ILO Meeting #26 Ongoing and forthcoming Procurement activities 29 th September 2014 - San Sebastian...

15
ILO Meeting #26 ILO Meeting #26 Ongoing and forthcoming Ongoing and forthcoming Procurement activities Procurement activities 29 29 th th September 2014 - San Sebastian September 2014 - San Sebastian F4E Market Intelligence group - ILO Meeting #26 – 29th September 2014 – San Sebastian 1

Transcript of ILO Meeting #26 Ongoing and forthcoming Procurement activities 29 th September 2014 - San Sebastian...

Page 1: ILO Meeting #26 Ongoing and forthcoming Procurement activities 29 th September 2014 - San Sebastian F4E Market Intelligence group - ILO Meeting #26 – 29th.

ILO Meeting #26ILO Meeting #26

Ongoing and forthcomingOngoing and forthcomingProcurement activitiesProcurement activities

2929thth September 2014 - San Sebastian September 2014 - San Sebastian

F4E Market Intelligence group - ILO Meeting #26 – 29th September 2014 – San Sebastian 1

Page 2: ILO Meeting #26 Ongoing and forthcoming Procurement activities 29 th September 2014 - San Sebastian F4E Market Intelligence group - ILO Meeting #26 – 29th.

Reminder: MIG/BI GroupReminder: MIG/BI Group

F4E Market Intelligence group - ILO Meeting #26 – 29th September 2014 – San Sebastian 2

ANTENNAS & PLASMA ENGINEERING A. COURTIAL NEUTRAL BEAM SYSTEM & PS (T. Bonicelli) B.PERIER;M.DAVAL ION CYCLOTRON H&CD ANTENNA A. COURTIAL ELECTRON CYCLOTRON M.DAVAL

Diamond Disks A. COURTIAL MITICA Beam Source B.PERIER

EC UL Cooling Water Distribution System A. COURTIAL SF6 Plant B.PERIER

BUILDINGS (L.Schmieder) M.DAVAL Gyrotron Magnets M.DAVAL

TB13 Emergency Electrical System M.DAVAL AGPS-CS B.PERIER

CODAC (F. Sartori) A. COURTIAL PROJECT OFFICE (F. Casci) A. COURTIAL;M.DAVAL Framework contract ENGINEERING SERVICES A. COURTIAL PROJECT MANAGEMENT A. COURTIAL;M.DAVAL

CRYOPLANT & FUEL CYCLE (A. Teissier) M.DAVAL;B.PERIER Indexation M.DAVAL

REMS B.PERIER;M.DAVAL Export Control Service Provider M.DAVAL

PRE PRODUCTION CRYOPUMP B.PERIER REMOTE HANDLING (C.Damiani) B.PERIER TRITIUM M.DAVAL DIVERTOR RH B.PERIER

VACUUM PUMPIMG M.DAVAL CASK & PLUG B.PERIER

DIAGNOSTICS (G. Counsell) A. COURTIAL;M.DAVAL NB RH B.PERIER

RH CONNECTORS A. COURTIAL IN VESSEL VIEWING SYSTEM (IVVS) B.PERIER

COLLECTIVE THOMSON SCATTERING M.DAVAL TECHNICAL SUPPORT SERVICES (PY. A. COURTIAL;M.DAVAL FEEDTHROUGH M.DAVAL MATERIALS DEVELOPMENT M.DAVAL

IN-VESSEL (P.Lorenzetto) M.DAVAL Helium Test M.DAVAL

DIVERTOR IVT M.DAVAL Engineering Support A. COURTIAL

DIVERTOR CASSETTE BODY M.DAVAL VACUUM VESSEL (P.Jucker) B.PERIER MANIFOLD M.DAVAL TBD B.PERIER

MAGNETS (S. Bonito) B.PERIER BROADER APPROACH (P. Barabaschi) B.PERIER PF COILS IMPREGNATION and ADDITIONAL TOOLING B.PERIER TBD B.PERIER

PF COILS WINDING TOOLING B.PERIER

PF COILS Site & Infra B.PERIER

PF COILS Cold Test B.PERIER

PF COILS MANUFACTURING B.PERIER

Page 3: ILO Meeting #26 Ongoing and forthcoming Procurement activities 29 th September 2014 - San Sebastian F4E Market Intelligence group - ILO Meeting #26 – 29th.

MagnetsMagnets

(PF Coils)Awarded:•Winding tooling {OPE-463]: signed with Sea-Alp consortium on 8th of MayOn-going:•Impregnation & Additional tooling [OPE-559]Under evaluation:•Site & Infrastructure Management [OPE-568]Under preparation:•Manufacturing and cold test [OPE-570](CFT 11/2014)•Cold test engineering study and facility construction [OPE-585]-cf market survey

F4E Market Intelligence group - ILO Meeting #26 – 29th September 2014 – San Sebastian 3

Page 4: ILO Meeting #26 Ongoing and forthcoming Procurement activities 29 th September 2014 - San Sebastian F4E Market Intelligence group - ILO Meeting #26 – 29th.

In VesselIn Vessel

DivertorUnder evaluation: •OMF-567: 3rd Tungsten IVT prototype (deadline 17/06): start of the dialogue in September 2014 (target contract signature June 2015).•Cassette body assembly: market survey mid-2015. (target CFT Q1 2016)

First WallAwarded:• [OPE-443] full scale prototype.

F4E Market Intelligence group - ILO Meeting #26 – 29th September 2014 – San Sebastian 4

Page 5: ILO Meeting #26 Ongoing and forthcoming Procurement activities 29 th September 2014 - San Sebastian F4E Market Intelligence group - ILO Meeting #26 – 29th.

Remote HandlingRemote Handling

Awarded: Divertor RHS [OMF 340-1] to Assystem UK (rank 1)

On-going:

•Cask & Plug RHS [OMF-577] CFEI published 3rd June 2014. Deadline for requests

to participate: 4 July 2014. Invitation to dialogue: expected October 2014.

•In-Vessel Viewing System [OMF-383] on-going dialogue since mid July 2014. Final

invitation to submit tender: December 2014. Tender submission deadline: January

2015. Expected Award: July 2015.

Under evaluation:

•Neutral Beam RHS [OMF 340-3] Tender phase ongoing, deadline for submission

of tenders 16/06/2014. Expected Award: ExCo Jan. 2015.

F4E Market Intelligence group - ILO Meeting #26 – 29th September 2014 – San Sebastian 5

Page 6: ILO Meeting #26 Ongoing and forthcoming Procurement activities 29 th September 2014 - San Sebastian F4E Market Intelligence group - ILO Meeting #26 – 29th.

Cryoplant & Fuel cycleCryoplant & Fuel cycle

Tritium PlantUnder preparation:•Conceptual design for Hydrogen Isotope Separation System [ex-OPE-441]. Possible ITA signature with IO. Target CFT Q3 2015.

Vacuum pumpingAwarded: OPE-551: He gas transfer lines. Signed on 04/09/2014 with Criotec Impianti.

F4E Market Intelligence group - ILO Meeting #26 – 29th September 2014 – San Sebastian 6

ITER Cryopump component

Page 7: ILO Meeting #26 Ongoing and forthcoming Procurement activities 29 th September 2014 - San Sebastian F4E Market Intelligence group - ILO Meeting #26 – 29th.

TBM & Materials developmentTBM & Materials development

Ancillary system

F4E Market Intelligence group - ILO Meeting #26 – 29th September 2014 – San Sebastian 7

Page 8: ILO Meeting #26 Ongoing and forthcoming Procurement activities 29 th September 2014 - San Sebastian F4E Market Intelligence group - ILO Meeting #26 – 29th.

Technical SupportTechnical Support

F4E Market Intelligence group - ILO Meeting #26 – 29th September 2014 – San Sebastian 8

Page 9: ILO Meeting #26 Ongoing and forthcoming Procurement activities 29 th September 2014 - San Sebastian F4E Market Intelligence group - ILO Meeting #26 – 29th.

Planning and SchedulingPlanning and Scheduling

Under evaluation:

•[OMF 555]: FW for dual use export compliance services

•[OMF 556]: FW for Planning and scheduling

•[OMF 557]: FW for Quality Inspection

F4E Market Intelligence group - ILO Meeting #26 – 29th September 2014 – San Sebastian 9

Page 10: ILO Meeting #26 Ongoing and forthcoming Procurement activities 29 th September 2014 - San Sebastian F4E Market Intelligence group - ILO Meeting #26 – 29th.

Neutral Beam & EC Power SuppliesNeutral Beam & EC Power Supplies

F4E Market Intelligence group - ILO Meeting #26 – 29th September 2014 – San Sebastian 10

1 MW CW Gyrotron (140 GHz) W7-X

Page 11: ILO Meeting #26 Ongoing and forthcoming Procurement activities 29 th September 2014 - San Sebastian F4E Market Intelligence group - ILO Meeting #26 – 29th.

DiagnosticsDiagnostics

F4E Market Intelligence group - ILO Meeting #26 – 29th September 2014 – San Sebastian 11

Page 12: ILO Meeting #26 Ongoing and forthcoming Procurement activities 29 th September 2014 - San Sebastian F4E Market Intelligence group - ILO Meeting #26 – 29th.

Buildings (and site adaptation) 1/2Buildings (and site adaptation) 1/2

F4E Market Intelligence group - ILO Meeting #26 – 29th September 2014 – San Sebastian 12

Page 13: ILO Meeting #26 Ongoing and forthcoming Procurement activities 29 th September 2014 - San Sebastian F4E Market Intelligence group - ILO Meeting #26 – 29th.

Buildings (and site adaptation) 2/2Buildings (and site adaptation) 2/2

F4E Market Intelligence group - ILO Meeting #26 – 29th September 2014 – San Sebastian 13

Page 14: ILO Meeting #26 Ongoing and forthcoming Procurement activities 29 th September 2014 - San Sebastian F4E Market Intelligence group - ILO Meeting #26 – 29th.

Antennas & Plasma EngineeringAntennas & Plasma Engineering

EC launcher

Antennas

F4E Market Intelligence group - ILO Meeting #26 – 29th September 2014 – San Sebastian 14

Page 15: ILO Meeting #26 Ongoing and forthcoming Procurement activities 29 th September 2014 - San Sebastian F4E Market Intelligence group - ILO Meeting #26 – 29th.

F4E Market Intelligence group - ILO Meeting #26 – 29th September 2014 – San Sebastian 15

ILO Meeting #26 Market surveysILO Meeting #26 Market surveys

Market Surveys on-going

DIAGNOSTICS- bolometer sensor manufacturingMAGNETS- PF coils cold tests

Market Surveys to comeDIVERTOR – Cassette assembly, Q1 2015EC UL/CODAC – System and Instrumentation Engineering Support, Q3 2014

Info Days to come

10th June 2015: F4E Forum