hydro_roth_refurbishment.pdf
Transcript of hydro_roth_refurbishment.pdf
-
7/25/2019 hydro_roth_refurbishment.pdf
1/20
Scope and Options for RefurbishingExisting Facilities
UN Symposium on Hydropower and Sustainable
Development
Beijing, October 2004
Presentation by
Dr. Konrad RothPresident
Shanghai Hydro Equipment Company SHEC'[email protected]'
-
7/25/2019 hydro_roth_refurbishment.pdf
2/20
2
Table of Content
Technical Scope
Market Scope
Benefits and Costs
Procedural Options
-
7/25/2019 hydro_roth_refurbishment.pdf
3/20
3
Modernization (beyond maintenance) consists of:
Plant Rehabilitation to restore it to its original designperformance. Improves plant reliability and extendsservice life
Plant Upgrading is based on advances in technology,
design and materials since the plant was commissioned orits last rehabilitation. Improves plant efficiency, outputand reliability, extends service life and reduces losses
Plant Automation is the replacement of obsolete andunreliable control systems with up-to-date technology.Enables an older power plant to be operated with thesame degree of reliability/performance as a new plant
HYDRO POWER PLANT MODERNIZATION
SCOPE DEFINITIONS (I)
3
-
7/25/2019 hydro_roth_refurbishment.pdf
4/20
4
HYDRO POWER PLANT MODERNIZATION
SCOPE DEFINITIONS (II)
Time
Revenues
End of warrantyCommissioning
Upgrading
Rehabilitation
Breakdown Repair
Degradation
of condition
4
-
7/25/2019 hydro_roth_refurbishment.pdf
5/20
5
ITEMS* IN HYDRO PLANTS
THAT CAN BE MODERNIZED
3
2
4
5
68
4
9
7
1011. Gates
2. Penstocks
3. Inlet valve
4. Turbine5. Generator
6. Automation, Control & Protection
7. Medium Voltage Switchgear
8. Power Transformer
9. High Voltage Switchgear (GIS)
10.Transmission Line
*Other than civil works 5
-
7/25/2019 hydro_roth_refurbishment.pdf
6/20
6
Applicable new technologies in modernizing
Hydropower Plants:
VPI High Voltage Generator Insulation
New Hydraulic Shapes to improve
output and efficiency Use of surface coatings extend the Service
Intervals and slow down efficiency decline
Oil-free and Fish-friendly turbines
TECHNICAL INNOVATIONS
6
-
7/25/2019 hydro_roth_refurbishment.pdf
7/20
7
Paldang, Korea, 4 X 30 MW Bulb
Head Increase of 2.2 m
newanchorsnew
statornew wicket
gates new drafttube
Comprehensive Refurbishment with actual increases of 38% inenergy generation and 50% in installed capacity (Source: Alstom)
-
7/25/2019 hydro_roth_refurbishment.pdf
8/20
8
Upgrading of the Raccoon Mountain1900 MVA pumped storage plant (built 1979),Source: Voith Siemens Hydro
Project objectives:increase plant capacity as well as plant reliability
CASE STUDIES:
TENNESSEE VALLEY AUTHORITY (USA)
Key Project Data
Contract Award
Unit Output
Increase
Efficiency Increase
Others
Pump Turbines
January 1998
422 MW481 MW
1.62% - points (T)
1.55% - points (P)
New/revised
spherical valves
Generators-Motors
December 1998
425 MVA476 MVA
12%
Excessive vibrations
eliminated8
-
7/25/2019 hydro_roth_refurbishment.pdf
9/20
9
Why is Modernization favourable?
Investments with short amortization times
Efficiency improvement / output improvementReduction of the maintenance costs
Avoiding CO2 emissions
(Kyoto approach European / intl. emission trading - JI/CDM)
NO additional impact on the environment
Almost half of the total installed hydro capacity worldwide is older than30 years. And it pays to modernize existing hydro systems:
-
7/25/2019 hydro_roth_refurbishment.pdf
10/20
10
Market Scope
Global Annually Installed Capacity
0
5.000
10.000
15.000
20.000
25.000
30.000
1.930 1.940 1.950 1.960 1.970 1.980 1.990 2.000
AnnualCapacityAddition(MW
)
North America Europe South & Central AmericaAsia Excl. China China Middle East & Africa
The ageing of the existing installed base generatesThe ageing of the existing installed base generates
a strong underlying growth trend for modernisationa strong underlying growth trend for modernisation
-
7/25/2019 hydro_roth_refurbishment.pdf
11/20
11
Hydro Modernization
Market Scope
0
2.000
4.000
6.000
8.000
10.000
12.000
92 93 94 95 96 97 98 99 00 01 F02 F03 F04
Orders(MW)
MIDDLE EAST & AFRICA
CHINA
ASIA EXCL_ CHINA
SOUTH & CENTRAL AMERICA
EUROPE
NORTH AMERICA
Total Orders for Refurbishment Close to 10 GW p.a.Total Orders for Refurbishment Close to 10 GW p.a.
With 100 US$/kW this requires 1000 mUS$!With 100 US$/kW this requires 1000 mUS$!
NAM and Europe Remain the Main Markets (70% of Total)NAM and Europe Remain the Main Markets (70% of Total)
-
7/25/2019 hydro_roth_refurbishment.pdf
12/20
12
Certificate Subsidies Increase Market
Scope (Source: VA Tech)
Legal initiation through ROCs (=Renewable Obligation Certificates) in 2001.Increasing the share of renewable energies up to 2010 is subsidized.
Investments in the refurbishment of existing small hydropower plants.
CruachanOutput improvement:+30%
CO2 reduction:
130,000 t/year
GaurOutput improvement:+12%
CO2 reduction:
4,000 t/year
KilmorackOutput improvement:+5%
CO2 reduction:
4,800 t/year
AigasOutput improvement:+5%
CO2 reduction:
4,800 t/year
Output Improvement of Hydropower Plants in the UK
Refurbishment: Renewable Obligation Certificates
-
7/25/2019 hydro_roth_refurbishment.pdf
13/20
13
Plant modernization can extend plant capacity ata fraction of the cost of greenfield plant capacity.
For example, the USBR has undertaken a major programof upgrading its hydro power electrical systems at anaverage cost of US$ 69/KW
Example: Rehabilitating a Hydro Power Plant of 100 MW,producing 500 GWh per year,will cost about 8 - 15 m$ capital cost (80-150 US$/kW),generate a revenue of 15 m$ per year
for an operating cost as low as 2,5 m$ per year (no fuel cost)
Low capital cost MW - Low operating cost MWh
BENEFITS AND COSTS OFHYDROPOWER PLANT MODERNIZATION
13
-
7/25/2019 hydro_roth_refurbishment.pdf
14/20
14
Capacity (MW)
Max. Uprate
for Turbine
GeneratorLimit
Transformer
Limit
ExistingTurbine
60
50
58
52
1.25 Uprate Costs ($M).5 1.6
IRR=27%
IRR=30%
IRR=23%
New Runner New Transformer New Winding
SIMPLE EXAMPLE OF OPTIMIZATION
ANALYSIS FOR UPRATE
Source:14
-
7/25/2019 hydro_roth_refurbishment.pdf
15/20
15
TimeEnergy=f(Availability,P
erformance,H
ydrology)
Existing As-New Energy
Current Energy-Before Mod
Failure
Life Extension Benefit -Avoidance of Future Failure
Restoration Benefit -
from Current Energy to
As-New Levels
Optimization Benefit
Uprate Benefit
Uprated Energy
Anticipated Future Energy - without Mod.
Optimized Operational Energy
Cost
allocation
30 - 40 %
70 - 60 %
Source:
COST ALLOCATION TO SPECIFIC
ENERGY INCREASES
15
-
7/25/2019 hydro_roth_refurbishment.pdf
16/20
16
OPTIONS TO PROCEED
Assessment of a number of preselected plants forprioritizing the plants to be modernized accordingto the highest IRR
a) either through a Consultant
b) or in direct cooperation with one or more
potential supplier(s)
Result of the assessment phase:
scope and cost of modernization power output,revenues,operating cost schedule
IRR
16
-
7/25/2019 hydro_roth_refurbishment.pdf
17/20
17
EVALUATION OF ALTERNATIVES (I)
Alternative a): Consultant
independance of supply interests
standard procedure of development banks
integrated approach for all plant elements
suppliers special modernization know howintroduced only indirectly
scope/specification does not reflect special
supplier technologies contract wording and performance inherently based
on diverging interests of customer,consultant andsupplier
17
-
7/25/2019 hydro_roth_refurbishment.pdf
18/20
18
EVALUATION OF ALTERNATIVES (II)
Alternative b): Supplier
special suppliers know how and technologies lead to
optimized scope and most precise cost information
performance based contract with bonus/malus system leads tocommon interests of customer and supplier during contract
execution in achieving highest IRR
shortening of time to re-commissioning by approx. one yearincreases return
corresponds to + of alternative a) 18
-
7/25/2019 hydro_roth_refurbishment.pdf
19/20
19
Assumptions
20 MW Plant
50% Capacity Factor
Average Value of Incremental Generation = $30/MW-HR
Total Project Value = $4M (Life Extension & Uprate)
Calculations
Capacity Increase
10% 15% 20%MW 2 3 4
MW-HRS 8,760 13,140 17,520
Revenue $263K $394K $525,600
% of Total Contract(Life Extension & Uprate)
7% 10% 13%
EXAMPLE OF SAVINGS FOR BEING
ONE YEAR EARLIER ON LINE
19
-
7/25/2019 hydro_roth_refurbishment.pdf
20/20
20
EVALUATION OF ALTERNATIVES (III)
Possible solution for combining advantages of a) and b):
consultant responsible for the overall project managementintegrating the environmental and regulatory tasks,the civilconstruction tasks and the equipment tasks
equipment tasks (starting with the assessment) performedon the basis of performance based contracting
different suppliers work on different projects
competitive benchmark of results (IRRs) before approval
of project execution 20