    Building and Construction Sector, Environment, Health and Safety Inspectorate Section of Al Ain City Municipality

    The Inspectorate Section was established to monitor entities in the Building & Construction Sector in the City of Al Ain forcompliance with the requirements of the Abu Dhabi Emirate Environment, Health and Safety Management System (EHSMS). TheSection main functions include: inspections of construction sites, auditing of entities EHS management systems and accidentinvestigation.

    In early 2011, the section started the first phase of the Inspection program which focused initially on the main construction projectsin Al Ain City. Currently, the scope of the inspection program covers all types of projects from infrastructure works to residentialvillas.

    The Inspectorate TeamThe Inspectorate Team consists of 21 experienced EHS inspectors

    and is led by the Inspectorate Manager Mr. Hashem Al Baloushi.

    All inspection sta are educated to degree level, and some hold the

    professional qualifications of the International General Certificate

    of National Examination Board in Occupational Safety and Health

    UK (NEBOSH IGC).

    All inspectors are required to undergo an extensive trainingprogram on construction EHS activities and also on the

    requirements of the Abu Dhabi Emirate Environment, Health and

    Safety Management System (ADEHSMS) which will enable them to

    guide the entities and assist them in establishing their EHS

    management system and help them to comply with the Building

    and Construction Sector regulations.

    Bulletin | December 2011Issue 2

    Bulletin Contents

    Building and Construction Sector, Environment,

    Health and Safety Inspectorate Section

    The Inspectorate Team

    Interviews with Representatives from Building and

    Construction Sector Entities

    Inspection Program

    Heat Stress Campaign

    Scaffolding Safety

    Ask Us

    New inspectors joined the Team in August

  • 7/27/2019 Images535File.pdf

    2/4

    Tel +971 3 712 7970 | Email [email protected] | www.ehs.dma.abudhabi.ae

    Over 4500 construction workers attended

    Heat Stress Sessions

    In coordination with the Health Authority - Abu Dhabi, Ministry ofLabor and the EHS Center, Al Ain City Municipality Building andConstruction Sector EHS Department has successfullycompleted the Heat Stress Prevention Campaign.

    The objective of the campaign was to increase the awareness

    level of heat stress related illness among the workers in theconstruction sector. The campaign started in June 2011 and wascontinued for 3 months. It included site visits to constructionprojects and labor camps in the city of Al Ain where heat stresstraining sessions were delivered by representatives from theInspectorate Section in dierent languages; including Arabic,English, Hindi and Urdu.Most of the main construction contractors in Al Ain city haveparticipated in this campaign and over 4500 constructionworkers were trained on how to identify the symptoms and toprevent heat stress related illnesses during the campaignsessions.The Inspectorate Section prepared and distributed posters, flyers,booklets and also provided food packs and gifts to the workers.

    The Inspectorate Section plans to launch additional campaigns inthe future covering other EHS issues.

    For any suggestions regarding our campaign, please contact uson [email protected]

    Over 700 site inspections carried out in 2011

    Al Ain City Municipality Building & Construction Sector EHSDepartment inspectors have conducted over 700 siteinspections in 2011; the inspections covered dierent typesof projects including government buildings, commercialbuildings, public schools, hotels, resorts, roads, bridges andalso residential villas.

    During these inspections, the inspectorate team has advisedthe site contractors and consultants about the environment,health and safety issues and prepared inspection reportsdetailing all EHS deviations and unsafe practices observed attheir sites during the inspection.

    The Inspectorate Team has not issued a single fine or penaltyduring these inspection as the projects contractors wereinformed that at this stage the aim of the inspection isfocusing on education and assistance to the entities toensure that they are aware of the ADEHSMS requirementsand understand what will be expected from them once theregulations come into eect.

    However, in many cases, inspectors have stopped unsafeactivities that could lead to accident with serious injury toworkers and have also requested for immediate corrective

    actions to be undertaken by the contractors to avoid anysafety incidents.

    Although the Department enforcement program ofADEHSMS requirements have not started yet, the inspectorsdo have a moral obligation to ensure that the health andsafety of workers and the environment are protected andwhere necessary, actions will be taken against violators.

    Currently, the inspectorate team inspects construction sitesof entities that have been nominated by the Department ofMunicipal Aairs (DMA). Nominated entities includedevelopers, consultants and contractors. The number ofnominated entities is increasing regularly with additional 25entities added this month.

    The Inspectorate Team also conducts surveys and issuesstatistic reports on the findings from the inspections. The lastsurvey indicated that most of the significant findings duringinspections were related to working at height andscaolding.

    Bulletin | December 2011Issue 2

  • 7/27/2019 Images535File.pdf

    3/4

    Tel +971 3 712 7970 | Email [email protected] | www.ehs.dma.abudhabi.ae

    Safety at Construction Sites - Scaffolding

    Falling from height is the main cause of fatalities in the construction industry. With theinformation drive from the inspectorate Section on scaolding safety standardstogether with the contractors implementation and compliance with the upcomingregulations for safe erection and usage of scaolding; it will definitely contributetowards reducing the number of potential fall from height incidents.

    A scaold or other suitable means must be provided for all work which cannot be safelydone from the ground, or from a part of a building or other permanent structure.

    Although scaolding is widely used in the construction industry, most builders are notaware of the safety standards that need to be followed. A review of the findings ofconstruction site inspections revealed that more eorts should be made by contractorsto improve their scaolding.

    Scaold work has evolved rapidly from wooden materials to steel framed systemscaold. The widely used systems now are the cuplock scaold and also tube andfitting component scaolding.In Al Ain city, most of the contractors still use the steel framed systems, but in manycases these are being misused or are damaged beyond serviceable repair.

    Basic requirementsfor Scaffolding Safety

    Scaffolding must only be erected,

    altered and dismantled under thesupervision of a competent person; Scaffolding must be constructed of

    sound, strong material; Tubes should not be split, cracked,

    rusty, bent or distorted, and the timberused for boarding must be of the righttype; A scaffold must be properly marinated

    and inspected frequently; and No scaffold shall be partly erected or

    dismantled unless adequate notices aredisplayed and access blocked.

    In a previous interview by the national newspaper, Mr. Chimanlal Gangaramani - vicechairman of Faraa Integrated Construction Group, which employs 18,000 workers in the UAE - saidthat health, safety and environment policies are always the first priority on the agenda." He alsoadded "Safety begins with everyone, its not one persons responsibility. Everyone on the job site hasto be thinking about safety all the time.

    Mr. Shadi al Sady - the health and safety manager at Nael and Bin Harmal Hydroexport - has alsomentioned during an interview that his company had introduced a simple, step-by-step trainingprocedure to help protect its 11,000-strong workforce, in compliance with EHSMS guidelines.Weve developed a system that we think is unique to our company, because we make theeducation very simple for the labourers in workshops and training, and very sophisticated on theadministration level, Mr al Sady said. He also added that his company even provided the workers

    with illustrated safety handouts. Everyone works well with paperwork, but it doesnt always make itdown the ladder to the worker, Mr al Sady concluded.

    Companies have begun oering training, workshops and induction programmes in dierent languages,with labourers receiving updates on safety procedures.

    In an interview with Mr. Mohammed Hassan - EHS Manager of Al Fara'a General Contracting Company he mentioned that health, safety and environment policies are one of their first priorities.

    ADEHSMS requirements are taking hold among main construction companies in the city of Al Ain

    Bulletin | December 2011Issue 2

  • 7/27/2019 Images535File.pdf

    4/4

    Tel +971 3 712 7970 | Email [email protected] | www.ehs.dma.abudhabi.ae

    Inspectorate Section offering assistance and advice to Al Ain City Contractors

    It is our aim to ensure any assistance we can give is oered. We will be running series of EHS workshops, one-to-one sessionson Construction Safety and the ADEHSMS requirements.

    Also, we will visit any entity on request to assist them in development of their EHSMS and help them in any site related EHSissues.

    Please visit our website (www.ehs.dma.abudhabi.ae) for any information about our EHSMS workshops or contact us on onethe following channels:

    E-mail: [email protected]: 03-712 7970

    Ask us

    Send us your questions to [email protected] or visit our social sites and post your questions. Our resident experts will

    answer these for you.

    Working at height

    We believe that prevention of accidents is certainly better than managing them. Consider removing the hazard

    in the first place. For example, close in the open edges with secure railing.

    Bulletin | December 2011Issue 2