CHAPTER 3 : HYDROGRAPHIC SURVEY Prepared By: Asst. Prof. Pramesh Hada MSC in Urban Planning B.E In Civil Asst. Professor, Civil Engineering Dept. Nepal Engineering College

Transcript of Hydrographic survey for std not print

Page 1: Hydrographic survey for std not print

CHAPTER 3 : HYDROGRAPHIC

SURVEYPrepared By:

Asst. Prof. Pramesh Hada

MSC in Urban Planning

B.E In Civil

Asst. Professor, Civil Engineering Dept.

Nepal Engineering College

Page 2: Hydrographic survey for std not print

CONTENTS

� 3.1 Introduction, Definition of Basic Terms(pu08)

� 3.2 Vertical & Horizontal Controls

� 3.3 Equipment & Methods of

Sounding(pu06,07,09,10,11,14)

� 3.4 Measurement of Cross-Section

� 3.5 Measurement of Velocity & Flow (pu07,09)

Er. P

ramesh Hada, Asst. P

rof, civ

il

Engineering Departm

ent,nec

� 3.5 Measurement of Velocity & Flow (pu07,09)

� 3.6 Instruction on Field Works

Er. P

ramesh Hada, Asst. P

rof, civ

il

Engineering Departm

ent,nec

Page 3: Hydrographic survey for std not print

3.1 INTRODUCTION, DEFINITION OF BASIC TERMS

HYDROGRAPHY

� Branch of science that deals with themeasurement of bodies of water.

� Is the branch of applied sciences whichdeals with the measurement anddescription of the physical features ofoceans, seas, coastal areas, lakes andrivers, as well as with the prediction of

Er. P

ramesh Hada, Asst. P

rof, civ

il

Engineering Departm

ent,nec

rivers, as well as with the prediction oftheir change over time, for the primarypurpose of safety of navigation and insupport of all other marine activities,including economic development,security and defence, scientific research,and environmental protection.

� Is a important tool for hydrologicstudies.

Er. P

ramesh Hada, Asst. P

rof, civ

il

Engineering Departm

ent,nec

Page 4: Hydrographic survey for std not print

HYDROGRAPHY

� Hydrographic surveying deals with the configurationof the bottom and adjacent land areas of oceans,lakes, rivers, harbors and other water forms onEarth.

� In strict sense, it is defined merely as the surveyingof a water area; however, in modern usage it mayinclude a wide variety of other objectives.

- such as measurements of tides, current, gravity, earthmagnetism, and determinations of the physical and a

da,Asst.

Prof,civil

artm

ent,nec

magnetism, and determinations of the physical andchemical properties of water.

� The principal objective of most hydrographic surveys, is to obtain basic data for the compilation of nautical charts with emphasis on the features that may affect safe navigation.

� Other objectives include acquiring the information necessary for related marine navigational products and

for coastal zone management, engineering, and science

Er.Pramesh

Engineering

Page 5: Hydrographic survey for std not print

SIGNIFICANCE OF HYDROGRAPHIC SURVEY

PU 2006,2007,2008

The Purpose of hydrographic survey are as follows:

� Used for controlling and planning of engineering projects

like bridge,dams,tunnels,reservoirs,harbours etc.

� To determine mean sea level and observation of tides.

� For the measurement of discharge of rivers.

� For the measurement of areas subjected to scour or silting

ada,Asst.

Prof,civil

artm

ent,nec

� For the measurement of areas subjected to scour or silting

and to ascertain the quantities of degraded material.

� For the determination of shore lines.

� For making subsequent investigation to secure information

needed for the construction, development & improvement

of port facilities.

� Determination of coastal erosion, silting.

� Determination of site of construction of harbours,

dockyards.

Er.Pramesh

Engineering

Page 6: Hydrographic survey for std not print

ada,Asst.

Prof,civil

artm

ent,nec

Er.Pramesh

Engineering

Page 7: Hydrographic survey for std not print

ada,Asst.

Prof,civil

artm

ent,nec

Er.Pramesh

Engineering

Page 8: Hydrographic survey for std not print

BASIC TERMS

� Sounding : A Measurement of depth of water.

� Harbour : A place where ships are parked for cargo

& others.

� Reef : A submerged ridge of rock near the surface of

the water

�M.S.L (Mean Sea level) : Average of Sea level,

Height according to mean sea level

Er. P

ramesh Hada, Asst. P

rof, civ

il

Engineering Departm

ent,nec

Height according to mean sea level

Er. P

ramesh Hada, Asst. P

rof, civ

il

Engineering Departm

ent,nec

Page 9: Hydrographic survey for std not print

Er. P

ramesh Hada, Asst. P

rof, civ

il

Engineering Departm

ent,nec

Er. P

ramesh Hada, Asst. P

rof, civ

il

Engineering Departm

ent,nec

Page 10: Hydrographic survey for std not print

Er. P

ramesh Hada, Asst. P

rof, civ

il

Engineering Departm

ent,nec

Er. P

ramesh Hada, Asst. P

rof, civ

il

Engineering Departm

ent,nec

Page 11: Hydrographic survey for std not print

Er. P

ramesh Hada, Asst. P

rof, civ

il

Engineering Departm

ent,nec

Er. P

ramesh Hada, Asst. P

rof, civ

il

Engineering Departm

ent,nec

Page 12: Hydrographic survey for std not print

3.2 VERTICAL & HORIZONTAL CONTROLS� Vertical control – Depth Calculated (R.l calculated)

� Horizontal control – Northing and Easting calculated (X & Y)

The main objective in hydrographic surveying is to determine the

depth of water at a certain point.

�Hence Sounding is the measurement of depth below the water

surface.

�For Sounding, A vertical control is needed and to locate the

sounding, a horizontal control is needed.

Horizontal control may consist of either a triangulation or a

Er. P

ramesh Hada, Asst. P

rof, civ

il

Engineering Departm

ent,nec

�Horizontal control may consist of either a triangulation or a

traverse. Triangulation may have to be employed for horizontal

connection of widely seperated points.

�Traverse may be done by chain,tape, plane tabling or by theodolite,

depending upon the stations.

�Hence the underwater & near water points may be located with

reference to the traverse or triangulation.

�Vertical connection may be affected by the determination of the

depth of the point below the water surface. Such determinations are

known as “Soundings”.

Er. P

ramesh Hada, Asst. P

rof, civ

il

Engineering Departm

ent,nec

Page 13: Hydrographic survey for std not print

3.3 EQUIPMENTS NEEDED FOR SOUNDING (IMP)� Sounding Boat

� Sounding Poles

� Lead lines

� Sounding Machine

� Eco – Sounding (Fathometer)

� Sounding Boat

� Used for taking sounding.

Er. P

ramesh Hada, Asst. P

rof, civ

il

Engineering Departm

ent,nec

� Used for taking sounding.

� should be sufficiently spacious and stable.

� For quiet water. a flat bottom boat is more suitable, but for rough water round-bottomed boat is more suitable.

� For regular soundings, a row boat may be provided with a well through which soundings are taken.

� Should be extended far enough over the side to prevent the line from striking the boat.

Er. P

ramesh Hada, Asst. P

rof, civ

il

Engineering Departm

ent,nec

Page 14: Hydrographic survey for std not print

Er. P

ramesh Hada, Asst. P

rof, civ

il

Engineering Departm

ent,nec

Er. P

ramesh Hada, Asst. P

rof, civ

il

Engineering Departm

ent,nec

Page 15: Hydrographic survey for std not print

SOUNDING POLES/RODSEr. P

ramesh Hada, Asst. P

rof, civ

il

Engineering Departm

ent,nec

� Is a pole of a sound straight-grained well

seasoned tough timber usually 5 to 8 cm in

diameter and 5 to 8 metre long.

� Suitable for shallow and quiet waters.

� An arrow or lead shoe of sufficient weight

is fitted at the end.

Helps in holding them upright in water.

Er. P

ramesh Hada, Asst. P

rof, civ

il

Engineering Departm

ent,nec

� Helps in holding them upright in water.

� lead or weight should be of sufficient area

so that it may not sink in mud or sand.

� Pole of 6 m can be used to depths upto 4

metres.

Page 16: Hydrographic survey for std not print

Er. P

ramesh Hada, Asst. P

rof, civ

il

Engineering Departm

ent,nec

Er. P

ramesh Hada, Asst. P

rof, civ

il

Engineering Departm

ent,nec

Page 17: Hydrographic survey for std not print

LEAD LINES

� lead line or a sounding line is usually a length of a such cord, or a brass chain with a sounding lead attached to the end.

� Due to prolonged use, a line of hemp or cotton is liable to get stretched.

� It should be soaked in water for about one hour before it is used for taking soundings.

� length of the line should be tested frequently with a tape.

Er. P

rameshHada

Engineering Departm

ent,nec

tape.

� For regular sounding. a chain of brass, steel or iron is preferred.

� usually used for depths over about 6 metres.

� Sounding lead is a weight (made of lead) attached to the line.

� weight is conical in shape and varies from 4 to 12 kg depending upon the depth of water and the strength of the current.

� often has cup-shaped cavity at the bottom.

Hada, Asst. P

rof, civ

il

Departm

ent,nec

Page 18: Hydrographic survey for std not print

Er. P

ramesh Hada, Asst. P

rof, civ

il

Engineering Departm

ent,nec

Er. P

ramesh Hada, Asst. P

rof, civ

il

Engineering Departm

ent,nec

Page 19: Hydrographic survey for std not print

SOUNDING MACHINE

� Where much of sounding is to be done, asounding machine as very useful.

� May either be hand driven or automatic. Fig.1 shows a typical hand driven Weddele’ssounding machine.

� lead weight is carried at the end of a flexiblewire cord attached to the barrel and can belowered at any desired rate, the speed of thedrum being controlled by means of a brake.

Er. P

ramesh Hada, Asst. P

rof, civ

il

Engineering Departm

ent,nec

drum being controlled by means of a brake.

� Readings are indicated in two dials — theouter dial showing the depth in feet and theinner showing tenths of a foot.

� Handle is used to raise the level which can besuspended at any height.

� Is mounted in a sounding boat and can beused up to a maximum depth of 100 ft.

Er. P

ramesh Hada, Asst. P

rof, civ

il

Engineering Departm

ent,nec

Page 20: Hydrographic survey for std not print

Er. P

ramesh Hada, Asst. P

rof, civ

il

Engineering Departm

ent,nec

Er. P

ramesh Hada, Asst. P

rof, civ

il

Engineering Departm

ent,nec

Page 21: Hydrographic survey for std not print

ECO – SOUNDING (FATHOMETER) (V.V.IMP)

� Echo sounder is used for measuring depths of large rivers, in excess of 10 m, and those of seas.

� Eco sounding is a technique of using sound pulse to find the depth of water.

� Is an electrical instrument, in which a sound impulse from the surface of water is Sent towards the bottom of the river or sea (Fig. 13.8).

� Sound waves are reflected back From the bed in the form of an echo which is arrested

Er. P

ramesh Hada, Asst. P

rof, civ

il

Engineering Departm

ent,nec

� Sound waves are reflected back From the bed in the form of an echo which is arrested by the receiver.

� There is an automatic recording of the time of onward and backward travel of the sound wave.

� Taking the velocity of sound in water to be approximately 1470 m/s, the depth of water can be computed.

� Generally the echo sounder is placed just at the water level to eliminate transmission loss and obtain an accurate result.

Er. P

ramesh Hada, Asst. P

rof, civ

il

Engineering Departm

ent,nec

Page 22: Hydrographic survey for std not print

ECO – SOUNDING (FATHOMETER)� Uses for Ocean sounding where depth is too much.

� It is adjusted to read depth in accordance with the velocity of sound in the type of water in which it is being used.

� For Eco sounding Instrument called “Fathometer” is used.

� A fathometer may indicate the depth visually or indicate graphically on a roll which

Er. P

ramesh Hada, Asst. P

rof, civ

il

Engineering Departm

ent,nec

or indicate graphically on a roll which continuously goes on revolving and provide a virtual of the lake or sea.

� The main parts of echo-sounding apparatus are : 1. Transmitting and receiving oscillator. 2. Recorder Unit 3. Transmitter/Power unit

Er. P

ramesh Hada, Asst. P

rof, civ

il

Engineering Departm

ent,nec

Page 23: Hydrographic survey for std not print

PRINCIPLE OF ECO SOUNDINGEr. P

ramesh Hada, Asst. P

rof, civ

il

Engineering Departm

ent,nec

•Fig Below illustrates, the principle of

echo sounding.

•Consists in recording the interval of

time between the emission of a sound

impulse direct to the bottom of the sea

and the reception of the wave or echo

reflected from the bottom.

•If the speed of sound in that water is V

and time interval between the

Er. P

ramesh Hada, Asst. P

rof, civ

il

Engineering Departm

ent,nec

and time interval between the

transmitter and receiver is t, then the

depth is given by , h = 1/2(Vt)

•Velocity varies with salinity & temp. of

sea water, so accoustic velocity in sea

water is -

S – in terms of per 1000.

Page 24: Hydrographic survey for std not print

ADVANTAGES OF ECO SOUNDING

It has the following advantages over the older method of lead

line and rod :

� Used when a strong current is running and when the

weather is unsuitable for the soundings to be taken with the

lead line & other methods.

� Is more accurate as a truly vertical sounding is obtained.

Under normal water conditions in ports and harbours an

accuracy of 7.5 cm may be obtained.

Er. P

ramesh Hada, Asst. P

rof, civ

il

Engineering Departm

ent,nec

accuracy of 7.5 cm may be obtained.

� Is more sensitive than the lead line.

� Record of the depth is plotted immediately and provides a

continuous record of the bottom as the vessel moves forward.

� Speed of sounding and plotting is increased.

� Error due to estimation of water level in a choppy

sea(irregular) is reduced owing to the instability of the boat.

Er. P

ramesh Hada, Asst. P

rof, civ

il

Engineering Departm

ent,nec

Page 25: Hydrographic survey for std not print

Er. P

rameshHada

Engineering Departm

ent,nec

�Shorelines are where oceans and seas meet land.

�The change is abrupt and sudden.

Hada, Asst. P

rof, civ

il

Departm

ent,nec

Page 26: Hydrographic survey for std not print

METHODS OF LOCATING SOUNDING

� Soundings are located with reference to the shore traverse by observations made (I) entirely from the boat, (ii) entirely from the shore or (iii) from both,

The following are the methods of location

1. By cross rope 2. By range and time intervals

Er. P

ramesh Hada, Asst. P

rof, civ

il

Engineering Departm

ent,nec

2. By range and time intervals

3. By range and one angle from the shore 4. By range and one angle from the boat 5. By two angles from the shore 6. By two angles from the boat 7. By one angle from shore and one from boat 8. By Intersecting ranges 9. By tacheometric Observation

Er. P

ramesh Hada, Asst. P

rof, civ

il

Engineering Departm

ent,nec

Page 27: Hydrographic survey for std not print

1. Location by Cross Rope

� most accurate method of locating the soundings and may be used for

rivers, narrow lakes and for harbors.

� Used to determine the quantity of materials removed by dredging,

the soundings being taken before and after the dredging work is

done. (dredging - Remove with a power shovel, usually from a bottom of a body of

water)

� Single wire or rope is stretched across the channel and is marked by

metal tags at appropriate known distance along the wire from a

reference point or zero station on shore.

Er. P

rameshHada, A

Engineering Departm

Methods of Locating Sounding

reference point or zero station on shore.

� The soundings are then taken by a weighted pole.

� The position of the pole during a Sounding is given by the

graduated rope or line.

, Asst. P

rof, civ

il

rtment,nec

Page 28: Hydrographic survey for std not print

2) Location by range and time interval :

� Method used when the width of channel is small and when great degree of accuracy is not required.

� In this method, boat is kept in range with the two signals on the shore and is rowed along it at constant speed.

� soundings are taken at different time intervals, knowing the constant speed and the total time elapsed at the instant of sounding.

� Distance of the total point can be known along the range.

Er. P

ramesh Hada, Asst. P

rof, civ

il

Engineering Departm

ent,nec

Methods of Locating Sounding

3. By range and one angle from the shore

� Boat is ranged in line with the two shore signals and rowed along the ranges.

� Point where sounding is taken is fixed on the range by observation of the angle from the shore.

� As the boat proceeds along the shore, other soundings are also fixed by the observation of angles from the shore.

contd……..

Er. P

ramesh Hada, Asst. P

rof, civ

il

Engineering Departm

ent,nec

Page 29: Hydrographic survey for std not print

Er. P

ramesh Hada, Asst. P

rof, civ

il

Engineering Departm

ent,nec

•Let “B” is the instrument station, A1-A2 is the

range along which the boat is rowed and α1, α2, α3

etc. are the angles measured at B to points 1, 2, 3

etc.

•This method is very accurate and very convenient

for plotting.

•If the angle at the sounding point is less than 30°,

a new instrument station must be chosen.

By range and one angle from the shore Er. P

ramesh Hada, Asst. P

rof, civ

il

Engineering Departm

ent,nec

a new instrument station must be chosen.

•After first and last soundings & every tenth

soundings are fixed by angular observations and

intermediate points are fixed by time interval.

Page 30: Hydrographic survey for std not print

4. Location by range and one angle from the boat

� Is similar to the previous one except that the angular fix is made by angular observation from the boat.

� Boat is kept in range with the two shore signals and is rowed along it.

� At the instant the sounding is taken, the angle subtended at the point between the range and some prominent point B on the shore is measured.

Er. P

ramesh Hada, Asst. P

rof, civ

il

Engineering Departm

ent,nec

Methods of Locating Sounding

some prominent point B on the shore is measured.

This method has the following advantages :

� Since all the observations are taken from the boat, the surveyor has better control over the operations.

� Mistakes are reduced since the recorder books the readings directly.

� On important fixes, check may be obtained by measuring a second angle towards some other signal on the shore.

� To obtain good intersections throughout, different shore objects may be used for reference to measure the angles.

Er. P

ramesh Hada, Asst. P

rof, civ

il

Engineering Departm

ent,nec

Page 31: Hydrographic survey for std not print

5) Location by two angles from the shore

� In this method, a point is fixed independent of therange by angular observations from two points onthe shore.

� Used to locate some isolated points.

� Two instruments & two surveyor are required & instrument is selected with accuracy.

� If A & B are two instrument station and ‘d’ is measured accurately.

� Instrument stations A and B are precisely connected to the ground and their positions on plan are known.

Er. P

ramesh Hada, Asst. P

rof, civ

il

Engineering Departm

ent,nec

Methods of Locating Sounding

to the ground and their positions on plan are known.

� Surveyor on the boat holds a flag for a few seconds, and on the fall of the flag the sounding and the angles are observed Simultaneously.

� co-ordinates of the position P of the sounding may be

computed from the relations :

Method has the following advantages

� Preliminary work of setting out and erecting range signals is eliminated..

� Suitable for strong current of water due to which it is difficult to row the boat a1on the range line.

Er. P

ramesh Hada, Asst. P

rof, civ

il

Engineering Departm

ent,nec

Page 32: Hydrographic survey for std not print

6. LOCATION BY TWO ANGLES FROM THE BOAT

� In this method, the position of the boat can be located by the solution of the three-point problem by observing the two angles subtended at the boat by three suitable shore objects of known position.

� Three-shore points should be well-defined and clearly visible.

� Prominent natural objects such as church spire, lighthouse, flagstaff, buoys etc. are selected for this purpose.

Er. P

ramesh Hada, Asst. P

rof, civ

il

Engineering Departm

ent,nec

spire, lighthouse, flagstaff, buoys etc. are selected for this purpose.

� Let A, B and C are the shore objects and P is the position of the boat from which the angles α and β are measured.

� Both the angles should be observed simultaneously with the help of two sextants, at the instant the sounding is taken.

� The method is used to take the soundings at isolated points.

Er. P

ramesh Hada, Asst. P

rof, civ

il

Engineering Departm

ent,nec

Page 33: Hydrographic survey for std not print

7. Location by one angle from shore and

one from boat

� This method is used to locate the isolated

points where soundings are taken.

� Let two points A and B are chosen on the

shore, one of the points (say A) is the

instrument station where a theodolite is set

up, and the other (say B) is a shore signal or

any other prominent object.

Er. P

ramesh Hada, Asst. P

rof, civ

il

Engineering Departm

ent,nec

Methods of Locating Sounding

any other prominent object.

� Sounding is taken at P, the angle α at A is

measured with a theodolite while the angle β

at the boat is measured with the help of a

sextant.

� Knowing distance d between the two points A

and B by ground survey, the position of P can

be located by calculating the two co-ordinates

x and y.

Er. P

ramesh Hada, Asst. P

rof, civ

il

Engineering Departm

ent,nec

Page 34: Hydrographic survey for std not print

8. Location by Intersecting Ranges

Method is used when it is required to

determine by periodical sounding at the

same points, the rate at which silting or

scouring is taking place.

� This is very essential on the harbors

and reservoirs.

� The position of sounding is located by

Er. P

ramesh Hada, Asst. P

rof, civ

il

Engineering Departm

ent,nec

Methods of Locating Sounding

� The position of sounding is located by

the intersection of two ranges, thus

completely avoiding the angular

observations.

� Suitable signals are erected at the shore.

� The boat is rowed along a range

perpendicular to the shore and

soundings are taken at the points in

which inclined ranges intersect the

range.

Er. P

ramesh Hada, Asst. P

rof, civ

il

Engineering Departm

ent,nec

Page 35: Hydrographic survey for std not print

9. Location by Tacheometric Observations

� Method is very much useful in smooth waters.

� Position of the boat is located by tachometric observations from the shore on a staff kept vertically on the boat.

� Observing the staff intercepts at the instant the sounding is taken, the horizontal distance between the

Er. P

ramesh Hada, Asst. P

rof, civ

il

Engineering Departm

ent,nec

Methods of Locating Sounding

horizontal distance between the instrument stations and the boat is calculated by :

� Direction of the boat (P) is established by observing the angle (α) at the instrument station B with reference to any prominent object A.

Er. P

ramesh Hada, Asst. P

rof, civ

il

Engineering Departm

ent,nec

Page 36: Hydrographic survey for std not print

3.4 MEASUREMENT OF CROSS-SECTION

Case I – When the River is small

� Two poles are fixed on both banks of the river & a rope isstretched between them.

� The water width of the river is divided into severalcompartments of equal width (say b) and the points aremarked by hanging tags or pendants.

� Depth of water corresponding to each pendant is measuredby a sounding rod or sounding cable.

� Let the depths of water be d0,d1,d2…..Considering the endcompartments as traing1es and other compartments as

Er. P

ramesh Hada, Asst. P

rof, civ

il

Engineering Departm

ent,nec

compartments as traing1es and other compartments astrapeziums, the area is calculated as follows.

Er. P

ramesh Hada, Asst. P

rof, civ

il

Engineering Departm

ent,nec

Page 37: Hydrographic survey for std not print

CASE II – WHEN THE AREA IS LARGE

� Two centre line AB is taken perpendicular to the river.

� Two stout pegs T1,T2 are fixed on AB.

� Then following procedure is adopted:

1. At station A, a theodolite is set up and the line is ranged properly. The width of the river is measured by stadia method. 2. The width is divided into equal parts, and the widths of these compartments are fixed. Thus the distances AP1, P1P2, P2P3,... are fixed. 3. Another theodolite is set up at C, so that

Er. P

ramesh Hada, Asst. P

rof, civ

il

Engineering Departm

ent,nec

3. Another theodolite is set up at C, so that AC is perpendicular to AB. The distance AC is measured (say it is equal to D).

4. Then the angles ( α1, α2… are calculated, in the following manner.

Er. P

ramesh Hada, Asst. P

rof, civ

il

Engineering Departm

ent,nec

5. The calculated angles α1, α2, ... arc set out from the theodolite at C.

Thus, the line of sight of the theodolite at A and that of the theodolite at C

coincide at the points P1, P2, P3, ... which are the points along the cross

section where soundings are to be taken.

6. The depths of water at these points arc measured by a sounding cable or

echo—sounder mounted on a boat.

7. Then the cross—sectional area of the water section is calculated in the

usual manner.

Page 38: Hydrographic survey for std not print

MEASUREMENT OF VELOCITY

� Measurement of velocity is an important aspect of many direct

stream flow measurement techniques.

� Different methods used for the measurement of velocity:

1. Surface float method

2. Sub-surface float method

3. Velocity rod method

4. Pitot tube method

Er. P

ramesh Hada, Asst. P

rof, civ

il

Engineering Departm

ent,nec

5. Current meter method

1. Surface float method

� Surface floats are made of cork. and can easily float on water.

� Are generally in the form of 10 cm cubes.

� The floats are painted red or white and have a small flag

attached on top [Fig. (a)].

(cork –cap or Outer bark of the cork oak; used for stoppers for bottles etc)

Er. P

ramesh Hada, Asst. P

rof, civ

il

Engineering Departm

ent,nec

Page 39: Hydrographic survey for std not print

1. SURFACE FLOAT METHOD

Velocity is measured in the following way:(a) At the discharge site, a rope is stretchedbetween two poles fixed on both banks ofthe river and the water section is divide dinto several compartments by hanging tagsfrom a rope [Fig. 13.9(b)].

b)velocity of each compartment ismeasured by the float, which is releasedslightly ahead of C/S-1. When the floatjust crosses the section, the stop watch is

Er. P

ramesh Hada, Asst. P

rof, civ

il

Engineering Departm

ent,nec

just crosses the section, the stop watch isstarted. When it just crosses C/S-2, thestopwatch is closed. The time taken bythe float to cover the ‘run’ (knowndistance) is noted, and from this thevelocity is calculated [Fig. I3.9(c)j.

Er. P

ramesh Hada, Asst. P

rof, civ

il

Engineering Departm

ent,nec

Page 40: Hydrographic survey for std not print

2. SUB-SURFACE FLOAT METHODEr. P

ramesh Hada, Asst. P

rof, civ

il

Engineering Departm

ent,nec

� Sub-surface float is a hollow cylinder which is attached

by a cord to a surface float.

� Position of the sub-surface float is adjusted according to

the depth of the river. Generally, it is kept 0.2D meters

above the bottom.

� In this case, the measured velocity is equal to the mean

velocity.

� The procedure of measurement is the same as that in the

Er. P

ramesh Hada, Asst. P

rof, civ

il

Engineering Departm

ent,nec

� The procedure of measurement is the same as that in the

surface float method (Fig. 13.10). Here, D is the depth of

water.

Page 41: Hydrographic survey for std not print

3. VELOCITY ROD METHOD

Er. P

rameshHada

Engineering Departm

ent,nec

� Velocity rod made of hollow metal or wood. Its

diameter is about 2.5 to 5 cm.

�Weight provided at the bottom of the rod to keep it

vertical. length of the rod is adjustable.

� Rod is generally submerged to the extent of O.6D.

� The procedure of measurement is exactly similar to

that in the surface float method (Fig. 13.11).

Hada, Asst. P

rof, civ

il

Departm

ent,nec

that in the surface float method (Fig. 13.11).

Page 42: Hydrographic survey for std not print

4. THE PITOT TUBE

� Pitot tube is a glass tube bent at anangle of 90° at the lower end.

� Upper end is open and kept above thewater level. The lower end is in theform of a nozzle, and is directedupstream.

� Due to the velocity of water, the water column rises in the right limb (Fig. 13.12). Let the rise in water

Er. P

rameshHada

Engineering Departm

ent,nec

(Fig. 13.12). Let the rise in water level be h. Then applying Bernoulli’s theorem between points A and B.

�Measuring the rise of water column the velocity can be calculated.

Hada, Asst. P

rof, civ

il

Departm

ent,nec

Page 43: Hydrographic survey for std not print

5. CURRENT METER METHOD� Commonly used for measuring the velocity of water.

� It consists of the following components. (a) A tail which keeps the meter in the direction of alignment, (b) A system of conical buckets fitted to a spindle which rotates due to current, (c) A counterweight which keeps the meter vertical, and (d) A headphone for registering the sound produced by the spindle at every revolution.

� Current meter is lowered to a depth of 0.6 D (D � Current meter is lowered to a depth of 0.6 D (D being the depth of water) by a suspension cable.

� Conical buckets is kept on the upstream side and the tail on the downstream side.

� Due to the velocity of water, the system of conical buckets rotates about the spindle and a ‘tick’ sound is emitted once for every revolution. Thus, a continuous “tick-tick” sound is heard through the headphone. The number of revolutions per minute 15 counted with the help of a stopwatch.

� velocity can be ascertained from the rating table (supplied by the manufacturer with the meter). This velocity gives the mean velocity of flow.

Er. P

rameshHada, Asst. P

rof, civ

il

Engineering Departm

ent,nec

Page 44: Hydrographic survey for std not print

Er. P

ramesh Hada, Asst. P

rof, civ

il

Engineering Departm

ent,nec

Er. P

ramesh Hada, Asst. P

rof, civ

il

Engineering Departm

ent,nec

Current meter Method

Page 45: Hydrographic survey for std not print

� Different structures like notch,weirs,sluice gates are used for

measuring flow or discharge.

� Notch – device used for measuring the rate of flow of liquid

through a small channel or a tank.

� Weir – concrete or masonary structure placed in an open channel

over which the flow occurs.

A/c to the shape of the opening, it is classified as:

Rectangular weir or notch

Er. P

ramesh Hada, Asst. P

rof, civ

il

Engineering Departm

ent,nec

3.4 Measurement of Flow

� Rectangular weir or notch

� Triangular weir or notch

� Trapezoidal weir or notch

� Broad crested weir

� Discharge over a Rectangular weir or notch

� Discharge through a Triangular weir or notch

� Discharge through a Trapezoidal weir or notch

� Discharge through a Broad crested weir

Er. P

ramesh Hada, Asst. P

rof, civ

il

Engineering Departm

ent,nec

Page 46: Hydrographic survey for std not print

Er. P

ramesh Hada, Asst. P

rof, civ

il

Engineering Departm

ent,nec

Discharge over a Rectangular weir or notch

Er. P

ramesh Hada, Asst. P

rof, civ

il

Engineering Departm

ent,nec

Discharge over a Rectangular weir or notch

Discharge through a Triangular or V-notch

dhh

Page 47: Hydrographic survey for std not print

Er. P

ramesh Hada, Asst. P

rof, civ

il

Engineering Departm

ent,nec

Discharge through a Trapezoidal notch or weirEr. P

ramesh Hada, Asst. P

rof, civ

il

Engineering Departm

ent,nec

Page 48: Hydrographic survey for std not print

Er. P

ramesh Hada, Asst. P

rof, civ

il

Engineering Departm

ent,nec

Discharge through a Broad - Crested weirEr. P

ramesh Hada, Asst. P

rof, civ

il

Engineering Departm

ent,nec

Page 49: Hydrographic survey for std not print

TUTORIAL 1 – HYDROGRAPHIC SURVEY(IMP PU QUESTIONS)

� What is Sounding? Explain two most accurate methods of locating sounding

Position. (7)

� What is the significance of underwater mapping in hydrographic survey?

Explain Rectangular weir & V-notch methods to find the volume of water in

the river?(8)

� Write the purposes of hydrographic survey & Explain the methods of locating

sounding positions.(9)

� Explain the terms i)Sounding ii)Echo-sounding iii)sextant (6)

Explain various methods used in the measurement of flow.(6)

Er. P

rameshHada

Engineering Departm

ent,nec

� Explain various methods used in the measurement of flow.(6)

� What is Echo sounding? Enlist the advantages of Echo Sounding.(7)

� What is Sounding ? Explain any three methods of sounding.(7)

� Define hydrographic survey. Write the purpose of hydrographic survey . (8)

� How do you find the discharge of a river in Hydrographic survey. Describe at

least two methods.(8)

� What is Eco-sounding? How it measures the depth of water bodies?

Discuss. (7)

Hada, Asst. P