ILC Global Design Effort

29
7-Nov-09 NRC BPA Global Design Effort 1 Barry Barish NRC BPA 7-Nov-09 ILC Global Design Effort FLASH TESTS

Transcript of ILC Global Design Effort

Page 1: ILC Global Design Effort

7-Nov-09 NRC BPA

Global Design Effort 1

Barry BarishNRC BPA7-Nov-09

ILC Global Design Effort

FLASH TESTS

Page 2: ILC Global Design Effort

7-Nov-09 NRC BPA

Global Design Effort 2

ILC Global Context• Advancing the energy frontier has been and will

continue to be our most important tool for probing the central scientific questions in our field– Worldwide consensus through long range

planning studies that LHC followed by a complementary lepton collider (ILC is the leading candidate) is the highest priority for the future of particle physics (e.g. EPP2010)

– Total global cost of a future investment will be about the same scale as LHC or ITER.

– If the U.S. is to remain a leader in the field, it must have a significant role in a global lepton collider

Page 3: ILC Global Design Effort

7-Nov-09 NRC BPA

Global Design Effort 3

Proton-Proton Collisions at the LHC 2835 + 2835 proton

bunchesseparated

by

7.5 m→

collisions

every

25 ns= 40 MHz crossing

rate

1011

protons

per bunch

at 1034/cm2/s≈

35 pp

interactions

per crossingpile-up

→ ≈ 109

pp

interactions

per second !!!

In

each

collision≈

1600 charged

particles

produced

Enormous

challenge

for

the

detectors

Page 4: ILC Global Design Effort

7-Nov-09 NRC BPA

Global Design Effort 4

Exploring the Terascale• The LHC

– It will lead the way and has large reach– Quark-quark, quark-gluon and gluon-gluon

collisions at 0.5 -

5 TeV– Broadband initial state

• The ILC– A second view with high precision– Electron-positron collisions with fixed

energies, adjustable between 0.1 and 1.0 TeV– Well defined initial state

• Together, these are our tools for the terascale

Page 5: ILC Global Design Effort

7-Nov-09 NRC BPA

Global Design Effort 5

What will e+e-

Collisions Contribute?

• elementary particles

• well-defined

– energy,– angular momentum

• uses full COM energy

• produces particles democratically

• can mostly fully reconstruct events

Page 6: ILC Global Design Effort

7-Nov-09 NRC BPA

Global Design Effort 6

LHC ILCe+ e– Z H

Z e+ e–, H b …

Higgs event Simulation Comparison

b

Page 7: ILC Global Design Effort

7-Nov-09 NRC BPA

Global Design Effort 7

LHC: Low mass Higgs:

H MH < 150 GeV/c2

Rare decay channel: BR~10-3

Requires excellent electromagnetic calorimeter performance

acceptance, energy and angle resolution,

/jet and /0 separation

Motivation for LAr/PbWO4 calorimeters for CMS

Resolution at 100 GeV:

1 GeV

Background large: S/B

1:20, but

can estimate from non signal areas

CMS

Page 8: ILC Global Design Effort

7-Nov-09 NRC BPA

Global Design Effort 8

Precision Higgs physics

Model-independent Studies• mass

• absolute branching ratios

• total width

• spin

• top Yukawa coupling

• self coupling

Precision MeasurementsGarcia-Abia et al

Page 9: ILC Global Design Effort

7-Nov-09 NRC BPA

Global Design Effort 9

The linear collider will measure the spin of any Higgs it can produce by measuring the energy dependence from threshold

ILC: Is it really the Higgs ?

Measure the quantum numbers. The Higgs must have spin zero !

Page 10: ILC Global Design Effort

7-Nov-09 NRC BPA

Global Design Effort 10

What can we learn from the Higgs?

Precision measurements of Higgs coupling

Higgs Coupling strength is proportional to Mass

Page 11: ILC Global Design Effort

7-Nov-09 NRC BPA

Global Design Effort 11

Possible TeV Scale Lepton Colliders

ILC < 1 TeVTechnically possible

~ 2015 +

QUADQUAD

POWER EXTRACTIONSTRUCTURE

BPM

ACCELERATINGSTRUCTURES

CLIC < 3 TeVFeasibility?

ILC + 5-10 yrsMain beam –

1 A, 200 ns from 9 GeV to 1.5 TeV

Drive beam -

95 A, 300 nsfrom 2.4 GeV to 240 MeV

Muon Collider< 4 TeV

FEASIBILITY??ILC + 15 yrs?

Much R&D Needed• Neutrino Factory R&D +• bunch merging• much more cooling?• precision detectors??

ILC

CLIC

Muon Collider

Page 12: ILC Global Design Effort

7-Nov-09 NRC BPA

Global Design Effort 12

ICFA: e+e-

Linear Collider

• Physics Parameters– International subcommittee

report

• Technology– Superconducting RF

• International Design Team– Global Design Effort (2005)

Page 13: ILC Global Design Effort

7-Nov-09 NRC BPA

Global Design Effort 13

ILC Collider Parameters ICFA Report

• Ecm adjustable from 200 – 500 GeV

• Luminosity

∫Ldt = 500 fb-1 in 4 years

• Ability to scan between 200 and 500 GeV

• Energy stability and precision below 0.1%

• Electron polarization of at least 80%

• The machine must be upgradeable to 1 TeV

Page 14: ILC Global Design Effort

7-Nov-09 NRC BPA

Global Design Effort 14

The ILC SCRF Cavity

- Achieve high gradient (35MV/m); develop multiplevendors; make cost effective, etc

- Focus is on high gradient; production yields; cryogeniclosses; radiation; system performance

Page 15: ILC Global Design Effort

7-Nov-09 NRC BPA

Global Design Effort 15

main linacbunchcompressor

dampingring

source

pre-accelerator

collimation

final focus

IP

extraction& dump

KeV

few GeV

few GeVfew GeV

250-500 GeV

Designing a Linear Collider

Superconducting RF Main Linac

Page 16: ILC Global Design Effort

7-Nov-09 NRC BPA

Global Design Effort 16

ILC Global Context (ILC)

• Large R&D and Design Effort Worldwide on Accelerator and Detectors for the ILC– Total program is ~ $100M / year worldwide to

be compared with a total world HEP program of ~$2500M / year.

– The underlying technology –

Superconducting RF acceleration is developing rapidly and is strong candidate for next generation particle accelerators (XFEL, ILC, Project X, etc). Also, broad applications beyond particle physics

– SCRF accounts for about half the total ILC R&D program

Page 17: ILC Global Design Effort

7-Nov-09 NRC BPA

Global Design Effort 17

– 11km SC linacs operating at 31.5 MV/m for 500 GeV– Centralized injector

• Circular damping rings for electrons and positrons• Undulator-based positron source

– Single IR with 14 mrad crossing angle– Dual tunnel configuration for safety and availability

ILC Reference Design

Reference Design – Feb 2007

Documented in Reference Design Report

Page 18: ILC Global Design Effort

7-Nov-09 NRC BPA

Global Design Effort 18

RDR Design Parameters

Max. Center-of-mass energy 500 GeV

Peak Luminosity ~2x1034 1/cm2s

Beam Current 9.0 mA

Repetition rate 5 Hz

Average accelerating gradient 31.5 MV/m

Beam pulse length 0.95 ms

Total Site Length 31 km

Total AC Power Consumption ~230 MW

Page 19: ILC Global Design Effort

7-Nov-09 NRC BPA

Global Design Effort 19

International Costing

• “Value” Costing System: International costing for International Project– Provides basic agreed to “value”

costs– Provides estimate of “explicit”

labor (man-hr)]

• Based on a call for world-wide tender:– Lowest reasonable price for required quality

• Classes of items in cost estimate:– Site-Specific: separate estimate for each sample site– Conventional: global capability (single world est.)– High Tech: cavities, cryomodules (regional estimates)

Page 20: ILC Global Design Effort

7-Nov-09 NRC BPA

Global Design Effort 20

RDR Design & “Value”

Costs• The reference design was “frozen”

as of 1-Dec-06 for

the purpose of producing the RDR, including costs.

• It is important to recognize this is a snapshot and the design will continue to evolve, due to results of the R&D, accelerator studies and value engineering

• The value costs have already been reviewed three time

Total Value

Estimate = 6.62 B$ (US 2007)(+ 24M person-hours explicit labor ~ $1.4 B U.S.)

• ILCSC MAC review• International Cost Review Total ~ 8.0 B 2007$

Page 21: ILC Global Design Effort

7-Nov-09 NRC BPA

Global Design Effort 21

RDR Design & “Value”

Costs

SummaryRDR “Value”

Costs

Total Value Cost (FY07)4.80 B ILC Units Shared

+1.82 B Units Site Specific

+14.1 K person-years

(“explicit” labor = 24.0 M person-hrs

@ 1,700 hrs/yr) 1 ILC Unit = $ 1 (2007)

Host Cost$1.82 B Site Specific$0.70 B (~ 1/2 manpower)$1.60 B (Shared Costs)-------------$4.1 B (approx 50% total)

Partners (off-shore cost)$0.30 B (manpower)$1.00 B (shared costs------------$1.30 B (~ 15-20% total)

FY 07 $$

Page 22: ILC Global Design Effort

7-Nov-09 NRC BPA

Global Design Effort 22

Translating to “U.S. Costs”

• No official or detailed translation has been performed

• What are the factors?• Add some contingency (note GDE estimates include some, but not all (DoE) contingency. It needs to be done item by item. (conservatively + 20%) [ $8B ~$10B]

• Escalation to “then year dollars.”

This is the big factor that people use –

escalating for ~ 15-20 years would be ~ 200%

• For the total project, this gives ~$20B+

(then year $$)

• Comments:• US costs will only be a fraction of total project costs (off shore or on shore).

• Thinking in “then year”

$$ in the far future can be quite misleading. (Wages, GDP, etc also scale with inflation; Japan no

inflation, etc)

Page 23: ILC Global Design Effort

7-Nov-09 NRC BPA

Global Design Effort 23Global Design Effort 23

Major R&D Goals for TDP 1SCRF

• High Gradient R&D -

globally coordinated program to demonstrate gradient by 2010 with 50%yield

• Preview of new results from FLASH

ATF-2 at KEK• Demonstrate Fast Kicker performance and Final Focus

Design

Electron Cloud Mitigation – (CesrTA)• Electron Cloud tests at Cornell to establish mitigation

and verify one damping ring is sufficient.

Accelerator Design and Integration (AD&I)• Studies of possible cost reduction designs and

strategies for consideration in a re-baseline in 2010

Page 24: ILC Global Design Effort

7-Nov-09 NRC BPA

Global Design Effort 24

Gradient GoalElectropolished 9-cell Cavities

0

10

20

30

40

50

60

70

80

90

100

>10 >15 >20 >25 >30 >35 >40

max gradient [MV/m]

yiel

d [%

]

DESY last test (25 cavities)JLab best test (14 cavities)DESY first successful test of cavities from qualified vendors - ACCEL+ZANON (15 cavities)JLab first successful test of cavities from qualified vendors - ACCEL (7 cavities)

OldNew

Page 25: ILC Global Design Effort

7-Nov-09 NRC BPA

Global Design Effort 25

TTF/FLASH 9mA Experiment

XFEL ILC FLASH design

9mA studies

Bunch charge

nC 1 3.2 1 3

# bunches 3250 2625 7200* 2400

Pulse length s 650 970 800 800

Current mA 5 9 9 9

Full beam-loading long pulse operation “S2”

• Stable 800 bunches, 3 nC at 1MHz (800 s pulse) for over 15 hours (uninterrupted)

• Several hours ~1600 bunches, ~2.5 nC at 3MHz (530 s pulse)

• >2200 bunches @ 3nC (3MHz) for short periods

Page 26: ILC Global Design Effort

7-Nov-09 NRC BPA

Global Design Effort 26

RF Gradient Long-Term Stability

Outliers caused by beam-loss trips prematurely shortening the beam pulse

Example Result

Page 27: ILC Global Design Effort

7-Nov-09 NRC BPA

Global Design Effort 27Global Design Effort 27

Major R&D Goals for TDP 1SCRF

• High Gradient R&D -

globally coordinated program to demonstrate gradient by 2010 with 50%yield

• Preview of new results from FLASH

ATF-2 at KEK• Demonstrate Fast Kicker performance and Final Focus

Design

Electron Cloud Mitigation – (CesrTA)• Electron Cloud tests at Cornell to establish mitigation

and verify one damping ring is sufficient.

Accelerator Design and Integration (AD&I)• Studies of possible cost reduction designs and

strategies for consideration in a re-baseline in 2010

Page 28: ILC Global Design Effort

7-Nov-09 NRC BPA

Global Design Effort 28

Technical Design Phase and Beyond

AD&I studies

2009 2010

RDR ACD concepts

R&D Demonstrations

TDP Baseline Technical Design

2011 2012 2013

RDR Baseline

New

baseline inputs

TDR

TDP-1 TDP-2 ChangeRequest

Page 29: ILC Global Design Effort

7-Nov-09 NRC BPA

Global Design Effort 29

Final Remarks• We will be well positioned to propose a robust well-

developed project on a 2012-2013 timescale. NO COST GROWTH

• Earliest start for a construction project is ~ 2015, assuming science case, funding, siting, etc are in place

• CERN (see Sept Physics World) has stated its intent (or desire) to host a linear collider (either ILC or CLIC). This must be considered the most serious possibility, because of CERN ‘stable’

funding (earliest start ~ 2018)

• Japan or US are possible alternatives for hosting (Russia?). Japan is actively working toward the possibility (strong support group, siting efforts, industrialization, etc). Hosting efforts in the US are presently dormant, but the option remains viable, since we are developing key US technical infrastructures, etc.