Hybrid Status

18
Hybrid Status Carl Haber 12-Aug-2008 UCSC

description

Hybrid Status. Carl Haber 12-Aug-2008 UCSC. Prototypes and Designs. 60 cm, 9 cm strip, 6 segments/side. Stave-06. 1 meter, 3 cm strip, 30 segments/side 192 Watts (ABCD chip), ~2.4 % Xo + support structure. Stave-07. 6 x 3 cm, 6 chips wide. - PowerPoint PPT Presentation

Transcript of Hybrid Status

Page 1: Hybrid Status

Hybrid Status

Carl Haber

12-Aug-2008

UCSC

Page 2: Hybrid Status

6 x 3 cm, 6 chips wide

10 x 10 cm, 10 chips wide

1 meter, 3 cm strip, 30 segments/side192 Watts (ABCD chip), ~2.4 % Xo + support structure

1.2 meter, 2.5 cm strip, 48 segments/side ~250-300 Watts (@0.25 W/chip)1.7 – 2.4 % Xo + support structure, depends upon coolant and hybrid design

Stave-07

Stave-06

60 cm, 9 cm strip, 6 segments/side

Stave-08

Prototypes and Designs

Page 3: Hybrid Status

Intro

• We have developed a 6 chip ceramic ABCD hybrid for the Stave-2007 program– In use for ongoing studies of stave and transmission

• A new flex version of this will be fabricated as well. Layout complete, check prints– This will used to test substrate issues (PM talk)

• Beyond this a hybrid series is needed for the ABC-Next and Stave-2008 program

• Liverpool will lead this program• July 30-31 I met with the Liverpool and Oxford groups, in

the UK, to discuss this program– Includes hybrid development and data transmission studies

Page 4: Hybrid Status

flex

ceramic

Page 5: Hybrid Status

Ongoing Program

• More in PM talk• Individual hybrids/modules work well electrically• Main issue has been data transmission on the

stave with multiple modules.• Lack of robust response to LVDS commands• Significant work on test bench with D.Nelson

(many thanks for this…)• While we have made a number of improvements

we are not there yet• This has delayed further mounting of modules

on Stave-2007

Page 6: Hybrid Status

Hybrid for Stave-2008, ABC-next

• Oxford Meeting July 30-31, 2008– Phil Allport, Ashley Greenal, Tony Affolder, CH, Richard

Nickerson, Tony Weidberg, Todd Huffman, Peter Phillips, Mike Tyndel

• A key issue has been how to accommodate robust early testing of the ABC-next and Stave-2008, considering the lack of a MCC

• Drive towards a minimum area design• Concern for data transmission problems

– Parallel bus testing program• Follow-up meeting in US, late Sept, proposed

Page 7: Hybrid Status

Conclusion of Meeting

• A plan was developed to systematically address these various needs

• Liverpool will under take the design and fabrication of a series of hybrids over the next 6-9 months

• Various design choices will be made as options are understand further.

Page 8: Hybrid Status

Proposal

• Hybrid-1: for ABC-next test in legacy mode.– Can 20 ABC-next operate as a system?– Not compatible with stave and bus cable– Large connector, control with modified Mustard– Interface to various powering options– To be ready this Fall along with ABC-next

Page 9: Hybrid Status

Proposal

•A single PCB which can accommodate 2 hybrid fingers (with sensor)• All module connections to PCB made using wire bonds (as done by US)

• Fusing current for 25µm Al wire is ~500mA• Topology of connections will be similar to that presently used on US Stave• Power/DCS towards one end and Data I/O at the opposite end of hybrid

•For module readout & configuration make use of SCTDAQ (Mustard+SLOG+LV3)• Requires ABCns to operate in Legacy Mode (1 x Master/column) with data rate limited to

40MHz• Mustard firmware will be modified to accept increased ChipID field

• AC-coupled LVDS data transmission to/from module• LVDS RX (CLK, COM, etc.) powered parasitically off module VDD (2V5)• LVDS TX (Module data) powered from LV3 power supply VDD (4V)

•Make use of plug-in boards to provide the various powering scheme – the main PCB is simply a carrier

• One plug-in per finger, coming in different flavours• SPi plug-in, Pseudo SPi (with own shunt regulation and bypass circuitry)• DC-DC powering

• Requirement for floating power supply I/P• SPi will be(?) configurable using SCTDAQ

•Direct connection to hybrid VDD/VCC for auxiliary powering• Allows for more thorough testing of ABCn powering• Over/under voltage scenarios + direct current monitoring

9

Hybrid Powering and Readout

Module Integration Working Group 17th July 2008

Ashley Greenall

Page 10: Hybrid Status

10

Shunt Regulator

M M M M

Linear Regulator

Sensor

Pseudo-SPi

RX TX RX TX

Power In

VCC

VDD

Shunt Regulator

Linear Regulator

Power Out/In

VCC

VDD

LV3

Power Out

LVDS TX (Module Data)

Powered from SCTDAQ

LVDS RX (CLK,COM, etc.)

Powered from Module VDD

ABCn’s Operate in Legacy mode

Data rate limited to 40MHz

SCTDAQ

Plug-in Circuit

Hybrid connections made using wire-bonds

Hyb

rid

0

Hyb

rid

1

Hybrids are floating w.r.t. each other

Auxiliary Power connections

Floating Power Supply

Powering and Readout Conceptually

Module Integration Working Group 17th July 2008

Plug-in Circuit

SPi

DC-DC

Page 11: Hybrid Status

11

A Tentative Roadmap•July’08 begin layout of hybrid

• Will be fabricated as a Cu Kapton flex circuit• Using 35µm Cu (final version will use 12µm Cu) – build will otherwise be identical• Removes any uncertainty regarding asic/hybrid operation• Circuit will be laminated to rigid base board (FR4, carbon, ??)

•Expect hybrid circuit(s) to start to become available Oct’08• Circuits are being designed for both ASIC and Power evaluation

•ABCns due back Oct’08?• First testing begins of asics

•Expect release of ABCn’s Nov/Dec’08?

Module Integration Working Group 17th July 2008

Consider using 18µm instead?

Page 12: Hybrid Status

Proposal - continued

• Hybrids for staves are challenged by available area at ends

• Hybrid-2: for testing on stave– Assume MCC(s) is not available– Provide MCC function with either COTS chips or an

FPGA, real-estate issue– Can consider a very wide hybrid (35 mm) to

accommodate this, which still fits on stave– Aim for early 2009

• Hybrid-3: on stave with MCC(s)– Push for minimum area– Impact on MCC aspect ratio

Page 13: Hybrid Status

Kapton H

ybrid

2.1

7.5

96.3100.00

(Sensor)

3.05

3.051.7

0402 Decoupling capacitor

110.00

(Bus cable width)

5.0 Bus Cable (Power+DCS)

Bus Cable (Digital I/O)

Hybrid Extension (?)

Hybrid Extension (?)

>24.0

Bus cable access aperture

7.6

ABCn

What it means – hybrid on sensor (unbridged) with integrated bus cable

Critical dimensio

ns

Notes:

•Min. length of hybrid is 96.3mm

•<2mm real estate available at ends, assuming sizing is to 100mm sensor

•Where to locate MCC etc? (tape topology means 2 devices: 1 for power and 1 for digital I/O?)

•Consider reducing gap between ABCns doesn’t help. A reduction of 0.5mm/gap increases asic-to-sensor bonding angle to 35º (max is 18º)

•Necessary to increase hybrid length, will overhang sensor (rigidise?)

•Dimensions fixed – no other option!

Ashley Greenall

Page 14: Hybrid Status

40 MHz Beam Clock

x2

x4

Data interleavetakes 2 80 MHzstreams into1 160 MHz stream

ABCnext, 2 strings of 10dataout

dataclock

multiplierU1

U2

Simplified hybrid scheme without a real MCC

Page 15: Hybrid Status

Required Die

• U1: clock multiplier: candidate identified

• U2: data MUX: candidate identified

• 3 channels of LVDS receiver

• 1 channel of LVDS driver

• Serial powering components

Page 16: Hybrid Status

Area• Strongly advocate an aggressive minimum

area design for Hybrid-3– Goal would be 97+? mm x 20 mm– Consider running bus work under the chips,

not just in the space between chips (asymmetric design)

– Driven by ceramic hybrid experience– Impact on location of pads in ABCnext Ver2?

5mm

Page 17: Hybrid Status

5mm

100 mm

20 mm

A goal would be to fit all the required die, and on-hybrid buswork in the5mm zone or (lines) under the chips

Layer (from bottom up)1) Static shield layer2) Traces and power3) Traces and ground4) Component and bond pads

Hybrid real estate

Page 18: Hybrid Status

40 MHz Beam Clock

x2

x4

Data mux takes 2 80 MHzstreams into one 160 MHz stream

ABCnext, 2 strings of 10dataout

dataclock

multiplier

com

clk

bco

L1

mux

Wiring scheme for minimum area hybrid, route below chips