ILC Dominant Technologies
Transcript of ILC Dominant Technologies
ILC Dominant Technologies
M. Ross, SLAC
Linac Coherent Light Source-II
Cryogenics System Manager
25 October 2018
LCWS 2018 UTA
LCLS-II Partnership
2
Background:
Involving Industry in Superconducting RF
LCWS18 M. Ross (SLAC)
TESLA and ILC – Design studies and Industrialization
R&D from 1992 to 2013; continuing to present
• 20 year technical and infrastructure development: Creating a
de-facto standard
EU-XFEL Project – Execution 2010 to 2016
LCLS-II Project – Execution 2013 – 2020
Two 7 year-long ~1B$ highly Industrialized Projects
realization of TESLA vision
10 years of effort and investment in support of photon science
1-15 keV X-ray
Free Electron Lasers
TDR ILC Cost Model:
Basis type
15.05.2013 IPAC 13, Marc Ross, SLAC 3
SC Linac: 35% Value
estimate
Cost Basis
type for
ENTIRE ILC
estimate
IPAC 2013 Industrial Session
LCLS-II large scale deployment of ILC technology
Fermilab 25 March 2015 (M. Ross, SLAC)
e.g. Cavity / Cryomodule:
• Cost Validation : few percent scale
• Cost Reduction
- Applied production balanced against continued R&D
- From C100 (JLab) to EXFEL: factor 2 cavity cost reduction
• Technical Risk Mitigation
- Demonstrate construction and performance of ILC-type
cryomodules for science in the US
For US, the work on ILC and now on LCLS II has brought
together SRF programs in a way that maximizes
collaboration, efficient sharing of IP, and facilities giving the
most “bang for the buck”.
5
ILC Dominant Technologies for LCLS-II:
Outline
• LCLS-II Industrialization Progress and Challenges
• Superconducting RF (SRF) Technology
• Cryogenic Systems
• Supporting Technologies
• Institutional Contributions
• Fermilab, Jefferson Lab, Cornell U, and SLAC
• Industrial-work in an institutional context
• Implications for ILC
• US team is better prepared, and may contribute to ILC as
a strong partner
LCWS18 M. Ross (SLAC)
Cryomodule Design
modifications by
Fermilab
LCWS18 M. Ross (SLAC)
Slide 6
LCLS-II(Linac Coherent Light Source-II)
New Injector and
New Superconducting Linac
Existing Bypass Line
New Transport Line
Two New Undulators
And X-Ray Transport
Exploit Existing
Experimental Stations
New Cryoplant
Remove SLAC
Linac from
Sectors 0-10
7
LCLS-II:
A CW linac using TESLA / ILC / XFEL technology
LCWS18 M. Ross (SLAC)
• 4 GeV, Low Current (100uA), High power (1.2 MW), 100% DF
• Cavity / Coupler Heat Load is a critical performance criteria
• Cavity “Q0” Improved 3x compared to XFEL/ILC
• Gradient v/v Heat Load: intrinsic / extrinsic
• Bulk Nb, Magnetic Hygiene, Fast cool-down, Quench
management
• 95% of the cryogenic load is DYNAMIC
• Re-evaluation of cryogenic plumbing and level control
• Removal of 5K shield: static load is too small to justify
• RF Power: Solid State Amplifiers
• Cryogenic Capacity
• Different philosophy from LHC primary heat load at 2 Kelvin
LCWS18 M. Ross (SLAC)
LCLS-II Cryogenic System:
(ILC Technologies)
Component Count Parameters
Linac 4 cold -
segments
35 each 8 cavity Cryomodules (1.3 GHz)
2 each 8 cavity Cryomodules (3.9 GHz)
1.3 GHz Cryomodule
(CM)
8 cavities/CM 13 m long. Cavities + SC Magnet package
+ BPM
3.9 GHz Cryomodule 8 cavities/CM 6.2 m long. Cavities + BPM
Additional
Cryomodules
1.3 GHz: 4 production + 1 spare
3.9 GHz: 1 spare
1.3 GHz 9-cell cavity 320 each 16 MV/m; Q0 ~ 2.7e10 (avg); 2.0 K;
gradient reach to 19 MV/m (No Q-spec);
bulk niobium sheet - metal
3.9 GHz 9-cell cavity 24 each 13.4 MV/m; Q0~2.0e9
Cryoplant (CP1/CP2) 2 each 4.5 K / 2.0 K cold boxes; 4 kW @ 2.0 K; 18
kW @ 4.5 K; 3.7 kW nom. tot. load
Spare compressors 2 Warm He Comp. 1 spare Cold Comp.
Cryogenic Distribution
System (CDS)
210 m vacuum-jacketed line, 2 each distribution boxes, 6
each feedcap / 2 each endcap 8
9
SRF Linac Dominant Technology Score-Card (2018)
LCWS18 M. Ross (SLAC)
Technology XFEL / LCLS-II
xfer to industry
Issues: XFEL Issues: LCLS-II
Niobium/NbTi Y OK Bulk Specification
Cavity Resonator Y OK – FE rerinse FE rerinse, high
Q performance
Power Coupler Y Plating Bellows
Tuner Y OK New design – OK
Helium Vessel Y Ti welding
(nearby pipes)
Ti bellows
Magnet (Q, X, Y) Y OK New design – OK
Cryostat/cold
mass
Y OK OK – high heat
load, magnetic
hygiene
Assembly Y/N OK Institution
Test Partner institute/N OK Institution
Cavity Resonator
LCWS18 M. Ross (SLAC)
LCLS-II Specification: Q0≥ 2.7x1010 @ Eacc = 16 MV/m in 5 mG remnant field
• Additionally the cavities must reach 19 MV/m in VT
• Reduce 2K cryogenic load, and thus operating cost of machine.
• Made possible by Nitrogen doping of SRF cavities.
• 2 trade-offs.
• Losses from trapped magnetic flux can be up to 3.6 times higher
• Reduction in maximum achievable gradient of cavity – not an issue for CW
• Remedied by:
• Improved magnetic hygiene and shielding
• Optimized design and cooldown procedures
10
N2 doping developed by
Fermilab and transferred to
industry by LCLS-II team
New results up to 49 MV/m in Tesla shape 1.3 GHz cavities
10/24/2018Anna Grassellino - highQ/high G R&D @ FNAL11
Modified low T bake cavities
Seven different single cell cavities have now achieved unprecedented accelerating gradients with Q > 1.5e10 at 40 MV/m, post the new low T bake tweak (addition of step at 50-75C); detailed investigations ongoing; cavities sent to Cornell and Jlab, then to KEK for verification in different dewars
Grassellino et al,
FNAL
arXiv:1806.09824
See Anna’s talk
Thursday 25 Oct
Power Coupler
RF input (room temperature)
Cryogenic
temperature
LCWS18 M. Ross (SLAC)
Bellows Challenges:
1. Failure
2. Plating quality
13
Cavity Tuner
LCWS18 M. Ross (SLAC)
Precision electro-mechanical
component @2K
Stepping motor; Piezo-actuator
14
Cavity Tuner Performance:
LCWS18 M. Ross (SLAC)
LCLS-II Data
Showing real-time resonator
tune
Spec: +/- 10 Hz deviation
must not happen more than
once ~ hours
15
XFEL vs ILC vs LCLS-II 2K
He vessel
LCWS18 M. Ross (SLAC)
ILC
LCLS-2
XFEL
Challenges:
Ti welding
Bellows weakness
16
Conduction-cooled SC Magnet
Package
LCWS18 M. Ross (SLAC)
Fermilab-design
Made by US company
XFEL Magnet package (Ciemat)
17
LCLS-II Cryomodule – adapted for 100W (2K) operation
~10x XFEL
LCWS18 M. Ross (SLAC)
18
Magnetic Hygiene, De-gaussing, Magnetic Shielding
LCWS18 M. Ross (SLAC)
LCLS-II Double-layer
‘hermetic’ shielding reduces
B_ambient to <5 mGauss
1.3 GHz CM Progress
Cavities Vendor performance good
• 256 cavities assigned to strings
• Avg Q0 of these cavities in vertical test: 3.0 x 1010
Cryomodules
• 30 (of 40) cryomodule assemblies started
• 20 cryomodule tests complete (4 require retest)
• Gradient performance 14% above spec (128MV/m)
• Net gradient reduction (from Vertical Test) due to Field
Emission: 128 MV
• Q0 at spec (2.7e10 @ 16 MV/m)
No CM delivered to SLAC yet
19DOE IPR, Aug 28-29th, 2018
CM Q0 Performance
Cryomodule Heat-Load (Average Q0) Test Results
X 1010 X 1010
FNAL pCM 2.9 Jlab pCM 2.7 *
* tested at Fermilab
F1.3-02 2.1 J1.3-02 1.7 JLab
slow
cool-
down
(now
fixed)
F1.3-03 3.4 J1.3-03 2.2
F1.3-04 3.1 J1.3-04 1.9
F1.3-05 3.0 J1.3-05 2.3
F1.3-06 1.9 J1.3-07 1.9
F1.3-07 2.6 J1.3-08 2.5
F1.3-08 2.3 J1.3-10 3.0
F1.3-09 3.3
F1.3-10 2.7
F1.3-11 3.6
F1.3-12 3.3
Operations model (with
test results shown here)
suggest that we will
have a total heat load
(@2K):
~3.7 kW
7.5% margin, one CP
Both 1.3-02 modules with low heat-treat cavities
JLab-tested CM are
expected to show in-
spec heat load with
proper cool-down
CM E_acc Performance
Cryomodule E_acc Test Results
MV MV
FNAL pCM 145 Jlab pCM 145
F1.3-02 166 J1.3-02 138
F1.3-03 146 J1.3-03 134
F1.3-04 164 J1.3-04 144
F1.3-05 158 J1.3-05 150
F1.3-06 166 J1.3-07 130
F1.3-07 167 J1.3-08 127
F1.3-08 162 J1.3-10 156
F1.3-09 171
F1.3-10 168
F1.3-11 163
F1.3-12 152
Spec:
128 MV/cryomodule
(avg)
Exceed spec in all but
one
Four CM have no field
emission
2. Cryogenics: “PROCESS”: Loads
22
1.3 GHz Cryo-Modules: x 35
• Cavities: 8
• Length 12 m
• Weight 8,000 kg
CP #1 CP #2
Cryo-Modules: x 37
3.9 GHz Cryo-Modules: x 2
• Cavities: 8
• Length 6 m
• Weight 4,000 kg
LCWS18 M. Ross (SLAC)
2. PROCESS: Loads
23
CAVITIES:
- A: 4K, 3.00 bar
- B: 2K, 0.03 bar
INTERCEPT:
- C: 5.5K, 3.0 bar
- D: 7.5K, 1.3 bar
SHIELDS:
- A: 35 K, 3.0 bar
- B: 55 K, 1.3 bar
• Loads: Cryo-Modules
LCWS18 M. Ross (SLAC)
2. Cryoplant: Capacity - 2x 18kW eq. @ 4.5K
24
3 421
45K Shield
8K Shield
Design Temp. kW eq @ 4.5K
Warm Sh. 45 K 1.8 kW
Cold Sh. 6.5 K 1.2 kW
Liquef. 4.5 K 1.5 kW
Cavities 2.0 K 13.7 kW
TOTAL eq. at 4.5K 18 kW / Plant
“2x Cryo-plants: LN2 Pre-Cooled, 4 Turbines, 75% Capacity @ 2.0K”
Eric Fauve
Cryoplant design: JLab
2. PROCESS: Cold Compressors
25
Comp. P [mbar] T [K]
C1 Suct. 27 3.5
C2 Suct. 85 6.3
C3 Suct. 202 9.8
C4 Suct. 410 14.1
C5 Suct. 781 19.9
C5 Disch. 1 202 25.2
Total Flow: 215 g/s
3 421
45K Shield
8K Shield
LCWS18 M. Ross (SLAC)
Difference wrt LHC
Critical Technology
3. EQUIPMENT: CRYO-PLANT / Compressors
26
• 12x HOWDEN 321 / 193
STAGE / Plant Power L W H Weight
LP 3 x 600 kW 800 hp 7.0 m 3.3 m 3.4 m 25 tons
MP 1 x 750 kW 1 000 hp 7.0 m 3.3 m 3.5 m 25 tons
HP 1 x1 850 kW 2 500 hp 7.6 m 3.3 m 3.6 m 27 tons
SWING 1 x
600 kW to 1 850 kW / L ~ 7.5 m x W ~ 3.5m x H ~ 3.5 m / ~ 25 tons
Dana Arenius
LCWS18 M. Ross (SLAC)
Difference wrt LHC
Integrated unit developed
and industrialized - JLab
3. EQUIPMENT: CRYO-PLANT / Compressors
27
• Compressor Skids:
“A JLab Design: Compact & Cost Effective” (~20 made)
Dana Arenius
28
LCLS-II Warm
Compressors
made by
PHPK,
(Columbus,
OH). Installed
at SLAC
LCWS18 M. Ross (SLAC)
3. EQUIPMENT: CRYO-PLANT / Cold Boxes
29
• Upper Cold Boxes:
• H: 13m x D: 4m, ~50 tons
• LN2 Pre-cooler.
• Lower Cold Boxes:
• L: 11m x D: 4m, ~50 tons
• 4x Turbines.
• 2.0 K Cold Boxes:
• H= 3.5 m, D= 3.5m, ~15 tons
• 5x Cold Compressors *
Dana Arenius
LCWS18 M. Ross (SLAC)
30
Jlab CEBAF 12 GeV
Upgrade 4.5 K cold-
box (Linde) ‘CHL 2’
OutlineLCWS18 M. Ross (SLAC)
31
Two large cold-boxes at SLAC, Oct 2018
LCWS18 M. Ross (SLAC)
32
Brazed Al Heat Exchanger:
Critical Technology
LCWS18 M. Ross (SLAC)
Performance
Issues:
SNS, JLab CHL2
Sumitomo PP (Kobe)
Chart Industries (LaCrosse, WI)
View along main linac:
LCWS18 M. Ross (SLAC) 33
RF Power Source and Distribution
Marx modulator 10MW MB Klystron
Adjustable local power distribution system
34LCWS18 M. Ross (SLAC)
LCWS18 M. Ross (SLAC) 35
Multi-beam klystron
The High-power RF
source for ILC
SLAC Marx Modulator:
32 cells x 4 kV / each to deliver
120 kV, 1.6 ms, 5 HzLCWS18 M. Ross (SLAC)
36
37LCWS18 M. Ross (SLAC)
Shielding
Cap
Conduits
38
Basic Layout at a typical LCLS-II 1.3 GHz HPRF
5 possible variations at the
accelerator housing ceiling:
• 4 upstream
• 4 downstream
• 2 upstream, 2 downstream
• 3 upstream, 1 downstream
• 1 upstream, 3 downstream
LCWS18 M. Ross (SLAC)
• Waveguide system consists of
• Isolator immediately after the SSA output
• Straights
• E, H and U bends
• 2 Flex Guides (downstream of Isolator and
final E-bend in the housing
• Directional Coupler after second flex guide
• Identical layouts for
• SSA to cryomodule (slight support variations
possible)
• in penetration
• cryomodule to accelerator housing ceiling
39
Basic LCLS-II Waveguide System
~10’
~ 20’
~36’
LCWS18 M. Ross (SLAC)
SS Amplifier (R&K Fuji-City)
Waveguide (Mega Gorham
ME)
40
Cryomodule Assembly and Testing at Institutes
LCWS18 M. Ross (SLAC)
Jefferson Lab and Fermilab
• Different infrastructure; equivalent process
• Experienced in-house staff
• Infrastructure (clean-room, rails and cantilever, tooling)
adapted from DESY/Saclay
• Critical welding, water-rinse, cryogenic testing, etc
technology
41
Summary
LCWS18 M. Ross (SLAC)
• 1.3 GHz CM produced every four days (CEA and DESY
and vendors)
• Three weeks for LCLS-II
• Mass Production of integrated SRF module
• EU-XFEL started in May 2017
• LCLS-II to start in early 2021
• LCLS-II-HE extension to 8GeV launched (CD0)
• ~20 new cavities
• New cavity doping to extend gradient
Cold Coupler Assembly into cavity
LCWS18 M. Ross (SLAC) CEA Saclay, France
Clean Room
work
44
Basic LCLS II 1.3 GHz SSA Unit
Basic SSA Units include
• Control Module
• Amplifier Modules
• Power supplies
• Heat Exchanger
45
Front and Side Back
The R&K 1.3 GHz SSA Rack for LCLS II
LCWS18 M. Ross (SLAC)
7 each 1.3 GHz SSAs Prior to Shipment
46LCWS18 M. Ross (SLAC)
Outline
(Fuji City)