Ice Test by Hydro Quebec IREQ Institute

65
Slide 79 Ice Test by Hydro Quebec IREQ Institute

Transcript of Ice Test by Hydro Quebec IREQ Institute

Slide 79

Ice Test by Hydro Quebec IREQ Institute

Slide 80

Slide 81

2010 Tests

1300 lbs concrete

2 ice blocks

2/10 x 21 inch

Drag distance

6.5 ft / block

Effective Pressure

83,500 lbf/ ft2

Slide 82

Trial 1 – 40-50°F

20 cycles

No damage

Small depression°

Trial 2 – 40-50°F

With sand

10 cycles

No damage

Small scratches°

Trial 3 – 5°F

20 cycles

No damage

Small depression°

Slide 83

Special geomembrane formulation for cold weather

Slide 84

Slide 85

Slide 86

Slide 87

Slide 88

Slide 89

Slide 90

Slide 91

Slide 92

UPPER BLUE DAM

•Country: United States (Colorado)

•Elevation at crest: 11,742 feet

•Latitude: 39°N

•Dam height: 72 feet

•Type of face: bituminious concrete

•Geocomposite installation completed 2007

•Surface of upstream face: 71,350 sq. feet

•Installation time: 2 months

•Construction of a new plinth: no

Slide 93

Slide 94

Upper Blue face condition

Slide 95

Slide 96

First, install tensioning profiles to hold geocomposite

against wind force

Slide 97

Slide 98

Slide 99

Second, install thick geotextile cushioning layer over rough spots

Slide 100

Third , install the top seal with geocomposite

Slide 101

Slide 102

Fourth in rough areas install geogrid to bridge depressions of face.

Slide 103

Fifth, install thick geotextile over the geogrid

Slide 104

Sixth, install the PVC geocomposite

Slide 105

Seven, weld geocomposite sheets (2.1 m wide) together

Slide 106

Eight, install the top tensioning profile

Slide 107

Slide 108

Membrane installed but not tensioned on left, on right after tensioning profile installed

Slide 109

Ninth , install cap strip over tensioning profile

Slide 110

Slide 111

Slide 112

Tenth, remove the asphalt to expose concrete plinth

Slide 113

Slide 114

Eleventh, install perimeter seal with anchors

Slide 115

Slide 116

Twelve, install geogrid

Slide 117

Thirteen, install geonet drainage collection layer

Slide 118

Fourteen, install sacrificial geocomposite

Slide 119

Slide 120

Fifteen, install gcocomposite over plinth

Slide 121

Sixteen, install battens with coverstrip in ice area

Slide 122

Slide 123

Seventeen, core drain through asphalt

Slide 124

Eigteen, install drain plates (4) over drain holes

Slide 125

Last step, complete installation of batten strip perimeter seal

Slide 126

Slide 127

Slide 128

Slide 129

Slide 130

Slide 131

Slide 132

Slide 133

Slide 134

Slide 135

Slide 136

Slide 137

Slide 138

Statistics on dams in cold weather with exposed PVC geomembranes

PVC geomembranes are elastic and conform to subgrade

PVC can be formulated for low temperatures

Ice does not adhere to PVC

At least 55+ cold weather installations worldwide

Oldest – 37 years 1980 (Italy)

Highest Latitude – 59.5° N (Mongolia)

Highest Altitude – 11,742 fasl (Colorado)

More than 3,700,000 sq. feet installed in cold climates

More than 700 years of service for exposed PVC geomembrane installations in cold climates

Slide 139

The End

Gem dam, USA, 84 feet, 20072008 ASDSO National Rehabilitation Project of the Year

Slide 140

De-icing system

Slide 141

PVC geomembrane resist impact by Rip Rap

Slide 142

NO damage to the PVC geomembrane under Rip Rap

Slide 143