IEA Project #1101122. One copy should be maintained with ...€¦ · IEA Project #1101122. One copy...

82
September 19, 2011 Ted Sherman Saint Paul Public Schools 1930 Como Avenue Saint Paul, MN 55108 Dear Ted, Enclosed please find the Groveland Park Elementary Summer 2011 Asbestos Removal Final Report, IEA Project #1101122. One copy should be maintained with the Individual Building’s AHERA Recordkeeping System and another with the district’s AHERA Recordkeeping System. Samples are retained by IEA for thirty (30) day s after submission of IEA’s Final Report to the client and will be disposed of unless otherwise instructed by the client. If there is anything we can do to assist with the preparation/design of any abatement you are considering for the future, please do not hesitate to contact me. Sincerely, IEA, INC. Brenda Fischer Senior Project Manager BF/sda 082411 Enc cc File

Transcript of IEA Project #1101122. One copy should be maintained with ...€¦ · IEA Project #1101122. One copy...

Page 1: IEA Project #1101122. One copy should be maintained with ...€¦ · IEA Project #1101122. One copy should be maintained with the Individual Building’s AHERA Recordkeeping System

September 19, 2011 Ted Sherman Saint Paul Public Schools 1930 Como Avenue Saint Paul, MN 55108 Dear Ted, Enclosed please find the Groveland Park Elementary – Summer 2011 Asbestos Removal Final Report, IEA Project #1101122. One copy should be maintained with the Individual Building’s AHERA Recordkeeping System and another with the district’s AHERA Recordkeeping System. Samples are retained by IEA for thirty (30) days after submission of IEA’s Final Report to the client and will be disposed of unless otherwise instructed by the client. If there is anything we can do to assist with the preparation/design of any abatement you are considering for the future, please do not hesitate to contact me. Sincerely, IEA, INC. Brenda Fischer Senior Project Manager BF/sda 082411 Enc cc File

Page 2: IEA Project #1101122. One copy should be maintained with ...€¦ · IEA Project #1101122. One copy should be maintained with the Individual Building’s AHERA Recordkeeping System

– Final Report –

Groveland Park Elementary Summer 2011 Asbestos Removal

2045 St. Clair Ave. Saint Paul, MN 55105

Saint Paul Public Schools

September 19, 2011

Client No. 2001

IEA Project No. 1101122

Page 3: IEA Project #1101122. One copy should be maintained with ...€¦ · IEA Project #1101122. One copy should be maintained with the Individual Building’s AHERA Recordkeeping System

Table of Contents Appendix A ...................... Final Reports Appendix B ...................... Air Monitoring Methodology

Certificate of Visual Inspection Clearance Air Sampling Sign-In Sheet Certificate of Air Clearance Laboratory Analysis Appendix C ...................... Contractor’s License Contractor’s Insurance Certificate(s) Contractor’s State Notification and Amendments (if applicable) Contractor’s Asbestos-Related Work Project Permit Contractor’s Asbestos Project Plan Appendix D ...................... Contractor’s Daily Sign-In Sheet(s) Contractor’s Daily Log(s) Contractor’s Enclosure Sign-In Sheet(s) (if applicable) Worker’s Certificates/Licenses/Medicals Appendix E ...................... Landfill Manifest(s) Appendix F ...................... On-Site Monitor Qualifications Project Designer Certification/License Air Monitoring Notification

Page 4: IEA Project #1101122. One copy should be maintained with ...€¦ · IEA Project #1101122. One copy should be maintained with the Individual Building’s AHERA Recordkeeping System

© IEA, INC. 2011 Page 1 of 6

Project Summary IEA Project No. 1101122

Groveland Park Elementary Start Date: June 30, 2011 No. of Phases: Three (3) Completion Date: July 25, 2011 Reason for Response Action: Planned Removal Project Design & Specification Development Provided By: Response Action Conducted By: IEA Project Designer: Contractor Name: (See Appendix F for license/certificate) Mavo Systems Brenda Fischer Contractor License No.: AC200

Designer Accreditation No.: AD2296

IEA Project Manager: Project Manager: Brenda Fischer Larry Reese

IEA On-Site Monitor(s)/Accreditation No.: Site Supervisor(s): (See Appendix F for qualifications) (See Appendix D for license/certificate/medical)

Steve Guse AS10817 Jeremy Johnson Jim Paulzine AS11714 Pedro Robles Wayne Voght

Were specifications/project design developed? Yes

Saint Paul Public Schools Project Specifications The specifications included the following items:

Requirements for contractor compliance with all applicable federal, state & local regulations.

Asbestos-containing material removal standards. Air monitoring protocol & analysis.

Scope of work to be conducted. Equipment and material to be used. Personal protection requirements. Environmental clean-up standards. Medical monitoring requirements. Project clearance requirements. Personnel entry & exit procedures. Worker certification & training requirements.

Inspection of the work area & documentation of removal procedures.

Waste disposal procedures. Preliminary Activities

The contractor supplied IEA with submittals including all licenses, permits, certifications, insurance policies, schedules and plans.

This project was regulated and required notification to the state. Contractor’s notification and amendments (if applicable) and the Asbestos-Related Work Project Permit are included in Appendix C. The air monitoring notification is included in Appendix F.

Waste Disposal

All asbestos-containing debris was stored in a secure area until transported to SKB Rosemount Industrial Waste Facility, 13425 Courthouse Blvd., Rosemount, MN 55068.

A waste disposal manifest is located in Appendix E.

Page 5: IEA Project #1101122. One copy should be maintained with ...€¦ · IEA Project #1101122. One copy should be maintained with the Individual Building’s AHERA Recordkeeping System

Appendix A

Final Reports

Page 6: IEA Project #1101122. One copy should be maintained with ...€¦ · IEA Project #1101122. One copy should be maintained with the Individual Building’s AHERA Recordkeeping System

© IEA, INC. 2011 Page 2 of 6

IEA Project No. 1101122 Phase No.: 1 Response Start Date: July 15, 2011 Response Completion Date: July 25, 2011 Location: Gymnasium Type of Containment: Full Enclosure Material Description

Material Type Asbestos Content Amount Response Action 12” x 12” Vinyl Floor Tile & Mastic <1% Chrysotile (Tile)

5% Chrysotile (Mastic) 5,240 square feet Removal

Response Stages I. Pre-Abatement Activities

The contractor developed a site-specific asbestos abatement plan. Baseline cleaning was performed prior to construction of protective barriers pursuant to MDH Rules 4620.3566,

Items A to E. Protective barriers were used to lock out all ventilation systems, doors, windows, permanent fixtures and any

other openings. Polyethylene was constructed along all walls. A five (5)-stage decontamination unit was constructed contiguous to the work area. A one (1)-stage bag-out unit was constructed. The HVAC system was shut down and locked out. The electrical power was shut down and locked out. Warning signs were posted at all access points.

II. Abatement Activities

The containment area was 62,400 cubic feet. A recording manometer was set up and monitored throughout the project. The enclosure was maintained at a pressure differential of –0.03 (inches of water). This was accomplished with four (4) HEPA units rated at 2,000 cubic feet per minute. There were approximately six (6) air exchanges per hour within the enclosure. A visual inspection was made of the enclosure prior to removal to verify its integrity and evaluate the direction of

air flow. All applicable posting requirements were met. Entrance to and exit from the work area was observed to ensure that the appropriate personal protective

equipment was worn and decontamination procedures were followed. Visual monitoring of work practices was accomplished by observation from inside the enclosure during removal

and cleanup. The asbestos-containing material was saturated with amended water prior to removal from the substrate. The removed asbestos-containing material was immediately placed into appropriately labeled disposal bags

and/or drums before it was allowed to dry. All debris was cleaned up at the end of each shift. Periodic inspections were conducted for damage or penetration of the barriers in order to maintain the integrity of

the containment area. HEPA-filtered pressure differential unit(s) were inspected for proper functioning and cleanliness of pre-filters. Asbestos-containing mastic (adhesive) was removed using chemical solvents.

Page 7: IEA Project #1101122. One copy should be maintained with ...€¦ · IEA Project #1101122. One copy should be maintained with the Individual Building’s AHERA Recordkeeping System

© IEA, INC. 2011 Page 3 of 6

III. Decontamination & Disposal

A final cleaning was conducted using HEPA-filtered vacuums and wet methods. All asbestos-containing material and contaminated debris was properly sealed in double 6-mil labeled bags or in

sealed drums. Forty (40) bags and fifty-three (53) barrels of containerized debris were decontaminated, removed from the

enclosure and stored in a locked storage area. A final inspection was conducted of the containment area on July 22, 2011, by Jim Paulzine. All surfaces were checked to ensure that no dust and/or debris remained.

IV. Clearance Procedures

After sufficient air exchanges, IEA initiated an aggressive air sampling protocol as required by the MDH Rules 4620.3594, Subpart 2, Item F, Subitems 1 to 3, which was accomplished as follows: One (1) one-horsepower leaf blower was utilized to sweep all surfaces in the containment area. Seven (7) twenty-inch box fans were placed approximately two meters from the floor, to circulate the air

upward. (One fan for each 10,000 cubic feet.) V. Air Quality

A. Outside the Enclosure

Two (2) ambient air samples were collected simultaneously no less than once during every zero to five (0-5)-hour period while asbestos-related work occurred. At least one (1) sample was collected within ten feet (10’) of the decontamination unit.

Laboratory analysis of the ambient air sample(s) indicated levels less than or equal to 0.01 f/cc, or the alternative indoor air standard. Details of actual analytical results are located in Appendix B.

B. Clearance Sampling

TEM analysis was utilized for all clearance air samples taken. Five (5) high volume pumps were placed inside the enclosure in a pattern designed to ensure representative

sampling of the area. All samples were taken simultaneously using aggressive sampling techniques. Laboratory analysis of clearance air samples indicated levels less than or equal to 0.01 f/cc or 70 structures

per square millimeter (s/mm2), the specified clearance level. All samples were taken simultaneously.

All air sampling and analysis was conducted in a manner consistent with all applicable codes and regulations by IEA. All laboratory results are located in Appendix B. VI. Project Closeout

After clearance was achieved, the temporary enclosure barriers were removed in accordance with specifications and disposed of as asbestos-contaminated debris.

All equipment and materials were removed from the area. An inspection was conducted of the area for damages and a punch list was compiled. The contractor is

responsible for addressing all punch list items prior to receiving final payment.

Page 8: IEA Project #1101122. One copy should be maintained with ...€¦ · IEA Project #1101122. One copy should be maintained with the Individual Building’s AHERA Recordkeeping System

© IEA, INC. 2011 Page 4 of 6

IEA Project No. 1101122 Phase No.: 2 Response Start Date: July 21, 2011 Response Completion Date: July 21, 2011 Location: Room 1119 Type of Containment: Critical Barrier Material Description

Material Type Asbestos Content Amount Response Action 9” x 9” Vinyl Floor Tile & Mastic 5% Chrysotile (Tile)

10% Chrysotile (Mastic) 175 square feet Removal

Response Stages I. Pre-Abatement Activities

Baseline cleaning was performed prior to construction of protective barriers. Critical barriers were used to lock out all ventilation systems, doors, windows, permanent fixtures and any other

openings. Polyethylene “splash guards” were constructed along all walls. A one (1)-stage decontamination unit was constructed contiguous to the work area. A one (1)-stage bag-out was constructed. The HVAC system was shut down and locked out. The electrical power was shut down and locked out. Warning signs were posted at all access points.

II. Abatement Activities

The containment area was 1,925 cubic feet. Negative air pressure was established within the work area. This was accomplished with one (1) HEPA unit rated at 2,000 cubic feet per minute. A visual inspection was made of the enclosure prior to removal to verify its integrity and evaluate the direction of

air flow. All applicable posting requirements were met. Entrance to and exit from the work area was observed to ensure that the appropriate personal protective

equipment was worn and decontamination procedures were followed. Visual monitoring of work practices was accomplished by observation from inside the enclosure during removal

and cleanup. The asbestos-containing material was saturated with amended water prior to removal from the substrate. All removal was completed in a nonfriable manner. The removed asbestos-containing material was immediately placed into appropriately labeled disposal bags

and/or drums before it was allowed to dry. All debris was cleaned up at the end of each shift. Periodic inspections were conducted for damage or penetration of the barriers in order to maintain the integrity of

the containment area. HEPA-filtered pressure differential unit(s) were inspected for proper functioning and cleanliness of pre-filters. Asbestos-containing mastic (adhesive) was removed using chemical solvents in a nonfriable manner.

Page 9: IEA Project #1101122. One copy should be maintained with ...€¦ · IEA Project #1101122. One copy should be maintained with the Individual Building’s AHERA Recordkeeping System

© IEA, INC. 2011 Page 5 of 6

III. Decontamination & Disposal

A final cleaning was conducted using HEPA-filtered vacuums and wet methods. All asbestos-containing material and contaminated debris was properly sealed in double 6-mil labeled bags or in

sealed drums. Three (3) bags and three (3) barrels of containerized debris were decontaminated, removed from the enclosure

and stored in a locked storage area. A final inspection was conducted of the containment area on July 21, 2011, by Jim Paulzine. All surfaces were checked to ensure that no dust and/or debris remained. After final inspection, the floor surface was scrubbed with a one percent (1%) liquid Tide and water solution.

IV. Air Quality

A. Outside the Enclosure

No air sampling was conducted during the nonfriable removal of asbestos-containing materials (not required).

B. Clearance Sampling

No clearance air sampling was conducted after the nonfriable removal of asbestos-containing material (not

required). V. Project Closeout

After the nonfriable removal was complete or clearance air was achieved, the temporary enclosure barriers were removed and disposed of as asbestos-contaminated debris.

All equipment and materials were removed from the area. An inspection was conducted of the area for damages and a punch list was compiled. The contractor is

responsible for addressing all punch list items prior to receiving final payment.

Page 10: IEA Project #1101122. One copy should be maintained with ...€¦ · IEA Project #1101122. One copy should be maintained with the Individual Building’s AHERA Recordkeeping System

© IEA, INC. 2011 Page 6 of 6

IEA Project No. 1101122 Phase No.: 3 Response Start Date: June 30, 2011 Response Completion Date: June 30, 2011 Location: Room 1105 Type of Containment: None Material Description

Material Type Asbestos Content Amount Response Action Tackboard Adhesive 3% Chrysotile 12 square feet Removal Response Stages I. Pre-Abatement Activities

Warning signs were posted at all access points. A drop sheet was placed and extended 6-10 feet beyond the work area. The HVAC system was shut down and locked out.

II. Abatement Activities

Asbestos-containing adhesive was removed in a non-friable manner using hand tools and wet methods. III. Decontamination & Disposal

All debris generated by the removal process was cleaned up utilizing HEPA-filtered vacuums and/or wet methods.

All asbestos-containing material and contaminated debris was properly sealed in two (2), 6-mil labeled bags, sealed barrels or wrapped bundles.

Two (2) bags and one (1) barrel of containerized debris were decontaminated, removed from the work area and stored in a locked storage area.

IV. Air Quality

A. Clearance Sampling

No clearance air sampling was conducted after the nonfriable removal of asbestos-containing material (not required).

V. Project Closeout

After the nonfriable removal was complete or clearance air was achieved, the temporary barriers were removed and disposed of as asbestos-contaminated debris.

All equipment and materials were removed from the area. An inspection was conducted of the area for damages and a punch list was compiled. The contractor is

responsible for addressing all punch list items prior to receiving final payment.

Page 11: IEA Project #1101122. One copy should be maintained with ...€¦ · IEA Project #1101122. One copy should be maintained with the Individual Building’s AHERA Recordkeeping System

Appendix B

Air Monitoring Methodology Certificate of Visual Inspection

Clearance Air Sampling Sign-In Sheet Certificate of Air Clearance

Laboratory Analysis

Page 12: IEA Project #1101122. One copy should be maintained with ...€¦ · IEA Project #1101122. One copy should be maintained with the Individual Building’s AHERA Recordkeeping System

Project Air Monitoring General The Asbestos Analytical Laboratory at the Institute for Environmental Assessment (IEA) is located at IEA’s Brooklyn Park office. The IEA field staff receives in-house training for air monitoring. The training is conducted by in-house staff, who are graduates of the NIOSH 582 course. Emphasis in the IEA air monitoring program is placed on good industrial hygiene sampling practices, sample names, analytical limits of quantification, time-weighted averages, equipment use and sampling strategies. Phase Contrast Microscopy Sampling Strategy. Air samples are collected on 25 millimeter mixed cellulose ester filters with a nominal pore size of 0.8 microns. These filters are used on conductive air sampling cassettes with 50 millimeter extension cowls. The cassettes are connected to high-volume sampling pumps via flexible plastic tubing. The tubing is suspended from a stand so that the cassette angles downward at 45 degrees from vertical, approximately four feet above the floor. Cassettes are positioned in areas representative of the conditions being monitored, away from walls, furniture and obstructions. Prior to commencement of sampling, pumps are calibrated by rotameter to flow rates between 4 and 12 liters per minute, depending upon conditions. Cassettes are opened and pumps are activated and allowed to run for sufficient time to sample a desired volume of air. For background and clearance sampling, five samples of a minimum of 1,200 liters each are normally drawn for the first 25,000 square feet of area, plus one sample for each additional 5,000 square feet. During each five (5) hour shift of abatement work, two samples of a minimum of 1,200 liters of air each are normally collected outside the work area within 10 feet of the containment barriers. For each set of samples, a minimum of two field blanks are forwarded to the laboratory. Field blanks are cassettes which are opened for 30 seconds within the area being monitored. Unexposed filters from each new set of cassettes received at the laboratory are analyzed to establish filter background levels. Analysis Methodology A pie wedge shaped section of the filter paper (1/6 to 1/4 of total filter) is mounted on a clear glass microscope slide. The paper is cleared using acetone vapor and fixed using three to seven microliters of glyceryl triacetate; a #1.5 cover glass is then placed on top of the preparation. IEA uses the NIOSH 7400 method for fiber counting procedures. Briefly, fibers are particulates longer than 5 microns with a length to width ratio equal to or greater than 3:1. Ends of fibers which fall within a defined portion of the field of view are counted. Between 20 and 200 fields are counted, depending on the number of fibers present. Calculations use the number of fibers counted, effective collection area of the filter paper, volume of air collected, area of counting field, and a dimensional correction factor; results are in fibers per cubic centimeter of air. IEA uses either an Olympus Model CH-30/CH-20 or Nikon Model Alphaphot-2, YS2 microscope equipped with a 40X phase contrast objective, appropriate phase contrast condenser, and a Walton-Beckett reticule in a 10X eyepiece; total magnification is 400X. Quality assurance and quality control practices are performed regularly by analysts at IEA. For fiber counting, a Koehler illumination check is made once a day. Duplicate counts of one sample or 10% of the day's samples (whichever is greater) are performed. The asbestos analytical laboratory at IEA is a successful participant in the National Institute for Occupational Safety and Health Proficiency Analytical Testing Program (Lab #010102; latest test results available upon request).

Page 13: IEA Project #1101122. One copy should be maintained with ...€¦ · IEA Project #1101122. One copy should be maintained with the Individual Building’s AHERA Recordkeeping System

Transmission Electron Microscopy Sampling Strategy Air samples are collected on 25 millimeter mixed cellulose ester filters with a nominal pore size of 0.45 microns. These filters are used in conductive air sampling cassettes with 50 millimeter extension cowls. The cassettes are connected to high-volume sampling pumps via flexible plastic tubing. The tubing is suspended from a stand so that the cassette angles downward at 45 degrees from vertical, approximately four feet above the floor. Cassettes are positioned in areas representative of the conditions being monitored, away from walls, furniture and obstructions. Prior to commencement of sampling, pumps are calibrated by rotameter to flow rates between four and nine liters per minute, depending upon conditions. Stationary box fans are set up to direct air toward the ceiling. One fan is used for each 10,000 cubic feet of work area volume. A one-horsepower leaf blower is used to sweep all floors, walls and ceilings in the space. The stationary fans are activated at low speed. Cassettes are opened and pumps are activated and allowed to run for sufficient time to sample a desired volume of air. For TEM clearance sampling, a minimum of five (5) samples of at least 1,200 liters each are collected inside the enclosure. Along with these samples, one field blank from inside the enclosure and one laboratory blank are forwarded to the laboratory. Field blanks are sample cassettes which are opened for 30 seconds in the area being monitored. Laboratory blanks are unopened cassettes from the same batch which can be used to establish a filter background level. Analysis TEM clearance samples are analyzed according to AHERA protocol as found in 40 CFR, Part 763, Appendix A to Subpart E.

Page 14: IEA Project #1101122. One copy should be maintained with ...€¦ · IEA Project #1101122. One copy should be maintained with the Individual Building’s AHERA Recordkeeping System
Page 15: IEA Project #1101122. One copy should be maintained with ...€¦ · IEA Project #1101122. One copy should be maintained with the Individual Building’s AHERA Recordkeeping System
Page 16: IEA Project #1101122. One copy should be maintained with ...€¦ · IEA Project #1101122. One copy should be maintained with the Individual Building’s AHERA Recordkeeping System
Page 17: IEA Project #1101122. One copy should be maintained with ...€¦ · IEA Project #1101122. One copy should be maintained with the Individual Building’s AHERA Recordkeeping System
Page 18: IEA Project #1101122. One copy should be maintained with ...€¦ · IEA Project #1101122. One copy should be maintained with the Individual Building’s AHERA Recordkeeping System
Page 19: IEA Project #1101122. One copy should be maintained with ...€¦ · IEA Project #1101122. One copy should be maintained with the Individual Building’s AHERA Recordkeeping System
Page 20: IEA Project #1101122. One copy should be maintained with ...€¦ · IEA Project #1101122. One copy should be maintained with the Individual Building’s AHERA Recordkeeping System
Page 21: IEA Project #1101122. One copy should be maintained with ...€¦ · IEA Project #1101122. One copy should be maintained with the Individual Building’s AHERA Recordkeeping System
Page 22: IEA Project #1101122. One copy should be maintained with ...€¦ · IEA Project #1101122. One copy should be maintained with the Individual Building’s AHERA Recordkeeping System
Page 23: IEA Project #1101122. One copy should be maintained with ...€¦ · IEA Project #1101122. One copy should be maintained with the Individual Building’s AHERA Recordkeeping System
Page 24: IEA Project #1101122. One copy should be maintained with ...€¦ · IEA Project #1101122. One copy should be maintained with the Individual Building’s AHERA Recordkeeping System
Page 25: IEA Project #1101122. One copy should be maintained with ...€¦ · IEA Project #1101122. One copy should be maintained with the Individual Building’s AHERA Recordkeeping System
Page 26: IEA Project #1101122. One copy should be maintained with ...€¦ · IEA Project #1101122. One copy should be maintained with the Individual Building’s AHERA Recordkeeping System
Page 27: IEA Project #1101122. One copy should be maintained with ...€¦ · IEA Project #1101122. One copy should be maintained with the Individual Building’s AHERA Recordkeeping System
Page 28: IEA Project #1101122. One copy should be maintained with ...€¦ · IEA Project #1101122. One copy should be maintained with the Individual Building’s AHERA Recordkeeping System
Page 29: IEA Project #1101122. One copy should be maintained with ...€¦ · IEA Project #1101122. One copy should be maintained with the Individual Building’s AHERA Recordkeeping System
Page 30: IEA Project #1101122. One copy should be maintained with ...€¦ · IEA Project #1101122. One copy should be maintained with the Individual Building’s AHERA Recordkeeping System

Appendix C

Contractor’s License Contractor’s Insurance Certificate(s)

Contractor’s State Notification and Amendments (if applicable) Contractor’s Asbestos-Related Work Project Permit

Asbestos Project Plan

Page 31: IEA Project #1101122. One copy should be maintained with ...€¦ · IEA Project #1101122. One copy should be maintained with the Individual Building’s AHERA Recordkeeping System
Page 32: IEA Project #1101122. One copy should be maintained with ...€¦ · IEA Project #1101122. One copy should be maintained with the Individual Building’s AHERA Recordkeeping System
Page 33: IEA Project #1101122. One copy should be maintained with ...€¦ · IEA Project #1101122. One copy should be maintained with the Individual Building’s AHERA Recordkeeping System
Page 34: IEA Project #1101122. One copy should be maintained with ...€¦ · IEA Project #1101122. One copy should be maintained with the Individual Building’s AHERA Recordkeeping System
Page 35: IEA Project #1101122. One copy should be maintained with ...€¦ · IEA Project #1101122. One copy should be maintained with the Individual Building’s AHERA Recordkeeping System
Page 36: IEA Project #1101122. One copy should be maintained with ...€¦ · IEA Project #1101122. One copy should be maintained with the Individual Building’s AHERA Recordkeeping System
Page 37: IEA Project #1101122. One copy should be maintained with ...€¦ · IEA Project #1101122. One copy should be maintained with the Individual Building’s AHERA Recordkeeping System
Page 38: IEA Project #1101122. One copy should be maintained with ...€¦ · IEA Project #1101122. One copy should be maintained with the Individual Building’s AHERA Recordkeeping System
Page 39: IEA Project #1101122. One copy should be maintained with ...€¦ · IEA Project #1101122. One copy should be maintained with the Individual Building’s AHERA Recordkeeping System
Page 40: IEA Project #1101122. One copy should be maintained with ...€¦ · IEA Project #1101122. One copy should be maintained with the Individual Building’s AHERA Recordkeeping System
Page 41: IEA Project #1101122. One copy should be maintained with ...€¦ · IEA Project #1101122. One copy should be maintained with the Individual Building’s AHERA Recordkeeping System
Page 42: IEA Project #1101122. One copy should be maintained with ...€¦ · IEA Project #1101122. One copy should be maintained with the Individual Building’s AHERA Recordkeeping System

Appendix D

Contractor’s Daily Sign-In Sheet(s) Contractor’s Daily Log(s)

Contractor’s Enclosure Sign-In Sheet(s) (if applicable) Worker Certificates/State Licenses/Medicals

Page 43: IEA Project #1101122. One copy should be maintained with ...€¦ · IEA Project #1101122. One copy should be maintained with the Individual Building’s AHERA Recordkeeping System
Page 44: IEA Project #1101122. One copy should be maintained with ...€¦ · IEA Project #1101122. One copy should be maintained with the Individual Building’s AHERA Recordkeeping System
Page 45: IEA Project #1101122. One copy should be maintained with ...€¦ · IEA Project #1101122. One copy should be maintained with the Individual Building’s AHERA Recordkeeping System
Page 46: IEA Project #1101122. One copy should be maintained with ...€¦ · IEA Project #1101122. One copy should be maintained with the Individual Building’s AHERA Recordkeeping System
Page 47: IEA Project #1101122. One copy should be maintained with ...€¦ · IEA Project #1101122. One copy should be maintained with the Individual Building’s AHERA Recordkeeping System
Page 48: IEA Project #1101122. One copy should be maintained with ...€¦ · IEA Project #1101122. One copy should be maintained with the Individual Building’s AHERA Recordkeeping System
Page 49: IEA Project #1101122. One copy should be maintained with ...€¦ · IEA Project #1101122. One copy should be maintained with the Individual Building’s AHERA Recordkeeping System
Page 50: IEA Project #1101122. One copy should be maintained with ...€¦ · IEA Project #1101122. One copy should be maintained with the Individual Building’s AHERA Recordkeeping System
Page 51: IEA Project #1101122. One copy should be maintained with ...€¦ · IEA Project #1101122. One copy should be maintained with the Individual Building’s AHERA Recordkeeping System
Page 52: IEA Project #1101122. One copy should be maintained with ...€¦ · IEA Project #1101122. One copy should be maintained with the Individual Building’s AHERA Recordkeeping System
Page 53: IEA Project #1101122. One copy should be maintained with ...€¦ · IEA Project #1101122. One copy should be maintained with the Individual Building’s AHERA Recordkeeping System
Page 54: IEA Project #1101122. One copy should be maintained with ...€¦ · IEA Project #1101122. One copy should be maintained with the Individual Building’s AHERA Recordkeeping System
Page 55: IEA Project #1101122. One copy should be maintained with ...€¦ · IEA Project #1101122. One copy should be maintained with the Individual Building’s AHERA Recordkeeping System
Page 56: IEA Project #1101122. One copy should be maintained with ...€¦ · IEA Project #1101122. One copy should be maintained with the Individual Building’s AHERA Recordkeeping System
Page 57: IEA Project #1101122. One copy should be maintained with ...€¦ · IEA Project #1101122. One copy should be maintained with the Individual Building’s AHERA Recordkeeping System
Page 58: IEA Project #1101122. One copy should be maintained with ...€¦ · IEA Project #1101122. One copy should be maintained with the Individual Building’s AHERA Recordkeeping System
Page 59: IEA Project #1101122. One copy should be maintained with ...€¦ · IEA Project #1101122. One copy should be maintained with the Individual Building’s AHERA Recordkeeping System
Page 60: IEA Project #1101122. One copy should be maintained with ...€¦ · IEA Project #1101122. One copy should be maintained with the Individual Building’s AHERA Recordkeeping System
Page 61: IEA Project #1101122. One copy should be maintained with ...€¦ · IEA Project #1101122. One copy should be maintained with the Individual Building’s AHERA Recordkeeping System
Page 62: IEA Project #1101122. One copy should be maintained with ...€¦ · IEA Project #1101122. One copy should be maintained with the Individual Building’s AHERA Recordkeeping System
Page 63: IEA Project #1101122. One copy should be maintained with ...€¦ · IEA Project #1101122. One copy should be maintained with the Individual Building’s AHERA Recordkeeping System
Page 64: IEA Project #1101122. One copy should be maintained with ...€¦ · IEA Project #1101122. One copy should be maintained with the Individual Building’s AHERA Recordkeeping System
Page 65: IEA Project #1101122. One copy should be maintained with ...€¦ · IEA Project #1101122. One copy should be maintained with the Individual Building’s AHERA Recordkeeping System
Page 66: IEA Project #1101122. One copy should be maintained with ...€¦ · IEA Project #1101122. One copy should be maintained with the Individual Building’s AHERA Recordkeeping System
Page 67: IEA Project #1101122. One copy should be maintained with ...€¦ · IEA Project #1101122. One copy should be maintained with the Individual Building’s AHERA Recordkeeping System
Page 68: IEA Project #1101122. One copy should be maintained with ...€¦ · IEA Project #1101122. One copy should be maintained with the Individual Building’s AHERA Recordkeeping System

Appendix E

Landfill Manifest(s)

Page 69: IEA Project #1101122. One copy should be maintained with ...€¦ · IEA Project #1101122. One copy should be maintained with the Individual Building’s AHERA Recordkeeping System
Page 70: IEA Project #1101122. One copy should be maintained with ...€¦ · IEA Project #1101122. One copy should be maintained with the Individual Building’s AHERA Recordkeeping System
Page 71: IEA Project #1101122. One copy should be maintained with ...€¦ · IEA Project #1101122. One copy should be maintained with the Individual Building’s AHERA Recordkeeping System

Appendix F

On-Site Monitor Qualifications Project Designer Certification/State License

Air Monitoring Notification

Page 72: IEA Project #1101122. One copy should be maintained with ...€¦ · IEA Project #1101122. One copy should be maintained with the Individual Building’s AHERA Recordkeeping System

The Institute for Environmental Assessment (IEA) requires individuals who perform on-site monitoring for response actions (removal, encapsulation, enclosure or operations and maintenance) have, at a minimum, the following qualifications: Regulated Projects

Licensed Contractor/Site Supervisor 2-Day Air Certification

Non-Regulated Projects

8-Hours of In-House Training Which Includes: - Health effects of asbestos - Detection, identification and assessment of ACM - Applicable state and federal regulations (AHERA, NESHAP, OSHA and

state requirements) - Air sampling protocols

Most of IEA’s on-site monitors are trained in PCM air sample analysis and have a NIOSH 582 Certification. All on-site monitors receive at least one week of supervised on-site training. The Institute requires all on-site technicians to be under the direct supervision of a project manager who is certified through EPA-accredited training (i.e., Inspector, Project Designer and Contractor/Site Supervisor).

Page 73: IEA Project #1101122. One copy should be maintained with ...€¦ · IEA Project #1101122. One copy should be maintained with the Individual Building’s AHERA Recordkeeping System
Page 74: IEA Project #1101122. One copy should be maintained with ...€¦ · IEA Project #1101122. One copy should be maintained with the Individual Building’s AHERA Recordkeeping System
Page 75: IEA Project #1101122. One copy should be maintained with ...€¦ · IEA Project #1101122. One copy should be maintained with the Individual Building’s AHERA Recordkeeping System
Page 76: IEA Project #1101122. One copy should be maintained with ...€¦ · IEA Project #1101122. One copy should be maintained with the Individual Building’s AHERA Recordkeeping System
Page 77: IEA Project #1101122. One copy should be maintained with ...€¦ · IEA Project #1101122. One copy should be maintained with the Individual Building’s AHERA Recordkeeping System
Page 78: IEA Project #1101122. One copy should be maintained with ...€¦ · IEA Project #1101122. One copy should be maintained with the Individual Building’s AHERA Recordkeeping System
Page 79: IEA Project #1101122. One copy should be maintained with ...€¦ · IEA Project #1101122. One copy should be maintained with the Individual Building’s AHERA Recordkeeping System
Page 80: IEA Project #1101122. One copy should be maintained with ...€¦ · IEA Project #1101122. One copy should be maintained with the Individual Building’s AHERA Recordkeeping System
Page 81: IEA Project #1101122. One copy should be maintained with ...€¦ · IEA Project #1101122. One copy should be maintained with the Individual Building’s AHERA Recordkeeping System
Page 82: IEA Project #1101122. One copy should be maintained with ...€¦ · IEA Project #1101122. One copy should be maintained with the Individual Building’s AHERA Recordkeeping System