IMPORTS 18072012

download IMPORTS 18072012

of 6

description

IMPORTS 18072012

Transcript of IMPORTS 18072012

  • TARIFF FOR CFS-IMPORTS- revised wef 18/07/2012

    20' 40'

    1 Import Cargo / UPTO 23 TON

    LOAD OUT Delivery (without De Stuffing) Up To 23 Ton

    Transport of Laden Containers from CCTL to CFS, PNR 5075 7025

    Processing, Laden Containers Lift Off, Inspection, Laden

    Lift On to partys vehicle for Load out delivery

    (If de-stuffing is required for Customs Inspection,

    it will be charged at extra as applicable)

    DE STUFFING Delivery Up To 23 Ton

    Transport of Laden Containers from CCTL to CFS, PNR 5750 8500

    Processing, Laden Containers Lift Off, Inspection, De-

    stuffing of the cargo, Direct loading of cargo into truck,

    Empty Container Lift On to partys vehicle

    2 Import Cargo / Above 23 TON

    LOAD OUT Delivery (without De Stuffing) Above 23 Ton

    Transport of Laden Containers from CCTL to CFS, PNR

    Processing, Laden Containers Lift Off, Inspection, Laden

    Lift On to partys vehicle for Load out delivery. 5575 7225

    (If de-stuffing is required for Customs Inspection,

    it will be charged at extra as applicable)

    DE STUFFING Delivery Above 23 Ton

    Transport of Laden Containers from CCTL to CFS, PNR

    Processing, Laden Containers Lift Off, Inspection,

    Destuffing of the cargo,Empty Container Lift on to

    partys vehicle. 6550 9025

    Revision 10 dt 18/07/2012Page 1 of 6

  • 3 Import Hazardous & Reefer Cargo / Upto 23 TON

    LOAD OUT Delivery (without De Stuffing) Above 23 Ton

    Transport of Laden Containers from CCTL to CFS, PNR

    Processing, Laden Containers Lift Off, Inspection, Laden

    Lift On to partys vehicle for Load out delivery. 6600 9135

    (If de-stuffing is required for Customs Inspection,

    it will be charged at extra as applicable)

    DE STUFFING Delivery Upto 23 Ton

    Transport of Laden Containers from CCTL to CFS, PNR

    Processing, Laden Containers Lift Off, Inspection,

    Destuffing of the cargo,Empty Container Lift on to

    partys vehicle. 7475 11050

    4 Import Hazardous & Reefer Cargo / Above 23 TON

    LOAD OUT Delivery (without De Stuffing) Above 23 Ton

    Transport of Laden Containers from CCTL to CFS, PNR

    Processing, Laden Containers Lift Off, Inspection, Laden

    Lift On to partys vehicle for Load out delivery. 7250 9400

    (If de-stuffing is required for Customs Inspection,

    it will be charged at extra as applicable)

    DE STUFFING Delivery Above 23 Ton

    Transport of Laden Containers from CCTL to CFS, PNR

    Processing, Laden Containers Lift Off, Inspection,

    Destuffing of the cargo,Empty Container Lift on to

    partys vehicle. 8515 11735

    5 Additional Charges for

    Polluting, Dusty & Fine Powder Cargo 950 1900

    Revision 10 dt 18/07/2012Page 2 of 6

  • 6 Empty Container Transportation

    Movement of Empty Container

    To Gesa Plot 1350 2100

    To other Plots ( at CFSs' discretion) 1550 3000

    7 Laden Container Storage Charges per day 20' 40'

    (General Cargo)

    1st day 3rd day (Free Slab) 0 0

    4th day 7th day 200 400

    8th day 12th day 450 900

    13th day 30th day 800 1600

    31st day 60th day 1100 2200

    61st day 90th day 1350 2700

    From 91st day onwards 1450 2900

    Laden Container Storage Charges per day

    for ENBLOCK

    1st day 7th day 200 400

    8th day 12th day 450 900

    13th day 30th day 800 1600

    31st day 60th day 1100 2200

    61st day 90th day 1350 2700

    From 91st day onwards 1450 2900

    Scrap Import

    1st day 3rd day (Free Slab) 0 0

    4th day 7th day 250 500

    8th day 12th day 500 1000

    13th day 30th day 900 1800

    31st day 60th day 1300 2650

    61st day 90th day 1650 3350

    From 91st day onwards 1750 3500

    Revision 10 dt 18/07/2012Page 3 of 6

  • 8 Charges for Goods warehoused under Sec 49 of Customs Act/

    Detained Goods

    a Storage Charges: Maximum of

    1 Rs.500/Grid/Week 1 Grid = 4 CBM

    or 2 Rs.550/M.T/Week

    Four weeks storage charges to be collected at the time of warehousing.

    b Destuffing Charges

    Manual 1300 2000

    Mechanical (upto 3 M.T) 2500 3500

    Above 3 M.T Crane Charges will also be applicable

    c Delivery Charges

    Upto 3 M.T Rs.80/ M.T ( MIN Rs.650)

    Above 3 M.T Rs.160/M.T ( Min Rs.1500)

    d Shifting of cargo within ware house- Rs.80/ M.T. (Min Rs.650)

    9 OTHERS FOR EXPORT OR IMPORT 20' 40'

    a Empty Con. Storage charges per Day 100 200

    b Laden Cont. Lift on/ Lift Off 725 1050

    c Empty Cont. Lift on/ Lift Off 225 400

    d 25% or above Examination Charges

    Manual & Mechanical 1500 2200

    e 100% Examination Charges ( General Cargo)

    Mechanical & Manual De Stuffing and Loading into the Container

    2100 3100

    f Auction Cargo ( per container)

    Handling and delivery expenses

    (Valuation & NOC Charges will also be applicable)

    Rs 7500.00

    Revision 10 dt 18/07/2012Page 4 of 6

  • g Crane charges if any will be extra as follows:

    Fork lift - 3M.T Rs 440 per hour or part thereof.

    Crane 5M.T capacity Rs.800 per hour or part thereof

    Crane 12M.T capacity Rs.980 per hour or part thereof

    Crane 40M.T capacity Rs.2950 per hour or part thereof

    20' 40'

    h Examination-Second & Subsequent Open Order 1025 1525

    ( for each operation)

    j Reefer Containers 20' 40'

    (per shift of 8 hours or part thereof)

    Electrical & Monitoring Charges per Shift 1550 2550

    k Weighment Charges

    l Additional transporation charges may apply for Over Dimensional Cargo./

    Reefer Cont. with Gen Set.

    20' 40'

    m Trailer Detention (Intercarting) 1250 1750

    (For a period of 3 hours)

    (For further detention Rs.300/ hour.)

    n Service tax and other statutory charges, as applicable, will be extra

    o 45' Container - Handling and Storage Charges at 125% of 40' container DC rates.

    p CFS Billing Cycle is from 0600 hrs (6 a.m. on day one) to 0559hrs of the next day.

    q Special Services for Hazardous & Reefer Containers-. handling and storage at 125%

    of DC container rates.

    r ODC Container handling at 125% of DC container rates and Storage charges for OT/FR/

    Platform and other ODC/OOG Cargo will be charged at twice the rate of DC Containers.

    150

    per operation

    Revision 10 dt 18/07/2012Page 5 of 6

  • s ODC- Additional Transportation Charges will be charged on a case to case basis.

    t Empty cont storage charges and Empty Lift On charges will be applicable in case empties

    are picked up after the free period of 1 day from destuffing.

    u Additional charges for Containers arriving with more than permissible weight will be decided

    on a case to case basis.

    v Fuel Surcharge wef 18/07/2012 300 600

    w Increase in movement charges w.e.f 05/11/2011 1000 2000

    x Insurance Charges 200 400

    y Import- Energy Surcharge wef 18/07/2012 400 650

    z Additional de-stuffing charges will be applicable for specialised/Over Dimensional cargo/

    fragile/delicate/ hazardous cargo. Prior intimation to be given for making arrangement

    to de-stuff.

    Revision 10 dt 18/07/2012Page 6 of 6