Increasing the Efficiency of UPS Systems – And Proving It! Richard L. Sawyer Director, Critical...
-
Upload
holly-dolphin -
Category
Documents
-
view
216 -
download
0
Transcript of Increasing the Efficiency of UPS Systems – And Proving It! Richard L. Sawyer Director, Critical...
Increasing the Efficiency of UPS Systems – And Proving It!Richard L. SawyerDirector, Critical Facilities AssuranceEYP Mission Critical Facilitieswww.eypmcf.com
Conference nameConference date
The Problem
| 60% of US Energy bill is in buildings.| Energy consumed by data centers more than
doubled between 2000 and 2005 – J. Koomey, Stanford University.
| U.S. Data center electrical bills totaled $2.7 Billion in 2005.
| A single, moderate size server in a data center has the same carbon foot print as a SUV that gets 15 MPG (R.Muirhead, Data Center Journal).
| A single rack with 6 Blade Server units consumes as much power as 3 kitchen electric ranges (24-30Kw)!
Conference nameConference date
Relative Power Densities
0
100
200
300
400
500
Watts/Sq.Ft.
StandardOffice
Building
MainframeData
Center
ModernServerData
Center
SuperData
Centers
Power Density
Conference nameConference date
21st Century Computing – Blade Servers
Power = Up to 6 kW per Blade chassis or 30 kW per rack
Conference nameConference date
Where does the power go?
0%
5%
10%
15%
20%
25%
30%
35%
UPS = 18%
Actual IT Load is 30% of Power Consumed
APC-MGE: Neil Rasmussen
Conference nameConference date
DISTORTION
SPIKE
SWELL
SAG
OUTAGE
Lightning StrikesFaulty SwitchgearStormsHigh WindsFalling TreesTraffic Accidents
Faulty SwitchgearHeavy LoadsPoor Distribution
Poor Distribution
Switching OperationsPoor FiltersFaulty Load Eq.Static ElectricityRF Interference
Harmonics/Electronic LoadsPoor Distribution
FREQUENCYMajor UtilityProblemsFaultyGenerator
INPUT POWERFROM
UTILITY/GENERATOR
UPSOUTPUT POWER
PURPOSES OF UNINTERRUPTIBLE POWER SUPPLY
1.Maintain clean, uninterrupted power during utility events2.Power Conditioning3.Isolation from other electrical loads4.Separately Derived Source of Power
Conference nameConference date
Strategy to Improve UPS Efficiency
| Technology: Make the units more efficient.
| Selection: Size the units more closely to the load.
| Application: Use redundancy only where it is needed.
IBM Blue Gene 1.2 Megawatt
Understanding UPS Inefficiency Factors
No-Load LossesProportional LossesSquare-Law Losses
Paying the price to process power!
Conference nameConference date
EPRI Efficiency Curves for UPS Products
Conference nameConference date
100%
90%
80%
70%
60%
50%
40%
30%
20%
10%
0%100%90%80%70%60%50%40%30%20%10%0%
UPSEfficiency
Nominal 92% efficiency only applies Nominal 92% efficiency only applies when UPS load is over 70%when UPS load is over 70%
Below 30% loadBelow 30% loadefficiency drops rapidlyefficiency drops rapidly
UPS Load% of full power rating
Typical UPS efficiency curve
Conference nameConference date
UPS
Bypass B
Static
Switch
PDU
Primary Bus A Primary Bus B
UPSUPS UPS UPS UPS
Bypass A
UPS Output 2A UPS Output 2B
13.5 KV
480
13.5 KV
480
Load Bank
Load Bank
Subsystem Bus A Subsystem Bus B
Critical Load Bus A Critical Load Bus B
Static
Switch
PDU
Each side must have capacity to support both critical loads but maintain redundancy.
Total load cannot exceed capacity of 2 UPS Modules.
EFFECTIVE DESIGN LOAD = 33% of total capacity, maximum.
Critical Load
2(N+1) System
Conference nameConference date
Aggregate UPS Power Losses
No-load portion of loss stays constant from full load all the way down to zero load
{
}
No-load loss is present even at no load
Many data centers operate in this rangeoperate in this range
UPS load% of full power rating
100%90%80%70%60%50%40%30%20%10%0%
Power delivered to load
UPS internal power consumption (loss) 93.4%93.4%
93.3%93.3%
93.1%93.1%
92.8%92.8%
92.4%92.4%
91.8%91.8%
90.7%90.7%
88.9%88.9%
85.5%85.5%
76.4%76.4%
0%0%
EFFICIENCY
}
Proportional and square losses
Conference nameConference date
No Load Losses
| Definition: The power consumed by the UPS at 0% load just to keep the UPS operating.
| Sources – Transformers, capacitors, logic systems, fans, communications cards.
| Sometimes referred to as “tare”, “constant”, “fixed”, “shunt” and “parallel” losses.
| Most significant inefficiency: Accounts for up to 40% of UPS losses.
Conference nameConference date
Proportional Losses
| Definition: The power needed to process more power through the UPS.
| Sources – Switching losses, capacitor and inductor impedance, internal resistance
| Proportional losses increase as the output load the UPS support increases.
| Proportional losses are directly related to the topology (internal design) of the UPS.
Conference nameConference date
Square - Law Losses
| Definition: Losses related to the amount of current flowing through the UPS.
| Power is the result of voltage times the current.
| Current does the work, and power is lost as the amount of current flowing increases, by a square factor, hence “square – law losses”.
| Power loss is in the form of heat.
| Square-Law losses are 1% to 4% at higher load levels.
Conference nameConference date
Power Loss Component Graph
No Load
Electrical Loss in kW(Waste due to inefficiency)
Equipment Loading
Full Load
50% 10% 30% 90% 70%
NO-LOADNO-LOAD loss
PROPORTIONALPROPORTIONAL loss
SQUARE-LAW SQUARE-LAW loss
Conference nameConference date
0kW
10kW
Equipment Loading
UPS A TOTAL LOSS
UPS B TOTAL LOSS
Example: Two different 100kW UPSs with 92% nameplate (full-load) efficiency
50%
UPS A No-load loss
UPS B No-load loss
UPS B has higher proportional loss (steeper line) but lower no-load loss
10% 30% 90% 70%
Loading where most data centers operate
Electrical Loss
(Waste due to inefficiency)
Two devices with same nameplate efficiency can have significantly different losses in actual operating range, due to the particular characteristics of their PROPORTIONAL and NO-LOAD losses
No Load
Full Load
Same nameplate efficiency (full-load loss)
But different performance at actual operating load
Conference nameConference date
0kW
10kW
Equipment Loading
UPS A TOTAL LOSS
UPS B TOTAL LOSS
Example: Two 100kW UPSs with same 92% nameplate (full-load) efficiency
50%
UPS A No-load loss
UPS B No-load loss
UPS B has higher proportional loss (steeper line) but lower no-load loss
10% 30% 90% 70%
Loading where most data centers operate
Electrical Loss
(Waste due to inefficiency)
No Load
Full Load
One device can even have WORSE nameplate efficiency than another, yet have lower loss in actual operating range, if it has a low NO-LOAD loss
UPS AA has better nameplate efficiency (lower full-load loss)
But UPS BB performs better at actual operating load
AB
Improving Efficiency
TechnologySelection
Application
Conference nameConference date
Total loss before improvement
Total loss after improvement
Loading where most data centers operate
0kW
10kW
Electrical Loss
(Waste due to inefficiency)
Equipment Loading
Effect of lowering NO-LOAD LOSSNO-LOAD LOSS
OriginalNo-load loss
Lowered No-load loss
Example: 100kW UPS with 92% full-load efficiency
Electric bill savings
But waste is roughly cut in half in actual operating range
50% 10% 30% 90% 70%
Nameplateefficiency goes from
92% to 94.5%
Same improvement in nameplate efficiency
No Load
Full Load
Improving Efficiency – Fixing No-Load Loss
Conference nameConference date
Loading where most data centers operate
0kW
10kW
Electrical Loss
(Waste due to inefficiency)
Equipment Loading
Effect of lowering PROPORTIONAL LOSSPROPORTIONAL LOSS Example: 100kW UPS with 92% full-load efficiency
Electric bill savings
Waste is reduced by 10-20% in actual operating range
50% 10% 30% 90% 70%
Nameplateefficiency goes from
92% to 94.5%
Total loss before improvement
Total loss after improvement
(UnchangedNo-load loss)
No Load
Full Load
Improving Efficiency – Fixing Proportional Loss
Conference nameConference date
Application Efficiency – Zoned Redundancy
M
M
CRAC CRAC CRAC CRAC
pdu
UPS
ColdAisle
pdu
UPS
HotAisle
pdu
UPS
pdu
UPS
FIRE
SECUR
HEATREJECT
HEATREJECT
EPO
SYSTEMMONITOR
WEBLINK
Site Availability – 99.995%
$2,000+ per square foot
HotAisle
ColdAisle
ColdAisle
CRACUPS
Battery
Central UPS for one “N” side,
scalable, modular system
Rack Based UPS Systems as needed for 2N redundancy
Commissioning UPS Systems
AvailabilityThe Cost of Downtime
The Value of Commssioning
Conference nameConference date
Data Center Tier Ratings
Tier 1
No Generator
Basic UPS for IDF Room,
non-redundant
Single Utility or on Radial line from Loop
99.671% *
Tier 2
Generator
N+1 UPS with redundant components
Single Utility Feeders, N+1 Mechanical
System
99.741%
Tier 3- Concurrently Maintainable
N+1 Generator System
N+1 UPS with redundant components
One Active, One Passive, Utility Source, N+1
Mechanical System
99.982%
Tier 4- Fault Tolerant
2N Generator System
2N UPS Systems
Dual Active Utility Feeders, 2N
Mechanical System, compartmentalization
99.995%
* The Uptime Institute
Conference nameConference date
Maximizing Availability
Availability =Total Time - Downtime
Total Time
• The only variable is Downtime
• Downtime sources: Equipment Failures, Human Error, External Causes, Maintenance
Cost of Downtime drives the Value of CFA!
Conference nameConference date
What does Downtime Cost?
Conference nameConference date
Infant Mortality Period End-of- Life Period
Fai
lure
Rat
e
Time (Data Center Life Span)
The Reliability Curve for equipment (IEEE)
“The Bathtub Curve”
High Probability of Downtime
Conference nameConference date
Infant Mortality Period End-of- Life Period
Fai
lure
s
Time
The Value of Commissioning
Minimize
Conference nameConference date
Commissioning UPS Systems
| Verify the full load performance of each module using load banks – typical burn in is 4 hours at rated KW load (hint: infrared inspections of all connections).
| Measure and verify the efficiency in the full operating range at 5%, 10%, 15%, 20%, 25%..........
| Verify system redundancy under design load levels.
| Verify failure modes (under-voltage transfers, bypass transfers, over load shutdown).
| Verify isolation modes for concurrent maintenance.
Assuring you get the reliability and efficiency you pay for!
Questions?
Richard L. [email protected]