IAQ Building 6 Basement

35
IAQ Building 6 Basement

description

IAQ Building 6 Basement. Initial Request To [email protected] January 3, 2012. Industrial Hygiene Responds January 9, 2012. Mold sampling conducted Noted very dusty conditions and recommend a thorough cleaning Notice the supply air vents are blocked with Plexiglas - PowerPoint PPT Presentation

Transcript of IAQ Building 6 Basement

Page 1: IAQ Building 6 Basement

IAQ Building 6 Basement

Page 2: IAQ Building 6 Basement

Initial Request To [email protected] 3, 2012

Hi, I would like an Indoor Air Quality assessment performed for rooms 6-022 and 6-031, with specific attention paid to mold levels. 6-022 is an office, and 6-031 is an associated lab space. Thanks,

Page 3: IAQ Building 6 Basement

Industrial Hygiene RespondsJanuary 9, 2012

• Mold sampling conducted• Noted very dusty conditions and recommend

a thorough cleaning• Notice the supply air vents are blocked with

Plexiglas• Decided to come back with the IAQ Meter to

take further measurements (CO2, CO, Temperature, humidity)

Page 4: IAQ Building 6 Basement

Industrial Hygiene RespondsJanuary 9, 2012

• Industrial Hygiene notifies the EHS Coordinator of the complaint and the blocked supply vents.

• EHS Coordinator determines multiple work-orders were placed by the group to have the heat fixed. Works with the Facilities and Security Supervisor for Chemistry to more actively engage Facilities about the problem.

Page 5: IAQ Building 6 Basement

January 6 Mold Sampling

Table 1: Jan 6, 2012 Culturable Mold Sampling

Location Colony Forming Units (CFU) per cubic meter of air.

Culturable species % of Control

6-022 110 CFM/m3 Heterogeneous mixture of species. 550%

6-031 5 CFU/m3 Heterogeneous mixture of species. 25%

Outdoor Control 20 CFU/m3

Heterogeneous mixture of species. N/A

Page 6: IAQ Building 6 Basement

January 11 to 20 CO2

0

200

400

600

800

1000

1200

14:0

0:12

19:5

5:12

1:50

:12

7:45

:12

13:4

0:12

19:3

5:12

1:30

:12

7:25

:12

13:2

0:12

19:1

5:12

1:10

:12

7:05

:12

13:0

0:12

18:5

5:12

0:50

:12

6:45

:12

12:4

0:12

18:3

5:12

0:30

:12

6:25

:12

12:2

0:12

18:1

5:12

0:10

:12

6:05

:12

12:0

0:12

17:5

5:12

23:5

0:12

5:45

:12

11:4

0:12

17:3

5:12

23:3

0:12

5:25

:12

11:2

0:12

17:1

5:12

23:1

0:12

5:05

:12

Figure 1: CO2 Levels 6-0221/11/2012-1/20/2012

Page 7: IAQ Building 6 Basement

Jan 11 to 20 Temperature

60

65

70

75

80

85

14:0

0:12

19:5

5:12

1:50

:12

7:45

:12

13:4

0:12

19:3

5:12

1:30

:12

7:25

:12

13:2

0:12

19:1

5:12

1:10

:12

7:05

:12

13:0

0:12

18:5

5:12

0:50

:12

6:45

:12

12:4

0:12

18:3

5:12

0:30

:12

6:25

:12

12:2

0:12

18:1

5:12

0:10

:12

6:05

:12

12:0

0:12

17:5

5:12

23:5

0:12

5:45

:12

11:4

0:12

17:3

5:12

23:3

0:12

5:25

:12

11:2

0:12

17:1

5:12

23:1

0:12

5:05

:12

Figure 2: Temperature in Rom 6-0221/11/2012-1/20/2012

Shaded area=recommended range

Page 8: IAQ Building 6 Basement

Jan 11 to Jan 20 RH

0

10

20

30

40

50

60

14:0

0:12

19:5

5:12

1:50

:12

7:45

:12

13:4

0:12

19:3

5:12

1:30

:12

7:25

:12

13:2

0:12

19:1

5:12

1:10

:12

7:05

:12

13:0

0:12

18:5

5:12

0:50

:12

6:45

:12

12:4

0:12

18:3

5:12

0:30

:12

6:25

:12

12:2

0:12

18:1

5:12

0:10

:12

6:05

:12

12:0

0:12

17:5

5:12

23:5

0:12

5:45

:12

11:4

0:12

17:3

5:12

23:3

0:12

5:25

:12

11:2

0:12

17:1

5:12

23:1

0:12

5:05

:12

Figure 3: Relative humidity in 6-0221/11/2012-1/20/2012 Shaded

area=recommended range

Page 9: IAQ Building 6 Basement

Symptoms (In Last 6 Months)

• Fatigue• 1 case of pneumonia• Headaches• Nose bleeds• Vertigo

Page 10: IAQ Building 6 Basement

Supply Air Vents

• All room vents blocked

• Reheat coils not functioning

• Cold air blowing on students

• Multiple work-orders placed by the group to have the heat fixed

Page 11: IAQ Building 6 Basement

Supply Air Vents

• Work-orders placed on: 9/28/1010/6/104/22/11

• Does not include “repeated phone calls”• On 4/27/11 the student decides he is not having

success with the work-order process and finds a Facilities Comments form on the web and submits another request.

Page 12: IAQ Building 6 Basement
Page 13: IAQ Building 6 Basement

Supply Air Vents

• Facilities technician informs group that reheat coils cannot be fixed.

• Facilities suggests as a solution they can cover over the supply vent blowing on the student.

Page 14: IAQ Building 6 Basement

Supply Air Vents

• Reheat Coils Fixed• Vents Unblocked On

or Around January 23rd

Page 15: IAQ Building 6 Basement

January 26 Mold Sampling

Table 1: Jan 26, 2012 Culturable Mold Sampling

Location Colony Forming Units (CFU) per cubic meter of air. Species

6-022 (1) 5 CFM/m3 Heterogeneous mixture of species.

6-022 (back) 5 CFU/m3 Heterogeneous mixture of species

6-021 0 CFU/m3 NA

Hallway 0 CFU/m3 NA

Stairwell 30 CFU/m3 Heterogeneous mixture of species

Outdoor 50 CFU/m3 Heterogeneous mixture of species

Page 16: IAQ Building 6 Basement

February 2nd

• Industrial Hygiene revisits the space to assess the air using the IAQ meter.

Page 17: IAQ Building 6 Basement

February 2 to February 9

0

200

400

600

800

1000

1200

1400

15:0

6:37

19:4

6:37

0:26

:37

5:06

:37

9:46

:37

14:2

6:37

19:0

6:37

23:4

6:37

4:26

:37

9:06

:37

13:4

6:37

18:2

6:37

23:0

6:37

3:46

:37

8:26

:37

13:0

6:37

17:4

6:37

22:2

6:37

3:06

:37

7:46

:37

12:2

6:37

17:0

6:37

21:4

6:37

2:26

:37

7:06

:37

11:4

6:37

16:2

6:37

21:0

6:37

1:46

:37

6:26

:37

11:0

6:37

15:4

6:37

20:2

6:37

1:06

:37

5:46

:37

Figure 1: CO2 Levels in 6-0222/2/12-2/9/12

Shadedarea=reccomended range

Page 18: IAQ Building 6 Basement

February 2 to February 9

60

65

70

75

80

15:0

6:37

19:3

8:37

0:10

:37

4:42

:37

9:14

:37

13:4

6:37

18:1

8:37

22:5

0:37

3:22

:37

7:54

:37

12:2

6:37

16:5

8:37

21:3

0:37

2:02

:37

6:34

:37

11:0

6:37

15:3

8:37

20:1

0:37

0:42

:37

5:14

:37

9:46

:37

14:1

8:37

18:5

0:37

23:2

2:37

3:54

:37

8:26

:37

12:5

8:37

17:3

0:37

22:0

2:37

2:34

:37

7:06

:37

11:3

8:37

16:1

0:37

20:4

2:37

1:14

:37

5:46

:37

Figure 2: Temperature Levels in 6-0222/2/12-2/9/12

shadedarea=reccomended range

Page 19: IAQ Building 6 Basement

February 2 to February 9

0

10

20

30

40

50

60

70

15:0

6:37

19:3

8:37

0:10

:37

4:42

:37

9:14

:37

13:4

6:37

18:1

8:37

22:5

0:37

3:22

:37

7:54

:37

12:2

6:37

16:5

8:37

21:3

0:37

2:02

:37

6:34

:37

11:0

6:37

15:3

8:37

20:1

0:37

0:42

:37

5:14

:37

9:46

:37

14:1

8:37

18:5

0:37

23:2

2:37

3:54

:37

8:26

:37

12:5

8:37

17:3

0:37

22:0

2:37

2:34

:37

7:06

:37

11:3

8:37

16:1

0:37

20:4

2:37

1:14

:37

5:46

:37

FIgure 3: RH in % in 6-0222/2/12-2/9/12

shaded area=reccomended range

Page 20: IAQ Building 6 Basement

MIT Medical

• Industrial Hygiene contacts MIT Medical on February 6 to inform Dr. David Diamond of group members suffering from adverse medical conditions that they believe are related to the office space 6-022

• On February 13, Dr. Diamond visits the space and talks with some of the occupants.

Page 21: IAQ Building 6 Basement

Action Taken

• It is recommended to seal up a trough in the floor that may be prone to flooding (and consequently prone to mold growth)

• Biosafety conducts another round of mold sampling on that day

• Biosafety submits a work order to Facilities to have the fan coil units checked to ensure they are not clogged, moldy, etc.

Page 22: IAQ Building 6 Basement

Fan Coil Units

• Facilities reported the fan coil units had not been put on a PM schedule and were not being serviced.

• New filters installed.

Page 23: IAQ Building 6 Basement

February 13

1BLocation Colony Forming Units (CFU) per cubic meter of air. 0BSpecies

6-022 kitchen 0 CFM/m3 NA

6-022a 0 CFU/m3 NA

6-022b near window 0 CFU/m3 NA

6-022b center 0 CFU/m3 NA

6-basement adjacent stairwell

5 CFU/m3 Aspergillus fumigatus

6-122 upstairs hallway 10 CFU/m3

Aspergillus niger

Page 24: IAQ Building 6 Basement

Actions Taken

• Gone from essentially no air flow to fresh supply air entering the space, and significantly lower CO2 levels.

• Established that there is no mold problem• Had the fan coil units serviced and put on a regular

PM, so room temperature can be maintained.• Also loaned the group a HEPA filter unit• Informal visits indicated that the original students

that complained felt like the air was better

Page 25: IAQ Building 6 Basement
Page 26: IAQ Building 6 Basement

April 2, 2012

• Two new lab group member emails EHS members involved and complain of being “more fatigued than usual”.

• On April 3 we meet with the group members and conduct another round of air sampling with the IAQ meter and another round of mold sampling.

Page 27: IAQ Building 6 Basement

April 3 Mold Sampling

1BLocation Colony Forming Units (CFU) per cubic meter of air.

Species

6-022 kitchen 5 CFM/m3 Lecythophora

6-022a 0 CFU/m3 N/A

6-022b near window 5 CFU/m3 Cladosporium

6-022b near hall 10 CFU/m3 Aspergillus,

Verticillium Outdoor control 10 CFU/m3 Aspergillus

6-122 Hallway control

15 CFU/m3 Heterogeneous species

Page 28: IAQ Building 6 Basement

April 3 to April 4

0

200

400

600

800

1000

1200

13:2

5:12

14:0

8:12

14:5

1:12

15:3

4:12

16:1

7:12

17:0

0:12

17:4

3:12

18:2

6:12

19:0

9:12

19:5

2:12

20:3

5:12

21:1

8:12

22:0

1:12

22:4

4:12

23:2

7:12

0:10

:12

0:53

:12

1:36

:12

2:19

:12

3:02

:12

3:45

:12

4:28

:12

5:11

:12

5:54

:12

6:37

:12

7:20

:12

8:03

:12

8:46

:12

9:29

:12

10:1

2:12

10:5

5:12

11:3

8:12

12:2

1:12

13:0

4:12

13:4

7:12

14:3

0:12

Shaded area=recommendrange

CO2 Levels in 6-0223 April 2012 to 4 April 2012

Page 29: IAQ Building 6 Basement

April 3 to April 4

65

66

67

68

69

70

71

72

73

74

75

13:2

5:12

14:0

7:12

14:4

9:12

15:3

1:12

16:1

3:12

16:5

5:12

17:3

7:12

18:1

9:12

19:0

1:12

19:4

3:12

20:2

5:12

21:0

7:12

21:4

9:12

22:3

1:12

23:1

3:12

23:5

5:12

0:37

:12

1:19

:12

2:01

:12

2:43

:12

3:25

:12

4:07

:12

4:49

:12

5:31

:12

6:13

:12

6:55

:12

7:37

:12

8:19

:12

9:01

:12

9:43

:12

10:2

5:12

11:0

7:12

11:4

9:12

12:3

1:12

13:1

3:12

13:5

5:12

14:3

7:12

Temperature in 6-0223 April 2012 to 4 April 2012

shaded area=recommended range

Page 30: IAQ Building 6 Basement

April 3 to April 4

1015202530354045505560

13:2

5:12

14:0

6:12

14:4

7:12

15:2

8:12

16:0

9:12

16:5

0:12

17:3

1:12

18:1

2:12

18:5

3:12

19:3

4:12

20:1

5:12

20:5

6:12

21:3

7:12

22:1

8:12

22:5

9:12

23:4

0:12

0:21

:12

1:02

:12

1:43

:12

2:24

:12

3:05

:12

3:46

:12

4:27

:12

5:08

:12

5:49

:12

6:30

:12

7:11

:12

7:52

:12

8:33

:12

9:14

:12

9:55

:12

10:3

6:12

11:1

7:12

11:5

8:12

12:3

9:12

13:2

0:12

14:0

1:12

14:4

2:12

Relative Humidity in % in 6-0223 April 2012 to 4 April 2012

shaded area=reccomended range

Page 31: IAQ Building 6 Basement

April 4

• The Facilities and Security Supervisor for Chemistry is asked to arrange with Facilities to have the volume of supply air tested.

Page 32: IAQ Building 6 Basement

April 8, Students Meet with Dean For Graduate Education

• 4 people report chronic fatigue, balance impairment, vertigo, CNS infections, pneumonia, sinus infections

• “Went unreported by EHS, despite air quality complaint SOP mandating reporting of this to MIT Medical”

• “Students notifying occupational health themselves”• “Months without any response to health concerns”• “Randomly removing air filters; high mold levels led to

mandatory HEPA filter installations, residual flooding”• “No tests or quantification of mold levels, allergens, air

quality, despite repeated requests”

Page 33: IAQ Building 6 Basement

Air Flow in Basement

Room No. Set Point Actual6-022 120 cfm 140 cfm

6-022B 320 cfm 130 cfm6-026 280 cfm 426 cfm6-030 160 cfm 152 cfm

SUPPLY AIR

Page 34: IAQ Building 6 Basement

Ongoing Issues

• Complaints of rust in the water led to a request to have the water tested…

• A second round of water testing involving glycols…

Page 35: IAQ Building 6 Basement

Lessons Learned

• Make sure researchers know who to contact if they are having trouble getting facilities to fix something.

• At the first report of “medical issues” refer to MIT Medical, and give MIT Medical a heads-up

• Communication is key!!!