Industrial Process Equipment

download Industrial Process Equipment

of 60

Transcript of Industrial Process Equipment

  • 8/10/2019 Industrial Process Equipment

    1/60

    TeIndting,

    PDH

    stri Ins

    P

    nline C

    l Pr ecti

    nstructor

    H Onli

    5272 MeaFairfax,

    Phone &

    www.www.

    ourse

    cesn &

    Jurandir

    2012

    e | PDH

    dow EstatesVA 22030-ax: 703-98

    DHonline.DHcenter.c

    475 (6

    EquCom Primo

    Center

    Drive658-0088

    rg om

    DH)

    ipmmiss

    ntioni

    g

  • 8/10/2019 Industrial Process Equipment

    2/60

    www.PDHcenter.com PDHonline Course M475 www.PDHonline.org

    Jurandir Primo 2 of 60

    Industrial Process EquipmentTesting, Inspection & Commissioning

    Contents:

    I. HYDROSTATIC TESTING

    II. PNEUMATIC TESTING

    III. PRESSURE TESTS FOR VALVES

    IV. LEAK TESTING FLUIDS AND PROCEDURES

    V. LEAK TESTING WELDED REINFORCING PLATES

    VI. THE DECIBEL

    VII. NOISE MEASUREMENTS AND TESTS VIII. VIBRATION MEASUREMENTS AND TESTS

    IX. PUMP PERFORMANCE AND TESTS

    X. BEARING TEMPERATURE EVALUATION

    XI. FAILURE DIAGNOSTIC DETECTION

    XII. BASIC ELECTRICAL FORMULAE

    XIII. BOLT TORQUE EVALUATION

    XIV. COMMISSIONING PROCESSES

  • 8/10/2019 Industrial Process Equipment

    3/60

    www.PDHcenter.com PDHonline Course M475 www.PDHonline.org

    Jurandir Primo 3 of 60

    I. HYDROSTATIC TESTING:

    A hydrostatic pressure test is a way in which atmospheric tanks, pressure vessels, pipelines, gascylinders, boilers and valves are tested for strength and leaks through the weld or bolting and canbe inspected and repaired. The ASME VIII Div. 1, UG-99 - Standard Hydrostatic Testing defines theconditions to carry on the procedures.

    The hydrostatic test Pressure Gage shall be equal at least one 1.5 times the Maximum AllowableWorking Pressure (MAWP), multiplied by the ratio of the stress value S (materials of which thevessel is constructed) at the Design Temperature for the materials of which the pressure vessel isconstructed.

    Hydrostatic Testing Assembly

    A hydrostatic test based on a calculated pressure may be used by agreement between the user andthe manufacturer . For the basis for calculating test pressures, see UA60(e) of the ASME Code . Thedescriptive paragraphs according to ASME B31.3 for Hydrostatic Test Pressure are:

    Hydrostatic Leak Testing:

    Paragraph 345.4.1 Test Fluid: The fluid shall be water unless there is the possibility of damage dueto freezing or to adverse effects of water on the piping or the process. In this case another suitablenontoxic liquid may be used. If the liquid is flammable, its flash point shall be at least 49C (120F) ,and consideration shall be given to the test environment.

    Paragraph 345.4.2 PressureTest: The hydrostatic test pressure at any point in a metallic piping sys-tem shall be as follows:

    (a) Not less than 1.5 times the design pressure;(b) For design temperature above the test temperature , the minimum test pressure shall be calculat-ed by the same equation as indicated below, except that the value of ST /S shall not exceed 6.5 :

    P T = 1.5.P.S T S D

  • 8/10/2019 Industrial Process Equipment

    4/60

    www.PDHcenter.com PDHonline Course M475 www.PDHonline.org

    Jurandir Primo 4 of 60

    Where:

    P T = Minimum hydrostatic pressure test gaugeP = Internal design gage pressure (MAWP)S T = Stress value of material at test temperatureS D = Stress value of material at design temperature (See Table A-1- ASME B31.3 Material Stresses).

    If the test pressure as above would produce a nominal pressure stress or longitudinal stress in ex-cess of the yield strength at test temperature, the pressure test may be reduced to the maximumpressure that will not exceed the yield strength at test temperature . The stress resulting from thehydrostatic test shall not exceed 90% of the yield stress of the material at the test temperature.

    The hydrostatic pressure test shall be applied for a sufficient period of time to permit a thoroughexamination of all joints and connections. The test shall not be conducted until the vessel and liquidare at approximately the same temperature.

    Defects detected during the Hydrostatic Testing or subsequent examination are completely removedand then inspected. The vessels requiring Stress Relieving after any welding repairs shall be stressrelieved conforms to UW40 of the ASME Code .

    After welding repairs have been made, the vessel should be hydro tested again in the regular way,and if it passes the test, the Inspector and the Quality Engineer may accept it. If it does not pass thetest they can order supplementary repairs, or, if the vessel is not suitable for service, they may perma-nently reject it.

    The fluid for the hydrostatic testing shall be water , unless there is a possibility of damage due tofreezing or to adverse effects of water on the piping or the process. In that case, another suitable non-toxic liquid may be used. So glycol/water is allowed.

    II. PNEUMATIC TESTING:

    Pneumatic testing for valves, pipelines and welded pressure vessels shall be permitted only forthose specially designed that cannot be safely filled with water , or for those which cannot be dried to be used in services where traces of the testing content cannot be tolerated.

    There are two types of procedures for pneumatic testing, as shown below:

    1) The pneumatic pressure test shall be at least equal to 1.25 times the Maximum AllowableWorking Pressure (MAWP) multiplied by the ratio of the stress value S at the test temperature.The Design Temperature is for materials which the equipment is constructed (see UG21 of ASME).

    P T = 1.25.P.S T S D

    Where:

    P T = Minimum pneumatic pressure test gaugeP = Internal design gage pressure (MAWP)S T = Stress value of material at test temperatureS D = Stress value of material at design temperature (See Table A-1- ASME B31.3 Material Stresses).

  • 8/10/2019 Industrial Process Equipment

    5/60

    www.PDHcenter.com PDHonline Course M475 www.PDHonline.org

    Jurandir Primo 5 of 60

    Pneumatic Test Sketch

    2) According to UG-100 , the pneumatic test shall be at least equal to 1.1 times the MAWP multiplied by the lowest ratio for the materials of the stress value S , at the test temperature . The Design

    Temperature may be used in lieu of the standard hydrostatic test prescribed in UG-99 for vesselsunder certain conditions:

    For vessels that cannot safely be filled with water;

    For vessels that cannot be dried and to be used in a service where traces of the testing con-tent cannot be tolerated and previously tested by hydrostatic pressure as required in UG-99 .

    Then, the formula becomes:

    P T = 1.1.P.S T S

    D

    As a general method, the pneumatic test pressure is 1.25 MAWP for materials ASME Section VIII -Division 1 and 1.1 MAWP for materials ASME Section VIII - Division 2 . The pneumatic test proce-dure for pressure vessels should be accomplished as follows:

    The pressure on the vessel shall be gradually increased to not more than half the test pressure . After, the pressure will then be increased at steps of approximately 1/10 the test pressures until thetest pressure has been reached. In order to permit examination, the pressure will then be reduced tothe Maximum Allowable Working Pressure of the vessel.

    The tank supports and saddles, connecting piping, and insulation if provided shall be examined to de-termine if they are satisfactory and that no leaks are evident. The pneumatic test is inherently verydangerous and more hazardous than a hydrostatic test , and suitable precautions shall be takento protect personnel and adjacent property.

    III. PRESSURE TESTS FOR VALVES:

    The API 598, API 6D, IS0 14313 and other standards covers inspection, examination, supplementaryexaminations and pressure test requirements for resilient-seated, nonmetallic-seated (e.g., ceramic)and metal-to-metal-seated valves of the gate, globe, plug, ball, check, and butter y types.

  • 8/10/2019 Industrial Process Equipment

    6/60

    www.PDHcenter.com PDHonline Course M475 www.PDHonline.org

    Jurandir Primo 6 of 60

    Shell Test (Hydrostatic Body Test):

    Every valve shall be subjected to a hydrostatic test of the body shell at 1.5 times the maximum per-missible working pressure at 100 F (38 C). The test shall show no leakage, no wetting of the externalsurfaces, and no permanent distortion under the full test pressure, as specified in Table 1 .

    The valve shall be set in the partially open position for this test, and completely filled with the test fluid. Any entrapped air should be vented from both ends and the body cavity. The valve shall then bebrought to the required test pressure. All external surfaces should be dried and the pressure held forat least the minimum test duration.

    There shall be no visible leakage during the test duration. The stem seals should be capable of retain-ing pressure at least 100 F (38 C) without leakage. If leakage is found, corrective action may be tak-en to eliminate the leakage and the test repeated, specified below and in Table 2 .

    a) Backseat Stem Test: (Hydrostatic Seat Test):

    When applicable (with exception of bellows seal valves), every valve shall be subjected to a hydrostat-ic test of the backseat stem at 1.1 times the maximum permissible working pressure at 100 F (38C), done by opening the valve to the fullest, loosening the packing gland and pressurizing the shell. All external surfaces should be dried and the pressure held for at least the minimum test duration, asspecified in Table 1 .

  • 8/10/2019 Industrial Process Equipment

    7/60

    www.PDHcenter.com PDHonline Course M475 www.PDHonline.org

    Jurandir Primo 7 of 60

    If unacceptable leakage is found, corrective action may be taken to eliminate the leakage and the testrepeated. If the valve is disassembled to eliminate the leakage, all previous testing must be repeatedupon re-assembly. There shall be no visible leakage during the test duration specified in Table 2 .

    b) High-pressure Closure Test (Hydrostatic Seat Test):

    Every valve shall be subjected to a hydrostatic seat test to 1.1 times the maximum permissible work-ing pressure at 100 F (38 C). The test shall show no leakage through the disc , behind the seatrings or past the shaft seals. The allowable leakage of test fluid for the seat seal, shall be according tothose listed in Table 3 .

    If unacceptable leakage is found, corrective action may be taken to eliminate the leakage and theseat test repeated. If the valve is disassembled to eliminate the leakage, all previous testing must berepeated upon re-assembly.

    c) Pneumatic Seat Test - Low-pressure Closure Test:

    Every valve shall be subjected to an air seat test at a minimum pressure from 4 to 7 bar (60-100psig) according to test duration specified in Table 2 . The test shall show no leakage through the disc,behind the seat rings or past the shaft seals. The allowable leakage of test fluid from the seat sealshall be according to those listed in Table 3 .

    Check for leakage using either a soap film solution or an inverted U tube with its outlet submergedunder water. If the seat pressure is held successfully then the other seat shall be tested in the samemanner where applicable.

    If unacceptable leakage is found, corrective action may be taken to eliminate the leakage and theseat test repeated. If the valve is disassembled to eliminate the leakage, all previous testing must berepeated upon re-assembly.

    d) Fluid for Testing:

    Hydrostatic tests shall be carried out with water at ambient temperatures, within the range of 41F(5C) and 122F (50C) and shall contain water-soluble oil or rust inhibitors . Potable water usedfor pressure test of austenitic stainless steel valves shall have a chloride content less than 30 ppm and for carbon steel valves shall be less than 200 ppm .

  • 8/10/2019 Industrial Process Equipment

    8/60

    www.PDHcenter.com PDHonline Course M475 www.PDHonline.org

    Jurandir Primo 8 of 60

    a) For the liquid test, 1 millilitre is considered equivalent to 16 drops;b) For the liquid test, 0 drops means no visible leakage per minimum duration of the test.c) For the gas test, 0 bubbles means less than 1 bubble per minimum duration of the test.d) For valves greater than or equal to 14 (NPS 14), the maximum permissible leakage rate shall

    be 2 drops per minute per inch NPS size.e) For valves greater than or equal to 14 (NPS 14), the maximum permissible leakage rate shall

    be 4 bubbles per minute per inch NPS size.

    Soft-seated valves and lubricated plug valves shall not exceed leakage in IS0 5208 Rate A . Formetal-seated valves the leakage rate shall not exceed (or not more than two times) the IS0 5208Rate D, unless otherwise specified.

  • 8/10/2019 Industrial Process Equipment

    9/60

    www.PDHcenter.com PDHonline Course M475 www.PDHonline.org

    Jurandir Primo 9 of 60

    e) Test Certification:

    All tests should be always specified by the Purchaser. The manufacturer should issue a test certifi-cate according to API 598 confirming that the valves have been tested in accordance with the re-quirements.

    f) Valve Hydrostatic Test - ASME B16.34 Requirements:

    Hydrostatic shell test at a pressure no less than 1.5 times the MAWP at 100 F, rounded off to nexthigher 25 psi increment . The test made with water must contain a corrosion inhibitor , with kero-sene or with other suitable fluid with a viscosity not greater than that of water, at a temperature notabove 125 F. Visually detectable leakage through pressure boundary walls shall not be acceptable.

    Valve sizeinches

    Test time(seconds)

    2 and smaller 15

    2.5 to 8 60

    10 and larger 180

    g) Valve Closure Tests:

    Each valve designed for shut-off or isolation service , such as a stop valve and each valve designedfor limiting flow reversal, such as a check valve, shall be given a hydrostatic closure test . The testpressure shall be not less than 110% at 100 F rating. Except that, a pneumatic closure test at apressure not less than 80 psi may be substituted for valve sizes and pressure classes shown below.

    Valve Size Pressure

    Class 4 All 12 400

    Note: The closure test shall follow the shell test except for valves 4 in. and smaller up to Class1500. The closure test may precede the shell test . When a pneumatic closure test is used, not lessthan duration shown below.

    Valve sizeinches

    Gas Test duration(Seconds)

    2 15

    2 1/2 to 8 30

    10 to 18 60

    20 120

    h) Seat Leakage Classification:

    There are actually six different seat leakage classifications as defined by ANSI/FCI 70-22006 (European equivalent standard IEC 60534-4 ).

  • 8/10/2019 Industrial Process Equipment

    10/60

    www.PDHcenter.com PDHonline Course M475 www.PDHonline.org

    Jurandir Primo 10 of 60

    Class I:

    Identical to Class II, III, and IV in construction and design, but no shop test is made, also known asdust tight and can refer to metal or resilient seated valves.

    Class II:

    For double port or balanced single port valves with a metal piston ring seal and metal to metal seats.

    0.5% leakage of full open valve capacity. Service dP or 50 psid (3.4 bar differential), whichever is lower at 50 to 125 F. Test medium air at 45 to 60 psig is the test fluid.

    Class III:

    0.1% leakage of full open valve capacity. Service dP or 50 psid ( 3.4 bar differential ), whichever is lower at 50 to 125 F.

    Test medium air at 45 to 60 psig is the test fluid. For the same types of valves as in Class II.

    Typical constructions:

    Balanced, double port, soft seats, low seat load Balanced, single port, single graphite piston ring, lapped metal seats, medium seat load

    Class IV:

    0.01% leakage of full open valve capacity.

    Service dP or 50 psid (3.4 bar differential) , whichever is lower at 50 to 125o

    F. Test medium air at 45 to 60 psig is the test fluid.

    Typical constructions:

    Class IV is also known as metal to metal Balanced, single port, Teflon piston ring, lapped metal seats, medium seat load Balanced, single port, multiple graphite piston rings, lapped metal seats Unbalanced, single port, lapped metal seats, medium seat load

    Class V:

    Leakage is limited to 5 x 10 ml per minute per inch of orifice diameter per psi differential. The test fluid is water at 100 psig or operating pressure. Service dP at 50 to 125 oF. For the same types of valves as Class IV.

    Typical constructions:

    Unbalanced, single port, lapped metal seats, high seat load

  • 8/10/2019 Industrial Process Equipment

    11/60

    www.PDHcenter.com PDHonline Course M475 www.PDHonline.org

    Jurandir Primo 11 of 60

    Balanced, single port, Teflon piston rings, soft seats, low seat load Unbalanced, single port, soft metal seats, high seat load

    Class VI:

    Commonly known as a soft seat classification, where the seat or shut-off disc or both are made fromsome material such as Teflon. Intended for resilient seating valves.

    The test fluid is air or nitrogen . Pressure is the lesser of 50 psig or operating pressure. Leakage depends on valve size, from 0.15 to 6.75 ml per minute, sizes from 1 to 8 inches .

    i) Most Common Leakage Tests:

    The most common used tests are:

    CLASS IV: is also known as metal to metal. Leakage rate with a metal plug and metal seat .

    CLASS VI: is known as soft seat. Plug or seat made from material such as Teflon or similar.

    j) Table for Valve Leakage Classification and Test Procedures:

    LeakageClass

    Designation

    MaximumLeakage

    AllowableTest Medium Test Pressure

    Testing ProceduresRating

    I x x x No test required

    II0.5% of rated

    capacity

    Air or water

    at 50 - 125o

    F(10 - 52 oC)

    45 - 60 psig ormaximum oper-

    ating differentialwhichever is

    lower

    45 - 60 psig or maximum

    operating differentialwhichever is lower

    III0.1% of rated

    capacity As above As above As above

    IV0.01% of rated

    capacity As above As above As above

    V

    0.0005 ml perminute of waterper inch of port

    diameter per psidifferential

    Water at 50to125 oF (10

    to 52oC)

    Maximum ser-vice pressuredrop across

    valve plug not toexceed ANSIbody rating

    Maximum service pres-sure drop across valve

    plug not to exceed ANSIbody rating

    VI

    Not to exceedamounts shown

    in the tableabove

    Air or nitro-gen at 50 to

    125 o F (10 to52 oC)

    50 psig or maxrated differentialpressure across

    valve plugwhichever is

    lower

    Actuator should be ad- justed to operating condi-

    tions specified with fullnormal closing thrust ap-plied to valve plug seat

  • 8/10/2019 Industrial Process Equipment

    12/60

    www.PDHcenter.com PDHonline Course M475 www.PDHonline.org

    Jurandir Primo 12 of 60

    k) Valve Bubble Shut-Off Test Procedure:

    Port Diameter Bubbles perminute

    ml perminute inches Millimeters

    1 25 1 0.15

    1 1/2 38 2 0.30

    2 51 3 0.45

    2 1/2 64 4 0.60

    3 76 6 0.90

    4 102 11 1.70

    6 152 27 4.00

    8 203 45 6.75

    10 254 63 9

    12 305 81 11.5

    Gate Valve & Screw Down Non-Return Globe Valve : The pressure shall be applied succes-sively to each side of the closed valve with the other side open to the atmosphere to check forleakage at the atmospheric side of the closure.

    Globe Valve : The pressure shall be applied in one direction with the pressure applied underthe disc (upstream side) of the closed valve with the other side open to the atmosphere tocheck for leakage at the atmospheric side of the closure.

    Check Valve : The pressure shall be applied in one direction with the pressure applied behindthe disc (downstream side) of the closed valve with the other side open to the atmosphere tocheck for leakage at the atmospheric side of the closure.

    l) Valve Flow Coefficients:

    The Flow Coefficient Cv (or Kv) , literally means coefficient of velocity used to compare flows of val-ves. The higher the Cv, the greater the flow. When the valve is opened, most of the time, a valveshould be selected with low head loss in order to save energy. Use the following equations:

    Volumetric flow rate units:

    Mass flow rate units:

    Other formulas considering Cv are:

  • 8/10/2019 Industrial Process Equipment

    13/60

    www.PDHcenter.com PDHonline Course M475 www.PDHonline.org

    Jurandir Primo 13 of 60

    Where:

    Q = Flow rate in gallons per minute (GPM); P = Pressure drop across the valve psi - (62.4 = fluid conversion factor); = Density of fluids in lb/ft - (according to temperature).

    Obs.:

    Kv is the Flow Coefficient in metric units. It is defined as the flow rate in cubic meters per hour [m/h] of water at a temperature of 16 C with a pressure drop across the valve of 1 bar.

    Cv is the Flow Coefficient in imperial units. It is defined as the flow rate in US gallons per minute[gpm] of water at a temperature of 60 F with a pressure drop across the valve of 1 psi .

    Kv = 0.865CvCv = 1,156Kv

    Flow Coefficient Table . Select the valve size using the appropriate manufacturers and the calculatedCv value , considering 100% travel:

    Obs.: See, as shown below, other Flow Coefficients may indicate different numbers, at 100% travel:

  • 8/10/2019 Industrial Process Equipment

    14/60

    www.PDHcenter.com PDHonline Course M475 www.PDHonline.org

    Jurandir Primo 14 of 60

    IV. LEAK TESTING - FLUIDS AND PROCEDURES:

    The choice of liquid or gas depends on the test purpose and the leakage that can be tolerated. Leak-

    ing air or gas can be detected by the sound of the escaping gas, by use of a soap film that formsbubbles , or by immersion in a liquid in which the escaping gas forms bubbles.

    For hydrostatic or gas tests, a pressure gage attached, indicates leaks by the drop in pressure afterthe tests begin. Dyes introduced in liquids and tracers introduced into gases can also indicate leakage.Weld defects that cause leakage are not always detected by the usual NDT methods.

    A tight crack or fissure may not appear on a radiograph , yet will form a leak path. A production op-eration, such as forming or a proof test, may make leaks develop in an otherwise acceptable weld joint. A leak test is usually done after the vessel is completed and all the weld joints can be inspected,there will be no more fabricating operations and the inspection should be taken with the empty vessel.

    The most common types of leak testings are described below:

    1. The pressure-rise test method, is a vessel attached to a vacuum pump evacuating to a pres-sure of 0.5 psi absolute. The connections to the vacuum pump are sealed off and the internal pres-sure of the part is measured.

    The pressure is measured again after 5 minutes . If the pressure in the evacuated space remainsconstant, the welds are free of leaks. If there is a pressure rise, at least one leak is present, then thehelium-leak test below must be used.

  • 8/10/2019 Industrial Process Equipment

    15/60

    www.PDHcenter.com PDHonline Course M475 www.PDHonline.org

    Jurandir Primo 15 of 60

    2. The helium-leak test, is more precise than the pressure-rise method and is used to find the ex-act location of these leaks. Helium-leak testing is not used to inspect large items. This inspectionmethod requires the use of a helium mass spectrometer to detect the presence of helium gas.

    The mass spectrometer is connected to the pumping system between the vacuum pump and thevessel being inspected. Then the vessel is evacuated by a vacuum pump to a pressure of less than50 microns of mercury. The mass spectrometer can detect helium directed at the atmosphere.

    If there is a small jet of helium gas is aside the weld joint exposed, there is a leak . Some of thehelium is sucked through the evacuated space and the mass spectrometer immediately indicatesthe presence of helium.

    When no leak is present, no indication of gas helium will appear on the mass spectrometer. Theexact location of leaks, shows the jet of helium on the surface of the weld joint. If there is an indica-tion of leak, it is at the point where the helium jet is hitting the surface of the weld joint.

    3. Ultrasonic translator detector, uses the ultrasonic sounds of gas molecules escaping from avessel under pressure or vacuum. The sound created is in the frequency range of 35,000 and45,000 Hz , which is above the range of human hearing is, therefore, classified as ultrasonic. Theshort wave length of the frequencies permits the use of highly directional microphones.

    Any piping or vessel pressurized or evacuated to a pressure of 3 psi can be inspected. The op-erator simply listens to the translated ultrasonic sounds while moving a hand-held probe along theweld (as a flashlight). The detectors are simple and require minimum operator training.

    4. The air-soap solution test , can be conducted on a vessel during or after assembly. The vesselis subjected to an internal gas pressure not exceeding the design pressure. A soap or equivalentsolution is applied so that connections and welded joints can be examined for leaks.

    5. Air-ammonia test, involves introducing air into the vessel until a percent of the design pressureis needed. Anhydrous ammonia is then introduced into the vessel until 55% of the design pressureis reached. Air is then reintroduced until the design pressure is reached.

    Each joint is carefully examined by using a probe or a swab wetted with 10N solution of muriaticacid (HCL), a sulphur candle, or sulphur dioxide. A wisp of white smoke indicates a leak.

    6. Hydrostatic tests, use distilled or demineralized water having a pH of 6 to 8 and an impuritycontent not greater than 5 ppm is used. Traces of water should be removed from the inside beforethe final leak testing is begun.

    7. Water submersion test, the vessel is completely submerged in clean water . The interior ispressurized with gas, but the design pressure must not be exceeded. The size and number of gasbubbles indicate the size of leaks.

    8. Halide torch test , the vessel is pressurized with a mixture of 50% Freon and carbon dioxide or50% Freon and nitrogen is used. Each joint is carefully probed with a halide torch to detect leaks,which are indicated by a change in the color of the flame.

  • 8/10/2019 Industrial Process Equipment

    16/60

    i

    www.PDH

    9. Halogpressure.passes t This probsecond.clothing,

    V. L

    his test aif storage t

    n plates an

    ) The posipected ofles outside

    ) The negets betweeeneath the

    he most colates or rei

    pplication

    Weld Fillet Bott

    he test me

    center.com

    n snifter t About 1 oe probe of

    e is held abince the inhe air shoul

    EAK TESTI

    s to detectnks and co castings.

    tive pressut least 0.7 (the welded

    tive pressn the sidesabsolute pr

    mmon testinforcing pla

    xamples:

    s of reinfor welds of ovm-side con

    hods are:

    st, use a Funce of Fr a halogen

    out 1/2 inctrument re

    ld be kept s

    NG - WEL

    defects innnection bohere are tw

    re is based10 psi) toreinforcing

    re is the aand bottom

    ssure. Thi

    hat aims totes is the p

    ing plates;erlapped joiection wel

    PDHonli

    reon inerton for eveapor analy

    from the sponds evebstantially

    ED REINF

    elds, for wttom-sides,o methods

    on applicat.0 kg/cm 2

    late.

    gle weldsof a tank wi pressure i

    guaranteesitive press

    nts in deepon tanks.

    e Course M

    gas mixtur ry 30 ft ofzer over th

    urface bein to cigarett

    clean.

    RCING PL

    lded reinf fillet welded: positive an

    ion of a bu(14.5 psi) , f

    esting in ovth formation obtained th

    he tightnesure test.

    tanks;

    475

    introducedvessel vol area to be

    tested and smoke an

    ATES:

    rcing plat. It is also ud negative

    ble forminorcing the

    erlapping jo of vacuumrough a va

    of a syste

    w

    into the veme is req

    explored.

    is moved ad vapor fro

    s ; overlappsed for theressure.

    g solution ,assage of

    ints (bottoof at leastuum box.

    , by locati

    w.PDHonli

    ssel until thired. The I

    t about 1/2newly dry

    ing joints filldetection o

    with eachir and form

    of tanks).15 kgf/cm

    g defects i

    e.org

    e designspector

    inch percleaned

    et weldsdefects

    iece in-ing bub-

    nd gas-2 (2 psi)

    welded

  • 8/10/2019 Industrial Process Equipment

    17/60

  • 8/10/2019 Industrial Process Equipment

    18/60

    www.PDH

    est seque

    Clea Test Appli Pres Insp Clea Rep

    apillarity:

    Net After Liqui

    center.com

    ce:

    ning of the jliquid applicication of nesurization tiction

    ningrt

    pplicationsome time

    d with diffic

    Essay by

    intsationgative pres

    e - usually

    ith large caof penetratilt evaporati

    : Angle Angle Angle Angle

    PDHonli

    ure10 second

    pillary effecn, inspect t

    on (diesel o

    welds on thwelds in flowelds essawelds testin

    e Course M

    s

    ;he oppositeil, kerosene,

    e board betting ceilingin overlap

    g in the gas

    475

    by looking f , liquid pene

    een the sicompartmeing joints (ket betwee

    w

    or traces oftrant test)

    es and bottnt;ottom of ta sides and

    w.PDHonli

    the liquid u

    om of the ta

    ks);bottom of th

    e.org

    ed;

    nk;

    e tank.

  • 8/10/2019 Industrial Process Equipment

    19/60

    www.PDHcenter.com PDHonline Course M475 www.PDHonline.org

    Jurandir Primo 19 of 60

    VI. THE DECIBEL

    The decibel (dB) is one tenth of a Bel, which is a unit of measure that was developed by engineers atBell Telephone Laboratories and named for Alexander Graham Bell . The dB is a logarithmic unit thatdescribes a ratio of two measurements. The basic equation that describes the difference in decibelsbetween two measurements is:

    Where:

    X = is the difference in some quantity expressed in decibels;X1 and X 2 = are two different measured values of X, and the log is to base 10.

    a) Use of the dB in Sound Measurements:

    The equation used to describe the difference in intensity between two ultrasonic or other sound meas-urements is:

    Where:

    I = difference in sound intensity expressed in decibels (dB);P 1 and P 2 = two different sound pressure measurements, log base 10.

    Note: The factor of two difference between this basic equation for the dB and the one used when mak-ing sound measurements. This difference will be explained in the next section.

    Sound intensity is defined as the sound power per unit area perpendicular to the wave. Units are typi-cally in watts/m 2 or watts/cm 2. For sound intensity, the dB equation becomes:

    However, the power or intensity of sound is generally not measured directly. Since sound consists ofpressure waves, one of the easiest ways to quantify sound is to measure variations in pressure (i.e.the amplitude of the pressure wave ). When making ultrasound measurements, a transducer is used,which is basically a small microphone.

    Transducers like most other microphones can produce a voltage that is approximately proportionally tothe sound pressure (P). The power carried by a traveling wave is proportional to the square of theamplitude. Therefore, the equation used to quantify a difference in sound intensity based on a meas-ured difference in sound pressure becomes:

  • 8/10/2019 Industrial Process Equipment

    20/60

    www.PDHcenter.com PDHonline Course M475 www.PDHonline.org

    Jurandir Primo 20 of 60

    The factor of 2 is added to the equation because the logarithm of the square of a quantity is equal to 2times the logarithm of the quantity. Since transducers and microphones produce a voltage that is pro-portional to the sound pressure, the equation could also be written as:

    Where:

    I = change in sound intensity incident on the transducer,V1 and V 2 = are two different transducer output voltages.

    b) Use of dB units:

    Use of dB units allows ratios of various sizes to be described using easy to work with numbers. Forexample, consider the information in the table, to dB = 10 log .

    Ratio between Measurement 1 and 2 Equation dB1/2 dB = 10 log (1/2) -3 dB1 dB = 10 log (1) 0 dB2 dB = 10 log (2) 3 dB10 dB = 10 log (10) 10 dB100 dB = 10 log (100) 20 dB1,000 dB = 10 log (1000) 30 dB10,000 dB = 10 log (10000) 40 dB100,000 dB = 10 log (100000) 50 dB1,000,000 dB = 10 log (1000000) 60 dB10,000,000 dB = 10 log (10000000) 70 dB100,000,000 dB = 10 log (100000000) 80 dB1,000,000,000 dB = 10 log (1000000000) 90 dB

    From this table it can be seen that ratios from one up to ten billion can be represented with a singleor double digit number. The focus of this discussion is on using the dB in measuring sound levels ,but it is also widely used when measuring power, pressure, voltage and a number of other things. Re-

    vising table to reflect the relationship between the ratio of the measured sound pressure and thechange in intensity expressed in dB produces, to dB = 20 log :

    Ratio between Measurement 1 and 2 Equation dB1/2 dB = 20 log (1/2) - 6 dB1 dB = 20 log (1) 0 dB2 dB = 20 log (2) 6 dB10 dB = 20 log (10) 20 dB100 dB = 20 log (100) 40 dB

  • 8/10/2019 Industrial Process Equipment

    21/60

    t

    t

    www.PDH

    ) Absolut

    henever telate differ ound preshreshold of0 micropas

    rom the ta

    ucing the s

    VII.

    he noise the client. In~1.0 m) an

    efore startisis. Commithout filter ery next th

    center.com

    1,00010,000100,0001,000,00010,000,000100,000,00

    1,000,000,

    e" Sound L

    e decibel unt sound inure (correshuman heacals (20 P

    le it can b

    ound press

    OISE MEA

    ests may fo any case t sound pr

    ng measureonly, the e, and anoth human he

    0

    00

    evels:

    nit is used,tensities it iponding toring, which i). To avoid

    seen that

    re by 2, res

    SUREMEN

    llow ISO-2e equipmessure the

    ment, the Iuipment ha

    er scale forring capaci

    PDHonli

    it always reis necessar a sound ps conventioconfusion

    dB equat

    ults in a 6

    S AND TE

    04, ISO-Rt distance,istance can

    spector shs 4 (four)the filter, cty, between

    e Course M

    dB = 20dB = 20dB = 20dB = 20dB = 20dB = 20

    dB = 20

    presents th to choose

    ressure levnally takenith other de

    s to a dou

    dB change

    TS:

    1996 or anyto measurebe 10 feet

    uld chooseeasurem

    pable of m31 Hz and

    475

    log (1000)log (10000)log (10000log (10000log (10000log (10000

    log (10000

    ratio of tw a standardl of 0 dB)o be 210cibel meas

    ling of the

    in intensity.

    other stanthe noise l

    (3.0 m) .

    the measur nt scales f easuring th16 KHz of th

    w

    )0)00)000)

    0000)

    o values. T reference lcommonly5 Newtonres, the ter

    sound pres

    ard requireevel , shoul

    ement scalor direct re incident se octave ba

    w.PDHonli

    60 dB80 dB

    100 dB120 dB140 dB160 dB

    180 dB

    herefore, inevel. The r used is ther square

    dB (SPL)

    ure. Altern

    ments, acc be always

    of the souading, (A,und in a fr

    nd.

    e.org

    order toferencet at theeter, or

    is used.

    tely, re-

    rding to3.3 feet

    nd anal-, C, D),

    equency

  • 8/10/2019 Industrial Process Equipment

    22/60

    I

    (

    www.PDH

    he measur B. The meoises, then

    dB ( dB ( dB (

    n critical neasuring aistance , thB, for exat 2.0 m (6.

    ) Sound L

    ound leveldB-SPL) unhe SI unit

    ote: Mostnderwater,

    ) Conversi

    center.com

    ement scalasurementcommon s

    ) up to 55) between) above 85

    ise environpparatus ane sound aple, measu feet) the n

    vel Meter (

    meter or Sits, used toor measuri

    sound levela reference

    on Table

    s A an B scale C corr ales are:

    B5 and 85 ddB

    ment the ted the equipplitude fallred at 1.0ise level fa

    SPL):

    L meter istest and meg SPL is t

    measureme level of 1

    SPL & dB

    PDHonli

    imulate theesponds to

    B

    st Inspectoment beings in aproxi (3.3 feet)

    lls to 68 dB

    a device tasure the loe pascal (

    nts relativePa is used.

    e Course M

    human heasound beyo

    should betested, sincmately 6 d

    ill be redu.

    at measur udness of ta) and in lo

    to this levelThese refer

    475

    ing soundnd 85 dB a

    aware of th when the, in such aed to 74 d

    s the soue sound an

    garithmic sc

    , means 1 Pnces are d

    w

    apacity betnd scale D i

    e distanceistance do

    way, thatB. When th

    d pressur d for noiseale the dB-

    a is equalefined in A

    w.PDHonli

    een 40 ds restrict to

    between tbles. Consihen a noi noise is m

    waves inpollution moPL is used

    n SPL of 9SI S1.1-19

    e.org

    and 85aircrafts

    e noisedering ae of 80

    easured

    decibelsnitoring.

    .

    4 dB, or4.

  • 8/10/2019 Industrial Process Equipment

    23/60

    i

    t

    www.PDH

    ) Table of

    ) Sound P

    ound presressure ca

    n water with

    he commoean squa

    red the thr

    VIII.

    ibration isuch as theion has twbject moveovements

    he vibratioechnology980 "Tech

    requency :ycle of vibr ack again.z). One Hz

    center.com

    common s

    ressure:

    sure or acoused by a s a hydroph

    nly used "zre rms iseshold of h

    IBRATION

    the mechanmotion of a

    measurabls helps detare freque

    n equipmen(NIST) in aique of Ma

    A vibratingation occur The repetiti equals one

    und press

    Soun

    Hearing th

    Whisper

    Air conditi

    ConversatTraffic

    Loud mus

    Airplane

    stic pressuound wavne. The SI

    ero" referena statistical

    uman heari

    MEASURE

    ical oscillatipendulume quantitieermine itscy, amplit

    t calibratioccordancehinery Vibr

    object mov when theon rate ofcycle per s

    PDHonli

    re levels i

    d type

    reshold

    oner

    ion

    ic

    re is the lo. In air, souunit for sou

    ce soundmeasure ong , at 1 kH

    ENTS AN

    ons of an or random s: how far ibrational cde and ac

    n : should bith ISO 10

    tion Measu

    es back anbject move periodic e

    econd (CP

    e Course M

    dB-SPL:

    Sound l

    0 dB-SPL

    30 dB-SP

    50-70 dB-

    50-70 dB-60-85 dB-

    90-110 dB

    120-140 d

    cal pressur nd pressured pressure

    pressure if the magniz - or roughl

    D TESTS:

    bject aboutuch as theamplitude

    haracteristiceleration .

    e traceable012-1/1992rement.

    d forth froms from oneent, usuall).

    475

    vel (dB-SP

    PL

    PLPL

    -SPL

    -SPL

    e deviation can be meis the pasca

    air or othude of a vy the sound

    an equilibriovement

    r intensity),s. The mai

    to the Natiand Sectio

    its normalextreme po expressed

    w

    L)

    from the asured usinl (Pa).

    er gases isrying quan of a mosqu

    m point, wf a tire onand howterms use

    onal Institutns 5.1 and

    stationarysition to the in cycles p

    w.PDHonli

    mbient atm a microph

    20 Pa Rity), usuallyito flying 3

    hich may b gravel roaast (frequed to descri

    e of Stand5.2 of ANS

    osition. Aother extre

    er second (

    e.org

    osphericne, and

    S (rootconsid- away.

    regulard. Vibra-ncy) thee these

    rds andI S2.17-

    ompleteme, andHertz or

  • 8/10/2019 Industrial Process Equipment

    24/60

    i

    l(

    f f

    www.PDH

    mplitude: ntensity of

    cceleratiole of vibratioves in th

    Mea

    ophisticateachine ce

    edure or ay range, as

    FFT

    he FFT (FPM for the

    ess than 4Higher resoetween 0.3

    For For The The

    Acc

    cceleromeuch a wayrequency r acturer and

    center.com

    is the distibration dep

    n: is when ton. The vibr opposite d

    urement S

    d and comrtificationtemplate an the FFT an

    Analyser:

    st Fourierfrequency0 lines oflution mayX and 0.8X

    isplacemencceleration

    Dynamic RaFFT analyz

    lerometers

    ers are usethat the minge of theor Section

    ance from tends on a

    he speed oating objectirection tow

    ystem Acc

    on vibrationd acceptd have a malyser, sho

    Transform)range speciesolution, ie required

    Running Sp

    t and velocimeasuremnge shall br shall be c

    :

    d for data cimum freqtransducer.3, ANSI S

    PDHonli

    he stationaplitude. Us

    a vibratingslows dowrd the othe

    racy:

    n equipmennce. All of

    easurementn below:

    Analyzer fied for man which cato resolve "eed.).

    y measurents 20% o a minimupable of lin

    ertificationuency (F) aand can be.17-1980).

    e Course M

    y position tally expres

    object vari as it appro

    r extreme. U

    t systems athem shoul system am

    hall be caphine certifie the requi

    Side Bands

    ents l0%r 1.5 dB.

    of 72 dB.ear non-ove

    nd acceptand maximuaccurately

    475

    o the extreed in mete

    s from zeroaches the esually expr

    re used to t be calibrat

    plitude accu

    ble of a lination unlesrement def ," or in Ban

    or 1 dB.

    rlap averag

    nce. Accelem frequenmeasured (

    w

    e positions (m) or fee

    to a maxixtreme whessed in m/

    ake vibratioed accordinracy over t

    resolutions this restriults to 400 1 to resol

    ing.

    rometers sy (Fmax)

    recommend

    w.PDHonli

    on either st (ft).

    um duringre it stops,2.

    n measureg to a stane selected

    bandwidthtion wouldlines of re

    e machine

    ould be selre within thations of th

    e.org

    ide. The

    each cy-nd then

    ents forard pro-frequen-

    f = 300result insolution.ibration

    lected ine usablee manu-

  • 8/10/2019 Industrial Process Equipment

    25/60

    www.PDH

    he mass oystem over ot exceedonvert acc

    Vibr

    xial Direc

    adial Dire

    ertical Diounting pl

    orizontalr in the dire

    ther Direc

    or motorseadings on

    center.com

    f the accele the selecte10 % of thleration me

    tion Meas

    ion (A) : sh

    tion (R) : s

    ection (V) :te.

    irection (ction of the

    tion : Any ra

    r pumps ena surface o

    rometer and measuree dynamicasurements

    rement Ax

    ll be paralle

    all be at 90

    shall be i

    ): shall be ishaft (rotor)

    dial directio

    d mounted,posite the

    PDHonli

    its assement range.mass of it

    to velocity

    is Directio

    l to the rota

    (perpendi

    a radial d

    n a radial di rotation (se

    n other than

    vertical reaachine to

    e Course M

    ly minimalTypical m assemblyr displace

    s:

    tional axis o

    ular) relativ

    irection on

    rection, at ae figures be

    Horizontal

    dings shallhich the m

    475

    influence oss of accelstructure).ent, or to c

    f the machi

    e to the sha

    a machine

    right anglelow).

    or Vertical.

    e taken inotor or pum

    w

    the frequeerometer ahe integratnvert veloc

    e (see figur

    t (rotor) ce

    surface op

    (90) from

    radial dire is attache

    w.PDHonli

    ncy respond mounting

    ion is acceity to displa

    es below).

    terline.

    posite the

    he vertical

    tion relativ (see belo

    e.org

    e of theshouldtable toement.

    machine

    eadings

    to axial).

  • 8/10/2019 Industrial Process Equipment

    26/60

    www.PDH

    ocation Idirection of

    osition 1 :

    osition N :

    Mac

    hen a maounted to

    onditions s

    center.com

    entificationower flow p

    designates t

    designates

    ine Assem

    chine is bebe tested ahall be, as e

    : Measureer the follo

    he "out-boa

    the bearing

    bly:

    tested asan assem

    quivalent a

    PDHonli

    ent locatioing:

    rd" Starting

    location at t

    n individualed unit (e possible, t

    e Course M

    s shall be

    Power Poin

    he "termina

    l unit (e.g..g. motor/pu those to b

    475

    numbered c

    t bearing lo

    ing" Power

    motor, spinmp, motor/f encounter

    w

    onsecutivel

    ation of the

    Point beari

    dle, etc.) than, etc.), thd upon ins

    w.PDHonli

    from 1 to

    driver unit.

    g location.

    e machinemachine

    allation at s

    e.org

    N in the

    must beounting

    ite.

  • 8/10/2019 Industrial Process Equipment

    27/60

    t

    l

    t

    tf

    www.PDH

    Bea

    earings ar o the machue to the f

    ne of the live vibratioynamic loalement bea

    here, L10 tant load (

    utions; andurers cata

    s shown,o the third p

    Bala

    recision baechniques f icient to sialance a ro

    recision bquation ca

    here:

    center.com

    ings Vibrat

    the machiine frame.ct that only

    eading caun caused bds on the bring life for

    is the num) prior to faP is the actlogue and

    earing life iower of loa

    nce Calcul

    lance of moor achievinply performtor until it a

    lance meth be used to

    ion Tests:

    e componehis results

    10% to 20

    es of prem imbalanceearings. Th

    all Bearin

    er of hour igue failure;ual bearing is calcula

    s inverselyfor ball an

    tions:

    tors, rotor increaseda single phieves lo

    ods shouldcalculate r

    PDHonli

    nts that supin the perc of rolling e

    ture rollingand misalig design for s and Roll

    s 90% of a; C is the b load , statied during e

    roportionalto the 10/

    , pump imbearing lifelane balan vibration l

    also includsidual imba

    e Course M

    port and tr ption that

    lement bear

    element benment. Themulas (SKFer Bearing

    group of bearing load and dynaquipment d

    to speed a power for r

    ellers andand resultae of a roto

    evels.

    e the calculance:

    475

    nsfer the f earings are

    ings achiev

    aring failur resulting p, 1973) use are:

    rings shoulwhich will r ic. C is obtsign.

    d more sigoller bearin

    fans are tht equipme

    r to a level

    lation of re

    w

    orces frominherentlytheir desig

    is parasitirasitic loadd to calcula

    d attain orsult in a lifeined from

    nificantly, ins.

    e most critict reliability.of 0.10 in/s

    idual imbal

    w.PDHonli

    the rotatinga reliabilityn life.

    load due ts result in inte theoretic

    xceed und of one milli bearing m

    versely pro

    al and costIt is not usec , is it suf

    ance. The

    e.org

    elementproblem

    exces-creased

    al rolling

    r a con-on revo-anufac-

    ortional

    effectiveally suf-icient to

    ollowing

  • 8/10/2019 Industrial Process Equipment

    28/60

    t

    www.PDH

    r = amounr = actual ie = trial m = trial ma

    Effe

    ibration anmall deveecome a trovides thchedules olant mana

    han the oth

    xample:

    onsider af centrifug

    hus, 1 oz .75 lbs , as

    ow calcula

    upport a 10

    center.com

    of residualmbalance,ss imbalans.

    t of Imbala

    alysis, proploping mereat to the necessar

    f the plant oement has

    er way arou

    otor turningal force du

    of imbalanccalculated a

    te the effec

    00 lb. rotor.

    imbalance,

    e,

    nce:

    rly applied,hanical d

    integrity of lead timeperators /

    control ovd.

    at 3600 R to imbalan

    on a rotorbove.

    t of this we

    The calcul

    PDHonli

    allows thefects longthe machito suit the

    anagementr the mac

    M with 1 oce as show

    12" radius

    ight on bea

    ted bearing

    e Course M

    etection obefore thee, and thu needs an. In this wayines, rathe

    z. of unbala below, wh

    at 3600 RP

    ring life. Su

    life is less t

    475

    f

    ,r

    nce on a 12re:

    M creates a

    ppose that

    han 50% of

    w

    " radius . C

    n effective

    the bearing

    the design l

    w.PDHonli

    alculate the

    entrifugal

    s were des

    life as show

    e.org

    amount

    force of

    igned to

    n below.

  • 8/10/2019 Industrial Process Equipment

    29/60

    www.PDHcenter.com PDHonline Course M475 www.PDHonline.org

    Jurandir Primo 29 of 60

    The table below contains the ISO1940/1-1986 balance quality grades for various groups of repre-sentative rigid rotors. The following equations and discussion of permissible imbalance is based onISO 1940/1, Mechanical vibrationBalance quality requirements of rigid rotors .

  • 8/10/2019 Industrial Process Equipment

    30/60

    www.PDHcenter.com PDHonline Course M475 www.PDHonline.org

    Jurandir Primo 30 of 60

    Notes:

    1. For allocating the permissible residual unbalance to correction planes.

    2. A crankshaft/drive is an assembly which, includes a crankshaft, flywheel, clutch, pulley, vibrationdamper, rotating portion of connecting rod, etc.

    3. For the purposes of this part of ISO 1940, slow diesel engines are those with a piston velocity ofless than 9 m/s; fast diesel engines are those with a piston velocity of greater than 9 m/s.

    4. In complete engines, the rotor mass comprises the sum of all masses belonging to the crank-shaft/drive described in note 3 above.

    Machine Alignment:

  • 8/10/2019 Industrial Process Equipment

    31/60

    t

    t

    www.PDH

    oupled She rotationa

    aser Shaf combined

    arget detec

    haft Alignpecified inr or by the

    center.com

    afts Aligml centerline

    Alignmentlaser emitte

    or.

    ment Toler the table bepurchasing

    nt : Couple of their sh

    : The Laser r and laser

    ances : Alllow, unlessngineer for

    PDHonli

    shaft alignfts are coli

    Alignmenttarget dete

    shaft-to-shamore preci special ap

    e Course M

    ment is theear at the c

    System is utor unit or

    ft centerlinee tolerancelications.

    475

    positioningoupling cen

    sed for Coueparate uni

    alignments are specif

    w

    f two or moer under op

    pled Shaftsts for its la

    shall beied by the

    w.PDHonli

    re machineerating con

    Alignment f er emitter a

    ithin the tolachine ma

    e.org

    s so thatditions.

    or eithernd laser

    lerancesufactur-

  • 8/10/2019 Industrial Process Equipment

    32/60

    i

    www.PDH

    xial Shaftent must b

    he table bmum accep

    he use oflignment to

    center.com

    Play : muste done with

    low providetable misali

    precisionlerances wit

    be no greaout inducin

    limitationsnment is b

    quipment hin precisio

    PDHonli

    er than 0.1 abnormal l

    and effect osed on exp

    and methon standards

    e Course M

    5 inch (3.1oads in the

    f misalignerience dat

    s, such as, is recomm

    475

    75 mm). Acconnecting

    ent on rolli in bearing

    reverse diended, as s

    w

    commodatiquipment.

    ng elementmanufactu

    al and lashown below

    w.PDHonli

    n of the en

    bearings. Trers catalo

    r systems:

    e.org

    d move-

    he max-gs .

    to bring

  • 8/10/2019 Industrial Process Equipment

    33/60

    www.PDHcenter.com PDHonline Course M475 www.PDHonline.org

    Jurandir Primo 33 of 60

    Contrary to popular belief, both laser alignment and reverse dial indicator equipment offer equallevels of precision; however, laser alignment is considerably easier and quicker to learn and use. Therecommended specifications for precision alignment are provided in the table shown below:

    Alignment Effects:

    The forces of vibration from misalignment also cause gradual deterioration of seals, couplings, drivewindings, and other rotating elements where close tolerances exist. Based on data from a petrochemi-cal industry survey, precision alignment practices achieve:

    Average bearing life increases by a factor of 8.0. Maintenance costs decrease by 7%. Machinery availability increases by 12%.

    IX. PUMP PERFORMANCE AND TESTS:

    A critical function of any pump manufacturer is the performance testing of their product to ensure that itmeets design specifications. Test facilities are designed to provide performance and NPSHR tests inaccordance with the latest edition of API 610 or the Hydraulic Institute.

    Test Softwares allow all parameters to be monitored and controlled from a central control station,providing precise control to achieve and maintain specific operating conditions, so that data from pre-cision electronic sensors can be collected and recorded for use in verifying pump performance.

    Variable Frequency Drive: is always utilized to maintain precise speed control on units to achieve acontrolled acceleration up to synchronous operating speed. Flow is commonly measured by calibratedmagnetic flow meters installed in metering runs, while calibrated electronic sensors measure pressureat compliant metering spools connected to the suction and discharge nozzles of the pump. NPSH test-ing is performed using vacuum suppression method.

  • 8/10/2019 Industrial Process Equipment

    34/60

    www.PDHcenter.com PDHonline Course M475 www.PDHonline.org

    Jurandir Primo 34 of 60

    Mechanical Seals:

    Pumps provided with mechanical seals should be tested with its own seal and no leaks shall be al-lowed. In case a leak is confirmed during the test, the mechanical seal should be dismounted, ana-lysed about the wearing and replaced.

    Drive Motor:

    When it is possible, the pump should be tested with its own motor , since there is the possiblity to usethe same operation conditions, such as the same flow fluid and power consumption. It is also neces-sary to correct fluid viscosity, flow curves, manometric height and hydraulic efficiency using definedtables or a mathematical abacus.

    Brake Horse Power (BHP) Evaluation:

    The best way to define a pump efficiency is to measure the consumed power during its performancetest. The measured power should not exceed 4% the specified value, considering some limitations ofelectrical energy in the work site. The BHP can be evaluated by two (2) methods:

    With a voltmeter and a wattmeter; Without instruments.

    a) With a voltmeter and a wattmeter:

    The Inspector shall read each flow point, the electric voltage and current using a voltmeter and awattmeter . Then, he should find in the calibrated motor performance curve, its efficiency and the pow-er factor in function of the measured current, using the following formula below:

    P = BHP PowerV = Electric VoltageI = Electric Current

    = Calibrated Motor Efficiency

    Cos = Power Factor

    Example:

    During a pump performance test, the following electrical variables below were found, for power evalua-tion of an electric motor 20 HP, 440V / II poles (remember 20 HP = 14.9 kW):

    V = 422 VI = 21 A

    = 0.84

    Cos = 0.89

  • 8/10/2019 Industrial Process Equipment

    35/60

    www.PDHcenter.com PDHonline Course M475 www.PDHonline.org

    Jurandir Primo 35 of 60

    P = 422 x 21 x 0.89 x 0.84 x 0.001732 =

    P = 11.46 kW

    Obs.: Then 11.46 kW is the correct power for this electric motor using the above electrical conditions.

    b) Without instruments:

    In case there is no possibility to have a voltmeter, wattmeter and the calibrated curve is not available,it is possible to estimate the consumed power associating the voltage, current and nominal motorpower. Due this calculation is not accurate, the power evaluation can be done using the formula below:

    Where:

    Vt = Estimated available tensionVn = Nominal electric motor tensionIt = Estimated available currentIn = Nominal electric motor currentPn = Nominal power

    Example:

    During a power evaluation with an electric motor 20 HP, 440V and 30A, in the operation point was veri-fied the following electric variables:

    Vt = 422 VIt = 21 A

    P = 422 x 21 x 20440 30

    P = 13.42 HP

    The hydraulic efficiency can also be calculated. The Brake Horsepower (BHP) is the actual horse-power delivered to the pump shaft, defined as follows:

    BHP = Q x H x SG x P 3960

    Where:

    Q = Capacity in gallons per minuteH = Total Differential Head in absolute feetSG = Specific Gravity of the liquidP = Pump efficiency as a percentage

  • 8/10/2019 Industrial Process Equipment

    36/60

    ------

    ---

    t

    i

    f

    www.PDH

    ote: The ceight of on

    Com

    DischargeSupply tan

    Vibration, t Variable F Soft start f Calibrated

    Torque co NPSHR te Pumping t

    Eval

    he term No avoid thePSH to be

    PSHr: can

    ng to applyumps man

    PSHa: is trom that mble NPSH

    PSHa (ava

    center.com

    onstant (3e gallon of

    mon Pump

    test pressur k rated fromorque, tempequency Dr r low impa

    magnetic fl

    plings provit accomplisst procedur

    uation of N

    SH meanscavitation

    understood

    be found i

    in a projectfactured by

    he normal cnufacturingf a pump is

    ilable) > NP

    60) is thewater (8.33

    ing Tests:

    es;full vacuuerature andive for precit motor star w meters;

    de data tohed througes based o

    PSH:

    Net Positivor corrosioare the the

    n a manuf

    or installat the compa

    alculation th catalog, wi necessary

    SHr (requir

    PDHonli

    umber of fo pounds) .

    ;speed mea

    se speed coting;

    alculate bra the use of API 610 cr

    e Suctionof the par

    NPSHr (re

    cturing ca

    ion. The my, indicatin

    e techniciall better fit ito know the

    ed).

    e Course M

    ot-pounds i

    suring equintrol;

    ke horsepoa vacuum piteria or me

    ead . Thets during thuired) and

    alog of pu

    nufacturerg the requir

    or the eng his projectfollowing co

    475

    n one hors

    ment;

    er and effiump;t specific c

    otive to cale normal pNPSHa (av

    ps , a tech

    lways shoed NPSH f

    ineer has to or installatincepts:

    w

    epower (33

    iency;

    stomer req

    ulate the Nocess. Theilable).

    nician or a

    s the grapr each prod

    perform toon. Then, t

    w.PDHonli

    ,000) divide

    uirements.

    PSH of anymain con

    engineer i

    ic curves ouct.

    find whichcalculate t

    e.org

    d by the

    pump isepts of

    choos-

    f all line

    f pump,he avail-

  • 8/10/2019 Industrial Process Equipment

    37/60

    t

    i

    www.PDH

    Calc

    s explainePSHa. Th

    PSHa =ressure H

    oss in pipinPSHa = +-

    = Staticive), in feeta = Atmos

    n feetv = Vaporf = See ta

    xample:

    1) Fi

    old waterlow velocitpecific grateel Piping

    H =Pa =Pv =

    ccording to

    sing the a

    PSHa = +-

    H - StatiPa - AtPv WaHf - 100

    Pipin

    Fittin

    otal friction

    PSHa (av

    PSHa (av

    PSHa (av

    center.com

    ulation of t

    above the NPSHa (c

    - Staticad - Vapo

    g, valves a H + Pa P

    uction He

    pheric pres

    pressure (ples indicati

    nd the NPS

    umping, Q , v = 10 ft/sity, Sg = 1.

    (suction a

    iquid level i AtmospheriWater vapo

    pump man

    ove formul

    H + Pa P

    head = +5ospheric pr ter vapor pr gpm - throu

    g friction lo

    gs friction lo

    loss for pip

    ilable) = +-

    ilable) = +

    ilable) = 32

    e NPSH P

    calculationnverted to

    ead + At Pressure

    d fittings:v - Hf

    d (positive

    sure (psi x

    i x 2.31/Sg)g friction lo

    Ha from be

    100 gpm(maximum

    0 (clean wand discharg

    s above puc pressurer pressure

    ufacturer th

    :

    v Hf

    feet ssure = psi

    essure at 6gh 2 inches

    s = Hf 1 = 1

    ss = Hf 2 =

    ing and fittin

    H + Pa P

    + 34 - 0.7

    .34 feet (N

    PDHonli

    ocess:

    is for theead) is:

    osphericFriction

    or nega-

    2.31/Sg),

    , in feet.ss. Fittings f

    low data:

    68F;;er).e) = 2 inch

    p centerlin 14.7 psi -t 68F = 0.

    NPSHr (re

    x 2.31/Sg.F = psi x 2pipe shows

    ft / 100 x 3

    x v/2g =

    gs = Hf = (

    v Hf =

    5.38 =

    SHa) > 24

    e Course M

    riction loss i

    diameter, to

    e = + 5 feetthe tank is39 psi .

    quired), as

    = 14.7 x 2.3.31/Sg = 0. a loss of 3

    6.1 = 3.61 f

    .57 x 10 (2 x 32.17

    f 1 + Hf 2) =

    feet (NPSH

    475

    s (K x v/2g

    tal length10

    t sea level

    er the pum

    1/1.0 = +3439 x 2.31/1.1 feet for e

    eet

    2) = 1.77

    .61 + 1.77

    r) , so, the s

    w

    ), in feet.

    feet, plus 2

    p curve) = 2

    feet absol.0 = 0.78 feach 100 fe

    = 5.38 feet.

    stem has p

    w.PDHonli

    x 90 elbo

    4 feet .

    te et t of pipe , t

    lenty to spa

    e.org

    ;

    en:

    re.

  • 8/10/2019 Industrial Process Equipment

    38/60

    www.PDHcenter.com PDHonline Course M475 www.PDHonline.org

    Jurandir Primo 38 of 60

    X. BEARING TEMPERATURE EVALUATION:

    We define temperature taken at the bearing cap surface . The normal procedure is that an operatingtemperature at the bearing cap can not exceed 175F (80 C) , as long as the temperature has leveledout and not still rising.

    Temperatures up to 200F (90 C) can also be satisfactory , but further investigation is recommend-ed to determine the cause of the higher bearing operating temperature. In pumps for boiler feed appli-cations, handling hot water, above boiling point and other high temperature applications, the bearingtemperature may approach this higher limit from heat transfer along the shaft and still perform satis-factorily.

    Special consideration of lubricants , water cooling or special bearing clearances may be required forpumping temperatures above 250F (120 C) on general-purpose bearings before heat treating fordimensional stability is recommended.

    Excessive lubrication of bearings should be avoided as it may result in overheating and possiblebearing failure. Under normal applications, adequate lubrication is assured if the amount of grease ismaintained at 1/3 to the capacity of the bearing and adjacent space surrounding it. We recommendusing a premium lubricant equal to Number 2 (polyurea base).

    These temperatures apply to grease-lubricated as well as oil-lubricated bearings. New bearingsoften require a break-in period of up to 100 hours . During this time, temperatures and noise levelscan be slightly elevated. However, these levels should decrease somewhat after this break-in period.

    Siemens, Westinghouse, and GE elliptical friction bearings typically alarm up to a temperature at265F (130C), well privileged to work on such currently alarm. For cooling water pumps and opendrip proof motors bearing housings the range is commonly

  • 8/10/2019 Industrial Process Equipment

    39/60

    www.PDHcenter.com PDHonline Course M475 www.PDHonline.org

    Jurandir Primo 39 of 60

    Pump Bearing Temperature:

    The maximum operating temperature for a ball bearing in a pump is the result of a number of factors,not limited to, but including some or all of the following:

    1) Operating speed;2) Shaft loading;3) Type of lubrication;4) Amount of lubricant in the bearing;5) Pump alignment;6) Pumping temperature;7) Ambient temperature;8) Bearing fits;9) Continuous or on-off service;10) Location of the pump duty point on the performance curve

    XI. FAILURE DIAGNOSTIC DETECTION:

    The advent of micro-processor based valve instruments in-service diagnostics capabilities has al-lowed companies to redesign their control valve maintenance work practices. More specifically, in-service diagnostics oversee:

    1. Instrument Air Leakage : This diagnostic can detect both positive (supply) and negative (exhaust)air mass flow not only to detect leaks in the actuator or related tubing, but also much more difficultproblems. For example, in piston actuators, the air mass flow diagnostic can detect leaking pistonseals or damaged O-rings.

    2. Supply Pressure : This in-service diagnostic will detect low and high supply pressure readings foradequate supply pressure to detect and quantify droop in the air supply during large travel excursions.

    This is particularly helpful in identifying supply line restrictions.

    3. Travel Deviation and Relay Adjustment : The travel deviation diagnostic is used to monitor actua-tor pressure and travel deviation from setpoint and identify a stuck control valve, active interlocks, lowsupply pressure or shifts in travel calibration.

    4. Instrument Air Quality : The I/P and relay monitoring diagnostic can identify problems such asplugging in the I/P primary or in the I/P nozzle, instrument diaphragm failures, I/P instrument O-ringfailures, and I/P calibration shifts, as well, in identifying problems from contaminants in the air supplyand from temperature extremes.

    Types of Protection:

    The types of protection commonly used for instruments are:

    1. Dust Ignition-proof: A type of protection that excludes ignitable amounts of dust will not allow arcs,sparks or heat otherwise generated or liberated inside the enclosure to cause ignition of exterior ac-cumulations or atmospheric suspensions of a specified dust.

  • 8/10/2019 Industrial Process Equipment

    40/60

    www.PDHcenter.com PDHonline Course M475 www.PDHonline.org

    Jurandir Primo 40 of 60

    2. Explosion-proof: A type of protection that utilizes an enclosure that is capable of withstanding anexplosion of a gas or vapor within it and of preventing the ignition of an explosive gas or vapor thatmay surround it.

    3. Intrinsically Safe: A type of protection in which the electrical equipment under normal or abnormalconditions is incapable of releasing sufficient electrical or thermal energy to cause ignition of a specifichazardous atmospheric mixture.

    4. Non-Incendive: A type of protection in which the equipment is incapable, under normal conditions,of causing ignition of a specified flammable gas or vapor-in-air mixture due to arcing or thermal effect.

    NEC Hazardous Location Classification:

    Hazardous areas procedures are classified by class, division, and group . The method was intro-duced into the 1996 edition of the NEC as an alternate method, but it is not yet in use. The zonemethod is common in Europe and most other countries.

    Class : defines the general nature of the hazardous material in the surrounding atmosphere.

    Class I . Locations in which flammable gases or vapors are, or may be, present in the air in quantitiessufficient to produce explosive or ignitable mixtures.

    Class II . Locations that are hazardous because of the presence of combustible dusts.

    Class III . Locations in which easily ignitable fibers or flyings may be present but not likely to be in sus-pension in sufficient quantities to product ignitable mixtures.

    Division : The Division defines the probability of hazardous material being present in an ignita-ble concentration in the surrounding atmosphere.

    Division 1 : Locations in which the probability of the atmosphere being hazardous is high due to flam-mable material being present continuously, intermittently, or periodically.

    Division 2 : Locations that are presumed to be hazardous only in an abnormal situation.

    Group: The Group defines the hazardous material in the surrounding atmosphere. The specifichazardous materials within each group and their automatic ignition temperatures can be found in Arti-cle 500 of the NEC and in NFPA 497M. Groups A, B, C and D apply to Class I, and Groups E, F and Gapply to Class II locations. The following definitions are from NEC:

    Group A : Atmospheres containing acetylene.

    Group B : Atmospheres containing hydrogen, fuel and combustible process gases containing morethan 30 percent hydrogen by volume, or gases or vapors of equivalent hazard such as butadiene, eth-ylene oxide, propylene oxide, and acrolein.

    Group C : Atmospheres such as ethyl ether, ethylene, or gases or vapors of equivalent hazard.

    Group D : Atmospheres as acetone, ammonia, benzene, butane, cyclopropane, ethanol, gasoline,hexane, methanol, methane, natural gas, naphtha, propane, or gases or vapors of equivalent hazard.

  • 8/10/2019 Industrial Process Equipment

    41/60

    www.PDHcenter.com PDHonline Course M475 www.PDHonline.org

    Jurandir Primo 41 of 60

    Group E : Atmospheres containing combustible metal dusts, including aluminum, magnesium, andtheir commercial alloy, or other combustible dusts whose particle size, abrasiveness, and conductivitypresent similar hazards in the use of electrical equipment.

    Group F : Atmospheres containing combustible carbonaceous dusts, including carbon black, charcoal,coal, or dusts that have been sensitized by other materials so that they present an explosion hazard.

    Group G : Atmospheres containing combustible dusts not included in Group E or F, including flour,grain, wood, plastic, and chemicals.

    The NEC states that any equipment that does not exceed a maximum surface temperature of 100 C(212 F) is not required to be marked with the temperature code. Therefore, when a temperature codeis not specified , it is assumed to be T5 .

    NEMA Hazardous Locations:

    Two of four enclosure ratings for classified locations are described as follows in NEMA 250:

    Type 7: (Class I, Division 1, Group A, B, C or D, Indoor hazardous location, Enclosure): For indooruse in locations classified as Class I, Division 1, Groups A, B, C or D as defined in the NEC and shallbe marked to show class, division, and group. Capable of withstanding the pressures resulting from aninternal explosion of specified gases.

    Type 9: (Class II, Division 1, Groups E, F or G, Indoor hazardous location, Enclosure): Intended foruse in indoor locations classified as Class II, Division 1, Groups E, F and G as defined in the NEC andshall be marked to show class, division, and group. Enclosures shall be capable of preventing the en-trance of dust.

    NEMA Enclosure Ratings:

    Enclosures may be tested to determine their ability to prevent the ingress of liquids and dusts. In theUnited States, equipment is tested to NEMA 250. Some of the more common enclosure ratings de-fined in NEMA 250 are as follows.

    Type 3R: (Rain-proof, Ice-resistance, Outdoor enclosure): Intended for outdoor use primarily to pro-vide a degree of protection against rain, sleet, and damage from external ice formation.

    Type 3S: (Dust-tight, Rain-tight, Ice-proof, Outdoor enclosure): Intended for outdoor use primarily toprovide a degree of protection against rain, sleet, windblown dust, and to provide for operation of ex-ternal mechanisms when ice ladened.

    Type 4: (Water-tight, Dust-tight, Ice-resistant, Indoor or outdoor enclosure): Intended for indoor oroutdoor use primarily to provide a degree of protection against windblown dust and rain, splashingwater, hose-directed water, and damage from external ice formation.

    Type 4X: (Water-tight, Dust-tight, Corrosion resistant, Indoor or outdoor enclosure): Intended for in-door or outdoor use primarily to provide a degree of protection against corrosion, windblown dust andrain, splashing water, and hose-directed water, and damage from external ice formation.

  • 8/10/2019 Industrial Process Equipment

    42/60

  • 8/10/2019 Industrial Process Equipment

    43/60

    www.PDH

    XII.

    ote: V c

    Com

    oltage - Vurrent - Iesistance ower - P =

    Tabl

    To Find

    AmpsHorsep

    AmpsKilowat

    AmpskVA is

    Kilowat

    Kilovolt

    Horsep(output)

    bs. : E = V

    center.com

    ASIC ELE

    omes from "

    mon Electr

    = I R = PV / R = P /

    - R = V / I = V I = R

    e of Comm

    henwer is kno

    hens is known

    hennown

    s

    -Amps

    wer

    ltage / I =

    TRICAL F

    voltage" an

    ical Formul

    I = (P RV = (P / R V2 / P = PI2 = V2 / R

    n Electric

    Direct

    wnHP x

    E x

    kW x

    I x10

    I x E74

    mps /W =

    PDHonli

    RMULAE:

    E from "

    ae:

    ) - in volts- in amper

    I2 - in ohm- in watts W

    l Formula

    AC/

    urrent AC11

    746Eff E

    1000 k

    k

    E0

    I

    x Eff6

    I x

    atts / PF =

    e Course M

    electromoti

    s A

    s

    :

    C Formula

    / 1phasev or 120v

    P x 746Eff X PF

    x 1000E x PF

    A x 1000E

    x E x PF1000

    I x E1000

    x Eff x PF746

    Power Fact

    475

    e force". E

    s

    AC / 1ph208,230, or

    HP x 74E x Eff x

    kW x 10E x PF

    kVA x 10E

    I x E x1000

    I x E1000

    I x E x Eff746

    or / Eff = Ef

    w

    means al

    se240v

    6PF 1.7

    01

    00

    F I

    I

    PF I x E

    iciency / H

    w.PDHonli

    o energy.

    C 3 phasell Voltages

    HP x 746 x E x Eff x

    kW x 1000.73 x E x P

    VA x 10001.73 x E

    E x 1.73 P1000

    x E x 1.731000

    Eff x 1.73746

    = Horsepo

    e.org

    PF

    PF

    wer

  • 8/10/2019 Industrial Process Equipment

    44/60

    I

    I

    l

    www.PDH

    xample:

    n this circuiepts, deter

    hen,

    o determin

    XIII.

    n pipelines,ressure ans that thehe ASME

    = gasket f = minimu

    he m factxerted on t

    og may spe

    = 1600 psi = 2100 psi = 2600 psi = 3000 psi

    xample:

    sing a car f 70F, flaalculate th

    center.com

    below, weine curren

    e power,

    BOLT T

    , choosingd temperatuasket is gr III Div.1 - A

    actor = 2.00 design sea

    or is an exphe gasket dcify:

    for a 3/16for 1/4;for 3/8;for 1/2;

    on steel wange class 1 bolting stre

    have a batt and power

    RQUE EV

    gasket thre such asup Ia and

    ppendix 2,

    ;ting pressu

    erimentallyring asse

    gasket,

    ter piping50 #, ASMss. Use mi

    PDHonli

    ry voltage:

    LUATION:

    t is compaa 1/8 thickur choice iive us two

    re = 1,600 p

    determinedbly, to the h

    ith 4, withB16.5. Kn

    imum requi

    e Course M

    f 18 V and

    tible with trubber gas compatibl

    gasket facto

    si.

    factor. It isighest syst

    a design pr owing the flred bolt prel

    475

    a lamp resi

    e fluid andet, the AS with the rers:

    the ratio ofm pressure

    ssure of 16nge will re

    oad, Wm =

    w

    tance of 3

    compatiblE VIII Div.

    commendat

    the compre in service.

    5 psi and aquire 8 bolt9,000 lb .

    w.PDHonli

    . Using ab

    with the o1 - Appendiion of ASM

    sive pressFor exampl

    design tems of 5/8 di

    e.org

    ve con-

    perating2, tellsB16.5.

    re to bea cata-

    peratureameter ,

  • 8/10/2019 Industrial Process Equipment

    45/60

    www.PDHcenter.com PDHonline Course M475 www.PDHonline.org

    Jurandir Primo 45 of 60

    Consider the load needed to stress the gasket to a value y and seat the gasket. In our case y =1600 psi . We need a class 150 flange, 8-bolts assembly , to sustain a preload Wm = 9000 lb. . Atthis installation, each bolt must have a tension of at least:

    Bolt tension : F = 9,000/8 = 1125 lb.

    According to the tabel below (and Table 8 of ASME B16.5), for a 4 class 150 lb flange. Using the ex-ternal diameter of the 5/8 bolt is we find an area of 0.5168, which corresponds to:

    Bolt root area : 5/8 11 threads/inch = 0.202 in.

    SizeMajor

    DiaThreads Per

    InchPitchDia

    Minor Dia Ex-ternal

    Minor DiaInternal

    Minor DiaArea

    3/8 0.375 16 0.3344 0.3005 0.3073 0.0678

    0.5 13 0.45 0.4084 0.4167 0.1257

    5/8 0.625 11 0.566 0.5168 0.5266 0.202

    0.75 10 0.685 0.6309 0.6417 0.302

    1 1 8 0.9188 0.8512 0.8647 0.551

    Given the installation tension of 1125 lb per bolt , over an area of 0.202 in , the tensile stress appliedto the bolt during preload to compress the joint is:

    Bolt tensile stress: = F/A bolt = 1125/0.202 = 5569 psi.

    The ASTM A193 Gr.B7 bolt at ambient temperature, its allowable stress is S = 23,000 psi. The boltyield and ultimate strength is Sy = 95,000 psi. Using the minor root diameter of bolt 5/8 , the pre-

    load stress of 5569 psi is well within the material allowable stress. Other calculation to minimumbolt torque Tmin ., needed to achieve a preload is:

    Tmin = K.Fi.d , where:

    Tmin = minimum bolt torque, in-lb,K = nut factor (lubricated bolts = 0.10 ~ 0.20); hot dip galvanized bolts = 0.25); (plain bolts = 0.20).Fi = (1125 lb recommended preload), lb,d = nominal bolt diameter, in.

    Using the table below : Clampload is calculated at 75% of the proofload and is only a estimatednumber, to be tensioned to a different value.

    T = K.D.P , where:

    T = Torque,K = torque coefficient (see table),D = nominal diameter (inches),P = bolt clamp load, lb (see table)

  • 8/10/2019 Industrial Process Equipment

    46/60

    www.PDHcenter.com PDHonline Course M475 www.PDHonline.org

    Jurandir Primo 46 of 60

    Calculation using the bolt stress area, according to ASTM 574:

    Using this formula a 5/8 11 threads/inch, the stress area is = 0.226 in 2

    Where:

    D = Nominal diameter, in.;n = Number of threads per inch;

  • 8/10/2019 Industrial Process Equipment

    47/60

    www.PDHcenter.com PDHonline Course M475 www.PDHonline.org

    Jurandir Primo 47 of 60

    Common Bolt Materials Torque:

    ASTM A307

    Bolt Size Tightening Torque (ft-lb)

    Waxed Galv Plain1 4 2 4 4

    5 16 4 9 7

    3 8 7 16 13

    7 16 10 26 21

    1 2 16 40 32

    9 16 23 58 46

    5 8 32 79 64

    3 4 56 141 113

    7 8 83 208 166

    1 125 313 250

    11 8 177 443 354

    11 4 250 625 500

    13 8 327 819 655

    11 2 435 1088 870

    13 4 748 1870 1496

    2 1125 2813 2250

    21 4 1645 4113 3291

    21 2 2250 5625 4500

    23 4 3050 7626 6101

    3 4030 10074 8060

    31 4 5192 12980 10384

    31 2 6560 16400 13120

    33 4 8151 20377 16301

    4 9972 24930 19944

    SAE GRADE 2

    Bolt Size Tightening Torque (ft-lb)

    Waxed Galv Plain1 4 3 7 5

    5 16 6 14 11

    3 8 10 25 20

    7 16 16 40 32

    1 2 24 61 49

    9 16 35 88 70

    5 8 48 121 97

    3 4 86 216 173

    7 8 83 208 166

    1 125 313 250

    11 8 177 443 354

    11 4 250 625 500

    13 8 327 819 655

    11 2 435 1088 870

    ASTM A325

    Bolt SizeTightening Torque Range (ft-lb)(Min - Max)

    Waxed Plain

    1 2 50 - 58 100 - 117

    5 8 99 - 120 198 - 240

    3 4 175 - 213 350 - 425

    7 8 284 - 343 569 - 685

    1 425 - 508 850 - 1017

    11 8 525 - 625 1050 - 1256

    11 4 740 - 885 1479 - 1771

    13 8 974 - 1169 1948 - 2338

    11 2 1288 - 1550 2575 - 3100

  • 8/10/2019 Industrial Process Equipment

    48/60

    www.PDHcenter.com PDHonline Course M475 www.PDHonline.org

    Jurandir Primo 48 of 60

    XIV. COMMISSIONING PROCESSES:

    Commissioning is a systematic process of ensuring that all equipment systems perform interac-tively according to the contract documents, the design intent and the owners operational needs. Thisis achieved ideally by beginning in the pre-design phase with design intent development and docu-mentation, and continuing through design, construction and the warranty period with actual verificationthrough review, testing and documentation of performance.

    The commissioning process integrates the traditionally separate functions of design peer review ,equipment startup, control system calibration, testing, adjusting and balancing, equipment documenta-tion and facility staff training, and adds the activities of documented functional testing and verification.

    Commissioning is occasionally confused with testing , adjusting and balancing (TAB) . Testing, ad- justing and balancing measures building air and fluid flows , but commissioning encompasses amuch broader scope of work. Building commissioning typically involves four distinct phases in whichspecific tasks are performed by the various team members throughout the construction process.

    The four phases are pre-design, design, construction, and warranty. As part of the constructionphase, commissioning involves functional testing to determine how well mechanical and electrical sys-tems meet the operational goals established during the design process. Although commissioning canbegin during the construction phase, owners receive the most cost-effective benefits when the processbegins during the pre-design phase at the time the project team is assembled.

    A properly commissioned facility can result in fewer change orders during the construction process,fewer call-backs, long-term tenant satisfaction, lower energy bills, avoided equipment replacement costs , and an improved profit margin for building owners once the building is occupied. Commis-sioning also assures that the buildings operational staff is properly trained and that the operations andmaintenance manuals are compiled correctly at project turn-over.

    Benefits of Commissioning:

    Until recently, the most frequently mentioned benefit of commissioning was its energy related value.Building commissioning ensures that the energy savings expected from the design intent are imple-mented correctly. While these benefits are significant, they are far outweighed by the non-energy-related benefits of commissioning. These include:

    Proper and efficient equipment operation Improved coordination between design, construction and occupancy Improved indoor air quality, occupant comfort, and productivity Decreased potential for liability related to indoor air quality, or other HVAC problems

    Reduced operation and maintenance costs

    Existing Building Commissioning:

    Commissioning also can be applied to existing buildings to restore them to optimal performance.Retrocommissioning is a systematic, documented process that identifies low-cost O&M (Operation &Maintenance) improvements in an existing building and brings it up to the design intentions of its cur-rent usage. In many cases as a building is used over time, equipment efficiency and tenant build-outsor renovations change how the building functions.

  • 8/10/2019 Industrial Process Equipment

    49/60

    www.PDHcenter.com PDHonline Course M475 www.PDHonline.org

    Jurandir Primo 49 of 60

    Retrocommissioning identifies and solves comfort and operational problems, explores the full potentialof the facilities energy management system, and ensures that the equipment performs properly afterspace changes have been made. Continuous commissioning is similar to retrocommissioning and be-gins by identifying and fixing HVAC and comfort problems in the building.

    In continuous commissioning, when the commissioning is complete, the team continues to work to-gether to monitor and analyze building performance data provided by permanently installed meteringequipment. This process works to ensure that the savings achieved from the commissioning continueto persist over time.

    The Commissioning Team:

    The commissioning team does not manage the design and construction of the project, but mayinclude facility staff for possibly testing or diagnostic the utility process equipment. Its purpose is topromote communication among team members and the early identification and resolution of problems.

    Any project involving commissioning should begin with a commissioning scoping meeting , which allteam members are required to attend. At this meeting, the roles of each team member are outlinedand the commissioning process and schedule are described. Commissioning team members mostoften include the building owner or project manager, commissioning provider, design professionals,installing contractors and manufacturers representatives.

    Professional Qualifications:

    Direct responsibility for project management of at least two commercial construction or installationprojects with mechanical costs greater than or equal to current project costs; Experience in design installation and/or troubleshooting of direct digital controls and energy man-agement systems, if applicable. Demonstrated familiarity with metering and monitoring procedures.

    Knowledge and familiarity with air/water testing and balancing. Experience in planning and delivering O&M training. Building contracting background and complete understanding of all the building systems, includingbuilding envelope, structural, and fire/life safety components.

    Testing Specialists:

    If the complexity of the project requires special testing , the specialists performing these tests shouldalso be involved in commissioning. Test results and recommendations from these specialists shouldbe submitted to the commissioning provider for review. They may also be required to review documen-tation relating to the systems they test and to train operators on the proper use of this equipment.

    Design Phase:

    The optimum time to hold the commissioning scoping meeting is during the design phase. At thismeeting, the commissioning provider outlines the roles and responsibilities of the project team mem-bers with respect to commissioning and reviews the commissioning plan outline and schedule. Teammembers provide comment on the plan and schedule, and the commissioning provider uses thesesuggestions to complete the final commissioning plan.

  • 8/10/2019 Industrial Process Equipment

    50/60

    (

    tt

    t

    t

    t

    www.PDH

    he main coowners proating comm

    uring the bo meet theheir designancy loadsment whicesign inten

    Con

    uring theests are uhecklists ahe construcefore the f

    uring thisent, opera

    he equipmeerve condit

    Mini

    . Commissiembers r

    ach test wil

    center.com

    mmissionin ject requireissioning int

    eginning ofowners projfor sizing a

    etc.) The d the comm

    t. As the de

    truction P

    constructioned to ensur re usually ction checklinctional tes

    phase, thetion and mant accessor ions that mi