Suites1 typical floors

  • 8/13/2019 Initial Presentation Group 3

    22/37

    Artist Impression of Majestic Hotel

    22

  • 8/13/2019 Initial Presentation Group 3

    23/37

    Construction planning 1

    23

  • 8/13/2019 Initial Presentation Group 3

    24/37

    Construction planning 2

    Provide an access road for the equipment route(traffic management on site)

    Determine the site area and provide safetybarrier, warning signs Established an exact location of underground

    services (electrical power, sewer pipes,telecommunications cables, etc.) before anyexcavation activity starts

    Provide an area for stockpiling on site

    24

  • 8/13/2019 Initial Presentation Group 3

    25/37

    Construction planning- layout plan of the site

    25

  • 8/13/2019 Initial Presentation Group 3

    26/37

    Construction planning- recommended access route

    26

  • 8/13/2019 Initial Presentation Group 3

    27/37

    Construction of Basement

    1) Diaphragm wall Reinforced concrete wall

    Can be designed to take very high structural load2) Steel sheet pile

    Consists of driven interlocked steel panels

    Each pile is engaged with and driven in alongsidethe previous one thereby creating an imperviouswall

    27

  • 8/13/2019 Initial Presentation Group 3

    28/37

    Construction of Basement using Diaphragm wall(conceptual installation)

    28

  • 8/13/2019 Initial Presentation Group 3

    29/37

    Construction of Basement using steelsheet pile

    29

  • 8/13/2019 Initial Presentation Group 3

    30/37

    Reason for diaphragm wall asbasement construction method

    30

    1. Can carry vertical loads too compare with steel sheet pile2. Noise levels limited to engine noise only3. No vibration during installation4. Commonly used in congested areas.5. Can be installed in close proximity to existing structure6. Flexible system in plan layout7. Can be installed to considerable depth8. Easily incorporated into permanent works9. Economic and positive solution for large deep basement in

    saturated and unstable soil profiles.

  • 8/13/2019 Initial Presentation Group 3

    31/37

    Why not steel sheet pile wall?

    Sections can rarely be used as part of the permanentstructure

    Installation is difficult in soils with boulders or cobbles. Excavation shapes are dictated by the sheet pile section

    and interlocking elements Sheet pile driving may cause neighbourhood

    disturbance Settlements in adjacent properties may take place due

    to installation vibrations

    31

  • 8/13/2019 Initial Presentation Group 3

    32/37

    Cost Estimation

    32

  • 8/13/2019 Initial Presentation Group 3

    33/37

    Environmental Assessment-the impact to the environment during construction phase

    Destroy habitat and alter biodiversity. Prevent the growth of native plant species. Change in drainage patterns of the area. Create dust or air pollution. Generates noise pollution.

    33

  • 8/13/2019 Initial Presentation Group 3

    34/37

    Environmental Assessment-measures to control the impact to the environment 1

    1. During site clearance Minimize the need for cutting of trees & damage to the native

    vegetation. Phase out the site clearing process to only areas that need excavation

    initially, this will reduce the dust emission from currently unusedareas.

    Vegetate the unused area by growing temporary groundcover plantsor flower beds.

    2. During construction of access road Frequent water sprinkling is required to reduce local dust emissions.

    3. During excavation On windy days avoid excavation activities to reduce dust emissions Prevent the excavated soil from spilling out of the site boundaries on

    to adjoining roads and properties.

    34

  • 8/13/2019 Initial Presentation Group 3

    35/37

    Environmental Assessment-measures to control the impact to the environment 2

    4. During drainage works Provide a basic surface drainage system for the site to avoid

    water runoff on to the surrounding properties and roads,especially during the monsoon months.

    If during excavation, water accumulates in the excavated areas,then it should be pumped out and disposed of either in themunicipal storm water drain or into recharge soak pits of drybore wells.

    5. During maintenance of vehicle

    Construction vehicles should be properly maintained tominimize smoke in the exhaust emissions Prevent contamination of surface and ground water sources by

    accidental spillages of oil and fuel.

    35

  • 8/13/2019 Initial Presentation Group 3

    36/37

    Environmental Assessment-measures to control the impact to the environment 3

    6. During loading and unloading material Sweep and clean adjacent roads of the site that

    get soiled due to the frequent movement of trucksto and fro from the site, at least once a day. Load and unload trucks on site and not on

    surrounding roadside.

    36

  • 8/13/2019 Initial Presentation Group 3

    37/37

    Q/A SESSION

    thank you

    37

    END OF PRESENTATION