Independent Power Projects in Sub-Saharan Africa Investment trends and … · 2017-06-18 ·...
Transcript of Independent Power Projects in Sub-Saharan Africa Investment trends and … · 2017-06-18 ·...
Contents lists available at ScienceDirect
Energy Policy
journal homepage: www.elsevier.com/locate/enpol
Independent Power Projects in Sub-Saharan Africa: Investment trends andpolicy lessons
Anton Eberharda,⁎, Katharine Gratwickb, Elvira Morellac, Pedro Antmannc
a Graduate School of Business, University of Cape Town, South Africab Independent Consultant, USAc World Bank, USA
A R T I C L E I N F O
Keywords:Independent power producersSub-Saharan AfricaInvestmentRenewable energyDevelopment finance institutionsPower sector reform
A B S T R A C T
Sub-Saharan Africa is in urgent need of more power. Private sector investment is key to achieving this. Alongwith Chinese-funded projects, Independent Power Projects (IPP) represent the fastest growing sources of powerinvestment in Sub-Saharan Africa. IPP investment flows show little concern for electricity market structures,but are more likely to gravitate to countries with strong planning, procurement and contracting capacity, as wellas good regulatory quality. Data from the continent also shows a variety of ownership and financing structuresfor IPPs, but generally development financing institutions (DFIs) play an important part in mitigating risk andbringing in private financiers. We also see renewable energy breaking through on the continent - both in scaleand price. This breakthrough is in part being facilitated by competitive procurement or auctions, which deliverlower prices and increased transparency when compared with renewable energy feed-in tariffs or directlynegotiated contracts. These developments have important policy implications, highlighting the need for:dynamic, least-cost planning, linked to the timely initiation of the competitive procurement of new generationcapacity; the building of effective regulatory capacity; and appropriate risk mitigation mechanisms. Such effortspromise to promote sustainable economic and social development across the continent.
1. The need for Independent Power Projects in Africa
Sub-Saharan Africa (SSA) has a severe shortage of power. In 2014the 49 Sub-Saharan African countries, with a combined population ofmore than 800 million, had less generating capacity (92 GW) installedthan Spain (106 GW), a country with a population of 45 million (Findtet al., 2014; U.S. EIA, 2014). What further sharpens this contrast is thefact that more than half of the region's installed capacity is based in asingle country: South Africa. The remaining 46 GW is therefore sharedamong the remaining 48 countries in the region, with only 14 countrieshaving power systems larger than 1 GW. Put another way: installedcapacity in Sub-Saharan Africa is 44 MW per million people, comparedwith 192 MW per million people in India, 590 MW in Latin America,and 815 MW in China (U.S. EIA, 2014). Electricity demand is set todouble by 2030, and triple by 2040 (International Energy Agency,2015). A recent report by McKinsey estimates that more than $490billion will need to be invested in additional power generation capacityby 2040 to meet projected demand (Castellano et al., 2015).Approximately $45.6 billion was invested in electric power generationin Sub-Saharan Africa between 1990 and 2013; excluding South Africa,
this total drops to $31.3 billion (Eberhard et al., 2016). Existinginvestment levels are therefore far below what is required, calling forincreased private sector involvement (Eberhard and Shkaratan, 2012).Independent Power Projects, or IPPs, are the main source of privateinvestment in the African power sector (Eberhard and Gratwick, 2013).While these entities are having a signficant impact on the Africanpower sector landscape, relatively little is known about their relatedoutcomes and the factors driving and underpinning these infrastruc-ture investments.
The research questions that we aim to address, are:
– What are the main power sector & IPP investment trends in Sub-Saharan Africa?
– Why are some countries more succesful in attracting private powerinvestments than others?
– What are the different IPP types (ownership structures, technologychoices, procurement methods) in Sub-Saharan Africa, and what arethe related outcomes?
– What are the key lessons for scaling up investment in powergeneration in Africa?
http://dx.doi.org/10.1016/j.enpol.2017.05.023Received 26 August 2016; Received in revised form 4 April 2017; Accepted 9 May 2017
⁎ Corresponding author.E-mail address: [email protected] (A. Eberhard).
Energy Policy 108 (2017) 390–424
0301-4215/ © 2017 Published by Elsevier Ltd.
MARK
2. Methods
We define IPPs as power projects that are, in the main, privatelydeveloped, constructed, operated and owned; have a significantproportion of private finance; and have long-term power purchaseagreements with a utility or another off-taker. IPPs included in thisstudy are all greenfield, grid-connected installations of 5 MW (MW) orgreater that have reached financial close, are under construction, or arein operation. A significant amount of data on power projects has beencollected and analyzed for this study. Sources include a series of WorldBank databases, including the Private Participation in Infrastructure(PPI) database; data from the Energy Information Administration(EIA); and databases prepared by Aid Data and the OECD, amongothers. In addition, the authors have conducted primary and secondarysource research, particularly on individual Independent PowerProjects.
Apart from the above-noted data sources, the analysis of IPP typesand outcomes, as well as the identification of lessons learned, is basedprimarily on original, in-depth case studies carried out in fivecountries, namely Kenya, Nigeria, South Africa, Tanzania, andUganda. The five case study countries were selected because theypresent the largest and most diversified experience with IPPs over thelongest time period, accounting for around 80% of IPP investment inSub-Saharan Africa. Each country has developed four or more IPPs, afact that facilitates an assessment of enabling policies and regulatoryframeworks, planning and procurement practices, and lessons learned.All five countries have been host to IPPs with different technologybases, which allows for a relatively in-depth evaluation of cost andreliability. Finally, each country has a mix of directly negotiated andcompetitively bid projects, which has the potential to shed light onwhich procurement methods are more effective.
2.1. Data limitations
Although an unprecedented body of data and case histories havebeen collected and analyzed, data limitations remain. Informationconcerning the composition of investments by funding source; theterms of IPP contracts (which remain mostly confidential); and thesize, composition, and types of investment from emerging financiers(notably China) was gathered from various sources and triangulated.For Chinese data specifically, the authors used Aid Data as a startingpoint. Additional secondary source research was conducted, and thenactual projects were verified with stakeholders in each of the studycountries. However, because nearly every Chinese-funded generationproject is directly negotiated with the government of a given Africancountry, limited public data is available.
Due to a lack of available data, government and utility megawattsand investments have largely been derived by (i) subtracting themegawatt totals of IPPs, Chinese, official development assistance(ODA), and multilateral finance institutions, and development financeinstitutions, and then (ii) using the Energy InformationAdministration's corresponding data on “megawatts installed by tech-nology” per country to determine residual megawatts per technology(U.S. EIA, 2014), and finally (iii) ascribing an investment value, basedon average costs per technology in Sub-Saharan Africa. Whereverpossible, efforts have been made to verify the megawatts and thetechnology with known projects undertaken by the government.
The focus of this paper is on power generation, as opposed to thetransmission and distribution (T &D) of electricity. While inadequateT &D is clearly a constraint on any effort to widen service access,countries must have sufficient generation capacity to be able to servenew customers, improve welfare, and accelerate economic develop-ment. Also, a detailed discussion of the environmental externalitiesattached to specific IPP technologies—which pose growing concern—lies outside the purview of this paper.
Finally, South Africa's size and prominence in the generation of
Sub-Saharan Africa's electric power is noteworthy and hence effortshave been made to present Sub-Saharan African tallies with andwithout South Africa.
3. Trends in power generation investment in Sub-SaharanAfrica
3.1. Investment trends
Power investments in Sub-Saharan Africa between 1990 and 2013were far below requirements: only 15.63 GW net was added across theregion, excluding South Africa (U.S. EIA, 2014). The 1990s saw a mere1.84 GW of new capacity installed. Investment picked up since 2000,with an additional 13.8 GW installed in the region. Around 94% of thiscapacity has been added in only 15 countries, with the rest addinghardly any capacity at all, and some even losing capacity as a result ofcivil wars or poor maintenance (U.S. EIA, 2014).
While historically public utilities have been the major sources ofnew investment, this trend is changing. Most African governments areunable to fully fund their power needs, and most utilities do not haveinvestment-grade ratings and so cannot raise sufficient debt at afford-able rates (Eberhard and Gratwick, 2013). Official DevelopmentAssistance (ODA) and development finance institutions (DFIs) haveonly partially filled the funding gap. The fastest growing sources offinance for Africa's power sector are now private investments in IPPsand Chinese funding (Eberhard et al., 2016). Nevertheless, around 50%of investment in the African power sector is still coming from the publicsector, but it has remained stagnant over the period analyzed. Inaddition, concessionary DFI funding, ODA and Arab funding representa small portion of the overall funding picture, with no real growth. Thecontinent therefore seems set to increase its dependence on private andforeign (Chinese) investments to fund its power generation needs in thenear and medium term (Fig. 1).
3.2. Chinese funding
While not the explicit focus of this paper, the growing size andprominence of China's involvement in the African power sectorwarrants some discussion. Chinese funded generation assets representan important area of significant capacity additions in Sub-SaharanAfrica, totalling 34 projects in 19 countries between 1990 and 2014(Fig. 2). Taken together, these represent a total of 7.5 GW in installedcapacity, with most capacity added in the years 2009 – 2014 (Eberhardet al., 2016). According to the International Energy Agency, Chinesecapacity additions account for more than 30% of new capacity
Fig. 1. Investments in Power Generation, Five-Year Moving Average: Sub-SaharanAfrica (Excluding South Africa), 1994 – 2013. Note: DFI = Development FinanceInstitutions; IPP = Independent Power Project; ODA = Official Development Assistance;OECD = Organization for Economic Co-operation and Development.
A. Eberhard et al. Energy Policy 108 (2017) 390–424
391
additions in Sub-Saharan Africa between 2010 and 2015 (InternationalEnergy Agency, 2016). The agency also reports that Chinese contrac-tors have built or are set to build more than 17 GW of new capacity inthe 2010 – 2020 period (International Energy Agency, 2016). It ishowever important to note that there is a considerable and growing gapbetween Chinese funding for African infrastructure and the involve-ment of Chinese contractors: close to 50% of the continent's infra-structure contracts in 2014 are being awarded to Chinese companies,while Chinese funding accounts for less than 5% of the continent'soverall infrastructure financing in the same period (Huang and Chen,2016).
Chinese power sector investments in Sub-Saharan Africa do notappear to follow an expected pattern, with no clear correlation betweenthe resource-wealth of a country and Chinese-backed investments.a
This is in line with findings by Brautigam (2009) as well as Dreher andFuchs (2006), which challenge the notion of Chinese aid and invest-ments in Africa being primarily motivated by resource-based consid-erations. What is however apparent is a preponderance for large ( >50 MW) hydro-power projects (Fig. 3) (Eberhard et al., 2016), compos-
ing 63% of Chinese-funded capacity between 2001 and 2014 and forwhich Chinese engineering, procurement and construction (EPC)contractors have become renowned worldwide. This is in line withfindings from the IEA's investigation into Chinese capacity additions,which finds that 49% of all power projects by Chinese companies forthe 2010 – 2020 period is hydropower focused (International EnergyAgency, 2016).
3.3. IPPs in Africa
Africa's experience with IPPs started in 1994 in Côte d′Ivoire,followed by Kenya in 1996 and Mauritius in 1997 (Eberhard andGratwick, 2011). IPPs have since spread to 18 countries (excludingSouth Africa), with 59 projects having been implemented. Most ofthese projects are concentrated in only a handful of countries(Eberhard et al., 2016) (Fig. 4). From 2011, investments began takingoff, with the years since (2011–2014) constituting the largest and mostsustained investment cycle to date, representing 14 projects (excludingSouth Africa), $4.9 billion in investment and an additional 2.1 GW incapacity. In total, IPPs in Sub-Saharan Africa represent more than$11.12 billion in investments and 6.8 GW of installed capacity. AddingSouth Africa's 92 renewable energy IPPs brings this total to 151projects, totalling more than $30 billion in investment and more than12 GW in installed capacity. IPPs however still represent a minority oftotal generation capacity, mainly complimenting state-owned utilities.
IPPs in Sub-Saharan Africa range in size from a few megawatts toaround 600 MW – though the majority of projects, about two thirds,are smaller than 100 MW (Eberhard et al., 2016) (Fig. 5). The over-whelming capacity (82%) is thermal –mostly open and combined-cyclegas turtbines. However, there is important growth in renewables –
Fig. 2. Comparison of Chinese-funded power projects and IPPs, by generation capacity:Sub-Saharan Africa, 1994 – 2014. Note: No IPPs recorded for 1995 or 2000, whichexplains the absence of those years in the figure. IPP = Independent Power Project; RSA= Republic of South Africa.Source: compiled by the authors, based on various primary and secondary sources.
Fig. 3. Chinese-supported power project capacity (% of MW), by technology: Sub-Saharan Africa, 2001 – 2014. Note: CCGT = combined-cycle gas turbine; HFO = heavyfuel oil; MSD = medium-speed diesel; MW = megawatt; OCGT = open-cycle gas turbine.Source: Compiled by the authors, based on various primary and secondary sources.
Fig. 4. Countries with the most independent power project capacity in Sub-SaharanAfrica, excluding South Africa, 1994 – 2014 (MW).
Fig. 5. Number of Independent Power Projects in various size categories (megawatt), tohave reached financial close as of 2014.Source: Compiled by authors, based on utility data, primary sources, and the PPIdatabase.
a Chinese-funded power generation projects exist in the following 19 countries:Botswana, Cameroon, the Central African Republic, the Democratic Republic of Congo,the Republic of Congo, Côte d′Ivoire, Equatorial Guinea, Ethiopia, Gabon, Ghana,Guinea, Liberia, Mali, Nigeria, Sudan, Togo, Uganda, Zambia and Zimbabwe.
A. Eberhard et al. Energy Policy 108 (2017) 390–424
392
most notably wind, solar PV and concentrated solar power (CSP)(Fig. 6).
There has been a wide variety of African IPP sponsors and debtproviders, though a few have backed multiple projects. Table 1 high-lights specific IPPs from the five country case studies (excluding SouthAfrica, which is treated separately due to its sheer size).
While state institutions have invested in some IPPs—for example,the Nigerian National Petroleum Corporation (Okpai and Afam) andthe government of Uganda (Bujagali), as well as the Kenya Power StaffPension Fund (Iberafrica)—private sponsors are prominent. PrivateAfrican partners are present in numerous projects and recently haveeven taken majority or full equity, as in the case of Aba Integrated(Nigeria), Gulf and Triumph (Kenya), and Tororo and Buseruka(Uganda). Following this, the most conspicuous equity sponsor,Globeleq, hails from Europe, and there are 15 other European entities,such as Aldwych and Wartsila, as well as numerous European bilateralDFIs, such as the Norwegian Investment Fund for DevelopingCountries (Norfund), the Netherlands Development FinanceCompany (FMO), and the Danish Investment Fund for DevelopingCountries (IFU). North America sponsors (primarily from the UnitedStates) are significantly fewer, at only seven, followed by South Asia(one), Southeast Asia (one), and the Middle East (one). Equity is alsoheld by multilateral agencies, namely, the International FinanceCorporation (IFC) and new infrastructure funds: for example, theAfrican Infrastructure Investment Fund (AIIF) managed by a SouthAfrican life insurer.
3.4. ODA and DFI financing
The sustained upward trend in IPP investments on the continent inthe past 5 years is all the more impressive if one considers that of the18 Sub-Saharan African countries with IPPs, only South Africa,Botswana and Mauritius have investment-grade ratings (Mecagniet al., 2014). This limits the possibilities of traditional project financedIPP deals. It is in this context where development finance institutions(DFIs) that invest in the private sector (e.g. International FinanceCorporation (IFC), the Netherlands Development Finance Company(FMO), Proparco, the Norwegian Investment Fund for DevelopingCountries (Norfund)) have played a significant role in funding IPPs
(Fig. 7) – bringing to financial close projects that would otherwise nothave been viable.b
4. Factors that support IPPs and their success
Despite the increase in funding, it is still only a small number ofcountries that are attracting IPPs. Why have some countries been moresuccesful than others in attracting private investment? The followingare some of the emergent determining factors for IPP investment flows.
4.1. Power markets
Sub-Saharan African utilities are often not credit-worthy off-takers,struggling to keep the lights on and unable to increase capacity(Eberhard and Shkaratan, 2012). The aim of power sector reform indeveloping countries is primarily to improve utility performance – bothtechnical & commercial - and in the process attract more investment,to provide sustainable, affordable, adequate and reliable services for all,and power economic growth (Gratwick and Eberhard, 2008).
The standard model of power sector reform – unbundle, privatise,create regulatory institutions, and create markets (Victor and Heller,2007) - is partly built on the premise that privatization will ultimatelyattract greater sector investment (Jamasb et al., 2005). The unbundlingof generation from Transmission and Distribution (T &D) was initiallyunderstood as a key reform element, and one that arguably should evenprecede the introduction of IPPs to ensure fairness in the contractingand dispatching of IPPs (versus the utility off-taker's own generation).However, nowhere in Africa is full wholesale or retail competition inplace (Kapika and Eberhard, 2013). Instead, we find various hybridmodels – where public and private investment co-exist - implementedacross the continent. IPPs are found in very different market structures(Fig. 8), with no clear correlation between the level or sequencing ofreform and IPP investment. The majority of IPPs are in fact found incountries with vertically integrated utilities. This does not negate theimportance of sector reform, especially from sustainability, perfor-mance and governance points of view; it does however pose animportant question regarding what was once assumed to be drivingprivate power sector investment. If power sector restructuring is notessential for attracting investment, then what is?
4.2. Independent regulation
By definition, IPPs are investment transactions regulated by theunderlying contracts. Regulations at the sector level are also importantin defining the rules of the game and ultimately shaping the enablingenvironment for IPPs (Findt et al., 2014). The establishment of energyregulators has been the most widespread power sector reform elementin Sub-Saharan Africa, with more than half of the region's countrieshaving such an agency (Kapika and Eberhard, 2013). As a rule, thecountries with the most IPPs all have an independent regulatoryauthority.
An independent regulator brings with it oversight capacity andcould potentially enforce the competitive procurement of IPPs. Thishas unfortunately not been the case in many Sub-Saharan Africancountries, and we are increasingly seeing regulatory risk serve as afurther disincentive to investment. Merely having a regulator is thusnot sufficient; rather, it is the quality of regulation produced andenforced by this regulator that is critical for attracting private invest-ment. Transparent, fair and accountable regulators that produce
Fig. 6. Independent Power Project Capacity (% of MW), by Technology: Sub-SaharanAfrica (Excluding South Africa), 1994 – 2014. Note: CCGT = combined-cycle gas turbine;HFO = heavy fuel oil; MSD = medium-speed diesel; MW = megawatts; OCGT = open-cycle gas turbine.Source: Compiled by the authors, based on utility data, primary sources, and the PrivateParticipation in Infrastructure (PPI) database.
b As stated before, only three countries in Sub-Saharan Africa have investment-gradecredit ratings: South Africa, Mauritius and Botswana. Of these three, only Mauritius andSouth Africa have IPPs. Because of South Africa's distorting effect, Fig. 7 excludes datafrom South Africa. Mauritius has six IPPs, but only one has any DFI involvement. This isthe Belle Vue Power Plant, a 71.2MW coal/bagasse plant that reached financial close in1998 and was provided with a US$17 million loan from the EIB.
A. Eberhard et al. Energy Policy 108 (2017) 390–424
393
Table 1Project sponsors and debt holders in selected case studies.Source: Compiled by authors, based on various primary and secondary source data.
Project Equity partners (country, % of equity held) Procurement Contract changeY=yes/N=no
Equity turnover(#)a
KenyaWestmont Equity: Westmont (Malaysia, 100%); sought to sell plant since 2004; ultimately towed back
to MalaysiaDN Not extended —
Debt: equity financedIberafrica Equity: Union Fenosa (Spain, 80%), KPLC Pension Fund (Kenya, 20%) since 1997 DN Y 0
Debt: Union Fenosa ($12.7 million in direct loans and guaranteed $20 million); KPLCStaff Pension Fund ($9.4 million in direct loans and guaranteed $5 million through localKenyan bank)
OrPower4 Equity: Ormat (USA, 100%) since 1998 ICB Y 0Debt: Equity financed until 2009, European DFIs $105 million loan in 2009, then OPICloan of $310 million drawn down in 2012–13
Tsavo Equity: Cinergy (USA) and IPS (Int’l) jointly owned 49.9%; Cinergy sold to Duke Energy(USA) in 2005, CDC/Globeleq (UK, 30%), Wartsila (Finland, 15%), and IFC (Int’l, 5%) retainremaining shares since 2000
ICB N 1
Debt: IFC own account ($16.5 million), IFC syndicated ($23.5 million), CDC own account($13 million), DEG own account (€11 million), DEG syndicated (€2 million)
Rabai Equity: Aldywch-International (Netherlands, 34.5%), BWSC (Danish, but owned by Mitsuiof Japan, 25.5%), FMO (Netherlands, 20%), IFU (Danish bilateral lender, 20%)
ICB N 0
Debt: FMO ($126 million), Proparco and EAIF (25% each), DEG (15%), EuropeanFinancing Partners (10%)
Mumias Equity: Mumias Sugar Company Limited (100%/Kenya) DN N 0Debt: Not available
Thika Equity: Melec Powergen (part of Maletec grp) (90%/Lebanon) ICB N 0Debt: AfDB (€28 million), IFC (€28 million), ABSA Capital (€28 million)
Triumph Equity: Broad Holding (Kenya), Interpel Investments (Kenya), Taceflex (Kenya), SouthernInter-trade (Kenya)
ICB N 0
Debt: Industrial and Commercial Bank of China (ICBC) ($80 million), and Kenya's CFCStanbic Bank ($28 million) (of which Standard Bank is the parent, in which ICBC has a20% stake)
Gulf Equity: Consortium of local investors, namely Gulf Energy Ltd and Noora Power Ltd ICB N 0Debt: $76 million in long-term debt financing (IFC A Loan, and commercial lendingthrough IFC B Loan and OPEC Fund for International Development)
Kinangop Equity: Aeolus Kenya, AIIF2, majority owner (South Africa/Mauritius), Norfund (Norway) REFiT N 0Debt: Kenyan CFC Stanbic Project stalled.
Turkana Equity: KP & P Africa BV (Netherlands) with Aldwych International (Netherlands) DN N 0Debt: (foreign and local): AfDB, EIB, the Standard Bank of South Africa, Nedbank, FMO,Proparco, East African Development Bank (EADB), PTA Bank, EKF, Triodos, and DEG.The project's debt raising for the generation project was led by the AfDB, as mandated leadarranger, with the Standard Bank of South Africa and Nedbank Limited as coarrangers
NigeriaAES Equity: Enron (USA, 100%) sold to AES (95%) and YFP (Nigeria, 5%) in 2000 DN Y 1Barge Debt: $120 million loan (foreign and local): RMB (South Africa), FMO, African Export
Import Bank, Diamond Bank Nigeria, Fortis Bank, KfW, United Bank for Africa, AfricaMerchant Bank
Okpai Equity: Nigerian National Petroleum Corporation (Nigeria, 60%), Nigerian Agip OilCompany (Italy, 20%), and Phillips Oil Company (USA, 20%) maintained equity since 2001
DN Y 0
Debt: 100% equity financedAfam VI Equity: Nigerian National Petroleum Corporation (Nigeria, 55%), Shell (UK/Netherlands,
30%), Elf (Total) (France, 10%), Agip (Italy, 5%)DN N 0
Debt: 100% equity financedAba Integrated Equity: Geometric DN N 0
Debt: Senior debt: Diamond Bank (Nigeria) and Stanbic IBTC Bank (Nigeria);Subordinated debt: EIB and EAIF
TanzaniaIPTL Equity: Mechmar (Malaysia, 70%), VIP (Tanzania, 30% in kind); sold to Pan Africa Power
Tanzania Ltd (PAP) in 2013 (disputed)DN Y 1
Debt: Bank Bumiputra and Sime Bank (Singapore); Standard Chartered Bank, Hong Kong(SCB-HK) bought debt, valued at $125 million, for $74 million (in 2005)
Songas Equity: TransCanada sold majority shares to AES (USA) in 1999 and AES sold majorityshares to Globeleq (UK) in 2003. All preferred equity shares were converted into “LoanNotes” in June 2009, only common shares remain
ICB Y 2
Debt: IDA ($120 million), EIB ($50 million), assumed loans of $69.2 million from initialTANESCO plant
Mtwara Equity: Artumas Group Inc. (Canada, 100%), sold shares to Wentworth Group, which in turnsold to TANESCO in 2012
ICB Y 2
Debt: 100% financed with balance sheet of shareholdersSymbion Equity: Built by Richmond, sold to Dowans, then to Symbion DN Y 2
Debt: equity financed
Ugandab
(continued on next page)
A. Eberhard et al. Energy Policy 108 (2017) 390–424
394
credible and predictable regulatory decisions are necessary for creatingcertainty around market access, tariffs, and revenues that encourageinvestment (Eberhard and Gratwick, 2011).
4.3. Planning, procurement & contracting
Apart from the quality of regulation, there are further elements thatplay an important role in attracting IPP investment. The first set ofissues relate to generation planning, procurement and contracting.
4.3.1. PlanningIn the course of power sector reform and restructuring, least-cost
power planning is often neglected. Typically, this responsibility shiftsfrom the incumbent national utility to the ministry of energy or theregulator, but these institutions seldom have the experience orresources to produce regular and flexible power plans. Additionally,in hybrid power markets it is often unclear who is responsible forgeneration expansion planning.
The ideal location for this function is the system operator, whichcan be assigned responsibility not only for short-term, but also mediumand long-term supply security. However, this only makes sense if thesystem operator and transmission utility are unbundled from the statepower generation company so that they can plan objectively and fairlyfor the entire national system. An unbundled system operator can alsobe responsible for procurement and contracting of new power genera-tion capacity. In several countries in Africa, this function remainswithin the national utility, in which case the government may exercisepolitical leadership to ensure that the incumbent utility works in thenational interest. Whatever the arrangements are, it is critical that theresponsible agency be resourced with adequate capacity.
The nature of power sector planning is equally important: it needsto be up-to-date and flexible to ensure security of supply, a least-costmix of generation plants, and the right combination of exports andimports. Currently, the majority of Sub-Saharan African countries haveinadequate planning capacity and end up contracting out this function
to consultants (Eberhard and Gratwick, 2011). All five case studycountries have some form of least cost power development plansdeveloped, although in the cases of South Africa, Nigeria and Ugandathese plans are severely outdated.
4.3.2. Procurement & contractingFor electricity plans to matter, they need to be translated into
timely procurement and well-delineated investment opportunities forthe private and public sector. Unfortunately, few African countries havean explicit connection between planning and procurement (Malgas andEberhard, 2011). In addition, clearly stated criteria for the allocation ofinvestment opportunities between state-owned enterprises (SOEs) andIPPs are lacking.
A key feature of power generation procurement in Africa is the lowrecourse to competitive bidding, despite the fact that this is frequentlyenshrined into legislation. A minority of IPPs in SSA, excluding SouthAfrica, have been competitively procured: only 16 competitive tendersversus 34 directly negotiated projects. This is partly due to the firstIPPs being procured in reaction to power shortages (in all five casestudy countries), in contexts where capacity planning was weak. Incontrast, competitive tenders require good planning, procurement andcontracting frameworks – and often impose higher transaction costs.They have, however, delivered better price outcomes than directlynegotiated power projects, even in situations with too few bidders(Fig. 9). Competitive tenders are also more transparent, providingbetter investment certainty and less chance of corruption.
More than two decades of experience in power procurement in Sub-Saharan Africa have demonstrated that a lack of competition inprocuring new generation capacity has extensive drawbacks, rangingfrom immediate effects on project outcomes (higher prices, unravellingcontracts, and so on) to more general effects on the overall governanceof the electricity sector and its investment climate. Despite this, we seeboth forms of procurement used relatively consistently from 1990 to2014, with no clear move away from or towards either direct negotia-tions or competitive bidding (Fig. 10).
Table 1 (continued)
Project Equity partners (country, % of equity held) Procurement Contract changeY=yes/N=no
Equity turnover(#)a
Bujagali Equity: Sithe Global (USA, 58%), IPS-AKFED (32%), Government of Uganda (10%) ICB N 0Debt: IFC, EIB, Proparco, KfW, AfDB, FMO, DEG, AfDB, Standard Chartered, ABSA
Namanve Equity: Jacobsen (Norway, 100%) ICB N 0Debt: Norwegian commercial bank and local Ugandan bank, and supported by theNorwegian Agency for Development Cooperation (NORAD)
Bugoye Equity: TrønderEnergi, Norfund (Norway) DN N 0Debt: EAIF/FMO
Mpanga Equity: South Asia Energy Management Systems (SAEMS) (USA, 100%) DN N 0Debt: EAIF, FMO, DEG
Tororo Equity: Electro-Maxx (Uganda, 100%) DN N 0Debt: funded by local Ugandan banks
Ishasha Equity: Eco Power Ltd (Sri Lanka, 100%) DN N 0Debt: Sri Lankan commercial banks
Buseruka Equity: Hydromax Limited (Uganda, 100%) DN N 0Debt: African Preferential Trade Area Bank (PTA), AfDB
ABSA = South African commercial bank; AfDB = African development Bank; AIIF = African Infrastructure Investment Fund; BWSC = Danish engineering company now owned byMitsui; CDC = Commonwealth Development Corporation; DEG = German Investment and Development Corporation; DFIs = development finance institutions; DN = direct negotiation;EAIF = Emerging Africa Infrastructure Fund; EIB = European Investment Bank; EKF = Eksport Kredit Fonden—Danish export credit fund; FMO = Netherlands Development FinanceCompany; GETFiT = global energy transfer feed-in-tariff; ICB = international competitive bid; IDA = International Development Association; IFC = International Finance Corporation;IFU = Danish Investment Fund for Developing Countries; IPS = Industrial Promotion Services; IPS-AKFED = Industrial Promotion Services Aga Khan Fund for Economic Development;IPTL = Independent Power Tanzania Ltd; KfW = German Development Bank; KP & P = Company registered in the Netherlands to develop the Lake Turkana Wind project; KPLC =Kenya Power and Lighting Company; OPEC = Organization of the Petroleum Exporting Countries; OPIC = Overseas Private Investment Corporation; REFiT = renewable energy feed-in-tariffs; RMB = Rand Merchant Bank; TANESCO = Tanzania Electric Supply Company; YFP = Yinka Folawiyo Power.
a Shareholders—particularly those with technical expertise—are often prohibited (by lenders) from selling until after commercial operation.b The balance of four Ugandan IPPs (Kilembe Mines aka Mubuku I, Kakira, Kinyara, and Kasese Cobalt aka Mubuku III), not included in the table above, were developed to source
electricity to the mining/sugar industries and have evacuated excess power to the national grid. Also not included are the eight GETFiTs and two solar ICBs for which financial close wasimminent but not yet complete in 2014.
A. Eberhard et al. Energy Policy 108 (2017) 390–424
395
In most cases, IPP contracts extend over a long period of time; thetypical contract is for 15–30 years. This long time frame is consideredboth a strength and a weakness. Predictable revenue streams allowequity risk capital to be rewarded, and sponsors can also service debtwith long tenors. Conversely, in an environment of power marketreform, both parties can encounter problems with fixed long-term take-or-pay contracts if the various conditions under which the contracts areagreed upon change. Governance frameworks, which shape the degree
of predictability and risk in the sector, ultimately impact on investmentand development outcomes.
4.4. Risk mitigation
At the crux of the investment conundrum is the security of revenueflows and hence the financial viability of the off-taker – usually thenational utility. Many African utilities have poor credit ratings andperform inefficiently (Eberhard and Shkaratan, 2012). Average dis-tribution losses in Sub-Saharan Africa are 23%, compared with thecommonly used norm of 10% or less in developed countries. Moreover,average collection rates are only 88.4% compared with the best practiceof 100%. Combining the costs of distribution losses and uncollectedrevenue, expressed as a percentage of utility turnover, provides ameasure of a utility's inefficiency. In Africa, this efficiency is equivalent,on average, to 50% of turnover (Eberhard et al., 2011).
At the sector level, governance reforms targeting ownership andshareholder quality, managerial and board autonomy, accountingstandards, performance monitoring, outsourcing, labour markets andcapital market discipline can critically improve the performance ofstate-owned utilities. Most utilities in Sub-Saharan Africa meet onlyabout half of the criteria for good governance. At the operational level,practices targeting technical and commercial efficiency will amelioratethe financial standing of a utility in a short period of time (Eberhardand Shkaratan, 2012). Such actions become increasingly important as autility approaches an IPP transaction, since these directly affect itsability to honour payment obligations.
Given the performance of most state-owned utilities in SSA, credit
Fig. 7. Total investment by IPPs and by Development Finance Institutions: Sub-SaharanAfrica (Excluding South Africa), 1994 – 2014. Note: DFI = development financeinstitution; IPP = Independent Power project;.
Fig. 8. Electricity sector structures in Sub-Saharan Africa, 2014. Note: includes vertical integration or unbundling of generation (G), transmission (T), and distribution (D) andpresence of IPPs. CAR = Central African Republic; DRC = Democratic Republic of Congo; IPP = independent power project; PSP = Private Sector Participation.
A. Eberhard et al. Energy Policy 108 (2017) 390–424
396
enhancement and risk mitigation – including payment and terminationrisks - are therefore important for attracting IPP investment in SSA.Robust PPAs – most often denominated in US dollars or euros - havebecome a requirement for new investors seeking to safeguard paymentstreams. Risks can furthermore be reduced through governance reforms;providing investor certainty around planning, procurement and con-tracting; through the involvement of development finance institutions;ring-fenced revenue, escrow accounts, letters of comfort and credit,guarantees, put-call options on termination; and political insurance. Ouranalysis of IPPs shows that significant de-risking is necessary to attractprivate equity and debt-providers (Eberhard et al., 2016).
DFI involvement, in particular, has played a critical role in bringingIPPs to financial close. DFIs appear to “crowd-in” private investments bytheir ability to exercise pressure on the host government to honourcontracts, as well as their offering risk mitigation products such asguarantees and insurance.c As a result, we have seen very few IPPs actuallyunravelling, and a renegotiation of contractsd (after the PPA was signed) inonly eight of the 27 IPPs in Kenya, Nigeria, Uganda and Tanzania.
Of the 47 IPPs that have reached financial close between 1990 and2015 in these four case study countries, 29 have some form or anotherof DFI involvement. 18 of these projects have received direct DFIinvestment totalling US$ 2 198 million through equity or loans,representing on average 47% of the total investment for these projects.While five IPPs have some form of “foreign” guarantee or riskinsurance in place, 12 projects have benefitted from some form ofODA grant (Eberhard et al., 2016). It is thus clear that for the majorityof IPPs in the case study countries, DFI's played a significant role,either through the use of risk mitigation products or, primarily,through actually investing in these projects.
4.5. Performance of five case study countries
Fig. 11 provides a visual breakdown of the number of IPPs percountry (excluding South Africa). Of the present pool of 58 IPPs thathave reached financial close, Kenya and Uganda have the highestnumber.e It is noteworthy that three-quarters of the projects in thesetwo countries have closed within the past three years. Thus, more than50% of the total IPP pool, in terms of number of projects, isconcentrated in two countries and is relatively new. The balancedeveloped slowly over the two decades since the first large-scale IPPreached financial close in 1994 in Côte d′Ivoire.
Table 2 below provides a summary of some of the key power sectorfeatures in the five case study countries.
Of the five countries, South Africa clearly has the best investmentclimate, a policy for expanding renewable energy, a power plan linkedto a series of competitive tenders, and a set of standardized contractsbacked by a sovereign guarantee. The country has an independentregulator, although its decisions have not always been consistent. Itcould be argued that utility tariffs do not fully reflect costs; never-theless, the regulator has mandated the full pass-through of IPP costs.The consequence has been a highly successful IPP program where moremegawatts and investment have been contracted in four years than inthe previous two decades across the rest of Sub-Saharan Africa.Remarkably, this has been achieved within an electricity sector thatis dominated by a large state-owned vertically integrated utility thatrelies mostly on coal and once was not receptive to IPPs.
Kenya has an investment climate that is better than that ofneighboring Tanzania and Uganda, as well as Nigeria, and has beenable to attract private investment at a lower cost than these countries.
Fig. 9. Comparison of price outcomes for Medium-Speed Diesel and Solar PV in SSA.Note: ICB – International Competitive Bid, DN – Directly Negotiated, REFiT –
Renewable Energy Feed-In Tariff, MSD – Medium-Speed Diesel, PV – Photovoltaic.
Fig. 10. Competitive tenders vs. directly negotiated projects, excluding South Africa,1994 – 2014 (MW). DN = direct negotiation; ICB = international competitive bid; MW =megawatts.Source: Based on authors’ calculations.
Fig. 11. Number of Independent Power Projects in Sub-Saharan Africa by country (excl.South Africa). 1994 – 2014.Source: Compiled by authors, based on utility data, primary sources, and the PPIdatabase.
c While risk mitigation has been critical to attract private investment to IPPs, in noproject have guarantees of any sort been invoked, including projects whose contractsultimately unraveled.
d Such changes vary, from a scaling back of project size, to a reconfiguration of theproject in its entirety. Further changes have included the rolling back or elimination ofcertain security arrangements to reduce the financial liability of the state-owned utility. Itshould be noted that changes occurred in what might be termed the first wave of IPPs inSub-Saharan Africa – which may signal there has been a learning process.
e Projects included in this tally are all grid-connected IPPs with a capacity of 5MW andgreater. A complete list is provided in Appendix 1. While Zimbabwe has three hydro-power IPPs, these projects are all under 5MW and are therefore excluded here.
A. Eberhard et al. Energy Policy 108 (2017) 390–424
397
Its electricity sector has been unbundled, it has an independentregulator, and it once had a clear power-planning process and acompetent procurement capability in the Kenya Power and LightingCompany (KPLC), the T &D company. The regulator has helped movetariffs to cost-reflective levels, and the KPLC has been reasonablycreditworthy. The consequence is a series of competitive procurementswith steadily better price outcomes.
Tanzania on the other hand has a weaker investment climate, someambivalence around private sector investment, a vertically integratedstate-owned utility with technical and financial performance chal-lenges, and poor planning and procurement practice—despite a reg-ulator that seeks to encourage more transparent and competitiveprocurement. Tanzania has relied more on unsolicited bids and directnegotiations than on competitive tenders. As a result, some IPPs herestand out for their high prices and controversial contracts.
Uganda's recent success has relied less on its overall investmentclimate and more on a clear power sector structure and a recentcompetitive tendering program for small renewable energy powerplants. With its power sector unbundled, IPPs contract directly withthe transmission company, free of conflicts with state-owned genera-tion, and the privately concessioned distribution company is increas-ingly more effective in reducing losses and improving its financialviability. The dedicated global energy transfer feed-in-tariff (GETFiT)intervention has provided transaction advice and support for runningcompetitive tenders coupled with standardized contracts. It remains tobe seen whether this initiative can be sustained in the future.
Nigeria's investment climate is challenging; its previous successwith IPPs had less to do with a clear policy framework and more withstrong political will at the highest levels. A protracted and torturouspower sector reform process—including full unbundling, privatization,and, eventually, competition—has, in the short term, probably made itharder to secure investments in new IPPs. It is hoped that, eventually,the reform process will improve the financial viability of the sector, andthe Nigerian Bulk Energy Trader (NBET) will become a dependableand attractive off-taker for IPPs.
This analysis of the case study countries reveals no single orconsistent element that guarantees IPP investment. Planning andcompetitive procurement practices are important; creditworthiness ofoff-taker utilities is also critical, but policy makers should not lose sightof the broader investment, policy, and regulatory climate.
5. Renewable energy technologies are breaking through
The majority of IPPs in Africa have historically been thermal, mainly
gas or diesel plants. However, we are seeing rapid growth in grid-connected renewable energy capacity, especially wind and solar. TheSouth African Renewable Energy Independent Power ProducerProcurement Programme (REIPPPP) is an important illustration of this,with more than 6327 MW of renewable energy contracted in 4 years,across 92 projects, with an investment of more then US$19 billion(Eberhard et al., 2016, 2014). South Africa has added more renewableenergy capacity and IPP projects in this short period of time, than the restof Sub-Saharan Africa has in more than 20 years. Over four bid rounds,prices fell 46% for wind energy and 71% for solar PV to levels lower thanthe utility's average cost of supply (Eberhard and Kåberger, 2016).
While South Africa clearly leads the region in terms of renewableenergy IPPs, it is important to note that this trend is not limited to asingle country. Fig. 12 below provides an overview of renewable energycapacity (excluding hydro) from 2006 to 2015 for Sub-Saharan Africa,clearly showing a significant increase in capacity beyond South Africa.
Most of the new RE capacity in the region has been contracted inSouth Africa, through the competitive procurement program(REIPPPP). Looking beyond South Africa, it is clear that theREIPPPP is having a signficant regional impact, with eight Sub-Saharan African countries officially having developed renewable energyauction policies by 2015 (REN21, 2016). This is a significant develop-ment given that, apart from South Africa, there were no competitiveprocurement programmes for renewable energy in the SSA region in
Fig. 12. Renewable Energy Installed Capacity (megawatt) in Africa, 2006 – 2015. Note:Excludes hydropower; SSA = Sub-Saharan Africa; SA = South Africa;.Source: Compiled by authors based on IRENA Annual Renewable Energy Statistics.
Table 2Summary of power sector features in case study countries.Source: Compiled by authors, based on various primary and secondary source data.
Country Unbundledutility
Privatizedutility
Wholesalecompetition
Independentregulator
Least-cost power developmentplan (LCPDP)
Predominant procurementpractices
South Africa No No No Yes Integrated Resource Plan for 2010–2030 out of date
Competitive
Kenya Yes No No Yes LCPDP based on stakeholderconsultations
Competitive
Tanzania No No No Yes Electricity Supply Mostly direct negotiationsReform Strategy and Roadmap,2014–2025; LCPDP, 2013
(some previous tenders with limitedcompetition)
Uganda Yes Partiala No Yes 2011 Power Sector Investment Plannot updated
Direct negotiations until advent ofGETFiT (hybrid feed-in tariff withcompetitive tenders)
Nigeria Yes Yes Transitional market Yes System operator is mandated toprepare a power master plan but hasnot been updating it
Direct negotiations
Note.a Uganda’s main distribution utility is concessioned to a private company, as is the previous state generation utility. Transmission remains public. There are also some small private
regional concessions not connected to the main transmission grid. GETFiT = global energy transfer feed-in-tariff.
A. Eberhard et al. Energy Policy 108 (2017) 390–424
398
2011 (REN21, 2012).The Ugandan GETFiT program further illustrates the growth in
competitively procured renewable power. In 2013, KfW assisted theUgandan Regulatory Authority to develop the GETFiT to incentivisenew investments, aiming to add 170 MW to the country's 840 MWinstalled capacity (in 2013) (Meyer et al., 2015). The primary GETFiTmechanism is a grant-based premium payment at the REFiT level toclose the gap with the levelised cost of electricity (LCOE) for eligibletechnologies, namely small hydropower, biomass, bagasse, and solarPV. A competitive tender run in 2014 for four 5 MW solar PV plantsdelivered an average levelised tariff of US$c 16.37/kWh – lower thanthe average retail tariff of US$c 16.6/kWh in 2013 (Meyer et al., 2015).
Furthermore, Zambia's very recent experience with solar PV IPPscould be a technological game-changer for the continent: through theIFC's Scaling Solar program, two 50 MW solar PV projects were put outto tender. The lowest winning bid came in at US$c 6.02/kWh – a newrecord for Africa. The tariffs are fixed (non-indexed) for the 25-yearcontract period (International Finance Corporation, 2016).
These are but two examples outside of South Africa in the region.Scaling Solar is set to soon being rolled out in Madagascar, Senegal andEthiopia (Eckhouse, 2016; Sibanda and MacInnis, 2016). Ghana andBurkina Faso concluded RE auction rounds in 2016, and Botswana,Namibia, Ethiopia and Senegal launched pre-qualification or proposalsubmission stages for their respective auction programmes in the sameyear. Kenya and Nigeria are additionally in the process of developingauction programmes and more countries are soon to follow. While themajority of renewable energy projects on the continent contracted inthe past 3 years remain based on feed-in tariffs or directly negotiateddeals, this surge in competitive procurement programmes seems toindicate a noteworthy shift.
Given these trends, the renewable energy sector is set to grow anddiversify on the continent, with major additions in especially wind,solar PV and geothermal generation projected to come online in thenext few years (Marks et al., 2016; Quitzow et al., 2016).
6. Conclusion and policy implications
As demonstrated by the data on investment trends reported in thispaper, IPPs make an important and growing contribution to meetingSub-Saharan Africa's power needs. These projects are concentrated in afew countries, but there is scope to widen private investment across thecontinent. Current experience with IPPs on the continent offersimportant lessons for how this can be done (Eberhard et al., 2016).
Previously published research on critical success factor for IPPsincludes a range of country specific factors (investment climate, powersector policies and regulation, effective planning and competitiveprocurement) and project specific factors (well structured, bankableprojects with experienced sponsors and debt providers, robust PPAs,risk mitigation and security measures, and strategic project manage-ment) (Eberhard and Gratwick, 2011).
An analysis of the case study countries that have had the mostsuccess in attracting IPPs in Sub-Saharan Africa, suggests that while allof the above success factors are important, more emphasis needs to beplaced on dynamic power planning, competitive procurement practicesand adequate contracting capacity. Power planning cannot be neglectedand is an essential first step towards greater private sector powerinvestment. Sound planning means that countries are able to projectfuture electricity demand correctly, decide on least-cost supply options,and anticipate how long it would take to procure, finance, and build therequired generation capacity. Planning tools must be updated fre-quently and new build opportunities should be allocated betweenpublic and private generators on the basis of clear criteria. Finally,there must be an explicit link between planning and the timely
initiation of international competitive bids or auctions for long-termcontracts for new power. Without these policy tools, capacity andreforms, a country is unlikely to see new privately financed powergeneration capacity.
IPP investments in Africa will rely on long-term contracts with off-takers. Competitive tenders for these long-term contracts – also calledcompetition for the market - more often than not result in betterinvestment and price outcomes than feed-in-tariffs or directly nego-tiated projects. This is especially true for standardised technologiessuch as renewable energy, diesel-generation and heavy-fuel oil gen-erators. Competitive tenders are also more transparent, leading to lesscorruption. The use of standard contracts in competitive tendersfurthermore result in a fair allocation of risk. And projects are morelikely to move to financial close, construction and commercial opera-tion. Competitive procurement has also been shown to lead to thedevelopment of a pipeline of bankable projects, especially for renew-able energy.
More competitive tenders should be run in a greater number ofcountries, both for standard thermal technologies as well as for othertechnologies and contexts where competition is possible. While thecosts of running a competitive procurement program might be higherthan those involved in directly negotiated projects, these are justifiedby the lower prices achieved. If directly negotiated projects are to beused, governments need to build capacity to ensure that they offervalue for money, and that the project developers have the requiredtechnical and financial capabilities.
IPP contracts should be undertaken with financially viable off-takers, whether these be utilities or large customers. Secure revenueflows are essential for ensuring the bankability of IPPs, most of whichare project-financed. While credit-enhancement and security measurescan mitigate some of this risk, the ultimate goal for host governmentsand development partners should be the improved performance of off-takers (in most cases utilities) as sustainable solution.
The case studies demonstrate that Development FinanceInstitutions are playing an important role in IPP financing and riskmitigation. The mere presence of these institutions seems to attractprivate sector interest, particularly due to their ability to exercisepressure on host governments to honour commitments. However, careshould still be taken to ensure that where adequate commercialfinancing appetite exists, DFIs are not taking on more than theirappropriate share of financing volume.
A further notable conclusion of the paper is that IPPs have beendeveloped in countries with very different power sector structures andlevels of reform. This conclusion does not imply that power sectorreform is unimportant but it does underline the relevance of additionalfactors, noted above, in accelerating investment in IPPs. In developingcountries in Sub-Saharan Africa, some reforms may be more importantthan others. Clearly full wholesale or retail competition is not a pre-condition for private investment in power. But clear policy and effectiveregulatory frameworks are important for securing market entry,revenue flows and contract prices. And the separation of state-ownedgeneration companies from the main transmission system (as inKenya) provides a level-playing for IPPs and more investment certaintyand confidence.
Finally, we have noted the extent to which renewable energy IPPsare breaking through and can be competitively procured. The signifi-cant renewable energy price reductions evidenced by the latest auctionsclearly show that renewable energy can compete with fossil-fuel basedsources and in many countries solar and wind energy are now thecheapest sources of power. This has significant implications for how thecontinent's relatively undeveloped power systems are designed. MostAfrican countries have excellent solar resources, and many have goodwind resources as well. But solar and wind energy are also variable and
A. Eberhard et al. Energy Policy 108 (2017) 390–424
399
need to be complemented with flexible resources. This calls for a re-evaluation of the role of utilities and power markets in balancing thesystem and contracting appropriate back-up and auxiliary services.
In conclusion, investment in African IPPs is growing, but not fastenough. Africa does not have sufficient power. All sources of invest-ment need to be encouraged. For IPPs to flourish, Africa needsdynamic, least-cost planning, linked to the timely initiation of thecompetitive procurement of new generation capacity. This must beaccompanied by the building of effective regulatory capacity thatencourages the distribution utilities that purchase power to improvetheir performance and prospects for financial sustainability – and to
widen access to electricity. IPP investment require appropriate riskmitigation, often helped by the participation of development financeinstitutions. Renewable energy are breaking through and competitiveprices are being achieved in auctions for new power. Such effortspromise to promote sustainable economic and social developmentacross the continent.
Acknowledgements
This paper is based, in part, on research supported by the WorldBank (UPI00217304).
Appendix A. Independent Power Projects in Sub-Saharan Africa
See:Tables A1–A18.
Table A1IPP investments in Angola by project.
Project Information Project Name Project Name2Chicapa Hydroelectric Plant Biocom (Malange)
Capacity (MW) 16 30Technology Hydro, Small ( < 20 MW) Waste/bagasseTotal Investment (US$ Million) 45.0 89.8Year of financial closure 2003 2014COD 2008Project status Operational OperationalProcurement method Direct Negotiation (DN) DNNumber of bidsContract period 40Contract type Build-Operate-Transfer (BOT)Sponsors/Developer ALROSA Co. Ltd. (The Almazy Rossii-Sakha Company) (55%/Russian Federation)EPCFuel arrangementDebt-equity RatioLocal shareholder equity (Entity, US$ Million)Foreign shareholder equity (Entity, US$ Million)DFI Agency and financing methodTotal DFI financing (US$ Million)ODA Grants (US$ Million)Local credit enhancements & security arrangementsForeign credit enhancements & security arrangements
Table A2IPP investments in Cameroon by project.
Project Information Project Name Project Name2Dibamba Power Plant Kribi Power Plant
Capacity (MW) 88 216Technology HFO/MSD CCGTTotal Investment (US$ Million) 126.0 342.0Year of financial closure 2009 2010COD 2009 2013Project status Operational OperationalProcurement method DN DNNumber of bidsContract period 20 20Contract type BOT BOTSponsors/Developer AES Corporation (56%/United States), Republic of
Cameroon (44%)KPDC was 56% owned by AES, with the remaining 44% in the hands of theCameroon government, built by Finland's Wartsila, running on natural gas from theoff-shore Sanaga-South field operated by Cameroon's state oil company, SNH, andindependent producer Perenco - the first major commercial development ofCameroon's substantial gas reserves. In Nov 2013, AES announced it would sell itsstake in Cameroon to Actis (Globeleq parent company), a global pan-emergingmarket investor, for $220 million of net equity proceeds. Sale was completed in2014.
(continued on next page)
A. Eberhard et al. Energy Policy 108 (2017) 390–424
400
Table A3IPP Investments in Cape Verde by Project.
Project Information Project NameElectra Cabeolica Wind Project
Capacity (MW) 25.5Technology Wind, OnshoreTotal Investment (US$ Million) 80.0Year of financial closure 2010COD 2010Project status OperationalProcurement methodNumber of bidsContract period 20Contract type Build-Own-Operate (BOO)Sponsors/Developer Electra (Cape Verde), Africa Finance
Corporation (Nigeria)EPCFuel arrangementDebt-equity RatioLocal shareholder equity (Entity, US$
Million)Foreign shareholder equity (Entity, US
$ Million)DFI Agency and financing method EIB (Loan/$39 Million/2010), AFDB
(Loan/$19 Million/2010)Total DFI financing (US$ Million) 58.0ODA Grants (US$ Million)Local credit enhancements & security
arrangementsVariable government payments
Foreign credit enhancements &security arrangements
Table A2 (continued)
Project Information Project Name Project Name2Dibamba Power Plant Kribi Power Plant
EPC WartsilaFuel arrangement HFO/Tolling agreement with AES Sonel as Toller A gas supply agreement has been signed with a state-owned gas supplier.Debt-equity Ratio 75/25Local shareholder equity (Entity, US
$ Million)Foreign shareholder equity (Entity,
US$ Million)DFI Agency and financing method IFC (Loan/$31 Million/2010), AFDB (Loan/$31
Million/2010), (FMO Loan/$31 Million/2010)AFDB (Loan/$57 Million/2011), EIB (Loan/$41 Million/2012), Other (Loan/$23Million/2012), IDA (Guarantee/$82 Million/2012), IFC (Loan/$77 Million/2012)
Total DFI financing (US$ Million) 93.0 198.0ODA Grants (US$ Million)Local credit enhancements &
security arrangementsSovereign guarantee
Foreign credit enhancements &security arrangements
Typical project finance security agreementsimplemented but details not made public
WB PRG (enabled local bank participation)
A. Eberhard et al. Energy Policy 108 (2017) 390–424
401
Table
A4
IPPinvestmen
tsin
Côted′Ivo
ireby
project.
Pro
ject
Info
rmation
Pro
ject
Nam
ePro
ject
Nam
e2
Pro
ject
Nam
e3
Pro
ject
Nam
e4
Pro
ject
Nam
e5
Pro
ject
Nam
e6
Com
pagnie
Ivoiriennede
Pro
duction
d′E
lectricite
(CIP
REL)
Com
pagnie
Ivoiriennede
Pro
duction
d′E
lectricite
(CIP
REL)
Azito
PowerPro
ject
Com
pagnie
Ivoiriennede
Pro
duction
d′E
lectricite
(CIP
REL)
Azito
Power
Pro
ject
Com
pagnie
Ivoiriennede
Pro
duction
d′E
lectricite
(CIP
REL)
Cap
acity(M
W)
9911
128
811
114
611
1Technolog
yOCGT
OCGT
OCGT
OCGT
OCGT+CCGT
OCGT+CCGT
Total
Investmen
t(U
S$Million
)10
8.0
134.0
223.0
134.0
207.0
134.0
Yearof
finan
cial
closure
1994
1997
1999
2009
2013
2013
COD
1995
2000
Project
status
Operational,Planning/reached
finan
cial
closure
Operational,Planning/reached
finan
cial
closure
Operational
Operational
Under
Con
struction
Reach
edfinan
cial
close
Procu
remen
tmethod
DN
DN
Intern
ational
Com
petitiveBid
(ICB)
DN
ICB
DN
Numbe
rof
bids
3Con
tractperiod
1924
Con
tracttype
Build-O
wn-O
perateTransfer
(BOOT)
BOOT
Spon
sors/D
evelop
erSA
UR
Intern
ational,with88
%(Joint
Ven
ture
(JV)be
tweenFrench
SAUR
Groupow
ned
byBou
ygues,65
%an
dEDF,35
%)BOAD,PROPARCO,and
IFCholdingtheremaining12
%;in
2005
allsh
ares
sold
toBou
ygues
(France,98
%),exceptBOAD
(2%)
SAUR
Intern
ational,with88
%(JV
betw
eenFrench
SAUR
Groupow
ned
byBou
ygues,65
%an
dEDF,35
%)
BOAD,PROPARCO,andIFCholding
theremaining12
%;in
2005
allshares
sold
toBou
ygues
(France,98
%),
exceptBOAD
(2%)
Globe
leq(77%
/United
Kingd
om),Aga
Khan
Fund
(Switzerlan
d)
SAUR
Intern
ational,with88
%(JV
betw
eenFrench
SAUR
Groupow
ned
byBou
ygues,65
%an
dEDF,35
%)
BOAD,PROPARCO,andIFCholding
theremaining12
%;in20
05allshares
sold
toBou
ygues
(France,98
%),
exceptBOAD
(2%)
SAUR
Intern
ational,with88
%(JV
betw
eenFrench
SAUR
Groupow
ned
byBou
ygues,65
%an
dEDF,35
%)
BOAD,PROPARCO,andIFCholding
theremaining12
%;in
2005
allshares
sold
toBou
ygues
(France,98
%),
exceptBOAD
(2%)
EPC
Fuel
arrangemen
tGov
ernmen
tprocu
resfuel
Gov
ernmen
tprocu
resfuel
Gov
ernmen
tprocu
resfuel
Gov
ernmen
tprocu
resfuel
Gov
ernmen
tprocu
resfuel
Gov
ernmen
tprocu
resfuel
Deb
t-eq
uityRatio
70/3
0Local
shareh
older
equity(E
ntity,US$
Million
)Foreign
shareh
older
equity(E
ntity,US$
Million
)DFIAgency
and
finan
cingmethod
BOAD
(Loa
n/$
9Million
/199
4),IFC
(Loa
n/$
18Million
/199
5),IFC
(Equ
ity/$1Million
/199
5),IB
RD
(Loa
n/$
80Million
/199
5)
AFDB(Loa
n/$
14Million
/19
98),ID
A(G
uaran
tee/$30
Million
/199
9),IFC(Loa
n/$
41Million
/199
9),IFC
(Syn
dication/$
31Million
/19
99)
IFC,AfD
Ban
dPROPARCO
Total
DFIfinan
cing
(US$
Million
)10
8.0
–11
6.0
––
–
ODA
Grants
(US$
Million
)Local
cred
iten
han
cemen
ts&
secu
rity
arrangemen
ts
Sovereigngu
aran
tee,
Escrow
accounteq
uivalen
tto
1mon
thcapacitych
arge
Foreign
cred
iten
han
cemen
ts&
secu
rity
arrangemen
ts
World
Ban
kPRG
A. Eberhard et al. Energy Policy 108 (2017) 390–424
402
Table A5IPP investments in Gambia by project.
Project Information Project NameBrikama
Capacity (MW) 25Technology HFO+MSD/HFOTotal Investment (US$ Million) 36.2Year of financial closure 2005COD 2006Project status OperationalProcurement methodNumber of bidsContract periodContract typeSponsors/Developer Global Electric Company
(GEG)EPCFuel arrangementDebt-equity RatioLocal shareholder equity (Entity, US$ Million)Foreign shareholder equity (Entity, US$
Million)DFI Agency and financing methodTotal DFI financing (US$ Million) –
ODA Grants (US$ Million)Local credit enhancements & security
arrangementsForeign credit enhancements & security
arrangements
A. Eberhard et al. Energy Policy 108 (2017) 390–424
403
Table
A6
IPPinvestmen
tsin
Ghan
aby
project.
Pro
ject
Info
rmation
Pro
ject
Nam
ePro
ject
Nam
e2
Pro
ject
Nam
e3
Pro
ject
Nam
e4
Pro
ject
Nam
e5
Takora
di2
Sunon-A
sogliPowerPlant
CENIT
Energ
yTakora
di2
KponeIP
P
Cap
acity(M
W)
220
200
126
110
350
Technolog
yOCGT/C
CGT
OCGT+CCGT
OCGT+CCGT
OCGT+CCGT
CCGT
Total
Investmen
t(U
S$Million
)11
0.0
200.0
140.0
330.0
900.0
Yearof
finan
cial
closure
1999
2007
2009
2013
2014
COD
2000
2011
2012
2014
x20
17Project
status
Operational
Operational
Operational
Under
construction
Finan
cial
close
Procu
remen
tmethod
DN
DN
DN
DN
Numbe
rof
bids
Con
tractperiod
25Con
tracttype
BOOT
BOO
BOO
Spon
sors/D
evelop
erCMS(U
SA,90
%),VRA
(Ghan
a,10
%),CMSsold
shares
toTAQA(U
AE,9
0%)in
2007
Shen
zenElectric(60%
/China),ChinaAfrica
Develop
men
tFund
(CADfund)(40%
/China)
Gecad
(100
%/U
nited
States)
CMS(U
SA,90
%),VRA
(Ghan
a,10
%),CMSsold
shares
toTAQA
(UAE,90
%)in
2007
AfricaFinan
ceCorporation(A
FC)(31,85
%),
Cen
Pow
erHoldings
Lim
ited
(21%
),a
consortium
ofGhan
aian
investors,
Sumitom
oCorporation(28%
),Mercu
ryPow
er(15%
),an
dFMO
(4,15%
)EPC
Mitsu
i&
Co(Jap
an)an
dKEPCO
E&C(K
orea),
Mitsu
i&
Co(Jap
an)an
dKEPCO
E&C(K
orea),
Fuel
arrangemen
tGov
ernmen
tprocu
resfuel
Interim
fuel
agreem
entfor
access
toWAGPga
sGov
ernmen
tprocu
resfuel
Deb
t-eq
uityRatio
72/2
8Local
shareh
older
equity
(Entity,US$
Million
)Local
strategicinvestor,
Tog
beAfedeXIV
Foreign
shareh
older
equity(E
ntity,US$
Million
)DFIAgency
andfinan
cing
method
IFC(Loa
n/$
60Million
/200
4)Other
(Loa
n/$
67Million
/20
08),Other
(Quasi-eq
uity/
$10
Million
/200
8),AFDB
(Loa
n/$
32Million
/201
1)
IFC,an
daconsortium
ofintern
ational
develop
men
tfinan
ceinstitution
sledby
FMO.Thelendersparticipatingin
the
consortium
includetheAfrican
Develop
men
tBan
k,Deu
tsch
eInvestitions-undEntw
icklungsgesellschafte,
EmergingAfricaInfrastructure
Fund,IC
F-D
ebtPoo
lan
dProparco.TheOpec
FundforIntern
ational
Develop
men
tan
dtheCan
adaClimateChan
geProgram
areparticipating
alon
gsideIFC
FMO(equ
ity,
$10
,3million
),DBSA
(loa
n,$
53million
),OFID
(loa
n,$7million
),EAIF
($25
million
),FMO
(loa
n,$24
million
),an
dothers
Total
DFIfinan
cing(U
S$Million
)60
.0–
109.0
347.5
207.0
ODA
Grants
(US$
Million
)Local
cred
iten
han
cemen
ts&
secu
rity
arrangemen
ts
Sovereigngu
aran
tee(phase1),
US$
3million
Letterof
Credit
provided
bygo
vern
men
t(phase1)
Variablego
vern
men
tpaymen
ts
Foreign
cred
iten
han
cemen
ts&
secu
rity
arrangemen
ts
A. Eberhard et al. Energy Policy 108 (2017) 390–424
404
Table
A7
A:IPPinvestmen
tsin
Ken
yaby
project.
Pro
ject
Info
rmation
Pro
ject
Nam
ePro
ject
Nam
e2
Pro
ject
Nam
e3
Pro
ject
Nam
e4
Pro
ject
Nam
e5
Pro
ject
Nam
e6
Mom
basa
Barg
e-M
ounted
PowerPro
ject/W
estm
ont
Ibera
fricaPowerLtd
.Kip
evu
II/T
savo
Orm
atOlkariaIIIGeoth
erm
al
PowerPlant,
OrP
ower4
(phase
1and2and3)
Ibera
fricaPowerLtd
.M
um
iasPower
Plant
Cap
acity(M
W)
4644
7513
1226
Technolog
yOCGT
MSD
/HFO
MSD
/HFO
Geo
thermal
MSD
/HFO
Waste
Total
Investmen
t(U
S$Million
)65
.050
.386
.010
5.0
13.7
50.0
Yearof
finan
cial
closure
1996
1996
1999
1999
1999
2008
COD
1997
1997
2001
2000
,20
0920
0020
09Project
status
Con
cluded
Operational
Operational
Operational
operational
Operational
Procu
remen
tmethod
DN
DN
ICB
ICB
DN
DN
Numbe
rof
bids
32
Con
tractperiod
77
2020
15Con
tracttype
BOO
BOO
BOO
BOO
BOO
BOO
Spon
sors/D
evelop
erWestm
ontLtd.(M
alaysia)
UnionFen
osa(Spain,80
%),
KPLCPen
sion
Fund(K
enya,
20%)since
1997
Cinergy
&IP
Sjointlyow
ned
49.9%
,Cinergy
sold
toDuke
Energy
in20
05,
CDC/G
lobe
leq(U
K,30
%),Wartsila
(Finland,15
%),IFC(5%)retain
remainingsh
ares
since
2000
Orm
atTurbines
Ltd
(100
%/Israel)
UnionFen
osa(Spain,80
%),
KPLCPen
sion
Fund(K
enya,
20%)since
1997
MumiasSu
gar
Com
pan
yLim
ited
(100
%/K
enya)
EPC
Fuel
arrangemen
tOriginally
Westm
ontto
procu
refuel
andthen
passthrough
toutility,
how
ever,follow
ingdispute
withfuel
supplier
abou
ttaxesafterthefirst
year
ofop
eration,utility
took
over
procu
remen
t
Iberafrica
buys
fuel
andpasses
cost
through
toKPLCba
sedon
theunitsgenerated
andsp
ecific
consu
mption
param
etersag
reed
onin
thePPA
Tsavo
buys
fuel
andpassescost
through
toKPLCba
sedon
theunits
generated
andsp
ecific
consu
mption
param
etersag
reed
onin
thePPA
Theon
lyfuel
arrangemen
tper
seis
that
OrP
ower4was
gran
teda
Geo
thermal
Resou
rceLicen
sefrom
the
govern
men
t,to
whichitpaysaroyalty
ofsorts(ofUS$
.004
/kWhor
USc
.4/
kWh)
Iberafrica
buys
fuel
andpasses
cost
through
toKPLCba
sedon
theunitsgenerated
andsp
ecific
consu
mption
param
etersag
reed
onin
thePPA
Deb
t-eq
uityRatio
72/2
878
/22
Local
shareh
older
equity
(Entity,US$
Million
)KPLCStaffPen
sion
Fund(U
S$9.4in
directloan
san
dgu
aran
teed
US$
5million
through
alocalKen
yanba
nk).
9.45
Foreign
shareh
older
equity
(Entity,US$
Million
)UnionFen
osa(Spain)(U
S$12
.7million
indirectloan
san
dgu
aran
teed
US$
20million
);
9.48
Orm
at(100
%)since
1998
-UNTIL
2008
DFIAgency
andfinan
cing
method
IFC(Loa
n/$
18Million
/200
0),IFC
(Equ
ity/$2Million
/200
0),IFC
(Quasi-eq
uity/$3Million
/200
0),IFC
(Syn
dication/$
24Million
/200
0),IFC
(Riskman
agem
ent/$2Million
/200
1),
CDCow
naccount(U
S$13
million
);DEG
ownaccount(€
11million
),DEG
syndicated
(€2million
)
MIG
A(G
uaran
tee/$49
Million
/200
0),
MIG
A(G
uaran
tee/$70
Million
/200
2),
MIG
A(G
uaran
tee/$89
Million
/200
9),
(Guaran
tee/$11
0Million
/201
1)
Total
DFIfinan
cing(U
S$Million
)–
–82
.0–
––
ODA
Grants
(US$
Million
)–
––
––
–
Local
cred
iten
han
cemen
ts&
secu
rity
arrangemen
tsAnad
vance
paymen
tcash
dep
ositinitially,
butIberafrica
presentlyhas
nopaymen
tsecu
rity
Letterof
Com
fort
provided
bygo
vern
men
t,escrow
account,
equivalen
tto
1mon
thcapacitych
arge,
andastan
d-byLetterof
Credit,
equivalen
tto
3mon
thsbilling
Astan
d-byLetterof
Credit,covering
severalmon
thsbilling(althou
ghon
lyfinalized
aten
d–20
06)
Anad
vance
paymen
tcash
dep
ositinitially,
butIberafrica
presentlyhas
nopaymen
tsecu
rity
Paymen
tGuaran
tee
Foreign
cred
iten
han
cemen
ts&
secu
rity
arrangemen
tsMIG
Agu
aran
tee
A. Eberhard et al. Energy Policy 108 (2017) 390–424
405
Table
A7
B:IPPinvestmen
tsin
Ken
yaby
project.
Pro
ject
Info
rmation
Pro
ject
Nam
e7
Pro
ject
Nam
e8
Pro
ject
Nam
e9
Pro
ject
Nam
e10
Pro
ject
Nam
e11
Pro
ject
Nam
e12
RabaiPowerPlant
Orm
atOlkariaIIIGeoth
erm
al
PowerPlant,
OrP
ower4
(phase
1and2and3)
Ibera
fricaPowerLtd
.Orm
atOlkariaIIIGeoth
erm
al
PowerPlant,
OrP
ower4
(phase
1and2and3)
Trium
ph
HFO
Power
Plant
ThikaTherm
alPower
Pro
ject
Cap
acity(M
W)
9035
52.5
3683
87Technolog
yMSD
/HFO
&steam
cycle
Geo
thermal
MSD
/HFO
Geo
thermal
MSD
/HFO
MSD
/HFO
Total
Investmen
t(U
S$Million
)15
5.0
128.7
59.9
126.2
140.0
144.0
Yearof
finan
cial
closure
2008
2009
2009
2011
2012
2012
COD
2010
2009
2009
2013
2015
2013
Project
status
Operational
Operational
operational
Operational
Con
struction
Operational
Procu
remen
tmethod
ICB
DN
DN
DN
ICB
ICB
Numbe
rof
bids
45
9Con
tractperiod
2025
2020
Con
tracttype
BOOT
BOO
BOO
BOO
BOO
BOO
Spon
sors/D
evelop
erAldyw
ch:34
.%,BWSC
(Dan
ish,bu
tow
ned
byMitsu
iof
Japan
):25
.5%,
FMO:20
%,IFU
(Dan
ishbilateral
lender):
20%
Orm
atTurbines
Ltd
(100
%/Israel)
UnionFen
osa(Spain,80
%),
KPLCPen
sion
Fund(K
enya,
20%)since
1997
Orm
atTurbines
Ltd
(100
%/Israel)
Broad
Holding(K
enya),
Interpel
Investmen
ts(K
enya),Taceflex(K
enya),
SouthernInter-trad
e(K
enya)
Melec
Pow
ergen(partof
Maletec
grp)(90%
/Leb
anon
)
EPC
BWSC
Co-develop
er,sp
onsor,
shareh
older,EPCcontractoran
dO
&M
contractor
XJIntern
ational
EngineeringCom
pan
y(w
holly
owned
subsidiary
ofStateGridCorporation
ofChina)
MAN
Diesel(G
erman
y)an
dMatelec
Grp
Fuel
arrangemen
tFuel
Supply
Agreemen
twithKen
olof
Ken
yaIberafrica
buys
fuel
andpasses
cost
through
toKPLCba
sedon
theunitsgenerated
andsp
ecific
consu
mption
param
eters
agreed
onin
thePPA
Deb
t-eq
uityRatio
75/2
574
/26
75/2
5Local
shareh
older
equity(E
ntity,US$
Million
)Foreign
shareh
older
equity(E
ntity,US$
Million
)
Orm
at(100
%)since
1998
-UNTIL
2008
Orm
at(100
%)since
1998
-UNTIL
2008
DFIAgency
and
finan
cingmethod
Other
(Loa
n/$
126Million
/200
8),
DEG:15
%,FMO:25
%,EAIF:25
%,
Proparco:25
%,EFP(E
uropean
Finan
cingPartners):10
%
MIG
A(G
uaran
tee/$49
Million
/20
00),MIG
A(G
uaran
tee/$70
Million
/200
2),MIG
A(G
uaran
tee/
$89
Million
/200
9),EIB
(Loa
n/$
155
Million
/201
0),MIG
A(G
uaran
tee/
MIG
A(G
uaran
tee/$49
Million
/20
00),MIG
A(G
uaran
tee/$70
Million
/200
2),MIG
A(G
uaran
tee/
$89
Million
/200
9),EIB
(Loa
n/$
155
Million
/201
0),MIG
A(G
uaran
tee/
MIG
A(G
uaran
tee/$12
Million
/201
2),ID
A(G
uaran
tee/$45
Million
/20
12)
AFDB(Loa
n/E
uro
28Million
/20
12),IFC(Loa
n/E
uro28
Million
/201
2),ID
A(G
uaran
tee/$45
Million
/20
12),MIG
A(G
uaran
tee/$62
(con
tinued
onnextpage)
A. Eberhard et al. Energy Policy 108 (2017) 390–424
406
Table
A7(con
tinued
)
Pro
ject
Info
rmation
Pro
ject
Nam
e7
Pro
ject
Nam
e8
Pro
ject
Nam
e9
Pro
ject
Nam
e10
Pro
ject
Nam
e11
Pro
ject
Nam
e12
RabaiPowerPlant
Orm
atOlkariaIIIGeoth
erm
al
PowerPlant,
OrP
ower4
(phase
1and2and3)
Ibera
fricaPowerLtd
.Orm
atOlkariaIIIGeoth
erm
al
PowerPlant,
OrP
ower4
(phase
1and2and3)
Trium
ph
HFO
Power
Plant
ThikaTherm
alPower
Pro
ject
$11
0Million
/201
1)$11
0Million
/201
1)Million
/201
2)Total
DFIfinan
cing
(US$
Million
)12
6.0
155.0
––
–64
.0
ODA
Grants
(US$
Million
)–
––
––
–
Local
cred
iten
han
cemen
ts&
secu
rity
arrangemen
ts
SupportLetterfrom
GoK
(cov
ers
political
risk
butfallssh
ortof
being
anou
trightgu
aran
tee),KPLC
issu
edaletter
ofcred
iteq
uivalen
tto
5mon
thsof
capacity(deb
tservice,
fixedcostsan
deq
uity
return
s)paymen
tsan
d2mon
thsof
fuel
paymen
ts
Letterof
Com
fort
provided
bygo
vern
men
t,escrow
account,
equivalen
tto
1mon
thcapacity
charge,an
dastan
d-byLetterof
Credit,e
quivalen
tto
3mon
thsbilling
Anad
vance
paymen
tcash
dep
ositinitially,
butIberafrica
presentlyhas
nopaymen
tsecu
rity
Letterof
Com
fort
provided
bygo
vern
men
t,escrow
account,
equivalen
tto
1mon
thcapacity
charge,an
dastan
d-byLetterof
Credit,e
quivalen
tto
3mon
thsbilling
Foreign
cred
iten
han
cemen
ts&
secu
rity
arrangemen
ts
PRG
PRG
Table
A7
C:IPPinvestmen
tsin
Ken
yaby
project.
Pro
ject
Info
rmation
Pro
ject
Nam
e13
Pro
ject
Nam
e14
Pro
ject
Nam
e15
Pro
ject
Nam
e16
Kin
angopgre
enfield
win
dpro
ject
Gulf
Power
LakeTurk
anaW
indPower
Orm
atOlkariaIIIGeoth
erm
al
PowerPlant,
OrP
ower4
(phase
1and2and3)
Cap
acity(M
W)
6080
300
26Technolog
yWind,Onsh
ore
MSD
/HFO
Wind,Onsh
ore
Geo
thermal
Total
Investmen
t(U
S$Million
)15
0.0
108.0
861.1
91.1
Yearof
finan
cial
closure
2013
2013
2014
2014
COD
Delayed
2014
2017
Project
status
Con
struction/stalled
Operational
Finan
cial
close
Operational
Procu
remen
tmethod
REFiT
ICB
DN
DN
Numbe
rof
bids
5Con
tractperiod
2020
Con
tracttype
BOO
BOO
BOO
BOO
Spon
sors/D
evelop
erAeo
lusKen
ya,AIIF2,
whichbe
cameinvo
lved
inthe
project
in20
12to
assist
thedevelop
erAeo
lusKen
yato
Con
sortium
oflocalinvestors,nam
elyGulfEnergy
Ltd
andNoo
raPow
erLtd
KP&PAfricaBV,a
grou
pof
Dutchen
trep
reneu
rs,w
ith
AldwychIntern
ational
asco-develop
ers
(con
tinued
onnextpage)
A. Eberhard et al. Energy Policy 108 (2017) 390–424
407
Table
A7(con
tinued
)
Pro
ject
Info
rmation
Pro
ject
Nam
e13
Pro
ject
Nam
e14
Pro
ject
Nam
e15
Pro
ject
Nam
e16
Kin
angopgre
enfield
win
dpro
ject
Gulf
Power
LakeTurk
anaW
indPower
Orm
atOlkariaIIIGeoth
erm
al
PowerPlant,
OrP
ower4
(phase
1and2and3)
concludeallmaterialcontracts
anddeliver
aba
nka
ble
project,is
themajorityow
ner
oftheproject
compan
yKinan
gopWindPark(K
WP),whileNorfundheldthe
remaininginterest.
EPC
Fuel
arrangemen
tDeb
t-eq
uityRatio
Local
shareh
older
equity
(Entity,US$
Million
)Foreign
shareh
older
equity
(Entity,US$
Million
)Finnfund,IFU,Norfund
DFIAgency
andfinan
cing
method
Abo
utthree-qu
arters
ofthe80
million
-euro
project
willbe
deb
t-finan
ced.IFC,theOPECFundfor
Intern
ational
Develop
men
tan
dStan
dardBan
kGroup
Ltd.areeach
lending20
million
euros($26
million
).$32
million
ofeq
uityinvestmen
tsan
d$76
million
inlong-term
deb
tfinan
cing.
Thedeb
tportion
consistsof
IFCA
Loa
n,an
dcommercial
lendingthrough
IFCB
Loa
nan
dOPECFundforIntern
ational
Develop
men
t(O
FID
)
SENIO
RDEBT:A
fDB€11
5m,T
ranch
e‘B′ECAFacility
Cov
ered
€20
m,Tranch
e‘B′ECAFacilityUncovered
€10
0m,EIB
SeniorLoa
n‘A′€50
m,EIB
SeniorLoa
n‘B′€50
m,FMO
€35
,Proparco
€20
,IC
CF€30
mMEZZANIN
E:DEG
€20
,EADB€5m,PTA
€10
m&
AfD
B2m
EQUIT
Y:IFU
€7.5m
Norfund€16
mFinnfund€16
m
Total
DFIfinan
cing(U
S$Million
)–
52.0
595.8
–
ODA
Grants
(US$
Million
)–
––
–
Local
cred
iten
han
cemen
ts&
secu
rity
arrangemen
tsGOK
letter
ofsu
pport
Foreign
cred
iten
han
cemen
ts&
secu
rity
arrangemen
ts
IDA
guaran
tee,
MIG
AEKF(D
anishexportcred
itag
ency)to
guaran
teeap
prox
billionDan
ishkron
erin
totalto:EIB
andAfD
B
A. Eberhard et al. Energy Policy 108 (2017) 390–424
408
Table A8IPP investments in Madagascar by project.
Project Information Project Name
Hydelec Madagascar S.A.
Capacity (MW) 15Technology Hydro, Small ( < 50 MW)Total Investment (US$ Million) 17.8Year of financial closure 2007COD 2008Project status OperationalProcurement methodNumber of bidsContract period 15Contract type BOTSponsors/Developer Hydelec Madagascar (100%/
Madagascar)EPCFuel arrangementDebt-equity RatioLocal shareholder equity (Entity, US
$ Million)Foreign shareholder equity (Entity,
US$ Million)DFI Agency and financing method AFDB (Loan/$9 Million/2007), MIGA
(Guarantee/$20 Million/2008)Total DFI financing (US$ Million) 9.0ODA Grants (US$ Million)Local credit enhancements &
security arrangementsForeign credit enhancements &
security arrangements
A. Eberhard et al. Energy Policy 108 (2017) 390–424
409
Table
A9
IPPinvestmen
tsin
Mau
ritiusby
project.
Pro
ject
Info
rmation
Pro
ject
Nam
ePro
ject
Nam
e2
Pro
ject
Nam
e3
Pro
ject
Nam
e4
Pro
ject
Nam
e5
Pro
ject
Nam
e6
DeepRiverBeauCham
paka
Conso
lidatedenerg
ylim
ited
FUEL
powerplant
BelleVuePowerPlant
St.
Aubin
PowerPro
ject
akaCom
pagnie
therm
ique
du
Sud
Com
pagnie
therm
iquede
Savannah
Medin
e
Cap
acity(M
W)
28.4
36.7
71.2
32.5
9013
Technolog
yWaste/b
agasse
Waste/b
agasse
Coa
l/ba
gasse
Waste/b
agasse
OCGT/C
CGT
Waste/b
agasse
Total
Investmen
t(U
S$Million
)85
.010
9.7
109.3
95.2
81.5
38.9
Yearof
finan
cial
closure
1997
1998
1998
2004
2005
1994
–20
11COD
Project
status
Operational
Operational
Operational
Operational
Operational
Operational
Procu
remen
tmethod
ICB
Numbe
rof
bids
Con
tractperiod
2020
20Con
tracttype
BOO
BOO
BOO
BOO
Spon
sors/D
evelop
erSu
garInvestmen
tTrust
(10%
/Mau
ritius)
Suga
rInvestmen
tTrust
(20%
/Mau
ritius)
Harel
Freres(51%
/Mau
ritius),
Suga
rInvestmen
tTrust
(14%
/Mau
ritius),SIDEC(27%
/France)
Suga
rInvestmen
tTrust
(15%
/Mau
ritius),Mon
TresorMon
Desert(19%
/Mau
ritius),Sa
vannah
Suga
rEstates
(15%
/Mau
ritius),So
cieteUnionSt
Aubin(15%
/Mau
ritius),
Sech
ilienne-SIDEC(25%
/France)
EPC
Fuel
arrangemen
tDeb
t-eq
uityRatio
Local
shareh
older
equity
(Entity,US$
Million
)Foreign
shareh
older
equity
(Entity,US$
Million
)DFIAgency
andfinan
cing
method
EIB
(Loa
n/$
17Million
/199
8)
Total
DFIfinan
cing(U
S$Million
)–
–17
.0–
––
ODA
Grants
(US$
Million
)Local
cred
iten
han
cemen
ts&
secu
rity
arrangemen
tsForeign
cred
iten
han
cemen
ts&
secu
rity
arrangemen
ts
A. Eberhard et al. Energy Policy 108 (2017) 390–424
410
Table
A10
IPPInvestmen
tsin
Nigeria
byProject.
Pro
ject
Info
rmation
Pro
ject
Nam
ePro
ject
Nam
e2
Pro
ject
Nam
e3
Pro
ject
Nam
e4
Pro
ject
Nam
e5
AESNigeriaBarg
eLim
ited
OkpaiIn
dependentPowerPro
ject
Afam
PowerPro
ject
Azu
raAbaIn
tegra
ted
(em
bedded)
Cap
acity(M
W)
270
480
630
450
141
Technolog
yOCGT/C
CGT
OCGT/C
CGT
OCGT/C
CGT
OCGT
OCGT
Total
Investmen
t(U
S$Million
)24
0.0
462.0
540.0
895.0
460.0
Yearof
finan
cial
closure
2001
2002
2008
2015
2013
COD
2001
2005
2008
2016
x20
13Project
status
Operational
Operational
Operational
Finan
cial
closeexpected
Operational
Procu
remen
tmethod
DN
Unsolicitedproposals
DN
DN
DN
Numbe
rof
bids
18
Con
tractperiod
1320
2020
Con
tracttype
BOO
BOO
BOO
BOO
Spon
sors/D
evelop
erEnron(U
SA,10
0%)sold
toAES(95%
)an
dYFP
(Nigeria,5%
)in
2000
NigerianNational
Petroleum
Corporation
(Nigeria,6
0%),NigerianAgipOilCom
pan
y(Italy,20
%,withAgipow
ned
byENIsince
2003
),an
dPhillipsOilCom
pan
y(U
SA,
20%)maintained
equitysince
2001
NNPC(N
igeria,55
%),Sh
ell
(UK/N
etherlands,
30%),Elf
(Total)(France,10
%),Agip
(Italy,5%
)
AldwychIntern
ational,Africa
Infrastructure
Investmen
tFund(A
IIM),
andAsset
andResou
rceMan
agem
ent
(ARM)in
conjunctionwiththego
vern
men
tof
Edostatewhichhas
abou
tfive
per
cent
equitystak
ein
theproject
Geo
metric
EPC
Siem
ensan
dJu
liusBergerNigeria
Gen
eral
Electric
Fuel
arrangemen
tUtility
arrangesfuel
Project
compan
yprovides
fuel
Project
compan
yprovides
fuel
15-yearfuel
supply
agreem
entwithSe
plat
withaga
ssu
pply
LC
Fuel
supply
agreem
entwith
Shell
Deb
t-eq
uityRatio
0/10
00/
100
80/2
0Local
shareh
older
equity
(Entity,US$
Million
)5%
Maineq
uitysp
onsors:Azu
ra-E
doLtd
97.5%
compromisingAPHL50
%(A
maya
Cap
ital
80%,American
Cap
ital
20%);
AIM
30%;ARM
6%;Aldwych14
%;an
dEdo
State2.5%
Foreign
shareh
older
equity
(Entity,US$
Million
)20
%.45
Maineq
uitysp
onsors:Azu
ra-E
doLtd
97.5%
compromisingAPHL50
%(A
maya
Cap
ital
80%,American
Cap
ital
20%);
AIM
30%;ARM
6%;Aldwych14
%;an
dEdo
State2.5%
DFIAgency
andfinan
cing
method
The$12
0million
finan
cingwas
funded
from
aconsortium
offourcommercial
banks
andthree
develop
men
tfinan
ceinstitution
s.Thedevelop
men
tfinan
cial
institution
sareFMO
(Ned
erlandse
Finan
cierings-M
aatsch
appijvo
orOntw
ikke
lingslanden
N.V.),African
Exp
ort-Im
port
Ban
k,an
dDEG
(Deu
tsch
eInvestitionsund
Entw
icklungsgesellschaftmbH
).Thecommercial
banks
areAfricaMerch
antBan
k(France),adivisionof
Belgo
laiseBan
k,United
Ban
kforAfrica(N
igeria),
Ran
dMerch
antBan
k(Sou
thAfrica),an
dDiamon
dBan
k(N
igeria)
KfW
Ban
kengruppeof
German
y,the
NetherlandsDevelop
men
tFinan
ceCom
pan
y(FMO),Intern
ational
Finan
ceCorporation(IFC),German
Investmen
tCorporation(D
EG),French
Investmen
tCorporation,EmergingAfrica
Infrastructure
Fund,theWorld
Ban
kGroup
andSw
edfund,OPIC
Subo
rdinated
deb
t:IFC,EiB,
andEmergingAfrica
Infrastructure
Fundan
d4m
nIFCeq
uity
Total
DFIfinan
cing(U
S$Million
)60
.0–
–33
2.5
4.0
ODA
Grants
(US$
Million
)Local
cred
iten
han
cemen
ts&
secu
rity
arrangemen
tsSo
vereigngu
aran
tee,
US$
60million
Letterof
Credit
from
Ministryof
Finan
cePPA
backed
byNigerianPetroleum
Develop
men
tCom
pan
y'soilrevenues
PPA
backed
byNigerian
Petroleum
Develop
men
tCom
pan
y'soilrevenues
Foreign
cred
iten
han
cemen
ts&
secu
rity
arrangemen
tsOPIC
political
risk
insu
rance
CreditEnhan
cemen
tPRG
(IBRD)
A. Eberhard et al. Energy Policy 108 (2017) 390–424
411
Table A11IPP investments in Rwanda by project.
Project Information Project Name
KivuWatt
Capacity (MW) 100Technology Methane GasTotal Investment (US$
Million)200.0
Year of financial closure 2011COD 2015Project status ConstructionProcurement method DNNumber of bidsContract period 25Contract type BOOSponsors/Developer ContourGlobal (100%/United States)EPCFuel arrangementDebt-equity RatioLocal shareholder equity
(Entity, US$ Million)Foreign shareholder equity
(Entity, US$ Million)DFI Agency and financing
methodMIGA (Guarantee/$26 Million/2011), AFDB(Loan/$25 Million/2011) UK, Dutch, Swedishand Swiss governments loaned $91mn
Total DFI financing (US$Million)
116.0
ODA Grants (US$ Million) –
Local credit enhancements &security arrangements
Foreign credit enhancements& security arrangements
A. Eberhard et al. Energy Policy 108 (2017) 390–424
412
Table
A12
IPPinvestmen
tsin
Senegal
byproject.
Pro
ject
Info
rmation
Pro
ject
Nam
ePro
ject
Nam
e2
Pro
ject
Nam
e3
Pro
ject
Nam
e4
Pro
ject
Nam
e5
GTiDakarLtd
.KounouneIIP
PSain
t-Louis
-Dagana-
PodorRura
lElectrifica
tion
Sendou
Tobene
Cap
acity(M
W)
5267
.519
125
87.5
Technolog
yOCGT+CCGT
MSD
/HFO
Solar,
PV
Coa
lMSD
/HFO
Total
Investmen
t(U
S$Million
)65
.011
0.0
22.0
254.3
163.5
Yearof
finan
cial
closure
1997
2005
2010
2013
2014
COD
2000
2008
2017
2015
Project
status
Operational
Operational
Operational
Con
struction
Con
struction
Procu
remen
tmethod
ICB
ICB
ICB
ICB
ICB,then
DN
Numbe
rof
bids
21
Con
tractperiod
1515
25Con
tracttype
BOOT
BOO
BOT
Spon
sors/D
evelop
erIFC,So
ndel
(Green
wichAir
Service,
Inc).
Melec
Pow
ergen(partof
Matelec
grpof
compan
ies)
(Leb
anon
),Mitsu
bish
i(Jap
an)
OfficeNational
del′Electricite
(73%
/Morocco),Intern
ational
Finan
ceCorporation(17%
)EPC
MEGS(M
editerraneanElectricGen
erating
Services)-ajointventure
betw
eenSo
ndel
and
Gen
eral
Electric
MHIEqu
ipmen
tEurope,
France,
(Mem
berof
Mitsu
bish
iHeavy
Industries
Group)
Fuel
arrangemen
tDuringtheproject
negotiation
s,the
structure
oftheFSA
andPPA
were
chan
gedto
turn
thePPA
into
atolling
agreem
ent
Deb
t-eq
uityRatio
70/3
0Local
shareh
older
equity
(Entity,US$
Million
)Foreign
shareh
older
equity(E
ntity,US$
Million
)DFIAgency
andfinan
cing
method
IFC(Loa
n/$
13Million
/199
7),IFC(E
quity/$2
Million
/199
7),IFC(Syn
dication/$
3Million
/19
97),IFC(E
quity/$1Million
/199
8),IFC
(Syn
dication/$
12Million
/199
8),IFC(Q
uasi-
equity/$7Million
/199
8),IFC(R
isk
man
agem
ent/$1Million
/200
2)
IDA
(Guaran
tee/$7Million
/200
5),ID
A(Loa
n/$
10Million
/200
5),IFC(Loa
n/
$21
Million
/200
5);MIR
also
listed
Proparco,AfD
B,BOAD
andCBAO
IFC(E
quity/$1Million
/201
0)African
Develop
men
tBan
k(A
fDB)-
Netherlands
Develop
men
tFinan
ceCom
pan
y(FMO)
IFClead
arranger,
Euro
tran
che=
€78
.5M–
€28
.5M
Aloan
byIFC,an
d€50
MBloan
(€25
Mby
FMO
and€25
Mby
EmergingAfrica
Infrastructure
Fund/E
AIF),an
dalocaltran
che
fortheCFAeq
uivalen
tof
€13
.5M
byBOAD
Total
DFIfinan
cing(U
S$Million
)39
.053
.71.0
108.0
135.1
ODA
Grants
(US$
Million
)Local
cred
iten
han
cemen
ts&
secu
rity
arrangemen
ts
Gov
ernmen
tgu
aran
tee,
escrow
account
Gov
ernmen
tgu
aran
tee,
aletter
ofcred
itfrom
Senelec
Foreign
cred
iten
han
cemen
ts&
secu
rity
arrangemen
ts
Creditinsu
rance
through
agu
aran
teeprogram
ofSA
CE,theItalianexportcred
itag
ency,an
da
partial
interest
subsidythrough
theMed
iocred
ito
Cen
tral
SubsidyDep
artm
ent(M
CSD
)
APRG,b
utnever
sign
edby
govern
men
tID
APRG
A. Eberhard et al. Energy Policy 108 (2017) 390–424
413
Table A13IPP investments in Sierra Leone by project.
Project Information Project Name
Addax Biomass Plant
Capacity (MW) 15Technology BiomassTotal Investment (US$ Million) 30.0Year of financial closure 2011COD 2013Project status OperationalProcurement method DNNumber of bidsContract periodContract type BOOSponsors/Developer Addax & Oryx Group (100%/
United Kingdom)EPCFuel arrangementDebt-equity Ratio 61/39Local shareholder equity (Entity, US$
Million)Foreign shareholder equity (Entity, US$
Million)DFI Agency and financing method AFDB (Loan/$30 Million/2011)Total DFI financing (US$ Million) 30.0ODA Grants (US$ Million)Local credit enhancements & security
arrangementsForeign credit enhancements & security
arrangements
A. Eberhard et al. Energy Policy 108 (2017) 390–424
414
Table
A14
IPPinvestmen
tsin
Tan
zania
byproject.
Pro
ject
Info
rmation
Pro
ject
Nam
ePro
ject
Nam
e2
Pro
ject
Nam
e3
Pro
ject
Nam
e4
IndependentPowerTanza
nia
Ltd
Songas-SongoSongoGasto
PowerPro
ject
Mtw
ara
Region
Gas-to
-PowerPro
ject
Sym
bion
Cap
acity(M
W)
100
189
1812
0Technolog
yMSD
/HFO
CCGT
OCGT/C
CGT
OCGT/C
CGT
Total
Investmen
t(U
S$Million
)12
7.2
316.0
32.0
123.2
Yearof
finan
cial
closure
1997
2001
2005
2006
COD
2002
2004
2007
2006
,20
07Project
status
Operational
Operational
Operational
Operational
Procu
remen
tmethod
DN
ICB
ICB
DN
Numbe
rof
bids
2Con
tractperiod
2020
25Exp
iryOct
2014
Con
tracttype
BOO
BOO
BOO
Emergency/short-term
Spon
sors/D
evelop
erVIP
Engineeringan
dMarke
tingLtd
(Tan
zania),MechMar
Energy
SdnBhd
TransC
anad
asold
majoritysh
ares
toAES(U
SA)in
1999
and
AESsold
majoritysh
ares
toGlobe
leq(U
K)in
2003
[1].All
preferred
equitysh
ares
wereconverted
into
“Loa
nNotes”in
June20
09.Only
common
shares
remain
Artumas
GroupInc.
(87%
/Can
ada)
FMO
13%
Builtby
Richmon
d,sold
toDow
ans,
then
toSy
mbion
EPC
Larsen
&Tou
bro(L
&T)
Fuel
arrangemen
tIPTLim
ports
fuel,w
hichis
apassthrough
totheutility
Songo
Songo
gasprovided
toproject
compan
yat
arate
ofUS
$.55/
MMBtu
forturbines
I-Van
dat
US$
2.17
MMBtu
for
turbineVI
Fuel
provided
byaconsortium
that
includes
theproject
spon
sor(has
a25
.4%
stak
ein
thega
sconcession),at
ach
arge
ofUS$
5.00
per
MMBTu,whichis
passedthrough
toutility
TANESC
Opurchases
natural
gasan
dfuel
isapassthrough
Deb
t-eq
uityRatio
0/10
070
/30
0/10
00/
100
Local
shareh
older
equity
(Entity,US$
Million
)VIP
(Tan
zania,30
%in
kind),(disputed),
hav
esough
tto
sellsh
ares
4.83
100%
finan
cedwithba
lance
sheetof
shareh
olders
Foreign
shareh
older
equity
(Entity,US$
Million
)Mechmar
(Malaysia,
70%)hav
esough
tto
sellsh
ares
5.67
100%
finan
cedwithba
lance
sheetof
shareh
olders
Equ
ityfinan
ced
DFIAgency
andfinan
cing
method
IBRD
(Loa
n/$
183Million
/200
1),EIB
(Loa
n/$
55Million
/20
01)
FMO,13
%eq
uitysh
areh
older
Total
DFIfinan
cing(U
S$Million
)–
249.0
4.2
–
ODAGrants
(US$
Million
)–
100.3
––
Local
cred
iten
han
cemen
ts&
secu
rity
arrangemen
tsSo
vereigngu
aran
tee,
liqu
idityfacility
equivalen
tto
4mon
thscapacitych
arge
(butnot
yetestablished
)
Escrow
account:forfirst11
5MW,withthego
vern
men
tmatch
ingeveryUS$
1sp
entby
theproject
compan
y;liqu
idity
facility
equivalen
tto
4mon
thscapacitych
arge
forthefirst3
years,
decliningto
2mon
thsstartingin
year
4through
the
remainingyearsof
thecontract
TariffEqu
alizationFundprovided
,afixed-valueaccount
designed
tomak
eupthedifference
betw
eenthenational
tariff
andthecost-based
tariff(w
hichwou
ldotherwisebe
charged
tothefinal
consu
mer)under
theproject
Nogo
vern
men
tgu
aran
tees
Foreign
cred
iten
han
cemen
ts&
secu
rity
arrangemen
ts
A. Eberhard et al. Energy Policy 108 (2017) 390–424
415
Table A15IPP investments in Togo by project.
Project Information Project Name
Centrale thermique de Lome
Capacity (MW) 100Technology Triple fuelTotal Investment (US$ Million) 196.0Year of financial closure 2008COD 2010Project status OperationalProcurement method DNNumber of bidsContract period 25Contract type BOTSponsors/Developer ContourGlobal (80%/United States),
International Finance Corporation (20%)EPCFuel arrangementDebt-equity RatioLocal shareholder equity (Entity,
US$ Million)Foreign shareholder equity (Entity,
US$ Million)DFI Agency and financing method IFC (Equity/Loan) and OPICTotal DFI financing (US$ Million) 161.0ODA Grants (US$ Million)Local credit enhancements &
security arrangementsPayment Guarantee
Foreign credit enhancements &security arrangements
A. Eberhard et al. Energy Policy 108 (2017) 390–424
416
Table
A16
A:IPPinvestmen
tsin
Uga
ndaby
project.
Pro
ject
Info
rmation
Pro
ject
Nam
ePro
ject
Nam
e2
Pro
ject
Nam
e3
Pro
ject
Nam
e4
Pro
ject
Nam
e5
Pro
ject
Nam
e6
Kase
seCobalt,
Mubuku
III
Kilem
beM
ines
(Mubuku
I)Kakiraco
genera
tion
plant
Bujagali
Hyd
roPro
ject
ECO
Ishash
aM
ini
Hyd
ropowerPlant
Tro
nder/Bugoye
Hyd
roElectricPowerPro
ject
(Mubuku
II)
Cap
acity(M
W)
9.9
5.4
3225
06.5
13Technolog
yHyd
ro,Sm
all(<
20MW)
Hyd
ro,Sm
all(<
20MW)
Waste/B
agasse
Hyd
roHyd
ro,Sm
all(<20
MW)
Hyd
ro,Sm
all(<20
MW)
Total
Investmen
t(U
S$Million
)22
.516
.256
.086
0.0
14.0
65.7
Yearof
finan
cial
closure
1999
1975
2003
2007
2008
2008
COD
2013
2012
2011
2009
Project
status
Operational
not
operational
Operational
Operational
Operational
Operational
Procu
remen
tmethod
DN
DN/R
EFiT(PPA3)
ICB
DN
DN
Numbe
rof
bids
3Con
tractperiod
2020
3030
20Con
tracttype
BOO
BOT
BOT
BOT
Spon
sors/D
evelop
erBlueEarth
Refineries
Inc(10
0%Uga
nda)
Gov
ernmen
tof
Uga
nda(51%
)Mad
hva
niGroup(100
%/
Uga
nda)
BELLtd
(SitheGloba
lPow
er(58%
/United
States),Aga
Khan
Fund(31%
/Switzerlan
d))
Eco
Pow
er(100
%/S
riLan
ka)
Tronder
Pow
erLim
ited
(100
%/
Norway)
EPC
In-hou
se/con
sultan
tFuel
arrangemen
tDeb
t-eq
uityRatio
78/2
270
/30
53/3
2(14%
gran
tby
Gov
ernmen
tof
Norway)
Local
shareh
older
equity
(Entity,US$
Million
)Non
-recou
rse
Tronder
Foreign
shareh
older
equity
(Entity,US$
Million
)Balan
cesh
eet
Norfund
DFIAgency
andfinan
cing
method
EADB
MIG
A(G
uaran
tee/$11
5Million
/200
7),IFC(Loa
n/
$13
0Million
/200
7),ID
A(G
uaran
tee/$11
5Million
/200
7),
ADB(Loa
n/$
110Million
/200
7),EIB
(Loa
n/$
130Million
/20
07)
EAIF/F
MO/N
orway
govt/
Norfund
Total
DFIfinan
cing(U
S$Million
)–
–15
.037
0.0
–48
.2
ODA
Grants
(US$
Million
)GETFiT
14%
gran
tby
Gov
ernmen
tof
Norway
Local
cred
iten
han
cemen
ts&
secu
rity
arrangemen
tsGov
ernmen
tpaymen
tgu
aran
tee
Gov
ernmen
tpaymen
tgu
aran
tee
Foreign
cred
iten
han
cemen
ts&
secu
rity
arrangemen
ts
A. Eberhard et al. Energy Policy 108 (2017) 390–424
417
Table A16B: IPP investments in Uganda by project.
Project Information Project Name7 Project Name8 Project Name9 Project Name10 Project Name11 ProjectName12
Mpanga Hydro PowerProject
NamanvePower Plant
KinyaraCogeneration Plant
Buseruka/HydromaxHydropower Plant
Tororo PowerStation
Tororo PowerStation
Capacity (MW) 18 50 7.5 9 16 34Technology Hydro, Small ( < 20 MW) MSD/HFO Waste/Bagasse Hydro, Small ( < 20 MW) MSD/HFO MSD/HFOTotal Investment (US$
Million)27.0 74.0 29.0 27.0 41.5 41.5
Year of financial closure 2008 2008 2009 2009 2009 2012COD 2011 2011 2012 2010Project status Operational Operational Operational Operational Operational OperationalProcurement method DN ICB DN DN DNNumber of bids 3Contract period 20 6 20 30 9Contract type BOT BOT BOO BOT BOOSponsors/Developer South Asia Energy
Management Systems(SAEMS) (100%/UnitedStates)
Jacobsen Elektro(100%/Norway)
Kinyara Sugar Group(100%/Uganda)
Hydromax Limited(100%/Uganda)
Electro-Maxx(100%/Uganda)
EPCFuel arrangementDebt-equity Ratio 70/30 60/40Local shareholder equity
(Entity, US$ Million)Foreign shareholder equity
(Entity, US$ Million)DFI Agency and financing
methodEAIF ($14 million)/FMO AFDB (Loan/$9 Million/
2009)Total DFI financing (US$
Million)20.0 – – 9.0 – –
ODA Grants (US$ Million)Local credit enhancements
& securityarrangements
Payment Guarantee PaymentGuarantee
Variable governmentpayments
Governmentpayment guarantee
Foreign creditenhancements &security arrangements
Table A16C: IPP investments in Uganda by project.
Project Information Project Name13 Project Name14 Project Name15 Project Name16 Project Name17 Project Name18
KakakaHydropowerProject
RwimiHydropwoerProject
Lubilia HydropowerProject
MuvumbeHydropowerProject
Nengo BridgeHydropower Project
SAIL Cogen
Capacity (MW) 5 5.4 5.4 6.5 6.9 6.9Technology Hydro, Small ( <
20 MW)Hydro, Small ( <20 MW)
Hydro, Small ( <20 MW)
Hydro, Small ( <20 MW)
Hydro, Small ( <20 MW)
Waste/Bagasse
Total Investment (US$Million)
18.0 18.0 18.0 14.0 27.0 22.0
Year of financial closure 2015 2015 2015 2015COD 2016 2017 2017 2017Project status Financing in process Under Construction Under Construction Under Construction Cancelled CancelledProcurement method REFiT REFiT REFiT REFiT REFiT REFiTNumber of bidsContract period 20 20 20 20 20 20Contract type BOT BOT BOT BOT BOT BOOSponsors/Developer Frontier (Danish
Private Equity Fund)Eco Power (100%/SriLanka)
Frontier (DanishPrivate Equity Fund)
Vidullanka (100%/SriLanka)
Jacobsen Elektro(100%/Norway)
Sugar AlliedIndustries(Ugandan)
EPCFuel arrangementDebt-equity Ratio 70/30 65/35Local shareholder equity
(continued on next page)
A. Eberhard et al. Energy Policy 108 (2017) 390–424
418
Table A16 (continued)
Project Information Project Name13 Project Name14 Project Name15 Project Name16 Project Name17 Project Name18
KakakaHydropowerProject
RwimiHydropwoerProject
Lubilia HydropowerProject
MuvumbeHydropowerProject
Nengo BridgeHydropower Project
SAIL Cogen
(Entity, US$ Million)Foreign shareholder equity
(Entity, US$ Million)DFI Agency and financing
methodEAIF/FMO EAIF/FMO EADB
Total DFI financing (US$Million)
– – – – – –
ODA Grants (US$ Million) GET FiT GET FiT GET FiT GET FiT GET FiTLocal credit enhancements
& securityarrangements
Foreign creditenhancements &security arrangements
Table A16D: IPP investments in Uganda by project.
Project Information Project Name19 Project Name20 Project Name21 Project Name22
SAEMS Nyamwamba SHPP Siti I/II Hydropower Project Tororo North/South
Soroti Solar
Capacity (MW) 9.2 21.5 10 10Technology Hydro, Small ( < 20 MW) Hydro Large Solar PV Solar PVTotal Investment (US$ Million) 34.0 48.0 18.0 18.0Year of financial closure 2015 2015 2015x 2015xCOD 2017 2017–18 2017 2016Project status Construction started in 2014 Under Construction Under Construction OperationalProcurement method REFiT REFiT ICB ICBNumber of bidsContract period 20 20Contract type BOT BOTSponsors/Developer South Asia Energy Management Systems
(SAEMS) (100%/United States)Frontier (Danish Private EquityFund)
Simba/BuildingEnergy
Access/TSK
EPCFuel arrangementDebt-equity Ratio 73/27 70/30 75/25 75/25Local shareholder equity (Entity, US$
Million)Foreign shareholder equity (Entity, US$
Million)DFI Agency and financing method Other (Loan/$24 Million/2012) Out of which
EAIF is 6 millionEAIF/FMO (5.3) FMO FMO
Total DFI financing (US$ Million) 6.0 5.3 – –
ODA Grants (US$ Million) GET FiT GET FiTLocal credit enhancements & security
arrangementsForeign credit enhancements & security
arrangements
A. Eberhard et al. Energy Policy 108 (2017) 390–424
419
Table A17IPP investments in Zambia by project.
Project Information Project Name Project Name2
Ndola Energy TATA Itezhi-Tezhi HPP
Capacity (MW) 50 120Technology MSD/HFO HydroTotal Investment (US$ Million) 72.0 230.0Year of financial closure 2012 2014COD 2013 2016Project status Operational ConstructionProcurement method DN DNNumber of bidsContract period 25Contract type BOTSponsors/Developer Subsidiary of Concordia Energy (Group of
Mauritius)Tata Enterprises (50%/India), Zambia Electric Supply Corporation(ZESCO) (50%/Zambia)
EPC Chinese EPC/ICB for EPCFuel arrangementDebt-equity RatioLocal shareholder equity (Entity, US$ Million)Foreign shareholder equity (Entity, US$ Million)DFI Agency and financing method EIB (Equity/$18 Million/2011), 2014: a $142 million loan by DBSA,
Proparco, ADB, and FMOTotal DFI financing (US$ Million) – 162.0ODA Grants (US$ Million)Local credit enhancements & security
arrangementsForeign credit enhancements & security
arrangements
A. Eberhard et al. Energy Policy 108 (2017) 390–424
420
Table
A18
IPPinvestmen
tsin
South
Africaby
project.
Pro
ject
Capacity
(MW
)Tech
nology
Total
Investm
ent
(US$M
illion)
Fin
ancial
closu
reCOD
Pro
ject
statu
sPro
cure
ment
meth
od
Sponso
rs/
Developer
DFIAgency
andfinancing
meth
od
TotalDFI
financing
(US$
Million)
Loca
lcr
edit
enhance
ments
&se
curity
arr
angem
ents
Bethlehem
Hyd
ro7
Hyd
ro,Sm
all(<
20MW)
13.7
2005
2009
,20
12Operational
DN
NuPlanet
(26%
/Netherlands)
Other
(Loa
n/$
5Million
/200
5)5.0
DarlingWindFarm
5Wind,Onsh
ore
9.9
2006
2008
Operational
DN
Darling
Indep
enden
tPow
erProducer
Pty
Ltd
(26%
/So
uth
Africa)
–
Sasol
373
OCGT/C
CGT
399.0
2010
2010
Operational
DN
Sasol
–
Slim
SunSw
artlan
dSo
larPark
5So
lar,
PV
26.1
2012
2013
Operational
ICB
IDC(in20
12ZAR)(E
xchan
gerate
.12)
8.9
Paymen
tGuaran
tee
RustMo1
Solar
Farm
6.9
Solar,
PV
28.0
2012
2013
Operational
ICB
IDC(in20
12ZAR)(E
xchan
gerate
.12)
9.8
Paymen
tGuaran
tee
Kon
koon
sies
Solar
Energy
Facility
9.7
Solar,
PV
43.9
2012
2013
Operational
ICB
IDC(in20
12ZAR)(E
xchan
gerate
.12)
15.0
Paymen
tGuaran
tee
Aries
SolarEnergy
Facility
9.7
Solar,
PV
44.5
2012
2013
Operational
ICB
IDC(in20
12ZAR)(E
xchan
gerate
.12)
15.0
Paymen
tGuaran
tee
Greefsp
anPVPow
erPlant
9.9
Solar,
PV
53.5
2012
2014
Operational
ICB
IDC(in20
12ZAR)(E
xchan
gerate
.12)
10.0
Paymen
tGuaran
tee
Mulilo
SolarPVDe
Aar
10So
lar,
PV
39.3
2012
2013
Operational
ICB
IDC(in20
12ZAR)(E
xchan
gerate
.12)
13.6
Paymen
tGuaran
tee
Herbe
rtPVPow
erPlant
20.0
Solar,
PV
105.3
2012
2013
Operational
ICB
IDC(in20
12ZAR)(E
xchan
gerate
.12)
12.8
Paymen
tGuaran
tee
Mulilo
SolarPV
Prieska
20So
lar,
PV
79.1
2012
2015
Operational
ICB
IDC(in20
12ZAR)(E
xchan
gerate
.12)
26.9
Paymen
tGuaran
tee
Dassiek
lipWind
Energy
Facility
27Wind,Onsh
ore
83.1
2012
2014
Operational
ICB
IDC(in20
12ZAR)(E
xchan
gerate
.12)
18.0
Paymen
tGuaran
tee
MetroWindVan
Stad
ensWind
Farm
27Wind,Onsh
ore
74.8
2012
2014
Operational
ICB
–Paymen
tGuaran
tee
Soutpan
SolarPark
28So
lar,
PV
155.7
2012
2014
Operational
ICB
–Paymen
tGuaran
tee
Witko
pSo
larPark
30So
lar,
PV
174.3
2012
2014
Operational
ICB
–Paymen
tGuaran
tee
Tou
wsrivierSo
lar
Park
36So
lar,
PV
197.5
2012
2014
Operational
ICB
–Paymen
tGuaran
tee
DeAar
SolarPV
45.6
Solar,
PV
178.0
2012
2014
Operational
ICB
Globe
leq
DBSA
in20
12ZAR
(Exchan
gerate
.12)
43.0
Paymen
tGuaran
tee
South
Africa
Mainstream
Ren
ewab
lePow
erDroog
fontein
45.6
Solar,
PV
173.6
2012
2014
Operational
ICB
Globe
leq
DBSA
in20
12ZAR
(Exchan
gerate
.12)
41.9
Paymen
tGuaran
tee
KhiSo
larOne
50So
larCS
509.8
2012
2016
Operational
ICB
IFC,EIB
,DBSA
andID
Call
hav
edeb
twhileID
Chas
29%
equityalso
298.7
Paymen
tGuaran
tee
LetsatsiSo
lar
Photov
oltaic
Park
64So
lar,
PV
320.9
2012
2014
Operational
ICB
–Paymen
tGuaran
tee
Lesed
iSo
lar
Photov
oltaic
Park
64So
lar,
PV
322.7
2012
2014
Operational
ICB
–Paymen
tGuaran
tee
Hop
efieldWind
Farm
65.4
Wind,Onsh
ore
195.6
2012
2014
Operational
ICB
–Paymen
tGuaran
tee
(con
tinued
onnextpage)
A. Eberhard et al. Energy Policy 108 (2017) 390–424
421
Table
A18(con
tinued
)
Pro
ject
Capacity
(MW
)Tech
nology
Total
Investm
ent
(US$M
illion)
Fin
ancial
closu
reCOD
Pro
ject
statu
sPro
cure
ment
meth
od
Sponso
rs/
Developer
DFIAgency
andfinancing
meth
od
TotalDFI
financing
(US$
Million)
Loca
lcr
edit
enhance
ments
&se
curity
arr
angem
ents
Kalkb
ult
72.5
Solar,
PV
274.9
2012
2013
Operational
ICB
DBSA
in20
12ZAR
(Exchan
gerate
.12)
29.8
Paymen
tGuaran
tee
KathuSo
larPlant
75So
lar,
PV
430.4
2012
2014
Operational
ICB
DBSA
in20
12ZAR
(Exchan
gerate
.12)
45.0
Paymen
tGuaran
tee
SolarCap
ital
DeAar
75So
lar,
PV
296.6
2012
2014
Operational
ICB
–Paymen
tGuaran
tee
Nob
elsfon
tein
Phase
175
Wind,Onsh
ore
196.8
2012
2014
Operational
ICB
–Paymen
tGuaran
tee
Kou
gaWindFarm
80Wind,Onsh
ore
235.6
2012
2014
Operational
ICB
IDC(in20
12ZAR)(E
xchan
gerate
.12)
53.9
Paymen
tGuaran
tee
Dorper
WindFarm
97.5
Wind,Onsh
ore
286.1
2012
2014
Operational
ICB
–Paymen
tGuaran
tee
KaX
uSo
larOne
100
SolarCS
976.3
2012
2014
Operational
ICB
DBSA
1,17
1,29
0,60
0,ID
C82
9,65
6,56
6,IFC
600,00
0,00
0,IFC(as
Implemen
tation
Entity
ofthe
Clean
Technolog
yFund)
232,40
5,00
0.MEZZDeb
t:DBSA
195,31
2,70
7,ID
C19
5,31
2,70
7Equ
ity:
IDC29
%
454.8
Paymen
tGuaran
tee
Jeffreys
Bay
138
Wind,Onsh
ore
366.5
2012
2014
Operational
ICB
Globe
leq
DBSA
848,70
0,00
010
1.8
Paymen
tGuaran
tee
Coo
khou
seWind
Farm
138.6
Wind,Onsh
ore
295.6
2012
2014
Operational
ICB
–Paymen
tGuaran
tee
Vreden
dal
Solar
Park
8.82
Solar,
PV
29.1
2013
Operational
ICB
–Paymen
tGuaran
tee
StortemelkHyd
ro(Pty)Ltd
4.4
Hyd
roSm
all(<
20MW)
17.4
2013
Operational
–Paymen
tGuaran
tee
Upington
SolarPV
8.9
Solar,
PV
26.5
2013
Operational
ICB
–Paymen
tGuaran
tee
Aurora-R
ietvlei
SolarPow
er9
Solar,
PV
30.3
2013
Operational
ICB
–Paymen
tGuaran
tee
Neu
sbergHyd
roElectricProject
A10
Hyd
ro,Sm
all(<
20MW)
73.5
2013
Operational
ICB
IDC(in20
13ZAR)(E
xchan
gerate
.12)
senioran
dmezzdeb
t19
.7Paymen
tGuaran
tee
Chab
aWindFarm
Project
21Wind,Onsh
ore
54.4
2013
Operational
ICB
IDCin
2013
ZAR
(Exchan
gerate
.12)
15.5
Paymen
tGuaran
tee
Waa
inek
Wind
Pow
er23
.3Wind,Onsh
ore
69.7
2013
2016
Operational
ICB
IDCin
2013
ZAR
(Exchan
gerate
.12)
19.9
Paymen
tGuaran
tee
Linde
36.8
Solar,
PV
147.2
2013
Operational
ICB
–Paymen
tGuaran
tee
Bok
poo
rtCSP
Project
50So
larCS
642.2
2013
Con
struction
ICB
IDC25
%eq
uity
45.1
Paymen
tGuaran
tee
Grassridge
Wind
Energy
Project
59.8
Wind,Onsh
ore
161.3
2013
Operational
ICB
IDC20
1346
.1Paymen
tGuaran
tee
Boshof
SolarPark
60So
lar,
PV
312.0
2013
Operational
ICB
OPIC
222.7
Paymen
tGuaran
tee
Dreunbe
rg69
.6So
lar,
PV
286.6
2013
Operational
ICB
–Paymen
tGuaran
tee
Sish
enSo
larFacility
74So
lar,
PV
294.8
2013
2014
Operational
ICB
–Paymen
tGuaran
tee
SolarCap
ital
DeAar
375
Solar,
PV
326.9
2013
Operational
ICB
IDC
111.1
Paymen
tGuaran
tee
Jasp
erPow
erCom
pan
y75
Solar,
PV
290.7
2013
Operational
ICB
DBSA
60.0
Paymen
tGuaran
tee
WestCoa
stOne
WindFarm
90.8
Wind,Onsh
ore
252.1
2013
Operational
ICB
DBSA
44.1
Paymen
tGuaran
tee
Tsitsikam
ma
Com
munity
WindFarm
94.8
Wind,Onsh
ore
365.9
2013
2016
Operational
ICB
–Paymen
tGuaran
tee
Amak
halaEmoy
eni
133.7
Wind,Onsh
ore
497.0
2013
2016
Operational
ICB
IFC
76.1
Paymen
tGuaran
tee
(con
tinued
onnextpage)
A. Eberhard et al. Energy Policy 108 (2017) 390–424
422
Table
A18(con
tinued
)
Pro
ject
Capacity
(MW
)Tech
nology
Total
Investm
ent
(US$M
illion)
Fin
ancial
closu
reCOD
Pro
ject
statu
sPro
cure
ment
meth
od
Sponso
rs/
Developer
DFIAgency
andfinancing
meth
od
TotalDFI
financing
(US$
Million)
Loca
lcr
edit
enhance
ments
&se
curity
arr
angem
ents
WindFarm
Gou
daWindProject
135.5
Wind,Onsh
ore
336.3
2013
Operational
ICB
–Paymen
tGuaran
tee
Mku
ze16
.5Biomass
95.6
2015
Finan
cingan
dApprova
lsunderway
ICB
–Paymen
tGuaran
tee
Johan
nesbu
rgLan
dfillGas
toElectricity
18Lan
dfillGas
24.8
2014
Partially
Operational
ICB
–Paymen
tGuaran
tee
Tom
BurkeSo
lar
Park
60Photov
oltaic
Thin
Film
Fixed
2014
2016
Operational
ICB
–Paymen
tGuaran
tee
Adam
sSo
larPV
275
Photov
oltaic
CrystallineFixed
2014
Con
struction
ICB
–Paymen
tGuaran
tee
Electra
Cap
ital
(Pty)
Ltd
75Photov
oltaic
CrystallineFixed
2014
2016
Operational
ICB
–Paymen
tGuaran
tee
Mulilo
Sonned
ixPrieska
PV
75Photov
oltaic
CrystallineFixed
108.0
2014
2016
Operational
ICB
–Paymen
tGuaran
tee
Mulilo
Prieska
PV
75Photov
oltaic
Crystalline-
Single
Axis
200.0
2014
Operational
ICB
IDCin
2014
20.2
Paymen
tGuaran
tee
PulidaSo
larPark
75Photov
oltaic
Thin
Film
Fixed
2014
Finan
cingDon
eIC
B–
Paymen
tGuaran
tee
Nou
poo
rtMainstream
Wind
80Wind,Onsh
ore
180.0
2014
2016
Operational
ICB
EKFan
dDBSA
108.5
Paymen
tGuaran
tee
NojoliWindFarm
86.6
Wind,Onsh
ore
2014
2017
Operational
ICB
–Paymen
tGuaran
tee
Lon
gyuan
Mulilo
De
Aar
Maa
nhaa
rberg
WindEnergy
Facility
96.5
Wind,Onsh
ore
180.0
2014
Con
struction
ICB
IDC
63.0
Paymen
tGuaran
tee
Ilan
gaCSP
1/Karoshoe
kSo
lar
One
100
Con
centrated
Solar
Pow
er,parab
olic
trou
gh,w
ithstorag
e(4.5
hper
day)
735.4
2014
Con
struction
ICB
IDCan
dDBSA
180.0
Paymen
tGuaran
tee
XinaSo
larOne
100
Con
centrated
Solar
Pow
er,parab
olic
trou
gh,w
ithstorag
e(5
hper
day)
880.0
2014
Con
struction
ICB
DBSA
800,00
0,00
0,ID
C75
0,00
0,00
0,AfD
B1,50
0,00
0,00
0an
dID
C20
%eq
uity
316.8
Paymen
tGuaran
tee
Red
Cap
-Gibson
Bay
110
Wind,Onsh
ore
202.5
2014
Con
struction
ICB
–Paymen
tGuaran
tee
Khob
abWindFarm
137.7
Wind,Onsh
ore
315.0
2014
Con
struction
ICB
DBSA
,EKF
214.2
Paymen
tGuaran
tee
Loe
riesfontein
2WindFarm
138.2
Wind,Onsh
ore
315.0
2014
Con
struction
ICB
DBSA
,EKF
208.5
Paymen
tGuaran
tee
Lon
gyuan
Mulilo
De
Aar
2North
WindEnergy
Facility
139.0
Wind,Onsh
ore
264.6
2014
Con
struction
ICB
IDC
85.5
Paymen
tGuaran
tee
Notes:
a)REIPPPPinvestmen
tdatais
derived
from
public
sources
andhas
anerrorrange
ofarou
nd10
%an
dthat
final
finan
cial
closedatais
differentfrom
biddataan
dis
not
yetpublicly
available
b)Cells
withnoinputrepresentinform
ationwedonot
hav
e.Investmen
tnumbe
rcellswitha"-"sign
mean0investmen
t.
A. Eberhard et al. Energy Policy 108 (2017) 390–424
423
References
Brautigam, D., 2009. The Dragon's Gift the Real Story of China in Africa. OxfordUniversity Press.
Castellano, A., Kendall, A., Nikomarov, M., Swemmer, T., 2015. Brighter Africa,McKinsey & Company Monthly Journal.
Dreher, A., Fuchs, A., 2006. Rogue Aid? The Determinants of China's Aid AllocationRogue Aid? The Determinants of China's Aid Allocation 32.
Eberhard, A., Gratwick, K.N., 2011. IPPs in Sub-Saharan Africa: determinants of success.Energy Policy 39, 5541–5549. http://dx.doi.org/10.1016/j.enpol.2011.05.004.
Eberhard, A., Gratwick, K., 2013. Investment power in Africa: where from and where to?Georg. J. Int. Aff., 39–46, (Winter/Spring).
Eberhard, A., Gratwick, K., Morella, E., Antmann, P., 2016. Independent Power Projectsin Sub-Saharan Africa: Lessons From Five Key Countries. The World Bank,Washington, D.C. http://dx.doi.org/10.1596/978-1-4648-0800-5.
Eberhard, A., Kåberger, T., 2016. Renewable energy auctions in South Africa outshinefeed-in tariffs. Energy Sci. Eng. 4, 190–193. http://dx.doi.org/10.1002/ese3.118.
Eberhard, A., Kolker, J., Leigland, J., 2014. South Africa's Renewable Energy IPPProcurement Program: Success Factors and Lessons. Public-Private InfrastructureAdvisory Facility & The World Bank Group, Washington, D.C.
Eberhard, A., Rosnes, O., Shkaratan, M., Vennemo, H., 2011. Africa's PowerInfrastructure: Investment, Integration, Efficiency. World Bank, Washington DC.
Eberhard, A., Shkaratan, M., 2012. Powering Africa: meeting the financing and reformchallenges. Energy Policy 42, 9–18. http://dx.doi.org/10.1016/j.enpol.2011.10.033.
Eckhouse, B., 2016. Senegal to Add 200 MW of Solar Through IFC Program [WWWDocument]. Bloomberg. URL ⟨http://www.bloomberg.com/news/articles/2016-02-10/senegal-to-add-200-megawatts-of-solar-through-ifc-program⟩ (Accessed 8February 2016).
Findt, K., Scott, D.B., Lindfeld, C., 2014. Sub-Saharan Africa Power Outlook 2014.Gratwick, K.N., Eberhard, A., 2008. Demise of the standard model for power sector
reform and the emergence of hybrid power markets. Energy Policy 36, 3948–3960.http://dx.doi.org/10.1016/j.enpol.2008.07.021.
Huang, Z., Chen, X., 2016. Is China Building Africa? Eur. Financ. Rev.International Energy Agency, 2015. World Energy Outlook 2015 - Executive Summary -
English Version. Paris, France.
International Energy Agency, 2016. Boosting the Power Sector in Sub-Saharan Africa:China’s Involvement. Paris, France.
International Finance Corporation, 2016. Scaling Solar Delivers Low-Cost Clean Energyfor Zambia [WWW Document]. URL ⟨http://www.ifc.org/wps/wcm/connect/news_ext_content/ifc_external_corporate_site/news+and+events/news/scaling+solar+delivers+low+cost+clean+energy+for+zambia⟩.
Jamasb, T., Mota, R., Newbery, D., Pollitt, M., 2005. Electricity sector reform indeveloping countries : a survey of empirical evidence on determinants andperformance, Policy Research Working Paper Series. The World Bank, World BankPolicy Research Working Paper Series 3549.
Kapika, J., Eberhard, A.A., 2013. Power-Sector Reform and Regulation in Africa: LessonsFrom Kenya, Tanzania, Uganda, Zambia, Namibia and Ghana. Human SciencesResearch Council, Cape Town.
Malgas, I., Eberhard, A., 2011. Hybrid power markets in Africa: generation planning,procurement and contracting challenges. Energy Policy 39, 3191–3198.
Marks, J., Ford, M., Marks, D., Slater, D., 2016. Africa-EU Energy Partnership StatusReport Update: 2016. Eschborn, Germany.
Mecagni, M., Canales-Kriljenko, J.I., Gueye, C.A., Mu, Y., Yabara, M., Weber, S., 2014.Issuing International Sovereign Bonds Opportunities and Challenges for Sub-Saharan Africa (African De. ed.). International Monetary Fund, Washington, DC.
Meyer, R., Tenenbaum, B., Hosier, R., 2015. Promoting Solar Energy Through Auctions:The Case of Uganda. The World Bank Group, 100982.
Quitzow, R., Roehkasten, S., Jacobs, D., Bayer, B., Jamea, E., Waweru, Y., Matschoss, P.,2016. The Future of Africa Energy Supply: Potentials and Development Options forRenewable Energy, IASS Study. Potsdam, Germany.
REN21, 2012. Renewables 2012: Global Status Report. Paris.REN21, 2016. Renewables 2016: Global Status Report. Paris, France.Sibanda, Z., MacInnis, L., 2016. World Bank Group’s Scaling Solar to Give Madagascar a
Clean Power Boost [WWW Document]. IFC Press Release. URL ⟨http://ifcextapps.ifc.org/ifcext%5Cpressroom%5Cifcpressroom.nsf%5C0%5C00E711964F470A4E85257F7D005866B4⟩ (Accessed 8 February 2016).
U.S. EIA, 2014. International Energy Statistics.Victor, D.G., Heller, T.C., 2007. The Political Economy of Power Sector Reform: The
Experiences of Five Major Developing Countries. Cambridge University Press,Cambridge.
A. Eberhard et al. Energy Policy 108 (2017) 390–424
424