ICE Raspunsuri Tehnologie
Click here to load reader
-
Upload
mois-daniel -
Category
Documents
-
view
8 -
download
4
description
Transcript of ICE Raspunsuri Tehnologie
TECHNOLOGY OF CIVIL WORKS
1. What should contain a technological chart (control tag)?
Description of the technological process;
Characteristic sketches that describe the erection stages involved in the process in
a logic order;
Necessary resources for works achievement: raw materials, equipment,
manpower;
Works inspection;
Works acceptance;
Bill of quantities, works duration
2. What are the steps to follow in order to trace a building?
- Finding the special topographical grid and verification of tracing landmarks of the
topographical grid as position and structural integrity
- Tracing of the construction axes
- Rigger construction or trestles positioning for each structure axis
- Axes marking on riggers (both main and secondary axes)
- Foundations tracing
- Vertical alignment
2. How can be checked the formwork horizontality and verticality?
Checking verticality can be done using spirit level or plumb. Plumb line is used mounted
on a balance blade, with a sign traced on the lower arm at a distance equal to the one
between end of lead wire and the upper arm. Formwork is vertical when the plumb line
coincides with the sign on the lower arm.
Horizontality check can be achieved with spirit level , by placing it on the track and
noticing that the air bubble level to be drawn between two landmarks on the glass tube. If
the surface is not horizontal bubble is moving towards the higher side.
4. What are the main technical requirements to be met by concrete aggregates?
To come from strong rocks, that ensure grain self resistance greater than the concrete
one
Granules are well sized, and the ratio between the three dimensions after the
rectangular directions of grain to be b / a ≤ 0.66, c / a ≤ 0.33
It is preferable to use gravel aggregates – rounded shape. In the case of aggregate
crushing – that have rough surface –a larger amount of water and cement is necessary
to obtain the same workability.
The maximum size of grain used to be correlated with the minimum cross section of
the building element and the distance between the reinforcement bars.
Aggregates used must be characterized by a continuous curve of grain.
5. What rules will be considered and what measures will be taken for concreting in
cold weather conditions?
During preparation of concrete: o ratio Water / Cement reduction o heating the aggregates and water o adding anti-freeze additives
During concrete transport: o Using a fast and cold insulated vehicles for transport o Avoiding a large transport distances
o Checking of vehicles
o During concrete pouring:
- Foundations pits to be protected against freezing. The construction joints
should be avoided, or if not possible, cleaned and heated when resume
pouring
- Poured concrete heating with steam / hot air or with metal electrodes
embedded in concrete, etc.
6. What are the main rules to be followed in carrying out technological joints
position in case of cast in place concrete structures?
Working joints are determined taking into account the following rules:
o Areas of minimum effort
o Thickness of the element to be poured
o Dimensions of the surface to be poured
o Contractions direction
Problema tehnologie
For the foundations plan attached, find the duration of concrete pouring in foundations when the site is equipped with two rod vibrators, one for site use and one for backup.
It is required to draw the compaction scheme for the studied case. Concrete used: C12/15 with L2 workability Rod vibrator characteristics:
- Rod diameter: 60 mm d1 = 60mm, r1=30 mm - Rod length: l = 575 mm - Maximum vibrations amplitude in the air: A1 = 1.8mm - Vibrations frequency: n = 2800 vibr/min
Optimum vibrations range from the point of productivity: 0.07 0.12 mm
35 400 400 35
35
350
350
35
35 35
70
35 35
70
35 35
70
35
35
70
35
35
70
35
35
70
-1.20
-1.20
-1.20
-1.2
0
-1.2
0
-1.2
0
CTN=-0.10m
Table 1: damping coefficient of vibrations in fresh concrete b and minimum amplitudes
Amin
Vibr. frequency
b[cm-1] Amin[mm]
Concrete workability
L1 L2 >L3 L1 L2 >L3
2800 0.18 0.10 0.77 0.10 0.014 0.006
4500 0.16 0.09 0.06 0.07 0.010 0.004
6000 0.14 0.08 0.05 0.02 0.004 0.0025
7000-12000
0.13 0.07 0.04 0.01 0.003 0.002
Table 2: Compaction duration for rod vibrators
Concrete workability
Compaction duration t1 [sec]
L1
l18045
L2
l4025
>L3
l205
Solution Finding the span range (r0) for rod vibrator.
From table. 1, for L2 si n=2800 vibr/min b=0.1 cm-1; Amin = 0.014 mm
It is chosen r2 = 40 cm mm077.0e40
38.1e
r
rAA 3401.01r2r
2
11
A(0.07; 0.12)mm r0 = 40 cm Finding the distance (l1) between 2 successive positions of rod vibrator.
01 r5.1l 405.0l1 mm60l1
Finding distance (l2) to the excavation edge.
021 r5.0ld2 405.0l62 2 l2 [12; 20] cm
Finding the thickness of vibrated concrete layer (δ).
cm105l
l4
3
cm1055.57
5.574
3
cm5.525.47
cm43
δ ≤ 43 cm Compaction scheme
R40
R40
R40
R40
R40
R40
R40
R40R
40
R40
l2=
20
l1=
60
l1=
60
l2=20 30 l2=20
l2=20 l1=60 l1=60 l1=60 l1=60
l2=
20
30
l2=
20
A
A
Section A-A
Stage 1
20 30 20
40
11
0
Stage 2
20 30 20
40
11
0
35
Stage 3
20 30 20
40
11
0
35
35
5..
.10
5..
.10
Compaction duration
Acc. to table 2, for L2 l
4025t1
sec28
5.57
4040t1
Hour average productivity of the rod vibrator
e
21
20lexp k
tt
3600r2P
where t1 = 8 10 sec (necessary duration to move the rod
vibrator between 2 successive positions)
h
m48.88.0
1028
36004.02P
32
lexp
Concrete volume necessary for the continuous foundations (according to the
foundation plan)
31 m333230.310.170.0370.710.170.0V
Volume of fresh concrete necessary to be poured in foundations
312 m47
70.0
33
K
VV
Works duration in order to erect the continuous foundation
hours648.8
47
P
Vt
lexp
2