UNNAO LUCKNOW EXPRESSWAY PROJECT(GREEN FIELD)(FROM KM 236.500 TO 299.588)
Submitted by: Pulkit ShuklaInstitute: NIT Jaipur
Duration: (25/05/15 to 9/07/15)
Industrial Training Presentation
SALIENT FEATURES OF UNNAO-LUCKNOW PROJECT
Sr. No.
Description
1 Name of Project Development of Unnao to Lucknow Access Controlled Expressway(Green Field) Project in the State of Uttar Pradesh on EPC Basis.
2 Chainage Ch 236+500 to 299+5883 Length of Project 63.088 km4 Total Construction Cost
of Project1630 Cr
5 Five Year Maintenance Cost
100 Cr
6 Total Cost 1730 Cr (Including Five Year Maintenance Cost)
7 Client Uttar Pradesh Expressways Industrial Development Authority
8 Authority Engineer Ayesa Jv Arvee Associates9 Design Consultant Highway-In House
Structure-M/s. Sai Consulting Engineers Pvt. Ltd.
Sr. No. Description 10 Proof Consultant M/s. Sowil Limited11 Safety
ConsultantM/s. Infro Trans Engineers Pvt. Ltd.
12 Contract Agreement Date
29/10/2014
13 Contract Duration
36 Months from NTP date (07/02/2015)
14 Project Start Date
16/02/2015
SCOPE OF WORKSr. No. Description No/Qty
1 Major Bridge 4
2 Minor Bridge 10
3 VUP 19
4 PUP 26
5 Box culvert 64 on MCW and 64 on SR
6 HPC 63 on MCW and 63 on SR
7 Interchange 1
8 Fascia Panel 11,467 Sqm
9 Service Road Length 69.30 Km
10 Embankment 92,34,640 Cum
11 Sub-grade 15,80,860 Cum
12 GSB 7,23,849 Cum
Sr. No. Description No/Qty
13 WMM 6,01,210 Cum
14 DBM 2,09,296 Cum
15 SDBC 10,739 Cum
16 BC 84, 860 Cum
17 Concrete 1,56,557 Cum
18 DLC 5,097 Cum
19 PQC 8,420 Cum
20 KERB 82,118 Lm
ORGANIZATION STRUCTURE
PLANNING DEPARTMENT
• Construction planning is a fundamental and challenging activity in the management and execution of construction projects.
• It involves the choice of technology, the definition of work tasks, the estimation of the required resources and durations for individual tasks, and the identification of any interactions among the different work tasks.
• Developing the construction plan is a critical task in the management of construction.
QUALITY ASSURANCE & QUALITY CHECK DEPARTMENT
Quality is the key component which propels performance and defines leadership traits. At L&T Construction, Quality Standards have been internalized and documented in Quality Assurance manuals. L&T Construction recognizes the crucial significance of the human element in ensuring quality. Structured training programes ensure that every L&T employee is conscious of his/her role and responsibility in extending L&T Construction’s tradition of leadership through quality.
PROJECT QUALITY PLAN• The Project Quality Plan is prepared and formulated
as a Management Summary of Quality related activities required to meet the terms of contract. This Quality plan sets out the Management practices and describes the Quality Management System based on PDCA (Plan, Check, Do and Act) Principle. The Project Quality Plan comprises of two sections:
A : Volume-I B : Volume-II
VARIOUS LAB TESTS PERFORMED
• O.G.L. sampling and testing• Embankment and borrow area soil sampling and
testing-Grain size analysis, Proctor test, Atterberg’s Limits test, Free swell index, CBR (required only for sub-grade).
• Aggregate Testing-Source of aggregate and sand is decided and then testing is done.
• Source of Bitumen and Cement is decided and testing is done.
TESTS PERFORMED ON CEMENT
Tests performed- • Consistency test• Initial Setting Time and Final Setting Time test• Fineness test• Mortar Cube Strength test ( 3,7 and 28 days
strength)
TESTS PERFORMED ON SOIL
Tests Performed- • Grain Size Analysis, • Free Swell Index Test• Atterberg’s Limit Test (Liquid Limit and Plastic Limit
Test)• Proctor Test• C.B.R Test• Specific Gravity Test • Field Dry Density Test (Sand Replacement/Core Cutter
Method)
TESTS PERFORMED ON AGGREGATES
Tests Performed- • Gradation• Flakiness Index and Elongation Index test• Aggregate Impact Value test• Los Angeles Abrasion Value test• Water Absorption test• Specific gravity test.
BORROW AREA TESTING (SOIL STABILISATION)
• Testing is done according to IRC:37-2012.• Cement is added as 1%,2% or 3% by weight of soil.
Lime can also be used depending upon soil.• Casting of mould for CBR is done at MDD and OMC.• 7 days curing of mould is done and then it is kept in
soaked condition for 4 days.• CBR test is performed and CBR value for different
percentage of cement is calculated.
CONCRETE MIX DESIGNIs Code Used- IS 10262: 2009Steps Involved:
• Target strength for mix proportioning• Standard deviation• Selection of Mix Proportions• Calculation of cementitious material• Estimation of Coarse Aggregate proportion• Estimate of fine aggregate proportion
ROAD DEPARTMENTMajor Road Works Involved are:• Clearing and Grubbing
• Setting out and Levelling
• Earthwork in Embankment (filling)
• Earthwork in subgrade (filling)
• Construction of sub-base course
• Construction of Wet Mix Macadam (WMM)
• Construction of Prime Coat and Tack Coat
• Construction of DBM and Bituminous Concrete
• Construction of Pavement Quality Concrete
• Miscellaneous works
SITE PHOTOGRAPHS-EARTHWORK IN EMBANKMENT
FIELD TEST-SAND REPLACEMENT TEST
• The apparatus - sand pouring cylinder, cylindrical calibrating container, soil cutting and excavating tools, glass plate
• The test is conducted in 2 stages –
A) Calibration of apparatus - For determination of weight of sand in the cone of pouring cylinder; For determination of bulk density of sand.
B) Measurement of In situ density
STRUCTURE DEPARTMENT
Structure DetailsSr. No. Structure Type Unit Nos.1 Major Bridges No 4
2 Minor Bridges No 10
3 PUP No 26
4 VUP No 18+1
5 Interchange No 1
6 Box Culvert(MCW+SR)
No 128
7 Pipe Culvert(MCW+SR)
No 126
8 Toll Plaza No 1
LEARNING OUTCOME
Drawing readingWorking DrawingBar Bending ScheduleQuantity SurveyingSite Observations-Piling WorkBox Culvert Concreting
BOX CULVERT CONCRETING
PILING WORKPilePile Diameter 1000mmDepth of pile 30.05 mCutoff level 121.36 m Concrete grade M35Clear cover 75 mmSlump requirement 150 mm – 200 mmPile working load capacity (vertical) 328 MTPile Test Load (vertical) 820 MTReinforcement Main reinforcement – 18 no. of 16 mm dia. Bar
Distribution reinforcement – helical reinforcement, 8 mm dia bars at 150 c/cMaster ring – 16 mm dia bars at …..
Lap length 51 X bar dia.Pile capSize 4.3 m X 4.3 mPCC 80 mm thick , M15 Reinforcement Fe 500Concrete Grade M35
SITE PHOTOGRAPHS
• Concrete mix is poured into the bore hole using tremie pipe which is 1600mm in length and 200mm in diameter. The concrete that is being poured moves the slurry up which is chiselled after drying.
SURVEY DEPARTMENT• A Survey is a data collection tool
used to gather information about individuals.
• Civil Surveying is the technique , profession and science of accurately determining terrestrial position of points , distances and angle between them .
• A civil engineering job always starts off by a surveying job .
INSTRUMENTS AVAILABLE
Total StationAuto LevelDumpy Level
AUTO LEVEL• Auto level is used for
determining elevations.• Leveling is still a cost-
effective way to produce elevation data with sub-meter accuracy. A Auto level is shown in the photograph.
FIXING OF ROAD ALIGNMENT, CENTER LINE & TOE LINE
• The Project Reference centre line of proposed cross section will be fixed by surveyor and marked on ground by either pegs /chainage boards or by suitable means at site for ready reference. This marking shall be done @ 50m interval on straight portion & 20m interval on curve portion.
• TBM shall be fixed at every 200m on ROW line. The pillar shall be 150*150*750 mm in square or 150mm diameter in case of round shape with a steel rod embedded in it. The pillar shall be established on hard ground and concreted with M15 Grade.
P&M DEPARTMENTSL No Description
of Plant Unit Qty Productivity Considered
1 Motor Graders No’s 28 23000 Cum /Team/Month
2 Roller- 12 T No’s 56 23000 Cum/Team/Month
3 Pug Mill – 100 TPH
No’s 2 31000 MT/Month
4 HMP – 120 TPH No’s 2 25000 MT/Month
5 Pavers No’s 46 Tandem
RollersNo’s 4
7 PTR No’s 28 Crushers 200
TPHNo’s 4 55000 MT/Month
9 BP – 12 /30 Cum
No’s 2 4500 Cum/Month
10 Kerb Casting No’s 1
BATCHING PLANTMain Parts-1. Silos2. Main Structure3. Stetter Pan Mixer4. Aggregate Conveyor5. HopperGeneral Features-Pneumatic Compact Batching Plant (CP-30) of capacity 30 m3/h by SCHWING Stetter.Capacity of Silos=100 tonneWorking Aggregate feeding,Powder feeding (fly ash, cement and expanding agent),Water andAdmixture for mixing the materials, conveyance and storage