LIST OF INFRASTRUCTURE PROJECTS CY 2010-2011
TYPE OF PROJECT: CONSTRUCTION OF COVERED COURT IMPLEMENTING PROCEDURE: BY ADMINISTRATION
IMPLEMENTING AGENCY: PROVINCIAL GOV’T OF MAGUINDANAO
IMPLEMENTING AGENCY: 20m X 30m
PROJECT
LOCATION
PROJECT
COST
IMPLEMENTING DATE
PERCENTAGE
ACCOM-
PLISHED
REMARKS
START
ACCOM-
PLISHED
1 Buluan 3,900,000.00 Feb.7,2011 On going- 47.83%
2 South Upi 4,200,000.00 Feb.7,2011 April 2011 100% COMPLETED
3 Datu Odin
Sinsuat
3,900,000.00 Feb.7,2011 June 2011 100% COMPLETED
4 Datu Blah
Sinsuat
3,900,000.00 Feb.7,2011 June 2011 100% COMPLETED
5 Datu Paglas 3,900,000.00 Feb.7,2011 April 2011 100% COMPLETED
6 Gen. SKP 3,900,000.00 Mar 10,2011 On going- 74.72%
7 Datu
Montawal
4,000,000.00 Mar 10,2011 On going- 11.25%
8 Parang 4,000,000.00 Apr 11,2011 On going- 84.82%
9 Guindulunga
n
4,200,000.00 Mar 10,2011 On going- 46.16%
10 Sultan sa
Barongis
4,200,000.00 Mar 10,2011 On going- 23.08%
11 Pandag 3,900,000.00 Feb.7,2011 On going- 84.82%
12 Mangudadatu 3,900,000.00 Feb.7,2011 On going- 31.84%
13 Ampatuan 3,900,000.00 Feb.7,2011 On going- 31.84%
4
GUINDULUNGAN, MAGUINDANAO DATU ODIN SINSUAT, MAGUINDANAO
COVERED COURT AT PANDAG,
MAGUINDANAO
SOUTH UPI, MAGUINDANAO
COVERED COURT AT DATU MONTAWAL,
MAGUINDANAO
COVERED COURT AT BULUAN,
MAGUINDANAO
5
COVERED COURT AT PARANG,
MAGUINDANAO
COVERED COURT AT SSB, MAGUINDANAO
COVERED COURT AT GEN. SKP,
MAGUINDANAO
6
LIST OF INFRASTRUCTURE PROJECTS CY 2010-2011
TYPE OF PROJECT: MULTI-PURPOSE BUILDING IMPLEMENTING PROCEDURE: BY ADMINISTRATION IMPLEMENTING AGENCY: PROVINCIAL GOVERNMENT OF
MAGUINDANAO
PROJECT
TITLE
PROJECT
LOCATION DIMENSION
PROJECT
COST
IMPLEMENTING
DATE
#
ACCOM-
PLISHED
REMARKS
START ACCOM-
PLISHED
1 Const. of
Eight (8)
Units
Prov'l.
Satellite
Office
Buluan 7.0m x 30m 3,500000.0
0
Jun.
15,
2010
Dec.
2010
100% COMPLE
TED
2 Constructi
on of Four
(4) Units
Comfort
Rooms
Buluan 4.0m x 10m 1283596.2
6
Jun.
15,
2010
Dec.
2010
100% COMPLE
TED
3 Constructi
on of
Multi-
purpose
Bldg. -
Shrine
Hall
Buluan - 939,947.20 Oct.
20,201
0
On
going-
COMPLE
TED
4 Repair of
Comelec
Office
Buluan - 189,,408.7
5
Oct.
2010
Nov.
2010
100% COMPLE
TED
5 Renovatio
n of Rural
Health
Unit
Building
Buluan - 728,227.51 Nov.
27,
2010
Jan.
2011
100% COMPLE
TED
6 Const. of
Rajah
Buayan -
Silongan
Peace
Center
Buluan - 4,500,000.
00
Dec. 5,
2010
On
going-
7 Constructi
on of
Training
Center
Buluan - 3,000,000.
00
Jan.13,
2011
On
going-
8 Constructi
on of
Paglat - 1,170,000.
00
Feb.10,
2011
On
going-
90.83
7
Justice
Hall
9 Constructi
on of
open
Shade at
Gov.
Office
Buluan -
400,000.00
Jun 15,
2010
Jul.
2011
100% COMPLE
TED
10 Constructi
on of
Justice
Hall
Buluan
- 1,170,000.
00
Feb.10,
2011
On
going-
90.83
COMMELEC OFFICE AT BULUAN, MAGUINDANAO
COMFORT ROOM AT BULUAN, MAGUINDANAO
TRAINING CENTER AT BULUAN,
MAGUINDANA
8
MULTI-PUPOSE BUILDING AT BULUAN,
MAGUINDANAO
JUSTICE HALL AT DATU PAGLAS,
MAGUINDANAO
PEACE CENTER AT BULUAN,
MAGUINDANAO
OPEN SHADE AT GOVERNOR'S OFFICE,
BULUAN MAGUINDANAO
9
LIST OF INFRASTRUCTURE PROJECTS CY 2010-2011
TYPE OF PROJECT: FARM TO MARKET ROAD (FMR) IMPLEMENTING PROCEDURE: BY ADMINISTRATION
IMPLEMENTING AGENCY: PROVINCIAL GOV’T OF MAGUINDANAO
PROJECT
TITLE
PROJECT
LOCATION
DIMEN-
SION
PROJECT
COST
IMPLEMENTING DATE
#
ACCOM-
PLISHED
REMARKS
DATE START DATE
ACCOMP-LISHED
1 Repair of
Mapayag
Farm to
Market
Road
Talitay 6.50 6, 430,
000.00
June 20,
2010
100% COMPLETED
2 Repair of
Tumbao -
Talitay
Farm to
Market
Road
Mangudad
atu
7.50 6, 650,
000.00
July 26,
2010
100% COMPLETED
3 Repair of
Buluan
Farm to
Market
Road
Buluan 9.50 8, 990,
000.00
July 27,
2010
100% COMPLETED
4 Repair of
Paitan -
Banaba
Farm to
Market
Road
Datu
Abdullah
Sangki
3.80 3, 300,
000.00
Aug. 28,
2010
100% COMPLETED
5 Repair of
Satan
Farm to
Market
Road
Datu
Unsay
1.50
1, 300,
000.00
Sept. 18,
2010
100% COMPLETED
6 Reapir of
Pandag
Farm to
Market
Road
Pandag 1.00 1, 000,
000.00
Oct. 11,
2010
100% COMPLETED
7 Repair of
Salman
Farm to
Market
Road
Ampatuan 3.60 4, 500,
000.00
Oct. 18,
2010
100% COMPLETED
8 Constructi
on of
Bagan-
Guindu-
lungan
7.00 4, 166,
000.00
Dec. 21,
2010
100% COMPLETED
10
Kateman
FMR
9 Repair of
Badak -
Makainis
Farm to
Market
Road
GEN. SKP 3.00 3, 000,
000.00
Sept. 2010 100% COMPLETED
10 Repair of
Tumaginti
ng -
Indatuan
FMR
Northern
Kabunta-
lan
3.40 5, 000,
000.00
Sept. 2010 100% COMPLETED
11 Repair of
South Upi
FMR
South UPI 3.40 2, 500,
000.00
Sept. 2010 100% COMPLETED
12 Repair of
Lao-Lao -
Panosolen
FMR
GEN. SKP 3.125 3, 000,
000.00
Sept. 2010 100% COMPLETED
13 Repair of
Pandag
Farm to
Market
Road
Pandag 3.50 3, 400,
000.00
Sept. 2010 100% COMPLETED
14 Repair of
South Upi
Farm tyo
Market
Road
South Upi 3.80 3, 800,
000.00
Sept. 2010 100% COMPLETED
15 Const. of
Poblacion
Kauran -
Sitio
Tinago
FMR
Ampatuan 0.834 1, 500,
000.00
Sept. 2010 100% COMPLETED
16 Const. of
Poblacion
Kauran -
Kilantan
Spring
FMR
Ampatuan 0.460 700,
000.00
Sept. 2010 100% COMPLETED
11
DINGANEN, BULDON
12
LIST OF INFRASTRUCTURE PROJECTS CY 2010-2011
TYPE OF PROJECT: ROADS IMPLEMENTING PROCEDURE: BY ADMINISTRATION IMPLEMENTING AGENCY: PROVINCIAL GOV’T OF MAGUINDANAO
PROJECT
TITLE
PROJECT
LOCATION
DIM
EN-
SION
PROJECT
COST
IMPLEMENTING
DATE
#
ACCOM-
PLISHED
REMARKS
DATE START
ACCOM-PLISHED
1 Const. of
Initian -
Paitan
Provincial
Road
Mangudadatu 8.00 4, 284, 000.00 July 22,
2010
100% COMPLETED
2 Upgrading
of Alip-
Limpoyon
Provincial
Road
Datu Paglas 8.16 7,400,000.00 Aug. 16,
2010
100% COMPLETED
3 Repair of
Ganta -
Tumbao -
Taviran
Prov'l. Road
Mother
Kabuntalan
3.00
2, 600, 000.00 Sept. 20,
2010
100% COMPLETED
4 Constructio
n of Kalian
Road
Mangudadatu 4.20 4, 100, 000.00 Sept.
2010
100% COMPLETED
5 Repair of
Nuyo -
Dinganen
Provincial
Road
Buldon 6.00 6, 000, 000.00 Sept.
2010
100% COMPLETED
6 Upgrading
of Rancho-
Quirino
Boundary
Road
Mangudadatu 5.10
0
3,800,000.00 Sept.
2010
100% COMPLETED
7 Repair of
Mercedes -
Lamin
Road
Barira 4.50 4, 500, 000.00 Feb.
2011
100% COMPLETED
8 Repair of
Mariga
Lupa Road
Parang 1.50 1, 500, 000.00 Feb.
2011
100% COMPLETED
9 Repair of
Landasan
Road
Parang 1.00 1, 500, 000.00 Feb.
2011
100% COMPLETED
10 Rehabilitati
on of
Parang-
Buldon
Prov'l. Road
Buldon 6.00 6, 000, 000.00 Feb.
2011
100% COMPLETED
13
BRGY. LANDASAN, PARANG
BRGY. LANDASAN, PARANG
14
LIST OF INFRASTRUCTURE PROJECTS CY 2010-2011
TIME OF PROJECT: PERIMETER FENCE AND STRUCTURAL
LANDMARKS IMPLEMENTING PROCEDURE: BY ADMINISTRATION IMPLEMENTING AGENCY: PROVINCIAL GOV’T OF MAGUINDANAO
DIMENSION: 80m X 200m
PROJECT
TITLE
PROJECT
LOCATION
PROJECT
COST
IMPLEMENTING
DATE
#
ACCOMPLI
SHED
REMARKS
START
ACCOMPLISHE
D
1 Const. of
Prov’l
Satellite
Office
Perimeter
Fence
Buluan 3,158,531.
45
Dec. 21,
2010
Dec.
2010
100% COMPLETED
2 Const.
Buluan
Mosque
Perimeter
Fence
Buluan 1,650,000.
00
Jan. 17,
2011
Dec.
2010
100% COMPLETED
3 Const. of
Mun.
Boundary
Structural
Landmark
Datu Saudi
Ampatuan,
Datu
Salibo
1,519,551.
60
Jan. 16,
2011
On
going-
4 Const.
Buluan
Mosque
Perimeter
Fence
Datu Saudi
Ampatuan,
Guindulun
gan
1,519,551.
60
Jan. 16,
2011
On
going-
PERIMETER FENCE AT PROVINCIAL SATELLITE
OFFICE, BULUAN, MAGUINDANAO
PERIMETER FENCE AT BULUAN MOSQUE,
BULUAN MAGUINDANAO
15
LIST OF INFRASTRUCTURE PROJECTS CY 2010-2011 TYPE OF PROJECT: REPAIR OF SCHOOL BUILDING/HOSPITAL & HOUSING
PROJECT IMPLEMENTING PROCEDURE: BY ADMINISTRATION
IMPLEMENTING AGENCY: PROVINCIAL GOVERNMENT OF MAGUINDANAO
PROJECT
TITLE
PROJECT
LOCA-
TION
DIMEN-
SION
PROJECT
COST
IMPLEMENTING
DATE
#
ACCOMP
-LISHED REMARKS
START ACCOM-PLISHED
1 Rerpair of
School
Building
Buluan
National
High
School
- - 100% COMPLETED
2 Repair of
Wooden
Bleacher
Luminpg
Elem.
School
Buluan
- 515,000.00 Jan. 20,
2011
100% COMPLETED
3 Repair of
Erap/Digs
Hospital
Parang - 3,637,059.00 Jan. 16,
2011
100% COMPLETED
4 Const. of
10-Units
Housing
Projects
Datu
Odin
Sinsuat
5m X5m
5 Const. of
10-Units
Housing
Projects
Buldon 5m X5m
6 Const. of
10-Units
Housing
Projects
Pandag 5m X5m
16
REPAIR OF WOODEN BLEACHER, BULUAN,
MAGUINDANAO
HOUSING PROJECTS AT PANDAG,
MAGUINADANAO
HOUSING PROJECT AT DATUODIN SINSUAT,
MAGUINADANAO
HOUSING PROJECTS AT BULUAN,
MAGUINADANAO
17
LIST OF INFRASTRUCTURE PROJECTS CY 2010-2011 TYPE OF PROJECT: STREET LIGHTS
IMPLEMENTING PROCEDURE: BY ADMINISTRATION
IMPLEMENTING AGENCY: PROVINCIAL GOVERNMENT OF MAGUINDANAO
PROJECT
TITLE
PROJECT
LOCATIO
N
PROJECT
COST
IMPLEMENTING
DATE
#
ACCOMP
LISHED
REMARKS
START
ACCOMPLIS
HED
1 Installation
of 20-units
Street Lights
Parang 200,000.0
0
2 Installation
of 20-units
Street Lights
Datu
Paglas
200,000.0
0
3 Installation
of 20-units
Street Lights
Pandag 200,000.0
0
4 Installation
of 20-units
Street Lights
Paglat 200,000.0
0
100% COMPLETED
5 Installation
of 20-units
Street Lights
Sultan
Kudarat
3,381,500
.00
6 Installation
of 20-units
Street Lights
Sultan
Kudarat
93,000.00 Oct.
28,2011
100% COMPLETED