ICOP Fulmar 2017 · The Fulmar platform processes production from the Fulmar field, Halley field...

4
Fulmar, Infrastructure Code of Practice FULMAR Last Updated: May 2017 The Fulmar platform was installed in 1981 with first oil production in 1982. The installation is located approximately 217 miles east of Dundee and comprises of two fixed steel jackets. It has facilities for drilling, production, accommodation and associated utilities. The Fulmar platform processes production from the Fulmar field, Halley field and Auk North sub-sea tieback. The Fulmar complex also acts as a gathering hub by providing a transportation and redelivery service for the Gannet, Auk, Clyde, Orion and Flyndre fields through the Oil Export Module. Oil is exported from the Fulmar platform via the Norpipe system for onward delivery to the Teesside terminal. The associated gas from the Fulmar, Halley and Auk North fields is used as fuel on the platform or flared. The Fulmar platform also has the facility to import gas via the Fulmar gas pipeline which runs from the St Fergus terminal. Gas compression is provided via the Borsig system. Gas export from the Orion and Flyndre fields is transported to the Fulmar platform and SEGAL system. 19 18 17 20 21 22 13 12 14 15 16 6 5 203 202 201 156 7 8 9 207 206 208 209 210 214 205 1 2 3 26 27 28 29 30 34 35 36 37 38 41 42 43 44 47 48 49 53 56 FULMAR SCOTLAND ENGLAND BELGIUM FRANCE GERMANY NORWAY WALES

Transcript of ICOP Fulmar 2017 · The Fulmar platform processes production from the Fulmar field, Halley field...

Page 1: ICOP Fulmar 2017 · The Fulmar platform processes production from the Fulmar field, Halley field and Auk North sub-sea tieback. The Fulmar complex also acts as a gathering hub by

Fulmar, Infrastructure Code of Practice

FULMAR

Last Updated: May 2017

The Fulmar platform was installed in 1981 with first oil production in 1982. The installation is located

approximately 217 miles east of Dundee and comprises of two fixed steel jackets. It has facilities for

drilling, production, accommodation and associated utilities.

The Fulmar platform processes production from the Fulmar field, Halley field and Auk North sub-sea

tieback. The Fulmar complex also acts as a gathering hub by providing a transportation and redelivery

service for the Gannet, Auk, Clyde, Orion and Flyndre fields through the Oil Export Module. Oil is

exported from the Fulmar platform via the Norpipe system for onward delivery to the Teesside terminal.

The associated gas from the Fulmar, Halley and Auk North fields is used as fuel on the platform or

flared. The Fulmar platform also has the facility to import gas via the Fulmar gas pipeline which runs

from the St Fergus terminal. Gas compression is provided via the Borsig system. Gas export from the

Orion and Flyndre fields is transported to the Fulmar platform and SEGAL system.

191817 20 21 22

1312 14 15 16

65203202

201156

7 8 9

207206

208 209 210214

205 1 2 3

26 27 28 29 30

34 35 36 37 38

41 42 43 44

47 48 49

53

56

FULMAR

SCOTLAND

ENGLAND

BELGIUM

FRANCE

GERMANY

NORWAY

WALES

Page 2: ICOP Fulmar 2017 · The Fulmar platform processes production from the Fulmar field, Halley field and Auk North sub-sea tieback. The Fulmar complex also acts as a gathering hub by

Fulmar, Infrastructure Code of Practice

OPERATIONAL INFORMATION

Licence P.185 & P.256

Licensees Repsol Sinopec North Sea Limited (Op) 100%

Platform Type Fulmar A: Eight–leg fixed steel jacket

Fulmar AD: Four-leg fixed steel jacket

Platform Weight

Fulmar A

Topsides: 26,940 Tonnes

Jacket: 12,400 Tonnes

Total: 44,140 Tonnes

Fulmar AD

Topsides: 260 Tonnes

Jacket: 1,406 Tonnes

Total: 1,666 Tonnes

Drilling Fulmar A: 36 well slots

Fulmar AD: 6 slots

Wells Production: 23 (6 in use)

Injection: 14 (5 in use)

Nearest Installations Auk: 12 km

Clyde: 9 km

Page 3: ICOP Fulmar 2017 · The Fulmar platform processes production from the Fulmar field, Halley field and Auk North sub-sea tieback. The Fulmar complex also acts as a gathering hub by

Fulmar, Infrastructure Code of Practice

CAPACITY PROJECTION

The platform process system is nominally designed for the following quantities:

Description Unit

Max. Cap.

Projected Ullage (% of maximum capacity)

2017 2018 2019 2020 2021

1st Stage Separator ‘A’ train BPD 163,500

1st Stage Separator ‘B’ train BPD 163,500

2nd Stage Separator BPD 33,000

3rd Stage Separator BPD 60,000

Crude Oil Export BPD 140,000

Produced Water Treatment BPD 140,000

Water Injection BPD 210,000

Available Capacities: > 25%

5% to 25%

< 5%

Page 4: ICOP Fulmar 2017 · The Fulmar platform processes production from the Fulmar field, Halley field and Auk North sub-sea tieback. The Fulmar complex also acts as a gathering hub by

Fulmar, Infrastructure Code of Practice

PIPELINES

Oil Export 24-inch * 16km oil export pipeline to a ‘Y’ piece on the J-Block/Norpipe

24-inch pipeline

Oil is then routed via the Norpipe system to the Teesside Terminal

Gas Export Gas is routed via the “SEGAL” system to the St. Fergus Terminal

ENTRY / EXIT SPECIFICATION

Crude Mixture Entry Flowing Wellhead up to 90°C

up to 25 bara

Crude Oil Export

TVP (True Vapour Pressure)

Base Sediment & Water

Salt

H2S

Total Sulphur

Nickel

Vanadium

Viscosity

pH

Mercury

2.3 barg @ 38°C

0.2 % vol

250 lb/Mbbl

10 ppm wt

0.35 % wt

10 ppm wt

10 ppm wt

40 cP @ 3°C

> 5

0.15 ppb wt

Produced Water <30 ppm oil in water