iEn 1'Enterg-- tg · iEn 1'"Enterg--tg Entergy Nuclear Operations, Inc.Pilgrim Nuclear Power...

6
iEn tg 1'"Enterg-- Entergy Nuclear Operations, Inc. Pilgrim Nuclear Power Station 600 Rocky Hill Road Plymouth, MA 02360 Kevin H. Bronson February 19, 2009 Kevin H. Bronson Site Vice President 10 CFR 50.90 U.S. Nuclear Regulatory Commission Attention: Document Control Desk Washington, DC 20555 SUBJECT: Entergy Nuclear Operations, Inc Pilgrim Nuclear Power Station Docket No. 50-293 License No. DPR-35 REFERENCES: Proposed Change to Pilgrim's Technical Specification Concerning the Safety Limit Minimum Critical Power Ratio (TAC # ME0241') 1. Entergy Letter No. 2.08.057, "Proposed Change to Pilgrim's Technical Speciation Concerning the Safety Limit Minimum Critical Power Ratio", dated December 16, 2008 2. GNF Additional Information Regarding the Requested Changes to the Technical Specifications SLMCPR, Pilgrim Cycle 18, Proprietary Version, eDRF Section 000-0090- 6001, dated October 16, 2008 LETTER NUMBER: 2.09.006 Dear Sir/Madam, By Reference 1, Entergy proposed changes to Pilgrim's Technical Speciation section 2.1.2, concerning Safety Limit Minimum Critical Power ratio (SLMCPR). In support of this proposed change NRC Staff requested additional information by electronic mail. The attachment to this letter provides the NRC requests and Pilgrim's responses. The additional information included in the Attachment does not invalidate the safety evaluation of the proposed changes, the Determination of No Significant Hazards Consideration, or the Environmental Assessment presented in the original application (Reference 1). Reference 2 was submitted as part of Reference 1. There are no regulatory commitments included in this submittal.

Transcript of iEn 1'Enterg-- tg · iEn 1'"Enterg--tg Entergy Nuclear Operations, Inc.Pilgrim Nuclear Power...

iEn tg1'"Enterg-- Entergy Nuclear Operations, Inc.

Pilgrim Nuclear Power Station600 Rocky Hill RoadPlymouth, MA 02360Kevin H. Bronson

February 19, 2009 Kevin H. BronsonSite Vice President

10 CFR 50.90

U.S. Nuclear Regulatory CommissionAttention: Document Control DeskWashington, DC 20555

SUBJECT: Entergy Nuclear Operations, IncPilgrim Nuclear Power StationDocket No. 50-293License No. DPR-35

REFERENCES:

Proposed Change to Pilgrim's Technical Specification Concerningthe Safety Limit Minimum Critical Power Ratio (TAC # ME0241')

1. Entergy Letter No. 2.08.057, "Proposed Change to Pilgrim'sTechnical Speciation Concerning the Safety Limit MinimumCritical Power Ratio", dated December 16, 2008

2. GNF Additional Information Regarding the RequestedChanges to the Technical Specifications SLMCPR, PilgrimCycle 18, Proprietary Version, eDRF Section 000-0090-6001, dated October 16, 2008

LETTER NUMBER: 2.09.006

Dear Sir/Madam,

By Reference 1, Entergy proposed changes to Pilgrim's Technical Speciation section 2.1.2,concerning Safety Limit Minimum Critical Power ratio (SLMCPR). In support of this proposedchange NRC Staff requested additional information by electronic mail. The attachment to thisletter provides the NRC requests and Pilgrim's responses.

The additional information included in the Attachment does not invalidate the safety evaluationof the proposed changes, the Determination of No Significant Hazards Consideration, or theEnvironmental Assessment presented in the original application (Reference 1). Reference 2was submitted as part of Reference 1.

There are no regulatory commitments included in this submittal.

Entergy Nuclear Operations, Inc.Pilgrim Nuclear Power Station

Letter No. 2.09.006Page 2

If you have questions regarding this subject, please feel free to contact Joseph Lynch at (508)830-8304.

I declare under the penalty of perjury that the foregoing information is true and correct.

Executed on the day of eo4dtAE,2009

Sincerely,

Kevin H. BronsonSite Vice President

Attachment: Pilgrim Response to NRC Request for Additional Information (4 pages)

cc: Mr. James S. Kim, Project ManagerPlant Licensing Branch I-1Division of Operator Reactor LicensingOffice of Nuclear Reactor RegulationU.S. Nuclear Regulatory CommissionOne White Flint North O-8C211555 Rockville PikeRockville, MD 20852

Regional Administrator, Region 1U.S. Nuclear Regulator Commission475 Allendale RoadKing of Prussia, PA 19406

Mr. RobertWalker, DirectorMassachusetts Department of Public HealthSchrafft Center Suite 1 M2ARadiation Control Program529 Main StreetCharlestown, MA 02129

Mr. John Giarrusso, Jr.Nuclear Preparedness ManagerMass. Emergency Management Agency400 Worcester RoadFramingham, MA 01702

Senior Resident InspectorPilgrim Nuclear Power Station

Pagqe 1/4

ATTACHMENT TO ENTERGY LETTER 2.09.006

PILGRIM RESPONSE TO REQUEST FOR ADDITIONAL INFORMATION (RAI)RELATED TO CYCLE 18 SLMCPR TECHNICAL SPECIFICATION (TS) CHANGE FOR

PILGRIM NUCLEAR POWER STATION (PILGRIM)(TAC # ME0241)

NRC RAI 1:Please describe the key differences that exist between the core designs for Cycles 17 and 18which resulted the values of safety limit minimum critical power ratio (SLMCPR) for Cycle 18 tobe higher than currently approved values in the Technical Specification (TS).

Pilgrim Response:Cycle 18 uses 156 new GNF2 Fuel bundles. Cycle 17 has all GE14 fuel. Thus the proposedchange relates to the fuel type change. Both cycles have similar design energy requirementsand are control cell core designs. For each new fuel cycle, Safety Limit MCPR is calculated.When the fuel type is changed, it is not unusual to have a more restrictive SLMCPR result, asshown in the summary of core design comparisons between Cycles 17 and 18, in Table 1 ofReference 2 attached to the Entergy Letter.No. 2.08.057. For Cycle 17, the MELLLA case wasmore limiting (SLMCPR calculated 1.061 rounded to 1.06), whereas for Cycle 18 the RatedCore Flow case is more limiting (SLMCPR 1.078 rounded to 1.08), as shown in Table 3 of theGE Report (Reference 2).

NRC RAI 2:Provide the currently approved Power/Flow map for Pilgrim. If Pilgrim was authorized tooperate in the Maximum Extended Load Line Limit Analysis (MELLLA) domain, please indicatefor how long the plant has been operating with MELLLA.

Pilgrim Response:Pilgrim Power-Flow Maps for Cycle 17 for Two Loop (Figure 2) and Single Loop (Figure 4)Operations are enclosed. PNPS has had MELLLA beginning with Cycle 11, which began on6/7/1995. The MELLLA Analysis report is NEDC-32306P dated March 1994. MELLLA wasimplemented using 10 CFR 50.59.

NRC RAI 3:The SLMCPR value for Single Loop Operation (SLO) in Cycle 17 is 0.02 higher than that of TwoLoop Operation (TLO); whereas, the SLMCPR value for SLO in Cycle 18 is 0.03 higher thanthat of TLO. Please explain why a higher margin in SLMCPR is necessary in order to operatewith SLO in Cycle 18, as opposed to Cycle 17.

Pilgrim Response:Single Loop Operation is analyzed separately from the Two Loop Operation and GNF Nuclearrounds off results. There is no particular attempt to provide a fixed adder on to TLO analysisfor SLO as shown in Table 3 (Reference 2) for SLMCPR calculations for Cycle 18.

NRC RAI 4:It is required that the latest approved amendment of NEDE-24011-P-A (GESTAR II)methodology be used to perform cycle-specific reload analysis. The staff has noted that in page1 of Attachment 1 of the submittal, it is stated that Pilgrim reload analysis for Cycle 18 followed

I Page 2/4

NEDE-2401 1-P-A (GESTAR II), Amendment 22 process; while in page 7 of Attachment 4 of thesubmittal, Amendment 25 to NEDE-2401 1-P-A was mentioned. Please respond to the followingconcerns:

a) Clarify the above mentioned apparent inconsistency in the submittal.b) Confirm whether the most recent amendment to NEDE-2401 1-P-A (GESTAR

II) methodology was used to perform Pilgrim Cycle 18 reload analysis; and ifnot, then why not.

Pilgrim Response:As described in the GNF Report, GESTAR II, Rev. 16 was used. This is the latest GESTAR IIRevision.

GESTAR II, Revision 16 includes all GESTAR Amendments including 22 and 25. There is noinconsistency. The confusion is caused by use of Revision numbers vs. Amendment numbers.GE publishes GESTAR Revisions that may include multiple Amendments. The Amendment 22process defines the generic activities and criteria for the licensing of a new fuel product. Futureamendments have not superseded Amendment 22 process, they deal with different issues. Allfuel types subsequent to establishment of Amendment 22 process were licensed using thatprocess. GNF2, the reload fuel for Cycle 18 was licensed by GNF using the Amendment 22process. Reload Design uses methods described in the most current Revision 16 of GESTARI1. Amendment 22 is referred to document that generic fuel licensing process was followed, notto indicate use of an older Revision of GESTAR I1. Reload Design uses methods described inthe most current Revision 16 of GESTAR I1.

Enclosure: Figure 2, Pilgrim Power/Flow Map, dated 05/01/07Figure 4, Pilgrim Power/Flow Map- Single Loop Operation, dated 05/01/07

REPORT NO. PNPS-RPT-03-00001, REV. 3 PAGE -__•

FIGURE 2PILGRIM POWER / FLOW MAP

Scram and Rod Block Data based on Nominal Trip SetpointsCORE FLOW, MLBIHR

0 5 10 15 20 25 30 35 40 45 50 55 60 65 70 75 80125

120 f APRM SCRAM CLAMP AT 1t8%

110 APRM ROD BLOCK CLAMP AT 113% a

105J OPERATION

100

0 95_• 90

85

75FW T CORE FLOW ,70 REGION

65_160

55 OPERATIONPROUHIBTEDn,50

X 45I--Lw 40 LOWER BOUND0, 35 NAT CIRC LINE

30PROHIBITED

2520 MINIMUM POWER15 -4.I

15 CmC EN PUMP SPEED (26%)10 LINE

50= 1

OF4

w3:

0_1

w=I-UJ

00.

0 5 10 15 20 25 30 35 40 45CORE FLOW, MLBIHR

50 55 60 65 70 75 80

Pilgrim C17 P-F Map.xls 05/01/2007

REPORT NO. PNPS-RPT-03-00001, REV. 3 PAGE A of 4

FIGURE 4PILGRIM POWER I FLOW MAP - Single Loop Operation

Scram and Rod Block Data based on Nominal Trip Setpoints

CORE FLOW, MLBIHR0 5 10 15 20 25 30 35 40 45 50 55 60 65 70 75 80

0w

60

uJoCL

0

0

o1

12512011511010510095908580757065605550454035302520151050

i--r rt 1-yrrrppIIp I!! "II 1mr riiim-1- i -rr-j! t-i-r-l-i- 25352434233222312129202819271825172416221521142013181217111510149138117106085074063042031010

uJ

0

0~-J

0 5 10 15 20 25 30 35 40 45CORE FLOW, MLBIHR

50 55 60 65 70 75 80

Pilgrim C17 P-F Map.xls,Fig 4 - SLO Chart - NTSP 05/01/2007