Hydrothermal system operation planning considering hydroelectrical plant production non-linearities
Title:
André L. M. Marcato Tales P. Ramos Ivo Chaves da Silva Junior Bruno Henriques Dias Rafael B da Silva Brandi
Authors:
September, 2015
![Page 2: Hydrothermal system operation planning considering ... · 1 Hydrothermal system operation planning considering hydroelectrical plant production non-linearities Title: André L. M.](https://reader030.fdocuments.us/reader030/viewer/2022040709/5e0dce4b0fad1c110057dca2/html5/thumbnails/2.jpg)
• Introduction
• Proposed Methodology
• Problem Formulation
• Results
• Conclusion
Agenda
2
![Page 3: Hydrothermal system operation planning considering ... · 1 Hydrothermal system operation planning considering hydroelectrical plant production non-linearities Title: André L. M.](https://reader030.fdocuments.us/reader030/viewer/2022040709/5e0dce4b0fad1c110057dca2/html5/thumbnails/3.jpg)
Introduction
• Hydrothermal System
The main objective of the hydrothermal system operation planning is to minimize the expected operating cost of the system over
the considered period.
These costs are composed by thermal generation and deficit costs
3
![Page 4: Hydrothermal system operation planning considering ... · 1 Hydrothermal system operation planning considering hydroelectrical plant production non-linearities Title: André L. M.](https://reader030.fdocuments.us/reader030/viewer/2022040709/5e0dce4b0fad1c110057dca2/html5/thumbnails/4.jpg)
Brazilian System Characteristics
Fonte: PEN 2013, ONS
Installed Capacity 31/12/2017
Installed Capacacity 31/12/2012
4
![Page 5: Hydrothermal system operation planning considering ... · 1 Hydrothermal system operation planning considering hydroelectrical plant production non-linearities Title: André L. M.](https://reader030.fdocuments.us/reader030/viewer/2022040709/5e0dce4b0fad1c110057dca2/html5/thumbnails/5.jpg)
Introduction
5
![Page 6: Hydrothermal system operation planning considering ... · 1 Hydrothermal system operation planning considering hydroelectrical plant production non-linearities Title: André L. M.](https://reader030.fdocuments.us/reader030/viewer/2022040709/5e0dce4b0fad1c110057dca2/html5/thumbnails/6.jpg)
Introduction
6
SCHEMATIC DIAGRAM OF HYDRO PLANTS
![Page 7: Hydrothermal system operation planning considering ... · 1 Hydrothermal system operation planning considering hydroelectrical plant production non-linearities Title: André L. M.](https://reader030.fdocuments.us/reader030/viewer/2022040709/5e0dce4b0fad1c110057dca2/html5/thumbnails/7.jpg)
Introduction
• Brazilian Systems Uses:
Aggregation of the hydroelectric system into energy equivalent system.
Stochastic Dual Dynamic Programming (SDDP).
7
![Page 8: Hydrothermal system operation planning considering ... · 1 Hydrothermal system operation planning considering hydroelectrical plant production non-linearities Title: André L. M.](https://reader030.fdocuments.us/reader030/viewer/2022040709/5e0dce4b0fad1c110057dca2/html5/thumbnails/8.jpg)
8
Introduction • Energy Equivalent System
STORED ENERGY
HYDRAULIC GENERATION
ENERGY
SPILLED ENERGY
ENERGY INFLOW
Reservoir Run of River
![Page 9: Hydrothermal system operation planning considering ... · 1 Hydrothermal system operation planning considering hydroelectrical plant production non-linearities Title: André L. M.](https://reader030.fdocuments.us/reader030/viewer/2022040709/5e0dce4b0fad1c110057dca2/html5/thumbnails/9.jpg)
• Energy Equivalent System
9
Introduction
N NE
SE
S
Node
![Page 10: Hydrothermal system operation planning considering ... · 1 Hydrothermal system operation planning considering hydroelectrical plant production non-linearities Title: André L. M.](https://reader030.fdocuments.us/reader030/viewer/2022040709/5e0dce4b0fad1c110057dca2/html5/thumbnails/10.jpg)
10
MDDH
Graphical interface
Java
Kernel C++ Net Beans
Official Data (ONS ou CCEE)
• Windows or Linux • Parallel Processing (SDP
and SDDP) • Running Desktop
computer, remote or distributed
• Wind Plants and Solar Plants (under development)
• Synthetic Scenarios • Energy Equivalent
System, Individualized plants, Hybrid
Computational Platform
![Page 11: Hydrothermal system operation planning considering ... · 1 Hydrothermal system operation planning considering hydroelectrical plant production non-linearities Title: André L. M.](https://reader030.fdocuments.us/reader030/viewer/2022040709/5e0dce4b0fad1c110057dca2/html5/thumbnails/11.jpg)
11
Computational Platform
![Page 12: Hydrothermal system operation planning considering ... · 1 Hydrothermal system operation planning considering hydroelectrical plant production non-linearities Title: André L. M.](https://reader030.fdocuments.us/reader030/viewer/2022040709/5e0dce4b0fad1c110057dca2/html5/thumbnails/12.jpg)
Proposed Methodology The long term operation planning can carried out:
• only representation through energy equivalent systems; • part of the system is represented by energy equivalent systems and the
remaining system by individualized plants; • All hydro power plants are individualized
The planner can choose a point in the time horizon when, before this time a hybrid representation is used and after this time, the representation is by equivalent systems. For individualized plants, It is considered all non-linarites of the hydraulic production function
12
![Page 13: Hydrothermal system operation planning considering ... · 1 Hydrothermal system operation planning considering hydroelectrical plant production non-linearities Title: André L. M.](https://reader030.fdocuments.us/reader030/viewer/2022040709/5e0dce4b0fad1c110057dca2/html5/thumbnails/13.jpg)
13
Proposed Methodology • Temporal Coupling
Break Down Time
![Page 14: Hydrothermal system operation planning considering ... · 1 Hydrothermal system operation planning considering hydroelectrical plant production non-linearities Title: André L. M.](https://reader030.fdocuments.us/reader030/viewer/2022040709/5e0dce4b0fad1c110057dca2/html5/thumbnails/14.jpg)
14
Proposed Methodology
![Page 15: Hydrothermal system operation planning considering ... · 1 Hydrothermal system operation planning considering hydroelectrical plant production non-linearities Title: André L. M.](https://reader030.fdocuments.us/reader030/viewer/2022040709/5e0dce4b0fad1c110057dca2/html5/thumbnails/15.jpg)
15
Tucuruí Hydro Plant
Forth Degree Polynomial
Hydraulic Production Function- HFP
![Page 16: Hydrothermal system operation planning considering ... · 1 Hydrothermal system operation planning considering hydroelectrical plant production non-linearities Title: André L. M.](https://reader030.fdocuments.us/reader030/viewer/2022040709/5e0dce4b0fad1c110057dca2/html5/thumbnails/16.jpg)
16
Hydraulic Production Function - HFP
Flow rate or turbined flow
(m3/s)
Head (m)
The piecewise linear function must be a convex polynomial
![Page 17: Hydrothermal system operation planning considering ... · 1 Hydrothermal system operation planning considering hydroelectrical plant production non-linearities Title: André L. M.](https://reader030.fdocuments.us/reader030/viewer/2022040709/5e0dce4b0fad1c110057dca2/html5/thumbnails/17.jpg)
17
Hydraulic Production Function- HFP U
pstr
eam
quo
ta (m
)
Stored volume (hm3) Spilled Outflow (hm3) Turbined discharge (hm3)
Dow
nstr
eam
quo
ta (m
)
![Page 18: Hydrothermal system operation planning considering ... · 1 Hydrothermal system operation planning considering hydroelectrical plant production non-linearities Title: André L. M.](https://reader030.fdocuments.us/reader030/viewer/2022040709/5e0dce4b0fad1c110057dca2/html5/thumbnails/18.jpg)
Y
X X1 X2 X3 X4 X5 18
• Convex Hull Algorithm:
Hydraulic Production Function- HFP
![Page 19: Hydrothermal system operation planning considering ... · 1 Hydrothermal system operation planning considering hydroelectrical plant production non-linearities Title: André L. M.](https://reader030.fdocuments.us/reader030/viewer/2022040709/5e0dce4b0fad1c110057dca2/html5/thumbnails/19.jpg)
Y
X X1 X2 X4 X5 19
The HPF, determined by convex hull algorithm, must be shifted up or down in order to minimize
the mean square error
Hydraulic Production Function- HPF
![Page 20: Hydrothermal system operation planning considering ... · 1 Hydrothermal system operation planning considering hydroelectrical plant production non-linearities Title: André L. M.](https://reader030.fdocuments.us/reader030/viewer/2022040709/5e0dce4b0fad1c110057dca2/html5/thumbnails/20.jpg)
Problem Formulation • The SDDP is formulated as the following optimization
model:
20
subject to:
Hydraulic Balance
Load Balance
![Page 21: Hydrothermal system operation planning considering ... · 1 Hydrothermal system operation planning considering hydroelectrical plant production non-linearities Title: André L. M.](https://reader030.fdocuments.us/reader030/viewer/2022040709/5e0dce4b0fad1c110057dca2/html5/thumbnails/21.jpg)
21
Hydraulic Production Function - HPF
![Page 22: Hydrothermal system operation planning considering ... · 1 Hydrothermal system operation planning considering hydroelectrical plant production non-linearities Title: André L. M.](https://reader030.fdocuments.us/reader030/viewer/2022040709/5e0dce4b0fad1c110057dca2/html5/thumbnails/22.jpg)
Results
• Evaluation of the approximated HPF
22
![Page 23: Hydrothermal system operation planning considering ... · 1 Hydrothermal system operation planning considering hydroelectrical plant production non-linearities Title: André L. M.](https://reader030.fdocuments.us/reader030/viewer/2022040709/5e0dce4b0fad1c110057dca2/html5/thumbnails/23.jpg)
Results
• Evaluation of the approximated HPF
23
![Page 24: Hydrothermal system operation planning considering ... · 1 Hydrothermal system operation planning considering hydroelectrical plant production non-linearities Title: André L. M.](https://reader030.fdocuments.us/reader030/viewer/2022040709/5e0dce4b0fad1c110057dca2/html5/thumbnails/24.jpg)
Results – Brazilian System – Mean of Final Simualtion
– Time horizon: 5 years – Final simulation with 70 scenarios – All results corresponds to monthly mean
• Two Cases: – EQV: representation by energy equivalent systems
only;
– SE_FPH: only Southeast subsystem was individualized
24
![Page 25: Hydrothermal system operation planning considering ... · 1 Hydrothermal system operation planning considering hydroelectrical plant production non-linearities Title: André L. M.](https://reader030.fdocuments.us/reader030/viewer/2022040709/5e0dce4b0fad1c110057dca2/html5/thumbnails/25.jpg)
Results – Brazilian System
25
Monthly Mean of Stored Energy
Equivalent reservoir representation presents a higher stored energy when compared to the hybrid representation.
![Page 26: Hydrothermal system operation planning considering ... · 1 Hydrothermal system operation planning considering hydroelectrical plant production non-linearities Title: André L. M.](https://reader030.fdocuments.us/reader030/viewer/2022040709/5e0dce4b0fad1c110057dca2/html5/thumbnails/26.jpg)
Results – Brazilian System
26
Monthly Mean of Hydro Generation
There is no significant difference in both methods and the equivalent system is a little higher
![Page 27: Hydrothermal system operation planning considering ... · 1 Hydrothermal system operation planning considering hydroelectrical plant production non-linearities Title: André L. M.](https://reader030.fdocuments.us/reader030/viewer/2022040709/5e0dce4b0fad1c110057dca2/html5/thumbnails/27.jpg)
Results – Brazilian System
27
Monthly Mean of Thermal Generation
Equivalent representation presents a smaller amount. This is due to the higher hydro generation presented before.
![Page 28: Hydrothermal system operation planning considering ... · 1 Hydrothermal system operation planning considering hydroelectrical plant production non-linearities Title: André L. M.](https://reader030.fdocuments.us/reader030/viewer/2022040709/5e0dce4b0fad1c110057dca2/html5/thumbnails/28.jpg)
Results – Brazilian System
28
Monthly Mean of Spilled Energy
The spilled energy amount is higher when the southeast is modelled by individual plants
![Page 29: Hydrothermal system operation planning considering ... · 1 Hydrothermal system operation planning considering hydroelectrical plant production non-linearities Title: André L. M.](https://reader030.fdocuments.us/reader030/viewer/2022040709/5e0dce4b0fad1c110057dca2/html5/thumbnails/29.jpg)
Results - PMO 01/2014
29
Produtibility
![Page 30: Hydrothermal system operation planning considering ... · 1 Hydrothermal system operation planning considering hydroelectrical plant production non-linearities Title: André L. M.](https://reader030.fdocuments.us/reader030/viewer/2022040709/5e0dce4b0fad1c110057dca2/html5/thumbnails/30.jpg)
Conclusions
• Nowadays, with the hardware/software advances, we must invest in new approaches to use more and more the individualized representation instead of energy equivalent representation.
30
![Page 32: Hydrothermal system operation planning considering ... · 1 Hydrothermal system operation planning considering hydroelectrical plant production non-linearities Title: André L. M.](https://reader030.fdocuments.us/reader030/viewer/2022040709/5e0dce4b0fad1c110057dca2/html5/thumbnails/32.jpg)
Resultados PMO 01/2014
32
• Energia Armazenada
![Page 33: Hydrothermal system operation planning considering ... · 1 Hydrothermal system operation planning considering hydroelectrical plant production non-linearities Title: André L. M.](https://reader030.fdocuments.us/reader030/viewer/2022040709/5e0dce4b0fad1c110057dca2/html5/thumbnails/33.jpg)
Resultados PMO 01/2014
33
• Geração Hidráulica
![Page 34: Hydrothermal system operation planning considering ... · 1 Hydrothermal system operation planning considering hydroelectrical plant production non-linearities Title: André L. M.](https://reader030.fdocuments.us/reader030/viewer/2022040709/5e0dce4b0fad1c110057dca2/html5/thumbnails/34.jpg)
Resultados PMO 01/2014
34
• Déficit
![Page 35: Hydrothermal system operation planning considering ... · 1 Hydrothermal system operation planning considering hydroelectrical plant production non-linearities Title: André L. M.](https://reader030.fdocuments.us/reader030/viewer/2022040709/5e0dce4b0fad1c110057dca2/html5/thumbnails/35.jpg)
Resultados PMO 01/2014
35
• Déficit