I I Reduction Strategy Annual Report 2012
-
Upload
donaldfahey -
Category
Documents
-
view
214 -
download
0
Transcript of I I Reduction Strategy Annual Report 2012
8/9/2019 I I Reduction Strategy Annual Report 2012
http://slidepdf.com/reader/full/i-i-reduction-strategy-annual-report-2012 1/103
8/9/2019 I I Reduction Strategy Annual Report 2012
http://slidepdf.com/reader/full/i-i-reduction-strategy-annual-report-2012 2/103
Table of Contents
1. Background
1.1. South
East
Collector
Trunk
Sewer
Conditions
of
Approval ...........................3
1.2. Purpose and Need of the Annual Report......................................................4
1.3. Comments and Feedback Received..............................................................4
2. Key Program Activities and 2011 Accomplishments
2.1. Inflow and Infiltration Reduction Strategy...................................................5
2.1.1. Summary of program activities and accomplishments ....................... 5
2.1.2. Pilot projects ....................................................................................... 12
2.1.3. Reporting of inflow and infiltration reduction to date....................... 13
2.1.4. Local municipal participation and collaboration ................................ 13
2.2. Long Term
Water
Conservation
Strategy....................................................15
2.2.1. Summary of program activities and accomplishments ..................... 15
2.2.2. Reporting of water saved to date ....................................................... 24
2.2.3. Local municipal participation and collaboration – billing data........... 24
2.2.4. Updated water demand by sector...................................................... 24
2.2.5. Updated Long Term Water Strategy targets ...................................... 26
3. 2012 Planned Deliverables and Outlook
3.1. Inflow and Infiltration Reduction Strategy ................................................27
3.1.1. Summary of 2012 Goals and Targets.................................................. 27
3.1.2. Mitigation plans ................................................................................. 30
3.2. Long Term Water Conservation Strategy ...................................................33
3.2.1. Summary of 2012 Goals and Targets.................................................. 33
3.2.2. Revised tactics and targets ................................................................ 38
3.2.3. Mitigation plans ..................................................................................38
List of Tables
Table 2.1 Inflow Infiltration Reduction Strategy 2011 Program Activities and
Accomplishments
Table 2.2 Long Term Water Conservation Strategy 2011 Key Deliverables and
Accomplishments Table 2.3 2010 Non‐Revenue Water by Municipality
Table 2.4 2010 Infrastructure Leakage Index by Municipality
Table 2.5 2010 Water Demand by Sector
Table 3.1 Inflow Infiltration Reduction Strategy 2012 Goals
Table 3.2 Long Term Water Conservation Strategy 2012 Goals and Targets
8/9/2019 I I Reduction Strategy Annual Report 2012
http://slidepdf.com/reader/full/i-i-reduction-strategy-annual-report-2012 3/103
Long Term Water Conservation Strategy and Inflow and Infiltration Strategy 2
Annual Report dated March 31, 2012
Appendices
Appendix A: Intra Basin Transfer Summary 2011 ...................................................... 40
Appendix B: Quantified Catchments for Inflow and
Infiltration
Reduction............................................................................. 42
Appendix C: Inflow and Infiltration Reduction Program
Annual Report to Council....................................................................... 59
Appendix D: Sanitary Sewer System Inspection, Testing
and Acceptance Guideline ..................................................................... 63
Appendix E: Long Term Water Conservation Strategy
Annual Report to Council....................................................................... 86
8/9/2019 I I Reduction Strategy Annual Report 2012
http://slidepdf.com/reader/full/i-i-reduction-strategy-annual-report-2012 4/103
Long Term Water Conservation Strategy and Inflow and Infiltration Strategy 3
Annual Report dated March 31, 2012
1. Background
1.1. Southeast Collector Trunk Sewer Conditions of Approval
The Regional
Municipality
of
York
is
currently
constructing
the
Southeast
Collector
Trunk
Sewer (SEC). The SEC is a 15 kilometre, tunnelled sanitary trunk sewer that starts in the
community of Box Grove in the Town of Markham and ends near the intersection of
Finch Avenue and Valley Farm Road in the City of Pickering. This capital project is vital to
service provincially‐approved growth to the year 2031. On March 31, 2010, the Minister
of the Environment of Ontario (MOE) approved the Individual Environmental
Assessment (IEA) for the project and added a number of stringent conditions of
approval.
Section 8 of the Minister’s conditions refers to a Water Efficiency and Inflow and
Infiltration Reduction Monitoring Strategy . The conditions pertinent to this section and
their requirements
are
as
follows:
• Condition 8.1 requires that a Water Conservation and Efficiency Strategy for water
and wastewater flows into the SEC be prepared.
• Condition 8.2 states specifically that York Region is required to develop an Inflow and
Infiltration Reduction Strategy (the Strategy), which “shall include a program for the
reduction of inflow and infiltration by The Regional Municipality of York to the Southeast
Collector (SEC) Trunk Sewer from its and its lower tier municipalities’ sewage systems.
This program shall include reduction priorities, targets, timelines, tactics and initiatives,
and the associated costs to implement these.”
• Condition
8.4
requires
York
Region
to
complete
a review
of
best
‐in
‐class
infiltration
and inflow (I/I) reduction programs, initiatives, strategies, and tactics adopted by other
jurisdictions.
York Region has ongoing programs in water conservation and I/I reduction that were
relied upon as mitigating measures to support developing the new SEC. Water
conservation and reducing I/I have been important parts of the Region’s servicing
considerations since the first water and wastewater master plan was developed in 1997.
The York Durham Sewage System (YDSS) Master Plan, as subsequently updated,
specifically identified water conservation and extraneous flow reduction as a significant
design consideration for all YDSS projects.
Although advances in water conservation, water use efficiency, and I/I reduction
measures have been significant, as detailed in subsequent sections, a considerable
amount of work is required to continue to meet the Minister’s conditions. In summary,
the approval of the SEC is subject to stringent conditions based upon the following
overall directions:
8/9/2019 I I Reduction Strategy Annual Report 2012
http://slidepdf.com/reader/full/i-i-reduction-strategy-annual-report-2012 5/103
Long Term Water Conservation Strategy and Inflow and Infiltration Strategy 4
Annual Report dated March 31, 2012
1. A compliance monitoring and reporting program is to be established to document
that the project will be undertaken and will continue to be operated in
conformance with the commitments made by the Region in the SEC IEA.
2. York Region is required to establish a stakeholder advisory committee, consisting
of representatives
from
local
and
Regional
municipalities,
agencies,
environmental
groups, and residents within three months of approval of the SEC IEA to enable
ongoing liaison between the community and the Region during the construction
period. The Southeast Collector Advisory Committee (SeCAC) was formed in April
2010 to meet this requirement.
3. Review of best‐in‐class water conservation and efficiency measures and
development of I/I reduction strategies are to be completed in conjunction with
York Region and the local municipalities. It is to be independently peer reviewed,
presented to the advisory committee, submitted to the MOE, implemented,
monitored and reported on annually to the MOE.
4. A performance management plan will be developed and submitted to the SeCAC
and the MOE to document performance targets for improvements to water
conservation, efficiency, and reductions in I/I.
1.2.1. Purpose and Need of the Annual Report
The purpose of this report is to provide the first annual update on progress made
towards implementation of the Long Term Water Conservation Strategy (LTWCS) and
the Inflow and Infiltration Reduction Strategy (I‐I Reduction Strategy). Where targets
have
not
been
met,
mitigation
plans
are
identified
to
implement
enhanced
initiatives
in
order to meet the targets, including the resources available. This fulfills the
requirements as outlined in the conditions of approval for the Southeast Collector Trunk
Sewer Individual Environmental Assessment.
1.3.2. Comments and Feedback Received
On October 14, 2011, the Ministry of the Environment provided comments on the Long
Term Water Conservation Strategy and Inflow and Infiltration Reduction Strategy,
submitted on March 31, 2011. Comments received from the Ministry indicate York
Region demonstrated significant leadership in the creation of the Strategy. While some
technical issues and clarification remain, which can adequately be address through
future meetings between Ministry and Regional staff, the Strategy is a strong step
forward in supporting the Region’s long term water conservation and efficiency efforts.
The Ministry provided notification of satisfaction that the Strategy met the intent of
Condition 8. No additional feedback on the contents of the Strategy has been received.
8/9/2019 I I Reduction Strategy Annual Report 2012
http://slidepdf.com/reader/full/i-i-reduction-strategy-annual-report-2012 6/103
Long Term Water Conservation Strategy and Inflow and Infiltration Strategy 5
Annual Report dated March 31, 2012
2. Key Program Activities and 2011 Accomplishments
2.1. Inflow and Infiltration Reduction Strategy
2.1.1. Summary of
program
activities
and
accomplishments
This section outlines the Inflow and Infiltration Reduction Program activities and
accomplishments through 2011, see Table 2.1 for details. Highlights of 2011 include:
• In February and March 2011, Regional and local Councils approved the Inflow and
Infiltration Reduction Strategy
• The all‐pipe sewer model for the York Durham Sewage System has been developed
• Sewer inspection and assessment programs are currently underway on both
Regional and municipal levels
• Development‐funded
investigation
and
remediation
efforts
are
tied
to
advanced
wastewater servicing allocation to promote inflow and infiltration reduction efforts;
this opportunity has been provided to all Regional local municipalities.
• Through the Region’s Infrastructure Management Program, inflow and infiltration,
as a result of deterioration, is identified within Regional trunk sewers and
remediation works are planned
• The York Region Sanitary Sewer Inspection, Testing and Acceptance Guidelines (see
Appendix D) were finalized and distributed to the nine local municipalities in
October 2011; the next phase will address improving the standards for municipal
development including subdivision agreements and site plan approvals
8/9/2019 I I Reduction Strategy Annual Report 2012
http://slidepdf.com/reader/full/i-i-reduction-strategy-annual-report-2012 7/103
8/9/2019 I I Reduction Strategy Annual Report 2012
http://slidepdf.com/reader/full/i-i-reduction-strategy-annual-report-2012 8/103
Long Term Water Conservation Strategy and Inflow and Infiltration Strategy 7
Annual Report dated March 31, 2012
Goals/Objectives Status Review flow analysis software applications to ensureexisting Regional software can replicate dry/wet weatheranalysis procedures developed in recent reduction analysisefforts.
• Flow analysis software applications have been reviewed and the alin Infoworks is used to replicate wet/dry weather flows. See previou
Contingent upon execution of I/I agreement with localmunicipalities and developer groups, validate flow monitoringand analysis findings of developer funded initiatives andany pre‐post mitigation.
• Agreements have been approved between York Region, Towns of Richmond Hill and City of Vaughan and representative developer g
• Catchments are being analyzed• Work has been identified in some areas• Potential reductions will be calculated.• Various rehab works are underway.• Total reductions will be monitored through 2012-2013.• This opportunity has been provided to all Regional municipalities.
Program Component: Investigate and MDevelop Sanitary Sewer Evaluation Studies (SSES)inspection program and develop budgetary costing for anypriority areas from the 40, 2009‐2010 flow monitoringlocations.
• Process in place to perform flow data analysis in-house.• Data review and recommendations will occur in parallel with Region
pilots in order to leverage newly established best practices.
Commence remediation at nine priority catchment areasincluding 12 kilometre mainline, 162 point and surface
repairs, and rehabilitation of 444 manholes.
• Total of eight catchments being remediated (9th was removed from
• Two contracts released.•
Contract 1 has four catchments and is underway.• Contract 2 has four catchments and will start April 2012.
8/9/2019 I I Reduction Strategy Annual Report 2012
http://slidepdf.com/reader/full/i-i-reduction-strategy-annual-report-2012 9/103
Long Term Water Conservation Strategy and Inflow and Infiltration Strategy 8
Annual Report dated March 31, 2012
Goals/Objectives Status Establish remediation schedule for 2012‐2015 resulting fromcompleted investigation program.
• Local work is derived from inspection programs(CCTV data for 2011):− Vaughan 210 kilometres− Markham 132 kilometres− Newmarket 8.25 kilometres−
King 1.8 kilometres− Aurora 33 kilometres− Richmond Hill 130 kilometres
• Local municipality rehabilitation work in 2011 included:− Vaughan – 10 manholes relined− Whitchurch-Stouffville – 1.16 kilometres of sewer relined,
two manholes repaired− Markham – 1.22 kilometres of sewer relined− Newmarket – 1.76 kilometres of sewer relined,
five manholes repaired− Aurora – five kilometres of sewer relined,
20 manholes repaired/relined− Richmond Hill – two kilometres of sewer relined
• Regional CCTV inspection program for 2011 included
24.4 kilometres of trunk sewer.• Regional 2012 CCTV inspection program will inspect
25 kilometres of trunk sewer.• Inflow and infiltration within Regional trunk sewers has been identif
works are planned. Three major projects have started:− One relining project is under construction− Two rehabilitation projects are underway
• Approximately $45M is committed over the next 10 years for Regiorehabilitation across York Region’s entire system
• Local municipalities have started inspection and repair of lateral con− Aurora – 200 inspected− Whitchurch-Stouffville – four inspected and replaced− Newmarket - 80 inspected, 15 replaced− Vaughan - 477 inspected, 33 repaired− Richmond Hill – 177 inspected and repaired.
• Regional remediation schedule established.
• Local scheduling has been established and will be finalized through
• Audit program will further inform remediation schedules.
8/9/2019 I I Reduction Strategy Annual Report 2012
http://slidepdf.com/reader/full/i-i-reduction-strategy-annual-report-2012 10/103
8/9/2019 I I Reduction Strategy Annual Report 2012
http://slidepdf.com/reader/full/i-i-reduction-strategy-annual-report-2012 11/103
8/9/2019 I I Reduction Strategy Annual Report 2012
http://slidepdf.com/reader/full/i-i-reduction-strategy-annual-report-2012 12/103
8/9/2019 I I Reduction Strategy Annual Report 2012
http://slidepdf.com/reader/full/i-i-reduction-strategy-annual-report-2012 13/103
Long Term Water Conservation Strategy and Inflow and Infiltration Strategy 12
Annual Report dated March 31, 2012
2.1.2. Pilot Projects
Remediation Pilots
A comprehensive Sanitary Sewer Evaluation Study (SSES) of sanitary sewers and manholes located within local municipal systems was completed in 2010. Remediation projects were
proposed for the eight projects categorized as the highest priority catchments in terms of
inflow and infiltration. The remediation will include relining of approximately 12 kilometres of
mainline sewer, 162 point and surface repairs and 375 manhole rehabilitations.
The main goals of this pilot effort are:
• Reduction or removal of inflow and infiltration generated in local municipal sewers
• Demonstrate the effectiveness of various inflow and infiltration reduction technologies
in municipal sewers
• Determine/delineate tributary
areas
to
the
Regional
conveyance
and
treatment
systems
• To generate data regarding unit costs and effectiveness of various reduction
technologies
The project was divided into two construction phases. Phase 1 includes rehabilitation work of
four catchments in Aurora, Newmarket (2) and Richmond Hill. Commencement of this phase
began in January 2012. Phase 2 includes rehabilitation work of four catchments in East
Gwillimbury, Georgina (2) and Whitchurch‐Stouffville. Commencement of this phase will
begin in Q2 2012. Completion of the project is expected by Q4 2012
Developer Funded
Pilots
In May 2011, the Region, Town of Markham and Upper Unionville Inc. signed a tri‐party
agreement for reducing inflow and infiltration within the Town of Markham. Upper Unionville
Inc. agreed to reduce inflow and infiltration within the municipality in exchange for advanced
wastewater servicing allocation to support a new residential development at the northeast
corner of Kennedy Road and Sixteenth Avenue. An implementation plan for inflow and
infiltration reduction was developed by Upper Unionville Inc. and reviewed by the Region and
Town. Remediation works are currently underway. The Region will determine eligible capacity
for assignment based on proven inflow and infiltration reduction through remedial work
performed by the developer and reviewed by the Region and Town.
Opportunities include:
• Developer funding of the project at no cost to the Region or the Town
• Quick commencement of work with readily available resources from the developer
• Acquiring project experience that can be used for other inflow and infiltration reduction
projects in the Region
• A reduction in inflow and infiltration and peak sewer flows
8/9/2019 I I Reduction Strategy Annual Report 2012
http://slidepdf.com/reader/full/i-i-reduction-strategy-annual-report-2012 14/103
Long Term Water Conservation Strategy and Inflow and Infiltration Strategy 13
Annual Report dated March 31, 2012
This opportunity has been provided to all Regional local municipalities and resolutions have
also been passed in the Towns of Aurora and Richmond Hill and the City of Vaughan to
participate in the program.
2.1.3 Reporting of inflow and infiltration reduction to date
The Inflow and Infiltration Reduction Strategy recommended a target flow volume reduction
at the Southeast Collector Trunk Sewer of 71 million litres (ML) within a 24‐hour period under
a 25‐year storm event, with approximately 40 ML to be achieved through inflow and
infiltration reduction and the balance through water conservation initiatives by 2031.
In order to accurately quantify inflow and infiltration reduction, it is essential to install flow
meters near
the
location
of
remediation
works
and
collect
data
before
and
after
construction
to carry out comparison analysis. Regional staff have been co‐ordinating with local municipal
staff to install flow meters at required locations for all new remediation projects including the
pilot projects noted in this report and carrying out analysis on projects as flow data becomes
available. To date, three catchments have completed pre and post construction flow data to
enable staff to quantify the inflow and infiltration reduction. There are another eight
catchments whereby reduction efforts have occurred from 2008 to 2011 however the post
monitoring to quantify volumes is not complete and will not be available until later in 2012.
The reduction measured to date represents 2.5 per cent (see Table 2.1) of the 20 year
requirement, but this is significant when considering that the Strategy was only finalized in
March of 2011 and approved by the Ministry of the Environment in October 2011. To see
reductions this early in the process is very promising. Also, given that the Strategy was only
endorsed by Regional and local councils in 2011, the first year of resource planning and
budgeting truly occurred for 2012. It is expected that the program will pick up significant
momentum in this first full year of implementation and further and greater reductions can be
expected for the future.
Additional details on each of the quantified catchments are provided in the Appendix.
2.1.4. Local municipal participation and collaboration
York Region and the local municipalities are working collaboratively to implement the various
activities and resource the role of their respective organizations to help support program
implementation and have committed to identifying and addressing the financial requirements
for the 20‐year horizon and the long term period beyond.
8/9/2019 I I Reduction Strategy Annual Report 2012
http://slidepdf.com/reader/full/i-i-reduction-strategy-annual-report-2012 15/103
Long Term Water Conservation Strategy and Inflow and Infiltration Strategy 14
Annual Report dated March 31, 2012
Local municipal staff has been involved in development of the Inflow and Infiltration
Reduction Strategy through participation in the Water and Wastewater Steering Committee.
Local municipal councils have endorsed the strategy to fulfill the conditions of approval for
the Southeast Collector Trunk Sewer Individual Environmental Assessment.
Local municipality participation also included (see Table 2.1 for additional details):
• Ongoing inspection programs
• Rehabilitation work for sanitary sewers and manholes
• Lateral inspection and repair
• Utilizing the York Region Sanitary Sewer Inspection, Testing and Acceptance Guidelines
8/9/2019 I I Reduction Strategy Annual Report 2012
http://slidepdf.com/reader/full/i-i-reduction-strategy-annual-report-2012 16/103
Long Term Water Conservation Strategy and Inflow and Infiltration Strategy 15
Annual Report dated March 31, 2012
2.2 Long Term Water Conservation Strategy
2.2.1. Summary
of
program
activities
and
accomplishments
There are seven major program components outlined it the LTWCS. Table 2.2 provides a
breakdown of 2011 targets, status and variance for the tactics associated with each
component.
Rebates and Other Financial Instruments
Overall participation in the rebate programs exceeded the 2011 target, due to the strong
popularity of the toilet rebate program among single‐family homeowners. The majority of
staff time, resources and program budget went into managing this highly successful program.
To avoid budget constraints (i.e. overspending) other rebates were not widely marketed. In
2012, a review
of
the
toilet
rebate
program
components
and
targets
will
be
conducted
and
a
focus on increasing participation in multi‐unit and ICI sector rebates and capacity buy back
programs will be introduced.
New Development
York Region has engaged the development industry and local municipal partners to review
and improve incentive programs for water efficiency in low and high density new
developments. East Gwillimbury is currently developing a pilot program that will provide
extra servicing allocation for low density housing built to sustainable standards. The Town of
Markham is requiring all new high rise developments to participate in York Region’s
Sustainable Development
through
LEED
program.
Additional
refinement
of
the
minimum
requirements for sustainable new development programs and research into implementation
incentives and monitoring protocols was initiated in 2011.
Governance and Administration
Detailed implementation planning and reporting processes for the strategy were initiated in
2011. Cost/benefit evaluations of existing water efficiency and conservation programs and
recommendations about improvements and new program directions to maximize return on
investment is underway. An updated methodology for analysis and reporting of water
demand and water savings was established in 2011. The process will be refined with
additional data and analysis tools in 2012.
To facilitate ongoing stakeholder input into the plan’s implementation, an advisory
committee comprised of representatives from the public, community and industry groups and
multi‐cultural and First Nations organizations was established. This group will act as a forum
for ongoing advice and feedback on new and existing water conservation and efficiency
programs and projects. They will also act as community ambassadors to encourage greater
engagement from the sectors they represent.
8/9/2019 I I Reduction Strategy Annual Report 2012
http://slidepdf.com/reader/full/i-i-reduction-strategy-annual-report-2012 17/103
Long Term Water Conservation Strategy and Inflow and Infiltration Strategy 16
Annual Report dated March 31, 2012
Policies and By‐laws
York Region began development of several policy tools to encourage adoption of water
conservation and efficiency technologies across all sectors. Research to support the
development of voluntary water efficiency and conservation guidelines for new industrial,
commercial and institutional facilities in the Region is underway. A review of the Region’s
existing sustainability incentive programs for new development was started in 2011. Staff
have also participated in provincial sessions reviewing building code updates to advocate for
the inclusion of water efficiency and water reuse.
Pilot and Demonstration Projects
Several innovative pilot projects were started in 2011. A front yard makeover project in
Richmond Hill will showcase water‐efficient landscape practices, rainwater harvesting and lot
level stormwater
management
on
two
residential
lots.
An
irrigation
audit
and
retrofit
pilot
program with multi‐unit and ICI properties also started in 2011. Funding was secured to
partner with a local builder, a municipality and Conservation Authority on an expedited
approvals process for new developments using low impact development practices.
Regional‐Municipal System
The International Water Audit (IWA) process was initiated in 2011. Collection of water
demand billing data from the nine lower tier municipalities proved to be more challenging
that anticipated due to privacy concerns and differing local systems for data management. All
required data has been collected and the analysis process is well underway with an expected
completion of the technical review in Q2 of 2012. This information will enable the calculation
of the Infrastructure Leakage Index (ILI) and determining consumption by sector.
A process for the ongoing collection of billing data has now been established and a database
will be constructed by the Region to house and analyse data going forward. Preliminary
analysis of 2010 data is complete. Once analysis of 2009 and 2011 data is complete, revised
targets for per capita demand will be calculated.
Marketing, Education and Outreach
York Region continued to offer its successful education and outreach programs, including free
landscape assessments, water efficient landscaping workshops and the York Children’s Water
Festival.
Some program
elements
will
be
reviewed
in
2012
as
they
may
be
reaching
market
saturation. Revamped options will be identified as an outcome of that review.
The Region also began exploring opportunities to partner with other delivery groups such as
conservation authorities to provide an education program to schools and other youth
organizations.
8/9/2019 I I Reduction Strategy Annual Report 2012
http://slidepdf.com/reader/full/i-i-reduction-strategy-annual-report-2012 18/103
Long Term Water Conservation Strategy and Inflow and Infiltration Strategy 17
Annual Report dated March 31, 2012
An overall marketing, education strategy will be developed to link to all program components
and support the implementation of the Long Term Water Conservation Strategy.
8/9/2019 I I Reduction Strategy Annual Report 2012
http://slidepdf.com/reader/full/i-i-reduction-strategy-annual-report-2012 19/103
Long Term Water Conservation Strategy and Inflow and Infiltration Strategy 18
Annual Report dated March 31, 2012
Table 2.2
Long Term Water Conservation Stra
2011 Key Deliverables and Accomplish
LegendExisting and Continuing ProgramsNew Programs
Pilot and Demonstration Projects
Goal
ProgramComponents
Tactics Sector 2011 Target
Rebates and Other Financial InstrumeFree water audits ICI 10 facilities Nine
pendImplementation of capacity buy-back ICI 1.5 facilities 0
Front-loading clothes washer installations ICI 120 10 re
HET Toilet rebate ICI 6,240 19 to
8/9/2019 I I Reduction Strategy Annual Report 2012
http://slidepdf.com/reader/full/i-i-reduction-strategy-annual-report-2012 20/103
Long Term Water Conservation Strategy and Inflow and Infiltration Strategy 19
Annual Report dated March 31, 2012
Pre-rinse spray valve for commercial kitchens (programhas reached market saturation)
ICI 30 comm. kitchens 0
Water efficient furnace humidifier Single familyresidential
1,000 57 hu
Subsidized rain barrels Single familyresidential
4,000 2,778
Front-loading clothes washer installations Multi familyresidential
150 0
WaterSense Toilet rebate Single andmulti familyresidential
12,000 29,7816,34houseight
New Development Uptake - Commitment by developers to adopt standard Single family
residentialFive per cent 0
Eastdeveadditfor lo
susta
Efficient NewDevelopmentLow DensityTotal (SHIP orother)
Estimated number of units constructed to standard Single familyresidential
0 0
8/9/2019 I I Reduction Strategy Annual Report 2012
http://slidepdf.com/reader/full/i-i-reduction-strategy-annual-report-2012 21/103
Long Term Water Conservation Strategy and Inflow and Infiltration Strategy 20
Annual Report dated March 31, 2012
Uptake - Commitment by developers to adopt standard Multi familyresidential
~10 per cent 218 uthe pagreMarkdevestand
Regi
Efficient NewDevelopmentHigh Density(SustainableDevelopmentthrough LEED
or other)
Estimated number of units constructed to standard x 0
Review suitability of development charge credits forparticipating developers
Single andmulti familyresidential
Complete Q4 Asse
Develop detailed monitoring program Single andmulti familyresidential
Start and complete In pro
Governance and AdministrationDevelop multi-stakeholder advisory group and determinesuitable meeting schedule and protocols
all Full implementation In proRefe
Develop detailed implementation plans with full cost-benefitand ROI assessments
all Start In prNove
Asso
Develop measurement and reporting framework to meetannual reporting requirements
all Start In pro
Policies and By-laws
Create commercial industrial conservation and efficiencyguideline
ICI Start In proretain
Evaluate thefollowingagainst best-in-class
New development incentive programs (Review of SHIP andLEED programs)
Single andmulti-familyresidential
Start Workinduscond
8/9/2019 I I Reduction Strategy Annual Report 2012
http://slidepdf.com/reader/full/i-i-reduction-strategy-annual-report-2012 22/103
Long Term Water Conservation Strategy and Inflow and Infiltration Strategy 21
Annual Report dated March 31, 2012
Advocacy to encourage water efficiency and reuse inProvincial permit to take water and building code changes
all Start AttenengaOntaSuppconsOnta
Pilot and Demonstration Projects
Outdoor water use reduction pilot – target high water usersand irrigation systems
ICI and multifamilyresidential
Start• Develop projectplan with localmunicipal staff
Irrigaaudit
Water efficient demonstration landscape on residentialproperty in Richmond Hill (part of SustainableNeighbourhood Retrofit Action Plan project)
Single family Start
• project plan beingdeveloped withToronto and RegionConservation
Authority and Townof Richmond Hill
SustRetroHomwinnstarte
Expedited approvals process Single andmulti family
residential
Fundthe p
Watepartn Authmuni
Retrofit and showcase municipal facilities Start • Complete
inventory of newand/or retrofittedfacilities
• Confirm possiblepartnerships
Compand/o
Regional-Munic ipal System International Water Association (IWA) AuditILI = Infrastructure Leakage Index – annual audit by eachmunicipality
Start ConsBillinis cocolleongocomp
Process for collecting water consumption data Start Billinbeenongobeen
8/9/2019 I I Reduction Strategy Annual Report 2012
http://slidepdf.com/reader/full/i-i-reduction-strategy-annual-report-2012 23/103
Long Term Water Conservation Strategy and Inflow and Infiltration Strategy 22
Annual Report dated March 31, 2012
Monitoring and evaluation program Start Eastdraft WorkcommoveradeveDeve
repre2011Determine consumption by sector Start In pro
colleprelimstarte
Guidelines for retrofits of municipally owned buildings Start In prProprevieguide
Marketing, Education and OutreachWater Efficiency and Conservation Seminars andWorkshops
all 20 20 se
Free Individual Landscape Assessments and Advice Single andmulti familyresidential
1,000 821 v
Updated Youth Education Programs Start Met w Authand p
Children’s Water Festival 5,000 students 5,000partic
Ten-year marketing, education and outreach strategylinked to all program components
All Start ShorqualiTwo cons
Auth
geneOutreach through local groups All
8/9/2019 I I Reduction Strategy Annual Report 2012
http://slidepdf.com/reader/full/i-i-reduction-strategy-annual-report-2012 24/103
Long Term Water Conservation Strategy and Inflow and Infiltration Strategy 23
Annual Report dated March 31, 2012
2.2.2. Reporting on water saved to date
The Long Term Water Conservation Strategy identifies five‐year targets and timelines for total
water savings and residential per capita demand. The Strategy also sets out the annual participation rates and program implementation status necessary to meet these five‐year
targets.
The Water for Tomorrow water‐efficiency program is designed to provide the tools York
Region residents need to conserve water in the home, the garden and at work. Participation
in this program for 2011 is estimated to be saving 1.8 million litres of water per day (MLD).
This is on track to meet the Long Term Water Conservation Strategy target of 10 million litres
of water saved per day by 2016 through existing York Region led water conservation
programs and 3.4 million litres of water from new programs identified in the strategy.
Water savings estimates are based on participation rates in each of the programs and
industry standards and peer‐reviewed research studies on water savings attributable to
specific conservation and efficiency practices. Methodologies used for estimating water
saved were reviewed and revised by a consultant as part of the implementation planning for
the LTWCS. The bulk of the water savings is attributed to participation in the toilet rebate
programs. Over 29,000 toilets were replaced through the rebate program in 2011.
2.2.3. Local municipal participation and collaboration – water billing data
One of the main constraints identified in the Long Term Water Conservation Strategy was the
lack of access to water demand data collected from water meters as part of local municipal
water billing practices. The Strategy stated that “securing access to usable, consistent water
demand data is absolutely imperative for the effective execution and ongoing monitoring of
the Strategy.”
A number of challenges had to be overcome before a process of data sharing could begin. For
most municipalities in York Region, the water billing process was not designed to report
demand data in the format required for the purposes of measuring per capita usage. Nor was
the data collected in a consistent format across the Region. Some municipalities also had
privacy concerns around sharing information from their billing database. Regional staff
worked closely
with
each
of
the
nine
local
municipalities
to
review
water
billing
data
for
2010
and to develop a process to share data at regular intervals starting in 2012.
2.2.4. Updated water demand sector
Access to complete water demand data has enabled the Region to begin to develop a more
accurate breakdown of water demand by sector, including residential, industrial, commercial
8/9/2019 I I Reduction Strategy Annual Report 2012
http://slidepdf.com/reader/full/i-i-reduction-strategy-annual-report-2012 25/103
Long Term Water Conservation Strategy and Inflow and Infiltration Strategy 24
Annual Report dated March 31, 2012
and institutional and non‐revenue water. A certain amount of non–revenue water is
expected in municipal systems, shown by municipality in Table 2.3. Non‐revenue water is
water supplied, but not metered, for example water used for emergency services such as
firefighting, operational purposes such as proactive system maintenance flushing, loss due to
leaks, etc.
Table 2.3
2010 Non‐Revenue Water by Municipality
Municipality
2010 Percentage Non‐Revenue
Water
King 22%
East Gwillimbury
22%
Whitchurch‐Stouffville 16%
Georgina 13%
Aurora 8%
Newmarket 15%
Richmond Hill 5%
Markham 16%
Vaughan 17%
Total 15%
The performance
of
the
water
distribution
systems
is
measured
through
the
infrastructure
leakage index, which is a performance indicator of real water loss from the supply
network. Table 2.4 is the infrastructure leakage index by municipality as calculated based
on the data provided by the municipalities.
8/9/2019 I I Reduction Strategy Annual Report 2012
http://slidepdf.com/reader/full/i-i-reduction-strategy-annual-report-2012 26/103
8/9/2019 I I Reduction Strategy Annual Report 2012
http://slidepdf.com/reader/full/i-i-reduction-strategy-annual-report-2012 27/103
Long Term Water Conservation Strategy and Inflow and Infiltration Strategy 26
Annual Report dated March 31, 2012
2.2.5. Updated Long Term Water Strategy Targets
Per capita demand targets in the Strategy are based on previously limited available data and
assumptions from the Water and Wastewater Master Plans. The Strategy forecasted the
2011 residential water demand to be approximately 252 litres per person per day. Analysis
using water billing meter data readings along with updated population estimates show 2010
per capita residential demand is approximately 220 litres per person per day.
Further analysis of additional billing data will be conducted to confirm that the lower per
capita demand is accurate and not an anomaly for 2010. The impact of a lower per capita
demand will result in a new 2011 baseline for per capital residential water demand in York
Region and require strategy targets to be updated. The analysis and review will be completed
in 2012.
8/9/2019 I I Reduction Strategy Annual Report 2012
http://slidepdf.com/reader/full/i-i-reduction-strategy-annual-report-2012 28/103
Long Term Water Conservation Strategy and Inflow and Infiltration Strategy 27
Annual Report dated March 31, 2012
3. 2012 Planned Deliverables and Outlook
3.1.
Inflow and
Infiltration
Reduction
Strategy
3.1.1. Summary of Goals and Targets
This section outlines the Inflow and Infiltration Reduction Program goals and targets for 2012,
see Table 3. Highlights of 2012 include;
• Calibration of the all‐pipe sewage model for the York Durham Sewage System
• Prepare strategy, program components and equipment tender, purchase additional flow
monitors and continue/develop flow monitoring program
•
Update
to
the
public
communication
plan
based
on
strategy
development
on
private
side
inflow and infiltration
• Develop and present annual report for the Ministry of the Environment and Regional/local
councils
• Review Regional and municipal design and construction standards
Table 3.1 below provides a summary of all goals and targets for 2012.
8/9/2019 I I Reduction Strategy Annual Report 2012
http://slidepdf.com/reader/full/i-i-reduction-strategy-annual-report-2012 29/103
Long Term Water Conservation Strategy and Inflow and Infiltration Strategy 28
Annual Report dated March 31, 2012
Table 3.1
Inflow and Infiltration Reduction Strategy
2012 Goals
2012 Goals/Object ives Estimated Start
Program Component: Goals and Objectives
Finalize and calibrate all pipes hydraulic model. Model completed, calibrationongoing
Refine the detailed audit and measure procedures using data from 2011flow monitoring program, flow reduction achievements and outputs from thecalibrated all pipes model.
Q2 2012
Program Component: Monitor and Analyze Flow
Prepare equipment tender, purchase additional flow monitors and continuewith flow monitor installations and maintenance for monitors that wereidentified in the flow monitoring program (estimated cost $1.0M). Continuethe installation and maintenance of 100 audit basin flow monitors.
Q4 2012
Select locations, relocate and maintain short term flow monitors at the minibasins based on 2010 analysis of audit basins (estimated 30 flowmonitors).
Q4 2012
Complete short‐term post construction flow monitoring and data analysis ofthe nine pilot remediation projects and determine the actual flow reductionachieved by pre‐2012 remediation projects.
Q4 2012
Contingent upon execution of I/I agreement with local municipalities anddeveloper groups, validate flow monitoring and flow reduction analysis ofdeveloper funded initiatives
Ongoing
Program Component: Investigate and Mitigate
Complete Sanitary Sewer Evaluation Study (SSES) investigations and assessinspection results to validate I/I sources within the priority mini-basin sites(estimated budget $1.0M)
Q4 2012
Prioritize and budget short-term capital and maintenance programs forhighest priority mini basins resulting from SSES analysis.
Q4 2012
Establish procedures, policies and complete a private side full length lateralrehabilitation “pilot” project (estimated budget $500k).
Q3 2012
Complete the remediation of e priority catchments and commence flowmonitoring to determine success of flow mitigation.
Ongoing
8/9/2019 I I Reduction Strategy Annual Report 2012
http://slidepdf.com/reader/full/i-i-reduction-strategy-annual-report-2012 30/103
Long Term Water Conservation Strategy and Inflow and Infiltration Strategy 29
Annual Report dated March 31, 2012
Program Component: Development & Capital Projects
Based on the flow analysis results from new development monitoring
locations from 2011 monitoring, establish common wording for newsub‐division agreements that could include additional testing andacceptance criteria.
Q2 2012
Program Component: Financial Management
Review and refine the short and long-term funding requirements for Capitaland Operating program costs, based on works and costs/benefitscompleted to date.
Q3 2012
Investigate private property subsidy and grant programs for lateralrehabilitation, downspout and foundation drain removal, review alternatives,establish funding impacts and potential funding sources.
Q3 2012
Program Component: Communication
Update the public communication plan and develop new Region and localmunicipal I/I reduction program websites to include promotional andoutreach materials (i.e. describe grant programs, overall program status,basement flooding awareness etc.).
Ongoing
Industry focus group will meet annually to discuss guidelines andprocedures.
Ongoing
Program Component: Report I/I Reduction
Develop and present the annual Council Report describing program status,financial impacts and progress to date based on information received fromlocal municipalities.
Q4 2012
York Region Program Manager to prepare and submit an annual report
meeting the compliance requirements for the MOE describing I/I reductionachieved in previous year, re‐confirm and/or update reduction goals andtargets.
Q4 2012
Program Component: Continuous Improvement
Review permanent flow monitoring procedures and analysis procedures andenhance flow monitoring programs including defining requirement foradditional or enhanced flow monitors (i.e. different technologies)
Q2 2012
Develop a Region-wide climate change model to identify the impact ofchanging weather patterns on I/I, review impact climate change could haveon I/I targets.
Q4 2012
Review Regional and Municipal Design and Construction Standard andrevise criteria where required (i.e. recommend and implement new I/Idesign allowance based on 2011 analysis results).
Q4 2012
Implement new sewer use by‐laws as developed for local municipalities. Q1 2013
Review potential impacts and reporting requirements of Water Opportunities Act , 2010, as subordinate regulations are developed.
Q4 2012
8/9/2019 I I Reduction Strategy Annual Report 2012
http://slidepdf.com/reader/full/i-i-reduction-strategy-annual-report-2012 31/103
Long Term Water Conservation Strategy and Inflow and Infiltration Strategy 30
Annual Report dated March 31, 2012
3.1.2. Mitigation Plans
This section outlines the Inflow and Infiltration Reduction Program mitigation plans for 2012.
Key activities to be completed in 2012, subset to Table 3 include:
Completion of pilot projects for 8 catchments
• Based on the Sanitary Sewer Evaluation Study (SSES), eight catchment areas were
identified as high priority areas in terms of inflow and infiltration
• Remediation works included relining of approximately 12 kilometres of mainline sewer,
162 point and surface repairs and 375 manhole rehabilitations
• The project was divided into two construction phases
• Phase 1 includes rehabilitation work in four catchments in Aurora, Newmarket (2) and
Richmond Hill; Phase 1 works began in January 2012
• Phase 2 includes
rehabilitation
work
in
four
catchments
in
East
Gwillimbury,
Georgina
(2)
and Whitchurch‐Stouffville; Phase 2 works will begin in Q2 2012
• Completion of the project is expected in Q4 2012
Phase 2 of pilot projects
• Based on outcome from the first round of pilot projects, a second round of pilot projects
will begin in 2012
• Initially a total of 77 catchments were identified as meeting pilot project selection criteria
• This number was reduced to 26 catchments in which SSES inspection were conducted
• Eight catchments were selected as high priority areas for remediation in 2012
• With a second phase of potential pilot projects, other high priority areas will be reviewed
and evaluated for inclusion in the project; these areas include catchments in Aurora,
Markham, Newmarket and Vaughan.
Monitoring audit program
• Through 2012 to 2015, permanent flow monitoring devices will be installed to audit flows
throughout the Region and will leverage the 2008 to 2011 pilot monitoring program in
terms of equipment, data and standard practices
• The flow data collected on a permanent basis will help determine inflow and infiltration
volumes for audit and reporting purposes
Phase 2 of
the
new
development
guidelines
–
Inspection,
Testing
and
Acceptance
• As part of the ongoing commitment to the Strategy, the next phase of work will address
improved standards for municipal development including subdivision agreements and site
plan approvals
• Specific areas to be addressed include the control of inflow during construction and the
timing of connections prior to occupancy and/or full build out
• A consultant has been retained to assist with data collection and review in Q1 2012
8/9/2019 I I Reduction Strategy Annual Report 2012
http://slidepdf.com/reader/full/i-i-reduction-strategy-annual-report-2012 32/103
Long Term Water Conservation Strategy and Inflow and Infiltration Strategy 31
Annual Report dated March 31, 2012
Development funded pilot projects
• Four, tri‐party agreements have been approved within the Region with local municipalities
(Markham, Vaughan, Aurora and Richmond Hill) and developers. • Work to be completed following final stages of approval
• As work proceeds, validation will occur through flow monitoring in 2012 / 2013 / 2014
• Third party consultant retained to validate process
• Flow monitoring has started in four municipalities
• Remedial work has started in one municipality
Regional CCTV program
• Inspection for inflow and infiltration flow reduction is a component of the Regional and
local ongoing condition assessment and asset management programs
• The Region’s
current
closed
circuit
television
program
undertakes
inspection
of
the
trunk
sewer network on a 10‐year cycle, based on sewer condition rating
• In 2011, the closed circuit television program inspected a total of 23.9 kilometres of trunk
sewers and 0.5 kilometres of siphons
• In 2012 the program will be inspecting 25 kilometres of trunk sewers
• Annual inspections cover approximately 10 per cent of the trunk system
Funding of $5M beyond pilots for local works and/or reserve funds
• The Inflow and Infiltration Reduction Strategy funding model has been approved based on
the following key funding principles:
−
Set
rate
will
be
collected
at
both
the
local
and
Regional
level
as
identified
through
the
needs of the Strategy and as agreed to by the municipal partners. An initial funding
target of $100 million over 20 years has been established. This equates to an annual
investment of $5 million per year across the Region for inflow and infiltration reduction.
− The amount collected at the local level will be used to address priorities identified both
through the Strategy and as determined by each local municipality.
− The amount collected at the Regional level will be used to address Regional inflow and
infiltration priorities both at the Regional and local level.
− Allocation of Regional funds intended for use in the local systems will be managed and
allocated by a joint team with staff representatives from each municipality and the
Region. Funding will be prioritized based on the most effective application to achieve
the desired
inflow
and
infiltration
improvements
as
quickly
as
possible.
8/9/2019 I I Reduction Strategy Annual Report 2012
http://slidepdf.com/reader/full/i-i-reduction-strategy-annual-report-2012 33/103
Long Term Water Conservation Strategy and Inflow and Infiltration Strategy 32
Annual Report dated March 31, 2012
Funding of $2.87M for Regional sewer works in 2012
• Through the Region’s Infrastructure Management Program, inflow and infiltration issues
within the Regional trunk sewers are also identified and remediation works planned.
• Approximately $2.87M is required in 2012 for locations requiring remediation
• Approximately $45 million will be required over the next 10 years for Regional sewer
rehabilitation across the entire sewer system, including remediation and upgrades to the
existing South East Collector Trunk Sewer after completion of the new Southeast Collector
Trunk Sewer.
8/9/2019 I I Reduction Strategy Annual Report 2012
http://slidepdf.com/reader/full/i-i-reduction-strategy-annual-report-2012 34/103
Long Term Water Conservation Strategy and Inflow and Infiltration Strategy 33
Annual Report dated March 31, 2012
3.2. Long Term Water Conservation Strategy
3.2.1. Summary
of
Goals
and
Targets
Table 4 provides a detailed summary of the goals and targets for 2012. The Region will be
launching a number of new initiatives in 2012 as part of the implementation of the LTWCS.
Rebates and Financial Incentives
York Region will pilot and evaluate offering discount coupons to encourage the purchase of
water efficient landscape plants. The subsidized rain barrel program and the commercial
kitchen valve replacements will be discontinued in 2012 due to market saturation and in the
case of rain barrels, limited water savings.
New Development
Moving forward with the efficiency standards for new developments, Region staff will
develop a methodology for setting targets for uptake based on available information about
development rates in York Region. Monitoring protocols for assessing the water savings
associated with pilot implementation of the standards will put into place when new home
construction is completed.
Governance and Administration
The multi‐stakeholder advisory committee will meet approximately five times in 2012.
Optimization of programs including the development of implementation plans with cost‐
benefit analysis
for
components
of
the
LTWCS
is
ongoing
with
priority
areas
for
2102
identified as an analysis of existing incentive programs and outdoor water use reduction
programs.
Policies and By‐laws
The development standards and summer water conservation by‐laws will be evaluated
against best‐in‐class programs. Draft guidelines for efficiency and conservation by
commercial and industrial water users will be completed.
Pilot and Demonstration Projects
Several new pilots will begin in 2012. In the Industrial, Commercial and Institutional sector, a
plan and
supporting
partnerships
will
be
established
for
implementation
of
the
new
industrial, commercial and institutional conservation and efficiency guidelines; in the
residential sector, planning and partnership development will be initiated to support the
‘unlawning’ challenge and a new expedited approvals process for sustainable developments.
Educational materials and monitoring plans to showcase municipal facilities with sustainable
technologies will also be created.
8/9/2019 I I Reduction Strategy Annual Report 2012
http://slidepdf.com/reader/full/i-i-reduction-strategy-annual-report-2012 35/103
Long Term Water Conservation Strategy and Inflow and Infiltration Strategy 34
Annual Report dated March 31, 2012
Pilot programs that were started in 2011, including the Sustainable Neighbourhood Retrofit
Action Plan front yard makeover project in partnership with Toronto and Region Conservation
and the Industrial, Commercial and Institutional irrigation reduction pilot, will be completed
and evaluated in 2012.
Regional‐Municipal System
The International Water Association (IWA) audit will be completed in Q2 of 2012. The
outcomes will lead into the development of a leak detection program based on the identified
priority areas.
Full implementation of the billing data sharing process will begin in 2012, including
development of a specialized database for storage and analysis reporting.
Marketing, Education
and
Outreach
2012 will see evaluation of existing programs and expansion of some outreach programs.
Delivery of existing landscape assessments and workshops will continue through 2012.
Evaluation of the efficacy of these programs will be conducted as part of the optimization
review. New youth education programming will be developed in addition to the existing York
Children’s Water Festival event.
8/9/2019 I I Reduction Strategy Annual Report 2012
http://slidepdf.com/reader/full/i-i-reduction-strategy-annual-report-2012 36/103
Long Term Water Conservation Strategy and Inflow and Infiltration Strategy 35
Annual Report dated March 31, 2012
Table 3.2Long Term Water Conservation Strategy
2012 Goals and Targets
ProgramComponentsbased onbest-in-classreview
Tactics Sector 2011 2012
Rebates and Other Financial InstrumentsFree water audits ICI 10 facilities 10 facilities Implementation of capacitybuy-back
ICI 1.5 facilities 1.5 facilities
Front-loading clothes washerinstallations
ICI 120 120
HET Toilet rebate ICI 6,240 6,240Pre-rinse spray valve forcommercial kitchens(program has reachedmarket saturation)
ICI 30 comm.kitchens
0 comm. kitchens
Water efficient furnacehumidifier
Single familyresidential
1,000 1,000
Subsidized rain barrels Single familyresidential
4,000 0
Front-loading clothes washerinstallations
Multi familyresidential
150 150
Pilot and Evaluate coupondiscounts for water efficientplants
Single and multifamily residential
StartEvaluate
WaterSense Toilet rebate Single and multifamily residential
12,000 12,000
New DevelopmentUptake - commitment bydevelopers to adopt standard
Single familyresidential 5 per cent Evaluate reporting
and goal settingmethodology
Efficient NewDevelopmentLow DensityTotal (SHIP orother)
Estimated number of unitsconstructed to standard
Single familyresidential
0 0
Uptake - Commitment by
developers to adopt standard
Multi family
residential
~10 per cent Evaluate reporting
and goal settingmethodology
Efficient New
DevelopmentHigh Density(SustainableDevelopmentthrough LEEDor other)
Estimated number of unitsconstructed to standard
X X
Develop detail monitoringprogram
Single and multifamily residential
Start andcomplete
Complete
8/9/2019 I I Reduction Strategy Annual Report 2012
http://slidepdf.com/reader/full/i-i-reduction-strategy-annual-report-2012 37/103
Long Term Water Conservation Strategy and Inflow and Infiltration Strategy 36
Annual Report dated March 31, 2012
Implement monitoringprogram
Single and multifamily residential
Fullimplementation
Governance and Administration
Develop multi-stakeholderadvisory group anddetermine suitable meetingschedule and protocols
all Fullimplementation Fullimplementation
Develop detailedimplementation plans withfull cost-benefit and ROIassessments
all Start Ongoing
Develop measurement andreporting framework to meetannual reportingrequirements
all Start Fullimplementation
Policies and BylawsCreate commercial industrialconservation and efficiency
guideline
ICI Start Create draftguidelines
Summer water conservationby-law
all Start Evaluate thefollowingagainst best-in-class New development incentive
programsSingle and multi-family residential
Start Ongoing
Advocacy to encouragewater efficiency and reuse inprovincial permit to takewater and building codechanges
all Start Ongoing
Pilot and Demonstration Projects – budgeted $2.7 million over 10 yearsOutdoor water use reductionpilot – target high waterusers and irrigation systems
ICI Start
• Develop projectplan with localmunicipal staff
Complete Pilot
Implement commercialindustrial guidelines
ICI Start
• Develop projectplan• Confirm possiblepartnerships
Water efficient demonstrationlandscape on residentialproperty in Richmond Hill(part of SNAP project)
Single family Start
• Project planbeing developedwith TRCA andRichmond Hill
Ongoing• Complete gardendesigns and install
Unlawning challenge Single and multi-family residential
Start
• Develop projectplan• Confirm possiblepartnerships
8/9/2019 I I Reduction Strategy Annual Report 2012
http://slidepdf.com/reader/full/i-i-reduction-strategy-annual-report-2012 38/103
Long Term Water Conservation Strategy and Inflow and Infiltration Strategy 37
Annual Report dated March 31, 2012
Expedited approvals process Single and multi-family residential
Start • Confirm possiblepartnerships forpilot
implementation• Develop projectplan with localmunicipal staff
Retrofit and showcasemunicipal facilities
• Completeinventory of newand/or retrofittedfacilities
Start
• Confirm possiblepartnerships• Develop plan andpublic material withlocal municipalstaff
Document water/energy
savings outcomes
Start
• Develop plan andmethodology withlocal municipalstaff
IWA AuditILI = Infrastructure LeakageIndex – annual audit by eachmunicipality
Start Complete
Leak Reduction – addressresults of IWA audits
Start Prioritize areas forleakdetection/reductionDevelop programplan up to 20DMAs per yearILI <2
Process for collecting waterconsumption data
Start Start fullimplementation
Monitoring and evaluationprogram
Start Ongoing
Determine consumption bysector
Start Ongoing
Guidelines for retrofits ofmunicipally owned buildings
Start Draft guidelinescomplete
8/9/2019 I I Reduction Strategy Annual Report 2012
http://slidepdf.com/reader/full/i-i-reduction-strategy-annual-report-2012 39/103
Long Term Water Conservation Strategy and Inflow and Infiltration Strategy 38
Annual Report dated March 31, 2012
3.2.2. Revised Tactics and Targets
The toilet rebate program exceeded its target in 2011 due to the program’s popularity with
single‐family home owners. In 2012, the Region will evaluate that program against best‐in‐
class examples to assess the opportunities to change the incentive or potential participants and shift resources to other rebate programs. Promotional resources will also be shifted to
increase uptake of other rebate programs such as the humidifier rebate and the multi‐unit
and ICI toilet and washer rebates. In 2012 staff resources will also be allocated to promoting
the capacity buy‐back program to encourage implementation of audit recommendations.
The Region will also be revising the targets for uptake of the new development standards. It
is proving to be difficult to assess uptake as a percentage of total new development because
the Region does not have access to all site plans approved by lower tier municipalities. A new
methodology for setting targets will be indentified in 2012.
Marketing, Education and OutreachWater Efficiency and
Conservation Seminars andWorkshops
all 20 20
Free Individual Landscape Assessments and advice
Single and multi-family residential
1,000 Evaluate
Updated youth educationprograms
Start Ongoing
York Children’s WaterFestival
5,000 students 5,000 students
Ten-year marketing,education and outreachstrategy linked to all programcomponents
All Start
Implementation of priorityeducation programs basedon 10-year education andoutreach strategy results
All Start
Outreach through localgroups
All Start fullimplementation
Water Efficiency outreach tonew Canadians
Start fullimplementation
8/9/2019 I I Reduction Strategy Annual Report 2012
http://slidepdf.com/reader/full/i-i-reduction-strategy-annual-report-2012 40/103
Long Term Water Conservation Strategy and Inflow and Infiltration Strategy 39
Annual Report dated March 31, 2012
3.2.3. Mitigation Plans
Several existing programs are reaching market saturation and will be discontinued or
evaluated in 2012. Due to both a decline in popularity and its low cost effectiveness, the rain
barrel sales program will be discontinued. The landscape visit program has also seen a
decline in uptake. It will continue in 2012, however, the Region will be evaluating its
effectiveness and identify ways to increase its effectiveness. The commercial kitchen valve
replacement program has also reached market saturation and will be discontinued.
8/9/2019 I I Reduction Strategy Annual Report 2012
http://slidepdf.com/reader/full/i-i-reduction-strategy-annual-report-2012 41/103
Long Term Water Conservation Strategy and Inflow and Infiltration Strategy 40
Annual
Report
dated
March
31,
2012
Appendix A: Intra Basin Transfer
Summary 2011
8/9/2019 I I Reduction Strategy Annual Report 2012
http://slidepdf.com/reader/full/i-i-reduction-strategy-annual-report-2012 42/103
2011 Intra Basin Transfer Summary of Monthly Volumes
The
Regional
Municipality
of
York
is
submitting
the
information
below
in
accordance
with
the
Ministry of Natural Resources and Ministry of the Environment letter dated September 14,
2010, regarding “Successful Completion of Prior Notice and Consultation on The Regional
Municipality of York's proposal for an increased intra‐basin water transfer under the Great
Lakes Charter.”
As stipulated in the aforementioned letter, Condition f) requires York Region to monitor and
report monthly volumes of its intra‐basin transfer in the preceding calendar year. In
satisfaction of that condition, the following table lists total monthly volumes transferred from
the Lake Ontario watershed into the Lake Huron watershed with return flow to Lake Ontario:
2011 Monthly Intra-basin Transfer Volumes
BloomingtonYonge(m3)
AuroraSouthRes(m3) Total Volume Days
Average(MLD)
January 65046 483118 548,164 31 17.7
February 53788 420568 474,356 28 16.9
March 66415 511862 578,277 31 18.7
Apri l 64457 329965 394,422 30 13.1
May 60750 444156 504,906 31 16.3
June 76553 390203 466,756 30 15.6
July 66506 477022 543,528 31 17.5
August 65976 510665 576,641 31 18.6
September 67071 420876 487,947 30 16.3
October 57659 399208 456,867 31 14.7
November 56952 363512 420,464 30 14.0
December 66015 418496 484,511 31 15.6
Total 767,188 5,169,651 5,936,838 365 16.3
8/9/2019 I I Reduction Strategy Annual Report 2012
http://slidepdf.com/reader/full/i-i-reduction-strategy-annual-report-2012 43/103
Long Term Water Conservation Strategy and Inflow and Infiltration Strategy 42
Annual
Report
dated
March
31,
2012
Appen ix B: Quantified Catchments
for Inflow
and
Infiltration Reduction
8/9/2019 I I Reduction Strategy Annual Report 2012
http://slidepdf.com/reader/full/i-i-reduction-strategy-annual-report-2012 44/103
Long Term Water Conservation Strategy and Inflow and Infiltration Strategy 43
Annual
Report
dated
March
31,
2012
8/9/2019 I I Reduction Strategy Annual Report 2012
http://slidepdf.com/reader/full/i-i-reduction-strategy-annual-report-2012 45/103
Long Term Water Conservation Strategy and Inflow and Infiltration Strategy 44
Annual
Report
dated
March
31,
2012
8/9/2019 I I Reduction Strategy Annual Report 2012
http://slidepdf.com/reader/full/i-i-reduction-strategy-annual-report-2012 46/103
Long Term Water Conservation Strategy and Inflow and Infiltration Strategy 45
Annual
Report
dated
March
31,
2012
8/9/2019 I I Reduction Strategy Annual Report 2012
http://slidepdf.com/reader/full/i-i-reduction-strategy-annual-report-2012 47/103
Long Term Water Conservation Strategy and Inflow and Infiltration Strategy 46
Annual
Report
dated
March
31,
2012
8/9/2019 I I Reduction Strategy Annual Report 2012
http://slidepdf.com/reader/full/i-i-reduction-strategy-annual-report-2012 48/103
Long Term Water Conservation Strategy and Inflow and Infiltration Strategy 47
Annual
Report
dated
March
31,
2012
8/9/2019 I I Reduction Strategy Annual Report 2012
http://slidepdf.com/reader/full/i-i-reduction-strategy-annual-report-2012 49/103
Long Term Water Conservation Strategy and Inflow and Infiltration Strategy 48
Annual
Report
dated
March
31,
2012
8/9/2019 I I Reduction Strategy Annual Report 2012
http://slidepdf.com/reader/full/i-i-reduction-strategy-annual-report-2012 50/103
Long Term Water Conservation Strategy and Inflow and Infiltration Strategy 49
Annual
Report
dated
March
31,
2012
8/9/2019 I I Reduction Strategy Annual Report 2012
http://slidepdf.com/reader/full/i-i-reduction-strategy-annual-report-2012 51/103
Long Term Water Conservation Strategy and Inflow and Infiltration Strategy 50
Annual
Report
dated
March
31,
2012
8/9/2019 I I Reduction Strategy Annual Report 2012
http://slidepdf.com/reader/full/i-i-reduction-strategy-annual-report-2012 52/103
Long Term Water Conservation Strategy and Inflow and Infiltration Strategy 51
Annual
Report
dated
March
31,
2012
8/9/2019 I I Reduction Strategy Annual Report 2012
http://slidepdf.com/reader/full/i-i-reduction-strategy-annual-report-2012 53/103
Long Term Water Conservation Strategy and Inflow and Infiltration Strategy 52
Annual
Report
dated
March
31,
2012
8/9/2019 I I Reduction Strategy Annual Report 2012
http://slidepdf.com/reader/full/i-i-reduction-strategy-annual-report-2012 54/103
Long Term Water Conservation Strategy and Inflow and Infiltration Strategy 53
Annual
Report
dated
March
31,
2012
8/9/2019 I I Reduction Strategy Annual Report 2012
http://slidepdf.com/reader/full/i-i-reduction-strategy-annual-report-2012 55/103
Long Term Water Conservation Strategy and Inflow and Infiltration Strategy 54
Annual
Report
dated
March
31,
2012
8/9/2019 I I Reduction Strategy Annual Report 2012
http://slidepdf.com/reader/full/i-i-reduction-strategy-annual-report-2012 56/103
Long Term Water Conservation Strategy and Inflow and Infiltration Strategy 55
Annual
Report
dated
March
31,
2012
8/9/2019 I I Reduction Strategy Annual Report 2012
http://slidepdf.com/reader/full/i-i-reduction-strategy-annual-report-2012 57/103
Long Term Water Conservation Strategy and Inflow and Infiltration Strategy 56
Annual
Report
dated
March
31,
2012
8/9/2019 I I Reduction Strategy Annual Report 2012
http://slidepdf.com/reader/full/i-i-reduction-strategy-annual-report-2012 58/103
Long Term Water Conservation Strategy and Inflow and Infiltration Strategy 57
Annual
Report
dated
March
31,
2012
8/9/2019 I I Reduction Strategy Annual Report 2012
http://slidepdf.com/reader/full/i-i-reduction-strategy-annual-report-2012 59/103
Long Term Water Conservation Strategy and Inflow and Infiltration Strategy 58
Annual
Report
dated
March
31,
2012
8/9/2019 I I Reduction Strategy Annual Report 2012
http://slidepdf.com/reader/full/i-i-reduction-strategy-annual-report-2012 60/103
Long Term Water Conservation Strategy and Inflow and Infiltration Strategy 59
Annual
Report
dated
March
31,
2012
Appen ix C: Inflow and Infiltration
Reduction Program
Annual Report to Council
8/9/2019 I I Reduction Strategy Annual Report 2012
http://slidepdf.com/reader/full/i-i-reduction-strategy-annual-report-2012 61/103
Environmental Services Committee 1March 7, 2012
THE REGIONAL MUNICIPALITY OF YORK
Environmental Services CommitteeMarch 7, 2012
Report of the
Commissioner of Environmental Services
INFLOW AND INFILTRATION REDUCTION PROGRAM ANNUAL REPORT
1. RECOMMENDATIONS
It is recommended that:
1. The Regional Clerk circulate this report to the Clerks of the local municipalities andthe Director, Central Region, Ministry of the Environment.
2. PURPOSE
The purpose of this report is to update Regional Council on the Inflow and InfiltrationReduction Program and the annual report required by conditions of the Minister of theEnvironment as part of the approval of the Southeast Collector Trunk Sewer IndividualEnvironmental Assessment. York Region is the first Regional Municipality required bythe Ministry of the Environment to meet such unique and stringent conditions related toinflow and infiltration in Regional and local sewer systems.
3. BACKGROUND
The 2001 York Durham Sewage System Master Plan update specifically identifiedextraneous flow reduction as a significant design consideration for all York DurhamSewage System projects. Although advances in inflow and infiltration reduction have been significant to date, a considerable amount of additional work is now underway. InFebruary and March 2011, Regional and local Councils approved the Inflow andInfiltration Reduction Strategy that focused on the following commitments:
• Develop and maintain the Strategy including the programs, goals and interagency andregulatory reporting requirements for staged reduction of inflow and infiltration over
the next 20 years• Recommend to future Councils that they commit funds for inflow and infiltration
reduction that is economically justified by the avoidance of future treatment andconveyance costs
• Measure wastewater flows before and after carrying out construction/rehabilitationworks on sewers and document inflow and infiltration reduction expenditures and flowreduction measures
8/9/2019 I I Reduction Strategy Annual Report 2012
http://slidepdf.com/reader/full/i-i-reduction-strategy-annual-report-2012 62/103
Inflow and Infiltration Reduction Program Annual Report
Environmental Services Committee 2March 7, 2012
• Continue to work together in a collaborative manner over the life of the Strategy andcommit appropriate staffing and financial resources toward implementation of theStrategy based on a business case analysis
Water and Wastewater Steering Committee, including representatives from
all local municipalities, is working collaboratively to implement the Strategy
The Region formed the Water and Wastewater Steering Committee in April 2010 tosuccessfully develop a comprehensive Strategy that addresses the Minister’s Conditions.The Steering Committee is comprised of representatives from all nine localmunicipalities and the Region and is responsible to review inflow and infiltration issuesand formulate the overall direction for development and implementation of the Strategy.York Region and the local municipalities are working collaboratively to implementvarious activities and resource the work required by their respective organizations todrive program implementation. All 10 municipal partners have committed to identifyingand addressing the financial requirements for the 20 year horizon and the long term
period beyond.
4. ANALYSIS AND OPTIONS
Inflow and infiltration reduction will require comprehensive flow monitoringprogram
Through 2012 to 2015, permanent flow monitoring devices will be installed to auditflows throughout the Region and will leverage the 2008 to 2011 pilot monitoring program in terms of equipment, data and standard practices. The flow data collected on a
permanent basis will help determine inflow and infiltration volumes for audit andreporting purposes. A Request for Proposal to develop the permanent flow monitoring program, including flow monitor selection, procurement, installation and monitoring wasreleased in February of 2012.
Most local municipalities do not currently have formal flow monitoring programs.However, as the audit program is developed and implemented, it may be required to begin isolating critical areas. Markham has purchased 4 monitors for their system and isevaluating flows on a smaller basin level.
The Region’s all-pipe sewage model provides detailed system flow analysis
Adequate continuous real time flow and rainfall data are essential to ensure an all-pipemodel is a reliable and functional tool to support reduction programs. York Region hasdeveloped an all-pipe sewage model for the York Durham Sewage System including the portion in Durham Region. The model will be used to:
• Support the York Region Wastewater Master Plan and ten-year capital programs
• Support system wide operational strategies including real time control
8/9/2019 I I Reduction Strategy Annual Report 2012
http://slidepdf.com/reader/full/i-i-reduction-strategy-annual-report-2012 63/103
Inflow and Infiltration Reduction Program Annual Report
Environmental Services Committee 3March 7, 2012
• Support the Inflow and Infiltration Reduction Program to identify areas of highinflow and infiltration as well as to quantify inflow and infiltration reduction asremedial works are carried out
Inspection and assessment programs successful in pinpointing sources of
inflow and infiltration
Inspection for inflow and infiltration flow reduction is a component of the Regional andlocal ongoing condition assessment and asset management programs. The Region’scurrent closed circuit television program undertakes inspection of the trunk sewernetwork on a 10 year cycle, based on sewer condition rating. In 2011, the closed circuittelevision program inspected a total of 23.9 km of trunk sewers and 0.5 km of siphons. In2012 the program will be inspecting 25 km of trunk sewers. Annual inspections coverapproximately 10% of the trunk system.
The following local municipalities have ongoing inspection programs in place:
•
Vaughan, 210 km closed circuit television in 2011• Markham, 132 km closed circuit television in 2011
• Newmarket, 8.25 km closed circuit television in 2011
• King, 1.8 km closed circuit television in 2011
• Aurora, 33 km closed circuit television in 2011, 500 manholes inspected
• Richmond Hill, 130 km, closed circuit television in 2011
Development funded investigation and remediation efforts t ied to allocationand proven reductions
In May 2011, the Region, Town of Markham and Upper Unionville Inc. signed a tri-party
agreement for reducing inflow and infiltration within the Town of Markham. UpperUnionville Inc. agreed to reduce inflow and infiltration within the municipality inexchange for advanced wastewater servicing allocation to support a new residentialdevelopment at the northeast corner of Kennedy Road and Sixteenth Avenue. Animplementation plan for inflow and infiltration reduction was developed by UpperUnionville Inc. and reviewed by the Region and Town. Remediation works are currentlyunderway. The Region will determine eligible capacity for assignment based on proveninflow and infiltration reduction through remedial work performed by the developer andreviewed by the Region and Town.
Opportunities include:
• Developer funding of the project at no cost to the Region or the Town• Quick commencement of work with readily available resources from the developer
• Acquiring project experience that can be used for other inflow and infiltrationreduction projects in the Region
• A reduction in inflow and infiltration and peak sewer flows
8/9/2019 I I Reduction Strategy Annual Report 2012
http://slidepdf.com/reader/full/i-i-reduction-strategy-annual-report-2012 64/103
Inflow and Infiltration Reduction Program Annual Report
Environmental Services Committee 4March 7, 2012
This opportunity has been provided to all Regional local municipalities and resolutionshave also been passed in the Towns of Aurora and Richmond Hill and the City ofVaughan to participate in the program.
Local remediation pilot pro jects will provide inflow and infiltration
reduction and determine effectiveness of reduction technologies
A comprehensive Sanitary Sewer Evaluation Study of sanitary sewers and manholeslocated within local municipal systems was completed in 2010. Remediation projectswere proposed for the eight projects categorized as the highest priority catchments interms of inflow and infiltration. Remediation will include relining of approximately 12km of mainline sewer, 162 point and surface repairs and 375 manhole rehabilitations.
The project was divided into two construction phases. Phase 1 includes rehabilitationwork of four catchments in Aurora, Newmarket (2) and Richmond Hill. Commencementof this phase began in January 2012. Phase 2 includes rehabilitation work of four
catchments in East Gwillimbury, Georgina (2) and Whitchurch-Stouffville.Commencement of this phase will begin in Q2 2012. Completion of the project isexpected by Q4 2012.
Local municipalities have also been completing rehabilitation work which shouldimprove system performance and assist in the reduction of inflow and infiltration. Workincludes:
• Vaughan, 10 manholes relined in 2011
• Whitchurch-Stouffville, 1.16 km of sewer relined, 2 manholes repaired in 2011
• Markham, 1.22 km of sewer relined in 2011
• Newmarket, 1.76 km of sewer relined, 5 manholes repaired in 2011
• Aurora, 5 km of sewer relined, 20 manholes repaired/relined in 2011• Richmond Hill, 2 km of sewer relined in 2011
York Region’s 10-year Capital Program identifies $45M investment thatsupports flow reduction
Through the Region’s Infrastructure Management Program, inflow and infiltration issueswithin the Regional trunk sewers are also identified and remediation works planned.Currently there are a number of locations planned for remediation and this remediationwill occur in the Regional trunk system over the next three years to reduce inflow andinfiltration, including portions of the York Durham Sewage System (YDSS).
Approximately $45 million will be required over the next 10 years for Regional sewerrehabilitation across the entire sewer system, including remediation and upgrades to theexisting South East Collector after completion of the new Southeast Collector.
8/9/2019 I I Reduction Strategy Annual Report 2012
http://slidepdf.com/reader/full/i-i-reduction-strategy-annual-report-2012 65/103
Inflow and Infiltration Reduction Program Annual Report
Environmental Services Committee 5March 7, 2012
Communication, education and advocacy have developed key relationshipsto support the Program
The Strategy was developed through a collaborative approach including initiatives withmulti-sector steering committees including representatives from the Ontario Concrete
Pipe Association, Greater Toronto Sewer and Watermain Contractors Association, BILD,consulting engineers, regulatory agencies and municipalities. The work examinednumerous sources of information on inflow and infiltration reduction includingworldwide best practices employing lifecycle based approaches. Through a sequence of programs at the Regional and local municipal level, inflow and infiltration will bereduced to optimize the system for new flow and growth within the Region as well asaddressing social and environmental demands.
As part of continued consultation with industry stakeholders, several presentations on theInflow and Infiltration Reduction Strategy have been given by the Region to illicitcomments on the Strategy. Presentations have been given to the Ontario Concrete Pipe
Association, Building Industry and Land Development Association, the MunicipalEngineers Association, National Water and Wastewater Benchmarking Initiative,Ministry of the Environment and the South East Collector Advisory Committee.
As representatives for the Municipal Engineers Association, Regional staff sit on thePlant Prequalification Committee held through the Ontario Concrete Pipe Association.This Committee drives the acceptance and testing requirements for concrete productmanufacturers in Ontario and also resources an audit program to monitor productioncertificates and compliance with performance thresholds. Participation has garneredexcellent discussion around product performance and enhanced testing.
Improved standards and guidelines will facilitate efficiency in newdevelopment
The York Region Sanitary Sewer Inspection, Testing and Acceptance Guidelines outline procedures and minimum requirements for inspection, testing and acceptance of newsanitary sewer systems commissioned in York Region and the nine local municipalities.The Guidelines were developed in conjunction with Regional staff, local municipalitiesand industry experts. The Guidelines have been finalized and were distributed to the ninelocal municipalities for implementation in October 2011.
As part of the ongoing commitment to the Strategy, the next phase of work will addressimproved standards for municipal development including subdivision agreements and site plan approvals. Specific areas to be addressed include the control of inflow duringconstruction and the timing of connections prior to occupancy and/or full build out. Tothis end, a consultant has been retained to assist with data collection and review in Q12012. To date the following municipalities have used the new guidelines to commissionnew developments and the remaining municipalities have committed to do so through theStrategy approval:
• Whitchurch-Stouffville, two developments
8/9/2019 I I Reduction Strategy Annual Report 2012
http://slidepdf.com/reader/full/i-i-reduction-strategy-annual-report-2012 66/103
Inflow and Infiltration Reduction Program Annual Report
Environmental Services Committee 6March 7, 2012
• King Township, four developments
• Markham, sixteen developments
Significant achievements in the first year o f implementation
The Inflow and Infiltration Reduction Strategy recommended a target flow volumereduction at the Southeast Collector Trunk Sewer of 71 ML within a 24-hour periodunder a 25-year storm event, with approximately 40 ML to be achieved through inflowand infiltration reduction and the balance through water conservation initiatives by 2031.
In order to accurately quantify inflow and infiltration reduction, it is essential to installflow meters near the location of remediation works and collect data before and afterconstruction to carry out comparison analysis. Regional staff have been coordinating withlocal municipal staff to install flow meters at required locations for all new remediation projects including the pilot projects noted in this report and are carrying out analysis on projects as flow data becomes available. To date, three catchments have complete pre and
post construction flow data to enable staff to quantify the inflow and infiltrationreduction. Reduction efforts have occurred in another eight catchments from 2008 to2011, however post monitoring to quantify volumes is not complete and will not beavailable until late 2012.
The above will be included in the first Annual Report to the Ministry of Environment andas more flow data becomes available in other catchments, it will be reported accordinglyin subsequent Annual Reports. Although the reduction only represents 2% of the 20 yearrequirement, it is significant to note that the Strategy was just finalized in March of 2011and approved by the Ministry of Environment in October 2011. To see reductions thisearly in the process is very promising. Also, given that the Strategy was only endorsed byRegional and Local Councils in 2011, the first full year of resource planning and budgeting starts in 2012. The program will pick up significant momentum in this firstyear of implementation and further and greater reductions are expected in the future.
Link to Key Council-approved Plans
The Inflow and Infiltration Reduction Program has direct links to the Regional 2011 to2015 Strategic Plan. More specifically, the Strategic Priority Area focussing on continueddelivery and sustainability of critical infrastructure, stipulates a key objective is toidentify and leverage capacity available in existing infrastructure to complete the build-out of developing communities. A key indicator of success for this objective is thedecrease of inflow and infiltration in Regional and local systems.
8/9/2019 I I Reduction Strategy Annual Report 2012
http://slidepdf.com/reader/full/i-i-reduction-strategy-annual-report-2012 67/103
Inflow and Infiltration Reduction Program Annual Report
Environmental Services Committee 7March 7, 2012
5. FINANCIAL IMPLICATIONS
The Inflow and Infiltration Reduction Strategy funding model has been approved basedon the following key funding principles:
• A set rate will be collected at both the local and Regional level as identified through
the needs of the Strategy and as agreed to by the municipal partners. An initialfunding target of $100 million over 20 years has been established. This equates toan annual investment of $5 million per year across the Region for inflow andinfiltration reduction.
• The amount collected at the local level will be used to address priorities identified both through the Strategy and as determined by each local municipality
• The amount collected at the Regional level will be used to address Regional inflowand infiltration priorities both at the Regional and local level
• Allocation of Regional funds intended for use in the local systems will be managedand allocated by a joint team with staff representatives from each municipality andthe Region. Funding will be prioritized based on the most effective application to
achieve the desired inflow and infiltration improvements as quickly as possible.
Funding for required Regional inflow and infiltration reduction work has been includedin the approved 2012 capital budget.
6. LOCAL MUNICIPAL IMPACT
Al l Local munic ipali ties have endorsed the Inflow and Inf il tration Reduct ionStrategy
Local municipal staff have been involved in development of the Inflow and Infiltration
Reduction Strategy through participation in the Water and Wastewater SteeringCommittee. Local municipal Councils have endorsed the strategy to fulfill the conditionsof approval for the Southeast Collector Trunk Sewer Individual EnvironmentalAssessment. Continued participation by all local municipalities is required to meetMinistry requirements and ensure successful implementation of the strategy.
Successful implementation of th is program will require inflow andinfiltration reduction from private property
Eliminating infiltration from the public sewers while ignoring the private infrastructurewill compromise the Region’s efforts to reduce infiltration into the Southeast Collector
Trunk Sewer and fall short of the overall program goals. Reducing inflow and infiltrationon private property is required for success of the Strategy and program. Access to private property will be a key discussion of the Steering Committee in 2012 and will be criticalto achieving continued inflow and infiltration reductions over and beyond the Regionaland local municipal systems. Local municipalities will play a lead role in consulting withresidents, facilitation of work on private property and improving performance of new private infrastructure.
8/9/2019 I I Reduction Strategy Annual Report 2012
http://slidepdf.com/reader/full/i-i-reduction-strategy-annual-report-2012 68/103
Inflow and Infiltration Reduction Program Annual Report
Environmental Services Committee 8March 7, 2012
Local bylaw enforcement required for lateral inspections and remediationon private property
To ensure access to the private portion of the sewer network, local municipalities willneed to ensure that their respective bylaws include provisions such as right of entry or
inspection that will allow for access by the municipality or their contractors. These bylaws are required to provide access to private property for all related work, includinginstalling cleanouts, liners or new pipe as well as conducting closed circuit televisionwork on laterals. By moving forward with bylaw development, the Region and localmunicipalities can:
• Create a strong program of communication and technical assistance to helphomeowners design an alternative discharge method for flows, includingdisconnection programs
• Establish a clear policy regarding responsibility for cost of repairs includingsubsidy or grant programs for rehabilitation of laterals and property piping
• Establish municipal authority to order the remediation of the problem by the
property owner, even if the municipality plans to cover the cost of disconnectingthe flows itself
• Include a program of follow up inspections after repairs are made and thereafter periodically inspect repairs/disconnections. Consider time of resale inspections orcertification programs.
• Establish a strong public outreach and education component so that the public isaware of the problem and the benefits of inflow reduction
Currently, the City of Vaughan and the Towns of Markham and Georgina have bylawswhich stipulate staff be given access into areas where wastes or storm waters aredischarged for the purpose of inspection and examination of processes, private sewer
connections and other works.
The following local municipalities have been doing lateral inspections and repair in theirsystems:
• Aurora, 200 laterals inspected
• Whitchurch-Stouffville, 4 laterals inspected and replaced
• Newmarket, 80 laterals inspected, 15 laterals replaced
• Vaughan, 477 laterals inspected, 35 laterals repaired
• Richmond Hill, 177 laterals inspected and repaired
8/9/2019 I I Reduction Strategy Annual Report 2012
http://slidepdf.com/reader/full/i-i-reduction-strategy-annual-report-2012 69/103
Inflow and Infiltration Reduction Program Annual Report
Environmental Services Committee 9March 7, 2012
7. CONCLUSION
York Region and local municipalities have joint responsibility to implement the Inflowand Infiltration Reduction Strategy. The Region and local municipalities are also requiredto further define and implement activities necessary to ensure the Strategy is continually
maintained, enhanced and implemented. This work has commenced and will continue asa sustained program. The Strategy will be updated as data is collected, new information islearned and new technology becomes available.Through development and implementation of this Strategy, the Region and its localmunicipalities have demonstrated leadership in inflow and infiltration reduction withinthe water and wastewater industry.
On March 31, 2012, York Region will submit to the Ministry of the Environment and theSoutheast Collector Advisory Committee an annual report detailing progress onimplementing the Strategy including inflow and infiltration reduction.
For more information on this report, please contact Daniel Kostopoulos, Director, CapitalPlanning and Delivery at (905) 830-4444, Ext. 5070.
The Senior Management Group has reviewed this report.
Recommended by:
Erin Mahoney, M. Eng.Commissioner of Environmental Services
Approved for Submission:
Bruce MacgregorChief Administrative Officer
February 15, 2012
MR/se
Report Wizard v.1.20104028729
8/9/2019 I I Reduction Strategy Annual Report 2012
http://slidepdf.com/reader/full/i-i-reduction-strategy-annual-report-2012 70/103
Long Term Water Conservation Strategy and Inflow and Infiltration Strategy 63
Annual Report dated March 31, 2012
Appen ix D:
Sanitary Sewer
System
Inspection, Testing
and Acceptance Guideline
8/9/2019 I I Reduction Strategy Annual Report 2012
http://slidepdf.com/reader/full/i-i-reduction-strategy-annual-report-2012 71/103
8/9/2019 I I Reduction Strategy Annual Report 2012
http://slidepdf.com/reader/full/i-i-reduction-strategy-annual-report-2012 72/103
Table of Contents
Page1.General 1
1.1 General Requirements......................................................................................................................... 1 2.Gravity Sanitary Sewer Testing Requirements 3
2.1 General Requirements......................................................................................................................... 3 2.2 Test Method & Sequence .................................................................................................................... 3 2.3 Exfiltration Test - Low Pressure Air ..................................................................................................... 4 2.4 Infiltration Test ..................................................................................................................................... 5 2.5 Exfiltration Test - Water ....................................................................................................................... 6 2.6 Joint Test – Concrete Pipe (Greater than 600mm Diameter).............................................................. 6
2.6.1 Supplementary Jo int Testing .............................................................................................. 6 2.7 Mandrel Deflection Testing.................................................................................................................. 7 2.8 CCTV Inspections................................................................................................................................ 8
2.8.1 Video Inspection Equipment ............................................................................................... 8 2.8.2 Video Camera Transport Equipment .................................................................................. 8
2.9 Testing Pressure Pipe Used as Gravity Sewer ................................................................................... 9
3.Forcemain Testing Requirements 9 3.1 General Requirements......................................................................................................................... 9 3.2 Hydrostatic Leak Test .......................................................................................................................... 9
4.Maintenance Hole Testing Requirements 10 4.1 General Requirements....................................................................................................................... 10 4.2 Maintenance Hole Exfiltration Water Test ......................................................................................... 10 4.3 Maintenance Hole Infiltration Water Test .......................................................................................... 10 4.4 Negative Air (Vacuum) Test .............................................................................................................. 10 4.5 Chimney Seal Leakage Test ............................................................................................................. 11
5.Groundwater Measurement 11 6.Referenced Standards 12
8/9/2019 I I Reduction Strategy Annual Report 2012
http://slidepdf.com/reader/full/i-i-reduction-strategy-annual-report-2012 73/103
YORK-#3533399 – York Region - Sanitary Sewer Inspection, Testing and Acceptance Guideline (Formerly Commissioning Guideline),October 2011
1
1. General
This Guideline outlines the general procedures and minimum requirementsrequired for inspection, testing and acceptance of new sanitary sewer systems
commissioned in York Region and the nine (9) Local Area Municipalities. TheGuideline is based on requirements and procedures from Ontario ProvincialStandard Specifications (OPSS) and American Society of Testing Materials(ASTM).
Without limiting the foregoing, it is a set of standards that outline specific requirements for inspecting andtesting the construction of sanitary sewer systems to help prevent Inflow and Infiltration (I/I) from enteringnew sanitary sewer systems. It provides direction for the preferred test methods, performance rates (testinglimits) and specific requirements for the construction of sanitary sewer systems dedicated to York Regionand the nine (9) Local Area Municipalities for the duration of the construction period, including the
installation of lateral connections to property line.
The details in the Guideline only delineate specific features of sanitary sewer system construction thatimpact I/I reduction, and are not intended to supplement or replace current York Region or nine (9) LocalArea Municipality Water and Wastewater Design Standards and Guidelines.
1.1 General Requirements
All newly constructed sanitary sewers and manholes shall be watertight and free from leakage.
The Contractor shall be responsible for payments and scheduling all testing required and informing the Municipalityand their Qualified Representative (e.g. consulting engineer) of the planned commencement date ten (10) days prior
to such commencement and reconfirm three (3) days prior to testing.
When specified in the Contract documents, leakage or water-tightness tests shall be carried out on completed pipesewers 1,200mm in diameter and smaller. There shall be no visible leakage for pipe sewers larger than 1,200mmdiameter. All tests shall be carried out in the presence of and accepted by the Municipality or their QualifiedRepresentative. Results for tests conducted in the absence of the Municipality or their Qualified Representative willnot be accepted.
The Municipality or their Qualified Representative shall inspect sanitary sewer and manhole installations and relatedwork during all phases of the construction.
No part of the work will be accepted until the sanitary sewers are satisfactorily tested following completion ofinstallation of service connections and backfilling. Upon completion, sanitary sewers and maintenance holes shall be
inspected by visual observation and tested in accordance with this Guideline for each sewer section (maintenancehole to maintenance hole). When tests are unsatisfactory, the test section shall be repaired at Contractor’s expenseand retested until satisfactory results are obtained. If the defective portion of the sanitary sewer cannot be located orrepaired, the Contractor shall remove and reconstruct as much of the work as is necessary to obtain a system thatpasses testing requirements. See Appendix A: York Region and Local Area Municipalities Sanitary SewerInspection, Testing and Acceptance Flow Charts for Concrete and Thermo-Plastic Pipes and Maintenance Holes.
8/9/2019 I I Reduction Strategy Annual Report 2012
http://slidepdf.com/reader/full/i-i-reduction-strategy-annual-report-2012 74/103
YORK-#3533399 – York Region - Sanitary Sewer Inspection, Testing and Acceptance Guideline (Formerly Commissioning Guideline),October 2011
2
The Contractor shall bear the complete cost and supply all equipment necessary to perform the tests required, referto Appendix A for acceptable testing processes.
Sanitary sewer construction shall be inspected throughout the construction period for general adherence to Contractspecifications and follow the sequence of testing provided in subsequent sections.
The test(s) shall be done after final backfill is placed in the trench and before asphalt has been placed (except wherevacuum testing of maintenance holes has been requested by the Municipality or their Qualified Representative).
Where the groundwater table cannot be visually monitored in terms of elevation from the pipe, the Municipality ortheir Qualified Representative may request that groundwater level be measured with piezometers placed inrepresentative locations throughout the length of sanitary sewers under construction and as detailed in Section 5.
Smoke and dye testing may be used only to locate leaks and in no case shall be considered conclusive.
General sequence of testing for sanitary sewer system is as follows (but not limited to):
1. Cleaning and flushing with high-pressure water blasting
2. Deflection or out of round testing (for Thermo-plastic pipes only)
3. Water-tightness (Leakage) testing
4. CCTV (photographic record & inspection form for maintenance holes) after testing and at the start ofmaintenance
5. Additional CCTV may be specified by the Municipality or their Qualified Representative at a time prior to
Maintenance, and at the time prior to Assumption of the works.
• For testing requirements specific to gravity sanitary sewers refer to Section 2
• For testing requirements specific to forcemains refer to Section 3
• For testing requirements specific to maintenance holes refer to Section 4
• For groundwater measurement refer to Section 5
8/9/2019 I I Reduction Strategy Annual Report 2012
http://slidepdf.com/reader/full/i-i-reduction-strategy-annual-report-2012 75/103
YORK-#3533399 – York Region - Sanitary Sewer Inspection, Testing and Acceptance Guideline (Formerly Commissioning Guideline),October 2011
3
2. Gravity Sanitary Sewer Testing Requirements
2.1 General Requirements
Gravity sanitary sewer pipes shall be cleaned and flushed with high pressure water blasting after construction and
just prior to inspection and testing.
Testing shall be carried out from maintenance hole to maintenance hole and shall include lateral connections toproperty line. Testing shall be conducted prior to any service connections being made. All service laterals, stubs, andfittings shall be plugged or capped prior to testing.
Sanitary sewers shall be repaired and re-tested, as required, until the test results are within the limits specified.Visible leaks shall be repaired regardless of the test results.
The testing requirements follow the OPSS and ASTM standards and are generally described in each subsection ofthis section. Changes or deviations to the OPSS standards are as noted herein.
2.2 Test Method & SequenceWater-tightness testing parameters are dependent on groundwater levels prior, during and after testing of thesanitary sewer, the static water level shall be recorded in accordance with Section 5.
The water-tightness test method for small diameter pipe (Thermo-plastic pipe 900mm diameter and less andconcrete pipe 600mm diameter and less) shall be Exfiltration Test – Low Pressure Air (Air Exfiltration), see Section2.3. In the event that air ex filtration testing fails and leak location and repair is unsuccessful, the use of other testmethodology may be accepted at the discretion of the Municipality or their Qualified Representative. Any otherwater-tightness method will only be allowed following the submittal of the procedure to the Municipality or theirQualified Representative for review and upon their written approval.
The water-tightness test method for large diameter pipe (Thermo-plastic pipe greater than 900mm diameter andconcrete pipe greater than 600mm diameter) and where the groundwater is at least 600mm above the highest sewer
crown shall be Infiltration Test, see Section 2.4. In the event that groundwater levels are less than 600mm above thecrown of the pipe, the Exfiltration Water Test or Joint Test as applicable shall be used only when specified by theMunicipality or their Qualified Representative, see Sections 2.5 and 2.6 respectively.
When specified by the Municipality or their Qualified Representative, supplementary joint testing on large concretepipe (greater than 600mm diameter) shall be conducted on representative joints, see Section 2.6.
8/9/2019 I I Reduction Strategy Annual Report 2012
http://slidepdf.com/reader/full/i-i-reduction-strategy-annual-report-2012 76/103
YORK-#3533399 – York Region - Sanitary Sewer Inspection, Testing and Acceptance Guideline (Formerly Commissioning Guideline),October 2011
4
2.3 Exfiltration Test - Low Pressure Air
Standard practice for testing, equipment used, and other specifications shall follow OPSS 410, ASTM C924, ASTMF1417-11 and as noted herein.
The Contractor is responsible for ensuring that the test is conducted in a safe manner and all applicable safetyprocedures are followed. Do not enter, or allow anyone to enter, the maintenance hole during testing.
Tests shall be conducted between two consecutive maintenance holes or to a stub end where the sewer does notterminate at a maintenance hole. The test section shall be plugged at each end. The test section shall be filledslowly until a constant pressure of 24kPa is maintained. If the groundwater is above the pipe sewer being tested,the air pressure shall be increased by 3.0kPa for each 300mm from interior pipe invert that the groundwater level isabove the invert of the pipe.
Whereby the groundwater table cannot be visually monitored in terms of elevation from pipe, the Municipality or theirQualified Representative may request that groundwater level be measured prior to testing in accordance withSection 5.
The air pressure shall be stabilized for five (5) minutes and then regulated to maintain it to 20.5kPa plus theallowance for groundwater, if any. After the stabilization period, the time taken for a pressure loss of 3.5kPa shall berecorded.
The time taken for a pressure drop of 3.5kPa shall not be less than the times shown in Table 1 (Column B) forlengths equal to or less than the length shown in Table 1 (Column C).
Table 1: Exfiltration Test – Low Pressure Air Testing (OPSS 410)
Column A Column B Column C Column D
Nominal Pipe
Size(mm)
Minimum
Time(min:sec)
Length of Pipefor Minimum
Time(m)
Time Per Unitfor Longer
Lengths ofPipe* (sec/m)
100 1:53 182 0.623150 2:50 121 1.140200 3:47 91 2.493250 4:43 73 3.893300 5:40 61 5.606375 7:05 48 8.761450 8:30 41 12.615525 9:55 35 17.171600 11:20 30 22.425675 12:45 27 28.382750 14:10 24 30.040825 15:35 22 42.397
900 17:00 20 50.450
*If the length of the test section is greater than the length shown in Column C, the testing time shall be the product of the length of the test section
multiplied by the value in Column D (i.e. Minimum time = test length x Column D).
8/9/2019 I I Reduction Strategy Annual Report 2012
http://slidepdf.com/reader/full/i-i-reduction-strategy-annual-report-2012 77/103
YORK-#3533399 – York Region - Sanitary Sewer Inspection, Testing and Acceptance Guideline (Formerly Commissioning Guideline),October 2011
5
Determination o f Acceptance
If the time shown in Table 1 for the designated pipe size and length elapses before the air pressure drops 3.5kPa,the section undergoing test shall have passed and shall be presumed to be free of defects. The test may bediscontinued once the prescribed time has elapsed even though the drop 3.5kPa has not occurred.
Determination of Failure
If the pressure drops 3.5kPa before the appropriate time shown in Table 1 has elapsed, the air loss shall beconsidered excessive and the section of pipe shall be determined to have failed the test.
In the event that air exfiltration testing on the sanitary sewer system or any section thereof fails, and/or leak repair isunsuccessful, the use of other test methodology at the discretion of the Municipality or their Qualified Representativemay be permitted. The Municipality or their Qualified Representative can also request air exfiltration testing againonce the repair is complete. The Contractor may conduct a water infiltration test in accordance with Section 2.4 toestablish whether the 0.0375 litres/millimeter diameter /100 metres of pipe sewer/hour maximum allowable infiltrationrate is being exceeded. If the field conditions do not allow for infiltration test due to low groundwater table, a waterexfiltration test in accordance with Section 2.5 may be used upon written approval from the Municipality or theirQualified Representative.
If the air test on the sanitary sewer system or any section thereof fails, but the water infiltration or exfiltration test onthe sanitary sewer system or section thereof passes, the sanitary sewer system or section thereof shall be deemedacceptable. However, the Contractor shall be responsible for repairing all visible leaks regardless of the ability of thesanitary sewer system or section thereof to pass any established test criteria specified in this Guideline.
2.4 Infiltration Test
Standard practice for testing, equipment used, and other specifications shall follow OPSS 410, ASTM C969M and asnoted herein
The rate of infiltration into the sanitary sewer system shall not be in excess of 0.0375 litres/millimeter diameter /100metres of pipe sewer/hour.
Infiltration test shall be conducted only where the ground water level at the time of testing is 600mm or more abovethe crown of the pipe for the entire length of the test section, otherwise infiltration will be considered an invalid watertightness test.
Prior to testing, discontinue dewatering operations at least three (3) days before conducting the test and allow thegroundwater level to stabilize. Measure groundwater levels in accordance with Section 5.
A V-notch weir or other suitable measuring device shall be installed at the downstream end of the test section.Infiltrating water shall be allowed to build up behind the weir until the flow through the V-notch has stabilized. Severaltests (minimum three) at 15-30 minutes intervals shall be performed to ensure that the flow through the weir issteady and not changing. The rate of flow shall then be measured and shall not exceed the maximum allowableinfiltration calculated for the test section.
8/9/2019 I I Reduction Strategy Annual Report 2012
http://slidepdf.com/reader/full/i-i-reduction-strategy-annual-report-2012 78/103
YORK-#3533399 – York Region - Sanitary Sewer Inspection, Testing and Acceptance Guideline (Formerly Commissioning Guideline),October 2011
6
2.5 Exfil tration Test - Water
Standard practice for testing, equipment used, and other specifications shall follow OPSS 410, ASTM C969M and asnoted herein.
Exfiltration tests utilizing water shall be conducted where the groundwater level is lower than 600mm above the
crown of the pipe or the highest point of the highest service connection included in the test section and only whenspecified by the Municipality or their Qualified Representative.
The leakage at the end of the one (1) hour test period shall not be in excess of 0.0375 litres/millimeter diameter/100metres of pipe sewer/hour.
An allowance for each maintenance hole included in the test section shall be made in accordance with theexfiltration rate for maintenance holes detailed in Section 4.
Water shall be added to the pipeline prior to testing until there is a head in the upstream maintenance hole of thegreater of 600mm minimum over the crown of the pipe or above the groundwater level (refer to Section 5 forGroundwater Measurement).
2.6 Joint Test – Concrete Pipe (Greater than 600mm Diameter)
Standard practice for testing, equipment used, and other specifications shall follow ASTM C 1103M and as notedherein.
This test shall be used when groundwater levels are less than 600mm above the crown of the pipe and only whenspecified by the Municipality or their Qualified Representative.
When directed to utilize this test method, all joints shall be tested unless otherwise directed by the Municipality ortheir Qualified Representative.
Equipment used shall be made specifically for joint testing of pipelines.
2.6.1 Supplementary Joint Testing
Standard practice for testing, equipment used, and other specifications shall follow ASTM C 1103M and as notedherein.
This test shall be used as an additional supplementary test only when specified by the Municipality or their QualifiedRepresentative. After successful water tightness testing, supplementary joint testing is to be completed as anadditional pass/fail test on selected joints on all precast concrete pipes greater than 600mm in diameter whenspecified by the Municipality or their Qualified Representative.
Representative testing on 5% of all joints, joints selected to be approved by the Municipality or their Qualified
Representative, is to be conducted. Joints shall be selected evenly spaced along the complete pipe sewer. Failed
joints are to be repaired.
All joints tested shall pass the test otherwise a different representative sample (5%) shall be tested following thesame sequence.
Joints that fail to meet the verified test criteria (stated in ASTM C 1103M) shall be resealed and retested until the test
criteria can be met.
8/9/2019 I I Reduction Strategy Annual Report 2012
http://slidepdf.com/reader/full/i-i-reduction-strategy-annual-report-2012 79/103
YORK-#3533399 – York Region - Sanitary Sewer Inspection, Testing and Acceptance Guideline (Formerly Commissioning Guideline),October 2011
7
2.7 Mandrel Deflection Testing
Standard practice for testing, equipment used, and other specifications shall follow OPSS 410.
Mandrel deflection testing shall be performed on all Thermo-plastic pipe sewers. The mandrel deflection test shall beperformed no sooner than thirty (30) days after final backfill to road subgrade elevation has been placed.
The mandrel shall be cylindrical in shape, and constructed with an odd number of evenly spaced arms or prongs,minimum 9 in number. The minimum diameter of the circle scribed around the outside of the mandrel arms shall beequal to the allowable deflected pipe diameter ± 1mm. The contact length of the mandrel shall be measuredbetween the points of contact on the mandrel arm or between sets of prongs. This length shall not be less than thatshown in Table 2.
The mandrel shall be checked with a go-no-go proving ring. The proving ring shall have a diameter equal to theallowable deflected pipe diameter ± 0.1mm. An acceptable mandrel shall not pass through the proving ring. Theproving ring shall be fabricated from steel a minimum of 6 mm thick.
For pipes 100mm to 750mm in diameter, the allowable deflected pipe diameter is 7.5% of the base inside diameterof the pipe. For pipes greater than 750mm in diameter, the allowable deflected pipe diameter is 5.0% of the base
inside diameter of the pipe. The base inside diameter is defined in the CSA or ASTM standard to which the pipe ismanufactured.
Any section of pipe that does not allow the mandrel to pass shall be considered to have failed the deflection test.
All sections of pipe that fail the deflection test shall be repaired and retested. Re-rounding is not accepted. Retestingshal be carried out no sooner than 30 days after backfill has been placed.
Table 2 -Deflection Testing of Pipe Sewers (from OPSS 410)
Nominal Pipe Size(mm)
Mandrel ContactLength(mm)
150 100200 150250 200300 250350 300375 300400 300450 350500 400525 450600 500675 575750 675900 750
1050 9001200 1050
8/9/2019 I I Reduction Strategy Annual Report 2012
http://slidepdf.com/reader/full/i-i-reduction-strategy-annual-report-2012 80/103
YORK-#3533399 – York Region - Sanitary Sewer Inspection, Testing and Acceptance Guideline (Formerly Commissioning Guideline),October 2011
8
2.8 CCTV Inspect ions
Standard practice for testing, equipment used, and other specifications shall follow OPSS 409. Observations anddefect coding standard shall be in accordance with Water Research Centre Publication Manual (WRc) Manual ofSewer Classification (3rd Edition).
Closed Circuit Television (CCTV) inspection shall be performed to observe and record structural and service defects,construction features, and to assess thoroughness of cleaning.Defects to be repaired shall be in accordance with the Municipalities specifications.
Media storage shall be high quality CD or DVD (reference 409.05.01).
Each digital .MPEG file and inspection report shall consist of one pipe section only (unless a reversal is required),where two inspection records will be required. A record on CD or DVD of the internal condition of the piping systemshall be provided in addition to a printed and digital inspection report. Two copies of the digital media (CD’s orDVD’s) shall be provided and 2 copies of the printed report (reference 409.07.05.01).
The camera lens should be positioned along the center axis of the pipe. Lighting in the sewer must be sufficient toilluminate approximately 2 m ahead of the camera and be evenly distributed around the periphery of the pipe withoutloss of contrast. The camera must maintain a speed that will allow for the defects to be observed clearly. Thecamera must stop and pan special features within the pipe, such as maintenance hole interfaces, junctions, serviceconnections and major defects.
2.8.1 Video Inspection Equipment
The video shall be of quality that all minor defects (hairline cracks, etc.) are clearly visible and the colour of the pipeinspected is true to actual conditions. Should the video not be of this quality, as determined by the Municipality ortheir Qualified Representative, the Contractor shall be required to re-inspect the line to produce an acceptablequality video at no additional cost. The picture quality on the monitor shall provide a minimum continuous 460 lineresolution video picture. Linear measure through pipes must be accurate to +/- 0.5%.
2.8.2 Video Camera Transport Equipment
The camera shall be transported through the sewer by means of a rubber tired or crawler tractor. The transport unitmust be capable of passing over minor surface imperfections including but not limited to broken joints and soliddebris up to 40mm in height.
Mounting of the camera on a float or skid for tow through the sewer shall only be permitted where the condition ofthe sewer precludes the use of a tractor and where authorized by the Municipality or their Qualified Representative.If the camera is towed the supporting equipment shall not impede the view of the camera and shall be stable toensure steady and smooth progress.
The camera transport shall permit complete inspection of the sewer from the centre of the start maintenance hole tothe centre of the finish maintenance hole. A remote reading counter shall be used to measure distance travelledfrom the centre of the start maintenance hole and measurements shall be recorded in metres to the nearest 100
mm.
8/9/2019 I I Reduction Strategy Annual Report 2012
http://slidepdf.com/reader/full/i-i-reduction-strategy-annual-report-2012 81/103
YORK-#3533399 – York Region - Sanitary Sewer Inspection, Testing and Acceptance Guideline (Formerly Commissioning Guideline),October 2011
9
2.9 Testing Pressure Pipe Used as Gravity Sewer
Standard practice for testing pressure pipe used for gravity sewer service, equipment used, and other specificationsshall follow OPSS 412.
Test pressure shall be 1035KPa and test duration of 2 hours.
Allowable leakage shall be in accordance with OPSS 412; 0.082 litres per millimetre of pipe diameter per kilometreof pipe for the 2 hour test period.
3. Forcemain Testing Requirements
This section provides the testing requirements specific to forcemains and low pressure systems.
3.1 General Requirements
All forcemains for lift stations and common force mains in low pressure systems shall be tested for leakage by aHydrostatic Leak Test
Forcemain construction shall be inspected throughout the construction period for general adherence to contractspecifications and good practice.
The testing requirements follow the standards and are generally described in each subsection of this section.
Changes or deviations to the OPSS standards are as noted herein.
3.2 Hydrostatic Leak Test
Standard practice for testing, equipment used, and other specifications, shall follow OPSS 412.
A test section shall be either a section between valves or the completed forcemain. The forcemain to be tested shallbe backfilled before testing commences.
Test pressure shall be as specified in the Contract Documents or be provided by the Municipality or their QualifiedRepresentative.
The test section shall be filled slowly with water, and all air shall be removed from the pipeline. A 24-hour absorptionperiod may be allowed before starting the test. The test section shall be subjected to the specified continuous testpressure for two (2) hours.
The leakage is the amount of water added to the test section to maintain the specified test pressure for the testduration.
No leakage will be permitted (the allowable leakage is zero (0)). All leaks shall be located and stopped and the testsection shall be retested until leakage is zero (0).
All defective pipe, fittings, valves and other appurtenances discovered shall be removed and replaced with soundmaterial and tests repeated until the leakage is zero (0).
8/9/2019 I I Reduction Strategy Annual Report 2012
http://slidepdf.com/reader/full/i-i-reduction-strategy-annual-report-2012 82/103
YORK-#3533399 – York Region - Sanitary Sewer Inspection, Testing and Acceptance Guideline (Formerly Commissioning Guideline),October 2011
10
4. Maintenance Hole Testing Requirements
4.1 General Requirements
Standard practice for testing, equipment used and other specifications shall follow OPSS 407 and ASTM C1244M.
Every maintenance hole shall be chimney seal tested and visually inspected, and whereby specified by theMunicipality or their Qualified Representative shall be tested by either exfiltration water testing or infiltration watertesting. As an alternative at the discretion of the Municipality or their Qualified Representative, testing may beperformed by vacuum testing. Vacuum testing shall be conducted on un-backfilled maintenance holes in accordancewith the standards noted above.
A photographic record and inspection with condition rating shall be completed on every maintenance hole,Municipality or their Qualified Representative to provide inspection form
Maintenance holes shall be inspected during all phases of construction. Each maintenance hole shall be visuallyinspected for leakage after assembly and backfilling.
4.2 Maintenance Hole Exfil tration Water Test
Each maintenance hole shall be tested for leakage after assembly and backfilling where requested by theMunicipality or their Qualified Representative.
Leakage shall not exceed a rate of 3 litres per hour per metre of head above the lowest pipe invert in themaintenance hole.
Maintenance holes shall be repaired and re-tested, as required, until the test results are within the limits specified.Visible leaks shall be repaired regardless of the test results. The method of repair shall be per the approval of theMunicipality or their Qualified Representative
4.3 Maintenance Hole Infil tration Water Test
This test shall be used in lieu of Maintenance Hole Exfiltration Water Test only when specified by the Municipality ortheir Qualified Representative.
Standard practice for testing, equipment used, and other specifications shall follow OPSS 407 or ASTM C1244M.The test shall be conducted as an Infiltration Water Test.
4.4 Negative Air (Vacuum) Test
All Joints between the top of the casting to the bottom of the maintenance hole base shall be included in the test.
Equipment used shall be made specifically for vacuum testing maintenance holes.
A vacuum will be drawn and the vacuum drop over a specified time period shall be within the limits in the standard todetermine the acceptability of the maintenance hole.
The maintenance hole shall pass if the time for the vacuum reading to drop from 33.8 kPa of Hg to 30.4 kPa of Hg
meets or exceeds the values in the Table 4 from ASTM 1244M.
If the maintenance hole fails the initial test, necessary repairs shall be made by an approved method. The
maintenance hole shall then be retested until a satisfactory test is obtained. Visible leaks shall be repaired
regardless of the test results.
8/9/2019 I I Reduction Strategy Annual Report 2012
http://slidepdf.com/reader/full/i-i-reduction-strategy-annual-report-2012 83/103
YORK-#3533399 – York Region - Sanitary Sewer Inspection, Testing and Acceptance Guideline (Formerly Commissioning Guideline),October 2011
11
4.5 Chimney Seal Leakage Test
If specified by the Municipality or their Qualified Representative, installed chimney seals (an internal flexible rubberframe seal) shall be tested in accordance with this guideline.
Install the chimney seal and only the bottom expansion band in accordance with the manufacturer’srecommendation. Fully tighten the bottom band. Do not install the top expansion band.
Pull the top of the seal away from the maintenance hole’s frame and pour approximately 4 litres of water behind theseal. Observe the bottom seal for a minimum of 1 minute for leakage. No leakage shall be allowed.
If the bottom expansion band holds water without leaking, the chimney seal will have passed the test.
If the bottom expansion band has any leakage during the test time, the chimney seal will have failed the test. TheContractor shall be required to remove, replace, or reposition the bottom expansion band and retest.
5. Groundwater Measurement
Whereby the groundwater table cannot be visually monitored in terms of elevation from the pipe, the Municipality or
a Qualified Representative may request that groundwater level be measured with piezometers placed inrepresentative locations throughout the length of sanitary sewers under construction.
The contractor shall provide all materials and equipment necessary for the construction of piezometers formeasuring groundwater level and equipment to measure the water level within the piezometer.
Piezometers shall be placed in the excavation alongside the sewer at approved locations.
Piezometers shall be constructed of 19mm PVC pipe and shall be equipped with 1.0m well screens or sections of aslotted PVC pipe at the end with gravel pack filled in around the screen to approximately 0.5m - 1m above and belowthe screen.
All casing and screen material shall be assembled and installed with sufficient care to prevent damage to the
sections and joints.
Prior to installation an end cap must be placed at the bottom of the PVC piping. During installation, a cap shall beplaced on top of the casing to avoid materials from entering the PVC piping.
A completed monitoring piezometer shall be sufficiently straight to allow passage of measuring devices.
Provide a Water Level Indicator designed to measure groundwater levels in small diameter tubes and piezometers.The cable reel device shall be equipped with a probe that on entry to water completes an electrical circuit and sendsa signal back to the reel where a light and audible buzzer are activated. The water level is then determined by takinga reading directly from the cable at the top of the piezometer casing. Prior, during and after testing of the sewer, thestatic water level shall be recorded.
8/9/2019 I I Reduction Strategy Annual Report 2012
http://slidepdf.com/reader/full/i-i-reduction-strategy-annual-report-2012 84/103
YORK-#3533399 – York Region - Sanitary Sewer Inspection, Testing and Acceptance Guideline (Formerly Commissioning Guideline),October 2011
12
6. Referenced Standards
1. OPSS 407 Construction Specification for Maintenance Hole, Catch Basin, Ditch Inlet and Valve Chamber
Installation
2. OPSS 409 Construction Specification for Closed-Circuit Television Inspection of Pipelines3. OPSS 410 Construction Specification for Pipe Sewer Installation in Open Cut
4. OPSS 412 Construction Specification for Sewage Forcemain Installation in Open Cut
5. ASTM C924 - 02(2009) Standard Practice for Testing Concrete Pipe Sewer Lines by Low-Pressure Air Test
Method
6. ASTM C969M - 02(2009) Standard Practice for Infiltration and Exfiltration Acceptance Testing of Installed
Precast Concrete Pipe Sewer Lines (Metric)
7. ASTM C 1103 Standard Practice for Joint Acceptance Testing of Installed Precast Concrete Pipe Sewer
Lines
8. ASTM F1417 - 11 Standard Test Method for Installation Acceptance of Plastic Gravity Sewer Lines Using
Low-Pressure Air
9. ASTM C1244M - 05ae1 Standard Test Method for Concrete Sewer Manholes by the Negative Air Pressure
(Vacuum) Test Prior to Backfill (Metric)10. Water Research Centre Publication Manual (WRc) Manual of Sewer Classification (3
rd Edition).
8/9/2019 I I Reduction Strategy Annual Report 2012
http://slidepdf.com/reader/full/i-i-reduction-strategy-annual-report-2012 85/103
YORK-#3533399 – York Region - Sanitary Sewer Inspection, Testing and Acceptance Guideline (Formerly Commissioning Guideline),October 2011
Appendix A:
York Region and Local Area Municipalities
Sanitary Sewer Inspection, Testing and
Acceptance Flow Charts for Concrete and Thermo‐
Plastic Pipes and Maintenance Holes
8/9/2019 I I Reduction Strategy Annual Report 2012
http://slidepdf.com/reader/full/i-i-reduction-strategy-annual-report-2012 86/103
YORK-#3533399 – York Region - Sanitary Sewer Inspection, Testing and Acceptance Guideline (Formerly Commissioning Guideline),October 2011
8/9/2019 I I Reduction Strategy Annual Report 2012
http://slidepdf.com/reader/full/i-i-reduction-strategy-annual-report-2012 87/103
YORK-#3533399 – York Region - Sanitary Sewer Inspection, Testing and Acceptance Guideline (Formerly Commissioning Guideline),October 2011
8/9/2019 I I Reduction Strategy Annual Report 2012
http://slidepdf.com/reader/full/i-i-reduction-strategy-annual-report-2012 88/103
YORK-#3533399 – York Region - Sanitary Sewer Inspection, Testing and Acceptance Guideline (Formerly Commissioning Guideline),October 2011
8/9/2019 I I Reduction Strategy Annual Report 2012
http://slidepdf.com/reader/full/i-i-reduction-strategy-annual-report-2012 89/103
YORK-#3533399 – York Region - Sanitary Sewer Inspection, Testing and Acceptance Guideline (Formerly Commissioning Guideline),October 2011
Appendix B:
Glossary of Terms
8/9/2019 I I Reduction Strategy Annual Report 2012
http://slidepdf.com/reader/full/i-i-reduction-strategy-annual-report-2012 90/103
YORK-#3533399 – York Region - Sanitary Sewer Inspection, Testing and Acceptance Guideline (Formerly Commissioning Guideline),October 2011
Borehole: A hole drilled into the earth into which well casings or piezometers may be installed.
CCTV: Closed‐circuit television. An inspection method using a closed‐circuit television camera system
with appropriate transport and lighting mechanisms to view the interior surface of sewer pipes and
structures.
CD: Compact disc.
Contract: An agreement between two or more parties, one that is written and enforceable by law; the
agreement between the municipality and the contractor for the construction of a sanitary sewer
system or components.
Contractor: A properly licensed individual of company that agrees to furnish labour, materials,
equipment and associated services to perform the work as specified for a specified price.
Crown: The top of the internal (the inside) cross section of the pipe.
Deflection: Any
change
in
the
inside
diameter
of
the
pipe
resulting
from
installation
and
imposed
loads. Deflection may be either vertical or horizontal and is usually reported as a percentage of the
base (un‐deflected) inside pipe diameter.
Exfiltration: Leakage or discharge of flows from sewer systems into the ground through leaks in pipes,
joints, Maintenance holes or other sewer system appurtenances.
Forcemain: A pipeline that conveys sewage from one area to another under pressurized flow. The
word "force" refers to the fact that the pipeline uses pressure, provided by pumping stations, rather
than gravity to move flows.
Good Practice: Is the proven and accepted methods, procedures, and practices that provide
appropriate, cost
‐effective,
and
well
‐documented
solutions
to
meet
user
‐requirements
and
compliance with applicable regulations.
Groundwater Level (table): Upper surface of the zone of saturation in permeable rock or soil.
Groundwater: All water under the surface of the ground whether in liquid or solid state. It originates
from rainfall or snowmelt that penetrates the layer of soil just below the surface.
Head: Fluid mechanical energy per unit weight of fluid, which correlates to the elevation that water
will rise to, also hydraulic head.
Hydrostatic Pressure: The pressure equal to that which is (or would be) induced by the weight of the
overlying column
of
water,
the
height
of
water
above
the
point
in
question.
Infiltration: The water entering a sewer system, including building sewers, from the ground through
such means as defective pipes, pipe joints, connections or maintenance hole walls. Flow deriving from
groundwater tends to be continuous and dependent on groundwater levels. Infiltration can
experience seasonal changes as the groundwater table varies. Infiltration does not include inflow
8/9/2019 I I Reduction Strategy Annual Report 2012
http://slidepdf.com/reader/full/i-i-reduction-strategy-annual-report-2012 91/103
YORK-#3533399 – York Region - Sanitary Sewer Inspection, Testing and Acceptance Guideline (Formerly Commissioning Guideline),October 2011
Inflow: Water other than wastewater that enters a wastewater system and building sewer from
sources such as roof leaders, cellar drains, yard drains, area drains, foundation drains, drains from
springs and swampy areas, maintenance hole covers, cross connections between storm drains and
sanitary sewers, catch basins, cooling towers, storm‐water, surface runoff, street wash waters, or
drainage
Inspection: The act of inspecting. An official examination or review of the work completed or in
progress to determine its compliance with contract requirements.
Invert: The lowest point of the internal cross section of a pipe or sewer.
Joint: The location at which two pieces of pipe or a pipe and a fitting are connected. The joint may be
made by a mechanical device, such as threads or ring seals, by heat fusion and cementing, or by
finished ends made to fit together (bell and spigot).
Lateral: Any pipe connected to the main sewer.
Maintenance (Manhole) Components: The sections of a maintenance hole include the base, riser
(which may include a conical section as the top riser), cover section (a conical section is built to
include the cover section), grade rings or chimney to adjust to final grade and the maintenance hole’s
frame and cover.
Maintenance Hole (Manhole): Sewer access large enough for a person to enter to troubleshoot
service problems or perform maintenance work.
Mandrel: Rigid device ‐ spindle or an axle – pulled through flexible thermo‐plastic pipe to test
alignment and deflection.
Monitoring Well: Well used to obtain water quality samples or measure groundwater levels.
Municipality: Corporation
of
a municipal
district
being
either
The
Regional
Municipality
of
York
or
one
of the nine local municipalities. The corporation that the provincial government, through an act of the
legislature, has granted decision‐making power over a part of the province.
Operator/Owner: Party that has operational control over construction plans and specifications,
including the ability to make modifications to those plans and specifications
Performance Test (Testing): Technical investigation done to determine or validate the characteristics
of the product under test.
Piezometer: Measuring device for groundwater level. This typically is an instrument that measures
fluid pressure or level at a given point.
Plastic: Material that contains as an essential ingredient one or more organic polymeric substances of
large molecular weights, is solid in its finished state, and, at some stage in its manufacture or
processing into finished articles, can be shaped by flow.
Qualified (Authorized) Representative: One hired by the owner or client to give professional advice
and may be a consultant hired by the Municipality. A qualified individual authorized by the owner to
assist in the administration of a specific construction contract.
8/9/2019 I I Reduction Strategy Annual Report 2012
http://slidepdf.com/reader/full/i-i-reduction-strategy-annual-report-2012 92/103
YORK-#3533399 – York Region - Sanitary Sewer Inspection, Testing and Acceptance Guideline (Formerly Commissioning Guideline),October 2011
Sanitary sewer: Sewer receiving and carrying liquid and water‐carried wastes under gravity flow, to
which storm, surface, or groundwater are not intentionally admitted.
Sewage (or wastewater) ‐ Used water and added waste of a community which is carried away by
drains and sewers
Sewer System:
Any
system
of
pipes,
drains,
pumping
works,
equipment,
structures,
and
other
things
used for the collection, transportation or disposal of wastewater, but does not include any building
drain, plumbing, or building sewer.
Specifications: Detailed, exact statement of particulars, especially statements prescribing materials
and methods, and quality of work for a specific project.
Standard: Prescribed, concise set of conditions and requirements that must be satisfied by a material,
product, process, procedure, convention, or test method, and the physical, functional, performance
and/or conformance characteristics thereof.
Thermo‐plastic: Plastic that repeatedly can be softened by heating and hardened by cooling through a
temperature range
characteristic
of
the
plastic,
and
that
in
the
softened
state
can
be
shaped
by
flow
into articles by molding or extrusion. Thermo‐plastic pipe is available in a variety of plastic
compositions including the most common in sewer systems being Polyvinyl chloride (PVC),
Polyethylene (PE), and Acrylonitrile‐butadiene‐styrene (ABS).
Visible Leak: Ingress or egress of water from the sewer system that can be seen by an inspection.
V‐Notch Weir: Structure, such as a bulkhead or plate, across the pipe to intercept the water flowing
down the pipe in order to determine flow rate. A V‐Notch weir has a specially shaped ‘V” opening or
notch. The V‐notch, sharp‐crested weir is especially good for measuring low flow rates.
Water‐Tightness: Put together in such a way that no water can get in or through‐ except in quantities
allowed
by
the
performance
test.
8/9/2019 I I Reduction Strategy Annual Report 2012
http://slidepdf.com/reader/full/i-i-reduction-strategy-annual-report-2012 93/103
Long Term Water Conservation Strategy and Inflow and Infiltration Strategy 86
Annual Report dated March 31, 2012
Appendix E:
Long Term
Water
Conservation Strategy
Annual Report to Council
8/9/2019 I I Reduction Strategy Annual Report 2012
http://slidepdf.com/reader/full/i-i-reduction-strategy-annual-report-2012 94/103
Environmental Services Committee 3March 7, 2012
THE REGIONAL MUNICIPALITY OF YORK
Environmental Services CommitteeMarch 7, 2012
Report of theCommissioner of Environmental Services
LONG TERM WATER CONSERVATION STRATEGY ANNUAL REPORT
1. RECOMMENDATION
It is recommended that:
1. The Regional Clerk circulate this report to the Clerks of the local municipalities andthe Director of Central Region at the Ontario Ministry of the Environment.
2. PURPOSE
The purpose of this report is to update Council on the status of water conservation andefficiency programs and the Long Term Water Conservation Strategy Annual Reportwhich meets the conditions of approval for the Southeast Collector Trunk SewerIndividual Environmental Assessment. York Region is the first Regional Municipality, inOntario, required by the Ministry of the Environment to meet such unique and stringentconditions related to water conservation.
3. BACKGROUND
Ministry of the Environment requires an annual report detailing progress ofthe Long Term Water Conservation Strategy to meet conditions of approvalfor the Southeast Collector Trunk Sewer Individual Environmental
Assessment
Approval of the Southeast Collector Trunk Sewer Individual Environmental Assessmentincluded several conditions regarding the development, implementation and monitoringof a Region-wide Water Conservation and Efficiency Strategy and Inflow and InfiltrationReduction Strategy. The environmental assessment conditions of approval also required
an annual report detailing the progress of implementing these Strategies which are to besubmitted to the Ministry of the Environment twelve months after finalizing the strategy.
On March 31, 2011 York Region submitted the Long Term Water Conservation Strategyto the Ministry of the Environment which met the environmental assessment conditionsof approval for the Southeast Collector Trunk Sewer. York Region will submit the firstannual report to the Ministry of the Environment on March 31, 2012 to provide an updateon the status of the targets and implementation plans set out in the Long Term Water
8/9/2019 I I Reduction Strategy Annual Report 2012
http://slidepdf.com/reader/full/i-i-reduction-strategy-annual-report-2012 95/103
Long Term Water Conservation Strategy Annual Report
Environmental Services Committee 4March 7, 2012
Conservation Strategy. Targets that are not met require mitigation plans to identifyenhanced initiatives to be implemented in order to meet the targets, including theresources available.
4. ANALYSIS AND OPTIONS
York Region is on schedule to meet targets set in the Long Term WaterConservation Strategy
The Long Term Water Conservation Strategy identifies five year targets and timelines fortotal water savings and residential per capita demand. The strategy also sets out theannual participation rates and program implementation status necessary to meet these fiveyear targets.
The Water for Tomorrow water-efficiency program is designed to provide the tools York
Region residents need to conserve water in the home, in the garden and at work.Participation in this program for 2011 is estimated to be saving 1.8 million litres of water per day (MLD). This is on track to meet the Long Term Water Conservation Strategytarget of 10 million litres of water saved per day by 2016 through existing York Regionled water conservation programs and 3.4 million litres of water from new programsidentified in the strategy.
Baseline residential per capita demand in 2011 was estimated to be 252 litres per capita per day (lpcd) in the Long Term Water Conservation Strategy. A summary of long termvision targets is shown in Table 1 below.
Table 1Long Term Water Conservation Strategy Targets
2011 2016 2021 2026 2031 2051
Long Term WaterConservation Strategy Target
252*lpcd
241lpcd
233lpcd
221lpcd
206lpcd
150lpcd
Total Estimated Water Savings13
MLD19
MLD34
MLD73
MLD244
MLD
*2011 value is baseline
Total water saved since Water for Tomorrow program began in 1998 is 24.2 million litresof water per day. That is equivalent to the average daily demand of approximately100,000 residents in York Region in 2011.
8/9/2019 I I Reduction Strategy Annual Report 2012
http://slidepdf.com/reader/full/i-i-reduction-strategy-annual-report-2012 96/103
Long Term Water Conservation Strategy Annual Report
Environmental Services Committee 5March 7, 2012
Collaboration with local municipalities to share water billing data overcamea major constraint identified in the Strategy
One of the main constraints identified in the Long Term Water Conservation Strategy
was the lack of access to water demand data collected from water meters as part of localmunicipal water billing practices. The Strategy stated that “securing access to usable,consistent water demand data is absolutely imperative for the effective execution andongoing monitoring of the Strategy”. Regional staff worked closely with each of the ninelocal municipalities to review water billing data for 2010 and to develop a process toshare data at regular intervals starting in 2012. Access to complete water demand data hasenabled the Region to begin to develop a more accurate breakdown of water demand bysector, including residential, industrial, commercial and institutional and non-revenuewater. A certain amount of non–revenue water is expected in municipal systems. Typicalnon-revenue water accounts for approximately 10-15 per cent of total flows in municipalsystems in Canada. Non-revenue water is water supplied, but not metered, for example
water used for emergency services such as firefighting, operational purposes such as proactive system maintenance flushing, loss due to leaks, etc.
Estimated total water demand by sector developed through preliminary analysis of 2010water billing data and York Region supply data is summarized by residential demand,industrial, commercial and institutional demand and non-revenue water in Table 2 below.
Table 22010 Water Demand by Sector
Sector Total 2010 Demand
Residential 213.8 MLDIndustrial, Commercial and Institutional 95.8 MLD Non-Revenue Water (system maintenance, fire fighting etc.) 30.1 MLD
Total Demand 339.7 MLD
As recommended in the 2009 Water and Wastewater Master Plan Update, the Long TermWater Conservation Strategy assumed total water demand split between residential andIndustrial, Commercial and Institutional demand was 67 per cent and 33 per centrespectively with non-revenue water assumed to be part of industrial, commercial and
institutional demand. Preliminary analysis of water billing data along with York Regionsupply data shows that the 2010 Regional demand breakdown for residential isapproximately 63 per cent with industrial, commercial and institutional demand at 28 percent and non-revenue water at 9 per cent.
Per capita demand targets in the Strategy are based on previously limited data availableand assumptions from the Water and Wastewater Master Plans. The Strategy forecastedthe 2011 residential water demand to be approximately 252 litres per person per day.
8/9/2019 I I Reduction Strategy Annual Report 2012
http://slidepdf.com/reader/full/i-i-reduction-strategy-annual-report-2012 97/103
Long Term Water Conservation Strategy Annual Report
Environmental Services Committee 6March 7, 2012
Analysis using water billing meter data readings along with updated population estimatesshow 2010 per capita residential demand is approximately 220 litres per person per day.
Further analysis of additional billing data will be conducted to confirm that the lower percapita demand is accurate and not an anomaly for 2010. The impact of a lower per capita
demand will result in a new 2011 baseline for water demand in York Region and requirestrategy targets to be updated.
Water for Tomorrow incentive programs saved 1.8 million li tres of water perday in 2011
Table 3 summarizes the targets of various incentive programs offered by York Region,2011 participation and estimated water saved from each program. Due to continuedsuccess of the residential toilet rebate program, program marketing for other rebatefixture programs has been limited to avoid budget constraints. Overall water savingscontinue to be on schedule to meet 2016 total water saved targets.
Table 3Water for Tomorrow Incentive Program Targets and 2011 Participation
Program Strategy Target 2011 Actual EstimatedWater Saved
(litres per day)
Residential Toilet Rebates 12,000 rebates 29,782 rebates 1,749,000
Single Family ResidentialHumidifier Rebates
1,000 rebates 57 rebates3,200
Multi-unit ResidentialWashing Machine Rebates
150 rebates 0 0
Rain Barrels Sales 4,000 rain barrels 2,778 rain barrels7,400
Industrial. CommercialInstitutional (ICI) ToiletRebates
6,250 rebates2 facilities,19 rebates
6,000
ICI Washing MachineRebates
120 rebates1 facility,10 rebates
2,700
ICI Water Audits andBuy Back
10 audits,1.5 buy back
9 audits complete,1 application for buy back pending
0
8/9/2019 I I Reduction Strategy Annual Report 2012
http://slidepdf.com/reader/full/i-i-reduction-strategy-annual-report-2012 98/103
Long Term Water Conservation Strategy Annual Report
Environmental Services Committee 7March 7, 2012
Total water saved in 2011 through Water for Tomorrow programs is approximately 1.8million litres of water per day, for a cumulative total of 24.2 million litres of water saved per day since program began in 1998. The total capital cost to implement these programsin 2011 was $3.68 million. In 2011 Water for Tomorrow programs cost approximately
$2.07 per litre of water saved per day.
Continual program evaluation and improvement ensures York Region stayson target
Mitigation plans for programs not meeting targets have been developed as required byMinistry of the Environment conditions of approval. Total rebate participants far exceedthe 2011 target. Staff will continue to monitor and evaluate the residential toilet rebate program against best in class jurisdictions and other Ontario municipalities to ensuretargets are met within annual budgets. Continued monitoring and evaluation of the potential uptake for all other incentive programs will result in increased marketing to
various sectors or, if required, an update of the targets based on the potential marketwithin York Region.
York Region’s standard for encouraging water efficient fixtures through incentive programs exceeds the requirements currently stipulated in the Ontario Building Code.Updates to the Ontario Building Code to incorporate higher efficiency fixtures couldallow York Region to target rebates to high water users. This could reduce the cost of therebate program by approximately $500,000 annually.
Based on high cost and low water savings, staff propose that rain barrelsubsidy and sales events be discontinued
Peer reviewers of the Long Term Water Conservation Strategy, including the Alliance forWater Efficiency, recommended the Region evaluate the efficacy of rain barrel salesevents as part of a water conservation program and consider discontinuing the incentive ifit does not prove to be cost effective. An evaluation of York Region rain barrel subsidyand sales events from 2009 to 2011 has demonstrated that due to high cost and low watersavings, rain barrels are not a cost effective component of York Region’s future waterconservation program.
• If used regularly, each participating household could save approximately 1,100 litres per year compared to one participating household changing from 13 litre toWaterSense® labelled toilets can save approximately 49,000 litres per year
• Based on surveys and inspections completed on randomly chosen participants eachyear, 77 per cent of rain barrels purchased at York Region events were installedwithin their first year
• Need for winter maintenance and re-installation of rain barrels lowers the likelihoodof installation each year
• Sales in 2011 declined significantly with only 2,778 out of 4,000 available rain barrels sold
8/9/2019 I I Reduction Strategy Annual Report 2012
http://slidepdf.com/reader/full/i-i-reduction-strategy-annual-report-2012 99/103
Long Term Water Conservation Strategy Annual Report
Environmental Services Committee 8March 7, 2012
Coordination of three sales events for 4,000 rain barrels cost $74,000. In addition, YorkRegion provided an average subsidy of $14 per rain barrel, putting the total cost of thesales events at $130,000. In 2011, the rain barrel program cost approximately $17.50 perlitre of water saved, this is considerably higher than the average cost for all Water for
Tomorrow programs of $2.07 per litre of water saved. Further, the significant drop ininterest for the 2011 sales events indicates that market saturation has been reached.
Over 13,000 rain barrels have been sold and raised the awareness of water conservationand summer water use. Rain barrel subsidies and sales events are not considered a costeffective program to reduce water demand and will no longer be offered as part of Water
for Tomorrow. Rain barrels are readily available at York Region retailers both online andseasonally in-store. Many sizes and varieties are available at costs ranging from $80 to$230. More cost effective programs to reduce outdoor water use are being developed as part of the Long Term water Conservation Strategy implementation plan.
Water for Tomorrow prov ides engaging education programs while seekingnew opportuni ties and partnerships
In addition to the ongoing successful education programs offered by Water for
Tomorrow, staff are collaborating with both Toronto Region Conservation Authority andLake Simcoe Region Conservation Authority to develop updated youth education programs.
Water savings resulting from education programs cannot be directly estimated in thesame manner as a fixture rebate. However, overall education contributes to lower percapita demand and is required to support water conservation program messaging anddrive long term behaviour changes necessary to meet long term goals. Education programs and targets set forth in the Strategy are summarized in Table 4 below.
Table 4Water for Tomorrow Education Program Summary
Program Strategy Target 2011 Actual
Water Efficiency Seminars 20 seminars 20 seminarsFree Landscape Visits 1,000 visits 821 visitsYork Children’s Water Festival 5,000 grade 4 students 5,000 grade 4 students
Free landscape visits have been offered through Water for Tomorrow for over ten yearsand popularity is beginning to decline. A more targeted approach to reduce outdoor wateruse is being developed as part of the Long Term water Conservation Strategyimplementation planning.
8/9/2019 I I Reduction Strategy Annual Report 2012
http://slidepdf.com/reader/full/i-i-reduction-strategy-annual-report-2012 100/103
Long Term Water Conservation Strategy Annual Report
Environmental Services Committee 9March 7, 2012
York Region s taff continue to improve programs targeting newdevelopment and municipal facilities
York Region currently has two sustainable development programs Sustainable HomesIncentive Program (SHIP) and Sustainable Development through LEED® aimed at low
density and high density respectively. Both of these programs provide an incentive ofwater and wastewater servicing allocation bonus and contain a strong water conservationcomponent.
In 2011, 218 high density housing units have been committed to be built as part of theRegion’s program. Developers have not yet committed to participating in the SHIP program. In November, 2011 Community Planning and Environmental Services staffheld a workshop with members of Building Industry and Land Development Association(BILD) to discuss challenges and opportunities for improving participation in YorkRegion’s programs. At minimum, the goal is to increase participation to meet targets ofthe Long Term Water Conservation Strategy and the Regional Official Plan.
Environmental Services and Property Services staff have begun to incorporate similarwater conservation measures, such as WaterSense® labelled fixtures and maximum flowrates into new municipal building standards and retrofit standards at York Regionfacilities.
Pilot projects prov ide an oppor tunity to test new and innovative programsin York Region
York Region has been conducting several pilot projects recommended in the Long TermWater Conservation Strategy, including a partnership with the Toronto RegionConservation Authority and the Town of Richmond Hill through the Sustainable Neighbourhood Retrofit Action Plan project in the Lake Wilcox community. This pilotincludes a “Front-yard Makeover” eco-landscape demonstration on two residential frontyards. The neighbourhood will be observed overtime to determine if the demonstrationfront-yards have influenced change within the neighbourhoods residential landscaping.
York Region is conducting an irrigation reduction pilot with ten industrial, commercialand institutional and multi-unit residential properties. The pilot includes a free analysis ofan automatic irrigation system, with recommendations to reduce water wasted throughirrigation technologies, equipment deficiencies and practices for each property. Anincentive is available on the purchase and installation of a controller, water savings willdocumented by a final audit. This pilot will wrap up in 2012 and if deemed a costeffective water conservation program, full implementation will follow in late 2012.
The Strategy recommends piloting an Expedited Approvals Process as an alternativeincentive for “green building” programs to the existing incentive available in SustainableDevelopment through LEED® and SHIP. The “York Region Innovative and SustainableDevelopment Approvals Project” application for funding was approved by the Provincein late 2011. The purpose of this pilot project is to test efficacy of employing an
8/9/2019 I I Reduction Strategy Annual Report 2012
http://slidepdf.com/reader/full/i-i-reduction-strategy-annual-report-2012 101/103
Long Term Water Conservation Strategy Annual Report
Environmental Services Committee 10March 7, 2012
expedited municipal planning approvals process as an incentive for builders anddevelopers to construct “green buildings” specific to the needs of York Region. TheRegion has partnered with the Toronto Region Conservation Authority on this project andis exploring opportunities for partnership with local municipalities and developers.
Water audit underway to identify prior ity areas for leak reduction
Water loss management is a key program component in the Long Term WaterConservation Strategy. The Region is currently conducting a water audit using theInternational Water Association and American Water Works Association best practicemethods to assess current levels of non-revenue water and water losses, includingleakage. The water audit will be distributed to local municipalities for review andcomment in April 2012. The results will identify priority municipalities to conduct adistribution system leak reduction program.
York Region continues to engage and seek input from the public during
implementation of the Strategy
As recommended in the Strategy, an essential part of creating a culture of waterconservation and efficiency in York Region is to establish a multi-stakeholder advisorycommittee to be a forum for ongoing advice, feedback and guidance to York Region withrespect to specific water conservation and efficiency projects. The role of the advisorycommittee will be to:
• Advise Region staff on strategies and approaches related to implementation of LongTerm Water Conservation Strategy
• Provide sector-specific insights and ideas
• Serve as water conservation program ambassadors to larger Regional community
•
Help identify champions in various sectors.
The advisory committee will specifically provide input related to:
• Public perception on programs, initiatives, and by-laws
• Enhancements or modifications to existing programs
• Increasing uptake in sector specific areas
• Public campaigns and messaging
Advisory committee members will include representatives from a wide range ofinterested and affected stakeholder organizations, as well as members of the public, a listof members is attached in Attachment 1. The advisory committee will meet six times per
year. The first meeting will be held in March 2012.
Link to Key Council–approved Plans
Integrating water conservation programming with water and wastewater infrastructure planning and sustainable community planning has been and continues to be a Regional priority. This commitment is reinforced in both the 2011-2015 Strategic Plan and theRegional Official Plan.
8/9/2019 I I Reduction Strategy Annual Report 2012
http://slidepdf.com/reader/full/i-i-reduction-strategy-annual-report-2012 102/103
Long Term Water Conservation Strategy Annual Report
Environmental Services Committee 11March 7, 2012
An objective of the Strategic Plan states that the Region will focus on continuing todeliver and sustain critical infrastructure necessary to support our growing communities by identifying and leveraging capacity available in the existing infrastructure. Onemethod to achieve this objective is through increased water conservation per capita.
An objective of the Regional Official Plan is to ensure adequate water resources fortoday’s residents and future generations, through conservation and efficiency.
• To develop a long term, innovative strategy for water conservation and efficiency
• To investigate full cost pricing of water, in co-operation with local municipalities, toencourage water conservation and facilitate system improvements
• To pursue with local municipalities and conservation authorities, the implementationof water efficiency innovations, such as water reuse systems, rainwater harvestingand innovative stormwater management
• To investigate innovative wastewater treatment technologies and approachesincluding grey water reuse, naturalized wastewater treatment and water recycling inresidential, commercial, institutional and industrial uses
The Regional Official Plan also highlights specific policies to ensure water conservationis integrated into new developments to create high-quality sustainable communities byencouraging new buildings to achieve greater water conservation efficiency thancurrently stipulated in the Ontario Building Code.
5. FINANCIAL IMPLICATIONS
Capital expenditures for water conservation programs in 2011 totalled $3.68 million, thisincluded the completion of the Long Term Water Conservation Strategy. The 2012 10-
year Capital Plan has committed to $40.8 million over 10 years to deliver waterconservation programming.
Water conservation programs are delivered at less than the cost of building or expandingwater systems. Between 1998 and 2004 the Regional Municipality of York Water for
Tomorrow conservation program deferred an estimated $40 million in new infrastructureat a cost of only $10 million. An analysis of the cost of programs recommended in theLong Term Water Conservation Strategy and their impact on deferring capital costs iscurrently under evaluation and will be available in the 2012 annual report to becompleted in March 2013. Reduced water use comes with increased pressure on waterrates. This will be considered as future updates on the rates are brought forward to
Council.
6. LOCAL MUNICIPAL IMPACT
Local municipal staff have been and will continue to be involved in developing andimplementing the Long Term Water Conservation Strategy. Local municipal staff playeda critical role in sharing water demand data collected through water billing to support the
8/9/2019 I I Reduction Strategy Annual Report 2012
http://slidepdf.com/reader/full/i-i-reduction-strategy-annual-report-2012 103/103
Long Term Water Conservation Strategy Annual Report
Region in meeting all Ministry of the Environment conditions. Accurately monitoring theamount of water saved will ensure that programs and initiatives remain on target now andin the future. To ensure ongoing success in water conservation is achieved, continuedcooperation by the local municipalities is essential.
It is the expectation of the Ministry of the Environment that the Region and localmunicipalities collaborate to deliver the program components outlined in the Long TermWater Conservation Strategy.
7. CONCLUSION
York Region is on track to meet the water saving targets outlined in the Long TermWater Conservation Strategy. Access to water data from the local municipalities hasallowed the Region to create a 2011 baseline for water demand by sector and residential per capita unit rate. The targets in the Long Term Water Conservation Strategy have been
updated to reflect the more accurate and baseline.
An annual report detailing status of the targets and implantation plan will be submitted tothe Ministry of the Environment and Southeast Collector Advisory Committee on March31, 2012, twelve months after submitting the Strategy.
For more information on this report, please contact Laura McDowell, Director,Environmental Promotion and Protection at 905-830-4444 Ext. 5077.
The Senior Management Group has reviewed this report.
Recommended by:
Erin Mahoney, M. Eng.
Approved for Submission:
Bruce Macgregor