I-70 Greenfield Rest Area Constructed Wetland Wastewater Treatment System Research Project

28
I-70 Greenfield Rest Area Constructed Wetland Wastewater Treatment System Research Project (SPR-2455, SPR-2456, SPR-2487) R. S. Govindaraju, J. E. Alleman, T. J. Cooper, T. P. Chan, V. Jain School of Civil Engineering Purdue University

description

I-70 Greenfield Rest Area Constructed Wetland Wastewater Treatment System Research Project. (SPR-2455, SPR-2456, SPR-2487) R. S. Govindaraju, J. E. Alleman, T. J. Cooper, T. P. Chan, V. Jain School of Civil Engineering Purdue University. Project Location. Project Overview. - PowerPoint PPT Presentation

Transcript of I-70 Greenfield Rest Area Constructed Wetland Wastewater Treatment System Research Project

Page 1: I-70 Greenfield Rest Area Constructed Wetland Wastewater Treatment System Research Project

I-70 Greenfield Rest AreaConstructed Wetland Wastewater Treatment System Research Project(SPR-2455, SPR-2456, SPR-2487)

R. S. Govindaraju, J. E. Alleman, T. J. Cooper,T. P. Chan, V. Jain

School of Civil EngineeringPurdue University

Page 2: I-70 Greenfield Rest Area Constructed Wetland Wastewater Treatment System Research Project

April 21, 2023 2

Project Location

Page 3: I-70 Greenfield Rest Area Constructed Wetland Wastewater Treatment System Research Project

April 21, 2023 3

Project Overview

Surcharges by City Unique challenges

Long (3+ miles) sewer line to City POTW Low flush toilets; flow restrictive faucets High strength wastes (BOD, Ammonia)

Pretreatment using constructed subsurface wetlands Biofield (and city sewer) for effluent disposal

Page 4: I-70 Greenfield Rest Area Constructed Wetland Wastewater Treatment System Research Project

April 21, 2023 4

Why Wetlands?

Conventional technologies Pros: proven technologies Cons: high capital and maintenance costs

Subsurface constructed wetlands Pros:

Low maintenance Aesthetic

Cons: Large footprint Lack of supporting data

Page 5: I-70 Greenfield Rest Area Constructed Wetland Wastewater Treatment System Research Project

April 21, 2023 5

Wastewater Charateristics

High strength BOD~450 mg/L NH3~150 mg/L

Flow rate Design: 10,000 GPD Peak: >20, 000 GPD

Page 6: I-70 Greenfield Rest Area Constructed Wetland Wastewater Treatment System Research Project

April 21, 2023 6

Treatment System Design

Features Functions/Benefits

2 10,000-gal septic tanks in series Primary treatment

2 parallel subsurface constructed wetlands (cells 1 & 2)~ alternately drained & filled~ 56 ft by 56 ft and 3 ft deep gravel beds with a peat moss top layer

Enhance oxygen transfer by constant draining and filling; thus promote nitrification and shorten designed hydraulic retention time

Recirculation of cells 1 & 2 effluent back to 2nd septic tank

Dilute high-strength wastewater; enhance mixing

Page 7: I-70 Greenfield Rest Area Constructed Wetland Wastewater Treatment System Research Project

April 21, 2023 7

Treatment System Design (con’t)Features Functions/Benefits

Polishing plug-flow wetland (cell 3)

~ 20 ft by 40 ft and 2 ft deep

gravel beds with a peat moss

top layer

Provide further treatment; allow comparison between plug-flow and draw-and-fill flow regimes

Biofield

~ elevated sand mound

seeded with prairie grass

~ bed area: 333 sq ft; basal

area: 1652 sq ft

Denitrification; disposal of treated effluent via evapotranspiration and infiltration to subsoil.

Page 8: I-70 Greenfield Rest Area Constructed Wetland Wastewater Treatment System Research Project

April 21, 2023 8

Instrumentations

Flow meters Magnetic flow meters for pressurized flow Flume and weir flow chambers with ultrasonic level sensors

for open channel (gravity) flows. Automatic samplers at various points of the system A weather station to measure rainfall, windspeed,

and temperature. Monitoring wells installed within the wetland cells

and also at the biofield.

Page 9: I-70 Greenfield Rest Area Constructed Wetland Wastewater Treatment System Research Project

April 21, 2023 9

Design Schematic

Magn.FlowMeter-2

Level Sensor w/ Flume-2

Level Sensor w/ Flume-3

Magn.Flow Meter-3

Auto. Sampler-4

Auto.Sampler-1

Auto.Sampler-3

Auto.Sampler-2

Magn.Flow Meter-1

RestStopBuilding(North Side)

FromSouth Side

Septic Tank 1

Level Sensorw/ Weir-1

P

P

P

P

WetlandCell No. 1

WetlandCell No. 2

To CityWastewater

WeatherStation-1

WetlandCell No. 3

Magn. Flow Meter-*

Septic Tank 2Magn. Flow Meter-4

Biofield

WaterSoftenerBldg

PVCPipes

Page 10: I-70 Greenfield Rest Area Constructed Wetland Wastewater Treatment System Research Project

April 21, 2023 10

1/17/2003

Page 11: I-70 Greenfield Rest Area Constructed Wetland Wastewater Treatment System Research Project

April 21, 2023 11

2/19/2003

Page 12: I-70 Greenfield Rest Area Constructed Wetland Wastewater Treatment System Research Project

April 21, 2023 12

4/15/2003

Page 13: I-70 Greenfield Rest Area Constructed Wetland Wastewater Treatment System Research Project

April 21, 2023 13

6/5/2003

Page 14: I-70 Greenfield Rest Area Constructed Wetland Wastewater Treatment System Research Project

April 21, 2023 14

6/5/2003

Page 15: I-70 Greenfield Rest Area Constructed Wetland Wastewater Treatment System Research Project

April 21, 2023 15

7/10/2003

Page 16: I-70 Greenfield Rest Area Constructed Wetland Wastewater Treatment System Research Project

April 21, 2023 16

7/10/2003

Page 17: I-70 Greenfield Rest Area Constructed Wetland Wastewater Treatment System Research Project

April 21, 2023 17

7/30/2003

Page 18: I-70 Greenfield Rest Area Constructed Wetland Wastewater Treatment System Research Project

April 21, 2023 18

8/12/2003

Page 19: I-70 Greenfield Rest Area Constructed Wetland Wastewater Treatment System Research Project

April 21, 2023 19

8/12/2003

Page 20: I-70 Greenfield Rest Area Constructed Wetland Wastewater Treatment System Research Project

April 21, 2023 20

9/25/2003

Page 21: I-70 Greenfield Rest Area Constructed Wetland Wastewater Treatment System Research Project

April 21, 2023 21

9/25/2003

Page 22: I-70 Greenfield Rest Area Constructed Wetland Wastewater Treatment System Research Project

April 21, 2023 22

9/25/2003

Page 23: I-70 Greenfield Rest Area Constructed Wetland Wastewater Treatment System Research Project

April 21, 2023 23

9/25/2003

Page 24: I-70 Greenfield Rest Area Constructed Wetland Wastewater Treatment System Research Project

April 21, 2023 24

Unfinished Items…

Installations of automatic samplers and weather stations

SCADA system Control, data logging and collection system Remote (web) access and control

Page 25: I-70 Greenfield Rest Area Constructed Wetland Wastewater Treatment System Research Project

April 21, 2023 25

What’s next?

Startup When? How?

Startup procedures (provided by RQAW) Who?

INDOT responsibilities … Purdue responsibilities …

Long-term monitoring

Page 26: I-70 Greenfield Rest Area Constructed Wetland Wastewater Treatment System Research Project

April 21, 2023 26

Research Activities

Dynamic model of the wetland hydraulics Alternate draw-and-fill scheme; time-varied inflow;

recirculation Model simulations

help formulate optimal managementstrategy

Page 27: I-70 Greenfield Rest Area Constructed Wetland Wastewater Treatment System Research Project

April 21, 2023 27

Research Activities (con’t)

Survey to rest area operators compare and evaluate the proposed system to

existing treatment technologies Tracer tests Evaluation of the effectiveness of the system Development of design guidelines for

constructed wetland systems with specific application in rest area facilities.

Page 28: I-70 Greenfield Rest Area Constructed Wetland Wastewater Treatment System Research Project

April 21, 2023 28

On the web

http://bridge.ecn.purdue.edu/~wetland