Hutch Neilson Princeton Plasma Physics Laboratory K-DEMO Project Meeting 26 June 2013 NFRI-PPPL K-DEMO Project Status and Plans Overview

Transcript of Hutch Neilson Princeton Plasma Physics Laboratory K-DEMO Project Meeting 26 June 2013 NFRI-PPPL...

Page 1: Hutch Neilson Princeton Plasma Physics Laboratory K-DEMO Project Meeting 26 June 2013 NFRI-PPPL K-DEMO Project Status and Plans Overview.

Hutch Neilson

Princeton Plasma Physics Laboratory

K-DEMO Project Meeting26 June 2013

NFRI-PPPL K-DEMO ProjectStatus and Plans Overview

Page 2: Hutch Neilson Princeton Plasma Physics Laboratory K-DEMO Project Meeting 26 June 2013 NFRI-PPPL K-DEMO Project Status and Plans Overview.

Goals for This Meeting

2K-DEMO Project Meeting / 26 June 2013 / H. Neilson

1. Updates of operating space, device modeling, structural analyses, blankets and divertor designs.

2. Plans for wrapping up Phase I, and planning for Phase II.

Page 3: Hutch Neilson Princeton Plasma Physics Laboratory K-DEMO Project Meeting 26 June 2013 NFRI-PPPL K-DEMO Project Status and Plans Overview.

3K-DEMO Project Meeting / 26 June 2013 / H. Neilson

Phase I Milestones & DeliverablesPlan (from Nov. 2012 Project Meeting at PPPL):

Jan 1, 2013 Start date.

Jan. 23, 2013. MT-23 Abstract deadline.

Feb. 1, 2013. SOFE-2013 Abstract deadline.

Feb. 20-22. Presentation of prelim. TF winding including joint and leads.

Feb. 28, 2013 Milestone: Update Design Point and “freeze” for remainder of 2013. (Further updates in the following year are anticipated.)

Feb. 28, 2013 Deliverable: A picture of the device including TF, PF, Coil Structure, supported by preliminary analysis.

Initial TF structural analysis- This meeting

June 10-14, 2013. Several presentations at SOFE-2013, San Francisco

• July 14-19, 2013 Presentation at MT-23 Conference, Boston

• July, 2013. Report of progress in Phase I contract performance period.

• Aug. 2013. Start of Phase II contract performance period

• Feb 28, 2014. Report of progress in Phase II contract performance period.

Page 4: Hutch Neilson Princeton Plasma Physics Laboratory K-DEMO Project Meeting 26 June 2013 NFRI-PPPL K-DEMO Project Status and Plans Overview.

4K-DEMO Project Meeting / 26 June 2013 / H. Neilson

PPPL Contract Accomplishments in Phase I• Contributions to initial design point selection, e.g.,

– System code performance analysis– Machine configuration model, based on PPPL AT Pilot Plant– PF coil configuration– Machine picture (shown several times at SOFE-2013)

• Analyses– Operating space– Structural– Superconductor

• Papers– C. E. Kessel, et al., “Systems Analysis Exploration of Operating Points for the Korean

Demo Program,” SOFE-2013.– T. Brown, et al., “Progress in Developing the K-DEMO Device Configuration,” SOFE-

2013.– K. Kim, et al., “A Preliminary Conceptual Design Study For Korean Fusion DEMO

Reactor Magnets,” SOFE-2103– G. S. Lee, et al., “Korean Fusion Roadmap: K-Demo Design and R&D Plan,” SOFE-

2013.– Y. Zhai, et al., “Performance evaluation of K-DEMO cable-in-conduit conductors using

the Florida electro-mechanical cable model,” MT-23.

Page 5: Hutch Neilson Princeton Plasma Physics Laboratory K-DEMO Project Meeting 26 June 2013 NFRI-PPPL K-DEMO Project Status and Plans Overview.

5K-DEMO Project Meeting / 26 June 2013 / H. Neilson

Phase I Records & Documentation• Meeting files and summaries (3 teleconference, 2 “live”):

http://advprojects.pppl.gov/Adv_Design/K_DEMO/K-DEMO_meetings.html

• SOFE-2013 and MT-23 papers and presentation files.

• Summary report to NFRI (by 31 July)

Page 6: Hutch Neilson Princeton Plasma Physics Laboratory K-DEMO Project Meeting 26 June 2013 NFRI-PPPL K-DEMO Project Status and Plans Overview.

6K-DEMO Project Meeting / 26 June 2013 / H. Neilson

PPPL Phase II Statement of Work - 1

Page 7: Hutch Neilson Princeton Plasma Physics Laboratory K-DEMO Project Meeting 26 June 2013 NFRI-PPPL K-DEMO Project Status and Plans Overview.

7K-DEMO Project Meeting / 26 June 2013 / H. Neilson

PPPL Phase II Statement of Work - 2

Page 8: Hutch Neilson Princeton Plasma Physics Laboratory K-DEMO Project Meeting 26 June 2013 NFRI-PPPL K-DEMO Project Status and Plans Overview.

8K-DEMO Project Meeting / 26 June 2013 / H. Neilson

Schedule & Budget

Budget required: $100k

Final report from PPPL: contributions to K-DEMO CSR, draft due 28 Feb. 2014.

Page 9: Hutch Neilson Princeton Plasma Physics Laboratory K-DEMO Project Meeting 26 June 2013 NFRI-PPPL K-DEMO Project Status and Plans Overview.

9K-DEMO Project Meeting / 26 June 2013 / H. Neilson

Plans• Complete administrative reviews of Phase II

Research Agreement, and sign.• Issue final Phase I report to NFRI within by 31 Aug.

Content as discussed at 26 June meeting. Including CD, and substantial report, 3 paper copies. (H. Neilson)

• Next Meeting: teleconference, August 27-28.–Establish milestones for Phase II.