INDUSTRYLINK WorkshopPoznan, 23 May 2005

Ingrid Ciabatti

TECNOTESSILE

EXPERIENCE OF

PROJECT REALISATION

Page 2: INDUSTRYLINK Workshop Poznan, 23 May 2005 Ingrid Ciabatti TECNOTESSILE EXPERIENCE OF PROJECT REALISATION.

INDUSTRYLINK WorkshopPoznan, 23 May 2005

TECNOTESSILE - Ingrid Ciabatti ([email protected])

2

Content of presentation

• Documents needed for the implementation of the project

• Payment and financial statements

• Control of the project budget

• Project meetings

• Project reports

Page 3: INDUSTRYLINK Workshop Poznan, 23 May 2005 Ingrid Ciabatti TECNOTESSILE EXPERIENCE OF PROJECT REALISATION.

INDUSTRYLINK WorkshopPoznan, 23 May 2005

TECNOTESSILE - Ingrid Ciabatti ([email protected])

3

Documents needed for the implementation of the project

Page 4: INDUSTRYLINK Workshop Poznan, 23 May 2005 Ingrid Ciabatti TECNOTESSILE EXPERIENCE OF PROJECT REALISATION.

INDUSTRYLINK WorkshopPoznan, 23 May 2005

TECNOTESSILE - Ingrid Ciabatti ([email protected])

4

The documents you need• A copy of the Contract and its annexes:

– Annex I - Description of Work (DoW)– Annex II – General conditions– Annex IV – Form A – consent of contractors to accede to

the contract– (Annex V – Form B – accession of new legal entities to

the contract)– Annex VI – Form C – financial statement

• A Consortium Agreement (CA)!• Project reporting in FP6 - Guidance notes• FP6 Financial Guidelines

www.cordis.lu(“Find a document”)

Page 5: INDUSTRYLINK Workshop Poznan, 23 May 2005 Ingrid Ciabatti TECNOTESSILE EXPERIENCE OF PROJECT REALISATION.

INDUSTRYLINK WorkshopPoznan, 23 May 2005

TECNOTESSILE - Ingrid Ciabatti ([email protected])

5

The Contract• It includes:

– Identities of all contractors– Scope– Duration– Maximum Community financial contribution– Reports– Payment modalities– Special clauses– Amendments– Applicable law and jurisdiction

• To be signed by Coordinator and EC – partners sign Form A!

Page 6: INDUSTRYLINK Workshop Poznan, 23 May 2005 Ingrid Ciabatti TECNOTESSILE EXPERIENCE OF PROJECT REALISATION.

INDUSTRYLINK WorkshopPoznan, 23 May 2005

TECNOTESSILE - Ingrid Ciabatti ([email protected])

6

Annex I to the contract – the DoW• Technical specification of work to be performed• Contents:

– Project summary– Project objectives– Participant list– Relevance to the objectives of the NMP priority– Potential impact– Project management and exploitation/dissemination plan– Workplan for whole duration of the project – Project resources and budget overview– Ethical issues– Other issues– Appendix A – Consortium description

Page 7: INDUSTRYLINK Workshop Poznan, 23 May 2005 Ingrid Ciabatti TECNOTESSILE EXPERIENCE OF PROJECT REALISATION.

INDUSTRYLINK WorkshopPoznan, 23 May 2005

TECNOTESSILE - Ingrid Ciabatti ([email protected])

10

Annex II to the contract – General conditions

• Definitions (art. II.1)

• Part A: implementation of the project (artt. II.2-II.18)

– Section 1 - implementation and deliverables

– Section 2 - termination of the contract and responsibility

• Part B: financial provisions (artt. II.19-II.31)

– Section 1: general financial provisions

– Section 2: controls, recoveries and sanctions

• Part C: Intellectual Property Rights (artt. II.32-II.36)

Page 8: INDUSTRYLINK Workshop Poznan, 23 May 2005 Ingrid Ciabatti TECNOTESSILE EXPERIENCE OF PROJECT REALISATION.

INDUSTRYLINK WorkshopPoznan, 23 May 2005

TECNOTESSILE - Ingrid Ciabatti ([email protected])

11

Annex II to the contract Part A, Section 1

• Activities (RTD and innovation, demonstration, management)

• Performance obligations of consortium, contractors, coordinator, and EC

• Force majeure

• Suspension and prolongation of the project

• Subcontracting

• Reports and deliverables

• Evaluation and approval of reports and deliverables

• Confidentiality

• Publicity

• …

Page 9: INDUSTRYLINK Workshop Poznan, 23 May 2005 Ingrid Ciabatti TECNOTESSILE EXPERIENCE OF PROJECT REALISATION.

INDUSTRYLINK WorkshopPoznan, 23 May 2005

TECNOTESSILE - Ingrid Ciabatti ([email protected])

16

Annex II to the contractPart A, Section 2

Termination of the contract and participation of contractors

• A Contractor X or the consortium may request the termination of the participation of X in the contract to the EC.

• The consortium may request the termination of the contract to the EC.

• The EC may terminate the contract or the participation of a contractor, e.g. for non performance by one or more contractors.

silence implies agreement by the EC

silence implies rejection by the EC

Page 10: INDUSTRYLINK Workshop Poznan, 23 May 2005 Ingrid Ciabatti TECNOTESSILE EXPERIENCE OF PROJECT REALISATION.

INDUSTRYLINK WorkshopPoznan, 23 May 2005

TECNOTESSILE - Ingrid Ciabatti ([email protected])

17

Annex II to the contract Part A, Section 2

Technical and financial collective responsibility• The technical implementation of the project is the

collective responsibility of the participants.• Each participant is liable for the use of the Community

financial contribution in proportion to his share of the project up to a maximum of the total payments he has received.– Should a participant breach the contract and should the

consortium not make good this breach, the Commission may, as a last resort and if all other approaches have been explored, hold the participants liable under certain conditions.

– A public body is solely responsible for its own debt.

Page 11: INDUSTRYLINK Workshop Poznan, 23 May 2005 Ingrid Ciabatti TECNOTESSILE EXPERIENCE OF PROJECT REALISATION.

INDUSTRYLINK WorkshopPoznan, 23 May 2005

TECNOTESSILE - Ingrid Ciabatti ([email protected])

18

Annex II to the contract Part C

Ownership and protection of knowledge

• Knowledge shall be the property of the contractor carrying out the work leading to that knowledge.

• Where knowledge is capable of industrial or commercial application, its owner shall provide for its adequate and effective protection.

• A contractor may publish or allow the publication of data, on whatever medium, concerning knowledge it owns provided that this does not affect the protection of that knowledge. The Commission and the other contractors shall be given 30 days prior written notice of any planned publication.

Page 12: INDUSTRYLINK Workshop Poznan, 23 May 2005 Ingrid Ciabatti TECNOTESSILE EXPERIENCE OF PROJECT REALISATION.

INDUSTRYLINK WorkshopPoznan, 23 May 2005

TECNOTESSILE - Ingrid Ciabatti ([email protected])

19

Annex II to the contract Part C

Access rights

To be specified by the CA!

Page 13: INDUSTRYLINK Workshop Poznan, 23 May 2005 Ingrid Ciabatti TECNOTESSILE EXPERIENCE OF PROJECT REALISATION.

INDUSTRYLINK WorkshopPoznan, 23 May 2005

TECNOTESSILE - Ingrid Ciabatti ([email protected])

20

Amendment to the contract• Reference articles in the contract: artt.10 and 11• Reasons for a contract amendment:

– Change in the name or legal status of a contractor– Important changes to the budget distribution between contractors– Changes to the composition of the consortium

• Documents needed for a contract amendment– Formal letter sent to the EC by the coordinator on behalf of the

consortium– Amendment to the DoW or entirely revised version– New Contract Preparation Forms plus annexes– Formal letter of explanation and financial statements for last period if a

partner has to withdraw• It may need 4 months!

Page 14: INDUSTRYLINK Workshop Poznan, 23 May 2005 Ingrid Ciabatti TECNOTESSILE EXPERIENCE OF PROJECT REALISATION.

INDUSTRYLINK WorkshopPoznan, 23 May 2005

TECNOTESSILE - Ingrid Ciabatti ([email protected])

21

The Consortium Agreement (CA)• Aim:

– Specifying the organisation of the work between the Contractors

– Organising the management of the Project

– Defining the rights and obligations of the Contractors

– Supplementing the provisions of the Contract concerning Access Rights

• It may not be requested by the EC, but it is very useful

• Models from some organisations available on www.ipr-helpdesk.org (no official documents from the EC)

• TO BE SIGNED BEFORE PROJECT START!!!

Page 15: INDUSTRYLINK Workshop Poznan, 23 May 2005 Ingrid Ciabatti TECNOTESSILE EXPERIENCE OF PROJECT REALISATION.

INDUSTRYLINK WorkshopPoznan, 23 May 2005

TECNOTESSILE - Ingrid Ciabatti ([email protected])

22

The CA – Outline of the content (1)• General Information (Identify each party to the agreement – Contractors to the EC

contract).• Preamble (Subject of the Consortium Agreement, including definitions based on the

contract, Rules and any additional definitions as needed by the consortium).• Subject of the contract (Title of project).• Technical provisions: (A) Technical contribution of each party (as set out in Annex I to

the EC contract); (B) Technical resources made available; (C) Production schedule for inter-related tasks and for planning purposes; (D) Expected contribution, maximum effort expected; (E) Modification procedure; (F) Provisions for dealing with non-performing contractor(s).

• Commercial provisions: (A) Confidentiality; (B) Ownership of results / joint ownership of results / difficult cases (i.e. pre-existing know-how that is very closely linked to the result, making it difficult to distinguish the pre-existing know-how from the result); (C) Legal protection of results (patent rights); (D) Commercial exploitation of results and any necessary access rights; (E) Commercial obligations; (F) Relevant patents, know-how, and information; (G) Sub-licensing; (H) Pre-existing know-how excluded from use in the project.

Page 16: INDUSTRYLINK Workshop Poznan, 23 May 2005 Ingrid Ciabatti TECNOTESSILE EXPERIENCE OF PROJECT REALISATION.

INDUSTRYLINK WorkshopPoznan, 23 May 2005

TECNOTESSILE - Ingrid Ciabatti ([email protected])

23

The CA – Outline of the content (2)• Organisational provisions: (A) Committees – establishment, composition,

procedures, role and nature (Steering, management, technical, IPR, financial etc); (B) Co-ordination of committees; (C) Amendment / revision of the agreement.

• Financial provisions: (A) Financing plan; (B) Modification procedure; (C) Mutual payments, common costs; (D) Distribution of management costs; (E) Auditing of costs; (F) Audit certificates; (G) How to deal with financial collective responsibility; (H) Provisions for dealing with non-performing contractor(s); (I) Third party resources - identifying parties and resources.

• Legal provisions: (A) Legal form of the co-operation; (B) Duration of the agreement versus duration of the EC contract (i.e. 6 months one year longer, etc); (C) Penalties for non-compliance with obligations under the agreement; (D) Applicable law and the settlement of disputes; (E) Secondment of personnel; (F) What to do if all the contractors do not sign the EC contract.

Page 17: INDUSTRYLINK Workshop Poznan, 23 May 2005 Ingrid Ciabatti TECNOTESSILE EXPERIENCE OF PROJECT REALISATION.

INDUSTRYLINK WorkshopPoznan, 23 May 2005

TECNOTESSILE - Ingrid Ciabatti ([email protected])

24

Payment and financial statements

Page 18: INDUSTRYLINK Workshop Poznan, 23 May 2005 Ingrid Ciabatti TECNOTESSILE EXPERIENCE OF PROJECT REALISATION.

INDUSTRYLINK WorkshopPoznan, 23 May 2005

TECNOTESSILE - Ingrid Ciabatti ([email protected])

25

Payments• Payment modalities (advance payment, periodic payments, final

payment) are set-out in art. 8 of the core contract• Some partners may not get any advance unlike providing a

financial guarantee as decided by the EC (Special clauses of the contract)

• Distribution of the grant between participants is not set in the contract (a common liability reserve can be defined by the CA)

• The coordinator should keep advance payments on a bank account separated from its normal business account ( CA)

TO BE REVIEWED AT INDUSTRYLINK WORKSHOP, DAY 2!

Page 19: INDUSTRYLINK Workshop Poznan, 23 May 2005 Ingrid Ciabatti TECNOTESSILE EXPERIENCE OF PROJECT REALISATION.

INDUSTRYLINK WorkshopPoznan, 23 May 2005

TECNOTESSILE - Ingrid Ciabatti ([email protected])

26

Financial statements• Annex VI to the Contract: Form C – Financial statements (available as .xls

file on www.cordis.lu)• References in the Contract: Annex II, Part B, Section 1• Check “FP6 Financial rules”!!!• All Forms C will be revised by an auditor audit certificates• Find an auditor, check his costs and arrange your audit in due time!!!

• Actions by the coordinator:– Notification of due dates to partners (due dates not shortly before deadline

with the EC!!!)– Follow up to ensure timely receipt of contributions– Check the documents of all contractors before submission to the EU– Preparation of the management report– Submission to Commission

TO BE REVIEWED AT INDUSTRYLINK WORKSHOP, DAY 2!

Page 20: INDUSTRYLINK Workshop Poznan, 23 May 2005 Ingrid Ciabatti TECNOTESSILE EXPERIENCE OF PROJECT REALISATION.

INDUSTRYLINK WorkshopPoznan, 23 May 2005

TECNOTESSILE - Ingrid Ciabatti ([email protected])

27

Control of the project budget• The coordinator must report to the EC on the resources deployed

by each contractor at the end of each reporting period (annual) management report

• The coordinator should check the financial and manpower situation budget situation of the partners on more frequent basis

• The coordinator must mantain careful records of project financial aspects

• Internal forms of the consortium with cost details may be asked to partners by the coordinator to verify that cost claims are correct and in track with the planning

• Significant deviations from project budget: to be discussed at project meetings and in the management reports – take remedial actions if needed

Page 21: INDUSTRYLINK Workshop Poznan, 23 May 2005 Ingrid Ciabatti TECNOTESSILE EXPERIENCE OF PROJECT REALISATION.

INDUSTRYLINK WorkshopPoznan, 23 May 2005

TECNOTESSILE - Ingrid Ciabatti ([email protected])

28

Project meetings

Page 22: INDUSTRYLINK Workshop Poznan, 23 May 2005 Ingrid Ciabatti TECNOTESSILE EXPERIENCE OF PROJECT REALISATION.

INDUSTRYLINK WorkshopPoznan, 23 May 2005

TECNOTESSILE - Ingrid Ciabatti ([email protected])

29

The kick-off meeting• Kick-off meeting to be planned shortly after the start date of the

project (the kick-off phase may determine the fate of the project!)

• All partners get to know

• Agreement on the people who will sit on the Steering Committee and who will be responsible for the day-to-day management of each aspect of the project (Exploitation Manager, Knowledge Manager, WP Leaders, Task Leaders…)

• Working relationships must be established

• Personal commitment to the project must be encouraged

• Resolution of first disagreements…

• ALL PARTNERS HAVE TO PARTICIPATE (THERE IS THE PROJECT OFFICER)!!!

Page 23: INDUSTRYLINK Workshop Poznan, 23 May 2005 Ingrid Ciabatti TECNOTESSILE EXPERIENCE OF PROJECT REALISATION.

INDUSTRYLINK WorkshopPoznan, 23 May 2005

TECNOTESSILE - Ingrid Ciabatti ([email protected])

30

The kick-off meeting agendaAgenda Item Remark Typical Time

PART 1 ADMINISTRATIVE SESSION

Welcome Introductions

Presentation of host organisation.

10 mins

Review History of the proposal; presentation by Co-ordinator

10 mins

Presentations Presentation of each partner organisation 10 minutes per partner

Commission requirements

Review / explanation of Commission requirements

30 minutes

Management Review of management structure and decision making mechanisms

15 minutes

Procedures Review of project administrative and financial procedures

30 minutes

Lunch

PART 2 TECHNICAL SESSION

Project overview Presentation of the Project Programme. Review of technical objectives, deliverables and timescales

60 minutes

Resources Review of finances and manpower situation, with appropriate charts.

10 minutes

Exploitation Review of exploitation potential.

Dissemination of results including plans for future publications.

40 minutes

Future plans Agree project calendar.

Actions for the coming period.

30 minutes

Page 24: INDUSTRYLINK Workshop Poznan, 23 May 2005 Ingrid Ciabatti TECNOTESSILE EXPERIENCE OF PROJECT REALISATION.

INDUSTRYLINK WorkshopPoznan, 23 May 2005

TECNOTESSILE - Ingrid Ciabatti ([email protected])

31

Technical and management meetings• They are needed to:

– maintain relationships

– promote information exchange

– make agreements and major decisions

• To be organised periodically at project, WP or task level

• Project meetings:

– Date (and location) to be agreed by all partners at the previous meeting

– A partner that cannot attend a meeting should make a proxy to another one that does to act on his behalf

– Participation of all partners needed at the mid-term meeting and the final meeting

Page 25: INDUSTRYLINK Workshop Poznan, 23 May 2005 Ingrid Ciabatti TECNOTESSILE EXPERIENCE OF PROJECT REALISATION.

INDUSTRYLINK WorkshopPoznan, 23 May 2005

TECNOTESSILE - Ingrid Ciabatti ([email protected])

32

Actions by the coordinator

– Reminder on the meeting date and location must be given to partners at least one month before the meeting with the agenda and info on accomodation, travel, meeting venue (to be agreed with the host organisation!)

– Agenda should also be agreed with the partners that will make a presentation

– Preparation and distribution of minutes to partners and, following their approval, to the PO

– Follow up of actions

Page 26: INDUSTRYLINK Workshop Poznan, 23 May 2005 Ingrid Ciabatti TECNOTESSILE EXPERIENCE OF PROJECT REALISATION.

INDUSTRYLINK WorkshopPoznan, 23 May 2005

TECNOTESSILE - Ingrid Ciabatti ([email protected])

33

Project management meetingsAgenda for Project Management Meeting

Agenda Item Remark Typical Time

Minutes Approve minutes of previous meeting.

Verify action items.

20 minutes

Management overview

Review of resources used, Co-ordination requirements, outstanding issues and their resolution

30 minutes

Work review Presentation of work to date on a task by task or partner by partner basis.

Identification of issues and their resolution.

Summarise achievements

30 - 45 mins per Workpackage

Resources Review of progress, finances and manpower situation, with appropriate charts.

30 mins

Exploitation and Dissemination issues

Review of status of each partners exploitation and dissemination activities and initiatives; suggestions for new initiatives.

60 mins

Future plans Summary of plans for remainder of project.

Requirements for update to the Description of Work

45 minutes

Action List Itemise actions and get person/time commitment

30 minutes

Page 27: INDUSTRYLINK Workshop Poznan, 23 May 2005 Ingrid Ciabatti TECNOTESSILE EXPERIENCE OF PROJECT REALISATION.

INDUSTRYLINK WorkshopPoznan, 23 May 2005

TECNOTESSILE - Ingrid Ciabatti ([email protected])

34

Mid-term meetingAgenda of Mid-Term Project Review

Agenda Item Remark Typical Time

Welcome Introduction of participants. Presentation of the day's agenda. Presentation of host organisation.

15 mins

Project overview Review project objectives, management, partner roles, interaction, plans for coming period.

10 mins

Response to previous actions

Present any response and actions you have taken in light of the reviewers' suggestions and recommendations made at the previous review.

20 minutes

Management report Presentation of progress status, finances and manpower situation, with appropriate charts. Presentation of any critical issues.

20 minutes

Detailed review Presentation of work to date on a task by task or partner by partner basis.

30 mins per partner

Achievements Summary of main achievements to date. Can follow structure of technical report.

10 mins

Exploitation and Dissemination

Review of items in report; suggestions for new initiatives.

60 mins

Administrative issues

Comments from the Project Officer 30 mins

Future plans Summary of plans for remainder of project.

20 mins

Discussion Can take the form of a question and answer session

20 mins

Demonstration Tour of plant and demonstration of results.

Typically at a convenient time during the day.

As required

A decision whether or not to continue the contract will be taken!!!

Page 28: INDUSTRYLINK Workshop Poznan, 23 May 2005 Ingrid Ciabatti TECNOTESSILE EXPERIENCE OF PROJECT REALISATION.

INDUSTRYLINK WorkshopPoznan, 23 May 2005

TECNOTESSILE - Ingrid Ciabatti ([email protected])

35

Agenda of a Final Project Review

Agenda Item Remark Typical Time

Introduction Welcome of participants

Presentation of host organisation

Review of overall objectives.

15 mins

Technical review Review of results

Conformity with Project

15 minutes per partner

Achievements Summary of main achievements 15 minutes

Exploitation and other follow-up following Final Plan for Using and Disseminating the Knowledge

Industrial applications

Market analysis

Exploitation and Marketing Plan

Intellectual Property Rights

Other follow-up of the project.

30 to 60 minutes

Management aspects

Review of administrative and financial situation with appropriate charts

Collaboration and interactions

Final Reporting

15 minutes

Address of PO Comments by the PO 30 mins

Conclusions Summary of the project by the coordinator

30 mins

Demonstration Tour of plant and demonstration of results.

Typically at a convenient time during the day.

60 minutes

Final meeting

Page 29: INDUSTRYLINK Workshop Poznan, 23 May 2005 Ingrid Ciabatti TECNOTESSILE EXPERIENCE OF PROJECT REALISATION.

INDUSTRYLINK WorkshopPoznan, 23 May 2005

TECNOTESSILE - Ingrid Ciabatti ([email protected])

36

Project reports

Page 30: INDUSTRYLINK Workshop Poznan, 23 May 2005 Ingrid Ciabatti TECNOTESSILE EXPERIENCE OF PROJECT REALISATION.

INDUSTRYLINK WorkshopPoznan, 23 May 2005

TECNOTESSILE - Ingrid Ciabatti ([email protected])

37

Basic info

• Reporting (project reports, WP reports, Task reports, partner reports) to be described in DoW, Chapter 6 (Project management)

• References in the Contract: Annex II, art.II.7

• Check “Project reporting in FP6 - Guidance notes”!!!

Page 31: INDUSTRYLINK Workshop Poznan, 23 May 2005 Ingrid Ciabatti TECNOTESSILE EXPERIENCE OF PROJECT REALISATION.

INDUSTRYLINK WorkshopPoznan, 23 May 2005

TECNOTESSILE - Ingrid Ciabatti ([email protected])

38

Actions by the coordinator

• Send templates for WP, Task and partner reports (in agreement with WP and Task Leaders)

• Notification of due dates to partners (due dates not shortly before deadline with the EC!!!)

• Follow up to ensure timely receipt of contributions• Preparation of consolidated document from task leader inputs• Preparation of distribution lists (according to the dissemination level

of reports and deliverables)• Photocopying and timely distribution of documents to the EC • Distribution of documents submitted to the EC to the partners

TO BE REVIEWED ATINDUSTRYLINK WORKSHOP, DAY 2!

Page 32: INDUSTRYLINK Workshop Poznan, 23 May 2005 Ingrid Ciabatti TECNOTESSILE EXPERIENCE OF PROJECT REALISATION.

INDUSTRYLINK WorkshopPoznan, 23 May 2005

TECNOTESSILE - Ingrid Ciabatti ([email protected])

39

Thank you for your attention!