I nternational S coping S tudy Accelerator Working Group Summary Report

31
March 29, 2007 IDS: CERN - Zisman International Scoping Study Accelerator Working Group Summary Report Michael S. Zisman Center for Beam Physics Accelerator & Fusion Research Division Lawrence Berkeley National Laboratory International Design Study Meeting–CERN March 29, 2007

description

I nternational S coping S tudy Accelerator Working Group Summary Report. Michael S. Zisman C enter for B eam P hysics Accelerator & Fusion Research Division Lawrence Berkeley National Laboratory International Design Study Meeting–CERN March 29, 2007. Introduction. - PowerPoint PPT Presentation

Transcript of I nternational S coping S tudy Accelerator Working Group Summary Report

Page 1: I nternational  S coping  S tudy  Accelerator Working Group Summary Report

March 29, 2007 IDS: CERN - Zisman

International Scoping Study Accelerator Working Group

Summary Report

Michael S. ZismanCenter for Beam Physics

Accelerator & Fusion Research DivisionLawrence Berkeley National Laboratory

International Design Study Meeting–CERNMarch 29, 2007

Page 2: I nternational  S coping  S tudy  Accelerator Working Group Summary Report

March 29, 2007 IDS: CERN - Zisman 2

Introduction

•NuFact06 marked formal culmination of the ISS— completed a one-year exploration of an optimized Neutrino

Factory designo carried out by international team (participants from Europe, Japan, U.S.)

— goal: study alternative configurations to arrive at baseline specifications for a system to pursue further

•Work was quite successful— but, we have not done everything

o final report not yet completed, but “abridged version” is now available

•Communications via NF-SB-ISS-ACCELERATOR e-mail list— worked well and should be continued for IDS

Page 3: I nternational  S coping  S tudy  Accelerator Working Group Summary Report

March 29, 2007 IDS: CERN - Zisman 3

Neutrino Factory Ingredients• Proton Driver

— primary beam on production target

• Target, Capture, Decay— create , decay into

• Bunching, Phase Rotation— reduce E of bunch

• Cooling— reduce transverse emittance

• Acceleration— 130 MeV 20–40 GeV

• Decay Ring— store for ~500 turns; long

straight section

“Front End”

ISS Baseline

Page 4: I nternational  S coping  S tudy  Accelerator Working Group Summary Report

March 29, 2007 IDS: CERN - Zisman 4

NF Design: Driving Issues•Constructing a muon-based NF is challenging

— muons have short lifetime (2.2 s at rest)o puts premium on rapid beam manipulations

– requires high-gradient NCRF for cooling (in B field)– requires presently untested ionization cooling

technique– requires fast, large acceptance acceleration system

— muons are created as a tertiary beam (p)o low production rate

– target that can handle multi-MW proton beamo large muon beam transverse phase space and large energy spread – high acceptance acceleration system and decay ring

— neutrinos themselves are a quaternary beamo even less intensity and “a mind of their own”

Page 5: I nternational  S coping  S tudy  Accelerator Working Group Summary Report

March 29, 2007 IDS: CERN - Zisman 5

Challenges•Challenges go well beyond those of standard beams— developing solutions requires substantial R&D effort

o R&D should aim to specify: – expected performance, technical feasibility/risk, cost

(matters!)

We must do experiments and build components. Paper studies are not enough!

Page 6: I nternational  S coping  S tudy  Accelerator Working Group Summary Report

March 29, 2007 IDS: CERN - Zisman 6

Accelerator WG Organization

•Accelerator Working Group program managed by “Accelerator Council”— R. Fernow, R. Garoby, Y. Mori, R. Palmer, C. Prior, M.

Zisman— met mainly by phone conference

•Aided by Task Coordinators— Proton Driver: R. Garoby, H. Kirk, Y. Mori, C. Prior— Target/Capture: J. Lettry, K. McDonald— Front End: R. Fernow— Acceleration: S. Berg, Y. Mori, C. Prior— Decay Ring: C. Johnstone, G. Rees

Page 7: I nternational  S coping  S tudy  Accelerator Working Group Summary Report

March 29, 2007 IDS: CERN - Zisman 7

Accelerator Study Aims•Study alternative configurations; arrive at baseline specifications for a system to pursue √— examine both cooling and no-cooling options

•Develop and validate tools for end-to-end simulations of alternative facility concepts (not completed)— correlations in beam and details of distributions have significant

effect on transmission at interfaces (muons have “memory”)— simulation effort ties all aspects together

•Develop R&D list as we proceed √— identify activities that must be accomplished to develop confidence

in the community that we have arrived at a design that is:o credibleo cost-effective

— until construction starts, R&D is what keeps the effort alive

Page 8: I nternational  S coping  S tudy  Accelerator Working Group Summary Report

March 29, 2007 IDS: CERN - Zisman 8

Accelerator Study Approach•Did trade-off studies including designs from all regions— also scientists from all regions (but uncorrelated)

o ensured common understanding of, and buy-in for, the results— examined possibilities to choose the best ones

•This “regional mixing” was actively fostered— recommend this approach continue during IDS phase

•ISS was partly a team-building exercise— number of Neutrino Factory facilities likely built worldwide 1

– voluntarily working together toward a single design increases odds of some facility being built

— for AWG, this worked pretty well

Page 9: I nternational  S coping  S tudy  Accelerator Working Group Summary Report

March 29, 2007 IDS: CERN - Zisman 9

Proton Driver Questions•Optimum beam energy √

— depends on choice of target— fairly broad

•Optimum repetition rate √ — depends on target and downstream RF systems

o find that 50 Hz is reasonable compromise for cases studied

•Bunch length trade-offs √

•Hardware options √— examined candidate machine types for 4 MW operation

o FFAG (scaling and/or non-scaling)o Linac (SPL and/or Fermilab approach)o Synchrotron (J-PARC and/or AGS approach)

— ultimately decided to specify only parameters, not hardware

Page 10: I nternational  S coping  S tudy  Accelerator Working Group Summary Report

March 29, 2007 IDS: CERN - Zisman 10

Optimum Energy

•Optimum (calculated) energy for high-Z targets is broad, but drops at low-energy

–: 6 – 11 GeV

+: 9 – 19 GeV

We adopted 10 ± 5 GeV as representative range

Page 11: I nternational  S coping  S tudy  Accelerator Working Group Summary Report

March 29, 2007 IDS: CERN - Zisman 11

Bunch Length Dependence•Investigated by Gallardo et al. using Study 2a channel— decrease starts beyond 1 ns bunch length

o 1 ns is preferred, but 2-3 ns is acceptable– such short bunches harder to achieve at low beam energy

— stronger sensitivity to bunch length than seen in Study 2o not yet understood in detail (different phase rotation and bunching)

Page 12: I nternational  S coping  S tudy  Accelerator Working Group Summary Report

March 29, 2007 IDS: CERN - Zisman

FFAG Proton Driver

180 MeV Hˉ linac

Achromatic Hˉ collimation line

3 GeV RCS boostermean radius = 63.788 m

n=5, h=5

10 GeV non-scaling FFAGn = 5, h = 40, radius = twice booster radius = 127.576 m

Bunch compression for 5 bunches:

Longitudinal bunch area = 0.66 eV-s

1.18 MV/turn compresses to 2.1 ns rms

Add h = 200, 3.77 MV/turn for 1.1 ns rms

Rees, Prior

Works for n = 3 also

Page 13: I nternational  S coping  S tudy  Accelerator Working Group Summary Report

March 29, 2007 IDS: CERN - Zisman 13

SPL Scheme•Proposed scheme increases energy to 5 GeV

— requires accumulator and compressor rings to deliver baseline bunch parameters

o delivery system for 2 ns bunches has been worked out

Page 14: I nternational  S coping  S tudy  Accelerator Working Group Summary Report

March 29, 2007 IDS: CERN - Zisman 14

Target/Capture/Decay

•Optimum target material √— studied by Fernow, Gallardo, Brooks, Kirk

o targets examined: C (5, 24 GeV); Hg (10, 24 GeV)– re-interactions included

o Hg (24 GeV) is nominal Study 2/2a “benchmark” case

•Target limitations for 4 MW operation— consider bunch intensity, spacing, repetition rate √— limits could come from target...or from beam dump

•Superbeam vs. Neutrino Factory trade-offs — horn vs. solenoid capture √

o can one solution serve both needs?

Page 15: I nternational  S coping  S tudy  Accelerator Working Group Summary Report

March 29, 2007 IDS: CERN - Zisman 15

Target Material Comparisons (1)Results from H. Kirk

Page 16: I nternational  S coping  S tudy  Accelerator Working Group Summary Report

March 29, 2007 IDS: CERN - Zisman 16

Target Material Comparisons (2)

•Results— Hg at 10 GeV looks best thus far

•Power handling capability of solid target materials is still an issue— R&D on solid target options is in progress (Bennett)— C at 4 MW still looks hard

o would require frequent target changes

•Can required short bunches be produced at E ~ 5 GeV?— important for Neutrino Factory but not for Superbeam

•Results all based on MARS predictions— need experimental data to validate

Page 17: I nternational  S coping  S tudy  Accelerator Working Group Summary Report

March 29, 2007 IDS: CERN - Zisman 17

Baseline Target System•Neutrino Factory solenoid capture system

Tapers from 20 T, 15 cm to 1.75 T, 60 cm over 20 m

Page 18: I nternational  S coping  S tudy  Accelerator Working Group Summary Report

March 29, 2007 IDS: CERN - Zisman 18

Front End•Compare performance of existing schemes (KEK, CERN, U.S.-FS 2a)— use common proton driver and target configuration(s) √— consider possibility of both signs simultaneously √— final conclusions require cost comparisons, which will come later

•Evaluate implications of reduced VRF √— take Vmax = 0.75 Vdes and 0.5 Vdes

•Evaluated trade-offs between cooling and downstream acceptance √

•Look at polarization issues √— still some issues left if bow-tie ring option considered

Page 19: I nternational  S coping  S tudy  Accelerator Working Group Summary Report

March 29, 2007 IDS: CERN - Zisman 19

Cooling Channel Comparisons (1)

•Palmer has looked at all current designs— FS2, FS2a, CERN, KEK channels

•Performance of FS2a channel is best— includes benefits of both sign muons— only FS2a (with both signs) meets NuFact99 goal of 1021 useful

decays per year

Page 20: I nternational  S coping  S tudy  Accelerator Working Group Summary Report

March 29, 2007 IDS: CERN - Zisman 20

Cooling vs. Acceptance•Evaluated trade-offs between cooling efficacy and downstream acceptance (Palmer)— increasing from 30 to 35 mm-rad halves the required length

of cooling channelo at 45 mm-rad, no cooling needed

•At present, A 30 mm-rad seems practical limit

Page 21: I nternational  S coping  S tudy  Accelerator Working Group Summary Report

March 29, 2007 IDS: CERN - Zisman 21

Acceleration•Compared different schemes on an even footing

— RLA, scaling FFAG, non-scaling FFAGo considered implications of keeping both sign muonso must consider not only performance but relative costs

— brought scaling FFAG design to same level as non-scaling design

•Look at implications of increasing acceptance — transverse and longitudinal

o acceptance issues have arisen in non-scaling case– leading to exploration of a revised acceleration scenario

Page 22: I nternational  S coping  S tudy  Accelerator Working Group Summary Report

March 29, 2007 IDS: CERN - Zisman 22

Non-scaling FFAGs (1)

•Discovered dynamics problem related to dependence of revolution time on transverse amplitude (Machida, Berg)— larger amplitudes and bigger angles give longer path length

o different flight times for different amplitudes lead to acceleration problems in FFAG– large-amplitude particles slip out of phase with RF and are

not fully accelerated

•Present conclusions— 30 mm-rad probably possible, but is already a stretch— cascading FFAG rings is harder than anticipated

o two in series probably possible, but three in series looks iffy

Page 23: I nternational  S coping  S tudy  Accelerator Working Group Summary Report

March 29, 2007 IDS: CERN - Zisman 23

Decay Ring•Design implications of final energy (20 vs. 40 GeV) √— 25 and 50 GeV?

•Optics requirements vs. beam emittance √— arcs, injection and decay straight sections

•Implications of keeping both sign muons √

•Implications of two simultaneous baselines √

•Both triangle and racetrack rings have been examined— recently started to re-examine “bow-tie” configuration

Page 24: I nternational  S coping  S tudy  Accelerator Working Group Summary Report

March 29, 2007 IDS: CERN - Zisman 24

Decay Ring Geometry (1)•Triangle rings would be stacked side by side in tunnel

— one ring stores + and one ring stores – o permits illuminating two detectors with (interleaved) neutrinos and antineutrinos simultaneously

Rees

Page 25: I nternational  S coping  S tudy  Accelerator Working Group Summary Report

March 29, 2007 IDS: CERN - Zisman 25

Decay Ring Geometry (2)•Racetrack rings have two long straight sections that can be aimed at a single detector site— could alternate storing + and – in one ring, or store both together— second ring, with both particles, would be used for another

detector site

•More flexibility than triangle case, but probably more expensive— can stage the rings if one detector is ready first— can point to two sites without constraints

Johnstone

Page 26: I nternational  S coping  S tudy  Accelerator Working Group Summary Report

March 29, 2007 IDS: CERN - Zisman 26

Decay Ring Geometry (3)•Triangle ring more efficient than racetrack ring for two suitable detector sites — for a single site, or sites in same direction from ring, racetrack

is better

Depth may be an issue for some sites, especially for racetrack with long baseline

Page 27: I nternational  S coping  S tudy  Accelerator Working Group Summary Report

March 29, 2007 IDS: CERN - Zisman 27

R&D Program•Neutrino Factory R&D programs under way in

— Europe under the auspices of BENE and UKNF— Japan, NuFact-J supported by university, and some U.S.-Japan,

fundso substantial scaling-FFAG results have come from this source

— U.S. under the auspices of the NFMCC (DOE + NSF supported)

•Several international experiments in progress— MERIT— MICE— EMMA (UK), electron model to study non-scaling FFAG

performance

•Proposals in preparation for new international efforts— high-power target test facility (CERN), to provide dedicated test-

bed for next generation of high-power targets

Page 28: I nternational  S coping  S tudy  Accelerator Working Group Summary Report

March 29, 2007 IDS: CERN - Zisman 28

Decisions on Baseline (1)•Proton Driver

— specified parameters, not designo implicitly assumes liquid-metal target

Parameter Value

Energy (GeV) 10 ± 5

Beam power (MW) 4

Repetition rate (Hz) 50

No. of bunch trains 3,5a)

Bunch length, rms (ns)

2 ± 1

Beam durationb) (s) 40

a)Values ranging from 1–5 possibly acceptable.b)Maximum spill duration for liquid-metal target.

Page 29: I nternational  S coping  S tudy  Accelerator Working Group Summary Report

March 29, 2007 IDS: CERN - Zisman 29

Decisions on Baseline (2)•Target

— assume Hg target; look at Pb-Bi also

•Front End— bunching and phase rotation

o use U.S. Study 2a configuration— cooling

o include in baseline; use U.S. Study 2a configuration— keep both signs of muons

o “waste not, want not”

•Acceleration— used mixed system

o linac, dog-bone RLA(s), FFAGs

Page 30: I nternational  S coping  S tudy  Accelerator Working Group Summary Report

March 29, 2007 IDS: CERN - Zisman 30

Decisions on Baseline (3)•Decay Ring

— adopt racetracko keep alive triangle as alternative

– depends on choice of source and baselineso energy 20 to 50 GeV

Page 31: I nternational  S coping  S tudy  Accelerator Working Group Summary Report

March 29, 2007 IDS: CERN - Zisman 31

Summary•Made good progress toward consensus on a single optimized Neutrino Factory scheme

•Must continue to articulate need for an adequately-funded accelerator R&D program— being encouraged to do this in an international framework

o IDS is one ingredient— synergy with Muon Collider R&D is an advantage (in U.S.)

•It was a privilege to work on the ISS with such a talented and dedicated group— my thanks to:

o Program Committee (Dornan, Blondel, Nagashima/Long)o Accelerator Council and task leaders (slide 6)o all members of Accelerator Group (see NF-SB-ISS-ACCELERATOR list)