Industrial attachment of paramount textile ltd
-
Upload
mazadul-hasan -
Category
Engineering
-
view
1.699 -
download
23
Transcript of Industrial attachment of paramount textile ltd
1
INDUSTRIAL TRAININGCourse Code: Tex -4036
INDUSTRIAL ATTACHMENTPARAMOUNT TEXTILE LIMITED
2
Project Description
3
PARAMOUNT TEXTILE LIMITED AT A GLANCE
PARAMOUNT TEXTILE LIMITED
1. Name of the project : Paramount Textile Limited
2.Location : Gilar Chala,Sreepur, Gazipur.
3. Address : About 60 kms north of Dhaka city.
Factory :
Village:Gilar Chala, P.O: 1 No C&B Bazar
Thana:Sreepur,Dist:Gazipur, Bangladesh.
Tele-Fax: 880-6825 52555
4
Office:
Chaklader House (Level-6), House # 22,Road #113/A,
Gulshan-2,Dhaka-1212,Banladesh
Ph:(+8802) +8809890618,9890467 Fax:(8802)9890783
E-mail:[email protected] Web;www.paramountgroupbd.com
5. Board of directors :
Chairman& Managing Director.
Md. Shakhawat Hossain
7. Communication :The project is easily accessible by road.
8. Product name :Woven yarn dyed ,solid dyed .
100% Cotton & TC
9. Product Mix :
A) Gray fabric:
1. Solid dyed
2. yarn dyed.
a. Stripe.
b. Check.
5
B) Design.
a. In Tappet loom.
i. Plain.
ii. Twill.
iii. Sateen.
iv. Some combination weave which are posible in tappet.
v. Oxford. (Warp rib and weft rib).
vi. Queen’s Oxford.
vii. Matt.
b. In Dobby loom:
i. Various types of weave.
ii. Diamond.
iii. Diaper.
iv. Herring bone.
v. Honey comb.
vi. The design which are possible in 16 heald frames.
10.Annual production capacity : 18millions per year.
11.Factory area :Approx. 180acres.(including ETP)
12.Type of the factory :Horizontally integrated
13.No. of employees :Approx. 100.
14.Project cost :Approx. 2000million taka
15.Different Departments :
a) Adminstration.
6
b) Human Resource and DevelomentDept.
c) Weaving Preperatory
d) Weaving.
e) Woven finishing.
f) Yarn dyeing Dept.
g) Store.
h) Planning Dept.
i) Utility Dept.
j) Procurement
k) Merketing
Location description: Paramount Textile Limited is located in Sreepur, Gazipur
about 60 kms North from Dhaka while it takes about 90 minutes by bus.There
are available bus services from Mohakhali Bus Terminal and also from Gulistan
Bus Terminal.
Transport:
For the Paramount officer’s there are two micro bus and one private car which
carry them on to the factory from Dhaka.
Cost of Transport:
About 100Taka per head from Gulistan
HISTORY OF PARAMOUNT TEXTILE LIMITED:
Paramount Textile limited was incorporated under the companies Act(Act-8) of1994 in june 12, 2006 and went into commercial production in November 2008
7
Man Power Management
8
Oraganogram
Chariman
Deputy Managing Director
Executive Director (Operation) Executive Director(Finance & Accounts)
G. M. (Admin, H. R., Compliance) DGM (A/F)
Manager (Admin / HR) Manager (Compliance) Manager (Purchase)
Executive Executive Executive
Jr. Executive Jr. Executive Jr. Executive
Officer - 1 Officer - 1 Officer - 1
Peon Peon Peon
SHIFT CHANGE:
There are three shifts per day in P.T.L. So each shiftcontain eight hour.
Shift Duration
A 06.00 AM – 02.00 PM
B 02.00 PM – 10.00 PM
C 10.00 PM – 06.00 AM
General shift 09.00 AM – 05.00 PM
9
General shift, which is applicable for some officers.
Man power in different section (weaving) of PTL
10
JOB DESCRIPTION:
SENIOR PRODUCTION OFFICER:
In a weaving factory a senior production officer plays a great role inproduction and man power management who are production related. Here weenlist the duties of senior production officer:
1) Follow up weaving production,
2) Regular observation of weaving floor,
3) Prepare weaving order status regularly,
4) Maintain the quality of the product,
5) To help the senior prod. Officer & co-operate with others for fulfillingthe required destination.
PRODUCTION OFFICER:
11
Production officer is the right hand of senior production officer andhe is directly related with production manpower and informs senior productionofficer time to time. Here are his listed duties:-
1) Follow up overall weaving production,
2) Decide every m/c utilization during production,
3) Recruit new labor,
4) To inform the authority on the overall weaving prod. and make itfinancial profitable,
5) Regular m/c maintenance,
6) Maintain sub-contract orders,
7) Help weaving manager & also guide the junior officers of the section,etc.
Function area:
Setting the different parameters of machines, using correctyarn for order, controlling machine store, controlling process qualitysystem.
Remarks:
The organization and management system are good for millenvironment and as the job description is classified, so duties are donehonestly and sincerely.
12
13
Machine Description
There are two ways woven fabric produced:
1. Solid dyed
2. Yarn dyed
Generally yarn dyed fabrics are costly item. Because dyed yarn arecostly and in case of yarn dyed fabric Sectional warping is necessarywhich is also costly and time consuming process.
Weaving
Solid dyed Yarn dyed
14
↓ ↓
Store Store
↓ ↓
Direct Winding Soft Winding
↓ ↓
Sizing Yarn Dyeing
↓ ↓
Drawing & Denting Hard Winding
↓ ↓
Weaving Sectional Waarping
↓
Sizing
↓
Drawing & Denting
↓
Weaving
Now the machines used in every stage are described below-
Soft winding:
Machine Type: A (HS 101C)
No. of M/cs:07
Name Of m/cs: Soft winding machine
Brand name: CORAL TEXTILE
Origin: China
15
No of head: (54×2)/machine
M/c rpm:2800
Machine Type: B (TH-8A)
No. of M/cs:06
Name of M/ca: Soft winding machine
Brand Name: TAIZHOU JINWEL TEXTILE
Origin: China
No. of head: (54x2)/mahine
M/cs rpm: 2800
YARN DYEING
A Dyeing machine
M/c model No. ofm/c
CapacityKg
Power Kw SteamKg/hr
Waterhrm /3
Labwin-3 1 4 2.1 2 .12
Labwin-6 2 8 3.5 34 .40
Labwin-12 4 12 8.5 62 .80
Allwin-53 3 48 11.5 214 1.9
16
Allwin-70 1 81 15 382 3.2
Allwin-85 6 108 27 638 6.5
Allwin-105 3 288 39.9 1233 11.5
Allwin-120 2 432 47 1808 17.31
Allwin-145 1 648 76 2609 25.9
Allwin-166 1 828 94.8 3633 33.1
GF24INT-21 1 12 2.1 9 .12
GF24INT-42 1 12 5.5 47 .20
GF24INT-50 1 48 7 118 .70
GF24INT-187 1 140 58 3165 36.5
GF24INT-21 1 12 2.1 13 .20
GF24IHLC-140
1 288 11.4 1105 15
30
B.Hydro-extractor
No. of machine:6
Brand Name:STALAM(Shanghai) DYET
Origin:China
Rotation speed:1530rpm
Capacity:32pkg
Power consumtion:11kw/machine
17
C.RF DRYER
No. of machine:2
Brand Name:STALAM(Shanghai) DYET
Origin:China
Capacity:12tons
Power consumtion:170kw/machine
Steam Consumtion:450kg
Hard Winding
M/c Type:A(HS 101C)
No. of machine:7
Name of m/c: Hard winding machine
Brand Name:CORAL TEXTILE
Origin:China
No of head: (54×2)/machine
M/c rpm:2800
M/c Type:B(TH-8A)
No. of machine:3
Name of m/c: Hard winding machine
Brand Name:TAIZHOU JINWEL TEXTILE
Origin:China
No of head: (54×2)/machine
M/c rpm:2800
18
M/c Type: C (SHA)
No. of machine: 1
Name of m/c: Hard winding machine
Brand Name: STLM (shanghai) DYET
Origin: China
No. of head: 108
Installed Power: 14kW
WARPING
A.High Speed Warping m/c
No. of machine: 1
Brand Name:TSUDAKOMA
Origin:JAPAN
Creel capacity:644
Creel Type: V type
Max beam width: 1780mm
B. Sectional warping m/c
Type 1
No. of machine: 2
Brand Name: UKIL MACHINARY
Origin: KOREA
Creel capacity: 720
Creel Type: V type
Max beam width: 1780mm
19
Type 2
No. of machine: 2
Brand Name: RABATEX
Origin: INDIA
Creel capacity:800
Creel Type: V type
Max beam width: 1780mm
Sizing:
Type 1
No. of machine:1
Brand Name: Tsudakoma
Origin: Japan
Back beam capacity: 16
No of drying cylinder: 12
No of size box: 02
No of wax box: 01
Power consumption: 76kw
Type 2
No. of machine: 1
Brand Name: JUPITAR
Origin: INDIA
Back beam capacity: 1
No of drying cylinder: 8
20
No of size box: 02
No of wax box: 01
Power consumption: 76kw
Loom
Total no of looms: 218
Brand nameof the Loom
SheddingDevice
WeftInsertion
RPM No. ofLooms
Picanolomniplus 800
Tappet 06 700-850 10
Picanolomniplus
TappetDobby
04 650-900 52
Toyota JAT710
Cam 06 725-950 15
Toyota JAT710
Dobby 06 600-700 01
Toyota JA600/610
TappetDobby
2+4+6 525-650 34
TsudakomaZAX 9100
Cam 06 750-850 12
TsudakomaZAX
DobbyTappet
04 500-650 13
TsudakomZAX 205,205i
Cam 02,06 450-600 81
21
Total 218
Finishing machines
1. Singeing and Desizing m/c
No. of m/c: 01
Company Name: Jaingsu Redflag Printing & Dyeing machinery Co. Ltd.
Origin: China
Speed: 80-85 m/min (Standard: 70 m/min)
Power Consumption: 60-70 kW
2. Scouring & Bleaching m/c
No. of m/c: 01
Origin: China
3 baths for hot wash (90 -100 degree celcius) where the first 2 arechemical bath.
One steamer (Steaming temperature: 100 degree celcius)
Again 4 baths for hot wash
Drying cylinder No. 24
Power Consumption: 70 kW
3. Stentering m/c:
Company name: HUNAN VIROCK TEXTILE PRINTING AND DYEINGMACHINERY CO. LTD.
22
No. of m/c: 01
Origin: China
Model: LVK4 000 – 200X8
Drying chamber: 08
Temperature: 120- 170 degree celcius
Fan Speed: 1480 rpm
Fabric dry: 43 m/min
Power Consumption: 140 kW
4. Peach Finishing M/c:
Company name: Xetma Vollenweider GmbH
No. of m/c: 01
Origin: Germany
Model: DE- 08280
Number: 160.008/NW 2200
Year of manufacturing : 2008
Power Consumption: 76 kW
5. Sanforizing m/c:
Company name: WuXi Dakai Printing and dyeing machinery Co. LTD.
No. of m/c: 01
Origin: China
Model: LMH 4P2 – 200
Number: 0804
Year of manufacturing : 2008
23
Power Consumption: 70 kW
Remarks:
Maximum m/cs are made of China& Japan. Looms are of oldmodel. If technology would have better and new version m/cs been usedproductivity would have been greatly increased.
24
Raw Materials
25
Main raw Material is yarn.
Yarn used mainly 100% cotton, PC, CVC, 100% Polyester, Lurax, lycracore spun yarn.
Some common type of yarns are tabulated below with local price
Count Type
10/1 Autocone
16/1 Autocone
16/1 Comb
20/1 Autocone
20/1 Comb
20/1 Kard
20/1 Open end
30/1 Comb
40/1 Comb
50/1 Comb
60/1 Comb
40/2 Comb
80/2 Comb
100/2 Comb
24/1 Slub
30/1 Slub
16/1 Kard
26
Some of the manufacturing companies from where Paramount procurethere yarn are
1 Zaber Spinning Mill
2.GTN (India)
27
Production Planning,
Sequences &Operations
28
There are two ways Woven fabric produced:
1. Solid dyed.
2. Yarn dyed.
Generally yarn dyed fabrics are costly item. Because dyed yarn arecostly and, In case of yarn dyed fabric Sectional warping is necessarywhich is also costly and time consuming process.
Weaving
↓ ↓
Store Store
↓ ↓
Direct Winding Soft Winding
↓ ↓
Sizing Yarn Dyeing
↓ ↓
Drawing & Denting Hard Winding
↓ ↓
Weaving Sectional Waarping
↓
Sizing
↓
Drawing & Denting
↓
Weaving
Solid dyed Yarn dyed
29
When Order Comes to the Marketing Section, then they contactwith the Product development (in case of new product) or Design cell (incase of available product) that, is it possible or not possible inPARAMOUNT. They Send a Article Request paper. After reaching theArticle Request paper Design cell produce Article Code and send mail tothe planning and marketing section.
Planning print a Dispo paper and send to 10 sections with relatedproduction of that fabric.
Dispo Paper:
Dispo Paper is a paper which contain All necessary information for theproduction of a specific item of fabric. A typical Dispo Paper is attachedbelow:
Buyer Merchandiser Marketing
Design CellPlanning
1. Design Cell2. Yarn Requisition3. yarn store4. winding5. yarn dyeing6. warping7. Sizing8. Drawing, denting9. Weaving10. Finishing.
Send Dispo Paper
30
Paramount Textiles Ltd.
Y/D GREIGE FABRIC SPECIFICATION.
PI No: T40824 Line No : 01 Conut ( Warp x Weft) 40X40
Costomer :Paramoun Textiles………..C & A
Yarn Composition (Warp xWeft) 100 % Cotton
FINISHED FABRIC DETAILS
Dispo No :F90001 Ends x Picks ( Finished ) 120X90
Fabrice Code : Blue Stripe Finished Fabric width ( inch 58/59"
Design : Plain Required Finished Length (Mater 9,076.00
Finish SOFT Delivery Date ( Finished 27/02/2009
GREIGE FABRIC DETAILS
DispoNo:W90001 Req No : Ends x Picks ( Greige ) 112X90
Article Code Greige Width ( Inch 63"
Reed No 108/2 Required Greige ( Mater ) 9,711.32
Reed Width (Inch
65.55 Required Loom Production (Mtr)
9809.41
FlowCode:TYD0412 R.P.M : 525 Required Warp Length ( Mtr) 11,630.04
Delivery Date 20/02/2009 Ground Ends 7080
D.C Comments D:4,G:1234,S:1234 Selvedge Ends 120
31
ColorBreakdown
Count Shade Color Code Quantity (kg)
Length(Mtr)
Warp
40/1 White 797 94874.90
40/1 Blue 443 47477.95
Warp Total 1240
Weft40/1 White 920
Weft Total 920
DYED YARN DETAILS
Dispo No : W90001 Delivery Date : 28/02/2009
BREAKDOWN OF YARN FOR DYEING
DispoLine Count Shade ALD NO Greige
Yarn ( kg)DyedYarn ( kg)
YarnType
1 40/1 White 1850 1805
2 40/1 Blue 478 466
Total 2328 2271
Design Cell:
Design Cell is one of the most important department of PARAMOUNTTEXTILE LTD.(weaving). When a order comes to the marketing ormerchandizing officer he/she send the fabric to the design cell that is itpossible or not possible in PARAMOUNT. They send a Article requestpaper. Design cell analyze the fabric design and test the feasibility of
32
produciton and create a Article code and send this article code themarketing or marchandizing officer and input data to the Data tex whichis a software used in PARAMOUNT for all types of information bynetworking.
PARAMOUNT’s Design department is equipped with hand loomand sophisticated software”TEX-DESIGN CLASSIC” byKOPPERMANN of GERMANY.
After getting Article code planning discuss with marketing officerabout costing. Then marketing officer send mail or discuss directly to thebuyer about pricing of the product.
If buyer agree with the price then marketing officer send mail tothe central planning section with Article code.
Planning take a print of dispo paper for the article code from thesystem data tex. After printing dispo paper they send it to the design cellto check or verify. Design cell check and give drawing and denting planand send it to the planning section again.
Planning then send it to the various section where theseinformation required and at a time requisition all necessary rawmaterials or other materials.
Organ gram of Design cell:
Assistant Manager
↓
Data Entry +
Design Analyzer (3 person)
↓
Peon (1 person)
33
Dispo paper goes to the following sections:
1. Design cell.
2. Store.
3. Winding.
4. yarn dyeing.
5. warping.
6. sizing.
7. Drawing and denting.
8. Loom.
9. Finishing
Dispo paper contains following types of informations:
1. Fabric Specification.
2. Yarn composition
3. Finished type.
4. Finished fabric’s EPI x PPI
5. Finished fabric’s width.
6. Required length.
7. Reed count.
8. Grey EPI and PPI.
9. Greige width.
34
10.Reed width.
11.Reed EPI
12.Required greige length.
13.Required warp length.
14.Ground Ends.
15.Selvedge Ends.
16.Cover Factor.
17.Numerical Plan (Warp & Weft)
18.Drawing & Denting Plan.
Possible Ends per inch by using Available Reed in Inventory inPARAMOUNT by denting 2,3 and 4 in a dent For yarn dyed fabric.
a) Read available for air jet Looms Jat-600-ZAX(Tsudakoma)
SiNo
ReadNo
1/1-2Ends/EPI
2/1-3Ends/EPI
3/1-4Ends/EPI
Present Required Short Remark
1 144 160 4 15 -11
2 131 146 218 291 3 3 0 Local
3 130 144 217 289 66 66 0 New 25
4 128 142 213 284 1 0 1
5 126 140 210 280 23 25 -2 10 New
6 122 136 203 271 41 41 0
7 120 133 200 267 36 36 0 37Available
8 118 131 197 162 36 30 0 36
35
9 116 129 193 258 2 10 -6
10 112 124 187 249 0 6 -6
11 108 120 180 240 89 90 -1 5 recountcount
12 99 110 165 220 58 60 -2 New 1 +25
13 98 109 163 218 2 10 -8 2 local
14 96 107 160 213 25 25 0 New 19
15 94 104 157 209 2 4 -2
16 92 102 153 204 3 10 -7 20indnt
17 90 100 150 200 42 42 0 40 New
18 86 96 143 191 3 8 -5
19 84 93 140 187 6 8 -2
20 82 91 137 182 1 10 -9
21 78 87 130 173 41 30 11 New12+15+18
22 75 83 125 167 3 12 -9
23 72 80 120 160 3 12 -9
24 70 78 117 156 31 31
25 68 76 113 151 3 10 -7
26 66 73 110 147 3 3 0
27 65 72 5+6 12 -6
28 62 69 103 138 4 8 -4
36
29 60 67 100 133 7 7 0
30 58 64 97 129 22 22 0 New20
31 54 60 90 120 5 5 0
32 52 58 87 116 5 5 0
33 50 56 83 111 6 6 0
34 48.5 54 81 108 9 9 0
35 46.25 51 77 103 10 10 0
36 41.5 46 69 92 8 8 0
37 38.5 43 64 56 6 6 0
38 37 41 62 82 2 2 0
39 35.75 40 60 79 5 5 0
Total 609 682 -73
b)Reed for picanol looms (10+7)
Si No Reed No Present Required Short Remark
1 130 7 7
2 108 10 10 Camewith loom
3 99 10 10 Indnted
4 65 4 10 -6
37
b) Requirements of cut reed of picanol 45 loom
Si No Reed No Present Require Short
1 130 4 4 0
2 108 35 36 -1
3 99 32 30 2
4 96 8 10 -2
5 90 32 32
6 87 4
7 86 2
8 78 8
9 72 1
10 71 1
11 58 1
12 65 5 10 5
Proposed Process Allowances For the different process:
38
Section
Yarn Dyeing
Warp% Weft%
Section Cumulative Section Cumulative
Yarn Dyeing 2.00 23.32 2.00 26.59
Winding 0.50 20.86 0.50 24.06
Warping 3.00 20.25 23.44
Sizing 0.50 16.64 23.44
Weaving (Crimp) 8.00 16.06 13.5 23.44
Greige (Reject) 1.00 6.78 1.00
Process Loss 1.50 5.71 1.50 5.71
Shrinkage 2.00 4.12 2.00 4.12
Inspection (Rejection 2.00 2.04 2.00 2.04
Total 23.32% 26.59%
SectionYarn Dyeing(pc/cvc)
Warp% Weft%
39
There are major departments are :
2. Winding.
Section Cumulative Section Cumulative
Yarn Dyeing 2.50 24.59 2.50 27.24
Winding 1.00 21.48 1.00 24.06
Warping 3.50 20.26 - 22.81
Sizing 0.50 16.05 - 22.81
Weaving (Crimp) 8.00 15.47 13.50 22.81
Greige (Reject) 1.00 6.23 1.00 6.23
Process Loss 1.50 5.17 1.50 5.17
Shrinkage 1.5 3.59 1.50 3.59
Inspection (Rejection 2.00 2.04 2.00 2.04
Total 24.59% 27.24%
40
3. Warping.
4. Sizing.
5. Drawing, Denting.
6. Weaving.
7. Inspection.
These departments are described below:
Winding Section
Definition: In fabric manufacturing (weaving) process this is the first
stage where rewinding of supplied yarn is done on to a desired package
suitable for use in the next process.
Types of Winding:
1. Soft Winding.
2. Hard widing
41
Soft Winding Section
Soft Winding: where the grey yarn is wond on to a special dye spring or
plastic bobbin and the package(spool) is made softer and bulkier to
make it suitable for dye penetration in the(package) dyeing machine.
42
Dye Spring Plastic bobbin
Organogram:
The organogram of this section is given below:
Section in charge
↓
Senior Operator
↓
Operator
↓
Helper
↓
Cleaner
Skill Level Man power
Section-in charge 3
Senior Operator.36
Operator
Helper 27
Cleaner. 12
Total 72
43
M/c Name : CORAL TEXTILE
Manufacturer : Shanghai Coral Textile machinery Co.
Ltd
Manuf. Year : 2008
R.P.M. of Motor : 1430
No. of Head : 2
No. of Drum /head : 54
Traversing system : Grooved drum
Motor : Individual
Stop motion : Automatic
No. of m/c : 07
Production per m/c : 86867 km /day [Assuming 80%
efficiency]
44
Flow Chart: DISPO
↓
Store Requisition
↓
Recieve the yarn
↓
Setting & Running
↓
Winding
↓
Checking(dia)
↓
Stop winding
↓
Quality assurance
↓
Root card making Delivery for dyeing
Assignment in soft winding :
1. Finding out package density
2. Production calculation
45
1.Finding out package density
We know package density ρ =mass(m)/volume(v) gm/cc
Volume= π( R2-r 2)h
R= outer radius of package
R= inner radius of pkg
h= height of pkg
Now we consider a sample of 40/1 cotton yarn whose
R=4.138
r= 1.59
h=15.24
mass m=1000gm
So package density ρ=1000/π(4.1382-1.592)15.24 gm/cc
=1.433 gm/cc
2.Production calculation
We know production= speed(m/min)×60×24 ×1.09/(840×40×2.2045)
kg/day/head
When speed is 800m/min at 80% efficiency
Production=800×60×24×1.09/(840×40×2.2045)kg/day/head
=10.5976kg/day/head
Total production=10.5976×54×12kg/day
=6867.2448kg/day
46
YARN DYEING
47
OBJECT:
To dye grey yarn to produce check and stripe fabric.
Dyeing procedure:
Deminerelization
↓
Bleaching
↓
Hot wash
↓
Dye run
↓
Neutralization
↓
Finishing
↓
Hydro extracting
↓
Drying
Dyeing process:
Process Recipies
48
Demineralization Ladiquest 0.5g/l
Acetic acid 0.1g/l
70°-15min
Bleaching Caustic 1g/l
Per- oxide 4g/l
115°-20min
Dyeing Ladiquest 0.80g/l
Salt 40g/l
Suffix Yellow SPD 4%
Suffix Red SPD 0.2325%
Suffix Nevy Blue 0.5663%
Soda ash 10g/l
Washing off Ladiphore RSK 0.4g/l
Finishing Permafix RDX 0.7%
Acetic acid 0.2g/l
Assignments
1.Observing Hydro Extracting Cycle & production calculation
2.Production calculation
2.Observing Hydro Extracting Cycle & production calculation
49
Hydro extracting cycle is with time required
Lowering(30sec)
↓
Circulation( 12 sec)
↓
Operation(5min,40sec)
↓
Lifting(21sec)
Water removing Efficiency:
Weight of cone after dyeing: 2.38kg
Weight of cone after drying: 1.11kg
Water removing Efficiency=(2.38-1.11)/2.38%
= 53.36%
3.Production calculation of RF Dryer
Length of RF Dryer=13m
At 28rpm it takes 21 min 9 sec to pass this length
Along this length it can accommodate 416 pkgs i.e 416kgs
So at 21 min9sec or 1269sec it can dry 416kgs
So in 1hr or 3600sec it can dry=416×3600/1269 kg/hr
=1180.14 kg/hr
so Production per day=1180.14×24kg
=22658.688 kg
=22.66 tons
Hard Winding Section
50
51
Hard Winding: Where the grey yarn dyeing machine is converted
from spool to paper cone, to make the yarn easily be fed to the sectional
warping machine.
The organogram of this section is given below:
Section in charge
↓
Senior Operator
↓
Operator
↓
Helper
↓
Cleaner
Manpower
Skill Level Man power
Section-in charge 3
Senior Operator.36
Operator
Helper 27
Cleaner. 12
Total 72
52
M/c Name : CORAL TEXTILE
Manufacturer : Shanghai Coral Textile machinery Co.
Ltd
Manuf. Year : 2008
R.P.M. of Motor : 1430
No. of Head : 2
No. of Drum /head : 54
Traversing system : Grooved drum
Motor : Individual
Stop motion : Automatic
No. of m/c : 07
Production per m/c : 6867 km /day [Assuming 80%
efficiency]
Flow Chart:
Root card
↓
Checking
↓
Recieving
↓
Prepare batch card
↓
Start Hard Winding
↓
Measuring weight
53
Assignment in Hard winding :
3. Finding out package density
4. Production calculation
1.Finding out package density
We know package density ρ =mass(m)/volume(v) gm/cc
Volume= π( R2-r2)h
R= outer dia of package
r = inner dia of pkg
h= height of pkg
Now we consider a sample of 40/1 cotton yarn whose
R=3.99cm
r= 1.60cm
h=15.24cm
mass m=1000gm
So package density ρ=1000/π(3.992-1.602)15.24 gm/cc
=1.563 gm/cc
2.Production calculation
We know production= speed(m/min)×60×24 ×1.09/(840×40×2.2045)
kg/day/head
When speed is 800m/min at80% efficiency
Production=800×60×24×1.09/(840×40×2.2045)kg/day/head
=10.5976kg/day/head
Total production=10.5976×54×12kg/day
=6862.32kg/day
54
Faults in winding section:
Faults Causes
1. Excessive Hard package Excess tension
2. Excessive Loose package Less tension
3. Ring Faulty drum
4. Stitching Vibration of Package
5. Ribbon Ribbon breaker problem.
6. Bulging Improper alignment of Package
7. Entanglement Jerking package
8. Bunch Improper store and handling
9. Cut cone Package drop
10.Reverse winding Low pressure
Types of Maintenance:
1. Schedule maintenance
2. Break down maintenance.
Spare item types:
1. Readymade / purchase:
2. Fabrication tool in work shop / other side
3. Import item.
Quality Control in winding Section:
The following quality is maintained in preparatory stage.
55
Shade matching:
The dyed yarn compared with lab drip sample or swatch card.
Level Checking:
During package dyeing dyes chemical enter in to package by pressure.
So there is a possibility to differ level in inner and outer side. It is
checked and allow up to (5 -6)%
Fastness:
Water and color fastness is checked.
Strength:
CSP, tenacity, CV% of tenacity, elongation are tested.
Package hardness:
Soft wound package is checked by hand if it is hard improper dyeing
will occur, the hard wound package also checked if it is less hard or too
hard it will create problem in subsequent process.
Material Handling Equipment For Winding Section:
1. Creel.
2. Trolley.
1. Creel: 2. Trolley
56
Warping
57
Operational Staff: Section in charge
↓
Senior Operator
↓
Operator
↓
Helper
Direct Warping
Process Flow:
Dispo
↓
Yarn from store
↓
Creeling
↓
Warping
58
A. High Speed Warping m/c
No of m/c: 1
Brand name : TSUDAKOMA
Origin:JAPAN
Creel capacity : 644
Creel type : V type
Maximum beamwidth: 1780mm
High Speed Warping m/c Setting:
Set up parameters Range Set value
Cone no. of Creel 400-600 As required
Warping Speed 1-1200 m/min
Warping length 1-999999 m
Shift selection 1-5 3
Beaming drum
pressure
1-11 mm scale 5 mm scale
Beam barrel dia 315 mm Fixed
Beam flange dia. 987 mm Fixed
Beam width 1800 mm As required
Operation Procedure Direct Warping:
1. As per production program given by assistant manager,
preparation through the yarn warp record register, the supervising
59
officer collects griege yarn from store as per required count, lot
number and quantity.
2. The machine operates and helpers open / break the yarn cartoon
and place the cones in the creel head as per program and draw the
head end of the cone through pretension rods, feeler guides, yarn
guides and then through expanded comb of beaming unit.
3. The basic creel data setting and machine data setting are done
according to the requirement as per m/c manufacturer operating
instruction.
4. An empty beam is set in between driving clutch and engaged by
means of electric switch.
5. All the ends from the creel is wrapped around the beam manually
one round.
6. The press roller is moved towards the beam by means of electric
switch.
7. The m/c is then run slowly and checked for yarn alignment with
beam flange on both sides. To ensure alignment the expanded
comb may be moved either to the right or left as required by
switch.
8. Thus the m/c is ready and the operational switch is to be turned
on.
9. As the present length is achieved the m/c will stop automatically.
The beam is doffed by switch and another beam is mounted.
10.In this way a set of beams are made to feed the subsequent sizing
process.
60
Sectional Warping
Process Flow:
Dispo
Yarn from store
Creeling
(According to warp plan)
Machine setup
Section wise warping
Beaming
61
B Sectional Warping m/c (Type 1):
No of m/c: 2
Brand name : UK IL MACHINARY
Origin: KOREA
Creel capacity : 720
Creel type : H type
Maximum beamwidth: 1780mm
Warp width:
Total Ends Warp Width
Below 7200 1800 mm
7200 2000 mm
Above 7200 2100 mm
. Causes of yarn breakage in warping:
1. Weak yarn.
2. Sloughing off.
3. Over lapping.
4. Knots/ bad splice.
5. Slubs.
6. Loose yarn.
7. Pig tail.
8. Cut yarn.
9. Bad tip cone.
10.Short cone.
62
Assignment: Observing the end breakage.
Serial no Position of breakage Time consumed
1 Between reed& drum 12sec
2 Near package 1min 4sec
3 Far package 1min 44sec
4 Between reed& drum 13sec
5 Missing end on Drum 2min 21sec
6 Between reed& drum 25 sec
7 Breakage from pkg 1min 33 sec
8 Missing end on Drum 2 min 33 sec
9 Missing end on Drum 2min 25 sec
10 Missing end on Drum 2 min
63
Sizing
Sizing is the processof applying an adhesive coating on the yarn
surface. it is done mainly to protect the yarn knot to get hairy while on
weaving.Paramount has a sizing machine which facilites the sizing need
of the whole factory.
Machine Specification (Type 1):
No.of m/c: 1
BrandName: Tsudakoma
Origin:Japan.
Back beem Capacity: 16
No. Of size Box: 2
No of Drying cylinder:12
No of Wax box:1
Power Consumption:76kw
64
Units of the m/c:
1.Back Beam unit
2.Sizing Unit
3.Drying Unit
4.Leasing Unit
5.Beaming or Take up unit
Controlling Points:
1.Speed of the Yarn Passing
2.Drying Unit-Cylinder temperature must not exceed 150˚C to maintain
R.H. less than 6% which is a requisite for cotton yarn.
65
3. Squeezing Pressure: A typical roller pressure for wide variteyof
cotton yarn is given below.
First Squeezee: 0.12MPa
Secondsquzee:0.2MPa
Immersion roller:0.1MPa
4.Separation Unit: Distances between the lease rods are to be care fully
set up for solid dyed & yarn dyed fabrics
5.Headstock : All the settings are done from here.
Size Box:
There are two size boxes and one hot wash box.
66
Main parts of size box are
301= TENSION DETECTION ROLL
302= IMMERSION ROLL
303= FIRST SIZING ROLL
304= FIRST SQUEEZE ROLL
306= SECOND SIZING ROLL
308= SIZE BOX
307= SECOND SQUEEZE ROLL
310= LEVEL ADJUSTER
311= STEAM PIPE
312= COVER
67
Some typical size recipes used in PARAMOUNT given below with
their function-
Construction: 30x30/120x70
Total ends:6876
Recipes:
Recipes: Yarn count 30/1
Total ends:6876
Yarn count 30/1
Total ends:6876
Water 600 Lt 600 Lt
Sure Bond 60 kg 60 kg
CMC 20 kg 18kg
Size CA 15 kg 18 kg
Wax 2 kg 3 kg
Polytex. 460 20 kg 20 kg
Function:
1. Sure Bond: It work’s as adhesive to increase solidity percentage in
the size recipes.
2. Starch : It also works as adhesive. As its price is of low it is mainly
used to reduce the size cost when yarn count is coarser
3. CMC: It is a synthetic adhesive used mainly to help in penetrating
other chemicals into yarn.
4. PVC :This adhesive is only used on finer count yarn.
5. Size CA:Its mainfunction is to bind protruding fibres with yarn.
6. wax: It acts as a lubricating agent.
68
Costing of Size Ingredients
Ingredients Cost tk/kg
Sure bond 43-53
Starch 29
CMC 139
PVA 267
Size CA 70
Wax 255
Assignment: Measuring of size take up% of a particular sample
Yarn count 40/1
Total ends 7420.
Recipes:
Water: 600 Lt
Sure bond: 60kg
Startch: 20kg
CMC: 20kg
Size CA: 15kg Sized yarn Unsized yarn
Wax: 2kg
Wt of 1m of total yarn before sizing = 0.12kg
Wt of 1m of total yarn before sizing=0.1340kg
So, Size take up %=(0.134-0.12)/0.12%
=11.67%
69
Drawing, Denting Section
Process definition:
After a sized beam or weaver’s beam is made, it is time to mount this
beam over the loom. There are two methods used to prepare this beam
for mounting on a loom.
1. Warp tying or knotting (Quick style) change process.
2. Reaching – in /Drawing – in and beam gaiting.
70
Warp tying:
This method is limited to use where and exactly same article or quality
of fabric is to be made that is already running in the loom. The following
points are considered-
1. The total number of warp ends should be the same as that of
running.
2. The count of yarn and weave design should be same.
Before tying a new beam with an older one, the new beam is to
undergo a process called leasing, whereby the adjacent yarns are kept
separated by placing a yarn in between them. This is very essential in
case of tying a yarn dyed beam; otherwise the warp pattern scheme
will be disturbed and lost.
For monocular beam (solid dyed beam), tying is performed without
leasing.
Drawing – in:
The method of mounting weaver’s beam on to the loom, which is
adopted for the same style of working of adjacent warp yarns or yarn
interlacement, compared to that of running in looms.
In this method warp yarns are separated individually as per count or
color pattern from the adjacent yarn and hooked to the access of
drawer’s hook called reaching – in.
71
The yarn as it comes to “reach” or drawer’s hook is then drawn
through dropper (or drop wire) and then passed through the split of the
reed dent called denting.
Operation procedure:
Warp tying:
1. According to that plan, knotting – in – charge & Drawing – in –
charge jointly arrange leasing of beams, the respective beams
being identified from the sizing data sticker.
2. As leasing is completed the beam is transported to a specific loom
and mounted on loom beam bracket. The tying frame is set on
proper position.
3. The ends of old beam and the ends of the new beam are accurately
brushed and gripped by the frame sothat older and newer ends,
make and upper & lower set of yarn placed in proper tension.
4. The warp tying head is mounted over the tying frame. In case of
STAUBLI machine, number of knots per repeat of color pattern is
entered in to machine.
5. Then the machine is started. After the programmed number of
knots per color is reached, knotting will stop. Operator will check
the correctness of the knot and start again by switch.
6. Thus knotting will be completed up to the end of set, tying up per
set of older yarn with lower set of new warp.
72
7. As knotting is completed, the knotting operator make a quality
card mentioning customer name, work number, beam number
beam length, knotting operator’s name and date and time of
knotting.
8. The sizing date sticker is set over the quality (of doffing) card, and
the card is set over the loom.
9. The knotting operator also makes a work record in his register
book.
10.As knotting is completed, tying head and frame are removed, the
old piece odd knotted yarn is pulled through the machine, i.e.
through heald wire and reeds and thus new warp set is allowed to
pass and made ready to run.
Drawing – in and reaching – in:
1. The customers fabric swatch is sent to the weaving section,
generally after warping is done, either by enclosed to the order
sheet to form or separately. Assistant manager (weaving) then
analyzes the swatch for reproduction. In this stage the determines
–
a. The design of sample i.e. whether dobby or tappet or
combination of two.
b. The drawing – in, denting and lifting or tappet/ cam setting
plan.
c. The required number of heald frame and reed count, draw
width etc.
73
2. Then whenever the sized beam is ready, the worked out drawing
– in plan, reed count etc. against an order number is given to the
drawing – in – charge for production. Drawing – in – charge for
production. Drawing – in – charge makes a work program
considering the following:
a. The availability of the run out loom for beam.
b. The availability or required number of reed count.
3. Drawing – in – charge and senior drawer find out the desired sized
beam number from the sizing production record, check against the
specific work order number and from transport these to the
drawing – in – section by trolley and start working there.
4. According to the work order number each design/ drawing – in
plan is recorded in the register book, the produced sample being
attached thereafter.
5. After drawing – in/ denting is completed each beam is set with a
quality/ doffing card, the sizing data sticker is being attached on
the card.
6. During deciding the loom number the drawing – in – charge takes
into consideration designing scope and color insertion scope of the
respective loom.
7. Finally beam gaiters carry this beam along with dropper, healds
and reed with trolley onto the specified loom and mount.
8. They will pull the new yarn from the beam and set in the loom
with dropper, healds and reed properly positioned and tie the new
74
yarn with the old piece of cloth wrapped around the surface
roller with a number of small knots.
Equipment used in Drawing denting and pinning Section:
Denting plate (Patti):
Drawing Hook:
Drop Wire:
75
WEAVING SECTION
Process Definition:
The act of inter lacing Warp yarn(of a beam) with the inserted weft yarn
in a definite order to form a fabric suitable for use as a dress material,
domestic or industrial purpose is called weaving. The machine used for
this purpose is called loom.
Weaving Floor of PARAMOUNT
76
Process equipment:
Air jet loom
Loom shed – 1:
Total no of loom - 178
Loom shed – 2:
Total no of loom - 40
EQUIPMENTS OF LOOM SECTION
The machine used for the purpose of weaving can be categorized as
follows:
Brand nameof the Loom
SheddingDevice
WeftInsertion
RPM No. ofLooms
Picanolomniplus 800
Tappet 06 700-850 10
Picanolomniplus
TappetDobby
04 650-900 52
Toyota JAT710
Cam 06 725-950 15
Toyota JAT710
Dobby 06 600-700 01
Toyota JA600/610
TappetDobby
2+4+6 525-650 34
77
TsudakomaZAX 9100
Cam 06 750-850 12
TsudakomaZAX
DobbyTappet
04 500-650 13
TsudakomaZAX 205,205i
Cam 02,06 450-600 81
Total 218
SPECIFICATIONS OF AIR JET LOOM:
GENERAL SPECIFICATION
Motor R.P.M : 1410
M/C speed : 625 PPM
Motor pulley dia : 100mm
M/C pulley dia : 225mm
Reed : Profiled reed
Shedding : Cam, Electric Dobby
Take up motion : Electronic
Let off motion : Electronic
Warp stop : Electrical
Weft stop : Electronic
78
HEALD SHAFT SPECIFICATION
Brand Name : New light
Manufacturer : Nankai industrial Co. Ltd.
Origin : Japan
PHOTO ELECTRIC SENSOR
Model : CY-21P-SK
Manufacturer : Sunx Ltd.
Origin : Taiwan
LENO BOBBIN WINDER
Brand Name : Precision spooler
79
Model : PS
Manufacturer : Sankin engineering Co. Ltd.
Origin : Japan
SIGNAL LAMP
Manufacturer : Hayashi feeler Co. Ltd.
Origin : Japan
CABLE
Manufacturer : Mitsubishi Cable Industries
Ltd.
Origin : Japan
REED SPECIFICATION
Brand Name : (i) RTOS (ii) Setia kiji reed
Origin : Japan
Type : Profile reed
Reed Count : 129, 121, 116, 106, 99, 92, 88/2,
74/4, 72/4 etc.
Reed Width 172.50cm
WARP BEEM CARRIER
Brand Name : TODO
Model : S-1500
Manker : Marubeni Corp
80
Origin : Japan
OVER ALL CLEANER
Brand Name : LUWA
Type : Suction
LOOM MOTOR SPECIFICATION (3 Phase Inductor Motor)
R.P.M : 1410
Maker : Meidensha Corp
H.P : 3KW
SIGNAL LAMP:
COLOR INDICATION
Red : Warp breakage
Green : Weft breakage
White : Loom stop
Yellow : Selvedge leno bobbin breakage
LENO SETTING:
Right side : 10°
Left side : 280°
PRODUCTION PROCEDURE:
81
Operation stuff:
Assistant Manager – section in charge
Production officer – shift in charge
Loom Technicians – shift wise running loom checking/ tuning/
setting & gauging
Senior loom operator – as a line jobber, for production & Q.C.
Loom Operator
Helpers & movers – for supplying yarn and yarn cartoons
Casual worker – For keeping the machine & section clean
Different parts of Air Jet loom:
1. EDP(Electronic Drum Prewinder).
2. Tappet(Cam).
3. Lever and Puller.
4. Reed.
5. Dobby.
6. Easing roller.
7. Back rest.
8. Take up roller.
9. Cloth roller.
10.Weft Feeler.
11.Dummy selvedge stop.
82
12.Weft cutter.
13.Drop wire and bar.
14.Leno selvedge attachment.
15.Main nozzle.
16.Sub nozzle.
17.Tample.
18.Dummy selvedge system.
19.Monitor and Mother board
20.Pressure control Switch.
21.Grease tank.
Adjustment of setting:
Cutter to reed distance: 1mm
Tample to reed: 3mm
EDP pin to bend: 0.5mm.
Sub nozzle to sub nozzle: 88mm.
Two pick gear: 0.23m
Shed Size:
→Plain:
Shed angle: 30°
Shed depth: 3 – 3.5cm
→Plain + Shateen:
Shed angle: 20°
83
Shed depth: 2.5cm
→Twill:
Shed angle: 25°
Shed depth: 3.5cm
A= WARP BEAM
B= BACK REST
C= DROPPER
D=HEALD FRAME
E= REED
F= FRONT REST
G= TAKE UP ROLLER
H= CLOTH ROLLER
84
Threading of catch cord
85
Fabric and recommended planetary yarn
Fabric Filament yarn Spun yarn
Oxford ,Industrial cloth Polyester texturized yarn
56dtex,84dtex
LH 80S/2
RH 40S/1
2/2,twill clothing Polyester texturized yarn
56dtex,84dtex
LH 120S/2
RH combed 60S/1
Poplin Polyester texturized yarn
56dtex,84dtex
LH 120S/2
RH combed60S/1
Polyester fabric Polyester texturized yarn
56dtex,84dtex
---------------------------
86
87
88
Hand Loom Section
In PARAMOUNT Textile Ltd there is a hand loom section. There
are several hand loom section with combined section, such as treadle,
treadle pad dobby, treadle and jacquard. There is also hank winding
frame, sample high speed warping machine, sectional warping machine
also.
When PARAMOUNT gets a new order without any swatch, then a cad
is prepared and sends it to the Hand loom section. There a small size of
sample is prepared. If the sample is prepared successfully according to
specification, then the planning department took necessary step for bulk
production.
89
Finishing section
Executive loom:
Four persons can do the job-
1. first meter checker
2. loom checker
3. loom checker
4. loom checker(reliever)
90
Grease inspection:
Two persons can do the job-
1. loom checker
2. grease inspection checker
First meter checking procedure:
Approved sheet by executive
Checking point:
For solid dyed:
1. construction
2. width(standard+/- 1”)
3. weave design as std
4. selvedge
5. reed number
6. denting order
7. design/color/pattern
For yarn dyed:
1. construction
2. width(standard+/- 1”)
3. weave design as std
4. selvedge
5. reed number
6. denting order
7. design/color/pattern
91
All check points are checked by first meter checker and executive will
confirm that ok or not ok. By comparing with the first meter of first loom
and approved sample.
Loom checkers job:
Any type of fault like
1. stop mark
2. miss pick
3. double pick
4. wrong knotting etc found then this sample is not approved
List of equipments:
1. scissor
2. pick counter
3. measuring tape
Quality Standard : Given on the dispo paper
FABRIC INSPECTION
PROCESS DEFINATION:
Fabric inspection is the process of identifying weaving faults in the
fabric just after the grey fabric production in the loom.
EQUIPMENT:
1. Inspection table
2. Fabric inspection machine(Nazer, L 90p, Pakistan)
92
KEY ACCESSORIES:
Nipper, Pointer, Cutter, Comb etc.
INSPECTION PROCEDURE:
Operation stuff: Shift In-charge ( 6 )
Operator( 36)
Helper( 36 )
Cleaner( 6 )
OPERATION PROCEDURE:
Operation Stuff:
Operation stuffs of Inspection Process include:
Factory Manager
↓
Manager, Quality Control
↓
Production Executive
↓
Supervisor
↓
Sr. Inspector
↓
Inspector
↓
Helper
93
MACHINE SET-UP:
M/C Set Value & Parameter
Check
: M/C Set Value &
Functionality
Check
1. Guide roller speed : 40 meter/min
2. Light : Artificial day light
3.Length measuring meter : Attached with the fabric &
the m/c
4. Automatic cutter(knife) : Functionality check
5. Slippage measuring roller : Functionality observe
6. Batcher : Check batcher setting with
motor
Operation Procedure:
The steps involved in the Inspection Process is as follows:
1. Inspector connects the batcher with motor and feeds the fabric by
the guide roller. The fabric goes through a special table where
there are arrangements for special lighting to detect faults in the
fabric visually.
2. Fabric is inspected as per inspection procedure of 4-point system.
After the inspection, the fabric is rolled or folded without any
crease and is packed by polythene paper. The inspector puts the
Identification Sticker on the fabric roll with details of the fabric (i.e.
order no, customer, batch no, shade, roll no, usable width
composition etc.).
94
Type of fabric : Maximum Roll size
(meter)
1. Poplin : 250
2. Yarn dyed : 250
3. T.C Fabric : 300
4. Twill : 150
3. The good as well as reject quantities are entered in the MASH
module of Datatex system with respective quality codes and then
they are transferred to the finished goods stores.
Four Point Inspection System:
Generally any piece of fabric with less than 40 points fault per 100
square yard is allowed to pass however for a roll; the average value
should not exceed 28 points per 100 square yards. More than 40 points
fault per 100 square yards is recorded as reject. Normally fabric faults
are recorded using the 4-point system given below:
4-Point Grading System
Fault length Points to be assigned
(0 to 7.5) cm or less than
3”
1 points
(7.5 to 15) cm or (3” to
6”)
2 points
(15 to 22.5) cm or (6” to
9”)
3 points
More than 22.5 cm or 9” 4 points
95
Assessing Fabric Fault
Faults name Definition Faults area PointsDouble pick In full width an extra pick 0 to 9 inch
over4
Miss pick Missing of one or more picks 0 to 9 inchover
4
Reverse pick After arriving reverse back andcauses double pick
0 to 3 inchover
1
Broken or halfpick
Pick less than full length 0 to 9 inchover
4
Crack More than three pick missing 0 to 9 inchover
4
Snarling Bunch of weft yarn woven in oneplace
1 inch 2
Pressure loose Loop formed in the fabric Between 1yards
4
Let-off mark Weft way mark for irregular pickdense
0 to 9 inchover
4
Wrong pattern Design broken on warp way 0 to 9 inchover
Starting mark Weft way mark while starting theloom
Full width 4
Reed mark Reed having more gap than thenormal way.So warp way line visible
Reject
Temple mark Along the temple one or more pinmark visible
Reject
Count mixing Mixing of various count RejectSlubs Bunch fibres in yarn 0 to 1 inch 1Double yarn One extra warp yarn woven along
with regular warpReject
Loose warp One or more warp yarn having morelooser than another warp
Mandible Reject
Tight warp One or more warp yarn having more Mandible Reject
96
tighter than another warpStitch/warp float One or more warp yarn not properly
interlaced with weft for somedistance
0 to 3 inchover
1
Oil spot Oil drop in the fabricZala Bunch of warp yarn breakage 0 to 9 inch
over4
Bad selvedge Narrow or higher width of selvedge Informedweaving
FINISHING SECTION
Finishing Machineries
1. Singeing-Desizing 1 set
2. Washing machine 1 set
3. Stenter 1 set
4. Peach Finishing 1 set
5. Sanforizing 1 set
1. Singeing – Desizing:
Singeing is a process by which projecting or floating fibers stand
out on the surface of the fabric are burned off. Singeing is done to
remove hairy fibers projecting from surface of cloth and given a
smoothen face. It is also done to increase lusture in the finished fabric
and to prepare the fabric for next process.
97
Desizing is the first wet processing textile finishing technology
employed to remove the sizing material from the fabric. It depends on
the solubility of the film forming polymer, on the effects of numerous
subsequent wet processing steps, on the interactions with added
chemicals. It is done to remove starch from the fabric and to increase
absorbency of the fabric.
2. Scouring and Bleaching:
Scouring is the process by which all natural and adventilious
impurities such as well as oil, wax, fat etc. are removed to produced
hydrophilic and clean textile material. It is vital precess of wet
processing. It is done to make the fabric highly hydrophilic and to
remove impurities such as olis, waxes, gum, husks as completely as
possible.
Bleaching of textile material is chemical or commercial process
which can be defined as destruction of natural coloring matters to
impart a pure permanent and basic white effects suitable for the
production of white finishes, level dyeing and desired printed shade
with the minimum or on tendering or without diminishing the tensile
strength. It is done to ensure a pure and permanent basic white color
fabric and to destruction of natural coloring matters from the fabric.
3. Stentering:
Stentering is done to soften and to control width of the fabric. It is
done to give the required finish to the fabric.
98
Some finishes:
1. Soft/regular finish
2. ETI (Easy to Iron)/wrinkle free finish/resin finish
3. Easy care
4. Paper touch finish
5. Peach finish
Typical recipe:
Soft finish:
Construction: 40x40/120x80
Tubingal 11/2: 8 gm/L
Jinssofter AS852: 20 gm/L
Terasil NNO: 10 gm/L
Acetic acid: 0.5 gm/L
Resin finish:
Construction: 50x50/144x90
Fixapreat eco: 50 gm/L
Condensol Fm: 10 gm/L (Catalyst)
Siligen pcp: 20 gm/L (Softening agent)
Aniston EPD: 20 gm/L (Softening agent)
Jinsofter AS822: 20 gm/L (Softening agent)
Acetic acid: 0.5 gm/L
Karoline jet B: 1gm/L (Wetting agent)
99
4. Peach finish:
Peach finishing is done to give soft, hairy and smooth surface
effect to the fabric. For this emery rollers used.
5. Sanforizing:
Sanforizing is mainly done to control shrinkage of the fabric. It is
also done to give a better softening effect and controlling width of the
fabric.
Step wise process:
Spraying Unit Steam Roller Rubber Belt Cylinder Steam Roller
Blanket Cylinder (Ironing for permanent shrinkage control)
Common Fabrics Produced In PARAMOUNT
Fabric name: Plain
Construction:130×80/40×40,60”
Composition: 100% Cotton
100
Finish Type: Peach
Fabric Name: Plain
Construction:110×80/50×50,58”
Composition: 100% Cotton
Finish Type: Soft
Fabric Name: Oxford
Construction:110×50/40×30/2,58”
Composition: 100% Cotton
Finish Type: Regular
101
Fabric Name: 2/2 ‘s’ twill
Construction:30×30/120×70,59”
Composition: 100% Cotton
Finish Type: Soft
Fabric Name: 2/2 ‘z’ twill
Construction:110×70/40/2×20,60”
Composition: 100% Cotton
Finish Type: Soft
102
Fabric Name: Plain
Construction:40×40/134130×80,60”
Composition: 100% Cotton
Finish Type: Regular
Fabric Name: Plain
Construction:40×40/120×80,59”
Composition: 100% Cotton
Finish Type: Soft (Silicon)
Fabric Name: Dobby
Construction:40×40/120×80,60”
Composition: 100% Cotton
Finish Type: Soft
103
Fabric Name: Plain
Construction:20×20/72×50,58”
Composition: 100% Cotton
Finish Type: Regular
Fabric Name: 2/2 ‘z’ twill
Construction:40/2×20/110×70,61”
Composition: 100% Cotton
Finish Type: Soft
104
Fabric Name: 2/2 ‘z’ twill
Construction:40×40/120×90,63”
Composition: 100% Cotton
Finish Type: Soft
Fabric Name: Plain
Construction:40×40/133×72,60”
Composition: 100% Cotton
Finish Type: Peach
Fabric Name: 2/2 ‘z’ twill
Construction:40/2x20/110×70,61”
Composition: 100% Cotton
Finish Type: Soft
105
Fabric Name: Plain
Construction:40×40/110×80,58”
Composition: 100% Cotton
Finish Type: Regular
Fabric Name: 2/2 ’z’ twill
Construction:40/2x20/110×70,61”
Composition: 100% Cotton
Finish Type: Soft
106
Fabric Name: Plain
Construction:40×40/133×100,60”
Composition: 100% Cotton
Finish Type: Regular
Fabric Name: Plain
Construction:40×40/130×80,60”
Composition: 100% Cotton
Finish Type: Peach
107
Fabric Name: Plain
Construction:40×40/130×80,59”
Composition: 100% Cotton
Finish Type: Peach
Fabric Name: 2/2 ’s’ twill
Construction:40x40/130×90,56”
Composition: 100% Cotton
Finish Type: Soft
108
Quality Assurance System
109
To ensure safe and consumer friendly fabric PARAMOUNT has its own
high- tech laboratory and computer data processing system.The
laboratory is fully equipped with modern testing equipments enabling
them to check the fabrics in all the stages of required testing criteria and
performances.Testing equipments are sourced from renowned
companies,such as-
JAMES H HEAL-UK
SDL ATLAS-UK
DATA COLOR Spectro Photometer-USA
QUALITY ASSURANCE & LAB TESTING SECTION
110
PHYSICAL TESTS:
Test Name Equipments Manufacturer
Thread per inch Thread counter James. H. Heal &
Company, Halifax,
England
Gram per square
meter
G.S.M tester James. H. Heal &
Company, Halifax,
England
Width test Measuring tape N/A
Tensile strength Elmendorf tearing
tester
1653
James. H. Heal &
Company, Halifax,
England
Seam slippage Alphatens James. H. Heal &
Company, Halifax,
England
Abrasion resistance Nu-Martindale
Abrasion & Pilling
tester
James. H. Heal &
Company, Halifax,
England
111
Pilling resistance ICI pilling box James. H. Heal &
Company, Halifax,
England
Thermal stability Roaches Roaches engineering
limited
Crease resistance Shirley crease
recovery tester
James. H. Heal &
Company, Halifax,
England
CHEMICAL TEST:
Test Name Equipments Manufacturer
Wash Fastness Gyro wash James. H. Heal &
Company, Halifax,
England
Water Fastness Perspirometer &
Carbolite
James. H. Heal &
Company, Halifax,
England
Sweat Fastness Perspirometer & James. H. Heal &
112
Carbolite Company, Halifax,
England
Light Fastness Light fastness
Tester(Mercury vapor
lamp)
James. H. Heal &
Company, Halifax,
England
Crocking Fastness Crocometer James. H. Heal &
Company, Halifax,
England
Washing stability Wascator James. H. Heal &
Company, Halifax,
England
ANALYSIS:
Test Name Equipments Manufacturer
Fiber analysis Electronic microscope James swift U.K.
Fabric analysis Balance, Thread
counter
N/A
Design analysis N/A N/A
113
DAILY WEAVING PERFORMANCE REPORT
QUALITY ASSURANCE DEPARTMENT
PARAMOUNT TEXTILES LIMITED
Date: ………
Order
#
Customer Construction Quality Shade Starting
time
Loom
#
Sample
Rcv
Time
Sign Remark
114
Maintenance
115
Maintenance is one of the main concerning points for any productionoriented organization. PARAMOUNT having its own maintenance departmentis a strong section. It has a skilled group of maintenance manpower.
Manpower:
Section Name of No of DescriptionManRequired
Coverage for offday, Total
Machine/Job Machine per Shiftleave &
absenteeismIn charge 0 0 1Asst Engineer 0 0 1
Maintenc Mechanical 218 Forman 0 0 1loom Senior Fitter 2 2 8
Fitter 2 2 8Asst Fitter 2 3 9Helper 3 3+General shift6 18
Total=46
In a weaving factory, Maintenance is done mainly on Sizing machine and onlooms.
Maintenance of sizing machine
Periodical Inspection
Daily Inspec tion
Remove any lint on the suction filter for the cooling fan for the driving motorsin each section. Check any trouble and the following points:
→Abnormal noise,
→surface condition, vibration, rotation irregularity of each roll;
→Tension in each section;
→Steam, air size and oil leakage;
→Steam pressure:
a. Main supply pressure
b. Supply pressure to the drying cylinder
c. Supply pressure to the sizing section.
116
→Air pressure:
a. Main supply pressure,
b. Pressure during power failure-at the beam stand and the middlesection,
c. pressure due to the cut mark device-standard 0.3MPa.
→Steam drain exhaust;
→Squeeze roll pressuring condition;
drain in the air filter equipment.
Weekly inspection
→Exhaust drain from the air compressor and the pressure reducing valve withthe filter;
1.Roll chain tention
Adjust tension with tension wheel.If the chain has slack replace it.Some checkpoints are-
a.Sizing section: Sizing roll driving
b.Drying Section: Pre-cylinder drying and main cylinder drying.
c.Take-up section:Warp beam and doffing driving,
Taking-up roll driving.
2.V-Belt Tension
Slide the motor base and the V-belt tension.Checking points are-
a.Size circulation pump
b.Winding motor
117
Every three month inspection
1.Steam strainer cleaning:
Clean the strainer two or three days after starting operation for the firsttime.Clean it every three months after that.
2.Take up box frame and hydraulic unit:
Check the oil amount in the take up box frame and hydraulic unit. Supply if it isnecessary.If oil is dirty replace it.
3.Pressuredrop after passing the air filter in the pneumatic piping
When the pressure difference between the primary and secondary sidereaches 0.1MPa repace the element.
4.Cleaning of the steam trap
Clean the steam trap two or three days after starting operation for the firsttime.Clean it every three months after that.
Every six month inspection
Polish the rubber rolls in the sizing section every six months.
Check the bearings.
#Tools for assembly
1. 1-ton chain block: Four sets2. 1-ton forklift: 1-2 sets3. Transit and stepladder
# Man power
A staff of four to six required to unpack, install and wire the machine.
Lubrication
1. Lubrication position and required amount
Model Oil or grease Application Q’ty/unit
HS40 Oil Take-up gear box 6.5 litres
118
Sizing gear motor 6.0 litres
Heatproof Oil Centralizedlubrication oil
3.0 litres
Hydraulicactuation oil
Oil tank 15.0 litres
Grease Sliding section,bearing
1.0 liters
2. Recommended Oil
Manufacturer Oil Grease Hydraulicactuation oil
Centralizedlubrication
Nippon oilCorporation
FBK OILRO150
MULTINOCGREASE 2
FAIRCOL A46
ESSO Teresso 150 Beacon EP2 Teresso32
MOBIL Mobil DTEExtra heavy
MobiluxGrease 2
Mobil Rarus425
119
Maintenance of loom
Periodical Inspection and Maintenance#Routine Inspection and MaintenanceInspection Position Check points Maintenance
Brake Check for abnormallyhighly temperature
ASdjust
Selvedge Check for abnormal noise Adjust to 0.2mm
Feeler Head Check for dirt on the lens Clean the lens
Cutter Check the weft is well Replace damaged edges
Selvedge formation Check that the selvedgeyarn is threaded properlyand in uniform tension
Correctly threading andadjust tension
Temple Check that the templemarks do not appear
Adjust
Catch cord Check that the tuft is notwound on the take up roll
Remove the tuft and clean
Inspection and Maintenance After weaving
Inspection Position Check points MaintenanceWhole loom Check driving and
lubrication sectionRemove lint and wasteyarnslubricate
Temple Check the temple ringrotates easily and arenot worn out
Remove lint anddirt,when neede replace
FDP Check that lint has notadhered to the hook pin,main drum or pin drum
Clean
Heald frame Check that the healdframe height differenceis 2mm or less compared
Adjust the heald frameheight
120
with specific valueAir filter Check if the drain is filled
upDrain
Let off Check that yarn has notadhered to the easingshaft
Remove waste yarn
Lubrication Grease nipples, teeth ofopen gears
Apply grease with brush
Every Six Month Inspection and Maintenance
Inspection Position Check points MaintenanceThread guide Check for dirt CleanHook pin assembly ofFDP
Check inside for dirt Clean
Sensors Check that they functionnormally
Replace
Gear box of take-up andlet-off Section
Check for dirt of oil Replace
Air Filter Check that the filterelement is not clogged
Clean ,replace
Reed Check for adhesivemonomer and abrasions
Clean, replace
Main nozzle Check that the pipe isnot bent
Replace
Sub nozzle Check for bent on thetips
Replace
Yearly Inspection and Maintenance
Inspection Position Check points MaintenanceWarp beam Check that abrasion of
journal section is 0.3mmor less
Shock absorber Check the function Replace
121
Cutter on the LH Check the edge forsharpness
Grind or replace
Hook pin assembly Check that abrasion is0.5mm or less
Remove burr
Cloth roll metal bush Check that bushabrasion is 0.8mm orless
Replace
Every Three yearly Inspection and Maintenance
Inspection Position Check points MaintenanceCloth roll Check that the roll
rotates smoothly andcloth is wound
Replace the brake lining
Sub nozzle Check for dirt Clean
Every Seven year Inspection and Maintenance
Inspection Position Check points MaintenanceOverhaul Loom, Bearings, Gear
,Cams, Hook pins, Mainmotor Shedding section,Let-off and take-upsection,FDP section
Lubrication PointsPosition Period Lubricant typeDriving Section Gear box- 6 months
Main motor-3 monthsOil AGrease C
Shedding Section Heald Frame Guide-1week
Gtrease A
Let off Section Gear box-6 monthsGears-After weaving
Oil BGrease A
Take-up Section Gear box-6 monthsGears-6 months
Oil BOil A
Selvedge Section Slide Gear-After weaving Grease A
122
Bobbin Shaft-Afterweaving
Cutter Section Cutter lever pin-AfterweavingCutter cam-Afterweaving
Grease A
Automation Support Bracket-Afterweaving
Grease A
Recommended Lubricants
Manufacturer NameNIPPON OIL CORPORATION FBK Oil RO100SHELL Tellus Oil C100JOMO Ratus 100MOBIL Mobil DTE Oil HeavyEXXON Teresso 100
Tools and Their FunctionsName FunctionsPulley PullerAdapter
For removing the motor pulley from the main motor shaft
G6 type puller For pulling out the loom pulley from the crank shaftTurnbuckle For opening the split of the motor baseTube Cutter When cutting the synthetic flexible tubeTorquewrench
When mounting the reed on the reed holder
AdjustingBracket
When adjusting the vertical position of the tension metalsupporter
G3 type puller For disassembling the FDP drum to remove the drum holderLifting rod bar Moving up the press roll in gaiting
123
Utility Services
124
Utility Services
There are following utility services are available in Paramount:1. Gas.2. Water.3. Electricity.4. A/c Plant (Chiller).5. Compressed Air.6. Steam.7. Efluent treatment plant.
125
Power generation
Facility:The main utility electricity is generated by generators which areoperated by Gas and Diesel engine. The diesel engine works as standbyengine.
There are 5 gas engine operated generators
Engine Name: JENBACHER GAS ENGINEManufacturing Country: AUSTRIA
Capacity:Total Capacity: 3543KW.
0.3 – 0.4 m3 Gas is required per KW electricity generationGas is supplied from Titas Gas.
Specification:1. Gas engine used.2. 20cylinders per engine3. Overall efficiency – 90%4. Heat recovery possible from 4 engines5. Stroke of engine – 185 mm6. Cylinder capacity – 71.6 dm37. Ignition pressure – 90 bar8. Piston speed – 9m/s9. Air flow of full load = 1.65 kg /hour.
10. Exhaust flow of full load= 1.7 kg /hour.11. Exhaust gas temperature =500ºC
126
12. Pressure of gas = 60 -62 millibar13. Air pressure =10 bar14. Engine rpm=150015. Engine temperature= 85º C – 90ºC16. Cylinder Temperature = 550º C – 650ºC17. Oil change after 750 hours18. Oil required /engine = 180 lt.
Distribution:Different Section of PTLWEAVING 1299KWYARN DYEING 1623KWOTHERS 620KW
Steam generation
Facility:Pure steam with required temperature must be produced to meet theconditions demand of steam in different sections.Fire tube type boiler is used to steam generation.No. of boiler: 2 twine boiler
Capacity:Total : 8+6=14 ton /hr.Steam flow 9 ton/hr each (approximately)
Specification:1) 3 phase heating system2) The lower drum is 100% water filled and the top drum is
60% water & 40% steam filled.
127
3) Measuring meter for water supply.4) 4” depth greasol insulation so no heat at outside.5) Steam pressure 8.2 kg/cm2
6) Water pressure 10.3 kg/cm2
7) Origin: Korea8) Steam temperature: 185ºC9) Boiler temperature (inner): 225 -275ºC
Chemicals used for boiler feed water:NaCl solution for regeneration.NALCO-4654 (Scale removal)
Distribution:
1. The major portion of the steam is supplied to the PTL dye house.To heating the drying Cylinder.To heating the calendar rollers.Heating the chemicals liqor.
2. Sizing section of PTLFor Size cookingSize box to keep required viscosity
Compressed AirFacility:
Natural gas is drawn by pipe through the filters above thecompressor & the air is compressed. In such a case the air becomesslightly hot. Hence cold water is drawn to reduce the temperature ofcompressed air. Thus the cold water becomes slightly hot & goesthrough outlet pipe to the overhead deserver. Then the water falls
128
slowly through a sieve and becomes cool & feed to the compressor. Atthe other hand the cooled compressed air along with some vapors aretransferred to the reservoir where the vapors are condensed and outletsdrop by drop.The moist compressed air is transferred to the dryer & a slight warmcompresses air is delivered to required sections of PARAMOUNTTEXTILE LIMITED.
Capacity:Total number ofCompressor
: 2+4 =6
Capacity : 41.4 * 6= 248.4Pressure of deliver air : 8.5 bars (designed)
6.5 – 7.0 bars (actually produced)The compressors deliver oil and moisture free compressed air.
Specification:a) Name: Air compressor (Cop co).b) Brand name: Electronikon-ZR5c) Manufacturer: ATLAS COPCO AIR POWER n.v. WILRIJK,
BELGIUM.d) Model: 2T-250V SDe) Type: Rotary screw type.f) Year of manufacture: 2007-2009
Parameters Set valueUnloading pressure 7 barPressure difference 0.6 barOil pressure 7 barMotor running time 15 sec
Distribution:1. The major consumption of compressed air is in weaving section.
min3m
129
2. To the looms for pick insertion (for Air jet loom).3. To clean different section and machinery4. To the sensors where pneumatic pressure required (computerized
control machines).5. For the compensator movement.6. Pneumatically controlled loading and unloading of yarn dyeing
machinery7. Pneumatically controlled loading and unloading of different
machinery.
Air conditioningFacility:
Water is cooled down below its normal temperature (i.e. 9 – 9.5ºC)through A/C plant. A/C plant to maintain required amount of relativehumidity and temp.
Capacity:Number of A/C plant: 2
Refrigerant specification:1. Lower shell pressure = 6.2 mm Hg (Absorbed +Evaporator)2. Upper shell pressure = 49.8 mm Hg (Low temp. generator)3. High temp. generator pressure = 671.5 mm Hg.4. Dilute solution concentration = 58.6%5. Medium solution concentration = 61.0%6. Strong / concentrated solution concentration=63.4%
130
Distribution:The maintenance of relative humidity and temp is very important
for weaving to reduce yarn breakage and produce quality fabric. A/Cplant maintain required amount of relative humidity (80 – 85%) andtemp (22 – 26ºC) in weaving 1,2,3 section. warping, winding and Finalinspection section.
WaterFacility:
Continuous supply of iron and hardness free water for PTL, PYDLmust be ensured by pump.Capacity:Mainly two pumps are used for water pick up.
Pump Capacity SetupSubmersible pump – I 160m3/hr Discharge value: 100% openSubmersible pump –II
150 m3/hr Discharge value: 100% open
Depth of pump: 140 ft.Also pump for chemical dosing & centrifugal pump for yarn dyeing.
Chemicals used: Soda Ash. Manganese – di – Oxide. Grease or lubricant.
Distribution:The major distributions of water are:
1. PTL dye house.2. PTL weaving preparetoryhouse.3. Boiler house for steam generation.
131
Gas
The gas is supplied from Titas Gas.Gas is used for steam production.Gas is used for power generation.
Generally 36 m3 gases are required to produce 1 ton steam.0.3 – 0.4 m3 Gas is required per KW electricity generation.
Cost:Utility CostElectricity 2.75 Tk/ KWAir 0.30-0.35 Tk/m3Water 17Tk/m3.Waste water 13 Tk/m3Steam 500 Tk/ton.
Effluent Treatment Plant
ETP is used to treat the water used in various purposes in textileprocessing in PARAMOUNT TEXTILE LTD.to make the waterenvironment friendly.Number of plant: 1Area of Plant :30 acresType of ETP : Chemi-Biological PlantCapacity /day : 150 tons ( 150m3)
132
Aeration Tank
Biological Tank-2
Biological Tank-1
Clearifier-1
Clearifier22222222222
Clear water tank
Clear water tank
BlowingTank
Chemical mixing Tank
Biological tank 3
SludgeTank
E.T.P
COLORED WATER
133
Number of treatment plant and their names:1. Tank 1:Blowing tank2. Tank 2:Chemical mixing tank3. Tank 3:Clarifier 14. Tank 4:Clarifier 25. Tank 5: Boilogical tank 16. Tank 6: Boilogical tank 27. Tank 7: Boilogical tank 38. Tank 8:Clear water tank
Chemicals used in ETPName Amount Price tk./kgLime 200 kg 8.5-9Ferrous Sulphate 250 kg 17Polyelctrolyte 2 kg 300
Biological Organ : Bacteria produced naturallyPH Controlling:
PH in ETP is less than 9.If PH is decreases in the ETP, the amount of lime is increased.If PH is increases in the ETP, the amount of Ferrous sulphate is increased.CostingTotal treating capacity per day is 150 tons( 150m3)Total cost per month is 1.5 lacsSo,water treating cost =150000/(150000×30)
=0.03 tk/kg of water
Remarks:Most utility are made of own machines. So the continuous supply ispossible. The costs of utilities are also less than government supply. Forlarge project it consumes more utilities.
134
Store & Inventory Control
135
STORE & INVENTORY CONTROL
INTRODUCTION:Inventory is planning and execution involves participation by
most of the fundamental segment of business sales, production,purchase, finance and accounting. Inventory is a wider sense is definedas any idle resource of an enterprise how ever it is semi-finished packingspares and other stocked in order to meet an expected demand ordistribution.
OBJECTIVES OF INVENTORY CONTROL:
1) Financial activities:a) To save amount of investmentb) To know the cash position
2) Property Protection:a) Preventable wasteb) Insurable damagec) Unauthorized use
3) Operating:a) To obtain the best overall balance between
production and inventory carrying cost.b) To minimize losses
c) To avoid stock out and to keep inventoryholding costs in costs in balance.
136
INVENTORY SYSTEMS:
For Raw Materials:In this factory, Paramount Textiles Limited, raw
materials are yarn of different type, different of count . As according toWeaving section demand yarn is produced in different spinning mills,some times from foreign country and they are kept in the store for rawmaterials in accordance with type and count. As like as polyester, cotton,lycra are kept separately and also to their count variation. Inventoryoffice keeps record of this raw materials amount, their usage andstorage.Raw material partially received from production planning & directlyfrom head office.Material receiving & inspection report (MRIR) is prepared. Receivequantity is mentioned & noted down.Department gives store requisition to warehouse.As per requisition materials supplied & this record is noted down.There is a software which is networking with various section wherethese information are required. The software is Data tex.
For Spares:Different spare parts of Weaving machines and
other equipments are kept in store as inventory so that there are no timeand money losses while it is being used. Here also Data tex software isused.
For Finished Goods:Finished goods in Paramount Textiles are the
Finished Fabric. Finished fabrics are delivered to the garments section orto the buyer. Here also Data tex software is used.
137
STORE ROOM:There are four type store room in PARAMOUNT TEXTILELimited.
a) Yarn Store.a. Grey.b. Dyed.
b) Fabric Store.a. Greige.b. Finished.
c) Main Store.The main store room contain this following goods-
a) Size Chemicals.b) Packing materials.c) Stationary books.d) Electrical & Mechanical parts.e) All kinds of weaving parts.
FREQUENCY ON INVENTORY UPDATE: Monthly inventory control Annual inventory control
SCOPE OF INVENTROY CONTROL: Raw materials : Yarn (Grey & Dyed) Finished fabric Spare parts General store (Capital equipment, Accessories, Stationary,
Maintenance parts)
REMARKS:
The space is noticed to be insufficient considerably. An expansion of space is thus desired for sound inventory. The department is computer oriented .
138
Cost Analysis
139
Costing is the most important tools in any business. In the weaving process,all the functions may go right but if the costing is wrong, the total process willgo on loss in spite of profit.PARAMOUNT has its own technique of costing. Though it is a matter of secretefor the company welfare, PARAMOUNT has given us idea about costing.Some important costing parameters of PARAMOUNT are given belowAverage ppm of loom 600Efficiency 80%Total running hour/day 24Average PPI 60Fixed cost/loom/day (Considering facility and overheads) tk.6000Production cost /picks tk.0.030
Some typical calculation#Total production =(PPM/PPI)×24×60×Efficiency
= (600/60)×24×60×0.80= 292 meters/day
#Costing on picksProduction cost /pick tk.0.025Production cost /min ( Production cost /pick)×PPM
= 0.030×600= 18 tkProduction cost /DAY ( Production cost /min)×60×24
=18×60×24=25920 TK.
Total Production Cost /day = Production cost /DAY + Fixed cost/loom/day=(25920+6000) tk.
=31920 tk.
Production cost /meters = (Total Production Cost /day )/( Totalproduction /day)
= 31920/292 tk=109.31 tk
#selling priceConsidering profit 20% tk.(109.31+109.31*20%)
=tk.131
140
Some important data regarding costing
#Costs of raw materialsCount Type Price$10/1 Autocone 1.616/1 Autocone 1.816/1 Comb 2.120/1 Autocone 2.1520/1 Comb 2.1520/1 Kard 2.020/1 Open end 1.8530/1 Comb 2.2540/1 Comb 3.550/1 Comb 3.760/1 Comb 4.540/2 Comb 3.180/2 Comb 6.5100/2 Comb 7.0024/1 Slub 3.330/1 Slub 3.416/1 Kard 1.95
#Some typical process costing
Construction: 40X40/120X90, 58/59” SoftWarp yarn cost: 0.367Weft yarn cost: 0.260Warp dye cost: 0.231Weft dye cost: 0.111Weaving cost: 0.509Finishing cost: 0.176Total cost/mtr: 1.71
141
Construction: 40X40/110X70, 58/59” SoftWarp yarn cost: 0.336Weft yarn cost: 0.203Warp dye cost: 0.231Weft dye cost: 0.128Weaving cost: 0.396Finishing cost: 0.176Total cost/mtr: 1.45
Construction: 50X50/150X90, 58/59” SoftWarp yarn cost: 0.475Weft yarn cost: 0.270Warp dye cost: 0.231Weft dye cost: 0.131Weaving cost: 0.509Finishing cost: 0.176Total cost/mtr: 1.75
Construction: 50X50/120X96, 58/59” SoftWarp yarn cost: 0.392Weft yarn cost: 0.288Warp dye cost: 0.185Weft dye cost: 0.140Weaving cost: 0.543Finishing cost: 0.176Total cost/mtr: 1.71
#Some typical and their selling priceName Construction Price-TK/meterPlain 40X40/120X80 147Plain 50X50/144X76 144Plain 40X40/110X70 1512/2,s-twill 30X30/110X70 143
142
Marketing Activities
143
PARAMOUNT has a strong marketing policy including a strong marketingmanagent.It has a group of skilled manpower that looks after the strongmarketing strategy.
Man power of markekingDeputy Managing Director
↓Executive Director
↓General Manager
↓Deputy General Manager
↓Assistant General Manager
↓Manager
↓Deputy Manager
↓Assistant Manager
↓Senior executive
↓Executive
↓Junior Executive
CONSUMER OF THE PRODUCTS:
The mill has a great number of renowned and international consumers. Themain consumers of this factory are European country such as Germany, France,Netherlands, Denmark, Italy & England. Following are some regular consumers:
1) C&A2) H&M3) M&S4) TEMA
144
5) MONDIAL6) RADHAMONI7) DEKKO8) CELLIO9) VISION APPAREL10) SHIRT MAKER11) DEFACTO12) CHERRY FIELD13) NEW YORAER14) NAK FASHION15) ULLA POPKEN16) PROMINENT17) DAVID HAWARD
Importing CountriesYarn Size materials Dyes and
chemicalsMachineries
INDIA INDIA INDIA JAPANTHAILAND KOREA INDIA
CHINAKOREA
Duties & Responsibilities of Marketing Officer:
Dealing with the buyer & convince the buyer is the main duty of themarketing officer. A marketing officer also has some other duties. The main dutiesresponsibilities of a marketing officer are given below :-
To prepare cost sheet by dealing with the buyer. To take different steps by discussing with the high officials & merchandisers. To maintain a regular & good relationship between commercial officer &
merchandisers. To maintain a regular communication with the buyer & buying houses. Communicate with the new buyers. Display the better criteria of the products.
145
Remarks :- The marketing activities of this mill is so good. The marketing &merchandising section is well organized
CONCLUSION
146
The industrial training gives us the opportunity to work in mills. It is anexperience of normal academic learning,
This training gives us actual picture about man, machine, material,methods and market. We have earned the direct knowledge about the rawmaterials, actual running condition of the m/c’s. Works technologist andadministration.
This mill is a well planed with enough expansion facilities. Their exist arewonderful employer and worker relation. Working environment for the laborsis also good.
During our training we visited administration section, store, boilersection, generator room, compressor section etc. Everywhere we got cordialbehavior from all employees
Above all this training for 46 days in the Paramount Textile Ltd. has given us anew experience for practical life.
College of Textile Technology has given me the field to perform theindustrial attachment with Paramount Textile Ltd. This attachment seems tome as a bridge to minimize the gap between theoretical and practicalknowledge. Undoubtedly, this attachment paved us the way to learn more
147
about Textile Technology, industrial practices, and industrial managementand production process.
Besides this attachment gave us the first opportunity to work in anIndustry and acquainted us with the internal sight and sound of TextileIndustries. I believe with all these, the experience of the industrial attachmentwill help our future life as a Textile Technologist.