MOP RIGGING ANTENNA SST (Self Supporting GF Towers) For Internal Use
QC&EHS Dept Huawei Confidential Page1/28
INDOSAT
MBS PROJECT
Method of Procedure
Antenna & Tower Rigging
Huawei Technologies Co., Ltd.
All rights reserved
Revision 2.0
-
MOP RIGGING ANTENNA SST (Self Supporting GF Towers) For Internal Use
QC&EHS Dept Huawei Confidential Page2/28
Method of Procedure
Antenna & Tower Rigging MOP
Version V2.0 Prepared by Mahardika
Doc. Code ISAT-Q-M-002/III/14 Reviewed by Arif Budiarto
Process owner QC, Training & EHS
dept.
Approved By Ian Reynolds
Revision Date May 2014 Revised HW Ian Reynolds
Indosat Review &
Acknowledgement
May 2014 Reviewed by John Shazel
Greg Sanger
Revision Date Revision Description
24-March-2014 Items Revised/Revisited.
Lifting Techniques & Pulley Installation on tower legs.
Knots correctly referenced and associated.
Nylon Endless Webbing slings not to be tied in knots, Can reduce the SWL
& shorten life span of the equipment.
Inclusion of drop zone areas to be included and implemented.
01-April-2014 Items Revised/Revisited.
Drop zone and emergency areas included.
Azimuth adjustment for mounting type 1.
Mechanical Tilting.
Lifting for Stiffening Mounting
10 May 2014 Items Revised/Revisited:
Wire Rope diameter 14mm. (Removed 12mm).
Tools list revision Included endless Nylon slings/Ratchet & sockets, long
reach.
Tag Line technique revised:
-
MOP RIGGING ANTENNA SST (Self Supporting GF Towers) For Internal Use
QC&EHS Dept Huawei Confidential Page3/28
CONTENTS
1 Flow Chart Lifting Processs ..........................................................................
2 Preparation .......................................................................................................
2.1 Tools and Equipment
2.2 Site Safety
2.3 Worker Preparation
3 Knot, Bends, and Hitches ..............................................................................
4. Lifting Process .
5 Lifting Technique .............................................................................................
6 Lifting Test at Site Salenrang .........................................................................
7 Lifting for Monopole .......................................................................................
8 Lifitng for Rooftop pole using Mounting type 3 ...........................................
9 Lifitng for Rooftop pole using Mounting type 6 ...........................................
10 Lifting for Stiffening Mounting ......................................................................
11 DOs and DONTs ..........................................................................................
-
MOP RIGGING ANTENNA SST (Self Supporting GF Towers) For Internal Use
QC&EHS Dept Huawei Confidential Page4/28
1 Flow Chart Lifting Process & Safety Checks
Work START
Work Permit, Access, TSSR, MOP, SIKA
Tools & Equipment check, Team tool box talk safety Briefing
team
Antenna lifts preparations & safety checks
Test Lifting / tools: pulley, wire rope, and winch
Replace item
Continue Lifting Antenna to Proposed Heights
Install Antenna on tower leg, fix the brackets & support arms
Antenna Mounting Checks Azimuth, Tilt & Alignment
Team Leader checks Installation Quality E2E Complete the SIR
Rectification
Site Cleaning / Final Site Safety Brief
NOK
OK
NOK
OK
Installation completion & Site de-Rigging
-
MOP RIGGING ANTENNA SST (Self Supporting GF Towers) For Internal Use
QC&EHS Dept Huawei Confidential Page5/28
2 Preparation
2.1 Tools and Equipments
A Pulley of the correct Safe Working Load (SWL), for the load to be lifted must be used and must be
of high quality; with SWL clearly marked on the pulley. (Snatch or closed Pulley block is acceptable).
Typically this will be rated at least 3x the load that will be lifted. Huawei Subcontractor must use
2000kg SWL as a minimum. The pulley shall be in good serviceable condition and fit for purpose
and visually checked before each use. Any obvious signs of damage or over use and the Pulley must
be replaced for the same type.
Only Manual Hand Winches are to be used and this must have a load capacity suitable for the load
to be lifted and must be in a serviceable condition. Typically this will be rated at 3x the load to be
lifted. Hand winches factory certified and complete with the correct leg mounting brackets (2000Kg
SWL).
For extra safety a 2000Kg nylon sling will be wrapped around the winch Leg brackets and fixed with
an appropriate Bow or D shackle (SWL 2000Kg - not tied). In addition to the above, the Operator
must be fully trained and experienced in the use of the hand winch and the rigging work must be
properly supervised by qualified And certified engineers at all times
The number of turns of wire rope on the drum should be a minimum of 4 turns and the Operator
Must be wearing good quality leather gloves and shall keep his hands away from the Winch
When in operation at all times.
Steel Wire Rope minimum 160m, 14mm in diameter with the factory pressed eye thumbnails (no
bulldog or other type of clips is to be used). Huawei teams will only use factory certified and tested
-
MOP RIGGING ANTENNA SST (Self Supporting GF Towers) For Internal Use
QC&EHS Dept Huawei Confidential Page6/28
Steel wire rope with pressed eye thumbnails as below,.
Huawei subcontractor rigging teams will not use or are not permitted to use Kernmantle ropes or
any other type of synthetic ropes for Rigging/lifting activities, the only ropes to be used are Tag
line (holding out) ropes.
Tag Lines will be 14 16mm polypropylene or equivalent min SWL 200Kg (none stretch).
Wire Rope / Steel Bond - 12/14mm Factory pressed eye ends.
Rigging attachment devices, such as Webbing slings, Shackles and Carabiners will also be required
and these should have a minimum SWL capability of 2000kg, the same as the other lifting items,
typically 3x the load to be lifted. All items shall be in good serviceable condition and fit for
purpose and visually checked before each use, any none conforming items must be replaced for
new serviceable items..
Radio Transceivers (Back to back Radios/Walkie Talkies) are to be used at all times for
communicating between ground crew and workers aloft. Use of Mobile phones is not
recommended.
General Hand tools, Ratchet socket wrench, wrenches, open ended spanners, water pass etc, are
required & must be fully fit for purpose and must be in good serviceable condition, tools must be
stored in tool boxes. All rigging engineers are to ensure that all hand tools are tethered (tied) to
their harness and canvas flapped (closed) tool bags used at all times when working at height.
Rigging Tools Checklist
-
MOP RIGGING ANTENNA SST (Self Supporting GF Towers) For Internal Use
QC&EHS Dept Huawei Confidential Page7/28
Item Description Qty
1 Hand Winch - Factory assembled -With Leg bracket - SWL 2000Kg 1
2 Wire / Steel Rope 14mm Diameter - 150M - SWL 2000Kg 1
3 Wire Rope factory pressed Eye Loop - SWL 2000Kg. 1
4 Pulley Block/Snatch Block - SWL 2000Kg 2
5 BOW Shackle 5/8 " - High tensile steel - SWL 2000Kg 6
6 BOW Shackle 1//2 " - High tensile steel - SWL 2000Kg 6
7 Carabiner Steel - 23Kn - Screw lock 6
8 Looped Nylon Endless Webbing Sling - Max Length 2m SWL 2000Kg 4
9 150m Polypropylene Tag Line Rope - SWL 2000Kg (None stretch) 1
10 Cable Drum Jacks 1 Set
11 Single Flat Webbing Cargo Sling - 5m - 2000Kg 2
12 Ratchet Spanner - 1/2 " - Long Reach socket 2
13 Long reach sockets 1/2 " - 13mm to 24mm 1 set
14 Safety Signs 2
15 Yellow Black Boundary tape (Plastic) 100m
16 Complete set of professional hand tools 1 Set
Personal Protective Safety Equipment (PPE) must be worn at all times when working on the
sites, this is none negotiable and any persons found not abiding to the HSE regulations will be
removed from the site and banned from the project without hesitation.
-
MOP RIGGING ANTENNA SST (Self Supporting GF Towers) For Internal Use
QC&EHS Dept Huawei Confidential Page8/28
First Aid Equipment:
A PMI approved First Aid Kit shall be on site at all times when work is being undertaken on site. It is
recommended that at least two PMI trained & certified First Aiders should be included in the
Rigging Team.
First aid kits are to be present on all site installations and stored within quick and easy access to the
whole site installation team, the kits must be complete and sterile.
Each vehicle used shall also carry one first aid kit and be fully complete as per the list below.
First aid Contents and Items:
Dressing Absorbent gauze
Crepe Bandage 7.5cm x 3.6cm
Eye Pad with Bandage No.16
Antiseptic cleaning wipes
Antiseptic/germicide Providone-Iodine U.S.P Prep Pads
Alcohol 2 ply medium Prep Pads Wash proof plasters
Triangular Bandages (4)
2 (Two) x Narrow Roller Bandage (2m long by 7.5cm wide)
Wide Roller Bandage (2m long by 15cm wide)
0.3ml Ammonia inhalant breakable vials
Safety Pins
Scissors
Tweezers
Bandage Shears
Latex Gloves
Face Shield (for CPR)
-
MOP RIGGING ANTENNA SST (Self Supporting GF Towers) For Internal Use
QC&EHS Dept Huawei Confidential Page9/28
2.2 Site Safety - Demarcation of working areas and Drop Zones.
The teams on site must attach Barricade Tape and place safety signs on and around the working
areas, as well as clearly identify the rigging drop zones (half the working height) these areas must
be taped and cordoned off, site access gates must be locked and secured when the rigging work is
ongoing & all engineers are made fully aware of the site safety emergency gathering area in case of
any sudden incidents/accidents.
Safety signs must include the below information:
1. Hard hat Area. (Boots, Hat, Harness, Gloves & Glasses).
2. Personal protective equipment area.
3. Emergency Call information / telephone numbers and emergency contact numbers:
4. No Access to the Public / Local community.
5. Danger men working overhead / at Heights.
Site barricading:
Red and white or yellow and Black cordon tapes can be used for marking out safety areas..
All sites must be taped off to mark the working area and the drop zones; the barricade tape must block the
access areas and be placed at a height of 1.5m AGL.
-
MOP RIGGING ANTENNA SST (Self Supporting GF Towers) For Internal Use
QC&EHS Dept Huawei Confidential Page10/28
2.3 Site Worker Preparation
Work Safety Analysis:
A complete Safety Analysis is to be carried out and analyze the risks of the specific site and the
activities of the rigging & planned installation work.
The process is to simply indentify the possible site dangers / risks and the probability or likely hood
of any occurrence due to the identified site risks, the TL must then measure the risks severities and
clearly instruct the team members on how to control all site risks and place tape or cordons around
any of the identified risk areas and brief the team in them all.
Tools box talk:
Each site Team Leader must hold a site installation tools box talk with all members on site, the TL
must fully explain all of the work activities and all engineers informed of their individual roles &
responsibilities be clearly defined.
All member of the team are to be briefed in the first aid and site accident procedures and be made
fully aware of the contact call numbers in case of any incidents, all near misses are to be recorded
and reported as they occur.
Tools box talk contents:
Visual checking analysis of tower or structure condition, site condition safe from danger animals
such as snakes, bees, monkeys etc, First Aid kit check.
Documentation check and brief on the installation requirements is needed. Safety brief, tools
checking, Installation tools checks, Job Arrangements, Rigging tools checking such as Pulley, Sling,
Webbing, Full body harness, all TB talk results logged and recorded.
Engineer Certification check:
Huawei identity Pass & ID as well as WAH Certificatation must be checked: All members of the
team should carry their WAH certification (Copy) with them on all site installations, they must be
fully trained at WAH and HSE by Huawei expert, and all Riggers must hold WAH Certificate from
Menakertrans / Professional Consultant, any persons found to be on site working without the
correct certification will be immediately removed from site and their photo taken, details logged
and reported to the HSE HW manager.
-
MOP RIGGING ANTENNA SST (Self Supporting GF Towers) For Internal Use
QC&EHS Dept Huawei Confidential Page11/28
3.0 Knots, Bends and Hitches
All rigging team personnel shall be proficient in and capable of tying the basic rigging Knots, Bends
and Hitches and be knowledgeable in their correct use. Knot tying is only applicable to the Tag lines
and all equipment that is to be lifted is attached with sling and shackle not tied in any way.
The following Knots Bends and Hitches apply and are to be used for the purpose described below
only, no other types of knots are to be used or attempted:
Reef Knot (for joining ropes together)
Clove Hitch (for securing NOT Lifting)
Double Sheet Bend (Lifting)
Bowline (Preferred Knot - Secure safe lifting easy to untie).
-
MOP RIGGING ANTENNA SST (Self Supporting GF Towers) For Internal Use
QC&EHS Dept Huawei Confidential Page12/28
4 Drop Zones, Safe working areas and emergency rendezvous areas:
4.1 Drop Zones:
The drop zone is 50% of the actual Working height, or the actual location of the installation.
Example: If the team is working at 30m height the drop zone then becomes 15m from tower base
to surrounding area.
4.2 Safe working areas:
If there are residents living or in the vicinity of the Working Drop Zone Area, inform them about the
dangers and risks involved, ensure safety arrangements are in place & tape off the the drop zone
working area, placing signs around the boundary..
4.3 Emergency Rendezvous Point:
The Team leader must chose a safe area of the site or immediate surrounding area as an
emergency gathering location for the whole team to use in case of any accidents occurring.
In case of any accident occurring or very bad weather, i.e. lightening, hard rain, all work must stop
immediately, climbers must return to ground level and wait in the safe area until the immediate
risks have been addressed or removed or the adverse weather has passed and cleared.
4.4 Site Visitors/ Inspectors:
In the case of any persons visiting the site or trying to gain access to the site whilst the work is
being undertaken, the team leader must ask the persons to wait outside the working area outside
of the cordoned off drop zone. The tea, leader must challenge the visitor for their I.D then allow
to enter site, only fully trained persons are to enter sites, they must show their professional
credentials & certification, TL must report all visitors to the HW RPM
-
MOP RIGGING ANTENNA SST (Self Supporting GF Towers) For Internal Use
QC&EHS Dept Huawei Confidential Page13/28
5 Basic Lifting Processes
Before any Lifting starts, the Team Leader must make sure that the Job Safety Analysis, safety sign
and barricade tape, emergency call and Tool box safety talk safety is completed.
Print out the plan or approved method of procedure (MOP, TSSR etc) and follow the plans and
make sure all team members who are involved in the lifting activity fully understand their roles, the
plan and the approved procedures. There must be 1 Team Leader/Supervisor assigned to the site
installation, he/she is fully responsible for making sure all activities run smoothly and as planned.
Test lifts, Lift slowly under control, communicate the lift progress and stop slowly when at the
correct height. Fully check & Ensure all wire rope and blocks are running freely and not snagging or
rubbing in any way possible, if there is any rubbing or snagging of the lifting line found the TL must
re route the lines and ensure that the lines are free from hindrance free pulley blocks and lines at
all times when under stress...
Stop the activity slowly & under control for any issues that arise or that cause concern, check them
thoroughly and then proceed under control with one engineer climbing with the lift in his vision
and manage the lift until it is in the correct landing position on the structure..
6 Lifting Techniques (in Brief).
Ensure the pulley blocks are secured firmly and correctly in the tower leg, not bracings.
The Wire rope is free from any friction and rubbing and wrapped on the winch correctly (4
turns).
Let Taglines run freely under control, avoid any damage to equipment on the tower
No member below the lift Antenna /communicate well with winch controller.
Lift slowly and stop slowly under control at all times, follow the lift & climb as it rises.
Use double pulley to lift the Antenna / safety and back up.
Install blocks/pulley horizontally across the tower face.
Mark the drop zone at location and barricade off.
Stop at the correct height and lock of all winches and tag lines. (Secure the lift/make safe.).
Square Rigging Pulleys and Line
Note: Installation Pulley to tower leg, the structure must be free from corrosion, strong and firm
and then the pulley blocks attached with Nylon slings and shackles.
-
MOP RIGGING ANTENNA SST (Self Supporting GF Towers) For Internal Use
QC&EHS Dept Huawei Confidential Page14/28
Pulley Block Placement:
All Pulley Blocks must be attach to the structures correctly by using webbing nylon slings and
shackle SWL 2000Kg. Pulley Blocks must be attached on the Leg & placed above a horizontal
bracing to prevent any slippage or displacement/movement of the pulley under stress.
6 Lifting Test & rigging checks.
6.1 SITE Process and Pre-Lifting checks.
1. Prepare all Lifting equipment and carry out the
Tool box talk, inform the team again for the
Plan of installation ensure all understand their
part clearly.
Team Tool Box talk briefing.
2. Attach the hand winch to the tower leg
Using the manufacturers winch mounting
bracket and a webbing sling for extra safety.
All Leg brackets must be factory, welded and
Installed correctly prior any lift testing taking
Place.
Lifting continued:
-
MOP RIGGING ANTENNA SST (Self Supporting GF Towers) For Internal Use
QC&EHS Dept Huawei Confidential Page15/28
3. Attach two pulley blocks in parallel at the
Relevant working height by using the above
Attachment Techniques double pulley blocks
Are used and must be serviceable and fit for
Purpose, installed horizontally and handled &
managed with respect. Pulley blocks must sit
flush and be free of snags and any potential
Interference, all engineers MUST NOT rest their
hands arms or and tools on the wire ropes as lifting
is taking place.
The rigging engineers must keep a Safe working
distance of 1.5m when pulley blocks are in Service
and lifts are in operation and being made.
4. The antenna assembly is to be checked
thoroughly and all cables are secure and
attached correctly, then Lift the antenna slowly
until max 3m where the assembly is vertical
then stop the lift and carry out a visual check of
the wire rope runs and communicate to the
tower riggers & confirm with them that the
pulleys are running freely.
5. The winch operator must use radio for all
communication the tower riggers, the operators
must be experienced and skilled in the winch
operation and wear the correct PPE at all times.
gloves are to be worn at all times.
The excess wire rope must be managed
correctly and stored on a wire rope drum for
management and protection from any potential
damage.
-
MOP RIGGING ANTENNA SST (Self Supporting GF Towers) For Internal Use
QC&EHS Dept Huawei Confidential Page16/28
6. Once the above checks have been completed the
lift can continue, one rigger must climb with the
assembly and ensure that he is in communication
with the winch operator at all times, under no
circumstances whatsoever are any persons to stand
under the load when it is being raised.
7. All antenna assemblies must be attached to the
Tower legs correctly and the brackets and bolts
tightened to the correct torque settings of 30Kn.
8. Install the brackets and check that all flat, spring
washers, bolts and both locking nuts are tightened
using ratchet spanners/sockets NOT open ended
spanners as this can round of the nut. The Bolts
must protrude equally and not be twisted or
Mis-aligned in any way.
9. Make sure that the Antenna is aligned to 0 degrees
and according Azimuth plan found in the approved
site installation designs.
-
MOP RIGGING ANTENNA SST (Self Supporting GF Towers) For Internal Use
QC&EHS Dept Huawei Confidential Page17/28
10. On completion of all antenna lifting Lifting and the
Antenna installation is finished, the Team leader
Must carry out a full and detailed do self inspection.
To fully check all aspects of the site installation. All
Aspects of the installation are the be in line with
the approved site designs and immediate
rectification made to any none conformances
found.
11. Site De-Rigging must be carried out in a controlled
and disciplined way, under NO circumstances are
any ropes, Pulleys, shackles etc, to be dropped or
thrown to the ground, all equipment and tools are
to be lowered to the ground in a controlled and
safe manner, all tools and equipment must be packed
and stored away correctly and Site clearing must
be made and the site left clean, tidy and secure.
No burning of any waste is to take place on any site
installation.
12. Tag Line Techniques:
Tag Lines or Holding out ropes are to be securely fastened to the antenna assembly and the far end
attached to a stable and load bearing structure (fence post, tree or equivalent), a 2000kg sling
wrapped around and Choked through itself, two 2000kg Bow shackles are then attached to the
sling loop and the Tag line fed through the shackle over itself. When lifting is in progress the
engineer simply feeds the Tag line through he shackle, the line is to be controlled carefully and
never held tight.
Tag Line Sling in Place Tag Line in Operation
-
MOP RIGGING ANTENNA SST (Self Supporting GF Towers) For Internal Use
QC&EHS Dept Huawei Confidential Page18/28
7 Mechanical Tilting Procedures
If antenna installed at the rake leg, mechanical tilt
Must adjust until the antenna 0 degree.
1. Loosen the bolt (red marking)
2. Adjust the bolt (red marking) in the bracket
until antenna 0 degree
Once the bolts have been adjusted and the rake
compensated for and the antenna leveled off and
Antenna finally Installed on the tower rake / leg of the
tower the antenna must be set at 0 degrees position.
All bolts and brackets must be tightened correctly and
no washers or locking nuts missing.
8 Azimuth Adjustments
The complete antenna pole with RRU, filter
and junction box will be rotated together, azimuth
adjustment is around +/- 45degree
2 person needed to loosen the antenna pole 2.One for the upper clamp
and one for the lower clamp
Rotate the Antenna, RRU, Filter
To a propose azimuth and lock off
the antenna system
-
MOP RIGGING ANTENNA SST (Self Supporting GF Towers) For Internal Use
QC&EHS Dept Huawei Confidential Page19/28
9 Processes for Installation of the Leg Stiffening Mounting
On a 4 legged SST where the tower leg size is lower then 70mm, the antenna triple band
must be installed once the Tower leg has been stiffened. The rigging and lifting process is
the exact same process as described above, the overall lifting procedures are the same
with the lifting of the antenna (compact type 1), and the only difference being the tower
Leg must be stiffened first then the antenna system can be installed not until.
Ensure the pulley blocks are secured firmly and correctly in the tower leg, not bracings.
The Wire rope is free from any friction and rubbing and wrapped on the winch correctly (4
turns).
Let Taglines run freely under control, avoid any damage to equipment on the tower
No member below the lift Antenna /communicate well with winch controller.
Pre Assembly Stiffening mounting in the ground
Stiffening mounting with 6 U Bolt
Use double pulley to lift the Antenna / safety and back up.
Lift the Stiffening mounting until reach the propose high, totally 4 Stiffening Mounting
need to be lift and install in the tower leg, Lift it piece by piece, then fix it to tower leg
Lift the Compact triple band antenna.
Lift slowly and stop slowly under control at all times.
Use double pulley to lift the Antenna / safety and back up.
Install blocks/pulley horizontally across the tower face.
Mark the drop zone at location and barricade off.
Stop at the correct height and lock of all winches and tag lines. (Secure the lift/make safe.)
-
MOP RIGGING ANTENNA SST (Self Supporting GF Towers) For Internal Use
QC&EHS Dept Huawei Confidential Page20/28
10 Installation of the Antenna system Support arms (Stick Rods).
Each Antenna system is to be supported by two support arms.
Each arm is to be installed as detailed below.
Each individual support arm is to be installed on the top of the antenna only.
Each support arm is to be installed correctly and all fixings tightened.
Stick Rod installation upper view
Stick Rod installation side view
-
MOP RIGGING ANTENNA SST (Self Supporting GF Towers) For Internal Use
QC&EHS Dept Huawei Confidential Page21/28
11 DO,s and DONT
-
MOP RIGGING ANTENNA SST (Self Supporting GF Towers) For Internal Use
QC&EHS Dept Huawei Confidential Page22/28
-
MOP RIGGING ANTENNA SST (Self Supporting GF Towers) For Internal Use
QC&EHS Dept Huawei Confidential Page23/28
-
MOP RIGGING ANTENNA SST (Self Supporting GF Towers) For Internal Use
QC&EHS Dept Huawei Confidential Page24/28
-
MOP RIGGING ANTENNA SST (Self Supporting GF Towers) For Internal Use
QC&EHS Dept Huawei Confidential Page25/28
-
MOP RIGGING ANTENNA SST (Self Supporting GF Towers) For Internal Use
QC&EHS Dept Huawei Confidential Page26/28
-
MOP RIGGING ANTENNA SST (Self Supporting GF Towers) For Internal Use
QC&EHS Dept Huawei Confidential Page27/28
Be Safe Not Sorry
Work professionally at all times and take
Pride in your installation quality.
-
MOP RIGGING ANTENNA SST (Self Supporting GF Towers) For Internal Use
QC&EHS Dept Huawei Confidential Page28/28
Utamakan Keselamatan,
Orang-orang yang mencintai anda
menunggu dirumah.
Drafted By:
Mahardika Dewayana