FNBE April 2014

Introduction to Construction Industry

Final Project Report

Name: Chong Yu Xuan (0317950)

Kong Zhen Chung (0319528)

Lecturer: Pn. Hasmanira Mokhtar

Page 2: Ici final project

Content

1.) Introduction

2.) Suggestion and Proposal

3.) Rationale and Benefits

4.) Site analysis and observation

5.) Sketch plan

6.) Introduction to the site

7.) Site Plan

8.) Authority Procedures

9.) Costing

Page 3: Ici final project

Introduction

In a group work of 2 people Chong Yu Xuan and Kong Zhen Chung. We are

required to find a specific land within Taylor Lakeside Campus to initiate a small

construction project. Size of the chosen land should not be more then

30mx30m.We choose to propose a food and beverage area idea for our site. As a

group , we are required to produce a project brief on the construction.

Page 4: Ici final project

Suggestion and proposal

For this project , we decided to propose a 24/7 food and beverage (dining area) that

provide full meals at our site. The dining area will have a restaurant that sells

economical and also healthy foods.

Page 5: Ici final project

Rationale and Benefits

Rationale

According to our survey and research many students usually does their

assignments till late night in the studios and classrooms of block E. The only eatery

available till late night are “Mamak” and seven eleven for snacks. These eatery are

oily and unhealthy which will cause health problems after overconsumption.

Furthermore, the food and beverages in Taylor’s Lakeside Campus are overpriced

and unsuitable for student ,all the more reason for an economical eatery.

Page 6: Ici final project

Benefits

This dining area in our site can bring much benefits to Taylor’s community

including:

1. Students around Block C/D/E do not need to walk long distance to the

commercial block to have a meal.

2. Enjoy beautiful scenery around that area.

3. Make use of the empty space.

4. Creating more business in the campus and improve social issues.

5. Economical food help students with financial burdens

6. Add choices to food variety in University compound

Page 7: Ici final project

Site Analysis

The site we had chosen is on the roof garden at level 2, right at the end of Block E.

Our site is approximately 27m x 15m. It is a public space roof terrace and an open

space with only a partial roof by the side. It has railing of 1.2 meters high along the

side of the site. There is a roof of 3 meters extending out from the right railing of

the site. To the south, there is a car park area and a sport court. To the west, there is

a view of the opposite roof terrace of the same level. To the east, there is a view of

large trees and residential area. There is a view of the Taylor’s lake on the south-

west

The site is located at Taylor’s lakeside campus, Block E, Level 2, balcony.

Page 8: Ici final project

Key Plan

Page 9: Ici final project

Location Plan

Page 10: Ici final project

Floor Plan

Page 11: Ici final project

In our site, it is free from air pollution, this is because our site is surrounded by

the car park spaces which is away from the roads. Our site also located at higher

level than the car park spaces. The wind strength in our site is average because our

site is attached to the block E building. Our site is located at block E, level 2. The

temperature in our site is normal because there are slow wind blowing toward our

site and our site is avoid from sun except in the afternoon half of our site will

explored by the sunlight. The only sound pollution faced in our site are the

condenser of the air conditional attached to the wall of buildings beside our site.

In front of the balcony, it’s a car park and

this is the view from our site looking

towards the car park.

The railing around the perimeter of the

balcony. It’s a 1m tall railing around the

balcony and it’s lifted by 15cm concrete step.

Sun Orientation

The sunlight will only reach the balcony

when afternoon 12pm to 2pm. Most area of

the site is shaded.

Page 12: Ici final project

Full Site view from the entrance, as you can

see it is empty and unused

Block E, view from balcony.

Human Traffic

The entrance is wide, no traffic congestion

as this place is not used for anything

Page 13: Ici final project

Proposed Site Introduction

After complete this project, our site had finally become a food and beverage area. It consists a

kitchen at the corner of our site. There will also be a bar beside the kitchen. The purpose that we

build a bar in it is to serve different types of drinks for the customers.

Rationale:

Students can dine at this area without walking very long distance to the

commercial block.

Page 14: Ici final project

Zoning

Restaurant

Dine area

Leisure and sightseeing area

Page 15: Ici final project

Site Plan

Door Benches Outdoor umbrella Table Potted plant

Kitchen Bar

Page 16: Ici final project
Page 17: Ici final project

Authority Procedure

Development order

Submit and obtain Dev elopment Approv al through OSC

Builders can now apply for construction permits through OSC 1Submission (single entry). OSC will then refer the submissions t o

the Planning Department, Building Department, Engineering Department, Fire Department, Sewerage Agency, Water Agency and

the Telecommunication Operators.

OSC will issue the development approval (Planning aprrovals, Building approvals, Engineering approvals, Fire safety plan

endorsements, water approvals, sewerage works approvals and Telecommunications approvals) to the builder. While all forms can

be obtained online at jprb.dbkl.gov.my/Pentadbir/MuatTurunBorangOSC/MTBorang11.asp, the fi ling has stil l to be done in person

at the OSC.

Builder will submit and obtain approval through OSC for the following documents:

• Planning plan

• Building plan

• Engineering plan (earthwork, road & drainage plan, road excavation permit & street l ighting plan)

• Landscape plan

• Water supply plan

• Sewerage plan

• Infrastructure communication plan

• Fire safety plan

Estimated Processing Costs

1. Planning plan = MYR 500.00

2. Building plan= MYR 1,300.

3. Engineering plan = MYR 100.00

Page 18: Ici final project

Development order

4. Water supply plan = MYR 1,000.00

1. Submission to Local Authority through OSC

2. Obtain Development Order (DO) from Planning Department

3. Obtain Water Approval

4. Obtain Sewerage Approval

5. Obtain Fire Safety (Arch) Comment

6. Obtain Earthwork Approval

7. Obtain Road and Drainage Approval

8. Obtain Landscape Approval

9. Obtain Street Lighting Approval

10. Obtain MSMA and SPAH Approvals

11. Obtain Building Plan Approval

12. Obtain Fire Safety (M&E) Approval

Agency: Kuala Lumpur City Hall’s One Stop Centre (OSC)

Submit pre-construction notifications to OSC

Under OSC 1Submission, all notifications are submitted via OSC. OSC will then distribute notifications to the relevant agencies

such as:

• Building Department (B Form - notification to start building work)

• Engineering Department (B Form - notification to start earthwork)

• Sewerage Certifying Agency (IWK) (PDC 6 Form - notification to start sewerage work)

Agency: Kuala Lumpur City Hall’s One Stop Centre (OSC)

Request final utilities inspections through OSC

Under OSC 1Submission, the builder has to request for inspections via OSC. OSC will arrange and coordinate inspections and

connections schedule with relevant agencies

1. TELCO connection = MYR495.00

2. Water connection = MYR 30.00

3. Fire safety inspection = MYR 111.00

Agency: Kuala Lumpur City Hall’s One Stop Centre (OSC)

Receiv e Road and Drainage Final Inspection

Once the road and drainage works has been completed, the builder will request the Road and Drainage clearance letter from the

Engineering Department of CHKL. The builder has to submit a construction report notification and by signing form G 17, the

Engineer certifies that all works were carried out according to regulations. Form G17 will be fi led along with Form F (Certif icate of

Completion and Compliance (CCC) via OSC to the Engineering Department.

Agency: Sewerage Certifying Agency (IWK)

Obtain Road and Drainage Clearance Letter

Page 19: Ici final project

Development order

A date for the inspection will be set-up prior to the issuance of clearance letter for the road and drainage work

Agency: Sewerage Certifying Agency (IWK)

Receiv e Sewage Final Inspection

The Sewerage Certifying Agency (IWK) will carry out an inspection of the sewerage system and issue to the builder a clearance

letter for sewerage.

Agency: Sewerage Certifying Agency (IWK)

Obtain Sewage Clearance Letter

Once the inspection has been carried out, a clearance letter is issued to the Builder. This clearance letter will allow the E ngineer to

issue the Certificate of Completion and compliance (CCC).

Agency: Sewerage Certifying Agency (IWK)

Receiv e Fire Safety Final Inspection

Fire and Rescue Department will carry out fire safety inspection

Agency: Fire and Rescue Department

Obtain Fire Safety Final Letter

Fire and Rescue Department will issue to the builder the clearance letter for fire safety

Agency: Fire Department

Receiv e Water Inspection

Water Authority SYABAS will conduct an onsite inspection of the works and make the connection to the public pipe.

Agency: Water Authority SYABAS

Submit Water Test and Commissioning (T&C) Report

Water Authority SYABAS will conduct an onsite inspection of the works and make the connection to the public pipe.

Agency: Water Authority SYABAS

Obtain Water Clearance Letter

The Water Authority SYABAS will issue a clearance letter to the builder and insta ll the water meter at the same time for water

connection.

Agency: Water Authority SYABAS

Builder’s Principal Submitting Person files the Certificate of Completion and compliance (CCC)

The Builder’s Principal Submitting Person (professional|architect) will issue Certificate of Completion and compliance (Form F -

CCC) to the Builder/Owner and 2 copies of the CCC will be fi led at the OSC for the Building Department (JRBB) and the Board o f

Architects/Engineers (LAM/LJM).

Agency: Building Department and Board of Architect via OSC.

Obtain Water Connection

Agency: Water Authority SYABAS

Obtain Telco Connection

Page 20: Ici final project

Costing

Description Single unit price Quantity Prices

Restaurant Restaurant RM20000 1 RM20000

Table RM120 40 RM480

Chairs RM25 200 RM5000 Kitchen utensils - - RM8000

Lighting RM30 10 RM300 Outdoor

Potted plant RM25 30 RM750 Advertisement board RM1300 2 RM2600

Outdoor umbrella RM150 10 RM1500