Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at...

756
A work based on personal experience for improving young engineers / students knowledge Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page 1 of Civil Engineering Buildings Practice Construction Method Statements General Activities P Eng Suraj Singh Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Transcript of Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at...

Page 1: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

1 of

Civil EngineeringBuildings Practice

Construction Method Statements

General Activities

P Eng Suraj Singh

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 2: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

2 of

Contents index For navigation please click these pasted hyperlinks

Construction Method Statements for various activities within civil engineering for plants worksSite Preparation & Earth Work PROTECTION OF EXISTING

SERVICESRE-ROUTING OF 33KV CABLESConcrete Pipe Culverts

CONCRETING TO WALLS OF CENTRAL CONTROL BUILDING / LABORATORY

CONCRETE PIPE CULVERTS

CULVERT CROSSINGS TO AVENUE E AND MAIN HIGHWAY.

PLACING CONCRETE ON SERVICE WATER TANK 58-TK-205 FOUNDATIONS

CONCRETE REPAIRTop

CONSTRUCTION OF PIPE RACK BASES

EXCAVATION IN Operating Authority CONTROLLED AREAS

CONSTRUCTION OF MAIN SUBSTATION

REMOVAL OF HAZARDOUS MATERIALS

CONSTRUCTION OF FLOOR SLAB CENTRAL CONTROL BUILDING

MORTAR FOR BLOCKWORK CONTROL OF CAMP SEWAGE SYSTEM

STRUCTURAL STEEL-PIPERACKS COMPRESSORS’ STRUCTURES RCC COLUMN PLATE INSERTS

EXCAVATION FOR 132KV CABLE INTERCONNECTION

ROAD CROSSING FOR 132 KV ROUTE

NIGHT SHIFT WORKING - EARTHWORKS

GROUTING TO PIPE RACK FOUNDATION BASES

CEMENTITIOUS GROUTING TO FOUNDATION BASES

ETYLENE COMPRESSOR MASSIVE FOUNDATION (CONCRETE POUR

PROPANE COMPRESSOR MASSIVE FOUNDATION (CONCRETE POUR)

PROPANE COMPRESSOR MASSIVE FOUNDATION (CONCRETE POUR)

PROPANE COMPRESSOR MASSIVE FOUNDATION (CONCRETE POUR

PROPANE COMPRESSOR MASSIVE FOUNDATION (CONCRETE POUR

PROPANE COMPRESSOR MASSIVE FOUNDATION (CONCRETE POUR

SEAWATER BASIN(WATER TIGHTNESS BS 8007 : 1987 )

SEAWATER BASIN(WATER TIGHTNESS BS 8007 : 1987 )

SEAWATER BASIN(WATER TIGHTNESS BS 8007 : 1987 )

ADMINISTRATION BUILDING STAIR LANDING EXTENSION AT GRID 4 J

ADMINISTRATION BUILDING STAIR LANDING EXTENSION AT GRID 4 J

ADMINISTRATION BUILDING STAIR LANDING EXTENSION AT GRID 4 J

FENCINGTop

ADMINISTRATION BUILDING CERAPlant Operating Authority TILES FLOORING SYSTEM

ADMINISTRATION BUILDING CERAPlant Operating Authority TILES FLOORING SYSTEM

ADMINISTRATION BUILDING PLASTERING AND RENDERING

ADMINISTRATION BUILDING ROOFING SYSTEM

ROOFING SYSTEM BUILDINGS ROOFING SYSTEM

CRACKED GAS COMPRESSOR TABLE TOP CONCRETE POUR

WATER TIGHTNESS TESTS FOR THE COLLECTION SUMPS ACCORDING TO

WATER TIGHTNESS TESTS FOR THE COLLECTION SUMPS ACCORDING TO

ADMINISTRATION BUILDING MARBLE FLOORING

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 3: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

3 of

BS 8007 : 1987 SECTION 9 BS 8007 : 1987 SECTION 9

ETHYLENE GAS COMPRESSOR TABLE TOP POUR

PROPANE GAS COMPRESSOR TABLE TOP POUR

EXPANSION JOINTS IN DITCHES

EXPANSION JOINTS IN DITCHES

TopCONCRETE COATING USING MASTER SEAL 550

DEWATERING FOR THE 84” GRE PAIR LINE PARALLEL TOCORNICHE ROAD EAST WEST

CERAPlant Operating Authority WALL TILES FIXING

BEDDING AND GRAVEL FILLING BENEATH 60 “ DIA PIPE COOLING WATER PIPE

EXTERNAL CONCRETE PROTECTION ADMINISTRATION BUILDING

ABOVE GROUND CONCRETE PROTECTION USING MASTERSEAL 300 H

ABOVE GROUND CONCRETE PROTECTION USING MASTERSEAL 300 H

HAND EXCAVATION TO INSTALLTELEPHONE DUCTS BETWEEN BOX NO. 20 TO TELECOM CENTRE

BACKFILLING OF THE WEST SIDE OF THE QUENCH TOWER FOUNDATION – (RIB)

EXCAVATION -COOLING WATER OUTFALL CHAMBER

DRILLING OF HOLES ON PIPE RACK & STRUCTURES ON SITE

SITE OFFICE ESTABLISHMENT Welding of Earthing Lugs on East West Piperack (SR0099A &B)

FILLING AROUND ALL THE PIPES WITHIN THE Plant AREA

PRECASTING MAN HOLES CATCH BASIN AND VALVE CHAMBERS

TERMINATION DETAIL TO PROTECTIVE MEMBRANE AROUND RCC COLUMNS SUPPORTING THE STRUCTURAL STEELCOLUMNS FOR PIPE RACKSCASE (1) WITH ALUMINIUM BEADCASE (2) WITH REBATECASE (3) GRAVEL FILLCASE (4) PAVING

TERMINATION DETAIL TO PROTECTIVE MEMBRANE AROUND RCC COLUMNS SUPPORTING THE STRUCTURAL STEELCOLUMNS FOR PIPE RACKSCASE (1) WITH ALUMINIUM BEADCASE (2) WITH REBATECASE (3) GRAVEL FILLCASE (4) PAVING

Top ROAD CROSSING FOR LAYING 2 PIPES 1 FOR 20” RAW ETHANE & 1 FOR 6” PROPANEFIRST STREET Operating Authority ENTRY

ROAD CROSSING FOR LAYING 2 PIPES1 FOR 20” RAW ETHANE&1 FOR 6” PROPANEFIRST STREET Operating Authority ENTRY

DIRECTIONAL BORINGFOR LAYING SLEEVES FOR2 PIPES1 # 20” RAW ETHANE&1 # 6” PROPANEOperating Authority Plant REFINERY ENTRY

2 #s ROAD CROSSINGSFOR LAYING1 FOR 14” DESALINATED WATER1 FOR 8”POTABLE WATER&1 FOR 20” RAW ETHANE1 FOR 8” NATURAL GAS1 FOR 6” PROPANEAVENUE ‘C’AT FIRE STATION

2 #s ROAD CROSSINGSFOR LAYING1 FOR 14” DESALINATED WATER1 FOR 8”POTABLE WATER&1 FOR 20” RAW ETHANE1 FOR 8” NATURAL GAS1 FOR 6” PROPANEAVENUE ‘C’AT FIRE STATION

ADMINISTRATION BUILDING GRC PANEL FIXING

PAINTING ADMINISTRATION BUILDING PAINTING ADMINISTRATION BUILDING

Top

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 4: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

4 of

ROAD CROSSING FOR LAYING 2 PIPES1 FOR 20” RAW ETHANE&1 FOR 6”PROPANEAVENUE ‘C’

EARTHWORKS SURVEY SYSTEM

ROAD CROSSING FOR LAYING84”G R E PAIR SEAWATERCOOLING LINESATAVENUE ‘D’ / CORNICHEJUNCTION

ROAD CROSSING FOR LAYING84”G R E PAIR SEAWATERCOOLING LINESATAVENUE ‘D’ / CORNICHEJUNCTION

TENNIS COURTS SURFACING

Top

PRECASTING LIGHTING POLES FOUNDATIONS

LIGHTING POLES FOUNDATIONS

SEA WATER SURGE BASINCONCRETE PROTECTION MASTER SEAL 550

CONCRETE COATING OF STRUCTURES USING MASTERSEAL 550

ABOVE GROUND CONCRETE PROTECTION SEAWATER SURGE BASIN

SEA WATER SURGE BASIN JOINT SEAL

PAINTING SUB STATIONS

PAINTING SUB STATIONS

ELECTRICAL & INSTRUMENTATION TRENCHES

ELECTRICAL & INSTRUMENTATION TRENCHES

PULL PITS ROAD CROSSING TO MAKE GOODWEARING COURSE OVER COMPLETED1# FOR 14” DESALINATED WATER&1# FOR 8”POTABLE WATERAVENUE ‘C’

PULL PITS ROAD CROSSING TO MAKE GOODWEARING COURSE OVER COMPLETED132 KV ELECTRIC CABLEAVENUE ‘C’

PULL PITS ROAD CROSSINGTO MAKE GOOD (temporarily) WEARING COURSE OVER COMPLETED132 KV ELECTRIC CABLEAVENUE ‘C’

DRINKING WATER CONNECTION

Top

PROTECTION TO TRANSFORMER FOUNDATION SIDES IN SUB STATIONS WITH ALUMINIUM BEAD TERMINATION FOR BELOW GROUND AND MASTERSEAL 300H FOR ABOVE GROUND IN GRAVEL FILL AREA

TIMBER DOORS FIXINGADMINISTRATION BUILDING

GROUTING TO STEEL TANKS BEARINGS ON RING BEAMS

GROUTING TO STEEL TANKS BEARINGS ON RING BEAMS

EXCAVATION FOR CCB UNDERGROUND WATER TANK

EXCAVATION FOR CCB UNDERGROUND WATER TANK

SOAKAWAY CHAMBERS EPOXY FLOORING BUILDINGS

EPOXY FLOORING BUILDINGS

EPOXY FLOORING BUILDINGS

VINYL WALL COVERING BUILDINGS

DRY WALL LININGS BUILDINGS

RUBBER FLOORING (BUILDINGS)

RUBBER FLOORING (BUILDINGS)

RUBBER FLOORING (BUILDINGS)

RUBBER FLOORING (BUILDINGS)

RUBBER FLOORING (BUILDINGS)

SUSPENDED CEILINGS PIT 21 WATER CONNECTION CEMENT BASED NON SHRINK GROUTING TO

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 5: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

5 of

ALL BUILDINGS

TopFOUNDATION BASESUSING MASTERFLOW 928 T

REPAIR OF CONCRETE FLOOR SCREEDS

Top

REPAIR OF CONCRETE FLOOR SCREEDS

EPOXY GROUTING TO VIBRATING INSTALLATION BASESUSING MASTERFLOW 648 CPGENERAL FOUNDATIONS

KERBS & INTERLOCKING BLOCKS PAVING AROUND BUILDINGS

ERECTION OF STEEL STRUCTURES (FOR HIGHER LEVELS)

VINYL FLOORING BUILDINGS

CONCRETE PAVING CENTRAL CONTROL BUILDING CERAPlant Operating Authority TILES FLOORING SYSTEM

CONCRETE PLACEMENT

PRECAST RCC COVERSCABLE & INSTRUMENTATION TRENCHES

BLACK TOP REPAIRIST STREET BETWEEN AVENUE C & B

REPAIR OF SINGLE LEAF SWING GATES

REPAIR TO FLOOR SCREED LEVELS

RESIN INJECTION TO LEAKING JOINT SEA WATER SURGE BASIN

RESIN INJECTION TO LEAKING JOINT SEA WATER SURGE BASIN

RESIN INJECTION TO LEAKING JOINT SEA WATER SURGE BASIN

FIRE WATER LINE EXCAVATION AROUND CONSUMER RECEIPT STATION

ROAD CROSSINGFOR LAYING1 FOR 20” RAW ETHANE1 FOR 6” PROPANEFIRST STREET

ROAD CROSSINGFOR LAYING1 FOR 20” RAW ETHANE1 FOR 6” PROPANEFIRST STREET

2 #s ROAD CROSSINGSFOR LAYING1 FOR 20” RAW ETHANE1 FOR 8” NATURAL GAS1 FOR 6” PROPANE&1 FOR 14”DESALINATED WATER1FOR 8” POTABLE WATERAVENUE -D

TREATMENT TO MOVED EXPANSION JOINTS SEA WATER SURGE BASIN

Top

TESTING OF FRESH CONCRETE ON SITE

Top

ROAD CROSSINGTO INSTALL CULVERT FOR1# 14” DESALINATED WATERCORNICHE ROAD / ROAD CAT GUP GATE NOTH

ROAD CROSSINGTO INSTALL CULVERTFOR1 # 14” DESALINATED WATERAVENUE ‘C’ ROAD GUP GATE EASTMAIN ENTRANCE

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 6: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

6 of

ROAD CROSSINGTO INSTALL CULVERTFOR1 # 14” DESALINATED WATERAVENUE ‘C’ ROAD GUP GATE EASTMAIN ENTRANCE

ROAD CROSSINGTO INSTALL CULVERTFOR1 # 14” DESALINATED WATERAVENUE ‘C’ ROAD GUP GATE EASTMAIN ENTRANCE

REPLACEMENT OF MISALIGNED ANCHOR BOLTS IN FOUNDATION 55-VV-906USING RENDEROC LAX TRA

REPLACEMENT OF MISALIGNED ANCHOR BOLTS IN FOUNDATION 55-VV-906USING RENDEROC LAX TRA

BUILDINGS SCREEDS FOR VINYL AND EPOXY FLOOR FINISHES

BUILDINGSSCREEDS FOR VINYL AND EPOXYFLOOR FINISHES

BUILDINGSSCREEDS FOR VINYL AND EPOXYFLOOR FINISHES

DIRECTIONAL BORING AT 3# LOCATIONS FOR 14”DESALINATED WATER PIPE CORNICHE ROAD NORTH OF Operating Authority

DIRECTIONAL BORING AT 3# LOCATIONS FOR 14”DESALINATED WATER PIPE CORNICHE ROAD NORTH OF Operating Authority

DIRECTIONAL BORING AT 3# LOCATIONS FOR 14”DESALINATED WATER PIPE CORNICHE ROAD NORTH OF GUP

DIRECTIONAL BORING AT 3# LOCATIONS FOR 14”DESALINATED WATER PIPE CORNICHE ROAD NORTH OF GUP

EPOXY SKIRTING IN CENTRAL CONTROL BUILDING & SUB STATIONS ON DRY LINING

EPOXY SKIRTING ON DRY LINING

EPOXY SKIRTING ON DRY LINING

ROAD SURFACE REINSTATEMENT OVER BOX CULVERT CROSSINGS

Top REPAIR TO LIFT CLADDING PANELADMINISTRATION BUILDING

FIXING SHEETING PANELSWALL & ROOF CLADDING

FIXING SHEETING PANELSWALL & ROOF CLADDING

ROAD CROSSINGAT FIRE STATION- FIRST STREETFOR LAYING2 # 100 mm SLEEVESFOR TELEPHONE CABLES

SEA WATER SURGE BASINCLOSING THE STRUCTURAL GAPON THE ROOF, WALL & BASE SLAB

HDPE PIPESBUTT FUSION

ROAD CROSSINGSTO CONSTRUCT BOX CULVERTS OFH 2 & 3CORNICHE ROADETHYLENE EXPORT

ROAD CROSSINGSTO INSTALL CULVERTS OFH 4 & 5CORNICHE ROAD ETHYLENE EXPORT

MDPE DRINKING WATER LINE – NY LINES

ROOF & SIDE CLADDING – Plant AREA FOUNDATIONS ALONG FENCE BELOW ‘FERTIL OVER HEAD CONVEYOR’ FOR PIPE RACK LEADING TO SEA

REINSTATEMENT TO ‘DAMAGE CAUSED FLARE PIPE RACK COLUMN MEMBER 01537’ AT GRID 19A

REINSTATEMENT TO ‘DAMAGE CAUSED FLARE PIPE RACK COLUMN MEMBER 01537’ AT GRID 19A

Maintenance Warehouse Overcoating To Epoxy Painted Surface With Mastertop Top Coat 44P Access to Corridors & Walkway

RoadsBituminous Concrete Surfacing

RoadsBituminous Concrete Surfacing

Excavation for 200 pair Telecom Route(Direct Buried) parallel to Avenue D & 3 rd street

Hand Excavation for 200 pair Telecom Route(Direct Buried)parallel to Avenue C

200 pair Telecom Road Crossingat Avenue D / 3 rd Street Intersection along E 676976

Manual Excavation200 pair Telecom Road Crossing @ Access road to GASCO camp @ C / L, co-ordinate N 2666305 / avenue C

Manual Excavation200 pair Telecom Road Crossing @ Access road to Operating Authority

REMOVAL OF CONTAMINATED SOIL

BLINDING CONCRETE

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 7: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

7 of

camp @ C / L, co-ordinate N 2666940 / avenue CREINFORCEMENT RECEIVAL & FABRICATION

REINFORCEMENT PLACEMENT FORMWORK ERECTION

CONCRETE TO PAVED AREAS EXCAVATION & BACKFILL TO STRUCTURES

TELEPHONE CABLE TO SITE OFFICE

ELECTRIC CABLE FROM RLIP SUBSTATION TO Civil Contractor CAMP

WATER SUPPLY TO Civil Contractor CAMP

ADMINISTRATION BUILDING SUBSTRUCTURE

WASTE MANAGEMENT SEA WATER BASIN EXCAVATION FOR ETHANE & PROPANE GAS PIPELINE INTERCONNECTION

GENERALTop

#1

Site Preparation & Earth WorkTopIndexScope - Reference documents – Definitions – Responsibilities – Safety – Method – Equipment - AttachmentScopeThe purpose of this method statement is to define the sequence of activities for the site preparation works related to the Company Petrochemical project. The extent of these activities are defined upon the attached site plan (Not included with this statement). Refer to indicative google photos.Reference documentsSpecifications for:Site preparation,Excavation & backfill for underground installations,Fill, Grading and Paving,Testing Laboratory,Geotechnical InvestigationDefinitionsGE Geotechnical EngineerPSM Project Site ManagerSE Site EngineerSO Safety OfficerQM/QE Quaity Manager/Quality EngineerIS Infrastructure SuperintendentST Survey TeamPPE Personal Protective EquipmentResponsibilities

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 8: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

8 of

It is an overall responsibility of the PSM to ensure that the site preparation activities are conducted according to the project specifications. PSM shall arrange all required resources.The IS shall ensure that the site preparation activities are conducted according to this method statement as well complying with all specifications. The GE shall ensure that the activities are conducted according to the project specifications and this method statement.SafetyPrior to the commencement of any activities, the workforce shall receive a toolbox talk on the project site as well as on general safety requirements. SO shall ensure that the persons being inducted on site are well aware of the safety procedure to be implemented on site for the activity concerned.All persons upon the site shall wear PPE issued to them. Where possible hazards may arise from excavation activities, the necessary safety measures shall be taken to prevent accident or injury at all times. This may include provision of signage, barriers, watchman and lighting.Where work upon existing services is required, the necessary authority, permits and safety equipment shall be attained prior to the activity commencing. Scanning of existing services shall be conducted by suitable methods.MethodThe survey team shall locate and mark all services that are present upon the site (This includes above ground services as well as buried services). These services, (Electric, telephone, gas, oil, chemical, water etc), shall be clearly marked using stakes and warning tapes, reflected upon a site drawing and the issues raised with the client. The survey team shall also mark upon the site plan all obstructions, structures and developments. Any obstruction encountered during excavation activities shall be plotted and recorded.

Where hazardous material is encountered, it shall be identified and isolatedin compliance with the safety procedures under SO supervision. The client shall be informed & hazardous material be collected and removed to a licensed tipping place. The details of the material and tipping arrangements shall be documented for review by the client as appropriate. Refer to Method statement Removal of hazardous materials.

Existing structures, fences and developments shall be demolished in a safe manner as site-stripping activities proceed. The necessary permits, approvals and permission shall be obtained from the concerned authorities prior to the commencement of the activity. The method of removal of these existing elements shall usually be conducted by dozer or breaker. Where necessary otherwise, discussions on site shall be made concerning alternate methods of removal when the full extent of these structures are exposed.

The removal of the topsoil shall include all vegetation and rubbish material from the work site. Prior to the start of topsoil removal, the surveyor shall peg out the haul roads to be used by the construction equipment to execute all the site preparation activities. These roads shall be constructed by leveling of the existing terrain. Grade pegs shall be set to an agreed grid to indicate existing grade and reduced grade. Dependant upon the quality of the existing soil

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 9: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

9 of

where the roads is to be built, suitable compactable fill may be imported or re-located from other parts of the site. The material shall be approved by the GE & QM/QE jointly.

These roads shall be maintained as the work proceeds.Where required, water shall be spayed for dust control.

For general removal of the topsoil activities using appropriate equipment, the areas concerned shall be excavated and graded to levels that ensure adequate surface water drainage. The GE/QM/QE shall monitor the activity to ensure that the topsoil material is removed. Sampling and testing of the resultant material shall be conducted for specification compliance & proper compaction.

Upon completion of the topsoil removal activities where appropriate, the exposed surface shall be scarified, moistened and compacted to achieve the required density criteria. The areas shall be divided into manageable sections that be defined upon sketches. The GE shall monitor and test all sections. The results of the tests shall be recorded upon the relevant QC format. The number of tests conducted shall reflect the specification requirement.

In excavation areas, the GE shall review the material to be excavated to ascertain its suitability for re-use as fill material. This excavated material shall be transported to areas that require filling. The material shall be deposited onto the areas to receive filling, leveled, moisture conditioned and compacted. If necessary, stockpiling may be required.

The excavated areas shall be divided into manageable sections, which be defined upon sketches. The excavated areas shall be monitored by the GE to ensure that any unsuitable material does not appear. Where unsuitable material appears, it shall be removed. The excavated formation surface shall be treated by scarification, moistened and compacted according to the specification criteria. All areas shall be tested and the results recorded.

Where areas are to receive fill, the material that has been excavated shall be transported to the fill area, tipped, leveled, moisture conditioned and compacted. The material shall be spread and leveled in 200mm layers. The areas to be filled shall be divided into manageable sections that be defined upon a sketch. The fill layer shall be moistened and compacted to achieve the required specification criteria. No further fill activity shall be conducted upon an area that has not been approved and released by the GE. Attention shall be observed at edges and slopes, to ensure that compaction criteria are achieved. Additional layers of fill material shall be placed similarly as described above until the desired elevation has been achieved.

Production procedure.Verification exercise for fill activity had been conducted to establish the economical and effective method for the fill activity.Import and place fill to controlled areas of approximately 25m wide by 100 - 150m long.Spread and level the imported fill.

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 10: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

10 of

Add water to the fill layer by passing the water tanker over the fill layer. The water tanker should pass over the layer twice.A time gap of approximately two hours is allowed for the water to soak into the fill material.The layer is now mixed with the grader until a uniform blend of moist material is achieved.Additional water is added by passing the water tanker over the layer in a uniform sequence. A time period of approximately one-hour is allowed for this water to soak into the fill layer.The fill layer is mixed again with the grader leaving the fill level to the correct grade.Vibrating rollers shall now compact the fill layer in a logical sequence that compacts the fill layer uniformly.Testing of the layer shall be conducted according to specification requirements.

EquipmentDozers & Graders, Vibrating drum rollers, Dumper trucks, Excavators & Loaders, Water tankers

AttachmentNone. Refer to indicative google photos as incuded as a facility. Assume there was nothing prior to construction & whole site was filled for preparationworks.

#2

Protection of existing servicesTop IndexScope - Reference documents – Definitions – Responsibilities – Safety – Method – Equipment - AttachmentScopeThe purpose of this method statement is to define the procedure that can be implemented, for the identification, protection and / or removal / relocation of existing services upon the site. Reference documentsSpecifications: Site preparation…, Fill…, Grading and Paving...(certain sections re to record services within the specifications)DefinitionsGE Geotechnical EngineerPSM Project Site ManagerSE Site EngineerSO Safety OfficerQM/QE Quaity Manager/Quality EngineerIS Infrastructure SuperintendentST Survey TeamPPE Personal Protective EquipmentStatements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 11: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

11 of

ResponsibilitiesIt is the overall responsibility of the PSM to ensure that the identification, protection and / or removal / rerouting to existing services are conducted in a safe methodical sequence as defined by this method statement as well as directed by the relevant authorities.The IS shall coordinate investigation of existing services with the Plant authorities.The ST shall accurately plot and record all existing services upon the site.The SE shall ensure that the excavation is rightly carried out.The SO shall ensure that excavations are safely carried out.SafetyPrior to the commencement of any activities, the workforce shall receive a safety induction talk on the project site safety requirements. The necessary permits that may be required to work near these services shall be obtained. Any special conditions imposed upon these permits shall be implemented.The use or restriction of specific mechanical equipment whilst locating these services shall be implemented. Generally, where appropriate, only manual excavation shall be carried out.MethodFrom the existing record drawings provided by the relevant authorities controlling Plant, existing services shall be located and exposed by hand excavation.The ST shall check and accurately record these services. A line of pegs shall be positioned to indicate the route of the existing services. The warning tape and / or nylon cord to indicate and protect the route of the service shall be provided. The ST shall inform the IS about the exact location of the services relative to the warning flags.

Should an existing service be disbanded or made redundant, that shall be exposed to allow for the inspection as well as confirmation of its status by the authorities. The IS through the EPC Contractor representative shall request the relevant authority to review the excavated service to confirm the status as well as instruct for necessary action required for removal or diversion. The redundant service shall be removed under the supervision of the IS according to the agreed criteria of that relevant authority.

Where an existing live service remains working or serving during the site preparation activity such as the 33KVA electric cable, that existing live service shall be protected in compliance with the regulations.

Upon location of the live service, the ST shall mark that location upon the ground using spray paint or small pegs. At necessary locations along the route of the existing live service indicated by the ST, small hand dug pits shall be excavated to expose live service to ensure its location. On ten meters (10m) either side of the route of the existing live service shall be erected posts at suitable centres. A nylon cord with warning tape streamers shall be strung between the posts to clearly indicate the service and its route.

Signboards that indicate what exactly the live service within the marked corridor is, shall also be displayed at sufficient locations conveniently within the view along the route.

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 12: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

12 of

Where temporary roads cross existing cables, sufficient suitable fill material shall be placed on top of the cables to afford adequate protection by distributing the axle loadings safely.

The Safety Officer shall periodically check the condition of the barriers where necessary refurbishment is conducted.

EquipmentExcavation Tools, Survey Equipment, Pegs, Nylon cord, Warning tape.AttachmentNone. Attachments depends on the available record drawings. #3

Re-routing of 33kv cablesTopIndexScope- Reference documents- Definitions- Responsibilities- Safety- Method- Equipment- AttachmentScopeThe purpose of this method statement is to define the procedure that can be implemented for re-routing of the existing 33KV electric cable that crosses the project site. This method statement includes the location, excavation, isolation, re-routing, jointing, testing and backfill.Reference documentsSite drawing, Record DrawingsDefinitionsGE Geotechnical EngineerPSM Project Site ManagerSE Site EngineerSO Safety OfficerQM/QE Quaity Manager/Quality EngineerIS Infrastructure SuperintendentST Survey TeamPPE Personal Protective EquipmentResponsibilitiesThe EPC Contractor PSM shall ensure the required permits from Operating Authority are obtained prior to the commencement of this activity.It is the overall responsibility of the PSM to ensure that the identification, protection and / or removal / rerouting to existing services are conducted in a safe methodical sequence as defined by this method statement as well as directed by the relevant authorities.The IS shall coordinate investigation of existing services with the Plant authorities.The ST shall accurately plot and record all existing services upon the site.The SE shall ensure that the excavation is rightly carried out.

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 13: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

13 of

The SO shall ensure that excavations are safely carried out & ensure that all safety issues are addressed as defined upon the work permits.SafetyPrior to the commencement of any activities, the workforce shall receive a safety induction talk on the project site safety requirements. The necessary permits that may be required to work near these services shall be obtained. Any special conditions imposed upon these permits shall be implemented.Only specifically approved mechanical equipment whilst locating these services shall be used.Generally, where appropriate, only manual excavation shall be carried out.MethodThe existing route of the 33KV cable shall be identified, marked & a barrier erected on either side clearly defining the route across the site.

The route proposed for the new 33KV cable on the AFC drawing shall be identified & marked with pegs by the ST. Excavation shall commence to the line and required level.

The appropriate sand bed shall be placed within the trench.

The new cable supplied by EPC Contractor shall be laid into the trench according to established methods and standards that would include placing of the cable drum on a cable trolley and rollers. The cable shall be unwound from the cable drum by pulling. If required, a cable tugger fitted with load cell control may be utilized.

The new cable shall be correctly placed to line and level upon the sand bed. Wherever joints occur, sufficient cable overlap to allow for the jointing shall be provided.

The insulation value of the new cable shall be tested by 5KV motorized megger.

Upon the EPC Contractor Electrical Engineers approval, the cable shall be covered with dune sand to the required thickness evenly. Cable tiles shall be placed on top of the sand above the new cable.

The trench shall be backfilled with approved material. The backfill activity shall continue until the trench is completely filled. Route markers shall be placed with the splice joints surveyed and recorded.

Where joints occur to the cable either at the two termination points with the old cable or along the length of the new cable, the same technique shall be adopted.

An experienced cable jointer under the supervision of an electrical engineer shall conduct all the jointing.

Approved jointing kits shall be utilized. The manufacturers recommendations relating to the installation of these jointing kits shall be followed. Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 14: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

14 of

Upon completion of the jointing of the new cable length, the entire length of the new cable shall be tested. The cable shall be subjected to a pressure test of 67KV DC for 15 minutes on the cable between each core and earth. The remaining cores shall be connected to earth. The engineer shall measure the leakage current. All readings shall be recorded upon the appropriate form. The testing shall be witnessed by the EPC Contractor engineer.

Prior to the excavation at the points where the new cable is to be connected to existing 33KV cable, the necessary permits shall be obtained. EPC Contractor method statement for conducting cable Diversion shall be complied with.

The old cable shall be hand dug. An area sufficient to conduct the jointing of the cable shall be excavated.

Electrical engineer in coordination with the EPC Contractor engineer shall ensure that the old cables are identified and isolated under the supervision of the Refinery Supervisor within the appropriate substation. The necessary earthing and isolation to the cables shall be conducted prior to the commencement of jointing the old cable to the new.The cables shall be jointed in the same manner as described previously.

Once the cables have been jointed, these shall be tested by mega test at 5KV and HV test at 53KVDC to establish its integrity and insulation.

The disbanded cable shall be removed from the new jointed cable by excavating and rolling the cable to allow the new cable route corridor to be covered with sand, cable tiles and backfill material.

Upon completion of the cable testing activities, the Refinery Electrical engineer shall authorize the energizing of the new cable route.

The disbanded cable route shall be excavated to expose the old cable. The old cable shall be removed onto the surplus cable drums from which the new cable was coiled. These drums shall be stored on site for EPC Contractor disposal.

A program to be developed by all parties of power outage windows shall be produced for the tie-in activities of the cables.

EquipmentExcavator,Dump trucks,Cable drum trolley,Cable rollers,Cable tugger with load cellAttachmentEPC Contractor standard method statement for cable diversion.(Since this statement may be submitted by the Civil Works subcontractor on behalf of the EPC contractor, the EPC standard method statement is required to be attached)

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 15: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

15 of

Top

Concrete Pipe CulvertsIndexScope-Reference documents-Definitions-Responsibilities-Safety-Method-Equipment-AttachmentScopeThe purpose of this Statement is to define the sequence and methodology for the laying, jointing and testing of the concrete pipe culverts.Reference documentsSpecification….,Drawing No….DefinitionsGE Geotechnical EngineerPSM Project Site ManagerSE Site EngineerSO Safety OfficerQM/QE Quaity Manager/Quality EngineerIS Infrastructure SuperintendentST Survey TeamPPE Personal Protective EquipmentResponsibilitiesThe CS shall Plan and Resource the concrete culvert laying activities to ensure that these are Carried out complying with the contract documents.The Construction Foreman shall actually execute the works controlling the workforce as necessary all according to the directions by the site engineer or the superintendant. SafetyPrior to the commencement of any activities, the labour force shall receive a toolbox talk on the Project Site Safety requirements. Any adopted process that may have a particular Safety risk, shall be assessed, shortcomings analysed and addressed accordingly meeting the operational requirement.MethodSetting OutThe edge co-ordinates of the concrete pipe shall be calculated from the information on IFC drawing. Allowing for the 1:1.5 slope, the edges shall be fixed in such a way that full length of pipes are used avoiding unnecessary cutting. The center line and the actual trench width shall be set out by marking on ground.ExcavationThe trench shall be excavated to the correct width, length and formation by using a Hydraulic backhoe. Once the bulk excavation is completed, wooden pegs with elevation marked on them shall be used for indication to complete the remaining excavation to accurate formation levels. The formation shall be watered and compacted with a plate compactor to achieve compaction

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 16: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

16 of

of 90% of MDD in accordance with specification documents. The compacted formation shall be inspected and field tested prior to the commencement of the Bedding activity.Bedding Once the excavation is approved, Bedding material shall be placed to a thickness of 150mm, watered and compacted in accordance with the specification. The compacted surface shall be inspected & field samples tested for approval.Pipe WorkThe socket positions shall be marked on the Bedding and Hand excavated to ensure that the barrel of the pipe rests firmly on the bedding with spigot ends remaining clean for installing the gaskets.The concrete pipes shall be transported from the store to the location of the trench and gently lowered keeping the socket end upstream into the trenches with a crane using belt slings only. The pipes shall be laid back to back to the correct orientation. The spigot end of the pipes shall be cleaned using a cloth with special care taken to clean the recess which shall be lubricated with liquid soap following gasket placement in position.Supports shall be placed at one end. The spigot shall be so placed that the gasket is in contact with the entry taper at the socket evenly all around.The spigot shall then be drawn into the socket using a 5 tonTirfor. Jointing shall be carried out. Upon completion of the Jointing operation, the Bedding material shall be packed below the pipes so that the barrel rests firmly on the bedding keeping the pipe intact. The top elevation of the pipe shall be checked to ensure that the pipe lebvel is accurate. The operation shall be repeated until all the pipes are laid. The completed pipework shall be inspected and approved. Each joint shall be visually inspected from inside the pipe.BackfillOnce the pipes are laid to the True gradient and alignment as described above, Bedding Material shall be carefully placed along the sides and in between the pipes by means of a backhoe. The bedding and surround material shall be placed in layers and watered and compacted until the bedding and surround material reaches 300mm above the top of the pipe. Excavated suitable material shall then be placed in 200mm layer, compacted, inspected and tested.A list of Do’s and Don’t’s provided by the manufacturer is attached herewith.EquipmentCrane 20Ton 1 No / Flat Bed TrailorPart time / Excavator Backhoe1 No / Trifor 5 To

2Nos / Fork liftParttime / Plate Compactor1 No / Water Tanker Part timeLabourForemanNo. 1 / PipefitterNos. 2 / LabourersNos. 4AttachmentManufacture’s datasheet.Top

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 17: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

17 of

#5

Concreting to walls of Central control building / laboratorySuper – structure activitiesTop

IndexScope / Reference documents / Definitions / Formwork Design / MethodScopeThe purpose of this method statement is to define the procedure that shall be adopted for the erection of formwork and placement of structural concrete to the wall sections of the CCB.Reference documentsSpecification Concrete Construction, Formwork and Coating.Specification Concrete Buildings.Drawing No. DefinitionsE EngineerPSM Project Site Manager.CM Construction Manager.Formwork system The basic formwork supporting system shall be as designed and supplied by M / s. Giffin Scaffco. The supplier of formwork shall provide all design drawings for approval as well as for implementation. Additional bracing and support props shall be added by Civil Contractor in compliance with the formwork design provided by the supplier. Surface forming materials such as plies & timber scantlings etc. shall be added by the civil contractor. Upon completion of the suspended slab formwork system particularly, Civil Contractor Site Engineer shall check and confirm the adequacy of the system. If so required, the whole form work shall then be checked by the supplier’s expert & the adequacy certified in as by third party. MethodThe surveyor shall set out, check the line and levels to establish the correct positions. The wall starter bars shall be installed in place in accordance with the IFC drawings for the foundations. The kicker to the base of the wall sections shall be planned to be cast along with the foundation.The vertical and horizontal reinforcement to the wall shall be installed according to the IFC drawings. Where service inserts (ducts pipes etc) are shown on IFC drawings, these shall be securely located,installed as well as checked.The continuity testing of the reinforcement for the cathodic protection requirement shall be conducted and witnessed by the QC department. The results shall be recorded. Connection bosses shall be fixed as detailed on the approved drawings.

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 18: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

18 of

One side of the formwork shall be erected and braced. A safe means of access to a working platform as well as working platform shall be erected for this formwork. This access shall allow the steel fixers, carpenters and concrete crew a safe working area.All service openings shall be boxed for block outs / ducted onto the formwork. The height and width of the wall section shall be agreed with EPC Contractor/ Engineer. The wall height shall terminate near the underside of the roof slab, where the remaining top part of the wall can be cast along with the roof slab.The walls shall be prepared and cast in sections not exceeding 6.0m length where a construction and or contraction joint shall be formed using plywood. After all the inspections of the preparatory works, the concrete pouring activity shall be carried out in lifts not more than 450 mm layers. This concrete surface at joint location shall be scabbled prior to the next section is formed formed. Where applicable, the laboratory portion outer wall form shall be erected with the profile strips prefixed to the formwork. The remaining wall form shall be erected and braced. A safe means of access to a working platform as well as working platform shall be erected for this formwork. This access shall allow the steel fixers, carpenters and concrete crew a safe working area.The surveyor shall check the alignment of the wall.The preparatory works shall be checked by the site engineer who then request the QC.The finished reinforcement and formwork configuration shall be inspected on an ongoing basis by the Civil Contractor QC department who in turn obtain concrete pouring permission from EPC Contractor. Having obtained approval, the structural concrete shall be poured by pumping. Curing shall be carried out according to the specification requirements.EquipmentCrane.Concrete Pump.VibratorsHand Tools.AttachmentNone.

#6

Concrete pipe culvertsTopIndexScopeReference documentsDefinitionsResponsibilitiesSafetyMethodEquipmentAttachmentStatements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 19: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

19 of

ScopeThe purpose of this Method Statement is to define the sequence and methodology for the laying, jointing and testing of the concrete pipe culverts.Reference documentsSpecification Specification Drawing No. DefinitionsE EngineerPSM Project Site Manager.CS Construction Superintendent ResponsibilitiesThe CS shall Plan and Resource the concrete lining activities, to ensure that they are Constructed according to the Drawings and Specification.The Construction Foreman shall actually execute the works, directing the workforce as necessary. SafetyPrior to the commencement of any activities, the labour force shall receive a toolbox talk on the Project Site Safety requirements. Any process that may have a particular Safety risk, shall be assessed and addressed as required in consultation with the safety engineer.MethodSetting OutThe edge co-ordinates of the pipe shall be calculated from the information on the drawing as well as allowing for the 1:1.5 slope & fixed in such a way that full length of pipes are used without pipe cutting. The center line and the actual width shall be marked on ground.ExcavationThe trench shall be excavated to the correct width, length and formation by using a Hydraulic backhoe. Once the bulk excavation is completed, wooden pegs shall be used showing the elevations marked on them to guide & complete the excavation to required formation levels. The formation shall be watered and compacted using a plate compactor to achieve compaction of 90% of MDD in accordance with specification. The compacted formation shall be inspected and field compaction tested prior to the commencement of the Bedding activity.Bedding Once the excavation is completed & approved, Bedding material shall be placed to a thickness of 150mm, watered and compacted in compliance with the specifications. The compacted surface shall be inspected, tested and approved.Pipe WorkThe socket positions shall be setout on the Bedding. Manual excavation shall be carried out for socket portion to ensure that the barrel of the pipe rests firmly on the bedding. It shall also be ensured that spigot ends remain clean to the same standard as were while installing the gaskets. The concrete pipes shall be transported from the store to the location of the trench and gently lowered into the trenches with a crane using belt slings only. The socket end shall be placed upstream. The pipes shall be laid back to back to the correct orientation. The spigot Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 20: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

20 of

end of the pipes shall be cleaned using a cloth with special care taken to clean the recess which be lubricated with liquid soap following which the gasket placed in position. Supports shall be placed at one end. The spigot shall be so placed that the gasket is in contact with the entry taper/bevel at the socket evenly on circumference. The spigot shall then be drawn into the socket using a 5 tonTirfor. Upon completion of the Jointing operation, the Bedding material shall be packed below the pipes so that the barrel rests firmly on the bedding and the pipe doesn’t move. The top elevation of the pipe shall be checked to ensure that the laid pipe is accurately placed to the correct alignment and elevations. The operation shall be repeated until all the pipes are laid. The completed pipework shall be inspected and approved. Each joint shall be visually inspected from inside the pipe if accessible.BackfillOnce the pipes have been laid to the True gradient and alignment as described above, Bedding Material shall be carefully placed along the sides and in between the pipes by means of a backhoe. The bedding and surround material shall be placed in layers, watered and compacted until the surround material reaches 300mm above the top of the pipe. Excavated suitable material shall then be used in compacted layers of 200mm inspected and tested until the backfilling operations are completed.A list of Do’s and Don’t’s provided by the manufacturer is attached herewith.EquipmentCrane 20Ton 1 No.Flat Bed Trailor Part timeExcavator Backhoe 1 No.Trifor 5 Ton 2 Nos.Fork lift Part timePlate Compactor 1 No.Water Tanker Part timeLabourForeman No. 1Pipefitter Nos. 2Labourers Nos. 4AttachmentManufacture’s datasheet.#7

Culvert crossings to avenue e and main highway.Top

IndexScopeReference documents

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 21: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

21 of

DefinitionsResponsibilitiesSafetyMethodEquipmentAttachmentScopeThe purpose of this statement is to define the sequence and methodology for the excavation, placement of culvert pipes, backfill and reinstatement to the culvert crossings on avenue E and the main highway next to the retention pond.Reference documentsDrawing No: Drawing No: DefinitionsE EngineerPSM Project Site Manager.CM Construction Manager.ResponsibilitiesThe CM shall plan and resource the culvert construction operation, including the permissions required from all authorities concerned.The Construction Foreman shall control and monitor these activities, directing the workforce as necessary.SafetyPrior to the commencement of any activities, the labour force shall receive a tool box talk on the project site safety requirements. Any process that may have a particular safety risk, shall be assessed and addressed as required.MethodThe route of the culvert trench shall be set-out by the surveyor. The existing services such as the fibre optic cable shall be located and protected. The cable shall be supported across the excavation, placed within a PVC duct, wrapped with polythene & tied to the support.The traffic diversion scheme wilth all signs installed shall be implemented according to the attachment and monitored regularly by the safety department to ensure a smooth traffic management. Concrete barriers shall be placed at the head of the diversion. The ditch along the side of the diversion shall be barricaded with nylon rope bearing warning tape. The initial excavation shall commence at the drainage ditch to the west side of avenue E and extend across avenue E up to the fibre optic cable location.The trench shall be excavated using appropriate equipment while dump trucks collect the surplus excavated earth to be removed from site to the spoil area. Material that is to be reused shall be stockpiled. The excavated asphalt shall be deposited at the tip area in the pre-agreed location. Any damage to the existing asphalt shall be repaired during the reinstatement operation.

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 22: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

22 of

The sides of the excavation shall be sloped where the excavation depth exceeds 1.2 m. A ladder shall be provided for ingress and egress of the excavation. Ladder shall be located every 8 m if so required depending on length of excavation.A banksman shall be provided to monitor the excavation machine operations.The bottom of the excavated trench shall be inspected by the EPC Contractor engineer prior to the compaction activity commences. All unsuitable material shall be removed. Inspection and testing of the compaction shall be conducted by the site test laboratory. The field density test results shall be submitted for approval.The surveyor shall monitor the line and level of the excavation regularly & provide level pins for the pipe bedding.

Approved bedding material shall be placed and compacted to the required levels and density values. The site test laboratory shall conduct the field density tests & reported accordingly. The concrete culvert pipes shall be placed correctly to the line and level as shown on the IFC drawing. The pipes shall be inspected for damage prior to placement. No damaged pipes shall be placed. The spigot head on the culvert pipe shall be on the up stream end of the pipe. A pair of nylon strap shall be used to lift the pipes using a 50 ton crane and place the pipes correctly in to the trench. Backfill material shall be placed around the pipes in layers of 150mm thickness duly compacted & tested by the laboratory. Backfill operations shall continue up to the existing road formation level.When the backfill activity is completed, asphalt repair to the existing highway shall be conducted & avenue E road construction shall be reinstated. The traffic management scheme shall be removed to allow the re-use of avenue E.A temporary security fence outside the existing RRD area shall be erected to allow the culvert construction to continue east towards the retention pond. The temporary security fence shall be erected to the agreement and requirements of the security police. When this activity is completed and approved by the security police, the existing security fence can be cut and rolled back sufficiently to allow the construction activities to be conducted.

The next section for the culvert trench shall be excavated taking care of where existing services have been exposed to be well protected.The trench formation shall be inspected, compacted and tested as previously described.Pipe bedding shall be placed, compacted and tested as previously described.The pipes shall be installed within the trench after inspection for transit damage is completed.Backfill around the pipes shall be placed, compacted and tested.The backfill shall be reinstated above the pipe surround up to existing ground level.Reinstatement of any existing services shall be done. The fibre optic cable shall be left protected by the PVC duct and polythene sheet, then surrounded with concrete. The existing security fence shall be replaced. The existing fabric shall be re-erected onto the existing poles which shall be re concreted in position. The barbed wire shall be re placed using new material where required.The temporary security fence shall be removed.

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 23: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

23 of

The final section of the culvert trench shall be set-out and excavated in the same sequence as the previous sections.The compaction and testing of the pipe bedding shall be carried out.The placement of the pipes to the correct line and level shall be carried out.The backfilling of the pipe surround shall be conducted. The reinstatement of the backfill above the pipe surround material shall be conducted. The site test laboratory shall conduct the field density testing. The inlet and outlet chambers of the crossing shall be constructed. Refer to the method statement for chambers. This procedure shall be similarly followed in principle for any other culvert crossings on avenue E.EquipmentExcavators.Dump trucks.Compactors.AttachmentNone.#8

Placing concrete on service Water tank 58-tk-205 foundationsTop

IndexScopeSafetyMethodEquipmentAttachmentScopeThe purpose of this method statement is to define the sequence and methodology for the placing of concrete on service water tank foundations.Reference documentsSpecification DefinitionsE EngineerPSM Project Site Manager.CM Construction Manager.ResponsibilitiesThe CM shall plan and resource the concrete repair activities, to ensure that they are implemented according to this method statement.The Construction Foreman shall monitor the concrete repair activities, directing the workforce as necessary.Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 24: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

24 of

SafetyPrior to the commencement of the concrete pour, the labour force shall receive a tool box talk on safety requirements with special care taken to ensure adequate lighting arrangements are made. We propose to use 2 Nos. Tower lights each with 4 X 1000 Watts bulbs. Accers platforms shall be provided all around the ground beam on the outside formwork, 2 Nos. Aluminium ladders shall be placed at opposite ends to reach the Accers platforms from the ground levels. The accers platform shall be provided with Hand Rails all around.MethodPreparatory works shall be carried out for the form works in circular profile for which due provisions shall be made for the specialist form. This form shall be well supported & anchored to resist ecpected forces during the our. As parallel activity, rebars shall be placed & fixed in the correct positions duly inspected.It is proposed to cast the Ring beam in two pours. Stopend forms shall be placed at opposite locations across the full width and depth to establish construction joints. The concrete shall be poured onto the section in one go 300 to 450 mm high around and compacted with suitable vibrators. Care shall be taken to ensure that concrete is placed and compacted in its final position within the time permissible form the time of batching to the time it should be compacted in accordance with the concrete production specification that may be generally 1 to 2 hours. Concrete delivery shall be planned accordingly to quantity & duration of pour to enable a smooth concreting operation. Concrete shall be continually poured from the start to the concrete por finish. No cold jointshall be allowed to form. All flash setting shall be avoided by keeping the rebars lower than the air temperature. Proper vibration shall be effected. After the concrete is completed, proper method of curing shall be carried out & continued for specified number of days. All tests for on site concreting shall be conducted by the RMC laboratory staff duly recorded.EquipmentConcrete pump, concrete trucks, vibrators, AttachmentNone.

#9

Concrete repairTopIndexScopeReference documentsDefinitionsResponsibilitiesSafety+MethodEquipmentAttachmentStatements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 25: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

25 of

ScopeThe purpose of this method statement, is to define the criteria for the concrete repair to all structures.Reference documentsSpecification DefinitionsE EngineerPSM Project Site Manager.CM Construction Manager.ResponsibilitiesThe CM shall plan and resource the concrete repair activities, to ensure that they are implemented according to this method statement.The Construction Foreman shall monitor the concrete repair activities, directing the workforce as necessary.SafetyPrior to the commencement of any activities, the labour force shall receive a tool box talk on the project site safety requirements. Any process that is adopted that may have a particular safety risk, shall be assessed and addressed as required.MethodUpon removal of the formwork, the concrete surface shall be inspected by the Site engineer & foreman to check surface defects.Where no surface imperfections have occurred, the concrete surface shall be cured according to the relevant procedure. Minor defects as described in A – D below shall be repaired as soon as practical. More significant defects as described in E – H shall be subject to joint inspection / agreement between Civil Contractor, EPC Contractor and Company.A.Pin holes / blow holesWhere small defects to the concrete surface has occurred such as pin holes or holes smaller than 3mm in diameter or depth, the surface shall be repaired using Nitomortar FC with an approved bonding agent. This surface repair shall be conducted as soon as the formwork is removed whilst the concrete is still green. The repair shall then be cured in accordance with manufacturer’s instructions or agreed procedures using water or curing agent as appropriate.B.Sand runs / scouringWater movement inside the shutter can result in a streaky appearance giving loose sandy finish. Where this occurs, any loose material shall be removed by stiff brushing and then repaired as described in A above.C.Plastic shrinkage cracksCracking caused by plastic shrinkage due to inadequate curing and protection of horizontal surfaces usually results in a series of diagonal cracks. These should be repaired by brushing dry cement powder directly into the cracks while the concrete is less than 3 days old and covering with damp hessian.Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 26: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

26 of

D.Minor misalignments (Typically Less than 2cm)Misalignments due to shutter movements etc, should be ground back to provide a smooth transition between areas. Where occurring at joints between panels, the ground profile length should be 2-3 times the size of the maximum misalignment. Following grinding, the surface should be reinstated as in A above. Care should be taken to ensure that concrete cover is maintained per specifications at all times.E.Honey combing / segregation / minor voidsThe repair shall be conducted as soon as the formwork is removed and the repair method agreed with EPC Contractor / Engineer. It shall require chipping the repair area free of laitance and exposing any voids. The repair area shall then be soaked, an approved bonding agent applied followed by working on with an approved mortar such as Master Flow 544 before the area dries out.. The materials shall be mixed using the bonding agent and not water. The mixed material shall be trowelled firmly into the repair area. Incase, the depth of the repair exceed 15mm, the repair shall be conducted in two layers providing a scratch coat on the first layer. The repair shall then be cured in accordance with the agreed procedure using water or curing compound as appropriate.F.Major voids (Typically Deeper than 5cm)This repair shall consist of chipping the affected area to remove any laitance and voids. Where reinforcement is exposed in a void, the surrounding concrete shall be chipped away to provide adequate space to place fresh concrete around the reinforcement including removal of all soft concrete. (Note- a distance of one and a half times the stone size must be allowed around all exposed reinforcement). Formwork shall be provided to retain the fresh concrete. The chipped area shall be soaked in and primed with a bonding agent. The bonding agent shall not be allowed to dry. Fresh concrete of the same grade as the surrounding concrete shall be used to fill in the void. The repair shall be water cured along with the parent concrete. The surface finishes to the repair shall be as the same standard as the surrounding concrete.G.Plastic settlement cracksCracking caused by settlement of concrete usually in deep lifts or at changes in section can result in a series of cracks which mirror the reinforcement pattern in horizontal surfaces or appear to arch on vertical surfaces. Any such cracks should be chased out to a depth of 10-15mm and filled with an epoxy mortar such as Nitomortar FC as in A above.H.Pourous / spongy surfaceWhere inadequate vibration and poor finishing techniques have caused excessive bleeding, horizontal surfaces can appear spongy and pourous. In this case all affected surfaces should be ground back to good concrete usually only 2-3mm below the surface. The surface should then be reinstated using Nitomortar as in A above. This type of defect often occurs with plastic settlement cracks which should be treated as In G above.

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 27: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

27 of

All repairs noted above shall be recorded on the post-pour inspection form (QCF). It is not necessary to raise a non-conformance report provided the repairs are carried out as indicated above and agreed with EPC Contractor where necessary. Any repairs not covered by the above procedure shall be dealt with on a case-by-case basis and agreed with EPC Contractor and Company before commencing repairs.EquipmentHand Tools.AttachmentNone.#10

Construction of pipe rack basesTop

IndexScopeReference DocumentsDefinitionResponsibilitiesSafetyMethodEquipmentAttachmentScopeThe purpose of this method statement is to define the sequence and methodology for the Construction of the pipes rack bare foundations.DocumentsSpecifications Drawing No:DefinitionsE EngineerPSM Project Site ManagerCM Construction ManagerCS Construction SuperintendentResponsibiltiesThe CS shall plan and resource the Construction of Pipe Rack Bases activities, to ensure that they are Constructed according to the Drawings and Specification.The Construction Foreman shall actually execute the works, directing the workforce as necessary.

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 28: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

28 of

SafetyPrior to the commencement of any activites, the labour force shall receive a toolbox talk on the Project Site Safety requirements. Any process that is adopted that may have a particular Safety risk, shall be assessed as required.MethodIt is proposed to cast the pipe rack bases and the columns at actual locations at site. The method of Construction of the pipe rack bases can be summarized in the following activities.Setting OutExcavationBlinding ConcreteFormworkSteel Reinforcement Concrete ConstructionConcrete ProtectionConstruction of Columns with Anchor BoltsBackfillingGroutingSetting Out- Pipe Rack BasesThe center lines of the Anchor bolt group shall be set out and offset provided 2m on either side of the foundation as reference line for blinding using manual methods of setting out.ExcavationThe bases shall be excavated with excavator, sides trimmed to avoid caving in. The formation shall be compacted, inspected, field tested and approved prior to the commencement of the blinding.Blinding ConcreteThe formation area to receive the blinding shal be prepared to the design levels & profiles. C20 PBFC grade concrete shall be placed to a minimum thickness of 50mm and the top surface smoothened by steel trowel. Curing shall be carried out for the blinding concrete for at least two days. Prior to the placement of the precast pipe rack base on it, mass concrete infill shall be placed as required in accordance with the drawings as necessary.Site Precast Yard for foundationsA precast yard shall be constructed on site at the location indicated in the attached sketch.A wind shield fence 2m high shall be erected on the Northern boundary as indicated in the proposed location in accordance with clause ………………… of the specification.Steel FormworkSteel Forms as shown in the attached sketch shall be used for casting the pipe rack base foundations. The forms should be easily struck as well placed in position. Separate forms shall be used for the bases and columns . The base slab formwork shall have 100mm high suspended kicker.Fosroc reebol mould release oil shall be used. The template for anchor bolts for piperack base type1, 3 & 5 shall be a 100mm wide strip of steel plate across the width of the column steel formwork at the top. The template for piperack type 2, 4, 6, & 7 shall be similar in Construction type with 2 plates and a connecting piece.Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 29: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

29 of

Anchor Bolts & Steel ReinforcementSteel Reinforcement cut and bent to the required shape and size shall be available on site. Reinforcement shall be timely fixed in place on the casting beds. Lifting HooksLifting hooks shall be inserted into the correct location & properly fastened so as not to be dislocated during concrete pouring.Casting ConcreteFormwork applied with a fresh coat of mould release oil shall be placed in position around the already assembled steel reinforcement. Lifting recess plugs shall be installed in position with a Template. All supports shall be fixed in position. Inspection shall be conducted to the ITP requirement. The Base shall be poured and compacted with vibrators. The surfaces shall be smoothened with steel trowel. Curing shall ne carried out. Formwork for the column shall be installed the following day. The plumb and alignment shall be checked and the anchor bolts with sleeves installed and held in position by the template . The widths of the template shall be kept to the minimum to allow room for concrete vibrators. Once the column is cast, the formwork shall be stripped after 36hrs and the concrete cured for a minimum period of 7 days.Protective CoatingsOnce the curing is completed as stated above, the polythene sheets and hessian shall be removed and the concrete faces allowed to dry for atleast 24hrs during which time minor repairs such as filling up of blow holes etc. shall be carried out. The faces shall be wiped clean with a wet sponge and surface prepared to receive the first coat of protective painting.Fosroc Nitocote ET 402 shall be mixed with a slow speed electric drill and spray applied with an airless sprayer equipment to the required thickness of 1mm as a single high build coat in accordance with the manufacture’s instructions.The column and the top sides of the boxes, vertical faces shall be painted as described above. The bottom of the base slab shall be left without painting. TraceabilityThe pipe rack bases shall be numbered and the date & time of casting marked on the concrete. Lifting, Transportation and InstallationAfter completion of the curing, certified cranes of required capacity shall be used to lift the pipe rack base from the casting bed to the flat low bed trailor. The bases shall be transported to the actual location of installation.On location preparatory pf preceeding activities shall be completed prior to the transportation of the bases. The screed shall be cast accurately to the actual dimension of the bone of the pipe rack foundation. Using a jack of adequate capacity, the unit shall be moved to the correct position accurately. The crane shall be used to lift the pipe rack base from the Trailor down onto the screed surface.The position of Anchor bolts shall be rechecked with a Theodalite and accuracy of the installation certified by a surveyor.Back fillingOnce the pipe rack base is installed, Backfilling with selected suitable fill material shall commence. The fill material shall be pre mixed with water 3% more than the optimum moisture Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 30: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

30 of

content for the daily requirement. Layers of premixed fill material shall be placed to a thickness of 200 mm and compacted properly. The compacted surface shall be inspected, field tested and these operations repeated until the Backfilling operations are completed.Anchor Bolts shall remain protected with PVC sleeves until completion of the Backfilling operations and only exposed at the time of installation / erection of steel works.EquipmentCrane 50Ton 2 No.Flat Bed Trailor 40 Ton 1 No.Excavator Backhoe 1 No.Plate Compactor 1 No.Water Tanker 1 No.LabourCasting Engineer 1 No.Placing Engineer 1 No.Casting Foreman 1 No.Placing Foreman 1 No.Carpenters 20 Nos.Steel fixers 30 Nos.Masons 20 Nos.Laborers 40 Nos.AttachmentManufacture’s datasheet.

#11

Excavation in Operating Authority controlled areasTop

IndexScopeReference DocumentsDefinitionResponsibilitiesSafetyMethodEquipmentAttachmentScopeThe purpose of this method statement is to define the methodology that shall be implemented, for construction activities that shall be conducted in areas under Operating Authority control. These areas shall primarily be the easement areas.DocumentsAll applicable Operating Authority easement drawings.Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 31: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

31 of

All applicable EPC Contractor project Drawings.All applicable EPC Contractor project specifications.DefinitionsE EngineerPSM Project Site ManagerCM Construction ManagerCF Construction Foreman.ResponsibilitiesThe CM shall plan and resource the construction activities, to reflect the conditions imposed upon the “Permit to Work” system.The CF shall actually execute the construction activities, directing the workforce as necessary.SafetyPrior to the commencement of any of the construction activities, the labour force shall receive a toolbox talk on the Project Site Safety requirements. Any activity that is conducted that may have a particular Safety risk, shall be assessed as required.MethodThe Construction Manager shall assign an Engineer and Construction Foreman to be responsible for the relevant activities.The Engineer shall be responsible for producing a method statement for the activities to be carried out. This method statement shall contain the procedure defined below. When the method statement has been agreed with EPC Contractor, a work permit covering the work activities within area of work shall be obtained from Operating Authority & duly registered into the work permit log.The Work area shall be surveyed to establish existing services location using the Operating Authority easement drawings and the cable detector. These services shall be exposed by hand dug trenches along the route. Where the existing service may cross the route of the proposed work activity, adequate protection and warning of that existing service shall be provided.The method of excavation for the work activity shall be defined upon the work permit. Where mechanical methods are accepted, a banksman shall be deployed with all mechanical excavation equipment to check for any existing service and advise the operator of the excavation machine. The excavated material where possible shall be stockpiled in a controlled area location. Any unsuitable material shall be removed from site to the spoil area immediately.Where soil conditions dictate, the sides of the trench shall be sloped.During the duration of the work activities, the site shall be kept clean.& tidyThe Civil Contractor QC department shall conduct the required inspection and test regime required under the ITP.Upon completion of the work activity, all rubbish shall be removed from the work site. The easement area shall be left graded.EquipmentCable scanner.Dump trucks Excavators as applicable.Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 32: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

32 of

Compactors.AttachmentChecklist MS#12

Construction of main substationTop

IndexScopeReference DocumentsDefinitionResponsibilitiesSafetyMethodEquipmentAttachmentScopeThe purpose of this method statement is to define the sequence and methodology for the Construction of the Main Substation.DocumentsSpecifications DefinitionsE EngineerPSM Project Site ManagerCM Construction ManagerCS Construction SuperintendentResponsibilitiesThe CS shall plan and resource the Construction of Main Substation activities, to ensure that they are Constructed according to the Drawings and Specification.The Construction Foreman shall actually execute the works, directing the workforce as necessary.SafetyPrior to the commencement of any activities, the labour force shall receive a toolbox talk on the Project Site Safety requirements. Any process that is adopted that may have a particular Safety risk shall be assessed as required.MethodThis method statement details only the Structural Concrete works. Finishes, Steel Sheet Roofs, Ladders, Access Platforms, Internal and External Insulation, Galvanised Steel Mesh etc are not Included in this Method Statement.The Main Substation structure is to be constructed in the following stages.Stage 1:Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 33: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

33 of

Earthworks, blinding, waterproofing, screed protection up to defined Elevation Stage 2.Footing pad construction including kicker up to 100mm above top of footing.Stage 3.Stub columns / walls including anchor bolts for galvanised screen mesh up to underside of floor slab / ground beam – defined Elevation.Stage 4.Ground slab of HVAC room including anchor bolts for ladder / access platforms TOC Stage 5.Floor slab for Main Building TOC (Top of Concrete)Stage 6.Wall construction up to bottom of roof slab / roof beam elevation Stage 7.Roof slab construction including kicker for parapet wall.Stage 8.Parapet wall construction.The Transformer Bays and the Foundation are to be constructed in the following sequence:

Stage 1Earthworks, blinding, waterproofing, screed protection.Stage 2.Footing pad construction and kicker 100mm above the top of footing including water stop bar for transformer bay partition wall and boundary wall footings.Stage 3.Transformer bay partition walls full height of 10m including cast in anchor plates for Roof truss.Stage 4Transformer bay boundary wall including cast in sleeves for Fence Posts.Stage 5.Transformer foundation bases including bases for Sump and Valve Pit.Stage 6.Gravel Fill between foundations and walls.Stage 7.Steel Roof Trusses and Roof.Setting OutGrid line (1) to (13) and (A) to (D) shall be offset 3m away from the edge of the walls. The points shall be marked by a nail driven on top of wooden pegs driven into the ground and set in concrete.STAGE IExcavate whole area to Formation Level.Further excavate for transformer bay partition wall. Foundations to required elevations.Create Access ramp at either short ends to allow Heavy equipment to get in and out.Using grader and 12T Formation roller, Scarify and compact formation to elevation + 20mm.Test for degree of Compaction and get approved.

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 34: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

34 of

Set out grid lines (1) – (13) and (A) to (D). Use steel pins to be 2m away at outer edge of Concrete face.Mark Grid lines with chalk powder.Use Timber reapers to construct edge forms and place blinding Concrete to Elevation 98.50 200mm wider than required. Cure the concrete according to specifications requirements.Apply waterproofing membranes in sections one day prior to fixing formwork for base pads.STAGE IIPlace Formwork directly on Waterproof membrane.Formwork height shall be the height of Footing Pad + 30mm for protection screed. Timber shall be placed on top of the base formwork to act as kicker for Columns / Walls.Place Steel Reinforcement with Starter bars for Columns / Walls. Place timber reapers on bothfaces of the formwork for Contraction Joint at location indicated in the attached sketch No. 1. Care would be taken to ensure that contraction joints in west wall would be hidden behind GRC FaciaCare to be taken to ensure that waterbars are placed at the right position on the edge of Pad Concrete for Transformer Bay partition walls and East wall.Isolated footing bases shall be cast. Bases for wall foundations shall be cast as per sequence shown in attached sketch no. 2.STAGE IIIPlace Reinforcement for Stub Columns and Walls up to Floor Level.Place Formwork for Stub Columns and walls up to Floor Level.Vertical Construction Joints shall be located at same positions as indicated in the attached sketch No. 1. The distance from the corner shall not exceed 4.5m and the distance between intermediate ones shall not exceed 6m.Horizontal Construction Joints shall be at locations shown in Drawing No. as described in this Method Statement.Cast Stub Columns and Walls up to underside of Floor Slab.STAGE IV & VInstall Formwork for floor beams and floor slab including 100mm Kicker for main walls.Construction Joints for floor slab shall be as shown in attached sketch No. 3.Install Reinforcement for floor beam and Floor slab.Place steel channels and Box outs for openings in floor slab for switchgear control panels.Penetration sleeves / ducts shall be boxed out for cables and utility services Cast Floor slab in alternate panels. Construction Joints shall be located within the middle third point of slabs and beams as shown in the attached sketch No. 2.STAGE VIExternal Formwork for vertical walls shall be placed in position, aligned and supported.Box outs for Bus duct penetration, rebates for Personnel and Equipment, Blast door frames, Air Conditioner openings and others shall be Boxed out.Cast in items such as Anchor plates for Roof truss shall be fixed in position.Timber reapers for Contraction Joints shall be fixed to the outer formwork face.Steel Reinforcement shall be installed as required.Inner Formwork not exceeding 6m lengths shall then be placed after inspection approval of rebars up to the bottom of Roof slab level. Design calculations included as attached.Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 35: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

35 of

The wall section shall be cast. Formwork design is similar to the ones used at Seawater surge basin. The rate of pour shall not exceed 2m vertical height / hr.

STAGE VIIRoof Slab scaffolding shall commence even as the wall construction activity is in progress on completed sections of walls.Roof Slab Construction Joints are shown in the attached sketch.Suspended kickers shall be placed for parapet wall.The Roof slab shall be cast. A set of four cubes shall be taken for each pour.Scaffolding shall not be removed for 14days and until the full design strength of concrete is reached. Cubes shall be crushed for 7,14 and 28 day strength.STAGE VIIIRainwater chutes shall be boxed out on parapet wall formwork. Reinforcement shall be placed and concrete cast in the same manner as for main wall.CURINGEvery pour be it a footing, stub column, wall, floor or roof, shall be wet cured with Hessian, covered with polythene sheet and kept wet for a minimum period 14 days in accordance with the specification. 2nos, 5000ltrs. Capacity water tanks in elevated platforms shall be provided for round the clock curing operations.Approved Curing Compound shall be used in Roof Soffits.EquipmentExcavator / JCBTransit MixerCrane 20 TAttachmentSketch No. 1: Showing locations of Contraction Joints. Sketch No. 4. Showing Concrete Pouring Sequence.Sketch No. 2. Showing Construction Joints for floor slab.Sketch No. 3. Showing Construction Joints for Roof slab.#13

Removal of hazardous materialsTopIndexScopeReference documentsDefinitionsResponsibilitiesSafetyMethodEquipmentAttachment

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 36: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

36 of

ScopeThe purpose of this method statement, is to define the procedure that shall be implemented, for the investigation, quantification and disposal of the hazardous material upon the site.Reference documentsOperating Authority regulations.Bechtel HSE Manual.DefinitionsPSM Project Site ManagerGE Geotechnical Engineer.IS Infrastructure Superintendent.ST Survey team.ResponsibilitiesEPC Contractor shall coordinate with all concerned authorities, for their approval of the hazardous material disposal.The PSM shall plan, resource and control the activities required for the orderly execution of the hazardous material disposal.The IS shall monitor the activities, in compliance with this procedure.The GE shall ensure accurate reporting of the materials.SafetyPrior to the commencement of any activities, the workforce shall receive a Tool Box Talk on the project site safety requirements. PPE where appropriate shall be provided to those persons who shall come into contact with any hazardous materials.MethodThe hazardous material shall be located and identified upon the site. The ST shall record these details upon a site sketch.The GE and IS shall inspect the hazardous material visually and complete an inspection report. An accurate description of the material shall be provided. Where elements such as barrels are part of the hazardous material, the identifying marks upon the barrel shall be checked. Where appropriate, samples shall be taken to verify the content. Where such liquids have leaked into the soil, samples of the soil shall be taken to verify the amount of contamination. The ST shall assist the GE and IS to establish the extent of contamination. Trial pits may be dug to visually gauge the penetration of contamination. Samples of soil from these pits shall verify the content and absorption if any of the contaminant. The ST shall record the details.Upon receipt of the laboratory results that verify the analysis of the contaminant, a specific safety plan if required, shall be prepared for the safe handling of suspect material or soil. Any precautions that are not defined within this method statement but essential shall be taken up.The solid items of contaminated material shall be lifted by loader shovel into the rear of a tipper truck. An inventory of the items loaded into the truck shall be produced. A permission shall be obtained from the operating authority for the purpose of disposal of hazardous material waste into a designated area. The truck covered with a dust preventive sheet shall transport the material to the approved Operating Authority waste disposal site in the industrial area. The Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 37: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

37 of

contents shall be offloaded in accordance with the facility rules and regulations monitored by the EPC Contractor representative.This process shall continue until all items of waste are removed from the site.The existing soil material that is contaminated shall be clearly marked with pegs. Using a loader shovel, the material shall be excavated and loaded into a tipper truck. The truck shall be covered whilst transporting the soil to the mixing area where the soil be stockpiled. This process shall continue until all contaminated soil is removed to the satisfaction of the GE.The stockpile of contaminated soil shall be lightly spread across the disposal area at levels above the water table. This shall be achieved by using loader shovel and grader. The layer thickness shall not exceed 150mm. A grader shall now mix this layer with the layer of uncontaminated material below. This shall have the affect of dispersing the material. A normal layer of uncontaminated material shall be placed upon the top of this mixed material. If required, a further layer of contaminated material shall be spread over this layer of material until the stockpile is depleted. This layer shall be mixed with the layer below as described previously.A topping layer of uncontaminated material shall be placed on top of all mixed material.The GE shall satisfy himself that the layer thickness is minimal and the material is adequately mixed with the layer below.Upon completion of the removal of the hazardous material, the GE shall prepare a report that identifies the material disposed as well as the areas of disposal.EquipmentExcavator.Grader.Dump trucks.AttachmentITP No: QCF, Visual inspection Report.#14

Construction of floor slab central control buildingTopIndexScopeReference DocumentsDefinitionResponsibilitiesSafetyMethodEquipmentAttachmentScopeStatements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 38: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

38 of

The purpose of this method statement is to define the sequence and methodology for the Construction of the floor slab to the Central Control Building. DocumentsGrade Slab General ArrangementGrade Slab Sections Foundation Details PenetrationDefinitionsPSM Project Site ManagerCM Construction ManagerCS Construction SuperintendentResponsibiltiesThe CS shall plan and resource the Structrual Backfill activity to achieve the required compaction as per the specification. The site test laboratory shall conduct and verify the compaction crireria.The surveyors shall be responsible for setting out the exact levels of fill and concrete up to designated drawings.The construction Foreman shall actually lead the execution operations by directing all Foreman and workforce as necessary.

SafetyPrior to the commencement of any of the required activities, the Labour force shall receive a tool box talk on the Project Site Safety requirements.MethodThe slab on grade level shall be casted over compacted fill by using a separation Polyethylene Membrane. The slab is divided into two main portions.The low level portion at EL shall have a smooth level finish in order to receive the bases of the access panel system. This portion is to be cast in panels to give the required joints as specified on the drawing.The high Level portion at EL shall be cast in panels according to the required joints shown on the drawings. The surface finish for this section shall be rough since Tiling and flooring systems are to be applied. In Electro-Mechanical rooms the surface finish shall be smooth to receive the epoxy coating finish as specified.General Curing shall be carried out to the norms of the Project Specifications.All cable trenches and separating Wall shall be cast up to levels and dimensions specified on related drawings.EquipmentCrane 50Ton 2 No.Flat Bed Trailor 40 Ton 1 No.Excavator Backhoe 1 No.Plate Compactor 1 No.Water Tanker 1 No.LabourCasting Engineer 1 No.Placing Engineer 1 No.Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 39: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

39 of

Casting Foreman 1 No.Placing Foreman 1 No.Carpenters 20 Nos.Steel fixers 30 Nos.Masons 20 Nos.Laborers 40 Nos.AttachmentNone.

#15

Mortar for blockworkTopIndexScopeReference DocumentsDefinitionResponsibilitiesSafetyMethodEquipmentAttachmentScopeThe purpose of this method statement is to define the sequence and methodology for the production of mortar for use with the blockwork activities.DocumentsMasonaryDefinitionsPSM Project Site ManagerCM Construction ManagerCS Construction SuperintendentResponsibiltiesThe CS shall plan and resource the blockwork activity, to achieve the required combination of workmanship and material quality.The construction Foreman shall actually lead the execution operations by directing all the workforce as necessary.SafetyPrior to the commencement of any of the required activities, the Labour force shall receive a tool box talk on the Project Site Safety requirements.MethodThe block supplier shall be submitted for approval to EPC Contractor.The sand aggregate for the mortar shall be submitted and approved by EPC Contractor.Potable water from the Operating Authority source shall be used for mixing sand and cement.Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 40: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

40 of

Storage of materials shall be on appropriate seggregated suitable areas adjacent to the work place with no possibility of contamination or deterioration of the materials.Mortar shall be mixed mechanically on site using standard boxes for measuring sand for each batch. The amount of water required shall also be defined depending on water cement ratio.The ingredients shall be mixed thouoghly until a uniform mix is achieved.Mix production quantiry in one batch shall be limited to a volume which can be consumed within the initial setting time of cement. The remixing of martar by adding additional water shall not be permitted.Once the mortar is produced, it shall be taken to the workplace and used within specified setting time that is generally 2 hours of adding into the mixer.EquipmentCement mixerGauge boxesHand tools.AttachmentNone.#16

Control of camp sewage systemTop

IndexScopeReference DocumentsDefinitionResponsibilitiesSafetyMethodAttachmentScopeThe purpose of this method statement is to actions that shall be implemented to monitor and control the sewage holding tank status, so that overflow is avoided.DocumentsMethod statement Waste Management.DefinitionsPSM Project Site ManagerCB Camp BossTM Transport Manager.ResponsibilitiesThe PSM shall be responsible for the implementation of the preventative measures. The CB shall execute the required monitoring and record keeping of the investigation.The TM shall ensure the provision of the disposal tankers as and when required.

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 41: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

41 of

SafetyAll relevant safety issues including hygiene precautions shall be implemented, monitored and maintained for this activity. The site safety department shall monitor the sewage disposal areas.MethodA new water meter to record water usage shall be installed prior to the water storage tanks. For the next one month, regular readings at specific times shall be recorded to establish water requirement trends.The information collected from this exercise shall help to understand the peak demand periods which also define the sewage disposal requirements. In parallel to this water input recording, a survey of the sewage holding tanks filling trends shall be established.A tank volume indicator system shall be installed at every sewage holding tank. This indicator system shall consist of a visible indicator rod. Based on a float system, the rod shall raise up as the holding tank fills. This visual system shall remind the CM to organise the emptying of the tank. Data obtained from the tanker drivers on number of loads discharged, shall help verify the water meter quantity to establish leakage’s.The existing provision for the trucking of the sewage waste shall be monitored. The fleet capacity shall be increased as required based upon the results of the survey.A review of the collected data shall be conducted after one month to supplement existing operational criteria as required. The responsibility for compiling the information shall be with the camp boss who ensure that water consumption is regularly monitored, that areas of water abuse are identified, that holding tank emptying schedule established as well as formulating measures to conserve and re-cycle water wherever possible.Initial trucking capacity that is dedicated to the sewage disposal activity is ‘two trucks’. These trucks operate on both suction fill and pump fill systems.The survey shall review and confirm the required trucking levels needed to service the holding tanks. Attachment.N / A#17

Structural steel-piperacksTop

IndexScopeReference documentsDefinitionsResponsibilitiesSafetyMethodEquipment

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 42: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

42 of

ScopeThe purpose of this Method Statement is to define the sequence and methodology that shall be implemented for the Erection of the steel structure piperacks.Reference DocumentsSpecification GroutingSpecification Steel Structure FabricationSpecification PaintingSpecification GalvanizingSpecification Project Preservation and Export PackingRelevant IFC drawings.DefinitionsCM Construction Manager.CS Construction Superintendent .EF Erection Foreman.ResponsibilitiesThe CM shall plan and resource the steel structure erection activities, to ensure that they are implemented according to this procedure, with the correct equipment resources.The CS shall ensure that all safety requirements are implemented and explained to the erection workforce. The CS shall control the day to day activitiesThe EF shall control the workforce ensuring the full implementation of this method statement including all safety measures.SafetyPrior to the commencement of any activity, the labour force shall receive a Toolbox Talk on the Project Site Safety Requirements. Any process that is adopted that may have a particular Safety risk, shall be assessed and addressed as required. The use of cranes shall be assessed and all safety regulations enforced.Men working at height shall be equiped with the required personal safety equipmentMethodMaterials Receivables.All Structural steel material to be used for permanent works shall be received on site in the appropriate laydown area. All tems shall be inspected to conduct a check of the delivery against necessary shipping documents. All structural steel members shall be checked for quantity, quality and identification.Then all materials shall be properly stored and protected.Concrete Foundations.The surface of the concrete foundation shall be prepared in accordance with the specification, to receive grout.All concrete foundations on which the steel structures are to be erected shall be released by the QC department upon completion of the civil activity.\\\\Fasteners (Bolts, Nuts & Washers).Upon receipt on site of the fasteners, a minimum of one sample (1bolt, 1 nut,& 1 washer) shall be selected and tested by an independent laboratory to confirm specification conformance.

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 43: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

43 of

Assembly Of Grid FramesMaterial for the necessary grids shall be placed near to the area of erection. This shall be carried out using a suitable trailer & a 50 ton crane.The grid frames for both rows (A&B) shall be assembled. All bolts, washers and nuts shall be fitted, fastened and tightened.Erection Of Columns \ Grid Frames.Stainless steel shim plates to the correct thickness of approx. 25mm shall be placed at the center of the foundation column between the holding down bolts. The shim plates shall be retained in position permanently by surrounding with mortar to avoid shim displacement during the erection of the columns. The shim placed on the foundation shall be embedded in mortar bed such that the top of the shim is level in all planes. The grid frames shall be installed leveled and plumbed on the foundation bases. Stay ropes shall be provided to maintain stability until such time when the horizontal members are connected. The stays shall be secured to purpose made anchor plates attached to adjacent foundations. Foundation bolts shall be only hand tightened. (Necessary tightening or torquing shall be done later after grouting). Horizontal members and the bracings that interconnect these grid frames shall be assembled and erected.The assembly of Verticals and Horizontal members shall be in sections. On completion of each section with all bolts and nuts in place and tightened, the final level and alignment shall be checked and inspected. GroutingAfter the structural steel frame assemblies have been inspected by the QC department, the application of grouting shall be carried out according to the Specifications & manufacturer’s instructions.EquipmentCrane 30Ton\ 50 TonFlat Bed Trailor to transport fabricated members to the location at siteFork lift – for minor movement of steel membersGuy ropes and tensioning equipmentMan baskets whenever requiredScaffolding (Movable & Non-movable Types)Air CompressorImpact WrenchWelding Generator( if required)Gas Cutting Equipment (if required)Portable Grinding MachinesPortable Drilling Machines

Exclusively written by PEng Suraj Singh

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 44: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

44 of

#18Compressors’ structures RCC column plate insertsTop

IndexScopeReference DocumentsDefinitionResponsibilitiesSafetyMethodEquipmentAttachmentScopeThe purpose of this method statement is to define the sequence and methodology that shall be implemented for the inclusion of RCC column plate inserts.DocumentsSpecification Drawing No:DefinitionsPSM Project Site ManagerCM Construction ManagerCS Construction SuperintendentFM ForemanResponsibilitiesCM shall plan and resource the required materials ensuring that these are implemented according to this procedure.CM shall ensure that all the Safety requirements are implemented and explained to the relevant work force and control the day to day activities.CS shall ensure the implementation of technicalities involved.FM shall control the work force ensuring the full implementation of the procedure.SafetyPrior to the commencement of any activites, the labour force shall receive a toolbox talk on the Project Site Safety requirements. Any process that is adopted that may have a particular Safety risk, shall be assessed as required.Method

1. Place & fix the column reinforcement be in design locations.2. Make the fabricated forms ready.3. Drill the holes on the marked locations on the forms ’2’ sides according to the

attached sketch to receive inserts holding bolts.Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 45: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

45 of

4. Fix the column inserts plates assembly on the fabricated forms and the bolts fastened as per sketch.

5. Erect the forms, support, well secure and concrete pour be carried out.6. Having the pour been over, before striking the forms, the threaded bolts be taken

out.7. Later the holes left shall be filled with Galvanised threaded rod 15mm long.

EquipmentFabricated Plates with Threaded holes, Pins and Bolts.AttachmentSketches#19

Excavation for 132kv cable interconnectionTop

Comments incorporatedDuct bank construction addedIndexScopeReference documentsDefinitionsResponsibilitiesSafety

MethodEquipmentAttachmentScopeThis statement is aimed to present the proposed procedures to be adopted to carry out the excavation in preparation for laying of the 132 KV electric cable from the GUP power station through to the Company project site substation.

Reference documentsSpecification , Excavation & Backfilling for Underground structures.DefinitionsPSM Project Site ManagerCM Construction ManagerStatements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 46: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

46 of

CS Construction Superintendant FM Foreman

ResponsibilitiesThe CM shall plan and resource the trench excavation and backfilling activity, in accordance with this method statement.The CS shall control, coordinate and supervise all the activities directing the Construction Foreman The Construction Foreman shall practically execute these activities, direct the workforce as necessary and report to the CS for all day to day operational matters. EPC Contractor shall control all the activities.SafetyPrior to the commencement of any activities, the labour force shall receive a tool box talk every day on the project site safety requirements. Any process to be adopted having a particular safety risk shall be assessed and addressed as required.MethodPermits for the involved area excavation shall be obtained from the relevant authorities.The surveyor shall set out the proposed route of the electric cable trench per IFC drawings. Any existing services shown on these drawings or on the record drawings shall be located and identified by an EPC Contractor approved method (i.e. catscan). Wherever necessary, trial pits shall be manually excavated to expose the existing services. Wherever, the protection of the existing services are required, adequate protection and warning shall be installed. Cables or pipes that span the excavation shall be supported. Rigid ducts and trays shall be provided to protect and support these cables. All existing services encountered, shall be plotted by the surveyor on an as-built drawing.The trench shall be excavated by a track excavator to the correct lines and levels. Wherever necessary or as defined on the work permit, manual hand excavation shall be carried out.The sides of the excavation shall be sloped. Barriers shall be placed to indicate an open excavation. The excavated material shall be stockpiled along the trench areas for re-use. Surplus material shall be removed to the tip area by dump trucks. The surveyor shall monitor the lines and levels of the excavation activity.Upon EPC Contractor inspection, the excavated trench shall be released for the next operation as indicated upon the activity ITP following which, compaction of the formation level be carried out to the specified density. The field compaction test report shall be submitted. The surveyor shall provide suitable level pins that indicate the correct elevation of the sand bedding required for the cables. The sand bedding shall be laid and compacted in accordance with the specification. The cables shall be placed correctly within the trench in line with the IFC drawings. Cables shall be laid by the electrical department upon completion of which, EPC Contractor release the trench for the backfill and subsequent activities. Suitable approved backfill material shall be placed in layers, compacted around the cable & field tested. Cable tiles and warning tape shall be placed on top of the sand fill per approved drawing.This backfill activity shall continue up to existing ground level & the site left tidy

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 47: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

47 of

For the construction of the duct banks, the duct pipes shall be laid according to the sectional design details with fixing arrangements, forms erected to the required profiles. The concrete shall be poured at various intermediate locations in the first instance to create temporary downward anchor to counteract any possible duct uplift by the underducts fluid concrete upward pressure. When the arrangement is completed, the whole section be concreted to the defined level & finished accordingly. Major EquipmentCable Markers.Excavation equipment.Dump trucks.Compactors.AttachmentNone#20

Road crossing for 132 kv route Top IndexScopeReference documentsDefinitionsResponsibilitiesSafetyMethod including traffic management schemeEquipmentAttachmentScopeThe purpose of this method statement, is to define the sequence and methodology for the excavation and laying of PVC ducts , that shall cross existing roads at locations identified on the attached drawing part . Reference documentsSpecification. Excavation & Backfilling for Underground structures.(INTERCONNECTS UNDERGROUND LAYOUT DRAWING SHEET ‘ 5 ‘)DefinitionsPSM Project Site Manager.CM Construction Manager.CS Construction SuperintendantFM Foreman ResponsibilitiesCM shall plan and resource the trench excavation and backfilling activity, in accordance with this method statement. The Construction Foreman shall monitor these activities, directing the workforce as necessary. Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 48: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

48 of

EPC Contractor shall control the service laying activities.SafetyPrior to the commencement of any activity, the labour force shall receive a tool box talk on the project site safety requirements. Any process that is adopted having a particular safety risk shall be assessed and addressed as required.A competent inspector shall inspect the trench daily to assess the safety measures adopted as well as after every rainstorm. If required , the shoring shall be provided to prevent the caving in . In case of the trench depth being more than 1200 mm , adequate means of exit such as ladder or steps shall be provided and located no more than 8 m of lateral travel. Barricades , markers and the night lights etc., shall be arranged as required.MethodThe required permit to work shall be obtained from the Plant Refinery Division.A traffic management scheme that has been presented herein as detailed on the attached sketch for this road crossing which includes, reduced speed sign, temporary diverted roads sign, men at work sign, warning signs, informatory signs, safety barriers,night lighting and road cleaning activities shall be implemented on site after review & approval by EPC Contractor prior to commencing the work.The aforesaid traffic management scheme is described below Traffic Scheme Road Crossing Inter Connects Underground Layout Drg This proposed crossing is located on the road avenue C as shown on the attached sketchThis is a 2 way road with a central verge and carrying 2 lanes on either wayThe road shall be divided in 2 parts as shown on the sketch as lane L1 and L 2 on either side of the carriage wayIn the first instance the work shall be carried out on part L1 diverting the traffic to the road portion on the part L2 as shown on the sketchIn the second instance the work shall be carried out on part L2 diverting the traffic to the road portion on the completed road portion on the part L1 as shown on the sketchThe first reduce speed for traffic diversion informatory board depicting shall be located at 300 m from the point of the proposed crossing, the second depicting diversion sign be located at 200 m and the third depicting men at work sign be located at 100 m on either way in the opposite directions.The first section of road crossing as per the attached sketch shall be marked by the surveyor on the actual road location. Any existing services shall be identified and protected.The asphalt shall be cut using a mechanical cutter machine.The road section shall be excavated to the correct level using mechanical means and removed from the site to stock pile area.The excavated material shall be removed to a stockpile area.Appropriate bedding material shall be placed within the excavated trench to the correct service level. Wherever required, this bedding shall be compacted and tested for field density.The cable ducts or service pipes shall be laid at the required levels and profile according to the drawings as well as the specifications and approved by the EPC Contractor’s Engineer.Backfill around the service pipes shall be carried out with the appropriate approved material. This service pipe surround material shall be compacted complying with the project specifications. Test results shall be reported.Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 49: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

49 of

General fill up to the underside of road formation shall be placed in 150mm layers compacted mechanically complying with the specifications.A concrete slab shall be cast up to the bottom of the finished asphalt level and the finishing done by using approved asphalt mix .The traffic management system shall be removed after the road crossing has been cleaned of any debris or obstructions.Either side of the road shall be provided with cable markers to indicate the servicesEquipmentExcavator .Dump trucks.Compactors.AttachmentSketch showing the traffic diversion.Sketch showing the location of the proposed crossing.

#21

Night shift working - earthworksTop

IndexScopeReference documentsDefinitionsResponsibilitiesSafetyMethodEquipmentAttachmentScopeThe purpose of this method statement, is to define the procedure that shall be adopted for the earthworks activity during Night Shift.Reference documentsSpecification DefinitionsEPC ContractorCivil Contractor IS Infrastructure Superintendent.PSM Project Site ManagerSO Safety OfficerResponsibilitiesThe PSM shall ensure that adequate site management and supervision is available for night shift working.Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 50: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

50 of

A dedicated SO shall patrol the site during the night shift activities, and where necessary, stopping the work if an unsafe situation arises.The necessary work permits shall be obtained prior to the start of the night shift activities.SafetyThe SO shall ensure all those persons who shall work on the night shift activities, are fully aware of the safety obligations expected from them. The emergency procedure for first aid shall be explained to every body. (Refer to the safety plan for night shift working).All equipment that shall operate on the site shall be in full working order with appropriate lighting.MethodThe activities that are schedules to be carried out during night shift comprise of excavation, hauling, stockpiling, spreading, leveling, watering and compaction. These activities do not require any specific QC inspection coverage other than the supervisor surveillance. The IS shall prepare the schedule define the work faces of the night shift activity prior to beginning.The work faces shall be illuminated by using tower-mounted easily repositionable floodlights.The routes which the construction equipment shall use for hauling ‘the excavated materia’, shall be made safe prior to work commencing.The area for stockpiling the material shall also be illuminated. A banksman wearing a high visibility vest shall direct the stockpile area. Similarly, a banksman shall direct the excavation area. The two banksmen shall be in communication with each other by two way communication facilities (mobile phones).The earthwork supervisor and the SO shall patrol the entire site overseeing all activities.Emergency Procedure.The Safety Officer shall be responsible for coordinating the night shift emergency procedure. Upon an emergency arising, the Safety Officer shall be notified.The Safety Officer shall immediately alert the relevant emergency services if so required.997 for Fire or civil defence998 for an Ambulance.999 for Police.The Safety Officer shall notify the Safety Manager of the emergency occurence. Should the camp doctor be required, he shall be notified. The Safety Manager shall attend the emergency and take control of the situation.The required notification, investigation and reporting of the emergency shall be conducted in accordance with the site HSE plan.First Aid.First aid facilities shall be made available for night shift operations at the camp clinic.The Safety Officer shall have the telephone number of the camp doctor who be summoned in the event of first aid requirements and emergencies.EquipmentExcavators.Dump trucks.AttachmentStatements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 51: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

51 of

None.

(Revised)Additional manufacturer’s instructions for mixing incorporatedForm details amendedManufacturer’s method statement attached

#22Grouting to pipe rack foundation basesTopIndexScopeReference documentsDefinitionsResponsibilitiesSafetyMethodEquipmentScopeThe purpose of this Method Statement is to grout the annular space between the foundation top and the structural steel base plates.Reference DocumentsSpecification DefinitionsPSM Project Site ManagerCM Construction Manager.CS Construction Superintendent .FM Foreman.ResponsibilitiesThe CM shall plan and resource the Cementitious grout activities, to ensure that they are implemented according to this procedure, with the correct equipment resources.The CS shall ensure that all safety requirements are implemented and explained to the erection workforce. The CS shall control the day to day activitiesThe FM shall control the workforce ensuring the full implementation of this method statement including all safety measures.SafetyPrior to the commencement of any activity, the suitably qualified labour force shall receive a Toolbox Talk on the Project Site Safety Requirements. Any process that is adopted that may have a particular Safety risk, shall be assessed and addressed as required. About the Chemical effect, Masks to be worn, Safety glasses and gloves to be usedAreas of Activity to be Barriered Off / No Unauthorized Entry, Sufficient Lighting to be provided where necessary.Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 52: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

52 of

MethodThe surface to be grouted shall be chipped / scabbled without using mechanical bush hammer to expose the aggregate and remove the laitance. The finished surface shall be free from oil, dust , dirt, paint, curing compounds etc and be soaked in with water for 24 hours prior to grouting to minimize the localized absorption as well as to assist the free flow of the grout.The bolt holes / pockets shall be waterfree prior to placement of grout.The baseplates / bolts shall be clean and free of oil, grease and paint and correctly aligned according to the approved drawings.The stainless steel shims 50x50x10 mm thick shall be in correct locations covered with mortar so as to allow at least 50 mm grout cover on shim sides.The forms as shown on the attached sketch shall be erected on the defined locations provided with chamfers.An electric drill fitted with a paddle shall be used for the grout mixing purpose using water @ 3.5 to 4.5 litres per 25 kg bag of Master flow 928 according to product datasheet.The mixer shall be clean with no standing water.Let 90 % of the applicable quantity of water required to achieve the desired consistency to meet the batch volume per manufacturer’s datasheet be added to the mixer before adding the grout and the Masterflow be added gradually while simultaneously, pouring in to the mixer the remaining 10 % water quantity during mixing which has to be kept on for at least 3 to 5 minutes until a uniform lump free consistency is achieved.The grout shall be poured continuously using the grout pour cone with a constant hydrostatic head of at least 15 cm Having poured the grout Masterflow 928 in place, cover all exposed grout material with clean damp Hessian and be kept moist until grout is firm enough to accept a curing membraneThe temperature range 4 to 32 degree C shall be maintained for the 3 post pour continuous days.The grout thickness varies between 25 to 50 mm.EquipmentPeddle MixerGrout Flow ConeAttachmentSketchMasterflow CatalogueMasterflow Method Statement

#23

Cementitious grouting to foundation basesTop

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 53: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

53 of

IndexScopeReference documentsSafetyMethodEquipmentScopeThis statement is aimed to propose the procedures to be adopted to grout the base plates of the stationary equipment / vessels foundation bases. Reference DocumentsSpecification SafetyPrior to commencement of any activity, the labour force shall receive a STARRTCard / Toolbox Talk relevant to the operation concerned on the project site safety requirements. Necessary measures shall be applied to any process involving a safety riskSafety Supervision A competent inspector shall visit the area daily to assess the safety measures adopted. Any snag observed during his visit shall be notified to the supervisor present who immediately act to bring the safety measures to an acceptable standard MethodThe surface to be grouted shall be chipped / scabbled without using mechanical bush hammer to expose the aggregate and remove the laitance. The finished surface shall be free from oil, dust , dirt, paint, curing compounds etc and soaked with water for 24 hours prior to grouting to minimize the localized absorption as well as to assist the free flow of the grout.The pockets shall be waterfree prior to placement of grout.The baseplates shall be clean and free of oil, grease and paint and correctly aligned in line with the approved drawings.The stainless steel shims 50x50x10 mm thick shall be in correct locations covered with mortar so as to allow at least 50 mm grout cover on shim sides.The forms as shown on the attached sketch shall be erected on the required locations with chamfers.An electric drill fitted with a paddle shall be used for the grout mixing purpose using water @ 3.5 to 4.5 litres per 25 kg bag of Master flow 928 according to requirement.The mixer shall be clean with no standing water.Let 90 % of the measured quantity of water required to achieve the desired consistency according to the batch volume be added to the mixer before adding the grout and the Masterflow be added gradually ,simultaneously pouring in the remaining 10 % water quantity during mixing , which has to be kept on for at least 3 to 5 minutes until a uniform lump free consistency is achieved.Let the grout be poured continuously using the grout pour cone with a constant hydrostatic head of at least 15 cm

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 54: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

54 of

Having poured the grout Masterflow 928 in place , cover all exposed grout with clean dampen Hessian and be kept moist until grout is firm enough to accept a curing membraneThe temperature range 4 to 32 degree C shall be maintained for the 3 post pour continuous daysThe grout thickness varies between 25 to 50 mm.Major EquipmentPeddle MixerGrout Flow ConeAttachmentSketchMasterflow CatalogueMasterflow Method Statement#24

Etylene compressor Massive foundation (concrete pour)Top

IndexScopeReference DocumentsDefinitionResponsibilitiesSafetyMethodAttachmentScopeThe purpose of this method statement is to define the sequence and methodology that shall be implemented for the Concrete pour of the Ethylene Compressor Foundation.DocumentsSpecification Drawing No:DefinitionsCM Construction ManagerCS Construction SuperintendentFM ForemanResponsibilitiesCM shall plan and resource the required materials ensuring that these are implemented according to this procedure.CM shall ensure that all the Safety requirements are implemented and explained to the relevant work force and control the day to day activities.CS shall ensure the implementation of technicalities involved.

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 55: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

55 of

FM shall control the work force ensuring the full implementation of the procedure.SafetyPrior to the commencement of any activites, the labour force shall receive a toolbox talk on the Project Site Safety requirements. Any process that is adopted that may have a particular Safety risk, shall be assessed as required.Method

1. Pour Size = (14.86 x 11.24 – 2.56 x 0.84) 1.7 = 280.2892 approximately2. Pour Plan = In Strips Courses of each 11.24m x 2m x 0.4m i.e. width wise (8.992

each).3. Sequence of strips shown in attached details in numbers.4. Time of Pour commencement 7.30 / 8.00 Hrs.5. Plants - Concrete Pumps 1No.

Batching Plant 1No. Full Time. / Stand by 1No.Transit mixer 7 Nos. 7m³ eachDelivery continuous @ 7minutes intervals.

6. Pour Duration 6 to 7 hrs.7. Equipment:

Vibrator – Pneumatic / Diesel Operated 3 Nos. (2Nos.in use and 1 Stand by) and 3 Nos. on other sites.

8. Curing-Thermal Immediate Post Pour: By Curing Compound covered by Polythene membrane. Post Pour Set concrete: By removing Polythene, adding saturated Hessian,

recovering with Polythene membrane and filling clean sand 150mm except the column portion which shall be surrounded by small sand embarkments. The sand shall be kept sprayed with water.

9. Water Supply: By tank, full tank ready on site with 50m water hose pipe.10. Manpower:

Concrete Crew Foreman - 1 No. Steel fixers – 2 Nos. Carpenters – 2 Nos. Masons - 12 Nos. Helper - 12 Nos.

11. Specifications High Slag blast furnace cement to BS 4246 with 70% replacement utilising 30% ASTM C150 Type II cement for use in massive concrete.

12. Concrete Temperature 30°C.Slump 150 – 175mm

Attachment1 Sketches2 Plan of Pour3 Sectional Sequence details of pour layers.

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 56: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

56 of

#25

Propane compressor Massive foundation (concrete pour)Top

IndexScopeReference DocumentsDefinitionResponsibilitiesSafetyMethodAttachmentScopeThe purpose of this method statement is to define the sequence and methodology that shall be implemented for the Concrete pour of the Ethylene Compressor Foundation.DocumentsSpecification Drawing No:DefinitionsPSM Project Site ManagerCM Construction ManagerCS Construction SuperintendentFM ForemanResponsibilitiesCM shall plan and resource the required materials ensuring that these are implemented according to this procedure.CM shall ensure that all the Safety requirements are implemented and explained to the relevant work force and control the day to day activities.CS shall ensure the implementation of technicalities involved.FM shall control the work force ensuring the full implementation of the procedure.

SafetyPrior to the commencement of any activites, the labour force shall receive a toolbox talk on the Project Site Safety requirements. Any process that is adopted that may have a particular Safety risk, shall be assessed as required.Method:

1 Pour Size = (12.0 x 7.5 – 2 x 0.44 x 0.78) 1.7 = 151.833 approximately2 Pour Plan = In Strips Courses of each 7.5 x 2 x 0.4m i.e. width wise (6.0m³ each).3 Sequence of strips shown in attached details in numbers.4 Time of Pour commencement 7.30 / 8.00 Hrs.5 Plants - Concrete Pumps 1No.

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 57: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

57 of

Batching Plant 1No. Full Time. / Stand by 1No.Transit mixer 7 Nos. 7m³ eachDelivery continuous @ 7minutes intervals.

6 Pour Duration 5 to 6 hrs.7 Equipment:

a. Vibrator – Pneumatic / Diesel Operated 3 Nos. (2Nos.in use and 1 Stand by) and 3 Nos. on other sites.

8 Curing-Thermala. Immediate Post Pour: By Curing Compound covered by Polythene membrane.b. Post Pour Set concrete: By removing Polythene, adding saturated Hessian,

recovering with Polythene membrane and filling clean sand 150mm except the column portion which shall be surrounded by small sand embarkments. The sand shall be kept sprayed with water.

9 Water Supply: By tank, full tank ready on site with 50m water hose pipe.10 Manpower:

Concrete Crew i. Foreman - 1 No. ii. Steel fixers – 2 Nos.iii. Carpenters – 2 Nos.iv. Masons - 12 Nos.v. Helper - 12 Nos.

11 Specifications 12 High Slag blast furnace cement to BS 4246 with 70% replacement utilising 30% ASTM

C150 Type II cement for use in massive concrete.13 Concrete Temperature 30°C.

Slump 150 – 175mmAttachment1 Sketches2 Plan of Pour3 Sectional Sequence details of pour layers.

#26

SeaWater Basin Baffle Walls (concrete pour)Top

IndexScopeReference DocumentsDefinitionResponsibilitiesSafety

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 58: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

58 of

MethodAttachmentScopeFor pouring the baffle walls 9 #s located on the deeper end slope of section AA between the PCJ and the commencement of the falls as the width of the slope being 5.35m.Since no provision of the starter rebars has been made for the slope portion at the ‘slab base level’ for the baffle walls to be connected with then to ensure the structural stability, we propose the following operational descriptions for the construction execution of these elements.DocumentsDrawing No:DefinitionsPSM Project Site ManagerCM Construction ManagerCS Construction SuperintendentFM ForemanResponsibilitiesCM shall plan and resource the required materials ensuring that these are implemented according to this procedure.CM shall ensure that all the Safety requirements are implemented and explained to the relevant work force and control the day to day activities.CS shall ensure the implementation of technicalities involved.FM shall control the work force ensuring the full implementation of the procedure.SafetyPrior to the commencement of any activites, the labour force shall receive a toolbox talk on the Project Site Safety requirements. Any process that is adopted that may have a particular Safety risk, shall be assessed as required.MethodStage 1: Pouring the walls in full heights between the wall designated ‘M’ and the

construction joints locations.Stage 2: Pouring the portion of the baffle walls between the construction joint and the wall

end upto a level of 7.14m from the slab base.Stage 3: Pouring the remaining portion of the baffle walls from the level 7.14 upto the level

13.5 with a simple construction joint at the level of 7.14m.AttachmentNone.#27

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 59: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

59 of

SeaWater BasinMinor Concrete Repair at Kicker Face

Top

IndexScopeDefinitionResponsibilitiesSafetyEquipmentMaterialMethodAttachmentScopeFor minor concrete repair specially at kicker face Filling of Tie rod holes.Reformation of grooves for sealant on floor slabs and walls.DefinitionsPSM Project Site ManagerCM Construction ManagerCS Construction SuperintendentFM ForemanResponsibilitiesCM shall plan and resource the required materials ensuring that these are implemented according to this procedure.CM shall ensure that all the Safety requirements are implemented and explained to the relevant work force and control the day to day activities.CS shall ensure the implementation of technicalities involved.FM shall control the work force ensuring the full implementation of the procedure.SafetyPrior to the commencement of any activites, the labour force shall receive a toolbox talk on the Project Site Safety requirements. Any process that is adopted that may have a particular Safety risk, shall be assessed as required. Use of safety glasses, gloves, mask, etc., shall be made.EquipmentROADCRAFT model #. 5615 NEEDLE Scaler (Light version for removal of rust, welding slag, old paint etc.)MaterialMaterial Epoxy bonding agent MBT Concresive 1414 (permanent epoxy adhesive for internal or external bonding for renderings, concrete repairs, bonding concrete to concrete, steel and granolithic toppings)

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 60: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

60 of

MBT Masterflow 544 (High strength, non shrink cementitious mortar ready to use product in powder form requiring only on site addition of water to produce a non–shrink mortar of predictable performance formulated for use at plastic consistency for bedding, repairing, grouting and void filling such as concrete repairs, void filling between old and new concrete, filling tie bar holes etc.)Method1 The existing surface shall be scabbled, all loose concrete and mortar drippings removed

by using a single head scabbler and / or RODCRAFT model # 5615 NEEDLE scaler. 2 Epoxy bonding agent MBT Concresive 1414 shall be applied by brush and allowed to cure.3 MBT Master flow 544 shall be mixed with water in small pails by hand complying with

manufacturer’s data sheet and trowelled onto the surface.4. Approved curing compound shall be applied immediately5 A wooden strip 25mm wide X 20 mm deep shall be placed at the centre of the joint on the

existing rebates in the floor slabs as well as walls and the space on either side be filled with MBT Master flow 544 to obtain a clear rebate of X-size 25mm x 20 mm followed by removal of the wooden strip within an hour of fill and the reformed surfaces be sprayed with approved curing compound.

AttachmentManufacturers Catalogue#28

Seawater basin(water tightness BS 8007: 1987)

Top

IndexScopeDefinitionResponsibilitiesSafetyMethod / ProceduresEquipmentAttachmentScopeTo transport the Sea Water to the Sea Water Basin and Testing the basinDefinitionsPSM Project Site ManagerCM Construction ManagerCS Construction SuperintendentFM ForemanResponsibilitiesCM shall plan and resource the required materials and plants ensuring that these are implemented according to this procedure.Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 61: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

61 of

CM shall ensure that all the Safety requirements are implemented and explained to the relevant work force and control the day to day activities.CS shall ensure the implementation of technicalities involved.FM shall control the work force ensuring the full implementation of the procedure.SafetyPrior to the commencement of any activites, the labour force shall receive a toolbox talk on the Project Site Safety requirements. Traffic directory signs for the ramp breakers on 3 nos road crossings shall be installed. On the exposed pipe route the safety tags shall be installed with cones. A protection arrangement shall be made for the plants at the intake. A full time attendant shall keep the watch and ward on the route.Procedures involvedLaying a 100 mm dia hose from the sea to the sea water approximately1800 m. Refer to sketch point # 1 to # 8 i.e. intake at sea and discharge to the basin respectively.Constructing a concrete anchor at the sea to fix the intake pipe spout horizontally and vertically as well as to fix 2 # heavy duty centrifugal pumps at point #1There are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted in the form of the ramped speed breakers.Ref to the sketch. Otherwise, sleeves shall be inserted by road cutting, filling and making good when the job is overInstall a ‘round the clock’ generator to supply electricity to the pumps with the Distribution Board at point # 1 or to have electric connection through an alternative source.Install a timber clamping platform on the ditch at point # 4Water Heads calculations indicative onlyAt intake suction 1 mAt intake disposal 1 mVertical head loss 25 mAt point Nos. 8 loss 10 mTotal vertical head loss 37 mLength of Pipe for friction loss 1800 m 4 f l v v / 2 g d= 4x.015x1800x1.5x1.5 / 2x 9.81x.1=123.9mTotal head loss = static loss + dynamic loss = 37 +123.9 = 160.90 m Work done= 42000x160.9 kgm, bhp = 42000x160.9 / 270000= 25 units, ihp = 35 unitsThe water flow velocity has been assumed to be 1.5 m / sec giving a discharge of 42 cum per hour. It shall take 20 days to reach 20000 cum of water to the basin keeping round the clock pumping.

SEA WATER BASIN PLANNED PUMPINGDAY # QTYPUMPED

INQTY CUMM

CUM CUM1 1008 10082 1008 20163 1008 30244 1008 4032

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 62: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

62 of

5 1008 50406 1008 60487 1008 70568 1008 80649 1008 907210 1008 1008011 1008 1108812 1008 1209613 1008 1310414 1008 1411215 1008 1512016 1008 1612817 1008 1713618 1008 1814419 1008 1915220 1008 2016021 1008 21168

First phase TestingThe tank completed with Protective Coatings as specified and sealant applied shall be cleaned and filled to the normal maximum level to meet the requirement of clause 9.2 BS 8007 : 1987 Testing of structures i.e. upto 11.5 m which should take 14 days and then be retained for a stabilising period of 7 days for a maximum design crack width of 0.1 mm, allowing absorption and the autogenous healing. Test period starts now for 7 days and the drop in level recording be made every 24 hours during this 7 days period. Total permissible drop in level allowing evaporation etc. should not be more than 1 / 500 of the average water depth of the full tank which limits to 10 mm or another specified or calculated amount.Having the test been successful, the backfill shall be carried outSecond phase TestingLet the tank be further filled upto 13 m level i.e another 7 daysStabilisation period Another 7 days (for absorption and autogeneous healing)Test period Another 7 days (level drop recording at an interval of 24 hours)Basin Filling and Testing Schedule

S # Description of the operation Duration in

daysRemark

1 Ist phase water pumping 14 Pumping from sea 2 Retained water stabilisation to

allow absorption and autogeneous healing

7

3 Testing at 24 hour intervals and monitoring

7 Loss should not be more than 1 / 500 of average fullwater depth or 10 mm or other specified value

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 63: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

63 of

but excluding evaporation.4 Backfilling after successful

testing14

5 II phase water pumping 7 Pumping from sea

6 Retained water stabilisation and autogeneus healing

7

7 Testing at 24 hours intervals 7

8 Water loss monitoring Loss should not be more than 1 / 500 of average fullwater depth or 10 mm or other specified value but excluding evaporation

The code provides that notwithstanding the satisfactory completion of the test, any evidence of seepage of the liquid to the outside faces of the liquid retaining walls should be assessed against the requirement of the specification. Any necessary remedial treatment of the concrete, cracks or joints should, where practicable, be carried out from the liquid face. When a remedial lining is applied to inhibit leakage at a crack, it should have adequate flexibility and have no reaction with the stored liquid.Should the structure not satisfy the 7 days test then after the completion of the remedial work, it should be refilled and if necessary, left for a further stabilising period followed by a further test of 7 days’ duration should then be undertaken in accordance with this clause.

Equipment.Pumps IHP 35, 2 Nos.Other General ArrangementsAttachmentSketch showing the Hose Route#29

Road Crossing for 132 kV route Top IndexScopeReference documentsDefinitionsResponsibilitiesSafety

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 64: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

64 of

Method including traffic management schemeEquipmentAttachment

ScopeThe purpose of this method statement, is to define the sequence and methodology for the excavation and laying of PVC ducts, that shall cross existing roads at locations identified on the attached drawing part. Reference documentsSpecification. Excavation & Backfilling for Underground structures.Drawing No. (INTERCONNECTS UNDERGROUND LAYOUT ‘) DefinitionsPSM Project Site Manager.CM Construction Manager.CS Construction SuperintendantFM Foreman ResponsibilitiesCM shall plan and resource the trench excavation and backfilling activity, in accordance with this method statement. The Construction Foreman shall monitor these activities, directing the workforce as necessary. EPC Contractor shall control the service laying activities.SafetyPrior to the commencement of any activity, the labour force shall receive a tool box talk on the project site safety requirements. Any process that is adopted having a particular safety risk shall be assessed and addressed as required.A competent inspector shall inspect the trench daily to assess the safety measures adopted as well as after every rainstorm. If required, the shoring shall be provided to prevent the caving in. In case of the trench depth being more than 1200 mm, adequate means of exit such as ladder or steps shall be provided and located no more than 8 m of lateral travel. Barricades, markers and the night-lights etc., shall be arranged as required.MethodThe required permit to work shall be obtained from the Plant Refinery Division.A traffic management scheme which includes, reduced speed sign, temporary diverted roads sign, men at work sign, warning signs, informatory signs, safety barriers, night lighting and road cleaning activities has been presented herein that shall be produced on site as detailed on the attached sketch for this road crossing. The traffic management scheme shall be reviewed and approved by EPC Contractor prior to commencing the work.The aforesaid traffic management scheme shall be implemented as described below:Traffic Scheme Road Crossing Drawing reference Inter Connects Underground Layout Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 65: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

65 of

This proposed crossing is located on the road avenue C as shown on the attached sketch.This is a 2 way road with a central verge and carrying 2 lanes on either wayThe road shall be divided in 2 parts as shown on the sketch as lane L1 and L 2 on either side of the carriage way.In the first instance the work shall be carried out on part L1 diverting the traffic to the road portion on the part L2 as shown on the sketch.In the second instance the work shall be carried out on part L2 diverting the traffic to the road portion on the completed road portion on the part L1 as shown on the sketch.The first reduce speed for traffic diversion informatory board depicting shall be located at 300 m from the point of the proposed crossing, the second depicting diversion signs be located at 200 m and the third depicting men at work sign be located at 100 m on either way in the opposite directions.The first section of road crossing as per the attached sketch shall be marked by the surveyor on the actual road location. Any existing services shall be identified and protected.The asphalt shall be cut using a mechanical cutter machine.The road section shall be excavated to the correct level using mechanical means and the excavated material removed from the site to stock pile area.Appropriate bedding material shall be placed within the excavated trench to the correct service level. Where required, this bedding shall be compacted and tested.The cable ducts or pipes service shall be laid at the required levels and profile complying with the drawings, the specifications and approved by the EPC Contractor Engineer.Backfill around the service shall be conducted using the appropriate material. This service surround material shall be compacted as per the project specification requirements. Test results shall be provided for the specification conformance verification.General fill up to the underside of road formation shall be placed in 200mm layers and compacted to 150mm using mechanical methods complying with the specification requirements.A concrete slab shall be cast up to the bottom of the finished asphalt level and the finishing shall be done by using approved asphalt mix.The traffic management system shall be removed after the road crossing has been cleared of any debris or obstructions.Either side of the road shall be provided with cable markers to indicate the servicesEquipmentExcavator.Dump trucks.Compactors.AttachmentSketch showing the traffic diversion.Sketch showing the location of the proposed crossing.#30

Administration building Stair landing extension at grid 4 jStatements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 66: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

66 of

Top

IndexScopeReference documentsDefinitionsResponsibilitiesSafetyMethod including traffic management schemeEquipmentAttachmentScopeThe aim of this statement is to define the methodology how the extension to the existing part of the stair first flight landing at grid 4 J shall be effected to and connected to the existing RCC column as well as the correction to the proposed rebars to be placed in the portion of the first flight. Reference documents

DefinitionsPSM Project Site Manager.CM Construction Manager.CS Construction SuperintendantFM Foreman ResponsibilitiesCM shall plan and resource the trench excavation and backfilling activity, in accordance with this method statement.

The Construction Foreman shall monitor these activities, directing the workforce as necessary. EPC Contractor shall control the service laying activities.SafetyParticular safety shall be taken to cover the drilling in concrete activity and the pouring in the resin into the holes. The person grinding the concrete, drilling and filling in wear safety glass, gloves, masks etc.MethodThe proposed method involves the following procedures:Extend the RCC landing from its existing line to the outside face of the column at grid 4 J.Provide a shear key at the connection as shown for the extension as well as at column faceMaintain the flight width 1450 mm as designed keeping the column face flush with the waist line of the first flight.

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 67: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

67 of

Arrange the rebars in the manner to be placed within the above dimensions according to the details on drawing no…... To accomplish the above operations, preparatory works shall be carried out as usual for the form fixing and reinforcement placement.A ground cut for the shear key shall be provided in the middle 1/3 portion 25 mm deep for the bondage according to the sketch shown on the revised drawing ……. which continue across the column face also.Hilti HIT - HY 150 resin anchor system shall be used to dowel in the rebars for the extension portion into the existing RC landing using 16 T dia bars into 22 mm dia. drilled hole 240 mm long according to the manufacturer’s instructions (System already approved). Hilti drill machine TE 75 with 22 mm dia drill bits and the Hilti pouring gun kit 2000 shall be used.The dowels shall be approved by the EPC Contractor engineer. The remaining procedures shall be the usual operations regarding the RCC. EquipmentGrinder, Hilti drill TE 75, Drill bits 22 mm dia, Kit 2000, Material HIT HY 150 In Cartridges according to the requirement.AttachmentExtract of Drawing

#31

SeaWater BasinMinor Concrete Repair at Kicker Face Top

Comments incorporatedMaterial already approvedRepairable depth shown on the sketchPreparation & application modifiedCuring method specifiedMINOR COMMENTS INCORPORATEDIndexScopeReference documentsDefinitionsResponsibilitiesSafetyMethod EquipmentAttachmentScope

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 68: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

68 of

This statement is aimed to describe the procedures to be used to carry out making good the existing concrete surfaces by rectifying the undulations formed during the slope pour through cut outs on the top side slope shutters by the application of a shrinkage compensated , high strength repair mortar reinforced with acrylic fibres on the broken and the prepared surface.The repairable thickness is only 10 mm.

DefinitionsPSM Project Site ManagerCM Construction ManagerCS Construction SuperintendentFM Foreman

ResponsibilitiesCM shall plan and resource all the activities in accordance with this method statement. The Construction Foreman shall monitor these activities, direct the workforce as necessary. EPC Contractor shall control the activities.SafetyThe work personnel shall be given a Tool Box talk every day before the commencement of any activity relevant to the operational requirements according to the Project Safety Needs.In addition to the general safety measures to use personal safety Equipment,all persons to work on the demolition breaker, and the proprietary products application shall wear gloves, masks safety glasses etcEquipmentHilti Demolition Breaker TE 905 completePointed mechanical chisel ( Bushing tool TP-SKHM 60 )MaterialEMACO S88C T in bags 25 kg each Sodapcure WH curing compoundMETHODA shrinkage compensated , high strength repair mortar reinforced with acrylic fibresThe area to be repaired shall be marked on siteA depth of 10 mm from the proposed top level of concrete surface on the effected areas shall be broken out to remove all substandard concrete using Hilti demolition breaker. The vertical edges shall be cut with a grinder.The substrata shall be prepared to a rough surface having at least 5-mm amplitude at 20-mm frequencyThe prepared surface shall be sound, dense, free of all oil, grease, loose and fractured aggregate or other contaminants that could impair adhesion between the repair mortar and the prepared concrete surface.Thoroughly the repairable surface shall be wetted in to provide a ‘saturated surface dry condition’. Any standing water shall be removed prior to application of the mortar is commencedPriming of concreteStatements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 69: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

69 of

Prior to the application of EMACO S 88 CT , the concrete shall be wetted out with potable water to give a saturated surface dry condition. No further bonding agent is required as per manufacturer’s instructions.TEMPERATURE CONDITIONSEMACO S 88 CT shall be used when the ambient temperature is between +5 degree Celsius and 50 degree C, otherwise chilled water be utilised to prevent the mix temperature exceeding 32 degree CSubstrata temperature should not be less than 5 degree C. In hot weather, areas to be repaired shall be shaded to prevent from direct sunlightMIXINGHand mixing with trowel or similar of EMACO S 88 C T is not permitted according to the manufacturer’s instructions, therefore, a low speed electric drill with paddle attachment with a forced action mixer shall be used.Water addition shall be between 3.5 to 4 litres of potable water per 25-kg bag.The required quantity of water shall be poured into the pre- wetted mixing drum, and mixer started followed by the addition of EMACO S 88 C T powder rapidly and continuously,The mixing shall continue for 3 to 4 minutes after all the powder has been added until the mortar is homogeneous and lump freeMore water shall be added within the limits given, if necessary,until the required consistency is achieved and mixed for a further 1-minute. APPLICATIONAfter mixing, EMACO S 88 C T , the material shall be trowel applied by forcing into the prepared substrate ensuring intimate contact and good compactionThe surface of the placed mortar shall be levelled using a wooden float. Final finishing mat is done with a steel trowel. CURINGCuring shall be done by spraying the approved compound SODAPCURE WHA polythene membrane shall be used to protect the finished surface from the wind blown sand.AttachmentManufacturer’s method statement Sketch showing section#32

FencingTop

IndexScopeReference documentsDefinitionsResponsibilitiesSafetyMethodStatements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 70: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

70 of

EquipmentAttachmentScopeThe purpose of this method statement, is to define the sequence and methodology for the construction and erection of the site security fencing.Reference documentsSpecification Standard Drawing Standard Drawing Site Fence Location drawing DefinitionsPSM Project Site Manager.CS Construction Superintendent.ResponsibilitiesThe CS shall plan and resource the fencing activities, to ensure that they are constructed and erected according to the specifications.The Construction Foreman shall monitor the precasting and erection activities, directing the workforce as necessary.SafetyPrior to the commencement of any activities, the labour force shall receive a tool box talk on the project site safety requirements. Any process that is adopted that may have a particular safety risk, shall be assessed and addressed as required.MethodPrecast elements.A precast yard shall be established as shown on the attached sketch. The casting beds shall be such that pouring, stripping, curing and coating can be achieved easily. A casting cycle of 4 days is anticipated for casting, initial curing and coating, prior to removal to site.Easily assembled and stripped steel prefabricated moulds shall be utilized for the fence foundation and ground beam.Fence erection.The final grade level of the area shall be the commencement point for the fence construction.A level survey shall demonstrate the accuracy of the site grading activity.The Survey Team shall set out the line and level of the fence, including post locations for all elements.Using a machine mounted auger, 300 and 450mm diameter holes as appropriate, shall be drilled for the fence post foundations.The drilled holes shall be cleaned and bedded to the correct base level. The fence post foundation shall be placed in the drilled hole to the correct line and level.Dune sand shall be compacted around the foundation.The fence fabric shall be strung and tensioned as per the drawing details and manufacturers recommendations attached items 1.14 through 1.21Using hand tools, a trench shall be excavated for the ground beam.The ground beam shall be placed to the correct line and level. Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 71: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

71 of

Suitable fill material shall be used to compact around the ground beam.The fence fabric tie staple shall be grouted in position once the fence fabric is tensioned.The gap between the ground beams, at the location of the fence post, shall be concreted to form a continuous beam.QC procedures shall be closed out on an on-going basis.EquipmentConcrete Mixer truck.Auger machine.Wagon with hyab.Plate compactor.AttachmentDrwg no: Drwg no: Method statement for Link Middle East Ltd, Fence manufacturer.#33

Administration building Ceramic tiles flooring system Top IndexScopeDefinitionsResponsibilitiesSafetyMaterialMethod EquipmentAttachmentScopeThis statement is aimed to propose the procedures to be adopted to construct the‘ceramic tiles flooring system’ which involves the laying of the bedding screed as well as the finishing layer with grouting the joints including movement joints.Reference documentsDrawing Nos. Specifications UBC & general construction practiceDefinitionsPSM Project Site ManagerCSM Construction ManagerCS Construction SuperintendentStatements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 72: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

72 of

FM ForemanQC Quality ControlResponsibilitiesPSM shall control the overall operations CM shall arrange the resources required accordinglyCS shall control, monitor and direct the FM and workforce for the operationsFM shall execute the operations deploying the workforceQC shall inspect all the operations according to the specificationsEPC Contractor shall conduct surveillanceSafetyThe workers shall receive a Tool Box Talk according to the project requirement relevant to the operation concerned every day prior to commencement of the activity Proper illumination shall be provided in the dark area The area to be tiled shall be closed for the general movement except those working there and be opened only when the tiling has properly been completed with hardboard cover protection spread on the newly laid flooring.MaterialsCeramic floor tiles 300 x 300 x 10mm, For General Area ‘RAK GP 21 G’ and for wet areas Johnson ‘Athena’Joint filling grout – Approved proprietary material with matching shade.Method (Laying ceramic floor tiles by SEMI DRY method)The areas of concrete sub strata to be tiled shall be brush cleaned and dampened until absorption ceases followed by the finished floor level establishment by means of dots and rules. The total thickness of the ceramic tile flooring is 100 mm which includes 90 mm bedding screed (1 cement: 4 mortar sand) by weight and shall be applied as described below.The finishing layer shall be ceramic tiles 10 mm thick and be laid as described below. The mortar for bedding the tiles shall be 1 part cement to 4 parts sand by weight, mixed semi dry by a mechanical mixer with only sufficient water added to give a crumbly consistency which retains its shape when squeezed by hand permitting no fluidityThe mix shall be placed to a thickness approximately 10 mm greater than that actually required for the bed, thoroughly compacted by tamping and drawing off to the required level with a screed board. Only sufficient mortar shall be mixed and spread as can be covered with tiles before it attains its initial set. Civil Contractor QC visual inspection shall be conducted A slurry of 1 part cement to 1 part sand by volume shall be poured over the surface of the semi – dry mix bedding and spread with a trowel until it is approximately 2 mm thickDry tiles shall then be laid on the slurry and beaten firmly into position with a wooden beater ensuring a true surface contact between the tiles and bedding is formed.

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 73: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

73 of

The tiles shall be correctly positioned in both directions the time these are placed forming joints using a proprietary tile spacer ( 1.5 mm for wall tiles and 3 mm for floor tiles)The tiles shall neatly and accurately be cut to a close fit where necessary at abutments, around outlets, pipes and the like.Civil Contractor QC Inspection shall be conducted for the correct formation of joint alignment and the level profileThe tiles shall be laid level or to 1- % falls in ‘wet’ areas as may be required. Localised variations in level for a nominally flat floor shall be a maximum of +- 2-mm under a 3-meter straight edge. Particular care shall be taken in ‘wet’ areas to prevent low spots that may promote water pooling. The tolerance in the overall level shall not be more than 10 mm from required finishes. (Reef STQ ) Grouting of the joints shall be carried out within a period of not less than 24 hours after completion of laying of tiles so as to allow the grout attach itself firmly to the bedding. MOVEMENT JOINTS IN TILED FLOORSUnless otherwise indicated in the documents, a 10 mm movement joint shall be formed at the perimeter of all the tiled floors and where the tiling meets structural features such as columns, machine bases etc.,Where a structural movement joint is provided in the base, a movement joint of the same width in the bedded finish shall be positioned immediately aboveThe movement joint cavities shall extend through the combined thickness of the finish and the bedding mortar, completely filled and sealed after grouting of the normal joints takes place.Major EquipmentMechanical MixerWheel barrowsMason’s tools in generalAttachmentNone#34

Administration building Ceramic tiles flooring systemTop

IndexScopeDefinitionsResponsibilitiesSafetyMaterialMethod Equipment

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 74: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

74 of

AttachmentScopeThis statement is aimed to propose the procedures to be adopted to construct the‘ceramic tiles flooring system’ which involves the laying of the bedding screed as well as the finishing layer with grouting the joints including movement joints.Reference documentsDrawing Nos. Specifications UBC & general construction practiceDefinitionsPSM Project Site ManagerCSM Construction ManagerCS Construction SuperintendentFM ForemanQC Quality ControlResponsibilitiesPSM shall control the overall operations CM shall arrange the resources required accordinglyCS shall control, monitor and direct the FM and workforce for the operationsFM shall execute the operations deploying the workforceQC shall inspect all the operations according to the specificationsEPC Contractor shall conduct surveillanceSafetyThe workers shall receive a Tool Box Talk according to the project requirement relevant to the operation concerned every day prior to commencement of the activity Proper illumination shall be provided in the dark area The area to be tiled shall be closed for the general movement except those working there and be opened only when the tiling has properly been completed with hardboard cover protection spread on the newly laid flooring.MaterialsCeramic floor tiles 300 x 300 x 10mm, For General Area ‘RAK GP 21 G’ and for wet areas Johnson ‘Athena’Joint filling grout – Approved proprietary material with matching shade.Method (Laying ceramic floor tiles by SEMI DRY method)A continuous procedure to lay tiles over the cement mortar screedThe areas of concrete sub strata to be tiled shall be brush cleaned and dampened until absorption ceases followed by the finished floor level establishment by means of dots and rules. The total thickness of the ceramic tile flooring is 100 mm which includes 90 mm bedding screed (1 cement: 4 mortar sand) by weight and shall be applied as described below.Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 75: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

75 of

The finishing layer shall be ceramic tiles 10 mm thick and be laid as described below.The mortar for bedding the tiles shall be 1 part cement to 4 parts sand by weight, mixed semi dry by a mechanical mixer with only sufficient water added to give a crumbly consistency which retains its shape when squeezed by hand permitting no fluidityThe mix shall be placed to a thickness approximately 10 mm greater than that actually required for the bed, thoroughly compacted by tamping and drawing off to the required level with a screed board. Only sufficient mortar shall be mixed and spread as can be covered with tiles before it attains its initial set. Civil Contractor QC visual inspection shall be conducted A slurry of 1 part cement to 1 part sand by volume shall be poured over the surface of the semi – dry mix bedding and spread with a trowel until it is approximately 2 mm thickDry tiles shall then be laid on the slurry and beaten firmly into position with a wooden beater ensuring a true surface contact between the tiles and bedding is formed.The tiles shall be correctly positioned in both directions the time these are placed forming joints using a proprietary tile spacer ( 1.5 mm for wall tiles and 3 mm for floor tiles)The tiles shall neatly and accurately be cut to a close fit where necessary at abutments, around outlets, pipes and the like.Civil Contractor QC Inspection shall be conducted for the correct formation of joint alignment and the level profileThe tiles shall be laid level or to 1- % falls in ‘wet’ areas as may be required. Localised variations in level for a nominally flat floor shall be a maximum of +- 2-mm under a 3-meter straight edge. Particular care shall be taken in ‘wet’ areas to prevent low spots that may promote water pooling. The tolerance in the overall level shall not be more than 10 mm from required finishes. (Reef STQ Q)Grouting of the joints shall be carried out within a period of not less than 24 hours after completion of laying of tiles so as to allow the grout attach itself firmly to the bedding. Movement joints in tiled floorsUnless otherwise indicated in the documents, a 10 mm movement joint shall be formed at the perimeter of all the tiled floors and where the tiling meets structural features such as columns, machine bases etc.,Where a structural movement joint is provided in the base, a movement joint of the same width in the bedded finish shall be positioned immediately aboveThe movement joint cavities shall extend through the combined thickness of the finish and the bedding mortar, completely filled and sealed after grouting of the normal joints takes place.Major EquipmentMechanical MixerWheel barrowsMason’s tools in generalAttachmentNone#35

Administration building Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 76: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

76 of

Plastering and renderingTop

IndexScopeDefinitionsResponsibilitiesSafetyMaterialMethod EquipmentAttachment

ScopeThis statement is aimed to present the proposed procedures to be implemented forcarrying out the plastering and rendering operations. The term ‘plastering’ herein is meant for the internal surfaces while ‘rendering’ for the external. Reference documentsDrawing Nos. Project specifications Nos. (For Sand) BS Code 1199, Table 1, (for Hydrated Lime) BS Code 890 Class B, (for cement) ASTM C150, (for galvanized metal lath, stops and beads) BS 1369, (for preparation and application) UBCDefinitionsPSM Project Site Manager.CM Construction Manager.CS Construction SuperintendantFM Foreman ResponsibilitiesCM shall plan and organise the Plastering and Rendering works in accordance with this Method Statement.The Construction Foreman shall monitor these activities, directing the workforce as per Site requirements. SafetyPrior to the commencement of work, the labour force shall receive the tool box talk on the Project Site Safety requirements. Any process that is adopted which may have a particular Safety risk, shall be assessed as required as per Site conditions and shall be taken care of. In addition to that proper mason’s scaffolding arrangements shall be made for providing access to the required heights adopting all relevant safety measures.Method

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 77: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

77 of

Preparation of backgrounds to be plastered or renderedAll surfaces to be plastered and rendered shall be thoroughly cleaned of all dust and loose particles. Concrete surfaces shall be scabbled by mechanical means to remove all laitance exposing the aggregates to 3 mm depthCivil Contractor / EPC Contractor inspections shall be conducted for the approval of the prepared surfaces.A slurry coat consisting of 400 kg Cement (white) to 1 cum of sand (No. 1 White Silica) as specified shall be applied on the surface by trowel and 1-day allowance given for the succeeding coat to commence with.Block work surfaces shall have the joints raked out as specified (Ref) during construction.Junctions of different background and the chases for the electrical conduits as well as other service pipes shall be treated by fixing 200mm wide metal lath. Plastering shall not commence until all the mechanical and electrical services, conduits, pipes and Ist stage fixtures have been installed and approved.Where a rendering or plaster is to be continuous across backgrounds of different types, a strip of metal lath minimum 300 mm wide with an isolating membrane of polythene sheet or building paper behind, shall be fixed across the junction. Where small widths of one material less than 300 mm wide are involved e.g. a concrete column, beam or slab dividing block panels, the width shall be bridged completely for a distance of 150 mm on both sides.The metal lath shall be stretched out and fixed along each edge at 100 mm centres using stainless steel fasteners such as washers and shot fired pins, nails or screws and lapped joints tied with galvanized wire, the screws fixed into plugs in predrilled holes if so required.Metal lath shall not be provided where drawing shows a groove in the rendering or the plaster.Fixing beads and stopsBeads, stops and the like shall be fixed plumb, square and true to line with clout nails or plaster dabs at not more than 600 mm centres to each mesh wing.Corner / angle beads at all openings as well as plaster ground stops at terminals shall be installed by using stainless steel fasteners. Profile dots shall be formed on the surfaces.Civil Contractor / EPC Contractor inspection shall be conducted for the proposed profile approval.Preparation of mixes for plastering or renderingSlurry coat400 kg cement: 1 cum sandSecond and third coats300 kg cement: 50 kg lime: 1 cum sandPlaster thickness 19 mm walls and 14 mm ceilingsThe hydrated lime shall first be thoroughly mixed with sand and then cement added keeping mixer on until the material is uniform in appearance, suitable to receive water which at this stage be added in sufficient quantity to produce the mix stuff workable, uniform in colour and consistency.To improve the workability of the mix, the hydrated lime, sand and water may first be mixed in the required proportion with allowance to stand undisturbed for at least 16 hours before mixing Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 78: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

78 of

with cement. If allowed to stand for a longer period, the ingredients mix must be protected from drying out. The whole of the batch shall be used within an hour of being mixedApplication of the various plaster or render coatsThe work shall not start until the background has been prepared and all the services have been finished according to requirement and the relevant specifications as described earlier.Slurry coat shall be trowel applied allowing at least one day to start the succeeding coat Two render coat applications shall be carried out.Before applying any coat, the background or the preceding coat shall be brushed down to remove any loose particles and dampened sufficiently to ensure uniform absorption.First coat shall be trowel applied and scored to form a key for the second coat allowing at least one day before the start of the next coat. The undercoat shall be applied either by laying on with or throwing from a trowel or float, as uniformly thick as possible and not less than 8 mm or more than 13 mm thick in any part.The undercoat shall be left rough and open by the edge of the trowel after it has been long enough to set firm, be combed with evenly spaced wavy horizontal lines approximately 20 mm apart and 5 mm deep (less in case of first coat on metal lathing). The surface shall not be scratched, however, when it is to receive a Tyrolean finish.First undercoat applied to metal lathing shall be well worked into the lath to ensure that the material is completely embedded.The finishing coat shall be steel trowel appliedThe finishing coat shall not be less than 5 mm or more than 10 mm thick and shall be laid on with a trowel and finished with a steel float, taking care not to over work the surface.All coats shall be applied with firm pressure to exclude air and to ensure a good bond.Plaster shall be rodded and straightened to uniform surfaces in true planes. Laps of one coat shall not occur over laps of preceding coat. Each coat shall finish free from cracks, checks or other structural defects. Finish surfaces shall be flush with grounds / stop beads, corner beads, outlet boxes and similar details, free from trowel marks, other blemishes displaying straight arises and true angles.All coats shall be prevented from drying out too quickly and the work be carried out in shade during hot period. All renderings shall be protected by properly constructed hessian or similar screen during hot periodEach coat shall be kept damp by means of a fog spray of water for a minimum of 3 days to allow before a subsequent coat is applied or in the case of a finish coat, before the protective screens are removedThe surface of the finish coat shall be smooth, true and free from waviness, irregularities or blemishes with straight, level or plumb angles. External angles shall be pencil roundedCare shall be taken when rendering up to beads or stops to avoid excessive polishing at the arris and damage to the galvanizing.Inspections for the approval shall be conducted.EquipmentMixerAttachment.None#36Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 79: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

79 of

Administration building Roofing system Top

IndexScopeDefinitionsResponsibilitiesSafetyMaterialMethod EquipmentAttachment

ScopeThis statement is aimed to present the procedures, sequences of operations and all the other details that shall be worked on the proposed roofing system to be laid over the suspended roof slabs.Reference documentsDrawings Nos. Specifications, Construction practiceDefinitionsPSM Project Site Manager.CM Construction Manager.CS Construction SuperintendantFM Foreman ResponsibilitiesCM shall plan and organise the works to be carried out by the specialist contractor in accordance with this Method Statement.The Construction superintendent shall control , monitor and direct the Foreman regarding the operations as requiredThe Construction Foreman and the supervisor of the specialist contractor shall execute the work according to the CS direction and direct the work personnel to carry out the operations as per Site requirements. SafetyPrior to the commencement of work, the labour force shall receive the tool box talk on the Project Site Safety requirements. Any process that is adopted which may have a particular Safety risk, shall be assessed as required as per Site conditions and shall be taken care of. In

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 80: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

80 of

addition the work shall not be carried out during fast winds and dust storms. All workers shall use masks and safety glasses in addition to other PPE.The insulation boards shall be protected from the excessive exposure to sunlight.Specialist ContractorMaterialsDERBIT PASTA, DERBIGUM UNIGUM, MGP, ROOF MASTER, TERRAM 700, PRECAST CONCRETE TILES 500 X500 X50 MM form part of MAR 046 were approved subject to the comments .The clarification on the DERBIGUM MGP – This is the membrane flashing from the same manufacturer of horizontal membrane and is a product finished with mineral granules to make it solar reflective as well as UV resistant, shall be used for the reason that:It is not recommended to mix a self adhesive membrane with a torch applied membrane as both are not compatibleFrom the experience in this climate it has been observed that the textured Aluminium faced membrane tends to delaminate after a few months if left exposed (due to the different co –efficient of expansion between the metal and the bitumen)For the aforesaid reasons the manufacturer recommend a mineral granules faced membrane as these special solar reflective granules are spread over the bitumen while still hot and form part of the roof membrane.This flashing membrane complements the main roof membrane and with this combination on vertical exposed areas the performance is guaranteed for the specified period.Aluminium Flashing- MAR 113 Dated 8.2.2000It is confirmed that the proposed Aluminium Flashing for the roof upstands is a plain mill finish manufactured to BS 1470 / ASTM B 209 Alloy, H 14 mill finishMethodThe roofing system shall be carried out to the following operational sequences.Construction of all large foundation pads if any, prior to the commencement of the system laying. Preparing the proposed area over RCC slab, parapet walls and upstands ready by fixing in positions all roof drains, cleaning the roof etc.,Laying the Light Weight screed using foam concrete Constructing an angle fillet aroundPriming with DERBIT PASTA and applying DERBIGUM UNIGUM the water proofing membrane over the screed.Applying flashing membrane MGP over the vertical exposed part of water proofing layerWater test for 72 hoursLaying ROOF MASTER insulation boards 75 mm thickLaying in TERRAM 700 membraneLaying loose the precast concrete tiles 500 x 500 x 50 mmInstalling Aluminium flashing as specified and approvedOn the existing RCC suspended slab all large foundations if any, shall be constructed prior to commencing any roofing system operation. A groove shall be formed around the periphery of the area, pad foundations and other upstands at a specified height from the slab level for tugging the water proofing membrane into the parapet with sealant applied over.All services drains or other necessary items required to be in place prior to the roofing starts shall be completed in all respects including grouting. The area shall be cleared and made dry. Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 81: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

81 of

Inspection shall be conducted.The lightweight screed using special foam concrete shall be laid in to the following mix design to produce a density of 650 to 750 Kgs / cumSand / Cement: 1 / 1 Cement: 350 Kg / cumSand: 350 Kg / cumWater: 210 Lit / cumFoaming agent: 1.2 Lit / cumThe ingredients shall be mixed using a mechanical mixer, an aerator and a pump.The surfaces to be laid with screed shall be formed using mortar dabs to the specified profiles to 1 % slope. The foam concrete screed shall be laid in two layers to avoid settlement. The second layer shall be laid when the first has dried out followed by forming smooth finish to the required falls and cross-fallsInspection shall be conductedThe completed screed shall be cured with fresh water for two days and thereafter, left for one day to dry out.A cement sand angle fillet of 50 x 50 mm triangular cross section shall be formed at all directional changes.Before laying in water proofing membrane, a coat of DERBIT PASTA bituminous primer shall be applied to all the proposed surfaces. Once dried, laying in 4 mm DERBIGUM UNIGUM membrane shall be commenced with by full torching over the primed screed allowing 100 mm wide side and end overlaps. The dressing shall be carried out over the angle fillet and upstands properly terminating into the preformed grooves by tugging the membrane into the groove as well as rainwater outlets and around penetrations.The exposed vertical surface of the membrane shall be protected by applying 4 mm thick MGP flashing membrane 300 mm girth, mineral surface finished, UV resistant, torched over main membrane and tugged into groove as aforesaid.Inspection shall be conductedThe surface shall be flooded with water for a period of 72 hours after plugging in all the roof drainsAfter successful completion of the test, water shall be drained out and the membrane left for being dried out. The ROOF MASTER insulation boards with rebated edges 75 mm thick shall be laid over the dry membrane ensuring all areas are properly covered.The TERRAM 700-filter membrane with 100 mm overlaps shall be laid over top of the insulation boards. All small and light precast pedestals / foundations for the cable trays, pipe supports etc., if any, shall be loosely laid over the filter membrane.Inspection shall be conducted by the manufacturer’s representative and all coordinations made.A warranty for the specified period of 10 years shall be issued by the specialist contractor and the Civil Contractor according to the contract requirementThe concrete paviors in the form of pre cast concrete tiles 500mm x 500 mm x 50 mm shall be laid loose over the ITALPROFILI PVC TILE PADS to be provided at all the intersections and

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 82: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

82 of

at the corners as shown on the sketch. At the borders where cut tiles may be required, gravels of nominal size 15 – 30 mm filling shall be carried out to create a good aesthetic.The membrane shall be tugged into the groove and sealed with JOINT SEAL bituminous Mastic.Plain mill Aluminium flashing 0.90mm thick, 80 mm girth, cut and bent to the required profile shape shall be fixed with stainless steel screws above the groove covering and protecting the sealant all according to details.Major EquipmentMixerAeratorPumpAttachment#37

Buildings Roofing systemTop

IndexScopeSafetyMaterialMethod EquipmentAttachmentScopeThis statement is aimed to propose the procedures to be adopted to carry out the operations on the proposed roofing system over the suspended slabs on buildings.Reference documentsDrawings Nos. Specifications, Construction practiceSafetyPrior to commencement of any activity, the labour force shall receive a STARRT Card / Toolbox Talk relevant to the operation concerned on the project site safety requirements. Necessary measures shall be applied to any process involving a safety risk

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 83: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

83 of

A competent inspector shall visit the area daily to assess the safety measures adopted. Any snag observed during his visit shall be notified to the supervisor present who immediately act to bring the safety measures to an acceptable standard Specialist ContractorM / S Al Nahda Contracting and Trading Company LimitedPO Box # 1053, SharjahMaterialsDERBIT PASTA, DERBIGUM UNIGUM, MGP, ROOF MASTER, TERRAM 700, PRECAST CONCRETE TILES 500 X500 X50 MM form part of MAR were approved subject to the comments.The clarification on the DERBIGUM MGP – This is the membrane flashing from the same manufacturer of horizontal membrane and is a product finished with mineral granules to make it solar reflective as well as UV resistant, shall be used for the reason that:It is not recommended to mix a self-adhesive membrane with a torch-applied membrane, as both are not compatibleFrom the experience in this climate it has been observed that the textured Aluminium faced membrane tends to delaminate after a few months if left exposed (due to the different co –efficient of expansion between the metal and the bitumen)For the aforesaid reasons the manufacturer recommend a mineral granules faced membrane as these special solar reflective granules are spread over the bitumen while still hot and form part of the roof membrane. This flashing membrane complements the main roof membrane and with this combination on vertical exposed areas, the performance is guaranteed for the specified period.Aluminium Flashing- MAR It is confirmed that the proposed Aluminium Flashing for the roof upstands is a plain mill finish manufactured to BS 1470 / ASTM B 209 Alloy, H 14 mill finishMethodThe roofing system shall be carried out to the following operational sequences.On the existing RCC suspended slab all large foundations if any, shall be constructed prior to commence any roofing system operation. A groove shall be formed around the periphery of the area, on the pad foundations and other upstands at a specified height from the slab level for tugging waterproofing membrane into the parapet with sealant applied over.All services drains or other necessary items required to be in place prior to the roofing commences, shall be completed in all respects including grouting. The area shall be cleared and made dry. An Civil Contractor QC Inspection shall be conducted.The lightweight screed using special foam concrete shall be laid in to the following mix design to produce a density of 650 to 750 Kgs / cumSand / Cement: 1 / 1 Cement: 350 Kg / cumSand: 350 Kg / cumWater: 210 Lit / cumStatements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 84: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

84 of

Foaming agent: 1.2 Lit / cumThe ingredients shall be mixed using a mechanical mixer, an aerator and a pump.The surfaces to be laid with screed shall be formed using mortar dabs to the specified profiles to 1 % slope. The ‘foam concrete screed’ shall be laid in two layers to avoid settlement. The second layer shall be laid when the first has dried out followed by forming smooth finish to the required falls and cross-fallsAn Civil Contractor QC Inspection shall be conductedThe completed screed shall be cured with fresh water for two days and thereafter, left for one day to dry out.A cement sand angle fillet of 50 x 50 mm triangular cross section shall be formed at all directional changes.Before laying water proofing membrane, a coat of DERBIT PASTA bituminous primer shall be applied to all the proposed surfaces. Once dried, laying in 4 mm DERBIGUM UNIGUM membrane shall be commenced with by full torching over the primed screed allowing 100mm wide side and end overlaps. The dressing shall be carried out over the angle fillet and upstands properly terminating into pre formed grooves by tugging the membrane into the groove as well as rainwater outlets and around penetrations.Exposed vertical surface of the membrane shall be protected by applying 4 mm thick MGP flashing membrane 300 mm girth, mineral surface finished, UV resistant, torched over main membrane and tugged into groove as aforesaid.Application on the AC foundation & upstands shall be carried out according to the details shown on the sketchA Civil Contractor QC Inspection shall be conducted & ITP signed offWhole surface shall be flooded with water for a period of 72 hours after plugging in all roof drainsAfter successful completion of the test, water shall be drained out and the membrane left to dry out. ROOF MASTER insulation boards with rebated edges 75 mm thick shall be laid over the dry membrane ensuring all areas are properly covered.TERRAM 700-filter membrane with 100-mm overlaps shall be laid over top of the insulation boards. All small and light pre cast pedestals / foundations for the cable trays, pipe supports etc., if any, shall be loosely laid over the filter membrane.An inspection shall be conducted by the manufacturer’s representative and all coordination made.A warranty for the specified period of 10 years shall be issued by the specialist contractor and the Civil Contractor according to the contract requirementConcrete paviors in the form of pre cast concrete tiles 500mm x 500 mm x 50 mm shall be laid loose over ITALPROFILI PVC TILE PADS to be provided at all the intersections and at the corners as shown on the sketch. At the borders where cut tiles may be required, gravel(nominal size 15 – 30 mm) filling shall be carried out to create a good aesthetic.The membrane shall be tugged into the groove and sealed with JOINT SEAL bituminous Mastic.

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 85: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

85 of

Plain mill Aluminium flashing 1 mm thick, 80 mm girth, cut and bent to the required profile, shall be fastened with stainless steel screws above the groove, covering and protecting the sealant all according to details.Major EquipmentMixer, Aerator, PumpAttachmentSketch (Typical upstands and at AC Foundation)Sub Contractor’s method StatementClarification regarding DERBIGUM MGPClarification regarding Aluminium FlashingClarification regarding 10 years guaranteeClarification regarding 72 hours water test#38

Buildings Roofing systemTop

IndexScopeSafetyMaterialMethod EquipmentAttachmentScopeThis statement is aimed to propose the procedures to be adopted to carry out the operations on the proposed roofing system over the suspended slabs on buildings.Reference documentsDrawings Nos. Specifications, Construction practiceSafetyPrior to commencement of any activity, the labour force shall receive a STARRT Card / Toolbox Talk relevant to the operation concerned on the project site safety requirements. Necessary measures shall be applied to any process involving a safety risk

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 86: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

86 of

A competent inspector shall visit the area daily to assess the safety measures adopted. Any snag observed during his visit shall be notified to the supervisor present who immediately act to bring the safety measures to an acceptable standard Specialist ContractorM / S Al Nahda Contracting and Trading Company LimitedPO Box # 1053, SharjahMaterialsDERBIT PASTA, DERBIGUM UNIGUM, MGP, ROOF MASTER, TERRAM 700, PRECAST CONCRETE TILES 500 X500 X50 MM form part of MAR 046 were approved subject to the comments.The clarification on the DERBIGUM MGP – This is the membrane flashing from the same manufacturer of horizontal membrane and is a product finished with mineral granules to make it solar reflective as well as UV resistant, shall be used for the reason that:It is not recommended to mix a self-adhesive membrane with a torch-applied membrane, as both are not compatibleFrom the experience in this climate it has been observed that the textured Aluminium faced membrane tends to delaminate after a few months if left exposed (due to the different co –efficient of expansion between the metal and the bitumen)For the aforesaid reasons the manufacturer recommend a mineral granules faced membrane as these special solar reflective granules are spread over the bitumen while still hot and form part of the roof membrane. This flashing membrane complements the main roof membrane and with this combination on vertical exposed areas, the performance is guaranteed for the specified period.Aluminium Flashing- MAR It is confirmed that the proposed Aluminium Flashing for the roof upstands is a plain mill finish manufactured to BS 1470 / ASTM B 209 Alloy, H 14 mill finishMethodThe roofing system shall be carried out to the following operational sequences.On the existing RCC suspended slab all large foundations if any, shall be constructed prior to commence any roofing system operation. A groove shall be formed around the periphery of the area, on the pad foundations and other upstands at a specified height from the slab level for tugging waterproofing membrane into the parapet with sealant applied over.All services drains or other necessary items required to be in place prior to the roofing commences, shall be completed in all respects including grouting. The area shall be cleared and made dry. A Civil Contractor QC Inspection shall be conducted.The lightweight screed using special foam concrete shall be laid in to the following mix design to produce a density of 650 to 750 Kgs / cumSand / Cement: 1 / 1 Cement: 350 Kg / cumSand: 350 Kg / cumWater: 210 Lit / cumFoaming agent: 1.2 Lit / cum

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 87: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

87 of

The ingredients shall be mixed using a mechanical mixer, an aerator and a pump.The surfaces to be laid with screed shall be formed using mortar dabs to the specified profiles to 1 % slope. The ‘foam concrete screed’ shall be laid in two layers to avoid settlement. The second layer shall be laid when the first has dried out followed by forming smooth finish to the required falls and cross-fallsA Civil Contractor QC Inspection shall be conductedThe completed screed shall be cured with fresh water for two days and thereafter, left for one day to dry out.A cement sand angle fillet of 50 x 50 mm triangular cross section shall be formed at all directional changes.Before laying water proofing membrane, a coat of DERBIT PASTA bituminous primer shall be applied to all the proposed surfaces. Once dried, laying in 4 mm DERBIGUM UNIGUM membrane shall be commenced with by full torching over the primed screed allowing 100mm wide side and end overlaps. The dressing shall be carried out over the angle fillet and upstands properly terminating into pre formed grooves by tugging the membrane into the groove as well as rainwater outlets and around penetrations.Exposed vertical surface of the membrane shall be protected by applying 4 mm thick MGP flashing membrane 300 mm girth, mineral surface finished, UV resistant, torched over main membrane and tugged into groove as aforesaid.Application on the AC foundation & upstands shall be carried out according to the details shown on the sketchA Civil Contractor QC Inspection shall be conducted & ITP signed offWhole surface shall be flooded with water for a period of 72 hours after plugging in all roof drainsAfter successful completion of the test, water shall be drained out and the membrane left to dry out. ROOF MASTER insulation boards with rebated edges 75 mm thick shall be laid over the dry membrane ensuring all areas are properly covered.TERRAM 700-filter membrane with 100-mm overlaps shall be laid over top of the insulation boards. All small and light pre cast pedestals / foundations for the cable trays, pipe supports etc., if any, shall be loosely laid over the filter membrane.An inspection shall be conducted by the manufacturer’s representative and all coordination made.A warranty for the specified period of 10 years shall be issued by the specialist contractor and the Civil Contractor according to the contract requirementConcrete paviors in the form of pre cast concrete tiles 500mm x 500 mm x 50 mm shall be laid loose over ITALPROFILI PVC TILE PADS to be provided at all the intersections and at the corners as shown on the sketch. At the borders where cut tiles may be required, gravel(nominal size 15 – 30 mm) filling shall be carried out to create a good aesthetic.The membrane shall be tugged into the groove and sealed with JOINT SEAL bituminous Mastic.Plain mill Aluminium flashing 1 mm thick, 80 mm girth, cut and bent to the required profile, shall be fastened with stainless steel screws above the groove, covering and protecting the sealant all according to details.Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 88: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

88 of

Major EquipmentMixer, Aerator, PumpAttachmentSketch (Typical upstands and at AC Foundation)Sub Contractor’s method StatementClarification regarding DERBIGUM MGPClarification regarding Aluminium FlashingClarification regarding 10 years guaranteeClarification regarding 72 hours water test#39

Cracked gas compressor table top concrete pourTop IndexScopeReference documentsDefinitionsResponsibilitiesSafetyMethod including traffic management schemeEquipmentAttachment

Scope This statement is aimed to present the proposed procedures to be adopted to pour the Table Top of the framed beam structure.ReferencesDrawing nos. Specifications and Rev D SafetyPrior to the commencement of work, the labour force shall receive the tool box talk on the Project Site Safety requirements. Any process that is adopted which may have a particular Safety risk, shall be assessed as required as per Site conditions and shall be taken care of. In addition proper scaffolding according to the project requirements shall be erected around the area to be poured along with providing complete access system such as stepped stairs and the working platforms with top and the bottom guardrails.The area shall be cleared on ground allowing free access to the concrete pumps, transit mixers water tank etc., and the provision of the night lights shall be made for curing

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 89: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

89 of

MaterialsThe gross volume of the pour is 173 cumThe volume of the steel plates inserts is 1.08 cumThe applicable volume of the pour is 170 cum approximately.(Details of the calculations attached).According to the specification the pour pertains to the definition of massive structure, hence C 30 high slag blast furnace cement to BS 4246 with 70 % replacement utilising 30 % ASTM C 150 Type II cement shall be utilised for the batching according to the specified design mix with the placing temperature not more than 24 degree CelciusCuring materials such as curing compound, polythene sheets, bur lap sheets / hessians and water shall be available according to the requirementPlants and EquipmentBatching plant 1 # and 1 standbyConcrete pump 1 # and 1 stand byTransit mixers 6 #Vibrator 2 # and 2 standbyWater tanker 1 #ManpowerMasons 6 #Carpenters 3 #Steel fixers 3 #Scaffolder 3 #Helpers 7 #MethodThe drawing shows the above pour to be carried out into 13 sections by forming 16 construction joints. Pour sequences are described as Pour ‘A’ and Pour’B’. A total of 5 pours ‘A’ sections, all shown to be concreted prior to Pour ‘B’. Remaining 16 Pours ‘ B’ sections shown to be concreted after 14 days of the Pour ‘A’ completion. But according to the decision vide STQ , the Table Top shall be poured one time monolithically without formation of any construction joint.The quantitities involved have been detailed in the attachment. The overall procedures that shall be carried out have been given as followsErection for the preparatory works horizontal forms for the complete pour based on the properitory details from SGB drawingsPlacing the insert plates on the horizontal forms and if required some tangs be welded or tied by binding wires to the rebars by link rebars Placing the holding down bolts sleeves in the proper locations as shown on the drawingsPlacing and binding all the design rebars to the drawings’ details. Placing and fixing the vertical and the top plates on the vertical forms.Erecting preparatory works vertical forms in positionsAligning all forms, the insert plates and the bolt sleeves from the shown ’ centre line of Turbine Exhaust axis’ to be used as a reference line.Inspection and approvals.

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 90: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

90 of

Pouring detailsThe pour shall commence from East End and be accomplished in 4 layers according to the attached sequences details proportioned in 12 sections. The concrete temperature shall not be more than 24 degree Celcius as specified for the massive structures. Immediately after pouring is finished, curing compound shall be sprayed and the surface be covered with polythene membrane.Lator within 2 hours polythene shall temporarily be lifted, the saturated hessian spread and the polythene relaid.A layer of insulation material 100 mm thick shall be laid over the polythene, covered with ply sheets to keep the insulation material intact / in place for 72 hours for thermal curing, and thereafter, the routine curing shall continue for the specified period.The differential thermometers shall be used to record the temperature variations.AttachmentQ.A. ProceduresPour sequence planPour quantities Insert plates volume

#40

Water tightness tests for the collection sumps according to BS 8007:1987 section 9 TopIndexScopeReference documentsDefinitionsResponsibilitiesSafetyMethod EquipmentAttachmentScope This statement is aimed to present the proposed procedures(Typical) that shall be adopted to conduct the water tightness tests for the following water retaining structures. Collection sump Utilities EastStatements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 91: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

91 of

Collection sump Ethylene Collection sump Utilities EastCollection sump Utilities SouthReferencesDefinitionsPSM Project Site ManagerCSM Construction ManagerCS Construction SuperintendentFM ForemanQC Quality ControlResponsibilitiesPSM shall control the overall operations CM shall arrange the resources required accordinglyCS shall control, monitor and direct the FM and workforce for the operationsFM shall execute the operations deploying the workforceQC shall inspect all the operations according to the specificationsEPC Contractor shall conduct surveillanceSafetyPrior to the commencement of work, the labour force shall receive the toolbox talk on the Project Site Safety requirements. Any process that is adopted which may have a particular Safety risk, shall be assessed to the requirement for Site conditions and be taken care of. The safety barricades shall be erected around the sumps.Night hazard indicator light illuminaries shall be installed on the necessary locations.No unauthorised persons shall be allowed to enter the test area.MaterialsWater requirementsFor 70-TB-201 370 cum and 5 % for stabilisation periodFor 70-TB-202 237cum and 5 % for stabilisation periodFor 70-TB-203 166cum and 5 % for stabilisation periodFor 70-TB-205 191cum and 5 % for stabilisation periodMethodThis test requires the following operational sequences to be completed prior to conductance such asComplete RCC construction of the structure Complete filling of the tie rod holes with MBT Master Flow 544External Protection to the concrete surfaces with Bitustick XL, Polybit- CorrotechCivil Contractor QC Inspection and the approval of the membraneStructural Backfilling around the tank to the required level with compaction testsCleaning the surface of the structure by using waterjetting Application of the floor screed as specified The following operations shall be required to conduct the water tightness testA graduated stick shall be provided on wall top to show the water levels to a’ mm’ count Filling the structure with potable water to the maximum supply levelStatements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 92: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

92 of

After water filling, 7 days allowance to stabilise for absorption and autogeneous healing.Test to be conducted for 7 days for a design crack width of 0.1 mm.Recording the water losses at 24 hours intervals by simple measurements or by float indicator.Monitoring the seepage and marking the locations.Recording level lossesAfter the test completion, pumping the water out and transporting off the site.Post water tightness testMBT shall produce a representative sample for approval prior to the coating is applied Approval of the sample by EPC Contractor / ClientApplying the concrete protection approved coating material according to the representative sample on the internal surfaces of the structure as specified.Inspection of the applied coating by Civil Contractor QC followed by EPC Contractor approval Details70-TB-201 / 202 / 203 Inlet pipes 600 mm dia and for 205 inlet pipes 450 and 400 mm dia to be in place according to the levels shown on the drawings as reflected on the schedule as the Inverted level for maximum supply level.The structure to be tested shall be completed of all RCC constructions according to the specified and agreed procedures. The tie rod holes shall be filled with Master Builder Technology MBT Masterflow 544 according to the instructionsThe external surfaces of the structure shall be prepared for the specified application Inspection of the prepared surface by Civil Contractor QC followed by EPC Contractor approval The external surfaces of the concrete around shall be applied with the specified protective system Bitustick XL, PolybitInspection of the applied membrane by Civil Contractor QC followed by EPC Contractor approval Structural backfilling shall be carried out according to the project specificationsNecessary fileld density tests shall be conducted by Civil Contractor and laboratoryAll the aforesaid operations shall be completed prior to the commencement of the water tightness test The structure to be tested shall be cleaned to the requirement by using waterjetting on the entire surface of concrete removing all loose spalls, dust dirt etc., The internal surfaces shall be inspected by Civil Contractor QC followed by EPC Contractor approvalCivil Contractor QC Inspection shall be conducted before the test commencesEPC Contractor approval shall be obtained.Water tightness test shall be conducted according to the BS 8007 : 1987 Section 9.1 applicable to liquid retaining structuresPotable water shall be filled into the respective sump pit structures at a rate 2 m per 24 hours for which the attached filling scheduled quantities shall apply.The records of the test shall be documented on the attached sample form QCF 61 STRUCTURE LEAK TEST form and the judgement on the test shall be made accordinglySCHEDULE PLANNED FOR THE PROPOSED TEST

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 93: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

93 of

S #

DESCRIPTION OF OPERATION NUMBER OF DAYS REMARK

1 Filling potable water in sump pit 1m deep below the base level of the catch pit and 1 m depth above the base slab to make a total depth 2 m

1 By tankers filled at a uniformRate not greater than 2 m in 24 hours

2 Filling potable water another 2 m depth to make 4 m

1 By tankers

3 Filling potable water the remaining depth to maximum supply level

1 By tankers

4 Stabilisation period to allow for absorption and autogenous healing

7 Additional water to be filled if required

5 Testing period to record the water loss by seepage and by evaporation every 24 hours

7 Monitoring regarding seepage loss and the provision of 1 / 500 of average depth or 10mm. (Visual inspection)

6 Pumping the filled water out offsite 1 To the other structure for test7 Total period of water Test 18 Days

The potable water shall be filled by the water tankers to the above schedule upto the maximum level.A 7 days stabilisation period shall be allowed for water absorption and autogenous healing for the requirement for a maximum design crack width 0.1 mm .The water level shall be maintained by filling in further water for stabilisation.After the stabilisation period, monitoring for the water loss excluding the evaporation shall be conducted every 24 hours either employing the level floats or manometers or by simple daily measurements.The observations shall be recorded on the form QCF 61 Structure Leak Test for documentation During this 7 days period the total permissible loss in level shall not exceed 1 / 500 of the average water depth of the full tank or 10 mm.After the test is successfully completed, the water shall be pumped out either to the other structure for testing should that be ready to receive it or if not, the other construction areas for curing or any other purpose as agreed leaving the pit empty. The application of the internal protective specified coating shall be carried out to the manufacturer’s instructionsCivil Contractor QC inspection shall be conducted followed by the EPC Contractor approvalRemedial Work if requiredIn case of unsatisfactory performance of the water tightness test and upon the agreement with EPC Contractor, injection grouting method shall be adopted to seal the seepage routes. Should the structure not satisfy the 7 days test then after the completion of the remedial work it should be refilled and if necessary left for a further stabilising period; a further test of 7 days’ duration should then be undertaken in accordance with this clause.

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 94: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

94 of

EquipmentWater TankerPump, sweep blasting package etc.,Graduated stickAttachmentWater quantity scheduleDocumentation form QCF for structural leak testSketchSub Contractor’s method StatementClarification regarding DERBIGUM MGPClarification regarding Aluminium FlashingClarification regarding 10 years guaranteeClarification regarding 72 hours water test

#41

Water tightness tests for the collection sumps according to BS 8007:1987 section 9TopIndexScopeReference documentsSafetyMethod EquipmentAttachmentScope This statement is aimed to present the proposed procedures (Typical) that shall be adopted to conduct the water tightness tests for the following water retaining structures. Collection sump 70-TB-201 Utilities EastCollection sump 70-TB-202 Ethylene Collection sump 70-TB-203 Utilities EastCollection sump 70-TB-205 Utilities SouthReferencesSpecification, Clause 7.0, Crack Control

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 95: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

95 of

SafetyPrior to commence any activity, the labour force shall receive a STARRT Card / Toolbox Talk relevant to the operation concerned on the project site safety requirements.Necessary measures shall be applied to any process involving a safety riskSafety Supervision A competent inspector shall visit the area daily to assess the safety measures adopted. Any snag observed during his visit shall be notified to the supervisor present who immediately act to bring the safety measures to an acceptable standard MaterialsWater requirementsFor 70-TB-201 370 cum and 5 % for stabilisation periodFor 70-TB-202 237cum and 5 % for stabilisation periodFor 70-TB-203 166cum and 5 % for stabilisation period For 70-TB-205 191cum and 5 % for stabilisation periodMethodThe structure to be tested shall be completed of all RCC constructions according to the specified and agreed procedures. Complete filling of the tie rod holes with MBT Master Flow 544 shall be carried out according to the manufacturer’s instructions70-TB-201 / 202 / 203 Inlet pipes 600 mm dia and for 70-TB-205 inlet pipes 450 and 400 mm dia shall be laid in place to the levels shown on the drawings as reflected on the water quantity schedule i.e the Invert levels at maximum supply elevations.The external surfaces of the structure shall be prepared & applied with the specified protective system Bitustick XL, PolybitCivil Contractor QC Inspection shall be conducted for the approval of the membraneStructural backfilling shall be carried out externally to the project specifications & necessary field density tests conducted to the requirement Application of the floor screed as specified shall be carried outThe entire surfaces of structure to be tested shall be sweep blasted removing all loose spalls, dust dirt etc., The prepared internal surfaces shall be inspected by Civil Contractor QC for approvalThe following operations shall be involved to conduct the water tightness test according to the BS 8007 : 1987 Section 9.1 applicable to liquid retaining structuresA graduated stick shall be provided on wall top to show the water levels to a’ mm’ count Potable water shall be filled into the respective sump pit structure at a rate 2 m per 24 hours for which the attached ‘filling scheduled quantities ‘shall apply.After water is filled in to the required level, it shall be allowed to stay for a period of 7 days for stabilisation, absorption and autogeneous healing. If so required, water shall be added to maintain the maximum test level in case it is lost during this period.Test shall commence from 8th day and continue for 7 days for a design crack width of 0.1 mm according to specification requirement.Observations regarding water level drops shall be recorded every 24 hours by visual measurements on mm scale

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 96: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

96 of

The test records shall be documented on the attached form QCF ‘ STRUCTURE LEAK TEST ‘and the judgement on the test made accordinglyDuring this 7 days period the total permissible loss in level shall not exceed 1 / 500 of the average water depth of the full tank or 10 mm.After the test is successfully completed, water shall be pumped out either to the other structure for testing should that be ready to receive it or if not, to the other construction areas for curing or any other purpose as agreed leaving the pit empty. Remedial Work if requiredIn case of unsatisfactory performance of the water tightness test and upon the agreement with EPC Contractor, injection grouting method may be adopted to seal the seepage routes. Should the structure not satisfy the 7 days test then after the completion of the remedial work it should be refilled and if necessary left for a further stabilising period; a further test of 7 days’ duration should then be undertaken in accordance with this clause.

SCHEDULE PLANNED FOR THE PROPOSED TESTS #

DESCRIPTION OF OPERATION NUMBER OF DAYS REMARK

1 Filling potable water in sump pit 1m deep below the base level of the catch pit and 1 m depth above the base slab to make a total depth 2 m

1 By tankers filled at a uniformRate not greater than 2 m in 24 hours

2 Filling potable water another 2 m depth to make 4 m

1 By tankers

3 Filling potable water the remaining depth to maximum supply level

1 By tankers

4 Stabilisation period to allow for absorption and autogenous healing

7 Additional water to be filled if required

5 Testing period to record the water loss by seepage and by evaporation every 24 hours

7 Monitoring regarding seepage loss and the provision of 1 / 500 of average depth or 10mm. (Visual inspection)

6 Pumping the filled water out offsite 1 To the other structure for test7 Total period of water Test 18 Days

Post water tightness testMBT shall produce a representative Masterseal 550 coating sample for approval by EPC Contractor and the client. The internal surfaces shall be coated according to the approved sample Civil Contractor QC inspection shall be conducted to approve the applied coatingEquipmentWater Tanker, Pump, sweep blasting package etc.,

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 97: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

97 of

Graduated stickAttachmentWater quantity schedule #42

Administration building Marble flooringTop

IndexScopeReference documentsDefinitionsResponsibilitiesSafetyMethod EquipmentAttachmentScope This statement is aimed to propose the procedures to be adopted to carry out marble flooring on the various room areas, FF Reception, Lobby, the stair case steps & landing ReferencesDrawing EPC Contractor UBC & General Construction Practice, STQ MAR Dated 2.4.2000 Approved 4.4.2000 Perlato Royal marble for Administration Building Reception, FF lobby & stairsMAR Dated 12.3.2000 Approved 30.3.2000 Blue Pearl marble for Worktop and Toilet CountersDefinitionsPSM Project Site ManagerCSM Construction ManagerCS Construction SuperintendentSE Site EngineerFM ForemanQC Quality ControlResponsibilitiesPSM shall control the overall operations CM shall arrange the resources required accordingly CS shall control, monitor and direct the SE, FM and workforce for the operationsSE shall be responsible for all the site operations and follow the instructions of the CSFM shall execute the operations deploying the workforce. FM shall explain in full in the

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 98: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

98 of

language the work persons understand about all the instruction and the ToolBox talks every day and check that the same are followed up regularlyQC shall inspect all the operations according to the specificationsEPC Contractor shall conduct surveillanceSafetyThe workers shall receive a ToolBox Talk according to the project requirement relevant to the operation concerned every day prior to commencement of the activity Proper illumination shall be provided in the dark area The area to be laid with marble flooring system shall be closed for the general movement except those working there and be opened only when the work has properly been completed with hardboard cover protection spread on the newly laid finishes.Only industrial cable / wires shall be used for the grinding machine with earthing arrangement to avoid any shock or mishapThe personnel working around the grinding machine shall use eyeglasses and all other Personal Protective EquipmentSafety SupervisionA competent inspector shall visit the area daily to assess the safety measures adopted. Any snag observed during the inspection shall be notified to the supervisor present who immediately act to bring the safety measures to an acceptable standard MaterialsMarble tiles 300x600x20mm (Directly placeable) and also Kitchen Work tops & toilet Counters, Reception Area + Lobby First Floor- Perlato Royal (Placeable according to the supplier’s details)(Al Ain Cement and Marble Product Co)Proprietary Grout Method (Laying Marble Floor Tiles by SEMI DRY method) The following activities are involved to carry out the marble flooring systemThe areas of the concrete sub strata to be laid with marble shall be brush cleaned and dampened until absorption ceases followed by the finished floor level establishment by means of dots and rulesTotal thickness for the marble flooring is 100 mm including 80 mm bedding screed(1 cement: 4 mortar sand) by weight and shall be applied as described belowThe finishing layer shall be marble tiles 20 mm thick and be laid as described belowDetailsThe mortar for bedding the tiles shall be 1 part cement to 4 parts sand by weight, mixed semidry by a mechanical mixer with only sufficient water added to give a crumbly consistency which retains its shape when squeezed by hand permitting no fluidityThe mix shall be placed to a thickness approximately 10 mm greater than that actually required for the bed, thoroughly compacted by tamping and drawing off to the required level with a screed board. Only sufficient mortar shall be mixed and spread as can be covered with tiles before it attains its initial set. Civil Contractor QC visual inspection shall be conducted Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 99: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

99 of

A slurry of 1 part cement to 1 part sand by volume shall be poured over the surface of the semi – dry mix bedding and spread with a trowel until it is approximately 2 mm thickDry marble tiles / flags shall then be laid on the slurry and beaten firmly into position with a wooden beater ensuring a true surface contact between the tiles and bedding is formed.The marble tiles / flags shall be correctly positioned in both directions the time these are placed The tiles shall neatly and accurately be cut to a close fit where necessary at abutments, around outlets, pipes and the like.Civil Contractor QC Inspection shall be conducted for the correct formation of joint alignment and the level profile followed by EPC Contractor approval The tiles shall be laid level or tops to 1- % falls in ‘wet’ areas as may be required. The floor finishing shall be carried out using an electrically operated rotary grinding machine fixed with a carborundum stone of varying grades for the uneven edges or the protrusions as well as the fine range for the even areas to attain a smooth surface texture allowing water lubrication.The grinding runs shall depend on the finishing profile formed. More varying profile shall be applied with additional grinding rotation till the acceptable one is achieved.Plenty of water shall be used for this purpose. All the water shall be washed away after the grinding is completed.Civil Contractor QC Inspection shall be conducted for the correct formation of joint alignment and the level profile followed by EPC Contractor approval During grinding any portion damaged or effected badly shall be replaced to the specification requirement. Minor blown up or damaged tile shall be grouted with the proprietary compatible colour to match the marble texture A seal coat shall be applied on the ground surface with an approved proprietary polishing material according to the manufacturer’s instructions after which the finished surface be cleaned, the arrangement to protect the finished areas be made by overlaying hardboards and closing the entry in general.MOVEMENT JOINTS IN TILED FLOORSUnless otherwise indicated in the documents, a 10-mm movement joint shall be formed at the perimeter of all the tiled floors and where the tiling meets structural features such as columns, machine bases etc.Where a structural movement joint is provided in the base, a movement joint of the same width in the bedded finish shall be positioned immediately aboveThe movement joint cavities shall extend through the combined thickness of the finish and the bedding mortar, completely filled and sealed after grouting of the normal joints takes place.Other standard items such as treads, risers, worktops and the counters shall be cut to the exact site dimensions with the wash basins and the sink blocks taken out. These preformed items shall be supplied completed in all respects and fixed to the supplier’s details Major EquipmentMechanical MixerWheel barrowsMason’s tools in generalGrinding Machine with varying carborundum stone grades attachmentStatements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 100: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

100 of

Attachment

#43

Ethylene gas compressor Table top pour TopIndexScopeReference documentsDefinitionsResponsibilitiesSafetyMaterialMethod EquipmentManpowerAttachmentScope This statement is aimed to present the proposed procedures to be adopted to pour the Table Top of the framed beam structure.ReferencesDrawing No.. SpecificationsSafetyPrior to the commencement of work, the labour force shall receive the tool box talk on the Project Site Safety requirements. Any process that is adopted which may have a particular Safety risk, shall be assessed to the requirement for Site conditions and be taken care of. Proper scaffolding according to the project requirements shall be erected around the area to be poured along with providing complete access system such as stepped stairs and the working platforms with top and the bottom guard rails.The area shall be cleared on ground allowing free access to the concrete pumps, transit mixers water tank etc., and the provision of the night lights shall be made for curing MaterialsThe gross volume of the pour is 81 cumThe volume of the steel plates inserts is 0.35 cumThe applicable volume of the pour is 80 cum apprx.(Details of the calculations attached).According to the specification the pour pertains to the definition of massive structure , hence, C 30 high slag blast furnace cement to BS 4246 with 70 % replacement utilising 30 % ASTM C 150 Type II cement shall be utilised for the batching according to the specified design mix with the placing temperature not more than 24 degree Celcius.Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 101: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

101 of

Curing materials such as curing compound, polythene sheets, bur lap sheets / hessians and water shall be available according to the requirementMethodThe drawing shows the above pour to be carried out into 7 sections by forming 8 construction joints. Pour sequences are described as Pour ‘A’ and Pour’B’. A total of 3 pours ‘A’ sections, all shown to be concreted prior to Pour ‘B’. Remaining 4 Pours ‘ B’ sections shown to be concreted after 14 days of the Pour ‘A’ completion. But according to the decision vide STQ, the Table Top shall be poured one time monolithically without formation of any construction joint.The quantitities involved have been detailed in the attachment. The overall procedures that shall be carried out have been given as follows;Erection for the preparatory works horizontal forms for the complete pour based on the properitory details from SGB drawingsPlacing the insert plates on the horizontal forms and if required some tangs be welded or tied by binding wires to the rebars by link rebars Placing the holding down bolts sleeves in the proper locations as shown on the drawingsPlacing and binding all the design rebars to the drawings’ details. Placing and fixing the vertical and the top plates on the vertical forms.Erecting preparatory works vertical forms in positionsAligning all forms, the insert plates and the bolt sleeves from the shown ’ centre line of Turbine Exhaust axis’ to be used as a reference line.Inspection and approvals.Pouring detailsThe pour shall commence from East End and be accomplished in 4 layers according to the attached sequences details proportioned in 7 sections. The concrete temperature shall not be more than 24 degree Celcius as specified for the massive structures. Immediately after pouring is finished, curing compound shall be sprayed and the surface be covered with polythene membrane.Lator within 2 hours polythene shall temporarily be lifted, the saturated hessian spread and the polythene relaid. A layer of insulation material 100 mm thick shall be laid over the polythene, covered with ply sheets to keep the insulation material intact / in place for 72 hours for thermal curing, and thereafter, the routine curing shall continue for the specified period.The differential thermometers shall be used to record the temperature variations.Plants and EquipmentBatching plant 1 and 1 No. stand byConcrete pump 1 and 1 No. stand byTransit mixers 6 Nos.Vibrator 2 and 2 Nos. standbyWater tanker 1 No.ManpowerMasons 6 Nos.Carpenters 3 Nos.Steel fixers 3 Nos.Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 102: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

102 of

Scaffolder 3 Nos.Helpers 7 Nos.AttachmentQA ProceduresPour sequence planPour quantities Insert plates volume#44

Propane gas compressortable top pourTopIndexScopeReference documentsDefinitionsResponsibilitiesSafetyMaterialMethod EquipmentManpowerAttachmentScope This statement is aimed to present the proposed procedures to be adopted to pour the Table Top of the framed beam structure.ReferencesDrawing nosSpecificationsSafetyPrior to the commencement of work, the labour force shall receive the tool box talk on the Project Site Safety requirements. Any process that is adopted which may have a particular Safety risk, shall be assessed to the requirement for Site conditions and be taken care of. Proper scaffolding according to the project requirements shall be erected around the area to be poured along with providing complete access system such as stepped stairs and the working platforms with top and the bottom guard rails.The area shall be cleared on ground allowing free access to the concrete pumps, transit mixers water tank etc., and the provision of the night lights shall be made for curing.MaterialsThe gross volume of the pour is 60 cumThe volume of the steel plates inserts is 0.75 cumThe applicable volume of the pour is 58 cum apprx. (Details of the calculations attached).Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 103: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

103 of

According to the specification the pour pertains to the definition of massive structure , hence, C 30 high slag blast furnace cement to BS 4246 with 70 % replacement utilising 30 % ASTM C 150 Type II cement shall be utilised for the batching according to the specified design mix with the placing temperature not more than 24 degree CelciusCuring materials such as curing compound, polythene sheets, bur lap sheets / hessians and water shall be available according to the requirement.MethodThe drawing shows the above pour to be carried out into 7 sections by forming 8 construction joints. Pour sequences are described as Pour ‘A’ and Pour’B’. A total of 3 pours ‘A’ sections, all shown to be concreted prior to Pour ‘B’. Remaining 4 Pours ‘ B’ sections shown to be concreted after 14 days of the Pour ‘A’ completion. But according to the decision vide STQ, the Table Top shall be poured one time monolithically without formation of any construction joint.The quantitities involved have been detailed in the attachment. The overall procedures that shall be carried out have been given as followsErection for the preparatory works horizontal forms for the complete pour based on the properitory details from SGB drawingsPlacing the insert plates on the horizontal forms and if required some tangs be welded or tied by binding wires to the rebars by link rebars Placing the holding down bolts sleeves in the proper locations as shown on the drawingsPlacing and binding all the design rebars to the drawings’ details . Placing and fixing the vertical and the top plates on the vertical forms.Erecting preparatory works vertical forms in positionsAligning all forms ,the insert plates and the bolt sleeves from the shown ’ centre line of Turbine Exhaust axis’ to be used as a reference line.Inspection and approvals.Pouring detailsThe pour shall commence from East End and be accomplished in 4 layers according to the attached sequences details proportioned in 5 sections. The concrete temperature shall not be more than 24 degree Celcius as specified for the massive structures. Immediately after pouring is finished , curing compound shall be sprayed and the surface be covered with polythene membrane.Lator within 2 hours polythene shall temporarily be lifted, the saturated hessian spread and the polythene relaid.A layer of insulation material 100 mm thick shall be laid over the polythene, covered with ply sheets to keep the insulation material intact / in place for 72 hours for thermal curing, and thereafter, the routine curing shall continue for the specified period.The differential thermometers shall be used to record the temperature variations.Plants and EquipmentBatching plant 1 and 1 No. stand byConcrete pump 1 and 1 No. stand byTransit mixers 6 Nos.Vibrator 2 and 2 Nos. standbyWater tanker 1 No.Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 104: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

104 of

ManpowerMasons 6 Nos.Carpenters 3 Nos.Steel fixers 3 Nos.Scaffolder 3 Nos.Helpers 7 Nos.AttachmentQ.A. ProceduresPour sequence planPour quantities Insert plates volume#45

Expansion joints in ditchesTop

IndexScopeReference documentsDefinitionsResponsibilitiesSafetyMethod EquipmentAttachmentScope This statement is aimed to present the proposed procedures to be adopted to seal the Expansion joints in the ditches.ReferencesDrawing nosSafetyPrior to the commencement of work, the labour force shall receive the tool box talk on the Project Site Safety requirements. Any process that is adopted which may have a particular Safety risk, shall be assessed to the requirement for Site conditions and be taken care of.The personnel working on this activity shall wear masks, safety glasses, gloves, etc., MethodTo seal the expansion joints the following operations shall be carried out.Cleaning of the joint surfaces.Preparing and filling the joints with BitumasticDetailsThe size of the proposed joints to be filled / sealed is 15 mm wide x 15 mm deep

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 105: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

105 of

Application procedureThe surface shall be cleaned of all dirt, dust and loosely adhering materials. All grease and oil contamination shall be removed using hard small brushes, compressed air etc. The fibre board shall be removed to the required depth.Masking tape shall be used to confine the joint borders keeping the adjoining concrete surfaces clean. The contents of the Can shall be removed by a Trowel or a Spatula. The Bitumastic shall be applied to the prepared and masked portions.In case of the vertical joints, bottom to top application sequence shall be followed ensuring that the entire volume of the joint is filled in using a spatula or a trowel to effect a total contact with joint surfaces. After application, the sealant shall be smoothened and compressed into the joint using a spatula or a putty knife moistened with cleaning solvent. Masking tape shall be removed immediately after the application has been over to keep the concrete surface clean.It shall take 4-6 weeks post application normally to a full cure at a stage when the solvent evaporation is completed. Over painting if so required, shall be carried out only after the full cure has taken place.CoverageCoverage for joint depth 10 mm and width 15mm 6.5 kg of Bitumastic per linear metreEquipmentTrowelSpatulaKnife etc.,AttachmentNone#46

Expansion joints in ditchesTop

IndexScopeReference documentsSafetyMethod EquipmentAttachmentScope This statement is aimed to propose the procedures to be adopted to seal the Expansion Joints in the ditches.

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 106: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

106 of

ReferencesDrawing nos. Specs: BITUMASTIC, Manufacturer - PolybitSafetyPrior to the commencement of work, the labour force shall receive a Toolbox talk on the Project Site Safety requirements. Necessary measures shall be applied for any process involving particular safety risk Personnel working on this activity shall wear masks, Eye protection, gloves, etc., MethodSize of the proposed joints to be filled / sealed is 15 mm wide x 15 mm deepThe surface shall be cleaned of all dirt, dust and loosely adhering materials.All grease and oil contamination shall be removed using hard small brushes, compressed air etc. The fibreboard shall be removed to the required depth.Under normal circumstances priming is not requiredMasking tape shall be used to confine the joint borders keeping the adjoining concrete surfaces clean.The contents of the Can shall be removed by a Trowel or a Spatula. The Bitumastic shall be applied to the prepared and masked portions.In case of the vertical joints, bottom to top application sequence using a spatula or a trowel, shall be followed ensuring that the entire volume of the joint is filled in to effect a total contact with joint surfaces. After application, the sealant shall be smoothened and compressed into the joint using a spatula or a putty knife moistened with cleaning solvent. Masking tape shall be removed immediately after the application is completed to keep the concrete surface clean.A full cure (a stage when the solvent evaporation is completed) shall normally consume4 to 6 weeks post application of the sealantPainting over concrete surface if so required, shall be carried out only after full cure has taken place.EquipmentTrowelSpatulaKnife etc.,AttachmentManufacturer Datasheet#47

Concrete coating Using master seal 550Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 107: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

107 of

TopIndexScopeReference documentsDefinitionsResponsibilitiesSafetyMaterialMethod EquipmentAttachmentScope This statement is aimed to present the proposed procedures that shall be adopted to apply the specialist material for concrete protection on the internal surfaces as specified.ReferencesCollection sump 70-TB-201 Utilities EastCollection sump 70-TB-202 Ethylene Collection sump 70-TB-203 Utilities EastCollection sump 70-TB-205 Utilities SouthDrawings Specifications Master seal 550-product data sheetDefinitionsPSM Project Site ManagerCSM Construction ManagerCS Construction SuperintendentFM ForemanQC Quality ControlResponsibilitiesPSM shall control the overall operations CM shall arrange the resources required accordinglyCS shall control, monitor and direct the FM and workforce for the operationsFM shall execute the operations deploying the workforceQC shall inspect all the operations according to the specificationsEPC Contractor shall conduct surveillanceSafetyPrior to the commencement of work, the labour force shall receive the tool box talk on the Project Site Safety requirements. Any process that is adopted which may have a particular Safety risk, shall be assessed to the requirement for Site conditions and be taken care of. Scaffolding shall be erected to afford access to the working personnel according to the project requirements. Hand rails ladders and the toe boards shall be fitted and inspected prior to use. Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 108: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

108 of

During mixing and application of master seal 550, personnel protective equipment shall be used i.e. overalls, goggles, gloves (to avoid material contact to eyes, mouth and skin)Material storage / disposal of used containers / waste materialMaterials shall be stored out of direct sunlight clear of ground and protected from rainfall.Used containers shall be collected and disposed off as per project requirements. MaterialsCoating, Masterseal 550Master seal 550 is a two component acrylic modified cementitious coating that requires only site mixing to form an ideal product to waterproof and resurface concrete, masonry and most other construction materials. Simply applied by stiff brush, roller or trowel it forms a waterproof, flexible coating providing an effective barrier to waterborne salts and atmospheric gases.MethodThe method involves the following sequences in general.Surface preparation MixingApplicationDetailsAll grease, oil, dust, residual curing compound, mould release agent or other contaminants, which could impair adhesion, shall be removed from the surface by degreasing and washing.The whole surface to be coated shall be cleaned using water jetting and visually inspected to ensure that the roughness does not exceed grade 80 sandpaper.All the holes, voids, depressions, spalls etc., shall be filled with Masterseal 550 mixed to a trowel consistency ,scraped lightly into the surface, allowed to dry and later roughened by hand wire brush on the small areas and gently water jetted on the larger areas.The filled areas shall be visually inspected to ensure that the correct mechanical key is achieved.MixingMaster seal is supplied in the pre measured units and shall be mixed on site using clean containers. The powder shall be slowly added to the liquid component and agitated / mixed for 2 minutes by using a slow speed hand power drill fitted with a suitable paddle attachment, until a homogeneous lump free consistency is obtained.The mix quantity shall be such that it could be consumed in one hour during application without allowing any retempering with water.ApplicationCoverage 1.8 Kg / sqm at 1 mm thicknessThe coating shall be 1 mm thick applied in one coatIn hot weather the surface to be coated shall be shaded from direct sunlight. The areas to be coated shall be saturated with fresh and clean water.The prepared and the saturated surface shall be inspected by Civil Contractor QC followed by EPC Contractor approvalThe mixed material shall be applied while the surface is visibly damp without standing water using short stiff brush or roller. (Roller shall be used in major / large areas)

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 109: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

109 of

The evenness and the thickness of the applied coating shall be regularly checked during application while the material is still wet.The materials shall be allowed to dry and visually inspected Civil Contractor QC inspection shall be conducted followed by EPC Contractor approvalAny missed areas shall be saturated and then touched up.EquipmentWater tanker with water jetting arrangementHard brushes for minor areasClean containerSlow speed drill with paddle attachmentStiff brush / RollerAttachmentMasterseal 550 Data sheet and statement#48

Dewatering for the 84” GRE pair line parallel to Corniche road east west TopIndexScopeReference documentsDefinitionsResponsibilitiesSafetyMethod EquipmentAttachmentScopeThe statement is aimed to present the proposed procedures to be adopted to keep the proceeding excavations, for the route respecting pair of 84 “ GRE pipe lines to be laid in, dry and free of inflowing water References Specifications Water Control / Dewatering Plan , Dewatering and DrainageExcavation Safety PlanExcavation & Backfilling for Underground structures. DefinitionsPSM Project Site Manager.CM Construction Manager.CS Construction Superintendent

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 110: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

110 of

FM Foreman ResponsibilitiesCM shall plan and resource the trench excavation and backfilling activity, in accordance with this method statement. The Construction Foreman shall monitor these activities directing the workforce as necessary. EPC Contractor shall control the activities.SafetyAppropriate means regarding safety shall be provided to the requirements .Round the clock watch and ward shall be maintained for the plants and the EquipmentSafety standard barriers posted with warning tags shall be installed on both the sides of the excavations covering the well point systems alsoNight indicator lights shall be provided according to the provisions of safetyAccess ladders shall be provided every 8 m intervals The safety inspector shall visit the site every day in the morning and the after noon to check whether the safety systems work to the requirement or else the corrective measures be applied.The water logged area shall not be allowed for the workers in general to acceed crossing the existing fence except, if so required , for the purpose of laying out hoses over used plies to be routed in to reach the proposed sumps for the pumped water disposal. METHOD Ref Attached Drawing and SketchesThe North South excavation has already been carried out to the intersection of the proposed line and the Corniche Road as indicated by point at ‘S’ On the proposed route of the lines i.e on the North of the road exist various services at a distance 4 m to 8 m at a depth of 2 to 3 m from the existing road level running along eitherside of the intersection i.e East and West as shown on the attached sketch as locations marked A to H for the exposed inspection pitsThe existing uneven ground level on the proposed area is 1.8 m average lower than the road level and the water is available at 2 m from the road level but fluctuates rapidly depending on the tides.The GRE pipe 2200 mm dia pair shall be laid at a bedding of not less than 4000 mm to 4500 mm from the road surface .Since the drawing shows the natural ground level 3.4 m , a 2.4 m depth is required to be excavated , while water level is shown at 2.15m level, water has to be bailed out upto 0-0 level requiring a 2m massive dewatering along the entire route commencing from the intersection at point ‘S‘ to the terminal point at ‘T’.The existing services shall be protected by the necessary measures according to the statutory regulations and the specifications prior to the excavation commencement for which an inquiry be conducted with the relevant Statutory Organizations / ClientSince this massive earth work is to be carried out in full to cover a length of 1200 m or more , dewatering shall be carried out accordingly by the standard Well Point System to be installed on both sides of the proposed route at a depth of minimum 3 m from the existing ground levels at the locations shown on the sketch / drawing and disposed off through the hoses into the proposed sumps to be located at varying distances from 100 to 200 m off

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 111: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

111 of

the road berm by the use of booster pumps installed next to the intermediate water tanks, so as not to allow the disposed water to flow back into the well point systems.For the route part besides the box culvert (under construction) leading to the pipelines West end after running beneath the overhead conveyors, the disposal may be made into the culvert manholes as being done by M / S ARCHIRODIN CONSTRUCTION OVERSEAS for that the matter was casually discussed with the supervisor on site Mr BADRI who expressed no concern should the water be discharged that way.Anyway should this option does not work, the disposal shall be carried on to the proposed sumps as shown since in the vicinity of the Sulpha Plant Building area further sumps to form may not be allowed.The sumps shall be located as shown on the drawing / sketch near the embankment north / south side , for south after jumping over the bund, whatever course be feasible. On the south of the embankment side the existing levels are low lying. A total of 8 to 10 sumps shall be needed be formed. The sump pits to receive the disposed water shall be filled with 75 mm clean aggregate prior to the disposal is commencedThe Well Points on both sides shall be installed in sections of 100 m average for each Sykes Pump catchment and the disposal be effected to as shown by boosting.It shall take a duration of around 60 days to carry out the excavation,bedding, layingpipes and the backfill,the system / s have to be kept working till these operations are over . Equipment / plantsWell point systemPlants and equipment requirement

S # ITEM DESCRIPTION UNIT QUANTITY REMARK1 Length of the proposed route m 2400 2 x 1200 m2 Length of the well point system m 2400 2 x 1200 m3 150mm dia Headers average 5 m or

so longeach 480 6 points in each

4 50 mm dia Well points 3 m long each 2880 Filterable 5 50 mm dia Well points / Headers

Flexible connections each 2880 6 connections each

header6 Sykes / Miller pumps with suction and

delivery headseach 24 1 pump / 100 well

points7 Intermediate water tanks (open top)

3 cum capacity each 6 1 tank for 4 Sykes

pumps8 Booster pumps 5 bhp with compatible

fittings for tanks connectionseach 6 1 booster pump for 4

Sykes pumps9 150 mm dia hose pipe to suit the pump

inlets and outlets with suction and disposal / delivery heads

m 500 Delivery upto the open water tanks

10 75 mm dia disposal hose to suit the water tank outlets

m 1500 Disposal from open water tanks to the proposed sumps

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 112: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

112 of

11 150 mm steel sleeve pipe for under ground use

m 50 To be installed for the incoming crossings

12 Drilling Rig with adjustable Auger attachment for 50 mm dia Well Points

each 1 For drilling well point bores

13 All other compatible fittings and miscellaneous items for the whole assembly not covered in above

ATTACHMENTDrawing showing the well point system installation layouts and sectionTypical details of the system indicative only#49

Ceramic wall tiles fixing Top

(INTERNAL)

Administration buildingIndexScopeReference documentsDefinitionsResponsibilitiesSafetyMethod EquipmentSCOPEThis statement is aimed to present the proposed procedures to be adopted to fix the Ceramic wall tiles by bedding with an approved adhesive on one coat plaster applied according to the specification with the pre spatterdash treatment except on metal lathing where 2 coats are permitted with wood float finish, uniformly as thick as possible and not less than 8 mm or more than 13 mmReferencesSpecification SafetyThe work force shall receive every day prior to the commencement of any activity a Tool Box talk regarding operational safety according to the project requirements in addition to the use of personal protective equipment.. Specifically the personnel engaged on the tiling items shall use masks to prevent inhale the grout or the adhesive smell.

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 113: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

113 of

In the rooms where proper ventilation or the sunlight is not available, electric lights shall be provided with due care regarding protection from the electric wires ,the distribution board and the other fixtures etc.,In hot weather standing upright fans shall be provided at the work areas.The work area shall be closed to general workers on other parts and opened only after the tiles have been finally cleaned as well the space cleared of electrical fittings.DefinitionsPSM Project Site ManagerCSM Construction ManagerCS Construction SuperintendentFM ForemanQC Quality ControlResponsibilitiesPSM shall control the overall operations CM shall arrange the resources required accordinglyCS shall control, monitor and direct the FM and workforce for the operationsFM shall execute the operations deploying the workforceQC shall inspect all the operations according to the specificationsEPC Contractor shall conduct surveillanceMaterial Glazed Tile size specified 108 x 108 mmSetting material (ultra set polyurethane adhesive ) recommended by manufacturer Cushion edgesRounded external cornersHead Jamb and Cill trim shapesWain scot cap Surface bullnose or bull nose capExternal corners Bullnose shapes or as specifiedInternal corners Field butted squareGrouting material Water proof epoxy tiling grout with antifungicide additive(Commercial white sanded latex portland cement type) MethodMesh reinforcement shall be incorporated in the plaster where 1 The structure is out of line and the thickness of the plaster exceeds 13 mm2 The plaster is to be applied over different structural materials3 The surfaces of the structural wall shall be subject to excessive movement .e.g., light

weight concrete block of all typesExaminationThe strata to receive the tiles shall be examined closely to ascertain that the moisture content are within limits to allow the fixing operation Where the tiling is to be bedded in a thin bed adhesive, the trueness of the plaster shall be such that when tested with a 3 m straight edge no gap exceeds 3 mm

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 114: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

114 of

Where the gap lies between 3 and 6 mm, if the walls are out of plumb by not more than 6 mm, a thick bed adhesive shall be applied in preferance to cutting the defective areas and making goodDeviation from true vertical or plumb in the surface of plastering exceeding 6 mm shall be made goodThin bed adhesive shall not be used for fixing tiles with backs incorporating deep keys or frogs for which thick - bed adhesives must be used Civil Contractor inspection followed by EPC Contractor approvalThe tiles shall be set out before the work commences so that cut tiles be kept to a minimum and where they do occur be as large as possibleJoints shall be horizontal and vertical, with horizontal joints aligning in walls that adjoin or be adjacentThe tiles shall be neatly and accurately cut to close fit where necessary at abutments and around outlets, pipes and the like The tiles shall be extended into recesses, under equipment and fixtures to form a complete covering without interruptions as well as terminated neatly at obstructions, edges or / and corners keeping the on going pattern or joint alignment. The tiles shall fit closely to the electrical outlets and fixtures allowing plates, collars, covers etc., overlap the tiles.Movement joints not less than 6 mm shall be provided:At all internal vertical cornersAt all angles with structural walls and ceilingsTo form bays not greater than 3000x4500 mmOver all structural movement joints:The joints shall be carried through the plastering to the structural wall, partially filled with an approved joint filler and finished flush with an approved sealant recommended by the manufacturer for the relevant situations.Glazed edge tiles shall be used at the exposed edges.The tiles shall be fixed in position prior to the adhesive gets dried for that it shall be prepared and applied on a small area not exceeding 1m x 1m at a time with a trowel to dry plaster surface in a manner recommended by the manufacturer followed by the tiles pressed firmly into with a twisting / sliding action tapping firmly and cleaned as soon as the bedding be completed.The finished surface of the tile shall be firm and true such that when checked with a 3 m straight edge, no gap exceeds 3 mm Civil Contractor inspection followed by EPC Contractor approvalThe joints shall be grouted well to completely fill in as well as appear flush after the adhesive has set and not less than 48 hours post fixing. Surplus grout shall be cleaned off from the tiles surfaces as neatly as possible as the work proceeds using a damp cloth and the joints tooled smooth. The grout haze shall be removed according to the manufacturer’s instructions for the use of acid and chemical cleanersThe tile work shall be rinsed thoroughly with clean water prior to and post using chemical cleaners followed by polishing with soft cloth.

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 115: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

115 of

Civil Contractor inspection followed by EPC Contractor approvalEquipmentTile cutter AttachmentApproved ITP Form

#50

Bedding and gravel filling beneath 60 “ dia pipe cooling water pipeTop

IndexScopeReference documentsDefinitionsResponsibilitiesSafetyMethod EquipmentAttachmentScopeThis statement is aimed to propose the procedures to be adopted for the execution of bedding and the sub strata gravel filling with the provision to prohibit the fine soil particles to migrate to the bedding beneath the pipe where the water table is met at the bedding level making the compaction and the density test unsustainableReference documents Drawing Specification. Excavation & Backfilling for Underground structures.

DefinitionsPSM Project Site Manager.CM Construction Manager.CS Construction SuperintendentFM Foreman

ResponsibilitiesCM shall plan and resource the trench excavation and backfilling activity, in accordance with this method statement. The Construction Foreman shall monitor these activities, directing the workforce as necessary. EPC Contractor shall control the service laying activities.

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 116: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

116 of

SafetyPrior to the commencement of any activity, the labour force shall receive a tool box talk on the project site safety requirements. Any process that is adopted having a particular safety risk shall be assessed and addressed as required.A competent inspector shall inspect the trench daily to assess the safety measures adopted as well as after every rainstorm. If required, the shoring shall be provided to prevent the caving in. In case of the trench depth being more than 1200 mm, adequate means of exit such as ladders or steps shall be provided and located no more than 8 m of lateral travel. Barricades, markers and the night lights etc., shall be arranged as required.SafetyMethodCOOLING WATER PIPE LINE 60 “ DIA PIPE BEDDING AND GRAVEL FILLINGThe attached sketch shows the proposed bedding and sub strata gravel filling wrapped by Geotextile.The excavation shall be carried out upto the formation level plus another 200 mm for crushed gravel filling as shown . The Geotextile TERRAM membrane shall be laid on the prepared substrata as shown.A well packed 200 mm thick crushed gravel filling shall be carried out on apprx.3000 mm wide base.The Geotextile TERRAM membrane shall be continued over the prepared crushed gravel filled formation level surface making gravels wrapped fully allowing no fine soil particles enter the strata. Over this wrapped strata a 150 mm thick sand bedding shall be carried out duly compacted according to the requirement of the specifications.After these operations are over and the inspection done, 60 “ dia pipe shall be laid according to the requirementEquipmentExcavatorCompactorAttachmentSketch#51

External concrete protectionAdministration buildingTop

IndexScopeReference documents

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 117: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

117 of

DefinitionsResponsibilitiesSafetyStorageMaterialMethod EquipmentAttachmentScope This statement is aimed to propose the procedures to be adopted to form a protection coating on the external concrete surface to be cladded with the Glass Reinforced Concrete elements.ReferencesDrawing Specificationabove ground concrete protection.

Definitions

PSM Project Site ManagerCSM Construction ManagerCS Construction SuperintendentFM ForemanQC Quality ControlResponsibilitiesPSM shall control the overall operations CM shall arrange the resources required accordinglyCS shall control, monitor and direct the FM and workforce for the operationsFM shall execute the operations deploying the workforceQC shall inspect all the operations according to the specificationsEPC Contractor shall conduct surveillanceSafetyPrior to the commencement of any activity, the labour force shall receive a toolbox talk relevant to the operation concerned on the project site safety requirements. Any process that is adopted having a particular safety risk shall be assessed and addressed as required. Only tagged scaffolding comprising all the guard rails foot rails etc.,shall be used for the work at heights according to safety requirements. The use shall be made in well-ventilated area and avoid inhalation.The personnel shall use protective clothing, gloves eye protection glasses, masks etc., for to avoid skin contact. Plenty of clean water shall be available all the time. Medical attention shall be available all time to treat the adverse effects. Transportation shall be available to move the effected personnel to the hospital should the circumstances so require.

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 118: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

118 of

StorageThe material shall be stored under cover out of direct sunlight and protected from temperature extremes. Product shelf life is 12 months subject to proper storageCare shall be taken during use and storage to avoid contact with eyes, mouth, skin and foodstuffs. The containers shall be resealed after use. Immediate medical attention shall be called for in case of any adverse effect to the personnel handling the productDamaged tins shall be disposed off according to the state regulations.MaterialMaster Builder Technology ProductMasterseal 300H - an acrylic based, elastomeric decorative, flexible, anti-carbonation and waterproof protective coating designed for the protection of concrete structures against carbonation and chloride ingress.Masterseal 181S- primer systemMasterseal 300 H fillerMethodThis application involves the following sequencesCleaning and making up the surfacePriming the surfaceCoating the surfaceDetailsPreparationAll surfaces shall be free from oil, grease, friable matters and curing compound. The surfaces shall be cleaned from dust / sand using compressed air. Arrises shall be rounded off and the protrusions ground so that the resulting surfaces appear smooth.The surfaces shall be brush primed with Masterkure 181S and subsequently Masterseal 300H mixed with Masterseal 300 H filler applied as a scrape coat over blow holes and depressions.The primed surface shall be allowed to dry tack free for a minimum duration of 2 hours before applying Masterseal 300H coating.ApplicationMasterseal 300 H shall be applied directly from the containers using a brush or roller @ 0.8 litre per sqm surface coverage to achieve a continuous coating The continuous coating may be achieved in 1 or 2 coats of applicationThe coating shall be protected from the rain and humidity for 24 hours / until it dries out using polythene sheets keeping off the area.The coating shall be applied when the humidity is less than 90 %The coating shall not be applied in the dusty weather conditionsNo post application curing is requiredThe areas to be coated shall be protected from direct sunlight by shading in the hot weather conditions and the ambient temperature be more than 5 degree Celsius.EquipmentBrush RollerStatements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 119: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

119 of

AttachmentMBT Statement#52

Above ground concrete protection Using masterseal 300 hTop

IndexScopeReference documentsSafetyMethod EquipmentAttachmentScope This statement is aimed to propose the procedures to be adopted to apply protection coating on above ground concrete surfaces.ReferencesSpecificationabove ground concrete protection. MAR -Material Approval for 181 S and 300HSafetyPrior to the commencement of any activity, the labour force shall receive a toolbox talk relevant to the operation concerned on the project site safety requirements. STARRT Card shall be used. Necessary measures shall be applied to any activity involving safety risk.Only tagged scaffolding with guardrails, foot rails etc., shall be used to afford access to high locations. Material shall be used in well-ventilated area and inhalation avoided.Personnel shall use protective clothing, gloves, eye protection, masks etc .to avoid skin contact. Plenty of clean water shall be made available. Safety Supervision A competent inspector shall visit the area daily to assess the safety measures adopted. Any snag observed during his visit, shall be notified to the supervisor present who immediately act to bring the safety measures to an acceptable standard MaterialMaster Builder Technology ProductMasterseal 300H - an acrylic based, elastomeric decorative, flexible, anti-carbonation and waterproof protective coating designed for the protection of concrete structures against carbonation and chloride ingress.Masterseal 181S- primer system

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 120: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

120 of

Masterseal 300 H fillerStorageThe material shall be stored under cover out of direct sunlight and protected from temperature extremes. The containers shall be resealed after use. Damaged tins shall be disposed off according to the state regulations.MethodSurface PreparationAll surfaces shall be free from oil, grease, friable matters and curing compound. Sweep blasting shall be used when necessary to obtain an acceptable surface for coating otherwise the surfaces shall be cleaned from dust / sand using compressed air. Arrises shall be rounded off and the protrusions ground so that the resulting surfaces appear smooth.PrimerThe surfaces shall be brush primed with Masterkure 181S and allowed to dry for 2 hoursSubsequently Masterseal 300H mixed with Masterseal 300 H filler applied as a scrape coat over blowholes and depressions and allowed to dry.ApplicationMasterseal 300 H shall be applied directly from the containers using a brush or roller @ a minimum of 0.8 litre per sqm surface coverage to achieve a continuous coating Continuous coating may be achieved in 1 or 2 coats of applicationThe coating shall not be applied in the dusty weather conditionsNo post application curing is requiredEquipmentBrush RollerAttachmentMBT Statement#53

Above ground concrete protection Using masterseal 300 h Top

IndexScopeReference documentsSafetyMethod EquipmentAttachment

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 121: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

121 of

Scope This statement is aimed to propose the procedures to be adopted to apply protection coating on above ground concrete surfaces.ReferencesSpecificationabove ground concrete protection. MAR -Material Approval for 181 S and 300HSafetyPrior to the commencement of any activity, the labour force shall receive a toolbox talk relevant to the operation concerned on the project site safety requirements. STARRT Card shall be used. Necessary measures shall be applied to any activity involving safety risk.Only tagged scaffolding with guardrails, foot rails etc., shall be used to afford access to high locations. Material shall be used in well-ventilated area and inhalation avoided.Personnel shall use protective clothing, gloves, eye protection, masks etc .to avoid skin contact. Plenty of clean water shall be made available. Safety Supervision A competent inspector shall visit the area daily to assess the safety measures adopted. Any snag observed during his visit, shall be notified to the supervisor present who immediately act to bring the safety measures to an acceptable standard MaterialMaster Builder Technology ProductMasterseal 300H - an acrylic based, elastomeric decorative, flexible, anti-carbonation and waterproof protective coating designed for the protection of concrete structures against carbonation and chloride ingress.Masterseal 181S- primer systemMasterseal 300 H fillerStorageThe material shall be stored under cover out of direct sunlight and protected from temperature extremes. The containers shall be resealed after use. Damaged tins shall be disposed off according to the state regulations.MethodThe system shall only be applied to surfaces that have been passed as being ready to receive them. All necessary repairs to the concrete surface shall have been carried out and relevant QC documentation completed.All surfaces shall be free from oil, grease, friable matters and curing compound. Sweep blasting shall be used to obtain an acceptable surface for coating and the surfaces shall be cleaned from dust / sand using compressed air. PrimerThe surfaces shall be brush primed with Masterkure 181S and allowed to dry for 2 hoursSubsequently Masterseal 300H mixed with Masterseal 300 H filler applied as a scrape coat and allowed to dry.

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 122: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

122 of

ApplicationMasterseal 300 H shall be applied directly from the containers using a brush or roller @ a minimum of 0.8 litre per sqm surface coverage to achieve a continuous coating Continuous coating may be achieved in 2 coats of application (minimum)The coating shall not be applied in the dusty weather conditionsNo post application curing is requiredEquipmentBrush RollerAttachmentMBT Statement#54

Hand excavation to installTelephone ducts between box no. 20 to telecom centreTop

IndexScopeReference documentsDefinitionsResponsibilitiesSafetyMethod EquipmentAttachmentScope This statement is aimed to propose the procedures to be adopted to carry out the laying in 2 No. 4 “ dia PVC ducts for telecommunication cables over the existing ducts between box No. 20 to telecom centre.ReferencesDrawing Nos. Specification. Excavation & Backfilling for Underground structures.

DefinitionsPSM Project Site Manager.CM Construction Manager.CS Construction SuperintendentFM Foreman

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 123: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

123 of

ResponsibilitiesCM shall plan and resource the trench excavation and backfilling activity, in accordance with this method statement. The Construction superintendent shall control and monitor the operations directing the construction ForemanThe Construction Foreman shall execute these activities directing the workforce as necessary. EPC Contractor shall control the activities.SafetyPrior to the commencement of any activity, the labour force shall receive a toolbox talk on the project site safety requirements. Any process that is adopted having a particular safety risk shall be assessed and addressed as required.A competent inspector shall inspect the trench daily to assess the safety measures adopted as well as after every rainstorm. If required, the shoring shall be provided to prevent the caving in. In case of the trench depth being more than 1200 mm, adequate means of exit such as ladders or steps shall be provided and located no more than 8 m of lateral travel. Barricades, markers and the night-lights etc., shall be arranged as required.StatusThe site is located at the police station where 2 no. manholes MH2 and MH3 existThe manholes centre-to-centre distance is 141 m. The proposed section to be excavated is 500mm wide and 1000 mm deep. Additional / spare 2 nos. PVC ducts 4 “ dia are to be provided above the existing ductsThe access road to the police station is wearing asphalt course From manhole no. 3 to no. 2 i.e. 141 m is running under the police station car park and the access road. The main portion of the line in the middle as shown is access road and the parking facility for the police stationThe internal portion of the line from man hole no. 2 to the internal Telecom Vault is also running beneath the interlocking blocks paving after crossing under the fence wall MethodThe work shall involve the following operational procedures. Between man hole No. 3 and No. 2.Remove the interlocking blocks Road cutting at the police station entrance across 500 mm wide or as requiredBridge the gap at the road cut using steel plates to facilitate the smooth traffic plying Manual excavation of the trench in the entire 141 m lengthSand bedding 75 mmInstall 2 nos. 100 mm dia pipe ductsSand filling over the ducts 75 mmBackfilling as specifiedRefixing the interlocking tilesMaking good the access road Removing the steel platesBetween the manhole No. 2 and the internal telecom vaultRemoving the interlocking blocks

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 124: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

124 of

Manual excavation of the trench to the existing ducts from the manhole No.2 to the internal vault crossing below the fence wallSand filling 75 mm thick below the proposed ductLaying ducts Filling 75 mm thick sand over the laid ductsEntering cable wayMaking good the entryBackfilling as specifiedRefixing the interlocking blocks to the patternClearing the siteDetailsExternalThe existing interlocking paving tiles shall be removed to a safer location from the required work area and stacked properlyThe access road shall be cut across to the required level exposing the existing ducts and the bridging steel plates be laid over completely to facilitate the car accessThe manual excavation shall be carried out in the entire length of 141 m to the given sectional dimensions upto the existing ducts as shownAfter the excavation to the required depth is completed, a 75 mm thick layer of sand shall be filled in on the existing ducts to receive 2 nos. 4 “ dia new ducts which be placed and further covered with another 75 mm thick sand layerAfter the sand is filled in, the backfilling shall be carried out according to the project specifications upto the bottom of the interlocking blocks to be refixed After the backfilling is completed, the interlocking blocks shall be refixed to the same location or the pattern, which existed before these were removed.The backfilling shall be done in the road cut part upto the concrete bottom and asphalt laid overAfter the whole backfilling is over, the effected access road shall be made good by asphalt laying on concrete baseInternalThe interlocking blocks shall be removed from the proposed marked route and stacked well and safe to be reusedThe excavation shall be carried out on the entire length from the fence to the existing vaultThe excavation shall be carried out from the manhole nos. 2 to the inside of the wall penetrating beneathThe whole route of the existing ducts shall be exposedSand shall be filled in 75 mm thickness over the existing ductsSpare ducts 2 nos shall be laid over the sand filling over the existing ducts Further sand filling 75 mm thick shall be carried out to cover the new ducts and the backfilling be commenced to the bottom of the existing interlocking pavement according to the specificationsAfter the backfilling is over, the interlocking blocks shall be refixed to the existing pattern and the effected wall portion be repaired to the extent of damage if any

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 125: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

125 of

The external portion from the wall to the manhole shall also be sand filled and backfilled according to the details The whole work shall be approvedEquipmentJackhammerCompressorAttachmentSketch#55

Backfilling of the west side of the quench tower foundation – (rib) Top

IndexScopeReference documentsExisting Windows Section as per drawingReasons for ProposalDetails of New proposal and Location change in PlacementMethod EquipmentAttachmentScope This statement is aimed to propose the procedures to be adopted for the construction of the west direction extended part of the design foundation / Cantilever rib. ReferencesDrawingThe revised IFC drawing was received after the completion of the blinding concrete and the Rebar binding works.DefinitionsPSM Project Site Manager.CM Construction Manager.CS Construction SuperintendentFM Foreman ResponsibilitiesCM shall plan and resource the activities in accordance with this method statement. The Construction Superintendent shall control and monitor the operations directing the construction Foreman.Foreman shall execute and assist monitor these activities directing the workforce as necessary. EPC Contractor shall control the activities.

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 126: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

126 of

SafetyThe workforce shall receive every day before the commencement of any activity a Tool Box talk relevant to the operation according to the project requirements. All the safety measures shall be arranged according to the operational requirement.MethodThe extended part shall be constructed to the following sequences.The concrete shall be poured to the preparatory works carried out on site.The deshuttering shall be done after 14 days.Application of the membrane to the underside / soffit of the slab.Backfilling the underside space by the lean mix PBFC 20 grade concrete.DetailsSince all the preparatory works such as the bending and binding of the reinforcement, centering and shuttering of form work, propping etc., and all the relevant activities have been carried out to the design requirement per previous revision and according to the project specifications, the concrete shall be poured to the works done.After the completion of the pour and the sequential curing and a lapse of 14 days, the forms shall be struck from the underside of the slab / soffitThe formed surface shall be applied with the protective concrete membrane as specified and shown on the sketchThe space left between the soffit and the prepared ground shall be prepared for the concrete filling by erecting the formwork in the letter box style The forms shall be fabricated according to the following descriptionsBottom panel of 600 mm height shall be erected around Top panel of 200 mm shall be prepared in letter box style to allow the pour of the concreteThe top panel post pour shutters shall be made ready before the commencement of the concreteImmediately after the pour reaches to the brims / soffit levelThe top panels shall be placed in position to close all the external surface and supported to the requirementThe forms shall be struck as per the project specificationEquipmentConcrete PumpConcrete Transit Mixers

AttachmentSketch #56

Excavation Cooling water outfall chamberTop

IndexScopeReference documentsStatements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 127: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

127 of

DefinitionsResponsibilitiesSafetyMethod EquipmentAttachmentScope This statement is aimed to present the proposed procedures to be adopted to carry out the excavation for the foundation in respect of the Cooling Water Outfall Chamber.ReferencesDrawing Specification Excavation & Backfilling for Underground structures.DefinitionsPSM Project Site Manager.CM Construction Manager.CS Construction SuperintendentFM Foreman ResponsibilitiesCM shall plan and resource the excavation activity in accordance with this method statement. The Construction Superintendent shall control and superintend and monitor the operations directing the Foreman as required. The Construction Foreman shall execute these activities, deploying the workforce on the job as necessary. EPC Contractor shall do surveillance on the operations.

SafetyPrior to the commencement of any activity, the labour force shall receive a tool box talk on the project site safety requirements. Any process that is adopted having a particular safety risk shall be assessed and addressed according to the project safety requirements.A competent inspector shall inspect the excavated area daily as well as after every rainstorm to assess the safety measures adopted. If required, the shoring shall be provided to prevent the caving in. In case of the trench depth being more than 1200 mm, adequate means of exit such as ladders or steps shall be provided and located no more than 8 m of lateral travel. Barricades, markers and the night-lights etc., shall be arranged as required.Design StatusThe centre lines of the proposed structure and the coordinates meet at N (Typ) and E (Typ)The plan size of the chamber is 10.025 m x 7.2 mThe excavation has to be carried out to the +2.3 m level from RGL +10.500 i.e a depth of 7.8 m shall be excavatedMethodThe excavation shall be carried out to the following sequencesSetting out the linesBarricading the areaExcavation in stages as shown on sketchStatements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 128: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

128 of

DetailsAttached sketch To start with, a surveyor shall set out the site for the excavationto the exact lines and coordinates references. After the setting out, the excavation lines shall be marked 4750 mm away from the proposed external faces of the structure as shown on the sketch. The excavation shall be carried out to the details shown on the sketch in 5 steps of size 750 mm tread and 1500mm riser and the bottom step of 675 mm riser.The size of the lowest level excavation shall be 120025 x 9200 mm and that of the top 19525 x 16700 mm.The excavation shall be started from one end and the top 750 mm deep be completedThe access shall be ramped for the equipment to enter.The excavation shall be carried out in strips of 750 mm depth until the whole earth mass is taken out.The excavated earth shall be transported to the stockpiles immediately keeping the site tidy. EquipmentExcavatorDumperAttachmentSketch #57

Drilling of holes on Pipe rack & structures on site Top

IndexScopeReference documentsDefinitionsResponsibilitiesSafetyMethod EquipmentScopeThe purpose of this Method Statement is to define the sequence and methodology that shall be implemented for the drilling of holes on structural steel members that have been erected and which requires the drilling of holes due to manufacturing error in location or design change after the beams have been primed or finished coated. Reference Documents

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 129: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

129 of

Specification Steel Structure FabricationSpecification PaintingSpecification GalvanizingSpecification Structural Steel ErectionANSI A 10.13 Safety Requirements for Steel ErectionRelevant Drawings

DefinitionsCM Construction Manager.CS Construction SuperintendentFM Foreman

ResponsibilitiesCM shall plan and resource the drilling of holes, in accordance with this method statement. The Construction Supertindent shall monitor these activities, directing the workforce as necessary. The Erection Foreman shall control the workforce ensuring the full implementation of this method statement including safety measures.SafetyPrior to the commencement of any activity, the labour force shall receive a tool box talk on the project site safety requirements. Any process that is adopted having a particular safety risk shall be assessed and addressed as required.The use of cranes or man lifts shall be assessed and all safety regulations enforced.Men working at heights shall be equipped with the required personal safety equipment.MethodThe new location of the hole centres on the specific member item shall be marked as per the details on the drawing or drawing revision.Using a drilling machine, preferably a magnetic base drilling machine, a pilot hole of size 8mm or 10mm diameter shall be initially drilled. These holes shall be subsequently drilled to the specified diameter.The area around the holes shall be cleaned, burrs removed and edges rounded off. This shall be effected by either using emery paper or grinding wheel.The bare surfaces is made dust free and cold galvanizing applied as a coat with ‘Jotun Barrier 86” , a two pack zinc-rich epoxy primer .Allow about 4 Hours for drying.Make necessary touch-ups using the same grade, colour which were used to paint the structure-prime coat and the top coat if necessary. EquipmentDrilling machineMan liftScaffolding if requiredGrinding machine#58

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 130: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

130 of

Site office establishmentTopIndexScopeReference documentsDefinitionsResponsibilitiesSafetyMethodEquipmentAttachmentScopeThe purpose of this method statement, is to define the procedure that shall be adopted for the establishment of the site office.Reference documentsApproved Site office layout and details drawings.DefinitionsEPC Contractor Civil Contractor . PSM Project Site Manager.CS Construction Superintendent.IS Infrastructure Superintendent.ST Survey team.ResponsibilitiesThe PSM shall ensure the establishment of the site office complex is in accordance with the drawings and agreed specifications. The Construction Superintendent shall coordinate and supervise the day to day activities, along with the Foremen and Survey Team.SafetyThe Safety Officer shall monitor the daily activities, advising and implementing all safety procedures.MethodThe site shall be graded and compacted to the levels indicated upon the approved grading drawings. The ST shall check the final grades. A record drawing of the final grades shall be produced.The ST, using approved drawings, shall set out the relevant issues such as service trenches and foundations.Services:Service trenches relating to the site office complex, for the drainage, water, electric and fire water, shall be set out.

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 131: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

131 of

Working to levels, a mechanical excavator shall excavate the trenches. Excavated material shall be re-used for backfilling when the services have been installed. Surplus material shall be removed from site. The services may share common trenches where appropriate.The drainage pipes shall be installed to grade. Manholes shall be placed at locations indicated upon the site office complex drainage drawings. Sewage holding tanks shall be located as per drawing. A steel tank shall be utilized for water storage. The tank shall be backfilled as appropriate. Draw pits and chambers for cabling shall be located in a similar manner. All service trenches shall receive appropriate sand bedding and surround, plus warning tape for cabling shall be provided. Where any services shall cross an area that shall be trafficked, the service shall be ducted or / and protected with concrete surround as appropriate.Foundations:For the pre-engineered office units, the foundation layout drawing that indicates the precast concrete block foundation locations, shall be utilized for the setting out. The precast concrete foundation blocks, shall be placed upon the pre graded ground. The pre-engineered office units, shall be off loaded from the delivery wagon, direct onto these blocks. Shim plates shall be used between the precast concrete block and the unit chassis where necessary.Power Supply:The relevant pre-engineered sections shall be sealed. The relevant utilities that require connection shall be connected. The appropriate electrical power supply and distribution network shall be provided and commissioned as per approved drawings and schematics. The appropriate checklist shall be utilized.Telephone Service.Etisalet shall provide the service to the designate locations within the building. The internal distribution system shall be installed as per approved scheme.Infra structure:Access roads to the site office shall be constructed according to the layout drawing. Footpaths around the site office shall be constructed as per drawing.Drainage ditches for stormwater shall be graded according to the site office layout drawing.Parking areas as indicated on the site office layout drawing, shall be constructed including covered shelters where appropriate.EquipmentExcavator.Dump trucks.Crane.AttachmentITP No: Temporary Building Checklist QCF08.

#59

Welding of Earthing Lugs on Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 132: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

132 of

East West Piperack (SR0099A &B)TopIndexScopeReference documentsDefinitionsResponsibilitiesSafetyMethod EquipmentAttachmentScopeThe purpose of this Method Statement is to define the sequence and methodology that shall be implemented for the welding of Earthing Lugs on the columns of the East West Piperack steel structure.Reference Documents Specification Steel Structure FabricationSpecification PaintingSpecification GalvanizingSpecification Structural Steel ErectionDrawing No. (Also Refer E-Mail of 6\11\99) - Attached for ReferenceDefinitionsPSM Project Site ManagerCM Construction Manager.CS Construction SuperintendentFM Foreman

ResponsibilitiesCM shall plan and resource this activity, in accordance with this method statement. The Construction Foreman shall monitor these activities, directing the workforce as necessary. The QC inspector shall ensure that the necessary visual inspection is carried out. SafetyAny process that is adopted having a particular safety risk shall be assessed and addressed as required.MethodThe location of the Earthing Lugs on the respective columns shall be marked off. Approximate 30mm of the surrounding area shall be cleaned to remove the primer and galvanising.The Lug shall be initially tack welded to the column and then fully welded to the required fillet size.The fillet weld shall be cleaned and free of defects.Welding shall be done according to the approved WPS using duly qualified welders.

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 133: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

133 of

Visual inspection to be done prior to surface finish.The surface shall be inspected prior to cold galvanizing and painting. The bare surfaces is made dust free and cold galvanizing applied as a coat with ‘Jotun Barrier 86”, a two pack zinc-rich epoxy primer.Allow about 4 Hours for drying.Make necessary touch-ups using the same grade, colour which were used to paint the structure-prime coat and the top coat if necessary. EquipmentWelding MachineGrinding MachineAttachmentDrawing N0. Copy of E-Mail (indicating location of Earthing Lug)PQR No. QP-009PQR No. QP-010WPS No. QW-009WPS No. QW-010 #60

Filling around all the pipes within the plant areaTop

IndexScopeReference documentsDefinitionsResponsibilitiesSafetyMethod EquipmentAttachmentScopeThis statement is aimed to propose the procedures to be adopted for the filling around the GRP pipes within the Plant Area. Reference Documents Specification PSM Project Site ManagerCM Construction Manager.CS Construction SuperintendentStatements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 134: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

134 of

FM Foreman QC Quality Control

ResponsibilitiesCM shall plan and resource this activity in accordance with this method statement. CS shall control, monitor and direct these activities.The Construction Foreman shall execute these activities deploying the workforce as necessary. The QC inspector shall ensure that the necessary inspection and test are carried out. SafetyAny process that is adopted having a particular safety risk shall be assessed and addressed according to Project requirement.MethodThe following activities shall be involved to fill around the pipes laid within the plant areaTo fill the sand in 150 mm thickness around the laid pipesTo fill the approved Red fill material in layers in the remaining trench space 150 mm compactedDetailsThe first layer shall be filled 200 mm apprx. compacted to 150 mm. The field density test shall be conducted for 95 % compaction. A portion of the compacted material 150 mm radially shall be removed to replace with sand circumferentially .The sand shall be placed in the first layer portion to replace the filled material circumferencially.The structural fill material for the second layer shall be placed in 200 mm thick compacted to 150 mm for 95 % field density and tested according to the specifications.Again a portion of the compacted material 150 mm radially shall be removed to replace with sand circumferentially.The sand shall be placed in the second layer portion to replace the filled material circumferentially.Similarly the succeeding layers of fill material shall be placed in 200mm thickness approximately compacted to 150 mm according to the specifications and replaced by the sand filling as aforesaid until the apex level of the pipe is covered with sand.The remaining strata upto the ground level / required level shall be filled in with fill material in 200 mm approximately compacted to 150 mm thick layers according to specifications.EquipmentCompactorAttachmentSketch showing various stages of filling#61

Precasting man holes Catch basin and Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 135: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

135 of

Valve chambersTop

IndexScopeReference documentsDefinitionsResponsibilitiesSafetyMethod EquipmentAttachmentScopeThis statement is aimed to propose the procedures to be adopted to precast the manholes, catch basins and fire water main valve box (wherever so required to be used precast) chambers and install in specified prepared locations.Reference Documents Drg Man Holes Drg Man HolesDrg Man HolesDrg Man HolesDrg Catch BasinsDrg Catch BasinsDrg Catch Basins Drg Typical Details

Specifications DefinitionsPSM Project Site ManagerCM Construction Manager.CS Construction SuperintendentFM ForemanQC Quality Control

ResponsibilitiesPSM shall control the overall operations CM shall arrange the resources required accordinglyCS shall control, monitor and direct the FM and workforce for the operationsFM shall execute the operations deploying the workforceQC shall inspect all the operations according to the specificationsEPC Contractor shall conduct surveillance

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 136: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

136 of

SafetyEvery day prior to the commencement of any activity, the work personnel shall receive a Tool Box talk relevant to the operation according to the project safety requirements.A safety inspector shall inspect the operation daily and direct the Foreman and superintendent address the snags if anyMethodThe following activities shall be involved:To prepare a precasting yard on siteTo fabricate the form works according to design detailsTo fabricate the box outs to be used in formsTo fabricate the reinforcementTo place the rebars and the non critical cathodic protectionTo cast bases with a kicker and shear key as shown in the first stage and cureTo scabble the kicker to roughen the construction joint surface To cast walls with pipes inlet and outlet boxes formed in the second stage with the lifting hooksTo cure the cast unitsTo cast the cover slabs in the third stage and cureExcavation of the relevant area / sBlinding and membraneTransportation of the completed open units to the locationsInstallation of the units on the correct alignment and levelsInspections by Civil Contractor QC and EPC Contractor approvalTo prepare the cover slab bearing mortar bed as specifiedTo provide the box out sleeves for steps insertionPipe laying by othersTo install the seals around the pipes and the box out concrete To cast the surrounding concrete 150 mm thick as specifiedTo apply 1 mm thick coal tar epoxy on the external surfaces as specifiedTo bench the invert levels between the pipe flows where specifiedInspections by Civil Contractor QC and EPC Contractor approvalTo plug the pipe spigot ends To place the covers DetailsA precast yard having a capacity of about 20 units as shown on the attached sketch shall be used for the precasting operations The yard shall have convenience for the vehicles to freely move for various activitiesStrong platforms of 100 mm thick concrete shall be used as the casting bases / floorsIn one go about 10 units shall be made ready for the bottom slab pouringThe overlap shall be provided from the top of the kicker as specified and if so convenient the rebars shall be fabricated continuouslyThe formwork for the base slabs with kickers to be cast monolithically shall be prepared according to the typical sketch attachedRequired rebars shall be placed in the correct locations with 75 mm covers / spacers

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 137: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

137 of

Shear key forms shall be erected according to the details and well clamped inCivil Contractor QC inspection shall be conducted followed by EPC Contractor approvalThe concrete shall be poured through a chuteThe curing shall be carried out by spraying compound and later by saturated hessian and polythene coverThe wall formwork shall be fabricated on site using marine ply The internal forms shall be fixed first to the correct dimensionsThe box outs shall be fixed to the required locations on the fixed formsThe rebars for the walls as well as the trimming around box outs shall be placed in positionThe external forms shall be fixed around well supported, in plumb and correct dimensionsThe lifting lugs shall be placed in the required locations in the walls using 16 mm dia rebar according to the detailed sketch attachedA binding wire length shall be tied to the horizontal rebars in continuity connected to the boss fixed near wall top for the cathodic non critical arrangement / connectionCivil Contractor QC inspection followed by EPC Contractor approvalPouring concrete into wall forms with wood float top surface finish and curing by compound and later by hessian and polythene cover for the specified periodForming cover slab shutters according to the specified details Forming the cover box out shutters into the required positionPlacing the rebars into the correct positionsFixing the cover lifting hooks according to details attachedCivil Contractor QC inspection followed by EPC Contractor approvalPouring concrete and curing as aforesaidInserting the steps shall be carried out by fixing the pieces into the preformed holes in the concrete walls as created by box sleeves with approved grout at a stage when the concrete has gained sufficient strengthThe excavation shall be carried out to the specified level and alignment followed by blinding and water proofingThe open precast chambers shall be crane lifted and transported by a trailor to the relevant locations followed by offloading into the correct alignment The pipes shall be laid by othersAfter the pipes are laid, specified seals shall be placed in with the surrounding concrete as well as the box out void forms erected followed by concrete pouring into the box out voids and the plug(concrete surround)The benching wherever specified shall be formed according to the channel flows and the detailsThe bedding of the joint 20 mm thick shall be carried out on site as specifiedAfter the levels and the alignment are ensured, the cover slab shall be correctly placed in followed by the formation of the concrete block work pad to suit the cover elevationThe cover shall be set in on the block work pad using cement sand mortarThe mass concrete shall be laid around the cover as specifiedThe external surfaces shall be applied with 1 mm dry film thickness non solvented coal tar epoxy in accordance with project specifications Civil Contractor QC inspection followed by EPC Contractor approvalStatements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 138: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

138 of

The whole levels and the alignment details shall be documented according to requirementEquipmentCraneConcrete Transit mixerTrailerVibratorAttachmentYard layoutKicker detailsSketch showing lifting hooks for unit walls and baseSketch showing lifting hooks for cover slab

#62

Termination detail to protective membrane around rcc columns supporting the structural steelColumns for pipe racksCASE (1) WITH ALUMINIUM BEADCASE (2) WITH REBATECASE (3) GRAVEL FILLCASE (4) PAVINGTop

IndexScopeReference documentsDefinitionsResponsibilitiesSafetyMethod EquipmentAttachmentScope This statement is aimed to present the proposed procedures that shall be adopted to clampin the waterproofing membrane termination using Aluminium Beads around the column sides to substitute the formation of the conventional rebate partly for the pipe racks foundations and for the other areas such as hard / soft landscapes. ReferencesSTQ , MAR

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 139: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

139 of

DefinitionsPSM Project Site ManagerCSM Construction ManagerCS Construction SuperintendentSE Site EngineerFM ForemanQC Quality ControlResponsibilitiesPSM shall control the overall operations CM shall arrange the resources required accordingly CS shall control, monitor and direct the SE, FM and workforce for the operationsSE shall be responsible for all the site operations and follow the instructions of the CSFM shall execute the operations deploying the workforce. FM shall explain in full in the language the work persons understand about all the instruction and the toolbox talks every day and check that the same are followed up regularlyQC shall inspect all the operations according to the specificationsEPC Contractor shall conduct surveillanceSafetyPrior to the commencement of work, the labour force shall receive a toolbox talk on the Project Site Safety requirements relevant to the activity involved Any process adopted which may involve a particular Safety risk shall be assessed to the requirement for Site conditions and be taken care of. The personnel shall use the PPE, gloves, masks, eyeglasses etc. To avoid skin contact, use of barrier cream to protect from the adverse effect of sealant application shall also be made.Industrial cleaner shall be used followed by washing with soap and water.Material safety data shall be referred to for disposal and any further information.A safety inspector shall visit the site every day and instruct the supervisor in case any snag is observed who shall immediately implement the instructions accordingly.StorageThe material including the sealant shall be stored under cover out of direct sunlight and protected from extreme temperatures. All the manufacturer’s instructions shall be followed for the purpose.MaterialsAluminium Bead lengths to the Sectional dimensions 30 mm x 2 mmDrilling and fixing screws 3 mm diaSealant- Polyurethane-Gun Grade Cold seal 200PF for horizontal usage on Aluminium strip (Manufacturer BCR) (Emirates Specialities) or equivalentMethodThe following operational sequences shall be involvedCase 1To cut the Aluminium beads to the exact dimensions according to the column size requirement.Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 140: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

140 of

To provide every column 4 # beads by drilling and fixing using Hilty equipmentTo connect the bead to the column side keeping the membrane tacked in by drilling and fixing screws 3 # each sideTo apply sealant a few mm above on the top of the bead covering the bead / column surface junction and a portion few mm downwards well finished to a smooth profileCase 2Where the grooves have already been chased, the waterproofing membrane shall be tacked in with the sealant applied according to the specifications and the manufacturer’s instructions. No Aluminium bead shall be used for this case.Case 3Where the area comprises soft landscape such as gravel or soil fill Case 4Where the area comprises hard landscape such as pavingDetailsCase 1Application of the waterproofing membrane according to the specifications to the defined levels keeping the top 200 mm or variable dimension according to the drawing above the finished ground levelMarking shall be made to the exact line and level to obtain the profile as per drawingRequired lengths to the exact site dimensions shall be cut to suit a close fit between the bead endsEvery bead shall be provided 3 # minimum screws to be drilled and fixed into the bead and the concrete penetrating the membraneThe screws shall be fixed using an electrical operated Drill and ScrewAfter the screws have been fixed into and the beads are in proper alignment / the location, approved sealant shall be applied to the top of the bead keeping about 5 mm above the bead with an overlap on the down ward on the bead as followsApplication of sealantThe material shall be applied using a sealant gun fitted with conical nozzles adjustable to suit the widthThe sealant shall be gunned into the junction using an even trigger pressure, cleaning the nozzle occasionally to avoid contamination. A smaller timber spatula soaked in soapy water shall be used to compact the sealant into the joint for a smooth polish finish formation. The mixing and application equipment shall be cured immediately

Civil Contractor QC inspection shall be conducted followed by EPC Contractor approvalCase 2Where the conventional groove is to be provided, the sealant shall be applied on to the space left in the groove after the application of the water proofing membrane termination has been trimmed .The sealant shall be applied around and formed continuous according to the manufacturer’s instructions

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 141: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

141 of

Civil Contractor QC inspection shall be conducted followed by the EPC Contractor approvalCase 3In gravel or soil area the membrane shall be terminated at a level 150mm plus below the footing top keeping the Aluminium bead strip details typical. All other details shall remain Civil Contractor QC inspection shall be conducted followed by the EPC Contractor approvalas in case 1 if no rebate be chasedCivil Contractor QC inspection shall be conducted followed by the EPC Contractor approvalCase 4 In the paved area the membrane shall continue upto the termination level but the protection board cease at 20 mm below the paving level filled with mastic on top keeping all other details as in case 1 if not chased for rebateCivil Contractor QC inspection shall be conducted followed by the EPC Contractor approvalEquipmentElectrical operated drillSealant applying gunAttachmentSketches as in STQCase wise description

#63

Termination detail to protective membrane around rcc columns supporting the structural steelColumns for pipe racksCASE (1) WITH ALUMINIUM BEADCASE (2) WITH REBATECASE (3) GRAVEL FILLCASE (4) PAVINGTop

IndexScopeReference documentsSafetyMethod EquipmentAttachment

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 142: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

142 of

Scope This statement is aimed to propose the procedures to be adopted to clampin the waterproofing membrane termination using Aluminium Beads around the column sides to substitute the formation of the conventional rebate partly for the pipe racks foundations, other structures and for the other areas such as hard / soft landscapes. ReferencesMAR (Site fixed sample approved) SafetyPrior to the commencement of work, the labour force shall receive a STARRT Card / Toolbox talk on the relevant activity to the Project Site Safety requirements Necessary measures shall be applied to address any risk involved on any processThe personnel shall use the PPE (gloves, masks, eyeglasses etc.) Use of barrier cream to protect skin from the adverse effect of sealant shall also be made.Material safety data shall be referred to for disposal and any further information. A safety inspector shall visit the site every day and instruct the supervisor in case any snag is noticed who must immediately implement the instructions MaterialsAluminium Bead lengths to the Sectional dimensions 30 mm x 2 mmScrews 3 mm diaSealant- Polyurethane-Gun Grade Cold seal 200PF for horizontal usage on Aluminium strip (Manufacturer BCR) (Emirates Specialities) or equivalent MethodThe following operational sequences shall be involvedCase 1Concrete surface shall be cleaned of all dirt & dust using a brushApplication of the waterproofing membrane according to the specifications to the defined levels keeping the top 200 mm or variable dimension according to the drawing above the finished ground levelLines shall be marked on all sides to correct level as per drawingBead Lengths to exact site dimensions shall be cut to suit a close fit between the endsEvery bead shall be provided with a minimum 3 # screws to be drilled and fastened into the concrete penetrating the membrane using an electrical operated Drill After the screws have been fastened and the beads are in proper alignment, approved sealant shall be applied to top of the bead keeping about 5 mm above the bead with a down ward lap as followsSealant shall be applied using a gun fitted with conical nozzles adjustable to suit the widthinto the corner using an even trigger pressure & cleaning the nozzle occasionally to avoid contamination. A smaller timber spatula soaked in soapy water shall be used to compact the sealant into the joint / junction for a smooth polish finish formation. The mixing and application equipment shall be cleaned immediately after useCivil Contractor QC inspection shall be conducted & the relevant ITP signed offCase 2

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 143: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

143 of

Where grooves have already been chased, the waterproofing membrane shall be tacked in & sealant applied to the space left in the groove according to specifications and the manufacturer’s instructions. No Aluminium bead shall be used in this case.Sealant shall be applied around bead continuously Civil Contractor QC inspection shall be conducted & the relevant ITP signed offCase 3In gravel or soil area, membrane shall be terminated at a level ‘150mm plus’ below the footing top level keeping Aluminium bead details typical. All other details shall remain as in ‘case 1’ if no rebate has been chasedCivil Contractor QC inspection shall be conducted & the relevant ITP signed offCase 4 In the paved area, membrane shall continue upto the termination level but the protection board cease at 20 mm below the paving level filled with mastic on top keeping all other details as in case 1 if not chased for rebate Civil Contractor QC inspection shall be conducted & the relevant ITP signed off Equipment Electrical operated drill Sealant applying gun Attachment Sketches Case wise description #64 Road crossing for laying 2 pipes 1 for 20” raw ethane & 1 for 6” propane

First street Operating Authority entry Top IndexScopeReference documentsDefinitionsResponsibilitiesSafetyMethod including traffic management schemeEquipmentAttachmentScopeThe statement is aimed to propose the procedures to be adopted to carry out the excavation at the road crossing to facilitate to lay the pipe lines 1 # each 20” Raw Ethane and 6” Propane at location identified on the attached drawing to the following referencesReference documentsSpecification. Excavation & Backfilling for Underground structures.Drawing No.

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 144: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

144 of

Easement Systems 1 ST StreetPiping Interconnection Drawings, First Street DefinitionsPSM Project Site ManagerCSM Construction ManagerCS Construction SuperintendentSE Site EngineerFM ForemanQC Quality ControlResponsibilitiesPSM shall control the overall operations CM shall arrange the resources required accordingly and be overall responsible for the excavation operationCS shall control, monitor and direct the SE, FM and workforce for the operationsSE shall be responsible for all the site operations and follow the instructions of the CSAny mishap on the excavation operation shall immediately be notified to the CS and the CM for the immediate action if so required for any possible remedy or record or the authority review whatsoever,the case may beFM shall execute the operations deploying the workforce. FM shall explain in full in the language the work persons understand about all the instruction and the ToolBox talks every day and check that the same are followed up regularlyQC shall inspect all the operations according to the specificationsEPC Contractor shall conduct surveillanceSafetyPrior to the commencement of any activity the labour force shall receive a Toolbox talk relevant to the operation concerned on the project site safety requirements. Any process is adopted having a particular safety risk shall be assessed and addressed as required to raise to a minimum standard / an acceptable mark.In the present case the excavation has to be carried out on the Operating Authority area, therefore all the regulated precautions shall be resorted to effect a full safety standard.ToolBox Talks- While conducting ToolBox Talks, a representative from the authority shall be involved to witness and sign the instruction imparted with the workers prior to the commencement of the operations to make a record. Only English literate Foreman shall be employed to work on the excavation execution. Excavation Work Permit- A copy of the work permit shall be posted on a mini board installed on site to be noticeable to all the relevant persons involved on the crossingTraffic Management-Sign boards keep up-All the personnel shall be briefed about the safe keep up of the boardsBarricades,cones, markers and the night-lights, flood lights etc. shall be arranged as required for a complete safety. No oil spillage shall be allowed. The sides of the excavation shall be sloped with the barriers placed to indicate the excavation work in progress

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 145: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

145 of

Flagman-On both the direction, in addition to the traffic sign boards, a flagman shall be engaged to operate full time to direct the traffic about the excavation work in progress by waving the flag for all the vehicles passing byHand Excavation- Excavation required to be by hand shall only be carried out manually. In case certain services not shown on the record drawings such as fibre optics cable is discovered, the excavation shall be ceased to be continued until the decision to hydrojetting is taken up and the authority are involved.Jack Hammer- The worker engaged on operating this equipment shall use protective glass and work in phases with pause intervals. The compressor air pressure shall be monitored from time to time so that the hammer works smoothly. The compressor shall be place within the barricade limits Access to trench- The workers shall clearly be instructed to use only the ladders to enter in or come out. No jumping shall be allowedMachine ExcavationThe operators shall be explicitly explained and instructed about the requirement of the reverse signal and sound when operating reverse. The truck driver shall also be instructed similarly. Banksman shall be engaged while the equipment operate.No violation of the traffic rules shall be allowedDeep TrenchesIf required, the shoring shall be provided to prevent the caving in. In case of the trench depth being more than 1200 mm. Adequate means of exit such as Aluminium ladder or steps shall be provided and located no more than 8 m of lateral travel. Plants preservationThe live plants and the trees arboricultured shall be deplanted integrally with the roots and preserved to the specialist requirement so that these remain live till the replantation is carried out all to the satisfaction of the specialistSafety SupervisionA competent inspector shall inspect the trench daily to assess the safety measures adopted. MethodThe required permit to work shall be obtained from the Plant Refinery Division.The record drawings regarding the existing services shall be obtained.A traffic management scheme has been presented herein and shall be produced on site as detailed on the attached sketch for this road crossing which includes, reduced speed sign, temporary diverted roads sign, men at work sign, warning signs, informatory signs, safety barriers, night lighting and road cleaning activities. The traffic management scheme shall be reviewed and approved by EPC Contractor prior to commencing the work.The aforesaid traffic management scheme shall be implemented as described below:TRAFFIC MANAGEMENT SCHEME ROAD CROSSING – First StreetDrawing reference –This proposed crossing is located on the road 1st Street between the following co-ordinates as shown on the referred drawing.This is a 2-way road with a central verge and carrying 1 lane on either way

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 146: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

146 of

Both ends of the crossing are existing earthen ramp. On the central verge 4 minor irrigation pipes are in service. On the West Side, one irrigation pipe is in service. On the East Side one irrigation pipe is disconnected. On the central verge one electric pole is in service. In addition to the aforesaid tiny plants are arboricultured.The proposed crossing is just situated at the access road to Operating Authority gate. The road shall be divided in 2 parts as shown on the sketch as lane L1 and L 2 on either side of the carriagewayIn the first instance the work shall be carried out on L1 diverting the traffic to the road portion on L2 as shown on the sketch.In the second instance the work shall be carried out on L2 diverting the traffic to the road portion on L1 as shown on the sketch.The road x-ing lies on the branch road hence one directory sign shall be fixed on both east and west side of the 1st street road at 200m from the location to indicate the work ahead .on the left and right directions respectively. The first board depicting ‘reduce speed’ for traffic diversion informatory shall be located at 100 m from the point of the proposed crossing and the second depicting ‘men at work’ sign be located at 100 m on either way in the opposite directions.A Flagman shall be engaged full time on both the directions to guide the traffic about the ongoing excavation operations in addition to the conventional signboardsThe following activities are involved. Reference to the marked note ‘B’ on the Easement Systems Drawing To produce the Traffic Management SchemeTo divert the minor irrigation, electric pole, plants etc. temporarily as required.To excavate by hand and expose all the underground facilities(5.5KV / 0.24KV cables are available)Trial pit to be excavated in size (5mx2mx1.5m) deep by hand toolsTo seam the area with the detectors to ascertain the existing cables.To expose the cable fully and to be inspected by the authorities / Operating AuthorityAfter the exposure & diversion, the cables to be covered with split PVC pipes by othersTo continue the excavation mechanically according to the authority directions / and as agreedTo excavate the remaining portion by the excavator machineTo have authority inspectionThe pipes to be laid by othersTo fill the bedding material according to the specification requirementTo reinstate the diverted servicesTo reinstate the central verge to the existing stateDetailsThe Traffic Management Scheme shall be executed as explained in the foregoing and to the traffic manual directions.The first section of road crossing on both sides as per the attached sketch shall be marked by the surveyor on the actual location.The asphalt shall be cut using jack hammers.

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 147: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

147 of

The road section shall be excavated to expose the existing cables manually for which the trial pit may be made prior the full manual excavation is proceeded with.The existing electrical pole shall be diverted accordingly.The minor irrigation lines shall be diverted according to the Officials instructions.The plants shall be taken off the site for preservation After the exposure of the cables, the Operating Authority authorities shall inspect and the cables be diverted accordingly following which the remaining machine excavation be carried out to the specified levels The excavated material shall be removed from the site to stockpile area.Appropriate bedding material shall be placed within the excavated trench to the correct service level. Where required, this bedding shall be compacted and tested.The excavated trench shall be inspected by the authorities as required.The potable and the Desalinated water pipes shall be laid by others.Backfill around the service pipes shall be carried using the appropriate material. The service pipes surrounding material shall be compacted as per the project specification requirements. Test results shall be provided for the specification conformance verification.The existing services shall be reinstated accordingly.The plants or trees if removed and so required, shall be reinstated accordingly.General fill up to the underside of road formation shall be placed in 150mm compacted layers using mechanical methods to the specification requirements.A concrete slab shall be cast up to the bottom of the finished asphalt level.The finishing shall be carried out using approved asphalt mix.The traffic management system shall be removed after the road crossing has been cleaned of any debris or obstructions.Either side of the road shall be provided with cable markers to indicate the servicesMajor EquipmentExcavator.Dump trucks.Compactors.Jack Hammer, Compressor, AttachmentSketch showing the traffic management scheme Drawings including the traffic diversion

#65

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 148: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

148 of

Road crossing for laying 2 pipes1 for 20” raw ethane& 1 for 6” propaneFirst street Operating Authority entry Top IndexScopeReference documentsSafetyMethod including traffic management schemeEquipmentAttachmentScopeThe statement is aimed to propose the procedures to be adopted to carry out the excavation at the road crossing to facilitate to lay the pipe lines 1 # each 20” Raw Ethane and 6” Propane at location identified on the attached drawing to the following referencesSafetyPrior to the commencement of any activity the labour force shall receive a / STARRT card / Toolbox talk. Any process involving a particular safety risk shall be assessed and adopted measures addressed to raise to a minimum standard In this case the excavation has to be carried out on the Operating Authority area, therefore all the regulated precautions shall be strictly adhered to effect a full safety standard.Excavation Work Permit- A copy of the work permit shall be posted on a mini board installed on site to be noticeable to all the persons involved on the crossingBarricades, cones, markers, the night-lights, and floodlights etc. shall be installed as required for a complete safety. No oil spillage shall be allowed. Flagman-On both directions, in addition to the traffic sign boards, a flagman shall be engaged full time to direct the traffic about the excavation work in progress by flag signal Hand Excavation- Excavation to expose the services be carried out manually. In case certain services not shown on the record drawings such as fibre optics but it is discovered, further excavation shall be ceased and hydrojetting applied.Access to trench- The workers shall clearly be instructed to use only the ladders to enter in or come out. No jumping shall be allowedMachine Excavation

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 149: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

149 of

The operators / drivers shall be explicitly instructed to abide by the requirement of the reverse signal and sound when operating reverse. Banksman shall be engaged while the equipment operates. No violation of the traffic rules shall be allowedMethodThe required permit to work shall be obtained from the Plant Refinery Division.The record drawings regarding the existing services shall be obtained.A traffic management scheme shall be produced as detailed on the attached sketch Drawing reference Piping Interconnections First Street’: Existing ServicesOne lighting pole is located on the central verge adjacent to the proposed excavation The minor irrigation / hoses exist to irrigate the central verge plantationSome minor trees and plants are also growing on the central verge.The road shall be divided in 2 parts as shown on the sketch as L1 and L 2 In the first instance the work shall be carried out on part L1 diverting the traffic to the road portion on the part L2 In the second instance the work shall be carried out on part L2 diverting the traffic to the road portion on the completed road portion on the part L1 Instance 1The asphalt shall be removedHand excavation shall be carried out to expose the cables & other services by seaming the area with detectorsAfter the exposure, all the cables shall be covered with split PVC pipe to continue the excavation mechanically Remaining portion of the trench shall be excavated by machinePreparation of the trench to lay RCC pipe sleeves shall be carried outBedding material shall be laid to receive the pipe sleevesPipe sleeves with dia 8 “ more than the specified respective pipes dia shall be laid to the design alignment and levels Filling over the pipe sleeves shall be carried out to specificationsThe diverted services shall be reinstatedBackfilling up to the road formation shall be carried out to specificationsThe above operations shall be repeated for Instance 2The central verge shall be made good & the diverted services reinstatedA 70 mm thick layer of concrete shall be laid in place of the asphalt concrete. This shall be subsequently broken out and replaced by asphalt when the asphalt plant is next in operationThe traffic management scheme shall be removed after the road crossing is cleared of all debris and obstructions.Either side of the road shall be provided with cable markers to indicate the servicesMajor EquipmentExcavator, Dumper trucks, Compactors. Jack Hammer, Compressor, AttachmentSketch showing the traffic management scheme #66

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 150: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

150 of

Directional boringFor laying sleeves for2 pipes1 # 20” raw ethane&1 # 6” propaneOperating Authority Plant refinery entry Top

IndexScopeReference documentsSafetyMethod EquipmentAttachmentScopeThe statement is aimed to propose the procedures to be adopted to carry out the directional boring under the road to facilitate to lay the sleeves for pipe lines 1 # each 20” Raw Ethane and 6” Propane at location identified on the attached drawing to the following referenceDrawing reference –Piping Interconnections First Street: SafetyPrior to the commencement of any activity the labour force shall receive a / STARRT card / Toolbox talk. Any process involving a particular safety risk shall be assessed and adopted measures addressed to raise to a minimum standard In this case the excavation has to be carried out on the Operating Authority area, therefore all the regulated precautions shall be strictly adhered to effect a full safety standard.Excavation Work Permit- A copy of the work permit shall be posted on a mini board installed on site at the location shown on the sketch to be noticeable to all the persons involved A copy shall also be transmitted to EPC ContractorBarricades, cones, markers, the night-lights, and floodlights etc. shall be installed as required at the pits for a complete safety. MethodThe necessary permit to work shall be obtained from the Plant Refinery Division.

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 151: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

151 of

The record drawings regarding the existing services shall be obtained2 # trial pits shall be made manually on both ends of the proposed boring to ascertain the availability of the existing services and protect these from any damage and shall also be used for the bentonite trial at the receiving endOn site, sufficient excavated space is available to lower the sleeve in to pull into the boreOn Eastern end, some electric cable is existing2 # 24” pipe lines are also existing adjacent to the proposed routeMinor trees on both ends may be effected in the rootsThe excavated trench does not show any sign of water therefore, no de watering shall be carried outExcavation shall be carried out according to the requirementOn East End missing the berm, boring machine shall be positioned in the trench at about 3 m from the berm The boring shall be carried out in stages. First stage-The sleeve is in the trench on the West end and the reamer fully underground. Second stage-The sleeve is partly pulled in and the reamer partly withdrawnThird stage- The sleeve further pulled and the reamer withdrawn accordingly Fourth stage-Full portion of the sleeve is underground in the bore and the reamer outThe excavated trenches on both ends shall be backfilled by Civil Contractor according to the specification requirement and the required tests carried outThe reinstatement of the effected services shall be carried out after the directional boring is completedDirectional Boring – A non- excavation Method which does not allow collapsing of the ground surfaceM / S Ditch Witch shall carry out the Directional Boring employing Jet Trac Directional Boring equipment according to their method statement attached. Refer to the attached sketches based on the Ditch Witch guidelines Bentonite is pure clay to be used as a fluid / slurry formed by mixing water. It shall be used to cool the drill bit and to lubricate the drill areaThe material displaced by the head / sleeves shall be discharged at the receiving end in the receiving pit and removed from the siteAll fully trained operators shall be used on the jobMajor EquipmentJet Track Unit (complete package), Crane, CompactorAttachmentPlan of the area indicating trial pits etc Ditch Witch Method StatementCross-Section Sketches showing the indicative procedures#67

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 152: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

152 of

Top

IndexScopeReference documentsSafetyMethod EquipmentAttachmentScopeThe statement is aimed to propose the procedures to be adopted to carry out the thrust boring under the road to facilitate to lay the pipe lines 1 # each 20” Raw Ethane and 6” Propane at location identified on the attached drawing to the following referenceDrawing reference –Piping Interconnections First StreetSafetyPrior to the commencement of any activity the labour force shall receive a / STARRT card / Toolbox talk. Any process involving a particular safety risk shall be assessed and adopted measures addressed to raise to a minimum standard In this case the excavation has to be carried out on the Operating Authority area, therefore all the regulated precautions shall be strictly adhered to effect a full safety standard.Excavation Work Permit- A copy of the work permit shall be posted on a mini board installed on site to be noticeable to all the persons involved Barricades, cones, markers, the night-lights, and floodlights etc. shall be installed as required at the pits for a complete safety. Traffic Signs- Necessary traffic signs at the pits shall be providedHand Excavation- Excavation to ascertain the routes of the existing services encountered during Thrust Boring in case not shown on the record drawings shall be carried out manually.MethodThe necessary permit to work shall be obtained from the Plant Refinery Division.The record drawings regarding the existing services shall be obtained.Non Excavation MethodNecessary drive and receiving pits shall be excavated by Civil Contractor according the approved proceduresM / S Ditch Witch shall carry out the Thrust Boring employing Jet Trac Directional Boring according to the brief procedures given belowThe Jet Track unit shall be anchored to the ground surface using hydraulically operated anchor stakesThe directional boring / Angled bit shall be drilled into the ground using fluid assistance to operate.

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 153: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

153 of

Bentonite and water shall be used to form a fluid to be sprayed at low pressure ejected out of the drill head to lubricate the drill procedure as well as to cool electronic tracking components in the drill headAn electronic receiver shall be used to track the head from the ground surface and when the directional control is required, the head shall be pushed by the drill unit without rotation until the drill head angle is reachedHead shall be steered to the ground surface when it reaches the destination endThen Drill head shall be removed from the drill pipe and a backreamer with a pipe puller attached alongwith the pipe / s to be installed undergroundDuring backreaming, the drill fluid shall assist the backreamer lubricate and form slurried area for the installable pipeBackreaming and pipe pulling simultaneously shall allow the pipe to be installed underground without excavation and continue until the backreamer and pipe reach the launch end of the Directional bore accomplishing boring completeNecessary tests shall be carried out by EPC ContractorMajor EquipmentJet Track Unit complete packageAttachmentDitch Witch Method StatementSketches showing the indicative procedures#68

2 #s road crossings For laying1 for 14” desalinated water1 for 8”potable water&1 for 20” raw ethane1 for 8” natural gas1 for 6” propaneAvenue ‘c’At fire stationTop

IndexScopeSafetyMethod including traffic management schemeEquipmentStatements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 154: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

154 of

AttachmentScopeThe statement is aimed to propose the procedures to be adopted to carry out the excavation at the road crossings to construct culverts to facilitate to lay the pipe lines 1 # each 14” Desalinated water, 8” Potable water and 1 # each 20” Raw Ethane, 8” Natural Gas and 6” Propane at locations identified on the attached drawing pertaining to avenue C at existing Fire StationSafetyPrior to the commencement of any activity the labour force shall receive a / STARRT card / Toolbox talk. Any process involving a particular safety risk shall be assessed and adopted measures addressed, to raise to a minimum standard In this case the excavation has to be carried out on the Operating Authority area, therefore all the regulated precautions shall be strictly adhered to have ‘ full safety standard’ effect.

Safety Supervision A competent inspector shall visit the area daily to assess the safety measures adopted. Any snag observed during his visit shall be notified to the supervisor present who immediately act to bring the adopted safety measures to an acceptable standard In case of incident where utilities not identified are discovered or damaged, all work shall stop in the area and the Operator Shift Controller and HSE department immediately notifiedPhone number : Shift Controller Emergency Number HSE Direct number Employees working in easement area shall have a daily pre-task briefing that includes;Reporting of incidentsMethods of work and tools to be usedPotential hazards found in the Easement areasThe approved work method statementEPC Contractor and Civil Contractor HSE department shall participate in presenting the STARRT card briefing and monitor the activities to ensure that the work methods are being followed and all personnel have an understanding of the hazards associated with working adjacent to live process areasExcavation Work Permit- A copy of the work permit shall be posted on a mini board installed on site to be noticeable to all persons involved with the crossingBarricades, cones, markers, night-lights, and floodlights etc. shall be installed as required for a complete safety. No oil spillage shall be allowed. Flagman-On all directions, in addition to the traffic sign boards, flagmen shall be engaged full time to direct the traffic about the ‘excavation work in progress’ by ‘flag signal’ Hand Excavation- Excavation to expose the services shall be carried out manually.

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 155: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

155 of

In case certain services not shown on the record drawings such as fibre optics but it is discovered, further excavation shall be ceased until a decision is taken for the method to be adopted for further excavationAccess to trench- The workers shall clearly be instructed to use only the ladders to enter in or come out of the trench. No jumping shall be allowedMachine ExcavationThe operators / drivers shall be explicitly instructed to abide by the requirement of the reverse signal and sound when operating reverse. Banksman shall be engaged during equipment operation. No violation of the traffic rules shall be allowedPre cast membersSince pre cast culvert units, covers and sleepers are heavy in load, proper care has to be exercised during raising & downing (handling) to the exact locations strictly adhering to the relevant safety measuresMethodThe required permit to work shall be obtained from the Plant Refinery Division.The record drawings regarding the existing services shall be obtained.A traffic management scheme shall be produced as detailed on the attached sketch Drawing reference – Piping Interconnections Road Avenue ‘C’: N Existing Services One serving electric pole is located away from the crossing towards NorthThe minor irrigation / hoses exist to irrigate the central verge plantationStreet light electric cables exist & Some minor plants also growing on the central verge.The road shall be excavated in one instance by diverting the traffic on both sides as shown ProceduresBackfilling shall be carried out to the existing excavated cross trenches on both end of the proposed crossings up to the natural ground level to provide effective traffic ‘divertion routes’ from the road carriageways according to the traffic management scheme attachedTraffic management scheme shall be implemented effectivelyExisting services from the central verge shall be diverted or protected as required and directed by the competent concerned authority The asphalt and the central verge pertaining to the crossings portion shall be removed Hand excavation shall be carried out to expose the cables & the other services by seaming the area with detectorsAfter the exposure, all the cables shall be covered with split PVC pipe & well supported temporarily to continue the excavation mechanically Remaining portion of the trench shall be excavated by machine to the defined levelsPreparation of the trench to construct RCC culverts shall be carried out The construction pertaining to the pipe carrying culverts including the laying of pipe sleepers anchored with standard dowels, covers, fixing steps etc.shall be carried out according to the drawings and the approved procedures using pre cast RCC units / membersIn addition, one access boxout on both ends shall be provided to design detailsThe diverted services shall be reinstatedInspections shall be conducted to the requirementBackfilling up to the road formation shall be carried out according to specificationsStatements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 156: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

156 of

The central verge shall be made good & the diverted services reinstatedThe broken asphalt portion shall be made good using new asphaltThe traffic management scheme shall be removed after the road crossing is cleared of all debris and obstructions.75 mm dia holes in the pre cast units meant for lifting shall be filled with concreteAccess boxout shall be closed with concrete after the pipes are laid Either side of the road shall be provided with cable markers to indicate the services8 mm galvanised removable chequer plate covers with 2 lifting handles shall be provided to design detailsMajor EquipmentExcavator, Dumper trucks, Compactors. Jack Hammer, Compressor, Asphalt finisher, Road RollersAttachmentSketch showing the traffic management scheme #692 #s road crossingsFor laying1 for 14” desalinated water1 for 8”potable water&1 for 20” raw ethane1 for 8” natural gas1 for 6” propaneAvenue ‘c’ At fire stationTop

IndexScopeSafetyMethod including traffic management schemeEquipmentAttachmentScopeThe statement is aimed to propose the procedures to be adopted to carry out the excavation at the road crossings to construct culverts to facilitate to lay the pipe lines 1 # each 14” Desalinated water, 8” Potable water and Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 157: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

157 of

1 # each 20” Raw Ethane, 8” Natural Gas and 6” Propane at locations identified on the attached drawing pertaining to avenue C / First Street Road Crossing at existing Fire Station SafetyPrior to the commencement of any activity the labour force shall receive a / STARRT card / Toolbox talk. Any process involving a particular safety risk shall be assessed and adopted measures addressed, to raise to a minimum standard In this case the excavation has to be carried out on the Operating Authority area, therefore all the regulated precautions shall be strictly adhered to have ‘ full safety standard’ effect.Safety Supervision A competent inspector shall visit the area daily to assess the safety measures adopted. Any snag observed during his visit shall be notified to the supervisor present who immediately act to bring the adopted safety measures to an acceptable standard In case of incident where utilities not identified are discovered or damaged, all work shall stop in the area and the Operator Shift Controller and HSE department immediately notifiedPhone number : Shift Controller Emergency Number HSE Direct number Employees working in easement area shall have a daily pre-task briefing that includes;Reporting of incidentsMethods of work and tools to be usedPotential hazards found in the Easement areasThe approved work method statement

EPC Contractor and Civil Contractor HSE department shall participate in presenting the STARRT card briefing and monitor the activities to ensure that the work methods are being followed and all personnel have an understanding of the hazards associated with working adjacent to live process areasExcavation Work Permit- A copy of the work permit shall be posted on a mini board installed on site to be noticeable to all persons involved with the crossingBarricades, cones, markers, night-lights, and floodlights etc. shall be installed as required for a complete safety. No oil spillage shall be allowed. Flagman-On all directions, in addition to the traffic sign boards, flagmen shall be engaged full time to direct the traffic about the ‘excavation work in progress’ by ‘flag signal’ Hand Excavation- Excavation to expose the services shall be carried out manually.In case certain services not shown on the record drawings such as fibre optics but it is discovered, further excavation shall be ceased until a decision is taken for the method to be adopted for further excavationAccess to trench- the workers shall clearly be instructed to use only the ladders to enter in or come out of the trench. No jumping shall be allowedMachine ExcavationThe operators / drivers shall be explicitly instructed to abide by the requirement of the reverse signal and sound when operating reverse. Banksman shall be engaged during equipment operation. No violation of the traffic rules shall be allowedStatements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 158: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

158 of

Pre cast membersSince pre cast culvert units, covers and sleepers are heavy in load, proper care has to be exercised during raising & downing (handling) to the exact locations strictly adhering to the relevant safety measuresMethodThe required permit to work shall be obtained from the Plant Refinery Division.The record drawings regarding the existing services shall be obtained.A traffic management scheme shall be produced as detailed on the attached sketch Drawing reference Piping Interconnections Road Avenue ‘C’: Existing Services One serving electric pole is located away from the crossing towards NorthThe minor irrigation / hoses exist to irrigate the central verge plantationStreet light electric cables exist & Some minor plants also growing on the central verge.The road shall be excavated in two instances by diverting the traffic on either lane completing one after the other as shown on the traffic management schemeProceduresTraffic management scheme shall be implemented effectivelyExisting services from the central verge shall be diverted or protected as required and directed by the competent concerned authority Instance 1The asphalt and the central verge pertaining to the crossing portion Stage-1 shall be removed Hand excavation shall be carried out to expose the cables & the other services employing seaming the area with detectors to detect the existence of cablesAfter the exposure, all the cables shall be covered with split PVC pipe & well supported temporarily to continue the excavation mechanically Remaining portion of the trench shall be excavated by machine to the defined levelsPreparation of the trench to construct RCC culverts shall be carried out The construction pertaining to the pipe carrying culverts including the laying of pipe sleepers anchored with standard dowels, covers, fixing steps etc.shall be carried out according to the drawings and the approved procedures using pre cast RCC units / membersIn addition, one access boxout at the end shall be provided to design detailsThe diverted services shall be reinstatedInspections shall be conducted to the requirementBackfilling up to the road formation shall be carried out according to specificationsThe broken asphalt portion shall be made good using new asphaltInstance 2The aforesaid activities shall be repeated for this instance for the crossing portion Stage-2The central verge shall be made good & the diverted services reinstatedThe traffic management scheme shall be removed after the road crossing is cleared of all debris and obstructions.75-mm dia holes in the pre cast units meant for lifting shall be filled with concreteAccess boxout shall be closed with concrete after the pipes are laid Either side of the road shall be provided with cable markers to indicate the services

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 159: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

159 of

8 mm galvanised removable chequer plate covers with 2 lifting handles shall be provided to design details. Other chequer plates shall be provided to the design detailsMajor EquipmentExcavator, Dumper trucks, Compactors. Jack Hammer, Compressor, Asphalt finisher, Road RollersAttachmentSketch showing the traffic management scheme

#70Administration building GRC Panel fixingTop

IndexScopeReference documentsDefinitionsResponsibilitiesSafetyMethod EquipmentAttachmentScopeThe statement is aimed to propose the procedures to be adopted to carry out the fixing of preformed GRC panels to columns, parapet and horizontal bands ( locations where there are no projected beams and also where the projected beams exist).Reference documentsDrawings- ELEVATIONSFIBREX Shop Drawings and Statement DefinitionsPSM Project Site ManagerCSM Construction ManagerCS Construction SuperintendentFM ForemanQC Quality ControlResponsibilitiesPSM shall control the overall operations Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 160: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

160 of

CM shall arrange the resources required accordinglyCS shall control, monitor and direct the FM and workforce for the operationsFM shall execute the operations deploying the workforceQC shall inspect all the operations according to the specificationsEPC Contractor shall conduct surveillanceSafetyPrior to the commencement of any activity the work force shall receive a Toolbox talk relevant to the operation concerned on the project site safety requirements. Any process is adopted having a particular safety risk shall be assessed and addressed as required to raise to a minimum standard / an acceptable mark.Adequate scaffolding shall be provided for the safe access to the work location Safety harness shall be provided for the personnel working at heightsMethodThe work of the GRC manufacturing and fixing shall be carried out by the Fibrex Co. W.L.L PO Box # All the metal hanger sub frames exposed surfaces shall be painted to specifications Fixing Column PanelsThe floor finish level shall be marked and the bottom defined.The bottom fixing level shall be marked using a template corresponding to the GRC bottom panel situation.2 #s Stainless Steel bracket 75x75x6 mm shall be fixed with 10 mm S / S Parabolt pinsdrilled on the wall The bottom panels C1 shall be located to the final true position with slotted holes in GRC panels prefilled with Polyurethane mastic prior to placingStainless Steel double side pin bracket 75x75x6mm shall be fixed on the top of the bottom panels to have a pin penetration at least 25 mm inside the slot at bottom panel to act as a lateral restraint with 25mm protrusion beyond top( panel top) level. FIBREX Drawing Ref The inverted S / S upper restraint bracket shall be fixed with over sized hole at the C1S panel top cast in sockets and the panel fixed to the bracket with M10 S / S bolt.The upper panel C1S shall be located and aligned to the final level and positionThe panel shall be fixed to the bracket with M10 S / S boltThe foregoing sequence shall be repeated for the other column panelsThe panel joints shall be filled with Polyurethane sealantCivil Contractor QC inspection shall be conducted followed by the EPC Contractor approvalFixing Parapet PanelsThe bottom level of the panel and the location of the steel box brackets shall be marked according to the details on the FIBREX shop drawingsThe steel box brackets shall be fixed to walls according to the details on the drawingsThe horizontal 70x60x6 mm U channels shall be fixed to the box bracket at 3 levels as marked on the drawing 16 mm holes shall be drilled on U channels corresponding to the panel fixing points using template

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 161: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

161 of

75x75x6xmm steel brackets shall be fixed with over sized holes to the wall locations corresponding to the cast in sockets in the GRC panels. (Ref drg)GRC panels shall be located and aligned to the final level and positionThe panel cast in socket shall be fixed to the bottom bracket with 10 mm S / S bolt with washer2 # S / S brackets shall be fixed on the concrete parapet corresponding to the cast in socket on the top level of the panel and the panel be fixed with the bracket with M 10 threaded bar, nuts and washersThe top GRP cover shall be fixed and screwed in to the GRC panel on one side and parapet on the other as shown on the shop drawingAll the slots / exposed fixings locations shall be closed with GRC closing piecesThe foregoing sequence shall be repeated for the other panels alsoThe panel joints shall be filled with Polyurethane sealantCivil Contractor QC inspection shall be conducted followed by the EPC Contractor approvalFixing Horizontal BandsFixing at locations where there is no projected beamsThe level and the fixing locations shall be marked on the wall according to the details on the shop drawings2 # 75x75x6mm S / S brackets shall be fixed with pin on the marked locations2 # 75x75x6mm S / S brackets shall be fixed with hole at higher level as shown on the shop drawingThe panel shall be located and aligned to final level and position. Slotted holes in GRC panels shall be prefilled with Polyurethane mastic prior to placingThe panel shall be fixed to the top brackets with S / S M 10 boltsThe top fixing slot shall be closed with GRC closing piecesThe foregoing sequence shall be repeated for the other panels alsoThe panel joints shall be filled with Polyurethane sealantCivil Contractor QC inspection shall be conducted followed by the EPC Contractor approvalFixing at locations where there is projected beamsThe level and fixing locations shall be marked on the wall as shown on the shop drawing12 mm dia holes shall be drilled on the wall fixing locationsM10 threaded bars shall be fixed to the panels ‘cast in sockets 4 #’ in the panel4# holes on the wall shall be filled with chemical (Upat chemical anchors)The panel shall be located and aligned to final level and positionThe panel shall be held until the chemical driesThe foregoing sequence shall be repeated for the other panels alsoThe panel joints shall be filled with Polyurethane sealantCivil Contractor QC inspection shall be conducted followed by the EPC Contractor approval

Major EquipmentAttachmentFibrex Statement

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 162: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

162 of

#71

Painting Administration buildingTop

IndexScopeReference documentsDefinitionsResponsibilitiesSafetyMethod EquipmentAttachmentScope This statement is aimed to present the proposed procedures that shall be adopted to apply the Painting System on the above building on various surfaces according to the specifications and the material system approved.ReferencesSpecifications DGMAR # DefinitionsPSM Project Site ManagerCSM Construction ManagerCS Construction SuperintendentFM ForemanQC Quality ControlResponsibilitiesPSM shall control the overall operations CM shall arrange the resources required accordinglyCS shall control, monitor and direct the FM and workforce for the operationsFM shall execute the operations deploying the workforceQC shall inspect all the operations according to the specifications

EPC Contractor shall conduct surveillanceSafetyPrior to the commencement of work, the labour force shall receive a Toolbox talk relevant to the operation concerned to the Project Site Safety requirements. Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 163: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

163 of

Any process that is adopted which may have a particular Safety risk shall be assessed to the requirement for Site conditions and be taken care of. The personnel shall use the PPE, gloves, masks, eyeglasses etc and to avoid skin contact. use of barrier cream shall also be made.Material safety data shall be referred to for disposal and any further information.Adequate arrangement shall be made to provide access to the top of the wall.Adequate scaffolding with proper netshade shall be provided wherever requiredThe personnel shall use the waist safety belt / harness while working on height.Immediate medical care shall be provided in case the eyes of any personnel are effected due to the paint splashes or any other reasonProper ventilation shall be provided to let the workers respirate properlyA safety inspector shall visit the site every day and instruct the supervisor in case any snag is observed who immediately implement the instructions accordingly.StorageThe material shall be stored under cover out of direct sunlight and protected from extreme temperatures. Shelf life 12 months between 5 deg and 35 CelsiusMaterialsBerger Paint systemsMAR #

Table 1S # Sub Strata Surface preparation Operating

temperature1 Galvanised steel-

Exterior,PolyurethaneMechanical cleaning to remove loose deposits

Upto 100 deg C

2 Mild steel-Exterior, Polyurethane

Blasting to Sa 2.5 Upto 100 deg C

3 Concrete Surface- Exterior, Polyurethane textured

Cleaning with sand stone to smoothen the surface free from all dirt etc

Upto 100 deg C

4 Galvanised Steel-Interior, Alkyd

Mechanical cleaning to remove loose deposits

Upto 60 deg C

5 Galvanised Steel-Interior, Primed ferrous metal Alkyd

Mechanical cleaning to St 2 to remove loose rust, scales

Upto 60 deg C

6 Plaster and Gypsum-Gypsum wall board and plaster, Acrylic

Cleaning with fine emery paper to remove dirt etc.

Upto 50 deg C

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 164: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

164 of

System # 1, Exterior Surfaces –Galvanised Steel, PolyurethaneTable 2Coats Generic

Type# of coats

Solids volume %

DFTMicrons

Colour Application

Berger Product

Primer Surface tolerant high build epoxy

1 82 100 Aluminium

Brush / Spray

Epimastic 5100 Al

Finish Gloss Polyurethane

1 50 50 White / Colours

Brush / Spray

Robbiathane

2 150

System # 2, Exterior Surfaces –Ferrous Metal, PolyurethaneTable 3Coats Generic

Type# of coats

Solids volume %

DFTMicrons

Colour Application

Berger Product

Primer High build epoxy polyamide primer

1 57 75 Red Brush / Spray

Epilux 78

Intermediate

High build epoxy polyamide

1 68 100 Grey Brush / Spray

Epilux 218HS

Finish Gloss Polyurethane

1 50 50 White / Colours

Brush / Spray

Robbiathane

3 225

Touch up if required with Epilux 78 after power tool cleaning on spots

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 165: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

165 of

System # 3, Exterior Surfaces –Concrete Masonry, Polyurethane TexturedTable 4Coats Generic

Type# of coats

Solids volume %

DFTMicrons

Colour Application

Berger Product

Primer Epoxy Concrete

1 45 50 White Brush / Spray / Roller

Epilux Concrete Primer

Intermediate

Epoxy spray compound in textured finish

1 68 1000 White Hopper Gun

Luxatile Epoxy Spray Compound

Finish Gloss / Semi Gloss Polyurethane

1 50 50 White / Colours

Roller / Spray

Robbiatathane

1100

The textured pattern is unpressed and the DFT could vary from 700 to 1000 micron or more as manually applied by hopper gunSystem # 4, Interior Surfaces –Galvanised Steel, Alkyd Table 5Coats Generic

Type# of coats

Solids volume %

DFTMicrons

Colour Application

Berger Product

Etch Primer(To be used in surface preparation instead of blasting)

Two Pack washer primer

1 8.5 5 Greenish Yellow

Brush / Spray

Luxaprime 1500

Primer Coat

Anticorrosive rust inhibitive

1 55 55 Red Brush / Spray

Luxaprime 1500

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 166: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

166 of

PrimerIntermediate Coat

Alkyd Undercoat

1 55 55 White Brush / Spray

Luxole 1000

Finish Coat

Alkyd Enamel 1 48 48 White / Colours

Brush / Spray

Luxole 5000

4 155Luxaprime 1000 has to be applied on the same day of Luxaprime 1500System # 5, Interior Surfaces –Primed Ferrous Metal, AlkydTable 6Coats Generic

Type# of coats

Solids volume %

DFTMicrons

Colour Application

Berger Product

Primer Coat(If required)

High build alkyd zinc phosphate primer

1 50 50 Red / Grey

Brush / Spray

Luxaprime 1400

Intermediate Coat

Alkyd undercoat

1 55 50 White Brush / Spray

Luxol 1000

Finish Coat

Alkyd Enamel 1 50 50 White / Colours

Brush / Spray

Luxol 5000

Note-Primer need not be applied if already primed

3 150

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 167: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

167 of

System # 6, Interior Surfaces –Gypsum Wallboard and plaster, AcrylicTable 7Coats Generic

Type# of coats

Solids volume %

DFTMicrons

Colour Application

Berger Product

Primer Coat

Premium quality alkali resisting primer

1 25 25 White Brush / Roller

Brolac Acrylic AR Primer

Filler Coat

High quality acrylic based wall filler

1(to seal & smoothen the surface)

81 To smoothen the surface

White Spatula Berger Super Wall Filler

Intermediate Coat

High quality acrylic emulsion

1 35 50 White / Colours

Roller Bergercoat Acrylic Emulsion

Finish Coat

Semi gloss acrylic emulsion

1 35 50 White / Colours

Roller Brolac Semi Gloss Emulsion

3 >100

MethodGENERALMarking of containersMaterials shall be delivered in sealed containers clearly labelled with the following information.Manufacturer’s name, initials or recognised trade markTitle and specification numberWhether primer or undercoat, finishing coat

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 168: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

168 of

Whether for internal or external use where appropriateColour reference from BS 4800Method of applicationBatch number and date of manufacture and re – testNo paint shall be used after 18 months of manufacture or re testCoating materials other than spray paints, bituminous pants and fine textured masonry paint shall be in containers not exceeding 5 litres capacitySamplesSample panel of 1 sqm in area shall be prepared for each type and colour of coating material to be used in the work for the approval Sample material of each paper / fibre material minimum size 500 x 500 mm showing at least the pattern repeat where applicable shall be submitted for approvalPart 2MaterialsPreparatory Materials Paint removers, abrasive papers and blocks, cleaning agents, etching solutions, stopping, knotting, fillers and other commodities shall be of the types recommended by the manufacturer of the coating to be appliedWhite spirit shall comply with BS 245Knotting shall comply with BS 1336Stopping and filler for woodwork shall be approved proprietary Leadless oil based type recommended for internal or external work as appropriate. Stopping for woodwork to receive a coat finish shall be tinted to match with the surrounding workFiller for plaster or rendering shall be approved proprietary type The following operational sequences shall be involvedPriming CoatFiller Coat to the requirementIntermediate CoatFinishing CoatAll according to the approved system as aforesaid detailed for reference.ApplicationPREPARATION OF THE GALVANIZED SURFACESDirt and other adherent contaminating matter / loose deposits shall be removed from galvanised surfaces by mechanical means using Berger tool cleaner. Cleaning shall not damage the galvanising. Oil or grease shall be removed from galvanised surfaces by the application of an emulsion cleaner. Any zinc corrosion products remaining shall be removed by washing with sweet water and scrubbing with hard bristle brushesAfter being cleaned and degreased, all galvanised surfaces shall be etched with T-wash as described in BS 5493. If any surface fails to turn black as cleaning, greasing and etching processes shall be repeated.APPLICATION OF PAINT GENERALLYAll paints shall be prepared and applied in strict accordance with the manufacturer’s instructions. Priming paints shall be applied by brush. Spray application shall only be used for painting of epoxy resin baseStatements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 169: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

169 of

Exposure of intermediate coats of paint for periods in excess of a few days shall not be permitted except in case of work delivered to site in a primed conditionThe dried films shall be free from bloom, shrinkage, sheeringness, wrinkling, sagging, curtailing, discoloration and extraneous matterNo exterior or exposed paint work shall be carried out under adverse weather conditions, during rain, mist, sandstorms nor when the relative humidity exceeds 80%Painting shall insofar as is practicable be shaded from direct sunlight by netting to prevent wrinkling and bristling. Whenever possible exterior painting shall be so programmed during the day so as to be carried out in shadowPainting of surfaces shall not be carried out when condensation is present on such surfaces or the application and / or drying of the paints is likely to be affectedSurfaces to be painted shall receive as first coat of paint as quickly as possible after the e preparation has been completedIn case of metal surfaces this shall preferably be within one hour but always before the metal temperature drops to less than 3 deg C above dew point and before any rustingMETHOD OF COATINGEach coat shall be applied uniformly over the entire surface. Skips, runs, sags and drips shall be avoided. When these occur they shall be brushed out immediately or the materials removed and the surface recoated. On beams and irregular surfaces, edges shall be strip coated first and at extra pass made later. Each coat shall be allowed to dry for the time specified by the manufacturer before application of any succeeding coatAny primer coat exposed to freezing, excess humidity, rain, dust etc., before drying, shall be removed, surface again prepared and primedThe time interval between application of coats shall not exceed that specified for optimum results by the manufacturerAll coatings shall be cleaned as specified by the manufacturer before the next coat is appliedAll areas not specifically mentioned in the painting specification shall be finished to conform to the adjacent comparable areasAll fixtures and surfaces not to be painted shall be properly protected during application and upon completion of the work all paint and varnish removed from glass, fixtures, covering, etc., Moveable parts shall not to be painted.All parts such as pipe supports, seatings and cleats, back to back sections which shall become inaccessible after fabrication shall be treated on both surfaces with the full paint system prior to final assembly, thus ensuring adequate protection.SPRAY APPLICATIONAll equipment for spray application shall be inspected and approved before any application begins. Spray guns, hoses and pumps shall be cleaned before new material is added. An adequate moisture and oil trap shall be installed between the air supply to each application unit.Suitable pressure regulators and gauges shall be provided for the air supply to the application units. Spray equipment and operating pressures shall comply with the manufacturer’s recommendations.Coating materials containing heavy pigments that have a tendency to settle shall be kept in suspension during the application by the power driven, continuous agitatorStatements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 170: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

170 of

The spray gun shall be held at right angles to the surface and each pass overlap the previous one by approximately 50%. All materials contained herein may be applied by airless spray.BRUSH APPLICATIONBrushes shall be of a style and quality that permit proper application of the materialFlat brushes shall not be more than 100 mm wide. No extending handles shall be used on brushes.Brushing shall be done so that a smooth coat as nearly uniform in thickness as possible is obtained without any deep or detrimental marksPaints shall be worked into all corners and crevices. When applying solvent type coating, care shall be taken to prevent lifting of previous coats.FILM THICKNESSSpecified film thickness for coating materials shall be strictly observed which be checked with an appropriate film thickness gauge. Calibration for the thickness range to be checked at least twice a dayWhen dry film thickness are less than those specified, additional coats shall be applied as required. Particular attention shall be paid to full film thickness on edgesIn hot weather such additional precautions as are necessary shall be taken to ensure that the specified dry film thickness on priming or finish coats is obtainedCOATING QUALITYCoatings shall be free from pinholes, voids, bubbles, dust, foreign inclusions and other holidays and any such defect shall be repaired. Prior to the application of a coating, any damage to the previous coating shall be repaired with the specified material. Upon completion of the fabrication any damage to the coating system shall be repaired TEST EQUIPMENTSvensk photographic standard SIS 05 59 00Coating thickness meter such as Elcometer ‘Minitector” Model 150Wet fill thickness combsHygrometerMaximum and minimum thermometerFlow cup type B # 4 and timerSurface profile meter such as Elcometer’Roughness detector’Bolted site connections other than faying surfaces of Grip Bolt connections shall be brought together ‘wet’EPOXY COATING WORK GENERALLYIn addition to the general requirements the following conditions shall apply wherever epoxy-coating work is being carried outForced draught ventilation shall be used wherever required for the needs of the personnel or for drying out surfacesOperatives shall work in pairsSamples areas on substrate shall be prepared and coated for approvalThere shall be strict control of surface cleanliness between primer and epoxy coating / and between coats of the same. Vacuum removal of dust and sand shall be employed and contamination removed. Where dirt or dust has been trapped in the painted surface it shall be

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 171: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

171 of

removed with suitable abrasive paper. The surface being painted shall be free of visible moisture throughout these operationsThe paint shall be applied only to the clean dry primed or previously coated surfaces. Any thick runs or collections of paint shall be removed before these hardenNot less than 2 coats shall be applied over the primer by airless spray, less than 3 by brushEach coat shall be distinctly different in colour from the primer or previous coat. The colour of the final coat shall be as approved. Each coat shall be seen to have completely covered the proceeding without ‘ misses’ or pinholes or any areas visibly low in thickness. A high voltage pinhole detector shall also be used to determine the integrity of the coatsThe manufacturer of the coating shall stipulate primer and epoxy recoat interval for all curing temperatures likely to be encountered and these be adopted with a maximum tolerance of +4 hours. Where this is exceeded, the surfaces to be recoated shall first be suitably abraded to remove gloss and provide a keyWet thickness gauges shall be used by the coating operators continually to check that sufficient paint is being applied to achieve the desired dry film thicknessEPOXY COATING FOR CONCRETE AND RENDERED SURFACESNo priming shall commence until the moisture content of the cementitious surface is less than 5% measured by Wetcheck Moisture meter or other instrument Similarly moisture measurements over the primer or any epoxy intercoat shall not exceed 1 % on the concrete scale of the instrument when the probe tips are held against such painted surfaces just prior to recoatingThe priming shall be applied by suitable Nylon bristle brush or spray over the whole area to be coated at such thickness that it may then be squeezed into the pores of the concrete. Any excess shall be removed by the most suitable means before application of the high build epoxyThe total DFT of the paint layer shall have a minimum specified value Whenever the paint inspection gauge has been used and wherever the coating has been otherwise damaged for 50 mm around such damage, the surfaces shall be abraded followed by the area touched in with not less than 2 # thick applications to restore the coating integrity to the specified thickness. Adhesion tests shall be carried out on the cured coating surface using the test equipment supplied in accordance with the best practice. The resulting test specimens shall show no indication of poor adhesion to the substrate, residual laitance or intercoat adhesion weakness.The following instrument shall be used 1 Adhesion Tester 0 to 35 kg / cm21 DC high voltage holiday detector # 105One paint inspection gauge PIG1 wet check moisture meter#72

PaintingAdministration buildingStatements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 172: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

172 of

Top

IndexScopeReference documentsDefinitionsResponsibilitiesSafetyMethod EquipmentAttachmentScope This statement is aimed to present the proposed procedures that shall be adopted to apply the Painting System on the above building on various surfaces according to the specifications and the material system approved.ReferencesSpecifications MAR # DefinitionsPSM Project Site ManagerCSM Construction ManagerCS Construction SuperintendentFM ForemanQC Quality ControlResponsibilitiesPSM shall control the overall operations CM shall arrange the resources required accordinglyCS shall control, monitor and direct the FM and workforce for the operationsFM shall execute the operations deploying the workforceQC shall inspect all the operations according to the specificationsEPC Contractor shall conduct surveillanceSafetyPrior to the commencement of work, the labour force shall receive a Toolbox talk relevant to the operation concerned to the Project Site Safety requirements. Any process that is adopted which may have a particular Safety risk shall be assessed to the requirement for Site conditions and be taken care of. The personnel shall use the PPE, gloves, masks, eyeglasses etc and to avoid skin contact. use of barrier cream shall also be made.Material safety data shall be referred to for disposal and any further information.Adequate arrangement shall be made to provide access to the top of the wall.Adequate scaffolding with proper netshade shall be provided wherever requiredThe personnel shall use the waist safety belt / harness while working on height.Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 173: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

173 of

Immediate medical care shall be provided in case the eyes of any personnel are effected due to the paint splashes or any other reasonProper ventilation shall be provided to let the workers respirate properlyA safety inspector shall visit the site every day and instruct the supervisor in case any snag is observed who immediately implement the instructions accordingly.StorageThe material shall be stored under cover out of direct sunlight and protected from extreme temperatures. Shelf life 12 months between 5 deg and 35 CelsiusMaterialsBerger Paint systemsMAR #

Table 8S # Sub Strata Surface preparation Operating

temperature1 Galvanised steel-

Exterior,PolyurethaneMechanical cleaning to remove loose deposits

Upto 100 deg C

2 Mild steel-Exterior, Polyurethane

Blasting to Sa 2.5 Upto 100 deg C

3 Concrete Surface- Exterior, Polyurethane textured

Cleaning with sand stone to smoothen the surface free from all dirt etc

Upto 100 deg C

4 Galvanised Steel-Interior, Alkyd

Mechanical cleaning to remove loose deposits

Upto 60 deg C

5 Galvanised Steel-Interior, Primed ferrous metal Alkyd

Mechanical cleaning to St 2 to remove loose rust, scales

Upto 60 deg C

6 Plaster and Gypsum-Gypsum wall board and plaster, Acrylic

Cleaning with fine emery paper to remove dirt etc.

Upto 50 deg C

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 174: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

174 of

System # 1, Exterior Surfaces –Galvanised Steel, PolyurethaneTable 9Coats Generic

Type# of coats

Solids volume %

DFTMicrons

Colour Application

Berger Product

Primer Surface tolerant high build epoxy

1 82 100 Aluminium

Brush / Spray

Epimastic 5100 Al

Finish Gloss Polyurethane

1 50 50 White / Colours

Brush / Spray

Robbiathane

2 150

System # 2, Exterior Surfaces –Ferrous Metal, PolyurethaneTable 10Coats Generic

Type# of coats

Solids volume %

DFTMicrons

Colour Application

Berger Product

Primer High build epoxy polyamide primer

1 57 75 Red Brush / Spray

Epilux 78

Intermediate

High build epoxy polyamide

1 68 100 Grey Brush / Spray

Epilux 218HS

Finish Gloss Polyurethane

1 50 50 White / Colours

Brush / Spray

Robbiathane

3 225

Touch up if required with Epilux 78 after power tool cleaning on spots

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 175: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

175 of

System # 3, Exterior Surfaces –Concrete Masonry, Polyurethane TexturedTable 11Coats Generic

Type# of coats

Solids volume %

DFTMicrons

Colour Application

Berger Product

Primer Epoxy Concrete

1 45 50 White Brush / Spray / Roller

Epilux Concrete Primer

Intermediate

Epoxy spray compound in textured finish

1 68 1000 White Hopper Gun

Luxatile Epoxy Spray Compound

Finish Gloss / Semi Gloss Polyurethane

1 50 50 White / Colours

Roller / Spray

Robbiatathane

1100

The textured pattern is unpressed and the DFT could vary from 700 to 1000 micron or more as manually applied by hopper gun

System # 4, Interior Surfaces –Galvanised Steel, Alkyd Table 12Coats Generic

Type# of coats

Solids volume %

DFTMicrons

Colour Application

Berger Product

Etch Primer(To be used in surface preparation instead of blasting)

Two Pack washer primer

1 8.5 5 Greenish Yellow

Brush / Spray

Luxaprime 1500

Primer Anticorrosive 1 55 55 Red Brush / Luxaprim

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 176: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

176 of

Coat rust inhibitive Primer

Spray e 1500

Intermediate Coat

Alkyd Undercoat

1 55 55 White Brush / Spray

Luxole 1000

Finish Coat

Alkyd Enamel 1 48 48 White / Colours

Brush / Spray

Luxole 5000

4 155

Luxaprime 1000 has to be applied on the same day of Luxaprime 1500

System # 5, Interior Surfaces –Primed Ferrous Metal, AlkydTable 13Coats Generic

Type# of coats

Solids volume %

DFTMicrons

Colour Application

Berger Product

Primer Coat(If required)

High build alkyd zinc phosphate primer

1 50 50 Red / Grey

Brush / Spray

Luxaprime 1400

Intermediate Coat

Alkyd undercoat

1 55 50 White Brush / Spray

Luxol 1000

Finish Coat

Alkyd Enamel 1 50 50 White / Colours

Brush / Spray

Luxol 5000

Note-Primer need not be applied if already primed

3 150

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 177: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

177 of

System # 6, Interior Surfaces –Gypsum Wallboard and plaster, AcrylicTable 14Coats Generic

Type# of coats

Solids volume %

DFTMicrons

Colour Application

Berger Product

Primer Coat

Premium quality alkali resisting primer

1 25 25 White Brush / Roller

Brolac Acrylic AR Primer

Filler Coat

High quality acrylic based wall filler

1(to seal & smoothen the surface)

81 To smoothen the surface

White Spatula Berger Super Wall Filler

Intermediate Coat

High quality acrylic emulsion

1 35 50 White / Colours

Roller Bergercoat Acrylic Emulsion

Finish Coat

Semi gloss acrylic emulsion

1 35 50 White / Colours

Roller Brolac Semi Gloss Emulsion

3 >100

MethodGENERALMarking of containersMaterials shall be delivered in sealed containers clearly labelled with the following information.Manufacturer’s name, initials or recognised trade markTitle and specification numberWhether primer or undercoat, finishing coatWhether for internal or external use where appropriateColour reference from BS 4800Method of applicationBatch number and date of manufacture and re – testNo paint shall be used after 18 months of manufacture or re testCoating materials other than spray paints, bituminous pants and fine textured masonry paint shall be in containers not exceeding 5 litres capacity

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 178: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

178 of

SamplesSample panel of 1 sqm in area shall be prepared for each type and colour of coating material to be used in the work for the approval Sample material of each paper / fibre material minimum size 500 x 500 mm showing at least the pattern repeat where applicable shall be submitted for approvalPart 2MaterialsPreparatory Materials Paint removers, abrasive papers and blocks, cleaning agents, etching solutions, stopping, knotting, fillers and other commodities shall be of the types recommended by the manufacturer of the coating to be appliedWhite spirit shall comply with BS 245Knotting shall comply with BS 1336Stopping and filler for woodwork shall be approved proprietary Leadless oil based type recommended for internal or external work as appropriate. Stopping for woodwork to receive a coat finish shall be tinted to match with the surrounding workFiller for plaster or rendering shall be approved proprietary type The following operational sequences shall be involvedPriming CoatFiller Coat to the requirementIntermediate CoatFinishing CoatAll according to the approved system as aforesaid detailed for reference.ApplicationPREPARATION OF THE GALVANIZED SURFACESDirt and other adherent contaminating matter / loose deposits shall be removed from galvanised surfaces by mechanical means using Berger tool cleaner. Cleaning shall not damage the galvanising. Oil or grease shall be removed from galvanised surfaces by the application of an emulsion cleaner. Any zinc corrosion products remaining shall be removed by washing with sweet water and scrubbing with hard bristle brushesAfter being cleaned and degreased, all galvanised surfaces shall be etched with T-wash as described in BS 5493. If any surface fails to turn black as cleaning, greasing and etching processes shall be repeated.APPLICATION OF PAINT GENERALLYAll paints shall be prepared and applied in strict accordance with the manufacturer’s instructions. Priming paints shall be applied by brush. Spray application shall only be used for painting of epoxy resin baseExposure of intermediate coats of paint for periods in excess of a few days shall not be permitted except in case of work delivered to site in a primed conditionThe dried films shall be free from bloom, shrinkage, sheeringness, wrinkling, sagging, curtailing, discoloration and extraneous matterNo exterior or exposed paint work shall be carried out under adverse weather conditions, during rain, mist, sandstorms nor when the relative humidity exceeds 80%

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 179: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

179 of

Painting shall insofar as is practicable be shaded from direct sunlight by netting to prevent wrinkling and bristling. Whenever possible exterior painting shall be so programmed during the day so as to be carried out in shadowPainting of surfaces shall not be carried out when condensation is present on such surfaces or the application and / or drying of the paints is likely to be affectedSurfaces to be painted shall receive as first coat of paint as quickly as possible after the e preparation has been completedIn case of metal surfaces this shall preferably be within one hour but always before the metal temperature drops to less than 3 deg C above dew point and before any rustingMETHOD OF COATINGEach coat shall be applied uniformly over the entire surface. Skips, runs, sags and drips shall be avoided. When these occur they shall be brushed out immediately or the materials removed and the surface recoated. On beams and irregular surfaces, edges shall be strip coated first and at extra pass made later. Each coat shall be allowed to dry for the time specified by the manufacturer before application of any succeeding coatAny primer coat exposed to freezing, excess humidity, rain, dust etc., before drying, shall be removed, surface again prepared and primedThe time interval between application of coats shall not exceed that specified for optimum results by the manufacturerAll coatings shall be cleaned as specified by the manufacturer before the next coat is appliedAll areas not specifically mentioned in the painting specification shall be finished to conform to the adjacent comparable areasAll fixtures and surfaces not to be painted shall be properly protected during application and upon completion of the work all paint and varnish removed from glass, fixtures, covering, etc., Moveable parts shall not to be painted.All parts such as pipe supports, seatings and cleats, back to back sections which shall become inaccessible after fabrication shall be treated on both surfaces with the full paint system prior to final assembly, thus ensuring adequate protection.SPRAY APPLICATIONAll equipment for spray application shall be inspected and approved before any application begins. Spray guns, hoses and pumps shall be cleaned before new material is added. An adequate moisture and oil trap shall be installed between the air supply to each application unit.Suitable pressure regulators and gauges shall be provided for the air supply to the application units. Spray equipment and operating pressures shall comply with the manufacturer’s recommendations.Coating materials containing heavy pigments that have a tendency to settle shall be kept in suspension during the application by the power driven, continuous agitatorThe spray gun shall be held at right angles to the surface and each pass overlap the previous one by approximately 50%. All materials contained herein may be applied by airless spray.BRUSH APPLICATIONBrushes shall be of a style and quality that permit proper application of the materialFlat brushes shall not be more than 100 mm wide. No extending handles shall be used on brushes.Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 180: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

180 of

Brushing shall be done so that a smooth coat as nearly uniform in thickness as possible is obtained without any deep or detrimental marksPaints shall be worked into all corners and crevices. When applying solvent type coating, care shall be taken to prevent lifting of previous coats.FILM THICKNESSSpecified film thickness for coating materials shall be strictly observed which be checked with an appropriate film thickness gauge. Calibration for the thickness range to be checked at least twice a dayWhen dry film thickness are less than those specified, additional coats shall be applied as required. Particular attention shall be paid to full film thickness on edgesIn hot weather such additional precautions as are necessary shall be taken to ensure that the specified dry film thickness on priming or finish coats is obtainedCOATING QUALITYCoatings shall be free from pinholes, voids, bubbles, dust, foreign inclusions and other holidays and any such defect shall be repaired. Prior to the application of a coating, any damage to the previous coating shall be repaired with the specified material. Upon completion of the fabrication any damage to the coating system shall be repaired TEST EQUIPMENTSvensk photographic standard SIS 05 59 00Coating thickness meter such as Elcometer ‘Minitector” Model 150Wet fill thickness combsHygrometerMaximum and minimum thermometerFlow cup type B # 4 and timerSurface profile meter such as Elcometer’Roughness detector’Bolted site connections other than faying surfaces of Grip Bolt connections shall be brought together ‘wet’EPOXY COATING WORK GENERALLYIn addition to the general requirements the following conditions shall apply wherever epoxy-coating work is being carried outForced draught ventilation shall be used wherever required for the needs of the personnel or for drying out surfacesOperatives shall work in pairsSamples areas on substrate shall be prepared and coated for approvalThere shall be strict control of surface cleanliness between primer and epoxy coating / and between coats of the same. Vacuum removal of dust and sand shall be employed and contamination removed. Where dirt or dust has been trapped in the painted surface it shall be removed with suitable abrasive paper. The surface being painted shall be free of visible moisture throughout these operationsThe paint shall be applied only to the clean dry primed or previously coated surfaces. Any thick runs or collections of paint shall be removed before these hardenNot less than 2 coats shall be applied over the primer by airless spray, less than 3 by brushEach coat shall be distinctly different in colour from the primer or previous coat. The colour of the final coat shall be as approved. Each coat shall be seen to have completely covered the Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 181: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

181 of

proceeding without ‘ misses’ or pinholes or any areas visibly low in thickness. A high voltage pinhole detector shall also be used to determine the integrity of the coatsThe manufacturer of the coating shall stipulate primer and epoxy recoat interval for all curing temperatures likely to be encountered and these be adopted with a maximum tolerance of +4 hours. Where this is exceeded, the surfaces to be recoated shall first be suitably abraded to remove gloss and provide a keyWet thickness gauges shall be used by the coating operators continually to check that sufficient paint is being applied to achieve the desired dry film thicknessEPOXY COATING FOR CONCRETE AND RENDERED SURFACESNo priming shall commence until the moisture content of the cementitious surface is less than 5% measured by Wetcheck Moisture meter or other instrument Similarly moisture measurements over the primer or any epoxy intercoat shall not exceed 1 % on the concrete scale of the instrument when the probe tips are held against such painted surfaces just prior to recoatingThe priming shall be applied by suitable Nylon bristle brush or spray over the whole area to be coated at such thickness that it may then be squeezed into the pores of the concrete. Any excess shall be removed by the most suitable means before application of the high build epoxyThe total DFT of the paint layer shall have a minimum specified value Whenever the paint inspection gauge has been used and wherever the coating has been otherwise damaged for 50 mm around such damage, the surfaces shall be abraded followed by the area touched in with not less than 2 # thick applications to restore the coating integrity to the specified thickness. Adhesion tests shall be carried out on the cured coating surface using the test equipment supplied in accordance with the best practice. The resulting test specimens shall show no indication of poor adhesion to the substrate, residual laitance or intercoat adhesion weakness.The following instrument shall be used 1 Adhesion Tester 0 to 35 kg / cm21 DC high voltage holiday detector # 105One paint inspection gauge PIG1 wet check moisture meter

#73

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 182: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

182 of

Road crossing for laying 2 pipes1 for 20” raw ethane&1 for 6”propaneAvenue ‘c’Top

IndexScopeReference documentsDefinitionsResponsibilitiesSafetyMethod including traffic management schemeEquipmentAttachmentScopeThe statement is aimed to propose the procedures to be adopted to carry out the excavation at the road crossing to facilitate to lay the pipe lines 1 # each 20” Raw Ethane and 6” Propane at locations identified on the attached drawing to the following referencesReference documentsSpecification Excavation & Backfilling for Underground structures.Drawing No. Easement Systems Avenue “C”Piping Interconnection Drawings, Avenue ‘C’ DefinitionsPSM Project Site ManagerCSM Construction ManagerCS Construction SuperintendentSE Site EngineerFM ForemanQC Quality ControlResponsibilitiesPSM shall control the overall operations CM shall arrange the resources required accordingly and be overall responsible for the excavation operationCS shall control, monitor and direct the SE, FM and workforce for the operations

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 183: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

183 of

SE shall be responsible for all the site operations and follow the instructions of the CSAny mishap on the excavation operation shall immediately be notified to the CS and the CM for the immediate action if so required for any possible remedy or record or the authority review whatsoever,the case may beFM shall execute the operations deploying the workforce. FM shall explain in full in the language the work persons understand about all the instruction and the ToolBox talks every day and check that the same are followed up regularlyQC shall inspect all the operations according to the specificationsEPC Contractor shall conduct surveillanceSafetyPrior to the commencement of any activity the labour force shall receive a Toolbox talk relevant to the operation concerned on the project site safety requirements. Any process is adopted having a particular safety risk shall be assessed and addressed as required to raise to a minimum standard / an acceptable mark.In the present case the excavation has to be carried out on the Operating Authority area, therefore all the regulated precautions shall be resorted to effect a full safety standard.ToolBox Talks- While conducting ToolBox Talks, a representative from the authority shall be involved to witness and sign the instruction imparted with the workers prior to the commencement of the operations to make a record. Only English literate Foreman shall be employed to work on the excavation execution. Excavation Work Permit- A copy of the work permit shall be posted on a mini board installed on site to be noticeable to all the relevant persons involved on the crossingTraffic Management-Sign boards keep up-All the personnel shall be briefed about the safe keep up of the boardsBarricades,cones, markers and the night-lights, flood lights etc. shall be arranged as required for a complete safety. No oil spillage shall be allowed. The sides of the excavation shall be sloped with the barriers placed to indicate the excavation work in progressFlagman-On both the direction, in addition to the traffic sign boards, a flagman shall be engaged to operate full time to direct the traffic about the excavation work in progress by waving the flag for all the vehicles passing byHand Excavation- Excavation required to be by hand shall only be carried out manually. In case certain services not shown on the record drawings such as fibre optics cable is discovered, the excavation shall be ceased to be continued until the decision to hydrojetting is taken up and the authority are involved.Jack Hammer- The worker engaged on operating this equipment shall use protective glass and work in phases with pause intervals. The compressor air pressure shall be monitored from time to time so that the hammer works smoothly. The compressor shall be place within the barricade limits Access to trench- The workers shall clearly be instructed to use only the ladders to enter in or come out. No jumping shall be allowedMachine Excavation

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 184: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

184 of

The operators shall be explicitly explained and instructed about the requirement of the reverse signal and sound when operating reverse. The truck driver shall also be instructed similarly. Banksman shall be engaged while the equipment operate.No violation of the traffic rules shall be allowedDeep TrenchesIf required, the shoring shall be provided to prevent the caving in. In case of the trench depth being more than 1200 mm. Adequate means of exit such as Aluminium ladder or steps shall be provided and located no more than 8 m of lateral travel. Plants preservationThe live plants and the trees arboricultured shall be deplanted integrally with the roots and preserved to the specialist requirement so that these remain live till the replantation is carried out all to the satisfaction of the specialistSafety SupervisionA competent inspector shall inspect the trench daily to assess the safety measures adopted. MethodThe required permit to work shall be obtained from the Plant Refinery Division.The record drawings regarding the existing services shall be obtained.

A traffic management scheme has been presented herein and shall be produced on site as detailed on the attached sketch for this road crossing which includes, reduced speed sign, temporary diverted roads sign, men at work sign, warning signs, informatory signs, safety barriers, night lighting and road cleaning activities etc. The traffic management scheme shall be reviewed and approved by EPC Contractor prior to commencing the work.The aforesaid traffic management scheme shall be implemented as described below:TRAFFIC MANAGEMENT SCHEME ROAD CROSSING – First Street / Avenue ‘C’Drawing reference –24168-P40-310-00005 Rev OThis proposed crossing is located on the Road Avenue ‘C’ between the followingCo-ordinates as shown on the referred drawing.This is a 2-way road with a central verge and carrying 2 lanes on either wayThe proposed crossing is located about 160 m from 1st street road towards NorthOne serving electric pole is located away from the x-ing The minor irrigation / hoses are serving on the central vergeSome minor trees and plants are arboricultured on the central verge.The road shall be divided in 2 parts as shown on the sketch as lane L1 and L 2 on either side of the carriageway.In the first instance the work shall be carried out on part L1 diverting the traffic to the road portion on the part L2 as shown on the sketch.In the second instance the work shall be carried out on part L2 diverting the traffic to the road portion on the completed road portion on the part L1 as shown on the sketch.The directory signboards shall also be placed on the 1st street road East West on both ways to indicate the work at the crossingFor the traffic North to South the first reduce speed for traffic diversion informatory board depicting shall be located at 300 m from the point of the proposed crossing, the second Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 185: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

185 of

depicting diversion signs be located at 200 m and the third depicting men at work sign be located at 100 m on either way in the opposite directions.For the traffic South to North past crossing, one sign shall be placed to direct for the diversion, to slow down and the men at work aheadA Flagman shall be engaged full time on both the directions to guide the traffic about the ongoing excavation operations in addition to the conventional signboardsThe following activities are involved. Reference to the marked note ‘B’ on the Easement Systems Drawing To produce the Traffic Diversion Management SchemeTo excavate by hand and expose all the underground facilities5.5KV / 0.24KV cables are availableTrial pits to be excavated in size 5mx2mx1.5m deep by hand toolsTo seam the area with the detectors to ascertain the access to the cableTo expose the cable fully and to be inspected by the authorities / Operating AuthorityAfter the exposure, all the cables to be covered with split PVC pipe to continue the excavation mechanically according to the authority directions and as agreedTo excavate the remaining portion by the excavator machineTo have authority inspectionThe pipes to be laid by othersTo fill the bedding material according to the specification requirementTo reinstate the diverted servicesTo reinstate the central verge to the existing stateDetailsThe Traffic Management Scheme shall be executed as explained in the foregoing and to the traffic manual directions.The first section of the proposed road crossing as per the attached sketch shall be marked by the surveyor on the actual location. Any existing services shall be identified from the Record drawings and measures to protect resorted to according to the regulations.The asphalt shall be cut using jackhammersThe road section shall be excavated to the existing cables manually for which the trial pit may be made prior to the full manual excavation is proceeded and after ascertaining the safe procedures the exposures be completed.After the exposure of the cables, the Operating Authority authorities shall inspect and the cables be diverted accordingly following which the remaining machine excavation be carried out to the specified levels The excavated material shall be removed from the site to stockpile area.Appropriate bedding material shall be placed within the excavated trench to the correct service level. Where required, this bedding shall be compacted and tested.The excavated trench shall be inspected by the authorities as required.The potable and the Desalinated water pipes shall be laid by others.Backfill around the service pipes shall be carried using the appropriate material. The service pipes surrounding material shall be compacted as per the project specification requirements. Test results shall be provided for the specification conformance verification.The existing services shall be reinstated accordingly.Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 186: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

186 of

The plants or trees if removed and so required, shall be reinstated accordingly.General fill up to the underside of road formation shall be placed in 150mm compacted layers using mechanical methods to the specification requirements.A concrete slab shall be cast up to the bottom of the finished asphalt level.The finishing shall be carried out using approved asphalt mix.The traffic management system shall be removed after the road crossing has been cleaned of any debris or obstructions.Either side of the road shall be provided with cable markers to indicate the servicesMajor EquipmentExcavator.Dump trucks.Compactors.Jack Hammer, Compressor, AttachmentSketch showing the traffic management scheme Drawings including the traffic diversion#74

Earthworks survey systemTop

IndexScopeReference documentsDefinitionsResponsibilitiesSafetyMethodEquipmentAttachmentScopeThe purpose of this method statement, is to define the procedure that shall be adopted for the control of the site earthwork activities.Reference documentsMethod statement. Site Preparation & Earthworks.Specification Site Preparation.DefinitionsEPC Contractor Civil Contractor . PSM Project Site Manager.IS Infrastructure Superintendent.ST Survey team.QM Quality Manager.RFI Request for Inspection.

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 187: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

187 of

ResponsibilitiesThe PSM shall ensure the implementation of this method statement upon the earthworks activities.The IS shall coordinate and supervise the implementation of this method statement by the ST on a day to day basis.SafetyThe Safety Officer shall monitor the daily earthworks activities, advising and implementing all safety procedures.MethodWhere areas are to be grubbed, the IS shall direct the ST to establish grid stakes, at 50m centers, within the area to be grubbed. The ST, prior to the commencement of the machine activities shall provide a sketch of the area defining the outer Northings and Eastings of the area.Upon completion of the establishment of the survey grid stakes and the site sketch, the IS shall inform the QM.The QM shall inspect the area to verify the correct establishment of the survey grid stakes.The QM shall notify the EPC Contractor Engineer of the proposed grubbing activity by using the RFI notification system.The EPC Contractor Engineer shall review the proposed grubbing area. Should the EPC Contractor Engineer have any comments or observations about the area, he shall inform the QM and / or IS of these observations. The appropriate actions shall be conducted.Upon completion of the grubbing activity, the IS shall notify the QM, who shall inspect the area and complete the appropriate RFI.The EPC Contractor Engineer shall review the area with the QM and Geotechnical Engineer, and comment if appropriate.Where the area requires to be “cut”’ the ST shall establish pegs to indicate the correct cut level. The cut activity shall be conducted.Upon completion of the “cut” activity, the ST shall produce a ground level survey of the cut area. This survey shall be forwarded to the QM for record purposes. The QM shall transmit a copy of the survey report to the EPC Contractor Engineer.Where the area requires a “fill” activity, the formation level shall be moisturized and compacted as defined within the earthworks method statement. The IS shall coordinate with the ST to establish fill stakes, that shall indicate the layer levels. Each fill layer shall be placed, moisturized and compacted according to the earthworks method statement.Upon completion of all the fill layers to the area, the ST shall produce a survey of finished ground levels. This survey shall be forwarded to the QM for record. A copy of this survey shall be transmitted to the EPC Contractor Engineer.Should a grubbing level stake or fill stake be damaged or moved, the ST shall re establish the stake correctly.The RFI system shall document the comments and observations of an activity by the EPC Contractor engineer.EquipmentTotal station distomat.

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 188: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

188 of

Stakes.Marker tape.AttachmentNone.

#75

Road crossing for laying84”GRE pair seawaterCooling linesAtAvenue ‘d’ / cornicheJunctionTop

IndexScopeReference documentsSafetyMethod including traffic management schemeEquipmentAttachmentScopeThe statement is aimed to propose the procedures to be adopted to carry out the excavation at the road to facilitate to lay the pipe lines 1 # pair 84” GRE Sea Water Cooling supply lines at Avenue’D’ and ‘Cornice Road’ junction identified on the attached drawing to the following referencesReference documentsSpecification. Excavation & Backfilling for Underground structures.Drawing No. Piping Interconnection Drawings- SeaWater Cooling Supply Lines SafetyPrior to the commencement of any activity the labour force shall receive a / STARRT card / Toolbox talk. Any process involving a particular safety risk shall be assessed and adopted measures addressed to raise to a minimum standard

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 189: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

189 of

In this case the excavation has to be carried out on the Operating Authority area, therefore all the regulated precautions shall be strictly adhered to effect ‘ full safety standard’.Safety Supervision A competent inspector shall visit the area daily to assess the safety measures adopted. Any snag observed during his visit shall be notified to the supervisor present who immediately act to bring the safety measures to an acceptable standard In case of incident where utilities not identified are discovered or damaged, all work shall stop in the area and the Operator Shift Controller and HSE department immediately notifiedPhone number : Shift Controller Emergency Number HSE Direct number Employees working in easement area shall have a daily pre-task briefing that includes;Reporting of incidentsMethods of work and tools to be usedPotential hazards found in the Easement areasThe approved work method statementEPC Contractor and Civil Contractor HSE department shall participate in presenting the STARRT card briefing and monitor the activities to ensure that the work methods are being followed and all personnel have an understanding of the hazards associated with working adjacent to live process areasExcavation Work Permit- A copy of the work permit shall be posted on a mini board installed on site to be noticeable to all persons involved with the crossingBarricades, cones, markers, the night-lights, and floodlights etc. shall be installed as required for a complete safety. No oil spillage shall be allowed. Flagman-On all directions, in addition to the traffic sign boards, a flagmen shall be engaged full time to direct the traffic about the ‘excavation work in progress’ by ‘flag signal’ Hand Excavation- Excavation to expose the services shall be carried out manually.In case certain services not shown on the record drawings such as fibre optics but it is discovered, further excavation shall be ceased until a decision is taken for the method to be adopted for further excavationAccess to trench- The workers shall clearly be instructed to use only the ladders to enter in or come out of the trench. No jumping shall be allowedMachine ExcavationThe operators / drivers shall be explicitly instructed to abide by the requirement of the reverse signal and sound when operating reverse. Banksman shall be engaged equipment operation. No violation of the traffic rules shall be allowedMethodCorniche Road / Avenue ‘D Junction’Avenue ‘D’ is a 2-way road carrying single lane on either wayCorniche Street is a 2-way road with a central verge, carrying 2 lanes on either way on the West direction and without a central verge but single lane on the Eastern direction.The essential permit to work shall be obtained from the Refinery Division.The record drawings pertaining to the existing services shall be obtained.Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 190: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

190 of

A traffic management scheme has been presented herein and shall be produced on site as detailed on the attached sketch for this road crossing Pumping out water shall be carried out continuously in case it is necessaryExisting Services2 # serving electric poles are located one at the curve and the other in the Northern central verge which shall be effected by the proposed trench as the excavation line is expected to pass through the verge and the general impacts shall be to the extent of, “The central verge partly, the island partly, guard rail fully about 30 m with channels, Corniche street sign board, Kerb stones” The road shall be divided in 2 parts on either side of the carriageway.First InstanceThe first section covering the length of one pipe to be connected to the existing pipeline at South of the proposed road crossing shall be marked on the actual location. The work shall be carried out on part 1 diverting the traffic to the road portion on part 2 and on the existing natural ground at South as shown on the sketch. The asphalt shall be cut using jackhammersThe road section shall be excavated to the existing cables manually and the existence of the cables confirmed by the use of seaming. After the exposure of the cables, the Operating Authority authorities shall be invited to inspect and the cables diverted accordingly The cables shall be protected by PVC split pipe and covered, supported well temporarily. The machine excavation shall be carried out to the final levels.The excavated material shall be removed from the site to stockpile area.Appropriate bedding material shall be placed within the excavated trench to the correct service level, compacted and tested.The excavated trench shall be inspected by EPC ContractorThe GRE pipes shall be laid & the line tested by EPC Contractor. Backfill around the service pipes shall be carried out using the appropriate material. and compacted to the project specification requirement with the test results provided confirming the conformance The existing services shall be reinstated accordingly.General fill up to the underside of road formation shall be carried out in 150mm compacted layers using mechanical methods to the specification conformance.The finishing shall be carried out using approved asphalt mix.Second InstanceIn the second instance the work shall be carried out on part 2 diverting the traffic to the road portion on the completed part 1.The second instance shall commence only when the first is completed allowing the traffic to ply.All the aforesaid operations shall be repeated for the 2nd instance allowing the traffic on the completed Instance 1The traffic management system shall be removed after the road crossing is cleared of all debris or obstructions.Either side of the road X-ing shall be provided with relevant markers to indicate the servicesMajor EquipmentExcavator.Dump trucks.Compactors.Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 191: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

191 of

Jack Hammer, Compressor, hydro jetting (depending on necessity)AttachmentSketch showing the traffic management scheme

#76

Road crossing for laying84”GRE pair seawaterCooling linesAtAvenue ‘d’ / cornicheJunction Top

IndexScopeReference documentsDefinitionsResponsibilitiesSafetyMethod including traffic management schemeEquipmentAttachmentScopeThe statement is aimed to propose the procedures to be adopted to carry out the excavation at the road to facilitate to lay the pipe lines 1 # PAIR 84” GRE SEA WATER COOLING SUPPLY LINES at Avenue’D’ and ‘Corniche Road’ junction identified on the attached drawing to the following referencesReference documentsSpecification Excavation & Backfilling for Underground structures.Drawing No. Piping Interconnection Drawings- SeaWater Cooling Supply Lines DefinitionsPSM Project Site ManagerCSM Construction ManagerCS Construction SuperintendentStatements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 192: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

192 of

SE Site EngineerFM ForemanQC Quality ControlResponsibilitiesPSM shall control the overall operations CM shall arrange the resources required accordingly and be overall responsible for the excavation operationCS shall control, monitor and direct the SE, FM and workforce for the operationsSE shall be responsible for all the site operations and follow the instructions of the CSAny mishap on the excavation operation shall immediately be notified to the CS and the CM for the immediate action if so required for any possible remedy or record or the authority review whatsoever,the case may beFM shall execute the operations deploying the workforce. FM shall explain in full in the language the work persons understand about all the instruction and the ToolBox talks every day and check that the same are followed up regularlyQC shall inspect all the operations according to the specificationsEPC Contractor shall conduct surveillanceSafetyPrior to the commencement of any activity the labour force shall receive a Toolbox talk relevant to the operation concerned on the project site safety requirements. Any process is adopted having a particular safety risk shall be assessed and addressed as required to raise to a minimum standard / an acceptable mark.In the present case the excavation has to be carried out on the Operating Authority area, therefore all the regulated precautions shall be resorted to effect a full safety standard.ToolBox Talks While conducting ToolBox Talks, a representative from the authority shall be involved to witness and sign the instruction imparted with the workers prior to the commencement of the operations to make a record.Only English literate Foreman shall be employed to work on the excavation execution. Excavation Work Permit- A copy of the work permit shall be posted on a mini board installed on site to be noticeable to all the relevant persons involved on the crossingTraffic Management-Sign boards keep up-All the personnel shall be briefed about the safe keep up of the boardsBarricades,cones, markers and the night-lights, flood lights etc. shall be arranged as required for a complete safety. No oil spillage shall be allowed. The sides of the excavation shall be sloped with the barriers placed to indicate the excavation work in progressFlagman-On all the direction, in addition to the traffic sign boards, a flagman shall be engaged to operate full time to direct the traffic about the excavation work in progress by waving the flag for all the vehicles passing byHand Excavation- Excavation required to be by hand shall only be carried out manually. In case certain services not shown on the record drawings such as fibre optics cable is

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 193: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

193 of

discovered, the excavation shall be ceased to be continued until the decision to hydrojetting is taken up and the authority are involved.Jack Hammer- The worker engaged on operating this equipment shall use protective glass and work in phases with pause intervals. The compressor air pressure shall be monitored from time to time so that the hammer works smoothly. The compressor shall be place within the barricade limits Access to trench- The workers shall clearly be instructed to use only the ladders to enter in or come out. No jumping shall be allowedMachine ExcavationThe operators shall be explicitly explained and instructed about the requirement of the reverse signal and sound when operating reverse. The truck driver shall also be instructed similarly. Banksman shall be engaged while the equipment operate.No violation of the traffic rules shall be allowedDeep TrenchesSince the proposed excavation is wide and deep all the safety measures shall be resorted to and If required, the shoring shall be provided to prevent the caving in. The trench depth being more than 1200 mm.adequate means of exit such as Aluminium ladder or steps shall be provided and located no more than 8 m of lateral travel. Existing Services2 # electric poles and the other various categories of about 8 to 10 # running services ducts and the cables etc shall be properly diverted according to the regulatory requirement and preserved until reinstatedSafety SupervisionA competent inspector shall inspect the trench daily to assess the safety measures adopted. MethodThe required permit to work shall be obtained from the Plant Refinery Division.The record drawings regarding the existing services shall be obtained.A traffic management scheme has been presented herein and shall be produced on site as detailed on the attached sketch for this road crossing which includes, reduced speed sign, temporary diverted roads sign, men at work sign, warning signs, informatory signs, safety barriers, night lighting and road cleaning activities etc. The traffic management scheme shall be reviewed and approved by EPC Contractor prior to commencing the work.The aforesaid traffic management scheme shall be implemented as described below:TRAFFIC MANAGEMENT SCHEME ROAD CROSSING – Corniche Road / Avenue ‘D Junction’Drawing reference This proposed crossing is located on the Road Avenue ‘D’ between the followingCo-ordinates as shown on the referred drawing.Avenue ‘D’ is a 2-way road carrying single lane on either wayCorniche Road is a 2-way road with a central verge, carrying 2 lanes on either way on the West direction and without a central verge but single lane on the Eastern direction.2 # serving electric pole are located 1 at the curve and the other in the Northern central verge which shall be effected by the proposed excavation because of encroachment on the verge. Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 194: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

194 of

The central verge partly, the island partly, guard rail fully about 30 m with channels, Corniche street sign board, Kerb stones shall all be effected by the construction of the proposed road crossingThe road shall be divided in 2 parts as shown on the sketch as L1 and L 2 on either side of the carriageway.In the first instance the work shall be carried out on part L1 diverting the traffic to the road portion on the part L2 as shown on the sketch.In the second instance the work shall be carried out on part L2 diverting the traffic to the road portion on the completed road portion on the part L1 as shown on the sketch.The second instant shall be commenced only when the first has been completed and the traffic can ply.The directory signboards shall also be placed on the 1st street road East West on both ways to indicate the work at the crossingFor the traffic on both roads at’ 3’ locations bothways, the first reduce speed for traffic diversion informatory board depicting shall be located at 300 m from the point of the proposed crossing, the second depicting diversion signs be located at 200 m and the third depicting men at work sign be located at 100 m on either way in the opposite directions.A Flagman shall be engaged full time on both the directions to guide the traffic about the ongoing excavation operations in addition to the conventional signboardsThe following activities are involved to produce the Traffic Diversion Management SchemeTo excavate by hand and expose all the underground facilitiesVarious types of electrical, telecom and other services are running below and near the proposed crossingTrial pits to be excavated in size 5mx2mx1.5m deep by hand toolsTo seam the area with the detectors to ascertain the access to the cableTo expose the cable fully and to be inspected by the authorities / Operating AuthorityAfter the exposure, all the cables to be covered with split PVC pipe to continue the excavation mechanically according to the authority directions and as agreedTo excavate the remaining portion by the excavator machineTo have authority inspectionThe pipes to be laid by othersTo fill the bedding material according to the specification requirementTo reinstate the diverted servicesTo reinstate the central verge to the existing stateTo reinstate the CORNICHE ROAD board and the metallic rail guardDetailsThe Traffic Management Scheme shall be executed as explained in the foregoing and to the traffic manual directions.The first section of the proposed road crossing as per the attached sketch shall be marked by the surveyor on the actual location. All the existing services shall be identified from the Record drawings as well as by digging and measures to protect or divert temporarily resorted to according to the regulations.The asphalt shall be cut using jackhammersStatements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 195: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

195 of

The road section shall be excavated to the existing cables manually for which the trial pit may be made prior to the full manual excavation is proceeded and after ascertaining the safe procedures the exposures be completed.After the exposure of the cables, the Operating Authority authorities shall inspect and the cables be diverted accordingly following which the remaining machine excavation be carried out to the specified levels The excavated material shall be removed from the site to stockpile area.Appropriate bedding material shall be placed within the excavated trench to the correct service level. Where required, this bedding shall be compacted and tested.The excavated trench shall be inspected by the authorities as required.The GRE pipes shall be laid by others. Backfill around the service pipes shall be carried using the appropriate material. The service pipes surrounding material shall be compacted as per the project specification requirements. Test results shall be provided for the specification conformance verification.The existing services shall be reinstated accordingly.General fill up to the underside of road formation shall be placed in 150mm compacted layers using mechanical methods to the specification requirements.A concrete slab shall be cast up to the bottom of the finished asphalt level.The finishing shall be carried out using approved asphalt mix.The traffic management system shall be removed after the road crossing has been cleaned of any debris or obstructions.Either side of the road X-ing shall be provided with markers to indicate the servicesMajor EquipmentExcavator.Dump trucks.Compactors.Jack Hammer, Compressor, hydro jetting (depending on necessity)AttachmentSketch showing the traffic management scheme Drawings including the traffic diversion#77

Tennis courts surfacingTop

IndexScopeReference documentsDefinitionsResponsibilitiesSafetyMethod EquipmentAttachment

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 196: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

196 of

ScopeThe statement is aimed to propose the procedures to be adopted to carry out the Surfacing on 2 #s Tennis Courts located in the CampReference documentsDrawing No. DefinitionsPSM Project Site ManagerCSM Construction ManagerCS Construction SuperintendentSE Site EngineerFM ForemanQC Quality ControlResponsibilitiesPSM shall control the overall operations CM shall arrange the resources required accordingly CS shall control, monitor and direct the SE, FM and workforce for the operationsSE shall be responsible for all the site operations and follow the instructions of the CSFM shall execute the operations deploying the workforce. FM shall explain in full in the language the work persons understand about all the instruction and the ToolBox talks every day and check that the same are followed up regularlyQC shall inspect all the operations according to the specificationsEPC Contractor shall conduct surveillanceSafetyPrior to the commencement of any activity the labour force shall receive a Toolbox talk relevant to the operation concerned on the project site safety requirements. Any process adopted having a particular safety risk shall be assessed and addressed as required to raise to a minimum standard / an acceptable mark.The workers shall take all the precautions to avoid the skin and the eye contacts by using the safety glasses, hand gloves, the uniform, gun shoes all according to the manufacturer’s instructions. Immediate medical attention shall be provide when requiredSafety SupervisionA competent inspector shall visit the area daily to assess the safety measures adopted. Any snag observed during the inspection shall be notified to the supervisor present who immediately act to bring the safety measures to an acceptable standardStorageThe bags shall be stored in a cool shaded area prior to use

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 197: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

197 of

MaterialMBT proprietary materialConcresive 1414 MasterTop 512 Concresive 1414 is a 2 parts epoxy bonding agentMastertop 512 is a ready to use non-metallic and non oxidising synthetic mineral aggregate and cementitious product applied as a topping onto the existing new concrete slab as a hard durable wearing course. 10 to 12 mm thick. Total surface area of the Tennis Courts 2 # 930 m2MethodThe following operations are involved to carry out the surfacingSubstrata preparationPriming and BondingMixing and ApplicationCuringDetailsThe area shall be closed to all persons except the workers and other personnel The surface of concrete shall be cleaned of all contamination such as oil, grease or fat which be removed before the preparations are commenced withHigh pressure water jetting shall be used to prepare the concrete surface to a coarse texture ensuring all weak or friable concrete be removed along with the contaminantsThe concrete is already more than 28 daysOil free Compressed air shall be used to remove dust making the surface clean & dry The surface shall be primed with Concresive 1414 ensuring total coverage of the surfaceA forced action Mixall mixer shall be used to mix Mastertop 512 according to the manufacturer’s instructionsThe content of the bag shall be poured into the mixer followed by blending for about 30 seconds, thereafter slowly adding 2.3 to 2.4 litres of water per 25 kg bag allowing to mix for 3 minutesIn hot weather chilled clean water shall be used for mixingThe primed surface shall be prepared to be guided for the proposed profile formation by using timber / wooden straightedge battens 10 mm thickThe mixed mortar shall have a plastic consistency exhibiting low slump which be evenly spread over the primed surface already prepared as expressed in the foregoingA straightedge shall be used to systematically tampen and level the Mastertop 512.The floating material shall be pressed firmly on the primed surface using a wooden float to produce the material evenly spread and compactedA steel trowel shall be used to carry out the finishing.CuringThe curing shall be carried out immediately after the final trowelling operation has been completed by either covering with polythene sheets or by the application of Masterkure 181 applied at a rate of 1 litre per 5 m2

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 198: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

198 of

All the surfaces shall be protected from traffic until hardened( for light traffic the limit is 24 hours and for heavy 72 to 96 hours )Major EquipmentCompressor, Mixer, Air BlowerJack Hammer, Compressor, hydro jetting (depending on necessity)AttachmentMBT Method Statement#78

Precasting lighting poles foundations Top

IndexScopeReference documentsDefinitionsResponsibilitiesSafetyMethod EquipmentAttachmentScopeThe statement is aimed to propose the procedures to be adopted to carry out the pre casting, transporting and installing on exact site locations the street lighting poles foundation bases 319 #Reference documentsDrawing No. Specification DefinitionsPSM Project Site ManagerCSM Construction ManagerCS Construction SuperintendentSE Site EngineerFM ForemanQC Quality ControlResponsibilitiesPSM shall control the overall operations CM shall arrange the resources required accordingly CS shall control, monitor and direct the SE, FM and workforce for the operationsSE shall be responsible for all the site operations and follow the instructions of the CSFM shall execute the operations deploying the workforce. FM shall explain in full in the

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 199: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

199 of

language the work persons understand about all the instruction and the ToolBox talks every day and check that the same are followed up regularlyQC shall inspect all the operations according to the specificationsEPC Contractor shall conduct surveillanceSafetyPrior to the commencement of any activity the labour force shall receive a Toolbox talk relevant to the operation concerned on the project site safety requirements. Any process adopted involving a particular safety risk shall be assessed and addressed as required to raise to a minimum standard / an acceptable mark.All the safety precautions required to be adhered to while working on the excavations, blinding, forms, rebars, concrete pouring, waterproofing etc.all according to the acceptable standards shall be adopted on the operations concernedAdequate safety shall be observed during lifting and offloading the precast foundations to the relevant locations to avoid any mishap BY OBSERVING THE REGULATORY CRANE FITNESS REQUIREMENT AND VALIDITY OF PERMIT. Only competent personnel shall be engaged to carry out the operationThe crane and the trailer operators shall adhere to all the traffic rules while carrying out the operations and if so required, a banksman be engaged to direct the movementThe crane shall not be operated during the inclement weather conditions with dust storms Immediate medical attention shall be provide as and when requiredSafety SupervisionA competent inspector shall visit the area daily to assess the safety measures adopted. Any snag observed during the inspection shall be notified to the supervisor present who immediately act to bring the safety measures to an acceptable standard MaterialConcrete, Rebars / Lifting Lugs, Anchor Bolts, 100 mm dia 350 internal radius PVC Cable Duct etc.MethodPre casting Area-The existing yard being used for the pre casting of manholes, catch basins etc. shall be employed for this purpose alsoThe following operations are involved to carry out the production of the light poles foundation basesPre installation operationsTo fabricate and erect the side forms 4 #s to the specified dimensionsTo fabricate the rebars according to the specified detailsTo provide the non critical cathodic protectionTo provide the PVC cable ductTo provide the bolt assesmbly to the requirement and locationTo provide the lifting lugs to carry a gravity load of at least 3 tonnes + handling stressesTo pour the concreteTo cure the concrete immediately after pouring

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 200: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

200 of

Post casting operationsTo cure for the specified periodTo excavate the location to the required formation levelTo blind the area to be founded with concreteTo waterproof the blinding as specifiedTo keep the area ready in all respects well oriented & aligned to receive the foundation directly to be offloadedTo apply the water proofing membrane around as specifiedTo provide the protection board as specifiedTo back fill the surrounding space to the relevant grade levelDetailsThe typical size of the foundation is 1000x1000mm in plan and 1100mm deep According to the drawing 319 # are specified to be constructed for a quantity 351 m3A possible of 10 units shall be produced by pre casting every day on an averageThe forms to the exact size with the preformed chamfers shall be prepared and erected The steel rebars shall be cut, bent to the required shape, placed and the cage prepared holding 75mm concrete spacers, be positioned into the forms.1 # 350 mm internal radius 100 mm dia PVC cable duct formed to the dimensions shall be anchored by binding wires to the exact locations shown on the drawing keeping the upper end flush with the concrete topThe Lifting lugs as shown on the sketch shall be fixed in to the correct locations The forms for the block outs for the lifting lugs shall be fixed in to the correct locations as shown without clashing with the duct or the rebars allowing a protrusion of the hook The bolt assembly shall be fixed in exact position according to the design detailsThe non-critical cathodic protection shall be arranged using a metallic continuous binding wire connecting all the horizontal rebars terminating into a boss fixed at one location near the top in the middle of the side opposite the duct carrying portionAll the supports and the dimensions shall be checked and the plumb monitoredCivil Contractor QC inspection shall be conducted followed by the EPC Contractor inspectionThe concrete shall be poured to all the prepared units in 3 layers in vertical sequenceThe appropriate vibrator shall be used for the compaction of the concrete During concreting, care shall be taken to keep the anchor bolts’ position undisturbed and the intermittent checks be continuously made to monitor the spacing / centres between the boltsAfter the concrete is poured in full & well compacted, the surface shall be levelled using a wooden float followed by light steel trowelImmediately after the concrete starts setting, approved curing compound shall be sprayed on the surface forming a continuous membrane which be covered over with a polythene sheet according to the specificationsAfter 2 hours, the polythene sheet shall be temporarily removed to spread over the concrete surface the saturated burlap cloth or hessian, and recovered immediately The side forms shall be removed within the specified period The vertical concrete surfaces shall be spread with the curing compound immediately after striking the forms and covered with the polythene sheet according to requirementThe curing shall be continued for the specified periodStatements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 201: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

201 of

The relevant locations shall be made ready to receive the precast units by completing the excavation, blinding, the horizontal waterproofing and forming the correct alignment Civil Contractor QC inspection shall be conducted for the’location to receive followed by EPC Contractor approvalThe unit shall be lifted by a mobile crane, loaded gently onto a trailer and transported to the location for offloading on to the prepared ‘location to receive’ the unitThe unit shall be installed on the marked location according to the correct orientation to the lighting layout drawingCivil Contractor QC inspection shall be conducted followed by EPC Contractor approvalThe protruding lifting lug eyes shall be cut to 60 mm inside the block out, the void filled with concrete by first scabbling the internal surface followed by cement slurry grouting and pouring concreteThe external surfaces of the foundation shall be applied with the concrete protective membrane according to the specificationsCivil Contractor QC inspection shall be conducted followed by the EPC Contractor approvalThe membrane protection board shall be provided covering the surface to the specified detailsThe back filling shall be carried out according to the specification upto the required levels in layers and upto the required ground grade or the pavement The points to locate the cathodic protection shall be provided with a marker to trace the bossThe sequence shall be repeated for all the lighting poles foundationsMajor EquipmentCompressor, Mobile Crane, TrailerConcrete Pump, Transit mixerAttachmentLifting arrangement sketch#79

Lighting poles foundations Top

IndexScopeReference documentsSafetyMethod EquipmentAttachmentScopeThe statement is aimed to propose the procedures to be adopted to carry out the pre casting, transporting and installing on exact site locations the street lighting poles foundation bases 319 #

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 202: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

202 of

Reference documentsDrawing No. Specification SafetyPrior to commencement of any activity, the labour force shall receive a STARRT Card / Toolbox talk relevant to the operation concerned on the project site safety requirements. Necessary measures shall be applied to any process involving a safety riskAll safety precautions necessary during working on excavations, blinding, forms, rebars, concrete pouring, concrete protection etc. shall be applied to acceptable standards Adequate safety measures shall be adhered to during lifting and offloading precast foundations to relevant locations avoiding any mishap BY OBSERVING THE REGULATORY CRANE FITNESS REQUIREMENT AND VALIDITY OF PERMIT.Only competent personnel shall be engaged to carry out the operationCrane and trailer operators shall abide by all traffic rules while carrying out operations and if so required, a banksman shall be engaged to direct the movementThe crane shall not be operated during the inclement weather conditions with dust storms Safety SupervisionA competent inspector shall visit the area daily to assess the safety measures adopted. Any snag observed during his visit shall be notified to the supervisor present who immediately act to bring the safety measures to an acceptable standard MaterialConcrete, Rebars / Lifting Lugs, Anchor Bolts, 100 mm dia 350 internal radius PVC Cable Duct, Bitustick XL, Masterseal 300HMethodPre casting Area- the existing yard being used to pre cast manholes, catch basins etc. shall be employed for this purpose alsoThe following operations are involved to carry out the production of the lighting poles foundation basesPre installation operationsThe typical size of the foundation is 1000x1000mm in plan and 1100mm deep According to drawing 319 # are specified to be constructed (quantity 351 m3)On an average 10 units shall be produced by pre casting every day The forms to the exact size with the preformed chamfers shall be prepared and erected The steel rebars shall be cut, bent to the required shape, placed and the cage prepared holding 75mm concrete spacers, and positioned into the forms.1 # 350 mm internal radius 100 mm dia PVC cable duct formed to the dimensions shall be anchored by binding wires to the exact locations shown on the drawing keeping the upper end flush with the concrete topThe Lifting lugs as shown on the sketch shall be fixed in at the correct locations The forms for the block outs for the lifting lugs shall be fixed in at the correct locations as shown without clashing with the duct or rebars allowing a protrusion of the hook Bolt assembly shall be fixed in at exact position according to the design details

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 203: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

203 of

Non-critical cathodic protection shall be arranged using a metallic continuous binding wire connecting all the horizontal rebars terminating into a boss fixed at one location near the top in the middle of the side opposite the duct carrying portionAll the supports and dimensions shall be checked, corrected if required and the plumb monitoredAn Civil Contractor QC inspection shall be conducted at regular intervals throughout the operationsThe concrete shall be poured to all the prepared units in 3 layers in vertical sequenceThe appropriate vibrator shall be used for the compaction of the concrete During concreting, care shall be taken to keep the anchor bolts’ position undisturbed and the intermittent checks be continuously made to monitor the spacing / centres between the boltsAn Civil Contractor QC inspection shall be conducted prior to concrete pour & ITP signed offAfter the concrete is poured in full & well compacted, the surface shall be levelled using a wooden float followed by light steel trowelCuring Immediately after the concrete is finished, the surface shall be covered with polythene sheet with the edge lapped or tied down to exclude air circulation without permitting the membrane to be in touch with concrete surface according to the specificationsAfter the concrete has stiffened but no longer than 2 hours, the polythene sheet shall be removed followed by immediate covering the surface with saturated( soaked with mix quality water) hessian and recovered with polythene sheet to prevent evaporation from the hessian. Throughout the curing period, the hessian shall be maintained in a permanent wet condition using mix quality water The side forms shall be removed after the specified period of 24 to 36 hours as agreedThe vertical concrete surfaces shall be draped with the saturated hessian immediately after striking the forms and covered with the polythene sheet held firmly in place along all edges & kept continuously wet for duration of curing The curing shall be continued for the specified period An Civil Contractor QC inspection shall be conducted from time to time throughout the operationsInstallation operationsThe relevant locations shall be made ready to receive the precast units by completing the excavation, blinding, the concrete protection and forming the correct alignment AN Civil Contractor QC inspection shall be conducted for the'location to receive' & ITP signed offThe unit shall be lifted by a mobile crane, loaded gently onto a trailer and transported to the relevant area to offload on to the prepared ‘location to receive’ The unit shall be installed on the marked location according to the correct orientation to the lighting layout drawingAN Civil Contractor QC inspection shall be conducted The protruding lifting lug eyes shall be cut to 60 mm inside the block out, the void filled with concrete by first scabbling the internal surface followed by cement slurry grouting and pouring concrete

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 204: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

204 of

The below ground surfaces of the foundation shall be applied with concrete protective membrane according to the specificationsAN Civil Contractor QC inspection shall be conducted The membrane protection board shall be provided covering the surface to the specified details. The backfilling shall be carried out in layers according to the specification upto the required levels The points to locate the cathodic protection shall be provided with a marker to trace the boss. Top surface of the foundation shall be applied with above ground concrete protection as specifiedEPC Contractor surveillance / inspection / approval shall be according to the approved ITPsMajor EquipmentCompressor, Mobile Crane, TrailerConcrete Pump, Transit mixerAttachmentLifting arrangement sketch#80

Sea water surge basinConcrete protection master seal 550Top

IndexScopeReference documentsDefinitionsResponsibilitiesSafetyMaterialMethod EquipmentAttachmentScope This statement is aimed to present the proposed procedures to be adopted to apply the specialist protection coating material on the internal concrete surfaces (shown on the drawings by cross hatching) of the sea water surge Basin according to the specifications.ReferencesDrawings Specifications Master seal 550-product data sheet

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 205: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

205 of

-Protection to concrete SurfacesDefinitionsPSM Project Site ManagerCSM Construction ManagerCS Construction SuperintendentSE Site EngineerFM ForemanQC Quality ControlResponsibilitiesPSM shall control the overall operations CM shall arrange the resources required accordingly CS shall control, monitor and direct the SE, FM and workforce for the operationsSE shall be responsible for all the site operations and follow the instructions of the CSFM shall execute the operations deploying the workforce. FM shall explain in full in the language the work persons understand about all the instruction and the toolbox talks every day and check that the same are followed up regularlyQC shall inspect all the operations according to the specificationsEPC Contractor shall conduct surveillanceSafetyPrior to the commencement of work, the labour force shall receive a tool box talk on the Project Site Safety requirements. Any process adopted which may involve a particular Safety risk, shall be assessed to the requirement for Site conditions and be taken care of. Scaffolding shall be erected to afford access to the working personnel according to the project requirements. Hand rails ladders and the toe boards shall be fitted and inspected prior to use. During mixing and application of master seal 550, personnel protective equipment shall be used i.e. overalls, goggles, gloves (to avoid material contact to eyes, mouth and skin)Material storage / disposal of used containers / waste materialMaterials shall be stored out of direct sunlight clear of ground and protected from rainfall.Used containers shall be collected and disposed off according to the state regulations. Medical attention shall immediately be made available as and when requiredMaterialsCoating, Masterseal 550Master seal 550 is a two component acrylic modified cementitious coating that requires only site mixing to form an ideal product to waterproof, resurface concrete, masonry and most other construction materials. Simply applied by stiff brush, roller or trowel it forms a waterproof and flexible coating providing an effective barrier to waterborne salts and atmospheric gases.MethodThe method involves the following sequences in general.Surface preparation MixingApplicationTo keep up the exact coverage to form 1 mm thick coating an area of 11 m2 shall be marked on the concrete surface. The contents of the bag shall be applied on this area onlyStatements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 206: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

206 of

At JointsThe material coating shall terminate at the joints (Refer to the attached sketch) which are to be treated with sealant. The part of the coating that has to be embedded into the joint sealant shall be applied first followed by the major area on the panel be coated thereafterDetailsAll grease, oil, dust, residual curing compound, mould release agent or other contaminants which could impair adhesion shall be removed from the surface by degreasing and washing.Arrises shall be rounded off and the surface protrusions ground down to ensure smooth substrataThe whole surface to be coated shall be cleaned using water jetting from a distance of 2 to 3 m from the panel surface and visually inspected to ensure that the required degree of roughness has been achieved which be evident at a stage when the aggregate be exposed on the surface.All the holes, voids, depressions, spalls etc. shall be filled with Masterseal 550 mixed to a trowel consistency, scraped lightly into the surface, allowed to dry and later roughened by hand wire brush on the small areas and gently water jetted on the larger areas.The filled areas shall be visually inspected to ensure that the correct mechanical key is formed.MixingMaster seal supplied in the pre-measured units shall be mixed on site using clean containers. The powder shall be slowly added to the liquid component and agitated / mixed for 2 minutes using a slow speed hand power drill fitted with a suitable paddle attachment until a homogeneous lump free consistency is obtained.The mix quantity shall be such that it could be consumed in one hour during application without allowing any retempering with water.ApplicationCoverage 1.8 Kg / sqm at 1 mm thicknessThe material shall be 1 mm thick applied in one coatIn hot weather the surface to be coated shall be shaded from direct sunlight. The prepared surface area to be coated shall be saturated with fresh and clean water Civil Contractor QC inspection shall be conducted followed by EPC Contractor approvalThe material shall in no case be applied on the dry surfaceThe mixed material shall be applied while the surface is visibly damp without standing water using short stiff brush or roller with short hair. (Roller shall be used in major / large areas)The evenness and the thickness of the applied coating shall be regularly ascertained by the consumed quantity to the applicable ratio of 11 m2 each container during application while the material is still wet.The coverage of 11-m2 surface shall be the evidence for the actual formation of 1-mm thick coating.The material shall be allowed to dry and visually inspected Civil Contractor QC inspection shall be conducted followed by EPC Contractor approvalAny missed areas shall be saturated and then touched up.No curing shall be carried outStatements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 207: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

207 of

EquipmentWater tanker with water jetting arrangementHard brushes for minor areasClean containerSlow speed drill with paddle attachmentStiff brush / RollerAttachmentMasterseal 550 Data sheet and statementTypical sketch for joint for guidance purpose#81

Concrete coating of structures using masterseal 550Top

IndexScopeReference documentsSafetyMaterialMethod EquipmentAttachmentScope This statement is aimed to propose the procedures to be adopted to apply the specialist protection coating material on those concrete surfaces requiring special protection e.g. The interior of Sea water Surge basin & Collection SumpsReferencesSpecifications Master seal 550-product data sheetProtection to concrete SurfacesSafetyPrior to the commencement of work, the labour force shall receive a STARRT card / Tool box talk relevant to the operation concerned on the Project Site Safety requirements. Necessary measures shall be applied to address any risk involved on any processTagged scaffolding shall be erected to afford access to the working personnel Personnel working on sand blasting & mixing and application of master seal 550, shall wear overalls, gloves, safety glasses and masks Used containers shall be collected and disposed off according to the state regulations.

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 208: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

208 of

MethodJoints - The material coating shall terminate at the joints to be treated with sealant. As shown on the attached sketchThe part of the coating to be embedded into the joint shall be applied first to permit sealant application followed by the major area on the panel to be coated thereafterSurface preparation Arrises shall be rounded off and protrusions ground down to ensure smooth substrataThe whole surface to be coated shall be lightly sand blasted & visually inspected to ensure that the required degree of roughness has been achieved.All holes, voids, depressions, spalls etc. shall be filled with Masterseal 550 mixed to a trowel consistency, scraped lightly into the surface, allowed to dry and later roughened by hand wire brush on small areas and lightly sand blasted on larger areas.The filled areas shall be visually inspected to ensure that the correct mechanical key is formed.MixingMaster seal supplied in the pre-measured units shall be mixed on site using clean containers. The powder shall be slowly added to the liquid component and agitated / mixed for 2 minutes using a slow speed hand power drill fitted with a suitable paddle attachment until a homogeneous lump free consistency is obtained.The mix quantity shall be consumed in one hour during application without allowing any retempering with water.ApplicationCoverage 1.8 Kg / sqm at 1 mm thicknessOne coat application shall be 1 mm thickIn hot weather the surface to be coated shall be shaded from direct sunlight. An area of 11 m2 shall be marked on Concrete surface to consume 1 bag content to produce 1 mm thick coating. Prepared surface area to be coated shall be saturated with fresh and clean water Civil Contractor QC inspection shall be conducted Material shall in no case be applied on the dry surfaceMixed material shall be applied on the visibly damp surface without standing water using short stiff brush or roller with short hair. (Roller shall be used in major / large areas)Evenness and the thickness of the applied coating shall be regularly monitored relating the consumed quantity @ 11 sqm / bag during application while the material is still wet.Applied material shall be allowed to dry and visually inspected Civil Contractor QC inspection shall be conducted and the ITP signed offAny missed areas shall be saturated and then touched up.No curing shall be carried outField samples shall be taken to confirm 1mm thick coating has been appliedEquipmentSand blasting packageCompressorsClean containerSlow speed drill with paddle attachmentStatements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 209: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

209 of

Hard brushes for minor areasStiff brush / RollerAttachmentMasterseal 550 Data sheet and statementTypical sketch for joint (for guidance)#82

Above ground concrete protection Seawater surge basinTop

IndexScopeReference documentsDefinitionsResponsibilitiesSafetyStorageMaterialMethod EquipmentAttachmentScope This statement is aimed to propose the procedures to be adopted to form a protection coating on the above ground RCC walls’ external faces as well as on the internal surface areas other than those where Masterseal 550 shall be appliedReferencesDrawing Specifications Master seal 300 H-product data sheetMaster seal 181 S-product data sheetProtection to concrete SurfacesMAR for Masterseal300 HMAR for Masterkure 181DefinitionsPSM Project Site ManagerCSM Construction ManagerCS Construction SuperintendentSE Site EngineerFM ForemanQC Quality ControlStatements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 210: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

210 of

ResponsibilitiesPSM shall control the overall operations CM shall arrange the resources required accordingly CS shall control, monitor and direct the SE, FM and workforce for the operationsSE shall be responsible for all the site operations and follow the instructions of the CSFM shall execute the operations deploying the workforce. FM shall explain in full in the language the work persons understand about all the instruction and the toolbox talks every day and check that the same are followed up regularlyQC shall inspect all the operations according to the specificationsEPC Contractor shall conduct surveillanceSafetyPrior to the commencement of work, the labour force shall receive a tool box talk on the Project Site Safety requirements. Any process adopted which may involve a particular Safety risk, shall be assessed to the requirement for Site conditions and be taken care of. Scaffolding with the hand rails, the ladders and the toe boards fitted and inspected prior to use shall be erected to provide access to the working personnel according to the project requirements. Only tagged scaffolding comprising all the guard rails foot rails etc. shall be used for the work at heights according to safety requirements. The personnel shall use protective clothing, gloves eye protection glasses, masks etc., for to avoid skin contact.Plenty of clean water shall be available all the time. Medical attention shall be available all time to treat the adverse effects. Transportation shall be available to move the effected personnel to the hospital should the circumstances so require.Material storage / disposal of used containers / waste materialThe material shall be stored under cover out of direct sunlight clear of ground, protected from rainfall as well as temperature extremes. Product shelf life is 12 months subject to proper storageCare shall be taken during use and storage to avoid contact with eyes, mouth, skin and foodstuffs. The containers shall be resealed after use.Immediate medical attention shall be called for in case of any adverse effect to the personnel handling the productDamaged tins shall be disposed off according to the state regulations.MaterialMaster Builder Technology ProductMasterseal 300H - an acrylic based, elastomeric decorative, flexible, anti-carbonation and waterproof protective coating designed for the protection of concrete structures against carbonation and chloride ingress.Masterseal 181S- primer system

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 211: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

211 of

Masterseal 300 H fillerMethodThis application involves the following sequencesCleaning and making up the surfacePriming the surfaceCoating the surfaceDetailsPreparationAll surfaces shall be free from oil; grease, friable matters and curing compound. The surfaces shall be cleaned from dust / sand using compressed air. Arrises shall be rounded off and the protrusions ground so that the resulting surfaces appear smooth.The surfaces shall be brush primed with Masterkure 181S and subsequently Masterseal 300H mixed with Masterseal 300 H filler applied as a scrape coat over blowholes and depressions.The primed surface shall be allowed to dry tack free for a minimum duration of 2 hours before applying Masterseal 300H coating.ApplicationMasterseal 300 H shall be applied directly from the containers using a brush or roller @ 0.8 litre per sqm surface coverage to achieve a continuous coating The continuous coating may be achieved in 1 or 2 coats of applicationThe coating shall be protected from the rain and humidity for 24 hours / until it dries out using polythene sheets keeping off the area.The coating shall be applied when the humidity is less than 90 %The coating shall not be applied in the dusty weather conditionsNo post application curing is requiredThe areas to be coated shall be protected from direct sunlight by net shading in the hot weather conditions and the ambient temperature be more than 5 degree Celsius.EquipmentBrush RollerAttachmentMBT datasheet & Statement#83

Sea water surge basinjoint seal

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 212: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

212 of

Top

IndexScopeReference documentsDefinitionsResponsibilitiesSafetyMethod EquipmentAttachmentScope This statement is aimed to present the proposed procedures that shall be adopted to apply the sealant to fill the joints formed in the walls and the base. This statement shall be construed in conjunction with Method Statement # approved / IFC vide Transmittal site-including an alternative to this document. Any of the 2 methods may be used for the joint treatment according to the convenience on siteReferencesSpecifications DefinitionsPSM Project Site ManagerCSM Construction ManagerCS Construction SuperintendentSE Site EngineerFM ForemanQC Quality ControlResponsibilitiesPSM shall control the overall operations CM shall arrange the resources required accordingly CS shall control, monitor and direct the SE, FM and workforce for the operationsSE shall be responsible for all the site operations and follow the instructions of the CSFM shall execute the operations deploying the workforce. FM shall explain in full in the language the work persons understand about all the instruction and the toolbox talks every day and check that the same are followed up regularlyQC shall inspect all the operations according to the specificationsEPC Contractor shall conduct surveillanceSafetyPrior to the commencement of work, the labour force shall receive a tool box talk on the Project Site Safety requirements. Any process adopted which may involve a particular Safety risk shall be assessed to the requirement for Site conditions and be taken care of.

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 213: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

213 of

Scaffolding with the hand rails, the ladders, the toe boards fitted and inspected prior to use shall be erected to provide access to the working personnel according to the project requirements. Only tagged scaffolding comprising all the guard rails foot rails etc. shall be used for the work at heights according to safety requirements. Material storage / disposal of used containers / waste materialMaterials shall be stored out of direct sunlight clear of ground and protected from rainfall.Used containers shall be collected and disposed off as per project requirements.

Medical attention shall immediately be made available as and when requiredThe personnel shall use the PPE, gloves, masks, eyeglasses etc, and to avoid skin contact. use of barrier cream shall also be made.Hands shall be cleaned by Industrial cleaner followed by washing with soap and water.Material safety data shall be referred to for disposal and any further information.A safety inspector shall visit the site every day and instruct the supervisor in case any snag is observed who immediately implement the instructions accordingly.StorageThe material shall be stored under cover out of direct sunlight and protected from extreme temperatures. Shelf life 12 months between 5 deg and 35 CelsiusMaterialsDe-bonding tape (to be applied before priming)Sealant Masterflex 700 (High performance, elastomeric joint sealant)Masterflex Primer # 1Masterflex 700 is a high grade, synthetic rubber sealant possessing outstanding resistance to deterioration due to weathering, ozone, ultra violet light and attack by chemicals present in industrial atmospheres. The product has the capability to withstand repeated cycles of compression and extension over a wide range of tempertaure range and has excellent adhesion properties to all materials employed in buildingsSupplied in pouring and gun grade for horizontal and vertical joints respectivelyMasterflex Primer # 1 is meant for porous surfaces such as concrete and masonry Coverage Joint depth 25 mm, width 25 mm, Filling length 1.6 m per litrePackages 3 litres sealed containers MethodThis following operational sequences shall be involvedPre application activityThe corner area to be embedded into the sealant to be made ready with Master seal 550Refer to Method Statement # 93ApplicationPreparation of the surface required to be sealedTaking the filler board to the required depthCleaning the surface and applying the de-bonding tapePriming the surfacesApplication of the sealant up to the profile shownStatements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 214: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

214 of

DetailsThe joint area shall be prepared according to the sketch and the site conditions.The filler shall be trimmed the the specified depth All surfaces shall be cleaned of dust and contaminants using wire brush and made dry.Civil Contractor QC inspection shall be conductedThe debonding tape shall be fixed as shown on the sketchThe surface shall be primed using brush according to the instructions given on the primer tinsThe primer shall be allowed to dry to a tack free state before Masterflex 700 is applied within 3 hours maximum to avoid reprimingMixingOne complete unit shall be mixed at one time without subdivisionMixing shall be carried out for 5 to 10 minutes using a paddle fitted 500 rpm electric drillA palette knife shall be used to scrap the container surface intermittently to ensure that all curing agent be completely blended with the base compound.The material shall immediately be used after mixingApplication The material shall be applied using a sealant gun fitted with conical nozzles adjustable to suit the joint width by cuttingThe sealant shall be gunned into the joint using an even trigger pressure and cleaning the nozzle occasionally to avoid contamination. Deep joints shall be filled in 2 runs to prevent air entrapmentA smaller timber spatula soaked in soapy water shall be used to compact the sealant into the joint for a smooth polish finish formation. The mixing and application equipment shall be cured immediatelyEquipmentPaddle mixerSealant gunAttachmentManufacturer’s statement#84

Painting Sub stationsTop

IndexScopeReference documentsDefinitionsResponsibilitiesSafetyStatements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 215: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

215 of

Method EquipmentAttachmentScope This statement is aimed to present the proposed procedures that shall be adopted to apply the Painting System on the above building on RCC surfaces, Galvanised surfaces,Metal surfaces, Dry wall partition and the plastered surfaces according to the specifications and the material system approved. A brief regarding the proposed surfaces has been mentioned below Concrete General Wall Surfaces- Textured Epoxy CoatingEquipment Enclosure External Concrete Walls at grade level- Textured Epoxy CoatingColumn Faces Features –50mm projection from general wall face with central vertical rebate- Smooth Epoxy coating & finishedFace-horizontal band finish-50mm projection beyond wall face. Top horizontal edge to be splayed at 45 degree-Smooth epoxy coating & finished Vertical ribs fair face concrete face- Smooth epoxy coating & finished

Electrical Equipment / HVAC / Battery / Air Lock- Walls- High Build Washable Acrylic EmulsionCeilings- High Build EmulsionSteel doors external- PolyurethaneGalvanised external- PolyurethaneReferencesNotes on the Drawings & the Finishing ScheduleSpecifications MAR # Berger Paint SystemsDefinitionsPSM Project Site ManagerCSM Construction ManagerCS Construction SuperintendentSE Site EngineerFM ForemanQC Quality ControlResponsibilitiesPSM shall control the overall operations CM shall arrange the resources required accordingly CS shall control, monitor and direct the SE, FM and workforce for the operationsSE shall be responsible for all the site operations and follow the instructions of the CSFM shall execute the operations deploying the workforce. FM shall explain in full in the language the work persons understand about all the instruction and the ToolBox talks every day and check that the same are followed up regularlyQC shall inspect all the operations according to the specifications

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 216: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

216 of

EPC Contractor shall conduct surveillanceSafetyPrior to the commencement of work, the labour force shall receive a Toolbox talk relevant to the operation concerned to the Project Site Safety requirements. Any process that is adopted which may have a particular Safety risk shall be assessed to the requirement for Site conditions and be taken care of. The personnel shall use the PPE, gloves, masks, eyeglasses etc and to avoid skin contact. use of barrier cream shall also be made.Material safety data shall be referred to for disposal and any further information.Adequate arrangement shall be made to provide access to the top of the wall.Adequate scaffolding with proper netshade shall be provided wherever requiredThe personnel shall use the waist safety belt / harness while working on height.Immediate medical care shall be provided in case the eyes of any personnel are effected due to the paint splashes or any other reasonProper ventilation shall be provided to let the workers respirate properlyA safety inspector shall visit the site every day and instruct the supervisor in case any snag is observed who immediately implement the instructions accordingly.StorageThe material shall be stored under cover out of direct sunlight and protected from extreme temperatures. Shelf life 12 months between 5 deg and 35 CelsiusMaterialsSpecified: Texotile from Jotun or EquivalentApproved:Berger Paint systemsMAR # dated 27.1The following table provides the details of the approved systems but the appropriate relevant system shall be followed according to the scope of the work.Appropriate arrangement adjustment shall be made for the Textured and the smooth surface applications to the manufacturer’s specifications / instructions Column head –50-mm epoxy coating shall be separately statedTable 15S # Sub Strata Surface preparation Operating

temperature1 Galvanised steel-

Exterior,PolyurethaneMechanical cleaning to remove loose deposits

Upto 100 deg C

2 Mild steel-Exterior, Polyurethane

Blasting to Sa 2.5 Upto 100 deg C

3 Concrete Surface- Exterior, Polyurethane textured

Cleaning with sand stone to smoothen the surface free from all dirt etc

Upto 100 deg C

4 Galvanised Steel-Interior, Alkyd

Mechanical cleaning to remove loose deposits

Upto 60 deg C

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 217: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

217 of

5 Galvanised Steel-Interior, Primed ferrous metal Alkyd

Mechanical cleaning to Sa 2 to remove loose rust, scales

Upto 60 deg C

6 Plaster and Gypsum-Gypsum wall board and plaster, Acrylic

Cleaning with fine emery paper to remove dirt etc.

Upto 50 deg C

System # 1, Exterior Surfaces –Galvanised Steel, PolyurethaneTable 16Coats Generic

Type# of coats

Solids volume %

DFTMicrons

Colour Application

Berger Product

Primer Surface tolerant high build epoxy

1 82 100 Aluminium

Brush / Spray

Epimastic 5100 Al

Finish Gloss Polyurethane

1 50 50 White / Colours

Brush / Spray

Robbiathane

2 150

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 218: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

218 of

System # 2, Exterior Surfaces –Ferrous Metal, PolyurethaneTable 17Coats Generic

Type# of coats

Solids volume %

DFTMicrons

Colour Application

Berger Product

Primer High build epoxy polyamide primer

1 57 75 Red Brush / Spray

Epilux 78

Intermediate

High build epoxy polyamide

1 68 100 Grey Brush / Spray

Epilux 218HS

Finish Gloss Polyurethane

1 50 50 White / Colours

Brush / Spray

Robbiathane

3 225

Touch up if required with Epilux 78 after power tool cleaning on spots

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 219: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

219 of

System # 3, Exterior Surfaces –Concrete Masonry, Polyurethane TexturedTable 18Coats Generic

Type# of coats

Solids volume %

DFTMicrons

Colour Application

Berger Product

Primer Epoxy Concrete

1 45 50 White Brush / Spray / Roller

Epilux Concrete Primer

Intermediate

Epoxy spray compound in textured finish

1 68 1000 White Hopper Gun

Luxatile Epoxy Spray Compound

Finish Gloss / Semi Gloss Polyurethane

1 50 50 White / Colours

Roller / Spray

Robbiatathane

1100

The textured pattern is unpressed and the DFT could vary from 700 to 1000 micron or more as manually applied by hopper gun. Appropriate instruction to apply the smooth coatshall be followed according to the manufacturer’s manual

System # 4, Interior Surfaces –Galvanised Steel, Alkyd Table 19Coats Generic

Type# of coats

Solids volume %

DFTMicrons

Colour Application

Berger Product

Etch Primer(To be used in surface preparation instead of

Two Pack washer primer

1 8.5 5 Greenish Yellow

Brush / Spray

Luxaprime 1500

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 220: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

220 of

blasting)Coats Generic

Type# of coats

Solids volume %

DFTMicrons

Colour Application

Berger Product

Primer Coat

Anticorrosive rust inhibitive Primer

1 55 55 Red Brush / Spray

Luxaprime 1500

Intermediate Coat

Alkyd Undercoat

1 55 55 White Brush / Spray

Luxole 1000

Finish Coat

Alkyd Enamel 1 48 48 White / Colours

Brush / Spray

Luxole 5000

4 155

Luxaprime 1000 has to be applied on the same day of Luxaprime 1500

System # 5, Interior Surfaces –Primed Ferrous Metal, AlkydTable 20Coats Generic

Type# of coats

Solids volume %

DFTMicrons

Colour Application

Berger Product

Primer Coat(If required)

High build alkyd zinc phosphate primer

1 50 50 Red / Grey

Brush / Spray

Luxaprime 1400

Intermediate Coat

Alkyd undercoat

1 55 50 White Brush / Spray

Luxol 1000

Finish Coat

Alkyd Enamel 1 50 50 White / Colours

Brush / Spray

Luxol 5000

Note-Primer need not be applied if already primed

3 150

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 221: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

221 of

System # 6, Interior Surfaces –Gypsum Wallboard and plaster, AcrylicTable 21Coats Generic

Type# of coats

Solids volume %

DFTMicrons

Colour Application

Berger Product

Primer Coat

Premium quality alkali resisting primer

1 25 25 White Brush / Roller

Brolac Acrylic AR Primer

Filler Coat

High quality acrylic based wall filler

1(to seal & smoothen the surface)

81 To smoothen the surface

White Spatula Berger Super Wall Filler

Intermediate Coat

High quality acrylic emulsion

1 35 50 White / Colours

Roller Bergercoat Acrylic Emulsion

Finish Coat

Semi gloss acrylic emulsion

1 35 50 White / Colours

Roller Brolac Semi Gloss Emulsion

3 >100

MethodGENERALMarking of containersMaterials shall be delivered in sealed containers clearly labelled with the following information.Manufacturer’s name, initials or recognised trade markTitle and specification numberWhether primer or undercoat, finishing coatWhether for internal or external use where appropriateColour reference from BS 4800Method of applicationBatch number and date of manufacture and re – testNo paint shall be used after 18 months of manufacture or re testCoating materials other than spray paints, bituminous pants and fine textured masonry paint shall be in containers not exceeding 5 litres capacity

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 222: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

222 of

SamplesSample panel of 1 sqm in area shall be prepared for each type and colour of coating material to be used in the work for the approval Sample material of each paper / fibre material minimum size 500 x 500 mm showing at least the pattern repeat where applicable shall be submitted for approvalPart 2MaterialsPreparatory Materials Paint removers, abrasive papers and blocks, cleaning agents, etching solutions, stopping, knotting, fillers and other commodities shall be of the types recommended by the manufacturer of the coating to be appliedWhite spirit shall comply with BS 245Knotting shall comply with BS 1336Stopping and filler for woodwork shall be approved proprietary Leadless oil based type recommended for internal or external work as appropriate. Stopping for woodwork to receive a coat finish shall be tinted to match with the surrounding workFiller for plaster or rendering shall be approved proprietary type The following operational sequences shall be involvedPriming CoatFiller Coat to the requirementIntermediate CoatFinishing CoatAll according to the approved system as aforesaid detailed for reference.ApplicationPREPARATION OF THE GALVANIZED SURFACESDirt and other adherent contaminating matter / loose deposits shall be removed from galvanised surfaces by mechanical means using Berger tool cleaner. Cleaning shall not damage the galvanising. Oil or grease shall be removed from galvanised surfaces by the application of an emulsion cleaner. Any zinc corrosion products remaining shall be removed by washing with sweet water and scrubbing with hard bristle brushesAfter being cleaned and degreased, all galvanised surfaces shall be etched with T-wash as described in BS 5493. If any surface fails to turn black as cleaning, greasing and etching processes shall be repeated.APPLICATION OF PAINT GENERALLYAll paints shall be prepared and applied in strict accordance with the manufacturer’s instructions. Priming paints shall be applied by brush. Spray application shall only be used for painting of epoxy resin baseExposure of intermediate coats of paint for periods in excess of a few days shall not be permitted except in case of work delivered to site in a primed conditionThe dried films shall be free from bloom, shrinkage, sheeringness, wrinkling, sagging, curtailing, discoloration and extraneous matterNo exterior or exposed paint work shall be carried out under adverse weather conditions, during rain, mist, sandstorms nor when the relative humidity exceeds 80%

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 223: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

223 of

Painting shall insofar as is practicable be shaded from direct sunlight by netting to prevent wrinkling and bristling. Whenever possible exterior painting shall be so programmed during the day so as to be carried out in shadowPainting of surfaces shall not be carried out when condensation is present on such surfaces or the application and / or drying of the paints is likely to be affectedSurfaces to be painted shall receive as first coat of paint as quickly as possible after the e preparation has been completedIn case of metal surfaces this shall preferably be within one hour but always before the metal temperature drops to less than 3 deg C above dew point and before any rustingCivil Contractor QC inspections shall be conducted at every stage of surface preparation , post application of the coat, prior to the proceeding and at the final coat completion followed by EPC Contractor approval all according to the ITP documents attachedMETHOD OF COATINGEach coat shall be applied uniformly over the entire surface. Skips, runs, sags and drips shall be avoided. When these occur they shall be brushed out immediately or the materials removed and the surface recoated. On beams and irregular surfaces, edges shall be strip coated first and at extra pass made later. Each coat shall be allowed to dry for the time specified by the manufacturer before application of any succeeding coatAny primer coat exposed to freezing, excess humidity, rain, dust etc., before drying, shall be removed, surface again prepared and primedThe time interval between application of coats shall not exceed that specified for optimum results by the manufacturerAll coatings shall be cleaned as specified by the manufacturer before the next coat is appliedAll areas not specifically mentioned in the painting specification shall be finished to conform to the adjacent comparable areasAll fixtures and surfaces not to be painted shall be properly protected during application and upon completion of the work all paint and varnish removed from glass, fixtures, covering, etc., Moveable parts shall not to be painted.All parts such as pipe supports, seatings and cleats, back to back sections which shall become inaccessible after fabrication shall be treated on both surfaces with the full paint system prior to final assembly, thus ensuring adequate protection.SPRAY APPLICATIONAll equipment for spray application shall be inspected and approved before any application begins. Spray guns, hoses and pumps shall be cleaned before new material is added. An adequate moisture and oil trap shall be installed between the air supply to each application unit.Suitable pressure regulators and gauges shall be provided for the air supply to the application units. Spray equipment and operating pressures shall comply with the manufacturer’s recommendations.Coating materials containing heavy pigments that have a tendency to settle shall be kept in suspension during the application by the power driven, continuous agitatorThe spray gun shall be held at right angles to the surface and each pass overlap the previous one by approximately 50%. All materials contained herein may be applied by airless spray.

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 224: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

224 of

BRUSH APPLICATIONBrushes shall be of a style and quality that permit proper application of the materialFlat brushes shall not be more than 100 mm wide. No extending handles shall be used on brushes.Brushing shall be done so that a smooth coat as nearly uniform in thickness as possible is obtained without any deep or detrimental marksPaints shall be worked into all corners and crevices. When applying solvent type coating, care shall be taken to prevent lifting of previous coats.FILM THICKNESSSpecified film thickness for coating materials shall be strictly observed which be checked with an appropriate film thickness gauge. Calibration for the thickness range to be checked at least twice a dayWhen dry film thickness are less than those specified, additional coats shall be applied as required. Particular attention shall be paid to full film thickness on edgesIn hot weather such additional precautions as are necessary shall be taken to ensure that the specified dry film thickness on priming or finish coats is obtainedCOATING QUALITYCoatings shall be free from pinholes, voids, bubbles, dust, foreign inclusions and other holidays and any such defect shall be repaired. Prior to the application of a coating, any damage to the previous coating shall be repaired with the specified material. Upon completion of the fabrication any damage to the coating system shall be repaired TEST EQUIPMENTSvensk photographic standard SIS 05 59 00Coating thickness meter such as Elcometer ‘Minitector” Model 150Wet fill thickness combsHygrometerMaximum and minimum thermometerFlow cup type B # 4 and timerSurface profile meter such as Elcometer’Roughness detector’Bolted site connections other than faying surfaces of Grip Bolt connections shall be brought together ‘wet’EPOXY COATING WORK GENERALLYIn addition to the general requirements the following conditions shall apply wherever epoxy-coating work is being carried outForced draught ventilation shall be used wherever required for the needs of the personnel or for drying out surfacesOperatives shall work in pairsSamples areas on substrate shall be prepared and coated for approvalThere shall be strict control of surface cleanliness between primer and epoxy coating / and between coats of the same. Vacuum removal of dust and sand shall be employed and contamination removed. Where dirt or dust has been trapped in the painted surface it shall be removed with suitable abrasive paper. The surface being painted shall be free of visible moisture throughout these operations

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 225: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

225 of

The paint shall be applied only to the clean dry primed or previously coated surfaces. Any thick runs or collections of paint shall be removed before these hardenNot less than 2 coats shall be applied over the primer by airless spray, less than 3 by brushEach coat shall be distinctly different in colour from the primer or previous coat. The colour of the final coat shall be as approved. Each coat shall be seen to have completely covered the proceeding without ‘ misses’ or pinholes or any areas visibly low in thickness. A high voltage pinhole detector shall also be used to determine the integrity of the coatsThe manufacturer of the coating shall stipulate primer and epoxy recoat interval for all curing temperatures likely to be encountered and these be adopted with a maximum tolerance of +4 hours. Where this is exceeded, the surfaces to be recoated shall first be suitably abraded to remove gloss and provide a keyWet thickness gauges shall be used by the coating operators continually to check that sufficient paint is being applied to achieve the desired dry film thicknessEPOXY COATING FOR CONCRETE AND RENDERED SURFACESNo priming shall commence until the moisture content of the cementitious surface is less than 5% measured by Wetcheck Moisture meter or other instrument Similarly moisture measurements over the primer or any epoxy intercoat shall not exceed 1 % on the concrete scale of the instrument when the probe tips are held against such painted surfaces just prior to recoatingThe priming shall be applied by suitable Nylon bristle brush or spray over the whole area to be coated at such thickness that it may then be squeezed into the pores of the concrete. Any excess shall be removed by the most suitable means before application of the high build epoxyThe total DFT of the paint layer shall have a minimum specified value Whenever the paint inspection gauge has been used and wherever the coating has been otherwise damaged for 50 mm around such damage, the surfaces shall be abraded followed by the area touched in with not less than 2 # thick applications to restore the coating integrity to the specified thickness. Adhesion tests shall be carried out on the cured coating surface using the test equipment supplied in accordance with the best practice. The resulting test specimens shall show no indication of poor adhesion to the substrate, residual laitance or intercoat adhesion weakness.The following instrument shall be used 1 Adhesion Tester 0 to 35 kg / cm21 DC high voltage holiday detector # 105One paint inspection gauge PIG1 wet check moisture meterEquipmentSpray applianceBrushesRollersAttachmentITP-Doc: QCF Rev BConcrete paint system checklistITP-Doc :QCF Rev B

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 226: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

226 of

Internal painting check list#85

Painting Sub stationsTop

IndexScopeReference documentsDefinitionsResponsibilitiesSafetyMethod EquipmentAttachmentScope This statement is aimed to present the procedures to be adopted to apply the Painting System on the various surfaces of all the Sub Station buildings according to the following specifications and the drawing references ReferencesSpecifications DefinitionsPSM Project Site ManagerCSM Construction ManagerCS Construction SuperintendentSE Site EngineerFM ForemanQC Quality ControlResponsibilitiesPSM shall control the overall operations CM shall arrange the resources required accordingly CS shall control, monitor and direct the SE, FM and workforce for the operationsSE shall be responsible for all the site operations and follow the instructions of the CSFM shall execute the operations deploying the workforce. FM shall explain in full in the language the work persons understand about all the instruction and the ToolBox talks every day and check that the same are followed up regularlyQC shall inspect all the operations according to the specificationsSafetyPrior to the commencement of work, the labour force shall receive a STARRT Card / Toolbox talk regarding the painting system operation concerned to the Project Site Safety requirements.

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 227: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

227 of

Any process involving a particular Safety risk shall be assessed to the requirement for Site conditions and be taken care of. In this case all the adverse effects of the epoxy paint shall be informed and the safety measures to be adopted instructed. The personnel shall use the PPE, gloves, masks, eyeglasses etc and to avoid skin contact. use of barrier cream shall also be made.Material safety data shall be referred to for disposal and any further information.Adequate arrangement shall be made to provide access up to the top of the wall.Tagged scaffolding with proper netshade shall be provided wherever requiredThe personnel shall use the waist safety belt / harness while working height.Immediate medical care shall be provided in case the eyes of any personnel are effected due to the paint splashes or any other reasonProper ventilation shall be provided to breathe properlyA safety inspector shall visit the site every day and instruct the supervisor in case any snag is observed who immediately implement the instructions accordingly.StorageThe material shall be stored under cover out of direct sunlight and protected from extreme temperatures. MaterialsSpecified: Texotile from Jotun or EquivalentApproved: Berger Paint systems MAR dated 27.1.The following table provides the details of the approved systems Table 22S # Sub Strata Surface preparation Operating

temperature1 Galvanised steel-

Exterior,PolyurethaneMechanical cleaning to remove loose deposits –Cleaning with Berger Cleaner-Refer to manufacturer’s recommendations

Upto 100 deg C

2 Mild steel-Exterior, Polyurethane

Blasting to Sa 2.5 Upto 100 deg C

3 Concrete Surface- Exterior, Polyurethane textured

Cleaning with sand stone to smoothen the surface free from all dirt etc

Upto 100 deg C

4 Galvanised Steel-Interior, Alkyd

Mechanical cleaning to remove loose deposits - Cleaning with Berger Cleaner -Refer to manufacturer’s recommendations

Upto 60 deg C

5 MS / Ferrous Metal-Interior, Primed ferrous metal Alkyd

Mechanical cleaning to Sa 2 to remove loose rust, scales

Upto 60 deg C

6 Plaster and Gypsum-Gypsum wall board

Cleaning with fine emery paper to remove dirt etc.

Upto 50 deg C

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 228: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

228 of

and plaster, Acrylic

System # 1, Exterior Surfaces –Galvanised Steel, PolyurethaneTable 23Coats Generic

Type# of coats

Solids volume %

DFTMicrons

Colour Application

Berger Product

Primer Surface tolerant high build epoxy

1 82 100 Aluminium

Brush / Spray

Epimastic 5100 Al

Finish Gloss Polyurethane

1 50 50 White / Colours

Brush / Spray

Robbiathane

2 150System # 2, Exterior Surfaces –Ferrous Metal, PolyurethaneTable 24Coats Generic

Type# of coats

Solids volume %

DFTMicrons

Colour Application

Berger Product

Primer High build epoxy polyamide primer

1 57 75 Red Brush / Spray

Epilux 78

Intermediate

High build epoxy polyamide

1 68 100 Grey Brush / Spray

Epilux 218HS

Finish Gloss Polyurethane

1 50 50 White / Colours

Brush / Spray

Robbiathane

3 225Touch up shall be carried out with ‘Epilux 78’ after cleaning the effected area using power tool

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 229: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

229 of

System # 3, Exterior Surfaces –Concrete Surface / Masonry, Polyurethane TexturedTable 25Coats Generic

Type# of coats

Solids volume %

DFTMicrons

Colour Application

Berger Product

Primer Epoxy Concrete

1 45 50 White Brush / Spray / Roller

Epilux Concrete Primer

Intermediate

Epoxy spray compound in textured finish

1 68 1000 White Hopper Gun

Luxatile Epoxy Spray Compound

Finish Gloss / Semi Gloss Polyurethane

1 50 50 White / Colours

Roller / Spray

Robbiatathane

3 1100

Because the textured pattern is unpressed the DFT may vary from 700 to 1000 micron or more as manually applied by hopper gun. The smooth surface shall be produced by following the relevant manufacturer’s instruction

System # 4, Interior Surfaces –Galvanised Steel, Alkyd Table 26Coats Generic

Type# of coats

Solids volume %

DFTMicrons

Colour Application

Berger Product

Etch Primer(To be used in surface preparation instead of blasting)

Two Pack wash primer

1 8.5 5 Greenish Yellow

Brush / Spray

Luxaprime 1500

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 230: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

230 of

Coats Generic Type

# of coats

Solids volume %

DFTMicrons

Colour Application

Berger Product

Primer Coat Anticorrosive rust inhibitive Primer

1 55 50 Red Brush / Spray

Luxaprime 1500

Intermediate Coat

Alkyd Undercoat

1 55 50 White Brush / Spray

Luxole 1000

Finish Coat Alkyd Enamel

1 48 50 White / Colours

Brush / Spray

Luxole 5000

4 155

Luxaprime 1000 primer coat shall be applied the same day when the surface is prepared by etching using Luxaprime 1500

System # 5, Interior Surfaces –Primed Ferrous Metal, AlkydTable 27Coats Generic

Type# of coats

Solids volume %

DFTMicrons

Colour Application

Berger Product

Primer Coat(If required)

High build alkyd zinc phosphate primer

1 50 50 Red / Grey

Brush / Spray

Luxaprime 1400

Intermediate Coat

Alkyd undercoat

1 55 50 White Brush / Spray

Luxol 1000

Finish Coat

Alkyd Enamel 1 50 50 White / Colours

Brush / Spray

Luxol 5000

Note-Primer need not be applied if already shop primed

3 150

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 231: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

231 of

System # 6, Interior Surfaces –Gypsum Wallboard and plaster, AcrylicTable 28Coats Generic

Type# of coats

Solids volume %

DFTMicrons

Colour Application

Berger Product

Primer Coat

Premium quality alkali resisting primer

1 25 25 White Brush / Roller

Brolac Acrylic AR Primer

Filler Coat

High quality acrylic based wall filler

1(to seal & smoothen the surface)

81 To smoothen the surface

White Spatula Berger Super Wall Filler

Intermediate Coat

High quality acrylic emulsion

1 35 50 White / Colours

Roller Bergercoat Acrylic Emulsion

Finish Coat

Semi gloss acrylic emulsion

1 35 50 White / Colours

Roller Brolac Semi Gloss Emulsion

3 >100

MethodGENERALMaterials shall be delivered in sealed containers clearly labelled with the following information.Manufacturer’s name or recognised trade markTitle and specification numberWhether primer or undercoat, finishing coatWhether for internal or external use where appropriateColour reference from BS 4800Method of applicationBatch number and date of manufacture SamplesSample panel of 1 sqm in area shall be prepared for each type of coating for approval on any of the surfaces to be applied with that paintThe following operational sequences shall be involvedPriming Coat

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 232: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

232 of

Filler Coat to the requirementIntermediate CoatFinishing CoatAll according to the approved system as aforesaid ApplicationPREPARATION OF THE GALVANIZED SURFACESDirt and other adherent contaminating matter / loose deposits shall be removed from galvanised surfaces by mechanical means using Berger tool cleaner. Cleaning shall not damage the galvanising. APPLICATION OF PAINT (GENERAL)All paints shall be prepared and applied in strict accordance with the manufacturer’s instructions. Exposure of intermediate coats of paint for periods in excess of specified time shall not be permitted except in case of work delivered to site in a primed conditionThe dried films shall be free from all defects such as bloom, shrinkage, sheerings, wrinkling, sagging, curtailing, discoloration and extraneous matterNo exterior or exposed paintwork shall be carried out under adverse weather conditions i.e., during neither sandstorms nor when the relative humidity exceeds 80%Painting shall insofar as is practicable be shaded from direct sunlight by netting to prevent wrinkling and bristling. Painting of surfaces shall not be carried out when condensation is present on such surfaces or the coating application on drying is likely to be affectedSurfaces to be painted shall receive the first coat of paint as quickly as possible after the preparation has been completedIn case of metal surfaces, this shall preferably be within one hour but always before the metal temperature drops to less than 3 deg C above dew point and before any rustingCivil Contractor QC inspections shall be conducted at every stage of surface preparation, post application of the coat, prior to the proceeding coat and at the final coat completion, all according to the ITP documents attachedMETHOD OF COATINGEach coat shall be applied uniformly over the entire surface. Skips, runs, sags and drips shall be avoided. When these do occur, they shall be brushed out immediately or the materials removed and the surface recoated. On beams and irregular surfaces, edges shall be strip coated first and an extra pass made later. Each coat shall be allowed to dry for the time specified by the manufacturer before application of any succeeding coatAny primer coat exposed to, excessive humidity, dust etc., before drying, shall be removed, and the surface again prepared and primedAll coatings shall be cleaned as specified by the manufacturer before the next coat is appliedAll fixtures and surfaces not to be painted shall be properly protected during application and upon completion of the work all paint and varnish removed from glass, fixtures, covering, etc., Moveable parts shall not to be painted.All parts such as pipe supports, seatings and cleats, back to back sections which shall become inaccessible after fabrication shall be treated on both surfaces with the full paint system prior to final assembly, thus ensuring adequate protection.Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 233: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

233 of

SPRAY APPLICATIONAll equipment for spray application shall be inspected and approved before any application begins. Spray guns, hoses and pumps shall be cleaned before new material is added. An adequate moisture and oil trap shall be installed between the air supply to each application unit.Suitable pressure regulators and gauges shall be provided for the air supply to the application units. Spray equipment and operating pressures shall comply with the manufacturer’s recommendations.Coating materials containing heavy pigments that have a tendency to settle shall be kept in suspension during the application by the power driven, continuous agitatorThe spray gun shall be held at right angles to the surface and each pass overlap the previous one by approximately 50%. All materials contained herein may be applied by airless spray.BRUSH APPLICATIONBrushes shall be of a style and quality that permit proper application of the materialNo extending handles shall be used on brushes.Brushing shall be done so that a smooth coat as nearly uniform in thickness as possible is achieved without any deep or detrimental marksPaints shall be worked into all corners and crevices. FILM THICKNESSSpecified film thickness for coating materials shall be strictly observed which is checked with an appropriate ‘film thickness gauge’. When dry film thickness is less than that specified, additional coats shall be applied as required. Particular attention shall be paid to full film thickness on edgesIn hot weather such additional precautions as are necessary shall be taken to ensure that the specified dry film thickness on priming or finishing coats is achieved by monitoring the wet film thickness using the appropriate gauge. Additional coats shall be applied on the deficient areaCOATING QUALITYCoatings shall be free from pinholes, voids, bubbles, dust, foreign inclusions and other holidays and all such defects shall be repaired. Prior to the application of a coating, any damage to the previous coating shall be repaired with the specified material. TEST EQUIPMENTCoating thickness meter such as Elcometer ‘Minitector” Model 150 or equivalentWet fill thickness combsHygrometerMaximum and minimum thermometerSurface profile meter such as Elcometer’Roughness detector’EPOXY COATING WORK (GENERAL)In addition to the general requirements the following conditions shall apply wherever epoxy-coating work is being carried outForced draught ventilation shall be used wherever required for the needs of the personnel or for drying out surfacesOperatives shall work in pairsSample on substrate shall be prepared and coated for approval

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 234: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

234 of

There shall be strict control of surface cleanliness between primer and epoxy coating / and between coats of the same application. Vacuum removal of dust and sand shall be employed and contamination removed. Where dirt or dust has been trapped in the painted surface, it shall be removed with suitable abrasive paper. The surface being painted shall be free of visible moisture throughout these operationsThe paint shall be applied only to the clean & dry primed or previously coated surfaces. Any thick runs or collections of paint shall be removed before these hardenEach coat shall be distinctly different in colour from the primer or previous coat. The colour of the final coat shall be as approved. Each coat shall be seen to have completely covered the proceeding without ‘ misses’ or pinholes or any areas ‘visibly low’ in thickness. A high voltage pinhole detector shall also be used to determine the integrity of the coats“The manufacturer of the coating shall stipulate primer and epoxy recoat interval for all curing temperatures likely to be encountered and these be adopted with a maximum tolerance of +4 hours”. Where this is exceeded, the surfaces to be recoated shall first be suitably abraded to remove gloss and provide a keyWet thickness gauges shall be used by the coating operators continually to check that sufficient paint is being applied to achieve the desired dry film thicknessEPOXY COATING FOR CONCRETE AND RENDERED SURFACESNo priming shall commence until the moisture content of the cementitious surface is less than 5% measured by Wetcheck Moisture meter or other instrument Similarly moisture measurements over the primer or any epoxy intercoat shall not exceed 1 % on the concrete scale of the instrument when the probe tips are held against such painted surfaces just prior to recoatingThe priming shall be applied by suitable Nylon bristle brush or spray over the whole area to be coated at such thickness that it may then be squeezed into the pores of the concrete. Any excess shall be removed by the most suitable means before application of the high build epoxyThe total DFT of the paint layer shall have a minimum specified value Whenever the paint inspection gauge has been used and wherever the coating has been otherwise damaged, the surfaces shall be abraded 50 mm around and the area touched in with not less than 2 # thick applications to restore the coating integrity to the specified thickness. Adhesion tests shall be carried out on the cured coating surface using the test equipment supplied in accordance with the best practice. The resulting test specimens shall show no indication of poor adhesion to the substrate, residual laitance or intercoat adhesion weakness.The following instrument shall be used 1 Adhesion Tester 0 to 35 kg / cm21 DC high voltage holiday detector # 105One paint inspection gauge PIG1 wet check moisture meterEquipmentSpray applianceBrushesRollers

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 235: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

235 of

AttachmentITP-Doc: QCF Rev BConcrete paint system checklistITP-Doc :QCF Rev BInternal painting check list#86

Electrical & instrumentation trenchesTopIndexScopeReference documentsDefinitionsResponsibilitiesSafetyMethod EquipmentAttachmentScope This statement is aimed to present the proposed procedures to be adopted to carry out the construction of the proposed Electrical and Instrumentation trenches to the following specified detailsCable trench X-ing with U / G pipeCable trench X-ing with U / G pipe with closed drain pipe trenchPipe X-ing direct buried cables onlyTypical elctrical layout at pumpsTypical corner details for walled trenchDirect buried trench X-ing under Dummy TrenchTrench with dummy Trench X-ing under direct buried cable trenchDummy + walled trench sectionReferencespaving & Under Ground servicesElectrical and Instrumentation Trench and Duct Bank detailsSpecifications DefinitionsPSM Project Site ManagerCSM Construction ManagerCS Construction SuperintendentSE Site EngineerStatements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 236: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

236 of

FM ForemanQC Quality ControlResponsibilitiesPSM shall control the overall operations CM shall arrange the resources required accordingly CS shall control, monitor and direct the SE, FM and workforce for the operationsSE shall be responsible for all the site operations and follow the instructions of the CSFM shall execute the operations deploying the workforce. FM shall explain in full in the language the work persons understand about all the instruction and the ToolBox talks every day and check that the same are followed up regularlyQC shall inspect all the operations according to the specificationsEPC Contractor shall conduct surveillanceSafetyPrior to the commencement of work, the labour force shall receive a Toolbox talk relevant to the operation concerned to the Project Site Safety requirements. Any process that is adopted which may have a particular Safety risk shall be assessed to the requirement for Site conditions and be taken care of. The personnel shall use the PPE, gloves, masks (for gas leak in area), eyeglasses (during dusty winds) etc Adequate arrangement shall be made to provide access to the top of the wall.A safety inspector shall visit the site every day and instruct the supervisor in case any snag is observed who immediately implement the instructions accordingly.MaterialsMass Concrete for strip foundation beam, Concrete blocks, precast covers, oil resistant sealantMethodGENERAL-Dummy and walled trench sectionThe following operational sequences shall be involvedTo set out the exact alignment of the trenches to the specified co-ordinatesTo barricade the involved area to the safety requirementTo excavate the trenches to the specified levelsTo dress the formations and compactTo prepare the sides for the mass concrete 100mm thickTo pour the mass concreteTo set out the block walls alignmentTo carry out 150mm thick block work to the specified levels upto the paving down beam levelTo carry out the down standing paving portion & extend to the block wall topTo fill the trench with the excavated earth back according to specificationsTo place the precast coloured concrete covers 1m or 3m lengths on the compacted groundTo Seal the paving and cover joint Where the dummy trench runs over the duct bank (Typical Trench Duct Bank Detail)

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 237: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

237 of

The duct bank with the uPVC sleeves in for the crossing portion below the underground pipe should be ready formed with the mass concrete the size of which shall vary according to the number of crossing pipesThe following operational sequences shall be involvedTo excavate down to the top of the duct concrete in case backfilling has been completedTo clean the concrete surfaceTo set out the trench alignmentTo set out the block wall alignment keeping maximum 50 mm overhangTo construct the block walls to paving down beam levelTo carry out the down standing paving portion & extend to the block wall topTo fill the trench with the excavated earth back according to specificationsTo place the precast coloured concrete covers 1m or 3m lengths on the compacted groundTo Seal the paving and cover jointAdditionally, in case the underground pipe runs X-ing the Trench, to lay the specified pipe prior to the block work operation by others To provide a flat crossing size equal (Duct Bank length + 300x2)The formation level of the duct bank and the dummy trench shall be the same at the exact crossing location Where the dummy trench and the direct buried trench run parallel The following operational sequences shall be involvedTo repeat all the sequences as in general in the aforesaidTo follow the profile of the dummy trench while constructing the buried trench for ease To form the down slope profile at the crossings as shown on the drawingThe slope grade shall be 1 in 2Where the cable trench crossing the closed drain pipe trenchThe following additional operational sequences to the general trench construction for the dummy or the direct buried shall be required To provide the profile of the direct buried trench same as that of the cable duct trench To provide the transition of levels between the dummy trench and the flat below X-ing by a slope grade 1 in 2 as specified on the drawingTo provide a duct bank of size depending on the dimension of the closed drain trench to pass above by providing a width (closed drain trench width + 100mmx2)To provide a total flat width below the crossing equal (duct bank length + 300x2).To provide the uPVC sleeves in the duct bank prior to the mass concretingTo allow a clear void of 100mm minimum between soffit of closed drain trench base and the duct bank topTo provide cable tiles under trench crossing in direct buried cable trenches only(By others)To allow the closed drain trench isolate from the paving Where direct buried trench crossing under dummy trenchThe following additional operational sequences to the general trench construction for the dummy or the direct buried shall be required To provide a level difference of 350 mm between the dummy trench elevation and the compacted surface below the crossing maintaining a transition slope grade 1 in 2

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 238: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

238 of

To allow the cables running in dummy trench to be protected by the cable tiles installed at 75 mm above the top of cables where no paving is shown (By others)To allow to provide the cable protection tiles above the cables where these pass in the walled trench to cross under the dummy trench (By others)To form the walled trench corner detail according to the corner splay internal size 8485 mmWhere dummy Trench crossing under direct buried cable trench The following additional operational sequences to the general trench construction for the dummy or the direct buried shall be required To provide a flat surface below the X-ing at the bottom of the duct bank of size equal (duct bank length + 300x2) with a slope grade transition 1 in 2To provide a level difference of 100 mm between soffit of the direct burried cable trench and the duct bank topWhere direct buried cable trench crossing under direct buried cable trench The following additional operational sequences to the general trench construction for the dummy or the direct buried shall be required To maintain a level difference 700 mm between direct buried trench and the crossing formation levelTo provide a transition grade 1 in 2To provide a cable tiles in unpaved areas only and at trench crossing (By others)To provide the formation crossing width equal (direct buried cable trench width + 400x2)Electric Trench Layout at PumpsThe following additional operational sequences to the general trench construction for the dummy or the direct buried shall be required To form the trench termination into an integral chamber of internal dimensions as (Pump base length / 2+trench internal width) x (Pump base width +300+500)Details in generalThe surveyor shall setout the alignment of the trench concerned according to the details given on the paving and underground services layouts to the reference co-ordinatesCivil Contractor QC shall conduct the inspection followed by EPC Contractor approval The required safety arrangement shall be discussed with the safety department and implemented accordingly to control the trench excavation, to provide barricades night-lights etc, to divert the traffic if so required and to adopt any other unforeseen measures.The excavation shall be carried out by an excavator to the lines and the surveyor monitor various stages during the operation to maintain the required profileThe excavated material shall be transported immediately after being taken out using a dumper, to the earth stockpiles temporarilyThe formation levels after the excavation is over shall be well dressed and compacted to the specification requirementThe forms of width 350mm and depth 100 mm shall be readily available to be fixed on the prepared compacted formation duly alignedCivil Contractor QC inspection shall be conducted followed by EPC Contractor approvalThe mass concrete shall be poured to the marked levels and tamped by wooden floatThe curing shall be carried out according to approved procedures

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 239: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

239 of

The alignment of the block walls 150 mm thick shall be set out, the block work carried out in courses in a straight line and plumbThe whole number of courses shall be laid, the fraction remained to be completed for the wall height shall be covered by pouring during the paving down beam concreteThe connecting integrated / pouring area including the down beam shall be carried out to the specified details according to the proceduresCivil Contractor QC inspection shall be conducted followed by the EPC Contractor approvalThe backfilling shall commence and the trench filled according to the specificationsThe precast covers of 1m or 3 m standard length already precast shall be placed on the formed trench internal surface to the specified levelsThe concrete shall be coloured to the specification requirementCivil Contractor QC inspection shall be conducted followed by EPC Contractor approval OptionIf so required and felt convenient for certain standard equal depth reaches, precast concrete members of 100 mm thick sections may be utilised to substitute 150 mm thick walls directly resting on the prepared formationEquipmentExcavatorDumper truckCompactorAttachmentNone#87

Electrical & instrumentation trenchesTopIndexScopeReference documentsDefinitionsResponsibilitiesSafetyMethod EquipmentAttachmentScope This statement is aimed to present the procedures to be adopted to carry out the construction of the Electrical and Instrumentation Trenches to the typical details.

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 240: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

240 of

ReferencesDrg Paving & Under Ground servicesElectrical and Instrumentation Trench and Duct Bank detailsSpecifications DefinitionsPSM Project Site ManagerCSM Construction ManagerCS Construction SuperintendentSE Site EngineerFM ForemanQC Quality ControlResponsibilitiesPSM shall control the overall operations CM shall arrange the resources required accordingly CS shall control, monitor and direct the SE, FM and workforce for the operationsSE shall be responsible for all the site operations and follow the instructions of the CSFM shall execute the operations deploying the workforce. FM shall explain in full in the language the work persons understand about all the instruction and the ToolBox talks every day and check that the same are followed up regularlyQC shall inspect all the operations according to the specificationsSafetyPrior to the commencement of work, the labour force shall receive a STARRT card / Toolbox talk relevant to the operation concerned to the Project Site Safety requirements. Any process involving a particular Safety risk shall be assessed to the requirement for Site conditions and be taken care of. The personnel shall use the PPE, gloves, masks (for gas leak in area), eyeglasses (during dusty winds) etc A safety inspector shall visit the site every day and instruct the supervisor in case any snag is observed who immediately implement the instructions accordingly.MaterialsMass Concrete for strip foundation beam, Concrete blocks, Precast trench covers, oil resistant joint sealantMethodGENERALDummy / walled trench section (Detail 5 on the reference drawing) The following operational sequences in brief are involvedSetting out to the exact alignment the route of the trench to the specified co-ordinatesBarricading the involved area to the safety department direction and requirementExcavating the trench to the specified levels and sectional detailsPreparing the formation to the required levels and dimensionsForm work for the sides of the mass concrete strip beamsPouring the mass concrete to the strip beam formsSetting out the alignment for the trench block wallsStatements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 241: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

241 of

Block work 150mm thick in walls to the specified levels upto the pavement downstand beam soffit levelPreparation and concreting the pavement portion monolithic with the downstand beam extended upto the top of the block wall Backfilling the trench with the excavated earth to the specificationsPlacing the precast coloured concrete covers in 1m or 3m standard lengths on the relevant compacted areaSealing the joint between the pavement and the trench cover Details about the above operations in generalThe surveyor shall set out the alignment of the trench concerned according to the relevant details given on the paving and underground services location plans to the reference Co-ordinatesCivil Contractor QC shall conduct the inspection The safety arrangement shall be discussed with the safety department and implemented accordingly to control the trench excavation, to provide barricades, night-lights, to divert the traffic if so required, and to adopt any other necessary measure.The excavation shall be carried out by an excavator to the lines and the levels.The surveyor shall monitor all stages of excavation to achieve the required profileThe excavated material shall be transported immediately by a dump truck to the earth stockpiles temporarilyAfter the excavation is over, the formation levels shall be well dressed and compacted to the specification requirementThe forms shall be fabricated for the mass concrete sectionThe fabricated forms of width 350mm and depth 100 mm shall be erected / fixed on the prepared compacted formation duly aligned and levelledCivil Contractor QC shall conduct the inspection throughout the stages of construction The mass concrete shall be poured to the marked levels and tamped by wooden floatThe forms shall be struck after the specified periodThe curing of the mass concrete shall be carried out according to approved procedures and for the specified periodThe alignment of the block walls 150 mm thick shall be set out and the block work carried out in courses in a straight line and plumbThe whole number of courses shall be laid. The fractional block course if so remained to make up the required wall height, shall be constructed as a part of the pavement down beam concrete by extending the bottom to the top of the block wallsThe pavement / down beam monolithic pouring shall be carried out to the specified details according to the proceduresCivil Contractor QC shall conduct the inspection throughout the stages of construction The backfilling shall commence and the trench filled according to the specificationsThe precast covers of 1m or 3 m standard length shall be placed on the filled trench internal surface to the specified levelsThe concrete shall be coloured to the specification requirementCivil Contractor QC shall conduct the inspection throughout the stages of construction Where the dummy trench runs over the duct bank (Ref drawing Detail 4, Sec A)Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 242: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

242 of

All the operations described in general shall be applicable herein as well with the following amendments / additions to certain activitiesExcavation shall be carried out to the top of the duct concrete onlyThe walls shall be started from the duct top levelAdditionally, where the underground pipe runs X-ing the Trench, the specified pipe shall be laid prior to the block work is commenced or openings shall be formed in the walls (Pipe laying operation by others) Flat width of the crossing shall be in size equal to the value given by the equation “Duct Bank length + 300x2 “Where the dummy trench and the direct buried trench run parallel (Ref Drg Detail 4,sec B) All the operations described in general shall be applicable herein as well with the following amendments / additions to certain activitiesWhile constructing the buried trench, the profile of the dummy trench shall dictate the profile of the buried trench Sloping profile to a grade 1 in 2 shall be formed as shown on the drawingWhere the cable trench crossing with the closed drain pipe trench (Ref drg Detail 6 sec C)All the operations described in general shall be applicable herein as well with the following amendments / additions to certain activitiesThe profile of the cable duct trench shall dictate the profile of the direct buried trenchThe transition of the formations between the trenches and the crossing shall be in grade 1 in 2 as shown on the drawingThe length of the duct bank shall be equal to the value given by the equationWidth of the closed drain trench in mm + 2x100The crossing flat width shall be the duct bank length + 2x300A gap of 100mm shall be kept between the duct bank top and the closed drain bottom surfacesThe duct bank shall be constructed according to the details Cable tiles under the closed drain trench shall be provided in the direct buried trench onlyA joint shall be provided between the pavement and the closed drain trench wall Where direct buried trench crossing under dummy trench(Ref Drg Detail) Sec G & H)All the operations described in general shall be applicable herein as well with the following amendments / additions to certain activitiesA level difference of 350mm shall be kept between the elevations of the crossing formation and the dummy trench The level transition shall be established by grading 1 in 2The cables passing under the dummy trench shall be protected by cable tiles (By others)The trench corner wall shall be constructed to the details showing the corner length on the trench internal face 8485mmWhere trench with dummy Trench crossing under direct buried cable trench (Ref Drg Detail 3 Sec E) All the operations described in general shall be applicable herein as well with the following amendments / additions to certain activitiesStatements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 243: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

243 of

The profile of the cable duct trench shall dictate the profile of the direct buried trenchThe transition of the formations between the trenches and the crossing shall be in grade 1 in 2 as shown on the drawingThe length of the duct bank shall be equal to the value given by the equationWidth of the direct buried cable trench in mm + 2x100The crossing flat width shall be the duct bank length + 2x300A gap of 100mm shall be kept between the duct bank top and the closed drain bottom surfacesThe duct bank shall be constructed according to the details Cable tiles under the closed drain trench shall be provided in the direct buried trench onlyWhere direct buried trench crossing under direct buried cable trench (Ref Drg Detail 7 Section D) All the operations described in general shall be applicable herein as well with the following amendments / additions to certain activitiesA level difference 700 mm shall be kept between direct buried trench and the crossing formation levelThe crossing formation width shall be equal to the value from the equation in mm(direct buried cable trench width + 400x2)The transition of the formations between the trenches and the crossing shall be to grade 1 in 2 as shown on the drawingCable tiles shall be provided in unpaved areas and at trench crossing (By others)Electric Trench Layout at Pumps (Ref Drg Detail 13)All the operations described in general shall be applicable herein as well with the following amendments / additions to certain activitiesThe pump base shall be constructed to the detailsThe trench walls shall be continued to the shape as shown OptionIf so required and felt convenient for certain uniform section reaches, precast concrete units 100 mm thick may be utilised to substitute 150 mm thick walls directly resting on the prepared formationEquipmentExcavatorDumper truckCompactorAttachmentNone#88

Pull pits Top

IndexScopeStatements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 244: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

244 of

Reference documentsDefinitionsResponsibilitiesSafetyMethod EquipmentAttachmentScope This statement is aimed to present the proposed procedures to be adopted to carry out the construction of the Pull Pits ReferencesSpecifications DefinitionsPSM Project Site ManagerCSM Construction ManagerCS Construction SuperintendentSE Site EngineerFM ForemanQC Quality ControlResponsibilitiesPSM shall control the overall operations CM shall arrange the resources required accordingly CS shall control, monitor and direct the SE, FM and workforce for the operationsSE shall be responsible for all the site operations and follow the instructions of the CSFM shall execute the operations deploying the workforce. FM shall explain in full in the language the work persons understand about all the instruction and the ToolBox talks every day and check that the same are followed up regularlyQC shall inspect all the operations according to the specificationsSafetyPrior to the commencement of any activity the labour force shall receive a Toolbox talk relevant to the operation concerned on the project site safety requirements. Any process involving a particular safety risk shall be assessed and addressed as required to raise to a minimum standard / an acceptable mark.All the safety precautions required to be adhered to while working on the excavations, mass concrete, forms, rebars, concrete pouring etc all according to the acceptable standards, shall be adopted on the operations concernedAdequate safety shall be observed during lifting and offloading the precast concrete covers to the relevant locations to avoid any mishap BY OBSERVING THE REGULATORY CRANE FITNESS REQUIREMENT AND VALIDITY OF PERMIT. Only competent personnel shall be engaged to carry out the operationThe crane and the trailer operators shall adhere to all the traffic rules while carrying out the operations and if so required, a banksman be engaged to direct the movementThe crane shall not be operated during the inclement weather conditions with dust storms Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 245: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

245 of

Safety SupervisionA competent inspector shall visit the area daily to assess the safety measures adopted. Any snag observed during the inspection shall be notified to the supervisor present who immediately act to bring the safety measures to an acceptable standard MaterialsMass Concrete of specified grade, Structural concrete of specified grade, Blocks, 16 mm dia GI Lifting Lugs, Rebars all according to requirementMethodThe following operations are involved (Brief description) ( Details on the following page)Operations in prcasting YardForm work to the details shown for Pit type 1 and 2 i.e. P1 and P2Rebars placement to the details shown for Pit type 1 and 2 i.e. P1 and P2Lifting lugs fixing to the details on the sketches attachedPouring concrete & finishing by a steel floatCuring according to specified proceduresLifting & loading by a crane to a trailer for transportationOn site operations- post laying of Cable ductsSetting outExcavation of the pit manually in case of the ducts are not encased in concreteMass concrete base on formation according to the details Concrete protection according to specificationsBlock work in walls according to specificationsUncompacted sand fill only for pit Type 1Compacted backfill only for pit Type 1Placing the precast covers300 mm deep sand backfill over the laid ducts not encased in concreteAs dug compacted backfill above to the specifications Pre casting Area-The existing yard being used for the pre casting of manholes, catch basins and lighting poles foundations etc. shall be employed for this purpose alsoDetails about operations in the pre-casting yardThe typical size of the Pit type 1 cover is 1990x500mm in plan and 200mm deep The typical size of the Pit type 2 cover is 2990x500mm in plan and 200mm deep According to the schedule 71 #s for type 1 and 81#s for type 2 are specified to be constructed On an average 5 units shall be produced by pre casting every day The forms to the exact size with the pre -formed chamfers shall be prepared and erected The steel rebars shall be cut, bent to the required shape, placed with 75mm concrete spacers and positioned into the forms.The Lifting lugs as shown on the sketch shall be fixed in to the correct locations All the supports and the dimensions shall be checked and corrected if requiredCivil Contractor QC inspection shall be conducted from time to time throughout the operationsThe concrete shall be poured to all the prepared units in 1 layers The appropriate vibrator shall be used for the compaction of the concrete After the concrete is poured in full & well compacted, the surface shall be levelled using a wooden float followed by light steel trowelStatements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 246: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

246 of

Immediately after the concrete starts setting, saturated hessian shall be spread over the finished surface covered with polythene sheet according to the specificationsThe side forms shall be removed after the specified period The vertical concrete surfaces shall be draped with the saturated hessian immediately after striking the forms and covered with the polythene sheet according to specificationsThe curing shall be continued for the specified periodCivil Contractor QC inspection shall be conducted from time to time throughout the operationsThe relevant locations shall be made ready to receive the precast units by completing the excavation, mass concrete, the horizontal concrete protection, block walls, backfill and forming the correct alignment The unit shall be lifted by a mobile crane, loaded gently onto a trailer and transported to the location for offloading on to the prepared ‘location to receive’ the unitThe unit shall be installed on the marked location according to the correct orientation to the lighting layout drawingCivil Contractor QC inspection shall be conducted from time to time throughout the operationsDetails about operations on siteThe area around the excavation coverage shall be barricaded to the site requirement based on the direction of the safety inchargeThe setting out shall be carried out by the surveyor to the required coordinatesCivil Contractor QC inspection shall be conducted from time to time throughout the operationsExcavation shall be carried out (manually if the ducts are not encased in concrete) to the specified formation levels i.e. 1300 mm from the finished grade monitored by surveyorCompaction and the tests if so required, shall be carried out accordinglyThe form work for the mass concrete 500mm wide and 150mm thick shall be prepared and erected to the settingsCivil Contractor QC inspection shall be conducted from time to time throughout the operationsConcrete shall be poured to the exact levels, finished properly and cured to the specified proceduresConcrete protection shall be applied to the mass concrete top to the details & specificationsBlock work shall be carried out in 200 mm width as shown on the drawings to the required levels so that the cover placing level is 1050mm from the top of mass concrete including the thickness of the levelling mortar. In case of the ducts are not laid in, opening shall be left in the wallCivil Contractor QC inspection shall be conducted from time to time throughout the operationsUncompacted sand shall be filled as shown on the drawing in case of pit type 1The remaining portion shall be backfilled and compacted to the specification requirement in case of pit type 1The top surface shall be well prepared, compacted and levelled to receive the precast covers in case of pit type 1The top of the block walls shall be given a cement mortar bearing in the form of a levelling course about 20mm thick allowed to be fully set in prior to the precast cover is placed on

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 247: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

247 of

The covers shall be offloaded by a crane from a trailer as transported from the precasting yard to the relevant locations. The covers shall be properly spaced and levelled to the details shown on the drawing#89

Pull pits TopIndexScopeReference documentsDefinitionsResponsibilitiesSafetyMethod EquipmentAttachmentScope This statement is aimed to present the proposed procedures to be adopted to carry out the construction of the Pull Pits References

Specifications DefinitionsPSM Project Site ManagerCSM Construction ManagerCS Construction SuperintendentSE Site EngineerFM ForemanQC Quality ControlResponsibilitiesPSM shall control the overall operations CM shall arrange the resources required accordingly CS shall control, monitor and direct the SE, FM and workforce for the operationsSE shall be responsible for all the site operations and follow the instructions of the CSFM shall execute the operations deploying the work force & Instruct, through the medium of language they understand, all safety precautions to be strictly adhered to as STARRT Card / ToolBox talks every day and ascertain that these are followed up regularlyQC shall inspect all the operations according to the specificationsSafetyPrior to the commencement of any activity the labour force shall receive a Toolbox talk relevant to the operation concerned on the project site safety requirements.

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 248: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

248 of

Any process involving a particular safety risk shall be assessed and addressed to raise the measures to a minimum standard / an acceptable mark.The safety precautions required while working on the excavations, mass concrete, forms, rebars, concrete pouring etc all according to the acceptable standards, shall be strictly adhered to on the operations concernedAdequate safety shall be observed during lifting and offloading the precast concrete covers to the relevant locations to avoid any mishap BY OBSERVING THE REGULATORY CRANE FITNESS REQUIREMENT AND VALIDITY OF PERMIT. Only competent personnel shall be engaged to carry out the operationThe crane and the trailer operators shall abide by all traffic rules while carrying out the operations and if so required, a banksman be engaged to direct the movementThe crane shall not be operated during the inclement weather conditions with dust storms Safety SupervisionA competent inspector shall visit the area daily to assess the safety measures adopted. Any snag observed during the inspection shall be notified to the supervisor present who must immediately act to bring the safety measures to an acceptable standard MaterialsMass Concrete of specified grade, Structural concrete of specified grade, Blocks, 16 mm dia GI Lifting Lugs, Rebars all according to requirementMethodThe following operations are involved Operations in Precasting YardPre casting AreaThe existing yard being used for the pre casting of manholes, catch basins and lighting poles foundations etc. shall be employed for this purpose alsoForm work The typical size of the Pit type 1 cover is 1900x500mm in plan and 200mm deep The typical size of the Pit type 2 cover is 2900x500mm in plan and 200mm deep According to the schedule 71x 6 #s each=426 #s Type 1 and 81x 6 #s each=486 #s Type 2 covers are quantified to be constructed On an average, 20 units shall be produced by pre casting every day The wooden forms to the exact dimensions with pre -formed chamfers shall be prepared and erected Rebars placement The steel rebars shall be cut, bent to the required shape, placed with 75mm concrete spacers and positioned into the forms according to the details shown for type P1 & P2Lifting lugs fixing The Lifting lugs as shown on the attached sketch shall be fixed in to the correct locations All supports and dimensions shall be checked and corrected if requiredCivil Contractor QC inspection shall be conducted before pouring concrete and signatures appended to ITPs Pouring concrete & finishing The concrete shall be poured into all the approved preparatory works in 1 layer by directly delivering from the concrete truck / transit mixer through the chute Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 249: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

249 of

1 # ¾” needle vibrator shall be used to compact the concrete and 1 # reserved standbyAfter the concrete is poured in full & well compacted, the surface shall be levelled using a wooden float followed by light steel trowelCuring Immediately after the concrete is finished, the surface shall be covered with polythene sheet with the edge lapped or tied down to exclude air circulation without permitting the membrane to be in touch with concrete surface according to the specificationsAfter the concrete has stiffened but no longer than 2 hours, the polythene sheet shall be removed followed by immediate covering the surface with saturated( soaked with mix quality water ) hessian and recovered with polythene sheet to prevent evaporation from the hessian. Throughout the curing period the hessian shall be maintained in a permanent wet condition using mix quality water The side forms shall be removed after the specified period of 24 to 36 hours as agreedThe vertical concrete surfaces shall be draped with the saturated hessian immediately after striking the forms and covered with the polythene sheet held firmly in place along all edges & kept continuously wet for duration of curing The curing shall be continued for the specified period of 14 daysCivil Contractor QC inspection shall be conducted from time to time throughout the operationsLifting, loading & transportationThe covers shall be lifted by a mobile crane, loaded gently onto a trailer and transported to the area concerned to offload on to the prepared ‘location to receive’ On site operations- post laying of Cable ductsThe area around the excavation coverage shall be barricaded to the site requirement based on the direction of the Construction SuperintendentSetting out The setting out shall be carried out by the surveyor to the required co-ordinatesCivil Contractor QC inspection shall be conducted throughout the operation and ITP for the survey check signed off Excavation Excavation shall be carried out (manually if the ducts are not encased in concrete) to the specified formation levels i.e. 1300 mm (varying from area to area) from the finished grade monitored by surveyorCompaction and the tests if so required, shall be carried out accordinglyMass concrete base The form work for the mass concrete 500mm wide and 150mm deep shall be prepared and erected to the settingsCivil Contractor QC inspection shall be conducted from time to time throughout the operations and concrete pour ITPs signed offConcrete shall be poured to the exact levels, finished properly and cured to the specified proceduresConcrete protection Concrete protection shall be applied to the mass concrete to the details & specificationsBlock work in walls Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 250: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

250 of

200mm Block work shall be carried out as shown on the drawings to the required levels so that the cover top level is 100mm from the finished grade / ground level.In case the ducts are not laid in, opening shall be provided in the wallCivil Contractor QC inspection shall be conducted from time to time throughout the operationsUncompacted sand fill Uncompacted sand shall be filled as shown on the drawing & in accordance with the specifications Compacted backfill The remaining portion shall be backfilled and compacted to the specification requirement The top surface shall be well prepared, compacted and levelled to receive precast covers Placing the precast coversThe covers shall be offloaded by a crane from a trailer as transported from the precasting yard to the relevant locations. The covers shall be properly spaced and levelled to the details shown on the drawingSand fill300mm deep sand backfill shall be carried out over the laid ducts not encased in concrete

BackfillAs dug compacted backfill shall be carried out above the sandfill to the specifications Civil Contractor QC inspection shall be conducted from time to time throughout the operations with the relevant ITPs signed offLugs FillThe sand shall be filled in the lifting lugs recessConcrete ProtectionThe exposed concrete surface is a part of pavement and therefore no protection shall be appliedEquipmentTransit mixer, Trailor, Vibrator, Crane,Attachment3 # Sketch -showing the lifting lugs arrangement

#89

Pull pits Top

IndexScopeReference documentsSafetyMethod EquipmentStatements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 251: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

251 of

AttachmentScope This statement is aimed to present the proposed procedures to be adopted to carry out the construction of the Pull Pits ReferencesSpecifications SafetyPrior to the commencement of any activity the labour force shall receive a Toolbox talk relevant to the operation concerned on the project site safety requirements. Any process involving a particular safety risk shall be assessed and addressed to raise the measures to a minimum standard / an acceptable mark.The safety precautions required while working on the excavations, mass concrete, forms, rebars, concrete pouring etc all according to the acceptable standards, shall be strictly adhered to on the operations concernedAdequate safety shall be observed during lifting and offloading the precast concrete covers to the relevant locations to avoid any mishap BY OBSERVING THE REGULATORY CRANE FITNESS REQUIREMENT AND VALIDITY OF PERMIT. Only competent personnel shall be engaged to carry out the operationThe crane and the trailer operators shall abide by all traffic rules while carrying out the operations and if so required, a banksman be engaged to direct the movementThe crane shall not be operated during the inclement weather conditions with dust storms Safety SupervisionA competent inspector shall visit the area daily to assess the safety measures adopted. Any snag observed during the inspection shall be notified to the supervisor present who must immediately act to bring the safety measures to an acceptable standard MaterialsMass Concrete of specified grade, Structural concrete of specified grade, Blocks, 16 mm dia GI Lifting Lugs (Exposed portion only), Rebars all according to requirementMethodThe following operations are involved Operations in Precasting YardPre casting AreaThe existing yard being used for the pre casting of manholes, catch basins and lighting poles foundations etc. shall be employed for this purpose alsoForm work The typical size of the Pit type 1 cover is 1900x500mm in plan and 200mm deep The typical size of the Pit type 2 cover is 2900x500mm in plan and 200mm deep According to the schedule 71x 6 #s each=426 #s Type 1 and 81x 6 #s each=486 #s Type 2 covers are quantified to be constructed On an average, 20 units shall be produced by pre casting every day The wooden forms to the exact dimensions with pre -formed chamfers shall be prepared and erected Rebars placement Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 252: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

252 of

The steel rebars shall be cut, bent to the required shape, placed with 75mm concrete spacers and positioned into the forms according to the details shown for type P1 & P2Lifting lugs fixing The Lifting lugs as shown on the attached sketch shall be fixed in to the correct locations All supports and dimensions shall be checked and corrected if requiredCivil Contractor QC inspection shall be conducted before pouring concrete and signatures appended to ITPs Pouring concrete & finishing The concrete shall be poured into all the approved preparatory works in 1 layer by directly delivering from the concrete truck / transit mixer through the chute 1 # ¾” needle vibrator shall be used to compact the concrete and 1 # reserved standbyAfter the concrete is poured in full & well compacted, the surface shall be levelled using a wooden float followed by light steel trowelCuring Immediately after the concrete is finished, the surface shall be covered with polythene sheet with the edge lapped or tied down to exclude air circulation without permitting the membrane to be in touch with concrete surface according to the specificationsAfter the concrete has stiffened but no longer than 2 hours, the polythene sheet shall be removed followed by immediate covering the surface with saturated( soaked with mix quality water ) hessian and recovered with polythene sheet to prevent evaporation from the hessian. Throughout the curing period the hessian shall be maintained in a permanent wet condition using mix quality water The side forms shall be removed after the specified period of 24 to 36 hours as agreedThe vertical concrete surfaces shall be draped with the saturated hessian immediately after striking the forms and covered with the polythene sheet held firmly in place along all edges & kept continuously wet for duration of curing The curing shall be continued for the specified period of 14 daysCivil Contractor QC inspection shall be conducted from time to time throughout the operationsLifting, loading & transportationThe covers shall be lifted by a mobile crane, loaded gently onto a trailer and transported to the area concerned to offload on to the prepared ‘location to receive’ On site operations- post laying of Cable ductsThe area around the excavation coverage shall be barricaded to the site requirement based on the direction of the Construction SuperintendentSetting out The setting out shall be carried out by the surveyor to the required co-ordinatesCivil Contractor QC inspection shall be conducted throughout the operation and ITP for the survey check signed off Excavation Excavation shall be carried out (manually if the ducts are not encased in concrete) to the specified formation levels i.e. 1300 mm (varying from area to area) from the finished grade monitored by surveyorCompaction and the tests if so required, shall be carried out accordinglyStatements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 253: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

253 of

Mass concrete base The form work for the mass concrete 500mm wide and 150mm deep shall be prepared and erected to the settingsCivil Contractor QC inspection shall be conducted from time to time throughout the operations and concrete pour ITPs signed offConcrete shall be poured to the exact levels, finished properly and cured to the specified proceduresConcrete protection Concrete protection shall be applied to the mass concrete to the details & specificationsBlock work in walls 200mm Block work shall be carried out as shown on the drawings to the required levels so that the cover top level is 100mm from the finished grade / ground level.In case the ducts are not laid in, opening shall be provided in the wallCivil Contractor QC inspection shall be conducted from time to time throughout the operationsUncompacted sand fill Uncompacted sand shall be filled as shown on the drawing & in accordance with the specifications Compacted backfill The remaining portion shall be backfilled and compacted to the specification requirement The top surface shall be well prepared, compacted and levelled to receive precast covers Placing the precast coversThe covers shall be offloaded by a crane from a trailer as transported from the precasting yard to the relevant locations ready with one layer 0.25mm thick polythene sheet with laps 300mm, spread over. The covers shall be properly spaced and levelled to the details shown on the drawingSand fill300mm deep sand backfill shall be carried out over the laid ducts not encased in concreteBackfillAs dug compacted backfill shall be carried out above the sandfill to the specifications Civil Contractor QC inspection shall be conducted from time to time throughout the operations with the relevant ITPs signed offLugs FillThe sand shall be filled in the lifting lugs recessConcrete ProtectionThe exposed concrete surface is a part of pavement and therefore no protection shall be appliedEquipmentTransit mixer, Trailor, Vibrator, Crane,Attachment3 # Sketch -showing the lifting lugs arrangement

#90

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 254: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

254 of

Road crossing to make goodWearing course over completed1# for 14” desalinated water&1# for 8”potable waterAvenue ‘c’ TopIndexScopeReference documentsDefinitionsResponsibilitiesSafetyMethod including traffic management schemeEquipmentAttachmentScopeThe statement is aimed to propose the procedures to be adopted to carry out to make good the wearing course over the completed road crossing to facilitate the smooth traffic plying.The pipe lines 1 # each 14” Desalinated water and 8” Potable water at locations identified on attached drawing for this X-ing were completed to the following referencesReference documentsSpecification. Excavation & Backfilling for Underground structures.Drawing No. -Easement Systems Avenue “C”Piping Interconnection Drawings, Avenue ‘C’ DefinitionsPSM Project Site ManagerCSM Construction ManagerCS Construction SuperintendentSE Site EngineerFM ForemanQC Quality ControlResponsibilitiesPSM shall control the overall operations

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 255: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

255 of

CM shall arrange the resources required accordingly and be overall responsible for the excavation operationCS shall control, monitor and direct the SE, FM and workforce for the operationsSE shall be responsible for all the site operations and follow the instructions of the CSAny mishap on the excavation operation shall immediately be notified to the CS and the CM for the immediate action if so required for any possible remedy or record or the authority review whatsoever,the case may beFM shall execute the operations deploying the workforce. FM shall explain in full in the language the work persons understand about all the instruction and the ToolBox talks every day and check that the same are followed up regularlyQC shall inspect all the operations according to the specificationsEPC Contractor shall conduct surveillanceSafetyPrior to the commencement of any activity the labour force shall receive a Toolbox talk relevant to the operation concerned on the project site safety requirements. Any process involving a particular safety risk shall be assessed and addressed as required to raise to a minimum standard / an acceptable mark.In the present case the minor debris removal / excavation has to be carried out on the Operating Authority area, therefore all the regulated precautions shall be resorted to effect a full safety standard.ToolBox Talks- While conducting ToolBox Talks, every precautionary measure to be adopted shall be explained expressely to all the personnel and translated to the language understood by themOnly English literate Foreman shall be employed to work on the critical execution. Excavation Work Permit- A copy of the work permit shall be posted on a mini board installed on site to be noticeable to all the relevant persons involved on the crossingTraffic Management-Sign boards keep up- All the personnel shall be briefed about the safe keep up of the boardsBarricades,cones, markers and the night-lights, flood lights etc. shall be arranged as required for a complete safety. No oil spillage shall be allowed. The barriers shall be placed to indicate the excavation work in progressFlagman-On both the direction, in addition to the traffic sign boards, a flagman shall be engaged to operate full time to direct the traffic about the excavation work in progress by waving the flag for all the vehicles passing byJack Hammer- The workers if engaged on operating this equipment shall use protective glass and work in phases with pause intervals. The compressor air pressure shall be monitored from time to time so that the hammer works smoothly. The compressor shall be place within the barricade limits Machine ExcavationThe operators shall be explicitly explained and instructed about the requirement of the reverse signal and sound when operating reverse. The truck driver shall also be instructed similarly. Banksman shall be engaged while the equipment operate.No violation of the traffic rules shall be allowedSafety SupervisionStatements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 256: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

256 of

A competent inspector shall inspect the trench daily to assess the safety measures adopted. MethodThe required permit to work shall be obtained from the Plant Refinery Division.A traffic management scheme has been presented herein and shall be produced on site as detailed on the attached sketch for this road crossing which includes, reduced speed sign, temporary diverted roads sign, men at work sign, warning signs, informatory signs, safety barriers, night lighting and road cleaning activities. The traffic management scheme shall be reviewed and approved by EPC Contractor prior to commencing the work.The aforesaid traffic management scheme shall be implemented as described below:TRAFFIC MANAGEMENT SCHEME ROAD CROSSING – First Street / Avenue ‘C’Drawing reference –This completed crossing is located on the Road Avenue ‘C’ between the followingCo-ordinates as shown on the referred drawing.

This is a 2-way road with a central verge and carrying 2 lanes on either wayThe proposed crossing is located about 60 m from 1st street road towards NorthOne serving electric pole is located away from the x-ing to NorthThe minor irrigation / hoses are lying disconnectedSome minor trees and plants are arboricultured on the central verge.The road shall be divided in 2 parts as shown on the sketch as lane L1 and L 2 on either side of the carriageway.In the first instance the work shall be carried out on part L1 diverting the traffic to the road portion on the part L2 as shown on the sketch.In the second instance the work shall be carried out on part L2 diverting the traffic to the road portion on the completed road portion on the part L1 as shown on the sketch.The directory signboards shall also be placed on the 1st street road East West on both ways to indicate the work at the crossingFor the traffic North to South the first reduce speed for traffic diversion informatory board depicting shall be located at 300 m from the point of the proposed crossing, the second depicting diversion signs be located at 200 m and the third depicting men at work sign be located at 100 m on either way in the opposite directions.For the traffic South to North past crossing, one sign shall be placed to direct for the diversion, to slow down and the men at work aheadA Flagman shall be engaged full time on both the directions to guide the traffic about the ongoing excavation operations in addition to the conventional signboardsThe following activities are involved. Reference to the marked note ‘B’ on the Easement Systems Drawing To produce the Traffic Diversion Management SchemeTo excavate mechaniclly the loose wearing portion to a depth so that a total concrete thickness of 70 mm is pouredTo have authority inspectionTo pour the concreteTo reinstate the central verge to the existing stateStatements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 257: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

257 of

DetailsThe Traffic Management Scheme shall be executed as explained in the foregoing and to the traffic manual directions.The first section of the proposed road crossing as per the attached sketch shall be marked by the surveyor on the actual location. The debris / asphalt shall be cut using jackhammers or grader to the require levels so that a final concrete thickness 70mm be pouredThe excavated material shall be removed from the site to stockpile area.The excavated trench shall be inspected by the authorities as required.A concrete slab shall be cast up to the bottom of the finished asphalt level.The traffic management system shall be removed after the road crossing has been cleaned of any debris or obstructions.Either side of the road shall be provided with cable markers to indicate the servicesMajor EquipmentGrader,Excavator,Dump trucks.Compactors.Jack Hammer, Compressor, AttachmentSketch showing the traffic management scheme

#91

Road crossing to make goodWearing course over completed132 kv electric cableAvenue ‘c’TopIndexScopeReference documentsDefinitionsResponsibilitiesSafetyMethod including traffic management schemeEquipmentAttachmentScopeThis statement is aimed to propose the procedures to be adopted to carry out to make good the wearing course over the completed road crossing to facilitate smooth traffic plying. Laying of 132 KV electric cable at location identified on the reference drawing for this X-ing has been completed Reference documentsSpecification. Excavation

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 258: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

258 of

Drawing No. -Easement Systems Avenue “C”DefinitionsPSM Project Site ManagerCSM Construction ManagerCS Construction SuperintendentSE Site EngineerFM ForemanQC Quality ControlResponsibilitiesPSM shall control the overall operations CM shall arrange the resources required accordingly and be overall responsible for the excavation operationCS shall control, monitor and direct the SE, FM and workforce for the operationsSE shall be responsible for all the site operations and follow the instructions of the CSAny mishap on the crossing operation shall immediately be notified to the CS and the CM for the immediate action if so required, for any possible remedy or record or the relevant authority review whatsoever the case may beFM shall execute the operations deploying the work force .and instruct in full in the medium of language the work persons understand about all the required measuresand the STARRT / ToolBox talks every day and check that the same are followed up regularlyQC shall inspect all the operations according to the specifications & ITP requirementSafetyPrior to the commencement of any activity the labour force shall receive a STARRT Card / Toolbox talk relevant to the operation concerned on the project site safety requirements. Any process involving a particular safety risk shall be assessed and addressed as required to raise to a minimum standard / an acceptable mark.In this case the minor debris removal / excavation has to be carried out on the Operating Authority area, therefore all the regulated precautionary measures shall be strictly adhered toToolBox Talks While conducting ToolBox Talks, every precautionary measure to be adopted shall be explicitly instructed to all personnel to abide by through the medium of language they understandA Foreman who also understands English shall be employed to work on the critical execution. Excavation Work Permit A copy of the work permit shall be posted on a mini board installed on site to be noticeable to all the relevant persons involved on the crossingBarricades, cones, markers and the night-lights, flood lights etc. shall be arranged as required for a complete safety. The barriers shall be placed to indicate the excavation work in progressFlagman-On both the direction, in addition to the traffic sign boards, a flagman shall be engaged full time to direct the traffic about the excavation work in progress by means of flag signal to all vehicles passing by

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 259: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

259 of

Jack Hammer- The workers if engaged on operating this equipment shall use protective glass and work in phases with pause intervals. The compressor air pressure shall be monitored from time to time so that the hammer works smoothly. The compressor shall be place within the barricade limits Machine ExcavationThe operators shall be explicitly instructed about the requirement of the reverse signal and sound when operating reverse. The truck driver shall also be instructed similarly. Banksman shall be engaged while the equipment operate.No violation of the traffic rules shall be allowedNo oil spillage shall be allowedSafety SupervisionA competent inspector shall inspect the area daily to assess the safety measures adopted. MethodThe required permit to work shall be obtained from the Plant Refinery Division.A traffic management scheme has been presented herein and shall be produced on site as detailed on the attached sketch for this road crossing which includes, reduced speed sign, temporary diverted roads sign, men at work sign, warning signs, safety barriers, night lighting and road cleaning activities. The traffic management scheme shall be reviewed and approved by EPC Contractor prior to commencing the work.The aforesaid traffic management scheme shall be implemented as described below:TRAFFIC MANAGEMENT SCHEME ROAD CROSSING – First Street / Avenue ‘C’Drawing reference –This completed crossing is located on the Road Avenue ‘C’ between the followingCo-ordinates as shown on the referred drawing.This is a 2-lane dual carriageway road with a central verge This crossing is located about 60 m from 1st street road towards NorthOne serving electric pole is located away from the crossing to NorthThe minor irrigation / hoses are lying disconnectedSome minor trees and plants are growing on the central verge.The road shall be divided in 2 parts as shown on the sketch as lane L1 and L 2 on either side of the carriageway.In the first instance the work shall be carried out on part L1 diverting the traffic to the road portion on the part L2 as shown on the sketch.In the second instance the work shall be carried out on part L2 diverting the traffic to the road portion on the completed portion on the part L1 as shown on the sketch.The directory signboards shall also be placed on the 1st street road East West on both ways to indicate the work at the crossingFor the traffic North to South, the first informatory board for traffic depicting ‘reduce speed’ shall be located at 300 m from the point of the proposed crossing, the second depicting ‘diversion’ signs be located at 200 m and the third depicting ‘men at work ‘sign be located at 100 m on either way in the opposite directions.For the traffic South to North past crossing, one signboard shall be located to depict ‘diversion’, ‘slow down’ and ‘the men at work ahead’Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 260: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

260 of

A Flagman shall be engaged full time on both the directions to guide the traffic about the ongoing excavation operations in addition to the conventional signboardsThe following activities are involved. The Traffic Diversion Management Scheme shall be executed as explained in the foregoing and to the traffic manual requirement reflected on the attached sketchThe first section of the crossing shall be marked by the surveyor on the actual location. The debris / asphalt shall be cut using jackhammers or grader to the required level so that a final concrete thickness 70mm can be pouredThe excavated material shall be removed from the site to stockpile area.Concrete wearing slab 70mm thick shall be cast up to the finished asphalt level These activities shall be repeated for the second section after the first is completedThe traffic management system shall be removed after the road crossing has been cleared of all debris or obstructions.Civil Contractor QC inspection shall be conducted to the ITP requirementEither side of the road shall be provided with cable markers to indicate the servicesIn future, after the completion of the proposed pipe laying operations(For which the methodology is included separately, ref. method statement # 86), an approved asphalt wearing course shall be laid to the requirement to replace 70mm concrete pavingMajor EquipmentGrader,Excavator,Dump trucks.Compactors.Jack Hammer, Compressor, AttachmentSketch showing the traffic management scheme Civil Contractor QC inspection shall be conducted from time to time throughout the operationsThe sand shall be filled in the lifting lugs recessThe exposed concrete surface is a part of pavement and therefore no protection shall be appliedEquipmentTransit mixer, Trailor, Vibrator, Crane,Attachment4 # Sketch -showing the lifting lugs arrangement

#92

Road crossingTo make good (temporarily)Wearing course over completed

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 261: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

261 of

132 kv electric cableAvenue ‘c’TopIndexScopeReference documentsSafetyMethod including traffic management schemeEquipmentAttachmentScopeThis statement is aimed to propose the procedures to be adopted to carry out to make good the wearing course over the completed road crossing to facilitate smooth traffic plying. Laying of 132 KV electric cable at location identified on the reference drawing for this X-ing has been completed Reference documentsSpecification. Excavation Drawing No. SafetyPrior to the commencement of any activity the labour force shall receive a STARRT Card / Toolbox talk relevant to the operation concerned on the project site safety requirements. Any process involving a particular safety risk shall be assessed and addressed as required to raise to a minimum standard / an acceptable mark.In this case the minor debris removal / excavation has to be carried out on the Operating Authority area, therefore all the regulated precautionary measures shall be strictly adhered toToolBox Talks While conducting ToolBox Talks, every precautionary measure to be adopted shall be explicitly instructed to all personnel to abide by through the medium of language they understandA Foreman who also understands English shall be employed to work on the critical execution. Excavation Work Permit A copy of the work permit shall be posted on a mini board installed on site to be noticeable to all the relevant persons involved on the crossingBarricades, cones, markers and the night-lights, flood lights etc. shall be arranged as required for a complete safety. The barriers shall be placed to indicate the excavation work in progressFlagman-On both the direction, in addition to the traffic sign boards, a flagman shall be engaged full time to direct the traffic about the excavation work in progress by means of flag signal to all vehicles passing byJack Hammer- The workers if engaged on operating this equipment shall use protective glass and work in phases with pause intervals. The compressor air pressure shall be monitored from time to time so that the hammer works smoothly. The compressor shall be place within the barricade limits

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 262: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

262 of

Machine ExcavationThe operators shall be explicitly instructed about the requirement of the reverse signal and sound when operating reverse. The truck driver shall also be instructed similarly. Banksman shall be engaged while the equipment operate.No violation of the traffic rules shall be allowedNo oil spillage shall be allowedSafety SupervisionA competent inspector shall inspect the area daily to assess the safety measures adopted. MethodThe required permit to work shall be obtained from the Plant Refinery Division.A traffic management scheme has been presented herein and shall be produced on site as detailed on the attached sketch for this road crossing which includes, reduced speed sign, temporary diverted roads sign, men at work sign, warning signs, safety barriers, night lighting and road cleaning activities. The traffic management scheme shall be reviewed and approved by EPC Contractor prior to commencing the work and agreed with Plant Refinery Division.The aforesaid traffic management scheme shall be implemented as described below:TRAFFIC MANAGEMENT SCHEME ROAD CROSSING – First Street / Avenue C’This crossing is located about 83 m from center line of 1st street road towards NorthThe road shall be divided in 2 parts as shown on the sketch as lane L1 and L 2 on either side of the carriageway.In the first instance the work shall be carried out on part L1 diverting the traffic to the road portion on the part L2 as shown on the sketch.In the second instance the work shall be carried out on part L2 diverting the traffic to the road portion on the completed portion on the part L1 as shown on the sketch.Signboards shall be positioned as shown on the sketchA Flagman shall be engaged full time on both the directions to guide the traffic about the ongoing excavation operations in addition to the conventional signboardsThe temporary stone surface on lane L1 shall be excavated to a depth of 70mm and replaced by mass concrete to level with the adjacent asphalt. Traffic shall be allowed on to the concrete after 2 days and the operation shall be repeated for lanes L2 All excavated material shall be removed to an approved tipping area. The concrete surface shall be replaced by asphalt to the same specification as the existing construction at the earliest opportunityMajor EquipmentGrader,Excavator,Dump trucks.Compactors.Jack Hammer, Compressor, AttachmentSketch showing the traffic management scheme

#93

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 263: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

263 of

Drinking water connectionTopIndexScopeReference documentsDefinitionsResponsibilitiesSafetyMethodEquipmentAttachmentScopeThe purpose of this method statement, is to define the procedure that shall be adopted for the connection and laying of the pipeline, from the Operating Authority supply pit No 21, to the Civil Contractor camp.Reference documentsExcavation permit.DefinitionsOperating Authority Abu Dhabi National Oil Company.EPC Contractor Civil Contractor . PSM Project Site Manager.ResponsibilitiesThe Civil Contractor PSM shall ensure this method statement is implementation for the connection and laying of the drinking water pipeline.SafetyThe Safety Officer shall monitor the daily activities, advising and implementing all safety procedures.MethodThe proposed drinking water connection location and route of the pipeline, shall be defined upon a drawing, which shall be reviewed and approved by Operating Authority.The approved pipeline route drawing shall define the materials and fitting locations.All trenching activities shall be excavated by hand. The excavated material shall be stockpiled for re-use as fill material. The pipe trench shall be excavated to a depth of 500mm.All stones and hard materials from the bottom of the trench shall be removed. The pipe shall be located within the trench. Selected backfill shall be placed around the pipe. The trench shall be backfilled with the excavated material. Any surplus material shall be removed from site. The laying and connection of the pipes shall be conducted by experienced people. Where the pipeline passes beneath a roadway, a sleeve pipe shall be incorporated to protect the water pipe from damage.Testing of the pipes shall be conducted to ensure that leakage does not occur.Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 264: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

264 of

Marker posts to indicate a buried service shall be installed upon completion of backfilling and clearing of the site.EquipmentHand tools.Pipe jointing and cutting tools.AttachmentWork permit.Drawing Site Sketch #94

Protection to transformer foundation sides in sub stationswith aluminium bead termination for below ground and masterseal 300h for above ground in gravel fill areaTopIndexScopeReference documentsDefinitionsResponsibilitiesSafetyMethod EquipmentAttachmentScope This statement is aimed to propose the procedures to be adopted to protect the vertical surfaces of the transformer bases concrete using Aluminium Beads to clampin the waterproofing membrane termination around the foundation sides and apply concrete protection coating on the surfaces above ground ReferencesMain Substation Drawing Transformer Foundations Sec A & D and the relevant drawings for all other sub stationsSpecifications- DefinitionsPSM Project Site ManagerCSM Construction ManagerCS Construction SuperintendentSE Site EngineerFM ForemanQC Quality Control

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 265: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

265 of

ResponsibilitiesPSM shall control the overall operations CM shall arrange the resources required accordingly CS shall control, monitor and direct the SE, FM and workforce for the operationsSE shall be responsible for all the site operations and follow the instructions of the CSFM shall execute the operations deploying the workforce. FM shall explain in full in the language the work persons understand about all the instruction and the toolbox talks every day and check that the same are followed up regularlyQC shall inspect all the operations according to the specificationsEPC Contractor shall conduct surveillanceSafetyPrior to the commencement of work, the labour force shall receive a toolbox talk on the Project Site Safety requirements relevant to the application of below ground and above ground concrete surface protection operations

Any process which may involve a particular Safety risk shall be assessed to the requirement for Site conditions and be taken care of. The personnel shall use the PPE, gloves, masks, eyeglasses etc. Care shall be taken during use and storage to avoid contact with eyes, mouth, skin and foodstuffs. To avoid skin contact, use of barrier cream to protect from the adverse effect of sealant and other chemicals application shall also be made.Industrial cleaner shall be used followed by washing with soap and water.The containers shall be resealed after use. Immediate medical attention shall be called for in case of any adverse effect to the personnel handling the productDamaged tins shall be disposed off according to the state regulations.Material safety data shall also be referred to for disposal and any further information.A safety inspector shall visit the site every day and instruct the supervisor in case any snag is observed who immediately implement the instructions accordingly.MaterialsBitustick XL Polybit MAR 003Aluminium Bead lengths to the Sectional dimensions 30 mm x 2 mmFixing screws 3 mm diaJoint filler Alpex Joint Fill BCR MAR 008Sealant- Polyurethane-Gun Grade Cold seal 200PF for horizontal usage on Aluminium strip (Manufacturer BCR) (Emirates Specialities) or equivalent MAR Masterseal 300H MBT MAR 059Masterseal 181S Primer systemMasterseal 300H fillerStorageThe manufacturer’s instructions shall be followed for this purpose.

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 266: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

266 of

The material shall be stored under cover out of direct sunlight and protected from temperature extremes.

MethodWaterproofing membrane shall be applied according to the specifications to the defined levels keeping the top 50 mm above the gravel fill Marking shall be made to the exact line and level as per drawingRequired lengths to the exact site dimensions shall be cut to suit a close fit between the bead endsEvery bead shall be fixed with screws @ 400mm centres drilled and tightened to the concrete penetrating the membraneThe screws shall be drilled and fixed using an electrical operated equipment After the screws are drilled in with the beads in proper alignment / location, compressed fibre shall be installed as protection over the Bitustick XL membrane as specifiedCivil Contractor QC inspection shall be conducted followed by EPC Contractor approvalThe vertical surface above the bead as well as a 50mm wide strip around the top periphery of the foundation shall be prepared for the above ground concrete protection and Master seal 300 H be applied to the manufacturer’s instructionsThis application involves the following sequencesCleaning and making up the surfacePriming the surfaceCoating the surfacePreparationAll surfaces shall be free from oil, grease, friable matters and curing compound. The surfaces shall be cleaned from dust / sand using compressed air. Arrises shall be rounded off and the protrusions ground so that the resulting surfaces appear smooth.The surfaces shall be brush primed with Masterkure 181S and subsequently Masterseal 300H mixed with Masterseal 300 H filler applied as a scrape coat over blow holes and depressions.The primed surface shall be allowed to dry tack free for a minimum duration of 2 hours before applying Masterseal 300H coating.ApplicationThe areas to be coated shall be protected from direct sunlight by shading in the hot weather conditions. At the time of coating application the ambient temperature shall be more than 5 degree Celsius with humidity less than 90 % and no dusty weather Masterseal 300 H shall be applied directly from the containers using a brush or roller @ 0.8 litre per sqm surface coverage to achieve a continuous coating The continuous coating shall be achieved in 1 or 2 coats of applicationThe coating shall be protected from the humidity for 24 hours / or until it dries out using polythene sheets keeping off the area.No post application curing is required

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 267: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

267 of

Civil Contractor QC inspection shall be conducted followed by EPC Contractor approvalApplication of sealant after 24 hours The material shall be applied using a sealant gun fitted with conical nozzles adjustable to suit the widthThe sealant shall be gunned into the junction using an even trigger pressure,The nozzle shall be cleaned occasionally to avoid contamination.A smaller timber spatula soaked in soapy water shall be used to compact the sealant into the joint for a smooth polish finish formation. The mixing and application equipment shall be cleaned immediately after useCivil Contractor QC inspection shall be conducted followed by EPC Contractor approvalEquipmentElectrical operated drillSealant applying gunBrush and rollerAttachmentNone#95

Timber doors fixingAdministration buildingTop

IndexScopeReference documentsDefinitionsResponsibilitiesSafetyMethod EquipmentAttachmentScope This statement is aimed to present the proposed procedures to be adopted to carry out the fixing of the workshop / factory builtin wooden doors to the exact locations on the prepared openings left in the walls

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 268: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

268 of

ReferencesSpecifications MAR Teak WoodDefinitionsPSM Project Site ManagerCSM Construction ManagerCS Construction SuperintendentSE Site EngineerFM ForemanQC Quality ControlResponsibilitiesPSM shall control the overall operations CM shall arrange the resources required accordingly CS shall control, monitor and direct the SE, FM and workforce for the operationsSE shall be responsible for all the site operations and follow the instructions of the CSFM shall execute the operations deploying the workforce. FM shall explain in full in the language the work persons understand about all the instruction and the ToolBox talks every day and check that the same are followed up regularlyQC shall inspect all the operations according to the specificationsEPC Contractor shall conduct surveillanceSafetyPrior to the commencement of work, the labour force shall receive a Toolbox talk relevant to the operation concerned to the Project Site Safety requirements. Any process that is adopted which may have a particular Safety risk shall be assessed to the requirement for Site conditions and be taken care of. The personnel shall use the PPE, gloves, masks (for gas leak in area), eyeglasses (during dusty winds) etc Adequate arrangement shall be made to provide access to the top of the wall.A safety inspector shall visit the site every day and instruct the supervisor in case any snag is observed who immediately implement the instructions accordingly.MaterialsMaterial from Aldiar UAE1 hour fire rated, ½ hour fire ratedMethodThe following operations are involvedEquipmentAttachmentNone#96

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 269: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

269 of

Grouting to steel tanks bearings on ring beamsTopIndexScopeReference documentsDefinitionsResponsibilitiesSafetyMethodEquipmentScopeThe statement is aimed to propose the procedures to be adopted to grout the space between the top of the ring beams and the steel tank base plate(acting as bearing) according to the following drawings and the specifications.Reference Documents.Drgs Demineralised Water TankDrgs Spent Caustic Storage TankDrgs Fire Water Storage TankDrgs Fire Water Storage TankDrgs Caustic Storage TankDrgs Neutralisation Tank Water TankSpecification DefinitionsPSM Project Site ManagerCSM Construction ManagerCS Construction SuperintendentSE Site EngineerFM ForemanQC Quality ControlResponsibilitiesPSM shall control the overall operations CM shall arrange the resources required accordingly CS shall control, monitor and direct the SE, FM and workforce for the operationsSE shall be responsible for all the site operations and follow the instructions of the CSFM shall execute the operations deploying the workforce. FM shall explain in full in the language the work persons understand about all the instruction and the toolbox talks every day and check that the same are followed up regularlyQC shall inspect all the operations according to the specifications

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 270: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

270 of

SafetyPrior to the commencement of work, the labour force shall receive a STARRT Card / Toolbox talk on the Project Site Safety requirements relevant to the application of Masterflow 928T MBT grouthing material according to the manufacturer’ s instruction and the filling the sand into minutely narrow spaces The personnel shall use the PPE, gloves, masks, eyeglasses etc. Care shall be taken during use and storage to avoid contact with eyes, mouth, skin and foodstuffs. To avoid skin contact, use of barrier cream to protect from the adverse effect of grouting material shall also be made.Industrial cleaner shall be used followed by washing with soap and water.The containers shall be resealed after use. Immediate medical attention shall be called for in case of any adverse effect to the personnel handling the productMaterial safety data shall be referred to for disposal and any further information.A safety inspector shall visit the site every day and instruct the supervisor in case any snag is observed who immediately implement the instructions accordingly.MethodRefer to the sketch attachedThe space to be grouted shall be cleaned to remove all dirt and loose particles using compressed air The surrounding area shall be shaded to avoid the effects of temperature extremesThe grouting operation shall be carried out in pieces on the tank circumferenceThe surface shall be soaked in water for 24 hours prior to conmmence the operationsSandfilling shall be carried out into the spaces leaving a clear portion 200 mm wide for the grouting purpose. A backing rod 25 mm dia shall be provided as shown on the sketchThe space to be filled in various locations shall be prepared by form strips of the size equal to the thickness of the grout circumferentially and radially. The pouring end shall be kept open and after the pouring is completed in the prepared area, shall be closedAn electric drill fitted with a paddle mixer shall be used for the grout mixing purpose. The mixer shall be cleaned with no standing water.Using water @ 3.5 to 4.5 litres per 25 kg bag of Master flow 928T according to the requirement, the mixing shall be carried out as follows 90 % of the measured quantity of water required to achieve the desired consistency according to the batch volume shall be added to the mixer followed by the grout material Masterflow 928 T added gradually.The remaining 10 % water quantity shall be poued during mixing, which has to be kept continued for at least 3 to 5 minutes until a uniform lump free consistency is achieved.Civil Contractor QC inspection shall be conducted according to the ITP requirementThe grout shall be poured continuously using the pour cone with a constant hydrostatic head of at least 15 cm Civil Contractor QC inspection shall be conducted according to the ITP requirement

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 271: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

271 of

After pouring the grout Masterflow 928 in place, all the exposed surfaces shall be covered with clean and damp Hessian to keep the applied material moist until it is firm enough to accept a curing membraneThe specified temperature range(4 to 32 degree C) shall be maintained for the 3 post pour continuous daysThe grout thickness varies between 25 to 35 mm.Major EquipmentPeddle MixerGrout Flow ConeAttachmentSketch#97

Grouting to steel tanks bearings on ring beams

TopIndexScopeReference documentsSafetyMethodEquipmentScopeThe statement is aimed to propose the procedures to be adopted to grout the space between the top of the ring beams and the steel tank base plate(acting as bearing) according to the following drawings and the specifications.Reference Documents.Drgs Demineralised Water TankDrgs Spent Caustic Storage TankDrgs Fire Water Storage TankDrgs E Fire Water Storage TankDrgs Caustic Storage TankDrgs Neutralisation Tank Water TankSpecification SafetyPrior to the commencement of work, the labour force shall receive a STARRT Card / Toolbox talk on the Project Site Safety requirements relevant to the application of Masterflow 928T

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 272: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

272 of

MBT grouting material according to the manufacturer’ s instruction and the filling the sand into minutely narrow spaces The personnel shall use the PPE, gloves, masks, eyeprotection etc. Care shall be taken during use and storage to avoid contact with eyes, mouth, skin and foodstuffs. To avoid skin contact, use of barrier cream to protect from the adverse effect of grouting material shall also be made.Industrial cleaner shall be used followed by washing with soap and water where grout comes in contact with skin.Immediate medical attention shall be called for in case of any adverse effect to the personnel handling the productMaterial safety data shall be referred to for disposal and any further information.A safety inspector shall visit the site every day and instruct the supervisor in case any snag is observed who immediately implement the instructions accordingly.MethodRefer to the sketch attachedThe space to be grouted shall be cleaned to remove all dirt and loose particles using compressed air The surrounding area shall be shaded to avoid the effects of temperature extremesThe grouting operation shall be carried out in pieces on the tank circumferenceThe surface shall be soaked in water for 24 hours prior to conmmence the operationsSandfilling shall be carried out into the spaces leaving a clear portion 200 mm wide for the grouting purpose. A backing rod 25 mm dia shall be provided as shown on the sketchThe space to be filled in various locations shall be prepared by form strips of the size equal to the thickness of the grout circumferentially and radially. The pouring end shall be kept open and after the pouring is completed in the prepared area, shall be closedAn electric drill fitted with a paddle mixer shall be used for the grout mixing purpose. The mixer shall be clean with no standing water.Using water @ 3.5 to 4.5 litres per 25 kg bag of Master flow 928T according to the requirement, the mixing shall be carried out as follows 90 % of the measured quantity of water required to achieve the desired consistency according to the batch volume shall be added to the mixer followed by the grout material Masterflow 928 T added gradually.The remaining 10 % water quantity shall be poued during mixing, which has to be kept continued for at least 3 to 5 minutes until a uniform lump free consistency is achieved.Civil Contractor QC inspection shall be conducted according to the ITP requirementThe grout shall be poured continuously using the pour cone with a constant hydrostatic head of at least 15 cm Civil Contractor QC inspection shall be conducted according to the ITP requirementAfter pouring the grout Masterflow 928 in place, all the exposed surfaces shall be covered with clean and damp Hessian to keep the applied material moist until it is firm enough to accept a curing membraneThe grout thickness varies between 25 to 35 mm.

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 273: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

273 of

Major EquipmentPaddle MixerGrout Flow ConeAttachmentSketch

#98

Excavation for ccb underground water tankTopIndexScopeReference documentsDefinitionsResponsibilitiesSafetyMethodEquipmentScopeThe statement is aimed to propose the procedures to be adopted to excavate the area for the underground water tank foundation where one cable trench is passing 1400 mm apart from one of the longitudnal (East) wallsReference Documents.Drgs Underground WaterTank Structural DetailsSpecification DefinitionsPSM Project Site ManagerCSM Construction ManagerCS Construction SuperintendentSE Site EngineerFM ForemanQC Quality ControlResponsibilitiesPSM shall control the overall operations CM shall arrange the resources required accordingly CS shall control, monitor and direct the SE, FM and workforce for the operationsSE shall be responsible for all the site operations and follow the instructions of the CSFM shall execute the operations deploying the workforce. FM shall explain in full in the language the work persons understand about all the instruction and the toolbox talks every day and check that the same are followed up regularlyStatements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 274: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

274 of

QC shall inspect all the operations according to the specificationsSafetyPrior to the commencement of work, the labour force shall receive a STARRT Card / Toolbox talk on the Project Site Safety requirements relevant to the deep excavation. Required safety arrangements shall be made by installing barricades and night lightsA safety inspector shall visit the site every day and instruct the supervisor in case any snag is observed, who immediately implement the instructions accordingly to get the measures to an acceptable standardMethodRefer to the sketch attachedThe setting out of the tank area shall be carried out to the relevant co-ordinatesCivil Contractor QC inspection shall be conducted to the ITP requirementSafety barricades shall be provided according to the requirmentSince the work is also in progress on the chiller area, the access to the formation shall be provided from the two shorter sides by benchingThe location of the longitudnal walls shall be marked adding 50 mm margin for the backblindingLongitudnally the excavation line shall be kept to vertical profile that is feasible for the soil is sufficiently stiff Necessary forms shall be erected in stages for the vertical / back blinding and the concrete poured to form a soil protective surfaceAfter the blinding is over, further activities of the tank construction shall be followed according to the relevant drawings and the specificationsMajor EquipmentExcavatorTruckAttachmentSketch#99

Excavation for ccb underground water tankTop

IndexScopeReference documentsSafetyMethod

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 275: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

275 of

EquipmentScopeThe statement is aimed to propose the procedures to be adopted to excavate the area for the underground water tank foundation where one cable trench is passing 1400 mm apart from one of the longitudnal (East) wallsReference Documents.Drgs Underground WaterTank Structural DetailsSpecification SafetyPrior to the commencement of work, the labour force shall receive a STARRT Card / Toolbox talk on the Project Site Safety requirements relevant to the deep excavation. Required safety arrangements shall be made by installing barricades and night lightsA safety inspector shall visit the site every day and instruct the supervisor in case any snag is observed, who immediately implement the instructions accordingly to get the measures to an acceptable standardMethodRefer to the sketch attachedThe setting out of the tank area shall be carried out to the relevant co-ordinatesCivil Contractor QC inspection shall be conducted to check the coordinates Safety barricades shall be provided according to the requirmentThe location of the longitudnal walls shall be marked & the excavation lines demarcated according to the sketch attachedExcavation shall commence from the free side and continued to the cable trench line following the section shown on the sketchThe existing soil is stiff enough to be excavated to a vertical profile but tempararily,on the cable trench side pre cast concrete cubes 1mx1mx1m shall be used to retain the earth pressure as shown on the sketchAfter the cubes are placed in, further construction operations shall be carried out to the drawings and specificationsCubes shall be used to act as a support to the formsAfter the cubes placement, further activities of the tank construction shall be followed according to the relevant drawings and the specificationsMajor EquipmentExcavatorTruckAttachmentSketch

#99

Soakaway chambers Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 276: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

276 of

TopIndexScopeReference documentsSafetyMethod EquipmentAttachmentScopeThe statement is aimed to propose the procedures to be adopted to carry out the construction of soakaway chambersReference documentsDrawing No Specification SafetyPrior to commencement of any activity, the labour force shall receive a STARRT Card / Toolbox talk relevant to the operation concerned on the project site safety requirements. Necessary measures shall be applied to any process involving a safety riskAll safety precautions necessary during working on excavations, mass concrete, forms, rebars, concrete pouring, etc. shall be applied to acceptable standards Adequate safety measures shall be adhered to during lifting and offloading precast perforated concrete manhole rings & covers to relevant locations avoiding any mishap BY OBSERVING THE REGULATORY CRANE FITNESS REQUIREMENT AND VALIDITY OF PERMIT. Only competent personnel shall be engaged to carry out the operationCrane and trailer operators shall abide by all traffic rules while carrying out operations and if so required, a banksman shall be engaged to direct the movementThe crane shall not be operated during the inclement weather conditions with dust storms Safety SupervisionA competent inspector shall visit the area daily to assess the safety measures adopted. Any snag observed during his visit shall be notified to the supervisor present who immediately act to bring the safety measures to an acceptable standard MaterialConcrete, Rebars / Lifting Lugs, Steps, Manhole coversMethodPre casting Area- the existing yard being used to pre cast manholes, catch basins, lighting poles etc. shall be employed for this purpose alsoThe following operations are involved to carry out the production of the soakaway chambers

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 277: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

277 of

The typical size of the precast rings are dia 1800mm and 1200 mm & other details as shown on the sketch The internal forms shall be erected to the exact internal dia and the specified height Drain holes blockout forms dia 75 mm shall be fixed to the internal shutter to suit circular profile at ends 8 #s in each row for 1200 mm dia and 12 #s in each row in 1400 mm dia staggered as shown on the sketchThe 8T(not specified) steel rebars shall be cut, bent to the circular shape, placed and the cage prepared holding concrete spacers, and positioned into the forms.The blockout form for the inlet pipe shall be prepared and fixed to the circular form wherever requiredPolystyrene sleeves shall be inserted for the steps to be grouted after the forms are struckAfter all the blackouts are fixed in, the dimensions and the plumb shall be checkedAn Civil Contractor preliminary inspection shall be conductedExternal forms shall be erected to specified dia and height & correctly supported. All the supports and dimensions shall be checked, corrected if required and the plumb monitoredAn Civil Contractor QC inspection shall be conducted & ITP for concrete pour signed offConcrete grade 30 shall be poured to the prepared units in 3 layers in vertical sequenceThe needle vibrator shall be used for the compaction of the concrete After the concrete is poured in full & well compacted, the surface shall be levelled using a wooden float Top circular strip shall be finished with a wooden float and covered with polythene sheetAn Civil Contractor QC inspection shall be conducted at regular intervals throughout the operationsImmediately after the concrete is finished, the surface shall be covered with polythene sheet with the edge lapped or tied down to exclude air circulation without permitting the membrane to be in touch with concrete surface according to the specificationsAfter the concrete has stiffened but no longer than 2 hours, the polythene sheet shall be removed followed by immediate covering the surface with saturated (soaked with mix quality water) hessian and recovered with polythene sheet to prevent evaporation from the hessian. Throughout the curing period, the hessian shall be maintained in a permanent wet condition using mix quality water The external and the internal forms shall be removed after a specified period of 24 to 36 hours as agreedThe vertical concrete surfaces shall be draped with the saturated hessian immediately after striking the forms and covered with the polythene sheet held firmly in place along all edges & kept continuously wet for the duration of curing The curing shall be continued for the specified period An Civil Contractor QC inspection shall be conducted from time to time throughout the operationsSimilarly RCC covers 250mm thick with circumferential web section 150x450mm shall be precast to specified dia The relevant locations shall be made ready to receive the precast rings by completing the excavation, mass concrete ring footing, and forming the correct alignment Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 278: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

278 of

AN Civil Contractor QC inspection shall be conducted for the'location to receive' & ITP signed offThe rings shall be lifted by a mobile crane, loaded gently onto a trailer and transported to the relevant area to offload on to the prepared ‘location to receive’ The rings shall be installed on the marked location according to the correct orientation to the relevant layout drawing keeping one ring above the other in such a way that the steps are formed in vertical alignment and the perforations are staggered but centred vertically AN Civil Contractor QC inspection shall be conducted Space surrounded by the mass concrete ring footing shall be backfilled with 40mm nominal single size stonesAnother ring shall be placed over the previous and jointed with cement mortarThe excavation and laying of inlet pipe shall be carried out to the details and the block out filled with concrete. The surrounding pipe and the rings shall be backfilled with 40 mm nominal single size stones AN Civil Contractor QC inspection shall be conducted Precast covers shall be transported from the precasting yard, offloaded and properly located over the approved rings to the correct alignmentManhole cover bedding / bearing shall be made of concrete by forming to the given profile to suit the cover placing levelAfter the bearing concrete stiffens, the cover frame shall be fixed and levelled using cement mortar 1 : 3Forms shall be erected for the mass concrete surround with preformed chamfers and concrete poured to a level 50 mm above the grade levelEPC Contractor surveillance / inspection / approval shall be according to the approved ITPsMajor EquipmentCompressor, Mobile Crane, TrailerTransit mixerAttachmentLifting arrangement sketchDrain Holes locations indicative only#100

Epoxy flooring Buildings TopIndexScopeReference documentsSafetyMethod EquipmentAttachment

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 279: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

279 of

ScopeThe statement is aimed to propose the procedures to be adopted to carry out the construction of Epoxy Flooring 3 and 5mm thick in buildingsReference documentsDrawing No. Specification SafetyPrior to commencement of any activity, the labour force shall receive a STARRT Card / Toolbox Talk relevant to the operation concerned on the project site safety requirements. Necessary measures shall be applied to any process involving a safety riskSafety Supervision A competent inspector shall visit the area daily to assess the safety measures adopted. Any snag observed during his visit shall be notified to the supervisor present who immediately act to bring the safety measures to an acceptable standard MaterialMastertop 1230i, MBT MAR # Mastertop 1200i ResinMethodSurface PreparationThe floor base concrete shall be lightly scabbled to remove the laitance Surface shall be cleaned of all dust and dirt by compressed air An Civil Contractor QC inspection shall be conducted Prior to the application of Mastertop1230i the concrete scabbled & cleaned surface shall be sealed by applying Mastertop1200i resin diluted with 5% solvent #2 as follows.Sealer MixingBase and reactor components shall be poured into a mixing vessel and half a litre of Solvent # 2 added.All these components shall be mixed using a slow speed drill with a paddle attachment for 1 minuteSealer shall be applied at a rate of 5-8 sqm per litre using a medium pile roller Sealed surface shall be allowed to become tack free before the application of Mastertop1230iAn Civil Contractor QC inspection shall be conducted Mastertop1230i shall be applied as followsMixingReactor base and colour pack components of the Mastertop1230i shall be poured into a vessel of 25 litre capacityThe components shall be mixed with a drill with paddle attachment until a uniform colour is achieved.1230i aggregate shall be slowly added to the mixed components keeping the mixer running until the mixture is of smooth and lumpsfree consistency

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 280: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

280 of

LayingMixed material shall be poured on to the primed & sealed surface & spread to 5mm thickness in stores & warehouses and 3 mm thickness in other areas using a pin screed, notched trowel or steel float.Immediately after the spread of the material to the required thickness, rolling shall be carried out by a ‘Spiked Roller’ to release entrapped air and remove the trowel marksRolling shall be continued until all air is released and a uniform colour is obtainedRolling shall again be carried out after 20 to 30 minutesOperator shall wear the ‘spiked shoes’ when using the ‘spiked roller’ to walk on wet material. Rolling shall cease before Mastertop 1230i begins to gelAn Civil Contractor QC inspection shall be conducted & ITP signed offMastertop1230i shall be removed from the tools and equipment whilst still wet using cleaning solvent # 2EquipmentSlow speed drill with suitable paddleBrushes, Short nap hair rollersGrinder, Spiked roller, Pin screedAttachmentMBT 1230 i Data sheet#101

Epoxy flooring Buildings TopIndexScopeReference documentsSafetyMethod EquipmentAttachmentScopeThe statement is aimed to propose the procedures to be adopted to carry out the construction of Epoxy Flooring 3 and 5mm thick in buildingsReference documentsDrawing No. & likeSpecification Clause 13SafetyPrior to commence any activity, the labour force shall receive a STARRT Card / Toolbox Talk relevant to the operation concerned on the project site safety requirements. Necessary measures shall be applied to any process involving a safety risk

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 281: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

281 of

Safety Supervision A competent inspector shall visit the area daily to assess the safety measures adopted. Any snag observed during his visit shall be notified to the supervisor present who immediately act to bring the safety measures to an acceptable standard MaterialMastertop 1230i, MBT MAR # Mastertop 1200i ResinApplicatorsSkilled applicators shall carry out the workManufacturer’s demonstrator shall train a group of personnel on site for one room and later the remaining work of epoxy coating shall be carried out by this groupMethod (Surface Preparation)Equipment shall be protected by covering with polythene sheetThe floor base concrete shall either be grit blasted or acid etching applied to remove the laitance Surface shall be cleaned of all dust and dirt by compressed air An Civil Contractor QC inspection shall be conducted to accept substratePrior to the application of Mastertop1230I, the prepared concrete surface shall be sealed by applying Mastertop1200i resin diluted with 5% solvent #2 as follows.(Sealer Mixing)Base and reactor components shall be poured into a mixing vessel and half a litre of Solvent # 2 added.All these components shall be mixed using a slow speed drill with a paddle attachment for 1 minuteSealer shall be applied at a rate of 5-8 sqm per litre using a medium pile roller Sealed surface shall be allowed to become tack free before the application of Mastertop1230iAn Civil Contractor QC inspection shall be conducted to approve that the surface is properly sealed with no imperfections.Mastertop1230i shall be applied as follows(Mixing)Reactor base and colour pack components of the Mastertop1230i shall be poured into a vessel of 25 litre capacityThe components shall be mixed with a drill with paddle attachment until a uniform colour is achieved.1230i aggregate shall be slowly added to the mixed components keeping the mixer running until the mixture is of smooth and lumpsfree consistency(Laying)Mixed material shall be poured on to the primed & sealed surface & spread to 5mm thickness in stores & warehouses and 3 mm thickness in other areas using a pin screed, notched trowel or steel float.Immediately after the spread of the material to the required thickness, rolling shall be carried out by a ‘Spiked Roller’ to release entrapped air and remove the trowel marks

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 282: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

282 of

Rolling shall be continued until all air is released and a uniform colour is obtainedRolling shall again be carried out after 20 to 30 minutesOperator shall wear the ‘spiked shoes’ when using the ‘spiked roller’ to walk on wet material. Rolling shall cease before Mastertop 1230i begins to gelAn Civil Contractor QC inspection shall be conducted & ITP signed offMastertop1230i shall be removed from the tools and equipment whilst still wet using cleaning solvent # 2EquipmentSlow speed drill with suitable paddleBrushes, Short nap hair rollersGrinder, Spiked roller, Pin screed, Spiked shoesAttachmentMBT 1230 i Data sheet#102

Epoxy flooring Buildings TopIndexScopeReference documentsSafetyMethod EquipmentAttachmentScopeThe statement is aimed to propose the procedures to be adopted to carry out the construction of Epoxy Flooring 3 and 5mm thick in buildingsReference documentsDrawing No. & likeSpecification Clause 13SafetyPrior to commence any activity, the labour force shall receive a STARRT Card / Toolbox Talk relevant to the operation concerned on the project site safety requirements. Necessary measures shall be applied to any process involving a safety riskSafety Supervision A competent inspector shall visit the area daily to assess the safety measures adopted. Any snag observed during his visit shall be notified to the supervisor present who immediately act to bring the safety measures to an acceptable standard MaterialMastertop 1230i, MBT MAR # Mastertop 1200i Resin

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 283: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

283 of

ApplicatorsSkilled applicators shall carry out the workManufacturer’s demonstrator shall train a group of personnel on site for one room and later the remaining work of epoxy coating shall be carried out by this groupMethod (Surface Preparation)Equipment shall be protected by covering with polythene sheetThe floor base concrete shall either be grit blasted or acid etching applied to remove the laitance Surface shall be cleaned of all dust and dirt by brush & vacuum cleaner An Civil Contractor QC inspection shall be conducted to accept substratePrior to the application of Mastertop1230I, the prepared concrete surface shall be sealed by applying Mastertop1200i resin diluted with 5% solvent #2 as follows.(Sealer Mixing)Base and reactor components shall be poured into a mixing vessel and half a litre of Solvent # 2 added.All these components shall be mixed using a slow speed drill with a paddle attachment for 1 minuteSealer shall be applied at a rate of 5-8 sqm per litre using a medium pile roller Sealed surface shall be allowed to become tack free before the application of Mastertop1230iAn Civil Contractor QC inspection shall be conducted to approve that the surface is properly sealed with no imperfections.Mastertop1230i shall be applied as follows(Mixing)Reactor base and colour pack components of the Mastertop1230i shall be poured into a vessel of 25 litre capacityThe components shall be mixed with a drill with paddle attachment until a uniform colour is achieved.1230i aggregate shall be slowly added to the mixed components keeping the mixer running until the mixture is of smooth and lumpsfree consistency(Laying)Mixed material shall be poured on to the primed & sealed surface & spread to 5mm thickness in stores & warehouses and 3 mm thickness in other areas using a pin screed, notched trowel or steel float.Immediately after the spread of the material to the required thickness, rolling shall be carried out by a ‘Spiked Roller’ to release entrapped air and remove the trowel marksRolling shall be continued until all air is released and a uniform colour is obtainedRolling shall again be carried out after 20 to 30 minutesOperator shall wear the ‘spiked shoes’ when using the ‘spiked roller’ to walk on wet material. Rolling shall cease before Mastertop 1230i begins to gelAn Civil Contractor QC inspection shall be conducted & ITP signed offMastertop1230i shall be removed from the tools and equipment whilst still wet using cleaning solvent # 2

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 284: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

284 of

EquipmentSlow speed drill with suitable paddleBrushes, Short nap hair rollersGrinder, Spiked roller, Pin screed, Spiked shoesAttachmentMBT 1230 i Data sheet#103

Vinyl wall covering Buildings TopIndexScopeReference documentsSafetyMethod EquipmentAttachmentScopeThe statement is aimed to propose the procedures to be adopted to apply Fabric Backed Vinyl Wall Covering paper over dry walls in buildingsReference documentsDrawing No. and likeMAR Ref SafetyPrior to commencement of any activity, the labour force shall receive a STARRT Card / Toolbox Talk relevant to the operation concerned on the project site safety requirements. Necessary measures shall be applied to any process involving a safety riskSafety Supervision A competent inspector shall visit the area daily to assess the safety measures adopted. Any snag observed during his visit shall be notified to the supervisor present who immediately act to bring the safety measures to an acceptable standard MaterialFabric backed Vinyl wall covering Suwide Scala N 5858 Manufacturer-Swide, Supplier / Sub Contractor-Trade LineMethodThe surface shall be made dry, firm, smooth & free from greaseA vertical line shall be marked at 200 mm from the corner to apply first drop Higher material roll # shall be used firstPlenty of adhesive shall be coated on the wall portion for the first piece of material using a lambswool roller or a block brush

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 285: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

285 of

Pieces shall be cut & numbered using a graphite pencilStrips shall be fixed in reverse alternateMaterial piece shall be cut to a length equal to wall height plus 40mm (20mm extra at ceiling and 20mm extra at skirting)Edge of the first piece shall be located against the vertical line making sure that there is a small selvedge at top and bottom for subsequent trimmingSmoothening shall be carried out using a spatula along the length of the materialSecond length shall be placed against the adhesive tape and smoothened out with a spatula and if necessary rolled overThe uppermost length shall fall off by itself while the lower length shall be removed.A thin coat of adhesive shall be applied to the wall before the joint is closedRubber roller shall be moved over the material to make sure that no bubble emergesA small vertical cut shall be made in the overlap near the ceiling using a Stanley knifeJoint shall be closed and sealed smooth with spatulaBefore hanging the second piece the marker pins shall be placed at about 4 cm from the edge of the first pieceOverlap shall be cut with a suitable cutting knifeSlevedge shall be removed from the ceiling and the plinth with Stanley knifeKnife shall be kept in cut and spatula movedAn Civil Contractor QC inspection shall be conducted and the ITP signed offEquipmentRubber roller, Stanley knife, Spatula, Marker pins AttachmentSUWIDE Instruction SheetITP- Civil Contractor / ITP / Rev BCheck List- QCF Rev B#104

Dry wall linings buildings TopIndexScopeReference documentsSafetyMethod EquipmentAttachmentScopeThis statement is aimed to propose the procedures to be adopted to install dry wall linings in the buildings.Reference documentsSpecs (Gypsum Wall boards Systems)

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 286: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

286 of

STQ SafetyPrior to commencement of any activity, the labour force shall receive a STARRTCard / Toolbox Talk relevant to the operation concerned on the project site safety requirements. Necessary measures shall be applied to any process involving a safety riskSafety Supervision A competent inspector shall visit the area daily to assess the safety measures adopted. Any snag observed during his visit shall be notified to the supervisor present who immediately act to bring the safety measures to an acceptable standard MaterialMAR 076 Galvanised Studs, Runners & Furrings (Metal Framing System)Gypsum wall lining & wall partitionsFraming System- TMI (Technical Material Industrial Company) UAEExternal wall lining-Studs & Runners Galvanised Steel Stud depth 63mm-Thickness 1mm, Runner depth 65mm-Thickness 0.7mm Metal Internal wall lining, Furring channels-Galvanised Steel, Material Width 50mm-Thickness 0.7mm, depth 22mmMetal Framing for dry wall partitions, Studs & Runners- Galvanised SteelStud width 92mm-Thickness 1mm, Runner Width 94mm-Thickness 0.7mm, MAR Gypsum Wall Board systemRegular wall board 12.5mm thick 1.2 x 2.4 m panel, tapered edges Moisture Resistant board 15 mm thick, tapered edges, Knauf Australia, Trade line, MAR Acoustical Fibreglass for demountable partitionsAccoustical glasswool insulation material 60mm thick for internal partition walls &50 mm thick for external walls, Kimmco- Isover Fibre Glass, Kimmco Specialist Sub Contractor- Trade LineMethodDe-mountable panels shall be fixed to flooring / top of tiles while the others to the screedFloors & Ceilings shall be constructed as specified For the levelling purpose, a chalk line shall be marked to be used as a datumFloor and ceiling tracks shall be fixed by shot firing nails as per detailsVertical studs shall be placed every 600mm c / c wherever possibleBracing shall be fixed between studs and walls & at all board joints for rigidity & strength to the requirement Gypsum boards shall be fixed using dry walls screws at 300 mm c / c in the middle and 200 mm c / c at the edges of the boardFor the internal partitions where the insulation is to be provided, shall be installed after one board is fixedCivil Contractor QC inspections shall be conducted The other board shall be fixed after the approval of the insulation

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 287: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

287 of

On the external walls where the insulation is to be provided, shall be installed prior to Gypsum board is fixedThe tapered surface at the board joints shall be pasted from lower to higher level vertically with fibre tape to act as a support for joint compound to be filled in. Joint compound shall be filled in to a suitable & acceptable profileHole ends posed due to the fasteners shall also be filled in with the compoundAll external corners shall have stainless steel corner beading fittedGypsum board shall be sanded to smoothen the surface to receive sequential finishing items Civil Contractor QC inspections shall be conducted throughout the above operations and the ITP signed offEquipmentHilty relevant drillsAttachmentTrade Line method statement#105

Rubber flooring (buildings) TopIndexScopeReference documentsSafetyMethod EquipmentAttachmentScopeThis statement is aimed to propose the procedures to be adopted to install Rubber Flooring in the buildings.Reference documentsMain Sub StationUtility Sub StationBuilding Sub StationSub StationMAR SafetyPrior to commencement of any activity, the labour force shall receive a STARRTCard / Toolbox Talk relevant to the operation concerned on the project site safety requirements. Necessary measures shall be applied to any process involving a safety risk

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 288: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

288 of

Safety Supervision A competent inspector shall visit the area daily to assess the safety measures adopted. Any snag observed during his visit shall be notified to the supervisor present who immediately act to bring the safety measures to an acceptable standard MaterialMAR, Norament 926 Manufactured by Nora / Freudenberg-Germany-Colour # 0884 Manufacturer recommended Adhesives from UZIN-Werk German (MAR in process)1) UZIN KR 430 A+B Two Component Polyurethane Adhesive for fixing 6mm thick Coned Back Rubber Tiles2) UZIN GN 276 Neoprene adhesive for fixing Cove Skirting and AnglesPrimer PE 412 PURKR 410 PUR Levelling Compound (To be used to remove large unevenness if so required)Specialist ApplicatorThe flooring application shall be carried out by M / S JOS HANSEN, the authorised agentMethodFor installation, the sub floor shall be even, clean, dry, firm, to the correct levels with no major unevenness & free of cracks. Surface shall be free from oil, wax, paint residues with minimum porosity and roughnessIf required on large uneven areas, KR410 shall be applied to self level the surfaceSmaller unevenness shall be made up by the adhesive itselfCivil Contractor QC inspections shall be conducted to approve that the surface is suitablePriming PE 12 PUR shall be applied in 1 or 2 coats depending on surface porosity Within 24 hours of priming while the surface is still tacky, floor covering operation shall proceed. In case the primed surface has cured, it shall be roughened to provide a satisfactory bond with adhesive Civil Contractor QC inspections shall be conducted to approve that the primed surface is fit to receive the floor covering “Rubber tiled” floor shall be installed fully in accordance with pages 2-6 of the attached installation instructionsCivil Contractor QC inspections shall be conducted throughout the above operations to ensure compliance with specifications and ITP requirementsEquipmentAdhesive spreader, Hooked blade, Smoothing spatula, waxSerrated blade 21AttachmentAdhesive data sheet from UZIN-WerkManufacturer’s Installation instructions#106

Rubber flooring (buildings)

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 289: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

289 of

TopIndexScopeReference documentsSafetyMethod EquipmentAttachmentScopeThis statement is aimed to propose the procedures to be adopted to install Rubber Flooring in the Sub Station buildings.Reference documentsMain Sub StationUtility Sub StationBuilding Sub StationSub StationMAR SafetyPrior to commencement of any activity, the labour force shall receive a STARRTCard / Toolbox Talk relevant to the operation concerned on the project site safety requirements. Necessary measures shall be applied to any process involving a safety riskSafety Supervision A competent inspector shall visit the area daily to assess the safety measures adopted. Any snag observed during his visit shall be notified to the supervisor present who immediately act to bring the safety measures to an acceptable standard MaterialMAR, Norament 926 Manufactured by Nora / Freudenberg-Germany-Colour # 0884 Manufacturer recommended Adhesives from UZIN-Werk German (MAR in process)1) UZIN KR 430 A+B Two Component Polyurethane Adhesive for fixing 6mm thick Coned Back Rubber Tiles2) UZIN GN 276 Neoprene adhesive for fixing Cove Skirting and AnglesSpecialist ApplicatorThe flooring application shall be carried out by an applicator approved and certified by M / S JOS HANSEN, the authorised agentMethodFor installation, the sub floor shall be even, clean, dry, firm, to the correct levels with no major unevenness & free of cracks. Surface shall be free from oil, wax, paint residues with minimum porosity and roughnessSmaller unevenness if any, shall be made up by the adhesive itselfThe concrete surfaces are more than 28 days oldCivil Contractor QC inspections shall be conducted to approve that the surface is suitable

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 290: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

290 of

“Rubber tiled” floor shall be installed fully in accordance with pages 2-6 of the attached installation instructionsCivil Contractor QC inspections shall be conducted throughout the above operations to ensure compliance with specifications and ITP requirementsEquipmentAdhesive spreader, Hooked blade, Smoothing spatula, waxSerrated blade 2150 Kg Metal RollerAttachmentAdhesive data sheet from UZIN-WerkManufacturer’s Installation instructions#107

Rubber flooring (buildings) Top

IndexScopeReference documentsSafetyMethod EquipmentAttachmentScopeThis statement is aimed to propose the procedures to be adopted to install Rubber Flooring in the buildings.Reference documentsMain Sub StationUtility Sub StationBuilding Sub StationSub StationMAR SafetyPrior to commencement of any activity, the labour force shall receive a STARRTCard / Toolbox Talk relevant to the operation concerned on the project site safety requirements. Necessary measures shall be applied to any process involving a safety risk

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 291: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

291 of

Safety Supervision A competent inspector shall visit the area daily to assess the safety measures adopted. Any snag observed during his visit shall be notified to the supervisor present who immediately act to bring the safety measures to an acceptable standard MaterialMAR, Norament 926 Manufactured by Nora / Freudenberg-Germany-Colour # 0884 Manufacturer recommended Adhesives from UZIN-Werk German (MAR in process)1) UZIN KR 430 A+B Two Component Polyurethane Adhesive for fixing 6mm thick Coned Back Rubber Tiles2) UZIN GN 276 Neoprene adhesive for fixing Cove Skirting and AnglesPrimer PE 412 PURKR 410 PUR Levelling Compound (To be used to remove large unevenness if so required)Specialist ApplicatorThe flooring application shall be carried out by M / S JOS HANSEN, the authorised agentMethodFor installation, the sub floor shall be even, clean, dry, firm, to the correct levels with no major unevenness & free of cracks. Surface shall be free from oil, wax, paint residues with minimum porosity and roughnessIf required on large uneven areas, KR410 shall be applied to self level the surfaceSmaller unevenness shall be made up by the adhesive itselfCivil Contractor QC inspections shall be conducted to approve that the surface is suitablePriming PE 12 PUR shall be applied in 1 or 2 coats depending on surface porosity Within 24 hours of priming while the surface is still tacky, floor covering operation shall proceed. In case the primed surface has cured, it shall be roughened to provide a satisfactory bond with adhesive Civil Contractor QC inspections shall be conducted to approve that the primed surface is fit to receive the floor covering “Rubber tiled” floor shall be installed fully in accordance with pages 2-6 of the attached installation instructionsCivil Contractor QC inspections shall be conducted throughout the above operations to ensure compliance with specifications and ITP requirementsEquipmentAdhesive spreader, Hooked blade, Smoothing spatula, waxSerrated blade 21AttachmentAdhesive data sheet from UZIN-WerkManufacturer’s Installation instructions#108

Rubber flooring (buildings)

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 292: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

292 of

TopIndexScopeReference documentsSafetyMethod EquipmentAttachmentScopeThis statement is aimed to propose the procedures to be adopted to install Rubber Flooring in the Sub Station buildings.Reference documentsMain Sub StationUtility Sub StationBuilding Sub StationSub StationMAR SafetyPrior to commencement of any activity, the labour force shall receive a STARRTCard / Toolbox Talk relevant to the operation concerned on the project site safety requirements. Necessary measures shall be applied to any process involving a safety riskSafety Supervision A competent inspector shall visit the area daily to assess the safety measures adopted. Any snag observed during his visit shall be notified to the supervisor present who immediately act to bring the safety measures to an acceptable standard MaterialMAR, Norament 926 Manufactured by Nora / Freudenberg-Germany-Colour # 0884 Manufacturer recommended Adhesives from UZIN-Werk German (MAR in process)1) UZIN KR 430 A+B Two Component Polyurethane Adhesive for fixing 6mm thick Coned Back Rubber Tiles2) UZIN GN 276 Neoprene adhesive for fixing Cove Skirting and AnglesSpecialist ApplicatorThe flooring application shall be carried out by an applicator approved and certified by M / S JOS HANSEN, the authorised agentMethodFor installation, the sub floor shall be even, clean, dry, firm, to the correct levels with no major unevenness & free of cracks. Surface shall be free from oil, wax, paint residues with minimum porosity and roughnessSmaller unevenness if any, shall be made up by the adhesive itselfThe concrete surfaces are more than 28 days oldCivil Contractor QC inspections shall be conducted to approve that the surface is suitable

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 293: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

293 of

“Rubber tiled” floor shall be installed fully in accordance with pages 2-6 of the attached installation instructionsCivil Contractor QC inspections shall be conducted throughout the above operations to ensure compliance with specifications and ITP requirementsEquipmentAdhesive spreader, Hooked blade, Smoothing spatula, waxSerrated blade 2150 Kg Metal RollerAttachmentAdhesive data sheet from UZIN-WerkManufacturer’s Installation instructions#109

Suspended ceilings All buildings TopIndexScopeReference documentsSafetyMethod EquipmentAttachmentScopeThis statement is aimed to propose the procedures to be adopted to install suspended ceilings in the buildings.Reference documentsSpecifications : for Acoustical CeilingsMAR MOM MM-SafetyPrior to commencement of any activity, the labour force shall receive a STARRTCard / Toolbox Talk relevant to the operation concerned on the project site safety requirements. Necessary measures shall be applied to any process involving a safety riskSafety Supervision A competent inspector shall visit the area daily to assess the safety measures adopted. Any snag observed during his visit shall be notified to the supervisor present who immediately act to bring the safety measures to an acceptable standard MaterialMAR - Acoustical Metal CeilingFully accessible suspended modular grid type perforated metal ceiling panels with concealed insulation pads- Telecom Room- Administration BuildingColour RAL 9010- Ref MAR for fire proof materialStatements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 294: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

294 of

MOM MM-SAS ceiling system 120, manufacturer SAS ceilings UK, MAR Mineral fiber ceiling- Mineral fiber lay in suspended ceiling-Plane Done Plus MOM MM- - Prima, manufactured-Armstrong UK, MAR Humidity resistant tile suspended CeilingCeramaguard, Armstrong UK, Trade LineDrg & Drg MAR Plastic Faced Ceiling- VL BIO, Armstrong USA, Drg 2& Drg MAR Metal Panel Suspended Ceiling600 x 600mm metal panel suspended ceiling in a lay-in-systemRAL 9010 (Cleaner’s Room Administration Building)System 130 TrueGrid T24 System, Manufacturer SAS Ceiling UK, Trade LineMAR Aluminium Strip Ceiling- Suspended Ceiling with colour coated Aluminium stripOnly one colour RAL 9016 (Toilets)-Matador 100, Manufacturer Matador, UAEMAR Satin Anodised Strip Ceiling with rounded off & closed cleatProduct SMSC 100, Manufacturer Saddi Metal, UAEMAR Insulation pads for metal acoustical ceilingRockwool fill material with non combustible black glass tissue, Man-SAS, UKMethodInstallation of Lay in suspended ceiling tiles- 600 x 600 mmAcoustic Tiles 600mmx600mm & Aluminium Tiles 600mmx600mm on exposed suspensionChalk line shall be marked around the periphery to form a datum to be used for levelling purposeSuspension hangers shall be shot fired to the slab using Hilty equipmentWall angles shall be fixed to the correct levels using steel nails Main channels shall be fixed at 1200mm c / c to the details shown on shop drawingsCross Tees 1200mm shall be fixed perpendicular to the main channels at 600mm c / c to form cells of grid (600mmx1200mm)Cross Tees 600mm shall further be fixed at the centre of 1200mm Cross Tees to form cells in final grid (600mmx600mm)Full tiles shall be installed in 600mmx600mm cells & the ‘cut tiles’ to suit the site requirement as agreedOpenings for AC diffusers, spot lights, smoke detectors, fire alarm etc, all shall be provided to the requirement

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 295: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

295 of

Civil Contractor QC inspections shall be conducted throughout the above operations and the ITPs signed off. Ceilings shall not be fully closed until QC confirms that all preceding electrical & HVAC installations have been completed.Installation of Aluminium Clip in TilesChalk line shall be marked around the periphery to form a datum to be used for levelling purposeSuspension hangers shall be shot fired to the slab at 1000mm c / c using Hilty equipment Wall edge trims shall be fixed to correct levels using steel nails Main channels shall be fixed at 1200mm c / c by holding clamps to the details shown on shop drawingsSpring Tees shall be secured every 600mm by wire clips perpendicular to main channels Tiles 600mmx600mm shall be inserted into Spring TeesOpenings for AC diffusers, spot lights, smoke detectors, fire alarm etc, shall be provided all to the requirement Civil Contractor QC inspections shall be conducted throughout the above operations and the ITPs signed off. Ceilings shall not be fully closed until QC confirms that all preceding electrical & HVAC installations have been completed.EquipmentShot firing gunAttachmentTrade Line method statement#110

Pit 21 water connectionTop IndexScopeReference documentsDefinitionsResponsibilitiesSafetyMethodEquipmentAttachmentScopeThe purpose of this method statement, is to define the procedure that shall be adopted for the connection of the water pipeline, from the Operating Authority supply pit No 21, to the Civil Contractor camp.Reference documentsExcavation permit.Drawing No: Operating Authority easement Drawing No: Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 296: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

296 of

DefinitionsOperating Authority EPC Contractor Civil Contractor PSM Project Site Manager.ResponsibilitiesThe Civil Contractor PSM shall ensure this method statement is implementation for the connection to pit 21, the laying of the drinking water pipeline, as well as the reinstatement to pit 21.SafetyThe Safety Officer shall monitor the daily activities, advising and implementing all safety procedures.MethodThe position of the proposed pipe location through the wall of pit 21 shall be marked. Using hand tools, a hole shall be made through the concrete pit wall. The size of the hole in the pit wall, shall be adequate to allow the positioning of a purpose made Upvc pipe sleeve. Upon the positioning of the pipe sleeve, the pit wall shall be made good using a mortar mix of 1 part cement to 3 part sand.As the hole is above the local water table, no provision against the ingress of water shall be required.When the water pipe is correctly located through the pipe sleeve, the gap between the water pipe and the pipe sleeve shall receive a mastic seal.The route of the pipe from pit 21 to the pipe sleeve in avenue C, is indicated upon the drawing The pipe shall be located in a hand excavated trench, above the existing services.Where necessary, thrust blocks shall be installed to resist any pressure movements.The relevant pipe fittings required to control and monitor the water flow within the pipe, shall be located inside of pit 21.The area around the pit and along the route of the pipeline shall be left clean of construction material. Upon completion of the project, the water pipe shall be removed in accordance with the instruction of Operating Authority. The fittings within the pit provided by Civil Contractor shall be removed, leaving the existing Operating Authority valve and small vent pipe.The pipe sleeve through the wall of pit 21, shall be capped with purpose made Upvc end caps, that may be removed at a later date for future use if required. EquipmentHand tools.Pipe jointing and cutting tools.AttachmentWork permit.Drawing Site Sketch Operating Authority drawing No: #111Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 297: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

297 of

Cement based non shrink grouting to foundation basesUsing masterflow 928 tTopIndexScopeReference documentsSafetyMethodEquipmentScopeThis statement is aimed to propose the procedures to be adopted to grout the base plates of stationary equipment / vessels foundation bases using cement based non shrink grout materia for a grouting thickness of 25 – 50 mm. Reference DocumentsSpecification SafetyPrior to commencement of any activity, the labour force shall receive a STARRTCard / Toolbox Talk relevant to the operation concerned on the project site safety requirements. Necessary measures shall be applied to any process involving a safety riskSafety Supervision A competent inspector shall visit the area daily to assess the safety measures adopted. Any snag observed during his visit shall be notified to the supervisor present who immediately act to bring the safety measures to an acceptable standard MethodThe surface of the foundation under the base plate or equipment to be grouted shall be chipped / scabbled & brushed to remove the weak upper layer of the concrete, damaged concrete and any oil soaked concrete areas without using mechanical bush hammerPrior to grouting, loose concrete or dust shall be removed by compressed air.The concrete surface shall be soaked with clean water for 24 hours prior to grouting grouting to minimize the localized absorption as well as to assist the free flow of the grout.Just prior to grouting,all standing water shall be removed leaving only a damp film. Baseplates shall be clean and free of oil, grease, paint and correctly aligned according to the drawings. The levelling plates shall be set to proper elevation.Base plates and equipment bases shall be uniformly supported in order to eliminate sag and distortion.Equipment bases shall be levelled using both anchor bolts and jackscrews.Stainless steel shims 50x50x10 mm thick shall be in correct locations covered with mortar so as to allow at least 50 mm grout cover on shim sides.

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 298: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

298 of

The forms as shown on the attached sketch shall be erected on the required locations with chamfers.An electric drill fitted with a paddle shall be used for the grout mixing purpose. Water @ 3.5 to 4.5 litres per 25 kg bag of Master flow 928 shall be used according to requirement. The mixer shall be clean with no standing water.90 % of the measured quantity of water required to achieve the desired consistency according to the batch volume, shall be added to the mixer prior to adding Masterflow grout material, which has to be added into the mixer gradually and remaining 10 % water quantity shall be poured during mixing , which has to be kept on for at least 3 to 5 minutes until a uniform lump free consistency is achieved.The grouting material shall be poured continuously using’ grout pour cone’ with a constant hydrostatic head of at least 15 cmGrouting shall extend to the edge of the concrete surface where it is to be finished with a 25 mm chamfer After pouring Masterflow 928 in place, all exposed grout shall be covered with clean dampen / saturated Hessian and kept moist until the applied grout is firm enough to receive a curing membraneTemperature less than 32 degree C shall be maintained for the 3 post pour continuous daysMajor EquipmentPeddle MixerGrout Flow ConeAttachmentSketchMasterflow CatalogueMasterflow Method Statement#112

Repair of concrete floor screedsTopIndexScopeReference documentsSafetyMethodEquipmentScopeThis statement outlines the repair procedures to be followed for the repair and reinstatement of defective floor screeds, so as to provide a durable and serviceable levelling layer for the floor covering placed above.SafetyPrior to commencement of any activity, the labour force shall receive a STARRT

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 299: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

299 of

Card / Toolbox Talk relevant to the operation concerned on the project site safety requirements. Necessary measures shall be applied to any process involving a safety riskSafety Supervision A competent inspector shall visit the area daily to assess the safety measures adopted. Any snag observed during his visit shall be notified to the supervisor present who immediately act to bring the safety measures to an acceptable standard ResponsibilitiesAll inspection and repair work related to the concrete floor screeds shall be under the sole direction of a dedicated Site Engineer (SE) who shall have full authority and responsibility for ensuring that the works are carried out in accordance with this Method Statement.Procedure1. Repair activities shall be restricted to a limited number of rooms at any time, and access to

the rooms restricted during repair. Before commencing any repair activity, including preparation, the SE shall ensure that previously completed works are suitably protected from damage and dust, using a combination of polythene sheeting and ply boarding as appropriate.

2. Before commencing any repairs in a room, the SE shall agree the scope of the repairs to be undertaken with the Site Quality Manager, with the agreed repair marked on the floor. The scope shall be recorded on a sketch and identify which type of repair is to be used and the approximate area of the repair. The repairs shall be selected from the following:Repair Type A – Removal and Reinstatement with Cement Screed.This repair should be adopted where the existing screed has completely disbonded and broken up, leaving loose isolated sections of screed.Repair Type B – Repair with Epoxy MortarThis repair should be adopted where there are significant isolated cracks in the screed. It is not intended to repair minor hairline cracks by this method, or construction joints between adjacent panels of screed, unless they have become otherwise damaged.Repair Type C – Repair with Resin InjectionThis repair should be adopted where the screed appears to be disbonded and cracked or lifting but is otherwise intact. This may be carried out in conjunction with repair Type B above. It is not necessary to use resin injection on hollow sounding areas where there is no other sign of failure.

Repair Type D – Surface Epoxy CoatingThis repair shall be applied as a final protective coating to all repaired areas. As well as sealing any un-repaired hairline cracks, this shall also ensure an overall uniform appearance of the repaired areas.

3. The repairs shall be carried out as follows:Repair Type A: Removal and reinstatement with Cement Screed

A1. The affected area shall be sawcut to the full depth of the top layer of screed (typically 35mm) and the affected section removed carefully so as to cause minimum disruption to adjacent areas.

A2. The removed area shall be fully cleaned of all dust and debris, and any loose material removed.

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 300: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

300 of

A3. The cleared area shall be thoroughly soaked (not just dampened) for at least one hour before reinstatement.

A4. Immediately before placing the replacement screed, remove any surplus water (the substrate should still be wet) and apply one coat of NITOBOND PVA bonding agent to all surfaces – horizontal and vertical.

A5. Place and compact the replacement screed material. Trowel and immediately cover with polythene sheeting placed flat against the surface.

A6. Remove the polythene sheet after 4 hours and replace with wet hessian, covered with polythene sheeting. Ensure that further water is added to the hessian at least twice daily for a minimum of three days.

A7. Ensure that no-one walks on the repair for minimum three days. If unavoidable, lay ply sheet over repair, ensuring it remains in place.

Repair Type B – Repair with Epoxy MortarB1. Using a hammer and chisel, carefully chase a ‘V’ notch along the length of any crack

and along the edge of any loosened area. This should typically be 5mm from the edge of the crack and 5mm deep.

B2. Physically remove all loose material and clean using a using a wire brush or similar. Remove all dust and debris, using a brush and / or vacuum cleaner.

B3. Mix the repair material – NITOMORTAR FC-B (or FC) – in accordance with manufacturers recommendations and firmly press the repair mortar into place using a steel trowel. Finish the material flush with the surrounding concrete. It may be necessary to apply a second levelling coat if the material settles.

B4. Ensure that the repair area is not walked on for 24 hours.

Repair Type C – Repair with Resin InjectionC1 Drill three 10mm holes in the area to be repaired, to a depth of approximately 35mm,

representing the interface between the two screed layers. This can be determined by the change in sound of the drill.

C2. Fix an injection nipple to the drilled holes using an epoxy mortar e.g NitoMortar FC-B, and seal using a trowel. Allow to set for eight hours.

C3. Mix the repair resin – NITOFILL EPLV – in accordance with the manufacturers reccomendations, and insert into injection gun.

C4. Commence filling the central nipple, and continue until resin is observed at the outer nipples. If neccesary, continue filling the outer nipples. Note that material usage rate should be approximately 1litre per 1m2. Do not attempt to place more than this, or the floor could lift further.

C5. Leave for 6 hours, then remove the nipples and fixing mortar, and make the surface good.

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 301: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

301 of

Repair Type D – Surface Epoxy Coating

D1. Ensure all repairs have been completed and allowed to cure (24 hours for epoxy repair – 5 days for cement screed repair).

D2. Brush the surface thoroughly to remove all dust and debris. Ensure that the surface is not wet or damp.

D3. Mix the material – NITOFLOR FC140 - in accordance with the manufacturers instructions. Firstly apply a stripe coat to any untreated minor cracks, taking care to work the paint into the crack.

D4. Starting at the furthest corner, apply a single coat to the entire surface using a brush or roller, ensuring that the material fully coats the surface but without ponding.

D5. Ensure that the surface is not walked on for 24 hours.

4. Details of all repairs shall be recorded on a Screed Repair Sheet – see QCF 91 attached.

AttachmentCheck list Doc QCF Rev ALocation Sketch#113

Repair of concrete floor screedsTopIndexScopeReference documentsSafetyMethodEquipmentScopeThis statement outlines the repair procedures to be followed for the repair and reinstatement of defective floor screeds, so as to provide a durable and serviceable levelling layer for the floor covering placed above.SafetyPrior to commencement of any activity, the labour force shall receive a STARRTCard / Toolbox Talk relevant to the operation concerned on the project site safety requirements. Necessary measures shall be applied to any process involving a safety risk

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 302: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

302 of

Safety Supervision A competent inspector shall visit the area daily to assess the safety measures adopted. Any snag observed during his visit shall be notified to the supervisor present who immediately act to bring the safety measures to an acceptable standard ResponsibilitiesAll inspection and repair work related to the concrete floor screeds shall be under the sole direction of a dedicated Site Engineer (SE) who shall have full authority and responsibility for ensuring that the works are carried out in accordance with this Method Statement.Procedure5. Repair activities shall be restricted to a limited number of rooms at any time, and access to

the rooms restricted during repair. Before commencing any repair activity, including preparation, the SE shall ensure that previously completed works are suitably protected from damage and dust, using a combination of polythene sheeting and ply boarding as appropriate.

6. Before commencing any repairs in a room, the SE shall agree the scope of the repairs to be undertaken with the Site Quality Manager, with the agreed repair marked on the floor. The scope shall be recorded on a sketch and identify which type of repair is to be used and the approximate area of the repair. The repairs shall be selected from the following:Repair Type A – Removal and Reinstatement with Cement Screed.This repair should be adopted where the existing screed has completely disbonded and cracked, leaving loose isolated sections of screed.Repair Type B – Repair with Epoxy MortarThis repair should be adopted where there are significant isolated cracks in the screed. It is not intended to repair minor hairline cracks by this method, or construction joints between adjacent panels of screed, unless they have become otherwise damaged.Repair Type C – Repair with Resin InjectionThis repair should be adopted where the screed appears to be disbonded and cracked or lifting but is otherwise intact. This may be carried out in conjunction with repair Type B above. It is not necessary to use resin injection on hollow sounding areas where there is no other sign of failure. Repair Type D – Surface Epoxy CoatingThis repair shall be applied as a final protective coating to all repaired areas. As well as sealing any un-repaired hairline cracks, this shall also ensure an overall uniform appearance of the repaired areas.

7. The repairs shall be carried out as follows:Repair Type A: Removal and reinstatement with Cement Screed

A8. The affected area shall be sawcut to the full depth of the screed to be removed and the affected section removed carefully so as to cause minimum disruption to adjacent areas.

A9. The removed area shall be fully cleaned of all dust and debris, and any loose material removed.

A10. The cleared area shall be thoroughly soaked (not just dampened) for at least one hour before reinstatement.

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 303: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

303 of

A11. Immediately before placing the replacement screed, remove any surplus water (the substrate should still be wet) and apply one coat of NITOBOND PVA bonding agent to all surfaces – horizontal and vertical.

A12. Place and compact the replacement screed material. Trowel and immediately cover with polythene sheeting placed flat against the surface.

A13. Remove the polythene sheet after 4 hours and replace with wet hessian, covered with polythene sheeting. Ensure that further water is added to the hessian at least twice daily for a minimum of three days. The hessian to be kept damp the whole time

A14. Ensure that no-one walks on the repair for minimum three days. If unavoidable, lay ply sheet over repair, ensuring it remains in place.

Repair Type B – Repair with Epoxy MortarB1. Using a hammer and chisel, carefully chase a ‘V’ notch along the length of any crack

and along the edge of any loosened area. This should typically be 5mm from the edge of the crack and 5mm deep.

B2. Physically remove all loose material and clean using a using a wire brush or similar. Remove all dust and debris, using a brush and / or vacuum cleaner.

B3. Mix the repair material – NITOMORTAR FC-B (or FC) – in accordance with manufacturers recommendations and firmly press the repair mortar into place using a steel trowel. Finish the material flush with the surrounding concrete. It may be necessary to apply a second levelling coat if the material settles.

B4. Ensure that the repair area is not walked on for 24 hours.

Repair Type C – Repair with Resin InjectionC1 Drill three 10mm holes in the area to be repaired, to a depth of approximately 35mm,

representing the interface between the two screed layers. This can be determined by the change in sound of the drill.

C2. Fix an injection nipple to the drilled holes using an epoxy mortar e.g NitoMortar FC-B, and seal using a trowel. Allow to set for eight hours.

C3. Mix the repair resin – NITOFILL EPLV – in accordance with the manufacturers reccomendations, and insert into injection gun.

C4. Commence filling the central nipple, and continue until resin is observed at the outer nipples. If neccesary, continue filling the outer nipples. Note that material usage rate should be approximately 1litre per 1m2. Do not attempt to place more than this, or the floor could lift further.

C5. Leave for 6 hours, then remove the nipples and fixing mortar, and make the surface good using epoxy mortar ( Nitomortar FC-B or FC).

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 304: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

304 of

Repair Type D – Surface Epoxy CoatingD1. Ensure all repairs have been completed and allowed to cure (24 hours for epoxy repair

– 5 days for cement screed repair).

D2. Brush the surface thoroughly to remove all dust and debris. Ensure that the surface is not wet or damp.

D3. Mix the material – NITOFLOR FC140 - in accordance with the manufacturers instructions. Firstly apply a stripe coat to any untreated minor cracks, taking care to work the paint into the crack.

D4. Starting at the furthest corner, apply a single coat to the entire surface using a brush or roller, ensuring that the material fully coats the surface but without ponding.

D5. Ensure that the surface is not walked on for 24 hours.

8. Details of all repairs shall be recorded on a Screed Repair Sheet – see QCF 91 attached.

AttachmentCheck list Doc QCF Rev ALocation Sketch#114

Epoxy grouting to Vibrating installation basesUsing masterflow 648 cpGeneral foundationsTopIndexScopeReference documentsSafetyMethodEquipmentScopeThis statement is aimed to propose the procedures to be adopted to grout the base plates of vibratory installations using epoxy grout material for varying grouting thickness for normal thickness range Reference DocumentsSpecification

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 305: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

305 of

SafetyPrior to commencement of any activity, the labour force shall receive a STARRT Card / Toolbox Talk relevant to the operation concerned on the project site safety requirements. Necessary measures shall be applied to any process involving a safety riskSafety Supervision A competent inspector shall visit the area daily to assess the safety measures adopted. Any snag observed during his visit shall be notified to the supervisor present who immediately act to bring the safety measures to an acceptable standard MethodThin section- A gap between a base plate and substrate below 25 mmThick section- A gap between a base plate and substrate above 80mm Normal thickness- In between the thin and the thick sectionsRefer to MBT clarification attachedThe following activities are involved for normal thickness

Surface preparationMetal parts that should not be bonded to the grout like jack screws of the reciprocating machinery and part of the foundation bolts shall be sealed with tape prior to grouting.Base plates and equipment bases shall be uniformly supported in order to eliminate sag, distortion and levelled using both anchor bolts and jackscrews.Stainless steel shims 50x50x10 mm thick shall be placed in correct locations covered with mortar so as to allow at least 50 mm grout cover on shim sides.Full extent of the foundation surface under the base plate or equipment to be grouted shall be chipped / scabbled & brushed to remove the weak upper layer of concrete and any oil soaked concrete areas prior to the installation of the base plate Base plate surfaces in contact with epoxy grout shall be grit blasted so as to expose white metal All surfaces and bolt pockets to receive grout must be clean & free of rust, oil, dirt, paint and residual curing compound All base plate holding down bolts etc must be free of rust, oil, dirt or contaminants that could impair bondFormwork Unless otherwise shown on design drawing, the entire area under the base plate shall be grouted and the forms fixed around the plate keeping a minimum of 25 mm clearance from the plate edge and at least 50 mm from the edge of the pouring side so that total groutable area is equal to underside of the plate and the clearance around the plate.Before the form work is fixed, it shall be ensured that the foundation area to be grouted and the bolts holes are cleanA liquid tight formwork as practicable, shall be fixed around the base plate to prevent the leakage of the resin keeping the top of the forms 25mm above the underside of the base plateA chamfer 25mm x 25mm shall be provided on the sides so that top of the chamfer and the top of grout are in one level in case the whole of the foundation area around the plate is to be grouted,

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 306: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

306 of

A 45 sloping surface above the form on the pouring side shall be constucted to create a pressure head to enable the grout material flow to cover full width of the pourA coating of an approved release agent shall be applied to the form work Civil Contractor QC inspection shall be conducted to ascertain the form profile and general preparatory worksGrouting applicationAll dirt and debris shall be removed from the form work using compressed air Sufficient Grout material to completely fill the prepared area in a continuous process shall be made available Mixing equipment shall be demonstrated to be in a suitable as well as in good working conditionA standby equipment shall also be made available Concrete surfaces to be grouted shall be completely dry before groutingMixingBase and reactor components shall be poured into a suitable mixing vessel and mixing carried out for 1 minute or until successfully blendedAll required quantity of aggregate shall be added to the mixing vessel which is to be kept turning and mixing continued until a uniform lumpfree consistency is achieved. Overmixing shall be avoided to prevent air entrainmentPlacingAll bolt pockets shall be filled with grout prior to pouring the rest of the underplate space as a separate operation to prevent voids formationPouring of the grout shall start from one end of the base plate and continued until the material reaches the far side. Mixed grout shall be steadily poured down the form work slope to avoid air entrapment Pouring shall be carried out only from one side of the base plate to avoid creation of voids and any reduction of the effective bearing areaWhen the grout reaches the far side of the formwork which shall be ensured by poured material rising above the bottom of base plate, the pouring location has to move along the length of the base plate keeping the process continued until the whole area is completed. Civil Contractor QC inspection shall be conducted throughout the above operations to ascertain the proper implementation of the procedures according to the manufacturer’s instructionsShoulders- Exposed surfaces shall be brushed with Solvent # 2 just before or as the grout gelsCuringNo curing is requiredMajor EquipmentPeddle Mixer / Mixing VesselAttachmentSketchesMasterflow 648 CP datasheetMBT Method statement

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 307: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

307 of

#115

Kerbs & interlocking blocks paving around buildingsTopIndexScopeReference documentsSafetyMethodEquipmentScopeThis statement is aimed to propose the procedures to be adopted to lay kerb stones and concrete interlocking blocks in paving around buildingsReference DocumentsSpecification MAR and SafetyPrior to commence any activity, the labour force shall receive a STARRT Card / Toolbox Talk relevant to the operation concerned on the project site safety requirements.Necessary measures shall be applied to any process involving a safety riskSafety Supervision A competent inspector shall visit the area daily to assess the safety measures adopted. Any snag observed during his visit shall be notified to the supervisor present who immediately act to bring the safety measures to an acceptable standard MaterialKerb stones, Interlocking Paving blocksMethod All loose soil shall be cleared and formation level made up and well compacted (Laying Kerb stones) Setting out kerb excavation lines according to drawingExcavation upto the formation level i.e 325mm from the kerb top levelForm work fixing and pouring grade 20 concrete 200mm wide and 100 mm thickBedding in cement mortar 1 :4, 25mm thick for kerb stonesFixing kerb on the mortar to the true lines and levels with chamfer facing pavement & jointing with mortarPlacing haunch back concrete grade 20, 150 mm high in triangular sectionFilling above haunch portion with soilAn Civil Contractor QC inspection shall be conducted for kerb laying approval and ITP signed off(Laying Paving Interlocking blocks)Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 308: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

308 of

Thickness of the interlocking blocks 60mmThickness of the sand bedding 50mmTop level of sand in joint from the kerb top level 50mmSharp sand to be consumed shall be piled up along the area to be paved and evenly spread with the blocks laid over snugly to the agreed pattern and colourPlank runs shall be used to allow barrows to move on to avoid level disturbanceThe blocks shall be laid in full but at the edges of the obstacles such as inspection covers where cut blocks may be required, whole blocks shall be laid first wherever possible and the trimmable blocks exactly marked & cut to the required size.After sufficient blocks have been laid, sand bedding shall be carried out using a plate vibrator pressing the blocks to the required level in 2 passes covering entire area with each pass to make the bedding evenSand shall be spread on the surface of the blocks with 2 more vibrator passes applied &brushed under the leading edge of the vibrator to allow the joints vibratedA Civil Contractor QC inspection shall be conducted to approve the pavingMajor EquipmentPlate CompactorAttachmentManufacturer’s Conctruction method#116

Erection of steel structures (for higher levels)TopIndexScopeReference documentsDefinitionsResponsibilitiesSafetyMethodEquipmentScopeThe purpose of this Method Statement is to define the sequence and methodology that shall be implemented for the erection of the steel structures.Reference DocumentsSpecification GroutingSpecification Steel Structure FabricationSpecification PaintingSpecification Galvanizing

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 309: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

309 of

Specification Structural Steel ErectionANSI A 10.13 Safety Requirements for Steel RequirementsRelevant IFC DrawingsMethod Statement – Structural SteelDefinitionsCM Construction ManagerCS Construction SuperintendentEF Erection ForemanResponsibilitiesThe CM shall plan and resourse the steel structure erection activies, to ensure that they are implemented according to this procedure, with the correct equipment resources. The CS shall ensure that all safety requirements are implemented and explained to the erection work force. The CS shall control the day to day activities.The EF shall control the workforce ensuring the full implementation of this method statement including all safety measures.SafetyBefore commencement of any task the relevant qualified labour force shall first receive a Safety Task Analysis Risk Reduction Talk about the task to be performed and all safety hazards shall be addressed as required.Main activities to be implemented are:

a) Safe access to elevated levelsb) Man basketsc) Full body harnessd) All P.P. Equipmente) Extra Harness Lanyardf) Stay ropesg) Life Line

MethodMaterial ReceivablesAll structural steel material to be used for permanent works shall be received on site and checked against relevant documents. All members shall be checked for quantity and identification and transportation damage.Concrete FoundationsThe surface of the concrete foundation shall be prepared in accordance with the specification to receive grout.All concrete foundations on which the steel structures shall be erected shall be released by the QC department, upon completion of the civil activity.Method BriefingStructures erected to date were low levels, varying from 6m to 16m and access was easy. Now the structures are at levels from 12m to 33m.These main columns or grid frames shall be assembled on the ground near the foundation. These shall then be installed on the columns using the appropriate capacity crane. Stay ropes

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 310: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

310 of

shall be used to secure these till the connecting horizontal member beams are installed. All splice plates shall be installed and bolted down before the horizontal members are connected.Steel Catcher crew with the necessary full body harness & lanyard shall be placed in position on the beams using either a man lift or man basket. The full body harness shall secure the steel catcher to the steel. Steel Catcher shall move around on the steel by the “Slip & Slide” method to get in position for the next member. Life lines shall also be pulled between columns, so that the steel catchers can walk on the beams below with their Safety Harnesses hooked onto the life line. Access ladders shall be installed as soon as possible for safe access. The other option shall be to install step ladders. All fasteners shall be installed and then the line & levels checked. When the first level of steel with the majority of the horizontal members are installed, line & levels checked, the grouting of the column base plates shall then be grouted as per the approved procedure.Platform\Handrails\Gratings:After completion of the main steel erection, the platform\handrails shall be installed as required as per drawings.Major EquipmentMobile cranesMan liftMan basketGuy ropes and tensioning equipmentFlat bed trailers and forklifts\other mobile shifting equipmentAir compressorImpact wrenchWelding generatorsGrinding machinesDrilling machines#117

Vinyl flooring buildingsTopIndexScopeReference documentsSafetyMethodEquipmentScopeThis statement is aimed to propose the procedures to be adopted to lay Vinyl tiles floor finish on cement sand screed in buildingsReference DocumentsSpecification

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 311: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

311 of

MAR SafetyPrior to commence any activity, the labour force shall receive a STARRT Card / Toolbox Talk relevant to the operation concerned on the project site safety requirements.Necessary measures shall be applied to any process involving a safety riskSafety Supervision A competent inspector shall visit the area daily to assess the safety measures adopted. Any snag observed during his visit shall be notified to the supervisor present who immediately act to bring the safety measures to an acceptable standard MaterialVinyle Tiles, Adhesive- Laybond Multibond Gold (Multi Purpose Acrylic ) Method Surface shall be broomed followed by vacuum cleaning. The sub floor shall be dry and free from contaminants, hardening compound , dust and other deleterious matter immediately prior to floor installationAdhesive shall be spread evenly over the surface with a triangular notched trowel 1.5mm deep cut at 5mm centres with a sweeping motion at about 60 degree angle to horizontal &allowed to reach a tacky consistency Vinyl covering shall be placed into position and rolled using 68 kg roller to ensure overall contact A Civil Contractor QC inspection shall be conducted for approval and ITP signed offMajor EquipmentRoller 68 Kg, Notched TrowelAttachmentAdhesive Manufacturer’s Conctruction method#118

Concrete pavingTopIndexScopeReference documentsSafetyMethodEquipmentScopeThis statement is aimed to propose the procedures to be adopted to construct the concrete paving Reference DocumentsDrawing Road & Paving Details Sheet 1

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 312: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

312 of

Specification SafetyPrior to commence any activity, the labour force shall receive a STARRT Card / Toolbox Talk relevant to the operation concerned on the project site safety requirements.Necessary measures shall be applied to any process involving a safety riskSafety Supervision A competent inspector shall visit the area daily to assess the safety measures adopted. Any snag observed during his visit shall be notified to the supervisor present who immediately act to bring the safety measures to an acceptable standard MaterialFibre Concrete grade 30, Joint filler board, Crack Inducer, Welded Wire Fabric, Oil resistant joint sealant Method All the relevant underground services shall be laid in all respects prior to the commencement of the pavement workThe area to be paved shall be made ready by clearing all weak soil & by scarifyingApproved sub base material 150mm thick shall be filled up to the bottom of the concrete slab following the profile given on the drawing and compacted to 95 % dry proctor densityWeed killer chemical shall be applied to the soil to prevent the organic growthThe whole area shall be divided into parts to suit the services and the contraction joints formations & as shown on drawingsOn the’ compacted filled area’ to be paved, polythene sheet 0.25mm shall be placed with end overlaps at least 150mm at all joints and intersectionsEnd forms shall be fixed on sides allowing a provision to place 20MS dowel bars 650mm long & 300mm centres half painted with 2 coats bitumastic paint with 100mm long cardboard cap containing compressible material such as cotton waste at the expansionjoint to the details shown on the drawing. The thickness of the expansion joint shall be 20mm Refer to detail 9At contraction joints 25x25 mm plastic crack inducer shall be provided as shown in the detail 10 & the joints cut for a depth of 20mm with a concrete cutting machineWelded wire fabric mesh dia 7mm –200# shall be placed in the bay centrally located with concrete spacers belowForms shall be set to correct levels so that the total thickness of the concrete is as specied on the drawingsCivil Contractor QC inspection shall be conducted for the pour approvalConcrete shall be poured in one layer and compacted using parker vibrator to brush finish & to correct levels.Curing compound shall be spread on the surface for immediate curing covered with polythene sheet and later within 2 hours damp hessian added by removing polythene sheet temporarily and recovered thereafter The expansion joints between the two adjacent slabs shall be filled with an elastic joint filler and sealed with a chemical resistant sealant complying with the details shown on the drawings Refer to detail 12 – Details A & B Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 313: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

313 of

Details A shows 20mm x 25 mm joint seal and detail B shows 15mm x 20mm slightly rounded to prevent damage to edgesCivil Contractor QC inspection shall be conducted Major EquipmentConcrete Pump, Transit Mixer, Parker / Dr Kewande Vibrator, Concrete cutting machine AttachmentNone#119

Central control building Ceramic tiles flooring systemTopIndexScopeDefinitionsMaterialMethod EquipmentAttachmentScopeThis statement is aimed to propose the procedures to be adopted to construct the‘ceramic tiles flooring system’ which involves the laying of the bedding screed as well as the finishing layer with grouting the joints including movement joints.Reference documentsDrawing Nos. Specifications page STQ Qand UBC & general construction practiceSafetyPrior to commence any activity, the labour force shall receive a STARRT Card / Toolbox Talk relevant to the operation concerned on the project site safety requirements.Necessary measures shall be applied to any process involving a safety riskProper illumination shall be provided in the dark area Safety Supervision The area to be tiled shall be closed for the general movement except those working there and be opened only when the tiling has properly been completed with hardboard cover protection spread on the newly laid flooring.

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 314: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

314 of

A competent inspector shall visit the area daily to assess the safety measures adopted. Any snag observed during his visit shall be notified to the supervisor present who immediately act to bring the safety measures to an acceptable standard MaterialsCeramic floor tiles 300 x 300 x 10mm, For General Area ‘RAK GP 21 G’ and for wet areas Johnson ‘Athena’Cementitious adhesive- Nitotile GPJoint filling grout – Approved proprietary material with matching shade.Method (Laying ceramic floor tiles by SEMI DRY method)The areas of concrete sub strata to be tiled shall be brush cleaned and dampened until absorption ceases followed by the finished floor level establishment by means of dots and rules. The total thickness of the ceramic tile flooring is 100 mm which includes 90 mm bedding screed (1 cement: 4 mortar sand) to be mixed by weight and 10 mm thick ceramic tiles, shall be applied as described below.The mortar for bedding the tiles shall be 1 part cement to 4 parts sand by weight, mixed semi dry by a mechanical mixer with only sufficient water added to give a crumbly consistency which retains its shape when squeezed by hand permitting no fluidityThe mix shall be placed to a thickness approximately 10 mm greater than that actually required for the bed, thoroughly compacted by tamping and drawing off to the required level with a screed board and given a smooth trowel finish. Civil Contractor QC visual inspection shall be conducted to ascertain proper compaction and levels.The surface of the screed shall be cleaned by brush prior to the application of the adhesive. The adhesive shall be mixed with water using a slow speed drill to the water adhesive ratio per manufacturer’s data sheet. Adhesive Nitotile GP mix shall be applied in uniform thickness of 2 to 3 mm over the surface of the cement sand screed bedding and then combed horizontally.

Tiles shall then be laid on the adhesive layer with a twisting motion ensuring good contact between the tile and the adhesive bed. For this purpose the adhesive manufacturer’s instruction shall be adhered to.The tiles shall be correctly positioned in both directions the time these are placed forming joints using a proprietary tile spacer ( 1.5 mm for wall tiles and 3 mm for floor tiles)The tiles shall neatly and accurately be cut to a close fit where necessary at abutments, around outlets, pipes and the like.Civil Contractor QC Inspection shall be conducted for the correct formation of joint alignment and the level profileThe tiles shall be laid level or to 1- % falls in ‘wet’ areas as may be required. Localised variations in level for a nominally flat floor shall be a maximum of +- 2-mm under a 3-meter straight edge. Particular care shall be taken in ‘wet’ areas to prevent low spots that may

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 315: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

315 of

promote water pooling. The tolerance in the overall level shall not be more than 10 mm from required finishes. (Reef STQ Q)Excessive adhesive shall be removed with a damp cloth before the material has set.Grouting of the joints shall be carried out after a period of 24 hours after completion of laying of tiles. MOVEMENT JOINTS IN TILED FLOORSUnless otherwise indicated in the documents, a 10 mm movement joint shall be formed at the perimeter of all the tiled floors and where the tiling meets structural features such as columns, machine bases etc.,Where a structural movement joint is provided in the base, a movement joint of the same width in the bedded finish shall be positioned immediately aboveThe movement joint cavities shall extend through the combined thickness of the finish and the bedding mortar, completely filled and sealed after grouting of the normal joints takes place.Major EquipmentMechanical MixerWheel barrowsMason’s tools in generalSlow speed drillAttachmentAdhesive manufacturer’s Datasheet#120

Concrete placementTop IndexScopeReference documentsDefinitionsResponsibilitiesSafetyMethodEquipmentAttachmentScopeThe purpose of this method statement, is to define the procedure that shall be adopted for the placement of structural concrete upon the project.Reference documentsProject Specification Project Specification ACI 301 chapter 8. DefinitionsEPC Contractor

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 316: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

316 of

Civil Contractor PSM Project Site Manager.ResponsibilitiesThe Construction Superintendent shall ensure that the concrete Foreman implements this procedure. The Concrete Foreman shall ensure that the concrete crew is fully aware of this procedure and the correct methods of working.SafetyThe Safety Officer shall monitor the concrete activities, advising and implementing all safety procedures.MethodThe structure that is to be concreted, shall be inspected and approved as correct, by both Civil Contractor and EPC Contractor.The permission to place concrete shall be authorized by EPC ContractorThe concrete Foreman shall ensure that he has adequate equipment resources (vibrating pokers, compressors, hoses, steelfixer, carpenter, water etc), at the location of concrete placement.When the site laboratory concrete technician, has approved the concrete delivery, the concrete placement activity can commence. Refer to Method statement, Testing of Fresh Concrete.The concrete shall be discharged by one of two methods. For pours greater than two cubic meters in volume, the concrete shall be discharged through a concrete pump. For pours less than two cubic meters, the concrete can be discharged direct from the truck mixer.Regardless of the method of discharge, no concrete shall be dropped from a height greater than two meters, or in a manner that shall cause the segregation of the aggregates.Immediately prior to placement activities commencing, the reinforcement within the concrete pour, shall be sprayed with clean water. The placement of the fresh concrete within the shutters, shall be in a logical sequence. Concrete shall be placed at locations that do not exceed 1.5 meters from the final location of the concrete. The maximum concrete layer thickness of 450 mm shall be observed.The fresh concrete shall be compacted with pokers of sufficient size and number. Consolidation of the fresh concrete, shall commence when the placement of the concrete is adequate, so that uncontrolled segregation does not occur. Concrete shall be placed in a sequence that ensures that cold joints are eliminated. Each subsequent layer of concrete shall be adequately compacted into the concrete layer below.Where encast plates, holding down bolts, or any other critical embedded item is included within the pour, the surveyor shall check the location and elevation of that item, when concrete placement has been completed.

Immediately the concrete finishing has been completed, the concrete shall be covered with white polythene sheeting, ensuring that the edges are sealed to prevent the circulation of air.Upon adequate setting of the concrete, the white polythene sheeting shall be removed. Hessian which has been soaked in water, shall be placed over the set concrete. The white polythene sheeting shall be replaced and sealed at the edges. The hessian shall be kept moist for a period of 14 days.

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 317: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

317 of

(Note: it is proposed to apply for a specification concession to use a water based curing compound, in leu of water curing.)When shuttering is removed from a pour, the resultant concrete surface shall be inspected. Where a defect is observed, the defect shall be classified as minor or major. A minor defect is one which does not impair the strength of the structure or is greater than 10mm by 10mm. This minor defect shall be repaired using a patching mortar.A major defect shall be brought to the attention of the QA department. A major defect shall be any other surface defect that is larger than 10mm by 10mm. The method of repair of such defects shall be discussed and agreed with EPC Contractor.The repairs to the concrete surfaces shall be cured according to the requirement for fresh concrete. EquipmentTruck Mixer.Concrete Pump.Vibrating Pokers.Compressors.AttachmentITP No: Concrete Placement.

#121

Precast rcc coversCable & instrumentation trenchesTopIndexScopeDefinitionsMaterialMethod EquipmentAttachmentScopeThis statement is aimed to propose the procedures to be adopted to carry out the construction of the covers for the Instrumentation and the electrical cable trenches.Reference documents

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 318: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

318 of

Drawing NosSpecifications SafetyPrior to commence any activity, the labour force shall receive a STARRT Card / Toolbox Talk relevant to the operation concerned on the project site safety requirements.Necessary measures shall be applied to any process involving a safety riskSafety Supervision A competent inspector shall visit the area daily to assess the safety measures adopted. Any snag observed during his visit shall be notified to the supervisor present who immediately act to bring the safety measures to an acceptable standard MaterialsColoured concrete Grade 30Red colour concrete for the covers to be used on Electric cable trenchesGreen colour concrete for the covers to be used on Instrumentation cable trenchesRed or Green oxides to be added to the concrete @ 9 kg per cumLifting Lugs, 16mm dia with exposed portion galvanised, to be flush with concretePre fabricated mesh, 7 dia at 200 / 200Method Since various dimensions are involved for these typical pre cast concrete covers, the details of the lifting lugs with the exposed steel portion of the lug to be galvanised, have been given on the Attachment.Relevant details 5 L & 5 H on the above drawing indicate transverse joints to be formed at a spacing of 3m in case of 150mm thick covers and 1 m in case of 50 mm (proposed to be substituted by 100 mm) covers

The pre casting shall be carried out in the pre cast yard to the approved procedures using coloured concrete All other procedures pertaining to the concreting & transporting the members to the site locations shall be similar to as being adoptedPrior to placing the covers, the filled compacted base in the trench shall be prepared and polythene sheet spread to receive the covers.The covers shall be offloaded to the locations at the specified spacing leaving a gap of 25 mm between the ends to allow for the oil resistant joint sealantCivil Contractor QC inspection shall be conducted to ascertain the correct alignment and levelMajor EquipmentTransit mixerWheel barrowsMason’s tools in generalTrailorCraneAttachment

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 319: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

319 of

Sketching showing lifting lugs#122

Black top repair Ist street between Avenue c & bTopIndexScopeDefinitionsMaterialMethod EquipmentAttachmentScopeThis statement is aimed to propose the procedures to be adopted to carry out the repair to the road-wearing course damaged superficially to a portion on Ist Street betweenAvenue ‘’ and Avenue ‘’.Reference documentsNoneSafetyPrior to commence any activity, the labour force shall receive a STARRT Card / Toolbox Talk relevant to the operation concerned on the project site safety requirements.Necessary measures shall be applied to any process involving a safety riskSafety Supervision A competent inspector shall visit the area daily to assess the safety measures adopted. Any snag observed during his visit shall be notified to the supervisor present who immediately act to bring the safety measures to an acceptable standard MaterialsTack coat bituminous material 60 / 100 penetration to be applied @ 2.5 litres per sqm of road surfaceAsphalt for 40mm thick course according to requirement WaterMethod Traffic diversion if so required shall be effected to the requirementDamaged portion of the ‘wearing course’ shall be removed using ‘Asphalt Remover’ and the surface cleaned using a ‘Mechanical Cleaner’Tack coat shall be applied to the clean surface according to the specified rate of application as aboveAsphalt shall be applied to a required thickness (minimum 40 mm) finished to full extent of the damaged area making up the level to the existing wearing course

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 320: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

320 of

Laid material shall be spread and finished to the required level using Asphalt Finisher First rolling shall be carried out using pneumatic roller ‘6’ tonne capacity giving required number of passesThen second rolling shall be carried out using Tandem roller 8 / 10 tonnes capacity according to the requirement giving required number of passes Water shall be used during rolling according to the requirementCivil Contractor QC inspection shall be conducted to ascertain the correct finished levelMajor EquipmentAsphalt RemoverAsphalt FinisherPneumatic RollerTandem RollerWater TankAttachmentNone#123

Repair of Single leaf swing gatesTop

IndexScopeDefinitionsMaterialMethod EquipmentAttachmentScopeThis statement is aimed to propose the procedures to be adopted to carry out the repair to the emergency gates to be installed in the sub station fence for transformers. A lock usable from outside is to be added to the gate.Reference documentsAttached sketch

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 321: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

321 of

SafetyPrior to commence any activity, the labour force shall receive a STARRT Card / Toolbox Talk relevant to the operation concerned on the project site safety requirements.Necessary measures shall be applied to any process involving a safety riskSafety Supervision A competent inspector shall visit the area daily to assess the safety measures adopted. Any snag observed during his visit shall be notified to the supervisor present who immediately act to bring the safety measures to an acceptable standard MaterialsNew postSelf levelling grout to specificationEpoxy paint system or galvafroidMethod Vendor – Link Middle East LtdExisting gate post shall be cut using gas cutting equipment to a level as shown on the sketch and discardedA new post dia 88.9mm including a locking lug shall be added with a sleeve- slot by welding at the vendor’s shop with 70 mm out to out PVC coated per specification. A circumferencial overlap shall be made in such a way that a minimum of 100mm overlapping length lies below finished concrete level in addition to projection above A portion of the concrete necessary to allow working area (150 mm deep apprx) to weld the circumference on site shall be removed prior to the new post is erected for installationThe new assembled post shall be properly aligned to the requirementWelding shall be carried out to the circumference After welding galvafroid or epoxy paint system shall be applied according to manufacturer’s instructionsAn Civil Contractor QC inspection shall be carried out for the approval of the welding and the paint systemThe surface of the broken concrete shall be cleaned and approved, forms if necessary, prepared and self-levelling grout shall then be applied to the manufacturer’s instructions and finished accordinglyMajor EquipmentOxy Acetylene Gas cutting systemWelding setAttachmentSketch showing proposed arrangement#124

Repair to Floor screed levels Top

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 322: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

322 of

IndexScopeDefinitionsMaterialMethod EquipmentAttachmentScopeThis statement is aimed to propose the procedures to be adopted to carry out the repair to eliminate the uneveness from the floor screed surface, prior to applying the Rubber flooringReference documentsNone SafetyPrior to commence any activity, the labour force shall receive a STARRT Card / Toolbox Talk relevant to the operation concerned on the project site safety requirements.Necessary measures shall be applied to any process involving a safety riskSafety Supervision A competent inspector shall visit the area daily to assess the safety measures adopted. Any snag observed during his visit shall be notified to the supervisor present who immediately act to bring the safety measures to an acceptable standard MaterialsFosroc Nitoflor LeveltopThis is a self-levelling, cementitious underlay for a wide variety of floors finishes requiring a smooth level substrateMethodPreparationThe sub strata shall be clean, sound and free from loose material and contamination such as plaster oil and greaseExcessive laitance shall be removed by light scabbling or acid etching followed by washing and debris removed using vacuum cleanerLarge cracks and holes shall be filled with a mix of Nitoflor leveltop and clean sharp sand made to a trowel consistency by adding small quantity of water.Substrate shall be primed with 1:1 water Nito bond PVA mixture prior to the repair is doneMixingMaterial shall be mixed using a heavy-duty drill fitted with a purpose made paddle. Clean water @ 6.5 liters per bag of 25 kg material shall be used as per manufacturer’s instructionsFirst 2 / 3 rd required quantity of water shall be added to the mixing vessel followed by gradually and slowly adding the material from the bag and mixed for 3 minutes minimum Remaining 1 / 3 rd required quantity of water shall be slowly added throughout to the mix and mixing continued until a smooth, self levelling & pourable mix consistency is obtained

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 323: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

323 of

Material shall be poured onto the primed substrate, spread with trowel or squeegee and allowed to self levelThe material shall be rolled with a Fosroc spiked roller to achieve air release with final level. Rolling shall be carried out immediately after material is placed. High spots or splashes shall be scraped off with the edge of a trowel after initial setRequired thicknesss shall be achieved in one application only with maintaining continuous process of pouring and levelling until the designated area is completedCuring is generally not requiredAn Civil Contractor QC inspection shall be carried out throughout during the above operationsMajor EquipmentHeavy duty drillMixing Vessel Squeegee and other toolsAttachmentFosroc Data Sheet#125

Resin injection to leaking joint Sea water surge basin TopIndexScopeDefinitionsMaterialMethod EquipmentAttachmentScopeThis statement is aimed to propose the procedures to be adopted to carry out the injection to the leaking joints at the sea water surge basin observed during water tightness test according to the BS code 8007.Reference documentsBS code 8007

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 324: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

324 of

SafetyPrior to commence any activity, the labour force shall receive a STARRT Card / Toolbox Talk relevant to the operation concerned on the project site safety requirements.Necessary measures shall be applied to any process involving a safety riskSafety Supervision A competent inspector shall visit the area daily to assess the safety measures adopted. Any snag observed during his visit shall be notified to the supervisor present who immediately act to bring the safety measures to an acceptable standard MaterialsMaster Building Technology, Masterseal 505Concresive 1335 and 1320MethodLeakage Control TechnologyThe’ leaking joints’ shall be reinstated by injecting resin using MBT material according to the MBT proposed statement and the material data sheet attachedPreparation and application of a ‘Low Viscosity Polyurethane Injection Resin’ used for reinstating the structural integrity of cracked concrete accommodating slight movementThe following operations are involvedPreparationThe location of the leakage shall be markedLeaking water shall be plugged with Masterseal 505Once the water running is temporarily stopped, holes shall be drilled on both sides of the expansion joint at an angle and at 200 to 500 mm spacingMetal screw packers shall be installed in the drilled holes and tightened so that the injected material does not leakApplicationFirst stage injectionConcresive 1335 shall be injected into the packers to further stop the water as it foams and cures within 30 seconds stopping any flow of waterSecond stage injectionConcresive 1320 shall be injected using a high pressure (up to 240 bars) an electrically operated injection machine at a suitable pressure. This injection shall react with water as well as bubble up to a fine foam and seal the leaking crack / joints permanentlyLeak shall be checked again after 24 hours and re-injection applied if requiredPackers shall be removed the next day and holes re-profiled using non shrink groutDuring the complete operations Civil Contractor QC inspection shall be carried out to record that the leakage has been controlled to the code requirementMajor EquipmentHigh pressure electric Injection systemMetallic PackersAttachment

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 325: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

325 of

MBT Method StatementMaterial Datasheet#126

Resin injection to leaking joint Sea water surge basin TopIndexScopeDefinitionsMaterialMethod EquipmentAttachmentScopeThis statement is aimed to propose the procedures to be adopted to carry out the injection to the leaking joints at the sea water surge basin observed during water tightness test according to the BS code 8007.Reference documentsBS code 8007 SafetyPrior to commence any activity, the labour force shall receive a STARRT Card / Toolbox Talk relevant to the operation concerned on the project site safety requirements.Necessary measures shall be applied to any process involving a safety riskSafety Supervision A competent inspector shall visit the area daily to assess the safety measures adopted. Any snag observed during his visit shall be notified to the supervisor present who immediately act to bring the safety measures to an acceptable standard MaterialsMaster Building Technology , Concresive 2200 / Masterseal 505Concresive 1335 and 1320MethodThe leaking joints shall be reinstated by injecting resin using the MBT material according to the MBT proposed statement and the material datasheet attachedPreparation and application of a low viscosity Polyurethane injection resin used for reinstating the structural integrity of cracked concrete accommodating slight movementThe following operations are involvedThe location of the leakage shall be markedThe water shall be pumped out from the basinLaitance and contaminants shall be removed from the surface from a band 50mm wide centered on crack using light grit blastingStatements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 326: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

326 of

Holes shall be drilled along the center of the crack for packers at not more than 300 mm apartCompressed air shall be used to remove dust and debrisMixed concresive 2200 shall be applied to the bottom of the flange at perimeter ensuring the paste does not block the portPorts shall be located over the crack centerConcresive 2200 shall be applied in a strip 20mm wide and 2-3 mm thick between the ports and the crack center after all the ports have been placedForcing the paste into the substrate to ensure intimate contact and seal around the port and allowed to cureApplicationIn case of flowing water Concresive 1335 shall be injected into the crack / joint befire using concresive 1320 and when the water ingress stops, the concresive 1320 shall be injected into the joint / crackInjection process shall be started from one end of the crack moving bottom upwards in the case of a vertical jointBoth the components of concresive 1320 shall be mixed for at least 1 minuteInjection gun shall be filled with mixed resinAnd connected to the port and injection startedResin shall continue to be injected until it starts flowing from the next port. The port under injectin shall be closed at this stage and the other started being injectedAll ports shall be injected similarlyResin shall be allowed to cure.Injection ports shall be removed and the paste ground ver the cracks if so requiredAn Civil Contractor QC inspection shall be carried out for the approval of the welding and the paint systemWater shall be filled to the specified test levl and test reconducted according to the code requirementMajor EquipmentInjection system / Hand gunCompressorGrit blasting unitPort flangesGrinderAttachmentMBT Method StatementMaterial Datasheet#127

resin injection to leaking joint sea water surge basin

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 327: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

327 of

TopIndexScopeDefinitionsMaterialMethod EquipmentAttachmentScopeThis statement is aimed to propose the procedures to be adopted to carry out the injection to the leaking joints at the sea water surge basin observed during water tightness test according to the BS code 8007.Reference documentsBS code 8007 SafetyPrior to commence any activity, the labour force shall receive a STARRT Card / Toolbox Talk relevant to the operation concerned on the project site safety requirements.Necessary measures shall be applied to any process involving a safety riskSafety Supervision A competent inspector shall visit the area daily to assess the safety measures adopted. Any snag observed during his visit shall be notified to the supervisor present who immediately act to bring the safety measures to an acceptable standard MaterialsMaster Building Technology, Masterseal 505Concresive 1335 and 1320Master Builders Technologies confirms that Concressive 1335 is a flexible / compressible material once set. No materials are to be introduced into the expansion joint that interfere with the function of the joint (ref the attachment)Applicator- Track record for appraisal respecting Dicotech, the applicator attachedMeasurement of injection quantitySince the material is supplied in small packing of 1 or 5 lts, the used quantity can be measured by counting the number of cans usedAccording to Dicotech the most effective means of injection is from outside as point of crack or leakage can be seen which is almost impossible from inside MethodLeakage Control TechnologyThe’ leaking joints’ shall be reinstated by injecting resin using MBT material according to the MBT proposed statement and the material data sheet attachedPreparation and application of a ‘Low Viscosity Polyurethane Injection Resin’ used for reinstating the structural integrity of cracked concrete accommodating slight movementThe following operations are involved

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 328: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

328 of

PreparationThe location of the leakage shall be markedLeaking water shall be plugged with Masterseal 505Once the water running is temporarily stopped, holes shall be drilled on both sides of the expansion joint at an angle and at 200 to 500 mm spacingMetal screw packers shall be installed in the drilled holes and tightened so that the injected material does not leakApplicationFirst stage injectionConcresive 1335 shall be injected into the packers to further stop the water as it foams and cures within 30 seconds stopping any flow of waterSecond stage injectionConcresive 1320 shall be injected using a high pressure (up to 240 bars) an electrically operated injection machine at a suitable pressure. This injection shall react with water as well as bubble up to a fine foam and seal the leaking crack / joints permanentlyLeak shall be checked again after 24 hours and re-injection applied if requiredPackers shall be removed the next day and holes re-profiled using non shrink groutDuring the complete operations Civil Contractor QC inspection shall be carried out to record that the leakage has been controlled to the code requirementMajor EquipmentHigh pressure electric Injection systemMetallic PackersAttachmentMBT Method StatementMaterial DatasheetDicotech ref containing all details giving clarifications

#128

Fire water line excavation around consumer receipt station TopIndexScopeDefinitionsMaterialMethod Equipment

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 329: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

329 of

AttachmentScopeThis statement is aimed to propose the procedures to be adopted to carry out the excavation for Fire Water Lines to be laid by EPC Contractor around Consumer Receipt Station. Method Statement for the part of road crossing shall be submitted separately Reference documentsSpecification Excavation & Backfilling for Underground installationsInterconnects underground layout drainage Sheet 16 SafetyPrior to commence any activity, the labour force shall receive a STARRT Card / Toolbox Talk relevant to the operation concerned on the project site safety requirements.Necessary measures shall be applied to any process involving a safety riskSafety Supervision A competent inspector shall visit the area daily to assess the safety measures adopted. Any snag observed during his visit shall be notified to the supervisor present who immediately act to bring the safety measures to an acceptable standard In case of incident where utilities not identified are discovered or damaged, all work shall stop in the area and the Operator Shift Controller and HSE department immediately notifiedPhone number : Shift Controller Emergency NumberHSE Direct numberEmployees working in easement area shall have a daily pre-task briefing that includes;Reporting of incidentsMethods of work and tools to be usedPotential hazards found in the Easement areasThe approved work method statementEPC Contractor and Civil Contractor HSE department shall participate in presenting the STARRT card briefing and monitor the activities to ensure that the work methods are being followed and all personnel have an understanding of the hazards associated with working adjacent to live process areasMethodPermit pertaining to the relevant excavation area shall be obtained from Plant Refinery division. Existing services drawings shall also be obtained to ascertain safetySupervision at the workface must have a copy of the permit, drawing andthe method statementAttached sketch shows the location of the proposed Fire Water Line and existing Natural Gas pipe. Any existing services shown on the record drawings shall be located, identified & protected adequately with warning as required Cables or pipes that span the excavation shall be supported using split ducts and trays All existing services encountered shall be plotted by the surveyor on as built drawingThe surveyor shall set out the routes of the proposed 8”dia fire water line trenches conforming to the IFC drawings and to the sections shown on the attached sketch keeping a clear level Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 330: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

330 of

difference between existing natural gas and proposed firewater line 1000mm. which shall also be applicable between the existing 132 kv cable and the proposed fire water line Where necessary or as defined on the work permit, hand excavation shall be carried outWhen cable markers have been exposed, work shall be temporarily suspended and an evaluation made about the soil conditions. This evaluation shall be conducted by EPC Contractor Superintendent and Operator operations representative. Where necessary, a revised method of work may be necessary and in this instance, all personnel shall be briefedCables shall be protected by fitting split sleeves after exposureThe trench shall be excavated by an excavator to correct lines and levels to the specification requirement providing benching where necessary and employing all safety means. Barriers (including warning tape) shall be placed to indicate an open excavationThe excavated material shall be stockpiled in agreed areas for reuse. Surplus material shall be removed to the tip area in dump trucks. The surveyor shall monitor the lines and levels of the excavation operationExposed (Existing) cables and pipelines shall be checked for damage by EPC Contractor supervision and combined inspection shall be held by EPC Contractor and Civil Contractor. Operation department shall be invited to attendEPC Contractor engineer shall approve the suitability of the formation material by inspecting the trench bottom and after the approval, compaction of the formation level shall be carried out , the specified tests conducted and the results reported accordinglyThe surveyor shall provide level pins to indicate the correct elevation of the bedding required for 8” Fire Water line. The bedding shall be laid, compacted, tested and the results reported accordingly. The fire water pipes shall be placed correctly within the trench by EPC Contractor (not Civil Contractor) in accordance with EPC Contractor own method statements (noting that Al Jaber equipment is under the Direct Control of EPC Contractor).Upon acceptance of the pipe installation, the laid pipes shall be surrounded with further bedding material that shall be compacted using suitable equipment, tested and reportedThe approved backfill material shall be spread uniformly in layers of 150 mm up to the existing ground level, compacted to the specification requirement, tested & reported accordinglyThe site shall be left tidy of excavated and backfill material Major EquipmentExcavatorDump TruckCompactorAttachmentSketch and the drawing extract depicting proposed excavation route#129

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 331: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

331 of

Road crossingFor laying1 for 20” raw ethane1 for 6” propaneFirst streetTopIndexScopeSafetyMethod including traffic management schemeEquipmentAttachmentScopeThe statement is aimed to propose the procedures to be adopted to carry out the excavation at the road crossings to construct culverts to facilitate to lay the pipe lines 1 # each 20” Raw Ethane and 6” Propane at location identified on the attached drawing pertaining to First Street SafetyPrior to the commencement of any activity the labour force shall receive a / STARRT card / Toolbox talk. Any process involving a particular safety risk shall be assessed and adopted measures addressed to raise to a minimum standard In this case the excavation has to be carried out on the Operating Authority area, therefore all the regulated precautions shall be strictly adhered to effect ‘ full safety standard’.Safety Supervision A competent inspector shall visit the area daily to assess the safety measures adopted. Any snag observed during his visit shall be notified to the supervisor present who immediately act to bring the safety measures to an acceptable standard In case of incident where utilities not identified are discovered or damaged, all work shall stop in the area and the Operator Shift Controller and HSE department immediately notifiedPhone number : Shift Controller Emergency Number HSE Direct number Employees working in easement area shall have a daily pre-task briefing that includes;Reporting of incidentsMethods of work and tools to be usedPotential hazards found in the Easement areasThe approved work method statementStatements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 332: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

332 of

EPC Contractor and Civil Contractor HSE department shall participate in presenting the STARRT card briefing and monitor the activities to ensure that the work methods are being followed and all personnel have an understanding of the hazards associated with working adjacent to live process areasExcavation Work Permit- A copy of the work permit shall be posted on a mini board installed on site to be noticeable to all persons involved with the crossingBarricades, cones, markers, the night-lights, and floodlights etc. shall be installed as required for a complete safety. No oil spillage shall be allowed. Flagman-On both directions, in addition to the traffic sign boards, a flagmen shall be engaged full time to direct the traffic about the ‘excavation work in progress’ by ‘flag signal’ Hand Excavation- Excavation to expose the services shall be carried out manually.In case certain services not shown on the record drawings such as fibre optics but it is discovered, further excavation shall be ceased until a decision is taken for the method to be adopted for further excavationAccess to trench- The workers shall clearly be instructed to use only the ladders to enter in or come out of the trench. No jumping shall be allowedMachine ExcavationThe operators / drivers shall be explicitly instructed to abide by the requirement of the reverse signal and sound when operating reverse. Banksman shall be engaged equipment operation. No violation of the traffic rules shall be allowedPre cast membersSince pre cast culvert units, covers and sleepers are heavy in load, proper care has to be exercised during raising and downing (handling) to the exact locations strictly adhering to the relevant safety measuresMethodThe required permit to work shall be obtained from the Plant Refinery Division.The record drawings regarding the existing services shall be obtained.A traffic management scheme shall be produced on site as detailed on the attached sketch Drawing reference –Piping Interconnections F Street Culvert XTH Existing Services 3 # cables exist north side of the proposed crossing already exposedThe road shall be excavated in two instances by diverting the traffic on either lane completing one after the other as shown on the traffic management schemeProceduresTraffic management scheme shall be implemented effectivelyInstance 1The asphalt pertaining to the crossing portion Stage-1 shall be removed Hand excavation shall be carried out to expose the cables & the other services employing seaming the area with detectors to detect the existence of cablesAfter the exposure, all the cables shall be covered with split PVC pipe & well supported temporarily to continue the excavation mechanically Remaining portion of the trench shall be excavated by machine to the defined levelsPreparation of the trench to construct RCC culverts shall be carried out Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 333: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

333 of

The construction pertaining to the pipe carrying culverts including the laying of pipe sleepers anchored with standard dowels, covers, fixing steps etc.shall be carried out according to the drawings and the approved procedures using pre cast RCC units / membersIn addition, one access boxout at the end shall be provided to design detailsThe diverted services shall be reinstatedInspections shall be conducted to the requirementBackfilling up to the road formation shall be carried out according to specificationsThe broken asphalt portion shall be made good using new asphaltInstance 2The aforesaid activities shall be repeated for this instance for the crossing portion Stage-2The traffic management scheme shall be removed after the road crossing is cleared of all debris and obstructions.75-mm dia holes in the pre cast units meant for lifting shall be filled with concreteAccess boxout shall be closed with concrete after the pipes are laid Either side of the road shall be provided with cable markers to indicate the services8 mm galvanised removable chequer plate covers with 2 lifting handles shall be provided to design details. Other chequer plates shall be provided to the design detailsMajor EquipmentExcavator, Dumper trucks, Compactors. Jack Hammer, Compressor, Asphalt finisher, Road RollersAttachmentSketch showing the traffic management scheme #130

Road crossingFor laying1 for 20” raw ethane1 for 6” propaneFirst streetTopIndexScopeSafetyMethod including traffic management schemeEquipmentAttachment

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 334: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

334 of

ScopeThe statement is aimed to propose the procedures to be adopted to carry out the excavation at the road crossings to construct culverts to facilitate to lay the pipe lines 1 # each 20” Raw Ethane and 6” Propane at location identified on the attached drawing pertaining to First Street SafetyPrior to the commencement of any activity the labour force shall receive a / STARRT card / Toolbox talk. Any process involving a particular safety risk shall be assessed and adopted measures addressed to raise to a minimum standard In this case the excavation has to be carried out on the Operating Authority area, therefore all the regulated precautions shall be strictly adhered to effect ‘ full safety standard’.Safety Supervision A competent inspector shall visit the area daily to assess the safety measures adopted. Any snag observed during his visit shall be notified to the supervisor present who immediately act to bring the safety measures to an acceptable standard In case of incident where utilities not identified are discovered or damaged, all work shall stop in the area and the Plant Shift Controller and HSE department immediately notifiedPhone number : Shift Controller Emergency Number HSE Direct number Employees working in easement area shall have a daily pre-task briefing that includes;Reporting of incidentsMethods of work and tools to be usedPotential hazards found in the Easement areasThe approved work method statementEPC Contractor and Civil Contractor HSE department shall participate in presenting the STARRT card briefing and monitor the activities to ensure that the work methods are being followed and all personnel have an understanding of the hazards associated with working adjacent to live process areasExcavation Work Permit- A copy of the work permit shall be posted on a mini board installed on site to be noticeable to all persons involved with the crossingBarricades, cones, markers, the night-lights, and floodlights etc. shall be installed as required for a complete safety. No oil spillage shall be allowed. Flagman-On both directions, in addition to the traffic sign boards, a flagmen shall be engaged full time to direct the traffic about the ‘excavation work in progress’ by ‘flag signal’ Hand Excavation- Excavation to expose the services shall be carried out manually.In case certain services not shown on the record drawings such as fibre optics but it is discovered, further excavation shall be ceased until a decision is taken for the method to be adopted for further excavationAccess to trench- The workers shall clearly be instructed to use only the ladders to enter in or come out of the trench. No jumping shall be allowedMachine ExcavationStatements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 335: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

335 of

The operators / drivers shall be explicitly instructed to abide by the requirement of the reverse signal and sound when operating reverse. Banksman shall be engaged equipment operation. No violation of the traffic rules shall be allowedPre cast membersSince pre cast culvert units, covers and sleepers are heavy in load, proper care has to be exercised during raising and downing (handling) to the exact locations strictly adhering to the relevant safety measuresMethodThe required permit to work shall be obtained from the Plant Refinery Division.The record drawings regarding the existing services shall be obtained.A traffic management scheme shall be produced on site as detailed on the attached sketch Drawing reference –Piping Interconnections F Street Existing Services 3 # cables exist north side of the proposed crossing already exposedThe road shall be excavated in one instance by diverting the traffic on north side as shown ProceduresBackfilling shall be carried out to the existing excavated cross trench on north end of the proposed crossing up to the natural ground level to provide effective traffic ‘divertion routes’ from the road carriageway according to the traffic management scheme attachedTraffic management scheme shall be implemented effectivelyThe asphalt pertaining to the crossing portion shall be removed Hand excavation shall be carried out to expose the cables & the other services employing seaming the area with detectors to detect the existence of cables After the exposure, all the cables shall be covered with split PVC pipe and well supported temporarily to continue the excavation mechanically Remaining portion of the trench shall be excavated by machine to the defined levelsPreparation of the trench to construct RCC culvert shall be carried out The construction pertaining to the pipe carrying culvert including the laying of pipe sleepers anchored with standard dowels, covers, fixing steps etc. shall be carried out according to the drawings and the approved procedures using pre cast RCC units / membersIn addition, one access boxout on both ends shall be provided to design detailsThe diverted services shall be reinstatedInspections shall be conducted to the requirementBackfilling up to the road formation shall be carried out according to specificationsThe broken asphalt portion shall be made good using new asphaltThe traffic management scheme shall be removed after the road crossing is cleared of all debris and obstructions.75 mm dia Holes in the pre cast units meant for lifting be filled in with concreteAccess box out shall be closed with concrete after the pipe are laid Either side of the road shall be provided with cable markers to indicate the services8 mm galvanised removable chequer plate covers with 2 lifting handles shall be provided to design details. Other chequer plates shall be provided to the design details

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 336: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

336 of

Major EquipmentExcavator, Dumper trucks, Compactors. Jack Hammer, Compressor, Asphalt finisher, Road RollersAttachmentSketch showing the traffic management scheme #131

2 #s road crossingsFor laying1 for 20” raw ethane1 for 8” natural gas1 for 6” propane&1 for 14”desalinated water1for 8” potable waterAvenue -dTopIndexScopeSafetyMethod including traffic management schemeEquipmentAttachmentScopeThe statement is aimed to propose the procedures to be adopted to carry out the excavation at the road crossings to construct culverts to facilitate to lay the pipe lines 1 # each 20” Raw Ethane, 6” Propane & 8”Natural Gas1# each 14” Desalinated Water and 8” Potable waterat locations identified on the attached drawing pertaining to Avenue -D SafetyPrior to the commencement of any activity, the labour force shall receive a STARRT card / Toolbox talk. Any process involving a particular safety risk shall be assessed and adopted measures addressed to raise to a minimum standard In this case, the excavation has to be carried out on the Operating Authority area, therefore, all the regulated precautions shall be strictly adhered to have ‘ full safety standard’ effect.

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 337: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

337 of

Safety Supervision A competent inspector shall visit the area daily to assess the safety measures adopted. Any snag observed during his visit shall be notified to the supervisor present who immediately act to bring the safety measures to an acceptable standard In case of incident where utilities not identified are discovered or damaged, all work shall stop in the area and the Operator Shift Controller and HSE department immediately notifiedPhone number : Shift Controller Emergency Number HSE Direct number Employees working in easement area shall have a daily pre-task briefing that includes;Reporting of incidentsMethods of work and tools to be usedPotential hazards found in the Easement areasThe approved work method statementEPC Contractor and Civil Contractor HSE department shall participate in presenting the STARRT card briefing and monitor the activities to ensure that the work methods are being followed and all personnel have an understanding of the hazards associated with working adjacent to live process areasExcavation Work Permit- A copy of the work permit shall be posted on a mini board installed on site to be noticeable to all persons involved with the crossingBarricades, cones, markers, the night-lights, and floodlights etc. shall be installed as required for a complete safety. No oil spillage shall be allowed. Flagman-On all directions, in addition to the traffic sign boards, flagmen shall be engaged full time to direct the traffic about the ‘excavation work in progress’ by ‘flag signal’ Hand Excavation- Excavation to expose the services if any, shall be carried out manually. In case certain services not shown on the record drawings such as fibre optics but it is discovered, further excavation shall be ceased until a decision is taken for the method to be adopted for further excavationAccess to trench- the workers shall clearly be instructed to use only the ladders to enter in or come out of the trench. No jumping shall be allowedMachine ExcavationThe operators / drivers shall be explicitly instructed to abide by the requirement of the reverse signal and sound when operating reverse. Banksman shall be engaged equipment operation. No violation of the traffic rules shall be allowedPre cast membersSince pre cast culvert units, covers and sleepers are heavy in load, proper care has to be exercised during raising and downing (handling) to the exact locations strictly adhering to the relevant safety measuresMethodThe required permit to work shall be obtained from the Plant Refinery Division.The record drawings regarding the existing services shall be obtained.A traffic management scheme shall be produced on site as detailed on the attached sketch Drawing reference –Piping Interconnections Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 338: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

338 of

Avenue D , Culvert ProceduresTraffic management scheme shall be implemented effectivelyBoth the crossings shall be excavated in one instance togetherThe asphalt pertaining to the crossing portion shall be removed Hand excavation shall be carried out to expose the cables & the other services if any, employing seaming the area with detectors to detect the existence of cables After the exposure, all the cables shall be covered with split PVC pipe and well supported temporarily to continue the excavation mechanically Remaining portion of the trench shall be excavated by machine to the defined levelsPreparation of the trench to construct RCC culvert shall be carried out The construction pertaining to the pipe carrying culvert including the laying of pipe sleepers anchored with standard dowels, covers, fixing steps etc. shall be carried out according to the drawings and the approved procedures using pre cast RCC units / membersIn addition, one access boxout on both ends shall be provided to design detailsThe diverted services shall be reinstatedInspections shall be conducted to the requirementBackfilling up to the road formation shall be carried out according to specificationsThe broken asphalt portion shall be made good using new asphaltThe traffic management scheme shall be removed after the road crossing is cleared of all debris and obstructions.75 mm dia Holes in the pre cast units meant for lifting be filled in with concreteAccess box out shall be closed with concrete after the pipe are laid Either side of the road shall be provided with cable markers to indicate the services8 mm-galvanised removable chequer plate covers with 2 lifting handles shall be provided to design details. Other chequer plates shall be provided to the design detailsMajor EquipmentExcavator, Dumper trucks, Compactors. Jack Hammer, Compressor, Asphalt finisher, Road RollersAttachmentSketch showing the traffic management scheme #132

Treatment to moved expansion joints Sea water surge basin TopIndexScopeDefinitionsMaterialMethod Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 339: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

339 of

EquipmentAttachmentScopeThis statement is aimed to propose the procedures to be adopted to carry out the injection to the moved expansion joints in the roof and the base at Sea Water Surge Basin observed during water tightness test Reference documentsBS code 8007 SafetyPrior to commence any activity, the labour force shall receive a STARRT Card / Toolbox Talk relevant to the operation concerned on the project site safety requirements.Necessary measures shall be applied to any process involving a safety riskSafety Supervision A competent inspector shall visit the area daily to assess the safety measures adopted. Any snag observed during his visit shall be notified to the supervisor present who immediately act to bring the safety measures to an acceptable standard MaterialsMaster Building Technology, Concresive 1320Epoxy putty Concressive 2200Hypaton / Combiflex TapeColma CleanerApplicator- DicotechMethodRoof Expansion JointPreparationThe joint shall be plugged with a rapid setting cement plug at top and soffit ApplicationWhen the cement is set, drilling shall be carried out and screw packers fixed to inject polyurethane in the jointConcresive 1320, a two component, low viscosity flexible polyurethane resin shall be injected into the prepared joint using an electric injection machine affecting the joint sealed after polyurethane curesNext day, cement plugs shall be removed from the top and sofit of the slab and the joint cleaned to a depth 100mm to get a uniform depthA suitable dia Backup rod shall be provided and the surface reprofiled using 2 part Polysulphide sealant “Arbokol AG2” and allow that to cureBase slab expansion JointThis joint shall be treated if the leakage is observed PreparationThe adjacent area of the joint shall be groind , cleaned and plugged by rapid setting mortarScrew packers shall be drilled and fixed for injection

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 340: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

340 of

ApplicationConcressive 1320 shall be injected into the prepared space using an electric injection machine so as to seal the joint permanently after the polyurethane resin comes in contact with waterThe cement plugs & the old sealant from the joint shall be removed the next daySides of the joint shall be ground using an angle grinder to remove any deleterious material to avoid debonding of the new sealantBackup rod shall be installed followed by priming the sides by “Arbo Primer”Joint shall be reprofiles using “Arbokol AG2” joint sealant and allowed to cureAdjacent area of the joint shall be ground to remove the coating from the surfaceAn Aluminium foil shall be provided on top of the joint sealant 1mm or 2 mm thick “Hypaton Tape / Combiflex Tape” 200 mm wide shall be fixed using “Concressive 2200” (a 2 parts epoxy putty) after activating the tape with “Colma Cleaner”The top surface of the tpe shall be closed with the putty leaving a neat band of 50 mm joint in between The system shall be allowed to cure for 3 days prior to the basin is put to useMajor EquipmentHigh pressure electric Injection systemMetallic PackersAttachmentMBT Method StatementMaterial Datasheet#133

Testing of fresh concrete on siteTopIndexScopeReference documentsDefinitionsResponsibilitiesSafetyMethodEquipmentAttachment

ScopeThe purpose of this method statement, is to define the procedure that shall be adopted for the on site testing of fresh concrete delivered from the Batch plant.Reference documentsProject Specification

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 341: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

341 of

Project Specification DefinitionsEPC ContractorCivil Contractor PSM Project Site Manager.ResponsibilitiesThe Construction Superintendent shall ensure that the laboratory technician is aware of the concrete program. The laboratory technician shall ensure that he implements this procedure.SafetyThe Safety Officer shall monitor the concrete activities, advising and implementing all safety procedures.MethodThe Site Laboratory shall be informed of the concreting program.Each delivery of concrete to the site, shall report to the concrete Foreman.The concrete Foreman shall assist the laboratory technician is testing the fresh concrete delivery.The delivery ticket shall first be checked for the correct grade and type of concrete.The truck mixer shall discharge his delivery into the concrete pump.Upon commencement of a pour, the concrete pump operator shall flush his line with the fresh concrete. The initial discharge from the concrete pump line shall be discarded.A sample of concrete circulated through the concrete pump, shall be taken from the end of the concrete pump line. The pumping operation shall then cease until the laboratory technician has completed his testing.The temperature of the concrete sample shall be determined according to ASTM C1064.A slump of the concrete sample shall be conducted according to ASTM C143.These details shall be recorded upon the test record format QC.Once these test results have been established as conforming to the specification requirements, the pumping operation can proceed.Subsequent deliveries of fresh concrete shall follow a similar procedure. The exemption being that the initial discharge of the subsequent truck mixers shall not be discarded.The laboratory technician shall take concrete samples from random truck mixers, for the purpose of concrete test cubes. The frequency of these concrete test cubes shall be three cubes per 100 cubic meters of delivered concrete. Additional concrete cubes shall be taken as directed by the laboratory manager, for conducting further tests upon hardened cubes as defined within the specifications.EquipmentTruck Mixer.Concrete Pump.Slump Cone.Thermometer.Cube molds.AttachmentITP No: Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 342: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

342 of

#134

Road crossingTo install culvert for1# 14” desalinated waterCorniche road / road cAt gup gate nothTopIndexScopeSafetyMethod including traffic management schemeEquipmentAttachmentScopeThe statement is aimed to propose the procedures to be adopted to carry out the excavation and installation of 1 # pre cast culvert at the road crossing as shown on the attached sketch SafetyPrior to the commencement of any activity the labour force shall receive a / STARRT card / Toolbox talk. Any process involving a particular safety risk shall be assessed and adopted measures addressed to raise to a minimum standard In this case the excavation has to be carried out on the Operating Authority area, therefore all the regulated precautions shall be strictly adhered to effect ‘ full safety standard’.Safety Supervision A competent inspector shall visit the area daily to assess the safety measures adopted. Any snag observed during his visit shall be notified to the supervisor present who immediately act to bring the safety measures to an acceptable standard In case of incident where utilities not identified are discovered or damaged, all work shall stop in the area and the Operator Shift Controller and HSE department immediately notifiedPhone number : Shift Controller Emergency Number HSE Direct number Employees working in easement area shall have a daily pre-task briefing that includes;Reporting of incidentsMethods of work and tools to be usedPotential hazards found in the Easement areasThe approved work method statementEPC Contractor and Civil Contractor HSE department shall participate in presenting the STARRT card briefing and monitor the activities to ensure that the work methods are being Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 343: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

343 of

followed and all personnel have an understanding of the hazards associated with working adjacent to live process areasExcavation Work Permit- A copy of the work permit shall be posted on a mini board installed on site to be noticeable to all persons involved with the crossingBarricades, cones, markers, the night-lights, and floodlights etc. shall be installed as required for a complete safety. No oil spillage shall be allowed. Flagman-On both directions, in addition to the traffic sign boards, a flagmen shall be engaged full time to direct the traffic about the ‘excavation work in progress’ by ‘flag signal’ Hand Excavation- Excavation to expose the services shall be carried out manually.In case certain services not shown on the record drawings such as fibre optics but it is discovered, further excavation shall be ceased until a decision is taken for the method to be adopted for further excavationAccess to trench- The workers shall clearly be instructed to use only the ladders to enter in or come out of the trench. No jumping shall be allowedMachine ExcavationThe operators / drivers shall be explicitly instructed to abide by the requirement of the reverse signal and sound when operating reverse. Banksman shall be engaged equipment operation. No violation of the traffic rules shall be allowedPre cast membersSince pre cast culvert units, covers and sleepers are heavy in load, proper care has to be exercised during raising and downing (handling) to the exact locations strictly adhering to the relevant safety measuresMethodThe required permit to work shall be obtained from the Plant Refinery Division.The record drawings regarding the existing services shall be obtained.A traffic management scheme shall be produced on site as detailed on the attached sketch Drawing reference –Piping Interconnections Corniche Road Culvert Existing Services On East End of the crossing exist banks of electrical cables & also exist some utility pipes.On West End exist certain servicesAn electric pole exists on the West of the gate but out of culvert reachOn the South adjacent to road exists sea water pipe in the trenchProceduresBackfilling shall be carried out to the existing excavated sea water trench on south of the Corniche road crossing up to the natural ground level to provide effective traffic access to the working area from the road carriageway according to the traffic management scheme attachedTraffic management scheme shall be implemented effectively subject to RRD approvalHand excavation shall be carried out to expose the cables & the other services employing seaming the area with detectors to detect the existence of cables After the exposure, all the cables shall be covered with split PVC pipe and well supported temporarily to continue the excavation mechanically Remaining portion of the trench shall be excavated by machine to the defined levelsPreparation of the trench to construct RCC culvert shall be carried out Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 344: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

344 of

The construction pertaining to the pipe carrying culvert including the laying of pipe sleepers anchored with standard dowels, covers, fixing steps etc. shall be carried out according to the drawings and the approved procedures using pre cast RCC units / membersIn addition, one access boxout on both ends shall be provided to design detailsThe diverted services shall be reinstatedInspections shall be conducted to the requirementBackfilling up to the road formation shall be carried out according to specificationsThe broken asphalt portion shall be made good using new asphaltThe traffic management scheme shall be removed after the road crossing is cleared of all debris and obstructions.75 mm dia Holes in the pre cast units meant for lifting be filled in with concreteAccess box out shall be closed with concrete after the pipe are laid Either side of the road shall be provided with cable markers to indicate the services8 mm-galvanised removable chequer plate covers with 2 lifting handles shall be provided to design details. Other chequer plates shall be provided to the design detailsMajor EquipmentExcavator, Dumper trucks, Compactors. Jack Hammer, Compressor, Asphalt finisher, Road RollersAttachmentSketch showing the traffic management scheme #135

Road crossingTo install culvertFor1 # 14” desalinated waterAvenue ‘c’ road gup gate eastMain entranceTopIndexScopeSafetyMethod including traffic management schemeEquipmentAttachmentScopeThe statement is aimed to propose the procedures to be adopted to carry out the excavation and installation of 1 # pre cast culvert at the road crossing as shown on the attached sketch Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 345: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

345 of

SafetyPrior to the commencement of any activity the labour force shall receive a / STARRT card / Toolbox talk. Any process involving a particular safety risk shall be assessed and adopted measures addressed to raise to a minimum standard In this case the excavation has to be carried out on the Operating Authority area, therefore all the regulated precautions shall be strictly adhered to effect ‘ full safety standard’.Safety Supervision A competent inspector shall visit the area daily to assess the safety measures adopted. Any snag observed during his visit shall be notified to the supervisor present who immediately act to bring the safety measures to an acceptable standard In case of incident where utilities not identified are discovered or damaged, all work shall stop in the area and the Shift Controller and HSE department immediately notifiedPhone number : Shift Controller Emergency Number HSE Direct number Employees working in easement area shall have a daily pre-task briefing that includes;Reporting of incidentsMethods of work and tools to be usedPotential hazards found in the Easement areasThe approved work method statementEPC Contractor and Civil Contractor HSE department shall participate in presenting the STARRT card briefing and monitor the activities to ensure that the work methods are being followed and all personnel have an understanding of the hazards associated with working adjacent to live process areasExcavation Work Permit- A copy of the work permit shall be posted on a mini board installed on site to be noticeable to all persons involved with the crossingBarricades, cones, markers, the night-lights, and floodlights etc. shall be installed as required for a complete safety. No oil spillage shall be allowed. Flagman-On both directions, in addition to the traffic sign boards, a flagmen shall be engaged full time to direct the traffic about the ‘excavation work in progress’ by ‘flag signal’ Hand Excavation- Excavation to expose the services shall be carried out manually.In case certain services not shown on the record drawings such as fibre optics but it is discovered, further excavation shall be ceased until a decision is taken for the method to be adopted for further excavationAccess to trench- The workers shall clearly be instructed to use only the ladders to enter in or come out of the trench. No jumping shall be allowedMachine ExcavationThe operators / drivers shall be explicitly instructed to abide by the requirement of the reverse signal and sound when operating reverse. Banksman shall be engaged equipment operation. No violation of the traffic rules shall be allowedPre cast members

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 346: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

346 of

Since pre cast culvert units, covers and sleepers are heavy in load, proper care has to be exercised during raising and downing (handling) to the exact locations strictly adhering to the relevant safety measuresMethodThe required permit to work shall be obtained from the Plant Refinery Division.The record drawings regarding the existing services shall be obtained.A traffic management scheme shall be produced on site as detailed on the attached sketch Drawing reference –Piping Interconnections Avenue C Culvert Existing Services On North and South end of the crossing exist many electrical cables, minor irrigation cables & also exist some utility pipes. Two trees on either end shall be effected and need preservationOn the side terrace a small portion of interlocking block paviors shall be effectedProceduresTraffic management scheme shall be implemented effectively subject to RRD approvalTrees under effect shall be removed and preservedThe crossing shall be carried out in two instancesInstance 1 Hand excavation shall be carried out to expose the cables & the other services employing seaming the area with detectors to detect the existence of cables After the exposure, all the cables shall be covered with split PVC pipe and well supported temporarily to continue the excavation mechanically Remaining portion of the trench shall be excavated by machine to the defined levelsPreparation of the trench to construct RCC culvert shall be carried out The construction pertaining to the pipe carrying culvert including the laying of pipe sleepers anchored with standard dowels, covers, fixing steps etc. shall be carried out according to the drawings and the approved procedures using pre cast RCC units / membersIn addition, one access boxout on both ends shall be provided to design detailsThe diverted services shall be reinstatedInspections shall be conducted to the requirementBackfilling up to the road formation shall be carried out according to specificationsThe broken asphalt portion shall be made good using new asphaltThe traffic management scheme shall be removed after the road crossing is cleared of all debris and obstructions.75 mm dia Holes in the pre cast units meant for lifting be filled in with concreteAccess box out shall be closed with concrete after the pipe are laidRemoved trees shall be replantedInstance 2 All the activities shall be repeated for this instanceEither side of the road shall be provided with cable markers to indicate the services8 mm-galvanised removable chequer plate covers with 2 lifting handles shall be provided to design details. Other chequer plates shall be provided to the design details

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 347: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

347 of

Major EquipmentExcavator, Dumper trucks, Compactors. Jack Hammer, Compressor, Asphalt finisher, Road RollersAttachmentSketch showing the traffic management scheme

#136ROAD CROSSINGTO INSTALL CULVERTFOR

1 # 14” desalinated waterAvenue ‘c’ road gup gate eastMain entranceTopIndexScopeSafetyMethod including traffic management schemeEquipmentAttachmentScopeThe statement is aimed to propose the procedures to be adopted to carry out the excavation and installation of 1 # pre cast culvert at the road crossing as shown on the attached sketch SafetyPrior to the commencement of any activity the labour force shall receive a / STARRT card / Toolbox talk. Any process involving a particular safety risk shall be assessed and adopted measures addressed to raise to a minimum standard In this case the excavation has to be carried out on the Operating Authority area, therefore all the regulated precautions shall be strictly adhered to effect ‘ full safety standard’.Safety Supervision A competent inspector shall visit the area daily to assess the safety measures adopted. Any snag observed during his visit shall be notified to the supervisor present who immediately act to bring the safety measures to an acceptable standard In case of incident where utilities not identified are discovered or damaged, all work shall stop in the area and the Operator Shift Controller and HSE department immediately notifiedPhone number : Shift Controller Emergency Number HSE Direct number Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 348: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

348 of

Employees working in easement area shall have a daily pre-task briefing that includes;Reporting of incidentsMethods of work and tools to be usedPotential hazards found in the Easement areasThe approved work method statementEPC Contractor and Civil Contractor HSE department shall participate in presenting the STARRT card briefing and monitor the activities to ensure that the work methods are being followed and all personnel have an understanding of the hazards associated with working adjacent to live process areasExcavation Work Permit- A copy of the work permit shall be posted on a mini board installed on site to be noticeable to all persons involved with the crossingBarricades, cones, markers, the night-lights, and floodlights etc. shall be installed as required for a complete safety. No oil spillage shall be allowed. Hand Excavation- Excavation to expose the services shall be carried out manually.In case certain services not shown on the record drawings such as fibre optics but it is discovered, further excavation shall be ceased until a decision is taken for the method to be adopted for further excavationAccess to trench- The workers shall clearly be instructed to use only the ladders whether to enter in or come out of the trench. No jumping shall be allowedMachine ExcavationThe operators / drivers shall be explicitly instructed to abide by the requirement of the reverse signal and sound when operating reverse. Banksman shall be engaged equipment operation. No violation of the traffic rules shall be allowedPre cast membersSince pre cast culvert units, covers and sleepers are heavy in load, proper care has to be exercised during raising and installing / downing (handling) to the exact locations strictly adhering to the relevant safety measuresMethodThe required permit to work shall be obtained from the Plant Refinery Division.The record drawings regarding the existing services shall be obtained.A traffic management scheme shall be produced on site as detailed on the attached sketch Drawing reference –Piping Interconnections Avenue C Culvert Existing Services On North and South end of the crossing exist many electrical cables, minor irrigation cables & also exist some utility pipes. Two trees on either end shall be effected and need preservationOn the side terrace a small portion of interlocking block paviors shall be effectedProceduresTraffic management scheme shall be implemented effectively subject to RRD approvalTrees under effect shall be removed and preservedThe crossing shall be carried out in one instanceHand excavation shall be carried out to expose the cables & the other services employing seaming the area with detectors to detect the existence of cables Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 349: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

349 of

After the exposure, all the cables shall be covered with split PVC pipe and well supported temporarily to continue the excavation mechanically Remaining portion of the trench shall be excavated by machine to the defined levelsPreparation of the trench to construct RCC culvert shall be carried out The construction pertaining to the pipe carrying culvert including the laying of pipe sleepers anchored with standard dowels, covers, fixing steps etc. shall be carried out according to the drawings and the approved procedures using pre cast RCC units / membersIn addition, one access boxout on both ends shall be provided to design detailsThe diverted services shall be reinstatedInspections shall be conducted to the requirementBackfilling up to the road formation shall be carried out according to specificationsThe broken asphalt portion shall be made good using new asphaltThe traffic management scheme shall be removed after the road crossing is cleared of all debris and obstructions.75 mm dia Holes in the pre cast units meant for lifting shall be filled in with concreteAccess box out shall be closed with concrete after the pipes are laidRemoved / Preserved trees shall be replantedEither side of the road shall be provided with cable markers to indicate the services8 mm-galvanised removable chequer plate covers with 2 lifting handles shall be provided to design details. Other chequer plates shall be provided to the design detailsMajor EquipmentExcavator, Dumper trucks, Compactors. Jack Hammer, Compressor, Asphalt finisher, Road RollersAttachmentSketch showing the traffic management scheme #137

Road crossingTo install culvertFor1 # 14” desalinated waterAvenue ‘c’ road gup gate eastMain entranceTopIndexScopeSafetyMethod including traffic management schemeEquipmentStatements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 350: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

350 of

AttachmentScopeThe statement is aimed to propose the procedures to be adopted to carry out the excavation and installation of 1 # pre cast culvert at the road crossing as shown on the attached sketch SafetyPrior to the commencement of any activity the labour force shall receive a / STARRT card / Toolbox talk. Any process involving a particular safety risk shall be assessed and adopted measures addressed to raise to a minimum standard In this case the excavation has to be carried out on the Operating Authority area, therefore all the regulated precautions shall be strictly adhered to effect ‘ full safety standard’.Safety Supervision A competent inspector shall visit the area daily to assess the safety measures adopted. Any snag observed during his visit shall be notified to the supervisor present who immediately act to bring the safety measures to an acceptable standard In case of incident where utilities not identified are discovered or damaged, all work shall stop in the area and the Operator Shift Controller and HSE department immediately notifiedPhone number : Shift Controller Emergency Number HSE Direct number Employees working in easement area shall have a daily pre-task briefing that includes;Reporting of incidentsMethods of work and tools to be usedPotential hazards found in the Easement areasThe approved work method statementEPC Contractor and Civil Contractor HSE department shall participate in presenting the STARRT card briefing and monitor the activities to ensure that the work methods are being followed and all personnel have an understanding of the hazards associated with working adjacent to live process areasExcavation Work Permit- A copy of the work permit shall be posted on a mini board installed on site to be noticeable to all persons involved with the crossingBarricades, cones, markers, the night-lights, and floodlights etc. shall be installed as required for a complete safety. No oil spillage shall be allowed. Hand Excavation- Excavation to expose the services shall be carried out manually.In case certain services not shown on the record drawings such as fibre optics but it is discovered, further excavation shall be ceased until a decision is taken for the method to be adopted for further excavationAccess to trench- The workers shall clearly be instructed to use only the ladders whether to enter in or come out of the trench. No jumping shall be allowedMachine ExcavationThe operators / drivers shall be explicitly instructed to abide by the requirement of the reverse signal and sound when operating reverse. Banksman shall be engaged equipment operation. No violation of the traffic rules shall be allowed

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 351: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

351 of

Pre cast membersSince pre cast culvert units, covers and sleepers are heavy in load, proper care has to be exercised during raising and installing / downing (handling) to the exact locations strictly adhering to the relevant safety measuresMethodThe required permit to work shall be obtained from the Plant Refinery Division.The record drawings regarding the existing services shall be obtained.A traffic management scheme shall be produced on site as detailed on the attached sketch Drawing reference –Piping Interconnections Avenue C Culvert Existing Services On North and South end of the crossing exist many electrical cables, minor irrigation cables & also exist some utility pipes. Two trees on either end shall be effected and need preservationOn the side terrace a small portion of interlocking block paviors shall be effectedProceduresThe entrance road shall be closed to all traffic. The traffic shall be diverted to use the North gateTrees under effect shall be removed and preservedThe crossing shall be carried out in one instanceHand excavation shall be carried out to expose the cables & the other services employing seaming the area with detectors to detect the existence of cables After the exposure, all the cables shall be covered with split PVC pipe and well supported temporarily to continue the excavation mechanically Remaining portion of the trench shall be excavated by machine to the defined levelsPreparation of the trench to construct RCC culvert shall be carried out The construction pertaining to the pipe carrying culvert including the laying of pipe sleepers anchored with standard dowels, covers, fixing steps etc. shall be carried out according to the drawings and the approved procedures using pre cast RCC units / members75 mm dia Holes in the pre cast units meant for lifting shall be filled in with concreteIn addition, one access boxout on both ends shall be provided to design detailsThe diverted services shall be reinstatedInspections shall be conducted to the requirementBackfilling up to the road formation shall be carried out according to specificationsThe broken asphalt portion shall be made good using new asphaltThe traffic diversion shall be removed after the road crossing is cleared of all debris and obstructions.Access box out shall be closed with concrete after the pipes are laidRemoved / Preserved trees shall be replanted & all landscaping reinstated to RRD / GUP satisfaction8 mm-galvanised removable chequer plate covers with 2 lifting handles shall be provided to design details. Other chequer plates shall be provided to the design details

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 352: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

352 of

Major EquipmentExcavator, Dumper trucks, Compactors. Jack Hammer, Compressor, Asphalt finisher, Road RollersAttachmentSketch showing the traffic diversion #138

Replacement of misaligned anchor bolts in Foundation 55-vv-906Using renderoc lax traTopIndexScopeReference documentsSafetyMethodEquipmentScopeThis statement is aimed to propose the procedures to be adopted to carry out the replacement to the foundation damaged anchor bolts. Reference DocumentsMethod Statement 36 approved for concrete repairs Item F (Renderoc Lax Tra FOSROC)SafetyPrior to commencement of any activity, the labour force shall receive a STARRTCard / Toolbox Talk relevant to the operation concerned on the project site safety requirements. Necessary measures shall be applied to any process involving a safety riskSafety Supervision A competent inspector shall visit the area daily to assess the safety measures adopted. Any snag observed during his visit shall be notified to the supervisor present who immediately act to bring the safety measures to an acceptable standard Method3 # Anchor bolts installed for this foundation were damaged post pouringThe following operations are invloved to reinstate the bolts into the foundationThe effected concrete portion shall be removed in a triangular form from the foundation corners in an approximate prismatic shape of base 250mmx200mm and height of the prism 600mm approximately.During breaking the concrete, care shall be taken to not to damage the rebars.The exposed rebars shall be properly cleaned using hard brush so that no loose particles remain intact to the rebar surface

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 353: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

353 of

The surface of the broken concrete shall be cleared of all debris and new bolts installed in correct locationsForms shall be erected to the correct profile, alignment , properly leveled and plumbed. Chamfer shall be aligned properly. The form and the concrete surface shall be properly sealed using silicon seal to avoid any leakage of the material Civil Contractor QC inspection shall be conducted to ascertain the correct alignment of the anchor bolts and the formsThen the prepared surface shall be soaked in water for 24 hours prior to grouting The material shall be mixed with specified quantity of clean water according to the manufacturer’s instruction and poured in layers 200 mm thickCivil Contractor QC inspection shall be conducted throughout the pouring operation After the approval of the repair works and giving allowance of specified number of days, further operations shall be carried outMajor EquipmentPeddle MixerAttachmentNone #139Replacement of misaligned anchor bolts in Foundation 55-vv-906Using renderoc lax traTopIndexScopeReference documentsSafetyMethodEquipmentScopeThis statement is aimed to propose the procedures to be adopted to carry out the replacement to the foundation damaged anchor bolts. Reference DocumentsMethod Statement 36 approved for concrete repairs Item F (Renderoc Lax Tra FOSROC)SafetyPrior to commencement of any activity, the labour force shall receive a STARRTCard / Toolbox Talk relevant to the operation concerned on the project site safety requirements. Necessary measures shall be applied to any process involving a safety risk

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 354: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

354 of

Safety Supervision A competent inspector shall visit the area daily to assess the safety measures adopted. Any snag observed during his visit shall be notified to the supervisor present who immediately act to bring the safety measures to an acceptable standard Method3 # Anchor bolts installed for this foundation were damaged post pouringThe following operations are invloved to reinstate the bolts into the foundationThe effected concrete portion shall be removed in a triangular form from the foundation corners in an approximate prismatic shape of base 250mmx200mm and height of the prism 600mm approximately.During breaking the concrete, care shall be taken to not to damage the rebars.The exposed rebars shall be properly cleaned using hard brush so that no loose particles remain intact to the rebar surfaceThe surface of the broken concrete shall be cleared of all debris and new bolts installed in correct locationsForms shall be erected to the correct profile, alignment , properly leveled and plumbed. Chamfer shall be aligned properly. The form and the concrete surface shall be properly sealed using silicon seal to avoid any leakage of the material Civil Contractor QC inspection shall be conducted to ascertain the correct alignment of the anchor bolts and the formsThen the prepared surface shall be soaked in water for 24 hours prior to grouting The material shall be mixed with specified quantity of clean water according to the manufacturer’s instruction and poured in layers 200 mm thickCivil Contractor QC inspection shall be conducted throughout the pouring operation After the approval of the repair works and giving allowance of specified number of days, further operations shall be carried outMajor EquipmentPeddle MixerAttachmentNone#140

Buildings screeds for vinyl and epoxy floor finishesTopIndexScopeSafetyMaterialMethod EquipmentStatements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 355: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

355 of

AttachmentScopeThis statement is aimed to propose the procedures to be adopted to lay the floor screed For the vinyl tile and the epoxy floor finishesReference documentsNoneSafetyPrior to commencement of any activity, the labour force shall receive a STARRTCard / Toolbox Talk relevant to the operation concerned on the project site safety requirements. Necessary measures shall be applied to any process involving a safety riskSafety Supervision A competent inspector shall visit the area daily to assess the safety measures adopted. Any snag observed during his visit shall be notified to the supervisor present who immediately act to bring the safety measures to an acceptable standard MaterialsCement, washed sand, screened sand, bonding agent, waterMethod (Laying floor screed by SEMI DRY method)The floor area to be laid with screed shall be divided in equal or as considered convenient strips / bays, not more than1500mm wide so that alternatively screed could be laid in.The concrete surface shall be cleared of all loose particles and cleaned using hard wire brush to ensure enough roughness on the concrete surfaceThe levels up to which the floor screed is to be laid, shall be profiled by using Mechanical levelling points with steel pipes to maintain levels so that complete compartment is given a proper level The cleaned area shall be soaked with water 24 hours prior to the application of screed. Civil Contractor QC inspection shall be conducted for the examination pertaining to the preparatory works for the ready to pour compartmentsApplication After the preparation for the alternate bays or strips of 1500 mm width or as sized on site is ready with all levels, cleaned, duly soaked in water for 24 hours and ready for pouring, the prepared surface shall be spread with cement slurry ratio 1:1 (1 part cement and 1 part sand) mixed with mix quality waterThe mortar for screed shall be mixed semi dry by a mechanical mixer with only sufficient water added to give a crumbly consistency which retains its shape when squeezed by hand permitting no fluidityOne layer application with 1:2.5 cement –screened sand mortarThe mix shall be placed to a thickness approximately 10 mm greater than that actually required, thoroughly compacted by tamping and drawing off to the required level with a screed board.

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 356: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

356 of

After compacting the layer of mortar, the compacted surface shall be finished by a steel float to achieve a smooth surface ready to receive the vinyl tiles or the epoxy painting floor finishes and then covered with polythene membrane for immediate curingThe finished surface shall be permanently cured by adding water soaked hessian after a few hours of finishing and recovered with polythene. The surface shall be kept wet for a period of 3 days and then protected till the floor finishes are laid over the surfaceThroughout the above operations Civil Contractor QC visual inspection shall be conductedMajor EquipmentMechanical MixerWheel barrowsMason’s tools in generalAttachmentNone#141

Buildings Screeds for vinyl and epoxy Floor finishes Top IndexScopeSafetyMaterialMethod EquipmentAttachmentScopeThis statement is aimed to propose the procedures to be adopted to lay the floor screed For the vinyl tile and the epoxy floor finishesReference documentsNoneSafetyPrior to commencement of any activity, the labour force shall receive a STARRTCard / Toolbox Talk relevant to the operation concerned on the project site safety requirements. Necessary measures shall be applied to any process involving a safety risk

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 357: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

357 of

Safety Supervision A competent inspector shall visit the area daily to assess the safety measures adopted. Any snag observed during his visit shall be notified to the supervisor present who immediately act to bring the safety measures to an acceptable standard MaterialsCement, washed sand, screened sand, bonding agent, waterMethod (Laying floor screed by SEMI DRY method)The floor area to be laid with screed shall be divided in equal or as considered convenient strips / bays, not more than1500mm wide so that alternatively screed could be laid in.The concrete surface shall be cleared of all loose particles and cleaned using hard wire brush to ensure enough roughness on the concrete surfaceThe levels up to which the floor screed is to be laid, shall be profiled by using Mechanical levelling points with steel pipes to maintain levels so that complete compartment is given a proper level The cleaned area shall be soaked with water 24 hours prior to the application of screed. Civil Contractor QC inspection shall be conducted for the examination pertaining to the preparatory works for the ready to pour compartmentsApplication After the preparation for the alternate bays or strips of 1500 mm width or as sized on site is ready with all levels, cleaned, duly soaked in water for 24 hours and ready for pouring, the prepared surface shall be spread with cement slurry ratio 1:1 (1 part cement and 1 part sand) mixed with mix quality waterThe mortar for screed shall be mixed semi dry by a mechanical mixer with only sufficient water added to give a crumbly consistency which retains its shape when squeezed by hand permitting no fluidityOne layer application with 1:2.5 cement –screened sand mortarThe mix shall be placed to a thickness approximately 10 mm greater than that actually required, thoroughly compacted by tamping and drawing off to the required level with a screed board. After compacting the layer of mortar, the compacted surface shall be finished by a steel float to achieve a smooth surface ready to receive the vinyl tiles or the epoxy painting floor finishes and then covered with polythene membrane for immediate curingThe finished surface shall be permanently cured by adding water soaked hessian after a few hours of finishing and recovered with polythene. The surface shall be kept wet for a period of 3 days and then protected till the floor finishes are laid over the surfaceThroughout the above operations Civil Contractor QC visual inspection shall be conductedMajor EquipmentMechanical MixerWheel barrowsMason’s tools in generalAttachmentStatements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 358: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

358 of

None

#142Buildings

Screeds for vinyl and epoxy Floor finishesTopIndexScopeSafetyMaterialMethod EquipmentAttachmentScopeThis statement is aimed to propose the procedures to be adopted to lay the floor screed For the vinyl tile and the epoxy floor finishesReference documentsNoneSafetyPrior to commencement of any activity, the labour force shall receive a STARRTCard / Toolbox Talk relevant to the operation concerned on the project site safety requirements. Necessary measures shall be applied to any process involving a safety riskSafety Supervision A competent inspector shall visit the area daily to assess the safety measures adopted. Any snag observed during his visit shall be notified to the supervisor present who immediately act to bring the safety measures to an acceptable standard MaterialsCement, washed sand, screened sand, bonding agent, waterMethod (Laying floor screed by SEMI DRY method)The floor area to be laid with screed shall be divided in equal or as considered practicable strips / bays, not more than1500mm wide (may be wider if convenient), so that alternatively screed could be laid in.Scabbling of the concrete surface shall be carried out if so required The concrete surface shall be cleared of all loose particles and cleaned using hard wire brush to ensure sufficient roughness to receive the screedThe levels up to which the floor screed is to be laid, shall be profiled by using Mechanical levelling points with steel pipes to maintain levels so that complete compartment is given a proper level The cleaned area shall be soaked with water 24 hours prior to the application of screed.

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 359: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

359 of

Civil Contractor QC inspection shall be conducted for the examination pertaining to the preparatory works for the ‘ready to pour’ compartmentsApplication After the preparation for the alternate bays or strips of 1500 mm width or as sized on site is ready with all levels, cleaned, duly soaked in water for 24 hours and ready for pouring, the pourable surface shall be spread with cement slurry ratio 1:1 (1 part cement and 1 part sand) mixed with mix quality waterThe mortar for screed shall be mixed semi dry by a mechanical mixer with only sufficient water added to give a crumbly consistency which retains its shape when squeezed by hand permitting no fluidityOne layer application with 1:2.5 cement –screened sand mortarThe mix shall be placed in one layer progressively to a thickness approximately 10 mm greater than that actually required, thoroughly compacted by tamping and drawn off to the marked level with a screed board. After compacting the layer of mortar, the compacted surface shall be finished by a steel float to achieve a smooth surface ready to receive the vinyl tiles or the epoxy painting floor finishes and then covered with polythene membrane for immediate curingThe finished surface shall be permanently cured by adding water soaked hessian after a few hours of finishing and recovered with polythene sheet. The surface shall be kept wet for a period of 3 days and then protected with hard boards spread over till the floor finishes are applied over the surfaceThroughout the above operations Civil Contractor QC visual inspection shall be conductedPrior to full-scale commencement of the screeding operation, a sample shall be produced on site in the presence of EPC Contractor representative so that an agreement pertaining to the stated procedures to carry out the screeding and about the Quality could reach Major EquipmentMechanical MixerWheel barrowsMason’s tools in generalAttachmentNone#143

Directional boring at 3# locations for 14”desalinated water pipe corniche road North of Operating AuthorityTopIndexScopeReference documentsStatements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 360: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

360 of

SafetyMethod EquipmentAttachmentScopeThe statement is aimed to propose the procedures to be adopted to carry out the directional boring under the existing culverts to facilitate to lay the sleeves for pipe lines 1 # 14” Desalinated Water at 3 # locations SafetyPrior to the commencement of any activity the labour force shall receive a / STARRT card / Toolbox talk. Any process involving a particular safety risk shall be assessed and adopted measures addressed to raise to a minimum standard In this case the excavation has to be carried out on the Operating Authority area, therefore all the regulated precautions shall be strictly adhered to effect a full safety standard.Excavation Work Permit- A copy of the work permit shall be posted on a mini board installed on site at the location shown on the sketch to be noticeable to all the persons involved A copy shall also be transmitted to EPC ContractorBarricades, cones, markers, the night-lights, and floodlights etc. shall be installed as required at the pits for a complete safety. MethodThe necessary permit to work shall be obtained from the Plant Refinery Division.The record drawings regarding the existing services shall be obtainedTrial pits shall be made manually on both ends of the proposed boring to ascertain the availability of the existing services and protect these from any damage and shall also be used for the bentonite trial at the receiving endCase 1 Existing 1 box culvert and a 14” dia pipe about 1 m from culvert A sleeve 5 m long of required material dia 20 “is to be laid beneath the box culvert (about 3m x 3m in section), 1 m below the base by directional boring so that 1 m projection remains on both sides of the culvert. The laying pertaining to the remaining portion of the pipes other than the sleeve shall be carried out by ordinary approved procedures by excavation to the required level, bedding, compaction and the filling above the portion over the pipe and tested accordingly Case 2Existing 1 box culvert and 1 pipe 1.5 m dia 2 m from the culvert and 1 pipe 1 m dia about 3.3 m below ground. 4 # existing services also have been exposed A sleeve 7.3 m long has to pass beneath the box culvert (about 3m x 3m in section) ,1 m below the base by directional boring so that 1 m projection remains on both sides of the culvert & the existing 1.5 m GRP pipe approximately 2.5 m below the existing ground. . The laying pertaining to the remaining portion of the pipes other than the sleeve shall be carried out by ordinary approved procedures by excavation to the required level, bedding, compaction and the filling above the portion over the pipe and tested accordingly after the pipes are laidStatements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 361: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

361 of

Case 3Existing 1 box culvert and 2 # 60” dia ABB Cooling water pipe laying at about 10 m from the culvert is in progress. Proposed 14 “ Desalinated water pipe has to cross over ABB pipes keeping 1 m apart verticallyA sleeve 5 m long has to pass beneath the box culvert (about 3m x 3m in section) below the base by directional boring so that 1 m projection remains on both sides of the culvert. The pipes shall then be raised over the existing 2 #s 6” dia ABB cooling water lines at about 2. 3 m from the existing ground level so that the top of the pipes is 1.2 m from the ground level. The laying pertaining to the remaining portion of the pipes other than the sleeve shall be carried out by ordinary approved procedures by excavation to the required level, bedding, compaction and the filling above the portion over the pipe and tested accordingly. The work for the portion to cross over ABB pipes shall be carried out after the ABB pipes are laid and backfilledOn site, sufficient excavated space is available to lower the sleeve in to pull into the boreThe excavated trench does not show any sign of water therefore, no de watering shall be carried outExcavation shall be carried out according to the requirementThe boring shall be carried out in stages. First stage-The sleeve is in the trench on one end and the reamer fully underground. Second stage-The sleeve is partly pulled in and the reamer partly withdrawnThird stage- The sleeve further pulled and the reamer withdrawn accordingly Fourth stage-Full portion of the sleeve is underground in the bore and the reamer outThe excavated trenches on both ends shall be backfilled by Civil Contractor according to the specification requirement and the required tests carried outThe reinstatement of the effected services shall be carried out after the directional boring is completedDirectional Boring – A non- excavation Method which does not allow collapsing of the ground surfaceM / S Ditch Witch shall carry out the Directional Boring employing Jet Trac Directional Boring equipment according to their approved method statement Refer to the attached sketches based on the Ditch Witch guidelines Bentonite is pure clay to be used as a fluid / slurry formed by mixing water. It shall be used to cool the drill bit and to lubricate the drill areaThe material displaced by the head / sleeves shall be discharged at the receiving end in the receiving pit and removed from the siteAll fully trained operators shall be used on the jobEquipmentJet Track Unit (complete package), Crane, CompactorAttachmentCross-Section Sketches showing 3 # cases

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 362: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

362 of

#144

Directional boring at 3# locations for 14”desalinated water pipe corniche road North of Operating AuthorityTopIndexScopeReference documentsSafetyMethod EquipmentAttachmentScopeThe statement is aimed to propose the procedures to be adopted to carry out the directional boring under the existing culverts to facilitate to lay the sleeves for pipe lines 1 # 14” Desalinated Water at 3 # locations SafetyPrior to the commencement of any activity the labour force shall receive a / STARRT card / Toolbox talk. Any process involving a particular safety risk shall be assessed and adopted measures addressed to raise to a minimum standard In this case the excavation has to be carried out on the Operating Authority area, therefore all the regulated precautions shall be strictly adhered to effect a full safety standard.Excavation Work Permit- A copy of the work permit shall be posted on a mini board installed on site at the location shown on the sketch to be noticeable to all the persons involved A copy shall also be transmitted to EPC ContractorBarricades, cones, markers, the night-lights, and floodlights etc. shall be installed as required at the pits for a complete safety. MethodThe necessary permit to work shall be obtained from the Plant Refinery Division.The record drawings regarding the existing services shall be obtainedTrial pits shall be made manually on both ends of the proposed boring to ascertain the availability of the existing services and protect these from any damage and shall also be used for the bentonite trial at the receiving endCase 1 Existing 1 box culvert and a 14” dia pipe about 1 m from culvert A sleeve 5 m long of required material dia 20 “is to be laid beneath the box culvert (about 3m x 3m in section), 1 m below the base by directional boring so that 1 m projection remains on both sides of the culvert. The laying pertaining to the remaining portion of the pipes other than the Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 363: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

363 of

sleeve shall be carried out by ordinary approved procedures by excavation to the required level, bedding, compaction and the filling above the portion over the pipe and tested accordingly Case 2Existing 1 box culvert and 1 pipe 1.5 m dia 2 m from the culvert and 1 pipe 1 m dia about 3.3 m below ground. 4 # existing services also have been exposed A sleeve 7.3 m long has to pass beneath the box culvert (about 3m x 3m in section) ,1 m below the base by directional boring so that 1 m projection remains on both sides of the culvert & the existing 1.5 m GRP pipe approximately 2.5 m below the existing ground. . The laying pertaining to the remaining portion of the pipes other than the sleeve shall be carried out by ordinary approved procedures by excavation to the required level, bedding, compaction and the filling above the portion over the pipe and tested accordingly after the pipes are laidCase 3Existing 1 box culvert and 2 # 60” dia ABB Cooling water pipe laying at about 10 m from the culvert is in progress. Proposed 14 “ Desalinated water pipe has to cross over ABB pipes keeping 1 m apart verticallyA sleeve 5 m long has to pass beneath the box culvert (about 3m x 3m in section) below the base by directional boring so that 1 m projection remains on both sides of the culvert. The pipes shall then be raised over the existing 2 #s 60” dia ABB cooling water lines at about 2. 3 m from the existing ground level so that the top of the pipes is 1.2 m from the ground level. The laying pertaining to the remaining portion of the pipes other than the sleeve shall be carried out by ordinary approved procedures by excavation to the required level, bedding, compaction and the filling above the portion over the pipe and tested accordingly. The work for the portion to cross over ABB pipes shall be carried out after the ABB pipes are laid and backfilledOn site, sufficient excavated space is available to lower the sleeve in to pull into the boreDe watering shall be carried out as per specification if necessaryExcavation shall be carried out according to the requirementThe boring shall be carried out in stages. First stage-The sleeve is in the trench on one end and the reamer fully underground. Second stage-The sleeve is partly pulled in and the reamer partly withdrawnThird stage- The sleeve further pulled and the reamer withdrawn accordingly Fourth stage-Full portion of the sleeve is underground in the bore and the reamer outThe excavated trenches on both ends shall be backfilled by Civil Contractor according to the specification requirement and the required tests carried outThe reinstatement of the effected services shall be carried out after the directional boring is completedDirectional Boring – A non- excavation Method which does not allow collapsing of the ground surfaceM / S Ditch Witch shall carry out the Directional Boring employing Jet Trac Directional Boring equipment according to their approved method statement Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 364: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

364 of

Refer to the attached sketches based on the Ditch Witch guidelines Bentonite is pure clay to be used as a fluid / slurry formed by mixing water. It shall be used to cool the drill bit and to lubricate the drill areaThe material displaced by the head / sleeves shall be discharged at the receiving end in the receiving pit and removed from the siteAll fully trained operators shall be used on the jobEquipmentJet Track Unit (complete package), Crane, CompactorAttachmentCross-Section Sketches showing 3 # cases#145

Directional boring at 3# locations for 14”desalinated water pipe corniche road North of gupTopIndexScopeReference documentsSafetyMethod EquipmentAttachmentScopeThe statement is aimed to propose the procedures to be adopted to carry out the directional boring under the existing culverts to facilitate to lay the sleeves for pipe lines 1 # 14” Desalinated Water at 3 # locations. The concrete culverts are not in good condition and directional drilling or thrust bore is the method preferred by Operator (RRD) for carrying out this work SafetyPrior to the commencement of any activity the labour force shall receive a / STARRT card / Toolbox talk. Any process involving a particular safety risk shall be assessed and adopted measures addressed to raise to a minimum standard In this case the excavation has to be carried out on the Operating Authority area, therefore all the regulated precautions shall be strictly adhered to effect a full safety standard.Excavation Work Permit- A copy of the work permit shall be posted on a mini board installed on site at the location shown on the sketch to be noticeable to all the persons involved A copy shall also be transmitted to EPC Contractor

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 365: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

365 of

Barricades, cones, markers, the night-lights, and floodlights etc. shall be installed as required at the works for complete safety. MethodThe necessary permit to work shall be obtained from the Plant Refinery Division.The record drawings regarding the existing services shall be obtainedTrial pits shall be made manually on both ends of the proposed boring to check for existing services and protect these from any damage and shall also be used for the bentonite trial at the receiving endCase 1 Existing 1 box culvert and a 14” dia pipe about 1 m from culvert A carbon steel sleeve 5 m long of dia 20 “is to be installed beneath the box culvert (about 3m x 3m in section), 1 m below the base by directional boring so that 1 m projection remains on both sides of the culvert. The 14” dia GRE pipe shall then pass through the installed sleeve Case 2Existing 1 box culvert and 1 pipe 1.5 m dia 2 m from the culvert and 1 pipe 1 m dia about 3.3 m below ground. 4 # existing services A sleeve 7.3 m long shall be installed beneath the box culvert (about 3m x 3m in section),1 m below the base by directional boring so that 1 m projection remains on both sides of the obstructions approximately 2.5 m below the existing ground. The 14” dia GRE pipe shall then pass through the installed sleeve Case 3Existing 1 box culvert A sleeve 5 m long shall be installed beneath the box culvert (about 3m x 3m in section) below the base by directional boring so that 1 m projection remains on both sides of the culvert. On site, sufficient excavated space is available to lower the sleeve in to pull into the boreThe excavated trench does not show any sign of water therefore, no de watering shall be carried outExcavation shall be carried out according to the requirementThe boring shall be carried out in stages. First stage-The sleeve is in the trench on one end and the reamer fully underground. Second stage-The sleeve is partly pulled in and the reamer partly withdrawnThird stage- The sleeve further pulled and the reamer withdrawn accordingly Fourth stage-Full portion of the sleeve is underground in the bore and the reamer outThe excavated trenches on both ends shall be backfilled by Civil Contractor according to the specification requirement and the required tests carried outThe reinstatement of the effected services shall be carried out after the directional boring is completedDirectional Boring – A non- excavation Method which does not allow collapsing of the ground surfaceStatements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 366: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

366 of

M / S Ditch Witch shall carry out the Directional Boring employing Jet Trac Directional Boring equipment according to their approved method statement Refer to the attached sketches based on the Ditch Witch guidelines Bentonite is pure clay to be used as a fluid / slurry formed by mixing water. It shall be used to cool the drill bit and to lubricate the drill areaThe material displaced by the head / sleeves shall be discharged at the receiving end in the receiving pit and removed from the siteAll fully trained operators shall be used on the jobMajor EquipmentJet Track Unit (complete package), Crane, CompactorAttachmentCross-Section Sketches showing 3 # cases#146

Directional boring at 3# locations for 14”desalinated water pipe corniche road North of gupTopIndexScopeReference documentsSafetyMethod EquipmentAttachmentScopeThe statement is aimed to propose the procedures to be adopted to carry out the directional boring under the existing culverts to facilitate to lay the sleeves for pipe lines 1 # 14” Desalinated Water at 3 # locations. The concrete culverts are not in good condition and directional drilling or thrust bore is the method preferred by Operator (RRD) for carrying out this work SafetyPrior to the commencement of any activity the labour force shall receive a / STARRT card / Toolbox talk. Any process involving a particular safety risk shall be assessed and adopted measures addressed to raise to a minimum standard In this case the excavation has to be carried out on the Operating Authority area, therefore all the regulated precautions shall be strictly adhered to effect a full safety standard.Excavation Work Permit- A copy of the work permit shall be posted on a mini board installed on site at the location shown on the sketch to be noticeable to all the persons involved Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 367: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

367 of

A copy shall also be transmitted to EPC ContractorBarricades, cones, markers, the night-lights, and floodlights etc. shall be installed as required at the works for complete safety. MethodThe necessary permit to work shall be obtained from the Plant Refinery Division.The record drawings regarding the existing services shall be obtainedTrial pits shall be made manually on both ends of the proposed boring to check for existing services and protect these from any damage and shall also be used for the bentonite trial at the receiving endCase 1 Existing 1 box culvert and a 14” dia pipe about 1 m from culvert A carbon steel sleeve 5 m long of dia 20 “is to be installed beneath the box culvert (about 3m x 3m in section), 1 m below the base by directional boring so that 1 m projection remains on both sides of the culvert. The 14” dia GRE pipe shall then pass through the installed sleeve Case 2Existing 1 box culvert and 1 pipe 1.5 m dia 2 m from the culvert and 1 pipe 1 m dia about 3.3 m below ground. 4 # existing services A sleeve 7.3 m long shall be installed beneath the box culvert (about 3m x 3m in section),1 m below the base by directional boring so that 1 m projection remains on both sides of the obstructions approximately 2.5 m below the existing ground. The 14” dia GRE pipe shall then pass through the installed sleeve Case 3Existing 1 box culvert A sleeve 5 m long shall be installed beneath the box culvert (about 3m x 3m in section) below the base by directional boring so that 1 m projection remains on both sides of the culvert. On site, sufficient excavated space is available to lower the sleeve in to pull into the boreDewatering shall be carried out as per specification if necessaryExcavation shall be carried out according to the requirementThe boring shall be carried out in stages. First stage-The sleeve is in the trench on one end and the reamer fully underground. Second stage-The sleeve is partly pulled in and the reamer partly withdrawnThird stage- The sleeve further pulled and the reamer withdrawn accordingly Fourth stage-Full portion of the sleeve is underground in the bore and the reamer outThe excavated trenches on both ends shall be backfilled by Civil Contractor according to the specification requirement and the required tests carried outThe reinstatement of the effected services shall be carried out after the directional boring is completedDirectional Boring – A non- excavation Method which does not allow collapsing of the ground surfaceStatements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 368: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

368 of

M / S Ditch Witch shall carry out the Directional Boring employing Jet Trac Directional Boring equipment according to their approved method statement Refer to the attached sketches based on the Ditch Witch guidelines Bentonite is pure clay to be used as a fluid / slurry formed by mixing water. It shall be used to cool the drill bit and to lubricate the drill areaThe material displaced by the head / sleeves shall be discharged at the receiving end in the receiving pit and removed from the siteAll fully trained operators shall be used on the jobMajor EquipmentJet Track Unit (complete package), Crane, CompactorAttachmentCross-Section Sketches showing 3 # cases#147

Epoxy skirting in Central control building & sub stations on dry liningTopIndexScopeReference documentsSafetyMethod EquipmentAttachmentScopeThe statement is aimed to propose the procedures to be adopted to carry out epoxy skirting on dry lining in areas not exposed to impact or abuseSafetyPrior to the commencement of any activity the labour force shall receive a / STARRT card / Toolbox talk. Any process involving a particular safety risk shall be assessed and adopted measures addressed to raise to a minimum standard Safety Supervision A competent inspector shall visit the area daily to assess the safety measures adopted. Any snag observed during his visit shall be notified to the supervisor present who immediately act to bring the safety measures to an acceptable standard MaterialMaster Builders TechnologiesConcresive 1020 primerConcresive 2020 Epoxy MortarStatements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 369: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

369 of

MethodSurface Preparation Surface shall be cleaned of all dust and dirt and other contaminantsA 5 mm groove shall be formed on the dry lining to cove in the skirtingCivil Contractor QC inspection shall be conducted to ensure that the surface is clean and contaminants freePrimer CoatMixing of the base and reactor components shall be carried out in a vessel using an electric operated slow speed drill with a suitable paddle attachment making sure that the paddle reaches to the bottom and sides of the vessel and mixing carried out for 1 to 2minutes until a uniform consistency and colour is achievedApplicationThe mixed material shall be applied to the surface using a stiff brush according to the stated coverage on the manufacturer’s datasheetHigh Build Epoxy Resin Mortar It is essential to apply the mortar while the primer being tacky otherwise a second priming coat shall be appliedThorough mixed mortar according to the manufacturer’s instruction shall be applied in a 3 mm layer to the primed surface with steel trowel pressed well into the surface compacting to ensure positive and permanent adhesion. Finishing shall be carried out by a steel trowel to bring the resin to the surface Mastertop Resin as suggested by the manufacturer is not applicable in this caseCivil Contractor QC inspection shall be conducted throughout the above operationsEquipmentMixing VesselElectric drill with paddle attachmentStiff brushSteel trowelAttachmentMBT method statement#148

Epoxy skirting on dry liningTopIndexScopeReference documentsSafetyMethod EquipmentAttachment

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 370: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

370 of

ScopeThe statement is aimed to propose the procedures to be adopted to carry out epoxy skirting on dry lining in areas not exposed to impact or abuseRef Specs Outline building specification Page SafetyPrior to the commencement of any activity the labour force shall receive a / STARRT card / Toolbox talk. Any process involving a particular safety risk shall be assessed and adopted measures addressed to raise to a minimum standard . MBT instructions shall be adhered strictlySafety Supervision A competent inspector shall visit the area daily to assess the safety measures adopted. Any snag observed during his visit shall be notified to the supervisor present who immediately act to bring the safety measures to an acceptable standard MaterialMaster Builders TechnologiesConcresive 2200 Epoxy Mortar 3mm thick‘Mastertop 1230 is’ resin without aggregate componentMethodA sample was prepared on site in Central Control Building Battery Room approved by EPC Contractor Surface Preparation Sandpaper shall be rubbed lightly on the acrylic wall coating followed by wiping with a clean cloth to remove any residual dust & laitanceCivil Contractor QC inspection shall be conducted to ensure that the surface is clean and contaminants freeHigh Build Epoxy Resin Mortar Concresive 2200Base and the reactor components shall be mixed together using a trowelThe mixed material shall be applied in 3mm thickness on the surface to the required level forming cove using the minimum of solvent on the trowel to aid workabilitySurface shall be finished smooth using a paint brush dipped in cleaning solvent # 2Civil Contractor QC inspection shall be conducted throughout the above operationsAn allowance of 24 hours for curing shall be given prior to overcoating with ‘Mastertop 1230 is’ flooring compound using only resin without aggregate componentOvercoating with Mastertop ‘1230is’ Resin (500 microns)The surface of the cured Concresive shall be rubbed lightly with sandpaper to remove any rough edgesAreas prone to splashing with wet resin shall be protected and the free edges masked with 50-mm wide tapeThe surface shall be sealed with Mastertop 1200 resin diluted with 5 % volume of solvent # 2 prior to applying ‘Mastertop 1230 is’ resin as followsReactor shall be poured into base and mixed together for 1-2 minutes using a slow speed drill fitted with a spiral mixer, then solvent added and mixed for 1 minuteStatements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 371: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

371 of

The mixed material shall be applied on the surface ensuring total coverage using a spiked roller. Sealer coat shall be allowed to cure to a tackfree state prior to applying ‘Mastercoat 1230 is’ resin coatingReactor B and Base A shall be poured into a suitable mixer and mixed together using a slow speed drill fitted with a suitable mixing paddle and mixed for about half a minute before ‘Mastertop 1230 is’ filler is added keeping the mixing on until a uniform colour is obtained free of streaks or lumps of unmixed fillerSmooth Finish For the base coat ‘Mastertop 1230 is’ shall be applied @ 1.1 liter per m2. For the second coat ‘Mastertop 1230 is’ shall be mixed and applied @ 0.4 liter per m248 hours curing allowance shall be givenCivil Contractor QC inspection shall be conducted throughout the above operationsEquipmentMixing Vessel, Electric drill with paddle attachment, Notched trowel, Soft brush,AttachmentMBT method statement ref #149

Epoxy skirting on dry liningTop

IndexScopeReference documentsSafetyMethod EquipmentAttachmentScopeThe statement is aimed to propose the procedures to be adopted to carry out epoxy skirting on dry lining in areas not exposed to impact or abuseRef Specs Outline building specification Page SafetyPrior to the commencement of any activity the labour force shall receive a / STARRT card / Toolbox talk. Any process involving a particular safety risk shall be assessed and adopted measures addressed to raise to a minimum standard. MBT instructions shall be adhered strictly

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 372: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

372 of

Safety Supervision A competent inspector shall visit the area daily to assess the safety measures adopted. Any snag observed during his visit shall be notified to the supervisor present who immediately act to bring the safety measures to an acceptable standard MaterialMaster Builders TechnologiesConcresive 2200 Epoxy Mortar 3mm thick‘Mastertop 1230 is’ resin without aggregate componentMethodA sample was prepared on site in Central Control Building Battery Room for inspection and acceptance by EPC Contractor Civil Contractor shall co-ordinate with EPC Contractor regarding moving of any UPS batteries that may be required prior to carrying out any skirtingSurface Preparation Sandpaper shall be rubbed lightly on the acrylic wall coating followed by wiping with a clean cloth to remove any residual dust & laitanceCivil Contractor QC inspection shall be conducted to ensure that the surface is clean and contaminants freeHigh Build Epoxy Resin Mortar Concresive 2200Base and the reactor components shall be mixed together using a trowelThe mixed material shall be applied in 3mm thickness on the surface to the required level forming cove using the minimum of solvent on the trowel to aid workabilitySurface shall be finished smooth using a paint brush dipped in cleaning solvent # 2Civil Contractor QC inspection shall be conducted throughout the above operationsAn allowance of 24 hours for curing shall be given prior to overcoating with ‘Mastertop 1230 is’ flooring compound using only resin without aggregate componentOvercoating with Mastertop ‘1230is’ Resin (500 microns)The surface of the cured Concresive shall be rubbed lightly with sandpaper to remove any rough edgesAreas prone to splashing with wet resin shall be protected and the free edges masked with 50-mm wide tapeThe surface shall be sealed with Mastertop 1200 resin diluted with 5 % volume of solvent # 2 prior to applying ‘Mastertop 1230 is’ resin as followsReactor shall be poured into base and mixed together for 1-2 minutes using a slow speed drill fitted with a spiral mixer, then solvent added and mixed for 1 minuteThe mixed material shall be applied on the surface ensuring total coverage using a spiked roller. Sealer coat shall be allowed to cure to a tackfree state prior to applying ‘Mastercoat 1230 is’ resin coatingReactor B and Base A shall be poured into a suitable mixer and mixed together using a slow speed drill fitted with a suitable mixing paddle and mixed for about half a minute before ‘Mastertop 1230 is’ filler is added keeping the mixing on until a uniform colour is obtained free of streaks or lumps of unmixed fillerSmooth Finish For the base coat ‘Mastertop 1230 is’ shall be applied @ 1.1 liter per m2. Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 373: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

373 of

For the second coat ‘Mastertop 1230 is’ shall be mixed and applied @ 0.4 liter per m248 hours curing allowance shall be givenCivil Contractor QC inspection shall be conducted throughout the above operationsEquipmentMixing Vessel, Electric drill with paddle attachment, Notched trowel, Soft brush,AttachmentMBT method statement ref RF / 2833 / 2000 / SRH / NH / 30.10.2000#150

Road surface Reinstatement over box culvert crossingsTopIndexScopeReference documentsSafetyMethod EquipmentAttachmentScopeThe statement is aimed to propose the procedures to be adopted to carry out the reinstatement to the existing road surfaces removed from the crossings effected portions pertaining to Roads Avenue C, D, First Street, GUP Entrance etc.Reference: Specification Section SafetyPrior to the commencement of any activity the labour force shall receive a / STARRT card / Toolbox talk. Any process involving a particular safety risk shall be assessed and adopted measures addressed to raise to a minimum standard. Safety Supervision A competent inspector shall visit the area daily to assess the safety measures adopted. Any snag observed during his visit shall be notified to the supervisor present who immediately act to bring the safety measures to an acceptable standard MaterialBitumen MC1Asphalt Concrete for Base / Under CourseTack Coat SS1hAsphalt Concrete for Wearing CourseMethodTraffic Management

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 374: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

374 of

RRD Approved Traffic Management Scheme shall be implemented to the requirementSurface Preparation Civil Contractor QC inspection shall be conducted for the backfill clearance PrimerThe portion of the backfilled earth 120mm deep shall be excavated from the existing road surface level followed by compaction, testing and preparation for the primerThe approved compacted surface shall be made ready for applying MC1 primerCivil Contractor QC inspection shall be conducted to ascertain the suitability of the surface to receive the primerPrimer shall be sprayed by tanker on the complete surface @ 0.8 to 1.4 litres / sqmThe surface shall be left for such time until the material dries out usually 24 hours post application otherwise, sand shall be used to blot the excessive bitumen prior to commence to lay the Base / Under course asphalt concrete60 mm Thick Base / Under Course Asphalt ConcreteCivil Contractor QC inspection shall be conducted to ascertain the suitability of the primed surface to receive asphalt concreteAsphalt concrete shall be laid on the approved surface to the prepared profile so that a uniform 60 mm compacted thickness is obtained after compaction by rollingAfter spreading the material, the rolling shall be carried out by one 3 wheel roller, one Pneumatic Tyre roller and one 2-axle Tandem rollers 8 to 10 tonnes capacity according to the specified procedures giving 6 passes overlapping the previous pass by 300mm of the previous trip using sufficient oil or water to moisten the wheels and fully compacted before asphalt concrete reaches 80 CAn allowance for one hour shall be given to commence to lay the Wearing course after the base course is compacted by rollingCivil Contractor QC inspection shall be conducted throughout the above operationsTack / Seal Coat using SS1hAn application of the tack coat @ 0.4 to 0.7 litres / sqm shall be carried out on the rolled surface of the Base / Under Course Civil Contractor QC inspection shall be conducted to ascertain the correct Base Course surface profile and the Tack Coat acceptability60mm Wearing Surface CourseAsphalt Concrete shall be laid for the Wearing coat also in a similar manner ensuring that the top of the compacted material is at the same level as the top of the existing road surface on both sides of the culvertCivil Contractor QC inspection shall be conducted to ensure that the surface is to the acceptable profile and compaction is carried out to the standardsThe area shall be fully cleared to the normal requirementThe Traffic management scheme shall be removed and normal traffic restoredEquipmentBitumen Tanker, Pressure boom, Asphalt Concrete Spreader and paver, Road Rollers AttachmentNone

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 375: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

375 of

#151

Repair to lift Cladding panel Administration buildingTopIndexScopeReference documentsSafetyMethod EquipmentAttachmentScopeThe statement is aimed to propose the procedures to be adopted to rectify the stainless cladding lift panel in the Administration BuildingSafetyPrior to the commencement of any activity the labour force shall receive a / STARRT card / Toolbox talk. Any process involving a particular safety risk shall be assessed and adopted measures addressed to raise to a minimum acceptable standard Safety Supervision A competent inspector shall visit the area daily to assess the safety measures adopted. Any snag observed during his visit shall be notified to the supervisor present who immediately act to bring the safety measures to an acceptable standard MaterialNew stainless steel lift panel from OTISMethodNew panel to be fixed over the damaged one shall be supplied by the factoryCivil Contractor QC inspection shall be conducted to ensure that the new panel adheres to the requirementThis panel shall be placed over the existing damaged panel to check the compatibility to fixingThen the new panel shall be removed & glue applied on both surfaces to be adhered Glue shall be allowed to dry for a few minutes and then both surfaces shall be bonded togetherThe protection film shall then be removed from the panel and surface cleaned using soft cotton clothCivil Contractor QC inspection shall be conducted to ensure that the new panel has been fixed properly to the damaged one

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 376: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

376 of

EquipmentAttachmentOTIS method statement#152

Fixing sheeting panelsWall & roof claddingTop

IndexScopeReference documentsSafetyMethod EquipmentAttachmentScopeThe statement is aimed to propose the procedures to be adopted to fix the roof and the wall panels for various structures to be claddedSafetyPrior to the commencement of any activity the labour force shall receive a / STARRT card / Toolbox talk. Any process involving a particular safety risk shall be assessed and adopted measures addressed to raise to a minimum acceptable standard Safety Supervision A competent inspector shall visit the area daily to assess the safety measures adopted. Any snag observed during his visit shall be notified to the supervisor present who immediately act to bring the safety measures to an acceptable standard MaterialMAR 120- Formawall for wall panels, Trisomet for Roof Panels, Profile EP3-Corrugated steel sheet (Single Skin)- by European Profiles (BS / HHR)Three types of panels shall be used as followsMaintenance Building-Roof Panels- Trisomet, Wall Panels- Formawall FlatCar Parks- Corrugated CladdingWork shall be carried out by M / S Khalidiya IntersystemsMethodPreparation Prior to the commencement of the sheeting operations, the structural items including the door posts and parapet etc shall be lined and levelled properly to the requirement within acceptable tolerances Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 377: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

377 of

Wind brace clips shall be removed and the building cleanedCivil Contractor QC inspection shall be conducted to ensure that the structural elements are aligned, levelled and fixed to the specified requirement Fixing Roof PanelsValley gutters shall be fixed and alignedInternal ridge flashing shall be fixed in positionInsulated Trisomet panels shall be fixed starting from the valley and rising to the ridge and all fixings fastened on the crownAll end laps shall be sealed with mastic to prevent capillary humidity riseProcedure shall be repeated for the parapet wall by fixing and aligning the gutter External ridge flashing shall be fixedThe entire roof shall be brush cleaned and colour caps fixedCivil Contractor QC inspection shall be conducted throughout the above operationsFixing Formawall Flat PanelsFirst TierDrip flashing shall be fixed at the base of the wall to be used as a straight datum lineThe first formawall vertical panel shall be fixed to true plumb and fastened by steel screws throughout the joints and the next panel fixed along side of the first panel by providing a tight vertical joint & the process repeated till the end is reachedSpecial flashing shall be fixed to the entire length of the first tier of vertical panelsSecond TierThe second tier of the blue panels shall be fixed in the same manner as the lower panelThe procedure shall continue till all the sides are completedSpecial corner flashing shall be used internally and externally to provide an aesthetic finish at the corner jointsCivil Contractor QC inspection shall be conducted throughout the above operationsCar ParkCorrugated claddingSingle long panel shall be fixed fastened to the straight end of the structure through the crown with one and a half profile overlapped on sides and mastic inserted between the sheetsThe procedure shall be continued to the curve where sheets are to be racked and cut to provide roof curvatureThe entire roof shall be brush cleaned and colour caps insertedCivil Contractor QC inspection shall be conducted throughout the above operationsEquipmentAttachmentKhalidiya method statement ref MAR approval reference #153

Fixing sheeting panelsStatements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 378: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

378 of

Wall & roof claddingTopIndexScopeReference documentsSafetyMethod EquipmentAttachmentScopeThe statement is aimed to propose the procedures to be adopted to fix the roof and the wall metal panels for various structures to be claddedSafetyPrior to the commencement of any activity the labour force shall receive a / STARRT card / Toolbox talk. Any process involving a particular safety risk shall be assessed and adopted measures addressed to raise to a minimum acceptable standard Safety Supervision A competent inspector shall visit the area daily to assess the safety measures adopted. Any snag observed during his visit shall be notified to the supervisor present who immediately act to bring the safety measures to an acceptable standard Reference Specification (Metals) for fasteners,MaterialMAR Formawall for wall panels,Trisomet for Roof Panels, Profile EP3-Corrugated steel sheet (Single Skin)- by European Profiles (BS / HHR)Three types of panels shall be used as followsMaintenance Building-Roof Panels- Trisomet, Wall Panels- Formawall FlatCar Parks- Corrugated CladdingWork shall be carried out by M / S Khalidiya IntersystemsMethodPreparation Prior to the commencement of the sheeting operations, the structural items including the door posts and parapet etc shall be lined and levelled properly to the requirement within acceptable tolerances Wind brace clips shall be removed and the building cleanedAll necessary documentation i.e Check List, RFI etc shall be completed and submitted prior to the work commencementCivil Contractor QC inspection shall be conducted to ensure that the structural elements are aligned, levelled and fixed to the specified requirement Installation shall be carried out in accordance with the provisions in specification Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 379: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

379 of

Fixing Roof PanelsValley gutters shall be fixed and alignedInternal ridge flashing shall be fixed in positionInsulated Trisomet panels shall be fixed starting from the valley, rising to the ridge and all fixings fastened on the crown to the specification requirementAll end laps shall be cleaned of all dust, dirt etc & sealed to the manufacturer’s instructions with mastic to prevent capillary humidity riseProcedure shall be repeated for the parapet wall by fixing and aligning the gutter External ridge flashing shall be fixedThe entire roof shall be brush cleaned and colour caps fixedCivil Contractor QC inspection shall be conducted throughout the above operations to the ITP requirementsFixing Formawall Flat PanelsFirst TierDrip flashing shall be fixed at the base of the wall to be used as a straight datum lineThe first formawall vertical panel shall be fixed to true plumb and fastened by steel screws throughout the joints and the next panel fixed along side of the first panel by providing a tight vertical joint & the process repeated till the end is reachedSpecial flashing shall be fixed to the entire length of the first tier of vertical panelsSecond TierThe second tier of the blue panels shall be fixed in the same manner as the lower panelThe procedure shall continue till all the sides are completedSpecial corner flashing shall be used internally and externally to provide an aesthetic finish at the corner jointsCivil Contractor QC inspection shall be conducted throughout the above operations to the ITP requirementsCar ParkCorrugated claddingSingle long panel shall be fixed & fastened to the straight end of the structure through the crown with one and a half profile overlapped on sides and mastic inserted between the sheetsThe procedure shall be continued to the curve where sheets are to be racked and cut to provide roof curvatureThe entire roof shall be brush cleaned and colour caps insertedCivil Contractor QC inspection shall be conducted throughout the above operationsWallsField Check for water leakageUpon completion of the installation the wall shall be checked for Water Penetration in accordance with AAMA standard 501.2-83“Field check of Metal Curtain Walls for water leakage” on the designated areaSite ClearanceAll debris & excess material shall be removed making sure no weep holes and the drainage channels are unobstructed and free of dust and the sealantsEquipmentMan LiftStatements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 380: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

380 of

Electric DrillsAttachmentM / S Khalidiya method statement ref MAR approval reference Note-QA Documentation Formats shall be submitted separately#154

Road crossingAt fire station- first streetFor laying

2 # 100 mm sleevesFor telephone cablesTopIndexScopeSafetyMethod including traffic management schemeEquipmentAttachmentScopeThe statement is aimed to propose the procedures to be adopted to carry out the excavation & lay the sleeves at the road crossings meant for the 2 # Telephone Cables SafetyPrior to the commencement of any activity the labour force shall receive a / STARRT card / Toolbox talk. Any process involving a particular safety risk shall be assessed and adopted measures addressed to raise to a minimum standard In this case the excavation has to be carried out on the Operating Authority area, therefore all the regulated precautions shall be strictly adhered to effect ‘ full safety standard’.Safety Supervision A competent inspector shall visit the area daily to assess the safety measures adopted. Any snag observed during his visit shall be notified to the supervisor present who immediately act to bring the safety measures to an acceptable standard In case of incident where utilities not identified are discovered or damaged, all work shall stop in the area and the Operator Shift Controller and HSE department immediately notifiedPhone number : Shift Controller Emergency Number HSE Direct number Employees working in easement area shall have a daily pre-task briefing that includes;Reporting of incidentsStatements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 381: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

381 of

Methods of work and tools to be usedPotential hazards found in the Easement areasThe approved work method statementEPC Contractor and Civil Contractor HSE department shall participate in presenting the STARRT card briefing and monitor the activities to ensure that the work methods are being followed and all personnel have an understanding of the hazards associated with working adjacent to live process areasExcavation Work Permit- A copy of the work permit shall be posted on a mini board installed on site to be noticeable to all persons involved with the crossingBarricades, cones, markers, the night-lights, and floodlights etc. shall be installed as required for a complete safety. No oil spillage shall be allowed. Hand Excavation- Excavation to expose the services shall be carried out manually.In case certain services not shown on the record drawings such as fibre optics but it is discovered, further excavation shall be ceased until a decision is taken for the method to be adopted for further excavationAccess to trench- The workers shall clearly be instructed to use only the ladders to enter in or come out of the trench. No jumping shall be allowedMachine ExcavationThe operators / drivers shall be explicitly instructed to abide by the requirement of the reverse signal and sound when operating reverse. Banksman shall be engaged equipment operation. No violation of the traffic rules shall be allowedMethodThe required permit to work shall be obtained from the Plant Refinery Division.The record drawings regarding the existing services shall be obtained.A traffic management scheme shall be produced on site as detailed on the attached sketch subject to RRD approvalDrawing reference –The road shall be excavated in one instance by diverting the traffic to North as shown ProceduresTraffic management scheme shall be implemented effectivelyThe asphalt pertaining to the crossing portion shall be removed Hand excavation shall be carried out to expose the cables & the other services employing seaming the area to detect the existence of cables After the exposure, all the cables shall be covered with split PVC pipe and well supported temporarily to continue the excavation mechanically Remaining portion of the trench shall be excavated by machine to the defined levelsThe formation shall be prepared to receive the bedding concreteCivil Contractor QC Inspections shall be conducted to approve the formation 100mm thick bedding Concrete shall be poured & cured according to the approved procedures2 # 100 mm PVC sleeves shall be laid to the exact locations and the levelsCivil Contractor QC Inspections shall be conducted to approve the levels and the alignment Haunch concrete shall be carried out according to the standard details followed by the curing to the approved procedures

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 382: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

382 of

Backfilling up to the road formation shall be carried out up to the road asphalt bottom level according to specificationsThe removed asphalt portion shall be made good using new asphalt concrete to the approved proceduresThe traffic management scheme shall be removed after the road crossing is cleared of all debris and obstructions.Either side of the road shall be provided with cable markers to indicate the servicesMajor EquipmentExcavator, Dumper Trucks, Concrete Trucks, Concrete Pump, Vibrators, Compactors. Jack Hammer, Compressor, Asphalt finisher, Road Rollers etc.AttachmentSketch showing the Traffic Management Scheme #155

Sea water surge basinClosing the structural gapOn the roof, wall & base slabTopIndexScopeSafetyMethod EquipmentAttachmentScopeThe statement is aimed to propose the procedures to be adopted to carry out the repair to the gaps created at the roof, wall and base slab movement joints due to the structural slideSafetyPrior to the commencement of any activity the labour force shall receive a / STARRT card / Toolbox talk. Any process involving a particular safety risk shall be assessed and adopted measures addressed to raise to a minimum standard. All safety means recommended by the manufacturer MBT as well as required to be adopted by the regulations shall be adhered to

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 383: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

383 of

Safety Supervision A competent inspector shall visit the area daily to assess the safety measures adopted. Any snag observed during his visit shall be notified to the supervisor present who immediately act to bring the safety measures to an acceptable standard Material Concresive 1320 from MBTMethodRoof Slab Joint GapThe soffit portion of the joint shall be closed by using a form provided with a polystyrene baking rod to suit the sealant profileThe internal surface and the external edges shall be cleaned using compressed air and the hard brushAn Civil Contractor QC inspection shall be conducted to ensure the cleanliness and that the joint is ready to receive the materialThe material Concresive 1320 shall be prepared according to the manufacturer’s instructions and poured into the prepared space between the compressed filler and filled fully to the required levelA bead shall be used to render a profile to suit the sealantNext day the form shall be removed and the sealant applied to the required profile giving the joint a smooth faceAn Civil Contractor QC inspection shall be conducted throughout the above operationsBase Slab Joint GapSimilarly, the above operations shall be repeated for the base slab with the exception of the soffit formsAn Civil Contractor QC inspection shall be conducted throughout these operationsWall Joint GapSimilarly, the above operations shall be repeated for the wall with the exception of the soffit form but side forms in stages shall be erectedAn Civil Contractor QC inspection shall be conducted throughout these operationsMajor EquipmentAttachmentCatalogue Page Concresive 1320

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 384: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

384 of

#156

Hdpe pipes Butt fusionTopIndexScopeSafetyMethod EquipmentAttachmentScopeThe statement is aimed to propose the procedures to be adopted to carry out the welding by fusion at joints between the HDPE pipes using COSMOPLAST advanced PE jointing technologySafetyPrior to the commencement of any activity the labour force shall receive a / STARRT card / Toolbox talk. Any process involving a particular safety risk shall be assessed and adopted measures addressed to raise to a minimum standard. All safety means recommended by the manufacturer COSMOPLAST (refer to page 14 & 35 on the catalogue) as well as required to be adopted by the regulations shall be adhered to Safety Supervision A competent inspector shall visit the area daily to assess the safety measures adopted. Any snag observed during his visit shall be notified to the supervisor present who immediately act to bring the safety measures to an acceptable standard Material Pipes & fittings (COSMOPLAST)MethodElectrofusion-PrecautionsA check shall be made that the pipes to be joined are of the same size to Standard Dimension Ratio (SDR) and material. Only compatible material shall be usedThe butt fusion machine shall be sited on a suitable clean, dry baseboard or ground inside a shelter to minimise contamination and wind effectIt shall be ensured that the control box voltage is compatible with fittingAlignment / restraining clamps shall be usedPipe ends shall be cut square for electrofusion sockets

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 385: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

385 of

Pipe / or spigot surfaces shall be scraped fully & surfaces & fittings kept cleanIt shall be ensured that correct fusion & cooling times are adhered toThe joint shall be assembled & fused immediately after scraping pipeThe joint shall be completed in one goThe fitting shall not be allowed to be out of protective bagsThe dirty fittings shall not be usedPrepared pipe surfaces shall not be touchedAssemblies shall not be allowed to get damp before joiningDuring welding cycle the weld shall not be touchedThe joint shall not be removed from the clamp unless full cooling time has elapsedThe integral cutter shall not be removed from the saddle once the main has been drilledPre jointing checksThe regularly serviced equipment in good condition only shall be usedIt shall be ensured that correct joining parameters for the machine and the pipe being welded are known and clearly understood It shall be ensured that the generator has sufficient quantity of fuel for the duration of the programmed work. Heater plate should be cleaned or washed using only clean and cold water and dried with a clean lint free cloth or paper towelA check shall be made to ascertain that the trimmer is clean with undamaged blades in good conditionIt shall be ensured that clamp liners and securing screws of the correct size are available for the size of pipe to be joined. Lines must be clean and should sit fully in the pipe clamps to ensure correct alignment.A check shall be made to ensure that the heater plate is at correct temperature Correct parameters shall be selected for the pipes to be joinedMaking the JointIn an emergency the ‘red stop reset button’ when put off shall stop all automatic cycles and set the machine safe and return to start of the cycleDummy weld shall be made to remove any fine particles from the heater plate before every welding session, after changing from one pipe size to another & also if heater has been allowed to coolConnection & Pipe selectionHeater, chassis and trimmer cables shall be connected to the computerAfter ensuring that hydraulic connections are clean, connection shall be made to the controllerGenerator shall be started & computer connected to the generatorThe pipe to be connected shall be selectedThe data shall be confirmed Pipe PreparationPipe Preparation shall be carried out according to the description given on page on the manufacturer’s catalogueMaking the weldMaking the weld shall be carried out according to the description on page on the manufacturer’s catalogueQuality checks shall be conducted according to the description on page Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 386: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

386 of

All Do’s described on page 13 shall be followed and don’ts on page 14 avoidedJoint assembly preparation shall be carried out to description on page Pressure testing of joint shall be conducted to description on page Quality CheckQuality shall be checked to description on page Check (Butt Fusion)That the fusion indicators have risen while fittedThat no melted material or wire has exuded from the fittingThat the pipe has not moved from the fittingThat the area around the joint is cleanEvidence of scraping shall be checkedThat the saddles are square on pipeThat the print out is taken from control box and result checkedIn case the weld fails any of these checks,For sockets the joint shall be cut out and use another fittingFor saddles the main shall not be taped but a repeat weld carried out using a new fitting at least 200mm from the failed jointCivil Contractor QC inspection shall be conducted throughout the above operations according to the ITP and procedural requirements Major EquipmentGenerator, Electrofusion control box, Restraining & alignment equipment, Welding tent / shelter & ground sheet, Scraping equipment, Pipe cutter, Indelible Marker penAttachmentCosmoplast Method Statement #

Road crossingsTo construct box culverts ofh 2 & 3Corniche roadEthylene exportTopIndexScopeSafetyMethod EquipmentAttachmentScopeThis statement is aimed to propose the procedures to be adopted to carry out the construction of cast in situ culverts at road crossings for OFH 2 , 4 & 5 on Corniche Road SafetyStatements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 387: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

387 of

Prior to the commencement of any activity the labour force shall receive a / STARRT card / Toolbox talk. Any process involving a particular safety risk shall be assessed and adopted measures addressed to raise to a minimum standard In this case the excavation has to be carried out on the Operating Authority area, therefore all the regulated precautions shall be strictly adhered to effect ‘ full safety standard’.Safety Supervision A competent inspector shall visit the area daily to assess the safety measures adopted. Any snag observed during his visit shall be notified to the supervisor present who immediately act to bring the adopted safety measures to an acceptable standard In case of incident where utilities not identified are discovered or damaged, all work shall stop in the area and the Operator Shift Controller and HSE department immediately notifiedPhone number : Shift Controller Emergency Number HSE Direct number Employees working in easement area shall have a daily pre-task briefing that includes;Reporting of incidentsMethods of work and tools to be usedPotential hazards found in the Easement areasThe approved work method statementEPC Contractor and Civil Contractor HSE department shall participate in presenting the STARRT card briefing and monitor the activities to ensure that the work methods are being followed and all personnel have an understanding of the hazards associated with working adjacent to live process areasExcavation Work Permit- A copy of the work permit shall be posted on a mini board installed on site to be noticeable to all persons involved with the crossingBarricades, cones, markers, the night-lights, and floodlights etc. shall be installed as required for a complete safety. No oil spillage shall be allowed. Hand Excavation- Excavation to expose the services shall be carried out manually.In case certain services not shown on the record drawings such as fibre optics but it is discovered, further excavation shall be ceased until a decision is taken for the method to be adopted for further excavationAccess to trench- The workers shall clearly be instructed to use only the ladders whether to enter in or come out of the trench. No jumping shall be allowedMachine ExcavationThe operators / drivers shall be explicitly instructed to abide by the requirement of the reverse signal and sound when operating reverse. Banksman shall be engaged equipment operation. No violation of the traffic rules shall be allowedPre cast membersSince pre cast culvert / cover units, covers and sleepers are heavy in load, proper care has to be exercised during raising and installing / downing (handling) to the exact locations strictly adhering to the relevant safety measuresMethodThe required permit to work shall be obtained from the Plant Refinery Division.Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 388: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

388 of

The record drawings regarding the existing services shall be obtained.Drawing reference – ProceduresFor culvert OFH 3 the traffic scheme shall be implemented subject to the RRD approvalHand excavation shall be carried out to expose the cables & the other services employing seaming the area with detectors to detect the existence of cables After the exposure, all the cables shall be covered with split PVC pipe and well supported temporarily to continue the excavation mechanically Remaining portion of the trench shall be excavated by machine to the defined levelsPreparation of the trench to construct RCC culvert shall be carried out The construction pertaining to the pipe carrying cast in situ culverts i.e laying blinding concrete, protection membrane application, preparatory form work, re-bar placing , concrete pouring , curing etc all shall be carried out in different stages according to the approved procedures. Civil Contractor QC inspections shall be conducted throughout the above construction stages according to the check lists and the ITPs requirementLaying of pipe sleepers anchored with standard dowels, placing covers, fixing steps etc. shall be carried out according to the drawings and approved procedures using pre cast RCC units / members for sleepers and the culvert covers and 75 mm sling holes filled in with concreteThe diverted services shall be reinstatedInspections shall be conducted to the requirementBackfilling up to the road formation shall be carried out according to specificationsThe broken asphalt portion shall be made good using new asphalt according to approved proceduresAccess box out shall be closed with concrete after the pipes are laid8 mm-galvanised removable chequer plate covers with 2 lifting handles shall be provided to design details. Other chequer plates shall be provided to the design detailsMajor EquipmentExcavator, Dumper trucks, Compactors. Jack Hammer, Compressor, Asphalt finisher, Road RollersAttachmentNone

#158

Road crossingsTo install culverts ofh 4 & 5Corniche road ethylene export TopIndexScope

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 389: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

389 of

SafetyMethod EquipmentAttachmentScopeThe statement is aimed to propose the procedures to be adopted to carry out the excavation and installation of pre cast culverts at the road crossings Corniche Road Culverts OFH & for Ethylene Exports SafetyPrior to the commencement of any activity the labour force shall receive a / STARRT card / Toolbox talk. Any process involving a particular safety risk shall be assessed and adopted measures addressed to raise to a minimum standard In this case the excavation has to be carried out on the Operating Authority area, therefore all the regulated precautions shall be strictly adhered to effect ‘ full safety standard’.Safety Supervision A competent inspector shall visit the area daily to assess the safety measures adopted. Any snag observed during his visit shall be notified to the supervisor present who immediately act to bring the adopted safety measures to an acceptable standard In case of incident where utilities not identified are discovered or damaged, all work shall stop in the area and the Operator Shift Controller and HSE department immediately notifiedPhone number : Shift Controller Emergency Number HSE Direct number Employees working in easement area shall have a daily pre-task briefing that includes;Reporting of incidentsMethods of work and tools to be usedPotential hazards found in the Easement areasThe approved work method statementEPC Contractor and Civil Contractor HSE department shall participate in presenting the STARRT card briefing and monitor the activities to ensure that the work methods are being followed and all personnel have an understanding of the hazards associated with working adjacent to live process areasExcavation Work Permit- A copy of the work permit shall be posted on a mini board installed on site to be noticeable to all persons involved with the crossingBarricades, cones, markers, the night-lights, and floodlights etc. shall be installed as required for a complete safety. No oil spillage shall be allowed. Hand Excavation- Excavation to expose the services shall be carried out manually.In case certain services not shown on the record drawings such as fibre optics but it is discovered, further excavation shall be ceased until a decision is taken for the method to be adopted for further excavationAccess to trench- The workers shall clearly be instructed to use only the ladders whether to enter in or come out of the trench. No jumping shall be allowedMachine ExcavationStatements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 390: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

390 of

The operators / drivers shall be explicitly instructed to abide by the requirement of the reverse signal and sound when operating reverse. Banksman shall be engaged equipment operation. No violation of the traffic rules shall be allowedPre cast membersSince pre cast culvert units, covers and sleepers are heavy in load, proper care has to be exercised during raising and installing / downing (handling) to the exact locations strictly adhering to the relevant safety measuresMethodThe required permit to work shall be obtained from the Plant Refinery Division.The record drawings regarding the existing services shall be obtained.Drawing reference –ProceduresHand excavation shall be carried out to expose the cables & the other services employing seaming the area with detectors to detect the existence of cables After the exposure, all the cables shall be covered with split PVC pipe and well supported temporarily to continue the excavation mechanically Remaining portion of the trench shall be excavated by machine to the defined levelsPreparation of the trench to construct RCC culvert shall be carried out The construction pertaining to the pipe carrying culvert including the laying of pipe sleepers anchored with standard dowels, covers, fixing steps etc. shall be carried out according to the drawings and the approved procedures using pre cast RCC units / members75 mm dia Holes in the pre cast units meant for lifting shall be filled in with concreteIn addition, one access boxout on both ends shall be provided to design detailsThe diverted services shall be reinstatedInspections shall be conducted to the requirementBackfilling up to the road formation shall be carried out according to specificationsThe broken asphalt portion shall be made good using new asphaltRemoved / Preserved trees shall be replanted & all landscaping reinstated to RRD / GUP satisfaction8 mm-galvanised removable chequer plate covers with 2 lifting handles shall be provided to design details. Other chequer plates shall be provided to the design detailsMajor EquipmentExcavator, Dumper trucks, Compactors. Jack Hammer, Compressor, Asphalt finisher, Road RollersAttachmentNone #159

Mdpe drinking water line – ny linesTopIndexScope

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 391: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

391 of

SafetyMethod EquipmentAttachmentScopeThe statement is aimed to propose the procedures to be adopted to carry out the testing of MDPE water line – NY lineSafetyPrior to the commencement of any activity the labour force shall receive a / STARRT card / Toolbox talk. Any process involving a particular safety risk shall be assessed and adopted measures addressed to raise to a minimum standard In this case the excavation has to be carried out on the Operating Authority area, therefore all the regulated precautions shall be strictly adhered to effect ‘ full safety standard’.Safety Supervision A competent inspector shall visit the area daily to assess the safety measures adopted. Any snag observed during his visit shall be notified to the supervisor present who immediately act to bring the adopted safety measures to an acceptable standard In case of incident where utilities not identified are discovered or damaged, all work shall stop in the area and the Operator Shift Controller and HSE department immediately notifiedPhone number : Shift Controller Emergency Number HSE Direct number Employees working in easement area shall have a daily pre-task briefing that includes;Reporting of incidentsMethods of work and tools to be usedPotential hazards found in the Easement areasThe approved work method statementEPC Contractor and Civil Contractor HSE department shall participate in presenting the STARRT card briefing and monitor the activities to ensure that the work methods are being followed and all personnel have an understanding of the hazards associated with working adjacent to live process areasExcavation Work Permit- A copy of the work permit shall be posted on a mini board installed on site to be noticeable to all persons involved with the crossingBarricades, cones, markers, the night-lights, and floodlights etc. shall be installed as required for a complete safety. No oil spillage shall be allowed. Hand Excavation- Excavation to expose the services shall be carried out manually.In case certain services not shown on the record drawings such as fibre optics but it is discovered, further excavation shall be ceased until a decision is taken for the method to be adopted for further excavationAccess to trench- The workers shall clearly be instructed to use only the ladders whether to enter in or come out of the trench. No jumping shall be allowedMachine Excavation

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 392: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

392 of

The operators / drivers shall be explicitly instructed to abide by the requirement of the reverse signal and sound when operating reverse. Banksman shall be engaged equipment operation. No violation of the traffic rules shall be allowedPre cast membersSince pre cast culvert units, covers and sleepers are heavy in load, proper care has to be exercised during raising and installing / downing (handling) to the exact locations strictly adhering to the relevant safety measuresMethodPretesting PreparationIt is deemed that the line shall have been kept clean during storage and construction by keeping the open ends capped, that the hydrotest package checklist points have been verified and that the line is released for hydrotest and all safety precautions are taken. It is important that the backfill and compaction of the line is done according to the installation procedures, as this shall prevent the line from moving during pressuring as well as as providing protection against impacts, shade etc. Joints shall not be backfilled; a taped off area shall be delimited around the test pump, the diameter of this area shall be 1.5 times the length of the test pressure hose between pump and blind flange; where only designated personnel shall have access.II Hydrotest Preparation1. Any required temporary piping facilities, make up dummy spools shall be installed.2. The main blind flange shall be fitted inter alia, with a manifold on which a pressure

safety valve adjusted at 1.5 times the piping design pressure shall be connected.3. Calibrated pressure gauge ranging from 0 to 25 bar G. shall be installed on the line.

They must have valid calibration certificate.4. The pressure hose shall be connected to the blind flange manifold through a NPT

connector.5. Venting facilities: All steel blind flanges shall be provided with bleed valves. All high

points shall have a venting facility.6. The line shall be filled with water the previous day to testing to allow for thermal

stabilization over-night.7. The filling of sloped lines shall be done from the lowest point. The filling shall be done

with all vents open, vents should be closed only when clear water with no air bubbles come through the vent. Only when all vents are closed should the filling pump stopped.

8. The pressure test pump, a triplex pump model shall be started and vents reopened to ensure any remaining air in the pipe escapes. Once closed the pressure shall be taken up to the field hydrotesting pressure of 1.5 times the design pressure. During the following time periods.a. Pressure Setting Testing

5 hours for Dias up to 4”b. Main Pressure Testing

The 1.5 times maximum design pressure must be held for the following duration.3 hours for Dias up to 4”

8.1 The start time should be recorded.8.2 30 minutes stand-up for stabilisation and monitoring shall be done for every 5 bar G.Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 393: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

393 of

8.3 At 1.5 operating pressure the starting time shall be logged.8.4 The test shall be monitored during this time. The pressure & temperature shall be

monitored.9. The piping systems are designed to withstand 1.5 times the design pressure of the

pipes and fittings; in the unlikely event the pressure would rise above this point, the safety valve shall release water which shall be kept for re-pumping at the end of the test period.

10. After the holding time, if no pressure drop exceeding 0.3 bar G / 1000 m of line, hydrotest shall be considered as successfully passed.

11. The pressure may then be slowly released and the line gravity drained back.12. If the pressure abnormally drops during the testing, indicating a leak, the pumping may

be continued until the leak is detected. The leak shall then be repaired and after depressurising and draining the line and then procedures 2 to 11 shall be followed.

13. The hydrotest package shall be submitted in advance for COMPANY / EPC Contractor’s review. The required representatives shall complete and sign all paper work pertaining to the test.

NOTES:During stages 10 to 15, utmost care shall be taken to avoid damage or shock to the lines.Personal movement shall be kept to a minimumHeavy equipment circulation shall be avoided.All Mechanical Compaction shall be stopped in the vicinity.No loose rocks or bounders shall be closer that 1 (one) meter from the trench edges.All civil works shall be stopped on the line.AttachmentTest Pack format. #160

Roof & side cladding – plant areaTop IndexScopeReference documentsDefinitionsResponsibilitiesSafetyMethodEquipmentScopeThe purpose of this Method Statement is to define the sequence and methodology that shall be implemented for the installation of the Roof and Side cladding on the mentioned structures.Reference DocumentsCENTRIA Drawings – CR-56 Roofing / Single SkinDefinitionsStatements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 394: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

394 of

CM Construction Manager.CS Construction Superintendent .EF Erection Foreman.ResponsibilitiesThe CM shall plan and resource the cladding erection activities, to ensure that they are implemented according to this procedure, with the correct equipment resources.The CS shall ensure that all safety requirements are implemented and explained to the erection workforce. The CS shall control the day to day activitiesThe EF shall control the workforce ensuring the full implementation of this method statement including all safety measures.SafetyPrior to the commencement of any activity the labour force shall receive a / STARRT card / Toolbox talk. Any process involving a particular safety risk shall be assessed and adopted measures addressed to raise to a minimum standard A competent inspector shall visit the area daily to assess the safety measures adopted. Any snag observed during his visit shall be notified to the supervisor present who immediately act to bring the adopted safety measures to an acceptable standard In case of incident, all work shall stop in the area and the HSE department immediately notifiedPhone number : HSE Direct number Employees working in roof and side cladding shall have a daily pre-task briefing that includes;Reporting of incidentsMethods of work and tools to be usedPotential hazards found in the Stee StructuresThe approved work method statementEPC Contractor and Civil Contractor HSE department shall participate in presenting the STARRT card briefing and monitor the activities to ensure that the work methods are being followed and all personnel have an understanding of the hazards associated with working adjacent to live process areasMethodMATERIALS RECEIVABLESAll cladding material to be used for permanent works, shall be received on site in the appropriate laydown area. The items shall be inspected against the necessary shipping documents.All cladding shall be checked for quantity and identification.Materials shall be properly stored and protected.FASTENERS (BOLTS, NUTS & WASHERS)Upon receipt on site of the fasteners, a minimum of one sample shall be selected and tested by the independent laboratory, to confirm specification conformance.INSTALLATION OF CLADDING : Roof and Side claddingThe cladding sheets shall be installed;

1. One by one from scaffolds and working platforms.2. Install in accordance with the approved erection drawings and instructions.3. All panels shall be erected left to right unless otherwise noted.

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 395: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

395 of

4. Panel cut offs shall be made after all material is erected.5. All cutting and notching of panels around windows, doors, louvers, etc, shall be done

on site, using the right tools as listed. All edge cuts shall be coated with clear spar varnish.

6. All bevel and notch cutting of panels shall be done on site.7. All panels notched around beams and channel shall be flashed properly.

(for further details see enclosed MOS from Centria)CONSTRUCTION SEQUENCE of SIDE & ROOF SHEETINGMonitor on roof shall be sheeted first.East and West sides shall follow, then North and South sides, including flashing infills.Roof and Flashings (corner) shall be last to be installed.ERECTION of SHEETING (SIDE)Erection of side sheeting shall be lifted from ground between floor beams and side girts, since the sheets are too long to lower from roof because it is in one piece.North side scaffolding shall be installed from ground floor and regarding laydown area EPC Contractor Construction team shall provide the same. EquipmentDrilling Machines 2 Nos.Screw Guns 2 Nos.Screw Gun Sockets 2 Nos.Rivet Gun 1 No.Nibbler 1 No.Double Cut Shear 1 No.Jigsaw 1 No.Vice Grips 2 Nos.Sheet metal Snips 1 No.Extension Cords 2 x 50mDrill bits 10 Nos.AttachmentScaffolding erection of side sheet#161Ethylene exportFoundations along fence below ‘fertil over head conveyor’ for pipe rack leading to sea TopIndexScopeSafetyMethod Equipment

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Miscellaneous Tools

Page 396: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

396 of

AttachmentScopeThe objective of this statement is to outline the procedures to be adopted to carry out the construction of the proposed pipe rack foundations along the fence from near PS 2061below ‘Fertil overhead conveyor’ & up to the sea for the Ethylene export facility Reference: Pipe Supports GA & RC Details FoundationsSafetyPrior to the commencement of any activity the labour force shall receive a / STARRT card / Toolbox talk. Any process involving a particular safety risk shall be assessed and adopted measures addressed to raise to a minimum standard In this case the excavation has to be carried out on the Operating Authority area, therefore all the regulated precautions shall be strictly adhered to effect ‘ full safety standard’.Safety Supervision A competent inspector shall visit the area daily to assess the safety measures adopted. Any snag observed during his visit shall be notified to the supervisor present who immediately act to bring the adopted safety measures to an acceptable standard In case of incident where utilities not identified are discovered or damaged, all work shall stop in the area and the Operator Shift Controller and HSE department immediately notifiedPhone number : Shift Controller Emergency Number HSE Direct number Employees working in easement area shall have a daily pre-task briefing that includes;Reporting of incidentsMethods of work and tools to be usedPotential hazards found in the Easement areasThe approved work method statementEPC Contractor and Civil Contractor HSE department shall participate in presenting the STARRT card briefing and monitor the activities to ensure that the work methods are being followed and all personnel have an understanding of the hazards associated with working adjacent to live process areasExcavation Work Permit- A copy of the work permit shall be posted on a mini board installed on site to be noticeable to all persons involved with the crossingBarricades, cones, markers, the night-lights, and floodlights etc. shall be installed as required for a complete safety. Hand Excavation- Excavation to expose the services shall be carried out manually.In case certain services not shown on the record drawings such as fibre optics but it is discovered, further excavation shall be ceased until a decision is taken for the method to be adopted for further excavationAccess to trench- The workers shall clearly be instructed to use only the ladders whether to enter in or come out of the trench. No jumping shall be allowedMethodThe required permit to work shall be obtained from the Plant Refinery Division.Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 397: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

397 of

The record drawings regarding the existing services shall be obtained.ProceduresThese foundations shall be located 3m off the existing Sulphur Plant fence towards the conveyorLayout shall be made by the surveyor to the design requirementCivil Contractor QC shall inspect the layout & approveHand excavation shall be carried out to expose the cables & the other services employing seaming the area with detectors to detect the existence of cables Remaining portion of the trench shall also be excavated manually to the defined levelsAll the post excavation operations shall be carried out according to the approved procedures such as formation levels, blinding, form work, placing steel reinforcement, bolts fixing, concrete pouring, non critical cathodic protection, concrete pouring, concrete curing, concrete protection, backfilling Civil Contractor QC inspections shall be conducted to the checklists & ITP requirement from time to timeMajor EquipmentCompactors. Concrete pump, Compressor, Shovel etcAttachmentDrawing Copies

#162

Reinstatement to ‘damage caused Flare pipe rack Column member 01537’ at grid 19a Top

IndexScopeReferencesSafetyMethodEquipmentAttachmentScopeThe objective of this statement is to outline the procedures to be adopted to carry out the reinstatement to the Flare Pipe Rack structural steel column located at grid which was damaged during construction operations by Civil Contractor effecting adversely the structural adequacy of the member necessitating the replacement & till that is achieved, the formation of a temporary arrangement to bear the existing erected structures and all dead & live elements. Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 398: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

398 of

One STQ was raised by Civil Contractor for the approval pertaining to the proposed and carried out operations but EPC Contractor responded to require a proper method statementReferences: STQ Specs- for Steel structure fabrication / for Painting / for Galvanizing / Project Preservation & Export PackingSafetyPrior to the commencement of any activity the labour force shall receive a / STARRT card / Toolbox talk. Any process involving a particular safety risk shall be assessed and adopted measures addressed to raise to a minimum standard In this case the work has to be carried out on the structural steel erection involving heavy cranes and other equipment movements for which all relevant required rules shall apply Safety Supervision A competent inspector shall visit the area daily to assess the safety measures adopted. Any snag observed during his visit shall be notified to the supervisor present who immediately act to bring the adopted safety measures to an acceptable standard EPC Contractor and Civil Contractor HSE department shall participate in presenting the STARRT card briefing and monitor the activities to ensure that the work methods are being followed MethodThe reinstatement involves the following main operationsFormation of a temporary arrangementErection of the new design structural steel column at grid 19ATemporary supporting arrangement to perform to achieve & maintain the structural stability pertaining to the permanent works as effected due to column at grid 19A damage as detailed on the attached sketch has been carried out to allow the dismantling & re-erection of the concerned members involving the following sub operations.Addition of 2 #s columns 203x46mm at mid spans both adjacent baysIn turn anchorage of these columns through the top of member by Turfer to the existing column baseSupport of top bore pipe by wire sling & chain block around pipe & beam2 #s chain blocks to support top beams around pipes Chain blocks to support 2#s bottom beamsThe arrangement applies to both additional columnsThe system is stable for the purpose of transferring the induced stresses until the new design column is erected to the original locationCivil Contractor QC inspection shall be conducted to ascertain the soundness of the temporary structureSafety officer shall ascertain the freeness of arrangements of the hazardsErection of the new column ProceduresCivil Contractor QC inspections shall be conducted to the checklists & ITP requirement prior to commencing any operation

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 399: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

399 of

Column structural material shall be received from Fabricator workshop & transported for galvanisationIdentification of the delivered members shall be checkedAll the materials received shall be properly stored and protectedFoundationThe pier surface shall be properly scabbled, brushed & made suitable for the further operations. Any damaged concrete shall be repaired to the agreed proceduresCivil Contractor QC inspection shall be conducted to make sure that the prepared surface is satisfactory for the grouting and erection operationsFasteners- One sample each of the bolt, nut & washer shall be selected & tested by an independent laboratoryStainless Steel shim plates (25 mm high) shall be placed at the column centre, secured and levelled followed by the application of an approved grout material around the shims with a minimum 50mm cover to the plates to be embedded in permanentlyCivil Contractor QC inspection shall be conducted to make sure that the plates are properly located & levelled & as built survey report recordedThe columns shall be installed on the pier using a crane, levelled and plumbed anchored by stay ropes to provide the stability to the member till the horizontal members are connectedThe foundation bolts shall be hands tightened onlyNecessary tightening or torquing shall be effected post groutingExisting horizontal members & bracing interconnecting these grid frames shall be joinedThe vertical & horizontal members assembly shall be carried out in sectionsOn completion of each beam with all fastenings in place, tightening shall be carried out & final level & alignment checkedCivil Contractor QC inspection shall be conducted to comply with the ITPs & check list requirementsAfter the assembly has been released, the grouting shall be carried out to the approved proceduresWhen the new structure is reinstated to full adequacy, the temporary structural arrangement provided to withstand the forces from the unstable structure shall be removed without effecting the permanent members Major EquipmentCrane 30T / 50T, Flat bed trailer for fabricated material transpoprt, Shovel for minor steel members movement, Guide ropes & tensioning equipment, men baskets to the requirement, Scaffolding movable & stationary, Air compressor, Impact wrench, Welding generator to the requirement, Portable grinding machines, Portable drilling machinesManpowerForeman, steel erectors, Crane operator, Riggers, Unskilled workersAttachmentSTQ copy#163

Maintenance warehouse Overcoating Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 400: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

400 of

To epoxy painted surface With Mastertop top coat 44p access to corridors & walkway

TopIndexScopeReferencesSafetyMethodEquipmentAttachmentScopeThe objective of this statement is to outline the procedures to be adopted to carry out the floor surface topcoat on the epoxy painted surfaces of Corridors M16, M27 & walkwayReferences:MAR 521 for Mastertop Coat 44Submitted dated (pending approval)SafetyPrior to the commencement of any activity the labour force shall receive a / STARRT card / Toolbox talk. Any process involving a particular safety risk shall be assessed and adopted measures addressed to raise to a minimum standard Safety Supervision Measures suggested by the Manufacturer’s datasheet shall be strictly adhered to A competent inspector shall visit the area daily to assess the safety measures adopted. Any snag observed during his visit shall be notified to the supervisor present who immediately act to bring the adopted safety measures to an acceptable standard EPC Contractor and Civil Contractor HSE department shall participate in presenting the STARRT card briefing and monitor the activities to ensure that the work methods are being followed Storage- The material Mastertop TopCoat 44 shall be stored in a shed out of direct sunlightMethodSurface preparationThe existing epoxy painted surface shall be wateredAfter the surface is dry, vacuum cleaner shall be used to clear all dust & dirt etc Masking tape shall be pasted on the periphery of the proposed area to receive Yellow colour paint coatingStatements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 401: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

401 of

MixingMix ratio Component A : Component B :: 4:1 by weightComponent B shall be poured into component A & mixed manually until streak free consistency is achievedThe mixed stuff shall be poured into a container & re-mixed for 30 secondsApplicationCoverage 0.08 to 0.12 Kg / SqmThe material shall be applied to the surface using rollers & the area completed The coated surface shall be left duly protected for 24 hours so that the applied coating is completely dried & cured After 24 hours, the masking tape shall be removed & surface vacuum cleanedMasking tape shall again be applied to the periphery of the coated area to receive Black colour coatingThe Black colour coating shall then be applied to give a smooth appearanceThe surface shall then be well protected for 24 hours for drying & curing & not allowed to foot trafficCivil Contractor QC inspections shall be conducted throughout the above operationsMajor EquipmentVacuum cleaner, For mixing -clean container, rollersAttachmentMAR 521 copy#164

Roads Bituminous Concrete Surfacing

TopIndexScopeReferencesSafetyMethodEquipmentAttachmentScopeThe objective of this statement is to outline the procedures to be adopted to carry out the Roads Bituminous Surfacing by Asphalt Concreting throughout the site planned permanent roads quantifying to, Binder CourseApproximate area 130,000 m^2Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 402: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

402 of

Wearing CourseApproximate area 70,000 m^2 Including areas completed & excluding access road to HighwayReferences:Roads & Paving DetailsSpecification All Paving & Underground Services IFC drawings QCF Rev D & ITP MAR for Bitumen 60 / 70MAR 525 for Bituminous primer MC 70MAR 526 for Bituminous Tack Coat SS-1HSafetyPrior to the commencement of any activity the labour force shall receive a / STARRT card / Toolbox talk. Any process involving a particular safety risk shall be assessed and adopted measures addressed to raise to a minimum standard Safety Supervision A competent inspector shall visit the area daily to assess the safety measures adopted. Any snag observed during his visit shall be notified to the supervisor present who immediately act to bring the adopted safety measures to an acceptable standard EPC Contractor and Civil Contractor HSE department shall participate in presenting the STARRT card briefing and monitor the activities to ensure that the work methods are being followed MaterialPremixed bituminous binder course and wearing course materials shall be supplied from Civil Contractor central batching, mixing & heating plant located on Highway MethodAccording to the project drawing the asphalt concrete shall be laid in overall widths of 13m & 9m for plant & access roads respectively13m width comprises of 9m central wearing course / carriage way & 2 m wide shoulder on each side9m width comprises of 6m central carriage way & 1.5 m wide shoulder on each sideWearing course thickness being 40mm & that of dense bitumen binder course 60mmPaving works shall be carried out in 2 stagesStage 1Laying & compacting bottom bituminous binder course Everyday production 7000 m^2 of laying & rolling during day timeStage 2Laying & compacting top wearing carriagewayThis layer shall be carried out in the 4th Quarter of year 2001 at a date to be determined in co-ordination with EPC ContractorThe proposed work shall be divided into areas & carried out in sequence in both stages depending on the priority & production co-ordination as necessary to be kept in line to the proper execution of other dependent items Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 403: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

403 of

Surface preparation Prior to the application of the dense bitumen binder course, already laid & compacted aggregate base course shall be prepared suitable for this purposeBase course shall be corrected of any deviation more than 13mm from the designed profile at any point & not more than 9mm in 3m on the longitudinal grade at any location by either adding to or removing from the surface the deficient or redundant material respectively to bring the surface to the design shape, watered & compacted in accordance to the specificationMain Operations The following main operations are involvedRe-preparation of aggregate base course surface with water & compaction by pneumatic roller Application of Priming coat & drying outApplication of 60mm thick dense binder coursePower brooming the completed dense binder courseApplication of Tack coat & drying outApplication of 40mm thick bitumen concrete wearing courseMixingAll materials shall be mixed at Civil Contractor calibrated & approved Plant Asphalt plantAll trucks and other equipment as included shall be readily available for inspection TransportationMaterial shall be transported from the plant to the planned location in good condition by trucks cleaned of all foreign material & covered with tarpaulin to prevent dust invasion in inclement / adverse weather conditions It shall be ensured by obtaining observations using thermometer that the material when laid is within 130 to 165 CApplicationCoverage Primer coat 0.8 to 1.4 litre / m^2Tack coat 0.4 to 0.7 litre / m^2PrimerCivil Contractor QC inspections shall be conducted to ascertain the correct profile of the aggregate base course & corrections applied if so requiredAll surfaces planned to be primed shall be barricaded & cleaned of all dirt & any objectionable materialBituminous material shall be applied evenly on the dry surface by means of a pressure distributor spray tanker within a temperature 30 to 70 C SurfacingBinder CourseCivil Contractor QC inspection shall be conducted prior to the commencement of binder course laying to make sure that the surface is satisfactorily clean, well dried & even to the specified priming conditions & to receive binder course The material upon arrival at the location shall be spread & struck off to the prepared profile by means of self powered spreading & finishing equipment attached with a strike off assembly distributing the mixture to a strip 3 m wideRollingStatements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 404: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

404 of

Steel Roller’s # of passes 6 to 8 depending on the surface conditionSteel rollers 10 T capacity equipped with adjustable wheel scrapes, water tanks & sprinkling apparatus to keep the wheel sufficiently wet to prevent the bituminous mixture from sticking to the steel surface shall be employed to roll the profiled material immediately after the material is laid to the acceptable profile to prevent the formation of undue displacement or hair crackingThe roller wheels shall be kept properly moistened without excess water or oilRolling shall be commenced from the side and proceed towards the centre each trip overlapping the previous by at least 300 mm with keeping alternate trip not more than 5 km / h & it shall continue until the surface is impression freeMechanical compactors shall be engaged to compact the roller inaccessible area layersPneumatic tyred rollers shall be engaged only after the compaction by wheel roller is overIt is significant to make sure that the asphalt temperature does not fall below 80 C prior to full compaction is achievedRoller shall not pass over the edges of the freshly laid material generally except when the edge is located at a discontinuation for that dayCivil Contractor QC inspection shall be conducted throughout the above operations to make sure that the material is compacted to the standards and the temperature remains within limits mentioned as well as levels are maintained within specification tolerances particularly over the areas involving shouldersAt the commencement of the work on the area involving the compacted & chilled edge, a bevel shall be cut out, cleaned & tack coat applied to receive adjoining materialNo traffic shall be permitted until 24 hours lapse post rolling completionWearing CourseThe planned surface shall be cleared of all dust & dirt using power broom or blowingTack coat shall be applied to the specification requirementImmediately upon arrival the material shall be spread & rolled similarly as described in the foregoingCivil Contractor QC inspection shall be conducted throughout the above operations to make sure that the material is compacted to the standards and the temperature remains within limits mentioned as well as levels are maintained within specification tolerances Major EquipmentRequired for the binder courseCentral Mixing Asphalt plant 1#Trucks 5 #s 38 Tonnes capacity eachPaver 3 #s, 1 # with 6m wide blade & 2 #s with 4m wide bladeSteel wheel Tandem Rollers 2 #s, 1 # 10 Tonnes capacity, 1# 15 Tonnes capacityPneumatic Tired Rollers(tyre inflatable at 0.62 Mpa )4 #s, 2 #s 38 T & 2 #s 20 TAir Compressor 1 #Asphalt Cutting Machine 1#Plate Compactor 1 #Jumping Jack Compactor 1 #Spray Tanker 1 #Additionally required for the Wearing Course shall be procured laterPower BroomStatements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 405: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

405 of

Vacuum CleanerAttachmentNone

#165

RoadsBituminous Concrete Surfacing

TopIndexScopeReferencesSafetyMethodEquipmentAttachmentScopeThe objective of this statement is to outline the procedures to be adopted to carry out the Roads Bituminous Surfacing by Asphalt Concreting throughout the site planned permanent roads quantifying to, Binder CourseApproximate area 130,000 m^2Wearing CourseApproximate area 70,000 m^2 Including areas completed & excluding access road to HighwayReferences:Roads & Paving DetailsSpecification All Paving & Underground Services IFC drawings QCF Rev D & ITP SafetyPrior to the commencement of any activity the labour force shall receive a / STARRT card / Toolbox talk. Any process involving a particular safety risk shall be assessed and adopted measures addressed to raise to a minimum standard

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 406: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

406 of

Safety Supervision A competent inspector shall visit the area daily to assess the safety measures adopted. Any snag observed during his visit shall be notified to the supervisor present who immediately act to bring the adopted safety measures to an acceptable standard EPC Contractor and Civil Contractor HSE department shall participate in presenting the STARRT card briefing and monitor the activities to ensure that the work methods are being followed MaterialPremixed bituminous binder course and wearing course materials shall be supplied from Civil Contractor central batching, mixing & heating plant located on Highway MethodAccording to the project drawing the asphalt concrete shall be laid in overall widths of 13m & 9m for plant & access roads respectively13m width comprises of 9m central wearing course / carriage way & 2 m wide shoulder on each side9m width comprises of 6m central carriage way & 1.5 m wide shoulder on each sideWearing course thickness being 40mm & that of dense bitumen binder course 60mmPaving works shall be carried out in 2 stagesStage 1Laying & compacting bottom bituminous binder course Everyday production 7000 m^2 of laying & rolling during day timeStage 2Laying & compacting top wearing carriagewayThis layer shall be carried out during November / December 2001The proposed work shall be divided into areas & carried out in sequence in both stages depending on the priority & production co-ordination as necessary to be kept in line to the proper execution of other dependent items Surface preparation Prior to the application of the dense bitumen binder course, already laid & compacted aggregate base course shall be prepared suitable for this purposeBase course shall be corrected of any deviation more than 13mm from the designed profile at any point & not more than 9mm in 3m on the longitudinal grade at any location by either adding to or removing from the surface the deficient or redundant material respectively to bring the surface to the design shape, watered & compacted in accordance to the specificationMain Operations The following main operations are involvedRe-preparation of aggregate base course surface with water & compaction by pneumatic roller Application of Priming coat & drying outApplication of 60mm thick dense binder coursePower brooming the completed dense binder courseApplication of Tack coat & drying outApplication of 40mm thick bitumen concrete wearing courseMixingAll materials shall be mixed at Civil Contractor calibrated & approved Plant Asphalt plantStatements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 407: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

407 of

All trucks and other equipment as included shall be readily available for inspection TransportationMaterial shall be transported from the plant to the planned location in good condition by trucks cleaned of all foreign material & covered with tarpaulin to prevent dust invasion in inclement / adverse weather conditions It shall be ensured by obtaining observations using thermometer that the material when laid is within 130 to 165 CApplicationCoverage Primer coat 0.8 to 1.4 litre / m^2Tack coat 0.4 to 0.7 litre / m^2PrimerCivil Contractor QC inspections shall be conducted to ascertain the correct profile of the aggregate base course & corrections applied if so requiredAll surfaces planned to be primed shall be barricaded & cleaned of all dirt & any objectionable materialBituminous material shall be applied evenly on the dry surface by means of a pressure distributor spray tanker within a temperature 30 to 70 C SurfacingBinder CourseCivil Contractor QC inspection shall be conducted prior to the commencement of binder course laying to make sure that the surface is satisfactorily clean, well dried & even to the specified priming conditions & to receive binder course The material upon arrival at the location shall be spread & struck off to the prepared profile by means of self powered spreading & finishing equipment attached with a strike off assembly distributing the mixture to a strip 3 m wideRollingSteel Roller’s # of passes 6 to 8 depending on the surface conditionSteel rollers 10 T capacity equipped with adjustable wheel scrapes, water tanks & sprinkling apparatus to keep the wheel sufficiently wet to prevent the bituminous mixture from sticking to the steel surface shall be employed to roll the profiled material immediately after the material is laid to the acceptable profile to prevent the formation of undue displacement or hair crackingThe roller wheels shall be kept properly moistened without excess water or oilRolling shall be commenced from the side and proceed towards the centre each trip overlapping the previous by at least 300 mm with keeping alternate trip not more than 5 km / h & it shall continue until the surface is impression freeMechanical compactors shall be engaged to compact the roller inaccessible area layersPneumatic tyred rollers shall be engaged only after the compaction by wheel roller is overIt is significant to make sure that the asphalt temperature does not fall below 80 C prior to full compaction is achievedRoller shall not pass over the edges of the freshly laid material generally except when the edge is located at a discontinuation for that dayCivil Contractor QC inspection shall be conducted throughout the above operations to make sure that the material is compacted to the standards and the temperature remains within limits Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 408: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

408 of

mentioned as well as levels are maintained within specification tolerances particularly over the areas involving shouldersAt the commencement of the work on the area involving the compacted & chilled edge, a bevel shall be cut out, cleaned & tack coat applied to receive adjoining materialNo traffic shall be permitted until 12 hours lapse post rolling completionWearing CourseThe planned surface shall be cleared of all dust & dirt using power broom or blowingTack coat shall be applied to the specification requirementImmediately upon arrival the material shall be spread & rolled similarly as described in the foregoingCivil Contractor QC inspection shall be conducted throughout the above operations to make sure that the material is compacted to the standards and the temperature remains within limits mentioned as well as levels are maintained within specification tolerances Major EquipmentRequired for the binder courseCentral Mixing Asphalt plant 1#Trucks 5 #s 38 Tonnes capacity eachPaver 3 #s, 1 # with 6m wide blade & 2 #s with 4m wide bladeSteel wheel Tandem Rollers 2 #s, 1 # 10 Tonnes capacity, 1# 15 Tonnes capacityPneumatic Tired Rollers(tyre inflatable at 0.62 Mpa )4 #s, 2 #s 38 T & 2 #s 20 TAir Compressor 1 #Asphalt Cutting Machine 1#Plate Compactor 1 #Jumping Jack Compactor 1 #Spray Tanker 1 #Additionally required for the Wearing Course shall be procured laterPower BroomVacuum CleanerAttachmentNone#166

Excavation for 200 pair Telecom Route(Direct Buried) parallel to Avenue D & 3rd street TopIndexScopeSafetyMethod EquipmentAttachmentStatements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 409: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

409 of

ScopeThis statement aims to propose the procedures to be adopted to carry out the excavation on the telecom route from N SafetyPrior to the commencement of any activity the labour force shall receive a / STARRT card / Toolbox talk. Any process involving a particular safety risk shall be assessed and adopted measures addressed to raise to a minimum standard In this case the excavation has to be carried out on the Operating Authority area, therefore all the regulated precautions shall be strictly adhered to effect ‘ full safety standard’.Safety Supervision A competent inspector shall visit the area daily to assess the safety measures adopted. Any snag observed during his visit shall be notified to the supervisor present who immediately act to bring the adopted safety measures to an acceptable standard In case of incident where utilities not identified are discovered or damaged, all work shall stop in the area and the Operator Shift Controller and HSE department immediately notifiedPhone references : Shift Controller Emergency Number HSE Direct number Employees working in easement area shall have a daily pre-task briefing that includes;Reporting of incidentsMethods of work and tools to be usedPotential hazards found in the Easement areasThe approved work method statementEPC Contractor and Civil Contractor HSE department shall participate in presenting the STARRT card briefing and monitor the activities to ensure that the work methods are being followed and all personnel have an understanding of the hazards associated with working adjacent to live process areasExcavation Work Permit- A copy of the work permit shall be posted on a mini board installed on site to be noticeable to all persons involved Barricades cones, markers, the night-lights, and floodlights etc. shall be installed as required for a complete safety. Hand Excavation- Excavation to expose the services shall be carried out manually.In case certain services not shown on the record drawings such as fibre optics but it is discovered, further excavation shall be ceased until a decision is taken for the method to be adopted for further excavationAccess to trench- The workers shall clearly be instructed to use only the ladders whether to enter in or come out of the trench. No jumping shall be allowedMachine ExcavationThe operators / drivers shall be explicitly instructed to abide by the requirement of the reverse signal and sound when operating reverse. Banksman shall be engaged equipment operation. No violation of the traffic rules shall be allowed

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 410: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

410 of

MethodThe required permit to work shall be obtained from the Plant Refinery Division.The record drawings regarding the existing services shall be obtained.Drawing reference –ProceduresThe record drawing pertaining to the existing services shall be obtained from the RRD The following main operations are involvedSetting out the proposed route in all respects from point marked #1 to #3Civil Contractor QC inspection shall be carried out to approve the layoutTrial pits shall be excavated manually to the dimensions 3mx2m in plus shape 1m wide & about 1 M deep @ 50 m intervals to expose the cables & the other services employing seaming the area with detectors to detect the existence of cables After the exposure, all the existing cables shall be covered with split PVC pipe and well supported temporarily to continue the excavation mechanically Remaining portion of the trench between the pits shall be excavated 500mm wide & 1000 mm deep by machine to the defined levels Civil Contractor QC inspection shall be carried out to approve the excavated profileA layer of sand bedding shall be filled to receive 200 pair telecom cables EPC Contractor shall lay the cable on the complete prepared routeAfter the release of the cable laying, sand shall be filled on the sides and as well as 100mm thick over the cablesCable tiles shall be laid en route according to the standard detailsA layer of gatch fill 250mm thick shall be laid over the cable tiles & warning tape providedOver gatch fill up to the finished grade level, backfill shall be carried out to the approved proceduresMajor EquipmentExcavator, Dumper trucks, Compactors AttachmentRoute sketch #167

Hand Excavation for 200 pair Telecom Route(Direct Buried) parallel to Avenue CTopIndexScopeSafetyMethod EquipmentAttachment

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 411: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

411 of

ScopeThis statement aims to propose the procedures to be adopted to carry out the excavation on the telecom route from existing 500mm sleeve at N under road Avenue C & passing to existing Telecom Centre from N to N at E SafetyPrior to the commencement of any activity the labour force shall receive a / STARRT card / Toolbox talk. Any process involving a particular safety risk shall be assessed and adopted measures addressed to raise to a minimum standard In this case the excavation has to be carried out on the Operating Authority area, therefore all the regulated precautions shall be strictly adhered to effect ‘ full safety standard’.Safety Supervision A competent inspector shall visit the area daily to assess the safety measures adopted. Any snag observed during his visit shall be notified to the supervisor present who immediately act to bring the adopted safety measures to an acceptable standard In case of incident where utilities not identified are discovered or damaged, all work shall stop in the area and the Operator Shift Controller and HSE department immediately notifiedPhone references : Shift Controller Emergency Number HSE Direct number Employees working in easement area shall have a daily pre-task briefing that includes;Reporting of incidentsMethods of work and tools to be usedPotential hazards found in the Easement areasThe approved work method statementEPC Contractor and Civil Contractor HSE department shall participate in presenting the STARRT card briefing and monitor the activities to ensure that the work methods are being followed and all personnel have an understanding of the hazards associated with working adjacent to live process areasExcavation Work Permit- A copy of the work permit shall be posted on a mini board installed on site to be noticeable to all persons involved Barricades cones, markers, the night-lights, and floodlights etc. shall be installed as required for a complete safety. Hand Excavation- Excavation to expose the services shall be carried out manually.In case certain services not shown on the record drawings such as fibre optics but it is discovered, further excavation shall be ceased until a decision is taken for the method to be adopted for further excavationAccess to trench- The workers shall clearly be instructed to use only the ladders whether to enter in or come out of the trench. No jumping shall be allowedMethodThe required permit to work shall be obtained from the Plant Refinery Division.The record drawings regarding the existing services shall be obtained.Drawing reference –Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 412: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

412 of

ProceduresThe record drawing pertaining to the existing services shall be obtained from the RRD The following main operations are involvedSetting out the proposed route in all respects Civil Contractor QC inspection shall be carried out to approve the layoutDuring manual excavation the exposed existing cables shall be properly protected and well supported temporarily Trench shall be excavated 500mm wide & 1000 mm deep manually to the defined levels Civil Contractor QC inspection shall be carried out to approve the excavated profileA layer of sand bedding shall be filled to receive 200 pair telecom cables EPC Contractor shall lay the cable on the complete prepared routeAfter the release of the cable laying, sand shall be filled on the sides as well as 100mm thick over the cablesCable tiles shall be laid en route according to the standard detailsA layer of gatch fill 250mm thick shall be laid over the cable tiles & warning tape providedOver gatch fill up to the finished grade level, backfill shall be carried out to the approved proceduresMajor EquipmentCompactors. Compressor AttachmentRoute sketch #168

200 pair Telecom Road Crossingat Avenue D / 3rd Street Intersectionalong E Top IndexScopeSafetyMethod EquipmentAttachmentScope This statement aims to propose the procedures to be adopted to carry out 2# 160 mm ducts laying work for the telecom route to cross at E near Avenue D / 3rd street intersectionDrawing reference –SafetyPrior to the commencement of any activity the labour force shall receive a / STARRT card / Toolbox talk. Any process involving a particular safety risk shall be assessed and adopted measures addressed to raise to a minimum standard

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 413: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

413 of

In this case the excavation has to be carried out on the Operating Authority area, therefore all the regulated precautions shall be strictly adhered to effect ‘ full safety standard’.Safety Supervision A competent inspector shall visit the area daily to assess the safety measures adopted. Any snag observed during his visit shall be notified to the supervisor present who immediately act to bring the adopted safety measures to an acceptable standard In case of incident where utilities not identified are discovered or damaged, all work shall stop in the area and the Operator Shift Controller and HSE department immediately notifiedPhone references : Shift Controller Emergency Number HSE Direct number Employees working in easement area shall have a daily pre-task briefing that includes;Reporting of incidentsMethods of work and tools to be usedPotential hazards found in the Easement areasThe approved work method statementEPC Contractor and Civil Contractor HSE department shall participate in presenting the STARRT card briefing and monitor the activities to ensure that the work methods are being followed and all personnel have an understanding of the hazards associated with working adjacent to live process areasExcavation Work Permit- A copy of the work permit shall be posted on a mini board installed on site to be noticeable to all persons involved Barricades cones, markers, the night-lights, and floodlights etc. shall be installed as required for a complete safety. Hand Excavation- Excavation to expose the services shall be carried out manually.In case certain services not shown on the record drawings such as fibre optics but it is discovered, further excavation shall be ceased until a decision is taken for the method to be adopted for further excavationAccess to trench- The workers shall clearly be instructed to use only the ladders whether to enter in or come out of the trench. No jumping shall be allowedMachine ExcavationThe operators / drivers shall be explicitly instructed to abide by the requirement of the reverse signal and sound when operating reverse. Banksman shall be engaged on for guiding equipment operation. No violation of the traffic rules shall be allowedMethodThe required permit to work shall be obtained from the Plant Refinery Division.The record drawings regarding the existing services shall be obtained.ProceduresThe record drawing pertaining to the existing services shall be obtained from the RRD The following main operations are involvedProduction of the approved Traffic diversion schemeSetting out the proposed route in all respects Manual & mechanical excavation followed by duct layingStatements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 414: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

414 of

Concrete surround & gatch fillCivil Contractor QC inspection shall be carried out to approve the layoutDuring manual excavation the exposed existing cables shall be properly protected and well supported temporarily Trial pit shall be excavated manually to the dimensions 3mx2m in plus shape 1m wide & about 1 M deep to expose the cables & any other services employing seaming the area with detectors to detect the existence of cables After the exposure, all the existing cables shall be covered with split PVC pipe and well supported temporarily to continue the excavation mechanically Remaining portion of the trench shall be excavated 500mm wide & 1000 mm plus deep by machine to the defined levels Civil Contractor QC inspection shall be conducted to approve the excavated profile2 # 160mm ducts shall be laid in position to be surrounded with concreteAfter the approval, concrete shall be poured on the sides as well as 100mm thick over the ducts Gatchfill in 250mm thick layers shall be carried out up to the finished grade level to the approved proceduresTraffic management scheme shall be removed after the backfill is completedMajor EquipmentExcavator, Truck, Compactors. Compressor AttachmentTraffic Management Scheme, Route sketch #169

Manual Excavation200 pair Telecom Road Crossing @ Access road to --------camp @ C / L, co-ordinate N / avenue CTopIndexScopeSafetyMethod EquipmentAttachmentScope This statement aims to propose the procedures to be adopted to carry out 2# 160 mm ducts laying work for the telecom route to cross at N @ Avenue C / Police check post intersectionDrawing reference –SafetyStatements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 415: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

415 of

Prior to the commencement of any activity the labour force shall receive a / STARRT card / Toolbox talk. Any process involving a particular safety risk shall be assessed and adopted measures addressed to raise to a minimum standard In this case the excavation has to be carried out on the Operating Authority area, therefore all the regulated precautions shall be strictly adhered to effect ‘ full safety standard’.Safety Supervision A competent inspector shall visit the area daily to assess the safety measures adopted. Any snag observed during his visit shall be notified to the supervisor present who immediately act to bring the adopted safety measures to an acceptable standard In case of incident where utilities not identified are discovered or damaged, all work shall stop in the area and the Operator Shift Controller and HSE department immediately notifiedPhone references : Shift Controller Emergency Number HSE Direct number Employees working in easement area shall have a daily pre-task briefing that includes;Reporting of incidentsMethods of work and tools to be usedPotential hazards found in the Easement areasThe approved work method statementEPC Contractor and Civil Contractor HSE department shall participate in presenting the STARRT card briefing and monitor the activities to ensure that the work methods are being followed and all personnel have an understanding of the hazards associated with working adjacent to live process areasExcavation Work Permit- A copy of the work permit shall be posted on a mini board installed on site to be noticeable to all persons involved Barricades cones, markers, the night-lights, and floodlights etc. shall be installed as required for a complete safety. Access to trench- The workers shall clearly be instructed to use only the ladders whether to enter in or come out of the trench. No jumping shall be allowedMethodThe required permit to work shall be obtained from the Plant Refinery Division.The record drawings regarding the existing services shall be obtained.ProceduresThe record drawing pertaining to the existing services shall be obtained from the RRD The following main operations are involvedProduction of the approved Traffic diversion scheme -sketch attached for diversionSetting out the proposed route in all respects Manual excavation followed by duct layingConcrete surround & gatch fillCivil Contractor QC inspection shall be carried out to approve the layoutAfter the exposure, all the existing cables shall be covered with split PVC pipe and well supported temporarily to continue the excavation to the defined levelsCivil Contractor QC inspection shall be conducted to approve the excavatedprofileStatements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 416: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

416 of

2 # 160mm ducts shall be laid in position to be surrounded with concreteAfter the approval, concrete shall be poured on the sides as well as 100mm thick over the ducts Gatchfill in 250mm thick layers shall be carried out up to the finished grade level to the approved proceduresCivil Contractor QC inspection shall be conducted throughout the above operations Traffic management scheme shall be removed after the backfill is completedMajor EquipmentCompactor, compressor AttachmentTraffic Management Scheme, Route sketch #170Manual Excavation200 pair Telecom Road Crossing@ Access road to Operating Authority camp @ C / L, co-ordinate N / avenue CTop

IndexScopeSafetyMethod EquipmentAttachmentScope This statement aims to propose the procedures to be adopted to carry out 2# 160 mm ducts laying work for the telecom route to cross at N @ Avenue C / between 5 th & 3rd street / Police check post intersectionDrawing reference –SafetyPrior to the commencement of any activity the labour force shall receive a / STARRT card / Toolbox talk. Any process involving a particular safety risk shall be assessed and adopted measures addressed to raise to a minimum standard In this case the excavation has to be carried out on the Operating Authority area, therefore all the regulated precautions shall be strictly adhered to effect ‘ full safety standard’.

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 417: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

417 of

Safety Supervision A competent inspector shall visit the area daily to assess the safety measures adopted. Any snag observed during his visit shall be notified to the supervisor present who immediately act to bring the adopted safety measures to an acceptable standard In case of incident where utilities not identified are discovered or damaged, all work shall stop in the area and the Operator Shift Controller and HSE department immediately notifiedPhone references : Shift Controller Emergency Number HSE Direct number Employees working in easement area shall have a daily pre-task briefing that includes;Reporting of incidentsMethods of work and tools to be usedPotential hazards found in the Easement areasThe approved work method statementEPC Contractor and Civil Contractor HSE department shall participate in presenting the STARRT card briefing and monitor the activities to ensure that the work methods are being followed and all personnel have an understanding of the hazards associated with working adjacent to live process areas

Excavation Work Permit- A copy of the work permit shall be posted on a mini board installed on site to be noticeable to all persons involved Barricades cones, markers, the night-lights, and floodlights etc. shall be installed as required for a complete safety. Access to trench- The workers shall clearly be instructed to use only the ladders whether to enter in or come out of the trench. No jumping shall be allowedMethodThe required permit to work shall be obtained from the Plant Refinery Division.The record drawings regarding the existing services shall be obtained.ProceduresThe record drawing pertaining to the existing services shall be obtained from the RRD The following main operations are involvedProduction of the approved Traffic diversion scheme-sketch attached for diversionSetting out the proposed route in all respects Manual excavation followed by duct layingConcrete surround & gatch fillCivil Contractor QC inspection shall be carried out to approve the layoutAfter the exposure, all the existing cables shall be covered with split PVC pipe and well supported temporarily to continue the excavation to the defined levelsCivil Contractor QC inspection shall be conducted to approve the excavated profile2 # 160mm ducts shall be laid in position to be surrounded with concreteAfter the approval, concrete shall be poured on the sides as well as 100mm thick over the ducts

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 418: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

418 of

Gatchfill in 250mm thick layers shall be carried out up to the finished grade level to the approved proceduresCivil Contractor QC inspection shall be conducted throughout the above operations Traffic management scheme shall be removed after the backfill is completedMajor EquipmentCompactor, compressor AttachmentTraffic Management Scheme, Route sketch #171

Removal of contaminated soilTopIndexScopeReference documentsDefinitionsResponsibilitiesSafetyMethodEquipmentAttachmentScopeThe purpose of this method statement, is to define the procedure that shall be adopted for the removal and disposal of the material within the “Hazardous Material” location.Reference documentsEPC Contractor HSE Manual.Operating Authority Regulations.Method Statement. Removal of Hazardous Materials.ACES Laboratory Report reference dated DefinitionsEPC Contractor Civil Contractor . PSM Project Site Manager.ACES Arab Center For Engineering Studies.ResponsibilitiesThe PSM shall ensure that the required safety and enviromental precautions are implemented for this activity. The Civil Contractor safety officer shall implement these requirements.The PSM shall record and document the disposal process.SafetyThe Safety Officer shall monitor and implement all HSE and environmental precautions.Method

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 419: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

419 of

The area identified and tested for “Hazardous materials”, shall be disposed, in acccordance with all relevant rules and regulations.

The identified contaminated soil shall be removed from the “Hazardous Material” area by excavator into the dump trucks.The dump truck shall be loaded carefully so that contaminated soil does not spill from the dumptruck whilst on route to the disposal area. A temporary stockpile area shall be designated whilst the permanent disposal location is agreed.The stockpile area shall be clearly identified. Barrier tape shall define the limits.As the material is stable and inert, no special precautions are required for stockpiling conditions.A visual inspection of the excavated area, to establish the removal of all the contaminated soil, shall be conducted. The contaminated soil is dark black in color. Samples of resultant exposed material shall be taken for analysis. EquipmentMembrane.Membrane accessoriesPrimer and brush.AttachmentITP No: #172

Blinding concrete Top IndexScopeReference documentsDefinitionsResponsibilitiesSafetyMethodEquipmentAttachment

ScopeThe purpose of this method statement, is to define the procedure that shall be adopted for the preparation and placement of blinding concrete, prior to subsequent activities.Reference documentsMethod statement. Concrete placement.Specification Concrete Construction, Formwork and Coatings.Specification. Concrete Mix Design.DefinitionsEPC ContractorStatements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 420: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

420 of

Civil Contractor PSM Project Site Manager.ResponsibilitiesThe PSM shall ensure that the relevant site supervision are aware of and understand the requirements of this method statement.The relevant foremen shall ensure that the blinding activities are conducted in accordance with this method statement.SafetyThe Safety Officer shall monitor and implement all HSE and environmental precautions.All persons who shall be involved in this activity, shall be made aware of all safety issues relating to this activity and situation.MethodThe Foreman shall ensure that the formation level has been inspected, tested and approved, prior to the supervisor commencing any blinding activity.The surveyor shall set out the relevant line and level information, in such a manner that the Foreman can relate the data to the tradesmen.The tradesman shall erect suitable battens and rails, to the correct outside lines and finished level of the blinding concrete. Where intermediate level rails are required, these shall be installed such that removal of them as concrete is progressed, can be achieved easily and quickly.When the blinding battens and rails are completed, the supervisor shall conduct line and level checks with the surveyor.Polythene sheeting shall be placed between the blinding battens. Adequate overlapping of the polythene sheeting shall be done where joints occur.The supervisor shall complete form QCF, Blinding Check list, prior to notifying the QC inspector.The QC inspector shall check the element for compliance with the check list. When the QC inspector countersign the check list, blinding concrete can be ordered and placed according to the relevant procedures.The blinding concrete shall be placed by one of the approved methods. (direct pour, skip or pump) The blinding concrete shall be finished to a smooth finish. The avoidance of ripples or protrusions must be avoided, as the application of the protective membrane requires a smooth finish.The blinding concrete, when sufficiently set, shall be covered with hessian and water cured for 3 days. EquipmentHand tools.AttachmentITP No:.QCF, Blinding Check List. #173

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 421: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

421 of

Reinforcement receival & fabricationTopIndexScopeReference documentsDefinitionsResponsibilitiesSafetyMethodEquipmentAttachmentScopeThe purpose of this method statement, is to define the procedure that shall be adopted for the material receipt, fabrication and storage of reinforcement.Reference documentsSpecification. Concrete Construction, Formwork and Coatings.DefinitionsEPC ContractorCivil Contractor . PSM Project Site Manager.ResponsibilitiesThe PSM shall ensure that the reinforcement fabrication department is aware of and understand the requirements of this method statement. The store department shall be aware of the quality documentation requirements for reinforcement.SafetyThe Safety Officer shall monitor and implement all HSE and environmental precautions.All persons who shall be involved in this activity, shall be made aware of all safety issues relating to this activity and situation.MethodThe storeman shall ensure that any reinforcement materials received upon site is in accordance with the specification requirements, purchase order and quality documentation requirements. The storeman shall inform the QA department when a delivery of reinforcement is made.The storeman and QC inspector shall review the reinforcement delivery and complete the Material receiving report QCF. The quality documentation shall be kept by the QC department.When the incoming material inspection is completed and acceptable, the reinforcement material shall be stored in the reinforcement fabrication yard, in the appropriate storage facilities.When reinforcement is to be “cut and bent,” the yard Foreman shall be issued with a current rebar schedule. The yard Foreman shall review the schedule and allocate the fabrication

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 422: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

422 of

process to the relevant operator. Material required shall be sourced from the yard storage facilities.The correct bar diameter shall be cropped into the specified length as given on the bar schedule. The cropper operator shall crop the required bars of each diameter.Upon bending of the first of each bar type, it shall be checked by the yard Foreman for correctness. This bar, if correct shall be utilized as a check bar for all concurrent bars of that type. The bending operator shall fabricate the required number of bars of each shape code, checking against the check bars as he completes each bar. Any error in bending of the bars shall be corrected prior to placement in storageThe correct bent bars shall be stored in bundles.The bundles shall be tagged with a suitable label, that indicate the relevant bar no and schedule number from which they have been fabricated.The completed bundles shall be stored within the reinforcement yard, until such time as they are required upon site. Storage shall be in accordance with the procedure for store control.EquipmentBar cropping machines.Bar bending machines.Fork lift truck.AttachmentITP No: QCF, Material Receiving Report.QCF, Reinforcement Fabrication Check List.#174

Reinforcement placementTopIndexScopeReference documentsDefinitionsResponsibilitiesSafetyMethodEquipmentAttachmentScopeThe purpose of this method statement, is to define the procedure that shall be adopted for the placement of reinforcement.Reference documentsSpecification. Concrete Construction, Formwork and Coatings.DefinitionsEPC ContractorCivil Contractor Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 423: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

423 of

PSM Project Site Manager.ResponsibilitiesThe PSM shall ensure that the reinforcement Foreman, is aware of and understands the requirements of this method statement. The reinforcement Foreman shall ensure that this method statement is understood by his steel fixers.SafetyThe Safety Officer shall monitor and implement all HSE and environmental precautions.All persons who shall be involved in this activity, shall be made aware of all safety issues relating to this activity and situation.MethodThe relevant reinforcement bars, spacer blocks, chairs, stirrups and tie wire, shall be collected from the stores and made available at the work site. The material shall be stored at the worksite, in accordance with the storage procedure.The current revision of the reinforcement drawing, that applies to the structure being constructed, shall be checked by the Foreman for validity.The steel fixers shall place and tie, reinforcement bars and accessories, in accordance with the current reinforcement drawing.Particular attention to the following items shall be monitored by the chargehand steel fixer and Foreman:lap length of bars.tie wire protrusions into cover areas.Concrete cover to formwork and outside faces.Placement of adequate support chairs and stirrups.Spacing of bars.The chargehand steelfixer shall inspect and check the fabricated reinforcement when all the placement of the reinforcement bars are complete. The result of this inspection shall be recorded upon form QCF, Pre concrete inspection.The Foreman steelfixer shall ensure that the reinforcement has been checked, prior to informing the QC inspector.Should any inserts, conduits, pipes, bolts etc, require fixing within the structure, the steel fixer shall assist with the placement of these items. Where a reinforcement bar clashes with such items, the steel fixer shall move the relevant bar. An additional bar may be required to offset this moved bar. Should any doubt arise about moving bars, the chargehand shall inform the Foreman to resolve the issue with the engineers.The requirement for installing the cathodic protection system to the reinforcement bars, shall be conducted. The Foreman shall inform the engineer when these activities are complete.The QC inspector shall inspect the structure for compliance with the reinforcement drawings and layout drawings.The QC inspector shall only allow the next activity to commence, when all issues are acceptable. The QC inspector shall endorse form QCF when acceptable.EquipmentHand tools.

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 424: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

424 of

AttachmentQCF, Pre Concrete Inspection form.#175

Formwork erectionTopIndexScopeReference documentsDefinitionsResponsibilitiesSafetyMethodEquipmentAttachmentScopeThe purpose of this method statement, is to define the procedure that shall be adopted for the erection of formwork.Reference documentsSpecification. Concrete Construction, Formwork and Coatings.DefinitionsEPC ContractorCivil Contractor PSM Project Site Manager.ResponsibilitiesThe PSM shall ensure that the formwork department is aware of and understand the requirements of this method statement. The formwork Foreman shall ensure that his tradesmen understand this method statement.SafetyThe Safety Officer shall monitor and implement all HSE and environmental precautions.All persons who shall be involved in this activity, shall be made aware of all safety issues relating to this activity and situation.MethodThe formwork Foreman shall review the drawing of the structure to be formed. He shall decide along with the engineer, the most suitable method of formwork erection.Where pre-fabricated formwork can be assembled in the formwork workshop, this shall be conducted. The surveyor shall establish the lines and levels for the erection of the formwork. These lines and levels shall be explained to the Foreman and supervisor in charge of the formwork activity.The Foreman shall check that the preceding activities have been approved, so that this activity may commence. The sections of formwork required to form the structure, shall be taken to the work site.

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 425: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

425 of

The tradesmen shall ensure that the formwork faces are clean, in good condition for the type of finish required, with shutter form oil applied as applicable.The tradesmen shall assemble and fix the formwork, in accordance with the current drawing.The chargehand carpenter shall monitor particular issues such as:Sealing of joints between formwork.Plumbness and verticality of formwork.Adequate bracing and supports.Provision where applicable for boxouts and inserts.Provision where applicable of chamfer and channels.The supervisor and surveyor shall check the lines and levels of the formwork when all bracing and strutting is completed. Where required, the formwork shall be adjusted to conform with the required lines and levels.The supervisor shall ensure that any damaged face of the formwork is repaired.The Foreman shall review the formwork when completed.Where anchor bolts or embedded plates are to be suspended in the structure, the supervisor shall ensure that these arrangements are securely braced. All embeddments and bolt groupings shall be checked for location and level prior to the placement of concrete as well as after the concrete is placed.When the formwork activity is complete, the supervisor shall inspect the formwork and associated works, recording his observations on form QCF, formwork check list and QCF, embeddment check list.The QC inspector shall confirm the acceptance of this activity after review of the items.Where large formwork elements are encountered, the QC inspector shall review the formwork bracing’s and supports with the engineer.EquipmentHand tools.Formwork.AttachmentITP No: QCF, Formwork check list.QCF, Embeddment check list.#176

Concrete to paved areasTopIndexScopeReference documentsDefinitionsResponsibilitiesSafetyMethodEquipmentStatements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 426: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

426 of

AttachmentScopeThe purpose of this method statement, is to define the procedure that shall be adopted for the placing of concrete to paved areas.Reference documentsSpecification. Concrete Construction, Formwork and Coatings.DefinitionsEPC ContractorCivil Contractor PSM Project Site Manager.ResponsibilitiesThe PSM shall ensure that the relevant department is aware of and understand the requirements of this method statement. The concrete Foreman shall ensure that his concrete crew understand this method statement.SafetyThe Safety Officer shall monitor and implement all HSE and environmental precautions.All persons who shall be involved in this activity, shall be made aware of all safety issues relating to this activity and situation.MethodThe concrete Foreman shall check to establish that the concerned paving areas are approved for placement of concrete.The concrete forman shall arrange for the equipment he requires to place the concrete is available at the work site.Provision shall be made for emergency stop ends in case of batchplant or equipment failure.The concrete Foreman shall order the required concrete, advising the batchplant of the schedule and type of concrete. Note: Fibre concrete.The concrete shall be tested by the laboratory technician upon arrival at site.Placement of the fibre concrete shall be by one of the approved methods.The sequence of placement for the fibre concrete shall be agreed with the EPC Contractor engineer.Consolidation of the fresh concrete shall be conducted under the supervision of the concrete Foreman.The finish required to the paved areas shall be as defined and presented on a test panel. The relevant finish shall be applied to the paved area. Attention to edges and finish shall be an important responsibility of the concrete Foreman and chargehand.Curing of the fibre concrete shall be in accordance with the method statement for curing concrete.EquipmentConcrete truck mixer.Concrete pump.Concrete skip.Compressor.Vibrators.Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 427: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

427 of

AttachmentITP No: #177

Excavation & backfill to structuresTopIndexScopeReference documentsDefinitionsResponsibilitiesSafetyMethodEquipmentAttachmentScopeThe purpose of this method statement, is to define the procedure that shall be adopted for the excavation and backfilling to structures.Reference documentsSpecification. Excavation and Backfill for underground Installations.DefinitionsEPC ContractorCivil Contractor PSM Project Site Manager.ResponsibilitiesThe PSM shall ensure that the relevant department is aware of and understand the requirements of this method statement. The excavation Foreman shall ensure that his excavation crew understand this method statement.SafetyThe Safety Officer shall monitor and implement all HSE and environmental precautions.All persons who shall be involved in this activity, shall be made aware of all safety issues relating to this activity and situation.MethodExcavation.The engineer shall ensure that the current drawings relating to the excavation activity, are approved for construction. The engineer shall ensure that there are no conflicts with existing services or other discipline issues.The surveyor shall provide line and level engineering that shall enable the excavation of the structure. A system for quick reference shall be established.The surveyor shall inform the excavation Foreman of these lines and levels.The excavation Foreman shall direct the excavation equipment in an agreed sequence. Excavated material shall be classified by laboratory test. Unsuitable material shall be removed

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 428: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

428 of

off site to the tip area. Where material is classified as suitable, the required volume shall be stockpiled on site in an agreed location.Safety barriers shall be erected as the work proceeds.Where applicable, the sides of the excavation shall be sloped.There is no requirement for ground de-watering equipment.Should restrictions be imposed by adjacent structures etc, that would make sloping of the sides un practical, shoring or support of the excavation side walls shall be agreed with EPC Contractor on site.The surveyor and site engineer shall check the excavation, to confirm compliance with his levels and lines. A survey shall be conducted of formation level upon completion of the excavation.The formation shall be visually inspected for unsuitable material. Any such material shall be removed.The formation shall be scarified and compacted to the required specification criteria. The laboratory test results shall be provided. Upon acceptance of these results, the area shall be released for consequent activities.Backfill.The engineer shall ensure that all subsequent activities are passed and completed.Upon approval to backfill, the engineer shall instruct the Foreman to conduct this activity.The backfill material shall be sourced from the suitable material stockpile. The backfill material shall be placed in layers according to the specification. The layer shall be moisturized and compacted to the agreed criteria.Each backfill layer shall be tested by the test laboratory. An acceptable test result shall allow the next layer of backfill to be placed and compacted. This process shall continue until the structure is completed.Upon completion of the backfill activity, the area shall be cleaned of waste materials and left tidy for the next activity. Any safety barriers shall be removed to the safety store.EquipmentExcavator.Dumptruck.Compactors.AttachmentITP No: QCF, Excavation and Backfill check list.#178

Telephone cable to site officeTopIndexScopeReference documents

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 429: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

429 of

DefinitionsResponsibilitiesSafetyMethodEquipmentAttachmentScopeThe purpose of this method statement, is to define the procedure that shall be adopted for the survey, excavation and placement of the telephone cable from the etisalet manhole to the north of the project site, to the new site offices.Reference documentsOperating Authority work permit.DefinitionsEPC ContractorCivil Contractor PSM Project Site Manager.ResponsibilitiesThe PSM shall ensure that the relevant permits are obtained prior to the commencement of work. The supervisor shall ensure that the conditions stated upon the work permits are implemented.SafetyThe Safety Officer shall monitor and implement all HSE and environmental precautions.All persons, who shall be involved in this activity, shall be made aware of all safety issues relating to this activity and situation. The safety officer shall survey the route of the cable using the cat scan machine, to locate all existing services.MethodThe surveyor shall peg the route of the telephone cable on site. The safety officer and the supervisor shall scan the route for existing services, using the cat scan machine. Any observations shall be recorded and indicated with spray paint upon the ground.The supervisor shall instruct the workforce, in the requirements of hand digging near existing services. A trench shall be excavated, approximately 600mm depth. The trench shall be dug with a smooth bottom. Dune sand shall be placed to a depth of 75mm at the bottom of the trench. The telephone cables shall be placed in the trench on the dune sand bed. A further layer of dune sand shall be placed over the cable, giving 75mm of cover. The trench shall be re-instated with general fill to ground level.Marker posts shall be erected along the line of the trench, to indicate a telephone cable location.Road Crossings.Where the line of the cable shall cross a road, the following procedure shall apply.The road crossing shall be constructed in two sections. Barriers and warning signs shall be erected to protect the section under construction. The safety officer shall scan the route for any existing services.Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 430: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

430 of

The asphalt shall be cut using a jackhammer with a spade tip. The trench shall be excavated by machine. Removing the spoil to a suitable place by dumper.A upvc duct, 150mm diameter shall be placed in the road crossing. A stop end shall be erected to both ends of the pipe. Lean mix concrete shall be placed and vibrated in the road-crossing trench. The concrete shall be placed flush with the level of the road surface. Wet hessian and polythene sheet shall be placed over the fresh concrete. Curing shall continue for 24 hours.The barricades and warning signs shall be repositioned to protect the second section of the road crossing. The procedure for the second section shall be similar to the first. The asphalt shall be cut using a jackhammer with spade tip. The trench shall be excavated using machine. The stop end placed in the first section of the road crossing shall be removed. The 150mm upvc pipe duct shall be extended from the first section to the side of the road of section two. A new stop end shall be positioned at the edge of the road shoulder, to contain the concrete surround. The concrete shall be placed, vibrated and cured as described for section one. The road barriers shall be removed when the concrete has cured.EquipmentExcavator.Dumptruck.Compactors.Compressor and jackhammer.AttachmentNone.#179

Electric cable from rlip substation to Civil Contractor campTopIndexScopeReference documentsDefinitionsResponsibilitiesSafetyMethodEquipmentAttachmentScopeThe purpose of this method statement, is to define the procedure that shall be adopted for the survey, excavation and placement of the electric power supply cable, from the Plant Light Industrial Park substation, to the Civil Contractor camp substation.Reference documentsOperating Authority work permit.Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 431: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

431 of

DefinitionsEPC ContractorCivil Contractor PSM Project Site Manager.ResponsibilitiesThe PSM shall ensure that the relevant permits are obtained prior to the commencement of work. The supervisor shall ensure that the conditions stated upon the work permits are implemented.SafetyThe Safety Officer shall monitor and implement all HSE and environmental precautions.All persons, who shall be involved in this activity, shall be made aware of all safety issues relating to this activity and situation. The safety officer shall survey the route of the cable using the cat scan machine, to locate all existing services.MethodThe surveyor shall peg the route of the electric power supply on site. A section of this route is within the new area of the Civil Contractor camp facility. The remainder of the route follows existing cables that supply other contractors camps.The safety officer and the supervisor shall scan the route for existing services, using the cat scan machine. Any observations shall be recorded and indicated with spray paint upon the ground.The supervisor shall instruct the workforce, in the requirements of hand digging near existing services. Within the Civil Contractor camp area, the trench shall be dug by machine.A trench shall be excavated, approximately 600mm depth. The trench shall be dug with a smooth bottom. Dune sand shall be placed to a depth of 75mm at the bottom of the trench. The electric power cable shall be placed in the trench on the dune sand bed. A further layer of dune sand shall be placed over the cable, giving 75mm of cover. Cable tiles shall be placed ontop of the dune sand, covering the cables. The trench shall be re-instated with general fill to ground level. A plastic warning tape shall be placed within the general fill, approximately 200mm below the finished grade level.Marker posts shall be erected along the line of the trench, to indicate the electric cable location.Road Crossings.Where the line of the cable shall cross a road, the following procedure shall apply.The road crossing shall be constructed in two sections. Barriers and warning signs shall be erected to protect the section under construction. The safety officer shall scan the route for any existing services.The asphalt shall be cut using a jackhammer with a spade tip. The trench shall be excavated by machine. Removing the spoil to a suitable place by dumper.A upvc duct, 150mm diameter shall be placed in the road crossing. A stop end shall be erected to both ends of the pipe. Lean mix concrete shall be placed and vibrated in the road-crossing trench. The concrete shall be placed flush with the level of the road surface. Wet hessian and polythene sheet shall be placed over the fresh concrete. Curing shall continue for 24 hours.

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 432: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

432 of

The barricades and warning signs shall be repositioned to protect the second section of the road crossing. The procedure for the second section shall be similar to the first. The asphalt shall be cut using a jackhammer with spade tip. The trench shall be excavated using machine. The stop end placed in the first section of the road crossing shall be removed. The 150mm upvc pipe duct shall be extended from the first section to the side of the road of section two. A new stop end shall be positioned at the edge of the road shoulder, to contain the concrete surround. The concrete shall be placed, vibrated and cured as described for section one. The road barriers shall be removed when the concrete has cured.EquipmentExcavator.Dumptruck.Compactors.Compressor and jackhammer.AttachmentNone.

#180

Water supply to Civil Contractor campTop IndexScopeReference documentsDefinitionsResponsibilitiesSafetyMethodEquipmentAttachmentScopeThe purpose of this method statement, is to define the procedure that shall be adopted for the survey, excavation and placement of the water supply pipe, to the Civil Contractor camp.Reference documentsOperating Authority work permit.DefinitionsEPC ContractorCivil Contractor PSM Project Site Manager.ResponsibilitiesThe PSM shall ensure that the relevant permits are obtained prior to the commencement of work. The supervisor shall ensure that the conditions stated upon the work permits are implemented.

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 433: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

433 of

SafetyThe Safety Officer shall monitor and implement all HSE and environmental precautions.All persons, who shall be involved in this activity, shall be made aware of all safety issues relating to this activity and situation. The safety officer shall survey the route of the water pipe, using the cat scan machine, to locate all existing services.MethodThe surveyor shall peg the route of the water supply pipe on site. A section of this route is within the new area of the Civil Contractor camp facility. The remainder of the route is within the easement of road 5.The safety officer and the supervisor shall scan the route of the water pipe, for existing services, using the cat scan machine. Any observations shall be recorded and indicated with spray paint upon the ground.The route within the easement area of road 5 shall be hand dug up to the fence line of the Civil Contractor camp. Machine excavation within the boundary of the Civil Contractor camp can be conducted.The trench shall be excavated 700mm deep, into which a dune sand bed of 75mm shall be placed. The 200mm dia upvc pipe shall be laid and jointed. Sand backfill 75mm above the pipe shall be placed. The rest of the trench shall be backfilled with general fill.The trench shall be compacted using a plate vibrator. EquipmentExcavator.Dumptruck.Compactors.Hand tools.AttachmentNone.#181

Administration building substructureTop

IndexScopeReference documentsDefinitionsResponsibilitiesSafetyMethodEquipmentAttachment

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 434: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

434 of

ScopeThe purpose of this method statement, is to define the procedure that shall be adopted, for the construction of the sub-structure to the Administration Building. This procedure shall define all the work activities included in the sub-structure.Reference documentsAFC Drawings.Specification. Excavation & Backfill for underground installations.Specification. Concrete construction, Formwork and Coatings.Specification. Concrete Buildings. DefinitionsEPC ContractorCivil Contractor ResponsibilitiesThe Building Superintendent shall coordinate and organize the site activities according to this procedure. The relevant site engineer and foremen shall supervise and control the activities according to the activity requirements.SafetyAll workers shall be inducted prior to commencing on site. Specific training for each task that may present a safety hazard shall be given in toolbox talks.MethodThe administration building shall be setout by the surveyor in accordance with the IFC drawings.The excavation for the foundations shall be a bulk excavation to formation level. The excavated material shall be removed from site.After the bulk excavation to the foundations, the area shall be hand dug to the relevant formation level. Where any loose material is encountered, it shall be removed.The Geotechnical engineer shall inspect the resultant formation for suitability. The surveyor shall set out for the blinding of the foundation pads.Timber forms shall be positioned to the pad footprint, plus 300mm greater.Blinding concrete shall be placed and water cured for 24 hours.The finished surface of the blinding concrete shall be smooth, in accordance with the membrane requirements.The blinding concrete shall be primed with polyprime SB, ready for the protective membrane application. The membrane shall be applied according to the manufacturers data sheet, with reference to the project specifications. The membrane system shall be inspected and accepted by either the vendor or his site trained representative, prior to any further activities continuing.A protective concrete screed shall be laid on top of the membrane. This protection screed shall be water cured for 24 hours.Traditional formwork of plywood and timber, shall be erected for the pad foundations. Timber braces shall be used for bracing the shutters. Design calculations shall be provided for this system. The reinforcement cage shall be pre-fabricated, according to the IFC drawing. The cage shall be lifted into position using a crane. Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 435: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

435 of

The reinforcement shall be checked by an electrician for electrical continuity relating to the cathodic protection requirement.The finishes formwork and reinforcement configuration shall be inspected and concrete placement permission obtained from Civil Contractor QC inspector and EPC Contractor.The column starter bars, shall be wrapped with polythene, while the pad concrete is placed, to avoid splash contamination.Structural concrete shall be placed and compacted according to the specification requirements. Initial water curing of the concrete shall be conducted. (Refer to the method statement for protective membrane application).Formwork for the column kicker shall be erected according to the column center lines provided by the surveyor. The surface preparation of the pad foundation at the kicker position shall be scabbled. Concrete shall be placed and vibrated to the kicker. Curing shall be conducted.The column steel shall be installed according to the IFC drawings.A proprietary column formwork system, shall be erected to the manufacturers formwork drawings. Adequate bracing of the column forms shall be provided.All formwork calculations shall be provided upon the formwork drawing.Inspection of the column forms and reinforcement configuration shall be conducted and concrete placement permission obtained from Civil Contractor QC inspector and EPC Contractor. Column concrete shall be pumped.The column shall be cured according to the specification.The protective membrane to the pad foundation and columns shall be applied by the trained applicators according to the manufacturers data sheet. The application shall be inspected and approved by the vendors site approved representative. Protection board shall be placed over the membrane. Specific details of the membrane application are defined in the method statement for protective membrane to below ground concrete. (Refer to the method statement for protective membrane application).Formwork to the leanmix blocks that sits on the pad foundation for the ring beam and the interconnecting beams, shall be placed. Pouring of the concrete shall be done by pump when approved.Backfill around the pad foundations shall be conducted using approved material, in 150mm layers to the required density value.The backfill shall be placed upto the level of the underside of the blinding concrete of the ring beam.The blinding concrete to the ring beam shall be placed in the same manner as the blinding for the pad foundation.The membrane and membrane protection screed shall be applied and approved as mentioned previously.The reinforcement shall be according to the approved drawings.Formwork to the ring beam, including the box-outs and inserts as applicable, shall be erected using traditional plywood and timber forms. Timber props shall be placed as required to brace the formwork.

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 436: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

436 of

The ring beam configuration shall be inspected by EPC Contractor and permission obtained for the placement of concrete.The ring beam shall be cured according to the specification. Protective membrane to the ring beam shall be applied and protected accordingly.Backfill against the ring beam shall be conducted using approved material in 150mm layers. Backfill shall be placed upto the underside of the floor slab. These backfill layers shall be tested and approved by the QC inspector.EquipmentExcavator.Dumptruck.Compactors.Concrete pump.Concrete truck mixers.Hand tools.AttachmentNone.#182

Waste managementTopScopeReference documentsDefinitionsResponsibilitiesSafetyMethodEquipmentAttachmentScopeThe purpose of this method statement, is to define the procedure that shall be adopted for the management of the solid and liquid waste products, produced by Civil Contractor on the Company Petrochemical Project.Reference documentsEPC Contractor Project Procedure DefinitionsEPC ContractorCivil Contractor ResponsibilitiesThe Civil Contractor Project Manager shall ensure that the management of the waste disposal activities, are clearly defined. The Disposal operation shall be managed by the transport department, in accordance with the requirements of Operating Authority waste management authority and the referenced EPC Contractor project procedure.

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 437: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

437 of

SafetyAll activities conducted in connection with the management of the solid and liquid waste disposal, shall be in a safe and environmentally acceptable manner.MethodLiquid WasteLiquid waste is identified as those materials, within the sewage holding tanks, located in the camp area, site area and Civil Contractor surrounding facilities.Purpose built tanker trucks shall be used for the removal and disposal of all liquid waste materials while Sewage treatment Plant that is being built in the Camp. This Plant is made up of 2 units each of 100m³ / day capacity.Transport Department has mobilized to Plant 2 nos. of Sewage Trailers each 12,000-gallon capacity.2 nos. of Sewage Truck, each 2000 gallon capacity1 no. Sewage Vacuum Truck 6000 gallon capacity

The trucking capacity of the above fleet is 80,000-gallons / 24 hour, and adequate drivers are on site to cater for transportation of sewage to the plant for treatment.All sewage at site shall be treated in plant as follows:200 m³ / day at Sewage Treatment Plant in the Camp, which is scheduled for final commissioning by 25,000 gallons / day shall be treated at Operating Authority Plant housing Complex as per agreement with Operating Authority Management.30,000 – 40,000 gallons / day shall be treated at Mirfa Sewage Treatment Plant per attached letter, which is annotated by Manager of Mirfa Authority.Consumption of fresh water along with sewage quantities in the camp are being currently recorded per attached. Figures demonstrate that the average daily sewage throughput is around 30g / day. Based on the above available sewage treating capacity, we can cater to more than 2400 persons when S.T.P is operational, and close to 1600 persons without S.T.P While S.T.P. is being commissioned, sewage is being pumped out from Sewage Holding Tanks to Plant and Mirfa using Civil Contractor fleet. Earth bunds around sewage tanks are built to stop possible water ingress to these tanks and avoid undue health hazards. We have provided sewage drip trays for these filling pumps and contain any sewage spills during filling of the trucks. These trays are piped back to the septic tanks.S.T.P. vendor has confirmed that water quality shall have 5-10 mg / litre of organic material, which makes throughput water suitable for irrigation and / or dumping in open desert.We intend to utilize around 150-200 m³ / day of treated water for the irrigation of lawns and trees in the camp. Balance quantities of water shall be either discharges in the Earth Retention Pond located East of Avenue E, pending receipt of Client approval.A flexible hose shall be laid along fence line to first storm water culvert box for discharge of above water. Daily, water quality shall be tested to confirm suitability for above two means of disposal.

Solid WasteSolid waste, is identified as waste material generated from the camp and site facilities, such as kitchen waste, dustbin waste, paper waste, general waste materials. Storage of these waste materials shall be in appropriate skips.Disposal arrangements for all categories of waste materials, have been agreed with Operating Authority waste management. The facilities at the landfill site are for general waste, where incineration and landfill is conducted. General waste includes kitchen waste, domestic waste, timber and burnable material.A purpose built waste truck, with facilities to tip skips into the on board collection unit, shall be operated on a pre arranged schedule by the transport department.

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 438: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

438 of

The waste truck shall empty the waste skips into the disposal unit of the waste truck. Any spillage of waste material shall be cleaned up as the operation continues.When the waste truck is full, it shall travel to the Operating Authority landfill site for emptying. At this site, under the direction of the landfill manager, the waste truck shall empty its contents into a pre dug hole. The waste truck shall inform the transport department each time this hole becomes full. A new hole shall be excavated as appropriate.The cycle shall continue during the operating hours of the land fill facility. The driver of the waste truck shall complete a daily log book that records the number of trips made each day.Permits to use the Operating Authority land fill site is displayed upon the waste truck windscreen.

EquipmentSewage Treatment PlantPurpose built liquid waste tankers.Purpose made solid waste disposal truck.Waste skips. AttachmentDaily Water ReportSewage Quantities ReportVendor Statement on Quality of Throughput WaterAnnotated letter for Sewage Treatment from Mirfa Authority#183

Sea water basinTopIndexScopeReference documentsDefinitionsResponsibilitiesSafetyMethodEquipmentAttachmentScopeThe purpose of this method statement, is to define the procedure that shall be adopted, for the construction of the Sea water basin. Reference documentsIFC Drawings.Specification. Excavation & Backfill for underground installations.Specification. Concrete construction, Formwork and Coatings.DefinitionsEPC ContractorCivil Contractor Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 439: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

439 of

ResponsibilitiesThe Civil Superintendent shall coordinate and organize the site activities according to this procedure. The relevant site engineer and foremen shall supervise and control the activities according to the activity requirements.SafetyAll workers shall be inducted prior to commencing on site. Specific training for each task that may present a safety hazard shall be given in toolbox talks.MethodThe Sea water basin shall be set out by the surveyor according to the IFC drawings.The area shall be excavated to the correct lines and levels. The formation levels shall be approved by the Geotechnical engineer. The appropriate testing of the formation level shall be conducted.The construction of the sea water basin shall be divided into the following gatagories:A) Blinding concrete and protective membrane.B) Base slabs.C) Wall slabs.A) Blinding Concrete & Protective Membrane.The shear key shall be excavated to the correct line and level. A reverse formwork system shall be adopted for this element. Using traditional plywood with timber batten construction formwork, the shear key shall be formed. This section of construction shall include the outside toe blinding plus the required 300mm membrane lap area.A further one metre section of blinding to the inside of the shear key shall provide the level for the internal blinding slabs. The finish to all these blinding slabs shall be in accordance with the membrane manufacturers details. This includes chamfers etc.As the work progresses, internal blinding slabs shall be cast to the correct level, in bay sizes that do not conflict with the base slab joint layout.When the high level area has been completed, the blinding system shall continue to the lower areas.In conjunction with these activities, a dewatering system shall be incorporated, that shall remove any water ingress from the working faces. Where water has been allowed to stand, any soft areas shall be excavated and removed from site. A suitable drainage system at low level shall be provided.The procedure of constructing the shear key to these lower areas and blinding layer, shall be as previously described.Water curing of the blinding concrete shall be conducted for 24 hours.The application of the membrane shall be applied by the approved application team, according to the manufacturers details, commencing with the application of the primer with the self adhesive membrane being laid as appropriate. The vendor or his approved site representative, shall monitor the application of the membrane system. B) Base Slabs.The reinforcement to the floor slab sections shall be assembled carefully to avoid damage to the membrane.

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 440: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

440 of

The waterstop requirement shall be fabricated and installed according to the IFC drawings and manufacturers details.The formwork to the floor slab sections shall be constructed from traditional plywood and battens.A sequence for the construction of these floor slab panels shall be discussed and agreed between EPC Contractor and Civil Contractor.The cathodic protection installation shall be installed and tested. Details of these tests shall be recorded.Prior to the placement of concrete to a floor slab section, the site engineer and Civil Contractor QC inspector, shall inspect the section for compliance shall all drawing requirements. Any errors shall be rectified. EPC Contractor shall be informed of the readiness of the section for concrete.Upon approval to place concrete from EPC Contractor, the structural concrete shall be placed. Curing of the slab section shall be according to the specification.The formwork shall be removed after the period defined in the specification. Any surface defects shall be inspected between Civil Contractor and EPC Contractor QC inspectors, who shall agree on the correct repair procedure. Curing shall continue.This sequence shall continue for each floor slab section. Where specific joint details between floor slab sections are shown on the IFC drawings, those details shall be included.Where the base section occurs on a slope, the various sections shall be placed and vibrated in careful controlled operation. Screeding to the correct lines shall be conducted using an aluminium straight edge.C) Wall Slabs.The wall pour sections shall be constructed as per the IFC drawing details. A proprietary formwork system shall be used for these sections. Giffin Scaffco detail drawings and calculations shall be provided.The inside wall form shall be erected and braced. Fixing details for the push-pull strongbacks shall be via a pre-drilled expansion bolt onto the floor slab section.The reinforcement shall be erected according to the IFC drawing.

Waterstop accessories shall be included within the wall section at this stage. All waterstop accessories shall be positioned and jointed in strict conformance with the vendors instructions.The reinforcement and accessories shall be inspected and approved prior to the placement of the outside form closure. The formwork shall be aligned and checked for completeness by the temporary work engineer.Placement of concrete shall be conducted after EPC Contractor approval.The pour rate and placement criteria shall be as defined by the formwork designer.Curing of the wall section shall be in accordance with the specification.Removal of the formwork shall be in accordance with the specification. Striking of the forms shall be done in a safe and controlled sequence.The resultant concrete surface shall be inspected for surface defects and repaired as required, according to the approved repair procedure.Each wall section shall follow this sequence. The joint details shall be in accordance with the relevant drawing detail.Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 441: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

441 of

The sequence of wall pours shall be provided by Civil Contractor, to conform to specification casting times.D) General.Upon completion of the sections, the application of the protective coating internally shall be applied. This application shall include all sealants to the expansion and contraction joints.Backfill around the structure shall be conducted according to the specification requirements. Each layer shall be tested as the work proceeds.The completed structure shall be filled with clean water, to test the integrity of the structure. EquipmentCrane.Concrete pump.Concrete truck mixers.Dewatering system.Hand tools.AttachmentNone.#184

Excavation for Ethane & propane Gas pipeline interconnection

TopIndexScopeDefinitionsMaterialMethod EquipmentAttachmentScopeThis statement is aimed to propose the procedures to be adopted to carry out the excavation and laying of Ethane and Propane pipeline from Gasco through to the Company project site and excludes the road crossings where separate method statements applyReference documentsSpecification. Excavation & Backfilling for Underground Structures SafetyPrior to commence any activity, the labour force shall receive a STARRT Card / Toolbox Talk relevant to the operation concerned on the project site safety requirements.Necessary measures shall be applied to any process involving a safety riskSafety Supervision

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 442: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

442 of

A competent inspector shall visit the area daily to assess the safety measures adopted. Any snag observed during his visit shall be notified to the supervisor present who immediately act to bring the safety measures to an acceptable standard In case of incident where utilities not identified are discovered or damaged, all work shall stop in the area and the Operator Shift Controller and HSE department immediately notifiedPhone number : Shift Controller Emergency Number HSE Direct numberEmployees working in easement area shall have a daily pre-task briefing that includes;Reporting of incidentsMethods of work and tools to be usedPotential hazards found in the Easement areasThe approved work method statementEPC Contractor and Civil Contractor HSE department shall participate in presenting the STARRT card briefing and monitor the activities to ensure that the work methods are being followed and all personnel have an understanding of the hazards associated with working adjacent to live process areasMethodPermits pertaining to the relevant excavation area shall be obtained from Plant Refinery division.The surveyor shall set out the route of the proposed gas pipeline trench conforming to the IFC drawingsSupervision at the workface must have a copy of the permit, drawing andthe method statementAny existing services shown on these drawings shall be located and identified. Where the protection of these services are required, then adequate protection and warning shall be installed. Cables or pipes that span the excavation shall be supported. Split ducts and trays shall be provided to protect and support these cables.Where necessary, trial pits shall be hand excavated to expose servicesAll existing services encountered shall be plotted by the surveyor on as built drawingThe trench shall be excavated by a tracked excavator to correct lines and levels. Where necessary or as defined on the work permit, hand excavation shall be carried outWhen cable markers have been exposed, work shall be temporarily suspended and an evaluation made about the soil conditions. This evaluation shall be conducted by EPC Contractor Superintendant and Operator operations representative. Where necessary, a revised method of work may be necessary and in this instance, all personnel shall be briefedExposed (Existing) cables and pipelines shall be checked for damage by EPC Contractor supervision and combined inspection shall be held by EPC Contractor and Civil Contractor. Operation department shall be invited to attendCables shall be protected by fitting split sleeves after exposureThe sides of the excavation shall be sloped . Barriers (including warning tape) shall be placed to indicate an open excavationStatements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 443: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

443 of

The excavated material shall be stockpiled in agreed areas for reuse. Surplus material shall be removed to the tip area in dump trucks. The surveyor shall monitor the lines and levels of the excavation operationEPC Contractor engineer shall approve the suitability of the formation material by inspecting the bottom of the trench and after the approval, compaction of the formation level shall be carried out to the required specified density values.The site test laboratory shall conduct the density test and the resulting values pertaining to density and moisture contents shall be reported to confirm that the compaction carried out conforms to the specification requirementThe surveyor shall provide level pins that indicate the correct elevation of the bedding required for the gas pipes. The bedding shall be laid and compacted in accordance with the specification requirement. The test laboratory shall conduct the test and report the resultsThe gas pipes shall be placed correctly within the trench by EPC Contractor (not Civil Contractor) in accordance with EPC Contractor own method statements (noting that Al Jaber equipment is under the Direct Control of EPC Contractor).Upon acceptance of the pipe installation, the pipes shall be surrounded with further bedding material which shall be compacted using suitable equipmentThe approved backfill material shall be spread uniformly in layers of 150 mm & compacted to the specification requirement and tested accordinglyWhen backfilling, tile markers and warning tape shall be replaced and provided between cable and tile markersThis activity shall continue up to existing ground level. The site shall be left tidy of excavated and backfill material Major EquipmentExcavatorDump TrucksCompactorsAttachmentNone

Top

GeneralScopeThis Procedure describes the civil works sequence pertaining to Water Pumping Station (Booster Pump Building, Main Pump Building, Electrical Building, Chlorination Building, Quality Metering Building) activities to be performed within the scope of the Water and Power Project (Pipelines).

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 444: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

444 of

Definitions and AbbreviationsDefinitionsThe following words and expressions shall have the following meanings hereby assigned to them:“Contract” means the agreement between the Owner and the Contractor for the execution of the Works.“Contractor” means the person designated as such in the Contract.The Contractor is: “Engineer” means the person appointed by Owner to act as Engineer for the purpose of the Contract.The Engineer is: “Owner” means the person designated as such in the Contract.The Owner is: “Plant” means machinery, computer hardware and software, apparatus, materials, articles and things of all kind to be provided under the Contract other than Contractor’s Equipment.“Project” means the Water and Power Project (Pipelines)“Site” means the actual place or places, provided or made available by the Owner, to which Plant is to be delivered or where work is to be done by Contractor.“Works” means all Plant to be provided and work to be done by the Contractor under the Contract.AbbreviationsThe following abbreviations may be used in the procedure (where applicable):Civil Contractor - QA Quality AssuranceQM Quality ManagementQC Quality ControlPQP Project Quality PlanHSE Heath, Safety and EnvironmentalPM Project ManagerCM Construction ManagerCS / SE Construction Superintendent / Site EngineerFM ForemanQCE Quality Control EngineerDescription of ResponsibilitiesPM shall control the overall operations & direct the CM & all divisional headsCM shall arrange the resources to the requirement & direct the divisional heads, CS & SECS shall control, monitor and direct the S E / FM and workforce for the operationsSE shall carry out the operational technicalities, co-ordination & direct the FMFM shall execute the operations deploying the workforceQC shall inspect all the operations according to the specifications & ITPsApproval / AuthorisationThis Procedure shall be reviewed by the QA Manager, Project Manager and released by the Project Director.

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 445: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

445 of

Distribution and ControlThis Procedure shall be distributed in a controlled manner by the Document Control Centre according to the Procedure Distribution MatrixReference documents.DrawingsSpecifications for civil worksThe records regarding the existing services shall be inquiredExcavationThe survey team shall set out the excavation lines to the details & fix the reference pegsThe excavation area shall be marked according to the details shown on the reference drawings & to the requirementAdditional area shall be included for the purpose to set out, to form the benches & the safety barriersCivil Contractor QC inspection shall be conducted for the approval of the setting outThe excavation shall be carried out to the design lines & depth where a firm formation giving 93% of the dry soil / proctor density is obtained using excavator (reference given below)The excavated material shall be dumped into trucks directly from the excavator & transported to the earth stock piles about 70 to 100m off the operation areaThe excavated formation shall be proof rolled / dressed / compacted with a smooth vibratory roller 10 tonnes capacityAny soft or compressible areas detected by the proof-rolling shall be removed, inspected & replaced with ordinary / structural backfillsoil density shall be tested by an independent laboratory In areas where the required density is not achievable, further 0.3 m excavation shall be carried out to accommodate approved granular fill materialThe sequence shall continue till the required area is completely excavatedRamp shall be excavated to the requirement where mass excavation is carried out for the heavy equipment to enter & exitCivil Contractor QC inspection shall be conducted throughout these operationsWater shall be sprinkled to protect the excessive dust flow into air as requiredAll the operations shall be carried out to the Engineer’s satisfactionProcedures- Operational Sequence for the following buildings Booster pump building for 4 # pumps (0-10)(A-B) Instance 1Electrical building (C-F)(1-8) located between pump buildings Instance 2Main pump building 4 # pumps (G-H)(1-10) Instance 1Chlorination building Instance 3Quality Metering building Instance 4Excavation shall be carried out to the methods described in the foregoingThe formation shall be prepared by proof rolling to 93% proctor density in case of ordinary fill & tested by heavy dynamic sounding 16 blows / 10 cm penetration or 160 bar point resistance by Dutch cone test (refer Testing of ordinary fill) Where selected fill is specified, 95% proctor density shall be required. In case the required density is not achieved, granular material shall be laid within the additional depth excavated & compacted to achieve the structural densityExcavation shall be carried out for the underground services (drainage) to the details given on the IFC drawings Proper dressing & compaction shall be carried out for the bedding which shall be laid toreceive the pipesPipes shall be laid to the stringing lines, levelled & jointedStatements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 446: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

446 of

Part backfill shall be carried out @ the joints for test pressure resistancePressure testing shall be carried out according to the specification & codes requirementAfter the approval is obtained, the remaining bedding & padding shall be completed according to the details & the backfill effected to the floor grade level to allow the work for blinding to proceedInstance 1After having the excavation approved, the preparations shall be carried out for the blinding concrete grade L to the design profile by placing timber scantling forms in positionThe surveyor shall fix the top of blinding level marksCivil Contractor QC inspection shall be conducted to the ITP & Checklist requirementThe prepared formation shall be cleaned, sprinkled with water & ready mix blinding concrete poured, spread by hand shovels, teeth shovel, levelled to the profile & finished properly by floating so that the surface is good to receive concrete protection membrane profileImmediately after the concrete is dry & good enough to receive shading over it by polythene sheets, the curing shall be carried out by covering the finished surface laid over with plastic sheets for 2 days Concrete protection membrane shall be applied according to the manufacturer’s instructions including the extended area around the foundationRebarsEpoxy coated rebars shall be cut & bent to shape in the yard & transported to the required location. All overlaps shall be increased to ACI requirement. On the damaged areas of the rebars where touch up is necessary, shall be applied with epoxy paint throughout the bars placement operation prior to any oxidation takes place. A holiday detector may be used to examine the coating surface The column rebars shall be placed after the slab rebar placement is over & properly alignedRebars for the cable trench wall shall be placed simultaneously with proper embedmentAll rebars shall be tied up using epoxy coated binding wireSuitable spacers shall be used to provide specified concrete coverAbove ground external 50mm, underground & ground water 75mm, slabs internal 30mm, beams & soffits internal 40mm, Sea water contact 100mmThe construct joint location shall be marked as shown on IFC drawingsThe formwork for the foundation slab shall be sawn to the accurate size & erected to the true setting out lines according to construction drawings & necessary supports & bracing to resist the concrete hydraulic pressure provided & not to have deflection more than 3 mm. The form surfaces shall be treated with an approved release agent (non staining mineral oil)The top of concrete marks shall be fixed on the form by a wooden / pvc beadTriangular chamfer 25x25mm shall be fixed to the external cornersKicker forms 70mm high shall be prepared for the columns to the requirement to be cast monolithic with previous slab concreteCivil Contractor QC inspection shall be carried out to ascertain proper alignment, rebars fixing & levelsCleaning shall be carried out by compressed air & the forms lightly watered to maintain the temperature to avoid concrete flash settingThe concrete pour shall commence & all site tests (slump, temperature, cubes & air void etc) shall be conducted selectively by an approved laboratory representative @ the arrival of the transit mixer to the spot during pour & pour continued until whole planned lot is completed.Proper vibration for compaction shall be done by trained persons to break the cement particle suspension from the coating of microsilica particles & achieve specified concrete density. The vibrators shall not be allowed to touch either the form surface or the rebars & complete concreting area shall be covered for compaction by the vibrators

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 447: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

447 of

During concreting any peeling / debonding of the rebars epoxy coating shall be repaired by touch up paint prior to the oxidation takes placeTemp @ discharge point not to exceed 30 C, Ambient not to exceed 40 C, Ambient not to exceed 37 C rising, Max permissible cast element 60 C & temperature difference on two elements 15 C During pouring, in case any pour break is inevitable due to accidental mechanical breakdown or any other cause, cold stopper joint with rebated vertical surfaces shall be provided which has to be scabbled & cleaned prior to next pour & shall be treated as a construction joint.Immediately after the concrete has stiffened enough to be surfaced, the finishing shall be carried out by steel float to the marked levels (by removing all extra material & filling in any depressions observed)To avoid the shrinkage cracks formation, polythene sheets shall be covered over the finished concrete surface immediately for shading & after about 5 to 6 hours, saturated hessian shall be added over the concrete surface by removing & replacing the polythene sheetThe surface of the concrete shall be covered with water for the required number of 7 days in generalThe side forms shall be struck after 24-36 hours, water sprinkled on the green surface & curing compound sprayed over for remaining period (7 days in general) of curing of the sidesThe column rebars shall be placed in correct position according to the design details upto the top of the column including the crane corbelCivil Contractor QC inspection shall be conducted according to ITP & checklist requirementTouch up epoxy paint to rebars shall be provided prior to the closure by the formsSawn formwork shall be fabricated to the column design dimensions to cover casting up to the top of the corbelCivil Contractor QC inspection shall be conducted according to concrete pour ITP & checklist requirementConcrete pour shall be carried out in 450 mm max vertical layers continued full height of pour While vibrating the second 450 mm layer, care shall be taken that the vibrator nozzle penetrates to the previous layer also to attain the concrete integrityThe top of the column & corbel shall be covered with polythene After a lapse of 24-48 hours the side forms shall be struck, the green surface sprinkled with water & the curing compound applied for the remaining period of curing In the second shift of structural casting, the remaining portion of the columns between the corbel & the ‘hollow core slab supporting girder’ shall be prepared for the steel placement & the formwork. Proper centring & shuttering shall be provided for the supporting girders soffitsCivil Contractor QC inspection shall be conducted according to concrete pour ITP & checklist requirementConcrete pour shall be carried out to the procedures explained above followed by the curingThe side forms shall be struck after 24-48 hours & curing compound sprayed as explained earlierThe girder soffit props shall remain intact for 21 days post pourApproved prefabricated ‘hollow core slabs’ (provided with the extract fan openings) from the specialist manufacturer shall be suspended according to the propriety system & to the approved shop drawings excepting the specified grids A & H reserved for the accessPumps Bases (Booster)The formations for the pump bases shall be prepared & compacted to structural densityCivil Contractor QC inspection shall be conducted according to concrete pour ITP & checklist requirement Blinding concrete shall be laid on the relevant areas, finished & cured as aforesaidConcrete protection membrane shall be applied according to the manufacturer’s instructions including the extended area around the foundation

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 448: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

448 of

Fabricated rebars shall be placed to the design details being given due continuous touch up at the epoxy coating damaged locations prior to any oxidation takes placeForms shall be prepared for the sides according to the dimensions with exposed corner chamferedAnchored bolts shall be fixed in to the design locations missing the rebarsNecessary care shall be exercised during the concrete pour that the anchor bolts remain @ locations fixed & no excessive movement takes placeA polystyrene sleeve may be used to allow for the grouting laterTop of concrete levels shall be marked Civil Contractor QC inspection shall be conducted according to concrete pour ITP & checklist requirement Concrete shall be poured into the prepared works according to the procedures explained in the foregoing as well as cured Pumps Bases (Main)Since these bases are designed to rest on the isolation over the foundation slab, elastic pads shall be installed to the design location over the foundation slabCivil Contractor QC inspection shall be conducted according to concrete pour ITP & checklist requirement Fabricated rebars shall be placed to the design details being given due continuous touch up at the epoxy coating damaged locationsForms shall be prepared for the sides according to the dimensions with exposed corner chamferedAnchored bolts shall be fixed in to the design locations missing the rebarsNecessary care shall be exercised during the concrete pour that the anchor bolts remain @ locations fixed & no intolerable excessive movement takes placeA polystyrene sleeve may be used to allow for the grouting laterTop of concrete levels shall be marked Civil Contractor QC inspection shall be conducted according to concrete pour ITP & checklist requirement Concrete shall be poured into the prepared works according to the procedures explained in the foregoing as well as cured accordinglyCable ducts (RCC)@ whatever locations these ducts run, the preparatory forms & rebar fixing works shall be carried out Closed Block outs to the design dimensions wherever shown shall be fixed by timber prepared forms at the correct locations on the duct formworkCivil Contractor QC inspection shall be conducted according to concrete pour ITP & checklist requirement Concrete shall be poured according to the procedures aforesaid & cured accordinglyThese ducts shall be covered with galvanized chequered plates (optional) fabricated to design details by providing a GI angle backing grid frame or if convenient & feasible, pre-cast covers shall be used in lieuPre- Cast Covers (optional)Pre casting shall be carried out in a yard on a prepared concrete / strong baseForms shall be sawn & prepared to the design size & chamfered accordinglyFabricated rebars shall be placed into the forms & spaced properlyAny epoxy paint touch up required shall be given accordingly prior to any further oxidationRecessed GI Lifting lugs shall be fixed @ 1 / 5th of the length from either end & part of the lugs without GI remain embed in the concreteCivil Contractor QC inspection shall be conducted according to the ITP & checklist prior to the concrete pourStatements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 449: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

449 of

Concrete shall be poured in to the agreed number of prepared units / covers in one time & steel float finish givenImmediately after finish is given, curing shall be carried out as explained in the foregoingAfter having the curing completed, approved protection shall be provided within specified period prior to deliver these units to the installation locationsAs & when required these covers shall be lifted by crane for loading onto a trailer & transported to the building location for off loading @ the correct location Roofing finishes shall be carried out to the upside down roofing system by the asphalt layer laid over with standard 500x500x50mm cement concrete tilesThe roof finish shall be laid to a profile slope 3%(further details)HVAC ducting operations shall be completed including all fittings en routeElectrical Fix shall be completed according to details on the shop drawingsPipe supports shall be completed prior to the start of flooring & other finishesFlooring Cement concrete screed flooring shall be carried out to the given 1 % slope by scabbling the foundation slab & dividing the area into the bays to be finished alternativelyDetails here The areas of concrete sub strata to be screeded shall be brush cleaned and dampened until absorption ceases followed by the finished floor level establishment by means of dots and rules. The total thickness of the screed flooring is 70 mm bedding screed (1 cement: 4 mortar sand) by weight and shall be applied as described below.The mortar for screed shall be 1 part cement to 4 parts sand by weight, mixed semi dry by a mechanical mixer with only sufficient water added to give a crumbly consistency which retains its shape when squeezed by hand permitting no fluidityThe mix shall be placed to a thickness approximately 10 mm greater than that actually required , thoroughly compacted by tamping and drawing off to the required level with a screed board. Only sufficient mortar shall be mixed and spread as can be consumed before it attains its initial set & rendered a steel float finishCivil Contractor QC visual inspection shall be conducted The screed surface shall be applied with approved oil resistant coating to the specificationExternal PC sandwitch panel shall be provided to the details shown on the manufacturer’s shop drawings & installation instructionsAccess ladders & platformsAccess ladders & platforms shall be fabricated in the workshop & hot dip galvanizedThese shall be transported to the site in completed form & fixed to the prepared locations with the necessary fastenings Instance 2 Electrical BuildingCable floor throughout excepting HVAC roomConcreting shall be carried out similarly to the base slab as aforesaidCable floor wallsShall be carried out similarly to the wall concreting as aforesaidHVAC room floorForms shall be erected supported on centring & all other preparatory works shall be carried out as explained in the foregoingStructural ColumnsShall be carried out in one instance up to the hollow core slab beam bottom as explained in the foregoingStatements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 450: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

450 of

Corridor structureIn the first go, the columns shall be poured followed by the slab to be cast monolithic with suspended girdersPrefabricated Hollow core slabsShall be carried out as explained in the foregoing in the instance 1Civil Contractor QC inspection shall be conducted according to concrete pour ITP & checklist requirement Block walls 200 mm thick / 150 mm thick as the case may beSS / GI Hold fasts shall be shot fired to the RCC columns @ 400 mm c / c to embed into the block course mortarMembrane treatment to the details shall be applied on the surface to receive the block wallIst levelling course shall be prepared with mortar spread & wet blocks arranged in position properly tamped with hammer & strung with line dori / threadAll the courses shall be laid in such a way that no plumb in joints are formedNecessary small pieces / bats may be cut using a suitable electric operated grinder Rebar 8-mm shall be laid on every alternate courseIn one day operation not more than 1.5 m of block wall shall be raisedWhere solid block wall is required, the hollows shall be filled with concrete the next dayProper curing of the mortar joints shall be carried outSmall gap shall be left between the wall top course & the structural concrete for expansion joint formationWall finishesCorridor, control room, office, HVAC room & all electrical rooms to be plastered with emulsion paint insideDetailsPREPARATION OF BACKGROUNDS TO BE PLASTERED OR RENDEREDAll surfaces to be plastered / rendered shall be thoroughly cleaned of all dust and loose particles. Concrete surfaces shall be scabbled by mechanical means to remove all laitance exposing the aggregates to 3 mm depthCivil Contractor QC inspections shall be conducted for the approval of the prepared surfaces.A slurry coat consisting of 400 kg Cement (white) to 1 cum of sand (No. 1 White Silica) as specified shall be applied on the surface by trowel and 1-day allowance given for the succeeding coat to commence with.Block work surfaces shall have the joints raked out during construction.Junctions of different background and the chases for the electrical conduits as well as other services pipes shall be treated by fixing 200mm wide metal lath. Plastering shall not commence until all the mechanical and electrical services, conduits, pipes and Ist stage fixtures have been installed and approved.Where a rendering or plaster is to be continuous across backgrounds of different types, a strip of metal lath minimum 300 mm wide with an isolating membrane of polythene sheet or building paper behind, shall be fixed across the junction. Where small widths of one material less than 300 mm wide are involved e.g. a concrete column, beam or slab dividing block panels, the width shall be bridged completely for a distance of 150 mm on both sides.The metal lath shall be stretched out and fixed along each edge at 100 mm centres using stainless steel fasteners such as washers and shot fired pins, nails or screws and lapped joints tied with galvanized wire, the screws fixed into plugs in predrilled holes if so required.Metal lath shall not be provided where drawing shows a groove in the rendering or the plaster.

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 451: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

451 of

FIXING BEADS AND STOPSBeads, stops and the like shall be fixed plumb, square and true to line with clout nails or plaster dabs at not more than 600 mm centres to each mesh wing.Corner / angle beads at all openings as well as plaster ground stops at terminals shall be installed by using stainless steel fasteners. Profile dots shall be formed on the surfaces.Civil Contractor inspection shall be conducted for the proposed profile approval.PREPARATION OF MIXES FOR PLASTERING OR RENDERINGSlurry coat400 kg cement: 1 cum sandSecond and third coats300 kg cement: 50 kg lime: 1 cum sandPlaster thickness 19 mm walls and 14 mm ceilingsThe hydrated lime shall first be thoroughly mixed with sand and then cement added keeping mixer on until the material is uniform in appearance, suitable to receive water which at this stage be added in sufficient quantity to produce the mix stuff workable, uniform in colour and consistency.To improve the workability of the mix, the hydrated lime, sand and water may first be mixed in the required proportion with allowance to stand undisturbed for at least 16 hours before mixing with cement. If allowed to stand for a longer period, the ingredients mix must be protected from drying out. The whole of the batch shall be used within an hour of being mixedAPPLICATION OF THE VARIOUS PLASTER OR RENDER COATSThe work shall not start until the background has been prepared and (all the services have been finished according to requirement and the relevant specifications as described earlier).Slurry coat shall be trowel applied allowing at least one day to start the succeeding coat Two render coat applications shall be carried out.Before applying any coat, the background or the preceding coat shall be brushed down to remove any loose particles and dampened sufficiently to ensure uniform absorption.First coat shall be trowel applied and scored to form a key for the second coat allowing at least one day before the start of the next coat. The undercoat shall be applied either by laying on with or throwing from a trowel or float, as uniformly thick as possible and not less than 8 mm or more than 13 mm thick in any part.The undercoat shall be left rough and open by the edge of the trowel after it has been long enough to set firm, be combed with evenly spaced wavy horizontal lines approximately 20 mm apart and 5 mm deep (less in case of first coat on metal lathing). The surface shall not be scratched, however, when it is to receive a Tyrolean finish.First undercoat applied to metal lathing shall be well worked into the lath to ensure that the material is completely embedded.The steel trowel applied steel float finishing coat shall not be less than 5 mm or more than 10 mm thick, taking care not to over work the surface.All coats shall be applied with firm pressure to exclude air and to ensure a good bond.Plaster shall be rodded and straightened to uniform surfaces in true planes. Laps of one coat shall not occur over laps of preceding coat. Each coat shall finish free from cracks, checks or other structural defects. Finish surfaces shall be flush with grounds / stop beads, corner beads, outlet boxes and similar details, free from trowel marks, other blemishes displaying straight arises and true angles.All coats shall be prevented from drying out too quickly and the work be carried out in shade during hot period. All renderings shall be protected by properly constructed hessian or similar screen during hot period

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 452: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

452 of

Each coat shall be kept damp by means of a fog spray of water for a minimum of 3 days to allow before a subsequent coat is applied or in the case of a finish coat, before the protective screens are removedThe surface of the finish coat shall be smooth, true and free from waviness, irregularities or blemishes with straight, level or plumb angles. External angles shall be pencil roundedCare shall be taken when rendering up to beads or stops to avoid excessive polishing at the arris and damage to the galvanizing.Inspections for the approval shall be conducted.Battery room shall be acid resistant tiles up to 1.2 m levelDetails given belowLounge (kitchen), washroom & lavatory shall be room height tilesDetails given belowMaterial Glazed Tile size specified 108 x 108 mmSetting material (ultra set polyurethane adhesive ) recommended by manufacturer Cushion edgesRounded external cornersHead Jamb and Cill trim shapesWain scot cap Surface bullnose or bull nose capExternal corners Bullnose shapes or as specifiedInternal corners Field butted squareGrouting material Water proof epoxy tiling grout with antifungicide additive(Commercial white sanded latex portland cement type) ApplicationMesh reinforcement shall be incorporated in the plaster where The structure is out of line and the thickness of the plaster exceeds 13 mmThe plaster is to be applied over different structural materialsThe surfaces of the structural wall shall be subject to excessive movement .e.g., light weight concrete block of all typesExaminationThe strata to receive the tiles shall be examined closely to ascertain that the moisture content is within permissible limits to allow the fixing operation Where the tiling is to be bedded in a thin bed adhesive, the trueness of the plaster shall be such that when tested with a 3 m straight edge no gap exceeds 3 mmWhere the gap lies between 3 and 6 mm, if the walls are out of plumb by not more than 6 mm, a thick bed adhesive shall be applied in preferance to cutting the defective areas and making goodDeviation from true vertical or plumb in the surface of plastering exceeding 6 mm shall be made goodThin bed adhesive shall not be used for fixing tiles with backs incorporating deep keys or frogs for which thick - bed adhesives must be used Civil Contractor QC inspection shall be conducted to ITP requirementThe tiles working sketch shall be approved before the work commences so that cut tiles be kept to a minimum and where they do occur be as large as possibleThe tiles shall be correctly positioned in both directions the time these are placed forming joints using a proprietary tile spacer (1.5 mm for wall tiles)Joints shall be horizontal and vertical, with horizontal joints aligning in walls that adjoin or be adjacentThe tiles shall be neatly and accurately cut to close fit where necessary at abutments and around outlets, pipes and the like

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 453: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

453 of

The tiles shall be extended into recesses, under equipment and fixtures to form a complete covering without interruptions as well as terminated neatly at obstructions, edges or / and corners keeping the ‘on going pattern’ or joint alignment. The tiles shall fit closely to the electrical outlets and fixtures allowing plates, collars, covers etc., overlap the tiles.Movement joints not less than 6 mm shall be provided:At all internal vertical cornersAt all angles with structural walls and ceilingsTo form bays not greater than 3000x4500 mmOver all structural movement joints:The joints shall be carried through the plastering to the structural wall, partially filled with an approved joint filler and finished flush with an approved sealant recommended by the manufacturer for the relevant situations.Glazed edge tiles shall be used at the exposed edges.The tiles shall be fixed in position prior to the adhesive gets dried for that it shall be prepared and applied on a small area not exceeding 1m x 1m at a time with a trowel to dry plaster surface in a manner recommended by the manufacturer followed by the tiles pressed firmly into with a twisting / sliding action tapping firmly and cleaned as soon as the bedding be completed.The finished surface of the tile shall be firm and true such that when checked with a 3 m straight edge, no gap exceeds 3 mm Civil Contractor QC inspection shall be conducted to ITP requirementThe joints shall be grouted well to completely fill in as well as appear flush after the adhesive has set and not less than 48 hours post fixing. Surplus grout shall be cleaned off from the tiles surfaces as neatly as possible as the work proceeds using a damp cloth and the joints tooled smooth. The grout haze shall be removed according to the manufacturer’s instructions for the use of acid and chemical cleanersThe tile work shall be rinsed thoroughly with clean water prior to and post using chemical cleaners followed by polishing with soft cloth.Flooring finishesCorridors, social rooms & HVAC rooms shall be tiled floorsDetails given belowOffice shall be heavy duty PVC tilesDetails Control room, electrical rooms shall be false floor with heavy duty PVC tiles

Details MaterialsCeramic floor tiles 300 x 300 x 10mm or as the size may be, For General Area ‘RAK GP 21 G’ and for wet areas Johnson ‘Athena’Cementitious adhesive- Nitotile GPJoint filling grout – Approved proprietary material with matching shade.Method (Laying ceramic floor tiles by SEMI DRY method)The areas of concrete sub strata to be tiled shall be brush cleaned and dampened until absorption ceases followed by the finished floor level establishment by means of dots and rules.

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 454: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

454 of

The total thickness of the ceramic tile flooring is 100 mm which includes 90 mm bedding screed (1 cement: 4 mortar sand) to be mixed by weight and 10 mm thick ceramic tiles, shall be applied as described below.

The mortar for bedding the tiles shall be 1 part cement to 4 parts sand by weight, mixed semi dry by a mechanical mixer with only sufficient water added to give a crumbly consistency which retains its shape when squeezed by hand permitting no fluidityThe mix shall be placed to a thickness approximately 10 mm greater than that actually required for the bed, thoroughly compacted by tamping and drawing off to the required level with a screed board and given a smooth trowel finish. Civil Contractor QC visual inspection shall be conducted to ascertain proper compaction and levels.The surface of the screed shall be cleaned by brush prior to the application of the adhesive. The adhesive shall be mixed with water using a slow speed drill to the water adhesive ratio per manufacturer’s data sheet. Adhesive Nitotile GP mix shall be applied in uniform thickness of 2 to 3 mm over the surface of the cement sand screed bedding and then combed horizontally.Tiles shall then be laid on the adhesive layer with a twisting motion ensuring good contact between the tile and the adhesive bed. For this purpose the adhesive manufacturer’s instruction shall be adhered to.The tiles shall be correctly positioned in both directions the time these are placed forming joints using a proprietary tile spacer (1.5 mm for wall tiles and 3 mm for floor tiles)The tiles shall neatly and accurately be cut to a close fit where necessary at abutments, around outlets, pipes and the like.Civil Contractor QC Inspection shall be conducted for the correct formation of joint alignment and the level profileThe tiles shall be laid level or to 1- % falls in ‘wet’ areas as may be required. Localised variations in level for a nominally flat floor shall be a maximum of + / - 2-mm under a 3-meter straight edge. Particular care shall be taken in ‘wet’ areas to prevent low spots that may promote water pooling. The tolerance in the overall level shall not be more than 10 mm from required finishes. Excessive adhesive shall be removed with a damp cloth before the material has set.Grouting of the joints shall be carried out after a period of 24 hours after completion of laying of tiles. MOVEMENT JOINTS IN TILED FLOORSUnless otherwise indicated in the documents, a 10 mm movement joint shall be formed at the perimeter of all the tiled floors and where the tiling meets structural features such as columns, machine bases etc.,Where a structural movement joint is provided in the base, a movement joint of the same width in the bedded finish shall be positioned immediately aboveThe movement joint cavities shall extend through the combined thickness of the finish and the bedding mortar, completely filled and sealed after grouting of the normal joints takes place.Battery room shall be acid resistant tilesDetails as aboveTransformer RCC works all shall be carried our in a similar manner as described in the foregoing & necessary concrete protection membrane applied accordinglyValve chambersThese shall be constructed to the details & include excavation, blinding, RCC bases & walls, RCC pre-cast covers

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 455: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

455 of

Chlorination building Instance 3Pipe ductAfter excavation, blinding, concrete protection membrane activities are completed in a similar manner as explained in instance 1 & 2, the preparatory works for the pipe duct shall be carried out to the design locationFoundation slab shall be carried out similarly with column starter rebars placed inStructural RCC columns shall be constructed accordinglyRCC wall between the chlorine storage & chlorine dosage shall be constructed to the roof soffit level according the foregoing explainationPrefabricated Hollow core slabsShall be carried out as explained in the foregoing the instance 1Parapet shall be constructed accordingly to the shown layoutCivil Contractor QC inspection shall be conducted throughout the above operations according to concrete pour ITP & checklist requirement Wall finishesInternally to be plastered & emulsion paintExternal surface to be emulsion paintConcrete surface shall be epoxy coatedDetailsApplication (painting)GENERALMaterials shall be delivered in sealed containers clearly labelled with the following information.Manufacturer’s name, initials or recognised trade markTitle and specification numberWhether primer or undercoat or finishing coatWhether for internal or external use Colour reference Method of applicationBatch number and date of manufacture SamplesSample panel of 1 sqm in area shall be prepared for each type The following operational sequences shall be involvedSurface PreparationPriming CoatFiller Coat to the requirementIntermediate CoatFinishing CoatAll according to the approved system as aforesaid detailed for reference.ApplicationAll paints shall be prepared and applied in strict accordance with the manufacturer’s instructions. Priming paints shall be applied by brush. Spray application shall only be used for painting of epoxy resin baseThe dried films shall be free from bloom, shrinkage, sheeringness, wrinkling, sagging, discoloration and extraneous matterNo exterior or exposed paint work shall be carried out under adverse weather conditions like sandstorms

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 456: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

456 of

Surfaces to be painted shall receive the first coat of paint as quickly as possible after the preparation has been completedEach coat shall be applied uniformly over the entire surface. Skips, runs, sags and drips shall be avoided. On beams and irregular surfaces, edges shall be strip coated first and at extra pass made later. Each coat shall be allowed to dry for the time specified by the manufacturer before application of any succeeding coatAll coatings shall be cleaned as specified by the manufacturer before the next coat is appliedAll fixtures and surfaces not to be painted shall be properly protected during application and upon completion of the work all paint and varnish removed from glass, fixtures, covering, etc., Moveable parts shall not to be painted.SPRAY APPLICATIONAll equipment for spray application shall be inspected before any application begins. Spray guns, hoses and pumps shall be cleaned before new material is added. Coating materials containing heavy pigments that have a tendency to settle shall be kept in suspension during the application by the power driven, continuous agitatorSpray gun shall be held at right angles to the surface and each pass overlap the previous one by approximately 50%. BRUSH APPLICATIONBrushes shall be of a style and quality that permit proper application of the materialBrushing shall be done so that a smooth coat as nearly uniform in thickness as possible is obtained without any deep or detrimental marksPaints shall be worked into all corners and crevices. FILM THICKNESSSpecified film thickness for coating materials shall be strictly adhered to and observed by checking with an appropriate film thickness gauge. In hot weather such additional precautions as are necessary shall be taken to ensure that the specified dry film thickness on priming or finish coats is obtainedCOATING QUALITYCoatings shall be free from pinholes, voids, bubbles, dust, foreign inclusions and any such defect shall be repaired. Prior to the application of a coating, any damage to the previous coating shall be repaired with the specified material. TEST EQUIPMENTCoating thickness meter such as Elcometer ‘Minitector” Model 150Wet fill thickness combsEPOXY COATING Priming shall be applied over the whole area to be coatedThere shall be strict control of surface cleanliness between primer and epoxy coating / and between coats of the same. Vacuum removal of dust and sand shall be employed and contamination removed. Where dirt or dust has been trapped in the painted surface, it shall be removed with suitable abrasive paper. The surface being painted shall be free of visible moisture throughout these operationsThe paint shall be applied only to the clean dry primed or previously coated surfaces. Any thick runs or collections of paint shall be removed before these hardenThe colour of the final coat shall be as approved. The manufacturer of the coating shall stipulate primer and epoxy recoat interval for all curing temperatures likely to be encountered and these be adhered to with a maximum tolerance of +4 hours. Where this is exceeded, surfaces to be recoated shall first be suitably abraded to remove gloss and provide a keyWet thickness gauges shall be used by the coating operators continually to check that sufficient paint is being applied to achieve the desired dry film thicknessFloor finishesStatements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 457: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

457 of

Cl2 storage shall be cement screed ½ % slope with Cl2 resistant finishDetailsDosing room shall be cement screed ½ % slope with acid resistant finishDetailsHVAC rooms shall be floor tilesDetails given aboveControl room shall be with floor tiles with special skirting for electrical equipmentDetails given aboveQuality Metering building Instance 4After excavation, blinding, concrete protection activities are completed in a similar manner as explained in instance 1 & 2, the preparatory works for the pipe duct shall be carried out to the design locationFoundation structural beams shall be constructed Foundation slab shall be carried out similarly with column starter rebarsStructural RCC columns shall be constructed accordinglyPreparation shall be carried out for the centring & shuttering for the suspended cast in situ slabPreparation shall be carried out for placing rebars Concrete Pouring arrangement shall be carried out all according to the requirementRCC Parapet shall be constructed according to the shown layoutCivil Contractor QC inspection shall be conducted according to concrete pour ITP & checklist requirement Wall finishesInternally to be plastered & emulsion paintExternal surface to be emulsion paintConcrete surface shall be fair face & epoxy coatedFloor finishesshall be cement screed ½ % slope with floor tilesMajor Equipment.Excavator 1 #Shovel 1 #Dumper trucks 2 #sDrum Vibratory Roller / Compactor 1 #Water tanker as & when required (The aforesaid equipment are required only for excavation operations)Concrete Batching plantWater tanker as & when required Concrete pump to requirementConcrete transit mixers to requirementThermometers for maxima / minima & ambientAll testing equipment such as slump cone, air voids Hessian rolls to requirementPlastic sheets to requirementInternal Vibrators to requirement (5000-10000 cycle / minute)Compressors to requirementAttachmentSketches & design of RCC precast coverPaint system table

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 458: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

458 of

TopBlinding concrete1. ScopeThe purpose of this statement is to define the procedure that shall be adopted for the preparation and placement of blinding concrete prior to subsequent activities.2. Reference documentsDrgs # Concrete General SpecificationsDrgs # GA at Ground Floor LevelQCS 3. ResponsibilitiesThe responsibilities regarding the supervising personnel on Site shall be according to Project Approved Quality PlanProject Manager / Engineer shall arrange all materials, equipment & man power for the item & direct the Site Engineer & Foreman to resort appropriate action for the smooth execution of the item. All materials for the immediate as well as set concrete curing shall be arranged by himSite Engineer shall direct the surveyor for the setting out lines & levels in conjunction with the Project EngineerSurveyor shall be responsible to set out form lines & establish top of blinding levels.Surveyor shall also prepare the pre pour survey report in conjunction with Site Engineer for check by QA EngineerQA Engineer shall check the report as well as the setting out all according to drawings & request inspection by Company4. SafetyThe Safety Engineer / Officer shall monitor and implement all HSE and environmental precautions.All persons involved shall be imparted tool box talk for the activities concerned & shall use PPE aw well as other required equipment whenever necessary5. MaterialSRC 20 from Ready Mix Qatar6. MethodThe surveyor set out the relevant line and level information in such a manner that the Foreman can relate the data to the tradesmen.Prior to commencing blinding, the formation shall be made to required levels & profiles. Timber forms shall be erected for the required thickness of 100 mm from the formation level. Necessary top of blinding levels shall be fixed The trades man shall erect suitable battens and rails to the correct outside lines and finished level of the blinding concrete. Where intermediate level rails are required, these shall be installed such that removal of them as concrete progresses can be achieved efficiently.When the blinding battens and rails are completed, the Site Engineer shall conduct line and level checks with the surveyor. QC Engineer shall check the correctness of the work done all according to design & specificationsStatements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 459: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

459 of

Prior to application of anti-termite treatment, Contractor QA / QC Engineer shall inspect the formation and RFI be prepared for the Company inspectionAnti-Termite application shall be carried out on the footing areas.Anti-termite treatment shall be applied according to specialist method statement.The Foreman & Site Engineer shall ensure that the formation level has been inspected, tested and approved prior to the commencing any blinding activity.The blinding concrete shall be placed by direct pour method. The blinding concrete shall be finished to a smooth surface. The occurrence of ripples or protrusions shall be avoided as the application of the protective membrane requires a smooth surface finish.The blinding concrete, when sufficiently set, shall be covered with hessian and water cured for specified period.7. Major EquipmentConcrete transit mixer, Batching Plant, Hand tools8. Attachment -Inspection Check Sheet9. Review of concrete test result & filing system- Cubes taken by the concrete supplier at arrival of the truck mixer at the Site shall be tested on 7 & 28 days in the presence of Company / Contractor QA Engineers, results recorded & signed by all parties immediately. All results shall be forwarded to Company office for information & necessary action if any, due to failure on any of 7 or 28 days. Filing of these results shall be made by the Contractor DCC based on QA & Project Engineer direction so as these reports are conveniently traceable

Blinding concrete1. ScopeThe purpose of this statement is to define the procedure that shall be adopted for the preparation and placement of blinding concrete prior to subsequent activities.2. Reference documentsDrgs # Concrete General SpecificationsDrgs # GA at Ground Floor LevelQCS 3. ResponsibilitiesThe responsibilities regarding the supervising personnel on Site shall be according to Project Approved Quality PlanProject Manager / Engineer shall arrange all materials, equipment & man power for the item & direct the Site Engineer & Foreman to resort appropriate action for the smooth execution of the item. All materials for the immediate as well as set concrete curing shall be arranged by himSite Engineer shall direct the surveyor for the setting out lines & levels in conjunction with the Project EngineerSurveyor shall be responsible to set out form lines & establish top of blinding levels.Surveyor shall also prepare the pre pour survey report in conjunction with Site Engineer for check by QA EngineerStatements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 460: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

460 of

QA Engineer shall check the report as well as the setting out all according to drawings & request inspection by Company4. SafetyThe Safety Engineer / Officer shall monitor and implement all HSE and environmental precautions.All persons involved shall be imparted tool box talk for the activities concerned & shall use PPE aw well as other required equipment whenever necessary5. MaterialSRC 20 from Ready Mix Qatar6. MethodThe surveyor set out the relevant line and level information in such a manner that the Foreman can relate the data to the tradesmen.Prior to commencing blinding, the formation shall be made to required levels & profiles. Timber forms shall be erected for the required thickness of 100 mm from the formation level. Necessary top of blinding levels shall be fixed The trades man shall erect suitable battens and rails to the correct outside lines and finished level of the blinding concrete. Where intermediate level rails are required, these shall be installed such that removal of them as concrete progresses can be achieved efficiently.When the blinding battens and rails are completed, the Site Engineer shall conduct line and level checks with the surveyor. QC Engineer shall check the correctness of the work done all according to design & specificationsPrior to application of anti-termite treatment, Contractor QA / QC Engineer shall inspect the formation and RFI be prepared for the Company inspectionAnti-Termite application shall be carried out on the footing areas.Anti-termite treatment shall be applied according to specialist method statement.The Foreman & Site Engineer shall ensure that the formation level has been inspected, tested and approved prior to the commencing any blinding activity.The blinding concrete shall be placed by direct pour method. The blinding concrete shall be finished to a smooth surface. The occurrence of ripples or protrusions shall be avoided as the application of the protective membrane requires a smooth surface finish.The blinding concrete, when sufficiently set, shall be covered with hessian and water cured for specified period.7. Major EquipmentConcrete transit mixer, Batching Plant, Hand tools8. Attachment -Inspection Check Sheet9. Review of concrete test result & filing system- Cubes taken by the concrete supplier at arrival of the truck mixer at the Site shall be tested on 7 & 28 days in the presence of Company / Contractor QA Engineers, results recorded & signed by all parties immediately. All results shall be forwarded to Company office for information & necessary action if any, due to failure on any of 7 or 28 days. Filing of these results shall be made by the Contractor DCC based on QA & Project Engineer direction so as these reports are conveniently traceableStatements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 461: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

461 of

Receipt, fabrication and storage of reinforcement1. ScopeThe purpose of this statement is to define the procedure that shall be adopted for the material receipt, fabrication and storage of reinforcement.2. Reference documentsDrgs # Concrete General SpecificationsAll Structural Drawings & Contractor’s produced BBS documentsQCS3. ResponsibilitiesThe responsibilities regarding the supervising personnel on Site shall be according to Project Approved Quality PlanProject Manager / Engineer shall arrange all materials, equipment, scaffolding, safety related items & man power for the item & direct the Site Engineer & Foreman to resort appropriate action for the smooth execution of the item. Site Engineer shall direct the rebar foremen / charge hand for the correct application to BBS in conjunction with the Project EngineerQA Engineer shall involve physically during fabrication & check the fabricated rebars all according to drawings & Bar Bending Schedule4. SafetyThe Safety Engineer / Officer monitor and implement all HSE and environmental precautions.All persons involved shall be imparted tool box talk for the activities concerned & shall use PPE as well as other required equipment whenever necessary5. MaterialAll re-bars shall be procured from the approved source according to material submittal documentation recordsThe Project Engineer, QA Engineer & store man shall ensure that any reinforcement materials received upon Site is in accordance with the specification requirements, purchase order and quality documentation requirements.The store man shall inform the QA / QC department when a delivery of reinforcement is made.The store man and QA / QC shall review the reinforcement delivery and complete the Material receiving report. The quality documentation shall be kept by the QA / QC department & filed accordingly.When the incoming material inspection is completed and acceptable, the reinforcement material shall be stored in the reinforcement fabrication yard in the appropriate storage facilities.6. Method

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 462: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

462 of

When reinforcement is to be “cut and bent,” the Foreman shall be issued with a current rebar schedule by the Project Engineer. The Site Engineer, QA & rebar Foreman shall review the schedule and allocate the fabrication process to the relevant fabricator / steel fixer. Material required shall be sourced from the yard storage facilities.The correct bar diameter shall be cropped into the specified length as given on the bar schedule. The cropping steel fixer shall crop the required bars of each diameter.Upon bending of the first of each bar type, it shall be checked by the Site Engineer, QA & Foreman for correctness. This bar if examined correct, shall be utilized as a check sample for all concurrent bars of that type. The bending steel fixer shall fabricate the required number of bars of each shape code checking against the check sample when each bar is completed. Any error in bending of the bars shall be corrected prior to placement in storage.The correct bent bars shall be stored in bundles & protected against ingress of moisture using plastic sheet cover at the end of the day.The bundles shall be tagged with a suitable label that indicate the relevant bar reference and BBS document reference from which these have been fabricated.The completed bundles shall be stored within the reinforcement yard until such time as those are required upon Site. Storage shall be in accordance with the procedure for store control by taking into stock the delivered quantity into permanent material file & issuing to Site for the required quantity for fabricationDetails for the total reinforcement required for the Project & the delivered quantity shall be recorded7. Major EquipmentBar cropper & Bar bending 8. Attachment BBS Proforma

Block works above grade level1. ScopeThe purpose of this statement is to define the procedure that shall be adopted for the construction of block works above grade level & upper floors.2. Reference documentsSpecification Section 53. ResponsibilitiesThe responsibilities regarding the supervising personnel on Site shall be according to Project Approved Quality PlanProject Manager / EngineerShall arrange all materials required such as concrete blocks, cement, washed Sand, water etc & ensure that the activity is carried out according to the contract & QCS / QNBS as well as all quality procedures are strictly adhered to.Project Quality EngineerShall control & supervise the activity making sure that the work is done according to quality procedures & ITPs & proceed for Company approval Site Engineer / Foreman

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 463: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

463 of

Shall carry out the execution of item physically according to the direction given by Project Engineer as well as Quality Engineer4. SafetyThe Safety Engineer / Officer shall monitor and implement all HSE and environmental precautions.All persons involved shall be imparted tool box talk for the activities concerned & shall use PPE as well as other required specific equipment whenever necessaryShall make sure that at higher levels of work, proper scaffolding as well as access arrangements are made5. MaterialBlocks 200 mm wide, Cement, Coarse Sand, Water, Wall ties (Catnic), Cavities ties (Catnic), Expanded Polystyrene 50 mm thick, Polythene sheets as specified6. MethodThe surveyor shall set out the relevant line on the beams or the slabThe surface to receive block work shall be cleared of all dust, dirt & oily material Prior to commencing block work, the concrete surface shall be made to required level & profile by mortar laying adjustment so that preferably whole number of block courses are formed.Mason shall establish the course profile line using string & level letting string pass around end control blocksWall ties shall be fixed to the RCC columns as required by shotfiring or concrete nails at every 4th courseMixing of Mortar 1:3 (1 cement: 3 c sand)The mortar layer shall be laid on the formation & leveled.Mortar shall be mixed using a small concrete mixer on SiteSand & cement shall be piled up near by mixerA timber measuring box shall be used to ensure that 1:3 ratio is maintained for dry mixing of cement & sand respectivelyDry washed sand shall be poured into mixer keeping the drum rotating & then cement added gentlyWhen both materials show a uniform colour of dry mix, required quantity of water shall be added into the drumMixing shall be allowed for a minimum period of 3 minutes to produce quantity of mortar sufficient to be consumed within one hour Laying of block coursesFirst layer shall be laid to the established profile on concrete surface width wise keeping block stretcher parallel to wall giving 10 to 12 mm gap for the mortar fillingMortar shall be filled into the gaps using mason trowelMortar shall be laid over the whole course 10 to 12 mm thick uniformly spread & leveledBlocks shall be kept on the bottom layer gently so that the joint of both are staggeredBlock shall be cut square if requiredMortar shall be filled into the joints as well as on the top surface, lined & leveledSimilarly further layers shall be formedNot more than 5 layers shall be constructed in one dayAll layers shall be true vertical & in horizontal profileStatements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 464: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

464 of

A gap 12 to 20 mm to be filled later with compressed filler board shall be left between the wall top & the beam / slab soffit in non suspended ceiling areasWall surface shall be cleaned using wire brush to take off all mortar peels & protrusionsAll joints shall be well surfaced & trowel raked in to make it good enough to receive plaster / renderingBlock cavities at the corners, junctions and column ties shall be filled with concreteNext day if required for further block layer, previous layer shall be cleaned well & further operation carried out & curing for the bottom layers done by spray water from sidesCuring shall be carried out to make sure that all the mortar is cured to a minimum of 3 daysCavity wallsBoth inner & outer skin walls shall be raised simultaneouslyExpanded Polystyrene & polythene sheet as vapour barrier shall be inserted between these skin walls Cavity ties shall be embedded into mortar layers placed perpendicular to the wall axis sloped towards outer skin @ spacing of 900 mm horizontally as well as 600 mm verticallyCare shall be taken not to permit any mortar falling into cavity7. Major EquipmentMechanical Mixer, Sand Measuring box, Hand tools

Plastering & Rendering the block walls & RCC surfaces1. ScopeThe purpose of this statement is to define the procedure that shall be adopted for plastering & rendering the block walls & RCC surfaces. ‘Rendering’ applies to external surface while ‘plastering’ applies to internal surface 2. Reference documentsSpecification Section 53. ResponsibilitiesThe responsibilities regarding the supervising personnel on Site shall be according to Project Approved Quality PlanProject Manager / EngineerShall arrange all materials required such as, cement, plaster sand water etc & ensure that the activity is carried out according to the contract & QCS / QNBS as well as all quality procedures are strictly adhered to.Project Quality EngineerShall control & supervise the activity making sure that the work is done according to quality procedures & ITPs & proceed for Company approval Finishing Engineer / ForemanShall carry out the execution of item physically according to the direction given by Project Engineer as well as Quality Engineer

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 465: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

465 of

4. SafetyThe Safety Engineer / Officer shall monitor and implement all HSE and environmental precautions.All persons involved shall be imparted tool box talk for the activities concerned & shall use PPE aw well as other required specific equipment whenever necessaryShall make sure that at higher levels of work, proper scaffolding as well as access arrangements are made5. MaterialCement, Plaster Sand, Water, Furring & Lathing (Internal Galvanized Steel, External Stainless Steel)6. MethodPreparation of backgrounds to be plastered or renderedAll surfaces to be plastered and rendered shall be thoroughly cleaned of all dust and loose particles. All bituminous & water repelling agents shall be removed if present on the surface Concrete surfaces shall be scabbled by mechanical means to remove all laitance exposing the aggregates to 3 mm depthContractor & Company inspections shall be conducted for the approval of the prepared surfaces.A slurry coat consisting of 400 kg Cement (white) to 1 cum of sand (No. 1 White Silica) as specified shall be applied on the surface by trowel and 1-day allowance given for the succeeding coat to commence with.Block work surfaces shall have the joints raked out as specified during construction.Junctions of different background and the chases for the electrical conduits as well as other service pipes shall be treated by fixing approved 200mm wide metal lath. Plastering shall not commence until all the mechanical and electrical services, conduits, pipes and Ist stage fixtures have been installed and approved.Where a rendering or plaster is to be continuous across backgrounds of different types, a strip of metal lath minimum 300 mm wide with an isolating membrane of polythene sheet or building paper behind, shall be fixed across the junction.Where small widths of one material less than 300 mm wide are involved e.g. a concrete column, beam or slab dividing block panels, the width shall be bridged completely for a distance of 150 mm on both sides.The metal lath shall be stretched out and fixed along each edge at 100 mm centres using steel fasteners such as washers and shot fired pins, nails or screws and lapped joints tied with galvanized wire, the screws fixed into plugs in predrilled holes if so required.Metal lath shall not be provided where drawing shows a groove in the rendering or the plaster.Fixing beads and stopsBeads, stops and the like shall be fixed plumb, square and true to line with clout nails or plaster dabs at not more than 600 mm centres to each mesh wing.Corner / angle beads at all openings as well as plaster ground stops at terminals shall be installed by using steel fasteners. Plaster profile dots shall be formed on the surfaces.All aforesaid activities shall be carried out under Contractor QA / QC checkCompany inspection shall be conducted for the proposed profile approval.

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 466: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

466 of

Preparation of mixes for plastering or renderingSlurry coat400 kg cement: 1 cum sandBase coat300 kg cement: 50 kg lime: 1 cum sand (1200 kg)Finish coat300 kg cement: 10 kg lime: 1 cum sand (900 kg)Plaster thickness According to drawings & specifications.Total thickness 15 mm internal, 20 mm externalThe hydrated lime shall first be thoroughly mixed with sand and then cement added keeping mixer on until the material is uniform in appearance, suitable to receive water which at this stage be added in sufficient quantity to produce the mix stuff workable, uniform in colour and consistency.To improve the workability of the mix, the hydrated lime, sand and water may first be mixed in the required proportion with allowance to stand undisturbed for at least 16 hours before mixing with cement. If allowed to stand for a longer period, the ingredients mix must be protected from drying out. The whole of the batch shall be used within an hour of being mixedMixing of semi dry mortar The mortar layer shall be laid on the formation & leveled.Mortar shall be mixed using a small concrete mixer on SiteSand, lime & cement shall be piled up near byA timber measuring box shall be used to ensure that the required ratio is maintained for dry mixing of cement & sand respectivelyDry washed sand shall be poured into mixer keeping the drum rotating & then cement added gently followed by hydrated limeWhen added materials show a uniform colour of dry mix, required quantity of water shall be added into the drum to produce semi dry mortarMixing shall be allowed for a minimum period of 3 minutes to produce quantity of mortar sufficient to be consumed within one hour Application of the various plaster or render coatsThe work shall not start until the background has been prepared and all the services have been finished according to requirement and the relevant specifications as described earlier.Slurry coat for proper adhesion shall be trowel applied allowing at least one day to start the succeeding coat Two plaster or render coat applications shall be carried out.Before applying any coat, the background or the preceding coat shall be brushed down to remove any loose particles and dampened sufficiently to ensure uniform absorption.First coat shall be trowel applied either by laying on with or throwing from a trowel or float, as uniformly thick as possible and not less than 8 mm or more than 13 mm thick in any part and scored to form a key for the second or final coat allowing at least one day before the start of the next coat.During this application care shall be taken to make sure that the material is well worked into the laths for proper embedmentStatements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 467: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

467 of

This coat shall be left rough and open by the edge of the trowel after it has been long enough to set firm, be combed with evenly spaced wavy horizontal lines approximately 20 mm apart and 5 mm deep (less in case of first coat on metal lathing). First coat applied to metal lathing shall be well worked into the lath to ensure that the material is completely embedded.The finishing coat shall be steel trowel appliedThe finishing coat shall not be less than 5 mm or more than 10 mm thick and shall be laid on with a trowel and finished with a steel float, taking care not to over work the surface.All coats shall be applied with firm pressure to exclude air and to ensure a good bond.Plaster shall be rodded and straightened to uniform surfaces in true planes. Laps of one coat shall not occur over laps of preceding coat. Each coat shall finish free from cracks, checks or other structural defects. Finish surfaces shall be flush with grounds / stop beads, corner beads, outlet boxes and similar details, free from trowel marks, other blemishes displaying straight arises and true angles.All coats shall be prevented from drying out too quickly and the work be carried out in shade during hot period. All renderings shall be protected by properly constructed hessian or similar net shade screen during hot periodEach coat shall be kept damp by means of a fog spray of water for a minimum of 3 days to allow before a subsequent coat is applied or in the case of a finish coat, before the protective screens are removedThe surface of the finish coat shall be smooth, true and free from waviness, irregularities or blemishes with straight, level or plumb angles. External angles shall be pencil roundedCare shall be taken when rendering up to beads or stops to avoid excessive polishing at the arris and damage to the galvanizing.All aforesaid activities shall be carried out under Contractor QA / QC Engineer checkInspections for the Company approval shall be requested.7. Major EquipmentMechanical Mixer, Sand Measuring box, Hand tools8. Attachment - Checklist, ITPMechanical Mixer, Sand Measuring box, Hand tools

Roofing system1. ScopeThe purpose of this statement is to define the procedure that shall be adopted for application of roofing system2. Reference documentsSpecification Section 5.b3. ResponsibilitiesThe responsibilities regarding the supervising personnel on Site shall be according to Project Approved Quality PlanProject Manager / Engineer

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 468: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

468 of

Shall arrange all materials required through the sub contractor ensure that the activity is carried out according to the contract & Specificationsas well as all quality procedures are strictly adhered to.Project Quality EngineerShall control & supervise the activity making sure that the work is done according to quality procedures & ITPs & proceed for Company approval Finishing Engineer / ForemanShall carry out the execution of item physically according to the direction given by Project Engineer as well as Quality Engineer4. SafetyThe Safety Engineer / Officer shall monitor and implement all HSE and environmental procedures.All persons involved shall be imparted tool box talk for the activities concerned & shall use PPE as well as other required specific equipment whenever necessaryShall make sure that at higher levels of work, proper scaffolding as well as access arrangements are madeNecessary measures shall be applied to any process involving a safety risk5. MaterialCement, Plaster Sand, Water, Foaming agent, Polystyrene, Geotextile / Terram, Waterproofing membrane, Paver, Lime chips, Aluminum flashing (All items according to approvals)6. MethodSpecialist ContractorSpecialist approved sub contractor shall be engaged for this system executionMethodThe roofing system shall be carried out to the following operational sequences.Concrete surface shall be scabbled mechanically or if approved by Company my be acid etched to remove laitance On the existing RCC suspended slab all large foundations if any, shall be constructed prior to commence any roofing system operation.A groove shall be formed around the periphery of the area, on the pad foundations and other up-stands at a specified height from the slab level for tugging waterproofing membrane into the parapet with sealant applied over.All services drains or other necessary items required to be in place prior to the roofing commences, shall be completed in all respects including grouting. The area shall be cleared and made dry. Company Inspection shall be conducted.These quantities are indicative only. Actual mix design shall be included by the sub contractorThe lightweight screed using special foam concrete shall be laid in to the following mix design to produce a density of 650 to 750 Kgs / cumSand / Cement: 1 / 1 Cement: 350 Kg / cumSand: 350 Kg / cumStatements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 469: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

469 of

Water: 210 Lit / cumFoaming agent: 1.2 Lit / cumThe ingredients shall be mixed using a mechanical mixer, an aerator and a pump.The surfaces to be laid with screed shall be formed using mortar dabs to the specified profiles to 1 % slope. The ‘foam concrete screed’ shall be laid in two layers to avoid settlement. The second layer shall be laid when the first has dried out followed by forming smooth finish to the required falls and cross-fallsCompany Inspection shall be conductedThe completed screed shall be cured with fresh water for two days and thereafter, left for one day to dry out.A cement sand angle fillet of 50 x 50 mm triangular cross section shall be formed at all directional changes.Before laying water proofing membrane, a coat of bituminous primer shall be applied to all the proposed surfaces. Once dried, laying in of water proofing membrane shall be commenced with by full torching over the primed screed allowing 100mm wide side and end overlaps. The dressing shall be carried out over the angle fillet and up-stands properly terminating into pre formed grooves by tugging the membrane into the groove as well as rainwater outlets and around penetrations.Exposed vertical surface of the membrane shall be protected by applying MGP flashing membrane 300 mm girth, mineral surface finished, UV resistant, torched over main membrane and tugged into groove as aforesaid.Application on the AC foundation & up-stands shall be carried out according to the details shown on the sketchCompany Inspection shall be conducted & ITP signed offWhole surface shall be flooded with water for a period of 72 hours after plugging in all roof drainsAfter successful completion of the test, water shall be drained out and the membrane left to dry out. Extruded polystyrene insulation boards with rebated edges 50 mm thick shall be laid over the dry membrane ensuring all areas are properly covered.TERRAM membrane with 100-mm overlaps shall be laid over top of the insulation boards. All small and light pre cast pedestals / foundations for the cable trays, pipe supports etc., if any, shall be loosely laid over the filter membrane.Company inspection shall be conducted by the manufacturer’s representative and all coordination made.A warranty for the specified period of 10 years shall be issued by the specialist contractor and Contractor according to the contract requirementConcrete pavers in the form of pre cast concrete tiles 400mm x 400 mm x 40 mm shall be laid loose over PVC TILE PADS to be provided at all the intersections and at the corners as shown on the sketch. At the borders where cut tiles may be required, gravel (nominal size 19 – 38 mm) filling shall be carried out to create a good aesthetic.The membrane shall be tugged into the groove and sealed with JOINT SEAL bituminous Mastic.Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 470: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

470 of

Plain mill Aluminum flashing of required girth, cut and bent to the given profile, shall be fastened with stainless steel screws above the groove, covering and protecting the sealant all according to details.Major EquipmentMixer, Aerator, PumpAttachmentITP & check list

Laying ceramic floor tiles1. ScopeThe purpose of this statement is to define the procedure that shall be adopted for Laying ceramic floor tiles on RCC floor surfaces. 2. Reference documentsSpecification, Appendix ASection 53. ResponsibilitiesThe responsibilities regarding the supervising personnel on Site shall be according to Project Approved Quality PlanProject Manager / EngineerShall arrange all materials required through the sub contractor ensure that the activity is carried out according to the contract & Specificationsas well as all quality procedures are strictly adhered to.Project Quality EngineerShall control & supervise the activity making sure that the work is done according to quality procedures & ITPs & proceed for Company approval Finishing Engineer / ForemanShall carry out the execution of item physically according to the direction given by Project Engineer as well as Quality Engineer4. SafetyThe Safety Engineer / Officer shall monitor and implement all HSE and environmental precautions.All persons involved shall be imparted tool box talk for the activities concerned & shall use PPE as well as other required specific equipment whenever necessaryProper illumination shall be provided in the dark area The area to be tiled shall be closed for the general movement except those working there and be opened only when the tiling has properly been completed with hardboard cover protection spread on the newly laid flooring.5. MaterialsApproved Ceramic floor tiles 200 x 200 x 8 mm, or 150 x 150 x 8 mm as approvedJoint filling grout – Approved proprietary material with matching shade.6. Method (Laying ceramic floor tiles by SEMI DRY method)

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 471: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

471 of

A continuous procedure to lay tiles over the cement mortar screedThe areas of concrete sub strata to be tiled shall be brush cleaned and dampened until absorption ceases followed by the finished floor level establishment by means of dots and rules. Application of Water Proofing treatment shall be carried out for the wet areas.The total thickness of the ceramic tile flooring is 100 mm which includes 90 mm bedding screed (1 cement: 4 mortar sand) by weight and shall be applied as described below.The finishing layer shall be 10 mm thick and be laid as described below.The mortar for bedding the tiles shall be 1 part cement to 4 parts sand by weight, mixed semi dry by a mechanical mixer with only sufficient water added to give a crumbly consistency which retains its shape when squeezed by hand permitting no fluidityThe mix shall be placed to a thickness approximately 10 mm greater than that actually required for the bed, thoroughly compacted by tamping and drawing off to the required level with a screed board. Only sufficient mortar shall be mixed and spread as can be covered with tiles before it attains its initial set. Company visual inspection shall be conducted A slurry of 1 part cement to 1 part sand by volume shall be poured over the surface of the semi – dry mix bedding and spread with a trowel until it is approximately 2 mm thickDry tiles shall then be laid on the slurry and beaten firmly into position with a wooden beater ensuring a true surface contact between the tiles and bedding is formed.The tiles shall be correctly positioned in both directions the time these are placed forming joints using a proprietary tile spacer (1.5 mm for wall tiles and 3 mm for floor tiles)The tiles shall neatly and accurately be cut to a close fit where necessary at abutments, around outlets, pipes and the like.Company Inspection shall be conducted for the correct formation of joint alignment and the level profileThe tiles shall be laid level or to 1- % falls in ‘wet’ areas as may be required. Localized variations in level for a nominally flat floor shall be a maximum of +- 2-mm under a 3-meter straight edge. Particular care shall be taken in ‘wet’ areas to prevent low spots that may promote water pooling. The tolerance in the overall level shall not be more than 10 mm from required finishes. Grouting of the joints shall be carried out within a period of not less than 24 hours after completion of laying of tiles so as to allow the grout attach itself firmly to the bedding. MOVEMENT JOINTS IN TILED FLOORSUnless otherwise indicated in the documents, a 10 mm movement joint shall be formed at the perimeter of all the tiled floors and where the tiling meets structural features such as columns, machine bases etc.,Where a structural movement joint is provided in the base, a movement joint of the same width in the bedded finish shall be positioned immediately aboveThe movement joint cavities shall extend through the combined thickness of the finish and the bedding mortar, completely filled and sealed after grouting of the normal joints takes place.Major EquipmentMechanical Mixer, Sand Measuring box, Hand tools, Tiles cutterAttachmentStatements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 472: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

472 of

ITP & check list

Laying ceramic floor tiles1. ScopeThe purpose of this statement is to define the procedure that shall be adopted for Laying ceramic floor tiles on RCC floor surfaces. 2. Reference documentsSpecification Appendix ASection 53. ResponsibilitiesThe responsibilities regarding the supervising personnel on Site shall be according to Project Approved Quality PlanProject Manager / EngineerShall arrange all materials required through the sub contractor ensure that the activity is carried out according to the contract & Specificationsas well as all quality procedures are strictly adhered to.Project Quality EngineerShall control & supervise the activity making sure that the work is done according to quality procedures & ITPs & proceed for Company approval Finishing Engineer / ForemanShall carry out the execution of item physically according to the direction given by Project Engineer as well as Quality Engineer4. SafetyThe Safety Engineer / Officer shall monitor and implement all HSE and environmental precautions.All persons involved shall be imparted tool box talk for the activities concerned & shall use PPE as well as other required specific equipment whenever necessaryProper illumination shall be provided in the dark area The area to be tiled shall be closed for the general movement except those working there and be opened only when the tiling has properly been completed with hardboard cover protection spread on the newly laid flooring.5. MaterialsApproved Ceramic floor tiles 200 x 200 x 8 mm, or 150 x 150 x 8 mm as approvedJoint filling grout – Approved proprietary material with matching shade.6. Method (Laying ceramic floor tiles by SEMI DRY method)A continuous procedure to lay tiles over the cement mortar screedThe areas of concrete sub strata to be tiled shall be brush cleaned and dampened until absorption ceases followed by the finished floor level establishment by means of dots and rules. Application of Water Proofing treatment shall be carried out for the wet areas.The total thickness of the ceramic tile flooring is 100 mm which includes 90 mm bedding screed (1 cement: 4 mortar sand) by weight and shall be applied as described below.The finishing layer shall be 10 mm thick and be laid as described below.Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 473: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

473 of

The mortar for bedding the tiles shall be 1 part cement to 4 parts sand by weight, mixed semi dry by a mechanical mixer with only sufficient water added to give a crumbly consistency which retains its shape when squeezed by hand permitting no fluidityThe mix shall be placed to a thickness approximately 10 mm greater than that actually required for the bed, thoroughly compacted by tamping and drawing off to the required level with a screed board. Only sufficient mortar shall be mixed and spread as can be covered with tiles before it attains its initial set. Company visual inspection shall be conducted A slurry of 1 part cement to 1 part sand by volume shall be poured over the surface of the semi – dry mix bedding and spread with a trowel until it is approximately 2 mm thickDry tiles shall then be laid on the slurry and beaten firmly into position with a wooden beater ensuring a true surface contact between the tiles and bedding is formed.The tiles shall be correctly positioned in both directions the time these are placed forming joints using a proprietary tile spacer (1.5 mm for wall tiles and 3 mm for floor tiles)The tiles shall neatly and accurately be cut to a close fit where necessary at abutments, around outlets, pipes and the like.Company Inspection shall be conducted for the correct formation of joint alignment and the level profileThe tiles shall be laid level or to 1- % falls in ‘wet’ areas as may be required. Localized variations in level for a nominally flat floor shall be a maximum of +- 2-mm under a 3-meter straight edge. Particular care shall be taken in ‘wet’ areas to prevent low spots that may promote water pooling. The tolerance in the overall level shall not be more than 10 mm from required finishes. Grouting of the joints shall be carried out within a period of not less than 24 hours after completion of laying of tiles so as to allow the grout attach itself firmly to the bedding. MOVEMENT JOINTS IN TILED FLOORSUnless otherwise indicated in the documents, a 10 mm movement joint shall be formed at the perimeter of all the tiled floors and where the tiling meets structural features such as columns, machine bases etc.,Where a structural movement joint is provided in the base, a movement joint of the same width in the bedded finish shall be positioned immediately aboveThe movement joint cavities shall extend through the combined thickness of the finish and the bedding mortar, completely filled and sealed after grouting of the normal joints takes place.Major EquipmentMechanical Mixer, Sand Measuring box, Hand tools, Tiles cutterAttachmentITP & check list

Building drainage systemScope The purpose of this statement is to define the procedure that shall be adopted for the installation, testing & commissioning of the building drainage system.Reference documents

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 474: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

474 of

Drgs # Concrete General Specifications referencesResponsibilitiesThe responsibilities regarding the supervising personnel on Site shall be according to Project Approved Quality Plan.Project Manager / Project Engineer shall arrange all materials, equipment, scaffolding, safety related items & man power for the item, direct the Site Engineer & plumbing Foreman to resort appropriate action for the smooth execution of the item. All materials for the disciplinary works shall be arranged by him.All working as well as shop drawings shall be prepared & submitted to Company for approval under his supervision.All permanent material pertaining to this discipline shall be submitted for Company approval & procured accordingly.Site Engineer shall direct the surveyor for the setting out lines & levels in conjunction with the Project Engineer & plumbing Foreman / coordinator. Surveyor shall be responsible to set out drainage lines & establish bedding levels. Site Engineer & Contractor QA / QC Engineer shall check all alignments & levels according to approved drawings & make sure that all works comply with specifications & request inspection by CompanySafetyThe Safety Engineer / Officer shall monitor and implement all HSE and environmental precautions.All persons involved shall be imparted with tool box talk for the activities concerned & would use PPE as well as other required equipment whenever necessary.All access to the work location at higher levels shall be checked & tagged by the safety Engineer.MaterialApproved pipes & fittings, bedding material (dune sand)MethodPrior to the commencement of the drainage works at the time of the below grade slab backfill, necessary PVC sleeves shall be inserted into RCC beam or block wall depending on the pipe level at the building line.

Backfill shall be carried out in layers & compacted all according to agreed procedure given somewhere else.

Pipe route shall be set out by the surveyor & checked by the Contractor Site as well as QA / QC.

Excavation shall be carried out in the compacted backfill to the trench width & depth from floor trap location to the building external wall from where, the pipe shall be embedded in the external landscape.

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 475: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

475 of

Proper slope or gradient shall be formed from inlet point at floor trap level to the building line calculated from the Manhole IL & the pipe level at Manhole inlet.

After all excavation is carried out for the pipe route & all other pipes for the area, granular bedding 130 mm thick shall be done & pipe laid to the prepared bedding & joints made according to manufacturer’s specification or instructionAlignment shall be corrected to the design profile & levels checkedPortion of the pipe shall be temporarily anchored to hold the pipe from uplift during testingContractor QA / QC shall check the laid pipe according to ITP & request Company Engineer for witnessing the testWater or air test as practical shall be conducted according to specifications & approval granted if the leakage is within acceptable limits or the pipe passes successfully defined air pressure.Similarly all other pipes shall be testedAfter the test is successful, granular backfill shall be carried out according to specification up to 300 mm top of pipeSimilarly all pipes shall be fixed from the WC seats to the building line to the Manhole & vertical stacks shall be provided on the walls for the vent pipe systemVertical stack shall be clamped into walls according to the standard details. These pipes shall be true plumb & joints filled according to the manufacturer’s specification & contract specifications.Rain water as well as condensate discharge from the terrace shall be collected, using given slope of 1 % to 1.25% to the roofing system graded on the foam concrete course, to the outlets provided at the locations shown on the contract as well as shop drawings & the standard details. This discharge shall be collected at these rain water units & further discharged into the vertical stacks of rain water pipes fixed in plumb & connected to the French drains to be constructed to the standard details, through the pipes located below the external landscape.These external pipes shall be laid to the specified grade from building line / bend to the outlet end into the French drain on the excavated & prepared concrete bedding 150mm thick over blinding 75 mm thick over 130 mm thick granular bedding for the hard landscape portionFor the pipe portion in the soft landscape portion, bedding shall be carried out by sand After initial testing & approval, surrounding concrete 150 mm thick shall be laidBackfill shall be carried over the surrounding concrete as well as over the soft fill material all according to specificationsAll pipes shall be checked by Contractor QA / QC Engineer & Company as well as final testing shall be conducted at final commissioning.EquipmentAll tools, testing apparatusAttachmentInspection Check Sheet

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 476: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

476 of

Floor screed

ScopeThis statement is aimed to propose the procedures to be adopted to lay the floor screed For the vinyl tile and the epoxy floor finishesReference documentsGround Floor PlanFirst Floor PlanSpecifications ResponsibilitiesThe responsibilities regarding the supervising personnel on Site shall be according to Project Approved Quality Plan.Project Manager / Project EngineerShall arrange all materials required ensuring that the activity is carried out according to the contract & Specificationsas well as all quality requirements procedures are strictly adhered to.Project Quality EngineerShall control & supervise the activity making sure that the work is done according to quality procedures, ITPs & proceed for Company approval. Finishing Engineer / ForemanShall carry out the execution of item physically according to the direction given by Project Engineer as well as Quality Engineer.SafetyPrior to commencement of any activity, the labour force shall receive a STARRT Card / Toolbox Talk relevant to the operation concerned on the Project Site safety requirements. Necessary measures shall be applied to any process involving a safety risk.Safety Supervision A competent officer shall visit the area daily to assess the safety measures being adopted. Any snag observed during visit, shall be notified to the supervisor present who immediately would act to bring the safety measures to an acceptable standard MaterialsCement, washed sand, bonding agent, waterMethod (Laying floor screed by SEMI DRY method)All the rooms shall be laid in full area in one go.

The proposed designated area shall be laid according to the location of joints as shown on shop drawing separately.

Scabbling of the concrete surface shall be carried out if so required, for proper bonding with the hardened surface or etching the surface if so agreed by Company.(Etching requires 10% concentration hydrochloric acid to be mixed with water for forceful application on RCC or Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 477: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

477 of

concrete surface followed by immediate washing out by water, which process roughenes the concrete surfaces. Border of portions to be applied etching, are taped for adjoining protection from scouring). Benefit of etching is that ot avoids scabbling or hacking.

The concrete surface shall be cleared of all loose particles and cleaned using hard wire brush to ensure achievement of sufficient roughness to receive the screed.

The levels up to which the floor screed is to be laid, shall be profiled by using Mechanical leveling points with steel pipes to maintain levels so that complete compartment is given a proper level. The cleaned area shall be soaked with water 24 hours prior to the application of screed.

Contractor QC & Company inspection shall be conducted for the examination pertaining to the preparatory works for the ‘ready to pour’ compartments.

Application After the preparation for the area or alternate bays or strips of 1500 mm width or as sized on, site is madeup with all levels, cleaned, duly soaked in water for 24 hours and ready for pouring, the prepared surface shall be spread with cement slurry ratio 1:1 (1 part cement and 1 part sand) mixed with mix quality water.

The mortar for screed shall be mixed semi dry by a mechanical mixer with only sufficient water added to give a crumbly consistency, which retains its shape when squeezed by hand permitting no fluidity.

One layer application with 1:2.5 cement – screened sand mortar.The mix shall be placed in one layer progressively to a thickness approximately 10 mm greater than that actually required, thoroughly compacted by tamping and drawn off to the marked level with a screed board.

In case, thickness of screed is more than 75mm, 8 mm T re-bars shall be placed in both directions @ 300 mm c / c to protect cracks formation.

After compacting the layer of mortar, the surface shall be finished by a steel power float to achieve a smooth surface ready to receive the vinyl tiles or the epoxy painting floor finishes and then, covered with polythene membrane for immediate curing.

The finished surface shall be permanently cured by adding water soaked hessian after a few hours of finishing and recovered with polythene sheet. The surface shall be kept wet for a period of 3 days and then protected with hard boards spread over till the floor finishes are applied over the surface. No traffic shall be allowed over the finished surface.

Throughout the above operations, Contractor QC visual inspection shall be conducted.Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 478: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

478 of

Prior to full-scale commencement of the screeding operation, a sample shall be produced on site in the presence of Company representative so that, an agreement pertaining to the stated procedures to carry out the screeding and about the Quality could reach. Major EquipmentMechanical MixerWheel barrowsMason’s tools in generalPower floatAttachmentITP

Concrete interlocking blocksScopeThis statement is aimed to propose the procedures to be adapted to lay kerbstones and concrete interlocking blocks in paving around buildingsReference DocumentsSite Development PlanMiscellaneous Details 2 & 6Specification ResponsibilitiesThe responsibilities regarding the supervising personnel on Site shall be according to Project Approved Quality PlanProject Manager / Project EngineerShall arrange all materials required through the subcontractor ensuring that the activity is carried out according to the contract & Specifications as well as all quality requirement procedures are strictly adhered to.Project Quality EngineerShall control & supervise the activity making sure that the work is done according to quality procedures & ITPs & proceed for Company approval Road Engineer / ForemanShall carry out the execution of relevant item physically according to the direction given by Project Engineer as well as Quality EngineerSafetyPrior to commence with any activity, the labour force shall receive a STARRT Card / Toolbox Talk relevant to the operation concerned on the Project Site safety requirements.Necessary measures shall be applied to any process involving a safety riskSafety Supervision A competent inspector shall visit the area daily to assess the safety measures whether or not, being rightly adopted. Any snag observed during visit shall be notified to the supervisor present who immediately, would act to bring the safety measures to an acceptable standard. MaterialStatements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 479: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

479 of

Approved Kerb stones, Approved Interlocking Paving blocks Red as well as Grey or other approved colour according to landscaper design drawings & specifications.Method All loose soil shall be cleared and formation level made up to defined requirement, well compacted properly to specifications & approved pesticide treatment applied.(Laying Kerb stones) Setting out kerb excavation lines according to as shown on drawing.

Excavation up to the formation level i.e. 450mm from the kerb top level.

Form work fixing and pouring grade 20 concrete 450mm wide and 150 mm thick.

Form work fixing and pouring grade 20 concrete 150mm wide and 150 mm thick high.

Pouring grade 20 concrete all according to approved procedures;

Fixing 12 T re-bars @ 200 c / c vertically supported to forms.

Bedding in cement mortar 1 :3, 25mm thick for kerb stones grade 20.

Fixing kerb on the mortar to the true lines and levels with chamfer facing pavement & jointing with mortar. Alignment tolerance shall be 3 mm in 75 mm both ways vertically as well horizontally. End to end butting mortar thickness shall be 3 mm.

Placing haunch back fillet concrete grade 20, as shown in (triangular fillet section)

Filling up to top of vertical concrete with earth fill & compaction. All areas below proposed interlocking course to be filled with 100 mm thick sand screed all according to conventional procedures.

Contractor QC inspection shall be conducted for kerb laying approval and ITP requested to be signed off by Company.

(Laying Paving Interlocking blocks)Thickness of the interlocking blocks 60mm.

Thickness of the sand screed bedding 100mm.

Plank runs shall be used to allow barrows to move on to avoid level disturbance.

First, surveyor shall set plotting the pattern borders all according to shop drawing as well as design drawings.

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 480: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

480 of

First, Grey colour interlock blocks shall be laid to position & profiled to form the border pattern or as agreed with Company.

The blocks shall be laid in full but at the edges of the obstacles such as inspection covers where cut blocks may be required, whole blocks shall be laid first wherever possible and the trim able blocks exactly marked & cut to the required size.

After profile is well formed to the Company approval, the fill in course to the border areas shall be carried out by laying Red colour blocks.

After sufficient blocks have been laid, sand bedding shall be carried out using a plate vibrator pressing the blocks to the required level in 2 passes covering entire area with each pass to make the bedding even.

Sand screed shall be spread on the surface of the blocks with 2 more vibrator passes applied & brushed under the leading edge of the vibrator to allow the joints vibrated.

Contractor QC inspection shall be conducted & Company requested to approve the paving.Major EquipmentPlate CompactorAttachmentITPs

Roads Works on the Drive waysScopeThe objective of this statement is to outline the procedures to be adopted to carry out the Roads Works on the Drive waysSub Grade - 200mmSub Base Class B-150mmPrime Coat MC 1Base Course BC Type 1- 80mmTack CoatWearing Course SC Type 1- 40mmReferences:Site Development PlanMiscellaneous Details 2Specification ResponsibilitiesThe responsibilities regarding the supervising personnel on Site shall be according to Project Approved Quality PlanProject Manager / Engineer

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 481: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

481 of

Shall arrange all materials required through the sub contractor ensure that the activity is carried out according to the contract & Specificationsas well as all quality procedures are strictly adhered to.Project Quality EngineerShall control & supervise the activity making sure that the work is done according to quality procedures & ITPs & proceed for Company approval Road Engineer / ForemanShall carry out the execution of item physically according to the direction given by Project Engineer as well as Quality EngineerSafetyPrior to commence any activity, the labour force shall receive a STARRT Card / Toolbox Talk relevant to the operation concerned on the Project Site safety requirements.Necessary measures shall be applied to any process involving a safety riskSafety Supervision A competent officer shall visit the area daily to assess the safety measures adopted. Any snag observed during his visit shall be notified to the supervisor present who immediately act to bring the safety measures to an acceptable standard MaterialApproved Sub Base Class B Approved Prime Coat MC1Tack CoatPremixed bituminous binder course and wearing course materials shall be supplied from Approved central batching, mixing & heating plant MethodThe following sequences shall be involved to do the road workClearing all services according to the Project drawings and inspections / ApprovalsPreparation of the area to be structured by removing top soil, placing in imported fill material, profiling levels to the Project drawing & compaction.Applying pesticide treatment if requiredApplication of all pre work items such as construction of kerb stone to complete section of detail 2 given on Project drawing Miscellaneous details 2Prepared surface shall be inspected by Contractor and CompanySub base class B material shall be spread on the area in strips of required thickness keeping more than design thickness by 25mm i.e. 150+25 mmSub base approved fill material to interlock the class B material shall be spread on the spread material & dry rolling carried out to produce correct profile of the sectionWater shall be sprayed on the surface to make it penetrate in to & around all the voids of the spread material & compaction by heavy roller started to densify the whole course.After required number of passes probably 6 given by 18 to 12 tonne rollers bringing the laid material to the required thickness 150 mm & exhibiting rebound on the surface, the compaction by rolling shall ceaseDensity test shall be conducted all according to approved ITPs requirement

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 482: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

482 of

Compacted course shall be left for drying in due course allowing it to be ready to receive Prime Coat MC1. Drying time shall not be less than 48 hoursPrior to the start of the Prime course spreading, any repair observed during visible inspection shall be repaired in rectangular or square shape or as agreed with CompanyAsphalt concreteAsphalt concrete shall be laid in widths of drive way roads according to the Project drawingWearing course thickness being 40mm & that of dense bitumen binder course 80mmPaving works shall be carried out in 2 stagesStage 1Laying & compacting bottom bituminous binder course Stage 2Laying & compacting top wearing carriagewaySurface preparation Prior to the application of the dense bitumen binder course, already laid & compacted aggregate base course shall be prepared suitable for this purposeBase course shall be corrected of any deviation more than 13mm from the designed profile at any point & not more than 9mm in 3m on the longitudinal grade at any location by either adding to or removing from the surface the deficient or redundant material respectively to bring the surface to the design shape, watered & compacted in accordance to the specification all as stated aboveMain Operations The following main operations are involvedRe-preparation of aggregate base course surface with water & compaction by pneumatic roller Application of Priming coat & drying outApplication of 60mm thick dense binder coursePower brooming the completed dense binder courseApplication of Tack coat & drying outApplication of 40mm thick bitumen concrete wearing courseMixingAll materials shall be mixed at Approved calibrated & approved Asphalt plantAll trucks and other equipment as included shall be readily available for inspection TransportationMaterial shall be transported from the plant to the planned location in good condition by trucks cleaned of all foreign material & covered with tarpaulin to prevent dust invasion in inclement / adverse weather conditions It shall be ensured by obtaining observations using thermometer that the material when laid is within 130 to 165 CApplicationCoverage Primer coat 0.8 to 1.4 litre / m^2Tack coat 0.4 to 0.7 litre / m^2PrimerContractor QC inspections shall be conducted to ascertain the correct profile of the aggregate base course & corrections applied if so requiredStatements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 483: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

483 of

All surfaces planned to be primed shall be barricaded & cleaned of all dirt & any objectionable materialBituminous material shall be applied evenly on the dry surface by means of a pressure distributor spray tanker within a temperature 30 to 70 C SurfacingBinder CourseContractor QC inspection shall be conducted prior to the commencement of binder course laying to make sure that the surface is satisfactorily clean, well dried & even to the specified priming conditions & to receive binder course The material upon arrival at the location shall be spread & struck off to the prepared profile by means of self powered spreading & finishing equipment attached with a strike off assembly distributing the mixture to a strip 3 m wideRollingSteel Roller’s # of passes 6 to 8 depending on the surface conditionSteel rollers 10 T capacity equipped with adjustable wheel scrapes, water tanks & sprinkling apparatus to keep the wheel sufficiently wet to prevent the bituminous mixture from sticking to the steel surface shall be employed to roll the profiled material immediately after the material is laid to the acceptable profile to prevent the formation of undue displacement or hair crackingThe roller wheels shall be kept properly moistened without excess water or oilRolling shall be commenced from the side and proceed towards the centre each trip overlapping the previous by at least 300 mm with keeping alternate trip not more than 5 km / h & it shall continue until the surface is impression freeMechanical compactors shall be engaged to compact the roller inaccessible area layersPneumatic tyred rollers shall be engaged only after the compaction by wheel roller is overIt is significant to make sure that the asphalt temperature does not fall below 80 C prior to full compaction is achievedRoller shall not pass over the edges of the freshly laid material generally except when the edge is located at a discontinuation for that dayContractor QC inspection shall be conducted throughout the above operations to make sure that the material is compacted to the standards and the temperature remains within limits mentioned as well as levels are maintained within specification tolerances particularly over the areas involving shouldersAt the commencement of the work on the area involving the compacted & chilled edge, a bevel shall be cut out, cleaned & tack coat applied to receive adjoining materialNo traffic shall be permitted until 12 hours lapse post rolling completionWearing CourseThe planned surface shall be cleared of all dust & dirt using power broom or blowingTack coat shall be applied to the specification requirementImmediately upon arrival the material shall be spread & rolled similarly as described in the foregoingContractor QC inspection shall be conducted throughout the above operations to make sure that the material is compacted to the standards and the temperature remains within limits mentioned as well as levels are maintained within specification tolerances

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 484: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

484 of

Major EquipmentRequired for the binder courseCentral Mixing Asphalt plant 1#Trucks 1 #s 38 Tonnes capacity eachPaver 1 #s, 1 # with 6m / 3m wide blades Steel wheel Tandem Rollers 1 #s, 10 Tonnes capacity, 1# ,15 Tonnes capacityPneumatic Tired Rollers (tyre inflatable at 0.62 Mpa ) -1 #s 38 T & 1 #s 20 TAir Compressor 1 #Asphalt Cutting Machine 1#Plate Compactor 1 #Jumping Jack Compactor 1 #Spray Tanker 1 #Additionally required for the Wearing Course Power BroomVacuum CleanerAttachmentITPs

Roads Works on the Drive ways (Revised)ScopeThe objective of this statement is to outline the procedures to be adopted to carry out the Roads Works on the Drive waysSub Grade - 200mmSub Base Class B-150mmPrime Coat MC 1Base Course BC Type 1- 80mmTack CoatWearing Course SC Type 1- 40mmReferences:Site Development PlanMiscellaneous Details 2 (use your reference)Specification (use your reference)ResponsibilitiesThe responsibilities regarding the supervising personnel on Site shall be according to Project Approved Quality PlanProject Manager / EngineerShall arrange all materials required through the sub contractor ensure that the activity is carried out according to the contract & Specificationsas well as all quality procedures are strictly adhered to.Project Quality EngineerShall control & supervise the activity making sure that the work is done according to quality procedures & ITPs & then would proceed for obtaining Company approval Road Engineer / ForemanStatements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 485: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

485 of

Shall carry out the execution of item physically according to the direction given by Project Engineer as well as Quality EngineerSafetyPrior to commence any activity, the labour force shall receive a STARRT Card / Toolbox Talk relevant to the operation concerned on the Project Site safety requirements.Necessary measures shall be applied to any process involving a safety riskSafety Supervision A competent officer shall visit the area daily to assess the safety measures adopted. Any snag observed during the visit shall be notified to the supervisor present who immediately would act to bring the safety measures implemented to an acceptable standard Material (all according to approvals)Approved Sub Base Class B Approved Prime Coat MC1Tack CoatPremixed bituminous binder course and wearing course materials shall be supplied from Approved central batching, mixing & heating plant MethodThe following sequences shall be involved to do the road work.

Clearing implementation of all services works according to the Project drawings and inspections / Approvals completed.

Preparation of the area to be road structured by removing top soil, placing in imported fill material, profiling levels to the Project drawing & compaction.

Applying pesticide treatment if so required.

Application of all pre work items such as construction of kerb stone to included section of detail 2 given on Project drawing Miscellaneous details 2 (ndicate your reference)

Prepared surface shall be inspected by Contractor and Company

Sub base class B material shall be spread on the area in strips of required thickness keeping more than design thickness by 25mm i.e. 150+25 mm

Sub base approved fill material to interlock the class B material shall be spread on the spread material & dry rolling carried out to produce correct profile of the section.

Water shall be sprayed on the surface to have it penetrate into & around all the voids of the spread material & compaction by heavy roller started to densify the whole course.

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 486: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

486 of

After required number of passes probably 6 given by 18 to 12 tonne rollers bringing the laid material to the required thickness 150 mm & exhibiting rebound on the surface, the compaction by rolling shall cease.

Density test shall be conducted all according to approved ITPs requirement

Compacted course shall be left for drying in due course, allowing it to be ready to receive Prime Coat MC1. Drying time shall not be less than 48 hours.Prior to the start of the Prime course spreading, any repair observed during visible inspection shall be repaired in rectangular or square shape or as agreed with Company

Asphalt concreteAsphalt concrete shall be laid in widths of drive way roads according to the Project drawingWearing course thickness being 40mm & that of dense bitumen binder course 80mmPaving works shall be carried out in 2 stagesStage 1Laying & compacting bottom bituminous binder course Stage 2Laying & compacting top wearing carriagewaySurface preparation Prior to the application of the dense bitumen binder course, already laid & compacted aggregate base course shall be prepared suitable for this purposeBase course shall be corrected of any deviation more than 13mm from the designed profile at any point & not more than 9mm in 3m on the longitudinal grade at any location by either adding to or removing from the surface the deficient or redundant material respectively to bring the surface to the design shape, watered & compacted in accordance to the specification all as stated aboveMain Operations The following main operations are involveRe-preparation of aggregate base course surface with water & compaction by pneumatic roller Application of Priming coat & drying outApplication of 60mm thick dense binder coursePower brooming the completed dense binder courseApplication of Tack coat & drying outApplication of 40mm thick bitumen concrete wearing courseMixingAll materials shall be mixed at Approved calibrated & approved Asphalt plantAll trucks and other equipment as included shall be readily available for inspection TransportationMaterial shall be transported from the plant to the planned location in good condition by trucks cleaned of all foreign material & covered with tarpaulin to prevent dust invasion in inclement / adverse weather conditions It shall be ensured by obtaining observations using thermometer that the material when laid is within 130 to 165 CStatements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 487: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

487 of

ApplicationCoverage Primer coat 0.8 to 1.4 litre / m^2Tack coat 0.4 to 0.7 litre / m^2PrimerContractor QC inspections shall be conducted to ascertain the correct profile of the aggregate base course & corrections applied if so requiredAll surfaces planned to be primed shall be barricaded & cleaned of all dirt & any objectionable materialBituminous material shall be applied evenly on the dry surface by means of a pressure distributor spray tanker within a temperature 30 to 70 C SurfacingBinder CourseContractor QC inspection shall be conducted prior to the commencement of binder course laying to make sure that the surface is satisfactorily clean, well dried & even to the specified priming conditions & to receive binder course The material upon arrival at the location shall be spread & struck off to the prepared profile by means of self powered spreading & finishing equipment attached with a strike off assembly distributing the mixture to a strip 3 m wideRollingSteel Roller’s # of passes 6 to 8 depending on the surface conditionSteel rollers 10 T capacity equipped with adjustable wheel scrapes, water tanks & sprinkling apparatus to keep the wheel sufficiently wet to prevent the bituminous mixture from sticking to the steel surface shall be employed to roll the profiled material immediately after the material is laid to the acceptable profile to prevent the formation of undue displacement or hair crackingThe roller wheels shall be kept properly moistened without excess water or oilRolling shall be commenced from the side and proceed towards the centre each trip overlapping the previous by at least 300 mm with keeping alternate trip not more than 5 km / hour & it shall continue until the surface is impression freeMechanical compactors shall be engaged to compact the roller inaccessible area layersPneumatic tyred rollers shall be engaged only after the compaction by wheel roller is overIt is significant to make sure that the asphalt temperature does not fall below 80 C prior to full compaction is achievedRoller shall not pass over the edges of the freshly laid material generally except when the edge is located at a discontinuation for that dayContractor QC inspection shall be conducted throughout the above operations to make sure that the material is compacted to the standards and the temperature remains within limits mentioned as well as levels are maintained within specification tolerances particularly over the areas involving shouldersAt the commencement of the work on the area involving the compacted & chilled edge, a bevel shall be cut out, cleaned & tack coat applied to receive adjoining materialNo traffic shall be permitted until 12 hours lapse post rolling completionWearing CourseThe planned surface shall be cleared of all dust & dirt using power broom or blowingStatements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 488: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

488 of

Tack coat shall be applied to the specification requirementImmediately upon arrival the material shall be spread & rolled similarly as described in the foregoingContractor QC inspection shall be conducted throughout the above operations to make sure that the material is compacted to the standards and the temperature remains within limits mentioned as well as levels are maintained within specification tolerances Major EquipmentRequired for the binder courseCentral Mixing Asphalt plant 1#Trucks 1 #s 38 Tonnes capacity eachPaver 1 #s, 1 # with 6m / 3m wide blades Steel wheel Tandem Rollers 1 #s, 10 Tonnes capacity, 1# ,15 Tonnes capacityPneumatic Tired Rollers (tyre inflatable at 0.62 Mpa ) -1 #s 38 T & 1 #s 20 TAir Compressor 1 #Asphalt Cutting Machine 1#Plate Compactor 1 #Jumping Jack Compactor 1 #Spray Tanker 1 #Additionally required for the Wearing Course Power BroomVacuum CleanerAttachmentITPs

Preparatory works pertaining reinforcement placement1. ScopeThe purpose of this statement is to define the procedure that shall be adopted for the preparatory works pertaining reinforcement placement on Site for all elements2. Reference documentsDrgs # Concrete General SpecificationsAll Structural Drawings & Contractor’s produced BBS documents3. ResponsibilitiesThe responsibilities regarding the supervising personnel on Site shall be according to Project Approved Quality PlanProject Manager / Engineer shall arrange all fabricated materials, binding wires, scaffolding, safety related items & manpower/workforce for the item & direct the Site Engineer & Foreman to resort appropriate action for the smooth execution of the item.

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 489: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

489 of

Site Engineer shall direct the rebar foremen / charge hand for the correct application all according to design & details to place the fabricated as well as well on Site cut re-bars in conjunction with the Project EngineerQA Engineer shall involve role physically during placement & check the assembled re-bars all comply or be in line according to drawings & details4. SafetyThe Safety Engineer / Officer shall monitor and implement all HSE and environmental precautions.All persons involved shall be imparted tool box talk for the activities concerned & shall use PPE as well as other required specific equipment whenever necessary5. MaterialAll fabricated re-bars shall be taken from the fabrication yard on Site location for placement. (generally, on industrial projects, practice of fabrication rebarssoffsites is made a contract condition for keeping the working site tidy)6. MethodThe relevant reinforcement bars, spacer blocks, chairs, stirrups and tie wire, shall be collected from the stores as well as fabrication yard and made available at the work Site. The material shall be stored at the workSite, in accordance with the storage procedure pertaining to fabricated & non fabricated re-bars.

The current revision of the reinforcement drawing that applies to the structure being constructed shall be checked by the Project Engineer, Site Engineer, QA for validity. On updated drawings shall be used on site.

The steel fixers shall place and tie, reinforcement bars and accessories, in accordance with the current reinforcement drawing under direct supervision of re-bar Foreman.

Particular attention to the following items shall be monitored by the chargehand steel fixer and Foreman:

Lap length of bars.Tie wire protrusions into cover areas (protrusions should be in to the non cover core areas).Appropriate concrete cover to formwork and outside faces.Placement of adequate support chairs and stirrups.Spacing of bars.

The Site Engineer & chargehand steel fixer / Foreman shall check the fabricated reinforcement when all the placement of the reinforcement bars are complete. The result of this inspection shall be recorded upon Pre concrete inspection check list by Site Engineer & QA.

The Foreman steel fixer shall ensure that the reinforcement has been correctly placed prior to informing the Site Engineer & QC.

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 490: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

490 of

QC shall check all items of different shapes, spacing & numbers, spacer blocks, additional chairs if required.

Should any inserts, conduits, pipes, bolts etc. require fixing within the structure according to design details or shop drawings, the steel fixer Foreman shall arrange for the placement of these items according to directions by Project Engineer / Site Engineer. Where a reinforcement bar clashes with such items, based on the decision of Company Engineer, Project or Site Engineer, the steel fixer shall move the relevant bar. An additional bar may be required to offset this moved bar. Should any doubt arise about moving bars, the chargehand shall inform the Foreman & Site Engineer to resolve the issue with the Company Engineer.

The Foreman shall inform the Site Engineer when these activities are complete.

The QC shall inspect the re-bars placed in the structure for compliance with the design drawings and details as well as other working and shop drawings.

The Company inspection shall be conducted based on QA recommendations after complete checking

7. Major EquipmentAppropriate material transportation arrangement to work location. Generally trailors are used.8. Attachment Check list proforma

Pouring of concrete1. ScopeThe purpose of this statement is to define the procedure that shall be adopted for the pouring of concrete into various elements of the structures such as foundations, stub columns, ground beams, grade slab, super structure columns, beams & suspended slabs, stairs, boundary walls2. Reference documentsDrgs # Concrete General SpecificationsAll Structural Drawings, contract documents Specifications section 5 (indicative)3. ResponsibilitiesThe responsibilities regarding the supervising personnel on Site shall be according to Project Approved Quality PlanProject Manager / Engineer shall arrange concrete from batching plant, scaffolding, temporary access to Site requirement, safety related items & manpower for the item & direct the Site Engineer & Foreman to resort appropriate action for the smooth execution of the item. Site Engineer shall direct the foremen / charge hand for the correct application of pours all according to specification & convention in conjunction with the Project Engineer. Site Engineer shall be physically available to control the pour

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 491: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

491 of

QA Engineer shall involve physically during pouring & check the slump, temperature, air volume etc all according to agreed procedures, codes & specification requirement4. SafetyThe Safety Engineer / Officer shall monitor and implement all HSE and environmental precautions.All persons involved shall be imparted with tool box talk for the activities concerned & shall use PPE as well as other required equipment whenever necessaryProper scaffolding shall be arranged for the formworks5. MaterialReady Mix Concrete From Qatar Ready Mix grade M 20, M 35 (Approved)Approved concrete repair compound for post pour repair if so necessary6. MethodThe supply order for estimated quantity may be placed in advance but real confirmation shall be done based on the pour approval.

After the inspections of the preparatory works pertaining to any element namely footings, stubs, columns, suspended slabs etc & the relevant approval by Company, the order for the release of concrete from the batching plant shall be placed.

The required quantity shall be sequenced depending on the consumption frequency on Site,

The concrete shall be poured either by the concrete pump or by the mobile crane depending on the necessity & convenience. Necessary access to the location shall be prepared using proper supports or platforms duly inspected by the safety in charge.

Immediately, at the arrival of the truck mixer of concrete on Site, slump, temperature, air voids etc. all to the specification requirement shall be taken care of by the ready mix supplier in the presence of the QA & Company Engineer.

In case the concrete does not meet the specification requirement, the truck load shall be liable to be rejected.

Arrangement shall also be made for the filling of the concrete cubes on Site to specification requirement according to standard procedures.

After the truck is approved by the QA / Company, has to be transported to the Site location, where the pump equipment shall receive the concrete load & pump out into the in situ delivery location.

The concrete laying gang already present on the Site location shall receive & pour the concrete mix into the prepared elements from not more than 2 m.

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 492: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

492 of

As soon as, enough mix is available in the element to compact the mix conveniently, insertion vibrator shall be used by a trained operator to compact the mix till no more bubbles appear.

Vibrator shall not be allowed to touch the forms side or re-bars.

Over vibration shall not be permitted.

Each Footing shall be poured in one go if not more than 500 mm in depth.

The widened portion of the stub in touch with soil shall also be poured in strips not more than 450 mm deep.

Into columns, the mix depth at one rotation shall be 450 mm & in different strips vertically, pouring shall be completed avoiding formation of cold joint.

Into lift well walls, the mix depth at one rotation shall be 450 mm & in different strips vertically, pouring shall be completed avoiding formation of cold joint.

Top level of the concrete shall be leveled & the columns / lift well wall form top covered with plastic sheet.

The portion of the pipe chute shall be inserted into column preparatory works to allow for a 2 m maximum vertical fall. Vertical forms of the columns shall be struck after 48 hours.

Inspection shall be made immediately post formstriking & any defect observed in concrete shall be brought to Company Engineer’s notice for deciding remedial action.

Vertical surface shall be covered with saturated Hessian further covered with polythene sheet or alternatively, curing compound shall be sprayed over the water wet surface to form a impermeable membrane not to permit evaporation.

The grade slab shall be poured in one go in depth bay wise between ground beams.

For the suspended slabs, beams shall be poured first around the slab & prior to the formation of cold joint, the slab concrete shall be poured & the whole slab completed. The joints if so required, shall be agreed in the beginning of the pour with the Company Engineer. Water shall be sprayed over the form during hot weather prior to pouring to avoid flash setting of concrete with re-bars.In case some plant’s breakdown is reported, immediately the last poured line shall be stopped by a formed surface arrangement to terminate concrete pour at that point & in no way, shall recommence prior to 24 hours with further approval obtained. In such case, previous formed Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 493: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

493 of

joint shall be scabbled / hacked to expose all aggregate by removing laitance completely, washed with cement slurry & new concrete pour commenced making proper bond with old concrete.

Due care shall be taken that no spacers, electric conduits or any other insert is disturbed from its design or worked location. If so disturbed, it shall be immediately relocated according to the Company Engineer Site approval.

Immediately after the compaction of concrete is over & concrete starts setting in, arrangements for applying U1 finish to the top of slab surface shall be done by timber tampering.

Immediate curing shall be applied by spreading polythene sheet cover on wet slabs & footings.

Then after about 2 hours, polythene sheet shall be withdrawn temporarily & saturated hessian placed over concrete & then, recovered with polythene sheet & concrete cured for specified period prabbly 7 yo 14 days depending on the defined specifications. Curing compound suits curing purpose only during the initial stages on the slabs but, later, water curing is required. Curing compound is either wax based or water based that works to 60% effective extent while water works to near equivalent laboratory conditions.

If so, repair to hardened concrete is required, approved repair material shall be used according to manufacturer’s instructions.

7. Major EquipmentBatching plant, transit trucks, mobile crane, vibrators, curing compound sprayer8. Attachment Quality check forms, Material sampling & testing forms

Post concrete repair1. ScopeThe purpose of this method statement is to define the general criteria for the post concrete repair to all structures & elements.2. Reference documentsConcrete General SpecificationsAll Structural Drawings 3. ResponsibilitiesThe responsibilities regarding the supervising personnel on Site shall be according to Project Approved Quality PlanProject Manager / Engineer shall arrange all required materials in time, scaffolding, temporary access to repair location, safety related items & man power for the item & direct the Site Engineer & Foreman to resort appropriate action for the smooth repair concerned. Site Engineer shall direct the foremen / charge hand for the correct application of repairs according to manufacturer’s specification / instruction & method statement in conjunction with Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 494: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

494 of

the Project Engineer. Site Engineer shall be physically available & be responsible to supervise the repair application in conjunction with QA / QCQA Engineer shall involve physically during repair, all according to manufacturer’s & agreed procedures & specification requirement4. SafetyThe Safety Engineer / Officer monitors and implement all HSE and environmental precautions.All persons involved shall be imparted tool box talk for the activities concerned & shall use PPE as well as other required equipment whenever necessaryAll precautions shall be adopted to protect attacks by propriety chemicals according to manufacturer’s instructions & proper disposal of the used items5. MaterialApproved concrete repair compound6. MethodUpon removal of the formwork, the concrete surface shall be inspected by the QA / QC & Site Engineer to establish if any surface defects have occurred.

Where no surface imperfections have occurred, the concrete surface shall be cured according to the relevant procedures included in concrete method statement i.e. application of curing by spraying curing compound to form a continuous membrane or by continuous application of water.

Minor defects as described in A – D below shall be repaired as soon as practical. More significant defects as described in E – H shall be subject to joint inspection / agreement between Company and Contractor.

A. Pin holes / blow holesWhere small defects to the concrete surface have occurred, such as pin holes or holes smaller than 3mm in diameter or depth, the surface shall be repaired using Nitomortar FC or equivalent other with compatible bonding agent Nitobond AR. This surface repair shall be conducted as soon as the formwork is removed whilst the concrete is still green.

The repair shall then be left for curing in for 24 hours using cover of polythene sheet on the repaired surface. Prior to polythene sheet covering, Nitobond AR shall be applied by brush on repaired surface

B. Sand runs / scouringWater movement inside the shutter can result in a streaky appearance with a loose sandy finish.Contractor QA / QC & Site Engineer shall inspect the struck surface & if such runs are observed, discuss with Company, who may inspect visually & finalise for Nitomortar FC application.Any loose material shall be removed by stiff brushing and then repaired as ‘A’ above.

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 495: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

495 of

C. Plastic shrinkage cracksCracking caused by plastic shrinkage usually results in a series of diagonal cracks 0.5mm wide & 3 mm deep. Contractor QA / QC & Site Engineer shall inspect the surface & if such cracks are observed, discuss with Company engineer who may inspect visually & finalise for repair application

These shall be repaired by brushing dry cement powder directly into the cracks while the concrete is less than 3 days old and covering with damp hessian.

D. Minor misalignments (Typically Less than 2cm)Contractor QA / QC & Site Engineer shall inspect the surface & if such misalignment is observed, discuss with Company engineer who may inspect visually & finalise for repair application

Misalignments due to shutter movements etc. shall be ground back to provide a smooth transition between areas. Where occurring at joints between panels, the ground profile length shall be 2-3 times the size of the maximum misalignment. After grinding, the surface shall be reinstated using ‘Nitomortar FC (B) & bonding agent Nitobond AR. Care shall be taken to ensure that specified concrete cover is maintained all times.

E. Honey combing / segregation / minor voidsContractor QA / QC & Site Engineer shall inspect the surface & if such honeycombing observed, discuss with Company engineer who may inspect visually & finalise for repair application.

The repair shall be conducted as soon as the formwork is removed.

It shall consist of chipping the repair area free of laitance and exposing any voids. The repair area shall then be soaked with water and Nitobond AR bonding agent applied. The bonding agent shall not be allowed to dry. The area shall be troweled with Renderoc TG mortar. The Renderoc TG mortar material shall be troweled firmly into the repair area. Should the depth of the repair exceed 15mm, the repair shall be conducted in two layers, providing a scratch coat on the first layer. The repair shall then be cured in accordance with the agreed procedure using water or curing compound as appropriate.

Renderoc TG mortarMinimum applied thickness 10 mm,Large overhead sections up to 20 mm, Vertical sections up to 50 mm,Small pockets horizontally up to 100mm,Maximum length up to 3 m

F. Major voids (Typically Deeper than 5cm)

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 496: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

496 of

Contractor QA / QC & Site Engineer shall inspect the surface & if such honeycombing observed, discuss with Company who may inspect visually & finalise for repair application

This repair shall consist of chipping the affected area to remove any laitance and voids. Where reinforcement is exposed in a void, the surrounding concrete shall be chipped away to provide adequate space to place fresh concrete around the reinforcement. (Note - a distance of one and a half times the stone size shall be allowed around all exposed reinforcement). Formwork shall be provided to retain the fresh concrete repair. The chipped repair area shall be soaked and then be primed with a bonding agent such as Nitobond AR. The bonding agent shall not be allowed to dry.

The repair area shall be formed to retain the concrete such as letter box type form for vertical surface. Fresh concrete of the same grade as the surrounding concrete shall be used to repair the defect. This repair shall be carried out while concreting some other elements of the same grade of concrete as repair element. The repair shall be water cured along with the parent concrete. The surface finishes to the repair shall be as the same standard as the surrounding concrete.

G. Plastic settlement cracksCracking caused by settlement of concrete can result in a series of cracks which mirror the reinforcement pattern in horizontal surfaces or appear to arch on vertical surfaces.

Contractor QA / QC & Site Engineer shall inspect the surface & if such cracks observed, discuss with Company engineer who may inspect visually & finalise for repair application

Any such cracks shall be chased out to a depth of 10-15mm and filled with an epoxy mortar such as Renderoc TG.

H. Porous / spongy surfaceContractor QA / QC & Site Engineer shall inspect the surface & if such cracks observed, discuss with Company engineer who may inspect visually & finalise for repair application

All affected surfaces shall be ground back to good concrete usually only 2-3mm below the surface. The surface shall then be reinstated using Nitomortar as ‘A’ above.

All repairs noted above shall be recorded on the post-pour inspection form. It may not be necessary to raise a non-conformance report provided the repairs are carried out as indicated above and agreed with Company. Any repairs not covered by the above procedure shall be dealt with on a case-by-case basis and agreed with Company before commencing repairs.

AttachmentManufacturer’s datasheets pertaining to the following materialsNitomortar FC,Nitomortar FC (B),Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 497: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

497 of

Nitobond AR,Renderoc TG

Note- MBT equivalent materials shall also be used for the aforesaid repairs after Company approvals

Sewerage pipeline from the circular manhole located in the premises to the existing manhole on the street1. ScopeThe purpose of this statement is to define the procedure that shall be adopted for the laying of sewerage pipeline from the circular manhole located in the premises to the existing manhole on the street2. Reference documentsDrgs # S D Plan- Drainage & Surface Water Lay out3. ResponsibilitiesThe responsibilities regarding the supervising personnel on Site shall be according to Project Approved Quality PlanProject Manager / Engineer shall arrange all required materials in time, safety related items, manpower & direct the Site Engineer & Foreman to resort to appropriate action for the smooth execution of the item. Site Engineer shall direct the foremen / chargehand for the correct execution of all operations to specification & traditional convention in conjunction with the Project Engineer. Site Engineer shall be physically available & be responsible to control the operationsQA Engineer shall involve physically during operations to inspect all works all according to agreed procedures, codes & specification requirement4. SafetyThe Safety Engineer / Officer monitor and implement all HSE, Plant Operating Authority road safety & traffic smooth flow requirement.All persons involved shall be imparted with tool box talk for the activities concerned & all workers shall use PPE as well as other required equipment whenever & whatsoever necessary5. MaterialReady Mix Concrete From Qatar Ready Mix grade M 20, M 35 (Approved)Approved fill material, Asphalt premix etc6. MethodFirst of all, traffic scheme shall be implemented to divert the traffic all according to the road crossing permit granted by Plant Operating Authority.

The setting out shall be done from the CMH-1 manhole location to the existing manhole location on the road as indicated on the included plan (no attached in this copy of publication)

Portion of the road surface shall be removed mechanically Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.

Page 498: Industrial Conctruction Procedures guidelines · Web viewThere are 3 nos road crossings en-route at points 2, 5 and 6 on which temporary 150 mm dia pipe sleeves are to be inserted

A work based on personal experience for improving young engineers / students knowledge

Engineering Construction Method Statements Revision No: Original Work by P Eng Suraj Singh April 11, 2006 Page

498 of

Portion of the soil below the road surface & that from the CMH-1 location shall be excavated manually.

Any existing services discovered during manual excavation shall be intimated to Plant

Operating Authority as well as to the concerned department for raking proper action.

Excavation shall be carried out to the formation profile according to the defined IL + bedding concrete for the pipe.

Formation shall be properly dressed & compacted.

Inspection shall be conducted all according to ITP requirement.

Bedding concrete shall be laid, finished to defined profile & cured.

Extra strength vitrified pipe 150 mm dia shall be laid on the bedding & jointed.

A hole shall be made in the wall of existing manhole under official supervision, required pipe inserted accordingly & sealed.

Inspection shall be conducted all according to ITP requirement.

Testing shall be conducted as required after the pipeline is properly anchored.

Upon successful completion of the test, surrounding concrete shall be poured & cured.

Approved material shall be filled in layers duly compacted accordingly up to the formation level of the existing road.

Road course that was dismantled or removed, shall be reinstated to the original status to the satisfaction of the Engineer.

Immediately after the completion of the operations, traffic diversion shall be removed & traffic reinstated.7. Major EquipmentBatching plant, transit trucks 8. Attachment Drawing not included

Statements were written by Professional Eng Suraj Singh Project Manager as well as Senior Project Engineer. Most of these were approved by EPC Contractor & Company (no sketches have been included with these for AUTO CAD ) References too have been eliminated from the statements for secrecy requirement of the contract These presents to be used only for acedemical / knowledge exchange purpose. The works were executed for major oil companies. All these statements constitute management documents.