ILC Accelerator SCRF R&D Plan and Organization Presented by Akira Yamamoto for ILC-GDE Project...

46
ILC Accelerator SCRF R&D Plan and Organization Presented by Akira Yamamoto for ILC-GDE Project Managers Marc Ross, Nick Walker, and A. Yamamoto To be presented at KEK LC Review, July 22, 2009 09-07-22, A. Yamamoto 1 ILC-GDE SCRF Plan

Transcript of ILC Accelerator SCRF R&D Plan and Organization Presented by Akira Yamamoto for ILC-GDE Project...

Page 1: ILC Accelerator SCRF R&D Plan and Organization Presented by Akira Yamamoto for ILC-GDE Project Managers Marc Ross, Nick Walker, and A. Yamamoto To be presented.

ILC AcceleratorSCRF

R&D Plan and Organization

Presented by Akira Yamamoto

for ILC-GDE Project Managers

Marc Ross, Nick Walker, and A. Yamamoto

To be presented at KEK LC Review, July 22, 2009

09-07-22, A. Yamamoto 1ILC-GDE SCRF Plan

Page 2: ILC Accelerator SCRF R&D Plan and Organization Presented by Akira Yamamoto for ILC-GDE Project Managers Marc Ross, Nick Walker, and A. Yamamoto To be presented.

2

Outline

Introduction R&D Status Plan for Technical Design Phase Industrialization Accelerator Design and Integration (AD&I) Summary

09-07-22, A. Yamamoto ILC-GDE SCRF Plan

Page 3: ILC Accelerator SCRF R&D Plan and Organization Presented by Akira Yamamoto for ILC-GDE Project Managers Marc Ross, Nick Walker, and A. Yamamoto To be presented.

SCRF Technology Required

Parameter Value

C.M. Energy 500 GeV

Peak luminosity 2x1034 cm-2s-1

Beam Rep. rate 5 Hz

Pulse time duration 1 ms

Average beam current

9 mA   (in pulse)

Av. field gradient

31.5 MV/m

# 9-cell cavity 14,560# cryomodule 1,680# RF units 560

309-07-22, A. Yamamoto ILC-GDE SCRF Plan

Page 4: ILC Accelerator SCRF R&D Plan and Organization Presented by Akira Yamamoto for ILC-GDE Project Managers Marc Ross, Nick Walker, and A. Yamamoto To be presented.

GDE Project Structure

09-07-22, A. Yamamoto ILC-GDE SCRF Plan 7

Page 5: ILC Accelerator SCRF R&D Plan and Organization Presented by Akira Yamamoto for ILC-GDE Project Managers Marc Ross, Nick Walker, and A. Yamamoto To be presented.

Nick WalkerProject Manager

Accelerator Systems

Junji Urakawa(KEK)

Frank Lehner(DESY)

Axel Brachmann (SLAC)Electron Source

Jim Clarke (STFC)Positron Source

Andy Wolski(Cockcroft Institute)

Damping Ring

Nikolay Solyak (FNAL)RTML

Kiyoshi Kubo (KEK)Simulation

Andre Seryi (SLAC)BDS

Akira YamamotoProject Manager

SCRF Tech.

Tetsuo Shidara (KEK)

Jim Kerby(FNAL)

Lutz Lilje (DESY)Cavity Processing

Hitoshi Hayano (KEK)Cavity Production &

Integration

Norihito Ohuchi (KEK) Leader

Harry Carter (FNAL)Co-Leader

Cryomodule

Shigeki Fukuda (KEK)HLRF

Tom Peterson (FNAL)Cryogenics

Chris Adolphsen (SLAC)

Main Linac Integration

Technical Areas and Groups

• Engineering and Scientific Management

• 25 (16 below PM)

– 7 Asia– 7 EU– 11 Americas

809-07-22, A. Yamamoto ILC-GDE SCRF Plan

L.Lilje >> R. Geng

Susanna Guiducci(infn)

Page 6: ILC Accelerator SCRF R&D Plan and Organization Presented by Akira Yamamoto for ILC-GDE Project Managers Marc Ross, Nick Walker, and A. Yamamoto To be presented.

Global Plan for SCRF R&DA Summary

Calender Year 2007 2008 2009 2010 2011 2012

Technical Design Phase TDP-1 TDP-2

Cavity Gradient R&D

to reach 35 MV/m

Process Yield > 50%

Production Yield >90%

Cavity-string test:

with 1 cryomoduleGlobal collab. For <31.5 MV/m>

System Test with beam

1 RF-unit (3-modulce)

FLASH (DESY) STF2 (KEK)

NML (FNAL)

909-07-22, A. Yamamoto ILC-GDE SCRF Plan

R&D/prepare for Industrialization

Page 7: ILC Accelerator SCRF R&D Plan and Organization Presented by Akira Yamamoto for ILC-GDE Project Managers Marc Ross, Nick Walker, and A. Yamamoto To be presented.

Cavity- and Cryomodule-String Program (S1G, S2) at KEK, Japan

C. Year 2008 2009 2010 2011 2012 2013 2014

Cavity String(S1-Global)

Cavity >> Ins Test

Cryomodule String Test (S2) *High Pressure Code Regulation/Stamp to be applied

Quant. Beam*(Compact L.S.)

Cavity >> Inst. Test

Cryomodule 1* Cavity >> >> Ins & T

Cryomodule 2,3*

Cavity >> >> Ins Ins & T

Technical Design Phase Development to be continued

09-07-22, A. Yamamoto ILC-GDE SCRF Plan 10

R&D/Prepare for Industrialization

Page 8: ILC Accelerator SCRF R&D Plan and Organization Presented by Akira Yamamoto for ILC-GDE Project Managers Marc Ross, Nick Walker, and A. Yamamoto To be presented.

11

TDP Goals of ILC-SCRF R&D

Cavity Field Gradient 35 MV/m with individual cavity in vertical test (S0)

Cavity-string Assembly in Cryomodule 31.5 MV/m in average (S1, S1-Global) “Plug-compatible” cavity assembly with:

Encouraging improvement and ‘creative work’ in R&D Motivating global share of advanced technology

Accelerator System Beam Acceleration with SCRF Accelerator Unit (S2)

Industrial Production R&D Preparation for cavity production, quality control, and

cost saving

09-07-22, A. Yamamoto ILC-GDE SCRF Plan

Page 9: ILC Accelerator SCRF R&D Plan and Organization Presented by Akira Yamamoto for ILC-GDE Project Managers Marc Ross, Nick Walker, and A. Yamamoto To be presented.

Status of 9-Cell Cavity

Europe (DESY, Saclay) Gradient: > ~ 40 MV/m (max) , Industrial (bulk) EP demonstrated Field emission reduced with ethanol rinsing Surface process with baking in Ar-gas

Americas (Jlab, Cornell, FNAL/ANL) Gradient: > ~ 40 MV/m (max), Field emission reduced by Ultrasonic Degreasing with Detergent

Asia (KEK, IHEP, RRCAT) Gradient: 36MV/m (LL, KEK-JLab), 32 MV/m (TESLA-like, KEK)

1209-07-22, A. Yamamoto ILC-GDE SCRF Plan

Page 10: ILC Accelerator SCRF R&D Plan and Organization Presented by Akira Yamamoto for ILC-GDE Project Managers Marc Ross, Nick Walker, and A. Yamamoto To be presented.

Standard Procedure Established

Standard Fabrication/Process

Fabrication Nb-sheet purchasing

Component Fabrication

Cavity assembly with EBW

Process EP-1 (~150um)

Ultrasonic degreasing with detergent, or ethanol rinse

High-pressure pure-water rinsing

Hydrogen degassing at > 600 C

Field flatness tuning

EP-2 (~20um)

Ultrasonic degreasing or ethanol (or EP 5 um with fresh acid)

High-pressure pure-water rinsing

Antenna Assembly

Baking at 120 C

Cold Test (vertical test)

Performance Test with temperature and mode measurement

1309-07-22, A. Yamamoto ILC-GDE SCRF Plan

Key ProcessFabrication• Material • EBW• Shape

Process• Electro-Polishing

• Ethanol Rinsing or • Ultra sonic. + Detergent

Rins.

• High Pr. Pure Water cleaning

Page 11: ILC Accelerator SCRF R&D Plan and Organization Presented by Akira Yamamoto for ILC-GDE Project Managers Marc Ross, Nick Walker, and A. Yamamoto To be presented.

09-07-22, A. Yamamoto ILC-GDE SCRF Plan 14

One Vendor Yield(A6, A7, A8, A11, A12, A15, AC115, AC117, AC122, 125, 126)

0

0.2

0.4

0.6

0.8

1

1.2

>15 >20 >25 >30 >35 >40

Gradient (MV/m)

Fra

cti

on

Global Yield of Cavities Recently Tested at Jlab and DESY

23 tests, 11 cavitiesOne Vendor

All Vendor Yield(A6, A7, A8, A11, A12, A15, AES 1- 4, Ichiro5, J2,AC115, AC117, AC122,

125, 126, Z139, 143)

0

0.2

0.4

0.6

0.8

1

1.2

>15 >20 >25 >30 >35 >40

Gradient (MV/m)

Fra

cti

on

48 Tests, 19 cavities ACCEL, AES, Zanon, Ichiro, Jlab

50%

Yield 45 % at 35 MV/m being achieved by cavities with a qualified vendor !!

14A Summary from TTC-08 (IUAC), ILC-08 (Chicago) by H. Padamsee

Page 12: ILC Accelerator SCRF R&D Plan and Organization Presented by Akira Yamamoto for ILC-GDE Project Managers Marc Ross, Nick Walker, and A. Yamamoto To be presented.

Progress Towards High-Gradient Yield

09-07-22, A. Yamamoto ILC-GDE SCRF Plan 15

Recent DESY/JLab “production” series.

Total 39 cavities (08/09)

Mostly result of first cold-test (few cases second-test)

Field Emission greatly reduced (rinses) identified RDR barrier

Baseline gradient re-evaluation (TDP1) expected to be based on sample of >60 cavities

Current status:50% yield at ~ 33 MV/m;(80% >25MV/m)

Current status:50% yield at ~ 33 MV/m;(80% >25MV/m)

Page 13: ILC Accelerator SCRF R&D Plan and Organization Presented by Akira Yamamoto for ILC-GDE Project Managers Marc Ross, Nick Walker, and A. Yamamoto To be presented.

What we need to make clear?Reported by

Date of Rep.

# of cavities ordered

# of cavities accepted & meas.

# of cavities w/ EP processed

# of meas. after EP

Yield at 35 MV/m

Note/Understanding

TTC H. Padamsee

08/10 ?19 19

(48)~50%~25 % Process Y.

DESY: D. Reschke W. Singer, L. Lilje,

09/03 ?25 25

25 +?~40 %

AcceptedProduct. Y.

Jlab R. Geng

09/02 1414 14

14+?

~50 % Product. Y.

DESY H. Weise

09/05 44+?44 44x~0.6

44x0.6+ ?15 %

Accepted Produc. Y.

09-07-22, A. YamamotoILC-GDE SCRF Plan 16We need more clear definition and rule to plot the yield

Page 14: ILC Accelerator SCRF R&D Plan and Organization Presented by Akira Yamamoto for ILC-GDE Project Managers Marc Ross, Nick Walker, and A. Yamamoto To be presented.

Creation of a Global Database for Better Understanding of “Production Yield” in TDP-2

• Global Data Base Team formed:– Camille Ginsburg (Fermilab) – Team Leader & Data Coordination– Zack Conway (Cornell University)– Sebastian Aderhold (DESY)– Yasuchika Yamamoto (KEK)– Rongli Geng (JLab) – GDE-SCRF Cavity TA Group Leader

• Activity Plan/Schedule– End July 2009:

- Determine whether DESY-DB is viable option, – Sept. 28 - Oct. 2, 2009: (ALCPG/GDE)

- Dataset web-based - Support by FNAL-TD or DESY

- Some well-checked, easily explainable, and near-final plots, available,– End Nov. 2009:

- Finalize DB tool, web I/F, standard plots, with longer-term tool improvement plans

09-07-22, A. Yamamoto 17ILC-GDE SCRF Plan

Page 15: ILC Accelerator SCRF R&D Plan and Organization Presented by Akira Yamamoto for ILC-GDE Project Managers Marc Ross, Nick Walker, and A. Yamamoto To be presented.

18

Outline

Introduction R&D Status Plan for Technical Design Phase Industrialization Accelerator Design and Integration (AD&I) Summary

09-07-22, A. Yamamoto ILC-GDE SCRF Plan

Page 16: ILC Accelerator SCRF R&D Plan and Organization Presented by Akira Yamamoto for ILC-GDE Project Managers Marc Ross, Nick Walker, and A. Yamamoto To be presented.

Push Quench Limit:• Defects from material• Defect from fabrication (EBW)• Renewed studies

Push Quench & field emission Limit• Classical defect/field emitter• EP specific…

Two Pushes Ahead

09-07-22, A. Yamamoto 19ILC-GDE SCRF Plan

Page 17: ILC Accelerator SCRF R&D Plan and Organization Presented by Akira Yamamoto for ILC-GDE Project Managers Marc Ross, Nick Walker, and A. Yamamoto To be presented.

09-07-22, A. Yamamoto ILC-GDE SCRF Plan 20

Plug Compatibility• R&D Phase

– Encourage creative work and innovation for performance improvement from a common baseline

– Global transfer of information– Sharing of components to continue progress world wide despite

outside uncertainties– Development of the RDR design for system tests and in

preparation for construction phase

• Production/Construction Phase– Keep competitive condition with free market/multiple-suppliers,

and effort for const-reduction, – Keep flexibility to accept industrial effort, with features and

constraints, to reduce the cost under acceptable flexibilities, – Maintain intellectual regional expertise base

Page 18: ILC Accelerator SCRF R&D Plan and Organization Presented by Akira Yamamoto for ILC-GDE Project Managers Marc Ross, Nick Walker, and A. Yamamoto To be presented.

09-07-22, A. Yamamoto ILC-GDE SCRF Plan 21

Cavity: Plug-compatible Interface

Component interfaces are

reduced to the minimum

necessary to allow for system

assembly

Page 19: ILC Accelerator SCRF R&D Plan and Organization Presented by Akira Yamamoto for ILC-GDE Project Managers Marc Ross, Nick Walker, and A. Yamamoto To be presented.

09-07-22, A. Yamamoto ILC-GDE SCRF Plan 22

Plug-compatibility• Plug Compatibility could be applied from a level of the whole

cryomodule, to the smallest component.

• During R&D, it is appropriate to set boundaries such that technical components can be most efficiently addressed.

Page 20: ILC Accelerator SCRF R&D Plan and Organization Presented by Akira Yamamoto for ILC-GDE Project Managers Marc Ross, Nick Walker, and A. Yamamoto To be presented.

S1-Global Collaboration

ILC-GDE SCRF Plan 23

KEK, Japan

09-07-22, A. Yamamoto

FNAL

x2

DESYx2 x4

INFN Milan

Complementary activity to regional cryomodule development

Page 21: ILC Accelerator SCRF R&D Plan and Organization Presented by Akira Yamamoto for ILC-GDE Project Managers Marc Ross, Nick Walker, and A. Yamamoto To be presented.

SRF Test Facilities

ILC-GDE SCRF Plan 24

KEK, Japan

DESY

FNAL

TTF/FLASH~1 GeVILC-like beamILC RF unit(* lower gradient)

NML facilityUnder constructionfirst beam 2010ILC RF unit test

STF (phase I & II)Under constructionfirst beam 2011ILC RF unit test

09-07-22, A. Yamamoto

Page 22: ILC Accelerator SCRF R&D Plan and Organization Presented by Akira Yamamoto for ILC-GDE Project Managers Marc Ross, Nick Walker, and A. Yamamoto To be presented.

A string test in each region

• Complementary testing:– Each region must develop industry and must develop

‘ownership’ of this critical technology

• No one system will exactly represent the baseline reference design RF unit design (before 2012)– FNAL: beam format [under review]– KEK: number of cryomodules [1 (of 3) by end 2012]– DESY: gradient [~27MV/m average over 3 cryomodules]

• Strategy must account for infrastructure limitations and construction schedules at each of the three main linac test facilities under development.

09-07-22, A. Yamamoto ILC-GDE SCRF Plan 25

Page 23: ILC Accelerator SCRF R&D Plan and Organization Presented by Akira Yamamoto for ILC-GDE Project Managers Marc Ross, Nick Walker, and A. Yamamoto To be presented.

TTF/FLASH Accelerator Layout

09-07-22, A. Yamamoto ILC-GDE SCRF Plan 26

Comparison of machine parameters

Waveguide distribution for klystron #4 (status 06.08.07)

Kly #4 3dB hybrid

ACC4 23 MV/m ACC5 24 MV/m ACC6 27 MV/m

TUNNEL

AST 2.4 dB2.2 MW1.6 MW1.5 MW

3.8 MW

1.6 MW 4.2 MW

3.7 MW

3.7 MW

Phaseshifter

42.8 m10%

27.6 m6%

2.4 dB

3.8 dB

2.9 MW

2.9 MW

DC

ACC456 is main focus of 9mA RF studies

XFEL ILC FLASHdesign

9mA studies

Bunch charge

nC 1 3.2 1 3

# bunches 3250 2625 7200* 2400

Pulse length s 650 970 800 800

Current mA

5 9 9 9

Page 24: ILC Accelerator SCRF R&D Plan and Organization Presented by Akira Yamamoto for ILC-GDE Project Managers Marc Ross, Nick Walker, and A. Yamamoto To be presented.

27

Beam Acceleration Test Plan

with RF unit at Fermilab and KEKin TDP-2

09-07-22, A. Yamamoto ILC-GDE SCRF Plan

Page 25: ILC Accelerator SCRF R&D Plan and Organization Presented by Akira Yamamoto for ILC-GDE Project Managers Marc Ross, Nick Walker, and A. Yamamoto To be presented.

   High Pressure Code Management

Element ProductionKHK特定設備申請

Company ECryogenics

KEK site ConstructionIbaraki L. Gov.工事/変更申請

On-siteCavity and CryomoduleAssembly

On-site cosntruction

Beam-line installation And Inpsection

完成検査KEK: 茨城県に完成検査申請

ExistingFacility

Page 26: ILC Accelerator SCRF R&D Plan and Organization Presented by Akira Yamamoto for ILC-GDE Project Managers Marc Ross, Nick Walker, and A. Yamamoto To be presented.

29

Outline

Introduction R&D Status Plan for Technical Design Phase Industrialization Accelerator Design and Integration (AD&I) Summary

09-07-22, A. Yamamoto ILC-GDE SCRF Plan

Page 27: ILC Accelerator SCRF R&D Plan and Organization Presented by Akira Yamamoto for ILC-GDE Project Managers Marc Ross, Nick Walker, and A. Yamamoto To be presented.

Toward Industrialization• Global status of Industries

– Research Instruments and Zanon in Europe

– AES, Niowave, PAVAC in Americas

– MHI in Asia

• Industrial Capacity: status and scope– No company currently has required ILC capacity– Understand what is needed (and cost) by 2012

09-07-22, A. Yamamoto ILC-GDE SCRF Plan 30

Project Scope

Euro XFEL ~800 2 years ~1 cavity / day

Project X ~400 3 years ~2 cavities/ week

ILC ~15,500 4 years ~20 cavities / day

( 3 regions ~7 cavities / day)

Page 28: ILC Accelerator SCRF R&D Plan and Organization Presented by Akira Yamamoto for ILC-GDE Project Managers Marc Ross, Nick Walker, and A. Yamamoto To be presented.

Visit to Cavity Manufacturers: 2009

ILC-GDE SCRF Plan 31

Asia MHI

Europe: RI << ACCEL

ZANON

Amecas: AES NIOWAVE PAVAC

09-07-22, A. Yamamoto

Notes: AES: Advanced Energy Systems RI: Research Instruments (previously, ACCEL) MHI: Mitsubishi Heavy Industries

Page 29: ILC Accelerator SCRF R&D Plan and Organization Presented by Akira Yamamoto for ILC-GDE Project Managers Marc Ross, Nick Walker, and A. Yamamoto To be presented.

Visit to Cavity Manufacturers: 2009

09-07-22, A. Yamamoto ILC-GDE SCRF Plan 32

Company # employees Features Date

AES ~26 Experience with RICH magnet production in the previous company, Dedicated for SC/NC RF technology

Feb. 24

NIOWAVE ~40 A New company dedicated for Niobium and microwave technology

Feb. 25

ACCEL/RI ~100 Most experienced company with SCRF, and adaptable for production scale of European XFEL

Mar. 4

ZANON ~200 Much experienced with plumbing work and SCRF cavities, and with HERA cryostat, Adaptable for scale of European XFEL

Mar. 6

MHI >>1,000 A leading company in heavy-industries in Japan, and experienced with SC/NC RF cavities and accelerator technologies

Mar. 10

PAVAC ~30 A unique features with EBW machine itself and SCRF cavity manufacturing

May 7

Page 30: ILC Accelerator SCRF R&D Plan and Organization Presented by Akira Yamamoto for ILC-GDE Project Managers Marc Ross, Nick Walker, and A. Yamamoto To be presented.

Industrialization and cost reduction

• Re-visit previous effort, and update the cost-estimate for production– Review the RDR cost estimate (based on TESLA)– Include recent R&D experience (industry/lab)

• Encourage R&D Facilities for industrialization – Develop cost-effective manufacturing, quality

control and cost-reduction in cooperation with industry

• Reflect the R&D progress for cost-reduction– Baseline Forming, EBW, assembly work…

09-07-22, A. Yamamoto ILC-GDE SCRF Plan 33

Page 31: ILC Accelerator SCRF R&D Plan and Organization Presented by Akira Yamamoto for ILC-GDE Project Managers Marc Ross, Nick Walker, and A. Yamamoto To be presented.

A Plan for R&D facilities and Preparation for Industrialization

• Bench-mark R&D facility (pilot plant) to study cost-effective manufacturing,

– Forming and preparation machining, – Pre-surface treatment and preparation, – EBW process with efficient automation, – In-line Inspection during fabrication process for quick-feedback,

• R&D facilities to be sited at Laboratories– Effort to seek for the most cost-efficient manufacturing with keeping

information to be open, – Development to seek for a bench-mark, manufacturing facilities (design

and/or itself can be applicable for the real production. – It is important for industries to participate to the program since Day-1.

for planning.

• We may discuss a possibility – An industrial meeting to be held as a satellite meeting at the 1st IPAC,

Kyoto, May, 2010.•

09-07-22, A. Yamamoto ILC-GDE SCRF Plan 34

Page 32: ILC Accelerator SCRF R&D Plan and Organization Presented by Akira Yamamoto for ILC-GDE Project Managers Marc Ross, Nick Walker, and A. Yamamoto To be presented.

Standard Procedure Established

Standard Fabrication/Process

Fabrication Nb-sheet purchasing

Component Fabrication

Cavity assembly with EBW

Process EP-1 (~150um)

Ultrasonic degreasing with detergent, or ethanol rinse

High-pressure pure-water rinsing

Hydrogen degassing at > 600 C

Field flatness tuning

EP-2 (~20um)

Ultrasonic degreasing or ethanol (or EP 5 um with fresh acid)

High-pressure pure-water rinsing

Antenna Assembly

Baking at 120 C

Cold Test (vertical test)

Performance Test with temperature and mode measurement

3509-07-22, A. Yamamoto ILC-GDE SCRF Plan

Key ProcessFabrication• Material • EBW• Shape

Process• Electro-Polishing

• Ethanol Rinsing or • Ultra sonic. + Detergent

Rins.

• High Pr. Pure Water cleaning

Page 33: ILC Accelerator SCRF R&D Plan and Organization Presented by Akira Yamamoto for ILC-GDE Project Managers Marc Ross, Nick Walker, and A. Yamamoto To be presented.

Field Gradient and Industrial R&D

Research and Development for Cavity Field Gradient

Mass production technology, quality control, andcost saving

Time

09-07-22, A. Yamamoto 36ILC-GDE SCRF Plan

Page 34: ILC Accelerator SCRF R&D Plan and Organization Presented by Akira Yamamoto for ILC-GDE Project Managers Marc Ross, Nick Walker, and A. Yamamoto To be presented.

37

Outline

Introduction R&D Status Plan for Technical Design Phase Industrialization Accelerator Design and Integration (AD&I) Summary

09-07-22, A. Yamamoto ILC-GDE SCRF Plan

Page 35: ILC Accelerator SCRF R&D Plan and Organization Presented by Akira Yamamoto for ILC-GDE Project Managers Marc Ross, Nick Walker, and A. Yamamoto To be presented.

Technical Design Phase and Beyond

09-07-22, A. Yamamoto ILC-GDE SCRF Plan 38

Accelerator designand integration studies

2009 2010

RDR ACD concepts

R&D Demonstrations

TDP Baseline Technical Design

2011 2012 2013

RDR Baseline

Ne

w b

ase

line

inp

uts

TDR

TDP-1 TDP-2 ChangeRequest

Page 36: ILC Accelerator SCRF R&D Plan and Organization Presented by Akira Yamamoto for ILC-GDE Project Managers Marc Ross, Nick Walker, and A. Yamamoto To be presented.

SB-2009 Design Proposal No. Subject Contents Note

1 ML/SCRF: Cavity Gradient to be re-evaluated 31.5 MV/m

2 CFS: Tunnel conf. Single tunnel either with Clusterde or Distributed RFS

3 AS: e+ source Undulator-based, and located at the end of ML (250 GeV),

Captured by ¼ wave transformer

4 AS: Low-Power Reduced power parameters N-b = 1312, T-rf = 2 ms

5 AS: Dumping Ring circumference L.= 3.2 km at 5- GeV

L-b = 6 mm

6 AS: Bunch Compressor

Single stage CF = 20

7 AS: Integ. e+/e- source Into common central region, together with BDS

8 Availability and Safety

09-07-22, A. Yamamoto ILC-GDE SCRF Plan 39

Page 37: ILC Accelerator SCRF R&D Plan and Organization Presented by Akira Yamamoto for ILC-GDE Project Managers Marc Ross, Nick Walker, and A. Yamamoto To be presented.

Novel RF Distribution Concepts

Klystron Cluster(SLAC)

DRFS(KEK)

Single Tunnel

Solutions

09-07-22, A. Yamamoto 40ILC-GDE SCRF Plan

Page 38: ILC Accelerator SCRF R&D Plan and Organization Presented by Akira Yamamoto for ILC-GDE Project Managers Marc Ross, Nick Walker, and A. Yamamoto To be presented.

41

Summary Technical Design Phase in progress:

Phase-1: Technical reality to be examined, 35 MV/m with yield 50 % in surface process

~ 33 MV/m with yield 50 % is being achieved 31.5 MV/m with the cavity-string in a cryomodule

Phase-2: Technical credibility to be demonstrated35 MV/m with the yield 90 % for 9-cell in manufacturing Beam acceleration with the field gradient 31.5 MV/m.

We aim for Global R&D efforts toward “High Gradient” keeping

“plug-compatibility” concept. Cooperation of world-wide Institutions and Industries

crucially important to prepare for industrialization.

09-07-22, A. Yamamoto ILC-GDE SCRF Plan

Page 39: ILC Accelerator SCRF R&D Plan and Organization Presented by Akira Yamamoto for ILC-GDE Project Managers Marc Ross, Nick Walker, and A. Yamamoto To be presented.

Backup for Discussions

09-07-22, A. Yamamoto ILC-GDE SCRF Plan 42

Page 40: ILC Accelerator SCRF R&D Plan and Organization Presented by Akira Yamamoto for ILC-GDE Project Managers Marc Ross, Nick Walker, and A. Yamamoto To be presented.

Summary of R&D Efforts/Subjects

• Establish technology for defect-free production, with “quick” feedback using inspection camera results– Upgrade “inspection camera”, and – Develop other inspection tools,

• Identify, more accurately, origin of field emission after surface treatment– Research and improve “surface-analysis”: XPS, SEM ,,,

• Establish and Demonstrate countermeasures:– The final treatment to remove FE source such as sponge wipe,

degreaser rinse, ethanol rise, – Repair method such as grinding tool for curing damaged

cavities

09-07-22, A. Yamamoto 43ILC-GDE SCRF Plan

Page 41: ILC Accelerator SCRF R&D Plan and Organization Presented by Akira Yamamoto for ILC-GDE Project Managers Marc Ross, Nick Walker, and A. Yamamoto To be presented.

Project Plan in 2008-2010 Field gradient (S0)

To be re-optimized, based on the R&D progress (2010),

Plug-compatibility Common interface conditions being fixed , Overview document published

System engineering/test plan, (S1, S2) Work sharing in cavity string in global effort (S1-Global) Accelerator system test with beam

Necessary detailed study and re-coordination under limited resources, including schedule

Effort for “Accelerator Design and Integration” optimization, Cluster or Distributed RF power sources and distribution,

Prepare for AAP Interium Review in April, 2009 Global Communication and cooperation with Laboratories & Industries

Visit Labs: DESY, INFN, CERN, CEA/Saclay, LAL/Orsay, CIEMAT, FNAL, SLAC, Cornell, Jlab, LANL, TRIUMF, KEK, IHEP, PKU, TU, PAL, KNU, IUAC, RRCAT, BARC, TTIF, VECC,

Visit Industries: ACCEL, ZANON, AES, Niowave, MHI, PAVAC

4409-07-22, A. Yamamoto ILC-GDE SCRF Plan

Page 42: ILC Accelerator SCRF R&D Plan and Organization Presented by Akira Yamamoto for ILC-GDE Project Managers Marc Ross, Nick Walker, and A. Yamamoto To be presented.

RDR Guidance for Baseline Definition

Alternate: A technology or concept which may provide a significant cost reduction, increase in performance (or both), but which will not be mature enough to be considered baseline by mid-end 2012

Baseline: a forward looking configuration which we are reasonably confident can achieve the required performance and can be used to give a reasonably accurate cost estimate by mid-end 2012 (→ TDR)

09-07-22, A. Yamamoto 45ILC-GDE SCRF Plan

Page 43: ILC Accelerator SCRF R&D Plan and Organization Presented by Akira Yamamoto for ILC-GDE Project Managers Marc Ross, Nick Walker, and A. Yamamoto To be presented.

How we may prepare for Industrialization and cost reduction?

• Re-visit previous effort, and update the cost-estimate for production– Understand the cost estimate in RDR

• mainly based on TESLA design work at ~ 10 years ago and the subsequent experience,

– Reflect recent R&D experience with laboratories and industries,

• Encourage R&D Facilities for industrialization – To Learn cost-effective manufacturing, quality control and cost-

reduction in cooperation with industries, • It is important to facilitate them at major SCRF laboratories and

extend the experiences at various laboratories (DESY, Jlab, Cornell and others),

• Reflect the R&D progress for cost-reduction• Main effort for Baseline >> Forming, EBW, assembly work … • Alternate effort with limited scale>> large-grain, seamless, or …

09-07-22, A. Yamamoto ILC-GDE SCRF Plan 46

Page 44: ILC Accelerator SCRF R&D Plan and Organization Presented by Akira Yamamoto for ILC-GDE Project Managers Marc Ross, Nick Walker, and A. Yamamoto To be presented.

SB-2009 Proposal (PMs)

1. A Main Linac length consistent with an optimal choice of average accelerating gradient

– RDR: 31.5 MV/m, to be re-evaluated

2. Single-tunnel solution for the Main Linacs and RTML, with two possible variants for the HLRF

– Klystron cluster scheme– DRFS scheme

3. Undulator-based e+ source located at the end of the electron Main Linac (250 GeV)

– Capture device: Quarter-wave transformer

09-07-22, A. Yamamoto 47ILC-GDE SCRF Plan

Page 45: ILC Accelerator SCRF R&D Plan and Organization Presented by Akira Yamamoto for ILC-GDE Project Managers Marc Ross, Nick Walker, and A. Yamamoto To be presented.

SB-2009 Proposal (PMs)

4. Reduced parameter set (with respect to the RDR)– nb = 1312 and a 2ms RF pulse (so-called “Low Power”)

5. Approx. 3.2 km circumference damping rings at5 GeV

– 6 mm bunch length

6. Single-stage bunch compressor– compression factor of 20

7. Integration of the e+ and e- sources into a common “central region beam tunnel”, together with the BDS.

09-07-22, A. Yamamoto 48ILC-GDE SCRF Plan

Page 46: ILC Accelerator SCRF R&D Plan and Organization Presented by Akira Yamamoto for ILC-GDE Project Managers Marc Ross, Nick Walker, and A. Yamamoto To be presented.

Focusing Points

• 全体、スケジュール、システム化、 R&D の優先順位、

• 空洞 (BL, LL), 問題点、対策のリストアップ、高勾配化への戦略、高圧ガス対策、

• 表面研究、実機との相関、実機へのフィードバック

• EP, EBW, 体制、中長期的展望• 国際的な比較(コスト)

09-07-22, A. Yamamoto ILC-GDE SCRF Plan 49