Mechanical Assembly of RPCs Status Report
L. M. Pant India-CMS Meeting, Delhi University 24 th & 25th Jan., 2008
L. M. PantNuclear Physics Division, BARC
RPC Lab. @ NPD-BARC
![Page 2: India CMS Meet DU 24Jan08 NPD Pant](https://reader038.fdocuments.us/reader038/viewer/2022103115/5571f1fd49795947648bee3c/html5/thumbnails/2.jpg)
SN Item Description Quantity Order placed with
Amount Amount in Rs.
1 Honey Comb Panels 12 Beijing BAMTRITech. & Devp. Co.
USD 7,000 Rs. 2,80,000/-
2 Cu + Mylar sheets for Faraday Cage, Read out strips, ferrules
12 Beijing GaoNengKedi Science & Tech. Co. Ltd.
USD 7,500
Rs. 3,00,000/-
3 FEBs 36 Matrix, Italy Euro 7,800
Rs. 4,68,000/-
4 Gaps (3 x RE*/3) 9 CMS, CERN Free -
5 Gaps (9 x RE*/2) 27 KODEL, Korea USD8,500
Rs. 3,40,000/-
6 cable, connectors, modules, shipping etc.
Rs. 2,00,000/-
7 Minor fabrications Rs. 4,00,000/-
8 Distribution Boards(order to be placed)
12 Matrix, Italy Euro960
Rs. 57,600/-
9 Despatch, Insuarance, invitation etc.
Rs. 2,00,000/-
TOTAL Rs. 22,45,600/-
The Final Tally : Estimate ~ 35 Lakhs; Actual ~ 23 Lakhs
L. M. Pant India-CMS Meeting, Delhi University 24 th & 25th Jan., 2008
![Page 3: India CMS Meet DU 24Jan08 NPD Pant](https://reader038.fdocuments.us/reader038/viewer/2022103115/5571f1fd49795947648bee3c/html5/thumbnails/3.jpg)
Minor Fabrication Jobs / Procurements
L. M. Pant India-CMS Meeting, Delhi University 24 th & 25th Jan., 2008
• Aluminum Screen box Complete Delivered
• Al Jigs for gas-pipes Complete Delivered gas pipes configured
• Transportation Crate Complete Delivered
• Cu cooling pipes Under Delivery by requiredFabrication mid Feb at the end
• Perspex spacers Under Delivery byFabrication Jan end
• Al Clamps, Al Angles Under Delivery byFabrication Jan end
• Mylar Insulation / nuts & bolts Procured
![Page 4: India CMS Meet DU 24Jan08 NPD Pant](https://reader038.fdocuments.us/reader038/viewer/2022103115/5571f1fd49795947648bee3c/html5/thumbnails/4.jpg)
Gas leak tests for gas-gaps
MANOMETER
few gas nozzles were found clogged because of dried up linseed oil
L. M. Pant India-CMS Meeting, Delhi University 24 th & 25th Jan., 2008
![Page 5: India CMS Meet DU 24Jan08 NPD Pant](https://reader038.fdocuments.us/reader038/viewer/2022103115/5571f1fd49795947648bee3c/html5/thumbnails/5.jpg)
Leakage Current measurements : gas-gaps
SN
Date gas-gaps characterised
Total
1 Sep ‘07 9 9
2 Oct ‘07 8 17
3 Jan ‘08 17 34
A) 9 GT gas-gapsB) 30 KODEL gas-gaps
Total of 39 gas-gaps arrived by Sep. ‘07
5 gas-gaps left to be characterised
Should be over by Jan end
Mechanical assembly in progress
KODELgas-gaps
L. M. Pant India-CMS Meeting, Delhi University 24 th & 25th Jan., 2008
![Page 6: India CMS Meet DU 24Jan08 NPD Pant](https://reader038.fdocuments.us/reader038/viewer/2022103115/5571f1fd49795947648bee3c/html5/thumbnails/6.jpg)
Effect of different gas mixtures (bakelite GT gas-gaps)
( 5 : 20 : 75 )
L. M. Pant India-CMS Meeting, Delhi University 24 th & 25th Jan., 2008
![Page 7: India CMS Meet DU 24Jan08 NPD Pant](https://reader038.fdocuments.us/reader038/viewer/2022103115/5571f1fd49795947648bee3c/html5/thumbnails/7.jpg)
L. M. Pant India-CMS Meeting, Delhi University 24 th & 25th Jan., 2008
![Page 8: India CMS Meet DU 24Jan08 NPD Pant](https://reader038.fdocuments.us/reader038/viewer/2022103115/5571f1fd49795947648bee3c/html5/thumbnails/8.jpg)
L. M. Pant India-CMS Meeting, Delhi University 24 th & 25th Jan., 2008
![Page 9: India CMS Meet DU 24Jan08 NPD Pant](https://reader038.fdocuments.us/reader038/viewer/2022103115/5571f1fd49795947648bee3c/html5/thumbnails/9.jpg)
Relocation of HV slots (precision job) at Centre for Design and Manufacture (CDM), BARC
L. M. Pant India-CMS Meeting, Delhi University 24 th & 25th Jan., 2008
![Page 10: India CMS Meet DU 24Jan08 NPD Pant](https://reader038.fdocuments.us/reader038/viewer/2022103115/5571f1fd49795947648bee3c/html5/thumbnails/10.jpg)
Relocation of HV slots (precision job) at Centre for Design and Manufacture (CDM), BARC
relocated slot
L. M. Pant India-CMS Meeting, Delhi University 24 th & 25th Jan., 2008
![Page 11: India CMS Meet DU 24Jan08 NPD Pant](https://reader038.fdocuments.us/reader038/viewer/2022103115/5571f1fd49795947648bee3c/html5/thumbnails/11.jpg)
Coaxial signal cables with adaptor cards : for 12 chambers
Patale, BARCAbhinav, DUSupreet, PUArchana, PU
L. M. Pant India-CMS Meeting, Delhi University 24 th & 25th Jan., 2008
![Page 12: India CMS Meet DU 24Jan08 NPD Pant](https://reader038.fdocuments.us/reader038/viewer/2022103115/5571f1fd49795947648bee3c/html5/thumbnails/12.jpg)
40 pin Twisted pair cables for the FEBs : for 12 chambers
L. M. Pant India-CMS Meeting, Delhi University 24 th & 25th Jan., 2008
Sachi, BARCSandhya, DUShilpi, DUSudha, DU
![Page 13: India CMS Meet DU 24Jan08 NPD Pant](https://reader038.fdocuments.us/reader038/viewer/2022103115/5571f1fd49795947648bee3c/html5/thumbnails/13.jpg)
Mechanical assembly of RPCs in progress
Mylar insulation
Cut Honey Comb Panel
Cut Faraday Cage
Cut gas-gap
Honey Comb Panel
Mylar insulation
Faraday Cage
Large gas-gapCu read out
Coaxial cables
L. M. Pant India-CMS Meeting, Delhi University 24 th & 25th Jan., 2008
![Page 14: India CMS Meet DU 24Jan08 NPD Pant](https://reader038.fdocuments.us/reader038/viewer/2022103115/5571f1fd49795947648bee3c/html5/thumbnails/14.jpg)
FEBs, Twisted Pair Cables and cooling pipes for the electronics
L. M. Pant India-CMS Meeting, Delhi University 24 th & 25th Jan., 2008
![Page 15: India CMS Meet DU 24Jan08 NPD Pant](https://reader038.fdocuments.us/reader038/viewer/2022103115/5571f1fd49795947648bee3c/html5/thumbnails/15.jpg)
Minor Fabrication : Al Screen box
L. M. Pant India-CMS Meeting, Delhi University 24 th & 25th Jan., 2008
![Page 16: India CMS Meet DU 24Jan08 NPD Pant](https://reader038.fdocuments.us/reader038/viewer/2022103115/5571f1fd49795947648bee3c/html5/thumbnails/16.jpg)
Minor Fabrication : Transportation Crate for RPCs
L. M. Pant India-CMS Meeting, Delhi University 24 th & 25th Jan., 2008
Small sized RPC (RE*/2)
![Page 17: India CMS Meet DU 24Jan08 NPD Pant](https://reader038.fdocuments.us/reader038/viewer/2022103115/5571f1fd49795947648bee3c/html5/thumbnails/17.jpg)
• almost all pre-assembly jobs are over(i) screen boxes(ii) Cu cooling pipes(iii) Al angles, L clamps(iv) thermoformable gas-pipes configured(v) perspex spacers
• mechanical assembly in progress (should be over by Feb. end)
• soldering of co-axial signal cables to the read out strips to start (2500 soldering points – delicate job )
• FEB installation and testing (to start by March 2008)
• Efficiency measurements (March/April 2008)
• Packaging and despatch (May - June 2008)
Summary and Outlook - I
L. M. Pant India-CMS Meeting, Delhi University 24 th & 25th Jan., 2008
![Page 18: India CMS Meet DU 24Jan08 NPD Pant](https://reader038.fdocuments.us/reader038/viewer/2022103115/5571f1fd49795947648bee3c/html5/thumbnails/18.jpg)
Summary & Outlook - II
• Order for Distribution Boards asap We have two of them for the moment • NPD-BARC, plans to invite Cai from China during the assembly process
• Abstract submitted to RPC 2007 on behalf of India-CMS-RPC collaboration
• CMS-RPC meeting on 12 Feb. (Tuesday), a day prior to RPC 2007, IX International Workshop on RPC, at TIFR
• RPC Phone meeting on 23rd January (Wed.)
L. M. Pant India-CMS Meeting, Delhi University 24 th & 25th Jan., 2008
![Page 19: India CMS Meet DU 24Jan08 NPD Pant](https://reader038.fdocuments.us/reader038/viewer/2022103115/5571f1fd49795947648bee3c/html5/thumbnails/19.jpg)
RPC Phone Meeting on 23rd Jan., ‘’08 (Wed) : 90 minutes
Attended by Walter, Archana and Ian at CERN
and joined by people on phone from
Italy (Pino), China, Korea, Pakistan (Hasan) and India (Lalit)
• All relevant RPCs are underground and 3-4 people are required immediately and urgently for commissioning. • Six high rate RPCs for the high eta region from Korea are at CERN to understand the technology for FRPC upgrade. Details to be presented on 12th Feb.
• Status of RPCs for CMS in India and delivery schedule was discussed. Performance of fresh KODEL gas-gaps.
• 12 Feb meeting (airport pickup for delegates on 11th Feb ?).
L. M. Pant India-CMS Meeting, Delhi University 24 th & 25th Jan., 2008
![Page 20: India CMS Meet DU 24Jan08 NPD Pant](https://reader038.fdocuments.us/reader038/viewer/2022103115/5571f1fd49795947648bee3c/html5/thumbnails/20.jpg)
Assembly, testing and production of bakelite RPCs for the end-cap region of the Compact Muon Solenoid experiment at CERN
The Final Assembly
The Cosmic Stand for characterising the gas-gaps, leakage current and efficiency measurements
RPCs can operate either in avalanche or streamer mode and accordingly need a proper mixture of Argon, Isobutane, RE134A and SF6 gases in a required proportion
1 to 8 channel flow divider with safety bubblers & dew point meter
References :[1] R. Santonico et. al. NIM 187 (1981) 377[2] INO Project Report INO/2006/01[3] J. Va’vra et. al. IEEE, Vol. 51, No.5, 2004
The infrastructure
Outlook• gap making technology
Resistive Plate Chambers are low cost detectors used in avalanche or streamer mode in various experiments both with cosmic rays and accelerators. They will play an important role for the generation of first level muon trigger at CMS and ATLAS at LHC [1]. 27,000 RPCs, each measuring 2m x 2m in area are required for the INO project [2]
RPC 2007, IX International Workshop on Resistive Plate Chambers and related Detectors, Tata Institute of Fundamental Research, Mumbai, India, February 13-16, 2008
Four channel on-line & pre-mix gas distribution system with purifiers and MFCs at NPD-BARC for Argon, Isobutane, RE134A and SF6
The pre-assembly jobs
relocated slot
MANOMETER
L. M. Pant1,*, A. K. Mohanty1 , P. Shukla1 , D. Dutta1 , V. Kumar1 , P. Patale1, S. D. Tripathi1, S. Kailas1 , R. K. Choudhury1 ,
S. Pal Singh2, A. Sharma2, ______________
A. K. Dubey3, Shilpi Jain3, Sandhya Jain3, Sudha Ahuja3, _______
1 Nuclear Physics Division, Bhabha Atomic Research Centre, Mumbai, India2 Department of Physics, Panjab University, Chandigarh, India
3 Department of Physics and Astrophysics, Delhi University, Delhi, India*email : [email protected]
on behalf of India-CMS collaboration
![Page 21: India CMS Meet DU 24Jan08 NPD Pant](https://reader038.fdocuments.us/reader038/viewer/2022103115/5571f1fd49795947648bee3c/html5/thumbnails/21.jpg)
L.M.Pant India-CMS Meeeting, Delhi University 27th Sep. 2007
![Page 22: India CMS Meet DU 24Jan08 NPD Pant](https://reader038.fdocuments.us/reader038/viewer/2022103115/5571f1fd49795947648bee3c/html5/thumbnails/22.jpg)
OptionsWe just keep waiting for funds approval till Dec end and can then happily say that funds were not made available in time
OR
We vigourously pursue it during the next few months with DST and get the approval
No funding by Dec end : We forget the issue(the best solution perhaps !! ??)
If funding comes : then how to ?Clearly, now this is a University call and
the Universities have to take the lead
It is being demonstrated how to go about
L.M.Pant India-CMS Meeeting, Delhi University 27th Sep. 2007