    Tiruchirappalli City Municipal Corporation

    Welcomes you

  • 8/12/2019 IAS Training Final

    2/31

    Tiruchirappalli city is the 4th largest city in Tamil

    Nadu, located on the banks of River Cauvery

    Srirangam,known as 'Thiruvarangam in Tamil is

    the abode of the Lord Sri Ranganathar, one of the

    108 Vaishanavaite Temples, which is popularly

    called as 'Bhoologa Vaikundam' (Earthly Heaven)

    Profile

  • 8/12/2019 IAS Training Final

    3/31

    Topography

    o Situated on the bank of River Cauvery and Coleroono River Cauvery flowing West to East across the City

    Terrain slopes from West to East

    Contour Level ranges 60 to 95 meters

    Max. and Min. Temperature 37.2 C and 24.0 C

    Average Annual Rainfall 685.80 mm

    Geographical Information

    Corporation Roads 1195.74 Kms

    Storm Water Drain 715.57 Kms

    No. of Ponds 31 Nos. 790 Acres

    No. of Channels 18 Nos. 50.31 Kms

  • 8/12/2019 IAS Training Final

    4/31

    Salient Features

    Total No. of Zones 4

    Total No. of Wards 65

    Area in Sq. Kms 167.23

    No. of Households 2,07,794

    No. of Slums 286

    2011 Population 9,16,674

    Slum Population 1,80,112

    Decadal Growth Rate 9.5 %

    Birth Rate 15.7

    Death Rate 6.4

    Population Density (Sq.Km) 5482

  • 8/12/2019 IAS Training Final

    5/31

    Length of Corporation Roads 1195.73 Km

    Length of Highways Road

    within Corporation limit 117.70 Km

    Length of Storm water drain 715.57 Km

    No. of streetlights 37517

    No. of Corporation Elementary Schools - 40

    No. of Corporation Middle Schools - 23

    No. of Corporation High Schools - 6

    No. of Corporation Hr. Sec. Schools - 1

    No. of Libraries - 4

    No. of Reading Rooms - 27

  • 8/12/2019 IAS Training Final

    6/31

    No. of Community Halls - 8

    No. of Daily Markets - 11

    No. of Corporation Dispensaries

    a. Alopathy - 14

    b. Siddha - 3

    No. of Corporation Maternity Centers - 13

    No. of Corporation Scan Centres - 8

    No. of Corporation Operation Theatres - 1

    No. of Corporation Urban Family Welfare Centres - 2

    No. of Corporation Urban Health Posts - 5

  • 8/12/2019 IAS Training Final

    7/31

    No. of Head Water Works maintained by Corporation - 5

    No. of Head Water Works maintained by TWAD Board - 1

    No. of Service Reservoirs - 65

    Total Capacity of Service Reservoirs - 423.90 Lakh Litre

    Length of Distribution Mains - 151.27 Km

    Length of Pumping Mains - 610.13 Km

    No. of Public Fountains - 2759

    No.of House Service Connections - 83877

    Average Quantity of water pumped per day - 90 MLD

    Per Capita Supply - 110 LPCD

  • 8/12/2019 IAS Training Final

    8/31

    Length of Underground Sewerage pumping main- 49.034 Km

    Length of Sewer Line - 330.57 Km

    No. of Pumping Stations (LT & HT) - 26

    No. of Lifting Stations - 26

    No. of STP site - 1

    Capacity of STP Site - 88.64 MLD

    Method of Treatment - WSP

    No. of House Service Connection - 40352

    Daily average sewage water pumped - 38 MLD

  • 8/12/2019 IAS Training Final

    9/31

    Daily average Quantity of Garbage Generated - 432 MT

    Daily average quantity of Garbage Collected - 415 MT

    Average Per capita generation - 461 gm

    No. of Compost Yard - 1

    Extent of Compost Yard - 47.70 Acres

    Method of disposal - Dumping

  • 8/12/2019 IAS Training Final

    10/31

    No. of Park sites - 83

    No. of Parks with greeneries - 27

    No. of Parks in public use - 7

    No. of Bus Stands - 2

    No. of Public FOL - 298

    No. of Integrated Sanitary Complexes - 72

    No. of Pay & Use Toilets - 20

    No. of Slaughter Houses - 2

    No. of Electric Crematorium - 1

    No. of Gasifier Crematorium - 2

  • 8/12/2019 IAS Training Final

    11/31

    1) Distribution of Water supply

    2) Formation / Maintenance of Roads

    3) Construction / Maintenance of Storm water drain

    4) Providing / Maintenance of Street light

    5) Under Ground Drainage facilities

    6)

    Health Activities - Roads & Streets sweeping, Toilets

    cleaning, D&O Trade Licences, Dispensaries, Maternity

    centers, Scan centers

    7) Solid Waste Management - Removal of Garbage

    8) Education - School buildings only

    9) Building plan approvals

    10) Issue of Survey sketches & extracts

    11) Birth & Death entries and issue of certificates

    12)

    Deletion & Additions in Electoral rolls for East & West

    Assembly constituency

    13) Population enumeration

    14)

    Conducting of Election to Tiruchirappalli East Assembly

    Constituency MLA & Council election

    15) Noon meal centers

    16) Daily Markets

    17) Slaughter houses

    18) Bus stands, Bus shelters

    19) Community Halls

    20) Commercial Complexes

    21) Parks maintenance

    22) Flood mitigation & relief measures

    23)

    Burial ground, Burning ghats, Electrical & Gasifier

    crematorium

    Corporation Activities

  • 8/12/2019 IAS Training Final

    12/31

  • 8/12/2019 IAS Training Final

    13/31

    Sl.

    No.

    Head

    Receipt ( a ) Expense ( b )

    2010-2011

    Budget

    2010-2011

    Revised

    Budget

    2011-

    2012

    Budget

    2010-2011

    Budget

    2010-2011

    Revised

    Budget

    2011-2012

    Budget

    1 Revenue Fund 9674.99 10262.50 10900.00 7204.28 8640.00 8821.00

    2 Capital Fund 11615.00 13730.00 10009.0016235.00

    15523.50

    13897.00

    3 SJSRY 71.25 71.25 106.00 71.25 71.25 106.00

    Total 21361.24 24063.75 21015.00 23510.53 24234.75 22824.00

    Revised Budget for 2010-2011&

    Budget for 2011-2012

    Sl.No.

    Head2010-2011

    Budget

    2010-2011

    Revised

    Budget

    2011-2012

    Budget

    1 Receipt ( a ) 21361.24 24063.75 21015.00

    2 Expense ( b ) 23510.53 24234.75 22824.00

    3 Deficit -2149.29 -171.00 -1809.00

  • 8/12/2019 IAS Training Final

    14/31

    Ongoing Projects Water supply Improvement Scheme

    Total Project Cost : Rs. 221.42 Cr.(Revised)

    Funding assistance : JICA through TNUIFSL (JBIC Grant)

    No. of Packages : 7

    Present population(2009) : 8,05,000

    Intermediate population(2024) : 9,66,643

    Ultimate population(2039) : 11,36,000,

    Designed quantity of water Present: 58.60 MLD

    Designed quantity of water Intermediate: 70.09 MLD

    Designed quantity of water Ultimate : 93.26 MLD

    Expected Yield from 3 Collector wells: 97.30 MLD

  • 8/12/2019 IAS Training Final

    15/31

    Important Works under this Scheme

    Collector Wells : 3 Nos.

    Common Sump : 2 Nos.

    No. of Service Reservoirs : 37 Nos.

    Total Capacity of SRs : 199 Lakh Litre

    Length of pumping mains : 81.15 Km

    Length of Distribution Mains : 487 Km

    Revamping of existing Distribution mains : 82.00 Km

    Probable date of completion : 30-04-2012

    Goal - On completion of this Scheme, all the residents will be provided with 135 LPCD

    as per CPHEEO norms

    Ongoing Projects Water supply Improvement Scheme

  • 8/12/2019 IAS Training Final

    16/31

    Ongoing Projects IHSDP

    Project Cost : Rs. 1996 Lakhs.

    For Housing component : Rs. 1515.50 Lakhs

    For Infrastructure : Rs. 480.50 Lakhs

    Total No. of Houses taken up : 1208

    No. of Houses completed : 854 No. of Houses in progress : 354

    Total No. of Infra works : 43

    No. of Works completed : 42

    No. of Works in progress : 1

    Total Expenditure : Rs. 1464.15 Lakhs

    Cost of one house : Rs. 1.30 Lakhs

    Area of House : 25 Sq. M.

  • 8/12/2019 IAS Training Final

    17/31

    Ongoing Projects Infra Gap Filling Fund

    Project Cost : Rs. 250 Lakhs.

    Construction of Sanitary Workers Quarters : 3 Works ( each work 12 Houses)

    Basic amenities works : 1

    No. of Works in progress : 4

    Total Expenditure : Rs. 98.03 Lakhs

  • 8/12/2019 IAS Training Final

    18/31

    Ongoing Projects O&M Gap Filling Fund

    Project Cost : Rs. 305 Lakhs.

    Chatram Bus Stand Improvement Works : 3

    Flood protection wall : 1

    Providing CC Road at Compost Yard : 2

    No. of Works in progress : 6

    Total Expenditure : Rs. 89.23 Lakhs

  • 8/12/2019 IAS Training Final

    19/31

    Ongoing Projects Seed Capital Assistance Fund

    Project Cost : Rs. 363 Lakhs.

    Construction of bridge across Uyyakondan channel : 1

    Formation of Link Road connecting

    Tennur Anna Nagar Main Road with Lawsons

    Road near MGR Statue : 1

    No. of Works in progress : 2

  • 8/12/2019 IAS Training Final

    20/31

    Projects to be taken for the year 2012-2013

    PARKING SLOT

    Improvements to the existing two wheeler parking slot

    at Chatram Bus Stand at an outlay of Rs. 5 Crores.

    Improvements to the existing two wheeler parking slot

    at Diamond Jubilee Campus opposite to Gandhi

    Market at an outlay of Rs. 15 Crores.

  • 8/12/2019 IAS Training Final

    21/31

    Projects to be taken for the year 2012-2013

    IMPROVEMENTS TO COMPOST YARD

    Formation of capping by compressing the

    dumped garbages at Ariyamangalam Compost

    Yard at an outlay of Rs. 5 Crores.

    Formation of Landfill for disposal of the garbage

    at Ariyamangalam Compost Yard at an outlay of

    Rs. 5 Crores.

  • 8/12/2019 IAS Training Final

    22/31

    Projects to be taken for the year 2012-2013

    Modernising the existing Fish Market and

    Slaughter House

    The existing Fish Market and Goats slaughter

    house in Gandhi Market will be modernised with

    all facilities and effluent treatment plant at an

    outlay of Rs.4.00.Crores.

  • 8/12/2019 IAS Training Final

    23/31

    Projects to be taken for the year 2012-2013

    Establishment of Integrated Bus Stand

    An Integrated Bus Stand with all facilities will be

    established in a suitable location at an outlay ofRs. 90 Crores to ease the traffic congestion at

    Central Bus Stand and Chatram Bus Stand.

  • 8/12/2019 IAS Training Final

    24/31

    Projects to be taken for the year 2012-2013

    Establishment of Bus Stand at Srirangam area

    A full-fledged Bus Stand will be established at

    Srirangam area to mitigate the hardships facedby the pilgrims to get into srirangam at an outlay

    of Rs. 9 Crores.

  • 8/12/2019 IAS Training Final

    25/31

    Projects to be taken for the year 2012-2013

    Roads

    It is proposed to convert the existing

    earthen road into BT road andimprovements to existing damaged roads

    the at an outlay of Rs. 25 Crores

  • 8/12/2019 IAS Training Final

    26/31

    Projects to be taken for the year 2012-2013

    Storm Water Drain

    It is proposed to construct storm water

    drain in uncovered areas and

    maintenance / repair works to the existing

    damaged drains at an outlay of

    Rs. 25 Crores

  • 8/12/2019 IAS Training Final

    27/31

    Sl.No.

    Name of work Estimate Cost(Rs. In Crores)

    1 Parking Slot 20.00

    2 Improvement to Compost Yard 10.00

    3 Modernising the existing Fish Marketand Slaughter House

    4.00

    4 Integrated Bus Stand 90.00

    5 Bus Stand at Srirangam 9.00

    6 Road 25.00

    7 Storm water drain 25.00

    Total 183.00

    Abstract for Projects to be taken up for the year 2012-2013

  • 8/12/2019 IAS Training Final

    28/31

    Long Term Projects

    Under Ground Sewerage Scheme

    There are still some areas in which under ground sewerage facilities are not available.For these uncovered areas, the detailed project report is being prepared by TWAD

    Board in the following 3 phases for providing under ground sewerage system.

    Phase I - Providing UGSS to the uncovered areas in Srirangam (Wards 1 to 6).

    Project Cost Rs.24.00 Crores (In-principle Sanction is obtained)

    Length of Sewer 40 Kms.

    Phase II - Providing UGSS to the uncovered areas in Tiruchirappalli City

    Corporation (excluding Srirangam).

    Project Cost Rs.195.00 Crores

    Length of Sewer 193 Kms.

    Phase III - - Providing UGSS to the uncovered areas in Tiruchirappalli City

    Corporation (excluding Srirangam but including extended area).

    Project Cost Rs. 508.00 Crores (Tentative figure. DPR under preparation)

    Total :Rs. 727.00 Crores

  • 8/12/2019 IAS Training Final

    29/31

    Sl. No. InfrastructureEstimated Amount

    (Rs.in Lakhs)1 Water Supply 413.30

    2 Under Ground Sewerage Scheme 7370.20

    3 Storm Water Drain 7500.00

    4 Roads 2500.00

    5 Street Lights 255.00

    6 Solid Waste Management 1571.60

    7 Bus Stand 9000.00

    8 Maternity Centres 2400.00

    9 Slaughter Houses 400.00

    10 Burial Ground / Crematoria 500.00

    11 Parks & Playfields 200.00

    12 Others, if any 2900.00

    Total 35010.10

    Next Year Plan (2012-13)

  • 8/12/2019 IAS Training Final

    30/31

    Further 4 Years Plan

    Sl.

    No.

    Infrastructure 2013-14 2014-15 2015-16 2016-17 Total EstimateCost (Rs.in

    lakh)1 Water Supply 275.53 275.53 206.65 206.65 964.36

    2 Under Ground

    Sewerage Scheme

    4913.46 4913.46 3685.10 3685.10 17197.12

    3 Storm Water Drain 4280.28 4280.28 3210.21 3210.21 14980.98

    4 Roads 2683.28 2683.28 2012.46 2012.46 9391.48

    5 Street Lights 170.00 170.00 127.50 127.50 595.00

    6 Solid Waste

    Management

    3575.72 3575.72 2681.79 2681.79 12515.02

    7 Bus Stand 12200.00 12200.00 9150.00 9150.00 42700.00

    8 Maternity Centres 60.00 60.00 45.00 45.00 210.00

    9 Slaughter Houses 40.00 40.00 30.00 30.00 140.00

    10 Burial Ground /

    Crematoria

    30.00 30.00 22.50 22.50 105.00

    11 Parks & Playfields 300.00 300.00 225.00 225.00 1050.00

    12 Others, if any 600.00 600.00 450.00 450.00 2100.00

    Total 29128.27 29128.27 21846.21 21846.21 101948.96