In-Situ Load Test of High Capacity Micropiles_Paper
description
Transcript of In-Situ Load Test of High Capacity Micropiles_Paper
![Page 1: In-Situ Load Test of High Capacity Micropiles_Paper](https://reader036.fdocuments.us/reader036/viewer/2022082409/5695d1bb1a28ab9b0297b6c4/html5/thumbnails/1.jpg)
IWM 5th 2002 In VeniceSession V
In-situ Load Test of High Capacity Micropiles foundation on mountain ground
In-situ Load Test of High Capacity Micropiles foundation on mountain ground
Masao Sagara *
Kouichiro Shito** Yoshinori Igase** Gaku Ohashi**
Etsuro Saito* Terukatsu Sasaya* Toshihisa Hatano*
Yoshito Maeda***
* FUJITA Corporation, Technology Development Division
** Japan Highway Public Corporation
***Professor of Kyushu Kyoritsu University, Development of Civil Engineering
Abstract
In general, the caisson type pile method is used on the mountain ground. However, there are
some problems in the caisson type pile method. The High Capacity Micropiles method is
expected as a method of taking the place of the caisson type pile method. This Paper describes
“In-situ Load Test of High Capacity Micropiles foundation on mountain ground”. The following
findings were obtained by the experiment.
1) It is possible to construct HMP in the bedrock ground. It has enough bearing capacity.
2) The Bearing capacity is transmitted from the upper part to the lower side. End bearing
capacity of HMP was confirmed.
3) The Bearing capacity is transmitted from the upper part to the lower side.
4) More batter piles than the straight piles are stronger.
5) Constructed HMP toe was confirmed by watching.
§1. Introduction
In general, the caisson type pile method is used on the mountain ground. The caisson type pile has
the problem in construction such as needing the installation of the digging machine on a narrow site.
Moreover, there is a problem in the environmental, which should be dispose of the dug gravel etc.,
too.
On the other hand, the High Capacity Micropiles method is known generically of the
cast-in-place pile of 300mm or less. The construction machine of the High
Capacity Micropiles method is small. It is suitable for construction on a narrow site.
Because the diameter of High Capacity Micropile is small, the digging soil volume
8/1Fujita Corporation
![Page 2: In-Situ Load Test of High Capacity Micropiles_Paper](https://reader036.fdocuments.us/reader036/viewer/2022082409/5695d1bb1a28ab9b0297b6c4/html5/thumbnails/2.jpg)
IWM 5th 2002 In VeniceSession V
In-situ Load Test of High Capacity Micropiles foundation on mountain ground
is also comparatively few. It is an expected method as a foundation pile in the
mountain ground. We are researching for High Capacity Micropiles method
(hereafter, HMP) which uses the high strength steel pipe, the deformed bar, and
the grout material. We have aimed to examine the applicability of HMP on the
mountain ground. I reported on “Lateral Loading Test for a Model of Micropiles
Foundation on slope ground" in IWM 2001. This Paper describes “In-situ Load Test of
High Capacity Micropiles foundation on mountain ground” and “ Confirmation of constructed
HMP toe ”.
§2. Test pile of HMP and Ground Condition
8/2Fujita Corporation
Table 1 The material of HMPmaterial specification
Steel pipe
The high strength steel pipe (API-N80) 、 Outside diameter =φ177.8mm,Thickness =12.7mm, Standard length =1,500mm, Yield Strength =550N/mm2, Elasticity coefficient =2.0×105N/mm2,
Deformed bar
Yield Strength =490N/mm2(SD490) Calling diameter=51mm(D51), Elasticity coefficient =2.0×105N/mm2,
GroutingCement ( cement water ratio W/C=50% ) , High-early-strength portland cement, Design Strength=30N/mm2, Elasticity coefficient =1.36×104/mm2(result of test)
Bond of HMP
Drilling diameter 205mm, Bond length=4000㎜(vertical pile),4061㎜(batter pile),
D強風化泥岩
8000
4000
4000
bearingstratum
900(5D)
7500
300
9500
1700
2362
4062
1077
2326
1674
8000
4000
4000
2500
1500
9000
6000
500
500500250
1250
a Test pile()(batter pile 10° )
b Test pile()(vertical pile)
311295
1356
1000
weatheringmudstone
crushedmudstone
mudstone
mudstone
crushed mudstone
mudstone
0
1
2
3
4
5
6
7
8
9
10
11
12
13
14
0 10 20 30 40 50
50/ 17
50/ 16
50/ 8
50/ 8
50/ 10
50/ 4
50/ 4
50/ 4
50/ 0
50/ 2
50/ 0
50/ 0
very weatheringmudstone
N Value
Figure1 The outline of geological column and the test pile of HMP
![Page 3: In-Situ Load Test of High Capacity Micropiles_Paper](https://reader036.fdocuments.us/reader036/viewer/2022082409/5695d1bb1a28ab9b0297b6c4/html5/thumbnails/3.jpg)
IWM 5th 2002 In VeniceSession V
In-situ Load Test of High Capacity Micropiles foundation on mountain ground
The material of HMP is shown in Table1. The load test of HMP was done in the bedrock ground on
the Nakaissiki bridge construction site in the second Toumei expressway of Japan Highway Public
Corporation. After the load test of HMP, caisson type pile of 13.5m in diameter and 16.5m in depth
will be constructed in the place. Therefore, there is no problem even if HMP is dug up. The outline
of geological column and the test pile of HMP are shown in Figure1. The stratum up to -1.17m in the
underground is weathering mudstone like the sand of the clay mixing. As for the stratum from -
1.17m in the underground to -2.8m, weathering becomes weak more than stratums located up.
However, it is weak mudstone, which has a lot of crack, and becomes crushed gravel easily. The
rock from -2.8m in the underground to -5.6m is fresh. However, there are some cracks. The stratum
at deeper position than -5.6m in the underground is fresh mudstone with little weathering.
8/3Fujita Corporation
500
500
500
500
500
500
500
1000
1500
1000
1300
200
8500
700
700
700
400
550
750
2000
2000
500
200
8500
10゚
508
508
508
508
508
508
1015
1523
1015
1320
203
Sec t ion ①
Sec t ion ②
Sec t ion ③
Sec t ion ④
Sec t ion ⑤
Sec t ion ⑥
Sec t ion ⑦
Sec t ion ⑧
Sec t ion ⑨ Sec t ion ⑪
Sec t ion ⑩
Sec t ion ⑨
Sec t ion ⑧
Sec t ion ⑦
Sec t ion ⑥
Sec t ion ⑤
Sec t ion ④
Sec t ion ③
Sec t ion ②
Sec t ion ① Sec t ion ①
Sec t ion ②
Sec t ion ③
Sec t ion ④
Sec t ion ⑤
Sec t ion ⑥
Sec t ion ⑦
Sec t ion ⑧
Sec t ion ⑨
Sec t ion ⑩
Sec t ion ⑪
Bond
leng
th4
.061
m
Bond
leng
th4
.0m
Bond
leng
th4
.0m
G rou t ing
De fo rmed ba r ,
H igh s t reng th s tee l p ipe
A l te rna t ing Ve r t ica l Load ing Tes t P i leVe r t ica l Load ing Tes t P i le
A l te rna t ing La te ra l Load ing Tes t P i le
A l te rna t ing La te ra l Load ing Tes t fo r a coup le o f ba t te r p i les
Figure2 Test Piles
![Page 4: In-Situ Load Test of High Capacity Micropiles_Paper](https://reader036.fdocuments.us/reader036/viewer/2022082409/5695d1bb1a28ab9b0297b6c4/html5/thumbnails/4.jpg)
IWM 5th 2002 In VeniceSession V
In-situ Load Test of High Capacity Micropiles foundation on mountain ground
8/4Fujita Corporation
0
20
40
60
80
100
0 1000 2000 3000 4000 5000Load (kN)P
Dis
pla
cem
ent
(m
m)
S
Yield bearing capacity2100kN
Ultimate bearing capacity4100kN
Fig.3 The relation of load-vertical displacement
0
1
2
3
4
5
6
7
8
9
0 1000 2000 3000 4000 5000Axis force (kN)
Depth
(
)m
Fig.4 The axis force
0
1000
2000
3000
4000
5000
6000
0 10 20 30 40 50Relative displacement δ (mm)
Ski
n f
rict
ion s
tress
τ(k
N/m2 )
① ②Section~② ③Section~③ ④Section~④ ⑤Section~⑤ ⑥Section~⑥ ⑦Section~⑦ ⑧Section~⑧ ⑨Section~
ultimatebearingcapacity
yieldbearingcapacity
Fig.5 The relation between skin friction stress and displacement
![Page 5: In-Situ Load Test of High Capacity Micropiles_Paper](https://reader036.fdocuments.us/reader036/viewer/2022082409/5695d1bb1a28ab9b0297b6c4/html5/thumbnails/5.jpg)
IWM 5th 2002 In VeniceSession V
In-situ Load Test of High Capacity Micropiles foundation on mountain ground
§3. Outline of the Loading Test for the HMP
The test piles of the full-scale HMP were constructed, and vertical loading test, alternating vertical
loading test, alternating lateral loading test, alternating lateral loading test for a couple of batter piles
were done. Details of the test piles of HMP are shown in Figure2. The confirmation of the
constructed paling targeted healthy anchor piles. Healthy anchor piles were targeted for the
confirmation of the constructed HMP. HMP were dug up by the casing drilling of 600 ㎜ diameter.
We confirmed HMP toe by watching.
§4. Result of The Loading Test
4.1 Vertical Loading Test
Figure 3 shows the relation of load-vertical displacement. The vertical yield bearing capacity is
2100kN when the pile top displacement is 12.4㎜. The vertical ultimate bearing capacity is 4100kN
when the pile top displacement is 60.0㎜. 60 ㎜ is the amounts of the displacement of about 30% of
the diameter of HMP. The surroundings area of bond length, counted divides ultimate bearing
capacity, and the obtained value is skin friction stress. Skin friction stress of the average is
1524kN/m2. This value corresponds to skin friction stress of hard rock in the ground anchor standard
(The Japanese Geotechnical Society). The axis force chart is shown in Figure4. The value with a
very big warp was indicated in the boundary part of the steel pipe and the deformed bar (⑥
from section ⑤) while becoming near yield bearing capacity. Because it seemed an abnormal value,
the revised value is indicated in figure. It is understood that bearing capacity is supported with bond
part of 5-8m in depth. And, we understood that bearing capacity is transmitted from the upper part to
pile toe in bond part of HMP. The axis force of about 800kN was confirmed in the pile toe, and end-
bearing capacity of HMP was confirmed in the bedrock ground when it is the vertical ultimate
bearing capacity. The relation between skin friction stress and displacement is shown in Figure5.
Skin friction stress indicates a big value in ⑦-⑧ section and ⑧-⑨section at the vertical ultimate
bearing capacity, and it is understood that the HMP is supported in ⑦-⑧ section.
8/5Fujita Corporation
![Page 6: In-Situ Load Test of High Capacity Micropiles_Paper](https://reader036.fdocuments.us/reader036/viewer/2022082409/5695d1bb1a28ab9b0297b6c4/html5/thumbnails/6.jpg)
IWM 5th 2002 In VeniceSession V
In-situ Load Test of High Capacity Micropiles foundation on mountain ground
4.2 Alternating Vertical Loading Test
Result of alternating vertical loading test is shown in Figure6. Both the pulling yield bearing
capacity and the pushing yield bearing capacity is 1200kN. Pulling resistance of HMP is 1800kN
when the pile top displacement is 20㎜. It is the amounts of the displacement of about 10% of the
diameter of HMP. When pulled when the paling is pushed, the inclination of stress-displacement is
equal. The relation between skin friction stress and the amount of relative displacement at the time of
8/6Fujita Corporation
-40
-20
0
20
40
60
80
100
-2000 -1000 0 1000 2000Load (kN)P
Dis
pla
cem
ent
(m
m)
SPullPush
up
down
Fig.6 Result of alternating vertical loading test
0
500
1000
1500
2000
2500
0 1 2 3 4
Relative displacement δ (mm)
Ski
n fric
tion
str
ess
τ
(k
N/m
2 )
① ②Section~
② ③Section~
③ ④Section~
④ ⑤Section~
⑤ ⑥Section~
⑥ ⑦Section~
⑦ ⑧Section~
⑧ ⑨Section~
Pull
yieldbearingcapacity
Fig.7 skin friction stress and the amount of relative displacement
![Page 7: In-Situ Load Test of High Capacity Micropiles_Paper](https://reader036.fdocuments.us/reader036/viewer/2022082409/5695d1bb1a28ab9b0297b6c4/html5/thumbnails/7.jpg)
IWM 5th 2002 In VeniceSession V
In-situ Load Test of High Capacity Micropiles foundation on mountain ground
pulling out is shown in Figure7. Skin friction stress increases in ⑦-⑧ section and ⑧-⑨ section
while the amount of relative displacement is large, and skin friction stress has decreased in ⑤-⑥
section and ⑥-⑦ section when it is pulling yield bearing capacity in Figure7. It is understood that
the bearing capacity has moved from the upper part of bond of HMP to pile toe when the paling is
pulled out.
4.3 Alternating Lateral Loading Test & Alternating Lateral Loading Test for a couple of batter
piles
8/7Fujita Corporation
Table2 The diameter of the HMP toeMeasurement position
(Distance from HMP toe)cm Surroundings
(cm)
Diameter (cm)
(Grout & Deformed bar)(24cm)
----- 24
(Pipe&Grout & Deformed bar) (3.5m)
93 29.6
(Pipe&Grout & Deformed bar) (4m)
94 29.9
Photograph1 Constructed HMP toe
![Page 8: In-Situ Load Test of High Capacity Micropiles_Paper](https://reader036.fdocuments.us/reader036/viewer/2022082409/5695d1bb1a28ab9b0297b6c4/html5/thumbnails/8.jpg)
IWM 5th 2002 In VeniceSession V
In-situ Load Test of High Capacity Micropiles foundation on mountain ground
Result of alternating lateral loading test and
alternating lateral loading test for a couple of
batter piles is shown in Figure8. In the model
test (batter pile angle was 15°) of last year, if
the number of the pile is the same, it is
confirmed that the batter piles have about three
times the horizontal bearing capacity than the
vertical piles. It is confirmed that the batter
piles have about eight times the horizontal
bearing capacity than the vertical piles though
the batter pile angle is 10° in this test.
4.4 Confirmation by watching constructed HMP
The diameter of the HMP of 24 ㎝ is confirmed in the pile toe. On the other hand, the diameter of
the HMP of about 30cm was confirmed in the bond part, which included the steel pipe (Table2 and
photograph1 reference). These values are larger than dug diameter (205 ㎜ ). It is thought that the
extension of the dug hole was secured by the pressed grouting.
§5. Conclusions
The following have been understood from this in-site load test.
1) It was confirmed to be able to construct HMP, and to have enough bearing capacity in the
bedrock.
2) It is understood that the bearing capacity has moved from the upper part of bond of HMP to pile
toe.
3) End bearing capacity of HMP was confirmed in the bedrock ground.
4) The horizontal bearing capacity of batter pile is larger than the vertical pile.
5) The bond of HMP was surely constructed by watching in the bedrock ground.
8/8Fujita Corporation
0
200
400
600
800
1000
1200
1400
1600
1800
0 50 100 150 200 250 300Horizontal displacement(㎜)
Late
ral l
oad(k
N)
Vertical pile
Batter piles 10°
Fig.8 Lateral load-Horizontal displacement