I-81 Exit 114 Bridge Replacement Project RFQ Information ...
Transcript of I-81 Exit 114 Bridge Replacement Project RFQ Information ...
I-81 Exit 114 Bridge
Replacement Project RFQ Information Meeting
July 25, 2017 Phil Hammack, P.E. – Design Project Manager Stephen Kindy, P.E. – APD Division Project Manager and POC
I-81 Bridge Replacement at Exit 114 Topics
• Project Location • Project Purpose & Need • Project Overview • RFQ Information Package • RFQ Summary • Questions / Answers
2
Project Location - General Land Use
5
Harkrader Sports Complex
Christiansburg Middle School
Route 8 Donuts
Deli Mart - Citgo
Humane Society
Clayton Homes
International Church of the Foursquare Gospel (ICFG)
Residential Area
Residential Area
Residential Area
Page Cemetery
Unofficial PnR
Residential Area
Project Purpose & Need
6
• Bridges were constructed 1964.
• The bridges are structurally deficient
with sufficiency ratings of 35.8 for the NB bridge and 29.4 for the SB bridge. The deck and the superstructure have a general condition rating of 4. The substructure has a general condition rating of 5.
• Has fatigue prone details. Needs to be
inspected every 6 months. The bridges were painted in 1995.
• The minimum vertical clearance is 14’-
11” under NBL; 15’-02” under SBL. • The bridges have required deck patching
and other repairs several times since 2010 with the most recent instance being a deck patching operation on February 15, 2017.
Project Purpose & Need
8
Southbound
Northbound Some Past Repairs • 02/03/11 NB & SB • 05/25/11 NB • 06/23/11 NB • 07/06/11 NB • 07/14/11 NB • 07/21/11 NB • 07/28/11 NB • 08/04/11 NB • 03/24/15 SB • 06/15/15 SB • 07/02/15 SB • 03/08/16 SB • 02/15/17 SB
Project Overview - Nearby Projects
• Christiansburg Wayfinding Signs
• I-81 NB Bridge over New River Replacement Exit 105 • Began Late 2016 • End Late 2020
12
Project Overview - Existing Features
13
OSS Crossover
4’ x 6’ Box Culvert
Woods Fill Site
C’burg San. Sewer Pump Station
Snyder-Hunt Property
Crossover
Springhouse
OHP
Traffic Camera
VDOT CMS Traffic Signal
Well
C’burg Waterline
Fiber Optic Lines
VDOT CMS
Phone/CATV
Project Overview
• Replace Bridges I-81 over Route 8
• Maintain two lanes of traffic each direction during construction
• Maintain interchange function • Do NOT preclude future
interchange configurations • MASH compliant MGS
guardrail • Right of Way Acquisition • Employ “Common Sense
Engineering” (IIM-LD-255)
21
Project Overview • RFQ Project Limits:
From 0.381 Mi. South to 0.510 Mi. North of Christiansburg SCL
Approximately 0.891 Mi. RFQ reflects DPH design done to facilitate an additional lane in each
direction on I-81 with minimal rework as well as facilitate MOT during construction. This is reflected in the geometry of the ramps. Future ramp gores would require some regrading and paving. Of further note:
Full depth shoulders were provided to facilitate future widening and possible use for incidents, maintenance or as a congestion bypass.
More extensive (worst case) milling and paving limits were shown to provide new pavement and accommodate new pavement markings. This included the ramps, portions of accel./decel. lanes and tapers. The limits were squared across lanes for a clean project outline.
Ramp A (NB Exit) was shifted to facilitate future widening and led to the relocation of Flanagan Drive to maintain the minimum 100’ urban access control distance from ramp intersection return and to provide some additional queuing length for future Route 8/NB I-81 ramp intersection approach.
22
Project Overview
Traffic: I-81 (2014) AADT – 22,300 NB; 21,700 SB
I-81 (2040) AADT – 34,500 NB; 33,600 SB
I-81 Trucks – 27% NB; 24% SB
Route 8 (2014) AADT – 12,900
Route 8 (2040) AADT – 20,000
Route 8 Trucks – 3%
23
Project Overview
Scope / Design Features • Future - Interchange
Configuration Modification
• “Future” Route 8 & I-81 • I-81 Grade Adjustments
for new Bridges • Possible Karst
• Guide Signage • School Proximity
24
Project Overview • I-81 classified as an
Urban/Rural Interstate
• VDOT GS-5/GS-1 Design Standard
• Design Speed 70 mph
• Posted Speed 70 mph
• Design Year = 2040
• Existing Mainline has 2 – 12’ lanes in each direction
• Existing outside paved shoulder width is 10’
• Inside paved shoulder width is 3’
25
Project Overview • Route 8 classified as an Urban
Other Principal Arterial
• VDOT GS-5 Design Standard with shoulders
• Design Speed 35-40 mph
• Posted Speed 35 mph
• Design Year = 2040
• Substandard vertical clearance
• Existing Mainline has 2 – 12’ lanes in each direction
• Raised median with 10’ left turn lanes
26
Project Overview • Existing bridges two-
12’ lanes with 3’ shoulders & curb
• Existing bridge has rolled beams & plate girders
• Bridges will be widened to provide two-12’ lanes, 6’ inside & 12’ outside shoulder
27
RFQ Summary
• VDOT POC Stephen D. Kindy, PE Alternative Project Delivery Division 1401 East Broad Street Richmond, Virginia 23219 Phone: (804) 786-6016 Fax: (804) 786-7221 E-mail: [email protected]
• Two-Phase Best Value Procurement
• Short-List 3 Highest Ranked Teams
• Estimated Contract Value - $21,000,000
28
RFQ Information Package • RFQ Conceptual Plans
• Roadway Plan and Profile • Bridge
• Programmatic Categorical Exclusion, June 2016
• Preliminary Geotechnical Evaluation
• Survey
• Draft Interchange Modification Report
29
Anticipated Schedule (Section 2.5) • RFQ Questions to VDOT 08/11/2017
• VDOT Response to Questions 08/23/2017
• SOQ Submission Date 09/06/2017
• Notification of Shortlist 10/18/2017
• Anticipated RFP Release Date 10/26/2017
• Anticipated Award Date 05/16/2018
• Final Completion 08/06/2021
30
FORM C-78 (ATTACHMENT 2.10)
• Watch VDOT’s Design-Build RFQ website for responses to RFQ questions and Addendums http://www.virginiadot.org/business/request-for-qualifications.asp
• If VDOT issues an addendum, a revised C-78 form will be included with the addendum
• Sign, date and include the C-78 with SOQ
31
Contents of Statements of Qualifications (SOQ)
• Letter of Submittal (Section 3.2) POC, Surety, Prequalification, Debarment, SCC, DPOR, etc. Commitment to achieving a 8% DBE participation goal
• Offeror’s Team Structure (Section 3.3) Key Personnel
• Design Build Project Manager • Quality Assurance Manager • Design Manager • Construction Manager
Organizational Chart and Narrative Clear separation between QA and QC Production Forces
32
Contents of Statements of Qualifications (SOQ)
• Experience of Offeror’s Team (Section 3.4) Lead Contractor Work History Form Lead Designer Work History Form
• Project Risks (Section 3.5) Identify 3 Critical Project Risks
• Why is the risk critical? • What is the potential impact? • Mitigation strategies? • VDOT’s role?
33
Evaluation Criteria (Section 4)
• Offeror’s Team Structure 20% • Experience of Offeror’s Team 40% • Project Risks 40% Total 100%
• Scoring Range Application Numerical score based on a 1-10 scale Evaluation Criteria included in the RFQ for each submittal
requirement
• Design-Build Evaluation Guidelines, Revised May 2014 (On VDOT’S DB Website)
http://www.virginiadot.org/business/design-build.asp
34
Submittal Requirements (Section 5) • Deadline for submitting a Statement of Qualifications is
September 6, 2017 at 4:00PM
• 1 original paper version with original signatures
• 1 CD-ROM with entire SOQ
• 10 abbreviated paper copies
• Statements of Qualifications shall be: Securely bound No more than 15 pages Typed on one-side only Separated by numbered tabs Original shall include all required documentation Written in Times New Roman with a 12 point font Prepared on 8.5” x 11” white paper
35
RFQ Questions (Section 6)
• All questions and request for clarifications shall be submitted in writing to the VDOT POC.
• Deadline for submittal is August 11, 2017
• Responses will be posted on VDOT’s RFQ website by August 23, 2017
36
Structure Inspection Reports
• Critical Infrastructure Information/Sensitive Security Information (CII/SSI)
• CII/SSI Form to be Added to RFQ Webpage • Submit Completed Form to VDOT POC • VDOT to Supply:
• Latest Bridge Inspection Reports
37
Conflict of Interest (Section 11.2)
• The following firms have been determined to have a conflict of interest: • Mead & Hunt, Inc. T3 Design Corporation Hassan Water Resources, PLC
• Reynolds Smith and Hills, Inc. (RS&H) CES Consulting Services McCormick Taylor, Inc. Rice Associates, Inc. AI Engineers, Inc. Rice Associates, Inc. Fugro Consultants, Inc.
• Hurt & Proffitt, Inc. • Johnson, Mirmiran & Thompson (JMT) • Schwartz & Associates, Inc.
38
Conflict of Interest (Section 11.2)
• Each Offeror shall identify potential conflicts of interest. • See Alternate Project Delivery Office Memorandum IIM-APD-2.1 dated
October 8, 2015 http://www.virginiadot.org/business/resources/APD_Docs/APD_Office_Page/IIM-APD-2.1.pdf
• If a potential conflict of interest or competitive advantage is identified, the Offeror shall submit in writing the pertinent information to VDOT’s POC.
• Embedded Employees within VDOT may pose a potential Conflict of Interest.
39