I-15 / LIMONITE AVENUE INTERCHANGE PROJECT PROPOSED IMPROVEMENTS The County of Riverside is proposing to improve the Limonite Interchange on Interstate 15. The improvements consist of a new 8-lane overcrossing, 3 through lanes in each direction plus 2 turn lanes, widening of the off-ramps from 2 to 4 lanes, the addition of 2 new loop on-ramps, and widening of Limonite Avenue to 4 lanes in each direction between Hamner Avenue and Wineville Avenue. Estimated Construction Cost: $48 Million EXISTING CONDITION/NEED Limonite Avenue is an east-west arterial roadway between Hamner Avenue and Wineville Avenue. West of the I-15 Interchange area, Limonite Avenue is a five-lane facility with three WB and two EB lanes. East of the interchange, Limonite Avenue is a four-lane facility with two WB and two EB lanes. In 2006, interim improvements to the interchange were made to widen the ramps and restripe the overcrossing to provide dual left turn lanes at the on-ramps. At that time, it was acknowledged that additional improvements would be needed to accommodate long range traffic forecasts. The Cities of Eastvale and Jurupa Valley are expected to grow and add new residences and businesses in the upcoming years, resulting in substantial traffic and circulation issues. The proposed I-15/Limonite Avenue interchange improvements are needed to alleviate the traffic congestion associated with the current and planned development. 15 15 I-15 NORTHBOUND I-15 SOUTHBOUND E V A E T I N O M I L E V A E T I N O M I L MAP NOT TO SCALE CITY OF EASTVALE CITY OF JURUPA VALLEY 33,050 VEHICLES Average Daily Traffic on Limonite Avenue Approximately 65,000 vehicles daily will be traveling Limonite Ave in 2035. PROJECT SCHEDULE Environmental Document March 2017 Approval Final Design March 2018 Utility Relocation April 2018 Construction Start Mid to Late 2018 PROJECT CONTACT John Marcinek Project Manager (951) 955-3727 [email protected] Website: RCProjects.org Hotline: (877) 672-7765

Transcript of I-15 / LIMONITE AVENUE INTERCHANGE...

I-15 / LIMONITE AVENUE INTERCHANGE PROJECT

PROPOSED IMPROVEMENTSThe County of Riverside is proposing to improve theLimonite Interchange on Interstate 15.The improvements consist of a new8-lane overcrossing, 3 throughlanes in each direction plus 2turn lanes, widening of the o�-rampsfrom 2 to 4 lanes, the addition of 2 new loopon-ramps, and widening of Limonite Avenue to4 lanes in each direction between Hamner Avenueand Wineville Avenue.

Estimated Construction Cost: $48 Million

EXISTING CONDITION/NEEDLimonite Avenue is an east-west arterial roadway between Hamner Avenue and Wineville Avenue. West of the I-15 Interchange area, Limonite Avenue is a five-lane facility with three WB and two EB lanes. East of the interchange, Limonite Avenue is a four-lane facility with two WB and two EB lanes. In 2006, interim improvements to the interchange were made to widen the ramps and restripe the overcrossing to provide dual left turn lanes at the on-ramps. At that time, it was acknowledged that additional improvements would be needed to accommodate long range tra�c forecasts. The Cities of Eastvale and Jurupa Valley are expected to grow and add new residences and businesses in the upcoming years, resulting in substantial tra�c and circulation issues. The proposed I-15/Limonite Avenue interchange improvements are needed to alleviate the tra�c congestion associated with the current and planned development.

15 15I-15 NORTHBOUND

I-15 SOUTHBOUND

EVA ETI

NO

MILE

VA ETIN

OMIL

MAP NOT TO SCALE

CITY OFEASTVALE

CITY OFJURUPA VALLEY

33,050 VEHICLESAverage Daily Tra�c on Limonite Avenue

Approximately 65,000 vehicles daily will betraveling Limonite Ave in 2035.

PROJECT SCHEDULEEnvironmental Document March 2017ApprovalFinal Design March 2018Utility Relocation April 2018Construction Start Mid to Late 2018

PROJECT CONTACTJohn MarcinekProject Manager

(951) [email protected]

Website: RCProjects.orgHotline: (877) 672-7765