PowerCube 1000 V300R005C13
Installation Guide (G2, ICC500, ESU-A)
Issue 02
Date 2014-02-15
HUAWEI TECHNOLOGIES CO., LTD.
-
Issue 02 (2014-02-15) Huawei Proprietary and Confidential
Copyright Huawei Technologies Co., Ltd. i
Copyright Huawei Technologies Co., Ltd. 2014. All rights reserved.
No part of this document may be reproduced or transmitted in any form or by any means without prior
written consent of Huawei Technologies Co., Ltd.
Trademarks and Permissions
and other Huawei trademarks are trademarks of Huawei Technologies Co., Ltd.
All other trademarks and trade names mentioned in this document are the property of their respective
holders.
Notice
The purchased products, services and features are stipulated by the contract made between Huawei and
the customer. All or part of the products, services and features described in this document may not be
within the purchase scope or the usage scope. Unless otherwise specified in the contract, all statements,
information, and recommendations in this document are provided "AS IS" without warranties, guarantees or
representations of any kind, either express or implied.
The information in this document is subject to change without notice. Every effort has been made in the
preparation of this document to ensure accuracy of the contents, but all statements, information, and
recommendations in this document do not constitute a warranty of any kind, express or implied.
Huawei Technologies Co., Ltd.
Address: Huawei Industrial Base
Bantian, Longgang
Shenzhen 518129
People's Republic of China
Website: http://www.huawei.com
Email: [email protected]
-
PowerCube 1000
Installation Guide (G2, ICC500, ESU-A) About This Document
Issue 02 (2014-02-15) Huawei Proprietary and Confidential
Copyright Huawei Technologies Co., Ltd.
ii
About This Document
Propose
This document describes how to install the cabinet, boards, modules and cables for reference.
Figures used in this document are for reference only.
Safety Precautions
To ensure safety of humans and the equipment, pay attention to the safety symbols on the
equipment and all the safety instructions in this document. The "NOTE", "CAUTION", and
"WARNING" marks in other documents do not represent all the safety instructions. They are
only supplements to the safety instructions. When operating Huawei equipment, in addition to
following the general precautions in this document, follow the specific safety instructions
given by Huawei. Huawei will not be liable for any consequences that are caused by the
violation of safety regulations and design, production, and usage standards.
Local Safety Regulations
Only trained and qualified personnel are allowed to install, operate, and maintain Huawei
equipment.
Personnel Requirements
Only trained and qualified personnel are allowed to install, operate, and maintain Huawei
equipment. You can modify default parameters only after being granted approval from
Huawei technical support.
-
PowerCube 1000
Installation Guide (G2, ICC500, ESU-A) About This Document
Issue 02 (2014-02-15) Huawei Proprietary and Confidential
Copyright Huawei Technologies Co., Ltd.
iii
Symbols
Indicates an imminently hazardous situation which, if not avoided, will result in death or
serious injury.
Alerts you to a potentially hazardous situation that could, if not avoided, result in equipment
damage, data loss, performance deterioration, or unanticipated results.
Provides additional information to emphasize or supplement important points in the main text.
Human Safety To prevent electric shock, get the tool insulated and wear insulated gloves when
connecting cables.
To prevent inhalation or eye contact with dust, take adequate preventive measures when
drilling holes.
To avoid potential damage, wear protective shoes when moving batteries.
-
PowerCube 1000
Installation Guide (G2, ICC500, ESU-A) Contents
Issue 02 (2014-02-15) Huawei Proprietary and Confidential
Copyright Huawei Technologies Co., Ltd.
iv
Contents
About This Document .................................................................................................................... ii
1 Network Diagram ......................................................................................................................... 1
1.1 Network Diagram ......................................................................................................................................................... 1
2 Install Preparation ........................................................................................................................ 2
2.1 Installation Dimensions ................................................................................................................................................ 2
2.2 Tools ............................................................................................................................................................................. 3
2.3 Appearance and Installation Positions .......................................................................................................................... 4
2.4 Cables Routing Reference ............................................................................................................................................ 6
3 Install Equipment ......................................................................................................................... 9
3.1 Installing an ICC500 Cabinet ....................................................................................................................................... 9
3.2 Installing PSUs ........................................................................................................................................................... 12
3.3 Installing a ESMU ...................................................................................................................................................... 13
3.4 Installing an ESS-A .................................................................................................................................................... 13
3.5 Turning off the Power Switch ..................................................................................................................................... 15
4 Install Cables ............................................................................................................................... 17
4.1 Installing Cables for ESS-A (ESU-A2400Wh/D) ....................................................................................................... 17
4.2 Installing a CAN Communications Cable with an RJ45 connector for the ECC500 .................................................. 19
4.3 (Optional) Installing a Communications Cable .......................................................................................................... 20
4.4 Installing Cables for Sensors ...................................................................................................................................... 21
4.5 Installing AC Power Cables ........................................................................................................................................ 26
4.6 Installing Load Power Cables ..................................................................................................................................... 26
5 Power On the PowerCube 1000 ................................................................................................ 27
5.1 Checking Before Power-on ......................................................................................................................................... 27
5.2 Connecting the AC Input and ESS Supply.................................................................................................................. 27
5.3 Setting parameters ...................................................................................................................................................... 30
5.4 Check the ESS-A ........................................................................................................................................................ 32
5.5 Connecting the Mains Supply ..................................................................................................................................... 34
5.6 Powering On Loads .................................................................................................................................................... 34
5.7 Checking After Power-On .......................................................................................................................................... 35
-
PowerCube 1000
Installation Guide (G2, ICC500, ESU-A) Contents
Issue 02 (2014-02-15) Huawei Proprietary and Confidential
Copyright Huawei Technologies Co., Ltd.
v
A Appendix ..................................................................................................................................... 36
A.1 Installing Floating Nuts ............................................................................................................................................. 36
A.2 Preparing Terminals ................................................................................................................................................... 38
A.3 Port Description ......................................................................................................................................................... 38
-
PowerCube 1000
Installation Guide (G2, ICC500, ESU-A) 1 Network Diagram
Issue 02 (2014-02-15) Huawei Proprietary and Confidential
Copyright Huawei Technologies Co., Ltd.
1
1 Network Diagram 1.1 Network Diagram
An integrated controller and converter 500 (ICC500) is applicable to mains+energy storage system-A
(ESS-A) scenario.
(a1) AC input power cable between the mains and the alternating current distribution unit (ACDU)
(d1) DC power cable between ESS-A and the direct current distribution unit (DCDU)
(d2) DC cable between the DCDU and the DC load
(s1) (Optional) Communications cable between the ECC500 and the transport network
(s2) Signal cable between the ESS-A and the ECC500
-
PowerCube 1000
Installation Guide (G2, ICC500, ESU-A) 2 Install Preparation
Issue 02 (2014-02-15) Huawei Proprietary and Confidential
Copyright Huawei Technologies Co., Ltd.
2
2 Install Preparation 2.1 Installation Dimensions
Figure 2-1 Installation Dimensions
Unit: mm
-
PowerCube 1000
Installation Guide (G2, ICC500, ESU-A) 2 Install Preparation
Issue 02 (2014-02-15) Huawei Proprietary and Confidential
Copyright Huawei Technologies Co., Ltd.
3
2.2 Tools
Before you begin, get the following tools ready.
-
PowerCube 1000
Installation Guide (G2, ICC500, ESU-A) 2 Install Preparation
Issue 02 (2014-02-15) Huawei Proprietary and Confidential
Copyright Huawei Technologies Co., Ltd.
4
2.3 Appearance and Installation Positions
Figure 2-2 Appearance (with 100 Ah ACBs)
(1) Fan assembly (2) Filler panel (3) ECC500 (4) DCDU
(5) PSU subracks (6) RTN(+) (7) NEG(-) (8) ESMU
(9) ESU-A2400wh/D (10) ACDU
-
PowerCube 1000
Installation Guide (G2, ICC500, ESU-A) 2 Install Preparation
Issue 02 (2014-02-15) Huawei Proprietary and Confidential
Copyright Huawei Technologies Co., Ltd.
5
Figure 2-3 Appearance (with 200 Ah ACBs)
(1) Fan assembly (2) Filler panel (3) ECC500 (4) DCDU
(5) PSU subracks (6) RTN(+) (7) NEG(-) (8) ESMU
(9) ESU-A2400wh/D (10) ACDU
-
PowerCube 1000
Installation Guide (G2, ICC500, ESU-A) 2 Install Preparation
Issue 02 (2014-02-15) Huawei Proprietary and Confidential
Copyright Huawei Technologies Co., Ltd.
6
2.4 Cables Routing Reference
Figure 2-4 Reference for routing cables through the cable holes at the bottom of the cabinet
(1) AC input power cable (2) Signal cable for customer equipment (3) Power cable for customer equipment
(4) Load power cable (5) Signal cable
-
PowerCube 1000
Installation Guide (G2, ICC500, ESU-A) 2 Install Preparation
Issue 02 (2014-02-15) Huawei Proprietary and Confidential
Copyright Huawei Technologies Co., Ltd.
7
Figure 2-5 Cables routing reference (with 100 Ah ACBs)
-
PowerCube 1000
Installation Guide (G2, ICC500, ESU-A) 2 Install Preparation
Issue 02 (2014-02-15) Huawei Proprietary and Confidential
Copyright Huawei Technologies Co., Ltd.
8
Figure 2-6 Cables routing reference (with 200 Ah ACBs)
-
PowerCube 1000
Installation Guide (G2, ICC500, ESU-A) 3 Install Equipment
Issue 02 (2014-02-15) Huawei Proprietary and Confidential
Copyright Huawei Technologies Co., Ltd.
9
3 Install Equipment 3.1 Installing an ICC500 Cabinet
Procedure
Step 1 Mark the position of the cabinet based on the delivered marking-off template to confirm the positions of the expansion bolt.
Figure 3-1 Mark the position of the cabinet
(1) Marker (2) Marking-off template (3) Mounting hole (4) concrete floor
-
PowerCube 1000
Installation Guide (G2, ICC500, ESU-A) 3 Install Equipment
Issue 02 (2014-02-15) Huawei Proprietary and Confidential
Copyright Huawei Technologies Co., Ltd.
10
Step 2 Drill holes and install expansion tubes.
Figure 3-2 Drill holes and install expansion tubes
(1) Bolt (2) Spring washer (3) Flat washer (4) Expansion tube (5) Socket wrench
Step 3 Install the cabinet.
Figure 3-3 Using a crane
Figure 3-4 Using a pallet truck
-
PowerCube 1000
Installation Guide (G2, ICC500, ESU-A) 3 Install Equipment
Issue 02 (2014-02-15) Huawei Proprietary and Confidential
Copyright Huawei Technologies Co., Ltd.
11
Step 4 Secure the cabinet.
Figure 3-5 Secure the cabinet
Step 5 Connect the ground cable.
Figure 3-6 Connect the ground cable
(1) Site ground bar (2) Cabinet ground bar
Ground the cabinet immediately after installing it.
----End
-
PowerCube 1000
Installation Guide (G2, ICC500, ESU-A) 3 Install Equipment
Issue 02 (2014-02-15) Huawei Proprietary and Confidential
Copyright Huawei Technologies Co., Ltd.
12
3.2 Installing PSUs
To avoid personal injury, install filler panels in vacant subracks.
Install a maximum of six PSUs based on the required capacity.
Procedure
Step 1 Remove the bolts from the handle. Ensure that the module handle is open.
Step 2 Pull handle out.
Step 3 Gently push the PSU into the related slot along the guide rail.
Step 4 Push the handle upwards, lock the handle.
Step 5 Tighten the bolts in the handle and secure the handle.
Figure 3-7 Installing aPSU
----End
-
PowerCube 1000
Installation Guide (G2, ICC500, ESU-A) 3 Install Equipment
Issue 02 (2014-02-15) Huawei Proprietary and Confidential
Copyright Huawei Technologies Co., Ltd.
13
3.3 Installing a ESMU
Procedure
Step 1 Install the ESMU in the cabinet.
Figure 3-8 Installing a ESMU
----End
3.4 Installing an ESS-A
Context
Misoperations on ESUs will cause damage.
To prevent short circuits or electrolyte overflow, pay attention to the following items before
installing ESUs:
Remove the watch and metal jewelry such as bracelets, bangles, and rings from your wrist.
Use dedicated insulated tools.
Carry ESUs gently.
-
PowerCube 1000
Installation Guide (G2, ICC500, ESU-A) 3 Install Equipment
Issue 02 (2014-02-15) Huawei Proprietary and Confidential
Copyright Huawei Technologies Co., Ltd.
14
Procedure
Step 1 Install the ESU-A2400Wh/N or ESU-A2400Wh/D.
Figure 3-9 Secure equipment by using Phillips bolts
Figure 3-10 Secure equipment by using antitheft bolts
-
PowerCube 1000
Installation Guide (G2, ICC500, ESU-A) 3 Install Equipment
Issue 02 (2014-02-15) Huawei Proprietary and Confidential
Copyright Huawei Technologies Co., Ltd.
15
Step 2 Set the dual in-line package (DIP) switch addresses in ascending order from the bottom ESMU to the top ESMU by referring to the following table.
The addresses of ESMU must be different from each other.
----End
3.5 Turning off the Power Switch
Procedure
Step 1 Remove the fuse from the DCDU.
1. Remove the DCDU panel.
2. Switch all DC load circuit breakers to OFF.
3. Flip the battery switch to NORMAL.
4. Remove the fuse from the DCDU by using a fuse extracting unit.
-
PowerCube 1000
Installation Guide (G2, ICC500, ESU-A) 3 Install Equipment
Issue 02 (2014-02-15) Huawei Proprietary and Confidential
Copyright Huawei Technologies Co., Ltd.
16
Step 2 Flip all switches on the ESMU to OFF.
Step 3 Switch the AC circuit breaker on the ACDU to OFF.
----End
-
PowerCube 1000
Installation Guide (G2, ICC500, ESU-A) 4 Install Cables
Issue 02 (2014-02-15) Huawei Proprietary and Confidential
Copyright Huawei Technologies Co., Ltd.
17
4 Install Cables 4.1 Installing Cables for ESS-A (ESU-A2400Wh/D)
Procedure
Step 1 Take down the power cable from the right side of the ESMU and connect the power cable to the ESMU
Step 2 Install cables for ESS-A
1. Connect an electronic label communications cable between the ESS-A and the ESMU.
2. Connect DB15 signal cables between the ESU-A and the ESMU.
-
PowerCube 1000
Installation Guide (G2, ICC500, ESU-A) 4 Install Cables
Issue 02 (2014-02-15) Huawei Proprietary and Confidential
Copyright Huawei Technologies Co., Ltd.
18
Step 3 Install cables between ESS-A and the busbar.
Before connecting a cable, partially tighten the ESU bolt.
Then tighten the ESU bolt to a torque of 3.5 N.m to 5.0 N.m after connecting the cable.
1. Remove the protective cover from the ESMU and install the negative ESS-A cable. Then reinstall the protective lid and protective cover.
-
PowerCube 1000
Installation Guide (G2, ICC500, ESU-A) 4 Install Cables
Issue 02 (2014-02-15) Huawei Proprietary and Confidential
Copyright Huawei Technologies Co., Ltd.
19
2. Install the positive ESS-A cable and then the protective lid.
----End
4.2 Installing a CAN Communications Cable with an RJ45 connector for the ECC500
When the CAN port serves as the last level on the communications circuit, switch the toggle switches 1
and 2 of the DIP switch corresponding to the CAN port both to bit 1. Otherwise, signal transmission may
be unreliable.
-
PowerCube 1000
Installation Guide (G2, ICC500, ESU-A) 4 Install Cables
Issue 02 (2014-02-15) Huawei Proprietary and Confidential
Copyright Huawei Technologies Co., Ltd.
20
4.3 (Optional) Installing a Communications Cable
Communication over Huawei communications equipment
The ECC500 connects to the baseband unit (BBU) of base transceiver station (BTS) for
in-band communication.
The BTS is required to be later than GBSS12.0 and supports in-band networking.
Figure 4-1 Communication over Huawei communications equipment
-
PowerCube 1000
Installation Guide (G2, ICC500, ESU-A) 4 Install Cables
Issue 02 (2014-02-15) Huawei Proprietary and Confidential
Copyright Huawei Technologies Co., Ltd.
21
4.4 Installing Cables for Sensors
Procedure
Step 1 Install the smoke sensor and the environment temperature sensor.
1. Remove the panel.
2. Instal the smoke sensor and the environment temperature sensor.
There are two types of smoke sensors, please install the delivered sensors.
-
PowerCube 1000
Installation Guide (G2, ICC500, ESU-A) 4 Install Cables
Issue 02 (2014-02-15) Huawei Proprietary and Confidential
Copyright Huawei Technologies Co., Ltd.
22
3. Reinstall the panel.
Step 2 Connect signal cable to the smoke sensor. Connect the cable to the SMOKE port on the MUS01A module.
There are two types of smoke sensors, please install the delivered sensors.
-
PowerCube 1000
Installation Guide (G2, ICC500, ESU-A) 4 Install Cables
Issue 02 (2014-02-15) Huawei Proprietary and Confidential
Copyright Huawei Technologies Co., Ltd.
23
(1) White (2) Purple
-
PowerCube 1000
Installation Guide (G2, ICC500, ESU-A) 4 Install Cables
Issue 02 (2014-02-15) Huawei Proprietary and Confidential
Copyright Huawei Technologies Co., Ltd.
24
Step 3 Connect signal cable to the environment temperature sensor. Connect the cable to the TEM_HUM port on the MUS01A module.
(1) White (2) Purple (3) Yellow (4) Green
Step 4 Install the water sensor.
-
PowerCube 1000
Installation Guide (G2, ICC500, ESU-A) 4 Install Cables
Issue 02 (2014-02-15) Huawei Proprietary and Confidential
Copyright Huawei Technologies Co., Ltd.
25
Step 5 Connect signal cable to the water sensor. Connect the cable to the WATER port on the MUS01A module.
The cable between the water sensor and the ECC500 is already connected before delivering,
please check cable connections.
----End
-
PowerCube 1000
Installation Guide (G2, ICC500, ESU-A) 4 Install Cables
Issue 02 (2014-02-15) Huawei Proprietary and Confidential
Copyright Huawei Technologies Co., Ltd.
26
4.5 Installing AC Power Cables
Before connecting AC input power cables, switch all circuit breakers to OFF.
When connecting cables, wear insulation gloves and use insulated tools.
The following figure is for reference only.
Figure 4-2 Installing AC Power Cables
4.6 Installing Load Power Cables
Figure 4-3 Installing Load Power Cables
Connect DC power cables to the circuit breakers for controlling primary or secondary loads based on
site requirements.
The following figure is for reference only.
(1) Primary load (2) Secondary load
-
PowerCube 1000
Installation Guide (G2, ICC500, ESU-A) 5 Power On the PowerCube 1000
Issue 02 (2014-02-15) Huawei Proprietary and Confidential
Copyright Huawei Technologies Co., Ltd.
27
5 Power On the PowerCube 1000 5.1 Checking Before Power-on
Procedure
Step 1 All cables are connected in accordance with the wiring diagram.
Step 2 Turn off all switches.
Step 3 The cabinet is secured, and cables are connected properly.
Step 4 No short circuit occurs between the 48 V power cable and any of the ground bar, positive busbar, three-phase live wire, neutral wire, and ground cable.
Step 5 No short circuit occurs between the three-phase live wire, the neutral wire, and the ground cable.
----End
5.2 Connecting the AC Input and ESS Supply
Context
In the scenario with only the mains, power on and commission the PowerCube 1000 directly if the mains
is normal. If the mains is abnormal, connect a mobile D.G. to the PowerCube 1000 and then perform
power-on and commissioning.
-
PowerCube 1000
Installation Guide (G2, ICC500, ESU-A) 5 Power On the PowerCube 1000
Issue 02 (2014-02-15) Huawei Proprietary and Confidential
Copyright Huawei Technologies Co., Ltd.
28
Procedure
Step 1 Switch the AC circuit breaker on the upper-level device for the ACDU to ON. Check that the AC input phase voltage is 85 V AC to 290 V AC and the line voltage is 147 V AC to 502 V
AC by using a clamp meter.
Check the AC input phase voltage
Check the AC input line voltage
Step 2 Check the AC input circuit breaker on the ACDU is OFF.
Step 3 Reinstall fuses by using a fuse extracting unit.
Before reinstalling the fuse, switch the AC input circuit breaker on the ACDU to OFF.
Otherwise, the fuse will produce sparks during operation.
-
PowerCube 1000
Installation Guide (G2, ICC500, ESU-A) 5 Power On the PowerCube 1000
Issue 02 (2014-02-15) Huawei Proprietary and Confidential
Copyright Huawei Technologies Co., Ltd.
29
Step 4 Switch on the AC circuit breakers on the ACDU.
Step 5 Check that the AC input voltage is between 80 V AC to 220 V AC, and the system voltage is between 44.5 V DC and 57.6 V DC by using a clamp meter.
Figure 5-1 Check the AC input voltage
-
PowerCube 1000
Installation Guide (G2, ICC500, ESU-A) 5 Power On the PowerCube 1000
Issue 02 (2014-02-15) Huawei Proprietary and Confidential
Copyright Huawei Technologies Co., Ltd.
30
Figure 5-2 Check the system voltage
----End
5.3 Setting parameters
Context
The ECC500 takes 1 minute to start.
The user name is admin, and the password is 001.
The following table describes the buttons on the panel.
The data on the LCD is for reference only.
Button Name Description
or
Arrow
Key
Allows you to view menu items and set the value of a menu item.
Cancel Returns to the previous menu without saving the settings of the
current menu item.
Enter Enters the main menu from the standby screen, enters a submenu
from the main menu, or changes or saves the settings of a submenu
item.
NOTE
After a menu is displayed, the standby screen is displayed and the LCD screen becomes dark if no
button is pressed for 5 minutes.
-
PowerCube 1000
Installation Guide (G2, ICC500, ESU-A) 5 Power On the PowerCube 1000
Issue 02 (2014-02-15) Huawei Proprietary and Confidential
Copyright Huawei Technologies Co., Ltd.
31
Procedure
Step 1 Select ENGLISH when starting the ECC500.
Step 2 Set system parameters.
Main Menu Second-Level Third-Level Fourth-Level Value
Func Para Set System Para Set Date N/A Actual date
Set Time N/A Actual time
Set Time Zone N/A Actual time zone
Set ID N/A The same as the site
number or name
Step 3 Tear the ESN label from the ECC500 and paste it on your notebook. Record the site name corresponding to the ESN label. The ESN is used for setting up a site on the NetEco.
Step 4 Check ESS parameters.
Main Menu Second-Level Third-Level Fourth-Level Value
Device Para Set Site Summary Battery Type N/A ESU-A
NOTE
The ECC500 restarts after the battery type is reset and the restarting takes about 1 minutes.
Step 5 Set EPS parameters.
Main Menu Second-Level Third-Level Fourth-Level Value
Device Para Set Site Summary DG Cfg Mode N/A No DG
-
PowerCube 1000
Installation Guide (G2, ICC500, ESU-A) 5 Power On the PowerCube 1000
Issue 02 (2014-02-15) Huawei Proprietary and Confidential
Copyright Huawei Technologies Co., Ltd.
32
Step 6 (Optional) Set communications parameters.
For details, please refer to ECC500 (PowerCube) User Manual (Document ID: SE0000641658).
Communication over Huawei communications equipment
Main Menu Second-Level Third-Level Fourth-Level Value
Func Para Set Comm Para Host Para Host Type NetEco
Host Addr 27
----End
5.4 Check the ESS-A
Procedure
Step 1 Flip all the power switch on the ESMU to ON.
Step 2 If the ESS-A are powered on for the first time, initialization starts automatically to balance the voltage differences between ESU strings
Step 3 Wait 15 minutes until the initialization is complete and check that:
Typically, the initialization is complete within 15 minutes
If the voltage difference between ESU strings is great, the initialization may take 3.5 hours
Stay at the site before the initialization is complete
1. The ECC500 operating information displays that the battery status changes from Firston to Boost Charge, Discharge or Float Charge.
2. The RUN indicators on all ESMUs blink at short intervals (If an indicator blinks slowly, it is on for 1s and then off for 1s. If an indicator blinks fast, it is on for 0.125s and then
off for 0.125s.), and the CHG or DCHG indicators are steady on
3. The ECC500 displays that the ESS voltage ranges from 50 V DC to 57 V DC
-
PowerCube 1000
Installation Guide (G2, ICC500, ESU-A) 5 Power On the PowerCube 1000
Issue 02 (2014-02-15) Huawei Proprietary and Confidential
Copyright Huawei Technologies Co., Ltd.
33
4. No ECC500 or ESMUs generate an alarm
Set parameters as shown in the following figure to check that the displayed number of
ESMUs is the same as the actual number
The following figure is for reference only.
----End
-
PowerCube 1000
Installation Guide (G2, ICC500, ESU-A) 5 Power On the PowerCube 1000
Issue 02 (2014-02-15) Huawei Proprietary and Confidential
Copyright Huawei Technologies Co., Ltd.
34
5.5 Connecting the Mains Supply
Procedure
Step 1 Check the AC input circuit breaker on the ACDU are ON.
Step 2 Switch on the AC circuit breakers on the upper-level device for the ACDU.
----End
5.6 Powering On Loads
Procedure
Step 1 Switch on all load circuit breakers one by one.
Step 2 During the process, measure the busbar voltage using a clamp meter after switching on each circuit breaker. Then continue to switch on another circuit breaker after ensuring that the
busbar voltage ranges from 44.5 V DC to 57.6 V DC.
Figure 5-3 Checking Voltage
----End
-
PowerCube 1000
Installation Guide (G2, ICC500, ESU-A) 5 Power On the PowerCube 1000
Issue 02 (2014-02-15) Huawei Proprietary and Confidential
Copyright Huawei Technologies Co., Ltd.
35
5.7 Checking After Power-On
Procedure
Step 1 Switch on the load circuit breakers as required.
Step 2 Check the DCDU battery switch to NORMAL.
Step 3 Verify that the values on the ECC500 LCD screen are the same as the actual configurations and no alarm indicator on any component is on. If an alarm is generated or an Alarm indicator
is on, please contact the professional engineers of HUAWEI.
Step 4 If no exception occurs after the PowerCube 1000 runs for about 1 hour, the commissioning is complete.
Step 5 Reinstall all panels and check that the cabinet paint is intact and repaint the areas devoid of paint.
Step 6 Seal cable holes by using fireproof mud and clean up unnecessary things.
Step 7 Close and lock the cabinet door, and hand the keys over to the person in charge.
----End
-
PowerCube 1000
Installation Guide (G2, ICC500, ESU-A) A Appendix
Issue 02 (2014-02-15) Huawei Proprietary and Confidential
Copyright Huawei Technologies Co., Ltd.
36
A Appendix A.1 Installing Floating Nuts
This section describes the positions and procedures for installing floating nuts for different
heights of components.
Prerequisites
A flat-head screwdriver and a pair of protective gloves have been prepared.
Procedure
Step 1 Determine the mounting holes for floating nuts based on the component height.
Figure A-1 shows the positions for installing floating nuts for a 1 U component.
Figure A-1 Positions for installing floating nuts for a 1 U component
Figure A-2 shows the positions for installing floating nuts for a 2 U component.
Figure A-2 Positions for installing floating nuts for a 2 U component
-
PowerCube 1000
Installation Guide (G2, ICC500, ESU-A) A Appendix
Issue 02 (2014-02-15) Huawei Proprietary and Confidential
Copyright Huawei Technologies Co., Ltd.
37
Figure A-3 shows the positions for installing floating nuts for a 3 U component.
Figure A-3 Positions for installing floating nuts for a 3 U component
Figure A-4 shows the positions for installing floating nuts for a 4 U component.
Figure A-4 Positions for installing floating nuts for a 4 U component
Step 2 Install floating nuts using a flat-head screwdriver, as shown in Figure A-5.
When installing floating nuts, wear protective gloves and do not exert excessive force.
Otherwise, the flat-head screwdriver may hurt your hand or damage the device.
Figure A-5 Installing a floating nut
----End
-
PowerCube 1000
Installation Guide (G2, ICC500, ESU-A) A Appendix
Issue 02 (2014-02-15) Huawei Proprietary and Confidential
Copyright Huawei Technologies Co., Ltd.
38
A.2 Preparing Terminals
This section describes how to prepare cord end terminals and OT terminals.
Cut a cable of a proper length and install an OT terminal or a cord end terminal. Figure A-6
and Figure A-7 show the procedures for preparing a cord end terminal and an OT terminal
respectively.
Figure A-6 Preparing a cord end terminal
(1) Cable (2) Cord end terminal (3) Crimping tool
Figure A-7 Preparing an OT terminal
(1) Cable (2) OT terminal (3) Heat shrink tubing
(4) Hydraulic pliers (5) Heat gun
A.3 Port Description
For details about how to change default dry contact settings, see the ECC500 (PowerCube) User Manual
(Document ID: SE0000641658).
Expansion DO Board (MUE04A)
Figure A-8 shows the expansion DO board panel.
-
PowerCube 1000
Installation Guide (G2, ICC500, ESU-A) A Appendix
Issue 02 (2014-02-15) Huawei Proprietary and Confidential
Copyright Huawei Technologies Co., Ltd.
39
Figure A-8 Expansion DO board panel
(1) DO_1 (2) DO_2 (3) DO_3 (4) DO_4
(5) DO_5 (6) DO_6 (7) DO_7 (8) DO_8
Table A-1 describes the ports on the expansion DO board.
Table A-1 Port description
Silk Screen Type Default Associated Alarm Default Status
DO_1 Dry contact output Smoke Alarm
Water Detector Alarm
High Ambient Temperature
Low Ambient Temperature
High Ambient Humidity
Low Ambient Humidity
If any of the dry contacts
is closed, an alarm is
generated.
If the dry contacts are
open, no alarm is
generated.
The status is user-defined.
DO_2 Dry contact output Door Status Sensor Alarm
DO_3 Dry contact output All PSU Communication Failure
Communication Failure (PSU)
PSU Fault
AC SPD Fault
DO_4 Dry contact output Bus Bar Undervoltage
DO_5 Dry contact output High Battery Temperature
DO_6 Dry contact output HEX Fault
Internal Fan Fault
External Fan Fault
Compressor Fault
Air-conditioner Fault
DO_7 Dry contact output Mains Failure
AC Failure
-
PowerCube 1000
Installation Guide (G2, ICC500, ESU-A) A Appendix
Issue 02 (2014-02-15) Huawei Proprietary and Confidential
Copyright Huawei Technologies Co., Ltd.
40
Silk Screen Type Default Associated Alarm Default Status
DO_8 Dry contact output Cell Fault
BMU Fault
BMU Communication Failure
Note: The expansion DO board can be configured with all alarms that the ECC500 supports. For the alarm list,
see the ECC500 (PowerCube) Alarm Online Help.
Expansion IO Board (MUE05A)
Figure A-9 shows the expansion IO board panel.
Figure A-9 Expansion IO board panel
(1) DO_1 (2) DO_2 (3) DI_1 (4) DI_2
(5) DI_3 (6) DI_4 (7) DI_5 (8) DI_6
Table A-2 describes the ports on the expansion IO board.
Table A-2 Port description
Silk Screen Type Default Associated Alarm Default Status
DO_1 Dry contact output Reserved Reserved
DO_2 Dry contact output
DI_1 Dry contact input AC SPD Fault
If an AC SPD is connected, set
MUE05A_DI_1 Set to Normal
Close.
If the dry contact is open, no
alarm is generated.
If the dry contact is closed, an
alarm is generated.
The status is user-defined. DI_2 Dry contact input Fan Failure
DI_3 Dry contact input Hex Fault
If a heat exchanger is connected,
set MUE05A_DI_3 Set to
Normal Close.
DI_4 Dry contact input Air-conditioner Fault
-
PowerCube 1000
Installation Guide (G2, ICC500, ESU-A) A Appendix
Issue 02 (2014-02-15) Huawei Proprietary and Confidential
Copyright Huawei Technologies Co., Ltd.
41
Silk Screen Type Default Associated Alarm Default Status
DI_5 Dry contact input D.G.1 operating status If the dry contact is open, D.G.1
stops.
If the dry contact is closed, D.G.1
starts.
The status is not user-defined.
DI_6 Dry contact input D.G.2 operating status If the dry contact is open, D.G.2
stops.
If the dry contact is closed, D.G.2
starts.
The status is not user-defined.
About This DocumentContents1 Network Diagram1.1 Network Diagram
2 Install Preparation2.1 Installation Dimensions2.2 Tools2.3 Appearance and Installation Positions2.4 Cables Routing Reference
3 Install Equipment3.1 Installing an ICC500 Cabinet3.2 Installing PSUs3.3 Installing a ESMU3.4 Installing an ESS-A3.5 Turning off the Power Switch
4 Install Cables4.1 Installing Cables for ESS-A (ESU-A2400Wh/D)4.2 Installing a CAN Communications Cable with an RJ45 connector for the ECC5004.3 (Optional) Installing a Communications Cable4.4 Installing Cables for Sensors4.5 Installing AC Power Cables4.6 Installing Load Power Cables
5 Power On the PowerCube 10005.1 Checking Before Power-on5.2 Connecting the AC Input and ESS Supply5.3 Setting parameters5.4 Check the ESS-A5.5 Connecting the Mains Supply5.6 Powering On Loads5.7 Checking After Power-On
A AppendixA.1 Installing Floating NutsA.2 Preparing TerminalsA.3 Port Description