Indicative Cost Estimate
Transcript of Indicative Cost Estimate
13 October 2017
Declan Brady Associate Director
Turner & Townsend Pty Ltd Level 13 140 Creek Street Brisbane QLD 4000
t: +64 223 27 4806
e: [email protected] w: www.turnerandtownsend.com.au
Indicative Cost Estimate
Underwood Park Development Masterplan
Tait Morton Johnson Architects
making the difference
Tait Morton Johnson Architects
Underwood Park Development Masterplan
Turner & Townsend 02
Contents
1 Introduction 3
2 Cost plan summary 3
3 Basis of cost plan 3
4 Cost plan pricing 3
Escalation Forecast 4
Contingency and Risk 4
Cost Plan Methodology 4
5 Assumptions and exclusions 4
Project specific assumptions and exclusions 4
6 Information used in cost plan 5
Appendix A – Detailed cost breakdown 6
Rev Originator Approved Date
0 Jennifer Wright Scott Winter 12/10/17
© Turner & Townsend Pty Ltd. This document is expressly provided to and solely for the use of Tait Morton Johnson Architects on the Underwood Park Development Masterplan and takes into account their particular instructions and requirements. It must not be made
available or copied or otherwise quoted or referred to in whole or in part in any way, including orally, to any other party without our
express written permission and we accept no liability of whatsoever nature for any use by any other party.
F:\Bne\projects\br xxx underwood park development\2000 Costplan\2200 Cost Plans\2210 Indicative CP\2211 Cost Plan Files
Tait Morton Johnson Architects
Underwood Park Development Masterplan
Turner & Townsend 03
1 Introduction
We have been requested by Tait Morton Johnson Architects to provide an indicative estimate
for the Underwood Park Development Masterplan based on the conceptual design information
that has been completed by TMJ Architects.
The works generally comprise;
New build - Multipurpose community facility
New build – Indoor Sports facility including under-croft carpark
New build – Netball clubhouse and external playing courts
External works including; new carpark and hard and soft landscaping
2 Cost plan summary
This indicative cost plan report has been requested to establish the likely budget for the
creation of above mentioned areas.
Please refer to Appendix A for a detailed breakdown of this cost plan
3 Basis of cost plan
It is anticipated that the works will be undertaken in a single phase and by a single contractor
on a design and construct basis. However, we have been requested to provide a separate split
of the likely costs per functional basis, should the project need to be phased.
4 Cost plan pricing
The rates included in this cost plan have been determined through the analysis of similar
projects and benchmarking accordingly. We emphasise that budget cost advice derived in this
manner is indicative only. We recommend that as the proposed development progresses to a
more advanced stage, a detailed elemental estimate be commissioned to provide a greater
level of costing accuracy.
Cost Summary Area Unit Rate Total
External works 60,000 m2 16 948,850
New Netball Courts & Club house 3,177 m2 391 1,240,800
Future Indoor Sports Building 2,640 m2 2,564 6,768,000
Multipurpose Community Facility 3,672 m2 1,219 4,477,200
Subtotal 9,489 m2 1,416 13,434,850
Preliminaries 14 % 13,434,850 1,881,000
Builders Margin 4 % 15,315,850 613,000
Construction contingency 15 % 15,928,850 2,389,000
Total Anticipated Project Budget (exclude GST) 9,489 m2 1,930 18,317,850
Tait Morton Johnson Architects
Underwood Park Development Masterplan
Turner & Townsend 04
Escalation Forecast
Escalation forecasts have been excluded as it is not understood when this project is intended
to commence. However, should the project be tendered in 2017 – 2018 we recommend an
allowance for budget purposes of 2-3% p.a. should be applied.
Contingency and Risk
We have included a 15% contingency allowance for this project which is intended to cover
minor construction risks and is not intended to cover scope changes.
Cost Plan Methodology
This Cost Plan is based upon the design documentation prepared by Tait Morton Johnson
Architects. Please also refer to the Assumptions and Exclusions section of this report.
5 Assumptions and exclusions
Project specific assumptions and exclusions
Noted exclusions:
Removal of contaminated material including any asbestos
Conservation of site biodiversity
Flood prevention works
Rock excavation
Legal costs and charges
Stamp duties on leases
Loose furniture
IT equipment and set up costs
Escalation
Design fees
GST
Client Costs
Consultant / Authority Fees
Works and services outside immediate site boundary have been excluded
Decorative or feature walls and ceilings
Loose furniture, fixtures and equipment
Allowance for statutory signage only
Upgrading of services, electrical supply, drainage capacity, fire services and the like
Other exclusions noted in the detailed measure
Tait Morton Johnson Architects
Underwood Park Development Masterplan
Turner & Townsend 05
6 Information used in cost plan
P.01 [P4] MASTER SITE LAYOUT 6_10_2017
P.02 [P4] SITE 6_10_2017
P.03 [P4] NETBALL GROUND FLOOR_OVERFLOW CARPARK (STAGE 1) 6_10_2017
P.04 [P4] NETBALL GROUND FLOOR_CARPARK (STAGE 2) 6_10_2017
P.05 [P4] GROUND FLOOR (STAGE 1) 6_10_2017
P.06 [P4] GROUND FLOOR (STAGE 2) 6_10_2017
P.07 [P4] UPPER FLOOR (STAGE 1) 6_10_2017
P.08 [P4] UPPER FLOOR (STAGE 2) 6_10_2017
P.09 [P4] SECTION 6_10_2017
P.10 [P4] 3D VIEWS 6_10_2017
Tait Morton Johnson Architects
Underwood Park Development Masterplan
Turner & Townsend 06
Appendix A – Detailed cost breakdown
SummarySummarySummarySummary
Project:Project:Project:Project: Underwood Park DevelopmentBui lding:Bui lding:Bui lding:Bui lding: Underwood Park Development Masterplan -
Concept
Details:Details:Details:Details: Concept Masterplan summary 171010
Code Description Quantity Unit Rate Subtotal Factor Total
External Works 60,000 m2 15.81 948,850 948,850
New Netball Courts & Club House 3,177 m2 390.56 1,240,800 1,240,800
Future Indoor Sports Building (Stage
2)
2,640 m2 2,563.64 6,768,000 6,768,000
Multipurpose Community facility
(Stage 1)
3,672 m2 1,219.28 4,477,200 4,477,200
Subtotal 9,489 m2 1,415.83 13,434,85
0
13,434,850
Preliminaries 14 % 13,434,850 1,881,000 1,881,000
Margin 4 % 15,315,850 613,000 613,000
Contingency 15 % 15,928,850 2,389,000 2,389,000
Total Construction Cost 9,489 m2 1,930.43 18,317,85
0
18,317,850
13/10/2017 3:36:09 PM Turner & Townsend Page 1 of 1
SummarySummarySummarySummary
Project:Project:Project:Project: Underwood Park DevelopmentBui lding:Bui lding:Bui lding:Bui lding: Underwood Park Development Masterplan -
Concept
Details:Details:Details:Details: external works
Code Description Quantity Unit Rate Subtotal Factor Total
Site Preparation
Allowance for demolition of existing
structures
2,753 m2 45.00 123,900 123,900
Allowance for 'removing' existingcaretaker building from currentlocation
110 m2 45.00 4,950 4,950
Allowance for breaking up existing
carpark
2,772 m2 28.00 78,000 78,000
Allowance for breaking up existing
roadworks; for connection to new
1 item 5,000.00 5,000 5,000
Allowance for site preparation and
clearing; including tree removal
1 item 20,000.00 20,000 20,000
Allowance for dewatering 1 item 20,000.00 20,000 20,000
Extra over allowance for low strength
rock excavation (approx 25%)
Excl
Alterations
Allowance for installation of existingcaretakers building; includingfoundations and service connections
110 m2 50.00 5,500 5,500
Allowance for making good existingfacilities; minor upgrade works tofollowing
bmx track 1 item 5,000.00 5,000 5,000
existing car park 1 item 5,000.00 5,000 5,000
football fields 1 item 5,000.00 5,000 5,000
netball courts 1 item 5,000.00 5,000 5,000
Roads, Footpaths etc
Allowance for new carpark; asphalt on
sub base, kerbing, linemarking etc
4,063 m2 85.00 345,400 345,400
Allowance for entrance roads to sports
building under croft
164 m2 85.00 14,000 14,000
Allowance for connecting walkway 338 m2 80.00 27,000 27,000
Allowance for paved access road 467 m2 100.00 46,700 46,700
Allowance for diversions and
relocations
1 item 15,000.00 15,000 15,000
Landscaping
Allowance for soft landscaping across
site; to suit concept design
60,000 m2 1.00 60,000 60,000
Allowance for hard landscaping across
site; unidentified
1 item 30,000.00 30,000 30,000
Allowance for retaining wall adjacent
netball clubhouse (assumed 1m high)
64 m2 600.00 38,400 38,400
Allowance for security fencing; as
required
Excl
13/10/2017 3:48:30 PM Turner & Townsend Page 1 of 2
SummarySummarySummarySummary
Project:Project:Project:Project: Underwood Park DevelopmentBui lding:Bui lding:Bui lding:Bui lding: Underwood Park Development Masterplan -
Concept
Details:Details:Details:Details: external works
Code Description Quantity Unit Rate Subtotal Factor Total
Services
Allowance for lighting and power
upgrade across site
1 item 10,000.00 10,000 10,000
Allowance for external stormwater
upgrade across site
1 item 50,000.00 50,000 50,000
Allowance for gas services upgrade
across site
1 item 35,000.00 35,000 35,000
Subtotal 60,000 m2 15.81 948,850 948,850
13/10/2017 3:48:30 PM Turner & Townsend Page 2 of 2
SummarySummarySummarySummary
Project:Project:Project:Project: Underwood Park DevelopmentBui lding:Bui lding:Bui lding:Bui lding: Underwood Park Development Masterplan -
Concept
Details:Details:Details:Details: Netball courts & clubhouse
Code Description Quantity Unit Rate Subtotal Factor Total
SW Siteworks 3,177 m2 61.98 196,900 196,900
SB Substructure 316 m2 80.70 25,500 25,500
RF Roof 316 m2 133.23 42,100 42,100
EW External Walls 316 m2 211.08 66,700 66,700
WW Windows and Glazing 316 m2 28.48 9,000 9,000
ED Doors 316 m2 42.72 13,500 13,500
NW Internal Walls 316 m2 53.80 17,000 17,000
WF Wall Finishes 316 m2 29.75 9,400 9,400
FF Floor Finishes 316 m2 107.91 34,100 34,100
CF Ceiling Finishes 316 m2 77.53 24,500 24,500
FT Fitments 316 m2 104.11 32,900 32,900
PD Sanitary Fixtures, Plumbing and Gas 316 m2 62.03 19,600 19,600
AC Air Conditioning Excl
FP Fire Protection 316 m2 8.23 2,600 2,600
LP Electric Light, Power and
Communications
316 m2 157.59 49,800 49,800
LD Landscaping 2,862 m2 243.61 697,200 697,200
Subtotal 3,177 m2 390.56 1,240,800 1,240,800
13/10/2017 3:49:56 PM Turner & Townsend Page 1 of 1
Detailed BreakdownDetailed BreakdownDetailed BreakdownDetailed Breakdown
Project:Project:Project:Project: Underwood Park DevelopmentBui lding:Bui lding:Bui lding:Bui lding: Underwood Park Development Masterplan -
Concept
Details:Details:Details:Details: Netball courts & clubhouse
Code Description Quantity Unit Rate Subtotal Factor Total
S iteworksS iteworksS iteworksS iteworks
Allowance for bulk excavations; to new
netball court and clubhouse
4,923 m3 25.00 123,100 123,100
Additional allowance for removal of
excavated spoil from site
4,923 m3 15.00 73,800 73,800
Extra over allowance for low strength rock
excavation (approx 25%)
Excl
SiteworksSiteworksSiteworksSiteworks 196,900196,900196,900196,900
To Collec t ionTo Collec t ionTo Collec t ionTo Collec t ion 196,900
13/10/2017 3:49:16 PM Turner & Townsend Page 1 of 15
Detailed BreakdownDetailed BreakdownDetailed BreakdownDetailed Breakdown
Project:Project:Project:Project: Underwood Park DevelopmentBui lding:Bui lding:Bui lding:Bui lding: Underwood Park Development Masterplan -
Concept
Details:Details:Details:Details: Netball courts & clubhouse
Code Description Quantity Unit Rate Subtotal Factor Total
Subs t ruc tureSubs t ruc tureSubs t ruc tureSubs t ruc ture
Allowance for detailed excavations 48 m3 100.00 4,800 4,800
Allowance for footings; including
reinforcement
48 m3 250.00 12,000 12,000
Allowance to concrete slab; including
reinforcement; assumed 120 thick
38 m2 230.00 8,700 8,700
SubstructureSubstructureSubstructureSubstructure 25,50025,50025,50025,500
To Collec t ionTo Collec t ionTo Collec t ionTo Collec t ion 25,500
13/10/2017 3:49:16 PM Turner & Townsend Page 2 of 15
Detailed BreakdownDetailed BreakdownDetailed BreakdownDetailed Breakdown
Project:Project:Project:Project: Underwood Park DevelopmentBui lding:Bui lding:Bui lding:Bui lding: Underwood Park Development Masterplan -
Concept
Details:Details:Details:Details: Netball courts & clubhouse
Code Description Quantity Unit Rate Subtotal Factor Total
RoofRoofRoofRoof
Allowance for roof sheeting complete;framing, metal sheet; including insulation,safety mesh, flashing, etc
316 m2 120.00 37,900 37,900
Allowance for roof plumbing; including
downpipes
84 m 50.00 4,200 4,200
RoofRoofRoofRoof 42,10042,10042,10042,100
To Collec t ionTo Collec t ionTo Collec t ionTo Collec t ion 42,100
13/10/2017 3:49:16 PM Turner & Townsend Page 3 of 15
Detailed BreakdownDetailed BreakdownDetailed BreakdownDetailed Breakdown
Project:Project:Project:Project: Underwood Park DevelopmentBui lding:Bui lding:Bui lding:Bui lding: Underwood Park Development Masterplan -
Concept
Details:Details:Details:Details: Netball courts & clubhouse
Code Description Quantity Unit Rate Subtotal Factor Total
Ex ternal Wal lsEx ternal Wal lsEx ternal Wal lsEx ternal Wal ls
Allowance for 190 thick blockwork 215 m2 250.00 53,800 53,800
Allowance to render coat and paint 215 m2 60.00 12,900 12,900
External WallsExternal WallsExternal WallsExternal Walls 66,70066,70066,70066,700
To Collec t ionTo Collec t ionTo Collec t ionTo Collec t ion 66,700
13/10/2017 3:49:16 PM Turner & Townsend Page 4 of 15
Detailed BreakdownDetailed BreakdownDetailed BreakdownDetailed Breakdown
Project:Project:Project:Project: Underwood Park DevelopmentBui lding:Bui lding:Bui lding:Bui lding: Underwood Park Development Masterplan -
Concept
Details:Details:Details:Details: Netball courts & clubhouse
Code Description Quantity Unit Rate Subtotal Factor Total
Windows and G laz ingWindows and G laz ingWindows and G laz ingWindows and G laz ing
Allowance for single glazing in clear anodised
aluminium framing (assumed 20%)
18 m2 500.00 9,000 9,000
Windows and GlazingWindows and GlazingWindows and GlazingWindows and Glazing 9,0009,0009,0009,000
To Collec t ionTo Collec t ionTo Collec t ionTo Collec t ion 9,000
13/10/2017 3:49:16 PM Turner & Townsend Page 5 of 15
Detailed BreakdownDetailed BreakdownDetailed BreakdownDetailed Breakdown
Project:Project:Project:Project: Underwood Park DevelopmentBui lding:Bui lding:Bui lding:Bui lding: Underwood Park Development Masterplan -
Concept
Details:Details:Details:Details: Netball courts & clubhouse
Code Description Quantity Unit Rate Subtotal Factor Total
DoorsDoorsDoorsDoors
External
Allowance for single timber doors; to change
rooms
4 no 1,500.00 6,000 6,000
Allowance for single timber doors; to toilet
facilities and Referee change rooms
5 no 1,500.00 7,500 7,500
DoorsDoorsDoorsDoors 13,50013,50013,50013,500
To Collec t ionTo Collec t ionTo Collec t ionTo Collec t ion 13,500
13/10/2017 3:49:16 PM Turner & Townsend Page 6 of 15
Detailed BreakdownDetailed BreakdownDetailed BreakdownDetailed Breakdown
Project:Project:Project:Project: Underwood Park DevelopmentBui lding:Bui lding:Bui lding:Bui lding: Underwood Park Development Masterplan -
Concept
Details:Details:Details:Details: Netball courts & clubhouse
Code Description Quantity Unit Rate Subtotal Factor Total
In ternal Wal lsIn ternal Wal lsIn ternal Wal lsIn ternal Wal ls
Allowance for internal walls; lightweight stud
framing lining to both sides
142 m2 120.00 17,000 17,000
Internal WallsInternal WallsInternal WallsInternal Walls 17,00017,00017,00017,000
To Collec t ionTo Collec t ionTo Collec t ionTo Collec t ion 17,000
13/10/2017 3:49:16 PM Turner & Townsend Page 7 of 15
Detailed BreakdownDetailed BreakdownDetailed BreakdownDetailed Breakdown
Project:Project:Project:Project: Underwood Park DevelopmentBui lding:Bui lding:Bui lding:Bui lding: Underwood Park Development Masterplan -
Concept
Details:Details:Details:Details: Netball courts & clubhouse
Code Description Quantity Unit Rate Subtotal Factor Total
Wal l Fin ishesWal l Fin ishesWal l Fin ishesWal l Fin ishes
Allowance to paint internal walls 472 m2 20.00 9,400 9,400
Wall FinishesWall FinishesWall FinishesWall Finishes 9,4009,4009,4009,400
To Collec t ionTo Collec t ionTo Collec t ionTo Collec t ion 9,400
13/10/2017 3:49:16 PM Turner & Townsend Page 8 of 15
Detailed BreakdownDetailed BreakdownDetailed BreakdownDetailed Breakdown
Project:Project:Project:Project: Underwood Park DevelopmentBui lding:Bui lding:Bui lding:Bui lding: Underwood Park Development Masterplan -
Concept
Details:Details:Details:Details: Netball courts & clubhouse
Code Description Quantity Unit Rate Subtotal Factor Total
F loor F in ishesFloor F in ishesFloor F in ishesFloor F in ishes
Allowance for ceramic tiling; to amenities and
change facilities
243 m2 100.00 24,300 24,300
Allowance for skirting; to amenities and
change facilities
158 m 25.00 4,000 4,000
Allowance for waterproof sealant; to veranda
slab
64 m2 90.00 5,800 5,800
Floor FinishesFloor FinishesFloor FinishesFloor Finishes 34,10034,10034,10034,100
To Collec t ionTo Collec t ionTo Collec t ionTo Collec t ion 34,100
13/10/2017 3:49:16 PM Turner & Townsend Page 9 of 15
Detailed BreakdownDetailed BreakdownDetailed BreakdownDetailed Breakdown
Project:Project:Project:Project: Underwood Park DevelopmentBui lding:Bui lding:Bui lding:Bui lding: Underwood Park Development Masterplan -
Concept
Details:Details:Details:Details: Netball courts & clubhouse
Code Description Quantity Unit Rate Subtotal Factor Total
Cei l ing F in ishesCei l ing F in ishesCei l ing F in ishesCei l ing F in ishes
Allowance for plasterboard and paint; to all
internal areas
243 m2 80.00 19,400 19,400
Allowance for Fibercement and paint; to
Veranda area
64 m2 80.00 5,100 5,100
Ceiling FinishesCeiling FinishesCeiling FinishesCeiling Finishes 24,50024,50024,50024,500
To Collec t ionTo Collec t ionTo Collec t ionTo Collec t ion 24,500
13/10/2017 3:49:16 PM Turner & Townsend Page 10 of 15
Detailed BreakdownDetailed BreakdownDetailed BreakdownDetailed Breakdown
Project:Project:Project:Project: Underwood Park DevelopmentBui lding:Bui lding:Bui lding:Bui lding: Underwood Park Development Masterplan -
Concept
Details:Details:Details:Details: Netball courts & clubhouse
Code Description Quantity Unit Rate Subtotal Factor Total
F i tmentsF i tmentsF i tmentsF i tments
Vanity bench 9 m 350.00 3,150 3,150
Mirror 8 m2 300.00 2,400 2,400
Soap dispenser 3 no 50.00 150 150
Toilet Roll holder 3 no 50.00 150 150
Hand dryer 3 no 200.00 600 600
Grab rail to PWD toilet 1 no 250.00 250 250
Baby change table to PWD 1 no 1,000.00 1,000 1,000
Change rooms bench seating including coat
rack
58 m 400.00 23,200 23,200
Allowance for signage 1 item 1,000.00 1,000 1,000
Allowance for sundries 1 item 1,000.00 1,000 1,000
FitmentsFitmentsFitmentsFitments 32,90032,90032,90032,900
To Collec t ionTo Collec t ionTo Collec t ionTo Collec t ion 32,900
13/10/2017 3:49:16 PM Turner & Townsend Page 11 of 15
Detailed BreakdownDetailed BreakdownDetailed BreakdownDetailed Breakdown
Project:Project:Project:Project: Underwood Park DevelopmentBui lding:Bui lding:Bui lding:Bui lding: Underwood Park Development Masterplan -
Concept
Details:Details:Details:Details: Netball courts & clubhouse
Code Description Quantity Unit Rate Subtotal Factor Total
Sani tary F ix tures , P lumbing and GasSani tary F ix tures , P lumbing and GasSani tary F ix tures , P lumbing and GasSani tary F ix tures , P lumbing and Gas
Sanitary Fixtures
WC 2 no 800.00 1,600 1,600
Accessible WC 1 no 850.00 800 800
Wall hung basin 2 no 450.00 900 900
Wall hung basin; to accessible WC 4 no 450.00 1,800 1,800
Allowance for plumbing points and drainage 9 no 1,500.00 13,500 13,500
Builders Work In Connection with Services 5 % 18,600.00 1,000 1,000
Sanitary Fixtures, Plumbing and GasSanitary Fixtures, Plumbing and GasSanitary Fixtures, Plumbing and GasSanitary Fixtures, Plumbing and Gas 19,60019,60019,60019,600
To Collec t ionTo Collec t ionTo Collec t ionTo Collec t ion 19,600
13/10/2017 3:49:16 PM Turner & Townsend Page 12 of 15
Detailed BreakdownDetailed BreakdownDetailed BreakdownDetailed Breakdown
Project:Project:Project:Project: Underwood Park DevelopmentBui lding:Bui lding:Bui lding:Bui lding: Underwood Park Development Masterplan -
Concept
Details:Details:Details:Details: Netball courts & clubhouse
Code Description Quantity Unit Rate Subtotal Factor Total
F i re Protec t ionF i re Protec t ionF i re Protec t ionF i re Protec t ion
Allowance for fire protection 316 m2 8.00 2,500 2,500
Builders Work In Connection with Services 5 % 2,500.00 100 100
Fire ProtectionFire ProtectionFire ProtectionFire Protection 2,6002,6002,6002,600
To Collec t ionTo Collec t ionTo Collec t ionTo Collec t ion 2,600
13/10/2017 3:49:16 PM Turner & Townsend Page 13 of 15
Detailed BreakdownDetailed BreakdownDetailed BreakdownDetailed Breakdown
Project:Project:Project:Project: Underwood Park DevelopmentBui lding:Bui lding:Bui lding:Bui lding: Underwood Park Development Masterplan -
Concept
Details:Details:Details:Details: Netball courts & clubhouse
Code Description Quantity Unit Rate Subtotal Factor Total
E lec t r ic Light , Power and Communicat ionsE lec t r ic Light , Power and Communicat ionsE lec t r ic Light , Power and Communicat ionsE lec t r ic Light , Power and Communicat ions
Allowance for electrical, communications and
security services
316 m2 150.00 47,400 47,400
Builders Work In Connection with Services 5 % 47,400.00 2,400 2,400
Electric Light, Power and CommunicationsElectric Light, Power and CommunicationsElectric Light, Power and CommunicationsElectric Light, Power and Communications 49,80049,80049,80049,800
To Collec t ionTo Collec t ionTo Collec t ionTo Collec t ion 49,800
13/10/2017 3:49:16 PM Turner & Townsend Page 14 of 15
Detailed BreakdownDetailed BreakdownDetailed BreakdownDetailed Breakdown
Project:Project:Project:Project: Underwood Park DevelopmentBui lding:Bui lding:Bui lding:Bui lding: Underwood Park Development Masterplan -
Concept
Details:Details:Details:Details: Netball courts & clubhouse
Code Description Quantity Unit Rate Subtotal Factor Total
LandscapingLandscapingLandscapingLandscaping
New concrete slab to netball court 2,862 m2 150.00 429,300 429,300
Allowance for acrylic surfacing to netball
courts
2,862 m2 40.00 114,500 114,500
Chain mesh fence to external courts;
including gates
222 m 250.00 55,500 55,500
Allowance for external steps to clubhouse;assumed 200 thick including formwork,reinforcement and finish
8 m3 300.00 2,400 2,400
Allowance for balustrade including handrail;
to either side
10 m 500.00 5,000 5,000
Fitments
Hoops 8 no 2,000.00 16,000 16,000
Line-marking; to netball court 1 item 10,000.00 10,000 10,000
Allowance for court side seating 1 item 10,000.00 10,000 10,000
Allowance for signage 1 item 2,000.00 2,000 2,000
Services
Allowance for lighting to courts 1 item 50,000.00 50,000 50,000
Builders work in connection 5 % 50,000.00 2,500 2,500
LandscapingLandscapingLandscapingLandscaping 697,200697,200697,200697,200
To Collec t ionTo Collec t ionTo Collec t ionTo Collec t ion 697,200
13/10/2017 3:49:16 PM Turner & Townsend Page 15 of 15
SummarySummarySummarySummary
Project:Project:Project:Project: Underwood Park DevelopmentBui lding:Bui lding:Bui lding:Bui lding: Underwood Park Development Masterplan -
Concept
Details:Details:Details:Details: Future Indoor Sports Building (Stage 2)
Code Description Quantity Unit Rate Subtotal Factor Total
SB Substructure 2,640 m2 1,100.00 2,904,000 2,904,000
SS Structural steel 2,640 m2 370.00 976,800 976,800
UF Upper Floors 2,640 m2 4.85 12,800 12,800
SC Staircase 2,640 m2 13.64 36,000 36,000
RF Roof 2,640 m2 200.30 528,800 528,800
EW External Walls 2,640 m2 121.48 320,700 320,700
WW Windows and Glazing 2,640 m2 143.60 379,100 379,100
ED External Doors 2,640 no 21.97 58,000 58,000
NW Internal Walls 2,640 m2 7.20 19,000 19,000
WF Wall Finishes 2,640 m2 23.71 62,600 62,600
FF Floor Finishes 2,640 m2 195.45 516,000 516,000
CF Ceiling Finishes 2,640 m2 133.48 352,400 352,400
FT Fitments 2,640 m2 39.39 104,000 104,000
PD Sanitary Fixtures, Plumbing and Gas 2,640 m2 15.76 41,600 41,600
AC Air Conditioning 2,640 m2 41.14 108,600 108,600
FP Fire Protection 2,640 m2 7.88 20,800 20,800
LP Electric Light, Power and
Communications
2,640 m2 123.79 326,800 326,800
Subtotal 2,640 m2 2,563.64 6,768,000 6,768,000
13/10/2017 3:45:21 PM Turner & Townsend Page 1 of 1
Detailed BreakdownDetailed BreakdownDetailed BreakdownDetailed Breakdown
Project:Project:Project:Project: Underwood Park DevelopmentBui lding:Bui lding:Bui lding:Bui lding: Underwood Park Development Masterplan -
Concept
Details:Details:Details:Details: Future Indoor Sports Building (Stage 2)
Code Description Quantity Unit Rate Subtotal Factor Total
Subs t ruc tureSubs t ruc tureSubs t ruc tureSubs t ruc ture
Undercroft carpark
Allowance for undercroft carpark; includingbulk excavations; foundations; ground floorslab; staircase and associated services
2,640 m2 1,100.00 2,904,000 2,904,000
SubstructureSubstructureSubstructureSubstructure 2,904,0002,904,0002,904,0002,904,000
To Collec t ionTo Collec t ionTo Collec t ionTo Collec t ion 2,904,000
13/10/2017 3:44:13 PM Turner & Townsend Page 1 of 17
Detailed BreakdownDetailed BreakdownDetailed BreakdownDetailed Breakdown
Project:Project:Project:Project: Underwood Park DevelopmentBui lding:Bui lding:Bui lding:Bui lding: Underwood Park Development Masterplan -
Concept
Details:Details:Details:Details: Future Indoor Sports Building (Stage 2)
Code Description Quantity Unit Rate Subtotal Factor Total
S t ruc tura l s tee lS t ruc tura l s tee lS t ruc tura l s tee lS t ruc tura l s tee l
Allowance for structural wall framing and
roofing; complete
2,640 m2 370.00 976,800 976,800
Structural steelStructural steelStructural steelStructural steel 976,800976,800976,800976,800
To Collec t ionTo Collec t ionTo Collec t ionTo Collec t ion 976,800
13/10/2017 3:44:13 PM Turner & Townsend Page 2 of 17
Detailed BreakdownDetailed BreakdownDetailed BreakdownDetailed Breakdown
Project:Project:Project:Project: Underwood Park DevelopmentBui lding:Bui lding:Bui lding:Bui lding: Underwood Park Development Masterplan -
Concept
Details:Details:Details:Details: Future Indoor Sports Building (Stage 2)
Code Description Quantity Unit Rate Subtotal Factor Total
Upper F loorsUpper F loorsUpper F loorsUpper F loors
Allowance for concrete slab; assumed 200thick including formwork, reinforcement andfinish; to gallery area
51 m3 250.00 12,800 12,800
Upper FloorsUpper FloorsUpper FloorsUpper Floors 12,80012,80012,80012,800
To Collec t ionTo Collec t ionTo Collec t ionTo Collec t ion 12,800
13/10/2017 3:44:13 PM Turner & Townsend Page 3 of 17
Detailed BreakdownDetailed BreakdownDetailed BreakdownDetailed Breakdown
Project:Project:Project:Project: Underwood Park DevelopmentBui lding:Bui lding:Bui lding:Bui lding: Underwood Park Development Masterplan -
Concept
Details:Details:Details:Details: Future Indoor Sports Building (Stage 2)
Code Description Quantity Unit Rate Subtotal Factor Total
S ta i rcaseSta i rcaseSta i rcaseSta i rcase
Concrete Stairs
Allowance for concrete stairs and landings
complete; connecting to undercroft
Incl
Allowance for balustrade including handrail;
to gallery
72 m 500.00 36,000 36,000
StaircaseStaircaseStaircaseStaircase 36,00036,00036,00036,000
To Collec t ionTo Collec t ionTo Collec t ionTo Collec t ion 36,000
13/10/2017 3:44:13 PM Turner & Townsend Page 4 of 17
Detailed BreakdownDetailed BreakdownDetailed BreakdownDetailed Breakdown
Project:Project:Project:Project: Underwood Park DevelopmentBui lding:Bui lding:Bui lding:Bui lding: Underwood Park Development Masterplan -
Concept
Details:Details:Details:Details: Future Indoor Sports Building (Stage 2)
Code Description Quantity Unit Rate Subtotal Factor Total
RoofRoofRoofRoof
Allowance for roof sheeting complete;framing, metal sheet; including insulation,flashing, etc
2,840 m2 160.00 454,400 454,400
Allowance for roof plumbing; including
downpipes
318 m 100.00 31,800 31,800
Allowance for fall arrest system 2,840 m2 15.00 42,600 42,600
RoofRoofRoofRoof 528,800528,800528,800528,800
To Collec t ionTo Collec t ionTo Collec t ionTo Collec t ion 528,800
13/10/2017 3:44:13 PM Turner & Townsend Page 5 of 17
Detailed BreakdownDetailed BreakdownDetailed BreakdownDetailed Breakdown
Project:Project:Project:Project: Underwood Park DevelopmentBui lding:Bui lding:Bui lding:Bui lding: Underwood Park Development Masterplan -
Concept
Details:Details:Details:Details: Future Indoor Sports Building (Stage 2)
Code Description Quantity Unit Rate Subtotal Factor Total
Ex ternal Wal lsEx ternal Wal lsEx ternal Wal lsEx ternal Wal ls
Allowance for blockwork, 190 wide; corefilled
including reinforcement (assumed to 40%)
594 m2 150.00 89,100 89,100
Allowance for metal sheet colourbond
cladding; including linings (assumed to 60%)
891 m2 220.00 196,000 196,000
Allowance to render coat and paint 594 m2 60.00 35,600 35,600
External WallsExternal WallsExternal WallsExternal Walls 320,700320,700320,700320,700
To Collec t ionTo Collec t ionTo Collec t ionTo Collec t ion 320,700
13/10/2017 3:44:13 PM Turner & Townsend Page 6 of 17
Detailed BreakdownDetailed BreakdownDetailed BreakdownDetailed Breakdown
Project:Project:Project:Project: Underwood Park DevelopmentBui lding:Bui lding:Bui lding:Bui lding: Underwood Park Development Masterplan -
Concept
Details:Details:Details:Details: Future Indoor Sports Building (Stage 2)
Code Description Quantity Unit Rate Subtotal Factor Total
Windows and G laz ingWindows and G laz ingWindows and G laz ingWindows and G laz ing
Allowance for curtain wall in clear anodised
aluminium framing; double glazed
446 m2 850.00 379,100 379,100
Windows and GlazingWindows and GlazingWindows and GlazingWindows and Glazing 379,100379,100379,100379,100
To Collec t ionTo Collec t ionTo Collec t ionTo Collec t ion 379,100
13/10/2017 3:44:13 PM Turner & Townsend Page 7 of 17
Detailed BreakdownDetailed BreakdownDetailed BreakdownDetailed Breakdown
Project:Project:Project:Project: Underwood Park DevelopmentBui lding:Bui lding:Bui lding:Bui lding: Underwood Park Development Masterplan -
Concept
Details:Details:Details:Details: Future Indoor Sports Building (Stage 2)
Code Description Quantity Unit Rate Subtotal Factor Total
Ex ternal DoorsEx ternal DoorsEx ternal DoorsEx ternal Doors
External
Allowance for automatic entrance double
glazed doors; including frame and hardware
3 no 8,000.00 24,000 24,000
Internal
Allowance for glazed double doors; including
frame and hardware
4 no 3,500.00 14,000 14,000
Allowance for timber sliding double doors;including frame and hardware; to gym &basketball courts
4 no 5,000.00 20,000 20,000
External DoorsExternal DoorsExternal DoorsExternal Doors 58,00058,00058,00058,000
To Collec t ionTo Collec t ionTo Collec t ionTo Collec t ion 58,000
13/10/2017 3:44:13 PM Turner & Townsend Page 8 of 17
Detailed BreakdownDetailed BreakdownDetailed BreakdownDetailed Breakdown
Project:Project:Project:Project: Underwood Park DevelopmentBui lding:Bui lding:Bui lding:Bui lding: Underwood Park Development Masterplan -
Concept
Details:Details:Details:Details: Future Indoor Sports Building (Stage 2)
Code Description Quantity Unit Rate Subtotal Factor Total
In ternal Wal lsIn ternal Wal lsIn ternal Wal lsIn ternal Wal ls
Allowance for blockwork, 190 wide; corefilled
including reinforcement
76 m2 250.00 19,000 19,000
Internal WallsInternal WallsInternal WallsInternal Walls 19,00019,00019,00019,000
To Collec t ionTo Collec t ionTo Collec t ionTo Collec t ion 19,000
13/10/2017 3:44:13 PM Turner & Townsend Page 9 of 17
Detailed BreakdownDetailed BreakdownDetailed BreakdownDetailed Breakdown
Project:Project:Project:Project: Underwood Park DevelopmentBui lding:Bui lding:Bui lding:Bui lding: Underwood Park Development Masterplan -
Concept
Details:Details:Details:Details: Future Indoor Sports Building (Stage 2)
Code Description Quantity Unit Rate Subtotal Factor Total
Wal l Fin ishesWal l Fin ishesWal l Fin ishesWal l Fin ishes
Allowance to paint internal walls 3,128 m2 20.00 62,600 62,600
EO to linings for high impact lining Excl
Wall FinishesWall FinishesWall FinishesWall Finishes 62,60062,60062,60062,600
To Collec t ionTo Collec t ionTo Collec t ionTo Collec t ion 62,600
13/10/2017 3:44:13 PM Turner & Townsend Page 10 of 17
Detailed BreakdownDetailed BreakdownDetailed BreakdownDetailed Breakdown
Project:Project:Project:Project: Underwood Park DevelopmentBui lding:Bui lding:Bui lding:Bui lding: Underwood Park Development Masterplan -
Concept
Details:Details:Details:Details: Future Indoor Sports Building (Stage 2)
Code Description Quantity Unit Rate Subtotal Factor Total
F loor F in ishesFloor F in ishesFloor F in ishesFloor F in ishes
Allowance for timber surface sports flooring;
including line marking
2,162 m2 200.00 432,400 432,400
Allowance for skirting 264 m2 20.00 5,300 5,300
Allowance for vinyl to communal areas 709 m2 80.00 56,600 56,600
Allowance for coved vinyl skirting 467 m2 25.00 11,700 11,700
Allowance for anchor points for sporting
equipment
1 item 5,000.00 5,000 5,000
Allowance for entry mats 1 item 5,000.00 5,000 5,000
Floor FinishesFloor FinishesFloor FinishesFloor Finishes 516,000516,000516,000516,000
To Collec t ionTo Collec t ionTo Collec t ionTo Collec t ion 516,000
13/10/2017 3:44:13 PM Turner & Townsend Page 11 of 17
Detailed BreakdownDetailed BreakdownDetailed BreakdownDetailed Breakdown
Project:Project:Project:Project: Underwood Park DevelopmentBui lding:Bui lding:Bui lding:Bui lding: Underwood Park Development Masterplan -
Concept
Details:Details:Details:Details: Future Indoor Sports Building (Stage 2)
Code Description Quantity Unit Rate Subtotal Factor Total
Cei l ing F in ishesCei l ing F in ishesCei l ing F in ishesCei l ing F in ishes
Allowance for FC sheeting, fixed to underside
of purlins
2,640 m2 120.00 316,800 316,800
Allowance for Fiber cement and paint; to
soffit of eaves
509 m2 70.00 35,600 35,600
Ceiling FinishesCeiling FinishesCeiling FinishesCeiling Finishes 352,400352,400352,400352,400
To Collec t ionTo Collec t ionTo Collec t ionTo Collec t ion 352,400
13/10/2017 3:44:13 PM Turner & Townsend Page 12 of 17
Detailed BreakdownDetailed BreakdownDetailed BreakdownDetailed Breakdown
Project:Project:Project:Project: Underwood Park DevelopmentBui lding:Bui lding:Bui lding:Bui lding: Underwood Park Development Masterplan -
Concept
Details:Details:Details:Details: Future Indoor Sports Building (Stage 2)
Code Description Quantity Unit Rate Subtotal Factor Total
F i tmentsF i tmentsF i tmentsF i tments
Allowance for blinds to all windows 1 item 20,000.00 20,000 20,000
Allowance for inbuilt joinery items;
unidentified
1 item 50,000.00 50,000 50,000
Allowance for statutory signage 1 item 5,000.00 5,000 5,000
Allowance for sports equipment;
Allowance for basketball hoops - roof
mounted
4 no 3,500.00 14,000 14,000
Allowance for center roll dividing curtain 1 no 5,000.00 5,000 5,000
Allowance for standard scoreboard 2 no 5,000.00 10,000 10,000
Allowance for sports equipment Excl
Allowance for loose furniture, fittings and
equipment
Excl
FitmentsFitmentsFitmentsFitments 104,000104,000104,000104,000
To Collec t ionTo Collec t ionTo Collec t ionTo Collec t ion 104,000
13/10/2017 3:44:13 PM Turner & Townsend Page 13 of 17
Detailed BreakdownDetailed BreakdownDetailed BreakdownDetailed Breakdown
Project:Project:Project:Project: Underwood Park DevelopmentBui lding:Bui lding:Bui lding:Bui lding: Underwood Park Development Masterplan -
Concept
Details:Details:Details:Details: Future Indoor Sports Building (Stage 2)
Code Description Quantity Unit Rate Subtotal Factor Total
Sani tary F ix tures , P lumbing and GasSani tary F ix tures , P lumbing and GasSani tary F ix tures , P lumbing and GasSani tary F ix tures , P lumbing and Gas
Allowance for hydraulic services; including
plumbing points and drainage
2,640 m2 15.00 39,600 39,600
Builders Work In Connection with Services 5 % 39,600.00 2,000 2,000
Sanitary Fixtures, Plumbing and GasSanitary Fixtures, Plumbing and GasSanitary Fixtures, Plumbing and GasSanitary Fixtures, Plumbing and Gas 41,60041,60041,60041,600
To Collec t ionTo Collec t ionTo Collec t ionTo Collec t ion 41,600
13/10/2017 3:44:13 PM Turner & Townsend Page 14 of 17
Detailed BreakdownDetailed BreakdownDetailed BreakdownDetailed Breakdown
Project:Project:Project:Project: Underwood Park DevelopmentBui lding:Bui lding:Bui lding:Bui lding: Underwood Park Development Masterplan -
Concept
Details:Details:Details:Details: Future Indoor Sports Building (Stage 2)
Code Description Quantity Unit Rate Subtotal Factor Total
A i r Condi t ion ingAi r Condi t ion ingAi r Condi t ion ingAi r Condi t ion ing
Air Conditioning to circulation areas and
recreational areas
2,640 m2 40.00 105,600 105,600
Builders Work In Connection with Services 3 % 105,600.00 3,000 3,000
Air ConditioningAir ConditioningAir ConditioningAir Conditioning 108,600108,600108,600108,600
To Collec t ionTo Collec t ionTo Collec t ionTo Collec t ion 108,600
13/10/2017 3:44:13 PM Turner & Townsend Page 15 of 17
Detailed BreakdownDetailed BreakdownDetailed BreakdownDetailed Breakdown
Project:Project:Project:Project: Underwood Park DevelopmentBui lding:Bui lding:Bui lding:Bui lding: Underwood Park Development Masterplan -
Concept
Details:Details:Details:Details: Future Indoor Sports Building (Stage 2)
Code Description Quantity Unit Rate Subtotal Factor Total
F i re Protec t ionF i re Protec t ionF i re Protec t ionF i re Protec t ion
Fire detection (assumed no sprinklers
required)
2,640 m2 7.50 19,800 19,800
Builders Work In Connection with Services 3 % 19,800.00 1,000 1,000
Fire ProtectionFire ProtectionFire ProtectionFire Protection 20,80020,80020,80020,800
To Collec t ionTo Collec t ionTo Collec t ionTo Collec t ion 20,800
13/10/2017 3:44:13 PM Turner & Townsend Page 16 of 17
Detailed BreakdownDetailed BreakdownDetailed BreakdownDetailed Breakdown
Project:Project:Project:Project: Underwood Park DevelopmentBui lding:Bui lding:Bui lding:Bui lding: Underwood Park Development Masterplan -
Concept
Details:Details:Details:Details: Future Indoor Sports Building (Stage 2)
Code Description Quantity Unit Rate Subtotal Factor Total
E lec t r ic Light , Power and Communicat ionsE lec t r ic Light , Power and Communicat ionsE lec t r ic Light , Power and Communicat ionsE lec t r ic Light , Power and Communicat ions
Air Conditioning to circulation areas, lounges
and recreational areas
2,640 m2 120.00 316,800 316,800
Builders Work In Connection with Services 3 % 316,800.00 10,000 10,000
Electric Light, Power and CommunicationsElectric Light, Power and CommunicationsElectric Light, Power and CommunicationsElectric Light, Power and Communications 326,800326,800326,800326,800
To Collec t ionTo Collec t ionTo Collec t ionTo Collec t ion 326,800
13/10/2017 3:44:13 PM Turner & Townsend Page 17 of 17
SummarySummarySummarySummary
Project:Project:Project:Project: Underwood Park DevelopmentBui lding:Bui lding:Bui lding:Bui lding: Underwood Park Development Masterplan -
Concept
Details:Details:Details:Details: Multipurpose facility (Stage 1)
Code Description Quantity Unit Rate Subtotal Factor Total
SB Substructure 3,672 m2 179.49 659,100 659,100
UF Upper Floors 3,672 m2 25.05 92,000 92,000
SC Staircase 3,672 m2 23.97 88,000 88,000
RF Roof 3,672 m2 126.53 464,600 464,600
EW External Walls 3,672 m2 58.80 215,900 215,900
WW Windows and Glazing 3,672 m2 36.85 135,300 135,300
ED External Doors 3,672 no 26.03 95,600 95,600
NW Internal Walls 3,672 m2 81.89 300,700 300,700
NS Internal Screens and Borrowed Lights 3,672 m2 26.03 95,600 95,600
WF Wall Finishes 3,672 m2 41.04 150,700 150,700
FF Floor Finishes 3,672 m2 113.40 416,400 416,400
CF Ceiling Finishes 3,672 m2 81.97 301,000 301,000
FT Fitments 3,672 m2 65.50 240,500 240,500
PD Sanitary Fixtures, Plumbing and Gas 3,672 m2 81.62 299,700 299,700
AC Air Conditioning 3,672 m2 77.26 283,700 283,700
FP Fire Protection 3,672 m2 7.30 26,800 26,800
LP Electric Light, Power and
Communications
3,672 m2 123.53 453,600 453,600
SP Special Equipment 3,672 m2 9.26 34,000 34,000
TS Transportation Systems 3,672 m2 33.77 124,000 124,000
Subtotal 3,672 m2 1,219.28 4,477,200 4,477,200
13/10/2017 3:51:47 PM Turner & Townsend Page 1 of 1
Detailed BreakdownDetailed BreakdownDetailed BreakdownDetailed Breakdown
Project:Project:Project:Project: Underwood Park DevelopmentBui lding:Bui lding:Bui lding:Bui lding: Underwood Park Development Masterplan -
Concept
Details:Details:Details:Details: Multipurpose facility (Stage 1)
Code Description Quantity Unit Rate Subtotal Factor Total
Subs t ruc tureSubs t ruc tureSubs t ruc tureSubs t ruc ture
Bulk Excavation
Allowance for site cut / excavation etc toachieve required site levels; basementexcavation
3,672 m3 25.00 91,800 91,800
Additional allowance for removal of
excavated spoil from site
3,672 m3 15.00 55,100 55,100
Dewatering
Allowance for dewatering 1 item 10,000.00 10,000 10,000
Sheet Pile
Allowance for sheet piled wall (assumed to
50% of GL external walls)
331 m2 850.00 281,400 281,400
Footings
Allowance for detailed excavations 368 m3 100.00 36,800 36,800
Allowance for footings; including
reinforcement
368 m3 250.00 92,000 92,000
Slab on Ground
Allowance to concrete slab; including
reinforcement; assumed 200 thick
368 m3 250.00 92,000 92,000
Termite treatment allowance Excl
SubstructureSubstructureSubstructureSubstructure 659,100659,100659,100659,100
To Collec t ionTo Collec t ionTo Collec t ionTo Collec t ion 659,100
13/10/2017 3:50:46 PM Turner & Townsend Page 1 of 19
Detailed BreakdownDetailed BreakdownDetailed BreakdownDetailed Breakdown
Project:Project:Project:Project: Underwood Park DevelopmentBui lding:Bui lding:Bui lding:Bui lding: Underwood Park Development Masterplan -
Concept
Details:Details:Details:Details: Multipurpose facility (Stage 1)
Code Description Quantity Unit Rate Subtotal Factor Total
Upper F loorsUpper F loorsUpper F loorsUpper F loors
Allowance for concrete slab; assumed 200thick including formwork, reinforcement andfinish
368 m3 250.00 92,000 92,000
Upper FloorsUpper FloorsUpper FloorsUpper Floors 92,00092,00092,00092,000
To Collec t ionTo Collec t ionTo Collec t ionTo Collec t ion 92,000
13/10/2017 3:50:46 PM Turner & Townsend Page 2 of 19
Detailed BreakdownDetailed BreakdownDetailed BreakdownDetailed Breakdown
Project:Project:Project:Project: Underwood Park DevelopmentBui lding:Bui lding:Bui lding:Bui lding: Underwood Park Development Masterplan -
Concept
Details:Details:Details:Details: Multipurpose facility (Stage 1)
Code Description Quantity Unit Rate Subtotal Factor Total
S ta i rcaseSta i rcaseSta i rcaseSta i rcase
Concrete Stairs
Allowance for concrete stairs and landings
complete; to field access
1 no 10,000.00 10,000 10,000
Allowance for concrete stair complete;
including powdercoated aluminium balustrade
2 no 20,000.00 40,000 40,000
Steel Stairs
Allowance for steel stairs and landings
complete; to veranda
1 no 12,000.00 12,000 12,000
Feature Timber Stairs
Timber feature stair complete; includingpowdercoated aluminium balustrade; to entrylobby
1 no 15,000.00 15,000 15,000
Grandstand
Allowance for concrete slab; assumed 200thick including formwork, reinforcement andfinish
20 m3 300.00 6,000 6,000
Allowance for balustrade including handrail;
to either side
10 m 500.00 5,000 5,000
StaircaseStaircaseStaircaseStaircase 88,00088,00088,00088,000
To Collec t ionTo Collec t ionTo Collec t ionTo Collec t ion 88,000
13/10/2017 3:50:46 PM Turner & Townsend Page 3 of 19
Detailed BreakdownDetailed BreakdownDetailed BreakdownDetailed Breakdown
Project:Project:Project:Project: Underwood Park DevelopmentBui lding:Bui lding:Bui lding:Bui lding: Underwood Park Development Masterplan -
Concept
Details:Details:Details:Details: Multipurpose facility (Stage 1)
Code Description Quantity Unit Rate Subtotal Factor Total
RoofRoofRoofRoof
Allowance for roof sheeting complete;framing, metal sheet; including insulation,safety mesh, flashing, etc
2,524 m2 160.00 403,800 403,800
Allowance for roof plumbing; including
downpipes
318 m 100.00 31,800 31,800
Allowance for fall arrest system 1,936 m2 15.00 29,000 29,000
RoofRoofRoofRoof 464,600464,600464,600464,600
To Collec t ionTo Collec t ionTo Collec t ionTo Collec t ion 464,600
13/10/2017 3:50:46 PM Turner & Townsend Page 4 of 19
Detailed BreakdownDetailed BreakdownDetailed BreakdownDetailed Breakdown
Project:Project:Project:Project: Underwood Park DevelopmentBui lding:Bui lding:Bui lding:Bui lding: Underwood Park Development Masterplan -
Concept
Details:Details:Details:Details: Multipurpose facility (Stage 1)
Code Description Quantity Unit Rate Subtotal Factor Total
Ex ternal Wal lsEx ternal Wal lsEx ternal Wal lsEx ternal Wal ls
Allowance for blockwork, 190 wide; corefilled
including reinforcement (assumed to 40%)
265 m2 150.00 39,800 39,800
Allowance for metal sheet colourbond
cladding; including linings (assumed to 60%)
397 m2 220.00 87,300 87,300
Allowance for blockwork, 190 wide; corefilledincluding reinforcement (Ground Levelexposed)
331 m2 150.00 49,600 49,600
Allowance to render coat and paint 596 m2 60.00 35,800 35,800
Allowance for enclosure to Plant / bins area
including associated gates
34 m2 100.00 3,400 3,400
External WallsExternal WallsExternal WallsExternal Walls 215,900215,900215,900215,900
To Collec t ionTo Collec t ionTo Collec t ionTo Collec t ion 215,900
13/10/2017 3:50:46 PM Turner & Townsend Page 5 of 19
Detailed BreakdownDetailed BreakdownDetailed BreakdownDetailed Breakdown
Project:Project:Project:Project: Underwood Park DevelopmentBui lding:Bui lding:Bui lding:Bui lding: Underwood Park Development Masterplan -
Concept
Details:Details:Details:Details: Multipurpose facility (Stage 1)
Code Description Quantity Unit Rate Subtotal Factor Total
Windows and G laz ingWindows and G laz ingWindows and G laz ingWindows and G laz ing
Allowance for curtain wall in clear anodisedaluminium framing; double glazed (assumedto 30%)
72 m2 850.00 61,200 61,200
Allowance for sliding serving windowincluding stainless steel service counter; fromcanteen to spectator area :[7 m]
1 no 18,000.00 18,000 18,000
Allowance for operable window; full height;
connecting cafe to external courtyard
19 m2 1,500.00 28,500 28,500
Allowance for glazed blaustrade including
handrail; to veranda area
46 m 600.00 27,600 27,600
Security screens to glazing Excl
Windows and GlazingWindows and GlazingWindows and GlazingWindows and Glazing 135,300135,300135,300135,300
To Collec t ionTo Collec t ionTo Collec t ionTo Collec t ion 135,300
13/10/2017 3:50:46 PM Turner & Townsend Page 6 of 19
Detailed BreakdownDetailed BreakdownDetailed BreakdownDetailed Breakdown
Project:Project:Project:Project: Underwood Park DevelopmentBui lding:Bui lding:Bui lding:Bui lding: Underwood Park Development Masterplan -
Concept
Details:Details:Details:Details: Multipurpose facility (Stage 1)
Code Description Quantity Unit Rate Subtotal Factor Total
Ex ternal DoorsEx ternal DoorsEx ternal DoorsEx ternal Doors
External
Allowance for automatic entrance double
glazed doors; including frame and hardware
2 no 8,000.00 16,000 16,000
Allowance for glazed double doors; including
frame and hardware
4 no 3,500.00 14,000 14,000
Allowance for timber single doors; including
frame and hardware
6 no 1,000.00 6,000 6,000
Allowance for timber double doors; including
frame and hardware
6 no 1,800.00 10,800 10,800
Allowance for roller shutter; including frame
and hardware
1 no 3,000.00 3,000 3,000
Internal
Allowance for timber single doors; including
frame and hardware
38 no 850.00 32,300 32,300
Allowance for timber double doors; including
frame and hardware
9 no 1,500.00 13,500 13,500
External DoorsExternal DoorsExternal DoorsExternal Doors 95,60095,60095,60095,600
To Collec t ionTo Collec t ionTo Collec t ionTo Collec t ion 95,600
13/10/2017 3:50:46 PM Turner & Townsend Page 7 of 19
Detailed BreakdownDetailed BreakdownDetailed BreakdownDetailed Breakdown
Project:Project:Project:Project: Underwood Park DevelopmentBui lding:Bui lding:Bui lding:Bui lding: Underwood Park Development Masterplan -
Concept
Details:Details:Details:Details: Multipurpose facility (Stage 1)
Code Description Quantity Unit Rate Subtotal Factor Total
In ternal Wal lsIn ternal Wal lsIn ternal Wal lsIn ternal Wal ls
Allowance for blockwork, 190 wide; corefilledincluding reinforcement (assumed to 70% GFinternal walls)
605 m2 250.00 151,200 151,200
Allowance for internal walls; lightweight stud
framing lining to both sides
1,246 m2 120.00 149,500 149,500
Internal WallsInternal WallsInternal WallsInternal Walls 300,700300,700300,700300,700
To Collec t ionTo Collec t ionTo Collec t ionTo Collec t ion 300,700
13/10/2017 3:50:46 PM Turner & Townsend Page 8 of 19
Detailed BreakdownDetailed BreakdownDetailed BreakdownDetailed Breakdown
Project:Project:Project:Project: Underwood Park DevelopmentBui lding:Bui lding:Bui lding:Bui lding: Underwood Park Development Masterplan -
Concept
Details:Details:Details:Details: Multipurpose facility (Stage 1)
Code Description Quantity Unit Rate Subtotal Factor Total
In ternal Sc reens and Bor rowed LightsInternal Sc reens and Bor rowed LightsInternal Sc reens and Bor rowed LightsInternal Sc reens and Bor rowed Lights
Shower / Toilet partition screen including
doors
273 m2 350.00 95,600 95,600
Internal Screens and Borrowed LightsInternal Screens and Borrowed LightsInternal Screens and Borrowed LightsInternal Screens and Borrowed Lights 95,60095,60095,60095,600
To Collec t ionTo Collec t ionTo Collec t ionTo Collec t ion 95,600
13/10/2017 3:50:46 PM Turner & Townsend Page 9 of 19
Detailed BreakdownDetailed BreakdownDetailed BreakdownDetailed Breakdown
Project:Project:Project:Project: Underwood Park DevelopmentBui lding:Bui lding:Bui lding:Bui lding: Underwood Park Development Masterplan -
Concept
Details:Details:Details:Details: Multipurpose facility (Stage 1)
Code Description Quantity Unit Rate Subtotal Factor Total
Wal l Fin ishesWal l Fin ishesWal l Fin ishesWal l Fin ishes
Allowance to paint internal walls 5,985 m2 20.00 119,700 119,700
Allowance for wall tiling including
waterproofing
172 m2 180.00 31,000 31,000
Wall FinishesWall FinishesWall FinishesWall Finishes 150,700150,700150,700150,700
To Collec t ionTo Collec t ionTo Collec t ionTo Collec t ion 150,700
13/10/2017 3:50:46 PM Turner & Townsend Page 10 of 19
Detailed BreakdownDetailed BreakdownDetailed BreakdownDetailed Breakdown
Project:Project:Project:Project: Underwood Park DevelopmentBui lding:Bui lding:Bui lding:Bui lding: Underwood Park Development Masterplan -
Concept
Details:Details:Details:Details: Multipurpose facility (Stage 1)
Code Description Quantity Unit Rate Subtotal Factor Total
F loor F in ishesFloor F in ishesFloor F in ishesFloor F in ishes
Allowance for carpet 1,190 m2 60.00 71,400 71,400
Allowance for skirting; to carpet 415 m 20.00 8,300 8,300
Allowance for porcelain tiles 290 m2 120.00 34,800 34,800
Allowance for skirting; to porcelain tiles 157 m 25.00 3,900 3,900
Allowance for ceramic tiles 494 m2 100.00 49,400 49,400
Allowance for skirting; to ceramic tiles 463 m 20.00 9,300 9,300
Alllowance for vinyl 772 m2 80.00 61,800 61,800
Allowance for coved vinyl skirting 596 m 25.00 14,900 14,900
Alllowance for timber flooring 177 m2 220.00 38,900 38,900
Allowance for sealer 542 m2 100.00 54,200 54,200
Allowance for entry mats 1 item 5,000.00 5,000 5,000
Stage
Allowance for timber stage; including framing
and steps to either side
1 item 20,000.00 20,000 20,000
Spectator Area
Allowance for paving to spectator area 494 m2 90.00 44,500 44,500
Floor FinishesFloor FinishesFloor FinishesFloor Finishes 416,400416,400416,400416,400
To Collec t ionTo Collec t ionTo Collec t ionTo Collec t ion 416,400
13/10/2017 3:50:46 PM Turner & Townsend Page 11 of 19
Detailed BreakdownDetailed BreakdownDetailed BreakdownDetailed Breakdown
Project:Project:Project:Project: Underwood Park DevelopmentBui lding:Bui lding:Bui lding:Bui lding: Underwood Park Development Masterplan -
Concept
Details:Details:Details:Details: Multipurpose facility (Stage 1)
Code Description Quantity Unit Rate Subtotal Factor Total
Cei l ing F in ishesCei l ing F in ishesCei l ing F in ishesCei l ing F in ishes
Allowance for plasterboard and paint; to all
internal areas
2,972 m2 85.00 252,600 252,600
Allowance for Fibercement and paint; to soffit
of eaves
689 m2 70.00 48,400 48,400
Ceiling FinishesCeiling FinishesCeiling FinishesCeiling Finishes 301,000301,000301,000301,000
To Collec t ionTo Collec t ionTo Collec t ionTo Collec t ion 301,000
13/10/2017 3:50:46 PM Turner & Townsend Page 12 of 19
Detailed BreakdownDetailed BreakdownDetailed BreakdownDetailed Breakdown
Project:Project:Project:Project: Underwood Park DevelopmentBui lding:Bui lding:Bui lding:Bui lding: Underwood Park Development Masterplan -
Concept
Details:Details:Details:Details: Multipurpose facility (Stage 1)
Code Description Quantity Unit Rate Subtotal Factor Total
F i tmentsF i tmentsF i tmentsF i tments
Vanity bench 33 m 350.00 11,550 11,550
Mirror 12 m2 300.00 3,600 3,600
Soap dispenser 21 no 50.00 1,050 1,050
Toilet Roll holder 52 no 50.00 2,600 2,600
Hand dryer 21 no 300.00 6,300 6,300
Grab rail to PWD toilet 4 no 500.00 2,000 2,000
Baby change table to PWD 1 no 1,000.00 1,000 1,000
Change rooms bench seating including coat
rack
41 m 400.00 16,400 16,400
Allowance for bar fit out; including joinery 2 no 3,000.00 6,000 6,000
Allowance for refrigeration units to bar &
kitchen
Excl
Allowance for kitchen fit-outs; including
joinery
3 no 35,000.00 105,000 105,000
Allowance for kitchen / bar appliances and
equipment
Excl
Allowance for stage curtains 1 no 10,000.00 10,000 10,000
Allowance for blinds to all windows 1 item 20,000.00 20,000 20,000
Allowance for inbuilt joinery items;
unidentified
1 item 30,000.00 30,000 30,000
Allowance for statutory signage 1 item 5,000.00 5,000 5,000
Allowance for fixed spectator seating; to
grandstand
1 item 20,000.00 20,000 20,000
Allowance for Allied health fit out Excl
FitmentsFitmentsFitmentsFitments 240,500240,500240,500240,500
To Collec t ionTo Collec t ionTo Collec t ionTo Collec t ion 240,500
13/10/2017 3:50:46 PM Turner & Townsend Page 13 of 19
Detailed BreakdownDetailed BreakdownDetailed BreakdownDetailed Breakdown
Project:Project:Project:Project: Underwood Park DevelopmentBui lding:Bui lding:Bui lding:Bui lding: Underwood Park Development Masterplan -
Concept
Details:Details:Details:Details: Multipurpose facility (Stage 1)
Code Description Quantity Unit Rate Subtotal Factor Total
Sani tary F ix tures , P lumbing and GasSani tary F ix tures , P lumbing and GasSani tary F ix tures , P lumbing and GasSani tary F ix tures , P lumbing and Gas
Sanitary Fixtures
WC 52 no 800.00 41,600 41,600
Accessible WC 4 no 850.00 3,400 3,400
Shower head & tapware 20 no 550.00 11,000 11,000
Urinal 10 no 850.00 8,500 8,500
Wall hung basin 40 no 450.00 18,000 18,000
Wall hung basin; to accessible WC 1 no 500.00 500 500
Cleaners sink 2 no 1,000.00 2,000 2,000
Allowance for sinks to kitchens and bars 5 no 1,000.00 5,000 5,000
Allowance for plumbing points and drainage 134 no 1,500.00 201,000 201,000
Builders Work In Connection with Services 3 % 291,000.00 8,700 8,700
Sanitary Fixtures, Plumbing and GasSanitary Fixtures, Plumbing and GasSanitary Fixtures, Plumbing and GasSanitary Fixtures, Plumbing and Gas 299,700299,700299,700299,700
To Collec t ionTo Collec t ionTo Collec t ionTo Collec t ion 299,700
13/10/2017 3:50:46 PM Turner & Townsend Page 14 of 19
Detailed BreakdownDetailed BreakdownDetailed BreakdownDetailed Breakdown
Project:Project:Project:Project: Underwood Park DevelopmentBui lding:Bui lding:Bui lding:Bui lding: Underwood Park Development Masterplan -
Concept
Details:Details:Details:Details: Multipurpose facility (Stage 1)
Code Description Quantity Unit Rate Subtotal Factor Total
A i r Condi t ion ingAi r Condi t ion ingAi r Condi t ion ingAi r Condi t ion ing
Air Conditioning to circulation areas, lounges
and recreational areas
3,672 m2 75.00 275,400 275,400
Builders Work In Connection with Services 3 % 275,400.00 8,300 8,300
Air ConditioningAir ConditioningAir ConditioningAir Conditioning 283,700283,700283,700283,700
To Collec t ionTo Collec t ionTo Collec t ionTo Collec t ion 283,700
13/10/2017 3:50:46 PM Turner & Townsend Page 15 of 19
Detailed BreakdownDetailed BreakdownDetailed BreakdownDetailed Breakdown
Project:Project:Project:Project: Underwood Park DevelopmentBui lding:Bui lding:Bui lding:Bui lding: Underwood Park Development Masterplan -
Concept
Details:Details:Details:Details: Multipurpose facility (Stage 1)
Code Description Quantity Unit Rate Subtotal Factor Total
F i re Protec t ionF i re Protec t ionF i re Protec t ionF i re Protec t ion
Allowance for fire detection 3,672 m2 7.00 26,000 26,000
Builders Work In Connection with Services 3 % 26,000.00 800 800
Fire ProtectionFire ProtectionFire ProtectionFire Protection 26,80026,80026,80026,800
To Collec t ionTo Collec t ionTo Collec t ionTo Collec t ion 26,800
13/10/2017 3:50:46 PM Turner & Townsend Page 16 of 19
Detailed BreakdownDetailed BreakdownDetailed BreakdownDetailed Breakdown
Project:Project:Project:Project: Underwood Park DevelopmentBui lding:Bui lding:Bui lding:Bui lding: Underwood Park Development Masterplan -
Concept
Details:Details:Details:Details: Multipurpose facility (Stage 1)
Code Description Quantity Unit Rate Subtotal Factor Total
E lec t r ic Light , Power and Communicat ionsE lec t r ic Light , Power and Communicat ionsE lec t r ic Light , Power and Communicat ionsE lec t r ic Light , Power and Communicat ions
Air Conditioning to circulation areas, lounges
and recreational areas
3,672 m2 120.00 440,600 440,600
Builders Work In Connection with Services 3 % 440,600.00 13,000 13,000
Electric Light, Power and CommunicationsElectric Light, Power and CommunicationsElectric Light, Power and CommunicationsElectric Light, Power and Communications 453,600453,600453,600453,600
To Collec t ionTo Collec t ionTo Collec t ionTo Collec t ion 453,600
13/10/2017 3:50:46 PM Turner & Townsend Page 17 of 19
Detailed BreakdownDetailed BreakdownDetailed BreakdownDetailed Breakdown
Project:Project:Project:Project: Underwood Park DevelopmentBui lding:Bui lding:Bui lding:Bui lding: Underwood Park Development Masterplan -
Concept
Details:Details:Details:Details: Multipurpose facility (Stage 1)
Code Description Quantity Unit Rate Subtotal Factor Total
Spec ia l EquipmentSpec ia l EquipmentSpec ia l EquipmentSpec ia l Equipment
Allowance for insulated wall panels for Cold
rooms; complete
165 m2 200.00 33,000 33,000
Builders work in connection 3 % 33,000.00 1,000 1,000
Special EquipmentSpecial EquipmentSpecial EquipmentSpecial Equipment 34,00034,00034,00034,000
To Collec t ionTo Collec t ionTo Collec t ionTo Collec t ion 34,000
13/10/2017 3:50:46 PM Turner & Townsend Page 18 of 19
Detailed BreakdownDetailed BreakdownDetailed BreakdownDetailed Breakdown
Project:Project:Project:Project: Underwood Park DevelopmentBui lding:Bui lding:Bui lding:Bui lding: Underwood Park Development Masterplan -
Concept
Details:Details:Details:Details: Multipurpose facility (Stage 1)
Code Description Quantity Unit Rate Subtotal Factor Total
Transpor ta t ion Sys temsTranspor ta t ion Sys temsTranspor ta t ion Sys temsTranspor ta t ion Sys tems
Allowance for passenger lift; assumed
hydraulic
1 no 120,000.00 120,000 120,000
Builders Work In Connection with Services 3 % 120,000 4,000 4,000
Transportation SystemsTransportation SystemsTransportation SystemsTransportation Systems 124,000124,000124,000124,000
To Collec t ionTo Collec t ionTo Collec t ionTo Collec t ion 124,000
13/10/2017 3:50:46 PM Turner & Townsend Page 19 of 19