Indian Institute of Technology Bombayrb/Professional Activities/Microgrids...Bhomji Ka...

52
Indian Institute of Technology Bombay

Transcript of Indian Institute of Technology Bombayrb/Professional Activities/Microgrids...Bhomji Ka...

Indian Institute of Technology Bombay

Department of

Energy Science and EngineeringIIT Bombay

To develop sustainable energy systems

and solutions for the future

ResearchConventional Energy

Energy efficiency,

Process Integration,

DSM, Benchmarking,

Underground Coal

Gasification, Waste to

Energy, Microgrids, Fuel

Cells

Renewable Energy

Solar PV, Solar Thermal,

Biomass, Novel

Batteries – Li , NaS,

Hydrogen Storage

Energy Systems

Analysis

Modelling and Simulation

Energy Planning and

Policy, Water and Energy

Lifecycle Analysis

0

2000

4000

6000

8000

10000

12000

14000

16000

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16

Furnace number

SE

C (

kJ

/kg

)

Target SEC Actual SEC

Microgrids in India: Status and Future

Rangan BanerjeeDepartment of Energy Science and Engineering

IIT Bombay

Presentation at Monash University - June 7 20174

Need for distributed power generation in India

Source: Government of India, 2011 Census

• Some states – higher poverty -

Bihar, UP, Jharkhand and Odisha.India - highest electricity access deficit

(Top 20 countries for access deficit in electricity, 2014)

Source: Status of electricity access report, 2017

5

What is a microgrid?

Interconnected loads, distributed generation and energy storage devices

A single controllable entity with respect to the grid with bidirectional power flow

DER’s

DER’s

Dis

trib

uti

on

n

etw

ork

De

ma

nd

Dis

trib

uti

on

n

etw

ork

De

ma

nd

Large Centralised Generation

Transmission network

Grid

ES

S

ES

S

6

Classification of Microgrids

Size

Microgrids

Mode of operation Type Source Scenario

Isolated Grid Connected

HybridAC DC

Renewables Diesel Hybrid

Wind Micro Hydro

Biomass HybridSolar

CommercialResidential Industrial

<10kW

>1 MW

10kW-1MW

7

Global Microgrid Capacity - 2016

Total microgrid power capacity market share by region

Total microgrid power capacity market share by country

Source : Microgrid Deployment Tracker 2Q16 by Navigant Research

Global Microgrid Capacity – 16552 MW

Approx 350 MW of microgrids in India

8

Grid outage for different urban areas

Source: ESMI, Prayas 9

Baghru, Jaipur

Garladinne,

Kundapur, Udupi

Pandeypur, Varanasi

Jamui

0

1

2

3

4

5

6

7

Baghru Garladinne Kundapur Pandeypur Jamui town

Jaipur Anantpur Udupi Varanasi Jamui

Ou

tage

du

rati

on

in h

ou

rs/d

ay

Urban location in India

Jan-16 Feb-16 Mar-16 Apr-16 May-16

Average number of outage hours in a day for a location

9

Microgrid estimates for India (samples)

Source: Schnitzer, D et al., 2014

Microgrid Installed Capacity by developer Microgrid Installed Capacity by generation type kW

*as on 2012

10

Gram Oorja, Darewada ,Pune

Source: Minigrids Electricity for all, CSE, 201611

Gram Power – Rajasthan

Micro-grid technology provider Gram Power

has installed prepaid smart metres in Pali

district, Rajasthan

Source: Minigrids Electricity for all, CSE, 201612

Husk Power System - Sahebganj Village

Source: Minigrids Electricity for all, CSE, 201613

Bhomji Ka Gaon,Rajasthan

Location Bhomji Ka Gaon

Type On grid and off grid connections

Size of power plant

500 kWp

Number of households

4000

Off grid dc inverter less system, Rajasthan

The power data measured over a day in an off-grid home in Rajasthan with a solar dc Inverter less system on 25 February 2016

The power data measured in an on-grid home with a solar-dc inverterless system from 23 February 2016 to 24 February 2016.

Source: Solar-dc Microgrid for Indian Homes, IEEE, 2016

14

Successful Commercial development – OMC power

Running more than 50 plants in UP

Solar PV based power generation systems

Typical plant size – 30-36 kW, 150 kWh battery

back up,

Focused around – Telecom tower as key customer

– Agreements with telecom tower suppliers

Meter based charging to large customer like

Telecom tower, other productive loads, package to

community customer

Use of DG as back up power for rainy seasons

Petrol PumpSolar Plant

Tower

DG

15

OMC power - PlantSolar Plant MPPT Battery Bank

MetersLoads

16

Husk Power – Biomass gasification based power generation system

Running more than 50 plants in Bihar & UP

Operation through various model based on level of engagement (Ex. BOOM –

Build own operate & Maintain )

Biomass Gasifier engine based power generation system, typical plant size – 32

kW

Rice Husk as fuel – Engagement with rice mills for bulk procuring

Focused around – Market places, small productive loads, collection on daily basis

Electricity supply in Different packages

Unique features:

Local fuel utilization – Lower fuel cost

Gas cleaning system – uses rice husk

Low cost material and local fabrication – Low capital cost

Training and capacity building of operator – Low downtime

Local material for distribution network – Low cost

Use of waste Ash from gasifier – Intense making ; local job creation

17

Husk Power – Biomass gasification systemRice huskGasifierGas CleaningEngine

Monitoring Distribution network End load

Remote data monitoring Billing & Payment collection Intense making from ash

18

Mini grid based on Hybrid system – HUSK Power

Recently husk power has installed hybrid system with an intent to supply 24X7 electricity

Around 3-4 hybrid plants being operated by Husk power

Technology – Biomass gasifier engine system, Solar PV system and Battery

Technical Arrangement: Electricity supply during day time by Solar PV system and during

evening time by Biomass gasification system

Electricity supply in Different packages

Motivation for hybrid system:

Lower solar PV cost

Increasing demand from users

Willingness to use electricity in day time also

19

Storage options

&m-grid scenario

20

For a renewable microgrid scenario

Log of time in seconds

1 (t=0) 3 (t=15minutes) 5 (t=1day) 7.5 (t=1year)

Short term storage Mid Term Storage Long term Storage

o Sudden fluctuation in load averaged over a second

o Load surges 4-8 times average load

o Context: Welding Load, lift load

o Load variation is averaged over 15 minutes

o Context - Residential Buildings with load shedding 2-3 hours

o Seasonal variation in load averaged over the day for an entire year

o Context - Variation in load like summer loads, winter loads

o Diurnal load variationo Load is averaged over the hour

for a dayo Context - Renewable microgrid

Supercapacitor

Classification of Energy Storage Systems

Lithium Battery

Lead Acid Battery

Flywheel Fuel Cell-Hydrogen Storage| Flow batteries

21

22

Scenario 1(a): Isolated Rural with PV battery system

Energy Source Solar PV – 4.3kW

Storage Lead Acid battery – 19kWh

Connected Load 4.4 kW

DistributionVoltage

48V dc (Safety Voltage for distribution)

Boost

Converter

24-48V

MPPT

Charge

Controller

Battery Bank

19kWh

48 VDC bus

Household

load 1 +

Farm 1

Household

load 2+

Farm 2

PV array

3.4kW

0

200

400

600

800

1000

1200

1400

1600

1800

2000

1 6 11 16 21

Lo

ad

(W)

Time(hours)

Load Average load Peak load

Average Load = 0.5kWPeak Load = 2.0kWTotal Load = 4.4kWTotal Energy Consumption/day = 12.7kWh/day

Battery Life in climatic zones and per unit cost

Shillong

Bangalore

Chennai

Jodhpur

New Delhi

Jacob A. S., et al., 2016 23

Sizing based on Pinch Analysis

In isolated energy system Source – Generator

Sink - Demand

Quality – Time (Driving force)

En

erg

yy

(De

ma

nd

, G

en

era

tio

n,

Sto

rag

e)

Time

Cumulative Demand Cumulative Generation

Mismatch

Pinch Point

Storage

24

Maximum mismatch

Design Space

We vary the generation size in order to get the design space

Sizing curve represents the minimum storage capacity for a given generator rating

Sizing curve divides the entire space into feasible and infeasible regions

The area below the curve is infeasible

25

Generation from renewable source (kW)

Sto

rag

e C

ap

aci

ty (

kW

h)

Un

der

size

d

Gen

era

tio

n

Undersized

storage capacity

Feasible region

(Design Space)

Minimum generator with max storage capacity

Scenario 1 (b)- Off grid Industrial with PV hybrid storage system

PV arrayBoost

Converter

MPPT

Charge

ControllerHybrid

Storage

24V DC bus

Small

industry –

Welding

Load

26

0

0.5

1

1.5

2

2.5

3

3.5

4

0 365 730 1095 1460 1826 2191 2556 2921 3287

Lo

ad

(k

W)

Time (seconds)

1 hour welding profile logged in Mumbai on Feb’14

Average Load = 428.51WPeak Load = 3800WLoad Factor = 0.113

0.000

0.001

0.002

0.003

0.004

PV size

0

10

20

30

Feasible regionInfeasible

region

Energ

y

cumulativegenerationcumulative load

mismatch

Sho

rt-t

erm

Dat

a in

sec

on

d

Mid

-ter

m

Dat

a in

ho

ur

Lon

g-te

rm

Dat

a in

wee

k

P1 P2

S1

M1

L1

S2

M2

Energ

y

Time

7.5

(t=

1ye

ar)

1 (

t=0

)3

(t=

15

min

ute

s)5

(t=

1d

ay)

tim

e (

in lo

g sc

ale

)

Design Space for hybrid energy storage (kWh)Pinch for ‘P1’ PV size

Pinch Point

Pinch Point

Pinch Point

Infeasibleregion

0.6

0.7

0.8

0.9

Infeasible

region

Feasible region

Energ

y

Feasible region

Ref: Communicated to Energy

Sizing of Hybrid Energy Storage

Sizing of hybrid energystorage for a isolatedsmall scale industry(Welding Shop)

27

Load profile generation

Max load 19.2Minimum load 0.0Average load 9.0

Load profile obtained through house

hold survey to have realistic

assessment of demand

Electricity demand – Peak in evening

but there is demand in afternoon also

Load Considered – Flour Mill, Mobile

Tower, Lighting, Entertainment Water

pumping, HH Chores activities

Load Type Power

Lighting 30 W

Entertainment 80 W

HH Chores 62 W

Water Pumping 1.4 kW

Productive Load 1 - Mobile Tower 2 kW

Productive Load 2 - Atta Chakki 4 kW

Scenario 1 (c)- Isolated Rural with biomass gasifier-battery system

28

Biomass Gasification system - battery Combination

6/23/2017

P = Power generated from Biomass gasifier systemD = Load DemandQB = Stored Energy in Battery

= represent part load power of generator

Minimum generatorrating with storage

Minimum generator

rating without

29

CoE - Continuous Vs Intermittent Operation

30

Continuous Vs Intermittent Operation –Effect of Fuel Cost

8

10

12

14

16

18

10 20 40 60 80 100 150 200 250

Co

E (R

s./k

Wh

)

Transportation distance (km.)

Effect of biomass transportation on CoE

Biomass only

Biomass + Battery

31

Design Space for Hybrid System

32

Cost Comparison for selected systems

33

34

*Load Profile of 1 household * Load Profile of each households are identical in the housing colony with 30 households

Scenario 2 : Urban (PV battery grid backup system)

Component Sizing SpecificationsPV module 26.5 kWp (104x250Wp)

1 x solar battery charger 30 kW

1 x Inverter 50 kW

Array support Rooftop Mounted

Battery VRLA

Li Ion NiCd NiMH NaS

Storage Capacity(kWh) 150 137 140 148 157

Parameter ValueTotal energy 250 kWh/day

Peak load 43 kWAverage load 10.4 kW

Costing PV & Balance of System

35

#1 PV prices : IRENA Renewable Power Generation Costs in 2014

PV Price37%

Battery Price31%

Balance of system

32%

Investment Cost

Assume, d = 10%;O&M PV & BoS = 1% p.a

Item Investment Cost (Million ₹)

Life Annualised life cycle costing(Million ₹)

PU electricity cost

PV Panel Ground mounted(0.9USD/W)#1

1.55 25 years 0.186 ₹5

Balance of System (0.8USD/W)#1

1.378 10 0.234 ₹7

Total 2.928 - 0.424 ₹12

Comparison of PV with different battery pu cost

37

Battery options

Battery size

(kWh)

Battery Cost ₹/kWh

Capital Cost (Million ₹)

Battery ₹/kWh

p.u cost of PV & BoS(₹/kWh)

Total p.ucost of the PV battery system (₹/kWh)

VRLA 150 8650 1.298 9 12 21

Li ion 137 37387 5.122 19 12 31

NiCd 140 36904 5.166 23 12 35

NiMH 148 66346 9.819 86 12 98

NaS 157 33000 5.181 19 12 31

per unit cost of different grid backup options 38

Cost Analysis of different grid backup options

0

10

20

30

40

50

60

70

80

90

100El

ectr

icit

y co

st (

₹/K

Wh

)

Grid Backup Options

p.u fuel cost

p.u O&M cost

p.u Capital Cost

Avg. Tariff rates for MSEB

Cradle to grave energy flow diagram

39

Silicon ProductionPV Cell manufacturing

Fabrication of Frameless PV modules

Material Production Energy

BatteryPV

ModuleBalance

of System

Raw materialsSteel,Al,Lead,Polypropylene

Frame productionInverter and

charge controller components

Manufacturing Energy

BatteryPV

ModuleBalance

of System

Transportation Energy

PV Battery Microgrid

system

Recycling Energy

Material recycling

Waste disposalEmissions to air,water

Life cycle energy analysis boundary for the PV battery system

Raw material production

Electrical and thermal energy

Production

Consumable production

External Scrap supply

Battery

PV module

Balance of System

System components

Material Production

Component Manufacturing

Electricity and heat

Manufacturing

Cradle to gate

Transportation

Decommissioning and recycling of

the system

Transportation Energy

Recycling Energy

Cradle to grave

40

Energy flow diagram for PV battery system

PrimaryFossil

Energy

Production and transport of

Frame and array support

Production and transport of solar charge controller

Production and transport of

battery

Production and transport of

Inverter

Eind,2(BOS)

/tBOS

Eind,1(PV)

Eind,2(BOS)

Eind,3(CH)

Production and transport of

PV array

Eind,4(B)

Eind,5(INV)

Eind,3(CH)

/tCH

Eind,4(B)

/tB

Eind,5(INV)

/tINV

Frame and array supportηBOS, tBOS

Solar Energy

Solar charge controllerηCH, tch

BatteryηB, tB

InverterηI, tI

Energy Output

PV arrayηPV, tPV

Conversion to electricity,αpf,elec=0.35

Conversion to heat,αpf,heat=1

Eind,1(PV)

/tPV

Indirect Energy Input to the system

Direct Energy Input

Legend:Eind – Indirect Energyt - service life (years)η - efficiencyαpf - conversion efficiency

41

Summary of battery energy values in Indian context

Battery Configuration

MaterialProduction Energy Emp

ManufacturingEnergy Emnf

Recycling EnergyErec

Transportation Energy-Etr

for finished product import

Etot=Ectg+ Etr

(MJpf/Wh)

MJpf/kgRecycled materials

MJpf /Wh(Recycled materials)

MJpf

/kgMJpf /Wh MJpf /kg MJpf /Wh (MJpf /kg) (MJpf

/Wh)

VRLA 21.87 0.681 11.6 0.385 2.4 0.075 - - 1.141

LFP-G 96.27 1.05 30 0.33 3.6 0.04 2.9 0.031 1.451

Nickel Metal Hydride(AB2)

41.99 0.763 75 1.36 19.6 0.36 0.988 0.018 2.501

Nickel Metal Hydride(AB5)

33.12 0.602 75 1.36 19.6 0.36 0.988 0.018 2.34

Nickel Cadmium 64.72 1.58 46 1.15 4.85 0.121 - - 2.851

Sodium Sulphur 128.31 0.855 56 0.373 - - 1.34 0.0089 1.24

Lithium Sulphur 242.06 1.59 172 1.13 51.2 0.34 - - 3.06

Energy Flow diagram of the PV panel for India

Quartz Mining 0.85 MJ/kg of

Quartz

Metallurgical Grade(MG) Silicon

188.30 MJ/kg-MG Si

Solar(Electronic) Grade Silicon 1778.78 MJ/kg-EG Si

Czochralski Single Crystal process

production2977.89 MJ/kg CZ-sc-Si

Casting of multi crystalline Silicon 3160.69 MJ/kg mc-Si

Silicon Wafer Production

Silicon Cell Production

2946.52 MJ/m2 of wafer area

3157.82 MJ/m2 of solar cell area

Frame

Panel and laminate assembly

BOS Electrical Installation

PV system

3107.14 MJ/m2 of panel area

Aluminium

Glass, Copper

Aluminium,Steel

Manufacturing Energy

InverterCharge controller

Zinc, Steel,Copper

49.9 MJ/m2 of panel area

507.7 MJ/m2 of panel area

422.22 MJ/m2 of panel area

149.17 MJ/kWp

1074.11 MJ/kWe

Growing of Silicon

Panel Production

43

Summary of photovoltaic panel energy values in Indian context

Component MaterialProduction Energy

ManufacturingEnergy of PV

panel,frame and BOS

Transportation Energy

PV system (polycrystalline-

Silicon)

3107.14MJpf/m2 of

sensing area

49.9 MJpf/m2 of

panel area

0.34 MJpf/kg of panel weight

Frame422.22 MJpf/m

2 of frame area

Balance of System(BOS)

507.7 MJpf/m2 of

panel area

Electrical Installation

149.17 MJpf/kWp

Charge Controller

1074.11 MJpf/kWe

Inverter 1074.11 MJpf/kWe44

Total Energy requirement for the components

Component Life(years) Material Production

Energy-Emp

Manufacturing Energy-

Emnf

Recycling Energy(Erec)

Transportation

Energy(Etr)GJpf GJpf GJpf GJpf

PV module(Polycrystalline Silicon)

25 542.8

8.7

- 0.9

Frame 25 9 1.4Balance of System 25 88.1 - -

Electrical Installation 25 3.9 - -Charge Controller 10 32.2 32.2 -

Inverter 10 53.6 53.6 -Batteries

VRLA 5 102.1 54.1 11.2 -LFP-G 13 145.8 45.1 5.4 4.4

Nickel Metal Hydride(AB2)

4 113.1 20.2 52.8 2.7

Nickel Metal Hydride(AB5)

4 89.2 20.2 52.8 2.7

Nickel Cadmium 3 254.9 18.1 19.1 -Sodium Sulphur 15 119.7 52.2 - 1.2Lithium Sulphur 5 206.7 14.7 43.7 -

45

Comparison of Energy Pay Back Time & Net Energy Ratio

0.0

0.5

1.0

1.5

2.0

2.5

3.0

3.5

4.0

EP

BT

in

ye

ars

PV+ battery technology

0

1

2

3

4

5

6

7

8

NER

PV+ battery technology

𝑁𝐸𝑅 =𝐴𝑛𝑛𝑢𝑎𝑙𝑖𝑠𝑒𝑑 𝑒𝑛𝑒𝑟𝑔𝑦 𝑜𝑢𝑡𝑝𝑢𝑡

𝐴𝑛𝑛𝑢𝑎𝑙𝑖𝑠𝑒𝑑 𝑒𝑛𝑒𝑟𝑔𝑦 𝑖𝑛𝑝𝑢𝑡

46

Results and graphs

0

1000

2000

3000

4000

5000

6000

MJp

f/kW

h o

f o

utp

ut

PV+Battery

PV ,BOS and frame battery inverter and CC

0

10

20

30

40

50

60

70

80

Perc

enta

ge o

f to

tal l

ife

cycl

eBattery

47

Sensitivity Analysis

48

Sensitivity Analysis

49

Summary

Two scenarios identified Isolated – with no grid access

Grid backup – with unreliable grid

Sizing, Design and economic analysis based on life cycle study for isolated scenario such as

PV – battery microgrid

PV – hybrid storage system

Biomass – battery microgrid

Sizing, Design, Life cycle cost and energy analysis for PV-battery grid back-up for an urban system.

Battery life impact

Net Energy Analysis 50

Conclusions

Microgrids – different contexts-urban and isolated –nearly cost effective

Reliability

Focus on large scale centralised renewables

Need for cost reduction, technology development

Hybrid storage technologies

Understanding of load variations

51

Acknowledgment

Balkrishna SurveAjit Paul A.

Thank [email protected]@gmail.com

52

Jani Das

Amit Kumar S. PariharAmmu Susanna Jacob Prakash Ghosh

IMASE

References Banerjee, Comparison of options for distributed generation in India, Energy Policy,34,pp.101-111, 2006.

http://assets.wwf.org.uk/downloads/powerofscotlandrenewed_full.pdf

ESMI, Prayas: Electricity Supply Monitoring Initiative, Prayas, http://www.watchyourpower.org/download_raw_data.php

Schnitzer, D et al., 2014: Microgrids for Rural Electrification: A critical review of best practices based on seven case studies,, United Nations Foundation, CMU and University of California, Feb. 2014. (http://energyaccess.org/wp-content/uploads/2015/07/MicrogridsReportFINAL_high.pdf)

Minigrids Electricity for all, Centrre for Science and Environment Report, 2016 (available online: http://www.cseindia.org/userfiles/mini-grids.pdf)

Solar-dc Microgrid for Indian Homes: A Transforming Power Scenario, IEEE Electrification Magazine, Volume: 4, Issue: 2, June 2016.

Jacob, A. S., Banerjee, R., Ghosh, P.C., Modelling and simulation of a PV battery grid backup system for various climatic zones of India', Proceedings of 43rd IEEE Photovoltaic Specialists Conference, PVSC 2016; Portland; United States; pp 1807-1812, Article number 7749934, June 5-10, 2016.

A. Chatzivasileiadi, E. Ampatzi, I. Knight, Renewable and Sustainable Energy Reviews, 25, 2013.

C.J. Rydh, B. A. Sandén, , Energy Conv. and Mgmt., 46, 2005

Tubular gel 2V VRLA battery Technical Manual, http://www.exideindustries.com/products/solar-batteries/tubular-solar-batteries.aspx, 19-11-2016.

A. Castillo, D.F. Gayme, Energy Conv. and Mgmt., 87, 2014.

J.M Sime, Evaluation of Nickel Cadmium Battery-Electric Subcompact Automobile in Connecticut as an Alternative for Work-trips and Commutes, Research Project: SPR-2223, 2004

NGK Insulators NaS Battery, https://www.ngk.co.jp/nas/specs, 19-11-201653