Impact of energy supply infrastructure in life cycle analysis of hydrogen and electric systems...
-
Upload
alexandre-lucas -
Category
Documents
-
view
214 -
download
0
Transcript of Impact of energy supply infrastructure in life cycle analysis of hydrogen and electric systems...
ww.sciencedirect.com
i n t e r n a t i o n a l j o u r n a l o f h y d r o g e n en e r g y 3 7 ( 2 0 1 2 ) 1 0 9 7 3e1 0 9 8 5
Available online at w
journal homepage: www.elsevier .com/locate/he
Impact of energy supply infrastructure in life cycle analysisof hydrogen and electric systems applied to the Portuguesetransportation sector
Alexandre Lucas a,*, Rui Costa Neto b, Carla Alexandra Silva b
aMassachusetts Institute of Technology Portugal Program, Avenida Prof. Cavaco Silva, Campus IST e TagusPark, Room e 16.6,
2780-990 Porto Salvo, PortugalbDepartment of Mechanical Engineering, IST-Technical University of Lisbon, Av. Rovisco Pais 1, Pav. Mec. I, 2� andar,
1049-001 Lisboa, Portugal
a r t i c l e i n f o
Article history:
Received 8 November 2011
Received in revised form
25 April 2012
Accepted 26 April 2012
Available online 7 June 2012
Keywords:
Hydrogen
Electric vehicle
Life cycle analysis
Infrastructure
Uncertainty
* Corresponding author. Tel.: þ35 1961741327E-mail addresses: [email protected]
utl.pt (C.A. Silva).0360-3199/$ e see front matter Copyright ªdoi:10.1016/j.ijhydene.2012.04.127
a b s t r a c t
Hydrogen and electric vehicle technologies are being considered as possible solutions to
mitigate environmental burdens and fossil fuel dependency. Life cycle analysis (LCA) of
energy use and emissions has been used with alternative vehicle technologies to assess the
Well-to-Wheel (WTW) fuel cycle or the Cradle-to-Grave (CTG) cycle of a vehicle’s materials.
Fuel infrastructures, however, have thus far been neglected. This study presents an
approach to evaluate energy use and CO2 emissions associated with the construction,
maintenance and decommissioning of energy supply infrastructures using the Portuguese
transportation system as a case study. Five light-duty vehicle technologies are considered:
conventional gasoline and diesel (ICE), pure electric (EV), fuel cell hybrid (FCHEV) and fuel
cell plug-in hybrid (FC-PHEV). With regard to hydrogen supply, two pathways are analysed:
centralised steam methane reforming (SMR) and on-site electrolysis conversion. Fast,
normal and home options are considered for electric chargers. We conclude that energy
supply infrastructures for FC vehicles are the most intensive with 0.03e0.53 MJeq/MJ
emitting 0.7e27.3 g CO2eq/MJ of final fuel. While fossil fuel infrastructures may be
considered negligible (presenting values below 2.5%), alternative technologies are not
negligible when their overall LCA contribution is considered. EV and FCHEV using elec-
trolysis report the highest infrastructure impact from emissions with approximately 8.4%
and 8.3%, respectively. Overall contributions including uncertainty do not go beyond 12%.
Copyright ª 2012, Hydrogen Energy Publications, LLC. Published by Elsevier Ltd. All rights
reserved.
1. Introduction growth in Europe and in the USA has been 8% and 20%,
In the last two decades, world energy use has risen 45%,
drivenmostly by the development in countries such as China,
India and the middle east [1,2]. From 1990 to 2008, the same
..pt, Alexandre.Lucas@efa
2012, Hydrogen Energy P
respectively [1,3]. In Portugal, this increase has been approx-
imately 57%. In 2009, primary energy imports represented
81.2%, making Portugal one of the most exterior energy-
dependent countries in Europe. In the same year, the
cec.com (A. Lucas), [email protected] (R.C. Neto), carla.silva@ist.
ublications, LLC. Published by Elsevier Ltd. All rights reserved.
i n t e rn a t i o n a l j o u r n a l o f h y d r o g e n en e r g y 3 7 ( 2 0 1 2 ) 1 0 9 7 3e1 0 9 8 510974
transportation sector in Portugal accounted for 38.2% of final
energy use. From this percentage, 86% was due to road
transportation [4]. Without substantial changes in policy and
practice, this unsustainable tendency will evidently continue.
In 2009, both the European Union (EU) and G8 leaders
agreed on the long-term goal that CO2 emissions should be cut
by 80% by 2050. However, achievement of this goal means that
95% decarbonisation must be achieved in the road trans-
portation sector [5]. The European 20-20-20 agreement set
ambitious goals for 2020, cutting greenhouse gases by 20%
(compared with 1990 levels), reducing energy use by 20% and
meeting 20% of European energy needs from renewable
energy sources (RES) [3]. Portugal has set its goals even higher,
with 20% efficiency, 60% electricity production from RES and
31% of final energy from RES, with 10% energy use reduction
within the transportation sector [6]. Hydrogen and electricity
have been regarded as possible solutions tomitigate fossil fuel
scarcity and environmental impact. However, hydrogen and
electricity alone cannot directly and unconditionally solve the
problem. Hydrogen in particular, when compared to elec-
tricity, has good filling time and provides a good range of
autonomy, despite the considerable amount of energy asso-
ciated with its compression.
Previous life cycle analysis (LCA) has focused on the fuel
cycle divided into its upstream impact (Well-to-Tank, WTT)
and downstream impact (Tank-to-Wheel, TTW) stages and
has included only fewmaterials typically related to the vehicle
itself (manufacturing, maintenance, end-of-life). The final
report of the Hysociety Project [7] shows an extensive amount
of research work related to LCA studies of hydrogen applied to
the transportation sector. No work refers to the energy supply
infrastructure, including final refuelling stations. Expected
energy use and emissions from passenger car transportation
with different engine technologies in 2020 have been analysed
by [8]. The study covered pure combustion engines (gasoline,
diesel), hybrids combining combustion engines with electrical
engines and fuel cells and battery-powered electric cars. The
study concluded that hybrids with a diesel combustion engine
combinedwith an electrical engine had the lowest energy use,
followed by a hybrid combining a CNG combustion engine
with an electrical engine and a similar hybrid using a gasoline
combustion engine. Reference studies from [9] present
a comprehensive report of WTW, clearly defining the term
WTT as the direct energy use for producing and distributing
the fuel required for propulsion of the vehicle, while TTW
corresponds to the term for direct energy use or propulsion
energy. Estimates are given for several hydrogen pathways,
electricity, and conventional fuels, as well as local or distrib-
uted philosophies. Regarding plug-in hybrids, possible
scenarios of infrastructure implementation and associated
costs are presented by [10]. A similar study for hydrogen
fuelling infrastructure assessment was performed by [11],
elaborating future costs of hydrogen fuel to develop large-
scale facilities. They demonstrate that a hydrogen infra-
structure that could support volume deployment of fuel cell-
electric vehicles can be commercially viable. Another study
by [12] compares and assesses the WTW impact of plug-in
technology with hybrid and conventional technologies
considering different AER (All Electric Range), with pure CD
(charge depletion), blended and CS (charge sustaining) mode.
They conclude that the PHEVs offer reductions in the use of
petroleum energy as compared with regular hybrid electric
vehicles (HEVs). More petroleum energy savings and Green-
house Gas (GHG) emissions reductions were realised as the
AER increased except when the marginal grid mix was
dominated by oil-fired and coal power generation.
The driving cycle considered in the different studies has
also been an issue for review, as the driving cycle is crucial for
a proper comparison between vehicles and estimations. A
consensus remains to be reached among academia, industry
and policy makers because driving behaviours differ from
region to region. Because public policies or decisions are also
often at a regional level, such behaviours have been inter-
esting to assess. Differences should, nevertheless, be well
understood and described. Using a Portuguese driving cycle
[13], estimate WTW and Cradle-to-Grave (CTG) for vehicle
materials impacting a large spectrum of vehicle technologies
in the same study, enhancing the importance of plug-in
vehicle penetration to mitigate both energy and emissions
problems. In another WTW study [14], an energy analysis of
electric vehicles using batteries or fuel cells using the ECE-
EUDC driving cycle was developed. The investigators
conclude that the best results are achieved by pure EVs for
only very limited driving range requirements, while the fuel
cell solutions achieve best performance for more extended
driving ranges where the battery weight becomes too high.
The energy use, emissions and cost of plug-in hybrid vehicles
were evaluated comparing different driving cycles (CAFE,
FTP75, NEDC and JC08), different driving distances and
different user behaviours regarding battery recharging, and
the main characteristics between them were described [15].
In terms of infrastructures, several passenger transport
systems, such as cars, buses, trains and air travel, were ana-
lysed [16]. Energy use and emissions arising from construc-
tion, operation and maintenance of the transport system
infrastructures, in addition to the WTW and CTG stages, were
included in the authors’ analysis. For road transportation,
these infrastructures dealtmostly with roadway construction,
operation and maintenance, which can also be found in [17]
LCA and parking lots. For on-road transportation, the
authors found that the life cycle component contributions are
roughly the same as the GHG contributions and produce
1.4e1.6 times larger life cycle factors than the operational
components. Infrastructures alone ranged from approxi-
mately 7 to 18% in MJ/PKT and CO2eq/PKT in the total LCA for
a conventional gasoline-powered sedan.
Regarding the actual fuel infrastructure, few studies
address direct and indirect energy and emissions contribu-
tions in vehicle LCA [18e20]. A study has identified the envi-
ronmental and economic aspects of hydrogen production
through water electrolysis, using wind power and the Korean
electricity mix, applying wind power and the Korean elec-
tricity mix to FCHEV and has compared them to conventional
fuels (gasoline and diesel) [18]. This study makes a scale-up
inventory from a small H2 station used in California and also
accounts for the wind structure. The authors conclude that
although the wind station may be economically viable, it is
extremely dependent on wind availability.
The first study to address energy supply infrastructures
applied to vehicles, comparing conventional fossil fuels and
i n t e r n a t i o n a l j o u r n a l o f h y d r o g e n en e r g y 3 7 ( 2 0 1 2 ) 1 0 9 7 3e1 0 9 8 5 10975
electricity supply chain facilities, was performed by [19]. The
study focuses on EV technology using estimations for other
LCA stages to assess the weight of infrastructure. Using the
2006 WTT average value from the EU electricity mix, the
impact of the EV energy supply infrastructure did not go
beyond 8%, while conventional fuel infrastructure remained
below 2% impact. The study uses estimated service ratios
based on the foreseen use of public charging facilities and
identifies these variables as sensitive to the results. Never-
theless, this study develops inventories for petrol stations and
charging points and presents a methodology to estimate
energy supply infrastructure impacts, contemplating other
scenarios of WTW and CTG stages.
A brief literature summary was performed and is pre-
sented in Table 1, identifying values for the most highly
influential parameters and differences between the studies.
Due to the use of different vehicle references within a given
technology, one may argue that it would be reasonable to
obtain different results of TTW, WTT or CTG. However, other
factors influence the results as well. One is the lifetime
parameter of kilometres driven, a parameter which can vary
from 150,000 km [13] to 300,000 km [8]. This parameter directly
affects the CTG stage because the absolute values of the LCA
are divided by the lifetime driving distance of the vehicle to
obtain a value per kilometre. Another important parameter is
the Driving Cycle considered in the study, fundamental to
determine the TTW impact. Europe has been adopting the
New European Driving Cycle (NEDC), while many car manu-
facturers still have their own driving cycles. In the USA, the
most common Driving Cycle used is the Federal Test Proce-
dure (FTP). The main differences between cycles are acceler-
ation, velocity and mobility dynamics. Other local or specific
cycles found in the literature can also be used to assess real
scenarios [13]. Within the scope and aim of LCA, although all
studies tend to address energy and emission impacts, not all
studies include the CTG stage [9].
Given the identified lack of assessments of the whole
energy supply infrastructure impacts in the literature, the aim
of this study is to perform a life cycle analysis to estimate
energy use and greenhouse gas emissions associated with the
construction, maintenance and decommissioning of fuel
support facilities for ICE vehicles, EV, FCHEV, FC-PHEV and
their impact in overall vehicle LCA. This LCA is particularly
important when considering alternative technologies with
different pathways to provide policy and decision makers the
most complete set of information about each choice. Despite
being applied to the specific case of Portugal, themethodology
could be extended to other countries, similar to the case of
fuel WTW studies.
2. Methodology
Life cycle analysis, particularly in the case of infrastructure,
raises two major methodological concerns. The first concern
is about system boundaries, where one should, on the one
hand, be cautious not to double-count efforts or activities
already assessed in other stages, and, on the other hand, not
disregard a relevant activity. Another concern deals with how
to allocate burdens to different products with different
energy contents that may share the same facilities. This
study addresses energy infrastructure according to each
technology and pathway. For that reason, roads, traffic signs,
parking lots, repair shops, and car factories were not
considered in this study as they are not a distinctive char-
acteristic between technologies. The principles of ISO 14040
[22] were followed. The methods used were Global Warming
Potential for 100 years (GWP100) and Cumulative Energy
Demand (CED). GWP is based on the heat-absorbing ability of
each gas relative to that of CO2, as well as the decay rate of
each gas, i.e., the amount removed from the atmosphere over
a given number of years [23]. Because infrastructures are
being considered in this study, and given the contribution of
different gases and their ability to linger in the atmosphere
for different time ranges, a 100 year time horizon was
considered. CED methodology was used to investigate the
energy use throughout the life cycle of a good, in this case
infrastructure. The CED methodology is especially suited to
determine and compare the energy intensity of processes,
including the direct as well as the indirect uses of energy.
Indirect energy inputs consider all inputs that are used for
purposes other than manufacturing products, such as infra-
structure and equipment. The Simapro tool [24] allows the
comparison between contributions of different sources.
However, because the goal of the study is to obtain compa-
rable values, the output unit of MJeq was used, assuming
Simapro primary energy conversion factors.
Supply chain scope and boundaries were outlined for the
technologies considered until the vehicle was reached. Three
major groups could be identified: primary fuel handling
infrastructure, end fuel transport system and distribution
facilities.
2.1. Scope
Fig. 1 systematises the boundaries for the base case supply
chain. For the extraction of raw material, an oil well and an
offshore platform were used. For the exploration well, the oil
hydrocarbon probability of concentration in depth formation
varies according to a normal distribution, so the mean value
was considered to be approximately 2,600 m [25], to represent
the depth and the corresponding drilling efforts to explore
a North Sea well. Despite the existence of two refineries in
Portugal, only Sines refinery was used, as this refinery repre-
sents almost the entire share of refining products [26].
Refinery efficiency was considered to be 85% [9]. As Simapro
does not account for construction of office buildings in the
refinery, 50% of the area was taken as ameasure for inventory
of buildings. Roads inside the refinerywere also accounted for.
Storage facilities were omitted. For fuel transportation, the
main existing infrastructure is a multiuse pipeline, so alloca-
tions were made to account only for the gasoline and diesel
share. There were 2.52 thousand refuelling stations in 2010,
and these stations were assumed to satisfy the demand of all
the fleet perfectly. The fleet was composed of 5.63 million
vehicles, of which approximately 3.00 million were gasoline-
powered and 2.63 million were diesel-powered [27]. Mainte-
nance was considered only for the refinery. The electric
infrastructure and H2 production supply chain using the
electrolysis pathway are represented in Fig. 2.
Table 1 e Brief LCA Literature Overview.
Study [9] [8] [13] [21]
Scope and
Aim
CO2eq (100y);
Energy Use;
WTW e 2010þ
CO2eq (100y); Energy Use;
WTW þ CTG for 2020
CO2; Energy Use;
WTW þ CTG
CO2eq (100y); Energy Use;
Criteria pollutants;
WTW þ CTG þ end of life
Software/
database
E3 database
by LBST
ADVISOR; TEDB; EPA;
NHTSA; FHWA 2005; ETH
Zurich Matlab Simulink
CTG e GREET
Copert
Advisor
Ecoscore
Ecoinvent
Technologies ICE; FCHEV ICE; FCHEV; EV ICE; FCHEV; FCPHEV; EV ICE; FCHEV; EV
Pathways Petrol and diesel
EU Mix
SMR:yes
Electrolysis:yes
Others
Petrol and diesel US Mix
SMR decentralized for H2
conversion; US average
mix for electricity
EU fossil fuel Mix
EU Electric Mix
SMR centralized
(a) Electrolysis
decentralized (b); Others
SMR:yes
Electric Mix BE and EU Mix
Power/Weight
t ratio (W/kg)
PISI- 65
DISI- 54
DICI-54
FC:54
Base SI:75
Adva. SI ICE:75
Adva. CI ICE:75
EV:75
FC:75
Petrol:75
diesel:55
EV:54
FCHEV:54
FCPHEV:57
Base SI:75
Adva. SI ICE:75
Adva. CI ICE 75
EV:75
FCHEV:59
Driving Cycle
Uncertainty
NEDC; Yes FTP; Yes Lisbon to Cascais; No NEDC; Yes
TTW PISI:1.90 Base SI:1.75 Petrol:1.96
DISI:1.88 Adva. SI ICE:1.54 diesel:1.67 Petrol: 1.98
DICI:1.61 Adva. CI ICE:1.35 FCHEV:1.08 diesel: 1.76
- MJeq/km FCEV:0.94 EV:0.51 FCPHEV:0.55 FCHEV: 1.25
FCHEV :0.81 EV: 0.57 EV: 0.54
- gCO2eq/km PISI:140.3 Base SI:126.0 Petrol:143.0 Petrol: 144.0
DISI: 138.8 Adva. SI ICE:111.0 diesel:124.4 diesel: 128.0
DICI: 119.7 Adva. CI ICE:103.0 FCHEV, FCPHEV and FCHEV and EV:0.0
FCEV: 0 FCHEV and EV:0.0 EV:0.0
CTG e Base SI:0.22 Petrol:0.48 CTG-End of life treatment
Adva. SI ICE:0.22 diesel:0.50 Petrol:0.28
Adva. CI ICE:0.23 FCHEV:0.73 diesel:0.28
- MJeq/km EV:0.28 FCPHEV:0.77 FCHEV: No ref.
FCHEV:0.27 EV: 0.77 EV:0.56
Base SI: 15.8 Petrol:30.7 CTG-End of life treatment
Adva. SI ICE (Petrol):15.4 diesel:32 Petrol:11.2
- gCO2eq/km e Adva. CI ICE (diesel):16.1 FCHEV:48.4 diesel:12.0
EV:19.1 FCPHEV:49.5 FCHEV: No ref.
FCHEV :18 EV: 47.8 EV:16.1
WTT
- MJeq/km
Crude Oil to Petrol:
0.32 (PISI); 0.32 (DISI)
Crude Oil to Diesel: 0.31
SMR with 4000 km
pipeline: 0.677
EU-mix electricity,
on-site electrolysis:
3.62 (MJx/MJf)
Petrol: 0.37 (Base SI);
0.32 (SI ICE);
diesel: 0.19
Electricity Mix:1.10
On site SMR:0.62
Petrol and diesel:0.27
FCHEV(a):0.62
FCHEV(b):3.89
FCPHEV(a):0.31
FCPHEV(b):1.97
EV: 1.06
Petrol: 0.76
diesel: 0.53
FCHEV: No ref.
EV: 1.18
- gCO2eq/km Petrol: 26.98 (PISI);
26.68 (DISI)
Diesel: 25.61
SMR with 4000 km
pipeline: 92.87;
EU-mix electricity,
on-site electrolysis:
209.1(gCO2/MJf)
Petrol: 31.5 (Base SI);
27.7 (SI ICE);
diesel:16.5
Electricity Mix:101.1
On site SMR:107.0
Petrol:24.5
diesel:23.7
FCHEV(a):95.4
FCHEV(b):223.3
FCPHEV(a):56.7
FCPHEV(b):96.4
EV:72.9
Petrol: 37.0
diesel: 26.0
FCHEV:110.1
EV: 56.5
Lifetime (km) 200,000 300,000 150,000 230,500
Note: (a) centralized Steam Methane Reforming (SMR) pathway; (b) On-site Electrolysis pathway. Port injection spark ignition (PISI), direct
injection spark ignition (DISI), and direct injection compression ignition (DICI). Net energy expended (MJx) (excluding the energy transferred to
the final fuel. Energy of final fuel (MJf).
i n t e rn a t i o n a l j o u r n a l o f h y d r o g e n en e r g y 3 7 ( 2 0 1 2 ) 1 0 9 7 3e1 0 9 8 510976
Each of the power plants composing the electric mix of
2010 in Portugal [28] was assessed. Infrastructure for extrac-
tion of raw materials such as coal, oil and gas was ignored.
Due to the high use of natural gas as a feedstock for power
plants, only the pipeline from Algeria crossing Spain and
Portugal was considered. For allocation purposes, only the
portion sold to Portugal and used by the power plants was
considered [29]. For the power plants, with the identification
Fig. 1 e System boundaries for conventional fossil fuel supply chain.
i n t e r n a t i o n a l j o u r n a l o f h y d r o g e n en e r g y 3 7 ( 2 0 1 2 ) 1 0 9 7 3e1 0 9 8 5 10977
of the feedstock types, the installed capacity of the power
plants and their sold energy, their capacity factor and mix
were determined. For the electric grid stage, 8% losses were
assumed. All 50.6 TWh of 2010 energy [28], without imports
and pumping, transited through the electric grid, so all high,
medium and low voltage lines were considered. For FC-PHEV
and EVs, a charging infrastructure had to be considered, so
they were divided into three categories according to charging
options in Portugal: normal charging, fast charging and home
charging, according to Table 4 of supporting information (SI).
While addressing EV technology [19] only considered public
charging service rates for diurnal and nocturnal areas.
Furthermore it assumes that the total charging needs would
be fulfilled the same way by normal and fast chargers.
However, private infrastructure must also to be considered,
and a better understanding of the use of charging options
must also be investigated further. According to comprehen-
sive studies for France performed by [30,31], public and private
service rates are suggested to be 1.1 (chargers or plugs/car) at
a stable penetration scenario. This ratio can be even higher if
installation of chargers at working places is also considered.
Regarding maintenance, electricity charging points have low
routine maintenance, requiring only periodic inspections,
cleaning, repairs and communication systems and lighting
testing, so only power plant maintenance activities were
considered [32]. Also represented in Fig. 2 is the centralised
SMR pathway, which includes the natural gas (NG) pipeline
Fig. 2 e System boundaries for electricity and Hydroge
and a hydrogen plant based on [33]. A compressor exiting the
plant was also considered to normalise the pressure of
hydrogen to be transported. For the H2 pipeline estimations,
the Simapro database was considered, assuming similarity
with the transport of CH4 in terms of technical specifications
and construction characteristics even though compression is
different. For this reason, the compressors used in the study
are, in fact, for H2 compression and not CH4. Compression
stations and required buildings were also included in the
pipeline analysis.
In the Inventory stage, Simapro 7.1 was considered as the
reference source and used in triangulationwith the GEMIS [34]
database and existing literature. Scaling techniqueswere used
to adjust raw data from the databases to the Portuguese
installation characteristics (for example, installed power,
capacity factor or mix).
An inventory for H2 refuelling stations had to be reformu-
lated based on [35,36], to contemplate an average-size station
comparable to a conventional Portuguese fuel station and also
to make the distinction between an incoming pipeline H2
station and an onsite electrolysis production station.
Charging points were also missing from the literature or
databases with few exceptions [32,37] where, although small
inventories were conducted, these inventories were somehow
scarce in information and quantities regarding the three
chargingmethods: normal, fast and home charging developed
in Portugal. Based on earlierwork [19] andwith further contact
n (Electrolysis and SMR pathways) supply chains.
i n t e rn a t i o n a l j o u r n a l o f h y d r o g e n en e r g y 3 7 ( 2 0 1 2 ) 1 0 9 7 3e1 0 9 8 510978
with the leading charging stations manufacturer in Portugal
(EFACEC), a more detailed inventory was developed.
In addition, petrol stations also had to be inventoried
because values from Simapro, although existing, did not
correspond to the size of an average fuel station in Portugal.
Furthermore, because fuel stations offer services other than
just fuel distribution, only the facilities attributable to that
activity had to be considered; thus, an adjusted inventory was
required. The same was conducted for H2 stations with the
necessary scale and technical adjustments based on [33],
whether SMR or electrolysis pathways were being considered.
The H2 plant from the SMR inventory was followed according
to [33].
Regarding the fleet, the 2010 Portuguese numbers were
considered as a reference for light-duty diesel and gasoline
vehicles only. Energy allocations were made according to the
2005 refining mix [26] for conventional fuels and the 2010
electric mix [28] for the EV, FCHEV(b) and FC-PHEV(b). Main-
tenance was considered only for power plants, the refinery
and the H2 station. Gross values were calculated, taking into
account [38], and then adjusted according to the installed
capacity and capacitor factor for each plant. Energy use in
power plant maintenance was considered to be mainly from
heavy duty diesel trucks or machinery operation.
Estimations were made using two functional units. First,
the energy and carbon intensity of construction, maintenance
and decommissioning of all facilities was calculated and
divided by the total output energy during its lifetime, so units
of MJeq/MJ were obtained. Second, those values were multi-
plied by the TTW stage of each technology, adjusted according
to each facility’s efficiency along the supply chain. This
procedure allows other investigators to use these energy-
based estimations with different TTW values or technologies.
A choice of similar characteristics between vehicle technolo-
gies should be taken into account when evaluating options.
The power/weight ratio is a determinant characteristic to
be described when comparing technologies. Vehicles used
should belong to the same performance class, otherwise an
error of judgment could occur due to performance issues. For
the purpose of this study, values from [21] were used for the
TTW stage and WTT estimations were calculated based on [9]
adapted to the 2010 Portuguese emissions and efficiency. For
Table 2 e Inventory for construction and installation of Chargi
Material Home Charger
Copper (kg) e
Aluminium (kg) e
Iron (kg) e
Concrete (kg) e
Stainless Steel (kg) 3.5
PVC - Polyvinyl chloride (kg) 7.5
ABS, Glass Fibre, PVC (kg) e
Characteristics
Lifetime (years) 15
Service rate (socket) 0.941
Impact kgCO2eq MJeqValues per charger 3.2 Eþ01 6.17 Eþ02
Source: Own inventory based on EFACEC product line. *Average values p
non-existent values of TTW for FC-PHEV technologies, esti-
mations were made based on the [13] study, using as a refer-
ence gasoline vehicles from both studies and applying the
same difference ratio between technologies. All used values
can be observed in Table 6 of (SI). For FC-PHEV technology,
a 0.21 MJ/km electricity use and 0.34 MJ/km of hydrogen were
considered. For the CTG values [21], adjustments were also
made keeping in mind the difference of kilometres driven
between the studies. A lifetime range of 150,000 km, corre-
sponding to an average of 12,800 km per year in Portugal, was
used. Values from EURO 5 legislationwere considered, and the
VW Golf was used as a reference vehicle by [21]. Another
factor that influenced the choice of the study was the use of
NEDC. On the one hand, use of NEDC allows a generalisation
for future studies, and on the other hand, NEDC is closer to
a Portuguese driving cycle than FTP. Energy use and emissions
LCA estimations are given by Eqs. (1) and (2) in terms of their
final units:
The infrastructure value is directly proportional to the
TTW stage given by MJ/km:
LCAMJeq ¼�MJWTT
MJþMJInfra:
MJ
��MJTTW
kmþMJTTW
kmþ MJCTGkmtotal
; (1)
LCACO2eq¼�gCO2eq:WTT
MJþgCO2eq:Infra
MJ
��MJTTW
kmþgCO2eq TTW
km
þgCO2eq:CTG
kmtotal(2)
Relevant losses for all facilities, presented in Table 5 of the
SI were added to the corresponding load (TTW) to be deman-
ded from each facility along the chain.
2.2. Inventory and data assembly
2.2.1. Construction and decommissioningDetails of inventory and complementary considerations
regarding the overall lack of data are described in Table 2 of
the SI section. Lifetimes considered can be found in Table 1
and Table 2 of the SI based on Simapro and the literature
[39e41]. Values simulated by Simapro for the transport and
distribution grid were validated by the literature [42,43]. The
power plant characterisation mix can be found in Table 1 of
ng Points.
Normal Charger* Quick Charger
2 206
2 34
e 228
960 2400
2.5 90
e 12
81 380
6 12
0.164 0.003
kgCO2eq MJeq kgCO2eq MJeq2.9 Eþ02 6.20 Eþ03 2.9 Eþ03 5.96 Eþ04
er satellite, considering 1 central column per 10 satellites.
Table 3 e Inventory for construction and installation ofa conventional refuelling station.
Total Gravel ETH U 31.6 ED04
Area covered with gravel equivalent 31.6 Eþ04
Total Concrete, sole plate and foundation 1.31 ED03
Foundation for 4 dispensers m3 4.80 Eþ02
Foundations for building support m3 3.50 Eþ02
Foundations for metallic structure m3 4.80 Eþ02
Total Building, hall/CH/I U 2.00 ED02
Payment building with storage room m2 2.00 Eþ02
Total Steel I 8.00 ED04
Support Gantries 3.00 Eþ04
Covering metallic structure 500m2 2.50 Eþ04
Interior metallic supports 2.50 Eþ04
Total Bitumen, at refinery/RER U 2.19 ED05
Interior accesses 2.19 Eþ05
Mechanic Componentsa MJeq kgCO2eq
Pipelines, tubes and accessories 1.05 Eþ05 3.0 Eþ03
Storage Tanks and reservoirs 8.90 Eþ05 4.5 Eþ04
Other components 1.32 Eþ04 6.0 Eþ02
Storage
Diesel Storage Tanks 4.81 Eþ06 4.4 Eþ04
Gasoline Storage Tanks 6.58 Eþ06 1.7 Eþ04
Total 2.70 Eþ07 5.5 Eþ05
a Data from contractor company (Petroassist). Values adjusted for
4 dispensers. Electrical components were not considered.
i n t e r n a t i o n a l j o u r n a l o f h y d r o g e n en e r g y 3 7 ( 2 0 1 2 ) 1 0 9 7 3e1 0 9 8 5 10979
the SI, excluding values of import/export or pumping.
Upstream from the power plants, only the natural gas pipeline
was considered to be representative of the main source of
natural gas importation in Portugal. All of the 1638 km [29]
length of the pipeline was taken into consideration.
However, because only 8.2% was found to be used for elec-
tricity conversion at Portuguese plants, only this portion was
added to natural gas power plants. Regarding hydro plants,
taking into account that Simapro data are based on five Swiss
and Austrian plants and that no installed power data are
provided, according to the UDI World Electric Power Plants
Database, a mean value of 544.77 MWwas used as a reference
for scaling up the Portuguese installed capacity. For the
charging point inventory, Table 2 presents a brief list of the
main materials and quantities considering installation
requirements. Normal charger average values consider
a central column and 10 satellites with 2 sockets each.
Using a total service ratio of 1.1 [30,31], partial ratios by
charging option were estimated. Although [44] present some
estimation to what these may be, the study never refers an
aggregate service ratio, thus estimations were followed
according to [30,31] expectations. They define that from the
1.1 service ratio, 0.105 are secondary public chargers, 1
primary chargers and 0.003 fast chargers. According to those
studies, 90% of the charging is expected to be 3 kVA primary
charging. Because not all users will be able to charge in private
garages, we consider that 6% of level 1 chargers will be on the
streets, which added to the 0.105 given by the study means
a total of 0.164 of normal chargers and 0.941 home chargers.
We also assume that on average 20.5% of all charging (15%
normal chargers and 5.5% fast chargers) will be performed
using public chargers. This means that from the 90% of
primary charging, 79.5% will be on home chargers, and 10.5%
on normal chargers. The other 4.5% of normal charging and
5.5% using fast chargers will be in other public spaces. Table 2
of SI presents a summary of these characteristics.
According to the same studies 3 kVA chargers are physi-
cally identical to level 2 normal chargers, only with minor
differences in connections and cabling. Every two normal
charger connections correspond to one satellite. Lifetimes in
years were estimated according to the manufacturer’s
expectations, taking into account technological transition,
usage degradation and the payback period. For FC-PHEV
technology, the EV MJ-based value of emissions and energy
use of all charging points was considered before calculating
the final km-based functional unit.
Table 3 presents the inventory for a conventional refuelling
station based on [19], making the necessary adjustments to
contemplate only the services attributable to fuel distribution.
The H2 station inventory shown in Table 4 was based on
the Grjothals station, situated on Reiquejavique Island. This
stationwas built by HydroStatoil, and its life cycle was studied
by [36]. Valueswere inventoried by quantity to be simulated in
Simapro and separated by modules, to distinguish the two
pathways analysed with or without electrolyser.
To obtain a relationship between distributed energy and
the LCA estimations for the H2 station, a service ratio
(stations/car) had to be estimated according to each pathway.
Regarding SMR, and from the demand side, considering that
the FCHEV has been increasing its autonomy range and even
though it is below conventional fuels range, it can be consid-
ered somewhat similar in refuelling time and frequency of
refills. As for the supply side, because production is central-
ised and the distribution is made by pipeline, no limitations
exist, so the same service rate as a conventional station was
considered. As for the on-site electrolysis scenario, there is
a supply limitation, and that limitation is the hydrogen
production capacity of the electrolyser. Because the installed
capacity of the station is 47,250 kg H2/year [36] and its capacity
factor is 92.88%, due to maintenance activities and general
idle hours, taking into account the TTW [21] energy use and
the vehicle lifetime driving range of 12,800 km per year,
a value of approximately 329 cars per station can be reached.
2.2.2. MaintenanceThemaintenance stage was considered for the refinery, for all
power plants and for the H2 refuelling station. Concerning
power plants, maintenance data from [38] were used. Because
operation values are part of WTW assessments, only data for
expendables and maintenance were considered. Data repor-
ted were given in g CO2/kWh units according to the specific
lifetime, capacitor factor and installed power. So that it could
be adapted to Portuguese reality, the gross value of CO2 was
calculated applying the values presented in the 2010 electric
mix characterisation shown in Table 1 of the SI section, and
new values of g CO2/kWh were found and are presented in
Table 5 of the SI. Because maintenance activities involve
mostly transportation and electricity use, and given that no
specific data were found, the CO2 released was considered to
be due to burned diesel fuel in the operation of trucks and
machinery. Regarding refinery data, no literature data were
found regarding quantities of materials used in passive or
active maintenance. However, the main activities include
tube restoration, painting and galvanisation, scaffolding,
Table 4 e Inventory for construction and installation of a H2 refuelling station.
Materials/Energy Quantity (kg) Compressor (cont.) kg
Buildings or foundations Stainless steel 18/8, installation 58.81
Steel for concrete, installation 278.68 Casting iron, installation 18.56
Smooth coated Glass, installation 100.5 Etilenoglicol, installation 0.22
Plaster fibre plate, installation 3.09 Lubricant oil, installation 0.56
Silica sand, installation 1781.77 Aluminium, production mix, installation 1.86
Concrete, installation m3 0.31 Insulation tube, installation 0.47
Resistant concrete, installation m3 4.02 Cooper, regional storage 1.39
Gravel, not specified, installation 55735.22 Electricity (kWh) 30.94
Lubricant oil, installation 0.62 Heat, NG, ind. furnace > 100 kW (MJ) 111.47
Electricity (kWh) 15.49 Transport lorry 32t (tkm) 15.89
Diesel (MJ) 1325.36 Additional Electrolysis module
Transport lorry 32t (tkm) 6846.22 Electrolyser
Storage module Chromium steel 18/8 at plant 262.88
Stainless Steel 18/8, installation 2602.44 Nickel 99,5% at plant 30.94
Electricity 29.71 Synthetic rubber, at plant 1.55
Diesel 26.51 Reinforcing steel at plant 82.07
Transport lorry 32t (tkm) 260.24 Cooper at regional storage 23.7
Other components Tube insulation, at plant 10.53
Steel for concrete, installation 50.91 Aluminium, production mix, at plant 6.8
Nitrogen, liquid, installation 4.43 Acrylonitrile-butadiene-styrene copolymer, ABS, at plant 2.48
Stainless Steel 18/8, installation 12.51 Polyethylene, LDPE, granulate, at plant 6.19
Polypropylene, granulated, installation 0.31 Glass fibre, at plant 6.19
Transport, lorry 32t (tkm) 3028.13 Cast iron, at plant 2.11
Compressor Nylon 66, glass-filled, at plant 0.77
Steel for concrete, installation 76.8 Transport lorry 32t (tkm) 43.49
Total kgCO2eq MJeqWithout Electrolyser 1.8 Eþ04 3.03 Eþ05
With Electrolyser 1.9 Eþ04 3.38 Eþ05
Source: Based on [36].
i n t e rn a t i o n a l j o u r n a l o f h y d r o g e n en e r g y 3 7 ( 2 0 1 2 ) 1 0 9 7 3e1 0 9 8 510980
insulation works, welding of materials and equipment lubri-
cation. Themainmaterials used and the expendables are rock
and glass wool, aluminium, copper, stainless steel, paint, steel
SAE 1020, zinc bath in the galvanisation process, diesel and
electricity. With the cost of construction of a similar refinery,
a direct relationship was established between the cost and
CO2eq emissions and energy use assessed by Simapro, and the
same relationship was attributed to the annual cost of
Table 5 e Complete LCA values of fossil fuels and EV technolo
WTT TTW VehicleMaterial
Gasoline MJeq/km 0.34 1.98 0.43
gCO2eq/km 28.1 144.0 17.7
Diesel MJeq/km 0.33 1.76 0.43
gCO2eq/km 28.0 128.0 18.5
FCHEV (a) MJeq/km 0.90 1.25 0.65
gCO2eq/km 123.5 0.0 28.0
FCHEV (b) MJeq/km 4.09 1.25 0.65
gCO2eq/km 141.2 0.0 28.0
FCPHEV (a) MJeq/km 0.57 0.56 0.69
gCO2eq/km 48.4 0.0 28.6
FCPHEV (b) MJeq/km 1.45 0.56 0.69
gCO2eq/km 53.3 0.0 28.6
EV MJeq/km 0.83 0.54 0.86
gCO2eq/km 36.60 0.00 24.80
a Difference in percentage when compared to gasoline base case.
maintenance. Knowing that 40% of the cost is spent in
material acquisition and the rest in hand labour [41], values
for maintenance were obtained. As for the H2 refuelling
station, compressor equipment has to be subjected to
a significant overhaul every few years (typically assumed to be
at 5-year intervals) [33]. Because the lifetime of the station is
15 years [36], calculations were made for two total
replacements.
gies.
Infrastructuremin-max (best est.)
Infrastructure Impactmin-max (best est.)
% of basecasea
0.03e0.06 (0.05) 0.9%e2.3% (1.8%) 100%
0.5e1.2 (1.0) 0.3%e0.6% (0.5%) 100%
0.02e0.06 (0.05) 0.9%e2.2% (1.8%) 89%
0.6e1.3 (1.2) 0.3%e0.7% (0.7%) 112%
0.06e0.17 (0.07) 2.0%e6.2% (2.4%) 127%
1.5e3.5 (2.0) 1.1%e2.5% (1.4%) 194%
0.20e0.41 (0.23) 3.2%e6.5% (3.7%) 452%
13.0e22.0 (15.4) 7.0%e11.9% (8.3%) 1489%
0.05e0.09 (0.06) 2.9%e5.0% (3.0%) 111%
2.4e3.4 (2.7) 3.1%e4.5% (3.5%) 262%
0.10e0.17(0.10) 3.4%e6.0% (3.7%) 203%
5.6e8.7 (6.5) 6.4%e10.0% (7.3%) 627%
0.09e0.14 (0.10) 3.8%e6.2% (4.3%) 197%
4.9e7.0 (5.6) 7.3%e10.3% (8.4%) 544%
i n t e r n a t i o n a l j o u r n a l o f h y d r o g e n en e r g y 3 7 ( 2 0 1 2 ) 1 0 9 7 3e1 0 9 8 5 10981
2.3. Uncertainty
A total of 166 variables were submitted to uncertainty anal-
ysis, according to the fit test distribution, observable in Table 3
of the SI. Uncertainty Simapro data are based on the Ecoin-
vent’s pedigree matrix, which refers to basic uncertainty and
under-specification uncertainty characterised by 6 indicators,
each with 5 levels. These values were subjected to 1000 iter-
ations, and variations were matched with a curve fit tool into
Crystal Ball.
Regarding inputs for own inventories such as chargers and
values used for H2 stations, because a case study is being
considered, only basic uncertainty, which relates to
measurements of quantities, was taken into consideration
and assumed to vary according to normal distributions (Table
3 of the SI). Attempting to generalise the study will certainly
increase uncertainty, especially for the inventories developed.
Issues such as the sample size, reliability, geographic corre-
lation, underspecification and impact uncertaintywill become
relevant issues to deal with [45].
A 10,000-trial simulation was then run in Crystal Ball with
all 166 variables. Maximum and minimum values were
obtained for each technology assessed. WTW and CTG
uncertainty stages were not considered. Calculations were
based on their best estimated values.
Fig. 3 e Energy Use (a) and emissions (b) uncertainty
analysis.
3. Results and discussion
All infrastructure values simulated in Simapro were corrobo-
rated by GEMIS or the literature. Regarding distribution facil-
ities, inventories were conducted for all technologies
according to the lifetime driving range characteristics and use
of energy. When comparing distribution infrastructures of
conventional with hydrogen, electric or plug-in vehicles,
caution should be exercised regarding refuelling or charging
times. In typical petrol or H2 stations, the time required for
filling a tank may vary between 4 and 7 min, whereas an
electric charge varies, according to Table 4 of the SI, from 20 to
480min. A questionmay be raised regarding levelling the time
of refuelling and only then comparing technologies and
facilities. However, because refuelling times are different
between technologies, one may assume that the service rate
will change accordingly. That is, if one facility is occupied for
more than a certain period, another installation should be
provided to the market. However, if charging/refuelling times
are sufficiently low to accommodatemore vehicles per time or
kilometres driven, fewer facilities are required, compensating
in terms of materials and corresponding construction, main-
tenance and decommissioning efforts. When comparing the
amount of energy supplied by distribution facilities, a refuel-
ling station provides more MJ than a charging facility.
However, electric vehicles are more efficient than an ICE,
resulting in a benefit to the system. This adjustment is
assumed to be linear in this study, even though we recognise
that further work should be performed.
Total results for all facilities are presented by technology in
Table 5 of the SI, in final energy use units, and for each
infrastructure group analysed, including construction,
decommissioning and maintenance. Energy use and emis-
sions uncertainty are represented in Fig. 3 for each of the
technologies studied. In total, five parameters are repre-
sented: median, 1st percentile, minimum, maximum and 3rd
percentile. The median value was preferred to the mean, so
that it could represent the central trend.
The uncertainty value range of infrastructures is higher in
FCHEV(b) when compared to other technologies in several
aspects. Higher amplitude of deviation from the median
value, both in minimum andmaximum extremes, is reported.
Furthermore, the interquartile range is higher in both FCHEV
than other technologies, reducing the probability of the best
estimate value falling far from the median. Overall, lower
amplitude of uncertainty in both emissions and energy use of
ICE vehicles can be explained by a higher accuracy in
measurements due to standardised practices and processes of
construction, appropriate for a mature technology. Regarding
alternative vehicle support infrastructures, construction
techniques, scale, and geographic positioning, raw materials
processing and technology used can differ widely, meaning
higher uncertainty. Regarding median positioning between
extremes, EV presents a midpoint location, expected when
most probability functions, or those that represent the most
weight, are normal distributions. Other technologies present
median values closer to the minimum extreme, which is
influenced by the use of lognormal distributions. To under-
stand the nature of this positioning, although the uncertainty
behaviour in terms of ranges and probabilities was identified,
i n t e rn a t i o n a l j o u r n a l o f h y d r o g e n en e r g y 3 7 ( 2 0 1 2 ) 1 0 9 7 3e1 0 9 8 510982
it is still crucial to knowwhat variables contribute the most to
such uncertainty. Contribution of the main variables to
emission and energy use variance is shown in Fig. 4. Only
variables with contribution to variance higher than 4% were
distinguished. Variables lower than 4%were added and placed
under the category “others”.
In Fig. 4, variables that contribute the most for EV, emis-
sions and energy use uncertainty are the normal charger
lifetime with 57.9% influence and overall power plant
construction, especially hydro plants. FC-PHEV(a) emissions
uncertainty also depends on 42.7% of the normal charger
lifetime and the H2 pipeline’s energy use with 52.4% influence,
as is FCHEV(a) with 75.7% and 37.3% for emissions. Both FC
technologies using the electrolysis pathway depend on
approximately 50% of power plants’ construction activities,
mostly hydro plants (30%) and H2 stations. Regarding both ICE
vehicle technologies, two variables report higher impact both
Fig. 4 e Contribution to energy use (a) and emissions (b)
variance.
in emissions and energy use. The first variable is the lifetime
of refuelling stations with an influence of approximately 60%
in the case of emissions and 83% in energy use for both
technologies. The second variable is civil works activities
during refinery construction, with an influence, for both
emissions and energy use, of approximately 25% and 7%,
respectively.
Fig. 5 presents the absolute values of infrastructure per
each technology, showing values per unit of final energy.
Absolute values report higher energy use and CO2 emissions
from construction, maintenance and decommissioning for
alternative vehicle technologies. Higher uncertainty in alter-
native fuels can be explained by a longer supply chain and
a variety of efficiencies, as well as the reason for higher energy
and carbon intensity for these technologies, as hybrid solu-
tions need complementary infrastructures for both fuels used.
The energy per kilometre travelled, relative to the infrastruc-
ture, is necessarily higher, as this energy will depend on its
TTW stage, as illustrated in Figs. 1 and 2 of the SI. Even though
some technology infrastructure best estimate values are
inferior to others, they can have a higher impact on their LCA
when presented in their final functional units.
Table 5 shows the results for all stages and the corre-
sponding impact of infrastructure usingminimum,maximum
and best estimated values. While the impact of conventional
Fig. 5 e Energy use (a) and emissions (b) of energy supply
infrastructures per technology.
i n t e r n a t i o n a l j o u r n a l o f h y d r o g e n en e r g y 3 7 ( 2 0 1 2 ) 1 0 9 7 3e1 0 9 8 5 10983
fuel can be neglected under the assessed conditions because
its contribution is below 2.5%, this is not the case in alterna-
tive vehicle technologies.
The difference between the contribution of fossil fuel
infrastructures and alternative technologies is illustrated
mostly by end distribution facilities, H2 pipelines and power
plants (see Table 5 of the SI). Charging point facilities are about
ten times higher in energy use and five times higher in
emissions than a conventional refuelling station. In the H2
supply chain, H2 refuelling stations, when using the SMR
pathway, are very similar to conventional refuelling stations.
However, when considering the on-site electrolysis system,
the H2 station emits about 6 times more CO2eq per unit of
distributed MJ than conventional stations. To compare the
contribution of fuel infrastructures in WTW and CTG LCA, all
stages are presented in Fig. 6. Uncertainty corresponds only to
infrastructure.
The impacts of infrastructures relate only to each tech-
nology LCA. Values are presented in this way to highlight the
weight of this stage on the total LCA of each technology.
Percentage weights among technologies should not be
compared. The best estimated impact of infrastructure on
total EV LCA was 4.3% for energy use and 8.4% for emissions.
The impact of diesel infrastructure in its total LCA is 1.8% of
Fig. 6 e LCA energy use (a) and emissions (b) per stage and
technology.
energy use and 0.7% of emissions. Gasoline energy supply
facilities represent 1.8% of energy use and 0.5% of emissions in
total LCA. H2 energy supply infrastructure represents 2.4% of
energy use and 1.4% of emissions using the SMR pathway and
3.7% and 8.3% using electrolysis. FC-PHEV infrastructures
account for 3.0% of energy use and 3.5% of emissions using the
SMR pathway and 3.7% and 7.3% using electrolysis.
Pipelines and end distribution facilities are extremely
significant for their overall contribution; thus, definition of
their service ratios is extremely important. In this study, we
have broadened the technologies assessed in terms of their
energy supply infrastructure and used service ratio estimates
of 0.941 for home chargers, 0.164 for normal chargers and
0.003 for fast chargers. A higher level of attention was given to
the input materials for all chargers. Being two times higher
than fast chargers, normal chargers report the highest values
of energy use and emissions per kilometre among all chargers,
being very sensitive to their lifetime usage. If the effective use
increases (i.e., if the energy flow increases in the normal
charger use), its impact would decrease. In addition, if the
overall service ratio of 1.1 estimated by [30] should decrease,
then the absolute value per kilometre of normal chargers
would be reduced the most. If a decrease should occur in the
CTG and WTT stages, both TTW and infrastructures will have
a higher impact on the total LCA. If the TTW stage decreases,
the contribution of infrastructures per kilometre will also
decrease due to the direct proportional relationship between
the absolute value of infrastructures and the TTW energy use
value. The more efficient vehicles become, the less impact
TTW and infrastructure per kilometre will have (see Eqs. (1)
and (2)).
4. Conclusions
The study goal was to provide energy use and CO2eq estima-
tions related to energy supply infrastructure for several
vehicles and to estimate the impact on their overall LCA. A
methodology [19] was used with Portugal as a case study and
applied to conventional diesel and petrol vehicles as well as
alternative technologies such as EV, FCHEV and FC-PHEV.
With the case study being analysed, alternative vehicle tech-
nologies energy supply infrastructures are more carbon- and
energy-intensive per unit of supplied fuel than conventional
energy supply infrastructures. For the current scenario of 2234
vehicles per conventional and H2 (SMR) refuelling station and
the foreseen service rate scenarios of 333.3 vehicles per fast
charger, 6.1 vehicles per normal charger (socket), 1.1 per home
charger and 329 vehicles per H2 (electrolysis) station, the LCA
of conventional fuel infrastructure potentially represents an
energy use of 0.01e0.04MJeq/MJfuel for both gasoline and diesel
fuels. Emissions represent 0.3e0.9 g CO2eq/MJfuel for gasoline
and 0.3e1.0 g CO2eq/MJfuel for diesel. For electricity, these
values are 0.15e0.30 MJeq/MJfuel with emissions of 8.5e14.7 g
CO2eq/MJfuel. For hybrid vehicles, FCHEV(a) shows 0.03e0.12
MJeq/MJfuel and 0.7e2.9 g CO2eq/MJfuel, the FCHEV(b) shows
0.08e0.23 MJeq/MJfuel and 5.5e12.0 g CO2eq/MJfuel. For plug-in
technologies, FC-PHEV(a) shows 0.18e0.36 MJeq/MJfuel and
8.7e16.6 g CO2eq/MJfuel, and FC-PHEV(b) shows 0.23e0.53 MJeq/
MJfuel and 13.6e26.7 g CO2eq/MJfuel.
i n t e rn a t i o n a l j o u r n a l o f h y d r o g e n en e r g y 3 7 ( 2 0 1 2 ) 1 0 9 7 3e1 0 9 8 510984
EV reports the highest infrastructure LCA contribution per
kilometre with 8.4%, followed by the FCHEV (b) with 8.3% in
emissions. Conventional fuel facilities report the lowest
values, contributing impacts below 2.5%. EV is mostly affected
by the charging infrastructure with approximately 60%weight
followed by power plants andmaintenancewith about a 33.2%
contribution in terms of energy use and 42.6% in emissions,
while FCHEV (b) is mostly affected by power plant construc-
tion andmaintenancewith approximately 68%,with 30% from
H2 stations. End distribution facilities tend to be the higher
contributors among energy supply infrastructures. Overall
contributions with uncertainty do not go beyond 12%with the
assessed conditions.
A more friendly choice of materials or higher efficiency in
H2 stations, H2 pipelines and electric chargers is advisable.
Total and partial service ratios as well as usage from each type
of chargers are crucial issues and should be further investi-
gated. Increasing the energy flow homogeneously in normal
chargers by promoting the vehicle to grid (V2G) concept would
decrease the impact of chargers. The set environmental goals
within the electricity generation mix and an increase in the
lifetime driven distance will lower the WTT and CTG stages.
These facts make the contribution of energy supply infra-
structure pertinent to analysis in future studies, particularly
in the alternative vehicle technologies studied. A generalisa-
tion of the study is, however, advisable. Due to a large range of
uncertainty, closer attention should be paid to how the
impacts vary according to different scenarios of behaviours,
geographies or material inputs.
Support information
Supplementary data attached in Appendix A.[46e48]
Acknowledgments
The authors would like to thank theMIT-PP and the support of
all companies that made this study possible, in particular
EFACEC for the financial support. Special thanks to Elsevier
Language Editing Services.
Appendix A. Supplementary material
Supplementary data associated with this article can be found,
in the online version, at doi:10.1016/j.ijhydene.2012.04.127.
Nomenclature
AER All Electric Range;
CAFE Corporate Average Fuel Economy;
CD Charge Depleting;
CED Cumulative Energy Demand;
CS Charge sustaining;
GHG Green House Gas;
CTG Cradle-to-Grave of vehicle materials;
DICI Direct Injection Compression Ignition;
DISI Direct Injection Spark Ignition;
ECE-EUDC European Driving Cycle Extra-Urban Driving Cycle;
EV Full Electric Vehicle;
FCHEV Fuel Cell Hybrid Electric Vehicle;
FC-PHEV Fuel Cell Plug-in Hybrid Electric Vehicle;
FTP Federal Test Procedure;
GWP Global Warming Potential;
ICE Internal Combustion Engine;
LCA Life Cycle Analysis;
NEDC New European Driving Cycle;
PISI Port Injection Spark Ignition;
PKT Passenger Kilometre travelled;
RES Renewable Energy Sources;
SI Supporting Information;
SM Steam Methane Reforming;
TTW Tank to Wheel;
WTT Well to Tank;
WTW Well to Wheel.
r e f e r e n c e s
[1] Key world energy 2010 statistics. Paris: OECD/IEA EnergyStatistics Division; 2010. 82 pp.
[2] European Environment Agency [Internet]. Primary energyconsumption by fuel in the EU-27, 1990-2008, [cited 2011 July]Available from: http://www.eea.europa.eu/.
[3] Communication from the commission to the Europeancouncil and the European parliament: an energy policy forEurope. Brussels: COM; 2007 Jan. 28 pp.
[4] DGGE [Internet] Balanco energetico - Direccao Geral deEnergia e Geologia. [updated 2010 Oct.; cited 2010 Oct.]Available from: http://www.dgge.pt/.
[5] McKinsey and Company. A portfolio of power-trains forEurope: a fact-based analysis. The Role of Battery ElectricVehicles, Plug-in Hybrids and Fuel Cell Electric Vehicles;2010. 68.
[6] Ministerio da Economia e da Inovacao. A Estrategia Nacionalpara a Energia com o horizonte de 2020. Lisboa (Portugal);2010 Apr.. 25 pp. Portuguese.
[7] Geerken T, Timmermans V, Lassaux S. Hydrogen and it’sapplications: review of life cycle assessment studies andwell-to-wheel studies, 10th European Roundtable onsustainable consumption and production, Antwerp(Belgium), Hysociety project, 5-6-7; 2005 Oct..
[8] Weiss M, Heywood J, Drake E, Schafer A, AuYeung F. On theroad in 2020-A life-cycle analysis of new automobiletechnologies. Cambridge (MA): MIT Energy Laboratory; 2000Oct. 160 pp. Report No.: MIT EL 00e003.
[9] Edwards R, Larive JF, Beziat JC. Well-to-wheels analysisof future automotive fuels and powertrains in theEuropean context. Version 3c. Concawe, JRC, EUCAR; 2011Jul. 74 pp.
[10] Morrow K, Karner D, Francfort J. Plug-in hybrid electricvehicle charging infrastructure review. Idaho Falls (ID):Battelle Energy Alliance; 2008. 40 pp. Report No.:58517.Contract No.: DEAC0705ID14517. Supported by theDepartment of Energy.
[11] Gross B, Sutherland I, Mooiweer H. Hydrogen fuellinginfrastructure assessment. Mound Road (MI): General MotorsResearch Development Center; 2007 Dec. 43 pp. ReportNo.:R&D11,065.
i n t e r n a t i o n a l j o u r n a l o f h y d r o g e n en e r g y 3 7 ( 2 0 1 2 ) 1 0 9 7 3e1 0 9 8 5 10985
[12] Elgowainy A, Burnham A, Wang M, Molburg J, Rousseau A.Well-to-Wheels energy use and greenhouse gas emissionsanalysis of plug-in hybrid electric vehicles. Chicago (IL): DOE;2009 Feb. 70 pp. Argonne Laboratories, Energy SystemsDivision Report No.: ANL/ESD/09e2. Contract No.: DE-AC02-06CH11357. Supported by U.S. Department of Energy.
[13] Baptista P, Tomas M, Silva C. Plug-in hybrid fuel cell vehiclesmarket penetration scenarios. Int J Hydrogen Energy 2010;35:10024e30.
[14] Campanari S, Manzolini G, Garcia de la Iglesia F. Energyanalysis of electric vehicles using batteries or fuel cellsthrough well-to-wheel driving cycle simulations. J PowerSources 2009;186:464e77.
[15] Silva C, Ross M, Farias T. Evaluation of energy consumption,emissions and cost of plug-in hybrid vehicles. EnergyConvers Manage 2009;50:1635e43.
[16] Chester MV, Horvath A. Environmental assessment ofpassenger transportation should include infrastructure andsupply chains. Environ Res Lett 2009;4:024008.
[17] Kendall A, Keoleian A, Helfand E. Integrated life-cycleassessment and life-cycle cost analysis model for concretebridge deck applications. J Infrastruct Syst 2008;14:214e22.
[18] Lee JY, An S, Cha K, Hur T. Life cycle environmental andeconomic analyses of a hydrogen station with wind energy.Int J Hydrogen Energy 2010;35:2213e25.
[19] Lucas A, Silva C, Neto R. Life cycle analysis of energy supplyinfrastructure for conventional and electric vehicles. EnergPolicy 2012;41:537e47.
[20] Granovskii M, Dincer I, Rosen M. Life cycle assessment ofhydrogen fuel cell and gasoline vehicles. Int J HydrogenEnergy 2006;31:337e52.
[21] Siddikou B, Vincent W, Nele S, Heijke R, Maarten M,Mierlo JV. LCA and policy measures report. CLEVER CleanVehicles Research ETEC and MOBI. Brussels (Belgium): VrijeUniversity Brussels; 2011. 83 pp.
[22] International Organization for Standardization. ISO 14040:2006and ISO 14044:2006: environmental management e life cycleassessment e principles and framework.
[23] Forster P, Ramaswamy V, Artaxo P, Berntsen T, Betts R,Fahey D, et al. Changes in atmospheric constituents and inradiative forcing. Climate Change 2007: the Physical ScienceBasis. IPCC Fourth Assessment Report. 106 pp. WorkingGroup I: [Chapter 2]. UK, New York, USA: Joint publication ofCambridge University Press; 2007 Feb.
[24] PRe Consultants [Internet]. Simapro tool [updated 2012 Apr.;cited 2012 Apr.] Available from: http://www.pre.nl/simapro
[25] Silva A. Energy risks and safety. Risk Management in oil andgas activities [slides], vol. 133. Lisbon (Portugal): Partex Oiland Gas Company (President): ISEG Risk Managementmeetings; 2010 June 6. slides: color 2 x 2 in.
[26] Data Book de seguranca saude e ambiente - Refinaria deSines 2009. Lisboa (Portugal): Galp Energia; 2009. 76 pp.Portuguese.
[27] ACAP [Internet]. Associacao Automovel de Portugal. ParqueAutomovel em [updated 2012 Fev.; cited 2012 Apr.] Availablefrom: http://www.acap.pt; 2010.
[28] Dados Tecnicos 2010. Lisboa (Portugal): Redes EnergeticasNacionais; 2011. 1 pp. Portuguese.
[29] DGGE [Internet]. Direccao Geral de Geologia e Energia. Infra-Estruturas de Petroleo e Gas Natural [updated 2010 Oct.; cited2010 Oct.] Available from: http://www.dgge.pt/.
[30] Groupe de travail sur le: Livre vert pour le developpementdes infrastructures de charge electrique Paris. MEEDDM; 2010Apr.. 198 pp. French.
[31] Depoorter S, Assimon P. Les vehicules electriques enperspective: analyse couts-avantages et demande potentielleParis. Commissariat general au developpement durable(France); 2011 May. 64 p. Etudes et documents No.: 41.French.
[32] Electric Transportation Engineering Corporation. Electricvehicle charging infrastructure deployment guidelines forGreater San Diego area. U.S. Department of Energy; 2010May. 62 pp. Document 024293.1, Contract No. DE-EE0002194.
[33] Spath PL, Mann MK. Life cycle assessment of renewablehydrogen production via natural gas steam reforming.Golden (CO): NREL; 2001. 33 pp. Report No.: NREL/TP-570-27637. Contract No.: DEA3699GO10337. Supported by theDepartment of Energy.
[34] OEKO [Internet]. Oko-Institut and Gesamthochschule Kassel[updated 2012 Apr.; cited 2012 Apr.] Available from: http://www.oeko.de/service/gemis/en/.
[35] Spath PL, Mann MK. Life cycle assessment of renewablehydrogen production via wind/electrolysis. Golden (CO):NREL; 2004. 13 pp. Report No.: NREL/MP-560-35404. ContractNo.: DE-AC36-99-GO10337. Supported by the Department ofEnergy.
[36] Maack M. Generation of the energy carrier hydrogen incontext with electricity buffering generation through fuelcells. NEEDS: New Energy Externalities Developments forSustainability; 2008. 47 pp. Report No.: 8-5 RS1a. Project No.:502687 for Icelandic New Energy. Co-sponsored by theEuropean Commission within the Sixth Framework.
[37] Nansai K, Tohno S, Kono M, Kasahara M, Moriguchi Y. Life-cycle analysis of charging infrastructure for electric vehicles.Appl Energ 2001;70:251e65.
[38] Hondo H. Life cycle GHG emission analysis of powergeneration systems: Japanese case. Energy 2005;30:2042e56.
[39] Ministerio das obras publicas, transportes e comunicacoes(PT), Diario da Republica; 2009. Set 4 Dec. L. No. 172-5975,artigo 5�, 1.a serie: 5972e5978. Portuguese.
[40] Varun Bhat IK, Prakash R. LCA of renewable energy forelectricity generation systems e a review. Renew Sust EnergRev 2009;13:1067e73.
[41] Vestas Wind Systems. Life cycle assessment of offshore andonshore sited wind power plants based on Vestas V90-3.0MW turbines. Denmark; 2006 Jun. 60 pp.
[42] Working Group B2.15. Life Cycle Assessment (LCA) foroverhead lines. Paris: Cigre; 2005 Jan. 168 pp. Report No.:265.
[43] Harrison GP, Maclean ENJ, Karamanlis S, Ochoa LF. Life cycleassessment of the transmission network in Great Britain.Energ Policy 2010;38:3622e31.
[44] Frost and Sullivan. Strategic technology and market analysisof electric vehicle charging station infrastructure; 2011 Mar.152 pp. Report No.: M616e18.
[45] Frischknecht R, Jungbluth N, Althaus HJ, Doka G, Dones R,Heck T, et al. Overview and methodology. Swiss Centre forLife Cycle Inventories; 2007c. Ecoinvent report No. 1, 2007Dec. 60 pp. vol. 2.0. Dubendorf, Switzerland.
[46] Total.com [Internet]. Total Group media information: oilprocessing, projects and achievements. Normandy refinery[updated 2011 Jan; cited 2011 Fev 11]. Available from: http://www.total.com/.
[47] Silva C. Raffinage, ajustement a un environnement enmutation. Lyon (France): Panorama annual; 2010 Jan. 7 pp.Report No.: Innovation Energy Environnement 2010.
[48] Edpsu.pt [Internet]. Energias de Portugal: Origens daelectricidade, emissoes 2009 e 2010. [updated 2011 Mar; cited2011 Oct. 11]. Available from: http://www.edpsu.pt.