  • Indoor Structures

    Contents

    B2 Traditional Buildings

    2

    B3 Air Supported Structures

    16

    B4 Frame Fabric Structure

    67

  • B2 INDOOR COURTS BUILDING BRIEF TRADITIONAL

    BUILDINGS

  • Contents

    Introduction

    2

    Project Lifecycle

    3

    LTA Funding

    4

    Standards

    4

    Statutory Approvals

    4

    Disabled Users Policy

    4

    Contract

    4

    Design Principles

    5

    Environmental Issues

    6

    Design Parameters -Tennis Hall Dimensions -Court Surface -Walls -Roof Lights -Ceilings -Heating and Ventilation -Electrical Services

    6 6 7 8 9 9

    10 10

    Lighting

    11

    Provisional Sums 14

    Outdoor Courts

    14

    Non-Traditional Buildings

    14

    Introduction

    The purpose of the Lawn Tennis Association (LTA) Indoor Building Brief is to provide a guide

    to the minimum standards to which indoor courts should be constructed. The Brief consists of

    recommended minimum design parameters. This information should not be considered to be

    a complete brief in itself but the basis from which a full project brief, design and specification

    can be evolved.

  • It should be noted that the standards contained in this document are for most levels of play

    however some dimensions require to be exceeded for specialist events, services and

    tournaments. In these instances further advice should be sought from the LTA. Further

    requirements will also need to be agreed where space is to be allocated for coaching, LTA

    county and area offices.

    Project Life Cycle

    START ON

    SITE

    Key

    Stage

    One

    FEASIBILITY /

    PLANNING

    Two

    DESIGN STAGE

    Three

    CONSTRUCTION

    STAGE

    Four

    OPERATION AND

    MAINTENANCE

    Confirm funding for

    tennis structure

    Appoint PM/ project

    team.

    Project team to decide

    Type of court surface

    Type of structure

    Sixe of structure (LTA

    dimensions met

    including foundations

    and drainage).

    Number, type and

    location of doors.

    Power supply

    required.

    Lighting (levels to be

    obtained and location)

    and heating required.

    Contact planning

    officer for there

    opinions on gaining

    planning permission.

    PM to submit planning

    application.

    Project team to:

    Select procurement

    route.

    Produce project brief

    / scope of works

    document.

    Prepare tender

    package (based on

    guidance note B2).

    Submit tender

    package to LTA for

    review and comment.

    Send approved

    tender to suitable

    suppliers.

    Review contractors

    bids and submit to

    LTA for comment and

    review.

    Appoint contractor.

    Review design

    packages submitted

    by contractor.

    Review design

    packages submitted

    by contractor.

    Submit final design to

    LTA and other

    bodies.

    PM to arrange a pre

    start meeting to confirm

    site logistics.

    PM to monitor

    construction of the

    building to ensure that it

    complies with the

    Employers Requirement

    and guidance note B2.

    On completion of the

    project the purchaser

    receives a maintenance

    manual from the

    contractor.

    PM in association with

    the LTA to undertake

    completion and

    commissioning checks

    and tests.

    Club to appoint person

    (s) to be responsible for

    maintenance.

    Commence

    maintenance regime in

    accordance with

    maintenance manual.

    Submit records to LTA

    quarterly.

  • LTA Funding

    All LTA funding for Indoor Tennis Court projects is conditional upon compliance with the

    minimum requirements of the LTA Indoor Building Brief.

    Standards

    All construction projects should conform to the minimum requirements of all relevant current building legislation, including British Standards and Codes of Practice.

    Statutory Approvals

    The LTA requires confirmation in writing that Building Regulation and appropriate Planning

    approvals have been obtained before construction begins.

    It should be noted that the Construction Design & Management Regulations 1994 (CDM

    Regulations) will apply to all but a few minor projects.

    Disabled Users Policy

    Please refer to Guidance Note B1 for details of the Disabled Users Policy.

    Contract

    All projects that require LTA funding should use a recognised standard form of building

    contract eg Joint Contracts Tribunal (JCT) standard forms, which are suitable for dealing with

    a range of project values and types.

    Space should be allocated on the construction site signboard for an LTA Building for Tennis

    sign (310mm x 1220mm).

  • Design Principles

    The design of the centre should create a building with warmth of character and environment

    that will be attractive to users of all ages and abilities.

    The accommodation should be fit for its intended purpose and made attractive by the considered use of materials, textures and colours in suitable combinations. In addition to satisfying the fundamental requirements of function, safety, elegance and economy, the design must minimise future maintenance needs and running costs.

    Effective regulation must be maintained of both natural and artificial lighting and of the

    internal environment. Mechanical and electrical systems should meet the requirements of the

    brief, be suitably concealed without prejudice to their operation and maintenance. They

    should not interfere with the use of the indoor courts or conflict with the clear height

    requirements above the courts.

    The relationship between internal and external spaces and between the tennis courts, and

    ancillary accommodation, etc should show creativity in design but should also provide an

    economically suitable solution. The following key issues should be considered:

    views from social area to indoor/ outdoor courts positioned so as to avoid distracting players

    accessibility for users to coaching/tennis development staff

    accessibility from car park to main entrance for all users

    a viewing area within the tennis hall, behind the baseline of indoor courts with easy access for disabled and family users

    good clear signage internally and externally combined with a considered use of colour and texture

    parent and child bays or a drop off point system should be included in any scheme in addition to statutory minimum requirements

    revenue facilities should be easily accessible to social/entrance spaces

  • each internal and external court should be easily accessible without disturbing users on adjacent courts e.g. by the use of separate access doors for each court

    the indoor hall should be positioned so that it does not overshadow any outdoor courts.

    Environmental Issues

    The LTA embraces environmental issues in the design of tennis facilities. The following

    areas should be considered:

    use of materials obtained from renewable sources

    measures to minimise dependence on finite fossil fuels, emissions and operating costs and improve energy efficiency.

    Design Parameters

    Tennis Hall Dimensions

    Principal Play

    Area

    Other

    Dimensions

    Length

    Width

    Length of net (doubles)

    23.77m (78 0)

    10.97m (36 0)

    12.8m (42 0)

    Min Runback (ie clear

    depth behind baselines, at

    each end)

    6.40m (21 0)

    Width of lines (white)

    included within above

    court size

    see drawing

    Min Side-run (ie clear

    width beside each side)

    3.66m (12 0)

    Min Side-run between

    courts not separately

    enclosed

    4.27m (14 0)

    Unobstructed height at

    netline

    9.00m (29 6) min

    Unobstructed height at

    base line

    5.75m (18 11) min

  • Unobstructed height at

    rear of run-back

    4.00m (13 1) min

    Total length 36.57m (120 0)

    Width for one enclosed ct 18.29m (60 0)

    Width for two enclosed cts 33.53m (110 0)

    Width for three enclosed

    cts

    48.77m (160 0)

    Width for four enclosed cts 64.01m (210 0)

    The minimum clearances and dimensions given above shall not be infringed without the prior approval of the LTA. In certain circumstances, space restrictions may reduce the available clearance, and the LTA will consider such situations on their individual merits. Special clearance requirements apply in the case of air-supported structures, as defined in the separate LTA Brief for Non-Traditional Structures (B3).

    Court Surface The LTA must approve the choice of playing surface and its colours.

    The main contractor will be required to obtain the written approval of the playing surface

    installer as to the suitability of the prepared sub-base before laying of the playing surface

    commences. This approval must be copied to the LTA.

    The playing surface must lie in a single level horizontal plain with no gradient. The maximum

    permitted tolerance in the level of the finished playing surface is a 6mm gap under a 3m

    straight edge.

    Movement joints will not be allowed in the court surface of