INFRASTRUCTURE ASSET MANAGEMENT PLAN and Wor… · Ensuring future growth is covered in long term...
Transcript of INFRASTRUCTURE ASSET MANAGEMENT PLAN and Wor… · Ensuring future growth is covered in long term...
INFRASTRUCTURE ASSET
MANAGEMENT PLAN TRANSPORT
Version 4.1 May 2017
This Transport Infrastructure Asset Management Plan has been declared by The Barossa Council as a
Strategic Management Plan pursuant to Section 122(8) of the Local Government Act 1999.
Document Control
TRIM Reference: 17/32485
Rev No Date Revision Details Author Reviewer Approver
1 18/11/2008 Version 1.0 DGH MJL MJL
2 20/11/2012 Version 2.0 DGH AMWP MJL
3 11/07/2016 Version 3.0 MAI OMG CMT
4 21/11/2016 Version 4.0 MAI Key Stakeholders Council
4.1 16/5/2017 Version 4.1 CAM Public& Key
Stakeholders Council
THE BAROSSA COUNCIL – TRANSPORT INFRASTRUCTURE ASSET MANAGEMENT PLAN
TABLE OF CONTENTS
1. EXECUTIVE SUMMARY................................................................................................................ 1
Context ........................................................................................................................................ 1
What does it Cost? .................................................................................................................... 3
What we will do ......................................................................................................................... 4
What we cannot do ................................................................................................................. 4
Managing the Risks ................................................................................................................... 4
Confidence Levels .................................................................................................................... 5
The Next Steps ............................................................................................................................ 5
2. INTRODUCTION........................................................................................................................... 6
2.1 Background ........................................................................................................................ 6
2.2 Goals and Objectives of Asset Management ........................................................... 10
2.3 Plan Framework ............................................................................................................... 11
2.4 Core and Advanced Asset Management................................................................. 13
2.5 Community Consultation ............................................................................................... 13
3. LEVELS OF SERVICE .................................................................................................................. 14
3.1 Customer Research and Expectations ....................................................................... 14
3.2 Strategic and Corporate Goals ................................................................................... 14
3.3 Legislative Requirements ............................................................................................... 15
3.4 Community Levels of Service ........................................................................................ 16
3.5 Technical Levels of Service ............................................................................................ 17
4. FUTURE DEMAND ...................................................................................................................... 35
4.1 Demand Drivers ............................................................................................................... 35
4.2 Demand Forecast ........................................................................................................... 35
4.3 Demand Impact on Assets ............................................................................................ 35
4.4 Demand Management Plan ........................................................................................ 37
4.5 Asset Programs to meet Demand ................................................................................ 37
5. LIFECYCLE MANAGEMENT PLAN ........................................................................................... 40
5.1 Background Data............................................................................................................ 41
5.2 Infrastructure Risk Management Plan ......................................................................... 68
5.3 Routine Operations and Maintenance Plan.............................................................. 69
5.4 Renewal/Replacement Plan......................................................................................... 76
5.5 Creation/Acquisition/Upgrade Plan ............................................................................ 82
5.6 Disposal Plan .................................................................................................................... 83
5.7 Service Consequences and Risks ................................................................................. 83
6. FINANCIAL SUMMARY ............................................................................................................. 85
6.1 Financial Statements and Projections ......................................................................... 85
6.2 Funding Strategy ............................................................................................................. 92
6.3 Valuation Forecasts ........................................................................................................ 93
6.4 Key Assumptions made in Financial Forecasts .......................................................... 98
6.5 Forecast Reliability and Confidence ........................................................................... 99
7. PLAN IMPROVEMENT AND MONITORING .......................................................................... 101
7.1 Status of Asset Management Practices .................................................................... 101
7.2 Improvement Plan ......................................................................................................... 106
7.3 Monitoring and Review Procedures .......................................................................... 107
7.4 Performance Measures ................................................................................................ 107
8. REFERENCES ............................................................................................................................ 108
9. APPENDICES............................................................................................................................ 109
Appendix A Maintenance Response Levels of Service ................................................ 109
Appendix B Projected 10 year Capital Renewal and Replacement Works
Program ........................................................................................................................... 114
Appendix C Budgeted Expenditures Accommodated in LTFP ................................... 123
Appendix D State of The Assets ......................................................................................... 125
Appendix E Abbreviations .................................................................................................. 126
Appendix F Glossary ............................................................................................................ 128
- 1 -
THE BAROSSA COUNCIL – TRANSPORT INFRASTRUCTURE ASSET MANAGEMENT PLAN
1. EXECUTIVE SUMMARY
Context
The Barossa Council covers 912 square kilometres and is located 80 kilometres north-east of the
Adelaide Central Business District. It is bordered by the municipalities of Town of Gawler, Light
Regional Council, Mid Murray Council, Adelaide Hills Council and the City of Playford. The Barossa
Council encompasses six major towns, Mount Pleasant, Angaston, Nuriootpa, Tanunda, Lyndoch
and Williamstown as well as 7 smaller towns and communities with a population of approximately
23,500.
Council’s Transport assets are maintained and managed in accordance with all regulatory
requirements, relevant Australian Standards and Local Government Act 1999.
Current service levels vary across the Council area and are managed and maintained in
partnership with other levels of government and stakeholders. Capacity is being met with existing
asset infrastructure and upgrade and renewal is considered against community expectations and
growth.
The Service
The Transport network comprises:
Asset Class Asset Type
Current
Replacement
Cost
Length
(m) Count
Footpath Bitumen - Spray Seal Footpath Surface Type $1,889,971 46,058 319
Footpath Bitumen - Hotmix Footpath Surface Type $1,147,499 12,087 25
Footpath Concrete Footpath Surface Type $1,108,052 8,693 124
Footpath Natural Footpath Surface Type $1,396.40 34,589 288
Footpath Paved Footpath Surface Type $3,011,488 30,793 339
Footpath Rubble Footpath Surface Type $832,798 37,785 347
Footpath $7,991,204 170,005 1442
Kerb and Gutter Median Kerb $308,265 2,792 26
Kerb and Gutter Rollover Kerb & gutter $12,629,502 71,236 623
Kerb and Gutter Stone Kerb & gutter $78,247 283 2
Kerb and Gutter Upright Kerb & gutter $29,521,805 166,298 1353
Kerb and Gutter $42,537,819 240,609 2004
Road Earth Road Earth Type $13,018,679 983,913 2175
Road Earth $13,018,679 983,913 2175
Rural Pavement Rural B Double Normal Use Hotmix Pavement
Type $786,581 2,218 4
Rural Pavement Rural B Double Normal Use Spray Pavement
Type $7,085,663 18,600 22
Rural Pavement Rural Heavy Use Hotmix Pavement Type $1,808,584 4780 25
Rural Pavement Rural Heavy Use Spray Pavement Type $13,207,669 35,904 47
Rural Pavement Rural Normal Use Hotmix Pavement Type $2,783,513 11,398 33
Rural Pavement Rural Normal Use Spray Pavement Type $32,721,732 125,372 285
- 2 -
THE BAROSSA COUNCIL – TRANSPORT INFRASTRUCTURE ASSET MANAGEMENT PLAN
Asset Class Asset Type
Current
Replacement
Cost
Length
(m) Count
Rural Pavement $58,393,742 198,272 416
Roundabout Barossa Roundabout $50,000
Roundabout $50,000 1
Rural Sheeted Surface Rural Road Reserve Surface $4,158 282 2
Rural Sheeted Surface Rural Sheeted Surface Function Priority 2,1 $8,125,585 334,364 350
Rural Sheeted Surface Rural Sheeted Surface Function Priority 3 $2,113,007 83,720 86
Rural Sheeted Surface Rural Sheeted Surface Function Priority 5,4 $5,166,838 128,979 138
Rural Sheeted Surface Rural Sheeted Surface Function Priority 6 $366,961 10,099 7
Rural Sheeted Surface Rural Sheeted Surface Function Priority 7 $508,938 10,726 13
Rural Sheeted Surface Rural Sheeted Surface Function Priority 10,9 $31,699.60 1,283 1
Rural Sheeted Surface $16,317,187 568,170 597
Sealed Surface Rural - B Double Route - Normal Use Hotmix $434,969 2,218 4
Sealed Surface Rural - B Double Route - Normal Use Spray Seal $907,714 16,444 20
Sealed Surface Rural Heavy Use Hotmix Bitumen Surface $958,311 6653 27
Sealed Surface Rural Heavy Use Spray Seal Bitumen Surface $1,804,555 38,105 50
Sealed Surface Rural Normal Use Hotmix Bitumen Surface $1,349,368 12,485 34
Sealed Surface Rural Normal Use Spray Seal Bitumen Surface $4,835,019 137,565 307
Sealed Surface Township Heavy Use Hotmix Bitumen Surface $919,986 4,202 25
Sealed Surface Township Heavy Use Spray Seal Bitumen
Surface $169,534 2,836 10
Sealed Surface Township Normal Use Hotmix Bitumen Surface $8,098,194 63,469 518
Sealed Surface Township Normal Use Skinny Hotmix Bitumen
Surface (20mm) $515,459 4,164 25
Sealed Surface Township Normal Use Slurry Seal / Cold Overlay
Surface $745,927 5,960 57
Sealed Surface Township Normal Use Spray Seal Bitumen
Surface $2,941,861 75,936 435
Sealed Surface Township Paver Surface $12,351 34 1
Sealed Surface $23,693,248 393,851 1513
Township Pavement Township Heavy Use Hotmix Pavement Type $1,411,684 3,791 22
Township Pavement Township Heavy Use Sprayseal Pavement Type $1,276,337 3,536 13
Township Pavement Township Normal Use Hotmix Pavement Type $12,813,898 59,880 492
Township Pavement Township Normal Use Skinny Pavement Type $590,738 2,709 15
Township Pavement Township Normal Use Slurry Pavement Type $1,535,808 7,059 57
Township Pavement Township Normal Use Sprayseal Pavement Type $17,887,183 79,977 460
Township Pavement $35,515,648 180,732 1061
Township Sheeted
Surface Township Sheeted Surface Function Priority 2,1 $12,158 815 4
Township Sheeted
Surface Township Sheeted Surface Function Priority 3 $23,537 1,513 10
Township Sheeted
Surface Township Sheeted Surface Function Priority 5,4 $108,023 4041 27
- 3 -
THE BAROSSA COUNCIL – TRANSPORT INFRASTRUCTURE ASSET MANAGEMENT PLAN
Asset Class Asset Type
Current
Replacement
Cost
Length
(m) Count
Township Sheeted
Surface $143,717 6369 41
Bike Path Surface Township Normal Use Skinny Hotmix Bitumen
Surface (20mm) - Bike Path $820,410 23,780 2
Bike Path Surface $820,410 23,780 2
Bike Path Pavement Township Normal Use Skinny Pavement Type -
Bike Path $1,321,574 23,780 2
Bike Path Pavement $1,321,574 23,780 2
Asset Class Asset Type
Current
Replacement
Cost
Area (m2) Count
Car Park Car Park - Hotmix Surface $291,503 16,899 10
Car Park Car Park - Paver Surface $119,640 1,638 2
Car Park Car Park - Spray Seal Surface $9,697 2,050 1
Car Park Car Park – Rubble Surface $50,000 1,413 1
Car Park $470,840 22,000 14
Total $200,274
As at 30 June 2016
These Transport assets have a current replacement cost of $200.274 M1
What does it Cost?
The projected outlays necessary to provide the services covered by this Asset Management Plan
(Asset Management Plan) includes operations, maintenance, renewal and upgrade of existing
assets over the 10 year planning period is $46.494 M or $4.649 M on average per year.
Estimated available funding for this period is $70.389 M or $7.039 M on average per year which is
132% of the cost to provide the service. Projected expenditure required to provide services in the
Asset Management Plan compared with planned expenditure currently included in the Long Term
Financial Plan are shown in the graph below.
1 Unless indicated otherwise all numbers will be represented in $000’s.
- 4 -
THE BAROSSA COUNCIL – TRANSPORT INFRASTRUCTURE ASSET MANAGEMENT PLAN
What we will do
We plan to provide Transport services as follows:
1. Ensure the Transport network is maintained at a safe and functional standard.
2. Minimise disruption to the network through regular maintenance.
3. Upgrade / replace Transport infrastructure where required.
What we cannot do
We cannot deviate from the projected operational and capital expenditure and need to account
for these costs in the LTFP and annual Transport budget.
Managing the Risks
There are risks associated with providing the service and being able to complete all identified
activities and projects. We have identified major risks as:
Legislative requirements
Disaster Management recommendations
Customer expectations
Population and Tourism growth
Environmental expectations
Climate change forecasts
Emergent flooding issues
We will endeavour to manage these risks within available funding by:
Transport
- 5 -
THE BAROSSA COUNCIL – TRANSPORT INFRASTRUCTURE ASSET MANAGEMENT PLAN
Continued effective programmed and preventative maintenance.
Continued operation improvements in tasks and activities.
Continued monitoring and condition assessment of the network.
Ensuring future growth is covered in long term capital works plans.
Confidence Levels
This Asset Management Plan is based on a high level of confidence information.
The Next Steps
The actions resulting from this asset management plan are:
Develop specific service levels including performance targets.
Develop and establish ongoing assessment in relationship to safety and specified maintenance
intervention levels.
Audit and review of maintenance response times (to confirm whether maintenance works are
delivered on time).
Random audit of maintenance works (to confirm whether maintenance works are delivered to
the specified quality).
Review and assess transport plans, community expectations and customer feedback/contact.
Consultation to ascertain the community’s service needs and preferences and confirm
performance targets.
Completing the improvement plan by November 2020.
Review of the customer request reports available in Pathway.
Questions you may have
What is this plan about?
This asset management plan covers the transport infrastructure assets that serve The Barossa
Council community. These assets include sealed roads, sheeted roads, car parks, footpaths, pavement, kerb and gutter and road earth.
What is an Asset Management Plan?
Asset management planning is a comprehensive process to ensure that the delivery of services
from infrastructure is provided in a financially sustainable manner.
An asset management plan details information about infrastructure assets including actions
required to provide an agreed level of service in the most cost effective manner. The plan defines
the services to be provided, how the services are provided and what funds are required to provide
the services.
Do we have a funding shortfall?
Based on the information available as at 30 June 2015; present funding levels are sufficient to
continue to provide existing services at current levels in the medium term.
What can we do?
Continue to provide services and budget to enable sufficient capacity improvements and
maintenance of the network.
What can you do?
Council through this asset management plan is open to suggestions on how we may change or
reduce its Transport network services to ensure that the appropriate level of service can be
provided to the community within available funding.
- 6 -
THE BAROSSA COUNCIL – TRANSPORT INFRASTRUCTURE ASSET MANAGEMENT PLAN
2. INTRODUCTION
2.1 Background
The goal of the asset management plan is to demonstrate responsive management of assets (and
services provided from assets), compliance with regulatory requirements, and to communicate funding needed to provide the required levels of service over a 20 year planning period.
The asset management plan follows the format for Asset Management Plans recommended in Section 4.2.4 of the International Infrastructure Management Manual2.
The asset management plan is to be read with the organisation’s Asset Management Policy, Asset
Management Strategy (draft document) and the following associated planning documents:
Council’s Long Term Financial Plan (as adopted July 2016)
The Barossa Council Corporate Plan 16/17 to 19/20
Barossa Community Plan 2016 – 2036
Annual Budget and Business Plan (as adopted July 2016)
Annual Financial Statements for the Year Ending 30 June 2015
This infrastructure assets covered by this asset management plan are shown in Table 2.1. These assets are used to provide effluent management and treatment services to the community.
Table 2.1: Assets covered by this Plan
Asset Class Dimension Units Count
Footpath 170,204 m 1442
Kerb and Gutter 240,609 m 2004
Road Earth 983,913 m 2175
Rural Pavement 198,272 m 416
Rural Sheeted Surface 568,170 m 597
Sealed Surface 393,851 m 1513
Township Pavement 180,732 m 1061
Township Sheeted Surface 6,369 m 41
Car Park 22,000 m2 14
Bike Path Surface 23,780 m 2
Bike Path Pavement 23,780 m 2
Roundabout 1 of 1
Key stakeholders in the preparation and implementation of this asset management plan are:
Shown in Table 2.1.1.
2 IPWEA, 2015, Sec 4.2.4, The Portfolio Asset Management Plan, pp 4|36 – 39.
- 7 -
THE BAROSSA COUNCIL – TRANSPORT INFRASTRUCTURE ASSET MANAGEMENT PLAN
Table 2.1.1: Key Stakeholders in the Asset Management Plan
Key Stakeholder Role in Asset Management Plan
Council Represent needs of community/shareholders,
Allocate resources to meet the organisation’s objectives in
providing services while managing risks,
Ensure organisation is financial sustainable.
CEO Ensuring effective AM practices, principles and processes are
considered at all levels within the organisation
Works and Engineering Services Ensuring effective AM practices, principles and processes are
considered at all levels within the organisation
Neighbouring Councils Ensuring integration and consideration of neighbouring plans
and practices to effectively collaborate on cost effective
service provision
Department of Planning Transport &
Infrastructure (DPTI)
Interface Agreement with the State road network
South Australian Power Networks (SAPN) Interface Agreement with power distribution network
SA Water Interface Agreement with the Water Supply Network
Dial Before You Dig Works coordination
Consultants/Contractors Design approvals, protection of assets (permit to work)
Developers Investing of new assets, (includes private and
public/government owned)
Community Service level expectation
Public transport providers Selection and changes to routes, Works coordination
Auditors Audits (financial and non-financial)
Emergency Services Works coordination
Environment Protection Authority Statutory environmental requirements
Department of Health Statutory health requirements
- 8 -
THE BAROSSA COUNCIL – TRANSPORT INFRASTRUCTURE ASSET MANAGEMENT PLAN
Our organisational structure for service delivery from infrastructure assets is detailed below
[As at June 2016]
- 9 -
THE BAROSSA COUNCIL – TRANSPORT INFRASTRUCTURE ASSET MANAGEMENT PLAN
[As at June 2016]
- 10 -
THE BAROSSA COUNCIL – TRANSPORT INFRASTRUCTURE ASSET MANAGEMENT PLAN
[As at June 2016]
- 11 -
THE BAROSSA COUNCIL – TRANSPORT INFRASTRUCTURE ASSET MANAGEMENT PLAN
2.2 Goals and Objectives of Asset Management
The organisation exists to provide services to its community. Some of these services are provided by
infrastructure assets. We have acquired infrastructure assets by ‘purchase’, by contract,
construction by our staff and by donation of assets constructed by developers and others to meet increased levels of service.
Our goal in managing infrastructure assets is to meet the defined level of service (as amended from
time to time) in the most cost effective manner for present and future consumers. The key elements of infrastructure asset management are:
Providing a defined level of service and monitoring performance,
Managing the impact of growth through demand management and infrastructure
investment,
Taking a lifecycle approach to developing cost-effective management strategies for the
long-term that meet the defined level of service,
Identifying, assessing and appropriately controlling risks, and
Having a long-term financial plan which identifies required, affordable expenditure and
how it will be financed.3
2.3 Plan Framework
Key elements of the plan are
Levels of service – specifies the services and levels of service to be provided by the
organisation,
Future demand – how this will impact on future service delivery and how this is to be met,
Life cycle management – how Council will manage its existing and future assets to provide
defined levels of service,
Financial summary – what funds are required to provide the defined services,
Asset management practices,
Monitoring – how the plan will be monitored to ensure it is meeting organisation’s objectives,
Asset management improvement plan.
The Asset Management Process is shown below.
3 Based on IPWEA, 2015, IIMM, Sec 1.3 p 1|8.
- 12 -
THE BAROSSA COUNCIL – TRANSPORT INFRASTRUCTURE ASSET MANAGEMENT PLAN
The Asset Management Process
Source: IPWEA, 2015, IIMM, Figure 1.3.4, p 1.10
- 13 -
THE BAROSSA COUNCIL – TRANSPORT INFRASTRUCTURE ASSET MANAGEMENT PLAN
2.4 Core and Advanced Asset Management
This asset management plan is prepared as a ‘core’ asset management plan over a 20 year
planning period in accordance with the International Infrastructure Management Manual4. It is
prepared to meet minimum legislative and organisational requirements for sustainable service
delivery and Long Term Financial Planning and reporting. Core asset management is a ‘top down’
approach where analysis is applied at the ‘system’ or ‘network’ level.
It is recommended, subject to resourcing capacity, that future revisions of this asset management
plan will move towards ‘advanced’ asset management using a ‘bottom up’ approach for
gathering asset information for individual assets to support the optimisation of activities and
programs to meet agreed service levels in a financially sustainable manner.
2.5 Community Consultation
This ‘core’ asset management plan is prepared to facilitate community consultation initially through
feedback on public display of draft asset management plans prior to adoption by the Council.
Future revisions of the asset management plan will incorporate community consultation on service
levels and costs of providing the service. This will assist the Council and the community in matching
the level of service needed by the community, service risks and consequences with the community’s ability and willingness to pay for the service.
4 IPWEA, 2015, IIMM.
- 14 -
THE BAROSSA COUNCIL – TRANSPORT INFRASTRUCTURE ASSET MANAGEMENT PLAN
3. LEVELS OF SERVICE
3.1 Customer Research and Expectations
The Barossa Council manages, drives and undertakes its own customer research with internal
resources utilising a combination of the following traditional and modern community engagement
strategies:
Social Media (Facebook)
Council website (www.barossa.sa.gov.au)
Council Customer Request Management System
Community Engagement Platform (www.ourbetterbarossa.com.au)
Newspaper advertising and editorial space
Newsletters (monthly and quarterly editions of d’Vine)
E-newsletter via Mailchimp
Direct communication and feedback to staff and elected members
The organisation uses this information to develop its plans and in allocation of resources in the budget.
At this time The Barossa Council does not undertake specific customer satisfaction surveys.
3.2 Strategic and Corporate Goals
This asset management plan is prepared under the direction of the organisation’s vision, mission, goals and objectives.
Our vision is:
Our Barossa
Enhancing our premium wine, food and tourism region and its unique lifestyle, heritage and community spirit
Our Themes are:
Natural Environment and Built Heritage
Business and Employment
Infrastructure
Community and Culture
Health and Wellbeing
Relevant organisational themes and how these are addressed in this asset management plan are:
- 15 -
THE BAROSSA COUNCIL – TRANSPORT INFRASTRUCTURE ASSET MANAGEMENT PLAN
Table 3.2: Organisational Goals and how these are addressed in this Plan
Theme How Goal and Objectives are addressed in Asset
Management Plan
Natural Environment and Built
Heritage
Minimisation of environmental impact through modern
construction techniques and compliance requirements
Business and Employment Consistent and compliant with Councils Procurement
Policy.
Infrastructure Renewal of existing assets and upgrade / new assets
created to account for increased demand and growth.
Community and Culture Ensuring access is maintained to all facilities and
culturally important areas of the city via a safe and
navigable network
Health and Wellbeing Provision safe and convenient transport system which
contributes to ensuring the safety of residents and visitors
as they commute through the region.
3.3 Legislative Requirements
The organisation has to meet many legislative requirements including Australian and State
legislation and State regulations. These include (but are not limited to):
Table 3.3: Legislative Requirements
Legislation , Guidelines and Standards
Local Government Act (1999)
Local Government (Financial Management & Rating) Amendment Act 2005
Road Traffic Act (1961)
Occupational Health, Safety and Welfare Act (1986)
Occupational Health, Safety and Welfare Regulations (2010)
Highways Act (1926)
Native Vegetation Act (1991)
Roads (Opening and Closing) Act (1991)
Environmental Protection Act (1993)
Australian Standards (AS)
Australian Road Rules (under Road Traffic Act (1961))
- 16 -
THE BAROSSA COUNCIL – TRANSPORT INFRASTRUCTURE ASSET MANAGEMENT PLAN
The organisation will exercise its duty of care to ensure public safety in accordance with the
Infrastructure Risk Management Plan linked to this Asset Management Plan. Management of risks is
discussed in Section 5.2.
3.4 Community Levels of Service
Service levels are defined service levels in two terms, community levels of service and technical
levels of service.
Community Levels of Service measure how the community receives the service and whether the
organisation is providing community value.
An integral part of the transport network is the inter-relationship with various physical and social
factors, assessment of risk and applying key performance indicators in a practical manner.
Community levels of service measures used in the asset management plan are:
Quality How good is the service?
Function Does it meet users’ needs?
Capacity/Utilisation Is the service over or under used?
The organisation’s current and expected community service levels for Transport Assets are detailed
in Tables 3.4 and 3.5.
Table 3.4: Community Level of Service
Service
Attribute
Service Objective Performance
Measure
Process
Current
Performance
Expected position in 10
years based on current
LTFP
COMMUNITY OUTCOMES
Provide a well maintained and safe transport network that enables users to travel from point A to
point B
COMMUNITY LEVELS OF SERVICE
Quality Provide all weather
access
Customer
complaints
Acceptable Continuing to meet the
service delivery needs
of the community.
Organisational measure
Confidence level
High High High
Function Ensure that the transport
network meets user
requirements for travel
time and availability
Customer
complaints
Acceptable Continuing to meet the
service delivery needs
of the community.
Travel across the
road network is
unrestricted
Acceptable Continuing to meet the
service delivery needs
of the community.
Organisational measure
Confidence levels
High High High
Capacity/
Utilisation
Provide appropriate
capacity for traffic
volumes and types
Customer
complaints
Acceptable Continuing to meet the
service delivery needs
of the community.
Organisational measure
Confidence levels
High High High
- 17 -
THE BAROSSA COUNCIL – TRANSPORT INFRASTRUCTURE ASSET MANAGEMENT PLAN
Service
Attribute
Service Objective Performance
Measure
Process
Current
Performance
Expected position in 10
years based on current
LTFP
Safety Provide safe suitable
roads, free from hazards Number of
incidents
Acceptable Continuing to meet the
service delivery needs
of the community.
Organisational measure
Confidence levels
High High High
As an improvement to the Level of Service used in this plan to measure performance of the assets,
it is proposed to expand the Level of Service to include road pavement condition assessment, the
assessment will define the overall condition of the network as “good/fair/poor”. This definition will
be based on the relevant combination of distress (extent and severity) and provided by condition
assessment.
In a strategic sense, this overall road pavement condition will assist in determining future funding
levels required so that the road network delivers the agreed levels of service and achieves its life
expectancy. This overall condition assessment will also assist in formulating appropriate ongoing
maintenance programs.
Council has developed a condition rating model with rating score based on field data collection
which is transferred into a Road Management System program which generates reports on the
road network condition and provides scenario based on various funding models to manage and
maintain the network. A weighting scored is determined for the road network in the following
categories;
Priority – This priority score is used in the modelling to sort roads for treatment in priority order. This is
particularly useful where budgets are limited and the model can assign funds to high priority
segments. The six fields provided for assessment are:
Function Priority – this differentiates roads by a generalised function from a track to a rural arterial.
This function ensures that high use roads are scored higher then low use roads.
Score Function
0 Road Reserve
1 Class 5: Track or laneway (no dwellings)
2 Class 5: Local Access (<5 dwellings)
3 Class 5: Local Access (up to 10 dwellings)
4 Class 4: Local Access (> 10 dwellings)
5 Class 4: Local Collector (Connecting activity nodes)
6 Class 4: Local Collector (Connecting arterial roads)
7 Class 4: Local Link (connecting centres)
8 Class 4: Local Link (connecting townships)
9 Class 3: Rural Arterial Road (mainly non local between towns > 300vpd)
10 Class 2: Designated Freight Route (B Double and HML Route)
- 18 -
THE BAROSSA COUNCIL – TRANSPORT INFRASTRUCTURE ASSET MANAGEMENT PLAN
Social Priority – this enables the social importance of the road to be scored. This ensures roads
that have significant community importance are given higher priority than roads leading to a
single dwelling.
Score Social Importance
0 No social importance (no dwelling)
2 Low social importance (less than 5 homes/road)
4 Medium social importance (5-10 dwellings/road)
6 High social importance (greater than 10 dwellings)
8 Very High social importance (bus route and/or link road between centres)
10 Critical social importance (link road between key towns)
Freight Priority – this enables the industry use to be assessed and its associated freight use in the
transport of goods.
Score Freight Use
0 No commercial vehicle use
1 Mainly residential occasional commercial vehicle
2 Mixture of residential and commercial
3 Light Industry (Seasonal)
4 Light Industry( All year round)
5 Medium Industry (Seasonal)
6 Medium Industry (all year round)
7 High Industry use (Seasonal)
8 High Industry use (All year round)
9 Extensive Industry (Seasonal)
10 Extensive Industry (All year round)
Tourist Priority – this enables the tourist use to be assessed which can be particularly important in
Councils that rely on the tourism industry.
Score Tourist Importance
0 No tourist importance
2 Low tourist importance
4 Some tourist importance
6 High tourist importance
8 Very High tourist importance
10 Critical tourist importance
- 19 -
THE BAROSSA COUNCIL – TRANSPORT INFRASTRUCTURE ASSET MANAGEMENT PLAN
Economic Development Priority – this enables the future potential of the road for development
and town growth to be flagged to assist in deciding on road surface treatment (e.g. upgrading
from unsealed to sealed).
Score Development Potential
0 No development potential
2 Low development potential
4 Medium development potential
6 Future town growth/residential/industrial development planned
Accident History Priority – where accident history is known then each segment can be assigned
a score based on accident history. This will enable special consideration for treatments.
Score Accident History
0 No accident history
2 Near miss reported
4 Minor
6 Minor repeated
8 Major non-fatal
10 Major fatal
3.5 Technical Levels of Service
Technical Levels of Service - Supporting the community service levels are operational or technical
measures of performance. These technical measures relate to the allocation of resources to service
activities that the organisation undertakes to best achieve the desired community outcomes and
demonstrate effective organisational performance.
Technical service measures are linked to annual budgets covering:
Operations – the regular activities to provide services such as inspections, etc.
Maintenance – the activities necessary to retain an asset as near as practicable to an
appropriate service condition (e.g. road patching, unsealed road grading),
Renewal – the activities that return the service capability of an asset up to that which it had
originally (e.g. frequency and cost of road resurfacing and pavement reconstruction),
Upgrade – the activities to provide a higher level of service (e.g. widening a road, sealing
an unsealed road) or a new service that did not exist previously (e.g. sealing an unsealed
road).
Service and asset managers plan, implement and control technical service levels to influence the
customer service levels.5
Growth in development and a more aware community has resulted in a demand for increased
services, and consequently, the expectations of the Barossa community are predicted to rise.
These expectations and the community's perception of Council's ability to provide services are
impacted significantly by issues related to resource allocation, funding and the possible creation of
5 IPWEA, 2015, IIMM, p 2.23
- 20 -
THE BAROSSA COUNCIL – TRANSPORT INFRASTRUCTURE ASSET MANAGEMENT PLAN
new assets measured against existing asset funding gap. While expenditure on road infrastructure
has been increased in past years, asset condition data and future community surveys may indicate
that financial resources are inadequate to maintain infrastructure to a level of service that the
community expects.
The issue of deterioration of the assets resulting from inadequate allocation of resources to
infrastructure maintenance must be considered against the level of revenue Council is able to raise
from rates, charges and grants. Limited revenue growth and rising costs to meet increasing
maintenance and service charges could result in an inability to bridge the funding gap between
revenue and costs. This could be reflected by a further deterioration of assets and infrastructure as
well as a reduction in other services and service levels.
Performance measures and targets for transport assets service criteria is required, and must
consider not only community expectations, strategic goals, and legislative requirements, but
technical standards and Council's ability to allocate sufficient resources to meet measures and
targets.
An integral part, in the establishment of the road classification model, is the inter-relationship with
various physical and social factors, assessment of risk and application of key performance
indicators in a practical manner.
Topography, extent of vegetation, soil conditions, traffic volumes and the type, practical width of
roads, must also be considered
In recognition of deteriorating road infrastructure, a road program has been developed which
identifies renewal of the road surface. Expenditure on the sealed road network was significantly
raised compared to earlier capital works budget immediately following amalgamation. In terms of
cost, best value has been achieved in the cost of road making materials through the assessment of
available quarry materials and its suitability to perform in various road condition environments.
Spray seals for resurfacing in urban areas has generally been discontinued because this type of
treatment in the past has raised community dissatisfaction. A minimum treatment of asphalt overlay
is used where spray seals may not be appropriate and the pavement condition is suitable for this
type of treatment. The use of asphalt increases cost compared to spray seals, however the seal life
is extended.
Sealed and Unsealed Roads:
Council’s sealed road surfacing program is an annual program that involves assessment and
treatments of both the road surface and road pavement. The primary focus is for the
renewal/replenishment of the surface, however small repairs to the road pavement need to occur
prior to the application of the new treatment.
In an ideal environment where funding is not constrained and the condition and the shape of the
roads are good, there are two primary objectives of a resurfacing program. The first is to replenish
or replace the surface of the road when the original service has aged or deteriorated. The second
objective is for the most cost effective, efficient and cost effective treatment to be selected
considering ongoing maintenance cost and the traffic type and volume that the road must
support.
The annual road surfacing program (reseal program) is currently developed by ranking the overall
condition of road segments (as identified by the sealed road surface inspection). This information is
then used following site visits to refine the list and make decisions which include the worst roads,
traffic type and volume, the most appropriate treatment and estimated costs.
The levels of service for road assets have been driven by legislative requirements, Australian
Standards, Regulations, Acts and Council policies that impact the way assets are managed. Levels
- 21 -
THE BAROSSA COUNCIL – TRANSPORT INFRASTRUCTURE ASSET MANAGEMENT PLAN
of service reflect standards currently in practice in the public realm which have been established
and will regularly be reviewed:
To inform customers of the level of service they could expect
As a focus for the development of Asset Management strategies to meet levels of service
As a measure of the effectiveness of Council’s Asset Management practices and the performance of its plans
To identify the costs and benefits of the services offered
To enable Council and customers to discuss and assess the suitability, affordability and
equality of the existing service level and to determine the impact of increasing or
decreasing this level in future
It is important to note that the annual road resealing and resheeting program is compiled from a
variety of inputs. These inputs are as follows:
10 year replacement program based on the asset expiry date (refer Appendix B)
The output from Councils Road Surface Manager modelling software that calculates
based on available budget and weighted defects of the road surface.
Community feedback.
Political drivers.
Council officer experience, knowledge and expertise.
- 22 -
THE BAROSSA COUNCIL – TRANSPORT INFRASTRUCTURE ASSET MANAGEMENT PLAN
Deterioration Modelling:
Modelling Curves for Barossa Sealed Roads
Function
Score Road Type Surface Asset type Seal Type
Useful
life -
Years
% of useful life
to reseal /
reseal life
Proposed seal type
for reseal
Number of
Segments
Total
length of
Segments
- metres
Pavement Asset type
Intervention
multiple of
surface
reseals
Pavement
life
10
Class 2:
Designated
Freight Route (B
Double & HML
Route)
Rural
Rural Heavy Use Hotmix Bitumen Surface Heavy use Hotmix 25 64% - (16 yrs) 40mm Hotmix 21 2,368 Rural Heavy Use Hotmix Pavement
Type 4 100
Rural Heavy Use Spray Seal Bitumen
Surface Heavy use Spray 22 68% - (15 yrs) 16/10 Spray Seal 45 35,956
Rural Heavy Use Spray Pavement
Type 4 88
Rural - B Double Route - Normal Use
Hotmix Normal use Hotmix 15 67% - (12 yrs) 40mm Hotmix 4 2,218
Rural B Double Normal Use Hotmix
Pavement Type 4 60
Rural - B Double Route - Normal Use Spray
Seal Normal use Spray 10 67% - (10 yrs) 16/10 Spray Seal 20 16,444
Rural B Double Normal Use Spray
Pavement Type 4 40
Township
Township Heavy Use Hotmix Bitumen
Surface Heavy use Hotmix 25 64% - (16 yrs) 40mm Hotmix 5 1,075
Township Heavy Use Hotmix
Pavement Type 4 100
Township Heavy Use Spray Seal Bitumen
Surface Heavy use Spray 22 68% - (15 yrs) 40mm Hotmix 7 1,627
Township Heavy Use Sprayseal
Pavement Type 4 88
Township Normal Use Hotmix Bitumen
Surface Normal Use Hotmix 30 68% - (15 yrs) 40mm Hotmix 1 120
Township Normal Use Hotmix
Pavement Type 5 150
9
Class 3: Rural
Arterial Road
(mainly non
local traffic
between
centres over
300 vpd)
Rural
Rural Heavy Use Hotmix Bitumen Surface Heavy use Hotmix 25 64% - (16 yrs) 40mm Hotmix 1 49 Rural Heavy Use Hotmix Pavement
Type 4 100
Rural Heavy Use Spray Seal Bitumen
Surface Heavy use Spray 22 68% - (15 yrs) 14/7 Spray Seal 4 2,192
Rural Heavy Use Spray Pavement
Type 4 88
Rural Normal Use Spray Seal Bitumen
Surface Normal use Spray 25 64% - (16 yrs) 14/7 Spray Seal 44 24,540
Rural Normal Use Spray Pavement
Type 5 125
Rural Normal Use Hotmix Bitumen Surface Normal use Hotmix 28 64% - (18 yrs) 30mm Hotmix 16 6,082 Rural Normal Use Hotmix
Pavement Type 5 140
Township
Township Heavy Use Hotmix Bitumen
Surface Heavy use Hotmix 25 64% - (16 yrs) 40mm Hotmix 20 3,217
Township Heavy Use Hotmix
Pavement Type 4 100
Township Heavy Use Spray Seal Bitumen
Surface Heavy use Spray 22 68% - (15 yrs) 40mm Hotmix 4 1,329
Township Heavy Use Sprayseal
Pavement Type 4 88
- 23 -
THE BAROSSA COUNCIL – TRANSPORT INFRASTRUCTURE ASSET MANAGEMENT PLAN
Function
Score Road Type Surface Asset type Seal Type
Useful
life -
Years
% of useful life
to reseal /
reseal life
Proposed seal type
for reseal
Number of
Segments
Total
length of
Segments
- metres
Pavement Asset type
Intervention
multiple of
surface
reseals
Pavement
life
Township Normal Use Spray Seal Bitumen
Surface Normal use Spray 25 64% - (18 yrs) 30mm Hotmix 20 4,988
Township Normal Use Sprayseal
Pavement Type 5 125
Township Normal Use Hotmix Bitumen
Surface Normal use Hotmix 30 64% - (16 yrs) 20/30mm Hotmix 9 1,525
Township Normal Use Hotmix
Pavement Type 5 150
7
Class 4: Local
link road
connecting
centres
Rural
Rural Heavy Use Spray Seal Bitumen
Surface Heavy use spray 22 68% - (15 yrs) 14/7 Spray Seal 1 1,177
Rural Heavy Use Spray Pavement
Type 4 88
Rural Normal Use Spray Seal Bitumen
Surface Normal use Spray 25 64% - (16 yrs) 14/7 Spray Seal 13 7,488
Rural Normal Use Spray Pavement
Type 5 125
Rural Normal Use Hotmix Bitumen Surface Normal use Hotmix 28 64% - (18 yrs) 30mm Hotmix 2 1,185 Rural Normal Use Hotmix
Pavement Type 5 140
Township
Township Normal Use Hotmix Bitumen
Surface Normal use Hotmix 30 64% - (18 yrs) 30mm Hotmix 1 53
Township Normal Use Hotmix
Pavement Type 5 150
Township Normal Use Spray Seal Bitumen
Surface Normal use Spray 25 64% - (16 yrs) 20/30mm Hotmix 4 1,713
Township Normal Use Sprayseal
Pavement Type 5 125
6
Class 4: Local
connector
connecting
arterial roads
Rural
Rural Normal Use Hotmix Bitumen Surface Normal use Hotmix 28 64% - (18 yrs) 30mm Hotmix 1 162 Rural Normal Use Hotmix
Pavement Type 5 140
Rural Normal Use Spray Seal Bitumen
Surface Normal use Spray 25 64% - (16 yrs) 14/7 Spray Seal 10 8,540
Rural Normal Use Spray Pavement
Type 5 125
Township
Township Normal Use Hotmix Bitumen
Surface Normal use Hotmix 30 64% - (18 yrs) 30mm Hotmix 13 3,034
Township Normal Use Hotmix
Pavement Type 5 150
Township Normal Use Spray Seal Bitumen
Surface Normal use Spray 25 64% - (16 yrs) 20/30mm Hotmix 4 929
Township Normal Use Sprayseal
Pavement Type 5 125
- 24 -
THE BAROSSA COUNCIL – TRANSPORT INFRASTRUCTURE ASSET MANAGEMENT PLAN
Function
Score Road Type Surface Asset type Seal Type
Useful
life -
Years
% of useful life
to reseal /
reseal life
Proposed seal type
for reseal
Number of
Segments
Total
length of
Segments
- metres
Pavement Asset type
Intervention
multiple of
surface
reseals
Pavement
life
5
Class 4: Local
connector
connecting
activity nodes
Rural
Rural Normal Use Hotmix Bitumen Surface Normal use Hotmix 28 64% - (18 yrs) 30mm Hotmix 4 910 Rural Normal Use Hotmix
Pavement Type 5 140
Rural Normal Use Spray Seal Bitumen
Surface Normal use Spray 25 64% - (16 yrs) 14/7 Spray Seal 74 40,816
Rural Normal Use Spray Pavement
Type 5 125
Rural Heavy Use Spray Seal Bitumen
Surface Heavy use Spray 22 68% - (15 yrs) 14/7 Spray Seal 1 250
Rural Heavy Use Spray Pavement
Type 4 88
Township
Township Normal Use Hotmix Bitumen
Surface Normal use Hotmix 30 64% - (18 yrs) 30mm Hotmix 8 1,383
Township Normal Use Hotmix
Pavement Type 5 150
Township Normal Use Spray Seal Bitumen
Surface Normal use Spray 25 64% - (16 yrs) 20/30mm Hotmix 10 2,487
Township Normal Use Sprayseal
Pavement Type 5 125
4
Class 4: Local
access street or
road (greater
than 10
dwellings)
Rural
Rural Normal Use Hotmix Bitumen Surface Normal use Hotmix 28 64% - (18 yrs) 30mm Hotmix 5 1,435 Rural Normal Use Hotmix
Pavement Type 5 140
Rural Normal Use Spray Seal Bitumen
Surface Normal use Spray 25 64% - (16 yrs) 14/7 Spray Seal 51 18,067
Rural Normal Use Spray Pavement
Type 5 125
Township
Township Normal Use Hotmix Bitumen
Surface Normal use Hotmix 30 64% - (18 yrs) 30mm Hotmix 466 54,860
Township Normal Use Hotmix
Pavement Type 5 150
Township Normal Use Spray Seal Bitumen
Surface Normal use Spray 25 64% - (16 yrs) 20/30mm Hotmix 366 61,527
Township Normal Use Sprayseal
Pavement Type 5 125
Township Normal Use Slurry Seal / Cold
Overlay Surface Normal use Slurry 20 67% - (10 yrs) 20/30mm Hotmix 48 5,960
Township Normal Use Slurry
Pavement Type 5 100
Township Paver Surface Paved 50 Paved 1 34
Township Normal Use Skinny Hotmix
Bitumen Surface (20mm)
Normal Skinny
Hotmix 25 64% - (16 yrs) 20mm Hotmix 24 4,164
Township Normal Use Skinny
Pavement Type 3 75
- 25 -
THE BAROSSA COUNCIL – TRANSPORT INFRASTRUCTURE ASSET MANAGEMENT PLAN
Function
Score Road Type Surface Asset type Seal Type
Useful
life -
Years
% of useful life
to reseal /
reseal life
Proposed seal type
for reseal
Number of
Segments
Total
length of
Segments
- metres
Pavement Asset type
Intervention
multiple of
surface
reseals
Pavement
life
3
Class 5: Local
access street or
road (multiple
dwellings up to
10)
Rural
Rural Heavy Use Spray Seal Bitumen
Surface Heavy use Spray 22 68% - (15 yrs) 14/7 Spray Seal 1 800
Rural Heavy Use Spray Pavement
Type 4 88
Rural Normal Use Hotmix Bitumen Surface Normal use Hotmix 28 64% - (18 yrs) 30mm Hotmix 1 373 Rural Normal Use Hotmix
Pavement Type 5 140
Rural Normal Use Spray Seal Bitumen
Surface Normal use Spray 25 64% - (16 yrs) 14/7 Spray Seal 19 5,969
Rural Normal Use Spray Pavement
Type 5 125
Township
Township Normal Use Spray Seal Bitumen
Surface Normal use Spray 25 64% - (16 yrs) 20/30mm Hotmix 16 2,570
Township Normal Use Sprayseal
Pavement Type 5 125
2
Class 5: Local
access street or
road (single
dwellings up to
5)
Rural
Rural Heavy Use Spray Seal Bitumen
Surface Heavy use Spray 22 14/7 Spray Seal 1 204
Rural Heavy Use Spray Pavement
Type 4 88
Rural Normal Use Spray Seal Bitumen
Surface Normal use Spray 25 64% - (16 yrs) 14/7 Spray Seal 69 15,999
Rural Normal Use Spray Pavement
Type 5 125
Township
Township Normal Use Hotmix Bitumen
Surface Normal use Hotmix 30 64% - (18 yrs) 30mm Hotmix 2 120
Township Normal Use Hotmix
Pavement Type 5 150
Township Normal Use Spray Seal Bitumen
Surface Normal use Spray 25 64% - (16 yrs) 20/30mm Hotmix 13 1,723
Township Normal Use Sprayseal
Pavement Type 5 125
- 26 -
THE BAROSSA COUNCIL – TRANSPORT INFRASTRUCTURE ASSET MANAGEMENT PLAN
Deterioration Modelling:
Deterioration Modelling Curves for Barossa Sheeted Roads
Function
Score Road Type
Modelling
Curve –
Material
Depth
Standard
life
% worn
when
resheeted
Unit Rate
per sq m
Number
of
Segment
s
Total
length of
Segments
- metres
7
Class 4: Rural Road A -
Local link road
connecting centres 150mm 12 Years 76% $ 6.53 14 11,468
6
Class 4: Rural Road B -
Local connector
connecting arterial
roads
100 mm 12 Years 72% $ 4.59 7 10,099
5
Class 4: Rural Road B –
Local connector
connecting activity
nodes
100mm 15 Years 65% $ 5.09 73 72,003
4
Class 4: Rural Road B -
Local access street or
road (greater than 10
dwellings)
100mm 15 Years 65% $ 5.09 69 59,152
Class 4: Township Road
Local access street or
road (greater than 10
dwellings)
100mm 15 Years 71% $ 4.66 29 4,443
- 27 -
THE BAROSSA COUNCIL – TRANSPORT INFRASTRUCTURE ASSET MANAGEMENT PLAN
Function
Score Road Type
Modelling
Curve –
Material
Depth
Standard
life
% worn
when
resheeted
Unit Rate
per sq m
Number
of
Segment
s
Total
length of
Segments
- metres
3
Class 5: Rural Road B -
Local access street or
road (multiple
dwellings up to 10)
75mm 20 Years 72% $ 3.44 83 80,956
Class 5: Township Road
Local access street or
road (multiple
dwellings up to 10)
75mm 17 Years 83% $ 2.99 9 1,268
2
Class 5: Rural Road B -
Local access street or
road (single dwellings
up to 5)
75mm 28 Years 72% $ 3.44 277 264,211
Class 5: Township Road
Local access street or
road (single dwellings
up to 5)
75mm 17 Years 83% $ 2.99 4 815
1
Class 5: Rural Road B -
Track or laneway (less
than 2 dwellings) 75mm 28 Years 72% $ 3.44 63 57,386
- 28 -
THE BAROSSA COUNCIL – TRANSPORT INFRASTRUCTURE ASSET MANAGEMENT PLAN
Grading Frequencies:
Grading Frequencies for Unsealed Roads
Function
Score Road Type
Modelling Curve
– Material Depth
Proposed
number of
grades per
year
Class 4: Rural Road A -
6 7
Local link road connecting centres 150mm
Class 4: Rural Road B -
5 6
Local connector connecting arterial roads 100 mm
Class 4: Rural Road B –
4 5
Local connector connecting activity nodes 100mm
Class 4: Rural Road B -
Local access street or road (greater than 10
dwellings) 100mm 3
4
Class 4: Township Road
Local access street or road (greater than 10
dwellings) 100mm 3
Class 5: Rural Road B -
Local access street or road (multiple dwellings up
to 10)
patch 75mm
resheet 75mm 2
3
Class 5: Township Road
Local access street or road (multiple dwellings up
to 10)
2
Class 5: Rural Road B -
2 Local access street or road (single dwellings up to
5)
patch 75mm
resheet 75mm 1
Class 5: Township Road Local access street or road
(single dwellings up to 5)
1
Class 5: Rural Road Track or laneway (less than 2
dwellings)
B - 0 – as
required
subject to
inspection
1
patch 75mm
- 29 -
THE BAROSSA COUNCIL – TRANSPORT INFRASTRUCTURE ASSET MANAGEMENT PLAN
Footpaths:
Generally the footpath network is more susceptible to damage resulting from work undertaken by
builders and contractors and from tree root problems rather than the failure of the materials.
Whereas the asset that requires refurbishment may be in good condition, it may be displaced or
lifted causing a safety hazard to occur.
Kerb and Channel:
Capital renewal and upgrade of kerb and channel is generally combined with road pavement
rehabilitation works.
Generally this results from two circumstances:
1. If the kerb and channel has deteriorated to the extent it requires renewal the adjacent road
pavement is often in a similar condition, requiring renewal;
2. Where the abutting road pavement is essentially structurally sound but the kerb and
channel is distressed, it is not practical or cost effective to renew large links of kerb and
channel without works on the road pavement. This is because of the difficulty in matching
grades and levels of the existing pavement.
Where smaller sections of kerb and channel are damaged from deterioration or tree roots cause
restricted stormwater flows, these sections will be removed and reinstated with new kerb and
channel.
This is generally carried out prior to reseal bituminous treatment being applied to the road surface
as part of seal rehabilitation.
Service levels can be defined in terms of:
Providing a safe and satisfactory access;
Maintaining the structural integrity of the footpath;
The type of surface;
Width of pathway;
Degree of accessibility, gradients and crossfall, effective stormwater runoff;
Condition of the path surface, smoothness, cracking, displacement etc.; and
Compliance to requirements of the elderly, frail or disabled community.
Table 3.5 shows the technical level of service expected to be provided under this Asset
Management Plan. The agreed sustainable position in the table documents the position agreed by
Council following the consultation process.
- 30 -
THE BAROSSA COUNCIL – TRANSPORT INFRASTRUCTURE ASSET MANAGEMENT PLAN
Table 3.5: Technical Levels of Service
Service
Attribute
Service Objective Activity Measure Process Current Performance *
Operations Transport network is safe
for users
Visual inspection Network inspected every
5 years
Transport network is clean
and safe for users
Regular street sweeping Based on sweeping
criteria
Maintenance Periodic visual assessment
to determine condition
Visual inspection Network inspected every
5 years
Maintain surface –
optimum maintenance
Grading frequency in
accordance with road
function table
Achieved
Maintain surface –
optimum maintenance
Resheeting frequency in
accordance with road
function table
Achieved
Condition of network is
sound to maintain function
without obstruction
Complaints Satisfaction within levels
of service
Condition of network is
sound to maintain function
without obstruction
Regular street sweeping Based on sweeping
criteria
Provide Transport network
that is low risk to workers
and the community
Number of injuries /
accidents
Nil per annum attributed
to asset condition
Renewal Apply appropriate useful
life
Useful life review Annual review of useful
life in accordance with
accounting standards
Road Assets 2015 / 2016 Budget $1.293 M
Footpath Assets and Kerb
and Gutter Assets
$300,000
Upgrade/New Increased level of service
as requested by EMs
EM satisfaction Satisfaction within levels
of service
Developer donated assets Cost / metre Review budget and
rates on an annual basis
Developer donated assets Number of assets
donated
Review budget and
rates on an annual basis
Ensure additional
maintenance /
operations costs are
included in future
budgets
Transport network
capacity matches usage
85% of transport assets
meet capacity
requirements
No capacity increases
planned
Sheeted Road Assets 2015 / 2016 Budget $1.383 M
Sealed Road Assets $1.852 M
Footpath Assets and Kerb
and Gutter Assets
$350,000
Note: * Current activities and costs (currently funded).
- 31 -
THE BAROSSA COUNCIL – TRANSPORT INFRASTRUCTURE ASSET MANAGEMENT PLAN
Transport Assets with Residual Values:
The Barossa Council like many other Councils have been using a residual value on a portion of the
sub components on a select number of transport asset types.
In view of clarification by AASB, discussions with Council's auditor and a high level assessment of
Council's asset register; we believe a second sub-component using a long life to identify the
previous residual value is one of the options going forward. Keeping in mind that the previous
practice of assigning residual values to portions of asset components meant no depreciation would
have been charged or recorded.
Various meetings have occurred with other City Councils (Adelaide City Council and
Campbelltown City Council) to consider other factors, experiences, road usage and local
conditions. As part of Councils application of a longer life, other road types / groups and classes
would need to be created in the asset register to isolate these asset components and apply their
expected useful lives. Factors to consider include (but are not limited to): soil types, construction
methodology, road use & type (e.g. township, transport, arterial, etc.), road materials and road
condition (sample) and traffic volumes.
A road is made of up of component layers, if these layers are broken up into sub-components a
lower layer component could not have a shorter life than an upper layer, it must align with the layer
immediately below it, normally at the a future renewal interval.
As the use of Residual Values in Australia is widespread across Local Government it is hoped that a
range of useful lives per asset type and intervention points is provided by engineers for application
to infrastructure assets (refer to SALGFMG & SALGAG draft paper May 2016: Infrastructure Assets,
Life without Residual Values).
The Barossa Council and Long Life 2 (or sub-component considerations):
The Barossa Council road network is mostly built on suitable soils, which provide a relatively stable
base for the road infrastructure assets.
Council's roads are made up from layers or components, as listed within Asset Accounting Policy
(Policy) and the asset register as components: earthworks, pavement and the surface. The Policy
has been reviewed for each asset type to incorporate the applicable long life period (in some
cases this could be a range) to each sub/second component.
Within the asset register the use of residual values had been assigned to various Infrastructure assets
to reflect parts of asset components that were either expected to last a very long time or part of
the long life 2 (LL2) layer/component is used as in-situ materials when the asset was renewed.
This includes selected transport asset types that require a review of the newly formed LL2 asset
components to ensure the lives (to the best of our understanding) represent the expected life for
these assets. This is to ensure adequate depreciation is being charged through the financials to
match the expected replacements as they occur.
There is correlation within each sub-component to its interval cycle(s) and in particular the asset
underneath must not have a shorter useful life than any above it within the road layers or structures.
The LL2 interval number should be a multiplier or divisible number of the other road layers, e.g. if the
surface sub-component LL1 has an interval of 15 then surface LL2 should be 3-5 times that amount
so 45, 60 or 75 and the layers below i.e. the pavement LL1 would then be 45, 60 or 75 and
pavement LL2 would then be an interval of that amount so 45x4 = 180 etc. (see Modelling Curves
for Barossa Sealed Roads above).
- 32 -
THE BAROSSA COUNCIL – TRANSPORT INFRASTRUCTURE ASSET MANAGEMENT PLAN
The difficulty being that as Council does not have the history on these replacement intervals. This
will be a judgment call that probably won’t be known in our lifetime so common sense is to be
applied and time will show if the number is too high or low.
Noting a suggestion from the AASB that a percentage of each component might be applicable
where there's is no defined physical change in the material or construction to apportion the split
from LL1 to LL2.
The residual value (RV) % portion applied to each LL2 will be taken in the first instance from existing
RVs' from the asset register and will only change as/if further information comes to hand to re-visit
this allocation. The LL2s' including surface (sealed roads) this will be allocated using advice from the
Councils engineering and asset road building knowledge and experience.
Considering these and other factors Council's road network in the main, should, if surface
replacement is undertaken as/when required these asset components should provide adequate
service levels for lower levels or components for a substantial time.
Earthwork
The earthwork (also referred to as the subgrade) is the original soil layer normally clay soils.
Council "Road earthworks” fall within the scope of Interpretation 1055 “Accounting for Road
Earthworks" and therefore is not depreciated.
Pavement
Pavement depth ranges from 100mm to 300mm in depth and is constructed by compacting rubble
to provide a solid base for the seal or surface layer.
If the surface layers are maintained and replacement intervals are kept in check (along with
drainage) the pavement should remain intact for a long time.
When the surface layer requires complete removal the normal practice is to remove a section of
the pavement, compacting and rebuilding this before a new surface layer is applied.
As only a section of the upper layer pavement is replaced a second or sub-component or lower
level will be created to help identify and isolate this longer life pavement.
This is referred to as component 2 or long life 2 (LL2).
Referring to AASB Alert no. 172 29 May 2015 “a percentage of the asset rather than the physical
materials compromising the asset”, might be considered that has an assigned renewal interval that
is relative to the other asset components reflecting the period in which replacement is expected to
occur.
Where road location(s) require a more frequent surface renewal interval, the upper level pavement
(or LL1) interval typically will also be a lower number or more frequent.
The short-life and long-life parts are not necessarily required to be physically identifiable i.e. they
could be based on difference between replacement cost and the cost of the renewal treatment.
Surface
The surface component has varying replacement intervals depending on its use, locality and local
conditions.
When the surface layer is to be renewed (the upper layer or component of the surface or LL1) there
is a section of the surface or a second component, this layer remaining this will also be referred to
as a sub-component or LL2.
- 33 -
THE BAROSSA COUNCIL – TRANSPORT INFRASTRUCTURE ASSET MANAGEMENT PLAN
The Surface LL2 has a similar use as the Pavement LL1 in that its purpose is to protect and extend
the life of the pavement, whereas the surface LL1 use is mostly as a wearing surface and needs to
be renewed more frequently (not illustrated).
Summary - outcome for 15-16
Councils preliminary on LL2s' and comparisons to depreciation predictions from Conquest have
shown that it is unlikely that application of LL2 into the asset register will have a material effect to
the depreciation amount.
The diagram below represents the breakdown of the Pavement component of the road into the
two components: Long Life 1 and Long Life 2.
Council’s asset register has not yet been updated to reflect these LL2 components at this stage.
Preliminary estimates from modelling have shown the depreciation movement from the application
of LL2 is likely to be insignificant / immaterial.
It is anticipated that further work will be undertaken throughout Australia to ascertain an
appropriate range of useful lives for each asset type taking into consideration local conditions,
material sources and construction methodologies.
Earth
Pavement LL2
Pavement LL1
Surface Footpath
Pro
pert
y B
ou
nd
ary
Pro
pert
y B
ou
nd
ary
Footpath
- 34 -
THE BAROSSA COUNCIL – TRANSPORT INFRASTRUCTURE ASSET MANAGEMENT PLAN
Example of application of LL2 to sealed & unsealed road:
Sealed Road - typical asset components
Useful Life
Component Complete
LL1 LL2
Surface
Year for the LL1 replacement of this asset component - surface (15
used in this example, others also include 10, 22, 25 and 28) 15
Every 4 reseal the remaining surface as well as part of the
pavement (LL1) is removed and re-constructed 60
Interval for LL2 replacement of this asset component (A 4 interval is
used in this example, IAMPS record 3, 4 and 5) 4
Pavement
Every 4 interval period of a completely new reseal construction the
remaining surface and a part of the pavement (LL1) is removed
and re-constructed
60
Interval for LL2 replacement of this asset component (A 4 interval
period used in this example, asset assessments may also include
3,4 or 5)
240
Interval for LL2 replacement of this asset component (A 4 interval is
used in this example, IAMPS record 3, 4 and 5) 4
Earthwork N/A
Unsealed Road - typical asset components
Useful Life
Component Component
LL1 LL2
Sheeted surface (rural sheeted surface function 3 used in this
example) 15
Every 14 interval period of a completely new re-sheet construction
for LL1 the part of the Sheeting component LL2 is removed and re-
constructed
210
Interval for LL2 replacement of this asset component (14 used in
this example) 14
Earthwork N/A
- 35 -
THE BAROSSA COUNCIL – TRANSPORT INFRASTRUCTURE ASSET MANAGEMENT PLAN
4. FUTURE DEMAND
4.1 Demand Drivers
Drivers affecting demand include population change, changes in demographics, seasonal factors,
vehicle ownership rates, consumer preferences and expectations, technological changes,
economic factors, agricultural practices, environmental awareness for example.
The impact of these trends are regularly examined and demand management strategies are
recommended as a technique to modify demand without compromising customer expectations.
The Population Projections by Local Government Area predicts the Estimated Resident Population
will increase. Nuriootpa is expected to accommodate the majority of growth in the next 5-10 years
as it contains the largest amount of available, ‘development ready’ or residential zoned land.
In forecasting on the future integration of land use and transport asset planning, the following are
reviewed:
Land use and travel demands
Regional transport demands
Changes to National Heavy Vehicle Regulations (weights and limits)
Proposed land divisions
Proposed property / housing developments
Urban Boundary Growth
Analysis of areas designated for future development
Local planning controls
4.2 Demand Forecast
The present position and projections for demand drivers that may impact future service delivery
and utilisation of assets are identified and documented in Table 4.3.
4.3 Demand Impact on Assets
The impact of demand drivers that may affect future service delivery and utilisation of assets are
shown in Table 4.3.
Table 4.3: Demand Drivers, Projections and Impact on Services
Demand drivers Present position Projection Impact on services
Population 23,490 (Community
Plan Information
2016)
29,584 by 2036 Demand for more sealed roads
and higher quality services from
Transport Assets.
Demographics Average growth rate
of 1.64% per year
between 1991-2011.
Future growth rate
will depend on
timing of rezoning
and servicing of
additional land
located in existing
It is anticipated a future growth
rate of around 1.64% per year
(within existing towns) will have
negligible impact on existing
services (within the 20 year
planning timeframe for this
- 36 -
THE BAROSSA COUNCIL – TRANSPORT INFRASTRUCTURE ASSET MANAGEMENT PLAN
Demand drivers Present position Projection Impact on services
townships or within
areas at Concordia
and Kalbeeba
identified in the 30-
year Plan as
“existing urban
land” or as a “long
term urban growth
area”.
IAMP) primarily because this
growth is based on infill aligned
with existing infrastructure. In
the long term should a new
town be provided, infrastructure
will be constructed by the
developer. The additional
revenue from this growth could
offset renewal and rehabilitation
costs for existing infrastructure
across the Council area.
If Concordia is developed, as a
complete “greenfield” site it will
require all appropriate services
and infrastructure.
Residential
Development
Limited by land
supply and township
boundaries.
Aged
accommodation.
Housing needed for
workers.
Expanded towns
and new town.
Augmentation of existing or new
infrastructure, services and
stormwater disposal.
Increased demands and
inability to provide affordable
housing.
Rural Living Range of lot sizes 0.5
hectare – 6 hectare.
Viability and
manageability of
large lots will result
in pressure to
reduce sizes.
Additional service and
infrastructure requirements in
rural localities.
Industrial
Development
Scattered rural
locations often
displacing
agricultural land e.g.
Wineries.
Regional location
needed to prevent
impacts and use of
significant
agricultural areas.
Road infrastructure, heavy
transport access, electricity and
water supply/drainage.
Agriculturally
productive
areas
Character
preservation
legislation in place
which restricts future
residential
development in rural
areas.
Continued
production
affected by
fragmented land
holding sizes and
water availability,
access issues,
strategies and
policies need to
acknowledge
larger holdings and
use of smaller
holdings.
Encroachment of conflicting
land uses resulting in interface
and buffer issues. Road and
infrastructure provision.
Each serviced town currently has land available for residential development, comprising vacant
lots, and land which is zoned for development but not yet the subject of a development proposal.
Within each town, sufficient capacity exists to accommodate the anticipated future demand (i.e.
proposed lots and zoned land yet to be developed).
- 37 -
THE BAROSSA COUNCIL – TRANSPORT INFRASTRUCTURE ASSET MANAGEMENT PLAN
Mount Pleasant is slightly different in that it has several large areas zoned “Deferred Urban” which
will need to be rezoned prior to any residential development. Future upgrades will be required to
accommodate development within those areas.
Council has undertaken modelling in respect to future population projections and future housing
demand. A lot yield analysis has been undertaken whereby it projected the ultimate number of lots
within zoned areas and applied 15 years of dwelling approvals (how long the supply might last in
each town). Naturally there are many unknowns – e.g. when supply in Tanunda is exhausted where
will that unmet demand ‘go’; would it ‘transfer’ to Nuriootpa or Angaston or another council?
In respect to Rural Living zoned land, there will be no further intensification of those. Council are
currently undertaking a study to determine if it can/should accommodate infill development in the
form of smaller lots.
Concordia is unique in that any development there will require completely new infrastructure which
would not impact on existing transport asset infrastructure. However, development at Concordia
could impact on Councils capacity to administer and maintain any new assets.
4.4 Demand Management Plan
Demand for new services will be managed through a combination of managing existing assets,
upgrading of existing assets and providing new assets to meet demand and demand
management. Demand management practices include non-asset solutions, insuring against risks and managing failures.
Non-asset solutions focus on providing the required service without the need for the organisation to
own the assets and management actions including reducing demand for the service, reducing the
level of service (allowing some assets to deteriorate beyond current service levels) or educating
customers to accept appropriate asset failures6. Examples of non-asset solutions include providing
services from existing infrastructure that may be in another community area or commercial premises.
Opportunities identified to date for demand management are shown in Table 4.4. Further opportunities will be developed in future revisions of this asset management plan.
Table 4.4: Demand Management Plan Summary
Demand Driver Impact on Services Demand Management Plan
Increased traffic
flows
Increased load on the
transport network
testing capacity
Continually assess network capacity and traffic
flows. Address network capacity issues with
improved capacity.
4.5 Asset Programs to meet Demand
The new assets required to meet growth will be acquired free of cost from land developments and
constructed/acquired by the organisation. New assets constructed/acquired by the organisation
are discussed in Section 5.5. The cumulative value of new contributed and constructed asset values are summarised in Figure 1.
It is important to note that some unsealed roads may be upgraded to become sealed surfaces. An assessment will be undertaken at an appropriate time to determine if this asset upgrade is required.
6 IPWEA, 2015, IIMM, Table 3.4.1, p 3|89.
- 38 -
THE BAROSSA COUNCIL – TRANSPORT INFRASTRUCTURE ASSET MANAGEMENT PLAN
Figure 1: Upgrade and New Assets to meet Demand
- 39 -
THE BAROSSA COUNCIL – TRANSPORT INFRASTRUCTURE ASSET MANAGEMENT PLAN
Acquiring these new assets will commit the organisation to fund ongoing operations, maintenance
and renewal costs for the period that the service provided from the assets is required. These future
costs are identified and considered in developing forecasts of future operations, maintenance and renewal costs in Section 5.
Barossa: Upgrade & New Assets to meet Demand Transport
Data
Category Year Contributed* Constructed*
Transport_S1_V3 2015 $200 $1,033
Transport_S1_V3 2016 $401 $2,422
Transport_S1_V3 2017 $601 $2,618
Transport_S1_V3 2018 $802 $2,822
Transport_S1_V3 2019 $1,003 $3,037
Transport_S1_V3 2020 $1,205 $3,258
Transport_S1_V3 2021 $1,406 $3,486
Transport_S1_V3 2022 $1,608 $3,722
Transport_S1_V3 2023 $1,810 $3,965
Transport_S1_V3 2024 $2,012 $4,217
Transport_S1_V3 2025 $2,214 $4,639
Transport_S1_V3 2026 $2,417 $5,061
Transport_S1_V3 2027 $2,619 $5,483
Transport_S1_V3 2028 $2,822 $5,904
Transport_S1_V3 2029 $3,025 $6,326
Transport_S1_V3 2030 $3,229 $6,748
Transport_S1_V3 2031 $3,432 $7,170
Transport_S1_V3 2032 $3,636 $7,591
Transport_S1_V3 2033 $3,840 $8,013
Transport_S1_V3 2034 $4,044 $8,435
*all dollar values in ($'000)'s
- 40 -
THE BAROSSA COUNCIL – TRANSPORT INFRASTRUCTURE ASSET MANAGEMENT PLAN
5. LIFECYCLE MANAGEMENT PLAN
Initial capital cost constitutes a significant up-front cost and often dominate the decision-making
process when acquiring new assets. However the ongoing recurrent expenditures (including
depreciation) usually represent a high portion of the total life-cycle costs of many assets. It is
important that they be included in the financial analysis undertaken to evaluate asset investment
options.
There may also be substantial costs associated with disposal at the end of an assets service life (e.g.
clean-up or demolition costs).
The way an asset is acquired or created may have a great impact on its future operation,
maintenance, or even disposal.
The Barossa Council, as custodians of the transport network, are charged with the responsibility to
ensure that the asset continues to function and meet the community needs and expectations as
well as maintaining asset in safe and usable condition within a reasonable duty of care.
In all cases, the asset functionality and asset maintenance targets need to be clearly defined with
the community (Users) and the asset service provider (Council) to determine the “ fit for purpose”
having regard to practicality and economics. That is, a level of service provided within a
reasonable duty of care in an affordable financial sustainable manner that considers community
expectations in regard to safety, and overall condition of the Transport network.
Asset functionality as a “level of service” to the community must take into consideration such
factors as, life cycle, capability and capacity, risk management and strategic compliance to the
needs and expectations of the overall community.
Asset maintenance “levels of service” provide for the day - to - day maintenance programs to
ensure that the asset operations are safe within practical constraints, maintain to perform targets
for day - to - day use and is managed and maintained to minimise environmental risk and
protection of residents.
The structure of maintenance and capital works is represented by the following diagram:
Transport
Categories
- 41 -
THE BAROSSA COUNCIL – TRANSPORT INFRASTRUCTURE ASSET MANAGEMENT PLAN
5.1 Background Data
5.1.1 Physical parameters
The assets covered by this asset management plan are shown in Table 2.1.
The age profile of the assets include in this Asset Management Plan is shown in Figure 2.
All Transport:
- All Transport Assets
- 42 -
THE BAROSSA COUNCIL – TRANSPORT INFRASTRUCTURE ASSET MANAGEMENT PLAN
Footpaths:
Figure 2: Asset Age Profile
- 43 -
THE BAROSSA COUNCIL – TRANSPORT INFRASTRUCTURE ASSET MANAGEMENT PLAN
- 44 -
THE BAROSSA COUNCIL – TRANSPORT INFRASTRUCTURE ASSET MANAGEMENT PLAN
Kerb and Gutter:
- 45 -
THE BAROSSA COUNCIL – TRANSPORT INFRASTRUCTURE ASSET MANAGEMENT PLAN
- 46 -
THE BAROSSA COUNCIL – TRANSPORT INFRASTRUCTURE ASSET MANAGEMENT PLAN
Rural Pavement:
- 47 -
THE BAROSSA COUNCIL – TRANSPORT INFRASTRUCTURE ASSET MANAGEMENT PLAN
- 48 -
THE BAROSSA COUNCIL – TRANSPORT INFRASTRUCTURE ASSET MANAGEMENT PLAN
- 49 -
THE BAROSSA COUNCIL – TRANSPORT INFRASTRUCTURE ASSET MANAGEMENT PLAN
Township Pavement:
- 50 -
THE BAROSSA COUNCIL – TRANSPORT INFRASTRUCTURE ASSET MANAGEMENT PLAN
- 51 -
THE BAROSSA COUNCIL – TRANSPORT INFRASTRUCTURE ASSET MANAGEMENT PLAN
- 52 -
THE BAROSSA COUNCIL – TRANSPORT INFRASTRUCTURE ASSET MANAGEMENT PLAN
Rural Sheeted Surface:
- 53 -
THE BAROSSA COUNCIL – TRANSPORT INFRASTRUCTURE ASSET MANAGEMENT PLAN
- 54 -
THE BAROSSA COUNCIL – TRANSPORT INFRASTRUCTURE ASSET MANAGEMENT PLAN
Rural Sealed Surface:
- 55 -
THE BAROSSA COUNCIL – TRANSPORT INFRASTRUCTURE ASSET MANAGEMENT PLAN
- 56 -
THE BAROSSA COUNCIL – TRANSPORT INFRASTRUCTURE ASSET MANAGEMENT PLAN
- 57 -
THE BAROSSA COUNCIL – TRANSPORT INFRASTRUCTURE ASSET MANAGEMENT PLAN
Township Sheeted Surface:
- 58 -
THE BAROSSA COUNCIL – TRANSPORT INFRASTRUCTURE ASSET MANAGEMENT PLAN
- 59 -
THE BAROSSA COUNCIL – TRANSPORT INFRASTRUCTURE ASSET MANAGEMENT PLAN
Township Sealed Surfaces:
- 60 -
THE BAROSSA COUNCIL – TRANSPORT INFRASTRUCTURE ASSET MANAGEMENT PLAN
- 61 -
THE BAROSSA COUNCIL – TRANSPORT INFRASTRUCTURE ASSET MANAGEMENT PLAN
- 62 -
THE BAROSSA COUNCIL – TRANSPORT INFRASTRUCTURE ASSET MANAGEMENT PLAN
Car Parks:
- 63 -
THE BAROSSA COUNCIL – TRANSPORT INFRASTRUCTURE ASSET MANAGEMENT PLAN
- 64 -
THE BAROSSA COUNCIL – TRANSPORT INFRASTRUCTURE ASSET MANAGEMENT PLAN
Bike Path Surface and Pavement:
- 65 -
THE BAROSSA COUNCIL – TRANSPORT INFRASTRUCTURE ASSET MANAGEMENT PLAN
5.1.2 Asset capacity and performance
Council’s services are generally provided to meet design standards where these are available.
Council's performance in the delivery of treated waste water services is monitored through key
performance indicators.
Level of Service (LoS) statements provide measurable performance indicators, describing the
means of delivering the desired outcomes. The key service areas are:
Capability of service
Service sustainability
Quality of service (responsiveness)
Cost effectiveness
Customer service/customer satisfaction
Locations where deficiencies in service performance are known are detailed in Table 5.1.2.
Table 5.1.2: Known Service Performance Deficiencies
Location Service Deficiency
Rural formed road network Sealing of unsealed road network will be determined based on
future demand for alternate traffic destinations
Stormwater function and capacity needs to be assessed to
ensure effective drainage to protect transport asset
Rural sealed road network Based on Councils capacity to identify backlog on rural road
resealing a review will be undertaken to ascertain any further
deficiencies and any rural roads requiring sealing.
Sealed road width needs to be increased to improve road safety
and reduce edge break defects and ongoing maintenance
costs
Road shoulder maintenance is insufficient and needs to be
programmed to improve road safety and reduce edge break
defects and ongoing maintenance costs
Due to freight demand (construction of NEXY and closure of
Penrice rail track), signs of accelerated deterioration of the
Heavy Freight Route is evident. This has been confirmed by
analysis on a 10 km section of Stockwell Road.
Footpath Network Access to network
Connectivity between old and new footpath networks
Kerb and Gutter Invert capacity and deformation of kerb channel
Rural formed road network Sealing of unsealed road network will be determined based on
future demand for alternate traffic destinations
Stormwater function and capacity needs to be assessed to
ensure effective drainage to protect transport asset
The above service deficiencies were identified by Council Engineering Officers.
- 66 -
THE BAROSSA COUNCIL – TRANSPORT INFRASTRUCTURE ASSET MANAGEMENT PLAN
5.1.3 Asset condition
Condition is monitored as below:
Service Objective Activity
Measure
Process
Current
Performance
Methodology
Periodic visual assessment to
determine condition of
Transport network
visual
inspection
Rolling condition
assessment
program based
on asset type
periodically (but
at least every 5
years to apply
with accounting
standard
requirements).
Resourcing levels determine if
inspection is undertaken by
specialist internal team
members utilising Conquest
Mobile or by specialist
maintenance and inspection
contractor or consulting firm.
The condition profile of our assets is shown in Figure 3.
Figure 3: Asset Condition Profile
- 67 -
THE BAROSSA COUNCIL – TRANSPORT INFRASTRUCTURE ASSET MANAGEMENT PLAN
Condition is measured using a 1 – 5 grading system7 as detailed in Table 5.1.3.
Table 5.1.3: Simple Condition Grading Model
Condition
Grading
Description of Condition
1 Very Good: only planned maintenance required
2 Good: minor maintenance required plus planned maintenance
3 Fair: significant maintenance required
4 Poor: significant renewal/rehabilitation required
5 Very Poor: physically unsound and/or beyond rehabilitation
Council will be undertaking a sealed road condition audit in the 16/17 Financial Year.
Other than a 10 km section of the heavy freight route along Stockwell Road, Council has not
undertaken a detailed condition assessment of its pavement assets.
5.1.4 Asset valuations
The value of assets recorded in the asset register as at 30 June 2015 covered by this asset management plan is shown below. Assets are valued at fair value.
Current Replacement Cost $200.3 M
Depreciable Amount $200.3 M
Depreciated Replacement Cost8 $143.4 M
Annual Depreciation Expense $3 M
The Transport Network was valued as at 1 July 2014 using unit rates provided by Tonkin Consulting.
Major changes from previous valuations are due to increases in unit rates, improvements in the accuracy of assumptions and improved accuracy of the data.
Various ratios of asset consumption and expenditure have been prepared to help guide and gauge asset management performance and trends over time.
Rate of Annual Asset Consumption 1.50%
Rate of Annual Asset Renewal 1.90%
Rate of Annual Asset Upgrade 0.50%
Rate of Asset Upgrade (Including Contributed Assets) 0.60%
Asset renewals as percentage of consumption 121.30%
Percentage Increase in asset stock 0.60%
5.1.5 Historical Data
Historical data on the physical location, dimensions and civil works are located in the Works and
Engineering Department and Council’s Electronic Document Records Management System
(EDRMS).
7 IPWEA, 2015, IIMM, Sec 2.5.4, p 2|80. 8 Also reported as Written Down Current Replacement Cost (WDCRC).
- 68 -
THE BAROSSA COUNCIL – TRANSPORT INFRASTRUCTURE ASSET MANAGEMENT PLAN
Historical Financial data can be found here:
https://www.barossa.sa.gov.au/sections/council/financial-documents/annual-financial-statements
Council’s Corporate Mapping System holds the spatial representation of the dataset.
5.2 Infrastructure Risk Management Plan
An assessment of risks associated with service delivery from infrastructure assets has identified
critical risks that will result in loss or reduction in service from infrastructure assets or a ‘financial
shock’ to the organisation. The risk assessment process identifies credible risks, the likelihood of the
risk event occurring, the consequences should the event occur, develops a risk rating, evaluates
the risk and develops a risk treatment plan for non-acceptable risks.
Critical risks, being those assessed as ‘Very High’ - requiring immediate corrective action and ‘High’
– requiring prioritised corrective action identified in the Infrastructure Risk Management Plan,
together with the estimated residual risk after the selected treatment plan is operational are summarised in Table 5.2. These risks are reported to management and Council.
Table 5.2: Critical Risks and Treatment Plans
Service or Asset at
Risk
What can Happen Risk Rating
(VH, H)
Risk Treatment Plan Residual
Risk *
Roads Closure / Damage
due to storm event
High Increased planned inspection and
cleaning frequency of stormwater
network and ongoing capacity
review
Moderate
Note * The residual risk is the risk remaining after the selected risk treatment plan is operational.
Some challenges facing the organisation are:
- 69 -
THE BAROSSA COUNCIL – TRANSPORT INFRASTRUCTURE ASSET MANAGEMENT PLAN
5.3 Routine Operations and Maintenance Plan
Operations include regular activities to provide services such as public health, safety and amenity,
e.g. street sweeping and street lighting.
Routine maintenance is the regular on-going work that is necessary to keep assets operating,
including instances where portions of the asset fail and need immediate repair to make the asset
operational again.
5.3.1 Operations and Maintenance Plan
Operations activities affect service levels including quality and function through street sweeping
frequency, intensity and spacing of street lights.
Maintenance includes all actions necessary for retaining an asset as near as practicable to an
appropriate service condition including regular ongoing day-to-day work necessary to keep assets
operating, e.g. road patching but excluding rehabilitation or renewal. Maintenance may be
classified into reactive, planned and specific maintenance work activities.
Reactive maintenance is unplanned repair work carried out in response to service requests and
management/supervisory directions.
Planned maintenance is repair work that is identified and managed through a maintenance
management system (MMS). MMS activities include inspection, assessing the condition against
failure/breakdown experience, prioritising, scheduling, actioning the work and reporting what was
done to develop a maintenance history and improve maintenance and service delivery
performance.
Specific maintenance is replacement of higher value components/sub-components of assets that
is undertaken on a regular cycle including repainting, replacing air conditioning units, etc. This work
falls below the capital/maintenance threshold but may require a specific budget allocation.
Actual past maintenance expenditure is shown in Table 5.3.1.
Table 5.3.1: Maintenance Expenditure Trends
Maintenance Expenditure
Year Operations
(M)
Planned
Maintenance
Reactive
Maintenance
Total
(M)
2012/2013 $1.430 $646 $291 $2.077 Actual
2013/2014 $1.655 $344 $285 $2.284 Actual
2014/2015 $1.718 $377 $294 $2.389 Actual
2015/2016 $1.620 $658 $604 $2.882 Budgeted
2016/2017 $1.613 $690 $636 $2.939 Budgeted
Operations work is currently 56% of total maintenance expenditure (15/16 Financial Year budgeted
expenditure).
Reactive Maintenance work is currently 21% of total maintenance expenditure (15/16 Financial
Year budgeted expenditure).
Planned Maintenance work is currently 23% of total maintenance expenditure (15/16 Financial Year
budgeted expenditure).
- 70 -
THE BAROSSA COUNCIL – TRANSPORT INFRASTRUCTURE ASSET MANAGEMENT PLAN
Maintenance expenditure levels are considered to be adequate to meet projected service levels,
which may be less than or equal to current service levels. Where maintenance expenditure levels
are such that will result in a lesser level of service, the service consequences and service risks have
been identified and service consequences highlighted in this Asset Management Plan and service
risks considered in the Infrastructure Risk Management Plan.
Assessment and prioritisation of reactive maintenance is undertaken by Council staff using
experience and judgement and is based on the inputs into the Customer Request Management
(CRM) System.
5.3.2 Operations and Maintenance Strategies
The organisation will operate and maintain assets to provide the defined level of service to
approved budgets in the most cost-efficient manner. The operation and maintenance activities
include:
Scheduling operations activities to deliver the defined level of service in the most efficient
manner,
Maintaining a current infrastructure risk register for assets and present service risks associated
with providing services from infrastructure assets and reporting Very High and High risks and
residual risks after treatment to management and Council,
Reviewing current and required skills base and implementing workforce training and
development to meet required operations and maintenance needs,
Reviewing asset utilisation to identify underutilised assets and appropriate remedies, and
over utilised assets and customer demand management options,
Maintaining a current hierarchy of critical assets and required operations and maintenance
activities,
Developing and regularly review appropriate emergency response capability,
Reviewing management of operations and maintenance activities to ensure Council is
obtaining best value for resources used.
Asset hierarchy
An asset hierarchy provides a framework for structuring data in an information system to assist in
collection of data, reporting information and making decisions. The hierarchy includes the asset
class and component used for asset planning and financial reporting and service level hierarchy
used for service planning and delivery.
- 71 -
THE BAROSSA COUNCIL – TRANSPORT INFRASTRUCTURE ASSET MANAGEMENT PLAN
The asset hierarchy in the Corporate Asset Management System is represented below:
- 72 -
THE BAROSSA COUNCIL – TRANSPORT INFRASTRUCTURE ASSET MANAGEMENT PLAN
Example of Rural Roads hierarchy:
Example of Township Road hierarchy:
- 73 -
THE BAROSSA COUNCIL – TRANSPORT INFRASTRUCTURE ASSET MANAGEMENT PLAN
The organisation’s service hierarchy is shown is Table 5.3.2.
Table 5.3.2: Asset Service Hierarchy
Service Hierarchy Service Level Objective
Township Transport network Provide a safe, smooth, well maintained and all weather township transport
network that enables users to travel from point A to point B at a reasonable
speed.
Ensure good drainage that protects and maximises the life of all
components of the asset.
Rural Transport network Provide a safe, smooth, well maintained and all weather rural transport
network that enables users to travel from point A to point B at a reasonable
speed.
Ensure good drainage that protects and maximises the life of all
components of the asset.
Footpath network Provide a safe, well interconnected, well maintained and suitably surfaced
footpath network that enables users to travel from point A to point B.
Kerb and Gutter Provide a structurally sound and aesthetically pleasing kerb and water
table network that enables the free and unrestricted flow of surface run off
into appropriate stormwater systems
Car Parks Provide off-street parking on a well maintained and homogenous surface
at an appropriate capacity for its function and usage.
Ensure good drainage that protects and maximises the life of all
components of the asset.
Critical Assets
Critical assets are those assets which have a high consequence of failure but not necessarily a high
likelihood of failure. By identifying critical assets and critical failure modes, organisations can target
and refine investigative activities, maintenance plans and capital expenditure plans at the
appropriate time.
Operations and maintenances activities may be targeted to mitigate critical asset failure and
maintain service levels. These activities may include increased inspection frequency, higher
maintenance intervention levels, etc. Critical asset failure modes and required operations and
maintenance activities are detailed in Table 5.3.2.1.
Table 5.3.2.1: Critical Assets and Service Level Objectives
Critical Assets Critical Failure Mode Operations & Maintenance Activities
Township Transport
network
Loss of sealed surface and
increase in surface
roughness
Resurfacing of sealed surface, continuous network
monitoring for operational performance including
corrective maintenance as required and within
budget allocations
Rural Transport
network
Loss of sheeted surface and
all weather access
Resheeting of rural road surface, continuous
monitoring including corrective maintenance as
required and within budget allocations
Footpath network Loss of ability to traverse /
access
Resurfacing of footpath surfaces, continuous network
monitoring for operational performance including
corrective maintenance as required and within
budget allocations
- 74 -
THE BAROSSA COUNCIL – TRANSPORT INFRASTRUCTURE ASSET MANAGEMENT PLAN
Critical Assets Critical Failure Mode Operations & Maintenance Activities
Kerb and Gutter Channel blockage and
flooding
Street sweeping program and condition monitoring
for operational performance including corrective
maintenance as required and within budget
allocations
Car Parks Loss of sealed surface and
increase in surface
roughness
Continuous monitoring including corrective
maintenance as required and within budget
allocations
Standards and specifications
Maintenance work is carried out in accordance with the following Standards and Specifications.
Refer 3.3 – Legislative Requirements
5.3.3 Summary of future operations and maintenance expenditures
Future operations and maintenance expenditure is forecast to trend in line with the value of the
asset stock as shown in Figure 4. Note that all costs are shown in current 2015 dollar values (i.e. real
values).
Figure 4: Projected Operations and Maintenance Expenditure
- 75 -
THE BAROSSA COUNCIL – TRANSPORT INFRASTRUCTURE ASSET MANAGEMENT PLAN
Barossa: Projected Operations & Maintenance Expenditure Transport Data
Category Year Maintenance* Operations* Budget*
Transport_S1_V3 2015 $1,262 $1,880 $3,142
Transport_S1_V3 2016 $1,332 $1,892 $3,204
Transport_S1_V3 2017 $1,343 $1,907 $3,204
Transport_S1_V3 2018 $1,345 $1,910 $3,204
Transport_S1_V3 2019 $1,348 $1,914 $3,204
Transport_S1_V3 2020 $1,351 $1,918 $3,204
Transport_S1_V3 2021 $1,353 $1,922 $3,204
Transport_S1_V3 2022 $1,356 $1,926 $3,204
Transport_S1_V3 2023 $1,359 $1,930 $3,204
Transport_S1_V3 2024 $1,362 $1,934 $3,204
Transport_S1_V3 2025 $1,359 $1,938 $3,198
Transport_S1_V3 2026 $1,363 $1,944 $3,198
Transport_S1_V3 2027 $1,367 $1,950 $3,198
Transport_S1_V3 2028 $1,371 $1,956 $3,198
Transport_S1_V3 2029 $1,375 $1,962 $3,198
Transport_S1_V3 2030 $1,379 $1,968 $3,198
Transport_S1_V3 2031 $1,383 $1,974 $3,198
Transport_S1_V3 2032 $1,388 $1,980 $3,198
Transport_S1_V3 2033 $1,392 $1,985 $3,198
Transport_S1_V3 2034 $1,396 $1,991 $3,198
*all dollar values in ($'000)'s
Deferred maintenance, i.e. works that are identified for maintenance and unable to be funded are to be included in the risk assessment and analysis in the Infrastructure Risk Management Plan.
Maintenance is funded from the operating budget where available. This is further discussed in
Section 6.2.
- 76 -
THE BAROSSA COUNCIL – TRANSPORT INFRASTRUCTURE ASSET MANAGEMENT PLAN
5.4 Renewal/Replacement Plan
Renewal and replacement expenditure is major work which does not increase the asset’s design
capacity but restores, rehabilitates, replaces or renews an existing asset to its original or lesser
required service potential. Work over and above restoring an asset to original service potential is
upgrade/expansion or new works expenditure.
5.4.1 Renewal plan
Assets requiring renewal/replacement are identified from one of three methods provided in the ‘Expenditure Template’.
Method 1 uses Asset Register data to project the renewal costs using acquisition year and
useful life to determine the renewal year, or
Method 2 uses capital renewal expenditure projections from external condition modelling
systems, or
Method 3 uses a combination of average network renewals plus defect repairs in the Renewal Plan and Defect Repair Plan worksheets on the ‘Expenditure template’.
Method 1 was used for this asset management plan.
The useful lives of assets used to develop projected asset renewal expenditures are shown in Table 5.4.1. Asset useful lives were last reviewed by Tonkin Consulting as at 1 July 2014.
Table 5.4.1: Useful Lives of Assets
Type Sub-Classification/ Component
Useful Life
Range
(years)
Sealed Roads
Sealed Roads - Earth N/A
Sealed Roads – Pavement (includes shoulders) - 2 components 40– 150
180 - 600
Sealed Roads – Surface - 2 components 10 – 30
40 - 150
Sheeted Roads Sheeted Roads – Earth 12 - 28
Sheeted Roads – Pavement or Surface - 2 components 168 - 392
Unformed Roads Unformed Roads - Earth N/A
Footpaths / Kerbs /
Car park Structures
Carpark Surfaces - 2 components 30 – 50
60 - 100
Footpaths 30 - 100
Kerb 70 - 100
5.4.2 Renewal and Replacement Strategies
The organisation will plan capital renewal and replacement projects to meet level of service objectives and minimise infrastructure service risks by:
Planning and scheduling renewal projects to deliver the defined level of service in the most
efficient manner,
- 77 -
THE BAROSSA COUNCIL – TRANSPORT INFRASTRUCTURE ASSET MANAGEMENT PLAN
Undertaking project scoping for all capital renewal and replacement projects to identify:
o the service delivery ‘deficiency’, present risk and optimum time for
renewal/replacement,
o the project objectives to rectify the deficiency,
o the range of options, estimated capital and life cycle costs for each option that
could address the service deficiency,
o and evaluate the options against evaluation criteria adopted by the organisation,
and
o select the best option to be included in capital renewal programs,
Using ‘low cost’ renewal methods (cost of renewal is less than replacement) wherever
possible,
Maintaining a current infrastructure risk register for assets and service risks associated with
providing services from infrastructure assets and reporting Very High and High risks and
residual risks after treatment to management and Council,
Reviewing current and required skills base and implementing workforce training and
development to meet required construction and renewal needs,
Maintaining a current hierarchy of critical assets and capital renewal treatments and
timings required ,
Reviewing management of capital renewal and replacement activities to ensure Council is
obtaining best value for resources used.
Renewal ranking criteria
Asset renewal and replacement is typically undertaken to either:
Ensure the reliability of the existing infrastructure to deliver the service it was constructed to
facilitate, or
To ensure the infrastructure is of sufficient quality to meet the service requirements (e.g. to meet capacity requirements).9
It is possible to get some indication of capital renewal and replacement priorities by identifying assets or asset groups that:
Have a high consequence of failure,
Have a high utilisation and subsequent impact on users would be greatest,
The total value represents the greatest net value to the organisation,
Have the highest average age relative to their expected lives,
Are identified in the Asset Management Plan as key cost factors,
Have high operational or maintenance costs, and Where replacement with modern equivalent assets would yield material savings.10
The ranking criteria used to determine priority of identified renewal and replacement proposals is detailed in Table 5.4.2.
9 IPWEA, 2015, IIMM, Sec 3.4.4, p 3|91. 10 Based on IPWEA, 2015, IIMM, Sec 3.4.5, p 3|97.
- 78 -
THE BAROSSA COUNCIL – TRANSPORT INFRASTRUCTURE ASSET MANAGEMENT PLAN
Table 5.4.2: Renewal and Replacement Priority Ranking Criteria
Criteria Weighting
Programmed renewal / replacement program generated from Road Surface
Modeller (RSM) software
30%
Road segments identified from routine inspection 30%
Social demand for renewal / replacement 20%
Political demand for renewal / replacement 20%
Total 100%
Renewal and replacement standards
Renewal work is carried out in accordance with the following Standards and Specifications.
Refer 3.3 – Legislative Requirements
5.4.3 Summary of future renewal and replacement expenditure
Projected future renewal and replacement expenditures are forecast to increase over time as the
asset stock increases from growth. The expenditure is summarised in Figure 5. Note that all amounts
are shown in real values.
The projected capital renewal and replacement program is shown in Appendix B.
Figure 5: Projected Capital Renewal and Replacement Expenditure
- 79 -
THE BAROSSA COUNCIL – TRANSPORT INFRASTRUCTURE ASSET MANAGEMENT PLAN
Barossa - Projected Capital Renewal Expenditure Transport Data
Category Year Renewal Cost
Transport_S1_V2 2010 $0
Transport_S1_V2 2011 $1,538
Transport_S1_V2 2012 $1,184
Transport_S1_V2 2013 $0
Transport_S1_V2 2014 $697
Transport_S1_V2 2015 $2,110
Transport_S1_V2 2016 $1,090
Transport_S1_V2 2017 $8
Transport_S1_V2 2018 $982
Transport_S1_V2 2019 $352
Transport_S1_V2 2020 $382
Transport_S1_V2 2021 $163
Transport_S1_V2 2022 $561
Transport_S1_V2 2023 $483
Transport_S1_V2 2024 $183
Transport_S1_V2 2025 $1,106
Transport_S1_V2 2026 $1,627
Transport_S1_V2 2027 $3,401
Transport_S1_V2 2028 $2,664
Transport_S1_V2 2029 $2,757
Transport_S1_V2 2030 $2,824
Transport_S1_V2 2031 $2,146
Transport_S1_V2 2032 $2,340
Transport_S1_V2 2033 $2,728
Transport_S1_V2 2034 $2,161
*all dollar values in ($'000)'s
- 80 -
THE BAROSSA COUNCIL – TRANSPORT INFRASTRUCTURE ASSET MANAGEMENT PLAN
- 81 -
THE BAROSSA COUNCIL – TRANSPORT INFRASTRUCTURE ASSET MANAGEMENT PLAN
Barossa - Projected Capital Renewal Expenditure (Transport_S1_V5) Data
Category Year Renewal Cost
Transport_S1_V5 2015 $2,110
Transport_S1_V5 2016 $1,090
Transport_S1_V5 2017 $8
Transport_S1_V5 2018 $982
Transport_S1_V5 2019 $352
Transport_S1_V5 2020 $382
Transport_S1_V5 2021 $163
Transport_S1_V5 2022 $561
Transport_S1_V5 2023 $483
Transport_S1_V5 2024 $183
Transport_S1_V5 2025 $1,106
Transport_S1_V5 2026 $1,623
Transport_S1_V5 2027 $3,401
Transport_S1_V5 2028 $2,664
Transport_S1_V5 2029 $2,757
Transport_S1_V5 2030 $2,824
Transport_S1_V5 2031 $2,146
Transport_S1_V5 2032 $2,340
Transport_S1_V5 2033 $2,728
Transport_S1_V5 2034 $2,161
*all dollar values in ($'000)'s*
Unfunded Renewals Year Renewal Cost
Transport_S1_V5 2010 $0
Transport_S1_V5 2011 $1,538
Transport_S1_V5 2012 $1,184
Transport_S1_V5 2013 $0
Transport_S1_V5 2014 $697
Total $3,419
*all Dollar Values in ($'000)'s*
- 82 -
THE BAROSSA COUNCIL – TRANSPORT INFRASTRUCTURE ASSET MANAGEMENT PLAN
Deferred renewal and replacement, i.e. those assets identified for renewal and/or replacement
and not scheduled in capital works programs are to be included in the risk analysis process in the
Risk Management Plan.
Renewals and replacement expenditure in the organisation’s capital works program will be
accommodated in the Long Term Financial Plan. This is further discussed in Section 6.2.
Unfunded renewals are the “backlog” of works. This can be somewhat addressed by ongoing
condition assessment to determine asset renewal and replacement.
5.5 Creation/Acquisition/Upgrade Plan
New works are those works that create a new asset that did not previously exist, or works which
upgrade or improve an existing asset beyond its existing capacity. They may result from growth,
social or environmental needs. Assets may also be acquired at no cost to the organisation from
land development. These assets from growth are considered in Section 4.4.
5.5.1 Selection criteria
New assets and upgrade/expansion of existing assets are identified from various sources such as
elected member or community requests, proposals identified by strategic plans or partnerships
with other organisations. Candidate proposals are inspected to verify need and to develop a
preliminary renewal estimate. Verified proposals are ranked by priority in accordance with the
Bid Analysis Tool (BAT) and available funds (as determined in the annual budget process and in
accordance with the adopted Long Term Financial Plan) and scheduled in future works
programs. The priority ranking criteria is detailed below.
Table 5.5.1: New Assets Priority Ranking Criteria
Criteria Weighting
Social demand for sealing roads in close proximity to rural and township links 25%
Requirement to upgrade heavy freight route to facilitate the bypass of major
townships
75%
Total 100%
5.5.2 Capital Investment Strategies
The organisation will plan capital upgrade and new projects to meet level of service objectives by:
Planning and scheduling capital upgrade and new projects to deliver the defined level of
service in the most efficient manner,
Undertake project scoping for all capital upgrade/new projects to identify:
o the service delivery ‘deficiency’, present risk and required timeline for delivery of the
upgrade/new asset,
o the project objectives to rectify the deficiency including value management for
major projects,
o the range of options, estimated capital and life cycle costs for each options that
could address the service deficiency,
o management of risks associated with alternative options,
o and evaluate the options against evaluation criteria adopted by Council, and
o select the best option to be included in capital upgrade/new programs,
Review current and required skills base and implement training and development to meet
required construction and project management needs,
Review management of capital project management activities to ensure Council is
obtaining best value for resources used.
- 83 -
THE BAROSSA COUNCIL – TRANSPORT INFRASTRUCTURE ASSET MANAGEMENT PLAN
Standards and specifications for new assets and for upgrade/expansion of existing assets are the
same as those for renewal shown in Section 5.4.2.
5.5.3 Summary of future upgrade/new assets expenditure
Projected upgrade/new asset expenditures are summarised in Figure 6. The projected
upgrade/new capital works program is shown in Appendix C. All amounts are shown in real values.
Figure 6: Projected Capital Upgrade/New Asset Expenditure
Expenditure on new assets and services in the organisation’s capital works program will be accommodated in the Long Term Financial Plan. This is further discussed in Section 6.2.
5.6 Disposal Plan
Disposal includes any activity associated with disposal of a decommissioned asset including sale,
demolition or relocation.
Council is not planning to dispose of any Transport network assets.
5.7 Service Consequences and Risks
The organisation has prioritised decisions made in adopting this Asset Management Plan to obtain
the optimum benefits from its available resources. Decisions were made based on the development of three scenarios of Asset Management Plans.
Scenario 1 - What we would like to do based on asset register data
- 84 -
THE BAROSSA COUNCIL – TRANSPORT INFRASTRUCTURE ASSET MANAGEMENT PLAN
Scenario 2 – What we should do with existing budgets and identifying level of service and risk
consequences (i.e. what are the operations and maintenance and capital projects we are unable
to do, what is the service and risk consequences associated with this position). This may require several versions of the Asset Management Plan.
Scenario 3 – What we can do and be financially sustainable with Asset Management Plans matching long-term financial plans.
The development of scenario 1 and scenario 2 Asset Management Plans provides the tools for
discussion with the Council and community on trade-offs between what we would like to do
(scenario 1) and what we should be doing with existing budgets (scenario 2) by balancing
changes in services and service levels with affordability and acceptance of the service and risk consequences of the trade-off position (scenario 3).
5.7.1 What we cannot do
There are some operations and maintenance activities and capital projects that are unable to be undertaken within the next 10 years. These include:
No specific projects identified.
5.7.2 Service consequences
Operations and maintenance activities and capital projects that cannot be undertaken will maintain or create service consequences for users. These include:
Nil
5.7.3 Risk consequences
The operations and maintenance activities and capital projects that cannot be undertaken may maintain or create risk consequences for the organisation. These include:
Nil
- 85 -
THE BAROSSA COUNCIL – TRANSPORT INFRASTRUCTURE ASSET MANAGEMENT PLAN
6. FINANCIAL SUMMARY
This section contains the financial requirements resulting from all the information presented in the
previous sections of this asset management plan. The financial projections will be improved as
further information becomes available on desired levels of service and current and projected
future asset performance.
6.1 Financial Statements and Projections
The financial projections are shown in Figure 7 for projected operating (operations and
maintenance) and capital expenditure (renewal and upgrade/expansion/new assets). Note that
all costs are shown in real values.
Figure 7: Projected Operating and Capital Expenditure
- 86 -
THE BAROSSA COUNCIL – TRANSPORT INFRASTRUCTURE ASSET MANAGEMENT PLAN
Barossa - Projected Operating and Capital Expenditure Data
Category Year Maintenance* Operations* Disposals* Capital
Upgrade* Capital
Renewal* Budget
Expenditure*
Transport 2015 $1,262 $1,880 $0 $1,033 $5,529 $7,886
Transport 2016 $1,332 $1,892 $0 $1,389 $1,090 $7,980
Transport 2017 $1,343 $1,907 $0 $196 $8 $6,787
Transport 2018 $1,345 $1,910 $0 $204 $982 $6,795
Transport 2019 $1,348 $1,914 $0 $215 $352 $6,806
Transport 2020 $1,351 $1,918 $0 $221 $382 $6,812
Transport 2021 $1,353 $1,922 $0 $228 $163 $6,819
Transport 2022 $1,356 $1,926 $0 $236 $561 $6,827
Transport 2023 $1,359 $1,930 $0 $243 $483 $6,834
Transport 2024 $1,362 $1,934 $0 $252 $183 $6,843
Transport 2025 $1,359 $1,938 $0 $422 $1,106 $6,877
Transport 2026 $1,363 $1,944 $0 $422 $1,623 $7,039
Transport 2027 $1,367 $1,950 $0 $422 $3,401 $7,039
Transport 2028 $1,371 $1,956 $0 $422 $2,664 $7,039
Transport 2029 $1,375 $1,962 $0 $422 $2,757 $7,039
Transport 2030 $1,379 $1,968 $0 $422 $2,828 $7,039
Transport 2031 $1,383 $1,974 $0 $422 $2,146 $7,039
Transport 2032 $1,388 $1,980 $0 $422 $2,340 $7,039
Transport 2033 $1,392 $1,985 $0 $422 $2,728 $7,039
Transport 2034 $1,396 $1,991 $0 $422 $2,161 $7,039
*all dollar values in ($'000)'s
6.1.1 Sustainability of service delivery
There are four key indicators for service delivery sustainability that have been considered in the
analysis of the services provided by this asset category, these being the asset renewal funding ratio,
long term life cycle costs/expenditures and medium term projected/budgeted expenditures over 5
and 10 years of the planning period.
Asset Renewal Funding Ratio
Asset Renewal Funding Ratio11 318%
The Asset Renewal Funding Ratio is the most important indicator and reveals that over the next 10
years, Council is forecasting that it will have 318% of the funds required for the optimal renewal and
replacement of its assets.
11 AIFMG, 2015, Version 1.3, Financial Sustainability Indicator 4, Sec 2.6, p 7
- 87 -
THE BAROSSA COUNCIL – TRANSPORT INFRASTRUCTURE ASSET MANAGEMENT PLAN
Long term - Life Cycle Cost
Life cycle costs (or whole of life costs) are the average costs that are required to sustain the service
levels over the asset life cycle. Life cycle costs include operations and maintenance expenditure
and asset consumption (depreciation expense). The life cycle cost for the services covered in this
asset management plan is $6.314 M per year (average operations and maintenance expenditure
plus depreciation expense projected over 10 years).
Life cycle costs can be compared to life cycle expenditure to give an initial indicator of
affordability of projected service levels when considered with age profiles. Life cycle expenditure
includes operations, maintenance and capital renewal expenditure. Life cycle expenditure will
vary depending on the timing of asset renewals. The life cycle expenditure over the 10 year
planning period is $6.617 M per year (average operations and maintenance plus capital renewal
budgeted expenditure in LTFP over 10 years).
A shortfall between life cycle cost and life cycle expenditure is the life cycle gap. The life cycle
gap for services covered by this asset management plan is $303,000 per year (-ve = gap, +ve =
surplus).
Life cycle expenditure is 105% of life cycle costs.
The life cycle costs and life cycle expenditure comparison highlights any difference between
present outlays and the average cost of providing the service over the long term. If the life cycle
expenditure is less than that life cycle cost, it is most likely that outlays will need to be increased or
cuts in services made in the future.
Knowing the extent and timing of any required increase in outlays and the service consequences if
funding is not available will assist organisations in providing services to their communities in a
financially sustainable manner. This is the purpose of the asset management plans and Long Term
Financial Plan.
Medium term – 10 year financial planning period
This asset management plan identifies the projected operations, maintenance and capital renewal
expenditures required to provide an agreed level of service to the community over a 10 year
period. This provides input into 10 year financial and funding plans aimed at providing the required
services in a sustainable manner.
These projected expenditures may be compared to budgeted expenditures in the 10 year period
to identify any funding shortfall. In a core asset management plan, a gap is generally due to
increasing asset renewals for ageing assets.
The projected operations, maintenance and capital renewal expenditure required over the 10 year
planning period is $4.228 M on average per year.
Estimated (budget) operations, maintenance and capital renewal funding is $6.617 M on average
per year giving a 10 year funding surplus of $2.390 M per year. This indicates that Council expects
to have 157% of the projected expenditures needed to provide the services documented in the
asset management plan.
Medium Term – 5 year financial planning period
The projected operations, maintenance and capital renewal expenditure required over the first 5
years of the planning period is $4.819 M on average per year.
Estimated (budget) operations, maintenance and capital renewal funding is $6.643 M on average
per year giving a 5 year funding surplus of $1.825 M. This indicates that Council expects to have
- 88 -
THE BAROSSA COUNCIL – TRANSPORT INFRASTRUCTURE ASSET MANAGEMENT PLAN
138% of projected expenditures required to provide the services shown in this asset management
plan.
Asset management financial indicators
Figure 7A shows the asset management financial indicators over the 10 year planning period and
for the long term life cycle.
Figure 7A: Asset Management Financial Indicators
Providing services from infrastructure in a sustainable manner requires the matching and managing
of service levels, risks, projected expenditures and financing to achieve a financial indicator of
approximately 1.0 for the first years of the asset management plan and ideally over the 10 year life
of the Long Term Financial Plan.
Figure 8 shows the projected asset renewal and replacement expenditure over the 20 years of the
Asset Management Plan. The projected asset renewal and replacement expenditure is compared
to renewal and replacement expenditure in the capital works program, which is accommodated
in the Long Term Financial Plan
- 89 -
THE BAROSSA COUNCIL – TRANSPORT INFRASTRUCTURE ASSET MANAGEMENT PLAN
Figure 8: Projected and LTFP Budgeted Renewal Expenditure
- 90 -
THE BAROSSA COUNCIL – TRANSPORT INFRASTRUCTURE ASSET MANAGEMENT PLAN
Barossa: Projected & LTFP Budgeted Renewal Expenditure Transport
Data
Category Year
Projected
Renewals
Planned
Renewals
Expenditure
Yr1
($'000) ($'000) ($'000)
Transport_S1_V3 2015 $5,529 $3,711 $3,711
Transport_S1_V3 2016 $1,090 $3,387 $3,711
Transport_S1_V3 2017 $8 $3,387 $3,711
Transport_S1_V3 2018 $982 $3,387 $3,711
Transport_S1_V3 2019 $352 $3,387 $3,711
Transport_S1_V3 2020 $382 $3,387 $3,711
Transport_S1_V3 2021 $163 $3,387 $3,711
Transport_S1_V3 2022 $561 $3,387 $3,711
Transport_S1_V3 2023 $483 $3,387 $3,711
Transport_S1_V3 2024 $183 $3,387 $3,711
Transport_S1_V3 2025 $1,106 $3,419 $3,711
Transport_S1_V3 2026 $1,623 $3,419 $3,711
Transport_S1_V3 2027 $3,401 $3,419 $3,711
Transport_S1_V3 2028 $2,664 $3,419 $3,711
Transport_S1_V3 2029 $2,757 $3,419 $3,711
Transport_S1_V3 2030 $2,828 $3,419 $3,711
Transport_S1_V3 2031 $2,146 $3,419 $3,711
Transport_S1_V3 2032 $2,340 $3,419 $3,711
Transport_S1_V3 2033 $2,728 $3,419 $3,711
Transport_S1_V3 2034 $2,161 $3,419 $3,711
*all dollar values in ($'000)'s
Table 6.1.1 shows the surplus between projected renewal and replacement expenditures and
expenditure accommodated in Long Term Financial Plan. Budget expenditures accommodated in
the Long Term Financial Plan or extrapolated from current budgets are shown in Appendix C.
- 91 -
THE BAROSSA COUNCIL – TRANSPORT INFRASTRUCTURE ASSET MANAGEMENT PLAN
Table 6.1.1: Projected and LTFP Budgeted Renewals and Financing Shortfall
Barossa - Report 4 - Table 6.1.1 Renewals Financing Transport
Year End Projected LTFP Renewal
Financing
Cumulative
Shortfall($'000)
Jun-30 Renewals Renewal Budget Shortfall ($'000) (- gap, + surplus)
($'000) ($'000) (- gap, + surplus)
2015 $5,529 $3,711 -$1,818 -$1,818
2016 $1,090 $3,387 $2,297 $480
2017 $8 $3,387 $3,379 $3,859
2018 $982 $3,387 $2,405 $6,264
2019 $352 $3,387 $3,035 $9,298
2020 $382 $3,387 $3,005 $12,303
2021 $163 $3,387 $3,224 $15,527
2022 $561 $3,387 $2,826 $18,353
2023 $483 $3,387 $2,904 $21,257
2024 $183 $3,387 $3,204 $24,461
2025 $1,106 $3,419 $2,313 $26,774
2026 $1,623 $3,419 $1,797 $28,571
2027 $3,401 $3,419 $18 $28,589
2028 $2,664 $3,419 $755 $29,344
2029 $2,757 $3,419 $662 $30,006
2030 $2,828 $3,419 $591 $30,597
2031 $2,146 $3,419 $1,273 $31,870
2032 $2,340 $3,419 $1,079 $32,950
2033 $2,728 $3,419 $692 $33,642
2034 $2,161 $3,419 $1,259 $34,900
Note: A negative shortfall indicates a financing gap, a positive shortfall indicates a surplus for that year.
6.1.2 Projected expenditures for Long Term Financial Plan
Table 6.1.2 shows the projected expenditures for the 10 year Long Term Financial Plan.
Expenditure projections are in 2015 real values.
- 92 -
THE BAROSSA COUNCIL – TRANSPORT INFRASTRUCTURE ASSET MANAGEMENT PLAN
Table 6.1.2: Projected Expenditures for Long Term Financial Plan
Barossa - Report 5 - Table 6.1.2 Long Term Financial Plan
Transport
Year Operations Maintenance Projected Capital
Capital
Renewal Upgrade/New
2015 $1,880 $1,262 $5,529 $1,033
2016 $1,892 $1,332 $1,090 $1,389
2017 $1,907 $1,343 $8 $196
2018 $1,910 $1,345 $982 $204
2019 $1,914 $1,348 $352 $215
2020 $1,918 $1,351 $382 $221
2021 $1,922 $1,353 $163 $228
2022 $1,926 $1,356 $561 $236
2023 $1,930 $1,359 $483 $243
2024 $1,934 $1,362 $183 $252
2025 $1,938 $1,359 $1,106 $422
2026 $1,944 $1,363 $1,623 $422
2027 $1,950 $1,367 $3,401 $422
2028 $1,956 $1,371 $2,664 $422
2029 $1,962 $1,375 $2,757 $422
2030 $1,968 $1,379 $2,828 $422
2031 $1,974 $1,383 $2,146 $422
2032 $1,980 $1,388 $2,340 $422
2033 $1,985 $1,392 $2,728 $422
2034 $1,991 $1,396 $2,161 $422
6.2 Funding Strategy
After reviewing service levels as appropriate, to ensure ongoing financial sustainability projected
expenditures identified in Section 6.1.2 will be accommodated in the Council’s 10 year Long Term
Financial Plan.
- 93 -
THE BAROSSA COUNCIL – TRANSPORT INFRASTRUCTURE ASSET MANAGEMENT PLAN
6.3 Valuation Forecasts
Asset values are forecast to increase as additional assets are added to the asset stock from assets
constructed by land developers and others and donated to Council. Figure 9 shows the projected replacement cost asset values over the planning period in real values.
Figure 9: Projected Asset Values
- 94 -
THE BAROSSA COUNCIL – TRANSPORT INFRASTRUCTURE ASSET MANAGEMENT PLAN
Barossa - Projected Asset Values Transport Data
Category Year ($'000)
Transport_S1_V3 2015 $201,508
Transport_S1_V3 2016 $203,097
Transport_S1_V3 2017 $203,494
Transport_S1_V3 2018 $203,899
Transport_S1_V3 2019 $204,315
Transport_S1_V3 2020 $204,737
Transport_S1_V3 2021 $205,167
Transport_S1_V3 2022 $205,604
Transport_S1_V3 2023 $206,049
Transport_S1_V3 2024 $206,503
Transport_S1_V3 2025 $207,127
Transport_S1_V3 2026 $207,751
Transport_S1_V3 2027 $208,376
Transport_S1_V3 2028 $209,000
Transport_S1_V3 2029 $209,625
Transport_S1_V3 2030 $210,250
Transport_S1_V3 2031 $210,876
Transport_S1_V3 2032 $211,501
Transport_S1_V3 2033 $212,127
Transport_S1_V3 2034 $212,753
*all dollar values in ($'000)'s
- 95 -
THE BAROSSA COUNCIL – TRANSPORT INFRASTRUCTURE ASSET MANAGEMENT PLAN
Depreciation expense values are forecast in line with asset values as shown in Figure 10.
Figure 10: Projected Depreciation Expense
- 96 -
THE BAROSSA COUNCIL – TRANSPORT INFRASTRUCTURE ASSET MANAGEMENT PLAN
Barossa - Projected Depreciation Expense Transport
Data
Category Year Annual Depreciation Charge
Transport_S1_V3 2015 $3,060
Transport_S1_V3 2016 $3,079
Transport_S1_V3 2017 $3,103
Transport_S1_V3 2018 $3,109
Transport_S1_V3 2019 $3,115
Transport_S1_V3 2020 $3,122
Transport_S1_V3 2021 $3,128
Transport_S1_V3 2022 $3,135
Transport_S1_V3 2023 $3,141
Transport_S1_V3 2024 $3,148
Transport_S1_V3 2025 $3,155
Transport_S1_V3 2026 $3,165
Transport_S1_V3 2027 $3,174
Transport_S1_V3 2028 $3,184
Transport_S1_V3 2029 $3,193
Transport_S1_V3 2030 $3,203
Transport_S1_V3 2031 $3,212
Transport_S1_V3 2032 $3,222
Transport_S1_V3 2033 $3,232
Transport_S1_V3 2034 $3,241
*all Dollar Values in ($'000)'s*
The depreciated replacement cost will vary over the forecast period depending on the rates of
addition of new assets, disposal of old assets and consumption and renewal of existing assets.
Forecast of the assets’ depreciated replacement cost is shown in Figure 11. The depreciated
replacement cost of contributed and new assets is shown in the darker colour and in the lighter colour for existing assets.
- 97 -
THE BAROSSA COUNCIL – TRANSPORT INFRASTRUCTURE ASSET MANAGEMENT PLAN
Figure 11: Projected Depreciated Replacement Cost
- 98 -
THE BAROSSA COUNCIL – TRANSPORT INFRASTRUCTURE ASSET MANAGEMENT PLAN
Barossa - Projected Depreciated Replacement Cost Transport
Data
Category Year Existing Assets New Assets
Transport_S1_V3 2015 $144,113 $1,234
Transport_S1_V3 2016 $144,440 $2,804
Transport_S1_V3 2017 $144,767 $3,158
Transport_S1_V3 2018 $145,094 $3,514
Transport_S1_V3 2019 $145,421 $3,874
Transport_S1_V3 2020 $145,748 $4,235
Transport_S1_V3 2021 $146,075 $4,596
Transport_S1_V3 2022 $146,402 $4,959
Transport_S1_V3 2023 $146,729 $5,322
Transport_S1_V3 2024 $147,056 $5,688
Transport_S1_V3 2025 $147,415 $6,217
Transport_S1_V3 2026 $147,775 $6,737
Transport_S1_V3 2027 $148,134 $7,247
Transport_S1_V3 2028 $148,494 $7,748
Transport_S1_V3 2029 $148,853 $8,239
Transport_S1_V3 2030 $149,212 $8,721
Transport_S1_V3 2031 $149,572 $9,194
Transport_S1_V3 2032 $149,931 $9,658
Transport_S1_V3 2033 $150,291 $10,112
Transport_S1_V3 2034 $150,650 $10,556
*all Dollar Values in ($'000)'s*
6.4 Key Assumptions made in Financial Forecasts
This section details the key assumptions made in presenting the information contained in this asset
management plan and in preparing forecasts of required operating and capital expenditure and
asset values, depreciation expense and carrying amount estimates. It is presented to enable
readers to gain an understanding of the levels of confidence in the data behind the financial forecasts.
- 99 -
THE BAROSSA COUNCIL – TRANSPORT INFRASTRUCTURE ASSET MANAGEMENT PLAN
Key assumptions made in this asset management plan and risks that these may change are shown in Table 6.4.
Table 6.4: Key Assumptions made in Asset Management Plan and Risks of Change
Key Assumptions Risks of Change to Assumptions
Growth will remain as predicted Low risk of change due to Character
Preservation (Barossa Valley) Act 2012
Asset condition will continue to be reviewed Failure to continue to condition assess assets
and refine data accuracy will result in the in a
reduced accuracy and relevance of renewal /
replacement programs. In addition, the
condition data is used to model future
expenditure and feed into the Long Term
Financial Plan. Failure to continue to invest in
data accuracy will result in inaccurate forward
estimates.
Asset data is accurate at time of IAMP
preparation
Changes to data accuracy will require the
IAMP to be updated.
Service levels will remain constant for life of the
IAMP
Changes to service levels will require the IAMP
to be updated.
Appropriate Capital Renewal/Replacement
funding is provided for within the Long Term
Financial Plan.
Changes to Capital Renewal / Replacement
funding levels used in this IAMP will affect asset
sustainability ratios and will require the IAMP to
be updated.
Maintenance and renewal practices will remain
the same for the duration of this IAMP
Changes to maintenance and renewal
practices documented in this IAMP will affect
asset sustainability ratios and will require the
IAMP to be updated.
Legislative compliance will remain constant Changes in legislation and regulation may
increase operating and maintenance
expenditure projections.
6.5 Forecast Reliability and Confidence
The expenditure and valuations projections in this Asset Management Plan are based on best
available data. Currency and accuracy of data is critical to effective asset and financial management. Data confidence is classified on a 5 level scale12 in accordance with Table 6.5.
Table 6.5: Data Confidence Grading System
Confidence Grade Description
A Highly reliable Data based on sound records, procedures, investigations and analysis,
documented properly and recognised as the best method of assessment.
Dataset is complete and estimated to be accurate ± 2%
B Reliable Data based on sound records, procedures, investigations and analysis,
documented properly but has minor shortcomings, for example some of the
data is old, some documentation is missing and/or reliance is placed on
unconfirmed reports or some extrapolation. Dataset is complete and
estimated to be accurate ± 10%
C Uncertain Data based on sound records, procedures, investigations and analysis which
is incomplete or unsupported, or extrapolated from a limited sample for
12 IPWEA, 2015, IIMM, Table 2.4.5, p 2|71.
- 100 -
THE BAROSSA COUNCIL – TRANSPORT INFRASTRUCTURE ASSET MANAGEMENT PLAN
Confidence Grade Description
which grade A or B data are available. Dataset is substantially complete
but up to 50% is extrapolated data and accuracy estimated ± 25%
D Very Uncertain Data is based on unconfirmed verbal reports and/or cursory inspections and
analysis. Dataset may not be fully complete and most data is estimated or
extrapolated. Accuracy ± 40%
E Unknown None or very little data held.
The estimated confidence level for and reliability of data used in this Asset Management Plan is shown in Table 6.5.1.
Table 6.5.1: Data Confidence Assessment for Data used in Asset Management Plan
Data Confidence Assessment Comment
Demand drivers A Highly reliable Dependent on Barossa
Development Plan
Growth projections A Highly reliable Dependent on Barossa
Development Plan
Operations expenditures A Highly reliable Dependent on inspection plan
Maintenance expenditures A Highly reliable Dependent on inspection plan
Projected Renewal expenditure A Highly reliable Dependent on renewals identified
in inspection plan
Asset useful lives A Highly reliable Annual review
Condition modelling B Reliable Increase in inspection program
required. A condition assessment of
outstanding assets to be
completed in 17/18 Financial Year
Network renewals B Reliable Dependent on inspection plan. A
condition assessment of
outstanding assets to be
completed in 17/18 financial year.
Defect repairs A Highly reliable Predominantly reactive unless
identified as part of inspection
program
Upgrade/New expenditures A Highly reliable Dependent on capital renewal
program generated from RSM.
Need to ensure frequent asset
condition assessment and useful life
review.
Disposal expenditures A Highly reliable N/A
Over all data sources the data confidence is assessed as having a reliable level for data used in the preparation of this Asset Management Plan.
- 101 -
THE BAROSSA COUNCIL – TRANSPORT INFRASTRUCTURE ASSET MANAGEMENT PLAN
7. PLAN IMPROVEMENT AND MONITORING
7.1 Status of Asset Management Practices
7.1.1 Accounting and financial systems
Council utilises the Technology One software product – Finance One.
Accountabilities for financial systems
Manager Financial Services
Senior Accountant - Budgets
Asset Accountant – Acquisition and disposal
Payroll Officer - Payroll
Accounts Payable Clerk – Accounts Payable
Finance Officer
Accounting standards and regulations
International Financial Reporting Standards (IFRS)
Accounting Standard AASB116 – Property Plant and Equipment
Accounting Standard AASB136 – Impairment of Assets
Accounting Standard AASB13 – Fair Value Measurement
Accounting Standard AASB108 – Accounting Policies, Changes in Estimates and Errors
Accounting Standard AASB1051 – Land Under Roads
Accounting Standard AASB141 – Agriculture
CPA Australia and the Australian Asset Management Collective Group – Guide to the valuation
and depreciation of not-for-profit and public sector physical assets under accrual based
accounting standards
Australian Infrastructure Financial management Guidelines – December 2015
Framework for the Preparation and Presentation of Financial Statements – Australian Accounting
Standards Board – December 2007
International Accounting Standards (IAS) Property, Plant and Equipment (paragraph 6)
South Australian Model Financial Statements – Local Government of South Australia
Councils Asset Class Revaluation and Condition Assessment Program
- 102 -
THE BAROSSA COUNCIL – TRANSPORT INFRASTRUCTURE ASSET MANAGEMENT PLAN
Capital/maintenance threshold
Asset
Class
Asset
Groups/Types within Class
Type
Sub-
Classificatio
n/ Component
Determining
Factor Capital Operating (including maintenance)
Transport
Road – Earth,
Pavement,
Surface & Seal,
Footpath,
Kerbing, Car
parks
Sealed
Roads
Sealed
Roads – Earth
Road
hierarchy &
construction
type
If satisfying at least one of the following
conditions:
All Resealing (other than patching that
constitutes a segment of road)
All other reconstruction and renewal work >=
$20,000
Expenditure >= 10% of the DRV of the
component
Any new assets acquired (e.g. from land
developments)
Any line marking undertaken in conjunction with
these works will be capital
Reactive maintenance and repair to road assets
not meeting capitalisation criteria
Programmed maintenance (partial sealed road
surfacing <$10,000, pothole repair) not meeting
capitalisation criteria
Line Marking, road cleaning and sweeping as part
of programmed maintenance
Shoulder grading
Sealed
Roads –
Pavement (includes
shoulders)
Sealed
Roads -
Surface
Sheeted
Roads
Sheeted
Roads -
Earth
If satisfying at least one of the following
conditions:
Resheeting (other than patching that
constitutes more than a segment of road)
Estimated work >= $15,000
Projects requiring >= 200 tonnes of material
Reactive maintenance and repair to road
assets(pothole repair) not meeting capitalisation
criteria
Programmed maintenance (unsealed road
grading) not meeting capitalisation criteria Sheeted
Roads –
Pavement
or Surface
Formed
and
Unformed
Roads
Unformed -
Earth
Any new assets acquired free of charge Any work carried out will be expensed
- 103 -
THE BAROSSA COUNCIL – TRANSPORT INFRASTRUCTURE ASSET MANAGEMENT PLAN
Asset
Class
Asset
Groups/Types
within Class
Type
Sub-
Classificatio
n/
Component
Determining
Factor Capital Operating (including maintenance)
Footpaths
/ Kerbs /
Car park
Structures
Car park
surfaces
Level of
usage
All new, upgrade or replacement work >=
$10,000
Any new assets acquired (e.g. from land
developments)
All repairs and maintenance, replacement or
upgrades that constitute <$10,000
Reactive maintenance to kerb and gutter assets
(repair, replacement of small lengths)
Required changes to accounting financial systems arising from this Asset Management Plan
Ability to split costs between Maintenance and Operating expenditure
7.1.2 Asset management system
Council utilises the Conquest Solutions Asset Management software product – Conquest III.
Asset registers
The Transport Asset Network register in Conquest III covers:
Car Parks:
- 104 -
THE BAROSSA COUNCIL – TRANSPORT INFRASTRUCTURE ASSET MANAGEMENT PLAN
Footpaths:
Kerb and Gutter:
Bike Path:
Road Earth:
Road Pavement:
- 105 -
THE BAROSSA COUNCIL – TRANSPORT INFRASTRUCTURE ASSET MANAGEMENT PLAN
Road Surface:
Linkage from asset management to financial system
No software integration at this point in time. Assets in Conquest do have Finance Asset ID listed against the assets.
Accountabilities for asset management system and data maintenance
Manager Assets and Infrastructure (MAI)
Required changes to asset management system arising from this Asset Management Plan
Improve the accuracy of data and the linkage of the Asset Management System data to the corporate mapping system.
- 106 -
THE BAROSSA COUNCIL – TRANSPORT INFRASTRUCTURE ASSET MANAGEMENT PLAN
7.2 Improvement Plan
The asset management improvement plan generated from this asset management
plan is shown in Table 7.2.
Table 7.2: Improvement Plan
Task
No
Task Responsibility Resources
Required
Timeline
1 Enable Finance System to record / allocate costs
between Operations and Maintenance
MFS MFS 17/18
2 Easily differentiate between operating and
maintenance expenditure in Finance System
MFS MFS 17/18
3 Easily differentiate between planned and
reactive maintenance expenditure in Finance
System
MFS MFS 17/18
4 Develop and establish ongoing assessment in
relationship to safety and specified maintenance
intervention levels.
MES MES Ongoing
5 Audit and review of maintenance response times
(to confirm whether maintenance works are
delivered on time).
MO MO Annual
6 Random audit of maintenance works (to confirm
whether maintenance works are delivered to the
specified quality).
MO MO Ongoing
7 Consultation to ascertain the community’s service
needs and preferences and confirm performance
targets.
Communications
and Marketing
Officer
Communi
cations
and
Marketing
Officer
Every 4
Years
8 Review of the customer request reports available
in Pathway.
Admin Officer Admin
Officer
Annual
9 Utilise Conquest to undertake and record planned
maintenance activities on the network.
DWES WES Team 16/17
10 Undertake maintenance activities through a
planned maintenance system to reduce
maintenance costs and improve maintenance
outcomes.
DWES MO 16/17
11 Split Capital budget for footpath assets from kerb
and gutter assets
MFS MFS 16/17
12 Determine Function data and include against
each asset on a 1 – 5 rating.
Function is the ability of the physical infrastructure
MES / CAM CAM 16/17
- 107 -
THE BAROSSA COUNCIL – TRANSPORT INFRASTRUCTURE ASSET MANAGEMENT PLAN
to meet program delivery needs
13 Determine Capacity/Utilisation data and include
against each asset on a 1 – 5 rating.
Capacity/Utilisation represents the ability of the
physical infrastructure to meet service delivery
needs.
MES / CAM CAM 16/17
14 Create a specific Infrastructure Asset
management Plan focussed on Council’s Freight
Route.
MES / CAM CAM 16/17
15 Detailed data collection and Pavement Strength
Analysis study via Falling Weight Deflectometer,
core samples and modelling on Freight Route to
identify specific locations requiring pavement
strengthening.
DWES / CAM MES /
CAM
17/18
16 A condition assessment of outstanding assets
including review of useful lives and condition
criteria to be completed.
DWES / CAM MAS /
CAM
17/18
7.3 Monitoring and Review Procedures
This asset management plan will be reviewed during annual budget planning
processes and amended to recognise any material changes in service levels and/or
resources available to provide those services as a result of budget decisions.
The Asset Management Plan will be updated annually to ensure it represents the
current service level, asset values, projected operations, maintenance, capital
renewal and replacement, capital upgrade/new and asset disposal expenditures
and projected expenditure values incorporated into the organisation’s Long Term
Financial Plan.
Resources will be allocated by Council to ensure annual updates occur.
The Asset Management Plan has a life of 4 years (Council election cycle) and is due
for complete revision and updating within two years of each Council/Board election.
7.4 Performance Measures
The effectiveness of the asset management plan can be measured in the following
ways:
The degree to which the required projected expenditures identified in this
asset management plan are incorporated into Council’s Long Term Financial
Plan,
The degree to which 1-5 year detailed works programs, budgets, business
plans and organisational structures take into account the ‘global’ works
program trends provided by the asset management plan,
The degree to which the existing and projected service levels and service
consequences (what we cannot do), risks and residual risks are incorporated
into the Council’s Strategic Plan and associated plans,
The Asset Renewal Funding Ratio achieving the target of 1.0.
- 108 -
THE BAROSSA COUNCIL – TRANSPORT INFRASTRUCTURE ASSET MANAGEMENT PLAN
8. REFERENCES
IPWEA, 2008, ‘NAMS.PLUS Asset Management’, Institute of Public Works Engineering
Australasia, Sydney, www.ipwea.org/namsplus.
IPWEA, 2015, ‘Australian Infrastructure Financial Management Guidelines’, Institute of
Public Works Engineering Australasia, Sydney, www.ipwea.org/AIFMG.
IPWEA, 2015, ‘International Infrastructure Management Manual’, Institute of Public
Works Engineering Australasia, Sydney, www.ipwea.org/IIMM
Barossa Community Plan 2016 - 2036
The Barossa Council – Annual Budget and Business Plan 2015 – 2016
http://www.barossa.sa.gov.au/sections/council/financial-documents/annual-
budget-business-plan
- 109 -
THE BAROSSA COUNCIL – TRANSPORT INFRASTRUCTURE ASSET MANAGEMENT PLAN
9. APPENDICES
Appendix A Maintenance Response Levels of Service
The response level of Service for Transport Assets is dependent on the answers given
by the customer. This determines which department the request will go to as per
below:
Footpath Assets:
- 110 -
THE BAROSSA COUNCIL – TRANSPORT INFRASTRUCTURE ASSET MANAGEMENT PLAN
Sealed Roads:
- 111 -
THE BAROSSA COUNCIL – TRANSPORT INFRASTRUCTURE ASSET MANAGEMENT PLAN
- 112 -
THE BAROSSA COUNCIL – TRANSPORT INFRASTRUCTURE ASSET MANAGEMENT PLAN
Unsealed Roads:
- 113 -
THE BAROSSA COUNCIL – TRANSPORT INFRASTRUCTURE ASSET MANAGEMENT PLAN
General Road Construction:
- 114 -
THE BAROSSA COUNCIL – TRANSPORT INFRASTRUCTURE ASSET MANAGEMENT PLAN
Appendix B Projected 10 year Capital Renewal and Replacement Works Program
PROJECTS IDENTIFIED. NOTE: PRIORITY TO BE GIVEN TO ROAD SHOULDER (SEAL WIDENING) AND TRAFFIC SAFETY HOT SPOTS.
Primary Road Township Start Location End Location Action Estimated Amount
Craneford Road Springton 6 way intersection - 1
Realignment to create T junction offsets $ 150,000
Penrice Products Penrice Intersection
Pave and 50 mm Hotmix Seal $ 100,000
Craneford Road Springton 6 way intersection - 2
Realignment to create T junction offsets $ 160,000
Para Road Tanunda Murray Street Richmond Grove Seal widening and kerb & drainage $ 220,000
MacDonnell Street Tanunda Kindergarten Fiedler Street Reconstruct pave, seal, kerb & concrete footpath both sides $ 155,445
**Historical data but still relevant – from 10 year Capital plan developed by WES
The following 10 year plan is generated based on asset expiry only. Please refer to the other drivers stated on p 21 of this asset management plan that are considered in creation of the final program.
Barossa - Report 6 - Appendix B 10 year Renewal & Replacement Program (Transport_S1_V5)
Asset ID
Sub
Asset Name From To
Rem Planned Renewal Useful
Category Life Renewal Cost Life
(Years) Year ($) (Years)
7391 Township Normal Use Slurry Seal / Cold Overlay Surface
Disposed - Surface - Barossa Street (0005) from Gawler Street to Warneckle Street
Gawler Street Warneckle Street -5 2010 $0 15
Subtotal $0
11426 Rural B Double Normal Use Spray Pavement Type
Pavement - Forreston Road (0005) from Warren Road to Segment limit-1km S
Warren Road Segment limit-1km S -4 2011 $383,657 40
11630 Rural B Double Normal Use Spray Pavement Type
Pavement - Springton Road (0055) from Wirra Wirra Road to Police Paddock Road
Wirra Wirra Road Police Paddock Road -4 2011 $428,784 40
11631 Rural B Double Normal Use Spray Pavement Type
Pavement - Springton Road (0060) from Police Paddock Road to Cowell Road
Police Paddock Road Cowell Road -4 2011 $458,800 40
11632 Rural B Double Normal Use Spray Pavement Type
Pavement - Springton Road (0065) from Cowell Road to Glen Devon Road
Cowell Road Glen Devon Road -4 2011 $262,354 40
9438 Rural Road Reserve Surface Surface - Ann Milroy Lane (0010) from Gates to Barossa Valley Way
Gates Barossa Valley Way -4 2011 $4,158 15
7291 Township Normal Use Slurry Seal / Cold Overlay Surface
Disposal - Surface - Sibley Street (0005) from Chinner Lane to Hodder Street
Chinner Lane Hodder Street -4 2011 $0 15
Subtotal $1,537,752
11635 Rural B Double Normal Use Spray Pavement Type
Pavement - Springton Road (0080) from Dawson Road to Segment limit-1km E
Dawson Road Segment limit-1km E -3 2012 $386,338 40
11636 Rural B Double Normal Use Spray Pavement Type
Pavement - Springton Road (0085) from Segment limit to High Eden Road
Segment limit High Eden Road -3 2012 $311,495 40
11637 Rural B Double Normal Use Spray Pavement Type
Pavement - Springton Road (0095) from High Eden Road to Barossa Boundary Road
High Eden Road Barossa Boundary Road -3 2012 $467,510 40
7368 Township Normal Use Slurry Seal / Cold Overlay Surface
Disposed - Surface - Ninnes Grove (0005) from Jubilee Avenue to end
Jubilee Avenue end -3 2012 $0 15
27654 Upright Kerb and gutter Left Kerb - Saleyard Road, (Mount Pleasant) From Showground Road to
Hocknull Place
Mount Pleasant From Showground Road to Hocknull Place -3 2012 $18,438 27
- 115 -
THE BAROSSA COUNCIL – TRANSPORT INFRASTRUCTURE ASSET MANAGEMENT PLAN
Subtotal $1,183,781
8636 Rural Normal Use Spray Seal Bitumen Surface
Disposed - Surface - Bethany Road (0015) from Menge Road to Nicolai Road
Menge Road Nicolai Road -2 2013 $0 25
8635 Rural Normal Use Spray Seal Bitumen Surface
Disposed - Surface - Bethany Road (0020) from Nicolai Road to Thiele Road
Nicolai Road Thiele Road -2 2013 $0 25
Subtotal $0
11624 Rural B Double Normal Use Spray Pavement Type
Pavement - Springton Road (0025) from Segment limit to Old Glen Road
Segment limit Old Glen Road -1 2014 $287,415 40
11625 Rural B Double Normal Use Spray Pavement Type
Pavement - Springton Road (0030) from Old Glen Road to Segment limit-1km SE
Old Glen Road Segment limit-1km SE -1 2014 $409,840 40
Subtotal $697,255
16227 Bitumen - Spray Seal Footpath Surface Type
Left footpath - Barossa Valley Way (Lyndoch) from foot bridge to Altona Road
Lyndoch foot bridge to Altona Road 0 2015 $0 30
16218 Bitumen - Spray Seal Footpath Surface Type
Left footpath - Boehm Street (Nuriootpa) from Below Street to Keuper Street
NURIOOTPA Below Street to Keuper Street 0 2015 $1,609 33
16219 Bitumen - Spray Seal Footpath Surface Type
Left footpath - Boehm Street (Nuriootpa) from Below Street to Keuper Street
NURIOOTPA Below Street to Keuper Street 0 2015 $3,312 33
16220 Bitumen - Spray Seal Footpath Surface Type
Left footpath - Boehm Street (Nuriootpa) from Keuper Street to end
NURIOOTPA Keuper Street to end 0 2015 $1,066 33
15705 Bitumen - Spray Seal Footpath Surface Type
Left footpath - Garrett Court (Tanunda) from MacDonnell Street to end
TANUNDA MacDonnell Street to end 0 2015 $3,733 22
16261 Bitumen - Spray Seal Footpath Surface Type
Left footpath - Keuper Street (Nuriootpa) from Below Street to Old Kapunda Road
NURIOOTPA Below Street to Old Kapunda Road 0 2015 $1,639 29
16258 Bitumen - Spray Seal Footpath Surface Type
Right footpath - Below Street (Nuriootpa) from Boehm Street to Keuper Street
NURIOOTPA Boehm Street to Keuper Street 0 2015 $4,782 29
16259 Bitumen - Spray Seal Footpath Surface Type
Right footpath - Below Street (Nuriootpa) from Keuper Street to end
NURIOOTPA Keuper Street to end 0 2015 $1,313 29
15144 Bitumen - Spray Seal Footpath Surface Type
Right footpath - Dean Street (Angaston) from end of pavers to Sturt Street
ANGASTON end of pavers to Sturt Street 0 2015 $1,721 25
16120 Bitumen - Spray Seal Footpath Surface Type
Right footpath - George Street (Williamstown) from Church Street to Eliza
Street
WILLIAMSTOWN Church Street to Eliza Street 0 2015 $2,021 22
16260 Bitumen - Spray Seal Footpath Surface Type
Right footpath - Keuper Street (Nuriootpa) from Below Street to Old Kapunda Road
NURIOOTPA Below Street to Old Kapunda Road 0 2015 $1,639 29
15408 Paved Footpath Surface Type Left footpath - Johnson Court (Nuriootpa) from Haese Court to end
NURIOOTPA Haese Court to end 0 2015 $7,064 18
15989 Rubble Footpath Surface Type Left footpath - Saleyard Road (Mount Pleasant) from Showground Road to
Hocknull Place
MOUNT PLEASANT Showground Road to Hocknull Place 0 2015 $2,693 17
16122 Rubble Footpath Surface Type Right footpath - Queen Street (Williamstown) from Lyndoch Valley Road
to end rubble
WILLIAMSTOWN Lyndoch Valley Road to end rubble 0 2015 $3,452 19
11369 Rural B Double Normal Use Spray Pavement Type
Pavement - Belvidere Road (0005) from Kalimna Road to Sturt Highway
Kalimna Road Sturt Highway 0 2015 $226,569 40
11616 Rural B Double Normal Use Spray Pavement Type
Pavement - Springton Road (0005) from Barossa Boundary Road to E. Lorkes Road
Barossa Boundary Road E. Lorkes Road 0 2015 $320,178 40
- 116 -
THE BAROSSA COUNCIL – TRANSPORT INFRASTRUCTURE ASSET MANAGEMENT PLAN
11617 Rural B Double Normal Use Spray Pavement Type
Pavement - Springton Road (0005) from Mt. Crawford Road to Segment limit-1km
Mt. Crawford Road Segment limit-1km 0 2015 $331,795 40
11619 Rural B Double Normal Use Spray Pavement Type
Pavement - Springton Road (0010) from Segment limit to Glen Gillian Road
Segment limit Glen Gillian Road 0 2015 $214,727 40
11626 Rural B Double Normal Use Spray Pavement Type
Pavement - Springton Road (0035) from Segment limit to Abbaston Road
Segment limit Abbaston Road 0 2015 $68,451 40
11627 Rural B Double Normal Use Spray Pavement Type
Pavement - Springton Road (0040) from Abbaston Road to Segment limit-870m SE
Abbaston Road Segment limit-870m SE 0 2015 $344,483 40
11628 Rural B Double Normal Use Spray Pavement Type
Pavement - Springton Road (0045) from Segment limit to Segment limit-1km E
Segment limit Segment limit-1km E 0 2015 $398,528 40
11629 Rural B Double Normal Use Spray Pavement Type
Pavement - Springton Road (0050) from Segment limit to Wirra Wirra Road
Segment limit Wirra Wirra Road 0 2015 $169,276 40
Subtotal $2,110,050
16314 Bitumen - Spray Seal Footpath Surface Type
Right footpath - Barossa Valley Way (Nuriootpa) from Kaiser Stuhl Avenue to
Nuraip Road
Nuriootpa Kaiser Stuhl Avenue to Nuraip Road 1 2016 $36,994 2
16315 Bitumen - Spray Seal Footpath Surface Type
Right footpath - Barossa Valley Way (Nuriootpa) from Nuraip Road to
Seppeltsfield Road
Nuriootpa Nuraip Road to Seppeltsfield Road 1 2016 $63,656 2
32457 Car Park - Hotmix Surface Car Park - Murray Street (behind Hall) - Nuriootpa
NURIOOTPA Memorial Avenue 1 2016 $65,912 21
11618 Rural B Double Normal Use Spray Pavement Type
Pavement - Springton Road (0010) from E Lorkes Road to E Staricks Road
E Lorkes Road E Staricks Road 1 2016 $457,737 40
11620 Rural B Double Normal Use Spray Pavement Type
Pavement - Springton Road (0015) from E Staricks Road to L. Staricks Road
E Staricks Road L. Staricks Road 1 2016 $423,684 40
11623 Rural B Double Normal Use Spray Pavement Type
Pavement - Williamstown Road (0025) from Drogmueller Road to Township
Fringe
Drogmueller Road Township Fringe 1 2016 $41,665 40
8787 Rural Normal Use Spray Seal Bitumen Surface
Dispose - Surface - Allendale Road (0005) from Balmoral Road to Segment limit-1km
S
Balmoral Road Segment limit-1km S 1 2016 $0 25
8785 Rural Normal Use Spray Seal Bitumen Surface
Disposed - Surface - Allendale Road (0010) from Surface change-Sheeted to
Surface change-Sheeted 1 2016 $0 25
Subtotal $1,089,648
9476 Rural Normal Use Hotmix Pavement Type Pavement - Needles Road (0005) from Yettie Road to Pappin Road
Yettie Road Pappin Road 2 2017 $7,678 15
Subtotal $7,678
16314 Bitumen - Spray Seal Footpath Surface Type
Right footpath - Barossa Valley Way (Nuriootpa) from Kaiser Stuhl Avenue to
Nuraip Road
Nuriootpa Kaiser Stuhl Avenue to Nuraip Road 3 2018 $36,994 2
16315 Bitumen - Spray Seal Footpath Surface Type
Right footpath - Barossa Valley Way (Nuriootpa) from Nuraip Road to
Seppeltsfield Road
Nuriootpa Nuraip Road to Seppeltsfield Road 3 2018 $63,656 2
15955 Natural Footpath Surface Type Left footpath - College Street (Tanunda) from Sobels Street to Bilyara Street
TANUNDA Sobels Street to Bilyara Street 3 2018 $0 20
16317 Rubble Footpath Surface Type Left footpath - Barossa Valley Way (Rowland Flat) from Winery carpark to
Community Centre carpark
Rowland Flat Winery carpark to Community Centre carpark
3 2018 $0 20
- 117 -
THE BAROSSA COUNCIL – TRANSPORT INFRASTRUCTURE ASSET MANAGEMENT PLAN
11427 Rural B Double Normal Use Spray Pavement Type
Pavement - Forreston Road (0010) from Segment limit to Dickers Road
Segment limit Dickers Road 3 2018 $397,255 40
11428 Rural B Double Normal Use Spray Pavement Type
Pavement - Forreston Road (0015) from Dickers Road to Ironstone Road
Dickers Road Ironstone Road 3 2018 $295,124 40
9182 Rural Normal Use Hotmix Pavement Type Pavement - Nuraip Road (0015) from Surface change-Sheeted to Surface
change-Spray Sealed 600m NW
Surface change-Sheeted Surface change-Spray Sealed 600m NW 3 2018 $154,233 15
8858 Rural Normal Use Spray Seal Bitumen Surface
Disposed - Surface - Alexander Murray Road (0005) from Gottwald Road to
Winters Road
Gottwald Road Winters Road 3 2018 $0 25
8670 Rural Normal Use Spray Seal Bitumen Surface
Surface - Long Gully Road (0015) from Hurns Road to Vine Vale Road
Hurns Road Vine Vale Road 3 2018 $34,987 25
32526 Township Normal Use Slurry Seal / Cold Overlay Surface
Disposed - Surface - Boehm Street (0006) from 94m from Below Street to Keuper
Street
Below Street Keuper Street 3 2018 $0 15
7318 Township Normal Use Slurry Seal / Cold Overlay Surface
Dispsed - Surface - Theodor Street (0005) from Murray Street to Maria Street
Murray Street Maria Street 3 2018 $0 15
Subtotal $982,250
8564 Rural - B Double Route - Normal Use Spray Seal
Surface - Belvidere Road (0005) from Kalimna Road to Sturt Highway
Kalimna Road Sturt Highway 4 2019 $33,223 14
8869 Rural - B Double Route - Normal Use Spray Seal
Surface - Forreston Road (0005) from Warren Road to Segment limit-1km S
Warren Road Segment limit-1km S 4 2019 $49,722 18
8749 Rural - B Double Route - Normal Use Spray Seal
Surface - Springton Road (0055) from Wirra Wirra Road to Police Paddock Road
Wirra Wirra Road Police Paddock Road 4 2019 $61,856 18
8734 Rural - B Double Route - Normal Use Spray Seal
Surface - Springton Road (0060) from Police Paddock Road to Cowell Road
Police Paddock Road Cowell Road 4 2019 $62,292 18
8738 Rural - B Double Route - Normal Use Spray Seal
Surface - Springton Road (0065) from Cowell Road to Glen Devon Road
Cowell Road Glen Devon Road 4 2019 $35,620 18
8743 Rural - B Double Route - Normal Use Spray Seal
Surface - Springton Road (0085) from Segment limit to High Eden Road
Segment limit High Eden Road 4 2019 $42,292 17
8744 Rural - B Double Route - Normal Use Spray Seal
Surface - Springton Road (0095) from High Eden Road to Barossa Boundary Road
High Eden Road Barossa Boundary Road 4 2019 $67,442 17
7299 Township Normal Use Slurry Seal / Cold Overlay Surface
Disposal - Surface - Chinner Street (0005) from Park Road to Chinner Lane
Park Road Chinner Lane 4 2019 $0 15
6874 Township Normal Use Slurry Seal / Cold Overlay Surface
Disposed - Surface - Kaiser Stuhl Avenue (0005) from Tanunda Road to John Harris
Drive
Tanunda Road John Harris Drive 4 2019 $0 15
6879 Township Normal Use Slurry Seal / Cold Overlay Surface
Disposed - Surface - Kaiser Stuhl Avenue (0010) from John Harris Drive to John
Harris Drive
John Harris Drive John Harris Drive 4 2019 $0 15
7189 Township Normal Use Slurry Seal / Cold Overlay Surface
Disposed - Surface - Kaiser Stuhl Avenue (0015) from John Harris Drive to end
John Harris Drive end 4 2019 $0 15
Subtotal $352,448
16314 Bitumen - Spray Seal Footpath Surface Type
Right footpath - Barossa Valley Way (Nuriootpa) from Kaiser Stuhl Avenue to
Nuraip Road
Nuriootpa Kaiser Stuhl Avenue to Nuraip Road 5 2020 $36,994 2
16315 Bitumen - Spray Seal Footpath Surface Type
Right footpath - Barossa Valley Way (Nuriootpa) from Nuraip Road to
Seppeltsfield Road
Nuriootpa Nuraip Road to Seppeltsfield Road 5 2020 $63,656 2
- 118 -
THE BAROSSA COUNCIL – TRANSPORT INFRASTRUCTURE ASSET MANAGEMENT PLAN
8871 Rural - B Double Route - Normal Use Spray Seal
Surface - Forreston Road (0010) from Segment limit to Dickers Road
Segment limit Dickers Road 5 2020 $47,807 12
8747 Rural - B Double Route - Normal Use Spray Seal
Surface - Springton Road (0005) from Barossa Boundary Road to E. Lorkes Road
Barossa Boundary Road E. Lorkes Road 5 2020 $43,471 15
8758 Rural - B Double Route - Normal Use Spray Seal
Surface - Springton Road (0005) from Mt. Crawford Road to Segment limit-1km
Mt. Crawford Road Segment limit-1km 5 2020 $49,144 15
8737 Rural - B Double Route - Normal Use Spray Seal
Surface - Springton Road (0010) from E Lorkes Road to E Staricks Road
E Lorkes Road E Staricks Road 5 2020 $62,148 14
8756 Rural - B Double Route - Normal Use Spray Seal
Surface - Springton Road (0010) from Segment limit to Glen Gillian Road
Segment limit Glen Gillian Road 5 2020 $31,804 15
8753 Rural - B Double Route - Normal Use Spray Seal
Surface - Springton Road (0025) from Segment limit to Old Glen Road
Segment limit Old Glen Road 5 2020 $39,023 16
8764 Rural - B Double Route - Normal Use Spray Seal
Surface - Williamstown Road (0025) from Drogmueller Road to Township Fringe
Drogmueller Road Township Fringe 5 2020 $5,400 14
8672 Rural Normal Use Spray Seal Bitumen Surface
Disposed - Surface - Menglers Hill Road - Angaston (0001) from Radford Road to
Segment Limit 1km S
Radford Road Segment Limit 1km S 5 2020 $0 25
8831 Rural Normal Use Spray Seal Bitumen Surface
Disposed - Surface - Yettie Road (0030) from Start-Rural Seal to Para Wirra Road
Start-Rural Seal Para Wirra Road 5 2020 $0 25
8859 Rural Normal Use Spray Seal Bitumen Surface
Disposed - Surface - Yettie Road (0035) from Para Wirra Road to Gottwald Road
Para Wirra Road Gottwald Road 5 2020 $0 25
8835 Rural Normal Use Spray Seal Bitumen Surface
Disposed - Surface - Yettie Road (0040) from Gottwald Road to Millington Road
Gottwald Road Millington Road 5 2020 $0 25
8828 Rural Normal Use Spray Seal Bitumen Surface
Disposed - Surface - Yettie Road (0045) from Millington Road to Needles Road
Millington Road Needles Road 5 2020 $0 25
8827 Rural Normal Use Spray Seal Bitumen Surface
Disposed - Surface - Yettie Road (0050) from Needles Road to Segment limit-670m
N
Needles Road Segment limit-670m N 5 2020 $0 25
7327 Township Normal Use Spray Seal Bitumen Surface
Disposed - Surface - Barossa Street (0010) from Warneckle Street to Orchard Court
Warneckle Street Orchard Court 5 2020 $0 25
6967 Township Normal Use Spray Seal Bitumen Surface
Disposed - Surface - Park Avenue (0005) from Penrice Road to Memorial Avenue
Penrice Road Memorial Avenue 5 2020 $0 25
6752 Township Normal Use Spray Seal Bitumen Surface
Surface - Rowland Street (0005) from Penrice Road to Sarah Street
Penrice Road Sarah Street 5 2020 $2,972 4
Subtotal $382,420
8865 Rural - B Double Route - Normal Use Spray Seal
Surface - Forreston Road (0015) from Dickers Road to Ironstone Road
Dickers Road Ironstone Road 6 2021 $35,516 13
9575 Rural Sheeted Surface Function Priority 2,1
Surface - Jaeger Road (0005) from Sturt Highway to End
Sturt Highway End 6 2021 $2,138 36
9326 Rural Sheeted Surface Function Priority 2,1
Surface - Menzel Road (0010) from Surface change-Formed to End
Surface change-Formed End 6 2021 $2,336 13
32625 Rural Sheeted Surface Function Priority 5,4
Surface - Cockatoo Lane (0001) from Barossa Valley Way to surface change -
Sealed
Barossa Valley Way surface change - sealed 6 2021 $7,101 23
9520 Rural Sheeted Surface Function Priority 5,4
Surface - Gottwald Road (0005) from Yetti Road to Winters Road
Yetti Road Winters Road 6 2021 $5 19
6726 Township Normal Use Spray Seal Bitumen Surface
Surface - Falkenberg Road (0010) from Oxley Street to Cook Street
Oxley Street Cook Street 6 2021 $69,719 25
7198 Township Normal Use Spray Seal Bitumen Surface
Surface - Falkenberg Road (0015) from Cook Street to Tolley Road
Cook Street Tolley Roadt 6 2021 $46,160 25
- 119 -
THE BAROSSA COUNCIL – TRANSPORT INFRASTRUCTURE ASSET MANAGEMENT PLAN
Subtotal $162,975
16314 Bitumen - Spray Seal Footpath Surface Type
Right footpath - Barossa Valley Way (Nuriootpa) from Kaiser Stuhl Avenue to
Nuraip Road
Nuriootpa Kaiser Stuhl Avenue to Nuraip Road 7 2022 $36,994 2
16315 Bitumen - Spray Seal Footpath Surface Type
Right footpath - Barossa Valley Way (Nuriootpa) from Nuraip Road to
Seppeltsfield Road
Nuriootpa Nuraip Road to Seppeltsfield Road 7 2022 $63,656 2
15235 Bitumen - Spray Seal Footpath Surface Type
Right footpath - Washington Street (Angaston) from Evans Street to end
bitumen
ANGASTON Evans Street to end bitumen 7 2022 $1,347 16
8745 Rural - B Double Route - Normal Use Spray Seal
Surface - Springton Road (0030) from Old Glen Road to Segment limit-1km SE
Old Glen Road Segment limit-1km SE 7 2022 $55,645 18
8740 Rural - B Double Route - Normal Use Spray Seal
Surface - Springton Road (0035) from Segment limit to Abbaston Road
Segment limit Abbaston Road 7 2022 $9,294 17
8735 Rural - B Double Route - Normal Use Spray Seal
Surface - Springton Road (0040) from Abbaston Road to Segment limit-870m SE
Abbaston Road Segment limit-870m SE 7 2022 $82,512 17
8741 Rural - B Double Route - Normal Use Spray Seal
Surface - Springton Road (0045) from Segment limit to Segment limit-1km E
Segment limit Segment limit-1km E 7 2022 $86,927 17
8742 Rural - B Double Route - Normal Use Spray Seal
Surface - Springton Road (0050) from Segment limit to Wirra Wirra Road
Segment limit Wirra Wirra Road 7 2022 $55,801 17
9559 Rural Sheeted Surface Function Priority 2,1
Surface - Hillview Road (0010) from Tungkillo Road to Ross Smith Road
Tungkillo Road Ross Smith Road 7 2022 $11,547 39
9370 Rural Sheeted Surface Function Priority 2,1
Surface - Malcolm Starick Road (0005) from McBeans Range Road to End
McBeans Range Road End 7 2022 $7,817 19
9237 Rural Sheeted Surface Function Priority 5,4
Surface - Heggies Range Road (0020) from Goodchild Road to Road No-0640
Goodchild Road Road No-0640 7 2022 $52,667 24
9273 Rural Sheeted Surface Function Priority 5,4
Surface - High Eden Road (0005) from Barossa Boundary Road to Springton Road
Barossa Boundary Road Springton Road 7 2022 $20,679 24
9344 Rural Sheeted Surface Function Priority 5,4
Surface - Steingarten Road (0015) from Surface change-Sheeted to End-Sheeted
1.53km SE
Surface change-Sheeted End-Sheeted 1.53km SE 7 2022 $46,833 18
9401 Rural Sheeted Surface Function Priority 7 Surface - McCallum Road (0010) from Kalperri Road to William Hawke Road
Kalperri Road William Hawke Road 7 2022 $28,865 15
Subtotal $560,584
15314 Bitumen - Spray Seal Footpath Surface Type
Left footpath - Barossa Street (Nuriootpa) from Gawler Street end
NURIOOTPA Gawler Street end 8 2023 $1,145 40
15102 Bitumen - Spray Seal Footpath Surface Type
Left footpath - Cross Street (Angaston) from Middle Street to Moculta Road
ANGASTON Middle Street to Moculta Road 8 2023 $4,631 20
15261 Bitumen - Spray Seal Footpath Surface Type
Left footpath - Dean Street (Angaston) from Schilling Street to Sturt Street
(middle section)
ANGASTON Schilling Street to Sturt Street (middle section)
8 2023 $6,034 33
16209 Bitumen - Spray Seal Footpath Surface Type
Left footpath - El Alamein Road (Nuriootpa) from Buna Terrace to end
NURIOOTPA Buna Terrace to end 8 2023 $1,497 20
15493 Bitumen - Spray Seal Footpath Surface Type
Left footpath - Elizabeth Avenue (Nuriootpa) from Phillip Street start of
bitumen
NURIOOTPA Phillip Street start of bitumen 8 2023 $3,256 32
16046 Bitumen - Spray Seal Footpath Surface Type
Left footpath - George Street (Williamstown) from Eliza Street to
Victoria Terrace
WILLIAMSTOWN Eliza Street to Victoria Terrace 8 2023 $2,863 30
- 120 -
THE BAROSSA COUNCIL – TRANSPORT INFRASTRUCTURE ASSET MANAGEMENT PLAN
16116 Bitumen - Spray Seal Footpath Surface Type
Left footpath - George Street (Williamstown) from Queen Street to Eliza
Street
WILLIAMSTOWN Queen Street to Eliza Street 8 2023 $3,957 22
15505 Bitumen - Spray Seal Footpath Surface Type
Left footpath - Greenock Road (Nuriootpa) from Hatch Street to Fifth Street
NURIOOTPA Hatch Street to Fifth Street 8 2023 $10,384 29
16204 Bitumen - Spray Seal Footpath Surface Type
Left footpath - Kleinig Street (Lyndoch) from Gilbert Street end
LYNDOCH Gilbert Street end 8 2023 $926 18
16184 Bitumen - Spray Seal Footpath Surface Type
Left footpath - Margaret Street (Lyndoch) from Gordon Street to John Street
LYNDOCH Gordon Street to John Street 8 2023 $1,055 23
16185 Bitumen - Spray Seal Footpath Surface Type
Left footpath - Margaret Street (Lyndoch) from John Street to end
LYNDOCH John Street to end 8 2023 $47,303 23
16305 Bitumen - Spray Seal Footpath Surface Type
Left footpath - Murray Street (Eden Valley) from William Street to Matthews Road
EDEN VALLEY William Street to Matthews Road 8 2023 $2,722 24
16169 Bitumen - Spray Seal Footpath Surface Type
Left footpath - Noske Street (Lyndoch) from Lyndoch Valley Road
LYNDOCH Lyndoch Valley Road 8 2023 $3,171 35
16038 Bitumen - Spray Seal Footpath Surface Type
Left footpath - Queen Street (Williamstown) from to Margaret Street &
Yettie Road intersection
WILLIAMSTOWN to Margaret Street & Yettie Road intersection
8 2023 $11,226 23
15990 Bitumen - Spray Seal Footpath Surface Type
Left footpath - Saleyard Road (Mount Pleasant) from Melrose Street to
Showground Road
MOUNT PLEASANT Melrose Street to Showground Road 8 2023 $4,911 38
15646 Bitumen - Spray Seal Footpath Surface Type
Left footpath - South Terrace (Nuriootpa) from The Crescent start of bitumen to end
of bitumen
NURIOOTPA The Crescent start of bitumen to end of bitumen
8 2023 $4,378 30
15292 Bitumen - Spray Seal Footpath Surface Type
Left footpath - Third Street (Nuriootpa) from First Street to Old Kapunda Road
NURIOOTPA First Street to Old Kapunda Road 8 2023 $8,588 29
15306 Bitumen - Spray Seal Footpath Surface Type
Left footpath - Third Street (Nuriootpa) from Gawler Street to First Street
NURIOOTPA Gawler Street to First Street 8 2023 $6,876 29
16252 Bitumen - Spray Seal Footpath Surface Type
Left footpath - William Street (Lyndoch) from Gilbert Street to Lindsay Court
LYNDOCH Gilbert Street to Lindsay Court 8 2023 $1,796 34
16233 Bitumen - Spray Seal Footpath Surface Type
Left footpath - Yettie Road (Williamstown) from Johnson Street to Adams Road
WILLIAMSTOWN Johnson Street to Adams Road 8 2023 $41,910 33
16225 Bitumen - Spray Seal Footpath Surface Type
Right footpath - Barossa Valley Way (Tanunda) from Seppeltsfield Road to
Burrings Road
Tanunda Seppeltsfield Road to Burrings Road 8 2023 $64,591 9
15298 Bitumen - Spray Seal Footpath Surface Type
Right footpath - First Street (Nuriootpa) from Third Street to Fourth Street
NURIOOTPA Third Street to Fourth Street 8 2023 $4,041 29
16175 Bitumen - Spray Seal Footpath Surface Type
Right footpath - Gilbert Street (Lyndoch) from Colonel Light Drive to Lord Lynedoch
Street
LYNDOCH Colonel Light Drive to Lord Lynedoch Street
8 2023 $7,484 30
16097 Bitumen - Spray Seal Footpath Surface Type
Right footpath - Gilbert Street (Lyndoch) from John Street to railway crossing
LYNDOCH John Street to railway crossing 8 2023 $3,929 18
16101 Bitumen - Spray Seal Footpath Surface Type
Right footpath - Gilbert Street (Lyndoch) from Robert Street to William Street
LYNDOCH Robert Street to William Street 8 2023 $4,865 18
15609 Bitumen - Spray Seal Footpath Surface Type
Right footpath - Julius Street (Tanunda) from Murray Street to Wiliam Street
TANUNDA Murray Street to Wiliam Street 8 2023 $842 30
16231 Bitumen - Spray Seal Footpath Surface Type
Right footpath - Lyndoch Valley Road (Lyndoch) from Railway line foot bridge
LYNDOCH Railway line foot bridge 8 2023 $842 42
15742 Bitumen - Spray Seal Footpath Surface Type
Right footpath - Magnolia Street (Tanunda) from Murray Street to end
bitumen footpath
TANUNDA Murray Street to end bitumen footpath 8 2023 $7,578 30
- 121 -
THE BAROSSA COUNCIL – TRANSPORT INFRASTRUCTURE ASSET MANAGEMENT PLAN
15937 Bitumen - Spray Seal Footpath Surface Type
Right footpath - Miller Street (Springton) from Johannes Street to Williamstown
Road
SPRINGTON Johannes Street to Williamstown Road 8 2023 $1,544 23
43078 Bitumen - Spray Seal Footpath Surface Type
Right Footpath - Muecke Court, (Tanunda) From MacDonnell Street to Edward Street
TANUNDA From MacDonnell Street To Edward Street 8 2023 $1,372 12
15265 Bitumen - Spray Seal Footpath Surface Type
Right footpath - Murray Street (Nuriootpa) from Old Sturt Highway to Chardonnay
Drive
NURIOOTPA Old Sturt Highway to Chardonnay Drive 8 2023 $12,629 21
15858 Bitumen - Spray Seal Footpath Surface Type
Right footpath - Murray Street (Tanunda) from Barossa Valley Highway end of rubble
TANUNDA Barossa Valley Highway end of rubble 8 2023 $9,591 22
15861 Bitumen - Spray Seal Footpath Surface Type
Right footpath - Murray Street (Tanunda) from end rubble to Fiedler Street
TANUNDA end rubble to Fiedler Street 8 2023 $2,666 15
15804 Bitumen - Spray Seal Footpath Surface Type
Right footpath - Murray Street (Tanunda) from Hobbs Street to Petras Street
TANUNDA Hobbs Street to Petras Street 8 2023 $2,470 22
16168 Bitumen - Spray Seal Footpath Surface Type
Right footpath - Noske Street (Lyndoch) from off Lyndoch Valley Road
LYNDOCH off Lyndoch Valley Road 8 2023 $3,171 35
16272 Bitumen - Spray Seal Footpath Surface Type
Right footpath - Research Road (Tanunda) from corner Magnolia Road
TANUNDA corner Magnolia Road 8 2023 $3,181 19
15134 Bitumen - Spray Seal Footpath Surface Type
Right footpath - Schilling Street (Angaston) from Murray Street to end bitumen
ANGASTON Murray Street to end bitumen 8 2023 $1,646 24
15956 Natural Footpath Surface Type Right footpath - College Street (Tanunda) from Murray Street to Bilyara Street
TANUNDA Murray Street to Bilyara Street 8 2023 $0 20
8624 Rural Heavy Use Spray Seal Bitumen Surface
Dispose - Surface - Light Pass Road (0105) from Surface change-Spray Sealed to
Magnolia Road
Surface change-Spray Sealed
Magnolia Road 8 2023 $0 22
8662 Rural Heavy Use Spray Seal Bitumen Surface
Surface - Hurns Road (0010) from Radford Road to Long Gully Road
Radford Road Long Gully Road 8 2023 $94,318 22
9190 Rural Sheeted Surface Function Priority 5,4
Surface - Nitschke Road (0010) from Koch Road to Koch Road + 600m
Koch Road Koch Road + 600m 8 2023 $18,324 20
32576 Rural Sheeted Surface Function Priority 5,4
Surface - Nitschke Road (0011) from Koch Road + 600m to end
Koch Road + 600m End 8 2023 $11,453 13
9407 Rural Sheeted Surface Function Priority 7 Surface - McCallum Road (0005) from Kalbeeba Road to Kalperri Road
Kalbeeba Road Kalperri Road 8 2023 $58,261 13
Subtotal $483,428
16314 Bitumen - Spray Seal Footpath Surface Type
Right footpath - Barossa Valley Way (Nuriootpa) from Kaiser Stuhl Avenue to
Nuraip Road
Nuriootpa Kaiser Stuhl Avenue to Nuraip Road 9 2024 $36,994 2
16315 Bitumen - Spray Seal Footpath Surface Type
Right footpath - Barossa Valley Way (Nuriootpa) from Nuraip Road to
Seppeltsfield Road
Nuriootpa Nuraip Road to Seppeltsfield Road 9 2024 $63,656 2
32531 Rural Heavy Use Spray Seal Bitumen Surface
Disposed - Surface - Burings Road (0006) from 356m from End to Barossa Valley
Highway
356m from end Barossa Valley Highway 9 2024 $0 22
8660 Rural Heavy Use Spray Seal Bitumen Surface
Disposed - Surface - Hurns Road (0005) from Eden Valley Road to Radford Road
Eden Valley Road Radford Road 9 2024 $0 22
8801 Rural Normal Use Spray Seal Bitumen Surface
Dipsosed - Surface - Balmoral Road - Kalbeeba (0005) from Calton Road to John
Schultz Court
Calton Road John Schultz Court 9 2024 $0 25
- 122 -
THE BAROSSA COUNCIL – TRANSPORT INFRASTRUCTURE ASSET MANAGEMENT PLAN
8816 Rural Normal Use Spray Seal Bitumen Surface
Disposed - Surface - Balmoral Road - Kalbeeba (0010) from John Schultz Court
to Road No-0788
John Schultz Court Road No-0788 9 2024 $0 25
32554 Rural Normal Use Spray Seal Bitumen Surface
Disposed - Surface - Balmoral Road - Kalbeeba (0015) from Road No-0788 to
Lucks Road
Road No-0788 Lucks Road 9 2024 $0 25
8796 Rural Normal Use Spray Seal Bitumen Surface
Disposed - Surface - Balmoral Road - Kalbeeba (0020) from Lucks Road to
Allendale Road
Lucks Road Allendale Road 9 2024 $0 25
8803 Rural Normal Use Spray Seal Bitumen Surface
Disposed - Surface - Balmoral Road - Kalbeeba (0025) from Allendale Road to
Devon Road
Allendale Road Devon Road 9 2024 $0 25
8792 Rural Normal Use Spray Seal Bitumen Surface
Disposed - Surface - Balmoral Road - Kalbeeba (0030) from Devon Road to
Kalbeeba Road
Devon Road Kalbeeba Road 9 2024 $0 25
9545 Rural Sheeted Surface Function Priority 2,1
Surface - Elder Road (0010) from Cromer Road to End - 0.306km
Cromer Road End - 0.306km 9 2024 $4,748 21
9458 Rural Sheeted Surface Function Priority 5,4
Surface - Allendale Road (0030) from Segment limit to Para Wirra Road
Segment limit Para Wirra Road 9 2024 $42,226 22
9431 Rural Sheeted Surface Function Priority 5,4
Surface - Lucks Road (0005) from Calton Road to Meadow Road
Calton Road Meadow Road 9 2024 $14,197 16
9397 Rural Sheeted Surface Function Priority 7 Surface - McCallum Road (0015) from William Hawke Road to Winton Road
William Hawke Road Winton Road 9 2024 $18,315 20
6752 Township Normal Use Spray Seal Bitumen Surface
Surface - Rowland Street (0005) from Penrice Road to Sarah Street
Penrice Road Sarah Street 9 2024 $2,972 4
Subtotal $183,109
Program Total $9,733,378
- 123 -
THE BAROSSA COUNCIL – TRANSPORT INFRASTRUCTURE ASSET MANAGEMENT PLAN
Appendix C Budgeted Expenditures Accommodated in LTFP
Barossa - Report 7 - LTFP Expenditure Projections
Projected Expenditure 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024
Capital Expenditure on
Renewal/Replacement of existing
assets
$5,529 $1,090 $8 $982 $352 $382 $163 $561 $483 $183
Capital Expenditure on
Upgrade/New assets
$1,033 $1,389 $196 $204 $215 $221 $228 $236 $243 $252
Operational cost of existing assets $1,880 $1,880 $1,880 $1,880 $1,880 $1,880 $1,880 $1,880 $1,880 $1,880
Maintenance cost of existing assets $1,262 $1,324 $1,324 $1,324 $1,324 $1,324 $1,324 $1,324 $1,324 $1,324
Operational cost of New assets $0 $12 $27 $30 $34 $38 $42 $46 $50 $54
Maintenance cost of New assets $0 $8 $19 $21 $24 $27 $30 $33 $35 $38
All dollar values in ($'000)'s
- 124 -
THE BAROSSA COUNCIL – TRANSPORT INFRASTRUCTURE ASSET MANAGEMENT PLAN
- 125 -
THE BAROSSA COUNCIL – TRANSPORT INFRASTRUCTURE ASSET MANAGEMENT PLAN
Appendix D State of The Assets
- 126 -
THE BAROSSA COUNCIL – TRANSPORT INFRASTRUCTURE ASSET MANAGEMENT PLAN
Appendix E Abbreviations
AAAC Average annual asset consumption
AM Asset management
Asset
Management
Plan
Asset management plan
ARI Average recurrence interval
ASC Annual service cost
BOD Biochemical (biological) oxygen demand
CRC Current replacement cost
CWMS Community wastewater management systems
DA Depreciable amount
DRC Depreciated replacement cost
EF Earthworks/formation
IRMP Infrastructure Risk Management Plan
LCC Life Cycle cost
LCE Life cycle expenditure
LTFP Long Term Financial Plan
MMS Maintenance management system
PCI Pavement condition index
RV Residual value
SoA State of the Assets
SS Suspended solids
vph Vehicles per hour
WDCRC Written down current replacement cost
OTR Office of the Technical Regulator
ESCOSA Essential Services Commission of South Australia
- 127 -
THE BAROSSA COUNCIL – TRANSPORT INFRASTRUCTURE ASSET MANAGEMENT PLAN
OMG Organisation Managers Group
DPTI Department of Planning, Transport and Infrastructure
SAPN SA Power Networks
AASB Australian Accounting Standards Board
SALGAG South Australian Local Government Auditors Group
SALGFMG
South Australian Local Government Financial Managers
Group
LL1 Long life Component 1
LL2 Long Life Component 2
- 128 -
THE BAROSSA COUNCIL – TRANSPORT INFRASTRUCTURE ASSET MANAGEMENT PLAN
Appendix F Glossary
Annual service cost (ASC)
Reporting actual cost
The annual (accrual) cost of providing
a service including operations,
maintenance, depreciation, finance /
opportunity and disposal costs less
revenue.
For investment analysis and budgeting
An estimate of the cost that would be
tendered, per annum, if tenders were
called for the supply of a service to a
performance specification for a fixed
term. The Annual Service Cost
includes operations, maintenance,
depreciation, finance / opportunity
and disposal costs, less revenue.
Asset
A resource controlled by an entity as a
result of past events and from which
future economic benefits are
expected to flow to the entity.
Infrastructure assets are a sub-class of
property, plant and equipment which
are non-current assets with a life
greater than 12 months and enable
services to be provided.
Asset category
Sub-group of assets within a class
hierarchy for financial reporting and
management purposes.
Asset class
A group of assets having a similar
nature or function in the operations of
an entity, and which, for purposes of
disclosure, is shown as a single item
without supplementary disclosure.
Asset condition assessment
The process of continuous or periodic
inspection, assessment, measurement
and interpretation of the resultant
data to indicate the condition of a
specific asset so as to determine the
need for some preventative or
remedial action.
Asset hierarchy
A framework for segmenting an asset
base into appropriate classifications.
The asset hierarchy can be based on
asset function or asset type or a
combination of the two.
Asset management (AM)
The combination of management,
financial, economic, engineering and
other practices applied to physical
assets with the objective of providing
the required level of service in the most
cost effective manner.
Asset renewal funding ratio
The ratio of the net present value of
asset renewal funding
accommodated over a 10 year period
in a Long Term Financial Plan relative
to the net present value of projected
capital renewal expenditures identified
in an asset management plan for the
same period [AIFMG Financial
Sustainability Indicator No 8].
Average annual asset consumption
(AAAC)*
The amount of an organisation’s asset
base consumed during a reporting
period (generally a year). This may be
calculated by dividing the
depreciable amount by the useful life
(or total future economic
benefits/service potential) and totalled
for each and every asset OR by
dividing the carrying amount
(depreciated replacement cost) by
the remaining useful life (or remaining
future economic benefits/service
potential) and totalled for each and
every asset in an asset category or
class.
Borrowings
A borrowing or loan is a contractual
obligation of the borrowing entity to
deliver cash or another financial asset
to the lending entity over a specified
period of time or at a specified point in
time, to cover both the initial capital
provided and the cost of the interest
incurred for providing this capital. A
borrowing or loan provides the means
for the borrowing entity to finance
outlays (typically physical assets) when
it has insufficient funds of its own to do
so, and for the lending entity to make
a financial return, normally in the form
- 129 -
THE BAROSSA COUNCIL – TRANSPORT INFRASTRUCTURE ASSET MANAGEMENT PLAN
of interest revenue, on the funding
provided.
Capital expenditure
Relatively large (material) expenditure,
which has benefits, expected to last
for more than 12 months. Capital
expenditure includes renewal,
expansion and upgrade. Where
capital projects involve a combination
of renewal, expansion and/or upgrade
expenditures, the total project cost
needs to be allocated accordingly.
Capital expenditure - expansion
Expenditure that extends the capacity
of an existing asset to provide benefits,
at the same standard as is currently
enjoyed by existing beneficiaries, to a
new group of users. It is discretionary
expenditure, which increases future
operations and maintenance costs,
because it increases the organisation’s
asset base, but may be associated
with additional revenue from the new
user group, eg. extending a drainage
or road network, the provision of an
oval or park in a new suburb for new
residents.
Capital expenditure - new
Expenditure which creates a new asset
providing a new service/output that
did not exist beforehand. As it
increases service potential it may
impact revenue and will increase
future operations and maintenance
expenditure.
Capital expenditure - renewal
Expenditure on an existing asset or on
replacing an existing asset, which
returns the service capability of the
asset up to that which it had originally.
It is periodically required expenditure,
relatively large (material) in value
compared with the value of the
components or sub-components of
the asset being renewed. As it
reinstates existing service potential, it
generally has no impact on revenue,
but may reduce future operations and
maintenance expenditure if
completed at the optimum time, eg.
resurfacing or resheeting a material
part of a road network, replacing a
material section of a drainage network
with pipes of the same capacity,
resurfacing an oval.
Capital expenditure - upgrade
Expenditure, which enhances an
existing asset to provide a higher level
of service or expenditure that will
increase the life of the asset beyond
that which it had originally. Upgrade
expenditure is discretionary and often
does not result in additional revenue
unless direct user charges apply. It will
increase operations and maintenance
expenditure in the future because of
the increase in the organisation’s asset
base, eg. widening the sealed area of
an existing road, replacing drainage
pipes with pipes of a greater capacity,
enlarging a grandstand at a sporting
facility.
Capital funding
Funding to pay for capital
expenditure.
Capital grants
Monies received generally tied to the
specific projects for which they are
granted, which are often upgrade
and/or expansion or new investment
proposals.
Capital investment expenditure
See capital expenditure definition
Capitalisation threshold
The value of expenditure on non-
current assets above which the
expenditure is recognised as capital
expenditure and below which the
expenditure is charged as an expense
in the year of acquisition.
Carrying amount
The amount at which an asset is
recognised after deducting any
accumulated depreciation /
amortisation and accumulated
impairment losses thereon.
Class of assets
See asset class definition
Component
Specific parts of an asset having
independent physical or functional
identity and having specific attributes
- 130 -
THE BAROSSA COUNCIL – TRANSPORT INFRASTRUCTURE ASSET MANAGEMENT PLAN
such as different life expectancy,
maintenance regimes, risk or criticality.
Core asset management
Asset management which relies
primarily on the use of an asset register,
maintenance management systems,
job resource management, inventory
control, condition assessment, simple
risk assessment and defined levels of
service, in order to establish alternative
treatment options and long-term
cashflow predictions. Priorities are
usually established on the basis of
financial return gained by carrying out
the work (rather than detailed risk
analysis and optimised decision-
making).
Cost of an asset
The amount of cash or cash
equivalents paid or the fair value of
the consideration given to acquire an
asset at the time of its acquisition or
construction, including any costs
necessary to place the asset into
service. This includes one-off design
and project management costs.
Critical assets
Assets for which the financial, business
or service level consequences of
failure are sufficiently severe to justify
proactive inspection and
rehabilitation. Critical assets have a
lower threshold for action than non-
critical assets.
Current replacement cost (CRC)
The cost the entity would incur to
acquire the asset on the reporting
date. The cost is measured by
reference to the lowest cost at which
the gross future economic benefits
could be obtained in the normal
course of business or the minimum it
would cost, to replace the existing
asset with a technologically modern
equivalent new asset (not a second
hand one) with the same economic
benefits (gross service potential)
allowing for any differences in the
quantity and quality of output and in
operating costs.
Deferred maintenance
The shortfall in rehabilitation work
undertaken relative to that required to
maintain the service potential of an
asset.
Depreciable amount
The cost of an asset, or other amount
substituted for its cost, less its residual
value.
Depreciated replacement cost (DRC)
The current replacement cost (CRC) of
an asset less, where applicable,
accumulated depreciation calculated
on the basis of such cost to reflect the
already consumed or expired future
economic benefits of the asset.
Depreciation / amortisation
The systematic allocation of the
depreciable amount (service
potential) of an asset over its useful life.
Economic life
See useful life definition.
Expenditure
The spending of money on goods and
services. Expenditure includes
recurrent and capital outlays.
Expenses
Decreases in economic benefits during
the accounting period in the form of
outflows or depletions of assets or
increases in liabilities that result in
decreases in equity, other than those
relating to distributions to equity participants.
Fair value
The amount for which an asset could
be exchanged, or a liability settled,
between knowledgeable, willing
parties, in an arms length transaction.
Financing gap
A financing gap exists whenever an
entity has insufficient capacity to
finance asset renewal and other
expenditure necessary to be able to
appropriately maintain the range and
level of services its existing asset stock
was originally designed and intended
to deliver. The service capability of the
existing asset stock should be
determined assuming no additional
- 131 -
THE BAROSSA COUNCIL – TRANSPORT INFRASTRUCTURE ASSET MANAGEMENT PLAN
operating revenue, productivity
improvements, or net financial liabilities
above levels currently planned or
projected. A current financing gap
means service levels have already or
are currently falling. A projected
financing gap if not addressed will
result in a future diminution of existing
service levels.
Heritage asset
An asset with historic, artistic, scientific,
technological, geographical or
environmental qualities that is held
and maintained principally for its
contribution to knowledge and culture
and this purpose is central to the
objectives of the entity holding it.
Impairment Loss
The amount by which the carrying
amount of an asset exceeds its
recoverable amount.
Infrastructure assets
Physical assets that contribute to
meeting the needs of organisations or
the need for access to major
economic and social facilities and
services, eg. roads, drainage,
footpaths and cycleways. These are
typically large, interconnected
networks or portfolios of composite
assets. The components of these
assets may be separately maintained,
renewed or replaced individually so
that the required level and standard of
service from the network of assets is
continuously sustained. Generally the
components and hence the assets
have long lives. They are fixed in place
and are often have no separate
market value.
Investment property
Property held to earn rentals or for
capital appreciation or both, rather
than for:
(a) use in the production or supply of
goods or services or for
administrative purposes; or
(b) sale in the ordinary course of
business.
Key performance indicator
A qualitative or quantitative measure
of a service or activity used to
compare actual performance against
a standard or other target.
Performance indicators commonly
relate to statutory limits, safety,
responsiveness, cost, comfort, asset
performance, reliability, efficiency,
environmental protection and
customer satisfaction.
Level of service
The defined service quality for a
particular service/activity against
which service performance may be
measured. Service levels usually relate
to quality, quantity, reliability,
responsiveness, environmental impact,
acceptability and cost.
Life Cycle Cost *
1. Total LCC The total cost of an asset
throughout its life including
planning, design, construction,
acquisition, operation,
maintenance, rehabilitation and
disposal costs.
2. Average LCC The life cycle cost
(LCC) is average cost to provide
the service over the longest asset
life cycle. It comprises average
operations, maintenance
expenditure plus asset
consumption expense, represented
by depreciation expense
projected over 10 years. The Life
Cycle Cost does not indicate the
funds required to provide the
service in a particular year.
Life Cycle Expenditure
The Life Cycle Expenditure (LCE) is the
average operations, maintenance
and capital renewal expenditure
accommodated in the Long Term
Financial Plan over 10 years. Life Cycle
Expenditure may be compared to
average Life Cycle Cost to give an
initial indicator of affordability of
projected service levels when considered with asset age profiles.
Loans / borrowings
See borrowings.
- 132 -
THE BAROSSA COUNCIL – TRANSPORT INFRASTRUCTURE ASSET MANAGEMENT PLAN
Maintenance
All actions necessary for retaining an
asset as near as practicable to an
appropriate service condition,
including regular ongoing day-to-day
work necessary to keep assets
operating, eg road patching but
excluding rehabilitation or renewal. It is
operating expenditure required to
ensure that the asset reaches its
expected useful life.
• Planned maintenance
Repair work that is identified and
managed through a maintenance
management system (MMS). MMS
activities include inspection,
assessing the condition against
failure/breakdown
criteria/experience, prioritising
scheduling, actioning the work and
reporting what was done to
develop a maintenance history
and improve maintenance and
service delivery performance.
• Reactive maintenance
Unplanned repair work that is
carried out in response to service
requests and management/
supervisory directions.
• Specific maintenance
Maintenance work to repair
components or replace sub-
components that needs to be
identified as a specific
maintenance item in the
maintenance budget.
• Unplanned maintenance
Corrective work required in the
short-term to restore an asset to
working condition so it can
continue to deliver the required
service or to maintain its level of
security and integrity.
Maintenance expenditure *
Recurrent expenditure, which is
periodically or regularly required as
part of the anticipated schedule of
works required to ensure that the asset
achieves its useful life and provides the
required level of service. It is
expenditure, which was anticipated in
determining the asset’s useful life.
Materiality
The notion of materiality guides the
margin of error acceptable, the
degree of precision required and the
extent of the disclosure required when
preparing general purpose financial
reports. Information is material if its
omission, misstatement or non-
disclosure has the potential,
individually or collectively, to influence
the economic decisions of users taken
on the basis of the financial report or
affect the discharge of accountability
by the management or governing
body of the entity.
Modern equivalent asset
Assets that replicate what is in
existence with the most cost-effective
asset performing the same level of
service. It is the most cost efficient,
currently available asset which will
provide the same stream of services as
the existing asset is capable of
producing. It allows for technology
changes and, improvements and
efficiencies in production and
installation techniques
Net present value (NPV)
The value to the organisation of the
cash flows associated with an asset,
liability, activity or event calculated
using a discount rate to reflect the
time value of money. It is the net
amount of discounted total cash
inflows after deducting the value of
the discounted total cash outflows
arising from eg the continued use and
subsequent disposal of the asset after
deducting the value of the discounted
total cash outflows.
Non-revenue generating investments
Investments for the provision of goods
and services to sustain or improve
services to the community that are not
expected to generate any savings or
revenue to the Council, eg. parks and
playgrounds, footpaths, roads and
bridges, libraries, etc.
Operations
Regular activities to provide services
such as public health, safety and
amenity, eg street sweeping, grass
mowing and street lighting.
- 133 -
THE BAROSSA COUNCIL – TRANSPORT INFRASTRUCTURE ASSET MANAGEMENT PLAN
Operating expenditure
Recurrent expenditure, which is
continuously required to provide a
service. In common use the term
typically includes, eg power, fuel, staff,
plant equipment, on-costs and
overheads but excludes maintenance
and depreciation. Maintenance and
depreciation is on the other hand
included in operating expenses.
Operating expense
The gross outflow of economic
benefits, being cash and non cash
items, during the period arising in the
course of ordinary activities of an
entity when those outflows result in
decreases in equity, other than
decreases relating to distributions to
equity participants.
Operating expenses
Recurrent expenses continuously
required to provide a service, including
power, fuel, staff, plant equipment,
maintenance, depreciation, on-costs
and overheads.
Operations, maintenance and renewal
financing ratio
Ratio of estimated budget to
projected expenditure for operations,
maintenance and renewal of assets
over a defined time (eg 5, 10 and 15
years).
Operations, maintenance and renewal
gap
Difference between budgeted
expenditures in a Long Term Financial
Plan (or estimated future budgets in
absence of a Long Term Financial
Plan) and projected expenditures for
operations, maintenance and renewal
of assets to achieve/maintain
specified service levels, totalled over a
defined time (e.g. 5, 10 and 15 years).
Pavement management system (PMS)
A systematic process for measuring
and predicting the condition of road
pavements and wearing surfaces over
time and recommending corrective
actions.
PMS Score
A measure of condition of a road
segment determined from a Pavement
Management System.
Rate of annual asset consumption *
The ratio of annual asset consumption
relative to the depreciable amount of
the assets. It measures the amount of
the consumable parts of assets that
are consumed in a period
(depreciation) expressed as a
percentage of the depreciable
amount.
Rate of annual asset renewal *
The ratio of asset renewal and
replacement expenditure relative to
depreciable amount for a period. It
measures whether assets are being
replaced at the rate they are wearing
out with capital renewal expenditure
expressed as a percentage of
depreciable amount (capital renewal
expenditure/DA).
Rate of annual asset upgrade/new *
A measure of the rate at which assets
are being upgraded and expanded
per annum with capital upgrade/new
expenditure expressed as a
percentage of depreciable amount
(capital upgrade/expansion
expenditure/DA).
Recoverable amount
The higher of an asset's fair value, less
costs to sell and its value in use.
Recurrent expenditure
Relatively small (immaterial)
expenditure or that which has benefits
expected to last less than 12 months.
Recurrent expenditure includes
operations and maintenance
expenditure.
Recurrent funding
Funding to pay for recurrent
expenditure.
Rehabilitation
See capital renewal expenditure
definition above.
- 134 -
THE BAROSSA COUNCIL – TRANSPORT INFRASTRUCTURE ASSET MANAGEMENT PLAN
Remaining useful life
The time remaining until an asset
ceases to provide the required service
level or economic usefulness. Age plus
remaining useful life is useful life.
Renewal
See capital renewal expenditure
definition above.
Residual value
The estimated amount that an entity
would currently obtain from disposal of
the asset, after deducting the
estimated costs of disposal, if the asset
were already of the age and in the
condition expected at the end of its
useful life.
Revenue generating investments
Investments for the provision of goods
and services to sustain or improve
services to the community that are
expected to generate some savings or
revenue to offset operating costs, eg
public halls and theatres, childcare
centres, sporting and recreation
facilities, tourist information centres,
etc.
Risk management
The application of a formal process to
the range of possible values relating to
key factors associated with a risk in
order to determine the resultant
ranges of outcomes and their
probability of occurrence.
Section or segment
A self-contained part or piece of an
infrastructure asset.
Service potential
The total future service capacity of an
asset. It is normally determined by
reference to the operating capacity
and economic life of an asset. A
measure of service potential is used in
the not-for-profit sector/public sector
to value assets, particularly those not
producing a cash flow.
Service potential remaining
A measure of the future economic
benefits remaining in assets. It may be
expressed in dollar values (Fair Value)
or as a percentage of total
anticipated future economic benefits.
It is also a measure of the percentage
of the asset’s potential to provide
services that is still available for use in
providing services (Depreciated
Replacement Cost/Depreciable
Amount).
Specific Maintenance
Replacement of higher value
components/sub-components of
assets that is undertaken on a regular
cycle including repainting,
replacement of air conditioning
equipment, etc. This work generally
falls below the capital/ maintenance
threshold and needs to be identified in
a specific maintenance budget
allocation.
Strategic Longer-Term Plan
A plan covering the term of office of
councillors (4 years minimum)
reflecting the needs of the community
for the foreseeable future. It brings
together the detailed requirements in
the Council’s longer-term plans such
as the asset management plan and
the long-term financial plan. The plan
is prepared in consultation with the
community and details where the
Council is at that point in time, where it
wants to go, how it is going to get
there, mechanisms for monitoring the
achievement of the outcomes and
how the plan will be resourced.
Sub-component
Smaller individual parts that make up a
component part.
Useful life
Either:
(a) the period over which an asset is
expected to be available for use by
an entity, or
(b) the number of production or similar
units expected to be obtained from
the asset by the entity.
It is estimated or expected time
between placing the asset into service
and removing it from service, or the
estimated period of time over which
the future economic benefits
embodied in a depreciable asset, are
- 135 -
THE BAROSSA COUNCIL – TRANSPORT INFRASTRUCTURE ASSET MANAGEMENT PLAN
expected to be consumed by the
Council.
Value in Use
The present value of future cash flows
expected to be derived from an asset
or cash generating unit. It is deemed
to be depreciated replacement cost
(DRC) for those assets whose future
economic benefits are not primarily
dependent on the asset's ability to
generate net cash inflows, where the
entity would, if deprived of the asset,
replace its remaining future economic
benefits.
Source: IPWEA, 2009, Glossary
Additional and modified glossary items
shown *