I-81 Exit 114 Bridge Replacement Project RFQ Information ...

40
I-81 Exit 114 Bridge Replacement Project RFQ Information Meeting July 25, 2017 Phil Hammack, P.E. – Design Project Manager Stephen Kindy, P.E. – APD Division Project Manager and POC

Transcript of I-81 Exit 114 Bridge Replacement Project RFQ Information ...

I-81 Exit 114 Bridge

Replacement Project RFQ Information Meeting

July 25, 2017 Phil Hammack, P.E. – Design Project Manager Stephen Kindy, P.E. – APD Division Project Manager and POC

I-81 Bridge Replacement at Exit 114 Topics

• Project Location • Project Purpose & Need • Project Overview • RFQ Information Package • RFQ Summary • Questions / Answers

2

Project Location: I-81 Corridor Montgomery County & Town of Christiansburg

3

Project Location - Roadways

4

Montgomery County

Town of Christiansburg

Project Location - General Land Use

5

Harkrader Sports Complex

Christiansburg Middle School

Route 8 Donuts

Deli Mart - Citgo

Humane Society

Clayton Homes

International Church of the Foursquare Gospel (ICFG)

Residential Area

Residential Area

Residential Area

Page Cemetery

Unofficial PnR

Residential Area

Project Purpose & Need

6

• Bridges were constructed 1964.

• The bridges are structurally deficient

with sufficiency ratings of 35.8 for the NB bridge and 29.4 for the SB bridge. The deck and the superstructure have a general condition rating of 4. The substructure has a general condition rating of 5.

• Has fatigue prone details. Needs to be

inspected every 6 months. The bridges were painted in 1995.

• The minimum vertical clearance is 14’-

11” under NBL; 15’-02” under SBL. • The bridges have required deck patching

and other repairs several times since 2010 with the most recent instance being a deck patching operation on February 15, 2017.

Project Purpose & Need

7

Project Purpose & Need

8

Southbound

Northbound Some Past Repairs • 02/03/11 NB & SB • 05/25/11 NB • 06/23/11 NB • 07/06/11 NB • 07/14/11 NB • 07/21/11 NB • 07/28/11 NB • 08/04/11 NB • 03/24/15 SB • 06/15/15 SB • 07/02/15 SB • 03/08/16 SB • 02/15/17 SB

Project Overview

Environmental Document • Programmatic Categorical Exclusion (PCE) June 29, 2016

9

Project Overview - Environmental • T&E/TOYR - Bats • Streams & Wetlands

10

Project Overview - Environmental

• Asbestos Containing Material(s) (ACM)

11

Project Overview - Nearby Projects

• Christiansburg Wayfinding Signs

• I-81 NB Bridge over New River Replacement Exit 105 • Began Late 2016 • End Late 2020

12

Project Overview - Existing Features

13

OSS Crossover

4’ x 6’ Box Culvert

Woods Fill Site

C’burg San. Sewer Pump Station

Snyder-Hunt Property

Crossover

Springhouse

OHP

Traffic Camera

VDOT CMS Traffic Signal

Well

C’burg Waterline

Fiber Optic Lines

VDOT CMS

Phone/CATV

Project Overview - VDOT Facilities • I-81 NB Overhead Sign Structure

14

Project Overview - VDOT Facilities

• Traffic Camera

15

Project Overview - VDOT Facilities

• Changeable Message Signs

16

Project Overview - Utilities

• Appalachian Power Overhead Lines

17

Project Overview – Utilities • Lumos Networks Fiber

Optic Line

18

Project Overview - Utilities

• Citizens Telephone Cooperative Fiber Optic Line

19

Project Overview - Utilities • Verizon

• Christiansburg Waterline

20

Project Overview

• Replace Bridges I-81 over Route 8

• Maintain two lanes of traffic each direction during construction

• Maintain interchange function • Do NOT preclude future

interchange configurations • MASH compliant MGS

guardrail • Right of Way Acquisition • Employ “Common Sense

Engineering” (IIM-LD-255)

21

Project Overview • RFQ Project Limits:

From 0.381 Mi. South to 0.510 Mi. North of Christiansburg SCL

Approximately 0.891 Mi. RFQ reflects DPH design done to facilitate an additional lane in each

direction on I-81 with minimal rework as well as facilitate MOT during construction. This is reflected in the geometry of the ramps. Future ramp gores would require some regrading and paving. Of further note:

Full depth shoulders were provided to facilitate future widening and possible use for incidents, maintenance or as a congestion bypass.

More extensive (worst case) milling and paving limits were shown to provide new pavement and accommodate new pavement markings. This included the ramps, portions of accel./decel. lanes and tapers. The limits were squared across lanes for a clean project outline.

Ramp A (NB Exit) was shifted to facilitate future widening and led to the relocation of Flanagan Drive to maintain the minimum 100’ urban access control distance from ramp intersection return and to provide some additional queuing length for future Route 8/NB I-81 ramp intersection approach.

22

Project Overview

Traffic: I-81 (2014) AADT – 22,300 NB; 21,700 SB

I-81 (2040) AADT – 34,500 NB; 33,600 SB

I-81 Trucks – 27% NB; 24% SB

Route 8 (2014) AADT – 12,900

Route 8 (2040) AADT – 20,000

Route 8 Trucks – 3%

23

Project Overview

Scope / Design Features • Future - Interchange

Configuration Modification

• “Future” Route 8 & I-81 • I-81 Grade Adjustments

for new Bridges • Possible Karst

• Guide Signage • School Proximity

24

Project Overview • I-81 classified as an

Urban/Rural Interstate

• VDOT GS-5/GS-1 Design Standard

• Design Speed 70 mph

• Posted Speed 70 mph

• Design Year = 2040

• Existing Mainline has 2 – 12’ lanes in each direction

• Existing outside paved shoulder width is 10’

• Inside paved shoulder width is 3’

25

Project Overview • Route 8 classified as an Urban

Other Principal Arterial

• VDOT GS-5 Design Standard with shoulders

• Design Speed 35-40 mph

• Posted Speed 35 mph

• Design Year = 2040

• Substandard vertical clearance

• Existing Mainline has 2 – 12’ lanes in each direction

• Raised median with 10’ left turn lanes

26

Project Overview • Existing bridges two-

12’ lanes with 3’ shoulders & curb

• Existing bridge has rolled beams & plate girders

• Bridges will be widened to provide two-12’ lanes, 6’ inside & 12’ outside shoulder

27

RFQ Summary

• VDOT POC Stephen D. Kindy, PE Alternative Project Delivery Division 1401 East Broad Street Richmond, Virginia 23219 Phone: (804) 786-6016 Fax: (804) 786-7221 E-mail: [email protected]

• Two-Phase Best Value Procurement

• Short-List 3 Highest Ranked Teams

• Estimated Contract Value - $21,000,000

28

RFQ Information Package • RFQ Conceptual Plans

• Roadway Plan and Profile • Bridge

• Programmatic Categorical Exclusion, June 2016

• Preliminary Geotechnical Evaluation

• Survey

• Draft Interchange Modification Report

29

Anticipated Schedule (Section 2.5) • RFQ Questions to VDOT 08/11/2017

• VDOT Response to Questions 08/23/2017

• SOQ Submission Date 09/06/2017

• Notification of Shortlist 10/18/2017

• Anticipated RFP Release Date 10/26/2017

• Anticipated Award Date 05/16/2018

• Final Completion 08/06/2021

30

FORM C-78 (ATTACHMENT 2.10)

• Watch VDOT’s Design-Build RFQ website for responses to RFQ questions and Addendums http://www.virginiadot.org/business/request-for-qualifications.asp

• If VDOT issues an addendum, a revised C-78 form will be included with the addendum

• Sign, date and include the C-78 with SOQ

31

Contents of Statements of Qualifications (SOQ)

• Letter of Submittal (Section 3.2) POC, Surety, Prequalification, Debarment, SCC, DPOR, etc. Commitment to achieving a 8% DBE participation goal

• Offeror’s Team Structure (Section 3.3) Key Personnel

• Design Build Project Manager • Quality Assurance Manager • Design Manager • Construction Manager

Organizational Chart and Narrative Clear separation between QA and QC Production Forces

32

Contents of Statements of Qualifications (SOQ)

• Experience of Offeror’s Team (Section 3.4) Lead Contractor Work History Form Lead Designer Work History Form

• Project Risks (Section 3.5) Identify 3 Critical Project Risks

• Why is the risk critical? • What is the potential impact? • Mitigation strategies? • VDOT’s role?

33

Evaluation Criteria (Section 4)

• Offeror’s Team Structure 20% • Experience of Offeror’s Team 40% • Project Risks 40% Total 100%

• Scoring Range Application Numerical score based on a 1-10 scale Evaluation Criteria included in the RFQ for each submittal

requirement

• Design-Build Evaluation Guidelines, Revised May 2014 (On VDOT’S DB Website)

http://www.virginiadot.org/business/design-build.asp

34

Submittal Requirements (Section 5) • Deadline for submitting a Statement of Qualifications is

September 6, 2017 at 4:00PM

• 1 original paper version with original signatures

• 1 CD-ROM with entire SOQ

• 10 abbreviated paper copies

• Statements of Qualifications shall be: Securely bound No more than 15 pages Typed on one-side only Separated by numbered tabs Original shall include all required documentation Written in Times New Roman with a 12 point font Prepared on 8.5” x 11” white paper

35

RFQ Questions (Section 6)

• All questions and request for clarifications shall be submitted in writing to the VDOT POC.

• Deadline for submittal is August 11, 2017

• Responses will be posted on VDOT’s RFQ website by August 23, 2017

36

Structure Inspection Reports

• Critical Infrastructure Information/Sensitive Security Information (CII/SSI)

• CII/SSI Form to be Added to RFQ Webpage • Submit Completed Form to VDOT POC • VDOT to Supply:

• Latest Bridge Inspection Reports

37

Conflict of Interest (Section 11.2)

• The following firms have been determined to have a conflict of interest: • Mead & Hunt, Inc. T3 Design Corporation Hassan Water Resources, PLC

• Reynolds Smith and Hills, Inc. (RS&H) CES Consulting Services McCormick Taylor, Inc. Rice Associates, Inc. AI Engineers, Inc. Rice Associates, Inc. Fugro Consultants, Inc.

• Hurt & Proffitt, Inc. • Johnson, Mirmiran & Thompson (JMT) • Schwartz & Associates, Inc.

38

Conflict of Interest (Section 11.2)

• Each Offeror shall identify potential conflicts of interest. • See Alternate Project Delivery Office Memorandum IIM-APD-2.1 dated

October 8, 2015 http://www.virginiadot.org/business/resources/APD_Docs/APD_Office_Page/IIM-APD-2.1.pdf

• If a potential conflict of interest or competitive advantage is identified, the Offeror shall submit in writing the pertinent information to VDOT’s POC.

• Embedded Employees within VDOT may pose a potential Conflict of Interest.

39

Questions