Industrial Training Ppt

32
UNNAO LUCKNOW EXPRESSWAY PROJECT (GREEN FIELD) (FROM KM 236.500 TO 299.588) Submitted by: Pulkit Shukla Institute: NIT Jaipur Duration: (25/05/15 to 9/07/15) Industrial Training Presentation

Transcript of Industrial Training Ppt

Page 1: Industrial Training Ppt

UNNAO LUCKNOW EXPRESSWAY PROJECT(GREEN FIELD)(FROM KM 236.500 TO 299.588)

Submitted by: Pulkit ShuklaInstitute: NIT Jaipur

Duration: (25/05/15 to 9/07/15)

Industrial Training Presentation

Page 2: Industrial Training Ppt

SALIENT FEATURES OF UNNAO-LUCKNOW PROJECT

Sr. No.

Description

1 Name of Project Development of Unnao to Lucknow Access Controlled Expressway(Green Field) Project in the State of Uttar Pradesh on EPC Basis.

2 Chainage Ch 236+500 to 299+5883 Length of Project 63.088 km4 Total Construction Cost

of Project1630 Cr

5 Five Year Maintenance Cost

100 Cr

6 Total Cost 1730 Cr (Including Five Year Maintenance Cost)

7 Client Uttar Pradesh Expressways Industrial Development Authority

8 Authority Engineer Ayesa Jv Arvee Associates9 Design Consultant Highway-In House

Structure-M/s. Sai Consulting Engineers Pvt. Ltd.

Page 3: Industrial Training Ppt

Sr. No. Description 10 Proof Consultant M/s. Sowil Limited11 Safety

ConsultantM/s. Infro Trans Engineers Pvt. Ltd.

12 Contract Agreement Date

29/10/2014

13 Contract Duration

36 Months from NTP date (07/02/2015)

14 Project Start Date

16/02/2015

Page 4: Industrial Training Ppt

SCOPE OF WORKSr. No. Description No/Qty

1 Major Bridge 4

2 Minor Bridge 10

3 VUP 19

4 PUP 26

5 Box culvert 64 on MCW and 64 on SR

6 HPC 63 on MCW and 63 on SR

7 Interchange 1

8 Fascia Panel 11,467 Sqm

9 Service Road Length 69.30 Km

10 Embankment 92,34,640 Cum

11 Sub-grade 15,80,860 Cum

12 GSB 7,23,849 Cum

Page 5: Industrial Training Ppt

Sr. No. Description No/Qty

13 WMM 6,01,210 Cum

14 DBM 2,09,296 Cum

15 SDBC 10,739 Cum

16 BC 84, 860 Cum

17 Concrete 1,56,557 Cum

18 DLC 5,097 Cum

19 PQC 8,420 Cum

20 KERB 82,118 Lm

Page 6: Industrial Training Ppt

ORGANIZATION STRUCTURE

Page 7: Industrial Training Ppt

PLANNING DEPARTMENT

• Construction planning is a fundamental and challenging activity in the management and execution of construction projects.

• It involves the choice of technology, the definition of work tasks, the estimation of the required resources and durations for individual tasks, and the identification of any interactions among the different work tasks.

• Developing the construction plan is a critical task in the management of construction.

Page 8: Industrial Training Ppt

QUALITY ASSURANCE & QUALITY CHECK DEPARTMENT

Quality is the key component which propels performance and defines leadership traits. At L&T Construction, Quality Standards have been internalized and documented in Quality Assurance manuals. L&T Construction recognizes the crucial significance of the human element in ensuring quality. Structured training programes ensure that every L&T employee is conscious of his/her role and responsibility in extending L&T Construction’s tradition of leadership through quality.

Page 9: Industrial Training Ppt

PROJECT QUALITY PLAN• The Project Quality Plan is prepared and formulated

as a Management Summary of Quality related activities required to meet the terms of contract. This Quality plan sets out the Management practices and describes the Quality Management System based on PDCA (Plan, Check, Do and Act) Principle. The Project Quality Plan comprises of two sections:

A : Volume-I B : Volume-II

Page 10: Industrial Training Ppt

VARIOUS LAB TESTS PERFORMED

• O.G.L. sampling and testing• Embankment and borrow area soil sampling and

testing-Grain size analysis, Proctor test, Atterberg’s Limits test, Free swell index, CBR (required only for sub-grade).

• Aggregate Testing-Source of aggregate and sand is decided and then testing is done.

• Source of Bitumen and Cement is decided and testing is done.

Page 11: Industrial Training Ppt

TESTS PERFORMED ON CEMENT

Tests performed- • Consistency test• Initial Setting Time and Final Setting Time test• Fineness test• Mortar Cube Strength test ( 3,7 and 28 days

strength)

Page 12: Industrial Training Ppt

TESTS PERFORMED ON SOIL

Tests Performed- • Grain Size Analysis, • Free Swell Index Test• Atterberg’s Limit Test (Liquid Limit and Plastic Limit

Test)• Proctor Test• C.B.R Test• Specific Gravity Test • Field Dry Density Test (Sand Replacement/Core Cutter

Method)

Page 13: Industrial Training Ppt

TESTS PERFORMED ON AGGREGATES

Tests Performed- • Gradation• Flakiness Index and Elongation Index test• Aggregate Impact Value test• Los Angeles Abrasion Value test• Water Absorption test• Specific gravity test.

Page 14: Industrial Training Ppt

BORROW AREA TESTING (SOIL STABILISATION)

• Testing is done according to IRC:37-2012.• Cement is added as 1%,2% or 3% by weight of soil.

Lime can also be used depending upon soil.• Casting of mould for CBR is done at MDD and OMC.• 7 days curing of mould is done and then it is kept in

soaked condition for 4 days.• CBR test is performed and CBR value for different

percentage of cement is calculated.

Page 15: Industrial Training Ppt

CONCRETE MIX DESIGNIs Code Used- IS 10262: 2009Steps Involved:

• Target strength for mix proportioning• Standard deviation• Selection of Mix Proportions• Calculation of cementitious material• Estimation of Coarse Aggregate proportion• Estimate of fine aggregate proportion

Page 16: Industrial Training Ppt

ROAD DEPARTMENTMajor Road Works Involved are:• Clearing and Grubbing

• Setting out and Levelling

• Earthwork in Embankment (filling)

• Earthwork in subgrade (filling)

• Construction of sub-base course

• Construction of Wet Mix Macadam (WMM)

• Construction of Prime Coat and Tack Coat

• Construction of DBM and Bituminous Concrete

• Construction of Pavement Quality Concrete

• Miscellaneous works

Page 17: Industrial Training Ppt

SITE PHOTOGRAPHS-EARTHWORK IN EMBANKMENT

Page 18: Industrial Training Ppt

FIELD TEST-SAND REPLACEMENT TEST

• The apparatus - sand pouring cylinder, cylindrical calibrating container, soil cutting and excavating tools, glass plate

• The test is conducted in 2 stages –

A) Calibration of apparatus - For determination of weight of sand in the cone of pouring cylinder; For determination of bulk density of sand.

B) Measurement of In situ density

Page 19: Industrial Training Ppt
Page 20: Industrial Training Ppt

STRUCTURE DEPARTMENT

Structure DetailsSr. No. Structure Type Unit Nos.1 Major Bridges No 4

2 Minor Bridges No 10

3 PUP No 26

4 VUP No 18+1

5 Interchange No 1

6 Box Culvert(MCW+SR)

No 128

7 Pipe Culvert(MCW+SR)

No 126

8 Toll Plaza No 1

Page 21: Industrial Training Ppt

LEARNING OUTCOME

Drawing readingWorking DrawingBar Bending ScheduleQuantity SurveyingSite Observations-Piling WorkBox Culvert Concreting

Page 22: Industrial Training Ppt

BOX CULVERT CONCRETING

Page 23: Industrial Training Ppt

PILING WORKPilePile Diameter 1000mmDepth of pile 30.05 mCutoff level 121.36 m Concrete grade M35Clear cover 75 mmSlump requirement 150 mm – 200 mmPile working load capacity (vertical) 328 MTPile Test Load (vertical) 820 MTReinforcement Main reinforcement – 18 no. of 16 mm dia. Bar

Distribution reinforcement – helical reinforcement, 8 mm dia bars at 150 c/cMaster ring – 16 mm dia bars at …..

Lap length 51 X bar dia.Pile capSize 4.3 m X 4.3 mPCC 80 mm thick , M15 Reinforcement Fe 500Concrete Grade M35

Page 24: Industrial Training Ppt

SITE PHOTOGRAPHS

Page 25: Industrial Training Ppt

• Concrete mix is poured into the bore hole using tremie pipe which is 1600mm in length and 200mm in diameter. The concrete that is being poured moves the slurry up which is chiselled after drying.

Page 26: Industrial Training Ppt

SURVEY DEPARTMENT• A Survey is a data collection tool

used to gather information about individuals.

• Civil Surveying is the technique , profession and science of accurately determining terrestrial position of points , distances and angle between them .

• A civil engineering job always starts off by a surveying job .

Page 27: Industrial Training Ppt

INSTRUMENTS AVAILABLE

Total StationAuto LevelDumpy Level

Page 28: Industrial Training Ppt

AUTO LEVEL• Auto level is used for

determining elevations.• Leveling is still a cost-

effective way to produce elevation data with sub-meter accuracy. A Auto level is shown in the photograph.

Page 29: Industrial Training Ppt

FIXING OF ROAD ALIGNMENT, CENTER LINE & TOE LINE

• The Project Reference centre line of proposed cross section will be fixed by surveyor and marked on ground by either pegs /chainage boards or by suitable means at site for ready reference. This marking shall be done @ 50m interval on straight portion & 20m interval on curve portion.

• TBM shall be fixed at every 200m on ROW line. The pillar shall be 150*150*750 mm in square or 150mm diameter in case of round shape with a steel rod embedded in it. The pillar shall be established on hard ground and concreted with M15 Grade.

Page 30: Industrial Training Ppt

P&M DEPARTMENTSL No Description

of Plant Unit Qty Productivity Considered

1 Motor Graders No’s 28 23000 Cum /Team/Month

2 Roller- 12 T No’s 56 23000 Cum/Team/Month

3 Pug Mill – 100 TPH

No’s 2 31000 MT/Month

4 HMP – 120 TPH No’s 2 25000 MT/Month

5 Pavers No’s 46 Tandem

RollersNo’s 4

7 PTR No’s 28 Crushers 200

TPHNo’s 4 55000 MT/Month

9 BP – 12 /30 Cum

No’s 2 4500 Cum/Month

10 Kerb Casting No’s 1

Page 31: Industrial Training Ppt

BATCHING PLANTMain Parts-1. Silos2. Main Structure3. Stetter Pan Mixer4. Aggregate Conveyor5. HopperGeneral Features-Pneumatic Compact Batching Plant (CP-30) of capacity 30 m3/h by SCHWING Stetter.Capacity of Silos=100 tonneWorking Aggregate feeding,Powder feeding (fly  ash, cement and expanding agent),Water andAdmixture for mixing the materials, conveyance and storage

Page 32: Industrial Training Ppt

THANK YOU